You are on page 1of 473

This softawre is based on Standard Data book for analysis of Rates for Road and Bridge

Works
This Software runs on Microsoft Excel
INPUT- Input the usage rates of Plant & Machinery, labour and material as applicable
SUMMARY - In this sheet summary of all the rates analysized is presented
ANALYSIS- The analysis has been presented in 16 nos. of spread sheets
Worksheet- 1 : CHAPTER-1 CARRIAGE OF MATERIALS
Worksheet- 2 : CHAPTER-2 SITE CLEARANCE
Worksheet- 3 : CHAPTER-3 EARTH WORK, EROSION CONTROL AND DRAINAGE
Worksheet- 4 : CHAPTER-4 SUB-BASES, BASES (NON- BITUMINOUS) AND
SHOULDERS
Worksheet- 5 : CHAPTER-5 BASES AND SURFACE COURSES (BITUMINOUS)
Worksheet- 6 : CHAPTER-6 CEMENT CONCRETE PAVEMENTS
Worksheet- 7 : CHAPTER-7 GEOSYNTHETICS AND REINFORCED EARTH
Worksheet- 8 : CHAPTER-8 TRAFFIC SIGNS, MARKINGS & OTHER ROAD
APPURTENANCES
Worksheet- 9 : CHAPTER-9 PIPE CULVERTS
Worksheet- 10 : CHAPTER-10 MAINTENANCE OF ROADS
Worksheet- 11 : CHAPTER-11 HORTICULTURE
Worksheet- 12 : CHAPTER-12 FOUNDATIONS
Worksheet- 13 : CHAPTER-13 SUB-STRUCTURE
Worksheet- 14 : CHAPTER-14 SUPER-STRUCTURE
Worksheet- 15 : CHAPTER-15 RIVER TRAINING AND PROTECTION WORKS
Worksheet- 16 : CHAPTER-16 REPAIR AND REHABILITATION

INPUT
(A) Usage Rates of Plant and Machinery

Sl. No.

Description of Machine

Activity

Output of
Machine

Output

Unit

Rate

P&M-001

Air Compressor

General Purpose

capacity in cfm

170/250

hour

293.76

P&M-002

Batching and Mixing Plant (a) 30 cum capacity

Concrete Mixing

cum/hour

20

hour

2488

P&M-003

Batching and Mixing Plant (b) 15 - 20 cum capacity

Concrete Mixing

cum/hour

13

hour

1704.24

P&M-004

Bitumen Pressure Distributor

Applying bitumen tack coat

sqm/hour

1750

hour

986.04

P&M-005

Bitumen Boiler oil fired

Bitumen Spraying

capacity in litre

1500

hour

182.52

P&M-006

Concrete Paver Finisher with 40 HP Motor

Paving of concrete surface

cum / hour

20

hour

2637.36

P&M-007

Concrete Pump of 45 & 30 cum capacity

Pumping of concrete

cum / hour

33 / 22

hour

234.36

P&M-008

Concrete Bucket

For Pouring concrete

capacity in cum

hour

14.472

P&M-009

Concrete Mixer (a) 0.4/0.28 cum

Concrete Mixing

cum/hour

2.5

hour

211.68

P&M-010

Concrete Mixer (b) 1 cum

Concrete Mixing

cum/hour

7.5

hour

198

P&M-011

Crane (a) 80 tonnes

Lifting Purpose

hour

1176.12

P&M-012

Cranes b) 35 tonnes

Lifting Purpose

hour

784.62

P&M-013

Cranes c) 3 tonnes

Lifting Purpose

hour

535

P&M-014

Dozer D - 80 - A 12

Spreading /Cutting / Clearing

cum/hour

300/ 150/250

hour

3135.24

P&M-015

Dozer D - 50 - A 15

Spreading /Cutting / Clearing

cum/hour

200/ 120/150

hour

2028.78

P&M-016

Emulsion Pressure Distributor

Applying emulsion tack coat

sqm/hour

1750

hour

735.48

P&M-017

Front End loader 1 cum bucket capacity

Soil loading / Aggregate loading

cum/hour

60 /25

hour

1188

P&M-018

Generator (a) 125 KVA

Genration of electric Energy

KVA

100

hour

2307

P&M-019

Generator( b) 63 KVA

Genration of electric Energy

KVA

50

hour

361.8

P&M-020

GSB Plant 50 cum

Producing GSB

cum/hour

40

hour

872.64

P&M-021

Hotmix Plant - 120 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

40

hour

44564

P&M-022

Hotmix Plant - 100 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

30

hour

33841

P&M-023

Hotmix Plant - 60 to 90 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

25

hour

28484

P&M-024

Hotmix Plant - 40 to 60 TPH capacity

DBM/BM/SDC/ Premix

cum/hour

17

hour

19868

P&M-025

Hydraulic Chip Spreader

Surface Dressing

sqm/hour

1500

hour

2423.52

P&M-026

Hydraulic Excavator of 1 cum bucket

Soil Ordinary/Soil Marshy / Soil


Unsuitable

cum/hour

60 /60 /60

hour

1516.32

P&M-027

Integrated Stone Crusher 100THP

Crushing of Spalls

TPH

100

hour

7967.16

P&M-028

Integrated Stone Crusher 200 HP

Crushing of Spalls

TPH

200

hour

16760.52

P&M-029

Kerb Casting Machine

Kerb Making

Rm/hour

80

hour

279.72

P&M-030

Mastic Cooker

Mastic Wearing coat

capacity in tonne

hour

54.81

P&M-031

Mechanical Broom Hydraulic

Surface Cleaning

sqm/hour

1250

hour

465

P&M-032

Motor Grader 3.35 mtr blade

Clearing /Spreading /GSB /WBM

cum/hour

200/200/50/50

hour

2519

P&M-033

Mobile slurry seal equipment

Mixing and laying slurry seal

sqm/hour

2700

hour

926.64

P&M-034

Paver Finisher Hydrostatic with sensor control 100


TPH

Paving of DBM/ BM/SDC/ Premix

cum/hour

40

hour

3128

P&M-035

Paver Finisher Mechanical 100 TPH

Paving of WMM /Paving of DLC

cum/hour

40/30

hour

1420

P&M-036

Piling Rig with Bantonite Pump

0.75 m dia to 1.2 m dia Boring


attachment

Rm/hour

2 to 3

hour

5023.08

P&M-037

Pneumatic Road Roller

Rolling of Asphalt Surface

cum/hour

25

hour

1143.72

P&M-038

Pneumatic Sinking Plant

Pneumatic Sinking of wells

cum/hour

1.5 to 2.00

hour

3834

P&M-039

Pot Hole Repair Machine

Repair of potholes

cum/hour

hour

827.28

P&M-040

Prestressing Jack with Pump & access

Stressing of steel wires/stands

hour

116.1

P&M-041

Ripper

Scarifying

cum/hour

60

hour

25.704

P&M-042

Rotavator

Scarifying

cum/hour

25

hour

15.66

P&M-043

Road marking machine

Road marking

Sqm/hour

100

hour

85.86

P&M-044

Smooth Wheeled Roller 8 tonne

Soil Compaction /BM Compaction

cum/hour

70/25

hour

665

P&M-045

Tandem Road Roller

Rolling of Aspalt Surface

cum/hour

30

hour

1051.92

P&M-046

Tipper - 5 cum

Transportation of soil, GSB, WMM,


Hotmix etc.

Capacity in cum

5.5

km

22.356

P&M-047

Tipper - 5 cum

Transportation of soil, GSB, WMM,


Hotmix etc.

Capacity in cum

5.5

tonne.km

2.6784

P&M-048

Tipper - 5 cum

Transportation of soil, GSB, WMM,


Hotmix etc.

Capacity in cum

5.5

hour

873

P&M-049

Transit Mixer 4.0/4.5 cum

Transportation of Concrete Mix to site

cum/hour

4.5

hour

854.55

P&M-050

Transit Mixer 4/4.5 cum

Transportation of Concrete Mix to site

cum/hour

4.5

tonne.km

4.32

P&M-051

Transit Mixer 3.0 cum

Transportation of Concrete Mix to site

cum/hour

hour

784.62

P&M-052

Transit Mixer 3.0 cum

Transportation of Concrete Mix to site

cum/hour

tonne.km

5.886

P&M-053

Tractor

Pulling

capacity in HP

50

hour

171.018

P&M-054

Tractor with Rotovator

Rate of Tractor + Rotevator

hour

227.88

P&M-055

Tractor with Ripper

Rate of Tractor 6+ Ripper

hour

285.12

P&M-056

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

km

20.088

P&M-057

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

hour

773

P&M-058

Truck 5.5 cum per 10 tonnes

Material Transport

capacity/cum

4.5

tonne.km

2.268

P&M-059

Vibratory Roller 8 tonne

Earth or soil / GSB / WBM

cum/hour

100/60/60

hour

1779

P&M-060

Water Tanker

Water Transport

capacity in KL

hour

111.24

P&M-061

Water Tanker

Water Transport

capacity in KL

km

22.356

P&M-062

Wet Mix Plant 60 TPH

Wet Mix

cum/hour

25

hour

1107

Sl. No.

Description of Machine

P&M-063

Air compressor with pneumatic chisel attachment for cutting hard clay.

hour

513

P&M-064

Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour

hour

2279.88

P&M-065

Belt conveyor system

hour

Value

P&M-066

Boat to carry atleast 20 persons

hour

142.56

P&M-067

Cement concrete batch mix plant @ 175 cum per hour (effective output)

hour

4787.64

P&M-068

Cement concrete batch mix plant @ 75 cum per hour

hour

2052

P&M-069

Cold milling machine @ 20 cum per hour

hour

855.36

P&M-070

Crane 5 tonne capacity

hour

599.4

P&M-071

Crane 10 tonne capacity

hour

627.48

P&M-072

Crane 15 tonne capacity

hour

770.04

P&M-073

Crane 20 tonne capacity

hour

785.16

P&M-074

Crane 40 T capacity

hour

1166.4

P&M-075

Crane with grab 0.75 cum capacity

hour

1176.12

P&M-076

Compressor with guniting equipment along with accessories

hour

Value

P&M-077

Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour.

hour

1107

P&M-078

Epoxy Injection gun

hour

Value

P&M-079

Generator 33 KVA

hour

342.36

P&M-080

Generator 100 KVA

hour

1698

P&M-081

Generator 250 KVA

hour

3237

P&M-082

Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well
sinking.

hour

Value

P&M-083

Joint Cutting Machine with 2-3 blades (for rigid pavement)

hour

214.92

P&M-084

Jack for Lifting 40 tonne lifting capacity.

day

758.16

P&M-085

Piling rig Including double acting pile driving hammer (Hydraulic rig)

hrs

5023.08

P&M-086

Plate compactor

hour

142.992

Unit

P&M-087

Snow blower equipment 140 HP @ 600 cum per hour

hour

Value

P&M-088

Texturing machine (for rigid pavement)

hour

71.496

P&M-089

Truck Trailor 30 tonne capacity

hour

1864.08

P&M-090

Truck Trailor 30 tonne capacity

t.km

2.268

P&M-091

Tunnel Boring machine

hour

Value

P&M-092

Vibrating Pile driving hammer complete with power unit and accessories.

hour

Value

P&M-093

Wet Mix Plant 100 TPH

hour

1128.6

P&M-094

Wet Mix Plant 75 TPH

hour

2454

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k lfefr


eq[; vfHk;ark] tkZ foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&eq[; vfHk;ark
xzkeh.k fodkl foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr
&lg&v/kh{k.k fHk;ark] rduhdh ijh{k.k
dks"kkax
eaf=keaMy fuxjkuh foHkkx]
>kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
ty lalk/ku foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
is;ty ,oa LoPNrk foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr&lg&vfHk;ark izeq[k]
xzkeh.k dk;Z foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr&lg&vfHk;ark izeq[k]
Hkou fuekZ.k foHkkx] >kj[k.M] jkph

la;kstd] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
iFk fuekZ.k foHkkx] >kj[k.M] jkph

(B) Labour
Sl. No.

Description of Labour

Basic Rate

D.A.

Unit

Rate

L-01

Blacksmith (IInd class)

153.00

55.99

day

208.99

L-02

Blacksmith (Ist class)/ Welder/ Plumber/ Electrician

172.00

62.29

day

234.29

L-03

Blaster (Stone cutter)

214.00

75.31

day

289.31

L-04

Carpenter I Class

172.00

62.29

day

234.29

L-05

Chiseller (Head Mazdoor)

135.00

50.07

day

185.07

L-06

Driller (Jumper)

151.00

55.99

day

206.99

L-07

Diver

151.00

55.99

day

206.99

L-08

Fitter

176.00

62.29

day

238.29

L-09

Mali

151.00

55.99

day

206.99

L-10

Mason (IInd class)

153.00

55.99

day

208.99

L-11

Mason (Ist class)

172.00

62.29

day

234.29

L-12

Mate / Supervisor

135.00

50.07

day

185.07

L-13

Mazdoor

127.00

50.07

day

177.07

L-14

Mazdoor/Dresser (Semi Skilled)

130.00

50.07

day

180.07

L-15

Mazdoor/Dresser/Sinker (Skilled)

151.00

55.99

day

206.99

L-16

Medical Officer

L-17

Operator(grouting)

143.00

55.99

day

198.99

L-18

Painter I class

161.00

62.29

day

223.29

L-19

Para medical personnel

day

day

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k lfefr


eq[; vfHk;ark] tkZ foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&eq[; vfHk;ark
xzkeh.k fodkl foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr
&lg&v/kh{k.k vfHk;ark] rduhdh
ijh{k.k dks"kkax
eaf=keaMy fuxjkuh foHkkx]
>kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
ty lalk/ku foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
is;ty ,oa LoPNrk foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr&lg&vfHk;ark izeq[k]
xzkeh.k dk;Z foHkkx] >kj[k.M] jkph

lnL;] jkT;Lrjh; vuwlwfpr nj fu/kZkj.k


lfefr&lg&vfHk;ark izeq[k]
Hkou fuekZ.k foHkkx] >kj[k.M] jkph

la;kstd] jkT;Lrjh; vuwlwfpr nj fu/kkZj.k


lfefr&lg&vfHk;ark izeq[k
iFk fuekZ.k foHkkx] >kj[k.M] jkph

(C) Materials
Sl. No.

Description

Unit

M-001

Stone Boulder of size 150 mm and below at Quarry

cum

511.80

M-002

Supply of quarried stone 150 - 200 mm size for Hand Broken at Quarry

cum

536.00

M-003

Boulder with minimum size of 300 mm for Pitching at Quarry

cum

343.79

M-004

Coarse sand at Quarry (Equivalent to Koliwar sand)

cum

203.75

M-005

Coarse sand at Quarry (Equivalent to Koliwar sand)

cum

203.75

M-006

Fine sand at Quarry

cum

109.09

M-007

Moorum at Quarry

cum

119.64

M-008

Gravel/Quarry spall at Quarry

Cum

317.10

Rate

M-009

Granular Material or hard murrum for GSB works at Quarry

Cum

153.00

M-010

Granular Material or hard murrum for GSB works at Quarry

Cum

153.00

M-011

Fly ash conforming to IS: 3812 ( Part II & I) at source

0.00

Cum

613.00

Unit

Rate at
Plant (HMP
/ Batching)

Rate at
Quarry Site

M-012

Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) at Quarry

Description
M-013

Close graded Granular sub-base Material 53 mm to 9.5 mm at Quarry

cum

745.00

745.00

M-014

Close graded Granular sub-base Material 37.5 mm to 9.5 mm at Quarry

cum

815.29

815.29

M-015

Close graded Granular sub-base Material 26.5 mm to 9.5 mm at Quarry

cum

800.00

800.00

M-016

Close graded Granular sub-base Material 9.5 mm to 4.75 mm at Quarry

cum

704.20

704.20

M-017

Close graded Granular sub-base Material 9.5 mm to 2.36 mm at Quarry

cum

630.59

630.59

M-018

Close graded Granular sub-base Material 4.75mm to 2.36 mm at Quarry

cum

481.00

481.00

M-019

Close graded Granular sub-base Material 4.75mm to 75 micron mm at Quarry

cum

459.00

459.00

M-020

Close graded Granular sub-base Material 2.36 mm at Quarry

cum

393.00

393.00

M-021

Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve at Quarry

cum

211.23

211.23

M-022

Coarse graded Granular sub-base Material 2.36 mm & below at Quarry

cum

239.00

239.00

M-023

Coarse graded Granular sub-base Material 4.75mm to 75 micron mm at Quarry

cum

261.00

261.00

M-024

Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm at Quarry

cum

261.00

261.00

M-025

Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm at Quarry

cum

743.09

743.09

M-026

Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm at Quarry

cum

711.13

711.13

M-027

Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm at Quarry

cum

783.34

783.34

M-028

Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm at Quarry

cum

711.13

711.13

M-029

Coarse graded Granular sub-base Material 53 mm to 26 .5 mm at Quarry

cum

662.54

662.54

M-030

Aggregates below 5.6 mm at Quarry

cum

217.00

217.00

M-031

Aggregates 22.4 mm to 2.36 mm at Quarry

cum

794.46

794.46

M-032

Aggregates 22.4 mm to 5.6 mm at Quarry

cum

766.69

766.69

M-033

Aggregates 45 mm to 2.8 mm at Quarry

cum

629.40

629.40

M-034

Aggregates 45 mm to 22.4 mm at Quarry

cum

723.00

723.00

M-035

Aggregates 53 mm to 2.8 mm at Quarry

cum

626.44

626.44

M-036

Aggregates 53 mm to 22.4 mm at Quarry

cum

552.21

552.21

M-037

Aggregates 63 mm to 2.8 mm at Quarry

cum

713.93

713.93

M-038

Aggregates 63 mm to 45 mm at Quarry

cum

532.91

532.91

M-039

Aggregates 90 mm to 45 mm at Quarry

cum

465.37

465.37

M-040

Aggregates 10 mm to 5 mm at Quarry

cum

701.00

701.00

M-041

Aggregates 11.2 mm to 0.09 mm at Quarry

cum

503.00

503.00

M-042

Aggregates 13.2 mm to 0.09 mm at Quarry

cum

624.00

624.00

M-043

Aggregates 13.2 mm to 5.6 mm at Quarry

cum

635.00

635.00

M-044

Aggregates 13.2 mm to 10 mm at Quarry

cum

910.00

910.00

M-045

Aggregates 20 mm to 10 mm at Quarry

cum

1087.74

1087.74

M-046

Aggregates 25 mm to 10 mm at Quarry

cum

911.09

911.09

M-047

Aggregates 19 mm to 6 mm at Quarry

cum

847.21

847.21

M-048

Aggregates 37.5 mm to 19 mm at Quarry

cum

829.17

829.17

M-049

Aggregates 37.5 mm to 25 mm at Quarry

cum

751.41

751.41

M-050

Aggregates 6 mm nominal size at Quarry

cum

484.67

484.67

M-051

Aggregates 10 mm nominal size at Quarry

cum

655.60

655.60

M-052

Aggregates 13.2/12.5 mm nominal size at Quarry

cum

756.00

756.00

M-053

Aggregates 20 mm nominal size at Quarry

cum

862.50

862.50

M-054

Aggregates 25 mm nominal size at Quarry

cum

862.50

862.50

M-055

Aggregates 40 mm nominal size at Quarry

cum

758.35

758.35

Sl. No.

Description

Unit

Rate

metre

50.28
129.48

M-056

AC pipe 100 mm dia

M-057

Acrylic polymer bonding coat

litre

M-058

Alluminium Paint

litre

193.17

M-059

Aluminium alloy plate 2mm Thick

sqm

1580.88

M-060

Aluminium alloy/galvanised steel

tonne

46239.26

M-061

Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of
drilling holes, nuts, bolts etc.and signs as applicable

sqm

7902.33

M-062

plastic body of RPM/ASA/HIPS 100 x 100 mm fitted with lense reflectors

nos

167.01

M-063

Barbed wire

kg

58.68

M-064

Bearing (Cost of parts)

nos

#VALUE!

M-065

Bearing (Cast steel rocker bearing assembly of 250 tonne )

nos

55883.28

M-066

Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation,)

nos

0.50

M-067

Bearing (Forged steel roller bearing of 250 tonne

nos

37256.21

M-068

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against
stainless steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components

nos

31752.36

M-069

Bearing (PTFE sliding plate bearing assembly of 80 tonnes )

nos

#VALUE!

M-070

Bearing (Supply of sliding plate bearing of 80 tonne)

nos

22579.27

M-071

Bentonite

kg

2.24

M-072

Binding wire

kg

62.52

M-073

Bitumen ( Cationic Emulsion ) Ex- Bokaro (M.S) Packed

tonne

44006.71

M-074

Bitumen (VG-30 Grade) Ex- Bokaroi Packed

tonne

52269.11

M-075

Bitumen (VG-10 Grade) Ex- Bokaro Packed

tonne

51344.59

M-076

Bitumen (Cutback ) Ex- Bokaro Packed

tonne

46274.16

M-077

Bitumen (emulsion) Ex- Bokaro (M.S) Packed

tonne

45849.96

M-078

Bitumen (modified graded) Ex - Bokaro (CRMB - 55) Packed

tonne

53320.75

M-079

Brick - 75A

each

4.33

M-080

C.I.shoes for the pile

kg

56.39

M-081

Cement

tonne

5789.47

M-082

Cold twisted bars (HYSD Bars) as per IS:1786-2008

tonne

46059.03

M-083

Coller for joints 300 mm dia

nos

#VALUE!

M-084

Compressible Fibre Board(20mm thick)

sqm

603.53

M-085

Connectors/ Staples

each

#VALUE!

M-086

Copper Plate(12m long x 250mmwide)

kg

481.39

(PSC / PPC)
average rate

M-087

Corrosion resistant Structural steel

tonne

46527.33

M-088

Corrugated sheet, 3 mm thick, "Thrie" beam section railing

kg

37.59

M-089

Credit for excavated rock found suitable for use

cum

102.33

M-090

Curing compound

litre

91.13

M-091

Delineators from ISI certified firm as per the standard drawing given in IRC - 79

each

451.08

M-092

Earth Cost or compensation for earth taken from private land

cum

25.10

M-093

Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit
conforming to clause 915.1 of IRC: 83 (part II),

metre

19422.70

M-094

Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each

100 nos

1426.61

M-095

Epoxy compound with accessories for preparing epoxy mortar

kg

282.81

M-096

Epoxy mortar

kg

169.69

M-097

Epoxy primer

kg

9.01

M-098

Epoxy resin-hardner mix for prime coat

kg

481.82

M-099

Flag of red color cloth 600 x 600 mm

each

34.46

M-100

Flowering Plants

each

23.94

M-101

Galvanised MS flat clamp

nos

11.07

M-102

Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size.

sqm

73.09

M-103

Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long

kg

38.63

M-104

Gelatin 80%

kg

112.77

M-105

Geo grids

sqm

77.51

M-106

Geomembrane

sqm

77.51

M-107

Geonets

sqm

77.51

M-108

Geotextile

sqm

60.75

M-109

Geotextile filter fabric

sqm

60.75

M-110

GI bolt 10 mm Dia

nos

11.07

M-111

Grouting pump with agitator

hour

112.77

M-112

Grass (Doob)

kg

3.04

M-113

Grass (Fine)

kg

3.04

M-114

HDPE pipes 75mm dia

metre

152.45

M-115

HDPE pipes 90mm dia

metre

152.45

M-116

Hedge plants

each

22.80

M-117

Helical pipes 600mm diameter

metre

#VALUE!

M-118

Hot applied thermoplastic compound (Sp. Gravity - 2.10)

M-119

HTS strand

M-120

Joint Sealant Compound

M-121

litre

127.55

tonne

62418.78

kg

17.81

Jute netting, open weave, 2.5 cm square opening for seeding and Mulching

sqm

28.71

M-122

LDO for steam curing

litre

#VALUE!

M-123

M.S. Clamps

nos

24.33

M-124

M.S. Clamps

kg

66.31

M-125

M.S.shoes @ 35 Kg per pile of 15 m

kg

42.08

M-126

Mild Steel bars

tonne

48690.69

M-127

Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm
assembly comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system,
all steel sections protected against corrosion and installed by the manufacturer or his authorised representative

metre

21404.46

M-128

Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint
assembly containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements,
support and control system, all steel sections protected against corrosion and installed by the manufacturer or his authorised
representative

M-129

metre

#VALUE!

Nipples 12mm

nos

5.64

M-130

Nuts and bolts

kg

45.42

M-131

Paint

litre

138.35

M-132

Pavement Marking Paint

litre

138.35

M-133

Paving Fabric

sqm

60.75

M-134

Perforated geosynthetic pipe 150 mm dia

metre

65.26

M-135

Perforated pipe of cement concrete, internal dia 100 mm

metre

107.89

M-136

Pesticide

kg

56.39

M-137

Pipes 200 mm dia, 2.5 m long for drainage

metre

124.65

M-138

Plastic sheath, 1.25 mm thick for dowel bars

sqm

10.96

M-139

Plastic tubes 50 cm dia, 1.2 m high

nos

#VALUE!

M-140

Polymer braids

metre

#VALUE!

M-141

Pre moulded Joint filler,25 mm thick for expansion joint.

sqm

708.07

M-142

Pre-coated stone chips of 13.2 mm nominal size

cum

#VALUE!

M-143

Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single
operation for the full length of a joint to ensure water tightness.

metre

#VALUE!

M-144

Pre-moulded asphalt filler board

sqm

708.07

M-145

Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days

kg

#VALUE!

M-146

Primer

kg

90.84

M-147

Quick setting compound

kg

99.20

M-148

Random Rubble Stone

cum

359.72

M-149

RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia

metre

4395.60

M-150

RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia

metre

5319.60

M-151

RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia

metre

924.00

M-152

Reflectorising glass beads

M-153
M-154

kg

70.68

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips)

metre

480.32

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips)

metre

480.32

M-155

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric
strips)

metre

480.32

M-156

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips)

metre

237.03

M-157

Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips)

metre

237.03

M-158

Rivets

each

5.64

M-159

Sand bags (Cost of sand and Empty cement bag)

nos

1.73

M-160

Sapling 2 m high 25 mm dia

each

17.54

M-161

Scrap tyres of size 900 x 20

nos

59.20

M-162

Seeds

kg

21.93

M-163

Selected earth (Including royality @ Rs. 15.0 per cum & compensation @ Rs. 1.10 per cum)

cum

25.10

M-164

Separation Membrane of impermeable plastic sheeting 125 micron thick

sqm

11.00

M-165

Sheathing duct

metre

61.80

M-166

Shrubs

each

11.40

M-167

Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing

cum

528.65

M-168

Sodium vapour lamp

each

679.79

M-169

Square Rubble Coursed Stone

cum

360.24

M-170

Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level

each

#VALUE!

M-171

Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level

each

#VALUE!

M-172

Steel drum 300 mm dia 1.2 m high/empty bitumen drum

nos

90.84

M-173

Steel helmet and cushion block on top of pile head during driving.

kg

51.16

M-174

Steel pipe 25 mm external dia as per

IS:1239

metre

97.11

M-175

Steel pipe 50 mm external dia as per

IS:1239

metre

172.29

M-176

Steel wire rope 20 mm

kg

29.76

M-177

Steel wire rope 40 mm

kg

29.76

M-178

Strip seal expansion join

metre

6043.69

M-179

Structural Steel

tonne

46527.33

M-180

Super plastisizer admixture IS marked as per 9103-1999

kg

112.77

M-181

Synthetic Geogrids as per clause 3102.8 and approved design and specifications.

sqm

85.89

M-182

Through and bond stone

each

6.06

M-183

Tie rods 20mm diameter

nos

47.51

M-184

Tiles size 300 x 300 mm and 25 mm thick

each

23.18

M-185

Timber

cum

31666.24

M-186

Traffic cones with 150 mm reflective sleeve

nos

394.70

M-187

Tube anchorage set complete with bearing plate, permanent wedges etc

nos

34.35

M-188

Unstaked lime

tonne

4427.31

M-189

Water

KL

167.07

M-190

Water based cement paint

litre

75.18

M-191

Welded steel wire fabric

Kg.

#VALUE!

M-192

Wire mesh 50mm x 50mm size of 3mm wire

kg

30.28

M-193

Wooden ballies 2" Dia for bracing

each

17.81

M-194

Wooden ballies 8" Dia and 9 m long (9 m @ Rs. 43.00/m)

each

49.23

M-195

Wooden packing

cum

#VALUE!

M-196

Wooden staff for fastening of flag 25 mm dia, 1.0 m long

each

22.52

VG-30 Grade Bulk Bitumen (Ex-Haldia)

MT

47539.64

M-074 B

average rate

Overheads for Road Works

0.1

Contractors profit for Road Works

0.1
0.25

for input of Overheads or Contractors profit please type in column C as


like below

Overheads for Bridge Works (Rehabilitation)

0.3

Type symble of apostrope(') then input value then one space then
symble of percentage (%) for example '08 %

Contractors profit for Bridge Works

0.1

Overheads for Bridge Works

Lead from Mixing Plant to working site

1 km

Lead for E/W borow area to site

1 km

Lead for fly ash from source to site

1 km

Items No.

Summary of Rates calculated and used for analysis of rates of other items

Unit

Rate

per cm height
per letter

0.30

Item 8.3

Printing new letter and figures of any shade (ii) English Roman

Item 8.8

Painting Two Coats on New Concrete Surfaces

sqm

45.00

Item 8.9

Painting angle iron post two coats

sqm

39.00

Item 12.6 (B)

Cement mortor 1:2 (Excluding OH & CP)

cum

4247.00

Item 12.6 (A)

Cement mortor 1:3 (Excluding OH & CP)

cum

3333.00

Item 12.6 (D)

Cement mortor 1:6 (Excluding OH & CP)

cum

2107.00

Item 12.7 (A )

Course Rubble masonary in cement mortor 1:3 (including OH & CP)

cum

2933.00

Item 12.7 ( B)

Random Rubble masonary in cement mortor 1:6 (including OH & CP)

cum

2879.00

Item 12.8 (A)

PCC Grade M15 including OH & CP for Open Foundation by Mixer

cum

4128.00

Item 12.8 (A)

PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

2887.00

Item 12.8 (B)


PCC

PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3277.00

Item 12.8 (C)

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3297.00

Item 12.8 (C)


RCC

RCC Grade M20 including OH & CP for Open Foundation by Batching Plant

cum

4624.00

Item 12.8 (C)

RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3234.00

Item 12.8 (D)

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3597.00

Item 12.8 (D)

PCC Grade M25 including OH & CP for Open Foundation by Batching Plant

cum

5046.00

Item 12.8 (D)

PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3538.00

Item 12.8 (E)

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3621.00

Item 12.8 (E)

RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3560.00

Item 12.8 (F)

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3632.00

Item 12.8 (F)

PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3569.00

Item 12.8 (G)

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3640.00

Item 12.8 (G)

RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3580.00

Item 12.8 (H)


Case I

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer

cum

3729.00

Item 12.8 (H)


Case II

RCC Grade M35 including OH & CP for Open Foundation by Batching Plant

cum

5195.00

Item 12.8 (H)

RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant

cum

3974.00

Item 12.8 (H)

RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by
Batching Plant

cum

3859.00

Item 12.11 (C) i

PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer

cum

3782.00

Item 12.11 (C) i

PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant

cum

3508.00

Item 12.11 (C)


ii

PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer

cum

3974.00

Item 12.11 (C)


ii

PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant

cum

3698.00

Item 12.11 (C)


iii

PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer

cum

4009.00

Item 12.11 (C)


iii

PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant

cum

3735.00

Item 12.11 (C)


iv

PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Mixer

cum

4090.00

Item 12.11 (C)


iv

PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant

cum

5478.00

Item 12.11 (C)


iv

PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material &
Mechinery by Batching Plant

cum

3814.00

Item 12.11 (F)


iv

PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant

cum

5195.00

Item No. 3.13

Excavation for Structures (Manual Means)

cum

179.00

Item No. 3.13

Excavation for Structures (Mechenical Meanse)

cum

43.00

Item 14.1(A)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

5279.00

Item 14.1(B)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

5839.00

Item 14.1(E)

RCC Grade M20 for super-structure including OH & CP by Batching Plant

cum

6677.76

Item 14.1(C)

RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant

cum

4298.00

Item 14.1(C)

RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant

cum

3582.00

Item 14.2 A

Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP

tonne

51064.00

Item 13.6

Supplying, fitting and placing HYSD including OH & CP for sub-structure

tonne

69327.00

Item 5.17

Fog Seal

sqm

43.00

Item 5.21
Case-I

Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm

sqm

67.00

Item 5.21
Case-II

Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm

sqm

82.00

Item 5.21
Case-IV

Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and
cracked area above 50 %

sqm

110.00

Item 5.21
Case-IV

Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile

sqm

149.00

Item 5.15
Case-I

Slurry Seal Case-I 5 mm thickness

sqm

72.00

Item 5.15
Case-II

Slurry Seal Case-II 3 mm thickness

sqm

51.00

Item 5.15
Case-III

Slurry Seal Case III 1.5 mm thickness

sqm

31.00

Item 5.9 Case-I

Surface Dressing Case-I 19 mm nominal chipping size

sqm

98.00

Item 5.9 CaseII

Surface Dressing Case-II 13 mm nominal size chipping

sqm

79.00

draft copy
Sr No

Directly Used Items


Ref. to
MoRTH
Spec.

1.1

Note
1.4

Description

Annexure - I
Unit

Loading and unloading of stone boulder / stone


aggregates / sand / kanker / moorum.
Placing tipper at loading point, loading with front end loader,
dumping, turning for return trip, excluding time for haulage
and return trip
Unit : cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading point
ii) Loading by front end loader 1 cum bucket capacity
@ 25 cum per hour
iii) Maneuvering, reversing, dumping and turning for
return
iv) Waiting time, unforeseen contingencies etc
Total
a) Machinery
Tipper 5.5 tonnes capacity
Front end-loader 1 cum bucket capacity @ 25
cum/hour
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
Cost for 5.5 cum = a+b+c
Rate per cum = (a+b+c)/ 5.5
Unloading will be by tipping.
Cost of Haulage Excluding Loading and Unloading

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

1 Min
13 Min
2 Min
4 Min
20 Min
hour
hour

0.330
0.330

873.00
1188.00

288.09
392.04

P&M-048
P&M-017

68.01
74.81
822.96
149.63
150.00

say

Haulage of materials by tipper excluding cost of loading,


unloading and stacking.
Unit : t.km
Taking output 10 tonnes load and lead 10 km = 100 t.km
1.4(I)

Case I

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty : 35 km / hour.
a) Machinery.
i) Tipper 10 tonne capacity
Time taken for onward haulage with load
Time taken for empty return trip.
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
cost for 100 t km = a+b+c
Rate per t.km = (a+b+c)/100

hour
hour

0.400
0.290

873.00
873.00

349.20
253.17
60.24
66.26
728.87
7.29
7.30

P&M-048
P&M-048

873.00
873.00

436.50
288.09
72.46
79.70
876.75
8.77
8.80

P&M-048
P&M-048

say
1.4(II)

Case II

Unsurfaced Gravelled Road


Speed with load : 20 km / hour
Speed for empty return trip : 30 km / hour
a)Machinery
Tipper 10 tonnes capacity
Time taken for onward hanlage with load
Time taken for empty return trip
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
Cost for 100 t .km = a+b+c
Rate per t.Km = (a+b+c)/100

hour
hour

0.500
0.330

say
1.4(III)

Case III

Katcha Track and Track in river bed / nallah bed and


choe bed.
Speed with load : 10 km / hour
30

draft copy

Directly Used Items


Speed while returning empty : 15 km / hour
a) Machinery
I) Tipper 10 tonnes capacity
Time taken for onward haulage
Time taken for empty return trip
b) Overheads @ 0.1 on (a)
c) Contractors profit @ 0.1 on (a+b)
Cost for 100 t .km = a+b+c
Rate per t.Km = (a+b+c)/100

Annexure - I

hour
hour

1.000
0.670

873.00
873.00

873.00
584.91
145.79
160.37
1764.07
17.64
17.60

say
1.5

P&M-048
P&M-048

Hand Broken Stone Aggregates 63 mm nominal size


Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and retained
on 50 mm sieve) and stacking as directed
Unit : cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.060

185.07

11.10

L-12

Mazdoor

day

1.500

177.07

265.61

L-13

cum

1.100

536.00

589.60

M-002

Material
Supply of quarried stone 150 - 200 mm size

c)

Overheads @ 0.1 on (a+b)

d)

Contractors profit @ 0.1 on (a+b+c)

86.63
95.29

Rate per cum = a+b+c+d

1048.23
say

1.6

1048.00

Crushing of stone aggregates 13.2 mm nominal size.


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 13 mm nominal size.
Unit : cum
Taking Output = 600 cum at crusher location.
a) Labour
Mate
Mazdoor Skilled
Mazdoor including breaking of any oversize boulder.
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
Cost for 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)*0.95/600

day
day
day

0.760
2.000
17.000

185.07
180.07
177.07

140.65
360.14
3010.19

cum

800.000

511.80

409440.00

M-001

Hour

6.000

16760.52

100563.12

P&M-028

Hour
Hour

20.000
20.000

1188.00
873.00

23760.00
17460.00
55473.41
61020.75
671228.26
1062.78
1063.00

P&M-017
P&M-048

say
Note

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 95% of above cost will be attributed to the production of
600 cum of stone chips of 13.2 mm size and balance 5% to
the production of stone dust which comes out as a byproduct.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.7

Crushing of stone aggregates 20 mm nominal size


31

L-12
L-14
L-13

draft copy

Directly Used Items

Annexure - I

Crushing of stone boulders of 150 mm size in an integrated


stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 20 mm nominal size.
Unit : cum
Taking Output = 670 cum at crusher location.
a) Labour
Mate
Mazdoor Skilled
Mazdoor including breaking of any size boulder.
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
Cost for 670 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)*0.90/670

day
day
day

0.760
2.000
17.000

185.07
180.07
177.07

140.65
360.14
3010.19

cum

800.000

511.80

409440.00

M-001

Hour

6.000

16760.52

100563.12

P&M-028

Hour
Hour

20.000
20.000

1188.00
873.00

23760.00
17460.00
55473.41
61020.75
671228.26
901.65
902.00

P&M-017
P&M-048

say
Note

L-12
L-14
L-13

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 20 and 40 mm.
2. 90% of above cost will be attributed to the production of
670 cum of stone aggregates of 20mm size and balance
10% will be for smaller size aggregates and stone dust
which comes out as a by-product.
3. The integrated stone crusher includes primary and
secondary crushing units.

1.8

Crushing of stone aggregates 40 mm nominal size


Crushing of stone boulders of 150 mm size in an integrated
stone crushing unit of 200 tonnes per hour capacity
comprising of primary and secondary crushing units, belt
conveyor and vibrating screens to obtain stone aggregates
of 40 mm nominal size.
Unit : cum
Taking Output = 750 cum at crusher location.
a) Labour
Mate
Mazdoor Skilled
Mazdoor
b) Material
Stone Boulder of size 150 mm and below
c) Machinery
Integrated stone crusher of 200 TPH including belt
conveyor and vibrating screens
Front end loader 1 cum bucket capacity
Tipper 5.5 cum capacity
d) Overheads @ 0.1 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
Cost for 750 cum = (a+b+c+d+e)x0.85
Rate per cum = (a+b+c+d+e)x0.85/750

day
day
day

0.760
2.000
17.000

185.07
180.07
177.07

140.65
360.14
3010.19

cum

800.000

511.80

409440.00

M-001

Hour

6.000

16760.52

100563.12

P&M-028

Hour
Hour

20.000
20.000

1188.00
873.00

23760.00
17460.00
55473.41
61020.75
570544.03
760.73
761.00

P&M-017
P&M-048

say
Note

1. 800 cum of stone boulders are needed to get 600 cum of


stone chips of size 13.2 mm.
2. 85% of above cost will be attributed to the production of
750 cum of stone aggregates of 40mm size and balance
15% will be for smaller size aggregates and stone dust
which comes out as a by-product.
32

L-12
L-14
L-13

draft copy

5.9

Directly Used Items

510

Annexure - I

3. The integrated stone crusher includes primary and


secondary crushing units.
Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller
Unit = sqm
Taking output = 9000 sqm
Case -1:-19 mm nominal chipping size
a) Labour

b)

c)

Mate

day

0.440

185.07

81.43

L-12

Mazdoor

day

9.000

177.07

1593.63

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

465.00

3348.00

P&M-031

Air compressor 250 cfm

hour

7.200

293.76

2115.07

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2423.52

14541.12

P&M-025

hour

6.000

873.00

5238.00

P&M-048

hour

6.000

1188.00

7128.00

P&M-017

Bitumen pressure distributor

hour

6.000

986.04

5916.24

P&M-004

Smooth wheeled roller 8-10 tonne weight

hour

6.000

665.00

3990.00

P&M-044

tonne

10.800

52269.11

564506.35

M-074

cum

135.000

862.50

116437.77

M-053

Machinery

Material
Bitumen@ 1.20 kg per sqm

d)

Crushed stone chipping,19 mm nominal size @ 0.015


cum per sqm
Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

72530.96
79784.06

Cost for 9000 sqm= a+b+c+d+e

877624.61

Rate per sqm = (a+b+c+d+e)/9000

97.51
say

98.00

Case - II13 mm nominal size chipping


a) Labour

b)

c)

Mate

day

0.440

185.07

81.43

L-12

Mazdoor

day

9.000

177.07

1593.63

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

465.00

3348.00

P&M-031

Air compressor 250 cfm

hour

7.200

293.76

2115.07

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips
from stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2423.52

14541.12

P&M-025

hour

6.000

873.00

5238.00

P&M-048

hour

6.000

1188.00

7128.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Vibratory roller 8-10 tonne weight

hour

6.000

1779.00

10674.00

P&M-059

tonne

9.000

52269.11

470421.96

M-074

cum

90.000

756.00

68040.00

M-052

Machinery

Material
Bitumen@ 1.00 kg per sqm

d)

Crushed stone chipping,13 mm nominal size @ 0.01


cum per sqm
Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

58951.14
64846.26

33

draft copy

Directly Used Items

Annexure - I

Cost for 9000 sqm= a+b+c+d+e

713308.83

Rate per sqm = (a+b+c+d+e)/9000

79.26
say

Note

5.15

516

79.00

1.Where the proposed aggregate fails to pass the stripping


test, an approved adhesion agent may be added to the
binder as per clause 510.2.4. Alternatively, chips may be
pre-coated as per clause 510.2.5
2.Input for the second coat, where required, will be the
same as per the Ist coat mentioned above
Slurry Seal
Providing andlaying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion
and water on a road surface including cleaning of surface,
mixing of slurry seal in a suitable mobile plant, laying and
compacting to provide even riding surface

Case I

5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum, weight of mix =
264 tonnes
weight of mix = 176 tonnes
a) Labour

b)

c)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mechanical broom

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not
exceeding 1.5 tonnes
Water tanker6 KL capacity

hour

6.000

873.00

5238.00

P&M-048

hour

6.000

1143.72

6862.32

P&M-037

hour

2.000

111.24

222.48

P&M-060

tonne

19.360

45849.96

887655.23

M-077

cum

102.080

203.75

20799.25

M-005

tonne

3.520

4427.31

15584.12

M-188

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Residual Binder @ 11 % of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 % of total
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking
density1.5,= 153.12/1.5 = 102.08 cum
Filler @ 2 % of total mix = 80 x 2.2 x 0.02
Cost of water

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

95671.35
105238.48

Cost for 16000 sqm= a+b+c+d+e

1157623.28

Rate per sqm = (a+b+c+d+e)/16000

72.35
say

Case II

72.00

3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour

b)

Mate

day

0.200

185.07

37.01

L-12

Mazdoor

day

5.000

177.07

885.35

L-13

hour

6.000

465.00

2790.00

P&M-031

Machinery
Mechanical broom
34

draft copy

Directly Used Items

c)

Annexure - I

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler
Water tanker6 KL capacity

hour

6.000

873.00

5238.00

P&M-048

hour

2.000

111.24

222.48

P&M-060

tonne

17.160

45849.96

786785.31

M-077

cum

74.800

203.75

15240.83

M-005

tonne

2.640

4427.31

11688.09

M-188

KL

12.000

167.07

2004.82

M-189

Material
Residual Binder @ 13 % of mix = 60 x 2.2 x 0.13
Fine aggregate 3 mm and below 85 % of total mix, 60x
2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,
Filler @ 2 % of total mix =60x 2.2 x 0.02
Cost of water

d)

Overheads @ 0.1 on (a+b+c)

83934.23

e)

Contractors profit @ 0.1 on (a+b+c+d)

92327.65

Cost for 30000 sqm= a+b+c+d+e

1015604.18

Rate per sqm = (a+b+c+d+e)/20000

50.78
say

Case III

51.00

1.5 mm thickness
Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour

b)

c)

Mate

day

0.200

185.07

37.01

L-12

Mazdoor

day

5.000

177.07

885.35

L-13

Mechanical broom

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment,bitumen
emulsion and filler.
Water tanker6 KL capacity

hour

6.000

873.00

5238.00

P&M-048

hour

2.000

111.24

222.48

P&M-060

tonne

12.670

45849.96

580918.99

M-077

cum

43.300

239.00

10348.70

M-022

tonne

1.580

4427.31

6995.15

M-188

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Residual Binder @ 16 % of mix, 36 x 2.2 x 0.16
Fine aggregate 2.36 mm and below,82 % of total
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 % of total mix = 36x 2.2 x 0.02
Cost of water

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

62389.09
68628.00

Cost for 24000 sqm= a+b+c+d+e

754907.99

Rate per sqm = (a+b+c+d+e)/24000

31.45
say

5.17

Note

1.Tack coat, if required to be provided, before laying slurry


seal may be measured and paid separately

518

Fog Spray
Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
35

31.50

draft copy

Directly Used Items

Annexure - I

a) Labour

b)

Mate

day

0.120

185.07

22.21

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

hour

6.000

465.00

2790.00

P&M-031

Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm

c)

hour

6.000

293.76

1762.56

P&M-001

Bitumen emulsion pressure distributor @ 1750 sqm per


hour
Material

tonne

6.000

986.04

5916.24

P&M-004

Bitumenemulsion @ 0.75 kg per sqm

tonne

7.880

45849.96

361297.68

d)

Overheads @ 0.1 on (a+b+c)

37231.99

e)

Contractors profit @ 0.1 on (a+b+c+d)

40955.19

Cost for 10500 sqm= a+b+c+d+e

M-077

450507.08

Rate per sqm = (a+b+c+d+e)/10500

42.91
say

43.00

1.In case it is decided by the engineer to blind the fog spray,


the following may be added
a) Labour

c)

Mate

day

0.160

185.07

29.61

L-12

Mazdoor for precoating of grit

day

4.000

177.07

708.28

L-13

cum

26.250

261.00

6851.25

M-024

tonne

0.790

45849.96

36221.47

M-077

Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm

c)

Bitumenemulsion for precoating grit @ 2 % of


grit,39.38 x 0.02
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4381.06
4819.17

Cost for 10500 sqm = a+b+c+d

53010.84

Rate per sqm = (a+b+c+d)/10500

5.05
say

5.21

522
Case - I

5.00

Crack Prevention Courses


Stress Absorbing Membrane (SAM) crack width less
than 6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @
0.11 cum per 10 sqm with hydraulic chip spreader,
sweeping the surface for uniform spread of aggregates and
surface finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

665.00

3990.00

P&M-044

tonne

9.450

53320.75

503881.06

Machinery

Material
Modified binder
36

M-078

draft copy

Directly Used Items


Crushed stone aggregates 5.6 mm size
d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

Annexure - I
cum

105.000

484.67

M-050

58487.78
64336.56

Cost for 10500 sqm= a+b+c+d+e

707702.16

Rate per sqm = (a+b+c+d+e)/10500

67.40
say

Case - II

50890.00

67.00

Stress Absorbing Membrane (SAM) with crack width 6


mm to 9 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfem capacity

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

665.00

3990.00

P&M-044

tonne

11.550

53320.75

615854.63

M-078

cum

105.000

655.60

68838.32

M-051

Machinery

Material
Modified binder
Crushed stone chipping 11.2 mm size

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

71479.97
78627.97

Cost for 10500 sqm= a+b+c+d+e

864907.64

Rate per sqm = (a+b+c+d+e)/10500

82.37
say

Case III

82.00

Stress Absorbing Membrane (SAM) crack width above 9


mm and cracked area above 50 %
Providing and laying a single coatn of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 % after cleaning
with a mechanical broom, using modified binder complying
with clause 521, sprayed at the rate of 15 kg per 10 sqm
and spreading 11.2 mm crushed stone aggregates @ 0.12
cum per 10 sqm, sweeping the surface for uniform spread
of aggregates and surface finished to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Machinery
37

draft copy

Directly Used Items

c)

Annexure - I

Mechanical broom @ 1250 sqm per hour

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfem capacity

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

665.00

3990.00

P&M-044

tonne

15.750

53320.75

839801.77

M-078

cum

126.000

655.60

82605.98

M-051

Material
Modified binder
Crushed stone aggregates 11.2 mm size

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

95292.85
104822.13

Cost for 10500 sqm= a+b+c+d+e

1153043.47

Rate per sqm = (a+b+c+d+e)/10500

109.81
say

Case IV

110.00

Case - IV : Bitumen Impregnated Geotextile


Providing and laying a bitumen impregnated geotextile layer
after cleaning the road surface, geotextile conforming to
requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration
and constructed to the requirement of clause 704.4.5
Unit = sqm
Taking output = 3500 sqm
a) Labour

b)

Mate

day

0.560

185.07

103.64

L-12

Mazdoor

day

12.000

177.07

2124.84

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

hour

2.800

465.00

1302.00

P&M-031

Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfem capacity
Bitumen pressure distributor @ 1750 sqm per hour
Pneumatic roller

c)

hour

2.800

293.76

822.53

P&M-001

tonne

2.000

986.04

1972.08

P&M-004

hour

2.000

1143.72

2287.44

P&M-037

tonne

3.680

51344.59

188948.09

M-075

sqm

3850.000

60.75

233893.61

M-108

Material
Paving grade bitumen of 80 - 100 penetration @ 1.05
kg per sqm
Geotextile including 10 % for overlaps

d)

Overheads @ 0.1 on (a+b+c)

e)

Contractors profit @ 0.1 on (a+b+c+d)

43186.82
47505.50

Cost for 10500 sqm= a+b+c+d+e

522560.53

Rate per sqm = (a+b+c+d+e)/3500

149.30
say

NOTE

8.3

801

As bitumen overlay construction shallfollow closely the fabric


placement on the same day, an output of 3500 sqm only
has been considered for the analysis which will cover a
length of 500 m, of 7 m widecarriagway. This can be
conveniently overlaid by a bitumenious course in a day
Printing new letter and figures of any shade
Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
ii) English and Roman
Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
38

149.00

draft copy

Directly Used Items

Annexure - I

a) Labour
Mate

day

0.07

185.07

12.95

L-12

Painter Ist class

day

1.25

223.29

279.11

L-18

Mazdoor

day

0.50

177.07

88.54

L-13

Litre

0.50

138.35

69.18

M-131

b) Material
Paint
c) Overheads @ 0.1 on (a+b)

44.98

d) Contractors profit @ 0.1 on (a+b+c)

49.48

Cost for 1600 cm = a+b+c+d

544.23

Rate per cm height per letter = (a+b+c +d)/1600

0.34
say

8.8

803

0.30

Painting Two Coats on New Concrete Surfaces


Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate

day

0.12

185

22.21

L-12

Painter

day

2.00

223

446.58

L-18

Mazdoor

day

1.00

177

177.07

L-13

Litre

6.00

138

830.12

M-132

b) Material
Paint conforming to requirement of clause 803.3.
Add for scaffolding @ 1% of labour cost where required

8.30

c) Overheads @ 0.1 on (a+b)

148.43

d) Contractors profit @ 0.1 on (a+b+c)

163.27

Cost for 40 sqm = a+b+c+d

1795.98

Rate per sqm = (a+b+c+d)/40


8.9

803

44.90
say

45.00

Painting on Steel Surfaces


Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate

day

0.03

185

5.55

L-12

Painter

day

0.45

223

100.48

L-18

Mazdoor

day

0.25

177

44.27

L-13

Litre

1.25

138

172.94

M-131

b) Material
Paint ready mixed approved brand.
Add @ 1% on cost of material for scaffolding

1.73

c) Overheads @ 0.1 on (a+b)

32.50

d) Contractors profit @ 0.1 on (a+b+c)

35.75

Cost for 10 sqm = a+b+c+d

393.22

Rate per sqm = (a+b+c+d)/10

39.32
say

12.6

SubCement mortar1:3 (1cement :3 sand)


analysis
(A)
Unit = 1 cum
Taking output = 1 cum
a) Materials
39

39.00

draft copy

Directly Used Items


Cement
Sand
b) Labour
Mate
Mazdoor
Total Material and Labour = (a+b)
SubCement mortar1:2 (1cement :2 sand)
analysis
(B)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement
Sand
b) Labour
Mate
Mazdoor
Total Material and Labour = (a+b)

12.7

Cement mortar1:6 (1cement :6 sand)


Subanalysis
(D)
Unit = 1 cum
Taking output = 1 cum
a) Materials
Cement
Sand
b) Labour
Mate
Mazdoor
Total Material and Labour = (a+b)
1400
Stone masonry work in cement mortar 1:3 in foundation
complete as drawing and Technical Specification

(A)

Annexure - I
MT
cum

0.51
1.05

5789.47
203.75

2952.63
213.94

M-81
M-5

day
day

0.04
0.90

185.07
177.07

MT
cum

0.672
0.933

5789.47
203.75

day
day

0.04
0.90

185.07
177.07

MT
cum

0.288
1.337

5789.47
203.75

day
day

0.04
0.90

185.07
177.07

7.40 L-12
159.36 L-13
2107.00

cum
each

5.50
35.00

360.24
6.06

1981.32
211.97

M-169
M-182

cum

1.50

3333.00

4999.50

Item 12.6
(A)

day
day
day

0.66
7.50
9.00

185.07
234.29
177.07

L-12
L-11
L-13

say

122.15
1757.18
1593.63
2666.44
1333.22
14665.40
2933.08
2933.00

M-148
M-182

7.40 L-12
159.36 L-13
3333.00

3890.53
190.17

M-81
M-5

7.40 L-12
159.36 L-13
4247.00

1667.37
272.45

M-81
M-5

Unit = cum
Taking output = 5 cum
Square Rubble Coursed Rubble Masonry (first sort)
a)

Material
Stone
Through and bond stone
(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5
1405.3

B) Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through and bond stone
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 12.6 A)
40

cum
Nos

5.50
35.00

359.72
6.06

1978.45
211.97

cum

1.55

3333.00

5166.15

draft copy

Directly Used Items


b) Labour
Mate
Mason
Mazdoor
c) Overheads @ 0.25 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

Annexure - I
day
day
day

0.62
6.00
9.00

185.07
234.29
177.07

say
@

12.7 (Add)

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry
works.
Stone masonry work in cement mortar 1:6 in foundation
complete as drawing and Technical Specification

1400

1405.3

Unit = cum
Taking output = 5 cum
B) Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a) Material
Stone
Through and bond stone
(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)
Cement mortar 1:3 (Rate as in item 13.6 D)
b) Labour
Mate
Mason
Mazdoor
c) Overheads @ 0.25 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

cum
Nos

5.50
35.00

359.72
6.06

1978.45
211.97

cum

1.55

280.00

434.00

day
day
day

0.62
6.00
9.00

185.07
234.29
177.07

say
@

12.8

114.74 L-12
1405.74
L-11
1593.63 L-13
2617.67
1308.84
14397.19
2879.44
2879.00

114.74 L-12
1405.74 L-11
1593.63 L-13
1434.63
717.32
7890.48
1578.10
1578.00

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry
works.

