Ref. No.: BPS-121082-F.

RP

CIKARANG POWER STATION PROJECT


Babelan, Bekasi, Jakarta, Indonesia
No. 032

WEEKLY REPORT OF
25th Apr 2016 01st May 2016

Prepared by DELUGE

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 1 of 6

1.
1.1

a.

SAFETY & SECURITY


HSE
The number of manpower having successfully completed Safety Induction Course and
updated are as follows:
PT Deluge Engineering Construction
: 12 (Last Week 11)
PT Surabaya Prakarsa Fire Service (Fire Alarm)
: 10 (No Update)
PT Piping System Indonesia (Aboveground)
: 79 (Last Week 74)
PT Valvtrol Global Flowsystem (Underground)
: 17 (Last Week 15)
Total Manpower
: 118

1.2 Manpower (PT Deluge Site Project Management)


a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)
2.
3.

Soh Kee Hong


Eko Kurniawan
Ismail
Amin
Limhot
Angga
Aditya
Rahmat
Lito Nosa
Yaakop
Joey
Rahman
Wahid

(Project Manager Ph. 0812 9605 0510)


(Construction Manager Ph. 0812 9396 1612)
(Doc, QA/QC Control - Ph. 0821 1062 4212)
(Safety Coordinator Ph. 0813 6844 1153)
(Draftsman Ph. 0813 1010 7275)
(Storeman Ph. 081 286 45 3134)
(Site Engineer Ph. 085659636791)
(Draftsman Ph. 085788087472)
(Design Manager)
(Asst Design Manager)
(Asst Design Manager)
(Fire Alarm Engineer)
(Site Engineer)

SITE FACILITIES
Sandblasting and Painting activities is still on going at PT. Deluge Site Office Workshop.
QA/ QC
- Hydrotest is done on Tuesday, 26th April 2016 for HDPE U/G Hydrant at Oil Unloading
Area.
- Hydrotest is done on Thursday, 28th April 2016 for HDPE U/G Hydrant at BC-09 Area
Section-01.
- Official Linecheck is done on Thursday, 28th April 2016 for HDPE U/G Hydrant at BC09 Area Section-02.

4.
PROGRESS
4.1 Engineering Issues
a.
Drawing Submission
- Attached
b.
Document Submission
- No Submission

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 2 of 6

4.2 Update Construction Progress


4.2.1 Fire System
Mechanical Under Ground;
a.
Parking Area;
Progress :
- Jointing Hydrant Line to Gate 01 area is continue on goin.
- Excavation and Back Fill to Main Road Pipe bridge continue.
b.
BC-07A Inside Coal Yard;
Progress : Official Line Check with PTCL will conducted on Tuesday, 03th May 2016.
c.
BC-07B Inside Coal Yard
Progress : Official Line Check with PTCL is done on Saturday, 30th Apr 2016.
d.
BC-08.1 & BC-08.2 Southern Coal Yard
Progress : Official Line Check with PTCL will conducted on Tuesday, 03th May 2016.
e.
Oil Pump Area;
- Progress : Hydrotest is done on Tuesday, 26th April 2016 for HDPE U/G Hydrant at Oil
Unloading Area. Backfill also done but keep open on Valve Pit & Hydrant Post Area.
f.
BC-09;
- Hydrotest is done on Thursday, 28th April 2016 for HDPE U/G Hydrant at BC-09 Area
Section-01.
- Official Linecheck is done on Thursday, 28th April 2016 for HDPE U/G Hydrant at BC09 Area Section-02.
Mechanical Above Ground;
a.
Piperack
WTP area;
Piping Progress :
Fit-Up Progress

Boiler 1 Area;
Piping Progress :
FHS Area;
Piping Progress :

Welding Progress

: 6 Joints (4 Fit Up joint already done by


Weeks 031)
: 10 Joints

Fit-Up Progress
Welding Progress

: 14 Joints
: 14 Joints

Fit-Up Progress
Welding Progress

: 4 Joints
: 4 Joints

Summary To Date Fit-Up Progress


Summary To Date Welding Progress
b.

: 58 Joints of Estimate 212 Joints


: 47 Joints of Estimate 212 Joints

Pump House
Power Island:
- Fire Pumps Leveling & Centering Internally is done.
- Daily Fuel Diesel Tank Internal Leveling and Centering is done.
FHS:

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 3 of 6

- Fire Pumps Leveling & Centering Internally still on going.


