Professional Documents
Culture Documents
Abstract:
This paper provides a cost-benefit-assessment of
reactive power supplied to network operators by
Wind Energy Converters (WECs). An approach is
proposed to estimate the costs of reactive power
supply by WECs with inverter-coupled generators.
A cost-benefit-analysis shows the economic
attractiveness of reactive power supply in many
cases, but also significantly varying costs. An
economic optimisation of both, the WECs and the
networks operation, must consider these cost
variations.
Keywords: Ancillary Services, Economic Analysis,
Inverter Losses, Reactive Power, Wind Energy
Converter
1 Introduction
In standard Alternating Current (AC) electrical
networks the voltage and current pulsate with the
networks frequency (in Europe: 50 Hz). Due to a
phase shift between voltage and current two
different types of power are distinguished: active
power for the useful work and reactive power
which oscillates between electrical storage
elements (capacitors and reactors). Many loads
and generators as well as the passive network
elements have a certain reactive power
characteristic. Different types of compensating
units can be installed to compensate reactive
power flows in the network. This goes alongside
with the objectives of network operators who have
to control the grids voltage within allowed limits
(e.g. EN50160). Furthermore, network operators
aim at reducing grid losses and congestions by
(1)
Q
kVAr
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
Availability of Q with
Smax =
Smax =
Smax =
1300 kVA
1400 kVA
1500 kVA
>99%
100%
100%
>99%
100%
100%
>99%
100%
100%
99%
100%
100%
97%
100%
100%
95%
>99%
100%
94%
98%
100%
94%
95%
>99%
93%
94%
97%
92%
93%
94%
89%
92%
94%
84%
90%
93%
5%
85%
90%
0%
5%
86%
0%
0%
5%
Additional Costs
[/kVAr]
8-15
15-30
22-44
29-58
36-71
Annual Costs
(20 a, 5%) [/kVAra]
0.6-1.2
1.2-2.4
1.8-3.5
2.4-4.7
2.9-5.7
(2)
PAC
PAC
=
PDC
PAC + P'loss
Ploss (t ) =
(3)
(4)
Ploss (t ) =
Ploss (t )
Q(t )
(5)
Efficiency
98%
2
96%
94%
92%
90%
Losses [%Smax]
0
0
20
40
60
80
100
are
distinguished
for
the
cost
Costs of Q [c/kVArh]
0.15
4 Cost-Benefit-Analysis
The benefits of reactive power supply by WECs
can be assessed by looking at alternative sources
of reactive power which are presently used. If
WECs have lower costs they can economically
substitute the conventional technologies. Another
approach is the analysis of the network effects by
Capacitor Banks
0.10
WEC:
0.03 - 0.10 c/kVArh
0.05
WEC:
< 0.03 c/kVArh
0.00
0
2000
4000
6000
Full Load Hours [h/a]
8000
Benefits
for
PL = dPL S 2 = dPL P2 + Q2
(6)
cos()
0.95
0.9
0.85
with
S =
2
1
1 > 0.
Q = P
cos( )
(7)
PL =
[(
dPL P 2 + Q 2 P 2
= dPL Q
Q
(8)
1
1
= dPL P
cos( )
S g P 2 + (Q Qw )
Qw
S g (S g cos( )) + (S g sin( ) Qw )
2
(9)
Qw
60%
Pw = 5%Sg
Pw = 20%Sg
Pw = 50%Sg
50%
40%
30%
20%
10%
0%
0.99
0.97
0.95
0.93
0.91
0.89
0.87
0.85
cos(phi)
5 Economic Impact
The cost-benefit analysis shows that the benefit
is in most cases greater than the costs of reactive
power supply by WECs. Although seeing costs in
the order of some 0.01 c/kVArh might result in a
statement like: negligible. It is correct that
reactive power supply has relatively seen no major
cost influence on the profitability of WECs.
However, in absolute terms we are discussing
about costs which should be taken into account.
The following two examples should give an idea
about the relevance.
We consider a 1 MW WEC with average reactive
power supply costs of 0.1 c/kVArh, secured
reactive power capacity of 0.5 MVAr, and full load
hours of 1000 h/a (for reactive power supply). The
operational costs of reactive power supply of this
single WEC are then 500 /a. In addition, an
oversizing to secured 0.5 MVAr results in
additional investment costs of 2.9-5.7 /kVAra or
1,450-2,850 /a. The total costs due to reactive
power supply are then 1,950-3,350 /a. This is a
minor cost factor (approx. 1%) for a 1 MW WEC
with active power generation revenues of 225,000
/a (full load hours for active power supply of 2,500
h/a and 9 c/kWh). But if we are looking at 50 GW
of WEC installed in Europe (beginning of 2007) we
are talking about annual reactive power supply
costs of 97.5-167.5 Mio .
From the network perspective we can have a look
at the total reactive power demand in the electricity
network which has been estimated in [17] to be
1759 TVArh annually for the EU-25 in 2002.
Further estimations in [17] result in 1069 TVArh to
be compensated and a corresponding network
loss reduction of 48 TWh. With costs of network
6 CONCLUSIONS
This paper describes the capabilities and
availabilities of reactive power supply by WECs
showing an interesting potential. This potential is
studied concerning its economic usability with an
approach of allocating costs of additional losses as
well as cost due to oversizing to reactive power
supply and assessing the benefits for network
operation.
The cost-benefit-analysis shows that reactive
power supply by WECs can be cheaper than
reactive power supply by conventional devices.
Reactive power supply by WECs for voltage
control can be an economic attractive supplement.
It can also be economically attractive for reducing
network losses and congestions as well as
providing better security of supply in case of faults.
One advantageous characteristic of reactive power
supply by WECs is its distribution in the network
and its location which is often next to loads. This
dispersion of reactive power sources can reduce
the overall network losses considerably.
The paper presents an economic potential of using
reactive power supplied by WECs. This potential
should be used to optimize the quality, economy
and security of network operation. Further on,
regulatory issues have to be analysed to design
appropriate market frameworks based on real
costs of reactive power and giving reasonable
incentives to operators of WECs for providing a
benefit for network operators. These frameworks
should lead to a win-win-situation: for the operators
of WECs as well as for network operators.
ACKNOWLEDGEMENT
This work was supported by the European
Commission in the framework of the FENIX project
(SES6 518272, see http://www.fenix-project.org)
as well as by the German Federal Ministry for the
Environment, Nature Conservation and Nuclear
Safety in the framework of the national project
Multifunktionale
Photovoltaik-Stromrichter