1500, 1700 Plain/Reinforced cement concrete in open foundation


& 2100 complete as per drawing and technical specifications
A

PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 63 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 4% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
41

M-148
M-182

MT
cum
cum
cum
cum

4.13
6.75
8.10
4.05
1.35

5789.47
203.75
758.35
862.50
655.60

23910.53
1375.34
6142.67
3493.13
885.06

day
day
day

0.86
1.50
20.00

185.07
234.29
177.07

159.16
351.44
3541.40

hour
hour

6.00
6.00
2,887.00

211.68
361.80

1270.08
2170.80
1731.98
11257.90
5628.95

draft copy

Directly Used Items

Annexure - I

Cost for 15 cum = a+b+c+d+e+f


Rate per cum (a+b+c+d+e+f)/15
say
Note

12.8

12.8

Nedle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
B
PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
C
RCC Grade M20
Unit = cum
Case I Using concrete mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump

61918.44
4127.90
4128.00

Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 km, L-lead in km
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 4% on cost of concrete i.e.cost of material,
labour and machinery
42

MT
cum
cum
cum
cum

5.16
6.75
5.40
5.40
2.70

5789.47
203.75
758.35
862.50
655.60

29873.68
1375.34
4095.11
4657.51
1770.13

day
day
day

0.86
1.50
20.00

185.07
234.29
177.07

159.16
351.44
3541.40

hour
hour

6.00
6.00
3,277.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum

5.21
6.75
8.10
5.40

5789.47
203.75
862.50
655.60

30163.16
1375.34
6986.27
3540.26

day
day
day

0.86
1.50
20.00

185.07
234.29
177.07

159.16
351.44
3541.40

hour
hour

6.00
6.00
3,297.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum

41.66
54.00
64.80
43.20

5789.47
203.75
862.50
655.60

241189.47
11002.74
55890.13
28322.05

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

hour
hour
hour
hour
T-km
hour

6.00
6.00
6.00
15.00
300L
6
3,234.00

2488.00
1698.00
1188.00
854.55
4.32
234.36

14928.00
10188.00
7128.00
12818.25
1140.00 L= 1
1406.16
15522.34

draft copy

Directly Used Items

Annexure - I

e) Overheads @ 0.25 on (a+b+c+d)


f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = ( a+b+c+d+e+f )/120
12.8

PCC Grade M25


Unit = cum
Case I Using concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3.75% of cost of concrete i.e.cost of
material, labour and machinery
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120
12.8

say

100895.18
50447.59
554923.50
4624.36
4624.00

E
Case I

RCC Grade M25


Unit = cum
Using concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour

MT
cum
cum
cum
cum

5.99
6.75
5.40
5.40
2.70

5789.47
203.75
758.35
862.50
655.60

34678.95
1375.34
4095.11
4657.51
1770.13

day
day
day

0.86
1.50
20.00

185.07
234.29
177.07

159.16
351.44
3541.40

hour
hour

6.00
6.00
3,597.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
cum

47.95
54.00
43.20
43.20
21.60

5789.47
203.75
758.35
862.50
655.60

277605.26
11002.74
32760.89
37260.09
14161.02

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

hour

6
3,538.00

234.36

1406.16
15916.65

MT
cum
cum
cum

43

14928.00
10188.00
7128.00
12818.25
1140.00 L= 1

6.05
6.75
8.10
5.40

say

110090.16
55045.08
605495.90
5045.80
5046.00

5789.47
203.75
862.50
655.60

35026.32
1375.34
6986.27
3540.26

draft copy

Directly Used Items


Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II With Batching Plant, Transit Mixer and Conrete Pump

12.8

Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
F
PCC Grade M30
Unit = cum
Case I Using Concrete Mixer
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
44

Annexure - I
day
day
day

0.86
1.50
20.00

185.07
234.29
177.07

159.16
351.44
3541.40

hour
hour

6.00
6.00
3,621.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
Kg

48.38
54.00
64.80
43.20
193.52

5789.47
203.75
862.50
655.60
112.77

280094.74
11002.74
55890.13
28322.05
21823.45

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

hour

6.00
3,740.00

234.36

1406.16

MT
cum
cum
cum
cum

6.08
6.75
5.40
5.40
2.70

5789.47
203.75
758.35
862.50
655.60

35200.00
1375.34
4095.11
4657.51
1770.13

day
day
day

0.86
1.50
20.00

185.07
234.29
177.07

159.16
351.44
3541.40

hour
hour

6.00
6.00
3,632.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
cum

48.60
54.00
43.20
43.20
21.60

5789.47
203.75
758.35
862.50
655.60

281368.42
11002.74
32760.89
37260.09
14161.02

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

14928.00
10188.00
7128.00
12818.25
1140.00 L= 1

draft copy

12.8

12.8

Directly Used Items


Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
G
RCC Grade M30
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II
Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
H
RCC Grade M35
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
45

Annexure - I
hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

14928.00
10188.00
7128.00
12818.25
1140.00 L= 1

hour

6.00
3,569.00

234.36

1406.16

MT
cum
cum
cum

6.10
6.75
8.10
5.40

5789.47
203.75
862.50
655.60

35315.79
1375.34
6986.27
3540.26

day
day
day

0.86
1.50
20.00

185.07
234.29
177.07

159.16
351.44
3541.40

hour
hour

6.00
6.00
3,640.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum

48.80
54.00
64.80
43.20

5789.47
203.75
862.50
655.60

282526.32
11002.74
55890.13
28322.05

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

hour

6.00
3,580.00

234.36

1406.16

MT
cum
cum
cum

6.33
6.75
8.10
5.40

5789.47
203.75
862.50
655.60

36647.37
1375.34
6986.27
3540.26

day
day
day

0.86
1.50
20.00

185.07
234.29
177.07

159.16
351.44
3541.40

hour
hour

6.00
6.00

211.68
342.36

1270.08
2054.16

14928.00
10188.00
7128.00
12818.25
1296.00 L= 1

draft copy

Directly Used Items

Annexure - I

Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)


Case II Using Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond
1 Km, L - lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
d) Formwork @ 3% on cost of concrete i.e.cost of material,
labour and machinery
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120

3,729.00

MT
cum
cum
cum
Kg

50.64
54.00
64.80
43.20
202.56

5789.47
203.75
862.50
655.60
112.77

293178.95
11002.74
55890.13
28322.05
22842.90

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

hour

6.00
3,859.00

234.36

12.11

1406.16
13891.40

say
Note:

14928.00
10188.00
7128.00
12818.25
1296.00 L= 1

Rate per cum (a+b+c+d)/120 Excluding OH & CP


Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

119234.54
59617.27
655789.98
5464.92
5465.00
3974.00

1200, 1500 Plain/Reinforced cement concrete, in well foundation


& 1700 complete as per drawing and technical specification

C
Case I
(i)

Bottom Plug
Concrete to be placed using tremie pipe
Using Concrete Mixer
PCC Grade M20
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane 3 tonnes capacity for handling tremie pipe

46

MT
cum
cum
cum
cum
Kg

5.55
6.75
5.40
5.40
2.70
18.60

5789.47
203.75
758.35
862.50
655.60
112.77

32131.58
1375.34
4095.11
4657.51
1770.13
2097.54

day
day
day

0.90
1.50
20.00

185.07
234.29
177.07

166.56
351.44
3541.40

hour
hour
hour

6.00
6.00
6.00

211.68
342.36
535.00

1270.08
2054.16
3210.00

draft copy

Directly Used Items


Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
10% extra cement may be added where under water
concreting is involved.
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

Annexure - I
3782.00

Note

(ii)

MT
cum
cum
cum
Kg

44.40
54.00
64.80
43.20
148.80

5789.47
203.75
862.50
655.60
112.77

257052.63
11002.74
55890.13
28322.05
16780.33

day
day
day

0.88
3.00
18.00

185.07
234.29
177.07

162.86
702.87
3187.26

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

hour

6.00
3508.00

234.36

1406.16

MT
cum
cum
cum
cum
Kg

5.99
6.75
5.40
5.40
2.70
21.60

5789.47
203.75
758.35
862.50
655.60
112.77

34678.95
1375.34
4095.11
4657.51
1770.13
2435.85

day
day
day

0.90
1.50
20.00

185.07
234.29
177.07

166.56
351.44
3541.40

hour
hour
hour

6.00
6.00
6.00

211.68
342.36
535.00

1270.08
2054.16
3210.00

14928.00
10188.00
7128.00
12818.25
1296.00 L= 1

PCC Grade M25

Case I

Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
47

3974.00

MT
cum
cum
cum
Kg

47.88
54.00
64.80
43.20
172.80

5789.47
203.75
862.50
655.60
112.77

277200.00
11002.74
55890.13
28322.05
19486.84

day
day
day

0.88
3.00
18.00

185.07
234.29
177.07

162.86
702.87
3187.26

draft copy

Directly Used Items


c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
PCC Grade M30
Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
(iv)
PCC Grade M35

Annexure - I
hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

14928.00
10188.00
7128.00
12818.25
1296.00 L= 1

hour

6.00
3698.00

234.36

1406.16

MT
cum
cum
cum
cum
Kg

6.08
6.75
5.40
5.40
2.70
21.60

5789.47
203.75
758.35
862.50
655.60
112.77

35200.00
1375.34
4095.11
4657.51
1770.13
2435.85

day
day
day

0.90
1.50
20.00

185.07
234.29
177.07

166.56
351.44
3541.40

hour
hour
hour

6.00
6.00
6.00

211.68
342.36
535.00

1270.08
2054.16
3210.00

(iii)
Case I

Case I

Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
48

4009.00

MT
cum
cum
cum
Kg

48.64
54.00
64.80
43.20
172.80

5789.47
203.75
862.50
655.60
112.77

281600.00
11002.74
55890.13
28322.05
19486.84

day
day
day

0.88
3.00
18.00

185.07
234.29
177.07

162.86
702.87
3187.26

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

hour

6.00
3735.00

234.36

1406.16

MT
cum
cum

6.29
6.75
5.40

5789.47
203.75
758.35

36415.79
1375.34
4095.11

14928.00
10188.00
7128.00
12818.25
1296.00 L= 1

draft copy

Directly Used Items


20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie
pipe
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Case II Using Batching Plant, Transit Mixer and Crane/concrete
pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer
Concrete Pump
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)
Add 5% of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreteing with tremie pipe..

Annexure - I
cum
cum
Kg

5.40
2.70
21.60

862.50
655.60
112.77

4657.51
1770.13
2435.85

day
day
day

0.90
1.50
20.00

185.07
234.29
177.07

166.56
351.44
3541.40

hour
hour
hour

6.00
6.00
6.00

211.68
342.36
535.00

1270.08
2054.16
3210.00

4090.00

MT
cum
cum
cum
Kg

50.28
54.00
64.80
43.20
172.80

5789.47
203.75
862.50
655.60
112.77

291094.74
11002.74
55890.13
28322.05
19486.84

day
day
day

0.88
3.00
18.00

185.07
234.29
177.07

162.86
702.87
3187.26

hour
hour
hour
hour
T-Km

6.00
6.00
6.00
15.00
300L

2488.00
1698.00
1188.00
854.55
4.32

hour

6.00
3814.00

234.36

1406.16
20492.47

d) Overheads @ 0.25 on (a+b+c)


e) Contractors profit @ 0.1 on (a+b+c+d)
cost of 120 cum = a+b+c+d+e
Rate per cum (a+b+c+d+e)/120
F
iv)
Case II

14928.00
10188.00
7128.00
12818.25
1296.00 L= 1

Say

119526.59
59763.30
657396.25
5478.30
5478.00

Well cap
RCC Grade M35
Using Batching Plant, Transit Mixer and Conrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
49

MT
cum
cum
cum

50.64
54.00
64.80
43.20

5789.47
203.75
862.50
655.60

293178.95
11002.74
55890.13
28322.05

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

hour
hour

6.00
6.00

2488.00
1698.00

14928.00
10188.00

draft copy

Directly Used Items


Loader(capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 3% of (a+b+c)
d) Overheads @ 0.25 on (a+b+c)
e) Contractors profit @ 0.1 on (a+b+c+d)
cost of 120 cum = a+b+c+d+e
Rate per cum (a+b+c+d+e)/120

Annexure - I
hour

6.00

1188.00

hour
T-Km
hour

15.00
300L
6.00

854.55
4.32
234.36

Say

3.13

Note

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, admixers @ 0.4% of weight of
cement may be added for achieving desired slump of
concrete.

304

Excavation for Structures

7128.00
12818.25
1296.00 L= 1
1406.16
13206.12
113352.49
56676.25
623438.72
5195.32
5195.00

Earth work in excavation of foundation of structures as per


drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaning earth locally for road work.
I) Ordinary soil
Unit = cum
Taking output = 10 cum
A

Manual Means
(i) Depth upto 3 m
a) Labour
Mate

day

0.320

185.07

59.22

L-12

Mazdoor

day

8.000

177.07

1416.56

L-13

b) Overheads @ 0.1 on (a)

147.58

c) Contractors profit @ 0.1 on (a+b)

162.34

Cost for 10 cum = a+b+c

1785.70

Rate per cum = (a+b+c)/10

178.57
say

Note

179.00

Cost of dewatering may be added where required upto 10 %


of labour cost Assessment for dewatering shall be made as
per site conditions..
Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 300 cum
a) Labour
Mate

day

0.32

185

59.22

Mazdoor

day

8.00

177

1416.56

hour

6.00

1516

9097.92

b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c) Overheads @ 0.1 on (a+b)

1057.37

d) Contractors profit @ 0.1 on (a+b+c)

1163.11

Cost for 300 cum = a+b+c+d

12794.18

Rate per cum = (a+b+c+d)/300

42.65
say

Note

Cost of dewatering upto 5% of (a+b) may be added, where


required. Assessment for dewatering shall be made as per
site conditions..
50

43.00

draft copy
13.6

14.1

Directly Used Items


Section
1600 &
2200

1500
&1600
1700
A
Case II

Supplying, fitting and placing HYSD bar reinforcement in


sub-structure complete as per drawing and technical
specifications
Output : MT
Taking output = 1 MT
a) Material
HYSD bars including 5% overlaps and wastage
Binding wire
b) Labour for cutting, bending, shifting to site, tying and
placing in position
Mate
Blacksmith
Mazdoor
c) Overheads @ 0.25 on (a+b)
d) Contractors profit @ 0.1 on (a+b+c)
Rate for per MT (a+b+c+d)

B
Case II

MT
kg

1.05
6.00

46059.03
63.00

48361.98
378.00

day
day
day

0.34
2.00
6.50

185.07
234.29
177.07

say

62.92
468.58
1150.96
12605.61
6302.81
69330.86
69331.00

Furnishing and Placing Reinforced/Prestressed cement


concrete in super-structure as per drawing and
Technical Specification
RCC Grade M20
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
(i)
(p)

Annexure - I

MT
cum
cum
cum

40.92
54.00
64.80
43.20

5789.47
203.75
862.50
655.60

236905.26
11002.74
55890.13
28322.05

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

hour
hour
hour

6.00
6.00
6.00

2488.00
1698.00
1188.00

14928.00
10188.00
7128.00

hour
T-Km
hour

15.00
300L
6.00
383931.00

854.55
4.32
234.36

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120
cum
d) Formwork and staging 20 % of (a+b+c)
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 15 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f)/120

12818.25
1296.00 L= 1
1406.16

383931.00
20.00

say

76786.20
115179.30
57589.65
633486.15
5279.05
5279.00

5789.47
203.75

277605.26
11043.49

RCC Grade M25


Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand

MT
cum
51

47.95
54.20

draft copy

Directly Used Items


20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 20 % of (a+b+c)
e)

Overheads @ 0.25 on (a+b+c+d)

f)

Contractors profit @ 0.1 on (a+b+c+d+e)

Annexure - I
cum
cum

64.80
43.20

862.50
655.60

55890.13
28322.05

day
day
day

0.84
3.00
18.00

185.07
234.29
177.07

155.46
702.87
3187.26

hour
hour
hour

6.00
6.00
6.00

2488.00
1698.00
1188.00

14928.00
10188.00
7128.00

hour
T-Km
hour

15.00
300L
6.00
424671.00

854.55
4.32
234.36

for

424671.00
20.00

84934.20
127401.30
63700.65

Cost for 15 cum= a+b+c+d+e+f

700707.15

Rate per cum (a+b+c+d+e+f)/120

C
Case II

5839.23
say

5839.00

RCC Grade M 30
Using Batching Plant, Transit Mixer and Concrete Pump.

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)
(p)

12818.25
1296.00 L= 1
1406.16

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120
cum
d) Formwork and staging 20 % of (a+b+c)
e) Overheads @ 0.25 on (a+b+c+d)
f) Contractors profit @ 0.1 on (a+b+c+d+e)
Cost for 120 cum = a+b+c+d+e+f
52

MT
cum
cum
cum

48.79
54.60
64.80
43.20

5789.47
203.75
862.50
655.60

282468.42
11124.99
55890.13
28322.05

day
day
day

0.88
3.00
19.00

185.07
234.29
177.07

162.86
702.87
3364.33

hour
hour
hour

6.00
6.00
6.00

2488.00
1698.00
1188.00

14928.00
10188.00
7128.00

hour
T-Km
hour

15.00
300L
6.00
429801.00

854.55
4.32
234.36

12818.25
1296.00 L= 1
1406.16

429801.00
20.00

85960.20
128940.30
64470.15
709171.65

draft copy

Directly Used Items

Annexure - I

Rate per cum (a+b+c+d+e+f)/120


say
Rate per cum (a+b+c+d)/120 ( including formwork and excluding OH & CP)
Rate per cum (a+b+c+d)/120 ( excluding formwork and Excluding OH & CP)

PSC Grade M-40


Using concret mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4% of cement
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Basic Cost of Labour, Material & Mechinery (a+b+c) for 15 cum

5909.76
5910.00
4298.00
3582.00

E
Case 1

Case II

MT
cum
cum
cum
kg

6.45
6.75
8.10
5.40
25.80

5789.47
203.75
862.50
655.60
112.77

37342.11
1375.34
6986.27
3540.26
2909.49

day
day
day

0.96
2.00
22.00

185.07
234.29
177.07

177.67
468.58
3895.54

hour
hour

6.00
6.00
60020.00

211.68
342.36

1270.08
2054.16

MT
cum
cum
cum
kg
Kg

51.60
54.00
64.80
43.20
206.40
216.00

5789.47
203.75
862.50
655.60
112.77
112.77

298736.84
11002.74
55890.13
28322.05
23275.94
24358.55

day
day
day

0.94
3.50
20.00

185.07
234.29
177.07

173.97
820.02
3541.40

hour
hour
hour

6.00
6.00
6.00

2488.00
1698.00
1188.00

14928.00
10188.00
7128.00

hour
T-Km
hour

15.00
300L
6.00
493887.00

854.55
4.32
234.36

Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture @ 0.4% of cement
Admixer
b) Labour
Mate
Mason
Mazdoor
c) Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Mechinery (a+b+c) for 120 cum
For formwork and staging add the following:
(i)

For solid slab super-structure, 18-28% of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Mechinery (a+b+c)
120 cum
d) Formwork and staging 18 % of (a+b+c)
e)

Overheads @ 0.25 on (a+b+c+d)

f)

Contractors profit @ 0.1 on (a+b+c+d+e)

for

12818.25
1296.00 L= 1
1406.16

493887.00
18.00

88899.66
145696.67
72848.33

Cost for 15 cum= a+b+c+d+e+f

801331.66

Rate per cum (a+b+c+d+e+f)/120

6677.76
say
53

6678.00

draft copy

Directly Used Items


Note

Annexure - I

1.Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, admixers conforming IS: 9103
@ 0.4% of weight of cement may be added for achieving
desired slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of
cement will be as per approved mix design. Similarly, the
provision for coarse and fine aggregates is for estimating
purpose and the exact quantity shall be as per the mix
design.
3. The items like needle and surface vibrators are part of
minor T & P which is already covered under the overhead
charges. As such these items have not been added
seperately in the rate analysis.

14.2

1600

A) Supplying ,fitting and placing HYSD bar


reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5% for laps and wastage
Binding wire
b) Labour for cutting, bending, tying and placing in position
Mate
Blacksmith
Mazdoor
Per Cum Basic Cost of Labour, Material & Mechinery (a+b+c)

54

MT
Kg

1.05
8.00

46059.03
62.52

48361.98
500.16

day
day
day

0.44
3.00
8.00
51064.00

185.07
234.29
177.07

81.43
702.87
1416.56

CHAPTER-1

D
i
f
f
.

CARRIAGE OF MATERIALS
Item
No.
1.1

1.2
1.3
1.4
(i)
(ii)
(iii)

Descriptions

Unit

Loading and unloading of stone boulder / stone aggregates / sand /


kanker /Earth/ moorum. (Placing tipper at loading point, loading with front
end loader, dumping, turning for return trip, excluding time for haulage and
return trip)

cum

a
150.00 ###

Loading and Unloading of Boulders by Manual Means

cum

178.00 ###

tonne

232.00 ###

Loading and Unloading of Cement, Steel ,Bitumen,Hume Pipe (NP4) by


Manual Means and stacking.

Rate (in Rs.)

i
n
R
t
e

Cost of Haulage Excluding Loading and Unloading


Surfaced Road

tonne.km

7.30

###

Unsurfaced Gravelled Road

tonne.km

8.80

###

Katcha Track and Track in river bed / nallah bed and choe bed.

tonne.km

17.60

###

25

CHAPTER-2

SITE CLEARANCE
Item
No.
2.1

(i)
(ii)
(iii)
(iv)
2.2
2.3

(i)

Descriptions

Unit

Rate (in Rs.)

Cutting of Trees, including Cutting of Trunks, Branches and Removal (Cutting of


trees, including cutting of trunks, branches and removal of stumps, roots, stacking
of serviceable material with all lifts and up to a lead of 1000 mtrs and earth filling in
the depression/pit.)
Girth from 300 mm to 600 mm

each

154.00 ###

Girth from 600 mm to 900 mm

each

264.00 ###

Girth from 900 mm to 1800 mm

each

529.00 ###

each

1017.00 ###

hectare

11161.00 ###

In area of light jungle

hectare

33689.00 ###

In area of thorny jungle

hectare

45056.00 ###

In area of light jungle

hectare

39036.00 ###

In area of thorny jungle

hectare

47173.00 ###

Girth above 1800 mm


Clearing Grass and Removal of Rubbish
Clearing and Grubbing Road Land .(Clearing and grubbing road land including
uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300
mm, removal of stumps of trees cut earlier and disposal of unserviceable materials
and stacking of serviceable material to be used or auctioned up to a lead of 1000
metres including removal and disposal of top organic soil not exceeding 150 mm in
thickness.)
By Manual Means:-

A
B
(ii)
A
B
2.4

(i)

By Mechanical Means

Dismantling of Structures (Dismantling of existing structures like culverts, bridges,


retaining walls and other structure comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding wherever necessary, sorting the
dismantled material, disposal of unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 metres)
Lime /Cement Concrete

By Manual Means

Lime Concrete, cement concrete grade M-10 and below

cum

223.00 ###

Cement Concrete Grade M-15 & M-20

cum

268.00 ###

Prestressed / Reinforced cement concrete grade M-20 & above

cum

728.00 ###

II

By Mechanical Means for items No. 202( b) & ( c)

Cement Concrete Grade M-15 & M-20

cum

325.00 ###

Prestressed / Reinforced cement concrete grade M-20 & above

cum

553.00 ###

(ii)

Dismantling Brick / Tile work

In lime mortar

cum

134.00 ###

In cement mortar

cum

179.00 ###

In mud mortar

cum

116.00 ###

Dry brick pitching or brick soling

cum

107.00 ###

(iii)

Dismantling Stone Masonry

Rubble stone masonry in lime mortar

cum

152.00 ###

Rubble stone masonry in cement mortar.

cum

179.00 ###

Rubble Stone Masonry in mud mortar.

cum

134.00 ###

Dry rubble masonry

cum

125.00 ###

Dismantling stone pitching/ dry stone spalls.

cum

116.00 ###

26

Dismantling boulders laid in wire crates including opening of crates and stacking
dismantled materials.

cum

134.00 ###

(iv)

Wood work wrought framed and fixed in frames of trusses upto a height of 5 m
above plinth level

cum

340.00 ###

(v)

Steel work in all types of sections upto a height of 5 m above plinth level excluding
cutting of rivet.

Including dismembering

tonne

907.00 ###

Excluding dismembering.

tonne

670.00 ###

Extra over item No( V ) A and( V ) B for cutting rivets.

tonne

(vi)

In lime/Cement mortar

In mud mortar

1000
numbers
1000
numbers

781.00 ###
279.00 ###

Scraping of Stone from dismantled stone masonry

In cement and lime mortar

cum

In Mud mortar

cum

(viii)

Scarping plaster in lime or cement mortar from brick/ stone masonry

sqm

(ix)

Removing all type of hume pipes and stacking within a lead of 1000 metres
including earthwork and dismantling of masonry works.

Up to 600 mm dia

metre

Above 600 mm to 900 mm dia

metre

Above 900 mm

metre

2.5

###

Scraping of bricks dismantled from brick work including stacking.

(vii)

6.70

313.00 ###
67.00 ###
9.60
###

116.00 ###
157.00 ###
268.00 ###

Dismantling of Flexible Pavements (Dismantling of flexible pavements and disposal


of dismantled materials up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately)

By Manual Means

Bituminous courses

cum

Granular courses

cum

413.00 ###
291.00 ###

cum

151.00 ###

cum

921.00 ###

II
A
2.6

2.7

By Mechanical Means
Bituminous course
Dismantling of Cement Concrete Pavement (Dismantling of cement concrete
pavement by mechanical means using pneumatic tools, breaking to pieces not
exceeding 0.02 cum in volume and stock piling at designated locations and disposal
of dismantled materials up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately)
Dismantling Guard Rails (Dismantling guard rails by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000 metres, stacking
serviceable materials and unserviceable materials separately.)

metre

44.00

###

2.8

Dismantling Kerb Stone (Dismantling kerb stone by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000 metre)

metre

8.00

###

2.9

Dismantling Kerb Stone channel (Dismantling kerb stone channel by manual means
and disposal of dismantled material with all lifts and up to a lead of 1000 metre)

metre

11.00

###

2.10

Dismantling Kilometre Stone (Dismantling of kilometre stone including cutting of


earth, foundation and disposal of dismantled material with all lifts and lead upto
1000 m and back filling of pit.)

5th KM stone

each

221.00 ###
132.00 ###
26.50 ###

Ordinary KM Stone

each

Hectometre Stone

each

Dismantling of Fencing (Dismantling of barbed wire fencing/ wire mesh fencing


including posts, foundation concrete, back filling of pit by manual means including
disposal of dismantled material with all lifts and up to a lead of 1000 metres,
stacking serviceable material and unserviceable material separately. )

metre

Dismantling of CI Water Pipe Line (Dismantling of CI water pipe line 600 mm dia
including disposal with all lifts and lead upto 1000 metres and stacking of
serviceable material and unserviceable material separately under supervision of
concerned department)

metre

108.00 ###

Removal of Cement Concrete Pipe of Sewer Gutter (Removal of cement concrete


pipe of sewer gutter 1500 mm dia under the supervision of concerned department
including disposal with all lifts and up to a lead of 1000 metres and stacking of
serviceable and unserviceable material separately but excluding earth excavation
and dismantling of masonry works.)

metre

171.00 ###

Removal of Telephone / Electric Poles and Lines (Removal of telephone / Electric


poles including excavation and dismantling of foundation concrete and lines under
the supervision of concerned department, disposal with all lifts and up to a lead of
1000 metres and stacking the serviceable and unserviceable material separately)

each

104.00 ###

2.11

2.12

2.13

2.14

27

30.70

###

CHAPTER-3

EARTH WORK, EROSION CONTROL AND DRAINAGE


Item
No.
3.1

Descriptions

Unit

Excavation in Soil by Manual Means. (Excavation for roadway in soil using manual
means including loading in truck for carrying of cut earth to embankment site with
all lifts and lead upto1000 metres.)

Rate (in Rs.)

###

(i)

Including Royalty @ Rs. 24.0 per cum but excluding the cost of watering, rolling &
compaction

cum

186.00 ###

(ii)

Including Royalty @ Rs. 24.0 per cum , cost of watering, rolling & compaction

cum

205.00 ###

In case there is a situation where the cross-section is of cut and fill and cut earth is
required to be used in embankment in the immediate vicinity, the item of carriage in
the truck shall be omitted. inclunding Royalty @ Rs. 24.00 per cum.

cum

108.00 ###

Excavation in ordinary rock by manual means (Excavation in ordinary rock using


manual means including loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres ) including Royalty @
Rs. 24.00 per cum but excluding cost of watering , rolling & compaction

cum

232.00 ###

Excavation in ordinary rock using manual means including loading in a truck and
carrying of excavated material to embankment site with in all lifts and leads upto 1000
metres including Royalty @ Rs. 24.00 per cum, cost of watering , rolling & compaction

cum

251.00 ###

In case there is a situation where the cross-section is of cut and fill and cut earth is
required to be used in embankment in the immediate vicinity, the item of carriage in the
truck shall be omitted - inclunding Royalty @ Rs. 24.00 per cum.

cum

154.00 ###

cum

129.00 ###

cum

217.00 ###

cum

269.00 ###

Note

3.2 (i)

(ii)

Note

3.3

3.4

3.5

3.6

(i)
(ii)
3.7

(i)
(ii)
3.8

Excavation in Soil with Dozer with lead upto 100 metres (Excavation for road way in
soil by mechanical means including cutting and pushing the earth to site of
embankment upto a distance of 100 metres (average lead50 metres), including
trimming bottom and side slopes in accordance with requirements of lines, grades
and cross sections.)
Excavation in Ordinary Rock with Dozer with lead upto 100 metres (Excavation for
roadway in ordinary rock by deploying a dozer, 80 HP including cutting and pushing
the cut earth to site of embankment upto a distance of 100 metres ( average lead
50 metres ), trimming bottom and side slopes in accordance with the requirements
of lines, grades and cross sections.)
Excavation in Hard Rock (requiring blasting)
with disposal upto 1000 metres
(Excavation for roadway in hard rock (requiring blasting) by drilling, blasting and
breaking, trimming of bottom and side slopes in accordance with requirements of
lines, grades and cross sections, loading and disposal of cut road with in all lifts and
leads upto 1000 metres )
Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto
1000 metres. (Excavation for roadwork in soil with hydraulic excavator of0.9 cum
bucket capacity including cutting and loading in tippers, trimming bottom and side
slopes, in accordance with requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and lead upto 1000m)

###

Including Royalty @ Rs. 24.00 per cum but excluding the cost of watering, rolling &
compaction.

cum

103.00 ###

Including Royalty @ Rs. 24.00 per cum, cost of watering, rolling & compaction.

cum

118.00 ###

Excavation in Ordinary Rockusing Hydraulic ExcavatorCK-90 and Tippers with


disposal upto 1000 metres. (Excavation for roadway in ordinary rock with hydraulic
excavator of 0.9 cum bucket capacity including cutting and loading in tippers,
transporting to embankment site within all lifts and lead upto 1000 m, trimming
bottom and side slopes in accordance with requirements of lines, grades and cross
sections.)

###

Including Royalty @ Rs. 24.00 per cum but excluding the cost of watering, rolling &
compaction.

cum

120.00 ###

Including Royalty @ Rs. 24.00 per cum, cost of watering, rolling & compaction.

cum

139.00 ###

497.00 ###
720.00 ###

Excavation in Hard Rock (blasting prohibited) (Excavation for roadway in hard rock
(blasting prohibited) with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres, trimming bottom and side
slopes in accordance with requirements of lines, grades and cross sections.)

Mechanised

cum

Manual Method

cum

28

3.9

3.10

Excavation in Hard Rock (controlled blasting)


with disposal upto 1000 metres
(Excavation for roadway in hard rock with controlled blasting by drilling, blasting and
breaking, trimming of bottom and side slopes in accordance with requirements of
lines, grades and cross sections, loading and disposal of cut road with in all lifts and
leads upto 1000 metres )

cum

341.00 ###

Excavation in Marshy Soil (Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and loading in tippers and
disposal with in all lifts and lead upto 1000 metres, trimming of bottom and side
slopes in accordance with requirements of lines, grades and cross sections.)

###

(i)

Including Royalty @ Rs. 24.00 per cum but excluding the cost of watering, rolling &
compaction.

cum

110.00 ###

(ii)

Including Royalty @ Rs. 24.00 per cum, cost of watering, rolling & compaction.

cum

129.00 ###

3.11

3.12

3.13

Removal of Unserviceable Soil with Disposal upto 1000 metres (Removal of


unserviceable soil including excavation, loading and disposal upto 1000 metres lead
but excluding replacement by suitable soil which shall be paid separately as per
clause 305.)
Pre-splitting of Rock Excavation Slopes (Carrying out excavation in hard rock to
achieve a specified slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill holes, collection of the
excavated rock by a 80 HP dozer, loading in tipper by a front end loader and
disposing of the material with all lifts and lead upto 1000 m, all as specified in
clause No. 303)
Excavation for Structures (Earth work in excavation of foundation of structures as
per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom, backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.)

cum

135.00 ###

179.00 ###
43.00 ###

Ordinary soil

Manual Means (Depth upto 3 m)

cum

Mechanical Means (Depth upto 3 m)

cum

A
B
(iii)
A
(iv)
A
(v)

###

sqm

(i)

(ii)

80.00

Ordinary rock (not requiring blasting)


Manual Means (Depth upto 3 m)

cum

223.00 ###
57.00 ###

cum

400.00 ###

cum

467.00 ###
294.00 ###
139.00 ###

cum

Mechanical Means
Hard rock ( requiring blasting )
Manual Means
Hard rock ( blasting prohibited )
Mechanical Means
Marshy soil

Manual means ( upto 3 m depth)

cum

Mechanical Means

cum

Scarifying Existing Granular Surface to a Depth of 50 mm by Manual Means


(Scarifying the existing granular road surface to a depth of 50 mm and disposal of
scarified material within all lifts and leads upto 1000 metres. )

sqm

14.60

###

Scarifying existing bituminous surface to a depth of 50 mm by mechanical means


(Scarifying the existing bituminous road surface to a depth of 50 mm and disposal of
scarified material with in all lifts and lead upto 1000 metres.)

sqm

6.10

###

3.14

3.15

3.16

(i)
(ii)
3.17

(i)
(ii)
3.18

(i)
(ii)

Embankment Construction with Material Obtained from Borrow Pits (Construction of


embankment with approved material obtained from borrow pits with all lifts and
leads, transporting to site, spreading, grading to required slope and compacting to
meet requirement of table 300-2)

Rolling with vibratory roller


Rolling with smooth wheeled roller

###
cum

194.00 ###

cum

184.00 ###

Construction of Embankment with Material Deposited from Roadway Cutting


(Construction of embankment with approved materials deposited at site from
roadway cutting and excavation from drain and foundation of other structures
graded and compacted to meet requirement of table 300-2)

Rolling with vibratory roller


Rolling with smooth wheeled roller

###
cum

126.00 ###

cum

116.00 ###

Construction of Subgrade and Earthen Shoulders (Construction of subgrade and


earthen shoulders with approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required slope and compacted to
meet requirement of table No. 300-2)

Rolling with vibratory roller


Rolling with smooth wheeled roller

29

###
cum

230.00 ###

cum

218.00 ###

3.19
Case-I

(i)
(ii)
Case-II
(i)
(ii)
3.20

3.21

3.22

3.23

3.24

Compacting Original Ground


Compacting original ground supporting subgrade (Loosening of the ground upto a
level of500 mm below the subgrade level, watered, graded and compacted in layers
to meet requirement of table 300-2 for subgrade construction.)

Rolling with vibratory roller


Rolling with smooth wheeled roller

###
cum

73.00

cum

60.00

###

###

Compacting original ground supporting embankment

Rolling with vibratory roller


Rolling with smooth wheeled roller

Stripping and Storing Top Soil (Stripping, storing of top soil by road side at 15 m
internal and re-application on embankment slopes, cut slopes and other areas in
localities where the available embankment material is not conducive to plant
growth)
Stripping, storing and re-laying top soil from borrow areas in agriculture fields.
(Stripping of top soil from borrow areas located in agriculture fields, storing at a
suitable place, spreading and re-laying after taking the borrow earth to maintain
fertility of the agricultural field, finishing it to the required levels and satisfaction of
the farmer.)
Turfing with Sods (Furnishing and laying of the live sods of perennial turf forming
grass on embankment slope, verges or other locations shown on the drawing or as
directed by the engineer including preparation of ground, fetching of rods and
watering)
Seeding and Mulching (Preparation of seed bed on previously laid top soil, furnishing
and placing of seeds, fertilizer, mulching material, applying bituminous emulsion at
the rate of0.23 litres per sqm and laying and fixing jute netting, including watering
for 3 months all as per clause 308)

cum

40.00

###

cum

28.00

###

cum

150.00 ###

cum

77.00

###

sqm

37.00

###

sqm

142.00 ###

Surface Drains in Soil (Construction of unlined surface drains of average cross


sectional area 0.40 sqm in soil to specified lines, grades, levels and dimensions to
the requirement of clause 301 and 309. Excavated material to be used in
embankment within a lead of50 metres (average lead 25 metres))

Mechanical means

metre

Manual Means

metre

3.25

###

66.00
45.00

###
###

Surface Drains in Ordinary Rock (Construction of unlined surface drain of average


cross sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and
dimensions as per approved design and to the requirement of clause 301 to 309.
Excavated material to be used in embankment at site.)

Mechanical Means

metre

Manual Means

metre

134.00 ###
67.00 ###

3.26

Surface Drains in Hard Rock (Rate per metre may be worked out based on quantity
of hard rock as per design.)

metre

VALUE

3.27

Sub Surface Drains with Perforated Pipe (Construction of subsurface drain with
perforated pipe of 100 mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3 mm to 6 mm depending
upon size of material surrounding the pipe, with 150 mm bedding below the pipe
and 300 mm cushion above the pipe, cross section of excavation 450 x 550 mm.
Excavated material to be utilised in roadway at site )

metre

352.00 ###

Aggregate Sub- Surface Drains (Construction of aggregate sub surface drain 300
mm x 450 mm with aggregates conforming to table 300-4, excavated material to be
utilised in roadway )

metre

133.00 ###

Underground Drain at Edge of Pavement (Construction of an underground drain 1 m


x 1 m (inside dimensions) lined with RCC-20 cm thick and covered with RCC slab10
cm in thickness on urban roads)

metre

2353.00 ###

3.28

3.29

3.30

3.31

3.32

3.33

3.34

3.35

Preparation and Surface Treatment of formation. (Preparation and surface treatment


of formation by removing mud and slurry, watering to the extent needed to maintain
the desired moisture content, trimming to the required line, grade, profile and rolling
with 8-10 tonne smooth wheeled roller, complete as per clause 310.)
Construction of Rock fill Embankment (Construction of rock fill embankment with
broken hard rock fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with stone spalls, blinding
top layer with granular material, rolled with vibratory road roller, all complete as per
clause 313)
Excavation in Hill Area in Soil by Mechanical Means (Excavation in soil in hilly area
by mechanical means including cutting and trimming of side slopes and disposing of
excavated earth with all lifts and lead upto 1000 metres)

sqm

2.00

###

cum

71.00

###

cum

175.00 ###

Excavation in Hilly Area in Ordinary Rock by Mechanical Means not Requiring


Blasting. (Excavation in hilly area in ordinary rock not requiring ballasting by
mechanical means including cutting and trimming of slopes and disposal of cut
material with all lift and lead upto 1000 metres )

cum

247.00 ###

Excavation in Hilly Areas in Hard Rock Requiring Blasting (Excavation in hilly areas in
hard rock requiring blasting, by mechanical means including trimming of slopes and
disposal of cut material with all lifts and lead upto 1000 metres.)

cum

306.00 ###

Work in Urban Roads (The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:)

30

VALUE

3.36

Embankment Construction with Fly ash/Pond ash available from coal or lignite
burning Thermal Plants as waste material. (Construction of embankment with fly ash
conforming to table 1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and compacted in layer of 200mm
thickness each at OMC, all as specified in IRC: SP: 58-2001 and as per approved
plans.)

31

cum

113.00 ###

CHAPTER-4

SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS


Item
No.

Descriptions

Unit

4.1
A

Granular Sub-base with Close Graded Material (Table:- 400-1)

(i)
(ii)
(iii)
B

for grading- I Material


for grading- II Material
for grading-III Material

(i)
(ii)
(iii)
4.2

for grading- I Material


for grading- II Material
for grading-III Material

(i)
(ii)
(iii)
4.3

for grading- I Material


for grading- II Material
for grading-III Material

A
B
4.4

4.5

Rate (in Rs.)

Plant Mix Method (Construction of granular sub-base by providing close


graded Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with motor grader
on prepared surface and compacting with vibratory power roller to achieve
the desired density, complete as per clause 401 )
cum
cum
cum

1328.00 ###
1296.00 ###
1169.00 ###

cum
cum
cum

1091.00 ###
1059.00 ###
932.00 ###

cum
cum
cum

1054.00 ###
1044.00 ###
1014.00 ###

By Mechanical Means
By Manual Means

cum
cum

445.00 ###
429.00 ###

Lime Treated Soil for Sub- Base (Providing, laying and spreading soil on a
prepared sub grade, pulverising, mixing the spread soil in place with
rotavator with 3 % slaked lime with minimum content of 70% of CaO,
grading with motor grader and compacting with the road roller at OMC to
achieve at least 98%of the max dry density to form a layer of sub base.)

cum

502.00 ###

Cement Treated Soil Sub Base/ Base (Providing, laying and spreading soil on
a prepared sub grade, pulverising, adding the designed quantity of cement
to the spread soil, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve the desired
unconfined compressive strength and to form a layer of sub-base/base.)

cum

711.00 ###

By Mix in Place Method (Construction of granular sub-base by providing


close graded material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator at OMC,
and compacting with vibratory roller to achieve the desired density,
complete as per clause 401)

Granular Sub-Base with Coarse Graded Material ( Table:- 400- 2)


(Construction of granular sub-base by providing coarse graded material,
spreading in uniform layers with motor grader on prepared surface, mixing
by mix in place method with rotavator at OMC, and compacting with
vibratory roller to achieve the desired density, complete as per clause 401)

Lime Stabilisation for Improving Subgrade (Laying and spreading available


soil in the subgrade on a prepared surface, pulverising, mixing the spread
soil in place with rotavator with 3 % slaked lime having minimum content of
70% of CaO, grading with motor grader and compacting with the road roller
at OMC to the desired density to form a layer of improved sub grade)

4.6

Cement Treated Crushed Rock or combination as per clause 403.2 and table
400.4 in Sub base/ Base (Providing, laying and spreading Material on a
prepared sub grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor grader and
compacting with the road roller at OMC to achieve the desired unconfined
compressive strength and to form a layer of sub-base/base.)

(i)

For Sub-Base course

cum

1832.00 ###

(ii)

For Base course


Making 50 mm x 50 mm Furrows (Making 50 mm x 50 mm furrows, 25mm
deep, 450 to the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping and disposal of
excavated material within 1000 metres lead)

cum

1398.00 ###

i) 25 mm deep furrow cutting

sqm

2.30

###

ii) 50 mm deep furrow cutting

sqm

4.60

###

4.7

32

4.8

4.9

Inverted Choke (Construction of inverted choke by providing, laying,


spreading and compacting screening B type/ coarse sand of specified grade
in uniform layer on a prepared surface with motor grader and compacting
with power roller etc)

cum

Water Bound Macadam (Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound macadam specification including
spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10
tonnes / Smooth 3 wheeled Steel Roller in stages to proper grade and camber,
applying and brooming requisite type of screening/ binding Materials to fill up the
interstices of coarse aggregate, watering and compacting to the required density.)

