Document Code :
Title, Subtitle
110 V DC PANEL
TEST REPORT
Format
A4
Rev. A
Date
15.09.2015
Lang.
En
Date
15.09.2015
Project No.
ISSUE DATE
16/09/2015
ENG. N
110 V DC PANEL TEST REPORT
SH/OF
2/9
CLIENT N
REV.
Revision
Summary
Page
A
2. PRELIMINARY CHECKS
3. ELECTRICAL TESTS
4. PLACING IN SERVICE
Project No.
ISSUE DATE
16/09/2015
ENG. N
110 V DC PANEL TEST REPORT
CLIENT N
REV.
Type / SerialNr
Microhmeter / FLUKE
Insulation tester /MEGER
Omicron CPC 100
X
X
X
X
2. PRELIMINARY CHECKS
Date
Test corresponding to
paragraph
4
5
SH/OF
3/9
A
Project No.
ISSUE DATE
16/09/2015
ENG. N
110 V DC PANEL TEST REPORT
SH/OF
4/9
CLIENT N
REV.
Checking
Results
3. ELECTRICAL TESTS
3.1. ELECTRICAL CONTINUITY OF METAL PART TO GROUND:
Checking
Results
Results
Project No.
ISSUE DATE
16/09/2015
ENG. N
110 V DC PANEL TEST REPORT
SH/OF
5/9
CLIENT N
REV.
Checking
Results
Injected Current
Trip Time
Project No.
ISSUE DATE
16/09/2015
ENG. N
110 V DC PANEL TEST REPORT
CLIENT N
REV.
SH/OF
6/9
A
Project No.
ISSUE DATE
16/09/2015
ENG. N
110 V DC PANEL TEST REPORT
SH/OF
7/9
CLIENT N
REV.
Busbar
Measured Value
Result
L+
LE
3.6. VOLTMETER ACCURACY CHECK
3.6.1. Voltmeter P481:
Manufacturer:
Scale:
Input:
Indicator reading
(Vdc)
Injected value
(Vdc)
Measured value
(Vdc)
% Error
L(+)-L(-)
Ratio:
Indicator reading
injected value
(A)
Measured value
(A)
% Error
Project No.
ISSUE DATE
16/09/2015
ENG. N
110 V DC PANEL TEST REPORT
SH/OF
8/9
CLIENT N
REV.
Operations
Closing order on
-
Q1 correct voltage
Q2 no voltage
Closing order on
Q1
Q3
Q1 no voltage
Q2 correc t voltage
Closing order on
Q2
Q4
Q1 correct voltage
Q2 correct voltage
Closing order on
Q1
Q2
Actions
Q1 remains open
Q2 remains open
Q3 remains open
Q4 remains open
Q1 closed
Q2 remains open
Q3 closed
Q4 remains open
Q1 remains open
Q2 closed
Q3 remains open
Q4 closed
Q1 closed
Q2 closed
Q3 remains open
Q4 remains open
Busvoltage
Results
BB1 no volt
BB2 no volt
3.8.2.Automatic mode:
Conditions
Q1 no voltage
Q2 no voltage
Operations
Automatic closing
-
Q1correct voltage
Q2 no voltage
Automatic closing
Q1
Q3
Q1 no voltage
Q2 correc t voltage
Automatic closing
Q2
Q4
Q1 correct voltage
Q2 correct voltage
Automatic closing
Q1
Q2
Actions
Q1 remains open
Q2 remains open
Q3 remains open
Q4 remains open
Q1 closed
Q2 remains open
Q3 closed
Q4 remains open
Q1 remains open
Q2 closed
Q3 remains open
Q4 closed
Q1 closed
Q2 closed
Q3 remains open
Q4 remains open
Busvoltage
BB1 no volt
BB2 no volt
Results
Project No.
ISSUE DATE
16/09/2015
ENG. N
110 V DC PANEL TEST REPORT
SH/OF
9/9
CLIENT N
REV.
4. PLACING IN SERVICE
4.1. Busbar1:
Reading Voltages
L(+) L(-)
L(+) Ground
L(-) Ground
Result