- Daily Fuel Diesel Tank Internal Leveling and Centering still on going.
c.
d.
e.
f.
g.
-

Boiler Cable Basement Unit 1;


Piping Progress :
Control Valve Header Installed
Internal Line Check is done
Temporary Test Flange for Hydrotest Installed.
Boiler Cable Basement Unit 2;
Piping Progress :
Control Valve Header Installed
Internal Line Check is done
Temporary Test Flange for Hydrotest Installed.
Switchgear Cable Basement;
Piping Progress :
Control Valve Header Installed
Internal Line Check
Install Temporary Test Flange
CAB Cable Basement
Control Valve Header Installed
Internal Line Check
Install Temporary Test Flange
Workshop
Fabrication;
Progress : Piping Fabrication, Pipe Support, Threading pipe.
Painting;
Progress : Painting and Sandblasting is continue on going.

Fire Alarm
a.
No Activity (Waiting Drawing for PTW)
4.3 Dust Suppression
a.
Parking & Water Pond Area ;
Progress :
- Excavation and Backfill continue to the Pipe Bridge Main Road.
5 Action Plan for this Week (May, 02nd 2016 May, 08th 2016)
5.1 Fire System
5.1.1 Mechanical
Under Ground;
a.
Parking Area:
- Excavation and Back Fill activities at Crossing to Pipe Bridge Line.
- Closing jointing under the U-ditch for Section - 01 (Crossing Area).
Cikarang Power Station Project Babelan,
Bekasi, Indonesia

Page 4 of 6

b.
c.

d.
e.
f.
g.

BC-07A Inside Coal Yard; Jointing HDPE Pipe


Progress Target: Official Line Check.
BC-09 Area;
Hydrotest for Section-02
Install tee pieces for future reservation near raw water electrical building.
Raw Water Electrical Building Area:
Stringing and jointing HDPE Pipe, Intall Flange for future reservation.
BC-07B Southern Area; Official Line Check & Hydrotest
Oil Pump Area; Install Valve Pit, Install Hydrant Post, Install Outdoor Hydrant Box.
West Side Boiler Area; Spreading and jointing HDPE Pipe

Above Ground;
a.
Pipe Rack;
- WTP Area; Fit-Up & Welding Pipe 10 on the Pipe Rack.
Progress Target : 14 Joints
- Boiler 1 Area; Fit-Up & Welding Pipe 10 on the Pipe Rack.
Progress Target : 14 Joints
- FHS Cable Bridge:
Progress Target : Erection pipe to the Cable Bridge for 20 Lengths Pipe.
b.
Boiler Cable Basement Unit 1;
Progress Target: Official Line Check, Hydrotest.
c.
Boiler Cable Basement Unit 2;
Progress Target: Official Line Check, Hydrotest.
d.
CAB Cable Basement;
Progress Target: Internal Line Check.
e.
Switchgear Cable Basement:
Progress Target: Internal Line Check.
f.
FHS Cable Basement:
Progress Target: Piping installation, Install Control Header.
g.
GIS Basement
Progress Target: Waiting ABB complete the Work
h.
Boiler #1 Transformer 1BFT20 & 1BFT25
Progress Target: Install Pipe & Support for Boiler 1 Transformer 1BFT20 continuing.
Internal Line Check and Official Joint Line check with Client
i.
Fire Pump House
Power Island;
Progress Target: Joint Inspection for Leveling and Centering Pump Installation, Internal
Line Check for Sprinkler Line.
Fuel Handling;
Progress Target: Internal check continue to Joint Inspection Centering and Leveling
Pump Installation.
j.
BC-09
Progress Target: Install Piping Sprinkler System
Cikarang Power Station Project Babelan,
Bekasi, Indonesia

Page 5 of 6

k.

Workshop
- Fabrication;
Pipe Header Fabrication, Pipe Support Fabrication, Pipe Spool Fabrication, Threading
Pipe Fabrication.
- Painting;
Daily Joint Inspection Painting with PTCL at PT. Deluge Workshop Babelan Site.
Continuing Painting and Sandblasting at PT. Deluge Workshop.

5.2 Fire Alarm


a.
CAB Building; Continue install cable conduit
5.3
a.
b.
c.

Dust Suppression
Coal Yard Area : Internal Line Check
Parking Area : Laying and Buried the Pipe under the drainage (Crossing Area).
Tanks Area : Continue Spreading and Joint pipe to Dust Suppression Pump.

6.
a.
b.

MATERIAL DELIVERIES
Raw Piping and Pipe Support Material; 1 Truck
Fire Alarm Control Panel 4 Unit, Smoke Detector 80 Pcs, Manual Call Point 20 Pcs.

7.
TIME SCHEDULE
7.1 Week Work Plan Schedule
- Attached
8.

Other Issues
- No Issues

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 6 of 6