By Manual Means

(i)

Grading- I (Using Screening Crushable type such as Moorum or Gravel)

(a)

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

(b)
(ii)

Grading- II (Using Screening Crushable type such as Moorum or Gravel)

(a)

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

(b)
(c)
(iii)

Grading- III (Using Screening Crushable type such as Moorum or Gravel)

(a)

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

(b)
B
(i)
(a)
(b)

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

(a)

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-A (13.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

(iii)

Grading- III (Using Screening Crushable type such as Moorum or Gravel)

(a)

Using Screening Crushable type such as Moorum or Gravel (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller

cum

Using Screening Type-B (11.2mm Agg.) (with Vibratory Roller)

cum

With Smooth 3 wheeled Steel Roller


Crushed Cement Concrete Sub-base / Base (Breaking and crushing of material
obtained by breaking damaged cement concrete slabs to size range not exceeding
75 mm as specified in table 400.7 transporting the aggregates obtained from
breaking of cement concrete slabs at a lead of L km., laying and compacting the
same as sub base/ base course, constructed as WBM to clause 404 except the use of
screening or binding Material.)
With Vibratory Roller

cum

(b)
4.10

With Smooth 3 wheeled Steel Roller


4.11

###
###
###
###

1105.00
1096.00
1195.00
1186.00
1236.00
1211.00

###
###
###
###
###
###

1133.00
1124.00
1248.00
1239.00

###
###
###
###

922.00
913.00
1094.00
1085.00

###
###
###
###

1020.00
1011.00
1110.00
1101.00
1152.00
1126.00

###
###
###
###
###
###

1048.00
1039.00
1164.00
1155.00

###
###
###
###

Grading- I (Using Screening Crushable type such as Moorum or Gravel)

Grading- II (Using Screening Crushable type such as Moorum or Gravel)

(c)

1007.00
998.00
1179.00
1170.00

By Mechanical Means:

(ii)

(b)

397.00 ###

Penetration Coat Over Top Layer of Crushed Cement Concrete Base (Spraying of
bitumen over cleaned dry surface of crushed cement concrete base at the rate of 25
kg per 10 sqm by a bitumen pressure distributor, spreading of key aggregates at the
rate of 0.13 cum per 10 sqm by a mechanical gritter and rolling the surface as per
clause 506.3.8)

33

###
cum

227.00 ###

cum

218.00 ###

sqm

19.40

###

4.12

Wet Mix Macadam (Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including premixing the Material with
water at OMC in mechanical mix plant carriage of mixed Material by tipper to site,
laying in uniform layers with paver in sub- base / base course on well prepared
surface and compacting with vibratory roller to achieve the desired density.)
cum

1290.00 ###
1295.00 ###

Construction of Median and Island with Soil Taken from Roadway Cutting
(Construction of Median and Island above road level with approved material
deposited at site from roadway cutting and excavation for drain and foundation of
other structures, spread, graded and compacted as per clause 407)

cum

177.00 ###

Construction of Median and Island with Soil Taken from Borrow Areas (Construction
of median and Island above road level with approved material brought from borrow
pits, spread, sloped and compacted as per clause 407)

cum

209.00 ###

With Vibratory Roller

cum

With Smooth 3 wheeled Steel Roller


4.13

4.14

4.15

4.16

4.17

(i)
(ii)
B

(i)
(ii)
4.18

###

Construction of Shoulders (A. Earthen Shoulders)


B.) Hard Shoulders

VALUE

C.) Paved Shoulders

VALUE

Footpaths and Separators (Construction of footpath/separator by providing a 150


mm compacted granular sub base as per clause 401 and 25 mm thick cement
concrete grade M15, over laid with precast concrete tiles in cement mortar 1:3
including provision of all drainage arrangements but excluding kerb channel.)

sqm

622.00 ###

cum
cum

919.00 ###
953.00 ###

For 53 mm maximum size


For 45 mm maximum size

cum
cum

1097.00 ###
1147.00 ###

Lime, Fly ash stabalised soil sub-base (Construction of Sub-base using lime - fly ash
admixture with granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and 20 and liquid limit less
than 25 and commercial dry lime, slaked at site or pre-slaked with CaO content not
less than 50%, fly ash to conform to gradation as per clause 4.3 of IRC: 88-1984,
lime + fly ash content ranging between 10 to 30%, the minimum un-confined
compressive strength and CBR value after 28 days curing and 4 days soaking to be
7.5 kg/sq, cm and 25% respectively, all as specified in IRC: 88-1984)

cum

478.00 ###

Crusher Run Macadam Base (Providing crushed stone aggregate, depositing on a


prepared surface by hauling vehicles, spreading and mixing with a motor grader,
watering and compacting with a vibratory roller to clause 410 to form a layer of subbase/Base)
By Mix in Place Method

For 53 mm maximum size


For 45 mm maximum size
By Mixing Plant :

34

CHAPTER-5

BASES AND SURFACE COURSES (BITUMINOUS)


Item
No.
5.1

5.2

Descriptions

Unit

Rate (in Rs.)

Prime coat (Providing and applying primer coat with bitumen emulsion on prepared
surface of granular Base including clearing of road surface and spraying primer at
the rate of 0.60 kg/sqm using mechanical means.)

sqm

35.00

###

sqm

12.00

###

Tack coat
Providing and applying tack coat with bitumen emulsion using emulsion pressure
distributor at the rate of 0.20 kg per sqm on the prepared bituminous/granular
surface cleaned with mechanical broom.

5.3

(i)
(ii)
5.3 A

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH
hot mix plant producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading premixed with bituminous binder, transported to
site, laid over a previously prepared surface with paver finisher to the required
grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the
desired compaction)
for Grading I ( 40 mm nominal size )
for GradingII(19 mm nominal size)

for Grading I ( 40 mm nominal size )


for GradingII(19 mm nominal size)

(i)
(ii)
5.4

for Grading I ( 40 mm nominal size )


for GradingII(19 mm nominal size)

A
B
5.5

50 mm thick
75 mm thick
Built-Up-Spray Grout (Providing, laying and rolling of built-up-spray grout layer over
prepared base consisting of a two layer composite construction of compacted
crushed coarse aggregates using motor grader for aggregates. key stone chips
spreader may be used with application of bituminous binder after each layer, and
with key aggregates placed on top of the second layer to serve as a Base
conforming to the line, grades and cross-section specified, the compacted layer
thickness being 75 mm)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MoRTH specification clause No. 507 complete in all respects.)
for Grading I ( 40 mm nominal size )
for GradingII(19 mm nominal size)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MoRTH specification clause No. 507 complete in all respects.) with Modifed Graded
Bitumen.
for Grading I ( 40 mm nominal size )
for GradingII(19 mm nominal size)
Dense Graded Bituminous Macadam (Providing and laying dense bituminous
macadam with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5% by weight of total mix of mix and filler,
transporting the hot mix to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MoRTH specification clause No. 507 complete in all respects.) with VG-30 Grade Bulk
Bitumen.

(i)
(ii)
5.6 A

(i)
(ii)
5.6 B

7420.00 ###
7348.00 ###

cum
cum

7512.00
7440.00

cum
cum

7006.00
6933.00

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH
hot mix plant producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading premixed with bituminous binder, transported to
site, laid over a previously prepared surface with paver finisher to the required
grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the
desired compaction)with modified graded bitumen.

(i)
(ii)
5.3 B

5.6

cum
cum

Bituminous Macadam (Providing and laying bituminous macadam with 100-120 TPH
hot mix plant producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading premixed with bituminous binder, transported to
site, laid over a previously prepared surface with paver finisher to the required
grade, level and alignment and rolled as per clauses 501.6 and 501.7 to achieve the
desired compaction)with VG-30 Bulk bitumen.

Bituminous Penetration Macadam (Construction of penetration macadam over


prepared Base by providing a layer of compacted crushed coarse aggregate using
chips spreader with alternate applications of bituminous binder and key aggregates
and rolling with a smooth wheeled steel roller 8-10 tonne capacity to achieve the
desired degree of compaction)

35

sqm
sqm

388.00 ###
536.00 ###

sqm

297.00 ###

cum
cum

9014.00 ###
9092.00 ###

cum
cum

9138.00
9217.00

(i)
(ii)

for Grading I ( 40 mm nominal size )


for GradingII(19 mm nominal size)

cum
cum

36

8452.00
8531.00

5.7

(i)
(ii)
5.7 A

Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous
concrete with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.5 to 5 % of mix and filler, transporting the hot mix to work
site, laying with a hydrostatic paver finisher with sensor control to the required
grade, level and alignment, rolling with smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as per MoRTH specification clause No. 508
complete in all respects)
for Grading I ( 13 mm nominal size )
for GradingII(10 mm nominal size)

cum
cum

9415.00 ###
10057.00 ###

cum
cum

9547.00
10204.00

cum
cum

10521.00 ###
10364.00 ###

Semi - Dense Bituminous Concrete (Providing and laying semi dense bituminous
concrete with 100-120 TPH batch type HMP producing an average output of 75
tonnes per hour using crushed aggregates of specified grading, premixed with
bituminous binder @ 4.5 to 5 % of mix and filler, transporting the hot mix to work
site, laying with a hydrostatic paver finisher with sensor control to the required
grade, level and alignment, rolling with smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as per MoRTH specification clause No. 508
complete in all respects) with Modified Graded Bitumen.

for Grading I ( 13 mm nominal size )


for GradingII(10 mm nominal size)
Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75 tonnes per hour using
crushed aggregates of specified grading, premixed with bituminous binder @ 5.4 to
5.6 % of mix and filler, transporting the hot mix to work site, laying with a
hydrostatic paver finisher with sensor control to the required grade, level and
alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the
desired compaction as per MORTH specification clause No. 509 complete in all
respects)
for Grading-I ( 13 mm nominal size )
(i)
for Grading-II(10 mm nominal size)
(ii)
Surface Dressing (Providing and laying surface dressing as wearing course in single
5.9
coat using crushed stone aggregates of specified size on a layer of bituminous
binder laid on prepared surface and rolling with 8-10 tonne smooth wheeled steel
roller)
Case -1 19 mm nominal chipping size
Case - II 13 mm nominal size chipping
(i)
(ii)
5.8

37

sqm
sqm

98.00
79.00

###
###

5.10

Open - Graded Premix Surfacing (Providing, laying and rolling of open - graded
premix surfacing of 20 mm thickness composed of 13.2 mm to 5.6 mm aggregates
either using penetration grade bitumen or cut-back or emulsion to required line,
grade and level to serve as wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a smooth wheeled roller 8-10
tonne capacity, finished to required level and grades.)

(i)

Case - I: Mechanical method using Penetration grade Bitumen and HMP of


appropriate capacity not less than 75 tonnes/hour .

sqm

144.00 ###

(ii)

Case - II: Open-Graded Premix Surfacing using cationic Bitumen Emulsion

sqm

148.00 ###

i) For Type A

sqm

186.00 ###

i) For Type B

sqm

171.00 ###

5.11

5.12
(i)
(ii)

5.13

5.14

5.15

(i)
(ii)
(iii)
5.16

5.17
added
5.18

(i)
(ii)
(iii)
(iv)
5.19

Close Graded Premix Surfacing/Mixed Seal Surfacing (Mechanical means using HMP
of appropriate capacity not less than 75 tonnes/hour. Providing, laying and rolling of
close-graded premix surfacing material of 20 mm thickness composed of 11.2 mm
to 0.09 mm (Type-a)
or 13.2 mm to 0.09 mm (Type-b)
aggregates using
penetration grade bitumen to the required line, grade and level to serve as wearing
course on a previously prepared base, including mixing in a suitable plant, laying
and rolling with a Smooth wheeled roller 8-10 tonne capacity, and finishing to
required level and grade. )

Seal Coat (Providing and laying seal coat sealing the voids in a bituminous surface
laid to the specified levels, grade and cross fall using Type A and B seal coats)
Case - I : Type A

sqm

72.00

###

Case - II : Type B (Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using crushed stone chipping
6.7 mm size and penetration bitumen of suitable grade.)

sqm

60.00

###

Supply of Stone Aggregates for Pavement Courses (Supply of stone aggregates from
approved sources confirming to the physical requirement, specified in the respective
specified clauses, including royalties, fees rents, collection, transportation, stacking
and testing and measured in cum as per clause 514.5 Competitive market rates to
be ascertained. Alternatively, rates for stone crushing given in chapter 1may be
adopted, if found economical. In case for supply of aggregates at site are not
available, nearest crusher site may be ascertained. Loading and un-loading charges
and cost of carriage may be added to these rates to arrive at the cost at site.)

cum

VALUE

Mastic Asphalt (Providing and laying 25 mm thick mastic asphalt wearing course
with paving grade bitumen meeting the requirements given in table 500-29,
prepared by using mastic cooker and laid to required level and slope after cleaning
the surface, including providing antiskid surface with bitumen precoated finegrained hard stone chipping of 13.2 mm nominal size at the rate of 0.005cum per 10
sqm and at an approximate spacing of 10 cm center to center in both directions,
pressed into surface when the temperature of surfaces not less than 1000C,
protruding 1 mm to 4 mm over mastic surface, all complete as per clause 515.)

sqm

Slurry Seal Providing and laying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion and water on a road
surface including cleaning of surface, mixing of slurry seal in a suitable mobile plant,
laying and compacting to provide even riding surface)

sqm

5 mm thickness
3 mm thickness
1.5 mm thickness
Recycling of Bituminous Pavement with Central Recycling Plant (Recycling pavement
by cold milling of exiting bituminous layers, planning the surface after cold milling,
reclaiming excavated material to the extent of 30 % of the required quantity,
hauling and stock piling the reclaimed material near the central recycling plant after
carrying out necessary checks and evaluation, adding fresh material including
rejuvenators as required, mixing in a hot mix plant, transporting and laying at site
and compacting to the required grade, level and thickness, all as specified in clause
517.)
Fog Spray
1.In case it is decided by the engineer to blind the fog spray, the following may be
added
Bituminous Cold Mix ( Including Gravel Emulsion) (Providing, laying and rolling of
bituminous cold mix on prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including mixing in a plant of suitable
type and capacity, transporting, laying, compacting and finishing to specified grades
and levels.)
Using bitumen emulsion and 9.5 mm or 13.2 mm nominal size aggregate
Using bitumen emulsion and 19 mm or 26.5 mm nominal size aggregate
Using cutback bitumen and 9.5 mm or 13.2 mm nominal size aggregate
Using cutback bitumen and 19 mm or 26.5 mm nominal size aggregate
Sand Asphalt Base Course (Providing, laying and rolling sand-asphalt base course
composed of sand, mineral filler and bituminous binder on a prepared sub-grade or
sub-base to the lines, levels, grades and cross sections as per the drawings
including mixing in a plant of suitable type and capacity, transporting, laying,
compacting and finishing.)

38

sqm
sqm
sqm

#VALUE! ###

72.00
51.00
31.00

###
###
###

cum

7914.00 ###

sqm

###

sqm

5.00

###

cum
cum
cum
cum

11313.00 ###
11285.00 ###
7760.00 ###
7700.00 ###

cum

8912.00 ###

5.20

5.21
(i)

(ii)

(iii)

(iv)

Modified Binder (Supply of modified binder produced by mixing bitumen


with modifier such as natural rubber or crumb rubber or any other polymer
found compatible with bitumen and which allows properties given in clause
521.3 and IRC: SP: 53 blending of modifier with bitumen to be done either
at the refinery or at the site plant capable of producing the modified binder
to be delivered in drums which shall be agitated in melted condition using
suitable device before use to ensure uniform dispersion.)

tonne

VALUE

Stress Absorbing Membrane (SAM) crack width less than 6 mm (Providing


and laying of a stress absorbing membrane over a cracked road surface,
with crack width below 6 mm after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 9 kg per
10 sqm and spreading 5.6 mm crushed stone aggregates @ 0.11 cum per
10 sqm with hydraulic chip spreader, sweeping the surface for uniform
spread of aggregates and surface finished to conform to clause 902.)

sqm

67.00

###

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm


(Providing and laying of a stress absorbing membrane over a cracked road
surface, with crack width 6 to 9 mm after cleaning with a mechanical
broom, using modified binder complying with clause 521, sprayed at the
rate of 11 kg per 10 sqm and spreading 11.2 mm crushed stone aggregates
@ 0.12 cum per 10 sqm, sweeping the surface for uniform spread of
aggregates and surface finished to conform to clause 902.)

sqm

82.00

###

Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked


area above 50 % (Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width above 9 mm and
cracked area above 50 % after cleaning with a mechanical broom, using
modified binder complying with clause 521, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates @ 0.12 cum per
10 sqm, sweeping the surface for uniform spread of aggregates and surface
finished to conform to clause 902.)

sqm

110.00 ###

Case - IV : Bitumen Impregnated Geotextile (Providing and laying a bitumen


impregnated geotextile layer after cleaning the road surface, geotextile
conforming to requirements of clause 704.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration and constructed
to the requirement of clause 704.4.5)

sqm

149.00 ###

cum
cum
cum

7201.00 ###
10196.00 ###
11515.00 ###

Crack Prevention Courses

5.22

Recipe Cold Mix (Providing and laying of premix of crushed stone


aggregates and emulsion binder, mixed in a batch type cold mixing plant,
laid over prepared surface, by paver finisher, rolled with a pneumatic tyred
roller initially and finished with a smooth steel wheel roller, all as per clause
519.3)

(i)
(ii)
(iii)
5.8 A

75 mm thickness
40 mm thickness
25 mm thickness

5.8 B

Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch
type hot mix plant producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix
and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH
specification clause No. 509 complete in all respects) with Modifed Graded Bitumen.
(i) for Grading-I ( 13 mm nominal size )

10671.00

(ii) for Grading-II(10 mm nominal size)

10514.00

Bituminous Concrete (Providing and laying bituminous concrete with 100-120 TPH batch
type hot mix plant producing an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with bituminous binder @ 5.4 to 5.6 % of mix
and filler, transporting the hot mix to work site, laying with a hydrostatic paver finisher
with sensor control to the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired compaction as per MORTH
specification clause No. 509 complete in all respects) with Bulk VG30 Bitumen.
(i) for Grading-I ( 13 mm nominal size )

cum

9847.00

(ii) for Grading-II(10 mm nominal size)

cum

9689.00

39

CHAPTER-6

CEMENT CONCRETE PAVEMENTS


Item No. Descriptions
6.1

6.2

6.3

6.4

6.5

6.6

Unit

Rate (in Rs.)

Dry Lean Cement Concrete Sub- base (Construction of dry lean cement
concrete Sub- base over a prepared sub-grade with coarse and fine
aggregate conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate
gradation after blending to be as per table 600-1, cement content not to be
less than 150 kg/ cum, optimum moisture content to be determined during
trial length construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a paver with
electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing
and curing.)

cum

2258.00 ###

Cement Concrete Pavement (Construction of un-reinforced, dowel jointed,


plain cement concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25 mm, mixed in a
batching and mixing plant as per approved mix design, transported to site,
laid with a fixed form or slip form paver, spread, compacted and finished in
a continuous operation including provision of contraction, expansion,
construction and longitudinal joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures
as approved, curing compound, finishing to lines and grades as per
drawing )

cum

5113.00 ###

Rolled Cement Concrete Base (Construction of rolled cement concrete base


course with coarse and fine aggregate conforming to IS:383, the size of
coarse aggregate not exceeding 25 mm with minimum, aggregate cement
ratio15:1 and minimum cement content of 200 kg/cum, aggregate
gradation to be as per table 600-4 after blending, mixing in batching plant
at optimum moisture content, transporting to site, laying with a paver with
electronic sensor, compacting with 8-10 tonnes smooth wheeled vibratory
roller to achieve, the designed flexural strength, finishing and curing.)

cum

2609.00 ###

Transition section between rigid and flexible pavement (Due to change in


the properties of materials and type of construction, a gradual changeover
from rigid pavement to flexible pavement is desirable to avoid any damage
at the butting joint. After provision of an expansion joint in the cement
concrete slab, the thickness of slab should be tapered to 10 cm over a
length of 3 m towards the flexible pavement. The deficiency of thickness
caused due to tapering of the slab should be made up by the asphaltic
layers.)
Construction of Base/Sub-base of pavement with lean concrete - fly ash.
(Construction of Base/sub-base using cement, sand, fly ash and coarse
aggregates proportioned as per table 4 of IRC: 74/1979 and with water
content ratio, slump and compressive strength as defined in the said table,
mix prepared in a batching and mixing plant and compacted with a
vibratory roller 8-10 tonnes capacity within the time limit laid down vide
clause 7.6.3 of IRC: 74-1979, construction joints properly formed at the end
of day's work, cured for 14 days, all as specified in IRC: 74-1979 and as per
approved plans.)
Cement - Fly ash concrete pavement. (Construction reinforced-reinforced,
dowel jointed, plain cement concrete pavement over a prepared sub base
with 43 grade cement, coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25 mm, replacing cement
by fly ash to the extent of 15% and sand by 10%, mixed in a batching and
mixing plant as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction, expansion,
construction and longitudinal joints, joint filler, separation membrane,
sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures
as approved, curing compound, finishing to lines and grades as per
drawing )

40

Value

cum

2130.00 ###

cum

4718.00 ###

CHAPTER-7

GEOSYNTHETICS AND REINFORCED EARTH


Item
No.
7.1

7.2

7.3

7.4

Descriptions

Unit

Rate (in Rs.)

Sub- Surface Drain with Geotextiles (Construction of sub surface drain 200 mm dia
using geotextiles treated with carbon black with physical properties as given in
clause 702.2.3 formed in to a stable network and a planar geocomposite structure,
joints wrapped with geotextile to prevent ingress of soil, all as per clause 702 and
approved drawings including excavation and backfilling)

metre

520.00

###

Narrow Filter Sub- Surface Drain (Construction of a narrow filter sub- surface drain
consisting of porous or perforated pipe laid in narrow trench surrounded by a
geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed as
per clause 702.3 and 309.3.5 including excavation and backfilling)

metre

353.00

###

Laying Paving Fabric Beneath a Pavement Overlay (Providing and laying paving
fabric with physical requirements as per table 704-2 over a tack coat of paving
grade Bitumen 80-100 penetration, laid at the rate of 1 kg per sqm over thoroughly
cleaned and repaired surface to provide a water resistant membrane and crack
retarding layer. Paving fabric to be free of wrinkling and folding and to be laid before
cooling of tack coat, brooming and rolling of surface with pneumatic roller to
maximise paving fabric contact with pavement surface)

sqm

143.00

###

Laying Boulder Apron in Crates of Synthetic Geogrids (Providing, preparing and


laying of geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and
backfilling with baffles at 1 metre interval, made with geogrids having
characteristics as per clause 704.2, joining sides with connectors/ring staples, top
corners to be tie tensioned, placing of suitable cross interval ties in layers of 300
mm connecting opposite side with lateral braces and tied with polymer braids to
avoid bulging, constructed as per clause 704.3. filled with stone with minimum size
of 200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed
to the foundation recess in case of sloping ground and laid over a layer of geotextile
to prevent migration of fines, all as per clause 704 and laid as per clause 2503.3 and
approved design.)

cum

#VALUE!

###

7.5

Reinforced Earth Retaining Wall (Reinforced earth retaining walls have four main
components as under: a)
Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for facing elements (facia
material). b) Facia material and its placement. c) Assembling, joining with facing
elements and laying of the reinforcing elements. d) Earthfill with granular material
which is to be retained by the wall.)

(i)

Assembling, joining and laying of reinforcing elements.

With reinforcing element of steel / Aluminium strips / polymeric strips.

Type 1

1.Galvanised carbon steel strips

metre

639.00

###

Type 2

2.Copper Strips

metre

639.00

###

Type 3

3.Aluminium Strips

metre

318.00

###

Type 4

4.Stainless steel strips

metre

318.00

###

Type 5

5.Glass reinforced polymer/fibre reinforced polymer/polymeric strips

metre

639.00

###

With reinforcing elements of synthetic geogrids

sqm

121.00

###

Facing elements of RCC

sqm

B
(ii)

41

1109.00 ###

CHAPTER-8

TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES


Item
No.
8.1

Descriptions

Unit

Cast in Situ Cement Concrete M20 kerb (Construction of cement concrete kerb with
top and bottom width 115 and 165 mm respectively, 250 mm high in M 20 grade
PCC on M-10 grade foundation 150 mm thick, foundation having 50 mm projection
beyond kerb stone, kerb stone laid with kerb laying machine, foundation concrete
laid manually, all complete as per clause 408)

Using Concrete Mixer

metre

Using Concrete Batching and Mixing Plant

metre

8.2

Using Concrete Mixer

metre

Using Concrete Batching and Mixing Plant


Printing new letter and figures of any shade (Printing new letter and figures of any
shade with synthetic enamel paint black or any other approved colour to give an
even shade)

metre

(i)

226.00 ###
235.00 ###

Cast in Situ Cement Concrete M 20 Kerb with Channel (Construction of cement


concrete kerb with channel with top and bottom width 115 and 165 mm
respectively, 250 mm high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCC M20 grade, sloped towards
the kerb, kerb stone with channel laid with kerb laying machine, foundation concrete
laid manually, all complete as per clause 408)

A
8.3

Rate (in Rs.)

414.00 ###
429.00 ###

Hindi ( Matras commas and the like not to be measured and paid for Half letter shall cm height
be counted as half )
per letter

0.60

###

cm height
per letter

0.30

###

(ii)

English and Roman

8.4

(i)

Retro- reflectorised Traffic signs (Providing and fixing of retro- reflectorised


cautionary, mandatory and informatory sign as per IRC :67 made of encapsulated
lens type reflective sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5
mm thick supported on a mild steel angle iron post 75 mm x 75 mm x 6 mm firmly
fixed to the ground by means of properly designed foundation with M15 grade
cement concrete 45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing)
90 cm equilateral triangle

each

5046.00 ###

( ii )

60 cm equilateral triangle

each

( iii )

60 cm circular

each

3191.00 ###
4406.00 ###

( iv )

80 mm x 60 mm rectangular

each

(v)

60 cm x 45 cm rectangular

each

(vi )

60 cm x 60 cm square

each

( vii )

90 cm high octagon

each

5142.00 ###
8125.00 ###

Direction and Place Identification signs upto 0.9 sqm size board. (Providing and
erecting direction and place identification retro-reflectorised sign asper IRC:67 made
of encapsulated lens type reflective sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm supported on a
mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the ground by means
of properly designed foundation with M15 grade cement concrete 45 x 45 x 60 cm,
60 cm below ground level as per approved drawing)

sqm

11632.00 ###

sqm

11989.00 ###

72122.00 ###
1978.00 ###

8.5

8.6

8.7

Direction and Place Identification signs with size more than 0.9 sqm size board.
(Providing and erecting direction and place identification retro- reflectorised sign
asper IRC :67 made of encapsulated lens type reflective sheeting vide clause 801.3,
fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported
on a mild steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly fixed to the
ground by means of properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level as per approved
drawing)
Overhead Signs (Providing and erecting overhead signs with a corrosion resistant
aluminium alloy sheet reflectorised with high intensity retro-reflective sheeting of
encapsulated lense type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed support system of
aluminium alloy or galvanised steel trestles and trusses of sections and type as per
structural design requirements and approved plans)

Truss and Vertical Support

tonne

Aluminium alloy plate for over head sign


Painting Two Coats on New Concrete Surfaces (Painting two coats after filling the
surface with synthetic enamel paint in all shades on new plastered concrete
surfaces)
Painting on Steel Surfaces (Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of surface to give an even
shade)
Painting on Wood Surfaces (Providing and applying two coats of ready mix paint of
approved brand on wood surface after through cleaning of surface to give an even
shade)
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on New Work (Painting
lines, dashes, arrows etc on roads in two coats on new work with ready mixed road
marking paint conforming to IS:164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation at site and traffic
control )
Over 10 cm in width

tonne

8.8
8.9
8.10
8.11

(i)

42

6289.00 ###
4281.00 ###

sqm

45.00

###

sqm

39.00

###

sqm

44.00

###

sqm

75.00

###

sqm

65.00

###

(i)

Up to 10 cm in width
Painting Lines, Dashes, Arrows etc on Roads in Two Coats on Old Work (Painting
lines, dashes, arrows etc on roads in two coats on old work with ready mixed road
marking paint confirming to IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation at site and traffic
control )
Over 10 cm in width

sqm

(ii)

Up to 10 cm in width

sqm

51.00
55.00

###
###

8.13

Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass
Beads on Bituminous Surface (Providing and laying of hot applied thermoplastic
compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm
area, thickness of 2.5 mm is exclusive of surface applied glass beads as per
IRC:35 .The finished surface to be level, uniform and free from streaks and holes.)

sqm

514.00 ###

(ii)
8.12

8.14

Kilo Metre Stone (Reinforced cement concrete M15grade kilometre stone of standard
design as per IRC:8-1980, fixing in position including painting and printing etc)

(i)

5th kilometre stone (precast)

each

(ii)

Ordinary Kilometer stone (Precast)

each

2545.00 ###
1571.00 ###

(iii)

Hectometer stone (Precast)

each

454.00 ###

Road Delineators (Supplying and installation of delineators (road way indicators,


hazard markers, object markers), 80-100 cm high above ground level, painted black
and white in 15 cm wide stripes, fitted with 80 x 100 mm rectangular or 75 mm dia
circular reflectorised panels at the top, buried or pressed into the ground and
confirming toIRC-79 and the drawings.)

each

608.00 ###

each

391.00 ###

metre

250.00 ###

metre

416.00 ###

metre

#VALUE! ###

metre

1587.00 ###

metre

1120.00 ###

metre

2849.00 ###

8.15

8.16
8.17

8.18

8.19

8.20

8.21

8.22

(i)

Boundary pillar (Reinforced cement concrete M15 grade boundary pillars of standard
design as per IRC:25-1967, fixed in position including finishing and lettering but
excluding painting)
G.I Barbed wire Fencing 1.2 metre high (Providing and fixing 1.2 metres high GI
barbed wire fencing with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and corner post shall be
strutted on both sides and end post on one side only and provided with 9 horizontal
lines and 2 diagonals interwoven with horizontal wires, fixed with GI staples, turn
buckles etc complete as per clause 807 )
G.I Barbed wire Fencing 1.8 metre high (Providing and fixing 1.8 metres high GI
barbed wire fencing with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade cement concrete, 0.6 metre
below ground level, every 15th post, last but one end post and corner post shall be
strutted on both sides and end post on one side only and provided with 12
horizontal lines and 2 diagonals interwoven with horizontal wires, fixed with GI
staples, turn buckles etc complete as per clause 807 )
Fencing with welded steel wire Fabric 75 mm x 50 mm (Suggestive) (Providing 1.20
metre high fencing with angle iron posts 50 mm x 50 mm x 6 mm at 3 metre center
to center with 0.40 metre embedded in M15 grade cement concrete, corner, end
and every 10th post to be strutted, provided with welded steel wire fabric of 75 mm
x 50 mm mesh or 75 mm x 25 mm mesh and fixed to iron posts by flat iron 50 x 5
mm and bolts etc. complete in all respects.)
Tubular Steel Railing on Medium Weight steel channel ( ISMC series) 100 mm x 50
mm (Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly
painted on medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2
metres high above ground, 2 m centre to centre, complete as per approved
drawings)
Tubular Steel Railing on Precast RCC posts, 1.2 m high above ground level
(Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on
precast M20 grade RCC vertical posts1.8 metres high (1.2 m above GL) with 3 holes
50 mm dia for pipe, fixed 2 metres centre to, complete as per approved drawing)
Reinforced Cement Concrete Crash Barrier (Provision of an Reinforced cement
concrete crash barrier at the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints
filled with pre-moulded asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST circular No. RW/NH 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing
and at locations directed by the Engineer, all as specified)
M 20 grade concrete

43

8.23
A

8.24

8.25

8.26
A

Metal Beam Crash Barrier


Type - A, "W" : Metal Beam Crash Barrier (Providing and erecting a "W" metal beam
crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm
above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5
mm spaced 2 m centre to centre, 1.8 m high, 1.1 m below ground/road level, all
steel parts and fitments to be galvanised by hot dip process, all fittings to conform
to IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a
spacer of channel section 150 x 75 x 5 mm, 330 mm long complete as per clause
810)
Type - B, "THRIE" : Metal Beam Crash Barrier (Providing and erecting a "Thrie" metal
beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 85
cm above road/ground level, fixed on ISMC series channel vertical post, 150 x 75 x 5
mm spaced 2 m centre to centre, 2 m high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip process, all fittings to conform to
IS:1367 and IS:1364, metal beam rail to be fixed on the vertical post with a space of
channel section 150 x 75 x 5 mm, 546 mm long complete as per clause 810)

metre

2675.00 ###

metre

3158.00 ###

Road Traffic Signals electrically operated (Since it is a ready made item


commercially produced and erected by specialised firm in the electrical and
electronic field, rate may be taken based on market enquiry from firms specialised in
this field and ISI certified for the approved design and drawing.)
Flexible Crash Barrier, Wire Rope Safety Barrier (Providing and erecting a wire rope
safety barrier with vertical posts of medium weight RS Joist (ISMB series) 100 mm x
75 mm (11.50 kg/m), 1.50 m long 0.85 m above ground and 0.65 m below ground
level, split at the bottom for better grip, embedded in M 15 grade cement concrete
450 x 450 x 450 mm, 1.50 m center to center and with 4 horizontal steel wire rope
40 mm dia and anchored at terminal posts 15 m apart. Terminal post to be
embedded in M 15 gradecementconcretefoundation2400 x 450 x 900 mm (depth),
strengthened by a strut of RS joist 100 x 75 mm, 2 m long at 450 inclination and a
tie 100 x 8 mm, 1.50 m long at the bottom, all embedded in foundation concrete as
per approved design and drawing, rate excluding excavation and cement concrete.)

Value

metre

1932.00 ###

Anti - Glare Devices in Median

(i)

Plantation (Plantation of shrubs and plants of approved species in the median. apart
from cutting off glare from vehicle coming from opposite direction, these plants
provide a pleasant envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture. )
Anti - Glare Screen with 25 mm steel pipe framework fixed with circular and
rectangular vans (Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of one metre length and
1.75 mtr height fixed with circular vane 250 mm dia at top and rectangular vane
600 x 300 mm at the middle, made out of steel sheet of 3 mm thickness, end
vertical pipes of the panel made larger for embedding in foundation concrete,
applying 2 coats of paint on all exposed surfaces, all as per approved design and
drawings.)
Anti - Glare Screen with Rectangular Vane of MS sheet (Providing and erecting anti glare screen with rectangular vanes of size 750 x 500 mm made from MS sheet, 3
mm thick and fixed on MS angle 50 x 50 x 6 mm at an angle of 450 to the direction
of flow of traffic, 1.5 m center to center, top edge of the screen 1.75 m above
ground level, vertical post firmly embedded in cement concrete foundation 0.60 m
below ground level, applying 2 coats of paint on exposed faces, all complete as per
approved design and drawings)
Street Lighting (Providing and erecting street light mounted on a steel circular
hollow pole of standard specifications for street lighting, 9 m high spaced 40 m
apart, 1.8 m overhang on both sides if fixed in the median and on one side if fixed
on the footpath, fitted with sodium vapour lamp and fixed firmly in concrete
foundation.)
For Fixing in Median

(ii)

For fixing in Footpath

each

#VALUE! ###
#VALUE! ###

Lighting on Bridges (Providing and fixing lighting on bridges, mounted on steel


hollow circular poles of standard specifications, 5 m high fixed on parapets with
cement concrete, 20 m apart and fitted with sodium vapour lamp)

each

#VALUE! ###

(i)

Cable Duct Across the Road (Providing and laying of a reinforced cement concrete
pipe duct, 300 mm dia, across the road (new construction), extending from drain to
drain in cuts and toe of slope to toe of slope in fills, constructing head walls at both
ends, providing a minimum fill of granular material over top and sides of RCC pipe
as per IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock
pieces, outer to outer distance of pipe at least half dia of pipe subject to minimum
450 mm in case of double and triple row ducts, joints to be made leak proof, invert
level of duct to be above higher than ground level to prevent entry of water and dirt,
all as per IRC: 98 - 1997 and approved drawings.)
Single Row for one utility service

metre

(ii)

Double Row for two utility services

metre

#VALUE! ###
#VALUE! ###

(iii)

Triple Row for three utility services

metre

#VALUE! ###

8.27

8.28

8.29

44

Value

metre

2607.00 ###

metre

822.00 ###

each

8.30

8.31

8.32

8.33

(i)
(ii)
8.34
A

8.35

8.36

8.37
A

C
8.38

8.39

Highway Patrolling and Traffic Aid Post (It is proposed to locate one Traffic Aid Post
every 50-60 km of the highway. )

VALUE

Items related to under pass/ subway/ overhead bridge/ overhead foot bridge (The
items involved for underpass/ subway/ overhead bridge/ overhead foot bridge are
earthwork, plain cement concrete, plastering, painting, information sign etc. The
rates for these items are available in respective chapters which can be adopted for
the quantities derived from the approved designs and drawings)

VALUE

Traffic Control System and Communication system (Providing a traffic control centre
and communication system including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central computer system These
are specialised item of telecommunication system and are the commercial products.
The designer is required to contact the manufacturers to ascertain market prices. In
case of civil works required to be executed for these installations, pricing may be
done as per rates in relevant chapters for quantities derived approved design and
drawing.)
Gantry Mounted Variable Message Sign board (Providing and erecting gantry
mounted variable message sign board electronically operated capable of flashing
the desired message over a designed support system of aluminium alloy or
galvanised steel, erected as per approved design and drawings and with lateral
clearance as per clause 802.3)
Gantry Support System

VALUE

tonne

Message Display (Message display board 6 sqm electronically operated with


complete electronic fitments for flashing the pre-determined messages.)

69821.00 ###
VALUE

Traffic Impact Attenuators at Abutments and Piers


With Scrap Tyres (Provision and installation of traffic attenuators at abutment/pier of
flyovers bridges using scrap tyres of size 100 x 20 retrieved from trucks laid in 2
rows and 4 tiers, one above the other and tied with 20 mm wire rope as per
approved design and drawings.)

sqm

611.00 ###

Using Plastic/Steel Barrel, Filled with Sand (Provision and installation of traffic impact
attenuator at abutment/pier of flyovers bridges using plastic/steel barrels 0.60 m dia
and 1.0 m in height, filled with sand in three rows and tied with20 mm steel wire
rope as per approved design and drawings)

sqm

459.00 ###

With HI - DRO cell Sandwich (Patented) ((In this patented HI - DRO cell system,
water gets discharged from plastic tubes on impact over a pre-determined time,
thus absorbing the energy))

sqm

#VALUE! ###

Road Markers/Road Stud with plastic body of RPM/ASA/HIPS as per clause 804.2.1 of
MORTH, fitted with lense reflectors, installed in concrete or asphaltic surface by
drilling hole 30 mm upto a depth of 60 mm and bedded in a suitable bituminous
grout or epoxy mortar, all as per BS 873 part 4:1973)

each

227.00 ###

each

480.00 ###

Traffic Cone (Provision of red fluorescent with white reflective sleeve traffic cone
made of low density polyethylene (LDPE) material with a square base of 390 x 390
x 35 mm and a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per
BS 873)
Roadside Amenities
Rest Areas (Providing plainly furnished accommodation for rest rooms, dormitories,
restaurants, stalls, shops, petrol pump, telephone booth, first aid room, traffic aid
post, police assistance booth, including electricity, toilet and sewerage system
Pricing may be done based on current plinth area rates approved by
PWD/CPWD/MES for a particular zone. Area is required to be assessed for specific
location as per actual site conditions)

VALUE

Parking areas and Bus Laybyes for Trucks, Buses and Light vehicles (Pricing of
parking areas may be done for the quantities of various items based on the
approved dimensions and pavement design for a particular terrain and soil. Rates
for items may be from respective chapters.)

VALUE

Lawn (Providing a lawn planted with grass and its maintenance )

VALUE

Rumble Strips (Provision of 15 nos rumble strips covered with premix bituminous
carpet,
15-20 mm high at center, 250 mm wide placed at 1 m center to center at approved
locations to control speed, marked with white strips of road marking paint.)

sqm

VALUE

Policeman Umbrella (Provision of a 2 m high (floor to roof) umbrella for traffic


policeman at road crossings, where necessary, installed on a raised platform, built
on a central support of a steel pipe 100 mm dia, roof made of 25 mm dia steel pipe
to provide covered area of 3 sqm, roofed with CGI sheets, all steel parts to be given
2 coats of paint)

each

VALUE

45

8.40

8.41
8.42

8.43

8.44
A

8.45

8.46

High Mast Pole Lighting at Interchanges and Flyovers (Providing and erecting a high
mast pole lighting with 30 m high hot dip galvanised mast designed to withstand
forces exerted with wind speeds of 180 km per hour with 3 seconds gust, as per
IS:875 (Part 3) - 1978, fitted with a base flange, door at the base of mast with
heavy duty internal lock, lantern carriage, suitable winching arrangement for safe
working load of 750 kg and high powered electrically driven power tools for raising
and lowering of lantern carriage,
flexible 8 core electric cable,
lightening
conductor, earthing terminal, and fixing 2 nos aviation obstruction lights on top of
the mast, all complete as per approved design and drawings This is a specialised
work and is generally done by firms who specialise in such jobs. The detailed
designs and estimates are submitted by the firms alongwith their tender for checks
by the Department. The cost of this work is required to be worked out based on
approved design, drawings and estimate of the lowest tender. A separate contract
for this work is concluded as the contractors for road and bridge works generally
donot undertake such jobs.)
Toll Plaza (The construction, operation and maintenance of Toll Plaza can be broken
into separate items of work as under based on the approved design and drawings:-)

VALUE

Safety Devices and signs in Construction Zones (Provision and fixing of traffic signs
for limited period at suitable locations in construction zone comprising of warning
zone, approach transition zone, working zone and terminal transition zone with a
minimum distance of 60 cm from the edge of the kerb in case of kerbed roads and 2
to 3 m from the edge of the carriageway in case of un-kerbed roads, the bottom
edge of the lowest sign plate to be not less than 2 m above the road level, fixed on
60 mm x 60 mm x 6 mm angle iron post, founded and installed as per approved
design and drawings, removed and disposed of after completion of construction
work, all as per IRC:SP:55-2001)
Portable Barricade in Construction Zone (Installation of a steel portable barricade
with horizontal rail 300 mm wide, 2.5 m in length fitted on a 'A' frame made with 45
x 45 x 5 mm angle iron section, 1.5 m in height, horizontal rail painted (2 coats)
with yellow and white stripes, 150 mm in width at an angle of 450, 'A' frame
painted with 2 coats of yellow paint, complete as per IRC: SP : 55-2001 )

VALUE

each

2645.00 ###

With Steel Components (Construction of a permanent type barricade made of steel


components, 1.5 m high from road level, fitted with 3 horizontal rails 200 mm wide
and 4 m long on 50 x 50 x 5 mm angle iron vertical support, painted with yellow
and white strips, 150 mm in width at an angle of450, complete as per IRC:SP:552001 )

each

4186.00 ###

With Wooden Components (Construction of a permanent type barricade made of


wooden components, 1.5 m high from road level, fitted with 3 horizontal planks
200 mm wide and 3.66 m long on 100 x 100mm wooden vertical post, painted with
yellow and white striups, 150 mm in width at an angle of450, complete as per
IRC:SP:55-2001 )

each

7374.00 ###

With Bricks (Construction of a permanent type barricade made with brick work in
mud mortar, 1.5 m high, 4 m long, 600 mm thick, plastered with cement mortar
1:6, painted with yellow and white strips)

each

11347.00 ###

Drum Delineator in Construction Zone (Provision of metal drum/empty bitumen


drum delineator, 300 mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white 100 mm wide fitted
with reflectors 3 Nos of 7.5 cm dia, all as per IRC:SP:55-2001)

each

319.00 ###

Flagman (Positioning of a smart flagman with a yellow vest and a yellow cap and a
red flag 600 x 600 mm securely fastened to a staff 1 m in length for guiding the
traffic)

each

292.00 ###

Permanent Type Barricade in Construction Zone

46

CHAPTER-9

PIPE CULVERTS
Item
No.
9.1

9.2

A
B
9.3

A
B

Descriptions

Unit

PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed in foundation and
compacted by vibration including curing for 14 days.)

cum

3279.00 ###

1000 mm dia

metre

5498.00 ###

1200 mm dia

metre

6682.00 ###

1000 mm dia

metre

11048.00 ###

1200 mm dia

metre

13420.00 ###

Rate (in Rs.)

Laying Reinforced Cement Concrete Pipe NP4/prestrssed concrete pipe on first class
bedding in single row . (Laying Reinforced cement concrete pipe NP4/prestrssed
concrete pipe for culverts on first class bedding of granular material in single row
including fixing collar with cement mortar 1:2 but excluding excavation, protection
works, backfilling, concrete and masonry works in head walls and parapets . )

Laying Reinforced Cement Concrete Pipe NP 4 /prestrssed concrete pipe on first


class bedding in double row . (Laying Reinforced cement concrete pipe NP4
/prestrssed concrete pipe for culverts on first class bedding of granular material in
double row including fixing collar with cement mortar 1:2 but excluding excavation,
protection works, backfilling, concrete and masonry works in head walls and
parapets . )

47

CHAPTER-10

MAINTENANCE OF ROADS
Item
No.
10.1

10.2

10.3
10.4

10.5

Descriptions

Unit

Rate (in Rs.)

Restoration of Rain Cuts (Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300 mm width, laying fresh
material in layers not exceeding 250 mm and compacting with plate compactor or
power rammers to restore the original alignment, levels and slopes)

cum

81.00

###

sqm

36.00

###

sqm

13.00

###

Maintenance of Earthen Shoulder (filling with fresh soil) (Making up loss of material/
irregularities on shoulder to the design level by adding fresh approved soil and
compacting it with appropriate equipment.)
Maintenance of Earth Shoulder (stripping excess soil) (Stripping excess soil from the
shoulder surface to achieve the approved level and compacting with plate
compactor)
Filling Pot- holes and Patch Repairs with open - graded Premix surfacing, 20mm.
(Removal of all failed material, trimming of completed excavation to provide firm
vertical faces, cleaning of surface, painting of tack coat on the sides and base of
excavation as per clause 503, back filling the pot holes with hot bituminous material
as per clause 511, compacting, trimming and finishing the surface to form a
smooth continuous surface, all as per clause 3004.2)

sqm

159.00 ###

Filling Pot- holes and Patch Repairs with - Bituminous concrete, 40mm. (Removal of
all failed material, trimming of completed excavation to provide firm vertical faces,
cleaning of surface, painting of tack coat on the sides and base of excavation as per
clause 503, back filling the pot holes with hot bituminous material as per clause
504, compacting, trimming and finishing the surface to form a smooth continuous
surface, all as per clause 3004.2)

(i)

for grading I Material

sqm

419.00 ###

(ii)

for grading II Material

sqm

413.00 ###

10.6

Crack Filling (Filling of crack using slow - curing bitumen emulsion and applying
crusher dust in case crack are wider than 3mm.)

metre

4.10

###

10.7

Dusting (Applying crusher dust to areas of road where bleeding of excess bitumen
has occurred.)

sqm

0.60

###

Fog Seal (ref item 5.17)

sqm

43.00

###

67.00
82.00

###
###

10.8 A
B

Crack Prevention courses. (ref item 5.21)

(i)

Stress Absorbing Membrane (SAM) crack width less than 6 mm

sqm

(ii)

Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm

sqm

(iii)

Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area above
50 %

sqm

110.00 ###

(iv)

Bitumen Impregnated Geotextile

sqm

149.00 ###

Slurry Seal (ref item 5.15)


sqm

72.00

###

(ii)

3 mm thickness

sqm

(iii)

1.5 mm thickness

sqm

51.00
31.00

###
###

98.00
79.00

###
###

(i)

5 mm thickness

Surface Dressing for maintance works. (ref item 5.9)

(i)

19 mm nominal chipping size

sqm

(ii)

13 mm nominal size chipping

sqm

10.9

10.10
10.11
10.12
10.13
10.14
10.15

Repair of joint Grooves with Epoxy Mortar Repair of spalled joint grooves of
contraction joints, longitudinal joints and expansion joints in concrete pavements
using epoxy mortar or epoxy concrete)
Repair of old Joints Sealant (Removal of existing sealant and re sealing of
contraction, longitudinal or expansion joints in concrete pavement with fresh
sealant material)
Hill Side Drain Clearance (Removal of earth from the choked hill side drain and
disposing it on the valley side manually)
Land Slide Clearance in soil (Clearance of land slides in soil and ordinary rock by a
bull-dozer D 80 A-12, 180 HP and disposal of the same on the valley side)
Land slide Clearance in Hard Rock Requiring Blasting (Clearing of land slide in hard
rock requiring blasting for 50% of the boulders and disposal of the same on the
valley side.)
Snow Clearance on Roads with Dozer (Snow clearance from road surface by a bulldozer 165 Hp and disposing it on the valley side)
Snow Clearance on Roads with Snow Blowers (Snow clearance from road surface by
a snow blower and disposing on the valley side.)

48

metre

370.00 ###

metre

18.30

###

metre

23.20

###

cum

66.00

###

cum
cum
cum

114.00 ###
4.60

###

#VALUE! ###

CHAPTER-11

HORTICULTURE
Item
No.

Descriptions

Unit

Rate (in Rs.)

Spreading of Sludge Farm Yard Manure or/and good Earth (Spreading of sludge farm
yard manure or/ and good earth in required thickness (cost of sludge, farm- yard
manure or/and good earth to be paid for separately))

cum

14.90

###

sqm

8.50

###

sqm

13.70

###

Making Lawns including Ploughing and Dragging with 'Swagha' Breaking of Clod
(Making lawns including ploughing and breaking of clod, removal of rubbish,
dressing and supplying doobs grass roots and planting at 15 cm apart, including
supplying and spreading of farm yard manure at rate of 0.18 cum per 100 sqm)

sqm

9.40

###

11.4

Maintenance of Lawns or Turfing of Slopes (Maintenance of lawns or Turfing of slopes


(rough grassing)
for a period of one year including watering etc)

sqm

11.5

Turfing Lawns with Fine Grassing including Ploughing, Dressing (Turfing lawns with
fine grassing including ploughing, dressing including breaking of clods, removal of
rubbish, dressing and supplying doobs grass roots at 10 cm apart, including
supplying and spreading of farm yard manure at rate of0.6 cum per 100 sqm)

sqm

Maintenance of Lawns with Fine Grassing for the First Year

11.1

11.2

(i)
(ii)
11.3

11.6
11.7

(b)

Grassing with ' Doobs' Grass (Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass forms a thick lawn free
from weeds and fit for moving including supplying good earth if needed)
In rows 15 cm apart in either direction
In rows 7.5 cm apart in either direction

227.00 ###

14.70

###

sqm

173.00 ###

a)
Planting Permanent Hedges including Digging of Trenches (Planting permanent
hedges including digging of trenches, 60 cm wide and 45 cm deep, refilling the
excavated earth mixed with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30 cm apart)

metre

258.00 ###

Maintenance of Hedge for one year

metre
km

170.00 ###
68495.00 ###

km

142948.00###

11.8

a)

(b)

Maintenance of Flowering Plants and Shrubs in Central Verge for one Year

11.9

Planting of Trees and their Maintenance for one Year (Planting of trees by the road
side (Avenue trees) in 0.60 m dia holes, 1 m deep dug in the ground, mixing the
soil with decayed farm yard/sludge mannure, planting the saplings, backfilling the
trench, watering, fixing the tree guard and maintaining the plants for one year)

each

Renovation Lawns including, Weeding, Forking the Ground, Top Dressing with
Forked Soil (Renovation lawns including, weeding, forking the ground, top dressing
with forked soil, watering and maintenance the lawns, for 30 days or more, till the
grass forms a thick lawn, free from weeds, and fit for moving and disposal of
rubbish as directed, including supplying good earth, if needed but excluding the
cost of well decayed farm yard manure)

sqm

Supply at Site Well Decayed Farm Yard Manure (Supply at site of work well decayed
farm yard manure, from any available source, approved by the engineer in charge
including screening and stacking)

cum

11.12

Supply at Site of Work/ Store - Deoiled Neem Cake (Supply at site of work/ storedeoiled neem cake duly packed in used gunny bags)

quintal

VALUE

11.13

Supplying Sludge (Supplying sludge duly stacked at site/ store)

cum

VALUE

11.14

Half Brick Circular Tree Guard, in 2nd class Brick, internal diametre 1.25 metres,
and height 1.2 metres, above ground and 0.20 metre below ground (Half brick
circular tree guard, in 2nd class brick, internal diametre 1.25 metres, and height
1.2 metres, above ground and 0.20 metre below ground, bottom two courses laid
dry, and top three courses in cement mortar 1:6 ( 1 cement 6 sand)
and the
intermediate courses being in dry honey comb masonry, as per design complete)

each

Edging with 2nd class Bricks, laid dry lengthwise (Edging with 2nd class bricks, laid
dry lengthwise, including excavation, refilling, consolidation, with a hand packing
and spreading nearly surplus earth within a lead of 50 metres)

metre

Making Tree Guard 53 cm dia and 1.3 m high as per design from empty bitumen
drum (Making tree guard 53 cm dia and 1.3 m high as per design from empty
bitumen drum, slit suitably to permit sun and air, (supplied by the department at
stock issue rate)
including providing and fixing 2 nos MS sheet rings 50 x 0.5 mm
with rivets, complete in all respect)

each

359.00 ###

Making Tree Guard 53 cm dia and 2 metres high as per design from empty bitumen
drums (Making tree guard 53 cm dia and 2 metres high as per design from empty
bitumen drums, slit suitably to permit sun and air, ( supplied by the department at
stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos MS sheet rings 50 x 0.5
mm with rivets complete in all respects)

each

724.00 ###

11.10

11.11

11.15

11.16

11.17

Planting Flowering Plants and Shrubs in Central Verge

49

757.00 ###

13.40

###

640.00 ###

1404.00 ###

28.70

###

11.18

11.19

11.20

11.21

Wrought Iron and Mild Steel Welded Work (Wrought iron and mild steel welded work)
(using angles, square bars, tees and channel grills, grating frames, gates and tree
guards of any size and design etc. including cost of screens and welding rods or
bolts and nuts complete fixed in position but without the cost of excavation and
concrete for fixing which will be paid separately)

quintal

7312.00 ###

Tree Guard with MS Iron (Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm)
each tree
vertical MS riveted to 3 Nos (25 x 6 mm) iron rings in two halves, bolted together
guard
with 8 mm dia and 30 mm long bolts including painting two coats with paint of
approved brand over a coat of priming, complete in all respects.)

1834.00 ###

Tree Guard with MS Angle Iron and Steel Wire (Providing and fixing tree guard 0.60
metre square, 2.00 metre high fabricated with MS angle iron 30 x 30 x 3 mm, MS each tree
iron 25 x 3 mm and steel wire3 mm dia welded and fabricated as per design in two
guard
halves bolted together)

2366.00 ###

Compensatory Afforestation (Planting trees as compensatory afforestation at the


rate of 290 trees per hectare at a spacing of 6 m by grubbing and leveling the
ground upto a depth of 150 mm, digging holes 0.9 m dia, 1 m deep, mixing farm
yard/sludge manure with soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering)

50

hectare

96772.00 ###

CHAPTER-12

FOUNDATIONS
Item
No.
12.1

Descriptions

Unit

Rate (in Rs.)

Excavation for Structures (Earth work in excavation of foundation of structures as


per drawing and technical specification, including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material.)

Ordinary soil

Manual Means

(i)

upto 3 m depth

cum

(ii)

3 m to 6 m depth

cum

(iii)

Above 6 m depth

cum

Mechanical Means

89.00

###

114.00 ###
152.00 ###

(i)

Depth upto 3 m

cum

(ii)

Depth 3 m to 6 m

cum

61.00
69.00

###
###

(iii)

Depth above 6m

cum

84.00

###

II

Ordinary rock (not requiring blasting)

Manual Means

(i)

Depth upto 3 m

cum

Mechanical Means

cum

III

Hard rock ( requiring blasting )

127.00 ###
78.00

###

cum

350.00 ###

cum

369.00 ###

Manual means

cum

Mechanical Means

cum

316.00 ###
140.00 ###

Back Filling in Marshy Foundation Pits

cum

205.00 ###

Manual Means

IV

Hard rock ( blasting prohibited )

Mechanical Means

Marshy soil

(i)

upto 3 m depth

A
B
VI
12.2

Filling Annular Space Around Footing in Rock (Lean cement concrete 1:3:6 nominal
mix. Rate may be taken as per items 13.4.)

12.3

Sand Filling in Foundation Trenches as per Drawing & Technical Specification

cum

256.00 ###

12.4

PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation
with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in
foundation and compacted by vibration including curing for 14 days.)

cum

3772.00 ###

12.5

Brick masonry work in cement mortar in foundation complete excluding pointing and
plastering, as per drawing and technical specifications

###

(i)

Rate for Brick Work in C. M. 1:2 in foundation

cum

5049.00 ###

(ii)

Rate for Brick Work in C. M. 1:3 in foundation

cum

(iii)

Rate for Brick Work in C. M. 1:4 in foundation

cum

4747.00 ###
4542.00 ###

(iv)

Rate for Brick Work in C. M. 1:6 in foundation

cum

12.6 A

Cement mortar1:3 (1cement :3 sand)

cum

Cement mortar1:2 (1cement :2 sand)

cum

Cement mortar1:4 (1cement :4 sand)

cum

Cement mortar1:6 (1cement :6 sand)

cum

4247.00 ###
2711.00 ###
2107.00 ###

12.7

4343.00 ###
3333.00 ###

Stone masonry work in cement mortar 1:3 in foundation complete as drawing and
Technical Specification

(a)

Square Rubble Coursed rubble masonry( first sort )

cum

2933.00 ###

(b)

Random Rubble Masonry

cum

2879.00 ###

12.8

Plain/Reinforced cement concrete in open foundation complete as per drawing and


technical specifications

PCC Grade M15

cum

PCC Grade M20

cum

4128.00 ###
4685.00 ###

RCC Grade M20


cum

4713.00 ###

Case I

Using concrete mixer

51

Case II
D

With Batching Plant, Transit Mixer and Concrete Pump

cum

4626.00 ###

PCC Grade M25

Case I

Using concrete Mixer

cum

5131.00 ###

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5048.00 ###

RCC Grade M25

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5165.00 ###
5078.00 ###

PCC Grade M30

Case I

Using Concrete Mixer

cum

5168.00 ###

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

5080.00 ###

Using Concrete Mixer

cum

5180.00 ###

Using Batching Plant, Transit Mixer and Concrete Pump

cum

5094.00 ###

G
Case I
Case II
H

RCC Grade M30

RCC Grade M35

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

5280.00 ###
5195.00 ###

12.9

Providing and constructing temporary island 16 m diameter for construction of well


foundation for 8m dia. Well.

Assuming depth of water 1.0 m and height of island to be 1.25m including Royalty
for earth @ Rs. 3768.00 for each Island.

each

36325.00 ###

Assuming depth of water 4.0 m and height of island 4.5 m including Royalty for
earth @ Rs. 13565.00 for each Island.

each

149682.00###

Providing and constructing one span service road to reach island location from one
pier location to another pier location including Royalty for earth @ Rs. 225.00 per m
for service Road.

metre

3183.00 ###

12.10

Providing and laying cutting edge of mild steel weighing 40 kg per metre for well
foundation complete as per drawing and technical specification.

tonne

84964.00 ###

12.11

Plain/Reinforced cement concrete, in well foundation complete as per drawing and


technical specification

A
(i)

Well curb
RCC M20 Grade

Case I

Using concrete mixer

cum

5440.00 ###

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5336.00 ###
5975.00 ###
5874.00 ###

(ii)

RCC M25 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(iii)

RCC M35 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

6153.00 ###
6367.00 ###

Well steining

(I)

PCC M15 Grade

cum

4367.00 ###

(ii)

PCC M20 Grade

cum

4956.00 ###

(iii)

RCC M20 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

4987.00 ###
4891.00 ###

(iv)

PCC M25 Grade

Case I

Using concrete mixer

cum

5440.00 ###

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5351.00 ###
5477.00 ###
5385.00 ###

(v)

RCC M25 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(vi)

PCC M30 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

52

5493.00 ###
5398.00 ###

(vii)

RCC M30 Grade

Case I

Using concrete mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5506.00 ###
5415.00 ###

(viii)

RCC M35 Grade

Case I

Using concrete mixer

cum

5640.00 ###

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5837.00 ###
5911.00 ###

5429.00 ###
5036.00 ###

(ix)

RCC M40 Grade

Bottom Plug

(i)

PCC Grade M20

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

(ii)

PCC Grade M25

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

5707.00 ###
5311.00 ###

(iii)

PCC Grade M30

Case I

Using Concrete Mixer

cum

5757.00 ###

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

5364.00 ###
5874.00 ###
5478.00 ###

(iv)

PCC Grade M35

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

Intermediate plug

(I)

Grade M20 PCC

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

(ii)

5200.00 ###
4824.00 ###

Grade M25 PCC

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

5464.00 ###
5085.00 ###

(iii)

Grade M30 PCC

Case I

Using Concrete Mixer

cum

5512.00 ###

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

5136.00 ###

cum

3970.00 ###

cum

4506.00 ###

Top plug

(i)

Grade M15 PCC

Case I
(ii)
Case I
(iii)

Using Concrete Mixer


Grade M20 PCC
Using Concrete Mixer
Grade M25 PCC

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

4946.00 ###
4865.00 ###

(iv)

Grade M30 PCC

Case I

Using Concrete Mixer

cum

4994.00 ###

Case II

Using Batching Plant, Transit Mixer and Crane/concrete pump

cum

4907.00 ###

F
(i)

Well cap
RCC Grade M20

Case I

Using concrete Mixer

cum

4664.00 ###

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

4575.00 ###
5165.00 ###
5079.00 ###

(ii)

RCC Grade M25

Case I

Using concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

(iii)

RCC Grade M30

Case I

Using Concrete Mixer

cum

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

(iv)

RCC Grade M35

53

5180.00 ###
5094.00 ###

Case I

Using Concrete Mixer

cum

5280.00 ###

Case II

Using Batching Plant, Transit Mixer and Concrete Pump

cum

RCC M40 Grade

cum

5195.00 ###
5576.00 ###

(v)
12.12

Sinking of 6 m external diameter well ( other than pneumatic method of sinking )


through all types of strata namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
Sandy soil

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

4368.00 ###
6350.00 ###

metre

8387.00 ###

metre

15733.00 ###

(iii)
a
(iv)
a
b
(v)
a
b

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

18880.00 ###
metre

37380.00 ###
metre

44856.00 ###

Clayey soil ( 6m dia. Well )

(i)

Depth below bed level upto 3.0 M

metre

6359.00 ###

(ii)

Beyond 3m upto 10m depth

metre

14269.00 ###

metre

18845.00 ###

metre

19787.00 ###

metre

35349.00 ###

metre

46395.00 ###

metre

44186.00 ###

metre

83985.00 ###

metre

105821.00###

metre

100782.00###

metre

16814.00 ###

metre

19136.00 ###

(iii)
a
b
(iv)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add for dewatering @ 5% of cost, if required.

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering of the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and
Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering, if required

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

a
b
c
(v)
a

Soft rock (6m dia well )

(i)

Depth of soft rock strata upto 3m

Hard rock (6m dia well )

(i)

Depth of soft rock strata upto 3m

12.13

Sinking of 7 m external diameter well ( other than pneumatic method of sinking )


through all types of strata namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
Sandy soil

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

6794.00 ###
9220.00 ###

(iii)

Beyond 10m upto 20m


metre

12177.00 ###

metre

22840.00 ###

a
(iv)
a

Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter

54

b
(v)
a
b
B

Add 20% of cost for Kentledge including supports, loading arrangement and
Labour) .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour
etc.
Clayey soil ( 7m dia. Well )

metre

27409.00 ###

metre

54265.00 ###

metre

65118.00 ###

metre

(ii)

Beyond 3m upto 10m depth

metre

9220.00 ###
14821.00 ###

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add for dewatering @ 5% of cost, if required.

metre

19574.00 ###

metre

20553.00 ###

metre

36719.00 ###

metre

48194.00 ###

metre

45899.00 ###

metre

87239.00 ###

metre

109922.00###

(I)

a
b
(iv)

Depth below bed level upto 3.0 M

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and
Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering, if required

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

a
b
c
(v)
a

Soft rock ( 7m dia well )

(i)

Depth of soft rock strata upto 3m

Hard rock ( 7m dia well )

(i)

Depth upto 3 m

12.14

104687.00###
metre

15585.00 ###

metre

21620.00 ###

Sinking of 8 m external diameter well ( other than pneumatic method of sinking )


through all types of strata namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
Sandy soil

(i)

Depth below bed level upto 3.0 M

metre

8331.00 ###

(ii)

Beyond 3m upto 10m depth

metre

10323.00 ###

metre

13634.00 ###

metre

25573.00 ###

metre

30688.00 ###

metre

60759.00 ###

metre

72910.00 ###

(iii)
a
(iv)
a
b
(v)
a
b
B

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour
etc.
Clayey soil ( 8m dia. Well )

metre

11276.00 ###

(ii)

Beyond 3m upto 10m depth

metre

15296.00 ###

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add for dewatering @ 5% of cost, if required.

metre

20201.00 ###

metre

21211.00 ###

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering on the cost, if required

metre

37891.00 ###

metre

49732.00 ###

(i)

a
b
(iv)
a
b

Depth upto 3.0 M

55

Add 25% of cost for Kentledge including supports, loading arrangement and
Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering, if required

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

c
(v)
a

Depth in soft rock strata upto 3m

Hard rock ( 8m dia well )

(i)

Depth in hard rock strata upto 3 m

47364.00 ###

metre

90025.00 ###

metre

113431.00###

metre

108030.00###

metre

17190.00 ###

metre

21535.00 ###

Soft rock ( 8m dia well )

(i)

12.15

metre

Sinking of 9 m external diameter well ( other than pneumatic method of sinking )


through all types of strata namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
Sandy soil

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

8395.00 ###
11341.00 ###

metre

14977.00 ###

metre

28094.00 ###

metre

33713.00 ###

metre

66746.00 ###

metre

80096.00 ###

(iii)
a
(iv)
a
b

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour
etc.
Clayey soil ( 9m dia. Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

11859.00 ###
16508.00 ###

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add for dewatering @ 5% of cost, if required.

metre

21801.00 ###

metre

22891.00 ###

metre

40892.00 ###

metre

53670.00 ###

metre

51115.00 ###

metre

97154.00 ###

metre

122414.00###

metre

116584.00###

metre

21787.00 ###

metre

24981.00 ###

metre

10239.00 ###

(v)
a
b

a
b

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and
Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering, if required

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

(iv)
a
b
c
(v)
a

Soft rock ( 9m dia well )

(i)

Depth upto 3m

Hard rock ( 9m dia well )

(i)

Depth of hard rock strata upto 3 m

12.16

A
(i)

Sinking of 10 m external diameter well ( other than pneumatic method of sinking )


through all types of strata namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
Sandy soil
Depth below bed level upto 3.0 M

56

(ii)

Beyond 3m upto 10m depth

(iii)

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

a
(iv)
a
b

metre

11929.00 ###

metre

15753.00 ###

metre

29547.00 ###

metre

35457.00 ###

metre

70200.00 ###

metre

84240.00 ###

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour
etc.
Clayey soil (10m dia. Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

12810.00 ###
16094.00 ###

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add for dewatering @ 5% of cost, if required.

metre

21255.00 ###

metre

22318.00 ###

metre

39869.00 ###

metre

52328.00 ###

metre

49836.00 ###

metre

94725.00 ###

metre

119354.00###

(v)
a
b

a
b

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and
Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering, if required

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

(iv)
a
'b
c
(v)
a

Soft rock (10m dia well )

(i)

Depth of soft rock strata upto 3m

Hard rock (10m dia well )

(i)

Depth of hard rock strata upto 3 m

12.17

113670.00###
metre

22255.00 ###

metre

29660.00 ###

Sinking of 11 m external diameter well ( other than pneumatic method of sinking )


through all types of strata namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
Sandy soil

(i)

Depth from bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

23941.00 ###
17761.00 ###

(iii)

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

metre

23456.00 ###

metre

43998.00 ###

metre

52798.00 ###

metre

104536.00###

metre

125443.00###
21325.00 ###
33000.00 ###

a
(iv)
a
b

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour
etc.
Clayey soil (11 m dia. Well )

(i)

Depth from bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

(iii)

Beyond 10 m upto 20 m

(v)
a
b

57

a
b

Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add for dewatering @ 5% of cost, if required.

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and
Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering, if required

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

(iv)
a
b
c
(v)
a

Soft rock (11m dia well )

(i)

Depth of soft rock strata upto 3m

Hard rock (11m dia well )

(i)

Depth of hard rock upto 3 m

12.18

metre

43583.00 ###

metre

45762.00 ###

metre

81752.00 ###

metre

107300.00###

metre

102190.00###

metre

194230.00###

metre

244730.00###

metre

233077.00###

metre

49888.00 ###

metre

67136.00 ###

Sinking of 12 m external diameter well ( other than pneumatic method of sinking )


through all types of strata namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical specifications. Depth of sinking is
reckoned from bed level.
Sandy soil

(i)

I) Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

48871.00 ###
54178.00 ###

(iii)

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

metre

71552.00 ###

metre

134212.00###

metre

161054.00###

metre

318868.00###

metre

382642.00###

a
(iv)
a
b

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour
etc.
Clayey soil (12 m dia. Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

52649.00 ###
83939.00 ###

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add for dewatering @ 5% of cost, if required.

metre

110857.00###

metre

116400.00###

metre

207940.00###

metre

272921.00###

metre

259925.00###

metre

494034.00###

metre

622483.00###

metre

592841.00###

metre

118194.00###

metre

156036.00###

(v)
a
b

a
b

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and
Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering, if required

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

(iv)
a
b
c
(v)
a

Soft rock (12m dia well )

(i)

Depth of soft rock strata upto 3m

Hard rock (12m dia well )

(i)

Depth of hard rock strata upto 3 m

58

12.19

Sinking of Twin D Type well ( other than pneumatic method of sinking ) through all
types of strata namely sandy soil, clayey soil and rock as shown against each case,
complete as per drawing and technical specifications. Depth of sinking is reckoned
from bed level.

Sandy soil

(i)

Depth from bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

11119.00 ###
11953.00 ###

(iii)

Beyond 10m upto 20m


Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Beyond 20m upto 30 m
Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement and Labour .

metre

15788.00 ###

metre

29613.00 ###

metre

35536.00 ###

metre

70359.00 ###

metre

84430.00 ###

a
(iv)
a
b

Beyond 30m upto 40 m


Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 20% of cost for Kentledge including supports, loading arrangement, and Labour
etc.
Clayey soil (Twin D Type Well )

(i)

Depth below bed level upto 3.0 M

metre

(ii)

Beyond 3m upto 10m depth

metre

12886.00 ###
17882.00 ###

(iii)

Beyond 10 m upto 20 m
Add 5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add for dewatering @ 5% of cost, if required.

metre

23617.00 ###

metre

24797.00 ###

metre

44299.00 ###

metre

58143.00 ###

metre

55374.00 ###

metre

105248.00###

metre

132612.00###

metre

126297.00###

metre

26088.00 ###

metre

32220.00 ###

(v)
a
b

a
b

Beyond 20m upto 30 m


Add 7.5% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering on the cost, if required
Add 25% of cost for Kentledge including supports, loading arrangement and
Labour ).
Beyond 30m upto 40 m
Add 10% for every additional meter depth of sinking over the rate of sinking for the
previous meter
Add 5% of cost for dewatering, if required

Add 20% of cost for Kentledge including supports, loading arrangement and Labour).

(iv)
a
b
c
(v)
a

Soft rock (Twin D Type well )

(i)

Depth of soft rock strata upto 3m

Hard rock (Twin D Type well )

(i)

Depth of hard rock strata upto 3 m

12.20

Pneumatic sinking of wells with equipment of approved design, drawing and


specifications worked by competent and trained personnel and comprising of
compression and decompression chambers, reducers, two air locks separately for
men and plant & materials, arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made from steel plates of riveted
construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required, staircases and 1 m wide landing
plate forms with railing, arrangement for compression and decompression, electric
lighting of 50 V maximum, proper rooms for rest and medical examinations and
compliance with safety precautions as per IS:4138, all as per clause1207.6 of
MoRTH Specifications.

#VALUE!

256.00 ###

12.21

Sand filling in wells complete as per drawing and technical specifications

12.22

Providing steel liner 10 mm thick for curbs and 6mm thick for steining of wells
including fabricating and setting out as per detailed drawing

tonne

78296.00 ###

12.23

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
drawing and technical specifications and removal of excavated earth with all lifts
and lead upto 1000 m. (Pile diameter-750 mm)

metre

5382.00 ###

12.24

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
drawing and technical specifications and removal of excavated earth with all lifts
and lead upto 1000 m. (Pile diameter-1000 mm)

metre

8804.00 ###

59

cum

12.25

Bored cast-in-situ M35 grade R.C.C. pile excluding reinforcement complete as per
drawing and technical specifications and removal of excavated earth with all lifts
and lead upto 1000 m. (Pile diameter-1200 mm)

metre

11252.00 ###

12.26

Driven cast-in-place vertical M35 grade R.C.C. pile excluding reinforcement complete
as per drawing and & Technical Specification (Pile diameter - 750 mm)

metre

4041.00 ###

12.27

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement


complete as per drawing and & Technical Specification (Pile diameter - 1000 mm)

metre

6485.00 ###

12.28

Driven cast-in-place vertical M35 grade R.C.C. piles excluding reinforcement


complete as per drawing and & Technical Specification (Pile diameter - 1200 mm)

metre

9458.00 ###

12.29

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as
per drawing and & Technical Specification (Pile Diameter=500 mm)

metre

#VALUE! ###

12.30

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as
per drawing and & Technical Specification (Pile Diameter=750 mm)

metre

#VALUE! ###

12.31

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as
per drawing and & Technical Specification (Pile Diameter=1000 mm)

metre

#VALUE! ###

12.32

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as
per drawing and & Technical Specification (Size of pile - 300 mm x 300 mm)

metre

#VALUE! ###

12.33

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as
per drawing and & Technical Specification (Size of pile - 500 mm x 500 mm)

metre

#VALUE! ###

12.34

Driven precast vertical M35 grade R.C.C. piles excluding reinforcement complete as
per drawing and & Technical Specification (Size of pile - 750 mm x 750 mm)

metre

#VALUE! ###

12.35

Driven vertical steel piles complete as per drawing and & Technical Specification
(Section of the pile - H Section steel column 400 x 250 mm (ISHB Series) )

metre

#VALUE! ###

12.36

Driven vertical steel piles complete as per drawing and & Technical Specification
(Section of the pile - H Section steel column 450 x 250 mm (ISHB Series) )

metre

#VALUE! ###

Pile load test on single vertical pile in accordance with IS:2911(Part-IV)

tonne

5300.00

12.37
12.38

Cement concrete for reinforced concrete in pile cap complete as per drawing and
Technical Specification

RCC Grade M20

(i)

Using Concrete Mixer

cum

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M25

(i)

Using concrete mixer.

cum

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M30

(i)

Using concrete mixer.

cum

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump

cum

4678.00 ###
4609.00 ###
5158.00 ###
5133.00 ###
5219.00 ###
5150.00 ###

RCC Grade M35

(i)

Using concrete mixer.

cum

(ii)

Using Batching Plant, Transit Mixer and Concrete Pump

cum

12.39

Levelling course for Pile cap

cum

5346.00 ###
5321.00 ###
3955.00 ###

12.40

Supplying, fitting and placing un-coated HYSD bar reinforcement in foundation


complete as per drawing and technical specifications

tonne

69220.00 ###

12.41

Supplying, fitting and placing un-coated Mild steel reinforcement complete in


foundation as per drawing and technical specification

tonne

73230.00 ###

60

CHAPTER-13

SUB-STRUCTURE
Item
No.

Descriptions

Unit

13.1

Brick masonry work in 1:3 in sub-structure complete excluding pointing and


plastering, as per drawing and technical specifications

cum

4771.00 ###

13.2

Pointing with cement mortar (1:3 ) on brick work in substructure as per Technical
specifications

10 sqm

430.00 ###

13.3

Plastering with cement mortar (1:3 ) on brick work in sub-structure as per Technical
specifications

10 sqm

953.00 ###

13.4

Stone masonry work in cement mortar 1:3 for substructure complete as per drawing
and Technical Specifications

Rate (in Rs.)

Random Rubble Masonry

cum

Coursed rubble masonry (first sort )

cum

Ashlar masonry ( first sort )

cum

2908.00 ###
2999.00 ###
3765.00 ###

cum

4367.00 ###

cum

4956.00 ###

5440.00 ###
5351.00 ###

13.5

Plain/Reinforced cement concrete in sub-structure complete as per drawing and


technical specifications

PCC Grade M15

(p)

Height upto 5m

PCC Grade M20

(p)

Height upto 5m

PCC Grade M25

(p)

Height upto 5m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(q)

Height 5m to 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(r)

Height above 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

PCC Grade M30

(p)

Height upto 5m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(q)

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M20

(p)

Height upto 5m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M25

(p)

Height upto 5m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5168.00 ###
5069.00 ###
5395.00 ###
5292.00 ###

5477.00 ###
5385.00 ###
5656.00 ###
5561.00 ###

Height above 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M30

(p)

Height upto 5m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(q)

4987.00 ###
4891.00 ###

Height 5m to 10m

Case I
(r)

5943.00 ###
5840.00 ###

Height above 10m

Case I

(q)

5693.00 ###
5594.00 ###

Height 5m to 10m

Case I
(r)

5493.00 ###
5398.00 ###

Height above 10m

Case I

(q)

5886.00 ###
5789.00 ###

Height 5m to 10m

Case I
(r)

5638.00 ###
5546.00 ###

Height 5m to 10m

61

5925.00 ###
5825.00 ###

5506.00 ###
5415.00 ###

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(r)

Height above 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

RCC Grade M35

(p)

Height upto 5m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(q)

5881.00 ###
5784.00 ###

5640.00 ###
5837.00 ###

Height 5m to 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

(r)

5661.00 ###
5567.00 ###

5763.00 ###
5964.00 ###

Height above 10m

Case I

Using concrete Mixer

cum

Case II

With Batching Plant, Transit Mixer and Concrete Pump

cum

5948.00 ###
6155.00 ###

13.6

Supplying, fitting and placing HYSD bar reinforcement in sub-structure complete as


per drawing and technical specifications

tonne

69327.00 ###

13.7

Supplying, fitting and placing Mild steel reinforcement complete in sub-structure as


per drawing and technical specification

tonne

72707.00 ###

13.8

Providing weep holes in Brick masonry/Plain/Reinforced concrete abutment, wing


wall/return wall with 100 mm dia AC pipe, extending through the full width of the
structure with slope of 1V :20H towards drawing foce. Complete as per drawing and
Technical specifications

each

124.00 ###

13.9

Back filling behind abutment, wing wall and return wall complete as per drawing
and Technical specification

Granular material

cum

Sandy material

cum

480.00 ###
408.00 ###

Providing and laying of Filter media with granular materials/stone crushed


aggregates satisfying the requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm with smaller size towards the
soil and bigger size towards the wall and provided over the entire surface behind
abutment, wing wall and return wall to the full height compacted to a firm condition
complete as per drawing and technical specification.

cum

1219.00 ###

Supplying, fitting and fixing in position true to line and level cast steel rocker
bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as per drawing and Technical
Specifications.

tonne
capacity

312.00 ###

Supplying, fitting and fixing in position true to line and level forged steel roller
bearing conforming to IRC: 83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as per drawing and Technical
Specifications.

tonne
capacity

209.00 ###

Supplying, fitting and fixing in position true to line and level sliding plate bearing
with PTFE surface sliding on stainless steel complete including all accessories as per
drawing and Technical Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE)
and clause 2004 of MoRTH Specifications.

tonne
capacity

#VALUE! ###

13.10

13.11

13.12

13.13

13.14

13.15

13.16

Supplying, fitting and fixing in position true to line and level elastomeric bearing
cubic
conforming to IRC: 83 (Part-II) section IX and clause 2005 of MoRTH specifications
centimetre
complete including all accessories as per drawing and Technical Specifications.

0.72

###

Supplying, fitting and fixing in position true to line and level sliding plate bearing
with stainless steel plate sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and Technical Specifications.

tonne
capacity

396.00 ###

Supplying, fitting and fixing in position true to line and level POT-PTFE bearing
consisting of a metal piston supported by a disc or unreinforced elastomer confined
within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against
stainless steel mating surface, completre assembly to be of cast steel/fabricated
structural steel, metal and elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400, section 9.1 & 9.2 and clause
2006 of MoRTH Specifications complete asper drawing and approved technical
specifications.

tonne
capacity

178.00 ###

62

CHAPTER-14

SUPER-STRUCTURE
Item
No.
14.1
A
Case I

Descriptions

Unit

Furnishing and Placing Reinforced/Prestressed cement concrete in super-structure as


per drawing and Technical Specification
RCC Grade M20
Using Concrete Mixer

(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

Case II
(i)

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

RCC Grade M25


For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

(i)

For solid slab super-structure, 20-30% of (a+b+c)


Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

RCC Grade M 30

5499.00 ###
5719.00 ###
5939.00 ###

5935.00 ###
6183.00 ###
6430.00 ###
6183.00 ###
6430.00 ###
6677.00 ###

5839.00 ###
6083.00 ###
6326.00 ###
6083.00 ###
6326.00 ###
6569.00 ###

Using Concrete Mixer

(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

Case II

5279.00 ###
5499.00 ###
5719.00 ###

Using Batching Plant, Transit Mixer and Concrete Pump

(p)

Case I

5606.00 ###
5830.00 ###
6054.00 ###

Using Concrete Mixer

(i)

Case II

5381.00 ###
5606.00 ###
5830.00 ###

Using Batching Plant, Transit Mixer and Concrete Pump

(p)

Case I

Rate (in Rs.)

Using Batching Plant, Transit Mixer and Concrete Pump.

63

6026.00 ###
6277.00 ###
6528.00 ###
6277.00 ###
6528.00 ###
6779.00 ###

(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

RCC/PSC Grade M35

Case 1

Using concrete mixer.

(i)

For solid slab super-structure, 18-28% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 23-33% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

(iii)

For box girder and balanced cantilever, 38-58% of cost of concrete.

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

Case II
(i)

For solid slab super-structure, 18-28% of (a+b+c)


Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 23-33% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

(iii)

For box girder and balanced cantilever, 38-58% of cost of concrete.

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

PSC Grade M-40

6069.00 ###
6326.00 ###
6584.00 ###
6326.00 ###
6584.00 ###
6841.00 ###
7098.00 ###
7612.00 ###
8127.00 ###

5954.00 ###
6207.00 ###
6459.00 ###
6207.00 ###
6459.00 ###
6711.00 ###
6964.00 ###
7468.00 ###
7973.00 ###

Using concrete mixer.

(i)

For solid slab super-structure, 20-30% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 25-35% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

Case II

6156.00 ###
6402.00 ###
6648.00 ###

Using Batching Plant, Transit Mixer and Concrete Pump

(p)

Case 1

5910.00 ###
6156.00 ###
6402.00 ###

6602.00 ###
6877.00 ###
7152.00 ###
6877.00 ###
7152.00 ###
7427.00 ###

Using Batching Plant, Transit Mixer and Concrete Pump

(i)

For solid slab super-structure, 18-28% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum
cum

(r)

Height above 10m

(ii)

For T-beam & slab, 23-33% of (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

(iii)

For box girder and balanced cantilever, 38-58% of cost of concrete.

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

64

6348.00 ###
6617.00 ###
6886.00 ###
6617.00 ###
6886.00 ###
7155.00 ###
7424.00 ###
7962.00 ###
8500.00 ###

F
(i)

PSC Grade M-45


For solid slab/voided slab super-structure, 16-26% of cost of concrete (a+b+c)

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

cum

(p)

Height above 10m


For I-beam & slab including launching of precast girders by launching truss upto 40
m span, 21-31% of cost of concrete.
Height upto 5m

(q)

Height 5m to 10m

cum

(r)

(p)

Height above 10m


For cast-in-situ box girder,
56% of cost of concrete.
Height upto 5m

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

(p)

PSC Grade M-50


For cast-in-situ box girder,
55% of cost of concrete
Height upto 5m

(q)

Height 5m to 10m

cum

(r)

Height above 10m

cum

PSC Grade M- 55

(i)

For cast-in-situ box girder,


55% of cost of concrete

(p)

Height upto 5m

cum

(q)

Height 5m to 10m

cum

(r)

Height above 10m

(ii)

(iii)

(i)

cum
cum

segmental construction and balanced cantilever,

7725.00 ###
8293.00 ###
8861.00 ###

35cum

segmental construction and balanced cantilever,

6873.00 ###
7157.00 ###
7441.00 ###

36cum

segmental construction and balanced cantilever,

6589.00 ###
6873.00 ###
7157.00 ###

7958.00 ###
8548.00 ###
9137.00 ###

35-

cum

8412.00 ###
9035.00 ###
9658.00 ###

14.2

a)
Supplying, fitting and placing HYSD bar reinforcement in super-structure
complete as per drawing and technical specifications

tonne

70212.00 ###

14.3

High tensile steel wires/strands including all accessories for stressing, stressing
operations and grouting complete as per drawing and Technical Specifications

tonne

111034.00###

14.4

Providing and laying Cement concrete wearing coat M-30 grade including
reinforcement complete as per drawing and Technical Specifications
Mastic Asphalt (Providing and laying 12 mm thick mastic asphalt wearing course on
top of deck slab excluding prime coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using mastic cooker and laid to
required level and slope after cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone chipping of 9.5 mm nominal
size at the rate of 0.005cum per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface when the temperature of
surfaces not less than 100 deg. C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.)

cum

10228.00 ###

sqm

#VALUE! ###

Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12
mm, true to line and grade, tolurence of vertical RCC post not to exceed 1 in 500,
centre to centre spacing between vertical post not to exceed 2000 mm, leaving
adequate space between vertical post for expansion, complete as per approved
drawings and technical specifications.

metre

1791.00 ###

Construction of RCC railing of M30 Grade in-situ with 20 mm nominal size


aggregate, true to line and grade, tolurence of vertical RCC post not to exceed 1 in
500, centre to centre spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion, complete as per
approved drawings and technical specifications.

metre

1736.00 ###

14.8

Providing, fitting and fixing mild steel railing complete as per drawing and Technical
Specification

metre

3123.00 ###

14.9

14.5

14.6

14.7

Drainage Spouts complete as per drawing and Technical specification

each

906.00 ###

14.10

PCC M15 Grade leveling course below approach slab complete as per drawing and
Technical specification

cum

3970.00 ###

14.11

Reinforced cement concrete approach slab including reinforcement and formwork


complete as per drawing and Technical specification

cum

8532.00 ###

14.12

Providing anti-corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy


Coating (FBEC)
(To be taken as per the prevailing market rates.)
Precast - pretensioned Girders (Providing, precasting, transportation and placing in
position precast pretensioned concrete girders as per drawing and technical
specifications)
Providing and fixing Helical pipes in voided concrete slabs

14.13
14.14

65

tonne

VALUE

cum

#VALUE! ###

metre

#VALUE! ###

14.15

14.16

14.17

14.18

Crash Barriers (The rate analysis for rigid crash barrier in reinforced cement
concrete, semi-rigid crash barrier with metal beam and flexible crash barrier with
wire ropes have been made and included in chapter-8 on Traffic and Transportation.)
Painting on concrete surface (Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil,
grease, efflorescence and applying paint @ of 1 litre for 2 Sq.m. )
Burried Joint (Providing and laying a burried expansion joint, expansion gap being
20 mm, covered with 12 mm thick, 200 mm wide galvanised wieldable structural
steel plate as per IS: 2062, placed symmetrical to centre line of the joint, resting
freely over the top surface of the deck concrete, welding of 8 mm dia. 100 mm long
galvanised nails spaced 300 mm c/c along the centre line of the plate, all as
specified in clause 2604.)
Filler joint

metre

VALUE

metre

67.00

###

metre

1284.00 ###

(i)

Providing & fixing 2 mm thick corrugated copper plate in expansion joint complete
as per drawing & Technical Specification.

metre

3057.00 ###

(ii)

Providing & fixing 20 mm thick compressible fibre board in expansion joint complete
as per drawing & Technical Specification.

metre

212.00 ###

(iii)

Providing and fixing in position 20 mm thick premoulded joint filler in expansion joint
for fixed ends of simply supported spans not exceeding 10 m to cater for a
horizontal movement upto 20 mm, covered with sealant complete as per drawing
and technical specifications.

metre

299.00 ###

(iv)
14.19

14.20

14.21

14.22

14.23

14.24

Providing and filling joint sealing compound as per drawings and technical
specifications with coarse sand and 6% bitumen by weight
Asphaltic Plug joint (Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2 mm, depth of joint
varying from 75 mm to 100 mm, width varying from 500 mm to 750 mm (in traffic
direction), covered with a closure plate of 200mm x 6mm of wieldable structural
steel conforming to IS: 2062, asphaltic plug to consist of polymer modified bitumen
binder, carefully selected single size aggregate of 12.5 mm nominal size and a heat
resistant foam caulking/backer rod,
all as per approved drawings and
specifications.)
Elastomeric Slab Steel Expansion Joint (Providing and laying of an elastomeric slab
steel expansion joint, catering to right or skew (less than 20 deg., moderately
curved with maximum horizontal movement upto 50 mm,
complete as per
approved drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative ensuring compliance to the
manufacturer's instructions for installation and clause 2606 of MoRTH specifications
for road & bridge works.)
Compression Seal Joint (Providing and laying of compression seal joint consisting of
steel armoured nosing at two edges of the joint gap suitably anchored to the deck
concrete and a preformed chloroprene elastomer or closed cell foam joint sealer
compressed and fixed into the joint gap with special adhesive binder to cater for a
horizontal movement upto 40 mm and vertical movement of 3 mm.)
Strip Seal Expansion Joint (Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm, complete as per approved
drawings and standard specifications to be installed by the manufacturer/supplier or
their authorised representative ensuring compliance to the manufacturer's
instructions for installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip Box steel
expansion joint including anchorage catering to a horizontal movement beyond 70
mm and upto 140mm,
complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's instructions for
installation.)
Modular Strip / Box Seal Joint (Providing and laying of a modular strip box seal
expansion joint catering to a horizontal movement beyond 140mm and upto
210mm, complete as per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.)

66

metre

19.20

###

metre

1122.00 ###

metre

28075.00 ###

metre

#VALUE! ###

metre

8754.00 ###

metre

29462.00 ###

metre

#VALUE! ###

CHAPTER-15

RIVER TRAINING AND PROTECTION WORKS


Item
No.
15.1

A
15.2

15.3

15.4

Descriptions

Unit

Rate (in Rs.)

Providing and laying boulders apron on river bed for protection against scour with
stone boulders weighing not less than 40 kg each complete as per drawing and
Technical specification.
Boulder laid dry without wire crates.

cum

865.00 ###

Boulder apron laid in wire crates (Providing and laying of boulder apron laid in wire
crates made with 4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x
100mm mesh (weaved diagonally) including 10% extra for laps and joints laid with
stone boulders weighing not less than 40 kg each.)

cum

1167.00 ###

Cement concrete blocks (size 0.5 x 0.5 x 0.5 m) (Providing and laying of apron with
cement concrete blocks of size 0.5x0.5x0.5 m cast in-situ and made with nominal
mix of M-15 grade cement concrete with a minimum cement content of 250 kg/cum
as per IRC: 21-2000.)

cum

4211.00 ###

Providing and laying Pitching on slopes laid over prepared filter media including
boulder apron laid dry in front of toe of embankment complete as per drawing and
Technical specifications

Stone/Boulder

cum

865.00 ###

Cement Concrete blocks of size 0.3x0.3 x0.3 m cast in cement concrete of Grade
M15

cum

4211.00 ###

15.5

Providing and laying Filter material underneath pitching in slopes complete as per
drawing and Technical specification

cum

1339.00 ###

15.6

Geotextile Filter (Laying of a geotextile filter between pitching and embankment


slopes on which pitching is laid to prevent escape of the embankment material
through the voids of the stone pitching/cement concrete blocks as well as to allow
free movement of water without creating any uplift head on the pitching.)

sqm

141.00 ###

cum

3592.00 ###
5545.00 ###
1117.00 ###

15.7

Toe protection (A toe wall for toe protection can either be in dry rubble masonry in
case of dry rubble pitching or pitching with stones in wire crates or it can be in PCC
M15 nominal mix if cement concrete block have been used for pitching . Rates for
toe wall can be adopted from respective clauses depending upon approved design.
The rate for excavation for foundation, dry rubble masonry and PCC M15 have been
analysed and given in respective chapters.)

15.8

Providing and laying Flooring complete as per drawing and Technical specifications
laid over cement concrete bedding.

A
B
15.9
15.10

Rubble stone laid in cement mortar 1:3


Cement Concrete blocks Grade M15

cum

Dry rubble Flooring

cum

Curtain wall complete as per drawing and Technical specification

Stone masonry in cement mortar (1:3)

cum

Cement concrete Grade M15

cum

2933.00 ###
4128.00 ###

cum

906.00 ###

cum

1194.00 ###

cum

1804.00 ###

15.11
15.12

15.13

Flexible Apron :Construction of flexible apron 1 m thick comprising of loose stone


boulders weighing not less than 40 kg beyond curtain wall.
Gabian Structure for Retaining Earth (Providing and construction of a gabain
structure for retaining earth with segments of wire crates of size 7 m x 3 m x 0.6 m
each divided into 1.5 m compartments by cross netting, made from 4 mm
galvanised steel wire @ 32 kg per 10 sqm having minimum tensile strength of 300
Mpa conforming to IS:280 and galvanizing coating conforming to IS:4826, woven
into mesh with double twist, mesh size not exceeding 100 x 100 mm, filled with
boulders with least dimension of 200 mm, all loose ends to be tied with 4 mm
galvanised steel wire)
Gabian Structure for Erosion Control, River Training Works and Protection works
(Providing and constructing gabain structures for erosion control, river training
works and protection works with wire crates of size 2 m x 1 m x 0.3 m each divided
into 1m compartments by cross netting, made from 4 mm galvanised steel wire @
32 kg per 10 sqm having minimum tensile strength of 300 Mpa conforming to IS:280
and galvanizing coating conforming to IS:4826, woven into mesh with double twist,
mesh size not exceeding 100 mm x 100 mm, filled with boulders with least
dimension of 200 mm, all loose ends to be securely tied with 4 mm galvanised steel
wire.)

67

CHAPTER-16

REPAIR AND REHABILITATION


Item
No.

Descriptions

Unit

Rate (in Rs.)

Removal of existing cement concrete wearing coat including its disposal complete as
per Technical specification without causing any detrimental effect to any part of the
bridge structure and removal of dismantled material with all lifts and lead upto
1000m (Thickness 75 mm)

sqm

81.00

###

Removal of existing asphaltic wearing coat comprising of 50 mm thick asphaltic


concrete laid over 12 mm thick mastic asphalt including disposal with all lift and
lead upto 1000m.

sqm

61.00

###

16.3

Guniting concrete surface with cement mortar applied with compressor after
cleaning surface and spraying with epoxy complete as per Technical specification

sqm

16.4

Providing and inserting nipples with approved fixing compound after drilling holes
for grouting as per Technical specifications including subsequent cutting/removal
and sealing of the hole as necessary of nipples after completion of grouting with
Cement/Epoxy

each

16.1

16.2

16.5

#VALUE! ###

75.00

###

Sealing of cracks/porous concrete by injection process through nipples/Grouting


complete as per Technical specification.
kg

103.00 ###
98.00 ###

Patching of damaged concrete surface with polymer concrete and curing


compounds, initiator and promoter, available in present formulations, to be
applied as per instructions of manufacturer and as approved by the Engineer.

sqm

#VALUE! ###

16.7

Sealing of crack / porous concrete with Epoxy Grout by injection through nipples
complete as per clause 2803.1.

kg

#VALUE! ###

16.8

Applying epoxy mortar over leached, honey combed and spalled concrete surface
and exposed steel reinforcement complete as per Technical specification

sqm

403.00 ###

16.9

Removal of defective concrete, cleaning the surface thoroughly, applying the


shotcrete mixture mechanically with compressed air under pressure, comprising of
cement, sand, coarse aggregates, water and quick setting compound in the
proportion as per clause 2807.1., sand and coarse aggregates conforming to IS: 383
and table 1 of IS: 9012 respectively, water cement ratio ranging from 0.35 to 0.50,
density of gunite not less than 2000 kg/cum, strength not less than 25 Mpa and
workmanship conforming to clause 2807.6.

sqm

#VALUE! ###

16.10

Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28 days


for replacement of spalled concrete

sqm

#VALUE! ###

16.11

Eproxy bonding of new concrete to old concrete

sqm

596.00 ###

16.12

Providing external prestressing with high tensile steel wires/strands including drilling
for passage of prestessing steel,
all accessories for stressing and stressing
operation and grouting complete as per drawing and Technical specification

tonne

324298.00###

Providing external prestressing with high tensile steel wires/strands including drilling
for passage of prestessing steel,
all accessories for stressing and stressing
operation and grouting complete as per drawing and Technical specification

tonne

317064.00###

Providing external prestressing with high tensile steel wires/strands including drilling
for passage of prestessing steel,
all accessories for stressing and stressing
operation and grouting complete as per drawing and Technical specification

tonne

307773.00###

16.15

Replacement of bearings complete as per Technical specification

each

#VALUE! ###

16.16

Rectification of bearings as per Technical specifications

each

#VALUE! ###

16.17

Replacement of Expansion Joints complete as per drawings

metre

2312.00 ###

16.18

Replacement of damaged concrete railing.

metre

156.00 ###

16.19

Replacement of crash barrier.

metre

288.00 ###

16.20

Replacement of damaged mild steel railing


Repair of crash barrier (Repair of concrete crash barrier with cement concrete of M30 grade by cutting and trimming the damaged portion to a regular shape, cleaning
the area to be repaired thoroughly, applying cement concrete after erection of
proper form work.)
Repair of RCC Railing (Carrying out repair of RCC M30 railing to bring it to the
original shape.)

metre

130.00 ###

metre

211.00 ###

metre

162.00 ###

Repair of steel Railing (Repair of steel railing to bring it to the original shape)

metre

291.00 ###

A
B
16.6

16.13

16.14

16.21

16.22
16.23

Cement Grout

kg

Cement mortar (1:1) Grouting

68

CHAPTER - 1
CARRIAGE OF MATERIALS
Sr Ref. to
MoRTH
No Spec.
1.1

Remark
Unit Quantity Rate Rs Cost Rs s/ Input
ref.

Description

cum
Loading and Unloading of Stone Boulder/ Stone
aggregates/Sand/ Kanker/Moorum
Placing tipper at loading point, loading with front end
loader, dumping, turning for return trip, excluding time
for haulage and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i)

Positioning of tipper at loading point

1 Min

ii)
Loading by front end loader 1 cum bucket capacity @
25 cum per hour
iii)
Maneuvering, reversing, dumping and turning for
return
iv)
Waiting time, unforeseen contingencies etc

13 Min
2 Min
4 Min

Total
a)

20 Min

Machinery
Tipper 5.5 tonnes capacity

hour

0.330

873.00

288.09

P&M-048

Front end-loader 1 cum bucket capacity @ 25 cum/hour

hour

0.330

1188.00

392.04

P&M-017

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

68.01
74.81

Cost for 5.5 cum = a+b+c

822.96

Rate per cum = (a+b+c)/ 5.5

149.63

Note Unloading will be by tipping.


1.2

say

150.00

Loading and Unloading of Boulders by Manual


Means
Unit = cum
Taking output = 5.5 cum
a)

b)

Labour
Mate

day

0.110

185.07

20.36

L-12

Mazdoor for loading and unloading

day

0.750

177.07

132.80

L-13

hour

0.750

873.00

654.75

P&M-048

Machinery
Tipper 5.5 tonne capacity

c)

Overhead charges @ 0.1 on (a+b)

80.79

d)

Contractor's profit @ 0.1 on (a+b+c)

88.87

Cost for5.5 cum = a+b+c+d

977.57

Rate per cum = (a+b+c+d)/5.5

177.74

Note Unloading will be by tipping.


1.3

say

178.00

Loading and Unloading of Cement or Steel by


Manual Means and Stacking.
Unit = tonne
Taking output = 10 tonnes
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor for loading and unloading

day

2.000

177.07

354.14

L-13

hour

2.000

773.00

1546.00

Machinery
Truck 10 tonne capacity

c)

Overhead charges @ 0.1 on (a+b)

191.49

d)

Contractor's profit @ 0.1 on (a+b+c)

210.64

Cost for10 tonnes = a+b+c+d

2317.08

Rate per tonnes = (a+b+c+d)/10

231.71
say

67

232.00

P&M-057

Sr Ref. to
MoRTH
No Spec.

Remark
Unit Quantity Rate Rs Cost Rs s/ Input
ref.

Description

1.4

Cost of Haulage Excluding Loading and Unloading


Haulage of materials by tipper excluding cost of loading,
unloading and stacking.
Unit = t.km
Taking output 10 tonnes load and lead 10 km = 100
t.km

(i)

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a)

Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with load

hour

0.400

873.00

349.20

P&M-048

Time taken for empty return trip.

hour

0.290

873.00

253.17

P&M-048

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

60.24
66.26

cost for 100 t km = a+b+c

728.87

Rate per t.km = (a+b+c)/100

7.29
say

1.4

(ii)

7.30

Unsurfaced Graveled Road


Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with load

hour

0.500

873.00

436.50

P&M-048

Time taken for empty return trip

hour

0.330

873.00

288.09

P&M-048

b)

Overhead charges @ 0.1 on (a)

72.46

c)

Contractor's profit @ 0.1 on (a+b)

79.70

Cost for 100 t .km = a+b+c

876.75

Rate per t.Km = (a+b+c)/100

8.77
say

1.4

(iii)

8.80

Katcha Track and Track in River Bed/Nallah Bed


and Choked Bed
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage

hour

1.000

873.00

873.00

P&M-048

Time taken for empty return trip

hour

0.670

873.00

584.91

P&M-048

b)

Overhead charges @ 0.1 on (a)

145.79

c)

Contractor's profit @ 0.1 on (a+b)

160.37

Cost for 100 t .km = a+b+c

1764.07

Rate per t.Km = (a+b+c)/100

17.64
say

68

17.60

Sr Ref. to
MoRTH
No Spec.
1.5

Remark
Unit Quantity Rate Rs Cost Rs s/ Input
ref.

Description
Hand Broken Stone Aggregates 63 mm Nominal
Size
Supply of quarried stone, hand breaking into coarse
aggregate 63 mm nominal size (passing 80 mm and
retained on 50 mm sieve) and stacking as directed
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.060

185.07

11.10

L-12

Mazdoor

day

1.500

177.07

265.61

L-13

cum

1.100

536.00

589.60

M-002

Material
Supply of quarried stone 150 - 200 mm size

c)

Overhead charges @ 0.1 on (a+b)

86.63

d)

Contractor's profit @ 0.1 on (a+b+c)

95.29

Rate per cum = a+b+c+d

1048.23
say

1.6

1048.00

Crushing of Stone Aggregates 13.2 mm Nominal


Size
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 200 tonnes per hour
capacity comprising of primary and secondary crushing
units, belt conveyor and vibrating screens to obtain
stone aggregates of 13.2 mm nominal size.
Unit = cum
Taking Output = 600 cum at crusher location.
a)

b)

Labour
Mate

day

0.760

185.07

140.65

L-12

Mazdoor Skilled

day

2.000

206.99

413.98

L-15

Mazdoor including breaking of any oversize boulder.

day

17.000

177.07

3010.19

L-13

cum

800.000

511.80

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

16760.52

Hour

20.000

1188.00

23760.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

873.00

17460.00

P&M-048

Material
Stone Boulder of size 150 mm and below

c)

###

M-001

Machinery
### P&M-028

d)

Overhead charges @ 0.1 on (a+b+c)

55478.79

e)

Contractor's profit @ 0.1 on (a+b+c+d)

61026.67

Cost for 600 cum = (a+b+c+d+e)x0.95

###

Rate per cum = (a+b+c+d+e) * 0.95 / 600

1062.88
say

1063.00

Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 95 per cent
of above cost will be attributed to the
production of 600 cum of stone chips of 13.2 mm size and
balance 5 per cent to the production of stone dust which
comes out as a by-product.
3. The integrated stone
secondary crushing units.
1.7

crusher

includes

primary

and

Crushing of Stone Aggregates 20 mm Nominal


Size
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 200 tonnes per hour
capacity comprising of primary and secondary crushing
units, belt conveyor and vibrating screens to obtain
stone aggregates of 20 mm nominal size.
Unit = cum
Taking Output = 670 cum at crusher location.
a)

Labour
Mate

day

69

0.760

185.07

140.65

L-12

Sr Ref. to
MoRTH
No Spec.

Remark
Unit Quantity Rate Rs Cost Rs s/ Input
ref.

Description

b)

Mazdoor Skilled

day

2.000

206.99

413.98

L-15

Mazdoor including breaking of any size boulder.

day

17.000

177.07

3010.19

L-13

cum

800.000

511.80

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

16760.52

Hour

20.000

1188.00

23760.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

873.00

17460.00

P&M-048

Material
Stone Boulder of size 150 mm and below

c)

###

M-001

Machinery
### P&M-028

d)

Overhead charges @ 0.1 on (a+b+c)

55478.79

e)

Contractor's profit @ 0.1 on (a+b+c+d)

61026.67

Cost for 670 cum = (a+b+c+d+e)x0.90

###

Rate per cum = (a+b+c+d+e) * 0.90 / 670

901.74
say

902.00

Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 20 and 40 mm.
2. 90 per cent
of above cost will be attributed to the
production of 670 cum of stone aggregates of 20mm size and
balance 10 per cent will be for smaller size aggregates and
stone dust which comes out as a by-product.
3. The integrated stone
secondary crushing units.
1.8

crusher

includes

primary

and

Crushing of Stone Aggregates 40 mm Nominal


Size
Crushing of stone boulders of 150 mm size in an
integrated stone crushing unit of 200 tonnes per hour
capacity comprising of primary and secondary crushing
units, belt conveyor and vibrating screens to obtain
stone aggregates of 40 mm nominal size.
Unit = cum
Taking Output = 750 cum at crusher location.
a)

b)

Labour
Mate

day

0.760

185.07

Mazdoor Skilled
Mazdoor

day

2.000

day

17.000

L-12

206.99

413.98

L-15

177.07

3010.19

L-13

cum

800.000

511.80

Integrated stone crusher of 200 TPH including belt


conveyor and vibrating screens
Front end loader 1 cum bucket capacity

Hour

6.000

16760.52

Hour

20.000

1188.00

23760.00

P&M-017

Tipper 5.5 cum capacity

Hour

20.000

873.00

17460.00

P&M-048

Material
Stone Boulder of size 150 mm and below

c)

140.65

###

M-001

Machinery
### P&M-028

d)

Overhead charges @ 0.1 on (a+b+c)

55478.79

e)

Contractor's profit @ 0.1 on (a+b+c+d)

61026.67

Cost for 750 cum = (a+b+c+d+e)x0.85

###

Rate per cum = (a+b+c+d+e)x0.85/750

760.80
say

Note 1. 800 cum of stone boulders are needed to get 600 cum of
stone chips of size 13.2 mm.
2. 85 per cent
of above cost will be attributed to the
production of 750 cum of stone aggregates of 40mm size and
balance 15 per cent will be for smaller size aggregates and
stone dust which comes out as a by-product.
3. The integrated stone
secondary crushing units.

crusher

includes

70

primary

and

761.00

CHAPTER - 2

SITE CLEARANCE
Sr No

Ref. to
MoRTH
Spec.

2.1

201

Description

Unit Quantity Rate Rs

Unit = Each
Girth from 300 mm to 600 mm
a)

b)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoors for cutting trees including cutting, refilling, compaction


of backfilling and stacking of serviceable materials within 1000
metres lead by manual means.

day

0.600

177.07

106.24

L-13

hour

0.100

171.02

17.10

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

12.70
13.97

Rate for each tree = a+b+c+d

153.72
say

(ii)

Mate

day

0.040

185.07

7.40

L-12

Mazdoors for cutting trees including cutting, refilling, compaction


of backfilling, and stacking of serviceable materials within 1000
metres lead by manual means

day

0.900

177.07

159.36

L-13

hour

0.300

171.02

51.31

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

21.81
23.99

Rate for each tree = a+b+c+d

263.87
say

(iii)

Mate

day

0.080

185.07

14.81

L-12

Mazdoors for cutting trees including cutting, refilling, compaction


of backfilling and stacking of serviceable materials within 1000
metres

day

2.000

177.07

354.14

L-13

hour

0.400

171.02

68.41

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

43.74

d)

Contractor's profit @ 0.1 on (a+b+c)

48.11

Rate for each tree = a+b+c+d


(iv)

264.00

Girth from 900 mm to 1800 mm


a) Labour

b)

2.1

154.00

Girth from 600 mm to 900 mm


a) Labour

b)

2.1

Remarks/
Input ref.

Cutting of Trees, including cutting of Trunks, Branches and


Removal
Cutting of trees, including cutting of trunks, branches and removal of
stumps, roots, stacking of serviceable material with all lifts and up to a
lead of 1000 metres and earth filling in the depression / pit.
(i)

2.1

Cost Rs

529.20

Girth above 1800 mm


a) Labour
Mate
Mazdoors for cutting trees including cutting, refilling, compaction
of backfilling and stacking of serviceable materials within 1000
metres
Machinery
Tractor-trolley
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate for each tree = a+b+c+d

say

529.00

day
day

0.160
4.000

185.07
177.07

29.61
708.28

L-12
L-13

hour

0.600

171.02

102.61
84.05
92.46
1017.01
1017.00

P&M-053

b)

say

71

Sr No

Ref. to
MoRTH
Spec.

2.2

201

Description

Unit Quantity Rate Rs

201

day
day

2.000
50.000

185.07
177.07

L-12
L-13

say

370.14
8853.50
922.36
1014.60
11160.60
11161.00

Clearing and Grubbing Road Land .


Clearing and grubbing road land including uprooting rank vegetation,
grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal
of stumps of trees cut earlier and disposal of unserviceable materials
and stacking of serviceable material to be used or auctioned, up to a
lead of 1000 metres including removal and disposal of top organic soil
not exceeding 150 mm in thickness.

(i)
A

Unit = Hectare
Taking output = 1 Hectare
By Manual Means:In area of light jungle
a)

b)

Labour
Mate

day

6.000

185.07

1110.42

L-12

Mazdoor

day

150.000

177.07

26560.50

L-13

hour

1.000

171.02

171.02

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3062.61
33688.74
say

33689.00

In area of thorny jungle


a)

b)

Labour
Mate

day

8.000

185.07

1480.56

L-12

Mazdoor

day

200.000

177.07

35414.00

L-13

hour

2.000

171.02

342.04

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4096.03
45056.28
say

(ii)

By Mechanical Means

In area of light jungle


a)

b)

P&M-053

3723.66

Rate per Hectare = a+b+c+d


2.3

P&M-053

2784.19

Rate per Hectare = a+b+c+d


2.3 (i)

Remarks/
Input ref.

Clearing Grass and Removal of Rubbish


Clearing grass and removal of rubbish up to a distance of 50 metres
outside the periphery of the area .
By Manual Means
Unit = Hectare
Taking output = 1 Hectare
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Rate per Hectare = a+b+c

2.3

Cost Rs

45056.00

Labour
Mate

day

0.160

185.07

29.61

L-12

Mazdoor

day

4.000

177.07

708.28

L-13

Dozer 80 HP with attachment for removal of trees & stumps

hour

10.000

3135.24

31352.40

P&M-014

Tractor-trolley

hour

1.000

171.02

171.02

P&M-053

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3226.13
3548.74

Rate per Hectare = a+b+c+d

39036.18
say

72

39036.00

Sr No

Ref. to
MoRTH
Spec.

2.3 (ii)

Description
B

Unit Quantity Rate Rs

b)

Labour
Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Dozer 80 HP with attachment for removal of trees & stumps

hour

12.000

3135.24

37622.88

P&M-014

Tractor-trolley

hour

1.500

171.02

256.53

P&M-053

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3898.62
4288.49

Rate per Hectare = a+b+c+d

47173.35
say

202

Remarks/
Input ref.

In area of thorny jungle


a)

2.4

Cost Rs

47173.00

Dismantling of Structures
Dismantling of existing structures like culverts, bridges, retaining walls
and other structure comprising of masonry, cement concrete, wood
work, steel work, including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of unserviceable material and
stacking the serviceable material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
(i)

Lime /Cement Concrete


I

By Manual Means

Lime Concrete, cement concrete grade M-10 and below


a)

b)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor for dismantling and loading

day

1.000

177.07

177.07

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

23.06

d)

Contractor's profit @ 0.1 on (a+b+c)

25.37

Cost for 1.25 cum = a+b+c+d

279.08

Rate per cum = (a+b+c+d)/ 1.25


2.4 (i)

223.27

b)

Labour
Mate

day

0.050

185.07

9.25

L-12

Mazdoor for dismantling and loading

day

1.250

177.07

221.34

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

223.00

Cement Concrete Grade M-15 & M-20


a)

2.4 (i)

say

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

27.68
30.44

Cost for 1.25 cum = a+b+c+d

334.89

Rate per cum = (a+b+c+d)/ 1.25

267.91
say

268.00

Prestressed / Reinforced cement concrete grade M-20 & above


a)

b)

Labour
Mate

day

0.150

185.07

27.76

L-12

Blacksmith

day

0.250

234.29

58.57

L-02

Mazdoor for dismantling, loading and unloading

day

3.500

177.07

619.75

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

75.23

73

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit Quantity Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

910.23

Rate per cum = (a+b+c+d)/ 1.25

728.18

II

By Mechanical Means for items No. 202( B)& ( C)

Cement Concrete Grade M-15 & M-20


a)

b)

Mate

day

0.020

185.07

3.70

L-12

Mazdoor for loading and unloading

day

0.250

177.07

44.27

L-13

Mazdoor with Pneumatic breaker

day

0.250

180.07

45.02

L-14

hour

0.670

293.76

196.82

P&M-001

hour

0.270

171.02

46.17

P&M-053

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

33.60
36.96

Cost for 1.25 cum = a+b+c+d

406.54

Rate per cum = (a+b+c+d)/ 1.25

325.23
say

b)

Labour
Mate

day

0.050

185.07

9.25

L-12

Mazdoor with Pneumatic breaker

day

0.660

180.07

118.85

L-14

Blacksmith

day

0.250

234.29

58.57

L-02

Mazdoor for loading and unloading

day

0.250

177.07

44.27

L-13

hour

1.000

293.76

293.76

P&M-001

hour

0.270

171.02

46.17

P&M-053

Machinery
Air Compressor 250 cfm with 2 leads of pneumatic breaker @
1.00 cum per hour
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

57.09

d)

Contractor's profit @ 0.1 on (a+b+c)

62.80

Cost for 1.25 cum = a+b+c+d

690.76

Rate per cum = (a+b+c+d)/ 1.25


(ii)

Dismantling Brick / Tile work

In lime mortar
a)

b)

552.61
say

553.00

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor for dismantling, loading and unloading

day

0.500

177.07

88.54

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13.84
15.23

Cost for 1.25 cum = a+b+c+d

167.48

Rate per cum = (a+b+c+d)/ 1.25

133.98
say

2.4 (ii)

325.00

Prestressed / reinforced cement concrete grade M-20 & above


a)

2.4

728.00

Labour

Air Compressor 250 cfm with 2 leads of pneumatic breaker @


1.5 cum per hour
Tractor-trolley

2.4 II

Remarks/
Input ref.

82.75

Cost for 1.25 cum = a+b+c+d


say
2.4

Cost Rs

134.00

In cement mortar
a)

b)

Labour
Mate

day

0.030

185.07

5.55

L-12

Mazdoor for dismantling, loading and unloading

day

0.750

177.07

132.80

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

18.45

74

Sr No

Ref. to
MoRTH
Spec.

Description
d)

2.4 (ii)

Unit Quantity Rate Rs

Contractor's profit @ 0.1 on (a+b+c)

223.28

Rate per cum = (a+b+c+d)/ 1.25

178.62
say

179.00

In mud mortar

b)

Labour
Mate

day

0.016

185.07

2.96

L-12

Mazdoor for dismantling and loading

day

0.400

177.07

70.83

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

12.00
13.20

Cost for 1.25 cum = a+b+c+d

145.16

Rate per cum = (a+b+c+d)/ 1.25

116.13
say

b)

Labour
Mate

day

0.014

185.07

2.59

L-12

Mazdoor for Dismantling, loading and unloading

day

0.350

177.07

61.97

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

11.07

d)

Contractor's profit @ 0.1 on (a+b+c)

12.18

Cost for 1.25 cum = a+b+c+d

134.00

Rate per cum = (a+b+c+d)/ 1.25


(iii)
A

107.20
say

107.00

Dismantling Stone Masonry


Rubble stone masonry in lime mortar
a)

b)

Labour
Mate

day

0.024

185.07

4.44

L-12

Mazdoor for dismantling, loading and unloading.

day

0.600

177.07

106.24

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

15.69
17.25

Cost for 1.25 cum = a+b+c+d

189.80

Rate per cum = (a+b+c+d)/ 1.25

151.84
say

2.4 (iii)

b)

Labour
Mate

day

0.030

185.07

5.55

L-12

Mazdoor for dismantling, loading and unloading.

day

0.750

177.07

132.80

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

18.45

d)

Contractor's profit @ 0.1 on (a+b+c)

20.30

Cost for 1.25 cum = a+b+c+d

223.28

Rate per cum = (a+b+c+d)/ 1.25

178.62
say

152.00

Rubble stone masonry in cement mortar.


a)

2.4 (iii)

116.00

Dry brick pitching or brick soling


a)

2.4

Remarks/
Input ref.

20.30

Cost for 1.25 cum = a+b+c+d

a)

2.4 (ii)

Cost Rs

179.00

Rubble Stone Masonry in mud mortar.


a)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor for dismantling, loading and unloading.

day

0.500

177.07

88.54

L-13

75

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit Quantity Rate Rs

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.270

171.02

15.23
133.98
say

134.00

Dry rubble masonry


a)

b)

Labour
Mate

day

0.018

185.07

3.33

L-12

Mazdoor for dismantling, loading and unloading.

day

0.450

177.07

79.68

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

12.92
14.21

Cost for 1.25 cum = a+b+c+d

156.32

Rate per cum = (a+b+c+d)/ 1.25

125.05
say

b)

Labour
Mate

day

0.016

185.07

2.96

L-12

Mazdoor for dismantling, loading and unloading.

day

0.400

177.07

70.83

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

12.00

d)

Contractor's profit @ 0.1 on (a+b+c)

13.20

Cost for 1.25 cum = a+b+c+d

145.16

Rate per cum = (a+b+c+d)/ 1.25


F

116.13
say

116.00

Dismantling boulders laid in wire crates including opening of


crates and stacking dismantled materials.
a)

b)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor for dismantling, loading and unloading

day

0.500

177.07

88.54

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13.84
15.23

Cost for 1.25 cum = a+b+c+d

167.48

Rate per cum = (a+b+c+d)/ 1.25

133.98
say

2.4

(iv)

125.00

Dismantling stone pitching/ dry stone spalls.


a)

2.4 (iii)

P&M-053

167.48

Rate per cum = (a+b+c+d)/ 1.25

2.4 (iii)

46.17
13.84

Cost for 1.25 cum = a+b+c+d

Remarks/
Input ref.

Machinery
Tractor-trolley

2.4 (iii)

Cost Rs

134.00

Wood Work wrought framed and fixed in frames of trusses upto a


height of 5 m above plinth level
a)

b)

Labour
Mate

day

0.060

185.07

11.10

L-12

Carpenter

day

0.500

234.29

117.15

L-04

Mazdoor for dismantling, loading and unloading.

day

1.000

177.07

177.07

L-13

hour

0.270

171.02

46.17

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

35.15
38.66

Cost for 1.25 cum = a+b+c+d

425.31

Rate per cum = (a+b+c+d)/ 1.25

340.25
say

76

340.00

Sr No
2.4

Ref. to
MoRTH
Spec.

Description
(v)

Unit Quantity Rate Rs

Cost Rs

Remarks/
Input ref.

Steel Work in all types of sections upto a height of 5 m above


plinth level excluding cutting of rivet.
Unit = tonne
Taking output = 1 tonne

Including dismembering
a)

Labour
Mate

day

0.140

185.07

25.91

L-12

Blacksmith

day

1.000

234.29

234.29

L-02

Mazdoor for dismantling, loading and unloading

day

2.500

177.07

442.68

L-13

Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc.
b)

17.57

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.170

171.02

82.45
906.92
say

Labour
Mate

day

0.220

185.07

40.72

L-12

Mazdoor for dismantling, loading and unloading

day

2.000

177.07

354.14

L-13

Blacksmith

day

0.500

234.29

117.15

L-02

Add 2.5 per cent of cost of labour for gas cutting, ropes, pulleys etc.
b)

12.80

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.170

171.02

29.07

P&M-053

55.39
60.93

Rate per tonne = a+b+c+d

670.19
say

907.00

Excluding dismembering.
a)

2.4 (v)

P&M-053

74.95

Rate per tonne = a+b+c+d


2.4 (v)

29.07

670.00

Extra over item No( v ) A and( v ) B for cutting rivets.


Unit = each
Taking output = 10 rivets
a)

Labour
Mate

day

0.010

185.07

1.85

L-12

Blacksmith

day

0.130

234.29

30.46

L-02

Mazdoor

day

0.130

177.07

23.02

L-13

b)

Overhead charges @ 0.1 on (a)

5.53

c)

Contractor's profit @ 0.1 on (a+b)

6.09

Cost for 10 rivets = a+b+c

66.95

Rate for each rivet = ( a+b+c)/10

6.69
say

2.4

(vi)

6.70

Scraping of Bricks Dismantled from Brick Work including


Stacking.
Unit = numbers
Taking output = 1000 numbers

In lime/Cement mortar
a)

Labour
Mate

day

0.140

185.07

25.91

L-12

Mazdoor

day

3.500

177.07

619.75

L-13

b)

Overhead charges @ 0.1 on (a)

64.57

c)

Contractor's profit @ 0.1 on (a+b)

71.02

Rate per1000 Nos = a+b+c

781.24
say

2.4 (iv)

In mud mortar
77

781.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit Quantity Rate Rs

(vii)

Remarks/
Input ref.

Labour
Mate

day

0.050

185.07

9.25

L-12

Mazdoor

day

1.250

177.07

221.34

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

23.06
25.37

Rate per1000 Nos = a+b+c


2.4

Cost Rs

279.02
say

279.00

Scraping of Stone from Dismantled Stone Masonry


Unit = cum
Taking output = 1 cum

In cement and lime mortar


a)

Labour
Mate

day

0.060

185.07

11.10

L-12

Mazdoor

day

1.400

177.07

247.90

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

25.90
28.49

Rate per cum = a+b+c

313.39
say

2.4 (vii)

a)

Labour
Mate

day

0.010

185.07

1.85

L-12

Mazdoor

day

0.300

177.07

53.12

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

5.50
6.05

Rate per cum = a+b+c

66.52
say

2.4

(viii)

313.00

In Mud mortar

67.00

Scarping Plaster in Lime or Cement Mortar from Brick/ Stone


Masonry
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.160

185.07

29.61

L-12

Mazdoor for scarping and loading

day

4.000

177.07

708.28

L-13

hour

0.320

171.02

54.73

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

79.26
87.19

Cost for 100 sqm = a+b+c+d

959.07

Rate per sqm = (a+b+c+d)/100

9.59
say

2.4

(ix)

9.60

Removing all type of Hume Pipes and Stacking within a lead of


1000 metres including Earthwork and Dismantling of Masonry
Works.
Unit = metre
Taking output = 1 metre

Up to 600 mm dia
a)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor

day

0.520

177.07

92.08

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

9.58
10.54

Rate per metre = a+b+c

115.89
say

2.4 (ix)

Above 600 mm to 900 mm dia


78

116.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit Quantity Rate Rs

Mate

day

0.030

185.07

5.55

L-12

Mazdoor

day

0.700

177.07

123.95

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

12.95
14.25
156.70
say

157.00

Above 900 mm
a)

Labour
Mate

day

0.050

185.07

9.25

L-12

Mazdoor

day

1.200

177.07

212.48

L-13

b)

Overhead charges @ 0.1 on (a)

22.17

c)

Contractor's profit @ 0.1 on (a+b)

24.39

Rate per metre = a+b+c

268.30
say

Note

Remarks/
Input ref.

Labour

Rate per metre = a+b+c


2.4 (ix)

Cost Rs

268.00

1. The excavation of earth, dismantling of stone masonry work in head


walls and protection works is not included which is to be measured
and paid separately.
2. Credit for retrieved stone from masonry work may be taken as per
actual availability.

2.5

202

Dismantling of Flexible Pavements


Dismantling of flexible pavements and disposal of dismantled
materials up to a lead of 1000 metres, stacking serviceable and
unserviceable materials separately
Unit = cum
Taking output = 1 cum
I

By Manual Means

Bituminous courses
a)

b)

Labour
Mate

day

0.060

185.07

11.10

L-12

Mazdoor for dismantling, loading and unloading

day

1.500

177.07

265.61

L-13

hour

0.380

171.02

64.99

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

34.17
37.59

Rate per cum = a+b+c+d

413.45
say

2.5 I

a)

b)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor for dismantling, loading and unloading.

day

1.000

177.07

177.07

L-13

hour

0.330

171.02

56.44

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

24.09

d)

Contractor's profit @ 0.1 on (a+b+c)

26.50

Rate per cum = a+b+c+d

291.50
say

2.5

413.00

Granular courses

II

By Mechanical Means

Bituminous course
a)

b)

291.00

Labour
Mate

day

0.010

185.07

1.85

L-12

Mazdoor

day

0.300

177.07

53.12

L-13

Tractor-trolley

hour

0.380

171.02

64.99

P&M-053

Farm tractor with ripper @ 60 cum per hour

hour

0.017

285.12

4.85

P&M-055

Machinery

79

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Unit Quantity Rate Rs

13.73
151.01
say

202

Remarks/
Input ref.

12.48

Rate per cum = a+b+c+d


2.6

Cost Rs

151.00

Dismantling of Cement Concrete Pavement


Dismantling of cement concrete pavement by mechanical means
using pneumatic tools, breaking to pieces not exceeding 0.02 cum in
volume and stock piling at designated locations and disposal of
dismantled materials up to a lead of 1000 metres, stacking serviceable
and unserviceable materials separately
Unit = cum
Taking output = 1 cum
a)

b)

Labour
Mate

day

0.030

185.07

5.55

L-12

Semi skilled mazdoor for operating pneumatic tools

day

0.500

180.07

90.04

L-14

Mazdoors as helpers including loading and unloading

day

0.500

177.07

88.54

L-13

Air compressor 250 cfm with two leads for pneumatic cutters/
hammers @ 1 cum per hour
Tractor-trolley

hour

1.000

293.76

293.76

P&M-001

hour

0.400

171.02

68.41

P&M-053

Joint Cutting Machine with 2-3 blades

hour

1.000

214.92

214.92

P&M-083

Machinery

c)

Overhead charges @ 0.1 on (a+b)

76.12

d)

Contractor's profit @ 0.1 on (a+b+c)

83.73

Rate per cum = a+b+c+d

921.06
say

Note

2.7

202

921.00

The above analysis is for removal of complete pavement. In case full


depth repair work is required to be done after dismantling, provision of
a concrete cutting and sawing machine may be added for 0.25 hours.
Dismantling of Guard Rails
Dismantling guard rails by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metres, stacking
serviceable materials and unserviceable materials separately.
Unit = running metre
Taking output = 1 metre
a)

b)

Labour
Mate

day

0.006

185.07

1.11

L-12

Mazdoor including loading and unloading

day

0.150

177.07

26.56

L-13

hour

0.050

171.02

8.55

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

3.62

d)

Contractor's profit @ 0.1 on (a+b+c)

3.98

Rate per metre = a+b+c+d

43.83
say

2.8

202

44.00

Dismantling of Kerb Stone


Dismantling kerb stone by manual means and disposal of dismantled
material with all lifts and up to a lead of 1000 metre
Unit = running metre
Taking output = 10 metre
a)

Labour
Mate

day

0.010

185.07

1.85

L-12

Mazdoor including loading and unloading

day

0.150

177.07

26.56

L-13

80

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit Quantity Rate Rs

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

hour

0.200

171.02

34.20

P&M-053

6.26
6.89

Cost for 10 m = a+b+c+d

75.76

Rate per metre = (a+b+c+d)/10

7.58
say

202

Remarks/
Input ref.

Machinery
Tractor-trolley

2.9

Cost Rs

8.00

Dismantling of Kerb Stone Channel


Dismantling kerb stone channel by manual means and disposal of
dismantled material with all lifts and up to a lead of 1000 metre
Unit = running metre
Taking output = 10 metre
a)

b)

Labour
Mate

day

0.015

185.07

2.78

L-12

Mazdoor including loading and unloading

day

0.225

177.07

39.84

L-13

hour

0.300

171.02

51.31

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

9.39
10.33

Cost for 10 m = a+b+c+d

113.65

Rate per metre = (a+b+c+d)/10

11.36
say

2.10

202

11.00

Dismantling of Kilometre Stone


Dismantling of kilometre stone including cutting of earth, foundation
and disposal of dismantled material with all lifts and lead upto 1000 m
and back filling of pit.
Unit = Each
Taking output = one KM stone

5th KM stone
Quantity of cement concrete = 0.392 cum
a)

b)

Labour
Mate

day

0.130

185.07

24.06

L-12

Mazdoor

day

0.750

177.07

132.80

L-13

hour

0.150

171.02

25.65

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

18.25
20.08

Rate for one 5th KM stone = a+b+c+d


B

220.84
say

221.00

Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a)

b)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor

day

0.500

177.07

88.54

L-13

hour

0.100

171.02

17.10

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

10.93
12.03

Rate for one ordinary KM stone = a+b+c+d


C

132.30
say

132.00

185.07

0.74

Hectometre Stone
Quantity of cement concrete = 0.048 cum
a)

Labour
Mate

day
81

0.004

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit Quantity Rate Rs

Mazdoor
b)

202

Remarks/
Input ref.

day

0.100

177.07

17.71

L-13

hour

0.020

171.02

3.42

P&M-053

Machinery
Tractor-trolley

2.11

Cost Rs

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2.19
2.41

Rate for one Hectometre stone = a+b+c+d

26.46
say

26.50

Dismantling of Fencing
Dismantling of barbed wire fencing/ wire mesh fencing including posts,
foundation concrete, back filling of pit by manual means including
disposal of dismantled material with all lifts and up to a lead of 1000
metres, stacking serviceable material and unserviceable material
separately.
Unit = running metre
Taking output = 30 metres
a)

b)

Labour
Mate

day

0.150

185.07

27.76

L-12

Mazdoor including loading and unloading

day

3.000

177.07

531.21

L-13

Blacksmith

day

0.750

234.29

175.72

L-02

hour

0.150

171.02

25.65

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

76.03

d)

Contractor's profit @ 0.1 on (a+b+c)

83.64

Cost for 30 metres = a+b+c+d

920.01

Rate per metre = (a+b+c+d)/30

30.67
say

2.12

202

30.70

Dismantling of CI Water Pipe Line


Dismantling of CI water pipe line 600 mm dia including disposal with
all lifts and lead upto 1000 metres and stacking of serviceable material
and unserviceable material separately under supervision of concerned
department
Unit = running metre
Taking output = 10 metres
a)

b)

Labour
Mate

day

0.090

185.07

16.66

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

Plumber

day

0.250

234.29

58.57

L-02

Truck 10 tonne capacity

hour

0.250

773.00

193.25

P&M-057

Light Crane 3 tonne capacity

hour

0.500

535.00

267.50

P&M-013

Machinery

c)

Overhead charges @ 0.1 on (a+b)

89.01

d)

Contractor's profit @ 0.1 on (a+b+c)

97.91

Cost for 10 metres = a+b+c+d

1077.04

Rate per metre = (a+b+c+d)/10

107.70
say

Note

2.13

202

The rate analysis does not include any excavation in earth or


dismantling of masonry works which are to be measured and paid
separately.
Removal of Cement Concrete Pipe of Sewer Gutter
Removal of cement concrete pipe of sewer gutter 1500 mm dia under
the supervision of concerned department including disposal with all
lifts and up to a lead of 1000 metres and stacking of serviceable and
unserviceable material separately but excluding earth excavation and
dismantling of masonry works.
Unit = running metre

82

108.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit Quantity Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 10 metres


a)

b)

Labour
Mate

day

0.100

185.07

18.51

L-12

Mazdoor

day

2.500

177.07

442.68

L-13

Crane 5 tonne capacity

hour

0.300

599.40

179.82

P&M-070

Truck flat body 10 tonne

hour

1.000

773.00

773.00

P&M-057

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

141.40
155.54

Cost for 10 metres = a+b+c+d

1710.94

Rate per metre = (a+b+c+d)/10

171.09
say

Note

2.14

202

171.00

The rate analysis does not include any excavation in earth or


dismantling of masonry works which are to be measured and paid
separately.
Removal of Telephone / Electric Poles and Lines
Removal of telephone / Electric poles including excavation and
dismantling of foundation concrete and lines under the supervision of
concerned department, disposal with all lifts and up to a lead of 1000
metres and stacking the serviceable and unserviceable material
separately
Unit = each
Taking output = 30 Nos
a)

b)

Labour
Mate

day

0.480

185.07

88.83

L-12

Mazdoor

day

10.000

177.07

1770.70

L-13

Electrician/Lineman

day

2.000

234.29

468.58

L-02

hour

1.500

171.02

256.53

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

258.46
284.31

Cost for 30 poles = a+b+c+d

3127.42

Rate per pole = (a+b+c+d)/30

104.25
say

83

104.00

Analysis of Rate

RCD/SOR

CHAPTER - 3

EARTH WORK, EROSION CONTROL AND DRAINAGE


Sr No

Ref. to
MoRTH
Spec.

3.1

301

Description

Quantity

Rate Rs

Cost Rs

Note

301

Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Royalty @ Rs. 24.00 per Cum
Rate per cum
Including Royalty @ Rs. 24.0 per cum, cost of watering,
rolling & compaction

day
day

1.800
45.000

185.07
177.07

333.13
7968.15

L-12
L-13

hour

10.000

773.00

P&M-057

say

7730.00
1603.13
1763.44
19397.84
161.65
24.00
186.00

Rate per cum


In case there is a situation where the cross-section is of cut
and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted.

say

205.00
205.00

Rate per cum

say

108.00

108.00

Excavation in Ordinary Rock by Manual Means


(i)

Excavation in ordinary rock using manual means including


loading in a truck and carrying of excavated material to
embankment site with in all lifts and leads upto 1000 metres
including Royalty but excluding rolling , copaction & watering
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Royalty @ Rs. 24.00 per Cum
Rate per cum

day
day

2.800
70.000

185.07
177.07

518.20
12394.90

L-12
L-13

hour

10.000

773.00

7730.00
2064.31
2270.74
24978.15
208.15
24.00
232.15
232.00

P&M-057

say

3.3

301

Remarks/
Input ref.

Excavation in Soil by Manual Means .


Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000 metres.

(ii)

3.2

Unit

(ii)

Including Royalty @ Rs. 24.00 per cum , watering , rolling &


compaction.

Note

In case there is a situation where the cross-section is of cut


and fill and cut earth is required to be used in embankment
in the immediate vicinity, the item of carriage in the truck
shall be omitted. including Royalty @ Rs. 24.00 per cum
Excavation in Soil with Dozer with lead upto 100 metres
Excavation for road way in soil by mechanical means
including cutting and pushing the earth to site of
embankment upto a distance of 100 metres (average lead50
metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.

84

251.00

154.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Unit = cum
Taking output = 180 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 30 cum per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
3.4

301

RCD/SOR
Quantity

Rate Rs

Cost Rs

day
day

0.080
2.000

185.07
177.07

14.81
354.14

hour

6.000

3135.24

say

18811.44
1918.04
2109.84
23208.27
128.93
129.00

day
day

0.120
3.000

185.07
177.07

22.21
531.21

hour

6.000

3135.24

18811.44
1936.49
2130.13
23431.48
216.96
217.00

say
301

L-12
L-13
P&M-014

Excavation in Ordinary Rock with Dozer with lead upto


100 metres
Excavation for roadway in ordinary rock by deploying a
dozer, 80 HP including cutting and pushing the cut earth to
site of embankment upto a distance of 100 metres ( average
lead 50 metres ), trimming bottom and side slopes in
accordance with the requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 108 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer, 80 HP @ 20 cum per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 108 cum = a+b+c+d
Rate per cum = (a+b+c+d)/108

3.5

Remarks/
Input ref.

L-12
L-13
P&M-014

Excavation in Hard Rock (requiring blasting)


with
disposal upto 1000 metres
Excavation for roadway in hard rock (requiring blasting)
by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking 0utput = 180 cum
a)

b)

c)

Labour
Mate

day

0.220

185.07

40.72

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

Driller

day

2.000

206.99

413.98

L-06

Blaster

day

0.250

289.31

72.33

L-03

Dozer, 80 HP @ 30 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Air compressor, 250 cfm with 2 jack hammer

hour

6.000

293.76

1762.56

P&M-001

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper10 tonne capacity

hour

11.250

873.00

9821.25

P&M-048

7104.58

M-104

Machinery

Materials
Gelatin 80 per cent

d)

Electric Detonators @ 1 detonator for 2 gelatin sticks of


125 gms each
Credit for excavated rock found suitable for use @ 50
per cent quantity blasted
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

kg

63.000

112.77

each

252.000

14.27

cum

90.000

-102.33

3595.07 M-094 /100


(9209.64)
4007.15
4407.86

Cost for 180 cum = a+b+c+d+e

48486.51

Rate per cum = (a+b+c+d+e)/180

269.37

85

M-089

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Remarks/
Input ref.

Cost Rs
say

269.00
`

Note

3.6

301

1. The quality and availability of rock shall be checked


before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced/restricted to that extent.
Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m (including Royalty @ Rs. 24.00 per cum
but excluding watering, rolling & compaction)
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

hour

6.000

1516.32

9097.92

P&M-026

hour

16.000

873.00

13968.00

P&M-048

Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2343.49
2577.84

Cost for 360 cum = a+b+c+d

28356.19

Rate per cum = (a+b+c+d)/360

78.77

Royalty @ Rs. 24.00 per Cum

24.00

Rate per cum


3.7

301

102.77
say

103.00

Excavation in Ordinary Rock using Hydraulic Excavator


CK-90 and Tippers with Disposal upto 1000 metres.
Excavation for roadway in ordinary rock with hydraulic
excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections (including Royalty @ Rs. 24.00 per cum but
excluding watering, rolling & compaction)
Unit = cum
Taking output = 240 cum
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

hour

6.000

1516.32

9097.92

P&M-026

hour

11.000

873.00

9603.00

P&M-048

Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

1906.99

d)

Contractor's profit @ 0.1 on (a+b+c)

2097.69

Cost for 240 cum = a+b+c+d

23074.54

Rate per cum = (a+b+c+d)/240

96.14

Royalty @ Rs. 24.00 per Cum

24.00

Rate per cum

120.14
say
86

120.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

3.8

301

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation in Hard Rock (blasting prohibited)


Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A

Mechanised
Unit = cum
Taking output = 36 cum
a)

Labour
Mate

day

0.400

185.07

74.03

L-12

Mazdoor for trimming slopes including mannul loading


in truck
Machinery

day

10.000

177.07

1770.70

L-13

Hydraulic excavator with rock breaker attachment @ 6


cum per hour
Tipper 5.5 cum capacity, 1 trip per hour.

hour

6.000

1516.32

9097.92

P&M-026

hour

6.500

873.00

5674.50

P&M-048

cum

18.000

-102.33

-1841.93

M-089

c)

Credit for excavated rock found suitable for use @ 50


per cent of excavated quantity
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

b)

1477.52
1625.27

Cost for 36 cum = a+b+c+d

17878.02

Rate per cum = (a+b+c+d)/36

496.61
say

Note

497.00

1. The quality and availability of rock shall be checked


before affording credit.
2. In case some rock is issued to the contractor at site, the
item of carriage shall be restricted/reduced to that extent.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.

3.8

Manual Method
Unit = cum
Taking output = 16 cum
a)

Labour
Mate

day

1.640

185.07

303.51

L-12

Mazdoor including loading in truck

day

16.000

177.07

2833.12

L-13

Chiseller

day

24.000

185.07

4441.68

L-05

Blacksmith

day

1.000

234.29

234.29

L-02

Tipper 5.5 cum capacity, 1 trip per hour.

hour

2.900

873.00

2531.70

P&M-048

cum

8.000

-102.33

-818.63

c)

Credit for excavated rock found suitable for use @ 50


per cent of excavated
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

b)

Machinery

952.57
1047.82

Cost for 16 cum = a+b+c+d

11526.06

Rate per cum = (a+b+c+d)/16

720.38
say

Note

1. Credit is considered for 50 per cent of quantity of work.


2. Loading for disposal will be done manually, being small
quantity.

3.9

301

3. In case some rock is issued to contractor at site, the item


of carriage shall be omitted to the extent of quantity issued
to the contractor.
Excavation in Hard Rock (controlled blasting) with
disposal upto 1000 metres

87

720.00

M-089

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation for roadway in hard rock with controlled blasting


by drilling, blasting and breaking, trimming of bottom and
side slopes in accordance with requirements of lines, grades
and cross sections, loading and disposal of cut road with in
all lifts and leads upto 1000 metres
Unit = cum
Taking output = 180 cum
a)

b)

c)

Labour
Mate

day

0.220

185.07

40.72

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

Driller

day

2.000

206.99

413.98

L-06

Blaster

day

0.500

289.31

144.66

L-03

Dozer 80 HP @ 30 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Air compressor, 250 cfm with 2 jack hammers

hour

6.000

293.76

1762.56

P&M-001

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper 5.5 cum capacity, 4 trips per hour.

hour

8.200

873.00

7158.60

P&M-048

kg

63.000

112.77

7104.58

M-104

each

1008.000

14.27

cum

90.000

-102.33

Machinery

Materials
Gelatin 80 per cent

d)

Electric Detonators @ 1 detonator for1/2 gelatin stick


of 125 gms each
Credit for excavated rock found suitable for use @ 50
per cent quantity blasted
Add 5 per cent of cost of a+b+c towards muffling
arrangements to guard against any rock fly off during
blasting
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14380.28 M-094 /100


-9209.64

M-089

2413.32

5067.97
5574.77

Cost for 180 cum = a+b+c+d+e

61322.43

Rate per cum = (a+b+c+d+e)/180

340.68
say

341.00

#VALUE!
Note

1. Credit is considered for 50 per cent of quantity of


blastered rock, if found suitable for construction..
2. In case some rock is issued to the contractor at site, the
item of carriage shall be reduced to that extent.

3.10

301

Excavation in Marshy Soil


Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting and
loading in tippers and disposal with in all lifts and lead upto
1000 metres, trimming of bottom and side slopes in
accordance with requirements of lines, grades and cross
sections (including Royalty @ Rs. 24.00 per cum but
excluding watering, rolling & compaction)
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

hour

6.000

1516.32

9097.92

P&M-026

hour

13.640

873.00

11907.72

P&M-048

Machinery
Hydraulic excavator 0.90 cum bucket capacity @ 50
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.1 on (a+b)

2137.46

d)

Contractor's profit @ 0.1 on (a+b+c)

2351.20

Cost for 300 cum = a+b+c+d

25863.25

Rate per cum = (a+b+c+d)/300

86.21

88

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Royalty @ Rs. 24.00 per Cum

24.00

Rate per cum


3.11

301

Remarks/
Input ref.

110.21
say

110.00

Removal of Unserviceable Soil with Disposal upto 1000


metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

Excavator0.90 cum bucket capacity @ 60 cum per hour

hour

6.000

1516.32

9097.92

P&M-026

Tipper 5.5 cum capacity, 4 trips per hour.

hour

16.360

873.00

14282.28

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

2374.91

d)

Contractor's profit @ 0.1 on (a+b+c)

2612.41

Cost for 360 cum = a+b+c+d

28736.47

Rate per cum = (a+b+c+d)/360


Note

3.12

303

79.82
say

80.00

This item does not include replacement of unsuitable soil by


suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
Presplitting of Rock Excavation Slopes
Carrying out excavation in hard rock to achieve a specified
slope of the rock face by controlled use of explosives and
blasting accessories in properly aligned and spaced drill
holes, collection of the excavated rock by a 80 HP dozer,
loading in tipper by a front end loader and disposing of the
material with all lifts and lead upto 1000 m, all as specified in
clause No. 303
Unit = sqm
Taking output = 400 sqm( 120 cum considering 300mm
average depth of excavation over the existing rock face)
a)

b)

c)

Labour
Mate

day

0.600

185.07

111.04

L-12

Mazdoor

day

15.000

177.07

2656.05

L-13

Air compressor 250 cfm with 2 leads @ 20 cum per


hour
Dozer, 80 HP

hour

6.000

293.76

1762.56

P&M-001

hour

6.000

3135.24

18811.44

P&M-014

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

kg

42.000

112.77

4736.38

M-104

each

672.000

14.27

Machinery

Materials
Gelatin 80 per cent

d)

Electric Detonators @ 1 detonator for 1/2 gelatin stick


of 125 gms each
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

9586.85 M-094 /100


4479.23
4927.16

Cost for 400 sqm = a+b+c+d+e

54198.72

Rate per sqm = (a+b+c+d+e)/400

135.50
say

89

135.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
Note

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

In case blasted rock is used to the contractor against


payment for constructed work, the cost of carriage shall be
reduced to that extent.
Excavation for Structures

3.13

304

Earth work in excavation of foundation of structures as per


drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom,
backfilling the excavation earth to the extent required and
utilising the remaining earth locally for road work.

(i)

Ordinary soil
Unit = cum
Taking output = 10 cum

Manual Means (Depth upto 3 m)


a)

Labour
Mate

day

0.320

185.07

59.22

L-12

Mazdoor

day

8.000

177.07

1416.56

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

147.58
162.34

Cost for 10 cum = a+b+c

1785.70

Rate per cum = (a+b+c)/10

178.57
say

Note

3.13 (i)

179.00

Cost of dewatering may be added where required upto 10


per cent of labour cost Assessment for dewatering shall be
made as per site conditions..
Mechanical Means (Depth upto 3 m)
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.320

185.07

59.22

L-12

Mazdoor

day

8.000

177.07

1416.56

L-13

hour

6.000

1516.32

9097.92

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1057.37
1163.11

Cost for 300 cum = a+b+c+d

12794.18

Rate per cum = (a+b+c+d)/300

42.65
say

Note

3.13

43.00

Cost of dewatering upto 5 per cent of (a+b)


may be
added, where required. Assessment for dewatering shall be
made as per site conditions..

(ii)

Ordinary Rock (not requiring blasting)

Manual Means (Depth upto 3 m)


Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.400

185.07

74.03

L-12

Mazdoor

day

10.000

177.07

1770.70

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

184.47
202.92

Cost for 10 cum = a+b+c

2232.12

Rate per cum = (a+b+c)/10

223.21
say

Note

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions..

90

223.00

Analysis of Rate
Sr No
3.13 (ii)

Ref. to
MoRTH
Spec.

Description
B

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Mechanical Means
Unit = cum
Taking output = 216 cum
a)

b)

Labour
Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

hour

6.000

1516.32

9097.92

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.1 on (a+b)

1020.48

d)

Contractor's profit @ 0.1 on (a+b+c)

1122.52

Cost for 216 cum = a+b+c+d

12347.76

Rate per cum = (a+b+c+d)/216


Note

57.17
say

57.00

1.Cost of dewatering upto 5 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.

3.13

(iii)
A

Hard Rock ( requiring blasting )


Manual Means
Unit = cum
Taking output = 10 cum
a)

Labour
i) Mate

day

0.530

185.07

98.09

L-12

ii) Driller

day

0.840

206.99

173.87

L-06

iii) Blaster

day

0.400

289.31

115.72

L-03

iv) Mazdoor

day

12.000

177.07

2124.84

L-13

hour

0.67

293.76

196.82

P&M-001

kg

3.500

112.77

394.70

M-104

each

14.000

14.27

b)

Machinery

c)

Air Compressor 250 cfm with 2 jack hammer @ 15 cum


per hour
Material
Blasting Material
Detonator electric

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

330.38
363.41

Cost for 10 cum = a+b+c+d+e

3997.56

Rate per cum = (a+b+c+d+e)/10

3.13

199.73 M-094 /100

399.76

Note

Cost of dewatering @ 10 per cent of labour cost may be


added, where required Assessment for dewatering shall be
made as per site conditions.

(iv)

Hard Rock ( blasting prohibited )

say

400.00

Unit = cum
Taking output = 10 cum
A

Mechanical Means
a)

Labour
Mate

day

0.200

185.07

37.01

L-12

Mazdoor

day

5.000

177.07

885.35

L-13

hour

10.000

293.76

2937.60

P&M-001

b)

Machinery

c)

Air Compressor 250 cfm with 2 leads of pneumatic


breaker @ 1 cum per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

386.00
424.60

Cost for 10 cum = a+b+c+d

4670.56
91

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Rate per cum = (a+b+c+d)/10


Note

Remarks/
Input ref.

467.06
say

467.00

1. Cost of dewatering upto 5 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.

3.13

(v)

Marshy soil
Unit = cum
Taking output = 10 cum

Manual means ( upto 3 m depth)


a)

b)

Labour
Mate/Supervisor

day

0.400

185.07

74.03

L-12

Mazdoor

day

10.000

177.07

1770.70

L-13

hour

2.670

171.02

456.62

P&M-053

cum

5.000

25.10

125.50

M-163

Machinery
Tractor-trolley

c)

Material
Selected earth for refilling

d)

Overhead charges @ 0.1 on (a+b+c)

242.68

e)

Contractor's profit @ 0.1 on (a+b+c+d)

266.95

Cost for 10 cum = a+b+c+d+e

2936.48

Rate per cum = ( a+b+c+d+e)/ 10

293.65
say

Note

294.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 20 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil

3.13 (v)

Mechanical Means
a)

b)

Labour
i) Mate

day

0.080

185.07

14.81

L-12

ii) Mazdoor for dressing sides, bottom and backfilling

day

2.000

177.07

354.14

L-13

hour

0.170

1516.32

257.77

P&M-026

hour

0.450

873.00

392.85

P&M-048

cum

5.000

25.10

125.50

M-163

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Material
Selected earth for refilling

d)

Overhead charges @ 0.1 on (a+b+c)

114.51

e)

Contractor's profit @ 0.1 on (a+b+c+d)

125.96

Cost for 10 cum = a+b+c+d+e

1385.53

Rate per cum = (a+b+c+d+e)/10

138.55
say

Note

1. Cost of dewatering @ 20 per cent of (a+b) may be


added, where required
2. Shoring & strutting @ 10 per cent of (a+b), where
required may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item (i) to (iv) for ordinary soil

3.14

305.4.3

Scarifying Existing Granular Surface to a Depth of 50


mm by Manual Means

92

139.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Scarifying the existing granular road surface to a depth of 50


mm and disposal of scarified material within all lifts and
leads upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.200

185.07

37.01

L-12

Mazdoor including loading and unloading

day

5.000

177.07

885.35

L-13

hour

1.670

171.02

285.60

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

120.80

d)

Contractor's profit @ 0.1 on (a+b+c)

132.88

Cost for 100 sqm = a+b+c+d

1461.64

Rate per sqm = (a+b+c+d)/100

14.62
say

Note
3.15

305.4.3

14.60

In case material is to be reused at site, transportation cost


catered above for disposal shall be deleted.
Scarifying Existing Bituminous Surface to a depth of 50
mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.010

185.07

1.85

L-12

Mazdoor

day

0.250

177.07

44.27

L-13

Tractor with ripper attachment @ 60 cum per hour

hour

0.080

285.12

22.81

P&M-055

Front end loader 1 cum bucket capacity @ 25 cum per


hour
Tipper 5.5 cum capacity, 4 trips per hour.

hour

0.200

1188.00

237.60

P&M-017

hour

0.230

873.00

200.79

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

50.73
55.80

Cost for 100 sqm = a+b+c+d

613.85

Rate per sqm = (a+b+c+d)/100

6.14
say

3.16

305

6.10

Construction of Embankment with Material obtained


from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
a)

b)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

hour

1.670

1516.32

2532.25

P&M-026

tonne.km

160 x L

2.68

Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity

428.54 Lead =1 km
& P&M-047

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3135.24

1567.62

P&M-014

Motor grader for grading @ 100 cum per hour

hour

1.000

2519.00

2519.00

P&M-032

93

42.85

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

c)

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Water tanker6 KL capacity

hour

4.000

111.24

444.96

P&M-060

Vibratory roller 8 -10 tonnes @ 100 cum per hour

hour

1.000

1779.00

1779.00

P&M-059

KL

24.000

167.07

4009.64

M-189

cum

100.000

25.10

2510.00

M-092

Material
Cost of water

d)

Compensation & Royalty for earth taken from private


land
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1601.83
1762.02

Cost for 100 cum = a+b+c+d+e

19382.19

Rate per cum = (a+b+c+d+e)/100


Note

3.17

305

Remarks/
Input ref.

193.82
say

194.00

Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a)

b)

c)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor

day

0.500

177.07

88.54

L-13

Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3135.24

1567.62

P&M-014

Motor grader for grading @ 100 cum per hour

hour

1.000

2519.00

2519.00

P&M-032

Water tanker6 KL capacity

hour

4.000

111.24

444.96

P&M-060

Vibratory roller 8-10 tonnes @ 100 cum per hour

hour

1.000

1779.00

1779.00

P&M-059

KL

24.000

167.07

4009.64

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

1041.25

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1145.37

Rate for 100 cum = a+b+c+d+e

12599.07

Rate per cum = (a+b+c+d+e)/100

125.99
say

Note

3.18

305

126.00

In case the earth cutting is done by dozer and pushed for


filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No.
300-2
Unit = cum
Taking output = 100 cum
a)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

94

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Rate Rs

Cost Rs

hour

1.670

1516.32

tonne.km

175xL

2.68

P&M-026

468.72 Lead =1 km
& P&M-047

hour

0.500

3135.24

1567.62

P&M-014

Motor grader for grading @ 50 cum per hour

hour

2.000

2519.00

5038.00

P&M-032

Water tanker with 6 km lead

hour

4.000

111.24

444.96

P&M-060

Vibratory roller 8-10 tonnes @ 80 cum per hour

hour

1.250

1779.00

2223.75

P&M-059

46.87

KL

24.000

167.07

4009.64

M-189

cum

100.000

25.10

2510.00

M-092

Material

Compensation & Royalty for earth taken from private land


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1902.63
2092.89

Cost for 100 cum = a+b+c+d+e

23021.81

Rate per cum = (a+b+c+d+e)/100

230.22
say

305.3.4

2532.25

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour

Cost of water

3.19

Remarks/
Input ref.

Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum
per hour
Tipper 10 tonne capacity

c)

RCD/SOR

230.00

Compacting Original Ground


Case-I Compacting original ground supporting sub-grade
Loosening of the ground upto a level of 500 mm below the
sub-grade level, watered, graded and compacted in layers to
meet requirement of table 300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.120

185.07

22.21

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

Tractor with ripper attachment

hour

9.000

285.12

2566.08

P&M-055

Motor grader for grading

hour

6.000

2519.00

15114.00

P&M-032

Water tanker 6 KL capacity

hour

4.000

111.24

444.96

P&M-060

Vibratory roller 8-10 tonne @ 80 cum/hour

hour

7.500

1779.00

13342.50

P&M-059

KL

24.000

167.07

4009.64

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3603.06
3963.37

Cost for 600 cum = a+b+c+d+e

43597.02

Rate per cum = (a+b+c+d+e)/600

72.66
say

3.19

73.00

Case-II :Compacting original ground supporting embankment


Loosening, leveling and Compacting original ground
supporting embankment to facilitate placement of first layer
of embankment, scarified to a depth of 150 mm, mixed with
water at OMC and then compacted by rolling so as to
achieve minimum dry density as given in Table 300-2 for
embankment construction.
Unit = cum
Taking output = 600 cum
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

Machinery

95

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

c)

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Tractor with ripper attachment

hour

6.000

285.12

1710.72

P&M-055

Vibratory road roller 8-10 tonne capacity

hour

7.500

1779.00

13342.50

P&M-059

Water tanker6 KL capacity

hour

4.000

111.24

444.96

P&M-060

KL

24.000

167.07

4009.64

M-189

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

1987.68

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2186.44

Cost for 600 cum = (a+b+c+d+e)

24050.88

Rate per sqm = (a+b+c+d+e)/600

40.08
say

3.20

305

Remarks/
Input ref.

40.00

Stripping and Storing Top Soil


Stripping, storing of top soil by road side at 15 m internal and
re-application on embankment slopes, cut slopes and other
areas in localities where the available embankment material
is not conducive to plant growth.
Unit = cum
Taking output = 10 cum
a)

b)

Labour
Mate

day

0.200

185.07

37.01

L-12

Mazdoor

day

5.000

177.07

885.35

L-13

hour

0.100

3135.24

313.52

P&M-014

Machinery
Dozer 80 HP @ 100 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

123.59
135.95

Cost for 10 cum = (a+b+c+d)

1495.42

Rate per cum = (a+b+c+d)/10

149.54
say

3.21

150.00

Stripping, Storing and Re-laying Top Soil from Borrow


Areas in Agriculture Fields.
Stripping of top soil from borrow areas located in agriculture
fields, storing at a suitable place, spreading and re-laying
after taking the borrow earth to maintain fertility of the
agricultural field, finishing it to the required levels and
satisfaction of the farmer.
Unit = cum
Taking output = 300 cum
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

hour

6.000

3135.24

18811.44

Machinery
Dozer, 80 HP

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1918.04
2109.84

Cost for 300 cum = (a+b+c+d)

23208.27

Rate per cum = (a+b+c+d)/300


3.22

307

P&M-014

77.36
say

77.00

185.07

22.21

Turfing with Sods


Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a)

Labour
Mate

day
96

0.120

L-12

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor for preparation of ground and fetching of sods


b)

c)

RCD/SOR
Quantity

Rate Rs

Cost Rs

day

3.000

177.07

531.21

L-13

Water tanker including watering for 3 months

hour

2.000

111.24

222.48

P&M-060

Tractor-trolley

hour

1.000

171.02

171.02

P&M-053

cum

0.180

528.65

95.16

M-167

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Farm yard manure @ 0.18 cum per 100 sqm at site of
work
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

304.69
335.16

Cost for 100 sqm = a+b+c+d+e

3686.74

Rate per 100 sqm = (a+b+c+d+e)/100

36.87
say

3.23

308

Remarks/
Input ref.

37.00

Seeding and Mulching


Preparation of seed bed on previously laid top soil,
furnishing and placing of seeds, fertilizer, mulching material,
applying bituminous emulsion at the rate of 0.23 litres per
sqm and laying and fixing jute netting, including watering for
3 months all as per clause 308.
Unit = sqm
Taking output = 240 sqm
a)

b)

Labour
Mate

day

0.400

185.07

74.03

L-12

Mazdoor

day

10.000

177.07

1770.70

L-13

hour

14.000

111.24

1557.36

P&M-060

hour

2.400

171.02

410.44

P&M-053

Machinery
Water tanker 6 KL capacity including watering for 3
months
Tractor-trolley

c)

Material
Seeds

kg

3.600

21.93

78.94

M-162

Sludge/Farm yard manure @ 0.18 cum per 100 sqm

cum

0.430

528.65

227.32

M-167

Bitumen Emulsion

litre

55.200

45.850

2530.92

M-077

Jute netting, open weave, 2.5 cm square opening

sqm

264.000

28.71

7580.72

M-121

KL

84.000

167.07

14033.73

M-189

Cost of water for 3 months


d)

Overhead charges @ 0.1 on (a+b+c)

2826.42

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3109.06

Cost for 240 sqm = a+b+c+d+e

34199.63

Rate per sqm = (a+b+c+d+e)/240

142.50
say

3.24

309

142.00

Surface Drains in Soil


Construction of unlined surface drains of average cross
sectional area 0.40 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
Unit = metre
Taking output = 10 metres
A

Mechanical means
a)

b)

Labour
Mate

day

0.010

185.07

1.85

L-12

Mazdoor for dressing of bed and side of drain

day

0.250

177.07

44.27

L-13

hour

0.330

1516.32

500.39

P&M-026

Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30
metres per hour

97

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs
54.65
60.12

Cost for 10 metres = a+b+c+d

661.27

Rate per metre = (a+b+c+d)/10

66.13
say

3.24

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

36.89
40.58

Cost for 10 metres = a+b+c

446.42

Rate per metre = (a+b+c)/10

44.64
say

3.25

309

66.00

Manual Means
a)

Note

Remarks/
Input ref.

45.00

Where lining of drain is provided, quantity shall be worked


out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.
Surface Drains in Ordinary Rock
Construction of unlined surface drain of average cross
sectional area 0.4 sqm in ordinary rock to specified lines,
grades, levels and dimensions as per approved design and
to the requirement of clause 301 to 309. Excavated material
to be used in embankment at site.
Unit = metre
Taking output = 10 metres

Mechanical Means
a)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor for dressing of bed and side of drain

day

0.500

177.07

88.54

L-13

hour

0.670

1516.32

1015.93

b)

Machinery

c)

Hydraulic Excavator 0.3 cum bucket capacity @ 15


metres per hour
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

110.82
121.90

Cost for 10 metres = a+b+c+d

1340.89

Rate per metre = (a+b+c+d)/10


3.25

134.09
say

134.00

Manual Means
a)

Labour
Mate

day

0.120

185.07

22.21

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

b)

Overhead charges @ 0.1 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

55.34
60.88

Cost for 10 metres = a+b+c

669.64

Rate per metre = (a+b+c)/10

66.96
say

3.26

309

Surface Drains in Hard Rock


Rate per metre may be worked out based on quantity of
hard rock as per design.
For rate of hard rock cutting, refer relevant item in this
chapter

3.27

309

P&M-026

Sub-Surface Drains with Perforated Pipe

98

67.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of subsurface drain with perforated pipe of 100


mm internal diameter of metal/ asbestos cement/ cement
concrete/PVC, closely jointed, perforations ranging from 3
mm to 6 mm depending upon size of material surrounding
the pipe, with 150 mm bedding below the pipe and 300 mm
cushion above the pipe, cross section of excavation 450 x
550 mm. Excavated material to be utilised in roadway at site.
Unit = metre
Taking output = 10 metres
a)

c)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor for excavation and back filling

day

2.000

177.07

354.14

L-13

metre

10.000

107.89

1078.86

M-135

cum

2.400

613.00

1471.20

M-012

Material
Perforated pipe of cement concrete, internal dia 100
mm
Crushed stone as per table 300-3

d)

Overhead charges @ 0.1 on (a+b+c)

291.16

e)

Contractor's profit @ 0.1 on (a+b+c+d)

320.28

Cost for 10 metres = a+b+c+d+e

3523.04

Rate per metre = (a+b+c+d+e)/10

352.30
say

Note
3.28

309

352.00

Type of pipe may be modified depending upon provision in


design.
Aggregate Sub-Surface Drains
Construction of aggregate sub surface drain 300 mm x 450
mm with aggregates conforming to table 300-4, excavated
material to be utilised in roadway.
Unit = metre
Taking output = 10 metres
a)

b)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor for excavation and back filling with aggregates

day

1.500

177.07

265.61

L-13

cum

1.350

613.00

827.55

M-012

Material
Crushed stone as per table 300-3

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

109.69
120.65

Cost for 10 metres = a+b+c+d

1327.20

Rate per metre = (a+b+c+d)/10

3.29

309

132.72
say

133.00

Underground Drain at Edge of Pavement


Construction of an underground drain 1 m x 1 m (inside
dimensions) lined with RCC-20 cm thick and covered with
RCC slab10 cm in thickness on urban roads.
Unit = Running metre
Taking output = one metre
a) Earthwork in soil

cum

1.500

43.00

64.50

b) RCC work M-20

cum

0.495

4624.00

2288.88
2353.38

Rate per metre = (a+b)


Rates for these items may be taken from chapters on earth
work and substructures respectively.

99

say

2353.00

Item No.
3.13
Item 12.8
(C) RCC

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

3.30

310

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Preparation and Surface Treatment of Formation.


Preparation and surface treatment of formation by removing
mud and slurry, watering to the extent needed to maintain
the desired moisture content, trimming to the required line,
grade, profile and rolling with 8-10 tonne smooth wheeled
roller, complete as per clause 310.
Unit = sqm
Taking output = 3500sqm
a)

b)

c)

Labour
Mate

day

0.280

185.07

51.82

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mazdoor skilled

day

1.000

206.99

206.99

L-15

Smooth 3 wheeled steel roller 8-10 tonnes

hour

3.000

665.00

1995.00

P&M-044

Water tanker 6 KL, one trip per hour

hour

3.000

111.24

333.72

P&M-060

KL

18.000

167.07

3007.23

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

665.72

e)

Contractor's profit @ 0.1 on (a+b+c+d)

732.29

Cost for 3500 sqm = a+b+c+d+e

8055.18

Rate per sqm = (a+b+c+d+e)/3500

2.30
say

3.31

313

2.00

Construction of Rock fill Embankment


Construction of rock fill embankment with broken hard rock
fragments of size not exceeding 300 mm laid in layers not
exceeding 500 mm thick including filling of surface voids with
stone spalls, blinding top layer with granular material, rolled
with vibratory road roller, all complete as per clause 313.
Unit = cum
Taking output = 100 cum
a)

b)

c)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

1.500

177.07

265.61

L-13

Dozer 80 HP for spreading @ 200 cum per hour

hour

0.500

3135.24

1567.62

P&M-014

Vibratory road roller 8-10 tonnes @ 100 cum per hour

hour

1.000

1779.00

1779.00

P&M-059

Water tanker 6 KL, one trip per hour

hour

2.000

111.24

222.48

P&M-060

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

584.69
643.16

Cost for 100 cum = a+b+c+d+e

7074.78

Rate per cum = (a+b+c+d+e)/100

70.75
say

Note

It is assumed that rock is available locally at site from


roadway cutting. In case, portion of the rock requires
breaking to acceptable size of 300 mm, breaking charges
will have to be added.
EARTH WORK ON HILL ROAD

3.32

301

Excavation in Hill Area in Soil by Mechanical Means


Excavation in soil in hilly area by mechanical means
including cutting and trimming of side slopes and disposing
of excavated earth with all lifts and lead upto 1000 metres.
100

71.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = cum
Taking output = 260 cum
a)

b)

Labour
Mate

day

0.240

185.07

44.42

L-12

Mazdoor for trimming slopes and helping in excavation


etc.
Machinery

day

6.000

177.07

1062.42

L-13

Dozer 80 HP (D-80 A 12)@ 43.28 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Front end loader

hour

6.000

1188.00

7128.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

12.000

873.00

10476.00

P&M-048

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3752.23
4127.45

Cost for 260 cum = a+b+c+d

45401.95

Rate per cum = (a+b+c+d)/260

174.62
say

Note

3.33

301

175.00

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth shall be disposed off on the valley side.
Excavation in Hilly Area in Ordinary Rock by Mechanical
Means not Requiring Blasting.
Excavation in hilly area in ordinary rock not requiring blasting
by mechanical means including cutting and trimming of
slopes and disposal of cut material with all lift and lead upto
1000 metres.
Unit = cum
Taking output = 170 cum
a)

b)

Labour
Mate

day

0.320

185.07

59.22

L-12

Mazdoor

day

8.000

177.07

1416.56

L-13

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Front end loader

hour

7.000

1188.00

8316.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

7.000

873.00

6111.00

P&M-048

Machinery

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3471.42
3818.56

Cost for 170 cum = a+b+c+d

42004.21

Rate per cum = (a+b+c+d)/170

247.08
say

Note

3.34

301

247.00

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
Excavation in Hilly Areas in Hard Rock Requiring
Blasting
Excavation in hilly areas in hard rock requiring blasting, by
mechanical means including trimming of slopes and disposal
of cut material with all lifts and lead upto 1000 metres.
Unit = cum
Taking output = 170 cum
a)

Labour
Mate

day

0.490

185.07

90.68

L-12

Mazdoor

day

10.000

177.07

1770.70

L-13

101

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Driller

day

2.000

206.99

413.98

L-06

Blaster

day

0.250

289.31

72.33

L-03

Dozer 80 HP (D-80 A 12)@ 28.32 cum per hour

hour

6.000

3135.24

18811.44

P&M-014

Air compressor 250 cfm with two jack hammer @ 20


cum per hour
Front end loader

hour

5.000

293.76

1468.80

P&M-001

hour

7.000

1188.00

8316.00

P&M-017

Tipper 5.5cum capacity, 4 trips per hour.

hour

7.000

873.00

6111.00

P&M-048

kg

35.000

112.77

3946.99

M-104

each

140.000

14.27

Machinery

Materials
Gelatine 80 per cent

d)

Electric Detonators @ 1 Detonator for 2 Gelatine sticks


of 125 gms each
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4729.91
52029.01

Rate per cum = (a+b+c+d+e)/170

306.05
say

In case the land on the valley side is barren and there is no


objection for disposing of excavated earth on the valley side,
the provision of front end loader and tipper shall be deleted
as excavated earth can be disposed off on the valley side.
In case of hill roads, the altitude effect comes into play. The
output of men and machines decreases progressively after
2100 m elevation leading to increase in cost . High altitude
effect has been explained in the basic approach.

3.35

Work in Urban Roads


The cost of earth work in urban roads inhabited area will be
comparatively higher due to following reasons:
a) There is mixed traffic on urban roads like slow moving
hand and animal driven carts, rickshaws, cycles, two/ three
wheeler apart from the usual vehicular traffic resulting into
traffic jams. This causes loss of working time which may be
in the range of 10 -15 per cent
b)
There is considerable disruption of traffic adversely
affecting the efficiency of the working parties including
machines due to congestion caused by pedestrian traffic,
local road side venders, parking of vehicles by the road side,
encroachments by the shopkeepers and local shops who
make use of the berms of the road in front of these shops
and unauthorised conversion of road berms into mini local
market The output of manpower and machines is
substantially reduced due to factors mentioned above.
c)
Cost of living in urban areas is comparatively more
resulting into higher wages.
d)
At times, work is executed during night time due to
heavy traffic during day time. This involves extra expenditure
by way of making arrangement for lighting and special
transport for working parties due to odd hour
In the light of above, the authorities engaged in preparing
the cost estimates may exercise their judgment and cater for
the additional cost to the extent of 2 to 3 per cent, keeping in
view the severity of factors mentioned above. Supporting
details for the extra cost based on the actual conditions in
specific cases will have to give in justification.

3.36

Suggest
ive

1997.26 M-094 /100


4299.92

Cost for 170 cum = a+b+c+d+e

Note

Remarks/
Input ref.

Embankment Construction with Flyash/Pond ash


available from coal or lignite burning Thermal Plants as
waste material.

102

306.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of embankment with Flyash conforming to table


1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.160

185.07

29.61

L-12

Mazdoor

day

4.000

177.07

708.28

L-13

hour

6.000

1516.32

9097.92

P&M-026

tonne.km

432 x L

2.68

Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes
Add 10 per cent of cost of carriagefor loading and
unloading
Dozer 80 HP for spreading @ 200 cum/hour

115.71
hour

1.800

3135.24

5643.43

P&M-014

Motor Grader for grading @ 100 cum/hour

hour

3.600

2519.00

9068.40

P&M-032

Water tanker6 KL capacity

hour

12.000

111.24

1334.88

P&M-060

Vibratory Roller 8-10 tonne @ 100 cum/hour

hour

3.600

1779.00

6404.40

P&M-059

c)

Overhead charges @ 0.1 on (a+b)

3355.97

d)

Contractor's profit @ 0.1 on (a+b+c)

3691.57

Cost for 360 cum = a+b+c+d

40607.24

Rate per cum = (a+b+c+d)/360

112.80
say

Note

1157.07 Lead =1 km
& P&M-047

1.As flyash is available free of cost as waste material from


Thermal Plants, cost of material has not been added.
2.The earth cover on sides and intermediate layers of earth
sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.

103

113.00

Analysis of Rate

RCD/SOR

CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Sr No

Ref. to
MoRTH
Spec.

4.1

401

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Granular Sub-Base with Close Graded Material (Table:400-1)


Plant Mix Method
Construction of granular sub-base by providing close graded
Material, mixing in a mechanical mix plant at OMC, carriage of
mixed Material to work site, spreading in uniform layers with
motor grader on prepared surface and compacting with
vibratory power roller to achieve the desired density, complete
as per clause 401
Unit = cum
Taking output = 225 cum (450 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Wet mix plant @ 75 tonne capacity per hour
Electric generator 125 KVA
Water tanker 6 KL capacity 5 km lead with one tripper
hour
Front end loader 1 cum bucket capacity
Tipper 10 tonne
Add 10 per cent of cost of carriage to cover loading and
unloading
Motor Grader 110 HP
Vibratory roller 8-10 t
c) Material
Close graded Granular sub-base Material as per table 400-1

4.1A

4.1A

4.1A

(i)

(ii)

(iii)

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent
9.5 mm to 2.36 mm @ 20 per cent
2.36 mm below @ 30 per cent
Cost of water
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent
9.5 mm to 2.36 mm @ 25 per cent
2.36 mm below @ 40 per cent
Cost of water
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent
4.75 mm to 2.36 mm @ 12.5 per cent
2.36 mm below @ 52.5 per cent
Cost of water
Rate per cum for grading-I Material
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

Rate per cum for grading-II Material


d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225
Rate per cum for grading-III Material
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 225 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/225

103

day
day
day

0.400
2.000
8.000

185.07
206.99
177.07

74.03
413.98
1416.56

L-12
L-15
L-13

hour
hour
hour

6.000
6.000
4.500

2454.00
2307.00
111.24

14724.00
13842.00
500.58

P&M-094
P&M-018
P&M-060

hour
tonne.km

6.000
450 x L

1188.00
2.68

7128.00
P&M-017
1205.28 Lead =1 km &
P&M-047
120.53

hour
hour

6.000
6.000

2519.00
1779.00

15114.00
10674.00

P&M-032
P&M-059

cum
cum
cum
KL

144.000
57.000
86.400
27.000

745.00
630.59
393.00
167.07

107280.00
35943.57
33955.20
4510.84

M-013
M-017
M-020
M-189

cum
cum
cum
KL

100.800
72.000
115.200
27.000

800.00
630.59
393.00
167.07

80640.00
45402.41
45273.60
4510.84

M-015
M-017
M-020
M-189

cum
cum
cum
KL

100.800
36.000
151.200
27.000

704.20
481.00
393.00
167.07

70983.46
17316.00
59421.60
4510.84

M-016
M-018
M-020
M-189

24690.26
27159.28
298752.11
1327.79
say
1328.00

24103.98
26514.38
291658.17
1296.26
say
1296.00
21744.49
23918.93
263108.28
1169.37
say
1169.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
Note

4.1

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Any one of the grading for material may be adopted as per


design
By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a)

b)

c)

Labour
Mate

day

0.480

185.07

88.83

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor unskilled

day

10.000

177.07

1770.70

L-13

Motor Grader 110 HP @ 50 cum

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8 -10 tonne

hour

6.000

1779.00

10674.00

P&M-059

Tractor - Rotavator

hour

12.000

227.88

2734.56

P&M-054

Water tanker 6 KL capacity

hour

3.000

111.24

333.72

P&M-060

53 mm to 9.5 mm @ 50 per cent

cum

192.000

745.00

143040.00

M-013

9.5 mm to 2.36 mm @ 20 per cent

cum

76.000

630.59

47924.76

M-017

2.36 mm below @ 30 per cent

cum

115.200

393.00

45273.60

M-020

KL

18.000

167.07

3007.23

M-189

26.5 mm to 9.5 mm @ 35 per cent

cum

134.400

800.00

107520.00

M-015

9.5 mm to 2.36 mm @ 25 per cent

cum

96.000

630.59

60536.54

M-017

2.36 mm below @ 40 per cent

cum

153.600

393.00

60364.80

M-020

KL

18.000

167.07

3007.23

M-189

9.5 mm to 4.75 mm @ 35 per cent

cum

134.400

704.20

94644.61

M-016

4.75 mm to 2.36 mm @ 12.5 per cent

cum

48.000

481.00

23088.00

M-018

2.36 mm below @ 52.5 per cent

cum

201.600

393.00

79228.80

M-020

KL

18.000

167.07

3007.23

M-189

Machinery

Material

Close graded Granular sub-base Material as per table 400-1


For Grading-I Material

Cost of water
OR
For Grading-II Material

Cost of water
OR
For Grading-III Material

Cost of water
4.1B

(i)

Rate per cum for grading-I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

27037.54
29741.29

Cost for 300 cum = a+b+c+d+e

327154.22

Rate per cum = (a+b+c+d+e)/300

1090.51
say

4.1B

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

26255.84

e)

Contractor's profit @ 0.1 on (a+b+c+d)

28881.42

Cost for 300 cum = a+b+c+d+e

317695.62

Rate per cum = (a+b+c+d+e)/300

1058.99
say

4.1B

(iii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

23109.84
25420.83
279629.11

Rate per cum = (a+b+c+d+e)/300

932.10
say

4.2

401

1059.00

Rate per cum for grading-III Material

Cost for 300 cum = a+b+c+d+e

Note

1091.00

Rate per cum for grading-II Material

Any one of the grading for material may be adopted as per


design
Granular Sub-Base with Coarse Graded Material (Table:400- 2)

104

932.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of granular sub-base by providing coarse graded


material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401.
Unit = cum
Taking output = 300 cum
a)

b)

c)

Labour
Mate

day

0.400

185.07

74.03

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

8.000

177.07

1416.56

L-13

Mortar Grader 110 HP @ 50 cum per hour

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8 -10 tonne

hour

6.000

1779.00

10674.00

P&M-059

Water tanker 6 KL capacity

hour

3.000

111.24

333.72

P&M-060

53 mm to 26.5 mm @ 35 per cent

cum

134.400

662.54

89045.91

M-029

26.5 mm to 4.75 mm @ 45 per cent

cum

172.800

711.13

122883.44

M-026

2.36 mm below @ 20 per cent (Coarse Sand)

cum

76.800

239.00

18355.20

M-022

KL

18.000

167.07

3007.23

M-189

26.5 mm to 4.75 mm @ 75 per cent

cum

288.000

711.13

204805.73

M-026

2.36 mm below @ 25 per cent

cum

96.000

239.00

22944.00

M-022

KL

18.000

167.07

3007.23

M-189

9.5 mm to 4.75 mm @ 66 per cent

cum

255.000

743.09

189486.93

M-025

2.36 mm below @ 34 per cent

cum

129.000

239.00

30831.00

M-022

KL

18.000

167.07

3007.23

M-189

Machinery

Material

For coarse graded Granular sub-base Materials per table 4002


For grading-I Material

Cost of water
OR
For Grading-II Material

Cost of water
OR
For Grading-III Material

Cost of water
4.2

(i)

Rate per cum for grading-I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

26131.81
28744.99

Cost for 300 cum = a+b+c+d+e

316194.86

Rate per cum = (a+b+c+d+e)/300

1053.98
say

4.2

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

25878.32
28466.16

Cost for 300 cum = a+b+c+d+e

313127.73

Rate per cum = (a+b+c+d+e)/300

1043.76
say

4.2

(iii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

25135.14
27648.66
304135.25

Rate per cum = (a+b+c+d+e)/300

1013.78
say

4.3

402

1044.00

Rate per cum for grading-III Material

Cost for 300 cum = a+b+c+d+e

Note

1054.00

Rate per cum for grading-II Material

Any one of the grading for material may be adopted as per


design
Lime Stabilisation for Improving Sub-grade
Laying and spreading available soil in the sub-grade on a
prepared surface, pulverising, mixing the spread soil in place
with rotavator with 3 per cent slaked lime having minimum
content of 70 per cent of CaO, grading with motor grader and
compacting with the road roller at OMC to the desired density
to form a layer of improved sub grade
Unit = cum
Taking output = 300 cum (525 tonne)

105

1014.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
A

RCD/SOR
Unit

Quantity

Rate Rs

b)

c)

Labour
Mate

day

0.360

185.07

66.63

L-12

Skilled mazdoor for alignment and geometrics

day

1.000

206.99

206.99

L-15

Mazdoor for spraying lime

day

8.000

177.07

1416.56

L-13

Tractor with ripper and rotavator attachments @ 60 cum


per hour for ripping and 25 cum per hour for mixing

hour

12.000

285.12

3421.44

P&M-055

Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8 - 10 tonne capacity

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Water tanker 6 KL capacity

hour

12.000

111.24

1334.88

P&M-060

tonne

15.750

4427.31

69730.10

M-188

KL

72.000

167.07

12028.91

M-189

Machinery

Material
Lime at site
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

11025.76

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12128.34

Cost for 300 cum= a+b+c+d+e

133411.70

Rate per cum =( a+b+c+d+e)/300

4.3

Remarks/
Input ref.

By Mechanical Means
a)

Note

Cost Rs

444.71
say

445.00

* Though vibratory roller is required only for 3 hours as per


norms, but the same has to be available at site for 6 hours as
other machines for spreading and mixing will take 6 hours. The
usage rates of roller have been multiplied with a factor of 0.65.
By Manual Means
Unit = cum
Taking output = 150 cum (263 tonnes)
a)

b)

c)

Labour
Mate

day

1.440

185.07

266.50

L-12

Mazdoor skilled

day

1.000

206.99

206.99

L-15

Mazdoor

day

35.000

177.07

6197.45

L-13

Vibratory roller 8 - 10 tonne @ 60 cum per hour

hour

2.500

1779.00

4447.50

P&M-059

Water tanker 6 KL capacity

hour

6.000

111.24

667.44

P&M-060

tonne

8.000

4427.31

35418.46

M-188

KL

36.000

167.07

6014.46

M-189

Machinery

Material
Lime at site
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

5321.88

e)

Contractor's profit @ 0.1 on (a+b+c+d)

5854.07

Cost for 150 cum= a+b+c+d+e

64394.75

Rate per cum =( a+b+c+d+e)/150

429.30
say

4.4

402

429.00

Lime Treated Soil for Sub- Base


Providing, laying and spreading soil on a prepared sub grade,
pulverising, mixing the spread soil in place with rotavator with
3 per cent slaked lime with minimum content of 70 per cent
of CaO, grading with motor grader and compacting with the
road roller at OMC to achieve at least 98 per cent of the max
dry density to form a layer of sub base.
Unit = cum
Taking output = 300 cum (525 tonnes)
a)

b)

Labour
Mate

day

0.480

185.07

88.83

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

10.000

177.07

1770.70

L-13

hour

6.000

1516.32

9097.92

P&M-026

tonne.km

525 x L

2.68

Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Motor Grader 110 HP @ 50 cum per hour
106

1406.16 Lead =1 km &


P&M-047
140.62

hour

6.000

2519.00

15114.00

P&M-032

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

c)

RCD/SOR
Unit

Quantity

Rate Rs

hour

6.000

1779.00

10674.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

227.88

2734.56

P&M-054

Water tanker 6 KL capacity

hour

12.000

111.24

1334.88

P&M-060

tonne

15.750

4427.31

69730.10

M-188

KL

72.000

167.07

12028.91

M-189

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

12453.47

e)

Contractor's profit @ 0.1 on (a+b+c+d)

13698.81

Cost for 300 cum = a+b+c+d+e

150686.94

Rate per cum= (a+b+c+d+e)/300

502.29
say

403

Remarks/
Input ref.

Vibratory roller 8 - 10 tonne

Lime at site

4.5

Cost Rs

502.00

Cement Treated Soil Sub Base/ Base


Providing, laying and spreading soil on a prepared sub grade,
pulverising, adding the designed quantity of cement to the
spread soil, mixing in place with rotavator, grading with the
motor grader and compacting with the road roller at OMC to
achieve the desired unconfined compressive strength and to
form a layer of sub-base/base.
Unit = cum
Taking output = 300 cum (525 tonnes)
For 4 per cent quantity of cement by weight of soil
a)

b)

Labour
Mate

day

0.480

185.07

88.83

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

10.000

177.07

1770.70

L-13

hour

6.000

1516.32

9097.92

P&M-026

tonne.km

525 x L

2.68

Machinery
Excavator 0.90 cum bucket capacity
Tipper for carriage of soil

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1779.00

10674.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

227.88

2734.56

P&M-054

Water tanker 6 KL capacity

hour

12.000

111.24

1334.88

140.62

P&M-060

tonne

21.000

5789.47

121578.95

M-081

KL

72.000

167.07

12028.91

M-189

Material
Cement at site (@ 4 per cent of 525 tonne)
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

17638.35

e)

Contractor's profit @ 0.1 on (a+b+c+d)

19402.19

Cost for 300 cum = a+b+c+d+e

213424.05

Rate per cum= (a+b+c+d+e)/300

711.41
say

4.6

403

1406.16 Lead =1 km &


P&M-047

711.00

Cement Treated Crushed Rock or combination as per


clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of
crushed rock by weight.
a) Labour

b)

Mate

day

0.480

185.07

88.83

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

10.000

177.07

1770.70

L-13

Motor Grader 110 HP @ 50 cum per hour

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1779.00

10674.00

P&M-059

Tractor with Rotavator and blade @ 25 cum per hour

hour

12.000

227.88

2734.56

P&M-054

Machinery

107

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Water tanker 6 KL capacity


c)

RCD/SOR
Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

hour

10.000

111.24

1112.40

P&M-060

tonne

24.000

5789.47

138947.37

M-081

37.5 mm to 9.5 mm @ 55 per cent

cum

211.200

815.29

172189.25

M-014

9.5 mm to 4.75 mm @ 20 per cent

cum

76.800

743.09

57069.00

M-025

4.75 mm to 75 micron @ 25 per cent

cum

96.000

459.00

44064.00

M-019

KL

60.000

167.07

10024.09

M-189

37.5 mm to 9.5 mm @ 32.5 per cent

cum

124.800

711.13

88749.15

M-028

9.5 mm to 4.75 mm @ 5 per cent

cum

19.200

743.09

14267.25

M-025

4.75 mm to 75 micron @ 62.5 per cent

cum

240.000

261.00

62640.00

M-023

KL

60.000

167.07

10024.09

M-189

Material

Cement at site @ 4 per cent by weight of crushed


aggregate (600 tonne)
Grading of material for sub-base course

Cost of water
or
Grading of material for Base course

Cost of water
4.6

(i)

For Sub-Base course


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

45420.22
49962.24

Cost for 300 cum = a+b+c+d+e

549584.65

Rate per cum = (a+b+c+d+e)/300

1831.95
say

4.6

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34653.63
38119.00

Cost for 300 cum = a+b+c+d+e

419308.97

Rate per cum = (a+b+c+d+e)/300

1397.70
say

Note
4.7

404.3.1

1832.00

For Base course

1398.00

Quantities of aggregates provided under 'c' above are


uncompacted quantities.
Making 50 mm x 50 mm Furrows
Making 50 mm x 50 mm furrows, 25mm/ 50mm deep, 450 C to
the center line of the road and at one metre interval in the
existing thin bituminous wearing coarse including sweeping
and disposal of excavated material within 1000 metres lead
Unit = sqm
Taking output = 30 m x 7 m = 210 sqm

(i)

25mm deep furrow cutting


a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

hour

0.200

171.02

34.20

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

40.31
44.35

Cost for 210 sqm= a+b+c+d

487.81

Rate per sqm =(a+b+c+d)/210

2.32
say

(ii)

a)

b)

Labour
Mate

day

0.160

185.07

29.61

L-12

Mazdoor

day

4.000

177.07

708.28

L-13

hour

0.400

171.02

68.41

P&M-053

Machinery
Tractor-trolley

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

80.63
88.69

Cost for 210 sqm= a+b+c+d

975.62

Rate per sqm =(a+b+c+d)/210

4.65
say

4.8

404.3.2

2.30

50mm deep furrow cutting

Inverted Choke

108

4.60

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Construction of inverted choke by providing, laying, spreading


and compacting screening B type/ coarse sand of specified
grade in uniform layer on a prepared surface with motor grader
and compacting with power roller etc
Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.920

185.07

170.26

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

21.000

177.07

3718.47

L-13

Motor Grader 110 HP

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8-10 tonnes @ 60 cum per hour

hour

6.000

1779.00

10674.00

P&M-059

Water tanker 6 KL capacity

hour

18.000

111.24

2002.32

P&M-060

cum

720.000

203.75

146703.16

M-004

KL

108.000

167.07

18043.37

M-189

Machinery

Material
Screening type 'B' or coarse sand
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

19683.96

e)

Contractor's profit @ 0.1 on (a+b+c+d)

21652.35

Cost for 600 cum = a+b+c+d+e

238175.87

Rate per cum = ( a+b+c+d+e)/600


4.9

404

396.96
say

397.00

Water Bound Macadam


Providing, laying, spreading and compacting stone aggregates
of specific sizes to water bound macadam specification
including spreading in uniform thickness, hand packing, rolling
with 3 wheeled steel/ vibratory roller 8-10 tonnes in stages to
proper grade and camber, applying and brooming requisite
type of screening/ binding Materials to fill up the interstices of
coarse aggregate, watering and compacting to the required
density.
A

By Manual Means
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

10.080

185.07

1865.51

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

250.000

177.07

44267.50

L-13

hour

6.000

1779.00

10674.00

P&M-059

Smooth 3 wheeled steel roller @ 30cum/hour

hour

12.000

Water tanker 6 KL capacity

hour

24.000

111.24

2669.76

P&M-060

cum

435.600

465.37

202714.48

M-039

cum

97.200

624.00

60652.80

M-042

cum

108.000

119.64

12921.35

M-007

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Machinery
Vibratory roller 8 - 10 tonne @ 60cum per hour
or

4.9A

(i)

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for
compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading-I
@ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I
material
Cost of water

4.9A (i)

(a)

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

29958.44

109

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
e)

RCD/SOR
Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

Cost Rs

Remarks/
Input ref.

32954.28

Cost for 360 cum = a+b+c+d+e

362497.13

Rate per cum = (a+b+c+d+e)/360

1006.94
say

1007.00

OR
4.9A (i)

(b)

Using Screening Type-A (13.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35076.15
38583.77

Cost for 360 cum = a+b+c+d+e

424421.47

Rate per cum = (a+b+c+d+e)/360

1178.95
say

4.9A

(ii)

1179.00

Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

cum

435.600

532.91

232136.59 M-038 / M-036

cum

57.600

624.00

35942.40

M-042

Crushable type such as Moorum or Gravel for grading II


&III @ 0.22 cum per 10 sqm
OR

cum

105.590

119.64

12633.01

M-007

Type B11.2 mm for grading-III @ 0.20 cum per 10 sqm

cum

96.010

503.00

48293.03

M-041

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening
Type A 13.2 mm for grading-II @ 0.12 cum per 10 sqm
OR

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9A (ii)

(a)

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

32871.82
36159.00

Cost for 360 cum = a+b+c+d+e

397748.98

Rate per cum = (a+b+c+d+e)/360

1104.86
say

1105.00

OR
4.9A (ii)

(b)

Using Screening Type-A (13.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35547.33
39102.06

Cost for 360 cum = a+b+c+d+e

430122.63

Rate per cum = (a+b+c+d+e)/360

1194.79
say

4.9A (ii)

(c)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36782.39
40460.63

Cost for 360 cum = a+b+c+d+e

445066.90

Rate per cum = (a+b+c+d+e)/360


4.9A

(iii)

1195.00

Using Screening Type-B (11.2mm agg.) with binding material

1236.30
say

1236.00

Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm
for compacted thickness of 75 mm

cum

435.600

552.21

240542.91

M-036

cum

86.400

503.00

43459.20

M-041

cum

105.590

119.64

12633.01

M-007

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading II
&III @ 0.22 cum per 10 sqm
Binding material

110

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Binding Material @ 0.06cum per 10 sqm for grading II


material
Cost of water
4.9A (iii)

(a)

RCD/SOR
Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

33712.45
37083.69

Cost for 360 cum = a+b+c+d+e

407920.63

Rate per cum = (a+b+c+d+e)/360

1133.11
say

1133.00

OR
4.9A (iii)

(b)

Using Screening Type-B (11.2mm agg.)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

37139.64
40853.60

Cost for 360 cum = a+b+c+d+e

449389.60

Rate per cum = (a+b+c+d+e)/360

1248.30
say

1248.00

( Anyone of the aggregate grading, screening and binding


material may be used as per design)
4.9

By Mechanical Means:
Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

0.680

185.07

125.85

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

15.000

177.07

2656.05

L-13

Motor grader 110 HP @ 50cum/hr. for spreading

hour

7.200

2519.00

18136.80

P&M-032

Vibratory roller 8-10 tonnes @ 60cum/hr.

hour

6.000

1779.00

10674.00

P&M-059

Smooth 3 wheeled steel roller @ 30cum/hr.

hour

12.000

Water tanker 6 KL capacity

hour

24.000

111.24

2669.76

P&M-060

cum

435.600

465.37

202714.48

M-039

cum

97.200

624.00

60652.80

M-042

cum

108.000

119.64

12921.35

M-007

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Machinery

or

4.9B

(i)

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading-I
Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10 sqm for
compacted thickness of 100 mm
Stone Screening
Type A 13.2 mm for grading-I @ 0.27 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading-I
@ 0.30 cum per 10 sqm
Binding material
Binding Material @ 0.08cum per 10 sqm for grading I
material
Cost of water

111

Analysis of Rate
Sr No
4.9B (i)

Ref. to
MoRTH
Spec.

Description
(a)

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

27437.01
30180.71

Cost for 360 cum = a+b+c+d+e

331987.81

Rate per cum = (a+b+c+d+e)/360

922.19
say

922.00

OR
4.9B (i)

(b)

Using Screening Type-A (13.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

32554.72
35810.20

Cost for 360 cum = a+b+c+d+e

393912.16

Rate per cum = (a+b+c+d+e)/360

1094.20
say

4.9B

(ii)

1094.00

Grading-II
Aggregate
Grading-II 63 mm to 45 mm /Grading-III 53 mm to 22.4
mm@ 0.91 cum per 10 sqm for compacted thickness of
75 mm

cum

435.600

532.91

232136.59 M-038 / M-036

cum

57.600

624.00

35942.40

M-042

Crushable type such as Moorum or Gravel for grading II


&III @ 0.22 cum per 10 sqm
OR

cum

105.590

119.64

12633.01

M-007

Type B 11.2 mm for grading-III @ 0.20 cum per 10 sqm

cum

96.010

503.00

48293.03

M-041

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening
Type A 13.2 mm for grading-II@ 0.12 cum per 10 sqm
OR

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9B (ii)

(a)

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

30350.39
33385.42

Cost for 360 cum = a+b+c+d+e

367239.67

Rate per cum = (a+b+c+d+e)/360

1020.11
say

1020.00

OR
4.9B (ii)

(b)

Using Screening Type-A (13.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

33025.89
36328.48

Cost for 360 cum = a+b+c+d+e

399613.32

Rate per cum = (a+b+c+d+e)/360

1110.04
say

4.9B (ii)

(c)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34260.96
37687.05

Cost for 360 cum = a+b+c+d+e

414557.58

Rate per cum = (a+b+c+d+e)/360


4.9B

(iii)

1110.00

Using Screening Type-B (11.2mm agg.) with binding material

1151.55
say

1152.00

Grading-III
Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per 10 sqm
for compacted thickness of 75 mm

cum

435.600

552.21

240542.91

M-036

cum

86.400

503.00

43459.20

M-041

cum

105.590

119.64

12633.01

M-007

Stone Screening
Type B 11.2 mm for grading-III @ 0.18 cum per 10 sqm
OR
Crushable type such as Moorum or Gravel for grading II
&III @ 0.22 cum per 10 sqm
112

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Binding material
Binding Material @ 0.06cum per 10 sqm for grading II
material
Cost of water
4.9B (iii)

(a)

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Using Screening Crushable type such as Moorum or Gravel


d)

Overhead charges @ 0.1 on (a+b+c)

31191.02

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34310.12

Cost for 360 cum = a+b+c+d+e

377411.31

Rate per cum = (a+b+c+d+e)/360

1048.36
say

1048.00

OR
4.9B (iii)

(b)

Using Screening Type-B (11.2mm agg.) with binding material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34618.21
38080.03

Cost for 360 cum = a+b+c+d+e

418880.29

Rate per cum = (a+b+c+d+e)/360


Note
4.10

405

1163.56
say

1164.00

As three wheeled smooth rollers are also very commonly


used, the same has been provided as an alternative.
Crushed Cement Concrete Sub-base / Base
Breaking and crushing of material obtained by breaking
damaged cement concrete slabs to size range not exceeding
75 mm as specified in table 400.7 transporting the aggregates
obtained from breaking of cement concrete slabs at a lead of L
km., laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except the use of
screening or binding Material.
Unit = cum
Taking output =360 cum
a)

b)

Labour
Mate

day

4.160

185.07

769.89

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor for crushing broken cement concrete


pavement/slabs into aggregate
Machinery

day

102.000

177.07

18061.14

L-13

Motor Grader,110 HP @ 50 cum/hr.

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8 - 10 tonne@ 60 cum per hour

hour

6.000

1779.00

10674.00

P&M-059

Smooth 3 wheeled steel roller @ 30cum/hr.

hour

12.000

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

720 x L

2.68

or

Tipper 10 tonne capacity

c)

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1 trip per
hour
Material

1928.45 Lead =1 km &


P&M-047
192.84

hour

12.000

111.24

1334.88

P&M-060

KL

72.000

167.07

12028.91

M-189

Material available from dismantled concrete slab after crushing


/ breaking and only carriage is required to be provided
Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

6764.61

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7441.07

Cost for 360 cum = a+b+c+d+e

81851.78

Rate per cum = (a+b+c+d+e)/360

227.37
say

With Vibratory Roller


With Smooth 3 wheeled Steel Roller

113

227.00

227.00
218.00

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
Note

RCD/SOR
Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

1. It is assumed that dismantling of concrete slab/pavement


has been considered separately. Hence same is not added in
this analysis. Only labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile to work
site has been provided with a lead of L km.
2. In case of breaking of slabs is done locally without
involvement of transportation, the provision of tipper, front end
loader and loading/unloading charges may be deleted.
3. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative.

4.11

405.2

Penetration Coat Over Top Layer of Crushed Cement


Concrete Base
Spraying of bitumen over cleaned dry surface of crushed
cement concrete base at the rate of 25 kg per 10 sqm by a
bitumen pressure distributor, spreading of key aggregates at
the rate of 0.13 cum per 10 sqm by a mechanical gritter and
rolling the surface as per clause 506.3.8
Unit = sqm
Taking output = 7500 sqm
a)

b)

c)

Labour
Mate

day

0.560

185.07

103.64

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

12.000

177.07

2124.84

L-13

Mechanical broom hydraulic @ 1250 sqm per hour

hour

6.000

465.00

2790.00

P&M-031

Hydraulic self propelled chips spreader

hour

6.000

2423.52

14541.12

P&M-025

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper 10 tonne capacity

hour

6.000

873.00

5238.00

P&M-048

Vibratory roller 8 -10 tonnes @ 30 cum per hour

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Bitumen pressure distributor @ 1750 sqm per hour

hour

4.280

986.04

4220.25

P&M-004

cum

97.500

655.60

63921.29

M-051

tonne

0.250

52269.11

13067.28

M-074

Machinery

Material
Crushed stone aggregate 11.2 mm size
Bitumen (60-70 grade)

d)

Overhead charges @ 0.1 on (a+b+c)

12048.65

e)

Contractor's profit @ 0.1 on (a+b+c+d)

13253.51

Cost for 7500 sqm = a+b+c+d+e

145788.66

Rate per sqm = (a+b+c+d+e)/7500

19.44
say

Note

4.12

406

19.40

Though vibratory roller is required only for 3 hours as per


norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65.
Wet Mix Macadam
Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a)

b)

Labour
Mate

day

0.480

185.07

88.83

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

10.000

177.07

1770.70

L-13

Wet mix plant of 75 tonne hourly capacity

hour

6.600

2454.00

16196.40

P&M-094

Electric generator 125 KVA

hour

6.000

2307.00

13842.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

1188.00

7128.00

P&M-017

Paver finisher

hour

6.000

1420.00

8520.00

P&M-035

Vibratory roller 8 - 10 tonne

hour

6x0.65

1779.00

6938.10

P&M-059

hour

12.000

Machinery

or
Smooth 3 wheeled steel roller @ 8-10 tonnes.
114

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Water tanker 6 KL capacity


Tipper

c)

RCD/SOR
Quantity

Rate Rs

hour

3.000

111.24

tonne.km

495 x L

2.68

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Material ( Table 400-11)

333.72

Remarks/
Input ref.
P&M-060

1325.81 Lead =1 km &


P&M-047
132.58

45 mm to 22.4 mm@ 30 per cent

cum

89.100

723.00

64419.30

M-034

22.4 mm to 2.36 mm @ 40 per cent

cum

118.800

794.46

94381.37

M-031

2.36 mm to 75 micron@ 30 per cent

cum

89.100

239.00

21294.90

M-022

KL

18.000

167.07

3007.23

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

23979.29

e)

Contractor's profit @ 0.1 on (a+b+c+d)

26377.22

Cost for 225 cum = a+b+c+d+e

290149.44

Rate per cum = (a+b+c+d+e)/225

1289.55
say

Note

Cost Rs

1290.00

1. Though vibratory roller is required only for 3 hours as per


norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm.

4.13

407

Construction of Median and Island with Soil Taken from


Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures,
spread, graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a)

b)

c)

Labour
Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Water tanker 6 KL with 5 km lead and 1 trip per hour

hour

1.000

111.24

111.24

P&M-060

Plate compactor @ 3.5 cum per hour

hour

6.000

142.99

857.95

P&M-086

KL

6.000

167.07

1002.41

M-189

Machinery

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

307.84

e)

Contractor's profit @ 0.1 on (a+b+c+d)

338.63

Cost for 21 cum = a+b+c+d+e

3724.91

Rate per cum = (a+b+c+d+e)/21

177.38
say

Note

4.14

407

177.00

This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.
Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a)

b)

Labour
Mate

day

0.160

185.07

29.61

L-12

Mazdoor

day

4.000

177.07

708.28

L-13

Water tanker with 5 km lead

hour

1.000

111.24

111.24

P&M-060

Plate Compactor @ 3.5 cum per hour

hour

6.000

142.99

857.95

P&M-086

Machinery

115

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

RCD/SOR
Unit

Hydraulic Excavator1.0 cum bucket capacity @60 cum


per hour
Tipper 10 tonne capacity

Quantity

Rate Rs

hour

0.500

1516.32

tonne.km

52.5 x L

2.68

Add 10 per cent of cost of transportation to cover cost


of loading and unloading
c) Material
Cost of water
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6.000

167.07

140.62 Lead =1 km &


P&M-047

1002.41

M-189

398.46
4383.02

Rate per cum = (a+b+c+d+e)/ 21

4.15

P&M-026

362.23

Cost for 21 cum = a+b+c+d+e

Note

758.16

Remarks/
Input ref.

14.06

KL

d)

Cost Rs

208.72
say

209.00

This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.
Construction of Shoulders
A. Earthen Shoulders
The rate as applicable for sub-grade construction may be
adopted.
B. Hard Shoulders
Rate as applicable for sub-base and or base may be adopted
as per approved design.
C. Paved shoulders
The rate may be adopted as applicable for different layers of
pavement depending upon approved design of paved
shoulders.

4.16

409

Footpaths and Separators


Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..
Unit = sqm
Taking output = 300 sqm
a)

b)

c)

Labour
Mate

day

1.360

185.07

251.70

Mason

day

4.000

234.29

937.16

L-12
L-11

Mazdoor

day

30.000

177.07

5312.10

L-13

Vibratory road roller 8 -10 tonnes @60 cum per hour

hour

0.750

1779.00

1334.25

P&M-059

Water tanker 6 KL capacity @ 1 trip per hour

hour

2.000

111.24

222.48

P&M-060

Concrete mixer 0.4/0.28 cum per hour

hour

6.000

211.68

1270.08

P&M-009

53 mm to 26.5 mm @ 35 per cent

cum

20.790

662.54

13774.29

M-029

26.5 mm to 4.75 mm @ 45 per cent

cum

26.730

711.13

19008.53

M-026

2.36 mm below @ 20 per cent

cum

11.880

239.00

2839.32

M-022

Aggregate 12 mm crushed @ 0.9 cum of concrete

cum

6.750

756.00

5103.00

M-052

Sand @ 0.45 cum/cum of concrete

cum

3.380

203.75

688.69

M-005

tonne

1.880

5789.47

10884.21

M-081

Machinery

Material

i) For Granular sub base material

ii) For cement concrete grade M157.5 cum

Cement
iii) For cement plaster 1:3
Sand
Cement

cum

3.840

203.75

782.42

M-005

tonne

1.830

5789.47

10594.74

M-081

each

3300.000

23.18

76496.36

M-184

metre

22.500

124.65

2804.52

M-137

KL

12.000

167.07

2004.82

M-189

iv) Pre-cast cement concrete tiles


Tiles size 300 x 300 mm and 25 mm thick
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage
vi) Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

15430.87
116

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description
e)

RCD/SOR
Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

186713.48

Rate per sqm = (a+b+c+d+e)/300

622.38
say

410

Remarks/
Input ref.

16973.95

Cost for 300 sqm = a+b+c+d+e

4.17

Cost Rs

622.00

Crusher Run Macadam Base


Providing crushed stone aggregate, depositing on a prepared
surface by hauling vehicles, spreading and mixing with a motor
grader, watering and compacting with a vibratory roller to
clause 410 to form a layer of sub-base/Base
Unit = cum
Taking output = 360 cum
A

By Mix in Place Method


a)

b)

c)

Labour
Mate

day

0.480

185.07

88.83

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

10.000

177.07

1770.70

L-13

Tractor attached with rotavator @ 25 cum per hour

hour

12.000

227.88

2734.56

P&M-054

Motor grader 110 HP

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8 -10 tonnes @ 60 cum per hour

hour

6.000

1779.00

10674.00

P&M-059

Water tanker 6 KL capacity

hour

6.000

111.24

667.44

P&M-060

63 mm to 45 mm @ 33 per cent

cum

157.460

532.91

83912.37

M-038

22.5 mm to 5.6 mm@ 32 per cent

cum

151.060

766.69

115816.49

M-032

Below 5.6 mm @ 35 per cent

cum

166.680

217.00

36169.56

M-030

KL

36.000

167.07

6014.46

M-189

Machinery

Material

Aggregate at site
i) For 53 mm maximum size

Cost of water
Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent

cum

24.120

723.00

17438.76

M-034

22.4 mm to 5.6 mm@ 50 per cent

cum

237.600

766.69

182166.02

M-032

Below 5.6 mm@ 45 per cent

cum

213.480

217.00

46325.16

M-030

KL

36.000

167.07

6014.46

M-189

Cost of water
4.17A

(i)

For 53 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

27337.64

e)

Contractor's profit @ 0.1 on (a+b+c+d)

30071.40

Cost for 360.0cum = a+b+c+d+e

330785.43

Rate per cum = (a+b+c+d+e)/360

918.85

or
4.17A

(ii)

say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

28340.79
31174.87

Cost for 360.0cum = a+b+c+d+e

342923.57

Rate per cum = (a+b+c+d+e)/360

952.57
say

Note
4.17

919.00

For 45 mm maximum size

953.00

Any one of the aggregate grading may be adopted


By Mixing Plant :
Unit = cum
Taking output = 225 cum (450 tonnes)
a)

b)

Labour
Mate

day

0.280

185.07

51.82

L-12

Mazdoor skilled

day

1.000

206.99

206.99

L-15

Mazdoor

day

6.000

177.07

1062.42

L-13

Wet mix plant @ 75 tonne per hour

hour

6.000

1128.60

6771.60

P&M-093

Electric generator 125 KVA

hour

6.000

2307.00

13842.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Motor grader 110 HP

hour

6.000

2519.00

15114.00

P&M-032

Vibratory roller 8 - 10 tonne

hour

6.000

1779.00

10674.00

P&M-059

Machinery

117

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Water tanker 6 KL capacity


Tipper 10 tonne capacity

c)

RCD/SOR
Quantity

Rate Rs

hour

3.000

111.24

tonne.km

450 x L

2.68

Add 10 per cent of cost of carriage to cover cost of


loading and unloading
Material

Cost Rs
333.72

Remarks/
Input ref.
P&M-060

1205.28 Lead =1 km &


P&M-047
120.53

Aggregate at site
i) For 53 mm maximum size
63 mm to 45 mm @ 33 per cent

cum

98.400

532.91

52438.57

M-038

22.5 mm to 5.6 mm@ 32 per cent

cum

94.410

766.69

72383.39

M-032

Below 5.6 mm @ 35 per cent

cum

104.180

217.00

22607.06

M-030

Or
ii) For 45 mm maximum size
45 mm to 22.5 mm@ 5 per cent

cum

15.060

723.00

10888.38

M-034

22.4 mm to 5.6 mm@ 50 per cent

cum

148.500

766.69

113853.76

M-032

Below 5.6 mm@ 45 per cent

cum

133.430

217.00

28954.31

M-030

KL

18.000

167.07

3007.23

M-189

Cost of water
4.17 B

(i)

For 53 mm maximum size


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

20393.94
22433.33

Cost for 225 cum = a+b+c+d+e

246766.65

Rate per cum = (a+b+c+d+e)/225

1096.74
say

4.17 B

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

21321.40
23453.54

Cost for 225 cum = a+b+c+d+e

257988.99

Rate per cum = (a+b+c+d+e)/225

1146.62
say

4.18

Suggest
ive

1097.00

For 45 mm maximum size

1147.00

Lime, Flyash Stabilised Soil Sub-Base


Construction of Sub-base using lime - Flyash admixture with
granular soil, free from organic matter/ deleterious material or
clayey silts and low plasticity clays having PI between 5 and
20 and liquid limit less than 25 and commercial dry lime,
slaked at site or pre-slaked with CaO content not less than 50
per cent, Flyash to conform to gradation as per clause 4.3 of
IRC: 88-1984, lime + Flyash content ranging between 10 to 30
per cent, the minimum un-confined compressive strength and
CBR value after 28 days curing and 4 days soaking to be
7.5kg/sq, cm and 25 per cent respectively, all as specified in
IRC: 88-1984.
Unit = cum
Taking output = 480 cum (720 tonnes, density 1.50 t/cum)
Assumptions made
Total mass taken for analysis = 720 t
Lime + Flyash admixture @ 20 per cent = 0.2 x 720=144 t
Soil = 720 -144 = 576 t
576 /1.6 = 360 cum
Lime + Flyash = 144 t
Ratio Lime 4 : Flyash 16
Lime = 29 kg.
Flyash = 115 kg.
a)

b)

Labour
Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mazdoor (Skilled)

day

1.000

206.99

206.99

L-15

hour

6.000

1516.32

9097.92

P&M-026

tonne.km

578 x L

2.68

Machinery
Hydraulic Excavator 0.90 cum bucket capacity @
60cum/hr. for 360 cum soil
Tipper 10T capacity for carriage of soil 576 tonnes

118

1548.12 Lead =1 km &


P&M-047

Analysis of Rate
Sr No

Ref. to
MoRTH
Spec.

c)

RCD/SOR
Quantity

Rate Rs

Unit

Tipper 10T capacity for carriage of 115 tonnes Flyash

tonne.km

115 x L

2.68

Tipper 10T capacity for carriage of 29 tonnes of lime from


store to work site
Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Tractor with disc harrows for pulverisation

hour

3.000

873.00

hour

6.000

171.02

1026.11

P&M-053

Motor Grader 110 HP @ 50 cum per hour for mixing inplace and grading
Vibratory roller 8 - 10 tonne

hour

9.600

2519.00

24182.40

P&M-032

hour

6.000

1779.00

10674.00

P&M-059

Water tanker 6 KL capacity

hour

12.000

111.24

1334.88

P&M-060

tonne

29.000

4427.31

128391.93

M-188

cum

360.000

25.10

9036.00

M-092

308.02 Lead =1 km &


P&M-047
2619.00

P&M-048

261.90

Material
Slaked Lime
Compensation for earth taken from private source

d)

Overhead charges @ 0.1 on (a+b+c)

18979.41

e)

Contractor's profit @ 0.1 on (a+b+c+d)

20877.35

Cost for 480 cum = a+b+c+d+e

229650.85

Rate per cum= (a+b+c+d+e)/480

478.44
say

Note

Cost Rs

Remarks/
Input ref.

Description

1.Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.
2.Cost of Flyash has not been considered as same will be
available free of cost. Only carriage of Flyash has been
provided.
3.Lime + Flyash has been taken as 20 per cent of total mass
and ratio of lime and Flyash as 1:4 for estimating purposes.
Total quantities will be as per approved design.

119

478.00

CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Sr No

Ref. to
MoRTH
Spec.

5.1

502

Description

Unit

Cost Rs

Remarks/
Input ref.

Quantity

Rate Rs

day
day

0.080
2.000

185.07
177.07

14.81
354.14

L-12
L-13

hour
hour
hour
hour

2.800
2.800
2.000
1.000

465.00
293.76
986.04
111.24

1302.00
822.53
1972.08
111.24

P&M-031
P&M-001
P&M-004
P&M-060

tonne
KL

2.100
6.000

45849.96
167.07

say

96284.92
1002.41
10186.41
11205.05
123255.58
35.22
35.00

Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base including
clearing of road surface and spraying primer at the rate of
0.60 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Bitumen pressure distributor @ 1750 sqm per hour
Water tanker 6 KL capacity @ 1 tripper hour
c) Material
Bitumen emulsion @ 0.6 kg per sqm
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500

Note

5.2

503

M-077
M-189

Bitumen primer has been provided @ 0.60 kg per sqm as per


clause 502.8. Payment shall be made with adjustment, plus or
minus, for the variation between this quantity and the actual
quantity approved by the Engineer after the preliminary trials
referred to in clause No. 502.4.3.
Tack Coat
Providing and applying tack coat with bitumen emulsion using
emulsion pressure distributor at the rate of 0.20 kg per sqm
on the prepared bituminous/granular surface cleaned with
mechanical broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Mechanical broom @ 1250 sqm per hour
Air compressor 250 cfm
Emulsion pressure distributor @ 1750 sqm per hour
c) Material
Bitumen emulsion @ 0.2 kg per sqm
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 3500 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/3500

day
day

0.080
2.000

185.07
177.07

14.81
354.14

L-12
L-13

hour
hour
hour

2.800
2.800
2.000

465.00
293.76
735.48

1302.00
822.53
1470.96

P&M-031
P&M-001
P&M-016

tonne

0.700

45849.96

32094.97
3605.94
3966.53
43631.88
12.47
12.00

M-077

say
Note

1. Bitumen emulsion has been provided @ 0.20 kg per sqm


as per clause 503.8. Payment shall be made with adjustment,
plus or minus, for the variation between this quantity and
actual quantity approved by the Engineer after preliminary
trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by bituminous
courses on the same day.

5.3

504

Bituminous Macadam

119

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and laying bituminous macadam with 100-120 TPH


hot mix plant producing an average output of 75 tonnes per
hour using crushed aggregates of specified grading premixed
with bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the required
grade, level and alignment and rolled as per clauses 501.6
and 501.7 to achieve the desired compaction.
Unit = cum
Taking output = 205 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction

day

16.000

177.07

2833.12

L-13

Skilled mazdoor for checking line & levels

day

5.000

206.99

1034.95

L-15

Batch mix HMP 100-120 TPH @ 75 tonne per hour


actual output
Mechanical broom hydraulic @ 1250 sqm per hour

hour

6.000

33841.00

203046.00

P&M-022

hour

2.200

465.00

1023.00

P&M-031

Air compressor 250 cfm

hour

2.200

293.76

646.27

P&M-001

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Generator 250 KVA

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

3237.00

19422.00

P&M-081

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Smooth wheeled roller 8-10 tonnes for initial break down


rolling.

hour 6.00x0.65*

665.00

2593.50

P&M-044

Vibratory roller 8 tonnes for intermediate rolling.

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material

hour 6.00x0.65*

1051.92

4102.49

P&M-045

14.850

52269.11

776196.23

M-074

Machinery

Front end loader 1 cum bucket capacity


Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading

c)

i) Bitumen@ 3.3 per cent of mix

tonne

1205.28 Lead =1 km
& P&M-047
120.53

weight of mix = 205 x 2.2 = 450 tonne


ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )
37.5 - 25 mm 15 per cent

cum

43.510

751.41

32693.98

M-049

25 - 10 mm 45 per cent

cum

130.550

911.09

118942.67

M-046

10 - 5 mm 25 per cent

cum

72.530

701.00

50843.53

M-040

5 mm and below15 per cent

cum

43.510

217.00

9441.67

M-030

25 - 10 mm 40 per cent

cum

116.040

911.09

105722.77

M-046

10 - 5 mm 40 per cent

cum

116.040

701.00

81344.04

M-040

5 mm and below 20 per cent

cum

58.020

217.00

12590.34

M-030

or
GradingII(19 mm nominal size)

* Any one of the alternative may be adopted as per approved


design
(i)

for Grading I ( 40 mm nominal size )


d)

Overhead charges @ 0.1 on (a+b+c)

125713.48

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 205 cum = a+b+c+d+e

138284.83
1521133.08

120

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per cum = (a+b+c+d+e)/205 (For Grading I)

7420.00

for GradingII(19 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

124487.01

e)

Contractor's profit @ 0.1 on (a+b+c+d)

136935.71

Cost for 205 cum = a+b+c+d+e

1506292.79

Rate per cum = (a+b+c+d+e)/205 (For Grading-II)

Note

Remarks/
Input ref.

7420.16
say

(ii)

Cost Rs

7347.77
say

7348.00

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of
Mechanical broom and 2 mazdoors for the same shall be
deleted as the same has been included in the cost of tack
coat.

5.3A

504

Bituminous Macadam with Modified Graded Bitumen


Providing and laying bituminous macadam with 100-120 TPH
hot mix plant producing an average output of 75 tonnes per
hour
Unit =using
cumcrushed aggregates of specified grading premixed
with bituminous binder, transported to site, laid over a
previously prepared surface with paver finisher to the required
Taking
output
= 205
cum (450
grade, level
and
alignment
andtonnes)
rolled as per clauses 501.6
and 501.7 to achieve the desired compaction.
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and
layoutfor
of checking
construction
Skilled
mazdoor
line & levels

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

Batch mix HMP 100-120 TPH @ 75 tonne per hour


actual output

hour

6.000

33841.00

203046.00

P&M-022

Mechanical broom hydraulic @ 1250 sqm per hour

hour

2.200

465.00

1023.00

P&M-031

Air compressor 250 cfm

hour

2.200

293.76

646.27

P&M-001

Paver finisher hydrostatic with sensor control @ 75 cum


per hour

hour

6.000

3128.00

18768.00

P&M-034

Generator 250 KVA

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Smooth wheeled roller 8-10 tonnes for initial break down
rolling.

121

1205.28 Lead =1 km
& P&M-047
120.53

hour 6.00x0.65*

665.00

2593.50

P&M-044

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Vibratory roller 8 tonnes for intermediate rolling.

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.

hour 6.00x0.65*

1051.92

4102.49

P&M-045

Material
i) Bitumen@ 3.3 per cent of mix

tonne

14.850

53320.75

791813.10

M-078

37.5 - 25 mm 15 per cent

cum

43.510

751.41

32693.98

M-049

25 - 10 mm 45 per cent

cum

130.550

911.09

118942.67

M-046

10 - 5 mm 25 per cent

cum

72.530

701.00

50843.53

M-040

5 mm and below15 per cent

cum

43.510

217.00

9441.67

M-030

25 - 10 mm 40 per cent

cum

116.040

911.09

105722.77

M-046

10 - 5 mm 40 per cent

cum

116.040

701.00

81344.04

M-040

5 mm and below 20 per cent

cum

58.020

217.00

12590.34

M-030

weight of mix = 205 x 2.2 = 450 tonne


ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )

or
GradingII(19 mm nominal size)

* Any one of the alternative may be adopted as per approved


design
(i)

for Grading I ( 40 mm nominal size )


d)

Overhead charges @ 0.1 on (a+b+c)

127275.16

e)

Contractor's profit @ 0.1 on (a+b+c+d)

140002.68

Cost for 205 cum = a+b+c+d+e

1540029.49

Rate per cum = (a+b+c+d+e)/205 (For Grading I)

7512.34
say

(ii)

7512.00

for GradingII(19 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

126048.69

122

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

1525189.20

Rate per cum = (a+b+c+d+e)/205 (For Grading-II)

504

Remarks/
Input ref.

138653.56

Cost for 205 cum = a+b+c+d+e

5.3B

Cost Rs

7439.95
say

7440.00

Bituminous Macadam with VG-30 Bulk Bitumen


Providing and laying bituminous macadam with 100-120 TPH
hot mix plant producing an average output of 75 tonnes per
hour
Unit =using
cumcrushed aggregates of specified grading premixed
with bituminous binder, transported to site, laid over a
previously
prepared
withtonnes)
paver finisher to the required
Taking output
= 205surface
cum (450
grade, level and alignment and rolled as per clauses 501.6
and
to achieve the desired compaction.
a) 501.7
Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels
layoutfor
of checking
construction
Skilledand
mazdoor
line & levels

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

Batch mix HMP 100-120 TPH @ 75 tonne per hour


actual output
Mechanical broom hydraulic @ 1250 sqm per hour

hour

6.000

33841.00

203046.00

P&M-022

hour

2.200

465.00

1023.00

P&M-031

Air compressor 250 cfm

hour

2.200

293.76

646.27

P&M-001

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Generator 250 KVA

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

hour 6.00x0.65*

665.00

2593.50

P&M-044

hour 6.00x0.65*

1779.00

6938.10

P&M-059

hour 6.00x0.65*

1051.92

4102.49

P&M-045

47539.64

705963.65

M-074 B

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Smooth wheeled roller 8-10 tonnes for initial break down
rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material
i) Bitumen@ 3.3 per cent of mix

tonne

weight of mix = 205 x 2.2 = 450 tonne


ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 14.85 tonnes
Weight of aggregate = 450 -14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
*Grading I ( 40 mm nominal size )

123

14.850

1205.28 Lead =1 km
& P&M-047
120.53

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

37.5 - 25 mm 15 per cent

cum

43.510

751.41

32693.98

M-049

25 - 10 mm 45 per cent

cum

130.550

911.09

118942.67

M-046

10 - 5 mm 25 per cent

cum

72.530

701.00

50843.53

M-040

5 mm and below15 per cent

cum

43.510

217.00

9441.67

M-030

25 - 10 mm 40 per cent

cum

116.040

911.09

105722.77

M-046

10 - 5 mm 40 per cent

cum

116.040

701.00

81344.04

M-040

5 mm and below 20 per cent

cum

58.020

217.00

12590.34

M-030

or
GradingII(19 mm nominal size)

(i)

* Any one of the alternative may be adopted as per approved


design
for Grading I ( 40 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

118690.22

e)

Contractor's profit @ 0.1 on (a+b+c+d)

130559.24

Cost for 205 cum = a+b+c+d+e

1436151.65

Rate per cum = (a+b+c+d+e)/205 (For Grading I)

7005.62
say

(ii)

for GradingII(19 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

117463.75

e)

Contractor's profit @ 0.1 on (a+b+c+d)

129210.12

Cost for 205 cum = a+b+c+d+e

1421311.36

Rate per cum = (a+b+c+d+e)/205 (For Grading-II)

6933.23
say

Note

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
2.Quantity of Bitumen has been taken for analysis purpose.
analysis. To cater for the idle period of these rollers, their
The actual quantity will depend upon job mix formula.
usage rates have been multiplied by a factor of 0.65.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BM is laid over freshly laid tack coat, provision of
Mechanical broom and 2 mazdoors for the same shall be
deleted as the same has been included in the cost of tack
coat.

5.4

505

Bituminous Penetration Macadam


Construction of penetration macadam over prepared Base by
providing a layer of compacted crushed coarse aggregate
using chips spreader with alternate applications of bituminous
binder and key aggregates and rolling with a smooth wheeled
steel roller 8-10 tonne capacity to achieve the desired degree
of compaction
A

7006.00

50 mm thick
Unit = sqm
Taking output = 4500 sqm (225 cum)
a) Labour
124

6933.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

day

0.320

185.07

59.22

L-12

Mazdoor including for brooming of key aggregates

day

6.000

177.07

1062.42

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm = 9000 sqm

hour

6.000

2423.52

14541.12

P&M-025

Bitumen pressure distributor for @ 1750 sqm per hour

hour

2.570

986.04

2534.12

P&M-004

Tipper 5.5 cum capacity for carriage of aggregates from


stockpile to chip spreader
Vibratory roller 8 tonnes

hour

10.000

873.00

8730.00

P&M-048

hour

6.000

1779.00

10674.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne

22.500

52269.11

1176054.89

M-074

cum

270.000

629.40

169938.95

M-033

cum

67.500

794.46

53625.78

M-031

Machinery

Material

d)

Crushed stone coarse aggregate passing 45 mm and


retained on 2.8 mm sieve @ 0.06 cum per sqm
Key aggregates passing 22.4 mm and retained on 2.8
mm sieve @ 0.015 cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

144476.25
158923.87

Cost for 4500 sqm = a+b+c+d+e

1748162.61

Rate per sqm = (a+b+c+d+e)/4500

388.48
say

5.4

Remarks/
Input ref.

Mate

Bitumen@ 5 kg per sqm

Note

Cost Rs

388.00

2 tippers will be needed to match the capacity of chip


spreader and front end loader.
75 mm thick
Unit = sqm
Taking output = 4500 sqm (337.5 cum compacted).
a) Labour

b)

c)

Mate

day

0.400

185.07

74.03

L-12

Mazdoor including for brooming of key aggregates

day

8.000

177.07

1416.56

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 4500 x 2 sqm
Bitumen pressure distributor for@ 1750 sqm per hour

hour

6.000

2423.52

14541.12

P&M-025

hour

2.570

986.04

2534.12

P&M-004

Tipper 5.5 cum capacity for carriage of aggregates from


stockpile to chip spreader
Vibratory roller 8 tonnes

hour

10.000

873.00

8730.00

P&M-048

hour

6.000

1779.00

10674.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne

30.600

52269.11

1599434.66

M-074

Crushed stone coarse aggregate (loose passing 63 mm


and retained on 2.8 mm sieve @ 0.09 cum per sqm

cum

405.000

713.93

289139.63

M-037

Key aggregates passing 26.5 mm and retained on 2.8


mm sieve @ 0.018 cum per sqm

cum

81.000

711.13

57601.61

M-026

Machinery

Material
Bitumen@ 6.8 kg per sqm

d)

Overhead charges @ 0.1 on (a+b+c)

199168.77

e)

Contractor's profit @ 0.1 on (a+b+c+d)

219085.65

Cost for 4500 sqm = a+b+c+d+e

2409942.12

Rate per sqm = (a+b+c+d+e)/4500

535.54
say

Note
5.5

506

2 tippers and 2 rollers will be needed to match the capacity of


chip spreader and front end loader.
Built-up-Spray Grout
125

536.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing, laying and rolling of built-up-spray grout layer over


prepared base consisting of a two layer composite
construction of compacted crushed coarse aggregates using
motor grader for aggregates. key stone chips spreader may
be used with application of bituminous binder after each layer,
and with key aggregates placed on top of the second layer to
serve as a Base conforming to the line, grades and crosssection specified, the compacted layer thickness being 75 mm
Unit = sqm
Taking output = 3000 sqm (225 cum)
a) Labour

b)

Mate

day

0.400

185.07

74.03

L-12

Mazdoor including for brooming of key aggregates

day

8.000

177.07

1416.56

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Hydraulic self propelled chip spreader both for


aggregates and key aggregates@ 1500 sqm per hour
for 3000 x 3 sqm
Bitumen pressure distributor for 3000 x 2 sqm @ 1750
sqm per hour
Tipper 5.5 cum capacity

hour

6.000

2423.52

14541.12

P&M-025

hour

3.430

986.04

3382.12

P&M-004

hour

10.000

873.00

8730.00

P&M-048

Vibratory roller 8 tonnes

hour

6.000

1779.00

10674.00

P&M-059

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne

9.000

52269.11

470421.96

M-074

cum

300.000

626.44

187932.60

M-035

cum

39.000

794.46

30983.78

M-031

Machinery

c)

Material

d)

Bitumen30 kg per 10 sqm @ 15 kg per 10 sqm for each


layer
Crushed stone coarse aggregate passing 53 mm and
retained on 2.8 mm sieve @ 0.5 cum per 10 sqm for
each layer
Key aggregates passing 22.4 mm and retained on 2.8
mm sieve @ 0.13 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

73569.81
80926.80

Cost for 3000 sqm = a+b+c+d+e

890194.76

Rate per sqm = (a+b+c+d+e)/3000

296.73
say

Note
5.6

507

297.00

2 tippers will be needed to match the capacity of hydraulic


chip spreader and front end loader.
Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous macadam with
100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.0 to 4.5 per
cent by weight of total mix and filler, transporting the hot mix
to work site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification
clause No. 507 complete in all respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75 cum


per hour

hour

6.000

3128.00

18768.00

P&M-034

Machinery

126

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

Generator 250 KVA

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
smooth wheeled roller 8-10 tonnes for initial break down
rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

Quantity

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Materials
Bitumen @ 4.25 per cent of weight of mix

1205.28 Lead =1 km
& P&M-047
120.53

hour 6.00x0.65*

665.00

2593.50

P&M-044

hour 6.00x0.65*

1779.00

6938.10

P&M-059

hour 6.00x0.65*

1051.92

4102.49

P&M-045

tonne

19.130

52269.11

999908.01

M-074

37.5 - 25 mm 22 per cent

cum

63.190

751.41

47481.79

M-049

25 - 10 mm 13 per cent

cum

37.340

911.09

34020.06

M-046

10 -4.75 mm 19 per cent

cum

54.580

701.00

38260.58

M-040

4.75 mm and below 44 per cent

cum

126.390

217.00

27426.63

M-030

tonne

8.620

4427.31

38163.39

M-188

25 - 10 mm 30 per cent

cum

86.160

911.09

78499.43

M-046

10 - 5 mm 28 per cent

cum

80.430

701.00

56381.43

M-040

5 mm and below 40 per cent

cum

114.900

217.00

24933.30

M-030

tonne

8.620

4427.31

38163.39

M-188

Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 287.25 cum
Grading - I

40 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.


or
Grading - II

19 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.

(i)

* Any one of the alternative may be adopted as per approved


design
For Grading I ( 40 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

145260.79

e)

Contractor's profit @ 0.1 on (a+b+c+d)

159786.87

Cost for 195 cum = a+b+c+d+e

1757655.54

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

9013.62
say

(ii)

For GradingII (19 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

146523.30

e)

Contractor's profit @ 0.1 on (a+b+c+d)

161175.63

Cost for 195 cum = a+b+c+d+e

1772931.91

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

9091.96
say

Note

9014.00

*1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

127

9092.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cost Rs

Remarks/
Input ref.

Quantity

Rate Rs

day

0.840

185.07

155.46

L-12

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75 cum


per hour

hour

6.000

3128.00

18768.00

P&M-034

Generator 250 KVA

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

4. In case DBM is laid over freshly laid tack coat, provision of


mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
5.6 A

507

Dense Graded Bituminous Macadam with Modified


Graded Bitumen
Providing and laying dense graded bituminous macadam with
100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified
Unit = cum
grading, premixed with bituminous binder @ 4.0 to 4.5 per
cent by weight of total mix and filler, transporting the hot mix
to
workoutput
site, laying
with (450
a hydrostatic
Taking
= 195 cum
tonnes) paver finisher with
sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to
a) Labour
achieve the desired compaction as per MoRTH specification
clause No. 507 complete in all respects.
Mate
Mazdoor working with HMP, mechanical broom, paver,
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels
b)

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading

c)

1205.28 Lead =1 km
& P&M-047
120.53

smooth wheeled roller 8-10 tonnes for initial break down


rolling.

hour 6.00x0.65*

665.00

2593.50

P&M-044

Vibratory roller 8 tonnes for intermediate rolling.

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.

hour 6.00x0.65*

1051.92

4102.49

P&M-045

53320.75

1020025.89

Materials
Bitumen @ 4.25 per cent of weight of mix
Aggregate

Total weight of mix = 450 tonnes


Weight of bitumen = 19.13 tonnes
Weight of aggregate = 450 -19.13 = 430.87 tonnes

128

tonne

19.130

M-078

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking density of aggregate = 1.5 ton/cum


Volume of aggregate = 287.25 cum
Grading - I

40 mm (Nominal Size)

37.5 - 25 mm 22 per cent

cum

63.190

751.41

47481.79

M-049

25 - 10 mm 13 per cent

cum

37.340

911.09

34020.06

M-046

10 -4.75 mm 19 per cent

cum

54.580

701.00

38260.58

M-040

4.75 mm and below 44 per cent

cum

126.390

217.00

27426.63

M-030

tonne

8.620

4427.31

38163.39

M-188

25 - 10 mm 30 per cent

cum

86.160

911.09

78499.43

M-046

10 - 5 mm 28 per cent

cum

80.430

701.00

56381.43

M-040

5 mm and below 40 per cent

cum

114.900

217.00

24933.30

M-030

tonne

8.620

4427.31

38163.39

M-188

Filler @ 2 per cent of weight of aggregates.


or
Grading - II

19 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.


* Any one of the alternative may be adopted as per approved
design
(i)

For Grading I ( 40 mm nominal size )


d)

Overhead charges @ 0.1 on (a+b+c)

147272.58

e)

Contractor's profit @ 0.1 on (a+b+c+d)

161999.84

Cost for 195 cum = a+b+c+d+e

1781998.19

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

9138.45
say

(ii)

For GradingII (19 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

148535.09

e)

Contractor's profit @ 0.1 on (a+b+c+d)

163388.60

Cost for 195 cum = a+b+c+d+e

1797274.55

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

9216.79
say

Note

9138.00

*1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
2.Quantity of Bitumen has been taken for analysis purpose.
mixing and paving the output of 450 tonnes considered in this
The actual quantity will depend upon job mix formula.
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
129

9217.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
6. The individual percentage of aggregates should be
should be ammended for use in field. The average density of
calculated from the total weight of dry aggregates i.e..
1.5 tonne/cum is only a reference density in this Data Book.
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
5.6 B

507

Dense Graded Bituminous Macadam with VG-30 Grade


Bulk Bitumen

Providing and laying dense graded bituminous macadam with


100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.0 to 4.5 per
cent by weight of total mix and filler, transporting the hot mix
Unit
= cum
to work
site, laying with a hydrostatic paver finisher with
sensor control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to
achieve the desired compaction as per MoRTH specification
clause
507 =complete
all respects.
Taking No.
output
195 cumin(450
tonnes)

a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction

day

16.000

177.07

2833.12

L-13

Skilled mazdoor for checking line & levels

day

5.000

206.99

1034.95

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75 cum


per hour

hour

6.000

3128.00

18768.00

P&M-034

Generator 250 KVA

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Machinery

130

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Tipper 10 tonne capacity

tonne.km

Quantity
450 x L

Rate Rs
2.68

Add 10 per cent of cost of carriage to cover cost of loading


and unloading

c)

Cost Rs

Remarks/
Input ref.

1205.28 Lead =1 km
& P&M-047

120.53

smooth wheeled roller 8-10 tonnes for initial break down


rolling.

hour 6.00x0.65*

665.00

2593.50

P&M-044

Vibratory roller 8 tonnes for intermediate rolling.

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.

hour 6.00x0.65*

1051.92

4102.49

P&M-045

Materials

Bitumen @ 4.25 per cent of weight of mix

tonne

19.130

47539.64

909433.30

M-074 B

37.5 - 25 mm 22 per cent

cum

63.190

751.41

47481.79

M-049

25 - 10 mm 13 per cent

cum

37.340

911.09

34020.06

M-046

Aggregate

Total weight of mix = 450 tonnes

Weight of bitumen = 19.13 tonnes

Weight of aggregate = 450 -19.13 = 430.87 tonnes

Taking density of aggregate = 1.5 ton/cum

Volume of aggregate = 287.25 cum

Grading - I

40 mm (Nominal Size)

131

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

10 -4.75 mm 19 per cent

cum

54.580

701.00

38260.58

M-040

4.75 mm and below 44 per cent

cum

126.390

217.00

27426.63

M-030

tonne

8.620

4427.31

38163.39

M-188

25 - 10 mm 30 per cent

cum

86.160

911.09

78499.43

M-046

10 - 5 mm 28 per cent

cum

80.430

701.00

56381.43

M-040

5 mm and below 40 per cent

cum

114.900

217.00

24933.30

M-030

tonne

8.620

4427.31

38163.39

M-188

Filler @ 2 per cent of weight of aggregates.

or

Grading - II

19 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.

* Any one of the alternative may be adopted as per approved


design

(i)

For Grading I ( 40 mm nominal size )

d)

Overhead charges @ 0.1 on (a+b+c)

136213.32

e)

Contractor's profit @ 0.1 on (a+b+c+d)

149834.65

Cost for 195 cum = a+b+c+d+e

1648181.15

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

8452.21

say

132

8452.00

Sr No

Ref. to
MoRTH
Spec.

Description
(ii)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

For GradingII (19 mm nominal size)

d)

Overhead charges @ 0.1 on (a+b+c)

137475.83

e)

Contractor's profit @ 0.1 on (a+b+c+d)

151223.41

Cost for 195 cum = a+b+c+d+e

1663457.52

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

Note

Cost Rs

8530.55

say

8531.00

185.07

155.46

*1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
2.Quantity
Bitumen
been by
taken
for analysis
usage ratesofhave
been has
multiplied
a factor
of 0.65. purpose.
The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case DBM is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
5.7

508

Semi-Dense Bituminous Concrete


Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.5 to 5 per cent
of mix and filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 508
complete in all respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate

day

133

0.840

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Rate Rs

Cost Rs

Remarks/
Input ref.

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction

day

16.000

177.07

2833.12

L-13

Skilled mazdoor for checking line & levels

day

5.000

206.99

1034.95

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Generator 250 KVA

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

hour 6.00x0.65*

665.00

2593.50

P&M-044

hour 6.00x0.65*

1779.00

6938.10

P&M-059

hour 6.00x0.65*

1051.92

4102.49

P&M-045

20.250

52269.11

1058449.40

M-074

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break down
rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

Quantity

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller
Material

1205.28 Lead =1 km
& P&M-047
120.53

* Grading I: 13 mm (Nominal Size)


i) Bitumen@ 4.5 per cent of weight of mix

tonne

ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
13.2 - 10 mm20 per cent

cum

57.300

910.00

52143.00

M-044

10 - 5 mm 38 per cent

cum

108.870

701.00

76317.87

M-040

5 mm and below 40 per cent


Filler @ 2 per cent of weight of aggregates.

cum

114.600

217.00

24868.20

M-030

tonne

8.620

4427.31

38163.39

M-188

tonne

22.500

52269.11

1176054.89

M-074

cum

162.450

701.00

113877.45

M-040

cum

116.850

217.00

25356.45

M-030

tonne

8.620

4427.31

38163.39

M-188

or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
9.5 - 4.75 mm@ 57 per cent
4.75 and below@ 41 per cent
Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

151728.93
166901.82

Cost for 195 cum = a+b+c+d+e

1835920.04

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

9414.97
say

5.7

(ii)

9415.00

for GradingII(10 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

162079.96

Cost for 195 cum = a+b+c+d+e

178287.96
1961167.53

134

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

Remarks/
Input ref.

10057.27
say

Note

Cost Rs

10057.00

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case SDBC is laid over freshly laid tack coat, provision of
broom and 2 mazdoor shall be deleted as the same has been
included in the cost of tack coat.

5.7 A

508

5. The quantity of Bitumen to be adjusted as per job mix


formula.
Semi-Dense Bituminous Concrete with Modified Graded
Bitumen.
Providing and laying semi dense bituminous concrete with
100-120 TPH batch type HMP producing an average output of
75 tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 4.5 to 5 per cent
of mix and filler, transporting the hot mix to work site, laying
with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRTH specification clause No. 508
complete in all respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Generator 250 KVA

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

hour 6.00x0.65*

665.00

2593.50

P&M-044

hour 6.00x0.65*

1779.00

6938.10

P&M-059

hour 6.00x0.65*

1051.92

4102.49

P&M-045

53320.75

1079745.13

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of
loading and unloading
Smooth wheeled roller 8-10 tonnes for initial break down
rolling.
Vibratory roller 8 tonnes for intermediate rolling.

c)

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller
Material

1205.28 Lead =1 km
& P&M-047
120.53

* Grading I: 13 mm (Nominal Size)


i) Bitumen@ 4.5 per cent of weight of mix
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450-20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
135

tonne

20.250

M-078

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

13.2 - 10 mm20 per cent

cum

57.300

910.00

52143.00

M-044

10 - 5 mm 38 per cent

cum

108.870

701.00

76317.87

M-040

5 mm and below 40 per cent

cum

114.600

217.00

24868.20

M-030

tonne

8.620

4427.31

38163.39

M-188

tonne

22.500

53320.75

1199716.81

M-078

9.5 - 4.75 mm@ 57 per cent

cum

162.450

701.00

113877.45

M-040

4.75 and below@ 41 per cent

cum

116.850

217.00

25356.45

M-030

tonne

8.620

4427.31

38163.39

M-188

Filler @ 2 per cent of weight of aggregates.


or
Grading II: 10 mm (Nominal Size)
Bitumen@5 per cent of weight of mix
weight of mix = 450 tonne
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum

Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

153858.50
169244.35

Cost for 195 cum = a+b+c+d+e

1861687.87

Rate per cum = (a+b+c+d+e)/195 (For Grading I)

9547.12
say

5.7

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

164446.15

e)

Contractor's profit @ 0.1 on (a+b+c+d)

180890.77

Cost for 195 cum = a+b+c+d+e

1989798.45

Rate per cum = (a+b+c+d+e)/195 (For Grading-II)

10204.09
say

Note

5.8

509

9547.00

for GradingII(10 mm nominal size)

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case SDBC is laid over freshly laid tack coat, provision of
broom and 2 mazdoor shall be deleted as the same has been
included in the cost of tack coat.
5. The quantity of Bitumen to be adjusted as per job mix
formula.
Bituminous Concrete
Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509
complete in all respects
Unit = cum

136

10204.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 191 cum (450 tonnes)


a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction

day

16.000

177.07

2833.12

L-13

Skilled mazdoor for checking line & levels

day

5.000

206.99

1034.95

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Generator 250 KVA

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

3237.00

19422.00

P&M-081

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery

Front end loader 1 cum bucket capacity


Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading

c)

1205.28 Lead =1 km
& P&M-047
120.53

Smooth wheeled roller 8-10 tonnes for initial break down


rolling.

hour 6.00x0.65*

665.00

2593.50

P&M-044

Vibratory roller 8 tonnes for intermediate rolling.

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material

hour 6.00x0.65*

1051.92

4102.49

P&M-045

i) Bitumen@ 5 per cent of weight of mix

tonne

22.500

52269.11

1176054.89

M-074

20 - 10 mm 35 per cent

cum

99.750

1087.74

108501.75

M-045

10 - 5 mm 23 per cent

cum

65.550

701.00

45950.55

M-040

ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)

5 mm and below 40 per cent

cum

114.000

217.00

24738.00

M-030

tonne

8.620

4427.31

38163.39

M-188

13.2 - 10 mm30 per cent

cum

85.500

910.00

77805.00

M-044

10 - 5 mm 25 per cent

cum

71.250

701.00

49946.25

M-040

5 mm and below43 per cent

cum

122.550

217.00

26593.35

M-030

tonne

8.620

4427.31

38163.39

M-188

Filler @ 2 per cent of weight of aggregates.


or
Grading - II-13 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading-I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

166075.60
182683.16

Cost for 191 cum = a+b+c+d+e

2009514.78

Rate per cum = (a+b+c+d+e)/191

10521.02
say

5.8

(ii)

10521.00

for Grading-II (10 mm nominal size)


d)

Overhead charges @ 0.1 on (a+b+c)

163591.03

e)

Contractor's profit @ 0.1 on (a+b+c+d)

179950.13

Cost for 191 cum = a+b+c+d+e

1979451.48

Rate per cum = (a+b+c+d+e)/191 (For Grading-II)

10363.62
say

137

10364.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.

5.9

510

Surface Dressing
Providing and laying surface dressing as wearing course in
single coat using crushed stone aggregates of specified size
on a layer of bituminous binder laid on prepared surface and
rolling with 8-10 tonne smooth wheeled steel roller.
Unit = sqm
Taking output = 9000 sqm
Case -1 :-19 mm nominal chipping size
a) Labour

b)

c)

Mate

day

0.440

185.07

81.43

L-12

Mazdoor

day

9.000

177.07

1593.63

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mechanical broom @ 1250 sqm per hour

hour

7.200

465.00

3348.00

P&M-031

Air compressor 250 cfm

hour

7.200

293.76

2115.07

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips from
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2423.52

14541.12

P&M-025

hour

6.000

873.00

5238.00

P&M-048

hour

6.000

1188.00

7128.00

P&M-017

Bitumen pressure distributor

hour

6.000

986.04

5916.24

P&M-004

Smooth wheeled roller 8-10 tonne weight

hour

6.000

665.00

3990.00

P&M-044

tonne

10.800

52269.11

564506.35

M-074

cum

135.000

862.50

116437.77

M-053

Machinery

Material
Bitumen@ 1.20 kg per sqm

d)

Crushed stone chipping,19 mm nominal size @ 0.015


cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

72530.96
79784.06

Cost for 9000 sqm = a+b+c+d+e

877624.61

Rate per sqm = (a+b+c+d+e)/9000

97.51
say

5.9

98.00

Case - II 13 mm nominal size chipping


a) Labour

b)

Mate

day

0.440

185.07

81.43

L-12

Mazdoor

day

9.000

177.07

1593.63

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Machinery

138

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

Mechanical broom @ 1250 sqm per hour

hour

7.200

465.00

3348.00

P&M-031

Air compressor 250 cfm

hour

7.200

293.76

2115.07

P&M-001

Hydraulic self propelled chip spreader @ 1500 sqm per


hour
Tipper 10 tonne capacity for carriage of stone chips from
stockpile on road side to chip spreader
Front end loader 1 cum bucket capacity

hour

6.000

2423.52

14541.12

P&M-025

hour

6.000

873.00

5238.00

P&M-048

hour

6.000

1188.00

7128.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Vibratory roller 8-10 tonne weight

hour

6.000

1779.00

10674.00

P&M-059

tonne

9.000

52269.11

470421.96

M-074

cum

90.000

756.00

68040.00

M-052

Material
Bitumen@ 1.00 kg per sqm

d)

Crushed stone chipping,13 mm nominal size @ 0.01


cum per sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

58951.14
64846.26

Cost for 9000 sqm = a+b+c+d+e

713308.83

Rate per sqm = (a+b+c+d+e)/9000


Note

Cost Rs

79.26
say

79.00

1. Where the proposed aggregate fails to pass the stripping


test, an approved adhesion agent may be added to the binder
as per clause 510.2.4. Alternatively, chips may be pre-coated
as per clause 510.2.5.
2. Input for the second coat, where required, will be the same
as per the Ist coat mentioned above.

5.10

511

Open - Graded Premix Surfacing


Providing, laying and rolling of open - graded premix surfacing
of 20 mm thickness composed of 13.2 mm to 5.6 mm
aggregates either using penetration grade bitumen or cutback or emulsion to required line, grade and level to serve as
wearing course on a previously prepared base, including
mixing in a suitable plant, laying and rolling with a smooth
wheeled roller 8-10 tonne capacity, finished to required level
and grades.
Unit = sqm
Taking output = 10250 sqm (205 cum)
(i)

Case - I: Mechanical method using Penetration grade


Bitumen and HMP of appropriate capacity not less than
75 tonnes/hour .
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, road sweeper, paver and


roller
Skilled mazdoor for checking line & levels

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

i) Batch type HMP 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

ii) Electric Generator Set 250 KVA

hour

6.000

3237.00

19422.00

P&M-081

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery

iii) Front end loader 1 cum bucket capacity


iv) Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
v) Paver finisher hydrostatic with sensor attachment
iv) Smooth wheeled/tandom roller 8-10 tonnes weight
c)

1205.28 Lead =1 km
& P&M-047
120.53

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

1051.92

6311.52

P&M-045

tonne

14.970

52269.11

782468.52

M-074

cum

276.750

635.00

175736.25

M-043

Material
Bitumen@ 14.60 kg per 10 sqm

d)

Crushed stone chipping,13.2 mm to 5.6 mm @ 0.27 cum


per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 10250 sqm = a+b+c+d+e

121822.96
134005.26
1474057.85

139

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per sqm = (a+b+c+d+e)/10250

Remarks/
Input ref.

143.81
say

5.10

Cost Rs

Note

If a premix sand seal coat of 'B' type is proposed, the same is


required to be provided over the open graded premix carpet
immediately on the same day. As the same HMP and other
machines will be used for laying of premix sand seal coat, out
of 6 effective working hours, 4.00 hours may be utilised for
laying of premix carpet and balance 2.00 hours for the seal
coat. The rate for the premix sand seal coat under clause 513
(case II) has been worked out accordingly by utilising the
HMP for 2.00 hours for the purpose of seal coat. In case type
'A' seal coat is proposed, HMP can be worked for six hours for
the premix carpet as type 'A' seal coat does not require the
use of HMP.

(ii)

Case - II: Open-Graded Premix Surfacing using cationic


Bitumen Emulsion
Unit = sqm

144.00

Taking output = 900 sqm (24.3 cum)


a) Labour

b)

c)

Mate

day

0.800

185.07

148.06

L-12

Mazdoor

day

18.000

177.07

3187.26

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Concrete mixer 0.4/0.28 cum capacity

hour

6.000

211.68

1270.08

P&M-009

Smooth wheeled steel roller 8-10 tonne

hour

6.000

665.00

3990.00

P&M-044

tonne

1.940

44006.71

85373.02

M-073

cum

24.300

635.00

15430.50

M-043

Machinery

Material
Cationic Bitumen Emulsion @ 21.50 kg per 10 sqm

d)

Crushed stone aggregates 13.2 mm to 5.6 mm @ 0.27


cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10981.29
12079.42

Cost for 900 sqm = a+b+c+d+e

132873.60

Rate per sqm = (a+b+c+d+e)/900

147.64
say

5.11

512

148.00

Close Graded Premix Surfacing/Mixed Seal Surfacing


Case I

Mechanical means using HMP of appropriate capacity not


less than 75 tonnes/hour.
Providing, laying and rolling of close-graded premix surfacing
material of 20 mm thickness composed of 11.2 mm to 0.09
mm (Type-A) or 13.2 mm to 0.09 mm (Type-B) aggregates
using penetration grade bitumen to the required line, grade
and level to serve as wearing course on a previously
prepared base, including mixing in a suitable plant, laying and
rolling with a Smooth wheeled roller 8-10 tonne capacity, and
finishing to required level and grade.
Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, road sweeper, paver and


roller
Skilled mazdoor for checking line & levels

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

i) HMP of appropicate capacity - 75 t per hour

hour

6.000

33841.00

203046.00

P&M-022

ii) Electric Generator Set 250 KVA

hour

6.000

3237.00

19422.00

P&M-081

iii) Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery

iv) Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
140

1205.28 Lead =1 km
& P&M-047
120.53

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

v) Paver finisher hydrostatic with sensor attachment

hour

6.000

3128.00

18768.00

P&M-034

iv) Smooth wheeled8-10 tonnes weight

hour

6.000

665.00

3990.00

P&M-044

tonne

22.500

52269.11

1176054.89

M-074

cum

276.750

503.00

139205.25

M-041

tonne

19.480

52269.11

1018202.19

M-074

cum

276.750

624.00

172692.00

M-042

Material

Type - A
* Bitumen@ 22 kg per 10 sqm
Stone crushed aggregates 11.2 mm to 0.09 @ 0.27 cum
per 10 sqm
or
Type - B
Bitumen @ 19 kg per 10 sqm

d)

Stone crushed aggregates 13.2 mm to 0.09 mm @ 0.27


cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

157296.35
173025.98

Cost for 10250 sqm = a+b+c+d+e

1903285.81

Rate per sqm = (a+b+c+d+e)/10250

185.69
For Type 'A'

say

186.00

For Type 'B'

say

171.00

* Any one of the alternative may be adopted


5.12

513

Seal Coat
Providing and laying seal coat sealing the voids in a
bituminous surface laid to the specified levels, grade and
cross fall using Type A and B seal coats
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
(i)

Case - I : Type A
a) Labour

b)

c)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Hydraulic self propelled chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Tipper 5.5 cum capacity

hour

6.000

873.00

5238.00

P&M-048

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Smooth wheeled roller 8 -10 tonne weight

hour

6.000

665.00

3990.00

P&M-044

tonne

10.050

52269.11

525304.52

M-074

cum

92.250

484.67

44710.50

M-050

Machinery

Material
Bitumen@ 9.80 kg per 10 sqm

d)

Crushed stone chipping of 6.7 mm size defined as 100


per cent passing 11.2 mm sieve and retained on 2.36
mm sieve applied @ 0.09 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

60793.52
66872.87

Cost for 10250 sqm = a+b+c+d+e

735601.61

Rate per sqm = (a+b+c+d+e)/10250

71.77
say

Note
5.12

(ii)

72.00

Since seal coat is provided immediately over the bituminous


layers, mechanical broom for clearing has not been catered.
Case - II : Type B
Providing and laying of premix sand seal coat with HMP of
appropriate capacity not less than 75 tonnes/ hours using
crushed stone chipping 6.7 mm size and penetration bitumen
of suitable grade.
Unit = sqm
Taking output = 7858 sqm (47.16 cum)
a) Labour
Mate

day

0.160

185.07

29.61

L-12

Mazdoor

day

4.000

177.07

708.28

L-13

141

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Rate Rs

HMP of 75 tonnes/hour.

hour

2.000

33841.00

67682.00

P&M-022

hour

2.000

3237.00

6474.00

P&M-081

hour

2.000

1188.00

2376.00

P&M-017

tonne.km

104 x 'L'

2.68

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher hydrostatic with sensor attachment
Smooth wheeled 8-10 tonnes capacity

27.86
hour

2.000

3128.00

6256.00

P&M-034

hour

2.000

665.00

1330.00

P&M-044

tonne

5.340

52269.11

279117.03

M-074

d)

Crushed stone chipping of 6.7 mm size defined as


passing 11.2 mm sieve and retained on 2.36 mm sieve
applied @ 0.06 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

cum

47.160

484.67

22856.88

M-050

e)

Contractor's profit @ 0.1 on (a+b+c+d)

38713.62
42584.98

Cost for 7858 sqm = a+b+c+d+e

468434.81

Rate per sqm = (a+b+c+d+e)/7858

514

278.55 Lead =1 km
& P&M-047

Material
Bitumen@ 6.80 kg per 10 sqm

5.13

Remarks/
Input ref.

Electric Generator Set 250 KVA


Tipper 10 tonne capacity

Note

Cost Rs

Machinery

Front end loader 1 cum bucket capacity

c)

Quantity

59.61
say

60.00

Since seal coat is required to be provided over the premix


carpet on the same day, out of the 6 working hours of the
HMP, 4.00 hours are proposed to be utilised for the premix
carpet and the balance 2.00 hours for the seal coat. Hence
2.00 hours have been considered for this case. This may be
linked to rate analysis worked out under clause 511.
Supply of Stone Aggregates for Pavement Courses
Supply of stone aggregates from approved sources
conforming to the physical requirement, specified in the
respective specified clauses, including royalties, fees rents,
collection, transportation, stacking and testing and measured
in cum as per clause 514.5
Competitive market rates to be ascertained. Alternatively,
rates for stone crushing given in chapter 1may be adopted, if
found economical. In case for supply of aggregates at site are
not available, nearest crusher site may be ascertained.
Loading and un-loading charges and cost of carriage may be
added to these rates to arrive at the cost at site.

5.14

515

Mastic Asphalt
Providing and laying 25 mm thick mastic asphalt wearing
course with paving grade bitumen meeting the requirements
given in table 500-29, prepared by using mastic cooker and
laid to required level and slope after cleaning the surface,
including providing antiskid surface with bitumen precoated
finegrained hard stone chipping of 13.2 mm nominal size at
the rate of 0.005cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed
into surface when the temperature of surfaces is not less than
100 0C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.
Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour

b)

Mate

day

0.440

185.07

81.43

L-12

Mazdoor

day

10.000

177.07

1770.70

L-13

Mazdoor skilled

day

1.000

206.99

206.99

L-15

Mechanical broom @ 1250 sqm per hour

hour

0.060

465.00

27.90

P&M-031

Air compressor 250 cfm

hour

0.060

293.76

17.63

P&M-001

Mastic cooker 1 tonne capacity

hour

6.000

54.81

328.86

P&M-030

Machinery

142

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Bitumen boiler 1500 litres capacity

hour

6.000

182.52

1095.12

P&M-005

Tractor for towing and positioning of mastic cooker and


bitumen boiler
Material

hour

1.000

171.02

171.02

P&M-053

I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight of


mix. 2 x 10.2/100 = 0.204

tonne

0.204

52269.11

10662.90

M-074

ii) Fine aggregate passing 2.36mm and retained on


0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39

cum

0.390

211.23

82.38

M-021

iii) Lime stone dust filler with calcium content not less
than 80 per cent by weight @ 17.92 per cent by weight
of mix = 2 x 17.92/100 = 0.36

tonne

0.360

4427.31

1593.83

M-188

iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per


cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456
= 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for
skid resistance = 35 x 0.005/10 = 0.018

cum

0.550

635.00

349.25

M-043

cum

0.018 #VALUE!

#VALUE!

M-142

0.500

16116.56

M-074

Base mastic (without coarse aggregates) = 60 per cent


Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific
case)

vi) Bitumen for coating of chips @ 2 per cent by weight


= 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg

kg

32233.12

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 35.00 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/35

#VALUE!
say

Note

1.The rates for 50 mm & 40 mm thick layers may be worked


out on pro-rata basis.
2.Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and paid
separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.

143

#VALUE!

Sr No
5.15

Ref. to
MoRTH
Spec.

Description

516

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Slurry Seal
Providing and laying slurry seal consisting of a mixture of fine
aggregates, portland cement filler, bituminous emulsion and
water on a road surface including cleaning of surface, mixing
of slurry seal in a suitable mobile plant, laying and compacting
to provide even riding surface.
Case (i)

5 mm thickness
Unit = sqm
Taking output = 16000 sqm (80 cum)
Taking density of 2.2 tonnes per cum
weight of mix = 176 tonnes
a) Labour

b)

c)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mechanical broom

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler.
Pneumatic tyred roller with individual wheel load not
exceeding 1.5 tonnes
Water tanker6 KL capacity

hour

6.000

873.00

5238.00

P&M-048

hour

6.000

1143.72

6862.32

P&M-037

hour

2.000

111.24

222.48

P&M-060

tonne

19.360

45849.96

887655.23

M-077

cum

102.080

217.00

22151.36

M-030

tonne

3.520

4427.31

15584.12

M-188

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Residual Binder @ 11 per cent of mix 80 x 2.2 x 0.11
Fine aggregate 4.75 mm and below 87 per cent of total
mix,80 x 2.2 x 0.87 = 153.12 tonnes. Taking density1.5,
= 153.12/1.5 = 102.08 cum
Filler @ 2 per cent of total mix = 80 x 2.2 x 0.02
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

95806.56
105387.21

Cost for 16000 sqm = a+b+c+d+e

1159259.33

Rate per sqm = (a+b+c+d+e)/16000

72.45
say

5.15

Case (ii)

72.00

3 mm thickness
Unit = sqm
Taking output = 20000 sqm (60 cum)
a) Labour

b)

c)

Mate

day

0.200

185.07

37.01

L-12

Mazdoor

day

5.000

177.07

885.35

L-13

Mechanical broom

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler

hour

6.000

873.00

5238.00

P&M-048

Water tanker6 KL capacity

hour

2.000

111.24

222.48

P&M-060

Residual Binder @ 13 per cent of mix = 60 x 2.2 x 0.13

tonne

17.160

45849.96

786785.31

M-077

Fine aggregate 3 mm and below 85 per cent of total


mix, 60x 2.2 x 0.85 = 112.2 tonnes. Taking density 1.5,

cum

74.800

239.00

17877.20

M-022

Machinery

Material

144

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Filler @ 2 per cent of total mix = 60x 2.2 x 0.02


Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Rate Rs

tonne

2.640

4427.31

11688.09

M-188

KL

12.000

167.07

2004.82

M-189

84197.87
92617.65

Cost for 20000 sqm = a+b+c+d+e

1018794.19

Rate per sqm = (a+b+c+d+e)/20000


5.15

Cost Rs

Remarks/
Input ref.

Quantity

50.94
say

51.00

Case (iii) 1.5 mm thickness


Unit = sqm
Taking output = 24000 sqm (36 cum)
a) Labour

b)

c)

Mate

day

0.200

185.07

37.01

L-12

Mazdoor

day

5.000

177.07

885.35

L-13

Mechanical broom

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Mobile slurry seal equipment

hour

6.000

926.64

5559.84

P&M-033

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Tipper 5.5 cum capacity for carriage of aggregate from


stockpile on road side to slurry equipment, bitumen
emulsion and filler.

hour

6.000

873.00

5238.00

P&M-048

Water tanker6 KL capacity

hour

2.000

111.24

222.48

P&M-060

tonne

12.670

45849.96

580918.99

M-077

cum

43.300

239.00

10348.70

M-022

tonne

1.580

4427.31

6995.15

M-188

KL

12.000

167.07

2004.82

M-189

Machinery

Material
Residual Binder @ 16 per cent of mix, 36 x 2.2 x 0.16
Fine aggregate 2.36 mm and below,82 per cent of total
mix,36x 2.2 x 0.82 = 64.94 tonnes. Taking density 1.5
Filler @ 2 per cent of total mix = 36x 2.2 x 0.02
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

62389.09

e)

Contractor's profit @ 0.1 on (a+b+c+d)

68628.00

Cost for 24000 sqm = a+b+c+d+e

754907.99

Rate per sqm = (a+b+c+d+e)/24000

31.45
say

Note
5.16

517

31.00

1.Tack coat, if required to be provided, before laying slurry


seal may be measured and paid separately
Recycling of Bituminous Pavement with Central
Recycling Plant
Recycling pavement by cold milling of existing bituminous
layers, planning the surface after cold milling, reclaiming
excavated material to the extent of 30 per cent of the
required quantity, hauling and stockpiling the reclaimed
material near the central recycling plant after carrying out
necessary checks and evaluation, adding fresh material
including rejuvenators as required, mixing in a hot mix plant,
transporting and laying at site and compacting to the required
grade, level and thickness, all as specified in clause 517.

Unit = cum
Taking output = 120 cum (276 tonnes)
a) Labour

b)

Mate

day

0.480

185.07

88.83

L-12

Mazdoor

day

10.000

177.07

1770.70

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Cold milling machine @ 20 cum per hour

hour

6.000

855.36

5132.16

P&M-069

Mechanical broom @ 1250 sqm per hour

hour

1.280

465.00

595.20

P&M-031

Machinery

145

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Air compressor 250 cfm

hour

1.280

293.76

376.01

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

0.910

986.04

897.30

P&M-004

Hot mix plant 100-120 TPH producing an average of 75


tonnes per hour
Electric generator set 250 KVA

hour

3.000

44564.00

133692.00

P&M-021

hour

3.000

3237.00

9711.00

P&M-081

Front end loader 1.00 cum bucket capacity

hour

3.000

1188.00

3564.00

P&M-017

Tipper 5.5 cum capacity

hour

18.000

873.00

15714.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour 3.00x0.65*

665.00

1296.75

P&M-044

Vibratory roller 8 tonnes

hour 3.00x0.65*

1779.00

3469.05

P&M-059

Smooth wheeled tandem roller 6-8 tonnes

hour 3.00x0.65*

1051.92

2051.24

P&M-045

Material

i) Bitumen
A bitumen content is 4.5 per cent bitumen weight of mix. For
reclaimed material, fresh bitumen will be required to the
extent of 60 per cent of normal requirement.
In a mix of 276 tonnes, 82.8 tonne is reclaimed and balance
193.2 tonne is fresh mix.
Bitumen required for reclaimed mix of 82.8 tonne @ 60
per cent = 82.8 x 0.60 x0.04 = 1.99
Bitumen required for fresh mix of 193.2 tonnes = 193.2 x
0.04 = 7.73
ii) Aggregates

tonne

1.9872

52269.11

103869.17

M-074

tonne

7.728

52269.11

403935.65

M-074

37.5 - 25 mm @ 23 per cent

cum

28.440

751.41

21370.19

M-049

Percentage of mix requiring fresh aggregates - 70 per cent


Weight of fresh mix = 276 x 0.70 = 193.2 tonne
Weight of fresh aggregate in the mix = 193.2 x 0.96 = 185.47
tonne
Taking average density of 1.5 tonnes/cum, total volume of
aggregate = 123.65 cum.
Size wise requirement of fresh aggregates
25 - 10 mm @ 15 per cent

cum

18.550

911.09

16900.70

M-046

10- 5 mm @ 20 per cent

cum

24.730

701.00

17335.73

M-040

Below 5 mm @40 per cent

cum

49.460

217.00

10732.82

M-030

tonne

5.520

5789.47

31957.89

M-081

Filler (cement) @ 2 per cent = 5.52tonnes of 276 tonne


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

78487.44
86336.18

Cost for 120 cum of DBM = a+b+c+d+e

949698.00

Rate per cum = (a+b+c+d+e)/120

7914.15
say

Note

5.17

518

7914.00

Although the total rolling time is only 4 hours as per norms, all
the three rollers have to be available at site for 3 hours each
to match with the output of re-cycling plant. To cater for their
idling time, these have been multiplied with a factor of 0.65.
Fog Spray
Providing and applying low viscosity bitumen emulsion for
sealing cracks less than 3 mm wide or incipient fretting or
disintegration in an existing bituminous surfacing.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.120

185.07

22.21

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

tonne

6.000

986.04

5916.24

P&M-004

Machinery

Bitumen emulsion pressure distributor @ 1750 sqm per


hour
Material
146

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Bitumen emulsion @ 0.75 kg per sqm

tonne

Quantity

Rate Rs

Cost Rs

7.880

45849.96

361297.68

d)

Overhead charges @ 0.1 on (a+b+c)

37231.99

e)

Contractor's profit @ 0.1 on (a+b+c+d)

40955.19

Cost for 10500 sqm = a+b+c+d+e

Remarks/
Input ref.
M-077

450507.08

Rate per sqm = (a+b+c+d+e)/10500

42.91
say

43.00

1.In case it is decided by the engineer to blind the fog spray,


the following may be added
a) Labour

b)

Mate

day

0.160

185.07

29.61

L-12

Mazdoor for precoating of grit

day

4.000

177.07

708.28

L-13

cum

26.250

261.00

6851.25

M-024

tonne

0.790

45849.96

36221.47

M-077

Material
Crushed stone grit 3 mm size @ 3.75 kg per sqm

c)

Bitumen emulsion for precoating grit @ 2 per cent of


grit,39.38 x 0.02
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4381.06
4819.17

Cost for 10500 sqm = a+b+c+d

53010.84

Rate per sqm = (a+b+c+d)/10500

5.05
say

5.18

519

5.00

Bituminous Cold Mix ( Including Gravel Emulsion)


Providing, laying and rolling of bituminous cold mix on
prepared base consisting of a mixture of unheated mineral
aggregate and emulsified or cutback bitumen, including
mixing in a plant of suitable type and capacity, transporting,
laying, compacting and finishing to specified grades and
levels.
Unit = cum
Taking output = 205 cum (450 tonne)
Case (i) Using bitumen emulsion and 9.5 mm or 13.2 mm size
aggregate
Composition of mix (450 tonne) is assumed to be as under:Bitumen Emulsion 8 per cent

By weight
of total
mix

Filler2 per cent


Total aggregates 90 per cent
Proportion of aggregates
19 mm to 9.5 mm25 per cent
9.5 mm to 6 mm29 per cent
6 mm to 0.075 mm 36 per cent
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor

day

16.000

177.07

2833.12

L-13

Mazdoor skilled

day

5.000

206.99

1034.95

L-15

Drum mix plant for cold mixes of appropriate capacity


but not less than 75 tonnes/hour.
Electric generator 125 KVA

hour

6.000

1107.00

6642.00

P&M-077

hour

6.000

2307.00

13842.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher

c)

1205.28 Lead =1 km
& P&M-047
120.53

6.000

3128.00

18768.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

hour 6.00x0.65*

1143.72

4460.51

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour 6.00x0.65*

1051.92

4102.49

P&M-045

45849.96

1650598.56

Material
Bitumen emulsion @ 8 per cent

tonne
147

36.000

M-077

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Filler (lime)@ 2 per cent

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

tonne

9.000

4427.31

39845.77

M-188

Aggregates size 19 to 9.5 mm - 450 x 0.25 x 1/1.5

cum

75.000

1087.74

81580.26

M-045

Aggregates size 9.5 to 6 mm - 450 x 0.29 x 1/1.5

cum

87.000

701.00

60987.00

M-040

Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5

cum

108.000

217.00

23436.00

M-030

d)

Overhead charges @ 0.1 on (a+b+c)

191673.99

e)

Contractor's profit @ 0.1 on (a+b+c+d)

210841.39

Cost for 205 cum = a+b+c+d+e

2319255.31

Rate per cum = (a+b+c+d+e)/205

11313.44
say

11313.00

(Applicable to cases I to IV)


Note

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each as
per norms of output, but these are required to be available at
site for 6 hours as the drum mix plant and the paver would
take 6 hours for mixing and paving. To cater for the idle
period, their usage rates have been multiplied by a factor of
0.65

5.18

Case (ii) Using bitumen emulsion and 19 mm or 26.5 mm nominal


size aggregate
Composition of mix (450 tonne)
is assumed to be as
under:Bitumen Emulsion 8 per cent
Filler2 per cent
Total aggregates 90 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 35 per cent
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor

day

16.000

177.07

2833.12

L-13

Mazdoor skilled

day

5.000

206.99

1034.95

L-15

hour

6.000

1107.00

6642.00

P&M-077

hour

6.000

2307.00

13842.00

P&M-018

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery
Drum mix plant for cold mixes 60-90 tonne per hour
producing average output of 75 tonnes per hour
Electric generator 125 KVA
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Paver finisher

c)

120.53
6.000

3128.00

18768.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

hour 6.00x0.65*

1143.72

4460.51

P&M-037

Smooth wheeled steel tandom roller 6-8 tonnes

hour 6.00x0.65*

1051.92

4102.49

P&M-045

36.000

45849.96

1650598.56

M-077

Material
Bitumen emulsion @ 8 per cent

tonne

Filler (lime)@ 2 per cent

tonne

9.000

4427.31

39845.77

M-188

Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5

cum

75.000

829.17

62187.90

M-048

Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5

cum

90.000

847.21

76249.08

M-047

Aggregates size 6 to 0.075 mm - 450 x 0.35 x 1/1.5

cum

105.000

217.00

22785.00

M-030

d)

Overhead charges @ 0.1 on (a+b+c)

191195.86

e)

Contractor's profit @ 0.1 on (a+b+c+d)

210315.45

Cost for 205 cum = a+b+c+d+e

2313469.96

Rate per cum = (a+b+c+d+e)/205

11285.22
say

Note

1205.28 Lead =1 km
& P&M-047

1.Density of aggregates has been assumed 1.5 gms/cc

148

11285.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

2. Tack coat where provided will be measured and paid


separately.
*3. Though the rollers are required only for 3.5 hours each as
per norms of output, but these are required to be available at
site for 6 hours as the drum mix plant and the paver would
take 6 hours for mixing and paving. To cater for the idle
period, their usage rates have been multiplied by a factor of
0.65
5.18

Case (iii) Using cutback bitumen and 9.5 mm or 13.2 mm nominal


size aggregate
Composition of mix (450 tonne)
under:-

is assumed to be as

Cutback bitumen 5 per cent


Filler (lime)

2 per cent

Total aggregates 93 per cent


Proportion of aggregates
19 mm to 9.5 mm26 per cent
9.5 mm to 6 mm31 per cent
6 mm to 0.075 mm 36 per cent
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor

day

16.000

177.07

2833.12

L-13

Mazdoor skilled

day

5.000

206.99

1034.95

L-15

Drum mix plant for cold mixes 60-90 tonne per hour
producing average output of 75 tonnes per hour
Electric generator 125 KVA

hour

6.000

1107.00

6642.00

P&M-077

hour

6.000

2307.00

13842.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher

c)

120.53
6.000

3128.00

18768.00

P&M-034

Pneumatic tyred roller 12-15 tonnes

hour

hour 6.00x0.65*

1143.72

4460.51

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour 6.00x0.65*

1051.92

4102.49

P&M-045

Material
Cutback bitumen @ 5 per cent

tonne

22.500

46274.16

1041168.60

M-076

Filler (lime)@ 2 per cent

tonne

9.000

4427.31

39845.77

M-188

Aggregates size 19 to 9.5 mm - 450 x 0.26 x 1/1.5

cum

78.000

1087.74

84843.47

M-045

Aggregates size 9.5 to 6 mm - 450 x 0..31 x 1/1.5

cum

93.000

701.00

65193.00

M-040

Aggregates size 6 to 0.075 mm - 450 x 0.36 x 1/1.5

cum

108.000

217.00

23436.00

M-030

d)

Overhead charges @ 0.1 on (a+b+c)

131477.92

e)

Contractor's profit @ 0.1 on (a+b+c+d)

144625.71

Cost for 205 cum = a+b+c+d+e

1590882.80

Rate per cum = (a+b+c+d+e)/205

7760.40
say

Note

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each as
per norms of output, but these are required to be available at
site for 6 hours as the drum mix plant and the paver would
take 6 hours for mixing and paving. To cater for the idle
period, their usage rates have been multiplied by a factor of
0.65

5.18

1205.28 Lead =1 km
& P&M-047

Case (iv) Using cutback bitumen and 19 mm or 26.5 mm nominal


size aggregate
Composition of mix (450 tonne)
is assumed to be as
under:Cutback bitumen 5 per cent

149

7760.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Filler2 per cent


Total aggregates 93 per cent
Proportion of aggregates
37.5 mm to 19 mm25 per cent
19 mm to 6 mm 30 per cent
6 mm to 0.075 mm 38 per cent
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor

day

16.000

177.07

2833.12

L-13

Mazdoor skilled

day

5.000

206.99

1034.95

L-15

Drum mix plant for cold mixes 60-90 tonne per hour
producing output of 75 tonnes per hour
Electric generator 125 KVA

hour

6.000

1107.00

6642.00

P&M-077

hour

6.000

2307.00

13842.00

P&M-018

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

hour

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher

c)

6.000

3128.00

18768.00

P&M-034

Pneumatic tyred roller 12-15 tonnes.

hour 6.00x0.65*

1143.72

4460.51

P&M-037

Smooth wheeled steel tandem roller 6-8 tonnes

hour 6.00x0.65*

1051.92

4102.49

P&M-045

Material
Cutback bitumen on @ 5 per cent

tonne

22.500

46274.16

1041168.60

M-076

Filler (lime)@ 2 per cent

tonne

9.000

4427.31

39845.77

M-188

Aggregates size 37.5 to 19 mm - 450 x 0.25 x 1/1.5

cum

75.000

829.17

62187.90

M-048

Aggregates size 19 to 6 mm - 450 x 0.3 x 1/1.5

cum

90.000

847.21

76249.08

M-047

Aggregates size 6 to 0.075 mm - 450 x0.38 x 1/1.5

cum

114.000

217.00

24738.00

M-030

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

130448.17
143492.99

Cost for 205 cum = a+b+c+d+e

1578422.84

Rate per cum = (a+b+c+d+e)/205

7699.62
say

Note

1205.28 Lead =1 km
& P&M-047
120.53

7700.00

1.Density of aggregates has been assumed 1.5 gms/cc


2. Tack coat where provided will be measured and paid
separately.
*3. Though the rollers are required only for 3.5 hours each as
per norms of output, but these are required to be available at
site for 6 hours as the drum mix plant and the paver would
take 6 hours for mixing and paving. To cater for the idle
period, their usage rates have been multiplied by a factor of
0.65

5.19

520

Sand Asphalt Base Course


Providing, laying and rolling sand-asphalt base course
composed of sand, mineral filler and bituminous binder on a
prepared sub-grade or sub-base to the lines, levels, grades
and cross sections as per the drawings including mixing in a
plant of suitable type and capacity, transporting, laying,
compacting and finishing.
Unit = cum
Taking output = 205 cum (450 tonne)
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor

day

16.000

177.07

2833.12

L-13

Mazdoor skilled

day

5.000

206.99

1034.95

L-15

hour

6.000

28484.00

170904.00

P&M-023

hour

6.000

3237.00

19422.00

P&M-081

Machinery
Hot Mix Plant of appropriate capacity but not less than
75 tonnes/hour
Electric generator set 250 KVA
150

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Front end loader 1 cum bucket capacity


Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Paver finisher

c)

Quantity

Rate Rs

hour

6.000

1188.00

tonne.km

450 x L

2.68

Cost Rs
7128.00

Remarks/
Input ref.
P&M-017

1205.28 Lead =1 km
& P&M-047
120.53

hour

6.000

3128.00

18768.00

P&M-034

smooth wheeled roller 8-10 tonnes for initial break down


rolling.
Vibratory roller 8 tonnes for intermediate rolling.

hour

6.00x0.65

665.00

2593.50

P&M-044

hour

6.00x0.65

1779.00

6938.10

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandom


rollers.
Material

hour

6.00x0.65

1051.92

4102.49

P&M-045

Bitumen@ 5 per cent

tonne

22.500

52269.11

1176054.89

M-074

Filler (lime)@ 2 per cent

tonne

9.000

4427.31

39845.77

M-188

cum

288.620

203.75

58807.59

M-004

Composition of mix (450 tonne)


under:Density 2.20 tonne per cum

is assumed to be as

Weight450 tonne
Bitumen5 per cent
Filler2 per cent
Sand of size 4.75 to 0.075 mm 93 per cent

Sand of size 4.75 to 0.075 mm - 450 x 0.93 x 1/1.5


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

150991.37
166090.50

Cost for 205 cum = a+b+c+d+e

1826995.55

Rate per cum = (a+b+c+d+e)/205

8912.17
say

Note

1. Tack coat will be measured and paid separately


2. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of this roller, their usage
rates has been multiplied by a factor of 0.65

5.20

521

Modified Binder
Supply of modified binder produced by mixing bitumen with
modifier such as natural rubber or crumb rubber or any other
polymer found compatible with bitumen and which allows
properties given in clause 521.3 and IRC:SP: 53 blending of
modifier with bitumen to be done either at the refinery or at
central unit with all facilities by proper industrial process, is
essential.
Unit = tonne
The use of modified binder is expected to result in an
extended service life of bituminous pavements subject to
heavy traffic loads in extreme climatic conditions, thus
justifying the entire cost of adding modifiers/fibres. Other
advantages include lower temperature susceptibility, higher
resistance to aging, higher fatigue life, higher resistance to
cracking and better adhesion between aggregates and binder.
Detailed information and inductive dose level on the use of
polymer modified binder is available in IRC : SP-53 / 2002. A
number of proprietary products are now available in the
market. For such proprietary products, test reports and cost
effectiveness should be the basis for their selection in road
works.
The modifier, in the required quantity shall be blended at the
refinery or at central unit with all facilities by proper industrial
process, is essential. If supplied in drums it shall be agitated
in melted condition with suitable device for achieving
homogeneity.

151

8912.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Proposals to use glass fibre, polypropylene fibres or any other


similar material in a bituminous mixture should be
substantiated, complete with all details including test results,
manufacturer's recommendations for addition or means of
incorporating the fibres, homogeneously, without segregation,
into the mixture.
Before agreeing to the use of a fibre, it should have been
proved to be satisfactory in use under circumstances, similar
to the work, elsewhere or it would have under gone
appropriate performance trials. Documented evidence of use
and trials of the fibre, in any country having conditions similar
to Indian will be acceptable.
where information on use of trials is inadequate or lacking,
trials may be required to be under taken before agreeing to
the use of the fibre.
Note

1. The modified binder is usually manufactured by specialised


firms as a proprietary product. The rate for this product is
required to be ascertained from the market.

2.The specifications for various item of road works using


polymer/rubber modified bitumens are same as those for
penetration grade bitumen except those for any special
conditions which the manufacturer may indicate.
3.The other controls during mixing, laying shall be same as
specified in IRC - 14, 29, 94 and 95 for open graded premix
carpet, bituminous concrete, DBM and SDBC respectively.
4.The temperature of mixing and rolling will be slightly higher
than conventional bituminous mixes as indicated in Table 8 of
IRC: SP: 53 - 2002.
5.21

522

Crack Prevention Courses


Case (i) Stress absorbing membrane (SAM) crack width less than
6 mm
Providing and laying of a stress absorbing membrane over a
cracked road surface, with crack width below 6 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 9 kg per 10
sqm and spreading 5.6 mm crushed stone aggregates @ 0.11
cum per 10 sqm with hydraulic chip spreader, sweeping the
surface for uniform spread of aggregates and surface finished
to conform to clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

665.00

3990.00

P&M-044

tonne

9.450

53320.75

503881.06

M-078

cum

105.000

484.67

50890.00

M-050

Machinery

Material
Modified binder
Crushed stone aggregates 5.6 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

58487.78
64336.56

Cost for 10500 sqm = a+b+c+d+e

707702.16

Rate per sqm = (a+b+c+d+e)/10500

67.40
say

5.21

Case (ii) Stress absorbing membrane (SAM) with crack width 6


mm to 9 mm

152

67.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and laying of a stress absorbing membrane over a


cracked road surface, with crack width 6 to 9 mm after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 11 kg per 10
sqm and spreading 11.2 mm crushed stone aggregates @
0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mechanical broom @ 1250 sqm per hour

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm capacity

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

665.00

3990.00

P&M-044

tonne

11.550

53320.75

615854.63

M-078

cum

105.000

655.60

68838.32

M-051

Machinery

Material
Modified binder
Crushed stone chipping 11.2 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

71479.97

e)

Contractor's profit @ 0.1 on (a+b+c+d)

78627.97

Cost for 10500 sqm = a+b+c+d+e

864907.64

Rate per sqm = (a+b+c+d+e)/10500


5.21

82.37
say

82.00

Case (iii) Stress absorbing membrane (SAM) crack width above 9


mm and cracked area above 50 per cent
Providing and laying a single coat of a stress absorbing
membrane over a cracked road surface, with crack width
above 9 mm and cracked area above 50 per cent after
cleaning with a mechanical broom, using modified binder
complying with clause 521, sprayed at the rate of 15 kg per
10 sqm and spreading 11.2 mm crushed stone aggregates @
0.12 cum per 10 sqm, sweeping the surface for uniform
spread of aggregates and surface finished to conform to
clause 902.
Unit = sqm
Taking output = 10500 sqm
a) Labour

b)

c)

Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mechanical broom @ 1250 sqm per hour

hour

6.000

465.00

2790.00

P&M-031

Air compressor 250 cfm capacity

hour

6.000

293.76

1762.56

P&M-001

Bitumen pressure distributor @ 1750 sqm per hour

hour

6.000

986.04

5916.24

P&M-004

Hydraulic Chip spreader

hour

6.000

2423.52

14541.12

P&M-025

Smooth wheeled road roller 8-10 tonne

hour

6.000

665.00

3990.00

P&M-044

tonne

15.750

53320.75

839801.77

M-078

cum

126.000

655.60

82605.98

M-051

Machinery

Material
Modified binder
Crushed stone aggregates 11.2 mm size

d)

Overhead charges @ 0.1 on (a+b+c)

95292.85

e)

Contractor's profit @ 0.1 on (a+b+c+d)

104822.13

Cost for 10500 sqm = a+b+c+d+e

1153043.47

Rate per sqm = (a+b+c+d+e)/10500

109.81
say

153

110.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Note

In case 2nd coat is also required to be provided, material


provided for the 2nd coat shall be as per table 500-47.
Case(iv) Case - IV : Bitumen impregnated geotextile

5.21

Providing and laying a bitumen impregnated geotextile layer


after cleaning the road surface, geotextile conforming to
requirements of clause 703.3, laid over a tack coat with 1.05
kg per sqm of paving grade bitumen 80 - 100 penetration and
constructed to the requirement of clause 703.4.5
Unit = sqm
Taking output = 3500 sqm
a) Labour

b)

Mate

day

0.560

185.07

103.64

L-12

Mazdoor

day

12.000

177.07

2124.84

L-13

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mechanical broom @ 1250 sqm per hour

hour

2.800

465.00

1302.00

P&M-031

Air compressor 250 cfm capacity

hour

2.800

293.76

822.53

P&M-001

tonne

2.000

986.04

1972.08

P&M-004

hour

2.000

1143.72

2287.44

P&M-037

tonne

3.680

51344.59

188948.09

M-075

sqm

3850.000

60.75

233893.61

M-108

Machinery

Bitumen pressure distributor @ 1750 sqm per hour


Pneumatic roller
c)

Material
Paving grade bitumen of 80 - 100 penetration @ 1.05 kg
per sqm
Geotextile including 10 per cent for overlaps

d)

Overhead charges @ 0.1 on (a+b+c)

43186.82

e)

Contractor's profit @ 0.1 on (a+b+c+d)

47505.50

Cost for 3500 sqm = a+b+c+d+e

522560.53

Rate per sqm = (a+b+c+d+e)/3500


NOTE

5.22

519.3

149.30
say

149.00

As bitumen overlay construction shall follow closely the fabric


placement on the same day, an output of 3500 sqm only has
been considered for the analysis which will cover a length of
500 m, of 7 m wide carriagway. This can be conveniently
overlaid by a bitumenious course in a day.
Recipe Cold Mix
Providing and laying of premix of crushed stone aggregates
and emulsion binder, mixed in a batch type cold mixing plant,
laid over prepared surface, by paver finisher, rolled with a
pneumatic tyred roller initially and finished with a smooth steel
wheel roller, all as per clause 519.3
Unit = cum
Taking output = 205 cum (450 tonnes)

Case(i)

75 mm thickness
a) Labour

b)

Mate

day

1.000

185.07

185.07

L-12

Mazdoor

day

12.000

177.07

2124.84

L-13

Mazdoor skilled

day

5.000

206.99

1034.95

L-15

Batch type cold mixing plant 100-120 TPH capacity


producing an average output of 75 tonne per hour
Electric generator 125 KVA

hour

6.000

2279.88

13679.28

P&M-064

hour

6.000

2307.00

13842.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

1188.00

7128.00

P&M-017

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Tipper 10 tonne capacity

hour

6.000

3128.00

18768.00

P&M-034

tonne.km

450 x L

2.68

Machinery

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller12-15 tonnes.
Smooth wheeled steel roller6-8 tonnes.
154

1205.28 Lead =1 km
& P&M-047
120.53

hour 6.00x0.65*

1143.72

4460.51

P&M-037

hour 6.00x0.65*

665.00

2593.50

P&M-044

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Water tanker6 KL capacity


c)

Rate Rs

hour

1.000

111.24

111.24

tonne

20.250

45849.96

928461.69

M-077

cum

297.000

758.35

225231.14

M-055

KL

6.000

167.07

1002.41

M-189

P&M-060

Material
Bitumen emulsion @ 45 litres per tonne
Crushed stone aggregates 40 mm nominal size
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

121994.84

e)

Contractor's profit @ 0.1 on (a+b+c+d)

134194.33

Cost for 205 sqm = a+b+c+d+e

1476137.60

Rate per sqm = (a+b+c+d+e)/205

7200.67
say

Note

Cost Rs

Remarks/
Input ref.

Quantity

7201.00

(Case I to III)
1. These mixes are considered suitable for minor repair work
and temporary road surface improvement.
2. In case concrete mixtures are required to be used for
mixing, a number of these will be needed to match the
capacity of road rollers.
3. Tack coat, where provided, will be measured and paid
separately.
*4.Both the rollers have to be available at site to match with
the output of batch mixing plant and paver finisher. A
multiplying factor of 0.65 has been adopted to cater for the
idling period of road rollers.

5.22

Case(ii) 40 mm thickness
a) Labour

b)

Mate

day

1.000

185.07

185.07

L-12

Mazdoor

day

12.000

177.07

2124.84

L-13

Mazdoor skilled

day

5.000

206.99

1034.95

L-15

Batch type cold mixing plant100-120 TPH capacity


producing an average output of 75 tonne per hour
Electric generator 125 KVA

hour

6.000

2279.88

13679.28

P&M-064

hour

6.000

2307.00

13842.00

P&M-018

Front end loader 1 cum capacity

hour

6.000

1188.00

7128.00

P&M-017

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Tipper 10 tonne capacity

hour

6.000

3128.00

18768.00

P&M-034

tonne.km

450 x L

2.68

Machinery

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller 12-15 tonnes.

c)

120.53
hour 6.00x0.65*

1143.72

4460.51

P&M-037

Smooth wheeled steel roller 6-8 tonnes.

hour 6.00x0.65*

665.00

2593.50

P&M-044

Water tanker6 KL capacity

hour

1.000

111.24

111.24

P&M-060

tonne

31.500

45849.96

1444273.74

M-077

cum

287.000

756.00

216972.00

M-052

KL

6.000

167.07

1002.41

M-189

Material
Bitumen emulsion @ 70 litres per tonne
Crushed stone aggregates 14 mm nominal size
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

172750.13
190025.15

Cost for 205 sqm = a+b+c+d+e

2090276.63

Rate per sqm = (a+b+c+d+e)/205

10196.47
say

5.22

1205.28 Lead =1 km
& P&M-047

10196.00

Case(iii) 25 mm thickness
a) Labour

b)

Mate

day

1.000

185.07

185.07

L-12

Mazdoor

day

12.000

177.07

2124.84

L-13

Mazdoor skilled

day

5.000

206.99

1034.95

L-15

hour

6.000

2279.88

13679.28

P&M-064

Machinery
Batch type cold mixing plant 100-120 TPH capacity
producing an average output of 75 tonne per hour

155

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Rate Rs

hour

6.000

2307.00

13842.00

P&M-018

hour

6.000

1188.00

7128.00

P&M-017

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Tipper 10 tonne capacity

hour

6.000

3128.00

18768.00

P&M-034

tonne.km

450 x L

2.68

1205.28 Lead =1 km
& P&M-047
120.53

hour 6.00x0.65*

1143.72

4460.51

P&M-037

Smooth wheeled steel roller

hour 6.00x0.65*

665.00

2593.50

P&M-044

Water tanker6 KL capacity

hour

1.000

111.24

111.24

P&M-060

tonne

38.250

45849.96

1753760.97

M-077

cum

270.000

484.67

130860.00

M-050

KL

6.000

167.07

1002.41

M-189

Material
Crushed stone aggregates 6 mm nominal size
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

195087.66

e)

Contractor's profit @ 0.1 on (a+b+c+d)

214596.42

Cost for 205 sqm = a+b+c+d+e

2360560.66

Rate per sqm = (a+b+c+d+e)/205

11514.93
say

509

Remarks/
Input ref.

Front end loader 1 cum capacity

Bitumen emulsion @ 85 litres per tonne

5.8 A

Cost Rs

Electric generator 125 KVA

Add 10 per cent of cost of carriage to cover cost of loading


and unloading
Pneumatic tyred roller

c)

Quantity

11515.00

Bituminous Concrete with Modified Graded Bitumen


Providing and laying bituminous concrete with 100-120 TPH
batch type hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of specified
grading, premixed with bituminous binder @ 5.4 to 5.6 per
cent of mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor control to
the required grade, level and alignment, rolling with smooth
wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No. 509
complete in all respects
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction

day

16.000

177.07

2833.12

L-13

Skilled mazdoor for checking line & levels

day

5.000

206.99

1034.95

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Generator 250 KVA

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading

c)

1205.28 Lead =1 km
& P&M-047
120.53

Smooth wheeled roller 8-10 tonnes for initial break down


rolling.

hour 6.00x0.65*

665.00

2593.50

P&M-044

Vibratory roller 8 tonnes for intermediate rolling.

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material

hour 6.00x0.65*

1051.92

4102.49

P&M-045

53320.75

1199716.81

i) Bitumen@ 5 per cent of weight of mix


ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
156

tonne

22.500

M-078

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking density of aggregate = 1.5 ton/cum


Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent

cum

99.750

1087.74

108501.75

M-045

10 - 5 mm 23 per cent

cum

65.550

701.00

45950.55

M-040

5 mm and below 40 per cent

cum

114.000

217.00

24738.00

M-030

tonne

8.620

4427.31

38163.39

M-188

13.2 - 10 mm30 per cent

cum

85.500

910.00

77805.00

M-044

10 - 5 mm 25 per cent

cum

71.250

701.00

49946.25

M-040

5 mm and below43 per cent

cum

122.550

217.00

26593.35

M-030

tonne

8.620

4427.31

38163.39

M-188

Filler @ 2 per cent of weight of aggregates.


or
Grading - II-13 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading-I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

168441.79

e)

Contractor's profit @ 0.1 on (a+b+c+d)

185285.97

Cost for 191 cum = a+b+c+d+e

2038145.70

Rate per cum = (a+b+c+d+e)/191

10670.92
say

5.8 A

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

165957.22

e)

Contractor's profit @ 0.1 on (a+b+c+d)

182552.95

Cost for 191 cum = a+b+c+d+e

2008082.40

Rate per cum = (a+b+c+d+e)/191 (For Grading-II)

10513.52
say

5.8 B

10671.00

for Grading-II (10 mm nominal size)

10514.00

Bituminous
Concrete
(Providing
and
laying
bituminous concrete with 100-120 TPH batch type
hot mix plant producing an average output of 75
tonnes per hour using crushed aggregates of
specified grading, premixed with bituminous binder
@ 5.4 to 5.6 % of mix and filler, transporting the hot
mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade,
level and alignment, rolling with smooth wheeled,
vibratory and tandem rollers to achieve the desired
compaction as per MORTH specification clause No.
509 complete in all respects) with Bulk VG30
Bitumen.
(i) for Grading-I ( 13 mm nominal size )

Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, mechanical broom, paver,


roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

Batch mix HMP @ 75 tonne per hour

hour

6.000

33841.00

203046.00

P&M-022

Paver finisher hydrostatic with sensor control @ 75 cum


per hour
Generator 250 KVA

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

3237.00

19422.00

P&M-081

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

hour 6.00x0.65*

665.00

2593.50

P&M-044

hour 6.00x0.65*

1779.00

6938.10

P&M-059

Machinery

Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Smooth wheeled roller 8-10 tonnes for initial break down
rolling.
Vibratory roller 8 tonnes for intermediate rolling.
157

1205.28 Lead =1 km
& P&M-047
120.53

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Finish rolling with 6-8 tonnes smooth wheeled tandem


roller.
Material
i) Bitumen@ 5 per cent of weight of mix

Quantity

hour 6.00x0.65*

Rate Rs

Cost Rs

Remarks/
Input ref.

1051.92

4102.49

P&M-045

tonne

22.500

47539.64

1069641.89

M-074 B

20 - 10 mm 35 per cent

cum

99.750

1087.74

108501.75

M-045

10 - 5 mm 23 per cent

cum

65.550

701.00

45950.55

M-040

ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 22.5 tonnes
Weight of aggregate = 450 -22.50 = 427.50 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
* Grading - I-19 mm (Nominal Size)

5 mm and below 40 per cent

cum

114.000

217.00

24738.00

M-030

tonne

8.620

4427.31

38163.39

M-188

13.2 - 10 mm30 per cent

cum

85.500

910.00

77805.00

M-044

10 - 5 mm 25 per cent

cum

71.250

701.00

49946.25

M-040

5 mm and below43 per cent

cum

122.550

217.00

26593.35

M-030

tonne

8.620

4427.31

38163.39

M-188

Filler @ 2 per cent of weight of aggregates.


or
Grading - II-13 mm (Nominal Size)

Filler @ 2 per cent of weight of aggregates.

(i)

*Any one of the alternative may be adopted as per


approved design
for Grading-I ( 13 mm nominal size )
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

155434.30
170977.73

Cost for 191 cum = a+b+c+d+e

1880755.04

Rate per cum = (a+b+c+d+e)/191

9846.89
say

(ii)

d)

Overhead charges @ 0.1 on (a+b+c)

152949.73

e)

Contractor's profit @ 0.1 on (a+b+c+d)

168244.70

Cost for 191 cum = a+b+c+d+e

1850691.74

Rate per cum = (a+b+c+d+e)/191 (For Grading-II)

9689.49
say

Note

9847.00

for Grading-II (10 mm nominal size)

*1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours for
mixing and paving the output of 450 tonnes considered in this
analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
2.Quantity of Bitumen has been taken for analysis purpose.
The actual quantity will depend upon job mix formula.
3. Labour for traffic control, watch and ward and other
miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.
4. In case BC is laid over freshly laid tack coat, provision of
mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
6. The individual percentage of aggregates should be
calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.

158

9689.00

RCD/SOR

CHAPTER- 6

CEMENT CONCRETE PAVEMENTS


Sr No
6.1

Ref. to
MoRTH
Spec.

Description

601

Unit

Quantity

Rate Rs

day
day
day

1.120
6.000
22.000

185.07
206.99
177.07

hour
hour
hour
hour
hour
hour
tonne.km

6.000
6.000
6.000
6.000
8.000
8.000
990 x L

1188.00
2052.00
1698.00
3128.00
1779.00
111.24
2.68

Cost Rs

Remarks/
Input ref.

Dry Lean Cement Concrete Sub- base


Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 810 tonnes vibratory roller, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 75 cum per hour
Electric generator 100 KVA
Paver with electronic sensor
Vibratory roller 8-10 t capacity
Water tanker6 KL capacity
Tipper
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5
mm nominal sizes graded as per table 600-1 @ 0.90
cum/cum of concrete conforming to clause 602.2.4.
Coarse Sand as per IS: 383 @ 0.45 cum/cum of
concrete
Cement @ 150 kg/cum of concrete
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 450 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/450
Note

6.2

602

207.28
1241.94
3895.54

L-12
L-15
L-13

7128.00 P&M-017
12312.00 P&M-068
10188.00 P&M-080
18768.00 P&M-034
14232.00 P&M-059
889.92 P&M-060
2651.62 Lead =1 km
& P&M-047
265.16

cum

405.000

809.00

cum

203.000

203.75

tonne
KL

67.500
48.000

5789.47
167.07

day

2.000

185.07

327645.00 M-052 and


M-054
41362.14

M-004

390789.47
8019.27
83959.53
92355.49
1015910.37
2257.58
say
2258.00

M-081
M-189

Quantity provided for aggregate is for estimating purpose.


Exact quantity shall be as per mix design.
Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, mixed in a batching and mixing plant
as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate
122

370.14

L-12

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mazdoor skilled
Mazdoor
b) Machinery
Road Sweeper @ 1250 sqm per hour
Front end loader 1 cum bucket capacity
Cement concrete batch mix plant @ 175 cum per hour
(effective output)
Electric generator 250 KVA
Slip form paver with electronic sensor
Water tanker6 KL capacity
Transit truck agitator 5 cum capacity.
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
Concrete joint cutting machine .
Texturing machine .
c) Material
Crushed stone coarse aggregates of 25mm and
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4
@ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete
32 mm mild steel dowel bars of grade S 240
16 mm deformed steel tie bars of grade S 415
Separation Membrane of impermeable plastic sheeting
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion
joint.
Joint sealant
Sealant primer
Plastic sheath,1.25 mm thick for dowel bars
Curing compound
Super plastisizer admixture IS marked as per 91031999 @ 0.5 per cent by weight of cement
Cost of water

Rate Rs

day
day

15.000
35.000

206.99
177.07

3104.85
6197.45

L-15
L-13

hour
hour
hour

2.800
18.000
6.000

465.00
1188.00
4787.64

1302.00
21384.00
28725.84

P&M-031
P&M-017
P&M-067

hour
hour
hour
tonne.km

6.000
6.000
36.000
2415xL

3237.00
2637.36
111.24
4.32

19422.00 P&M-081
15824.16 P&M-006
4004.64 P&M-060
10432.80 Lead =1 km
& P&M-050
1043.28

hour
hour

12.000
12.000

214.92
71.50

cum

945.000

809.00

cum

473.000

203.75

96375.82

M-004

tonne 414.000
tonne
9.450
tonne
1.170
sqm 3675.000

5789.47
48690.69
46059.03
11.00

2396842.11
460126.98
53889.07
40418.14

M-081
M-126
M-082
M-164

16.330

708.07

11562.79

M-141

kg 875.000
kg 116.670
sqm
46.670
liter 1850.000
kg 2070.000

17.81
9.01
10.96
91.13
112.77

15580.69
1050.96
511.68
168585.65
233436.07

M-120
M-097
M-138
M-090
M-180

167.07

36086.74

M-189

sqm

KL

216.000

Add 1 per cent of material for cost of miscellaneous


materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.
Overhead charges @ 0.1 on (a+b+c)

443700.96

e)

Contractor's profit @ 0.1 on (a+b+c+d)

488071.05
5368781.57
5113.13
say

603

The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
Rolled Cement Concrete Base
Construction of rolled cement concrete base course with
coarse and fine aggregate conforming to IS:383, the size of
coarse aggregate not exceeding 25 mm with minimum,
aggregate cement ratio15:1 and minimum cement content of
200 kg/cum, aggregate gradation to be as per table 600-4
after blending, mixing in batching plant at optimum moisture
content, transporting to site, laying with a paver with
electronic sensor, compacting with 8-10 tonnes smooth
wheeled vibratory roller to achieve, the designed flexural
strength, finishing and curing.
Unit = cum
123

P&M-083
P&M-088

764505.00 M-052 and


M-054

d)

Rate per cum = (a+b+c+d+e)/1050

6.3

2579.04
857.95

42789.72

Cost for 1050cum = a+b+c+d+e

Note

Cost Rs

Remarks/
Input ref.

Quantity

5113.00

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 450 cum (990 tonne)


a)

b)

Labour
Mate

day

1.200

185.07

222.08

L-12

Mazdoor skilled

day

7.000

206.99

1448.93

L-15

Mazdoor

day

23.000

177.07

4072.61

L-13

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Cement concrete batch mix plant @ 75 cum per hour

hour

6.000

2052.00

12312.00

P&M-068

Electric generator 100 KVA

hour

6.000

1698.00

10188.00

P&M-080

Paver with electronic sensor @ 75 cum/hr.

hour

6.000

3128.00

18768.00

P&M-034

Vibratory roller 8-10 t capacity

hour

8.000

1779.00

14232.00

P&M-059

hour

8.000

111.24

889.92

P&M-060

tonne.km

990xL

2.68

Machinery

Water tanker with 5 km lead 6 KL capacity


Tipper
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
c)

265.16

Material
Crushed stone coarse aggregates of 25mm and
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.3.

cum

405.000

809.00

Sand as per IS: 383 and conforming to clause 602.2.3


@ 0.45 cum/cum of concrete

cum

203.000

203.75

41362.14

M-004

tonne

90.000

5789.47

521052.63

M-081

KL

48.000

167.07

8019.27

M-189

Cement @ 200 kg/cum of concrete


Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

97025.74
1174011.42

Rate per cum = (a+b+c+d+e)/450

2608.91
say

6.4

New

The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
Transition Section between Rigid and Flexible Pavement
Due to change in the properties of materials and type of
construction, a gradual changeover from rigid pavement to
flexible pavement is desirable to avoid any damage at the
butting joint. After provision of an expansion joint in the
cement concrete slab, the thickness of slab should be
tapered to 10 cm over a length of 3 m towards the flexible
pavement. The deficiency of thickness caused due to
tapering of the slab should be made up by the asphaltic
layers.
The quantities of items should be worked out based on the
approved design and drawings and priced as per rates given
under respective clauses for cement concrete and asphaltic
work.

6.5

Suggestive

327645.00 M-052 and


M-054

106728.31

Cost for 450cum = a+b+c+d+e

Note

2651.62 Lead =1 km
& P&M-047

Construction of Base/Sub-Base of Pavement with Lean


Concrete - Flyash.
Construction of Base/sub-base using cement, sand, fly ash
and coarse aggregates proportioned as per table 4 of IRC:
74/1979 and with water content ratio, slump and
compressive strength as defined in the said table, mix
prepared in a batching and mixing plant and compacted with
a vibratory roller 8-10 tonnes capacity within the time limit
laid down vide clause 7.6.3 of IRC: 74-1979, construction
joints properly formed at the end of day's work, cured for 14
days, all as specified in IRC: 74-1979 and as per approved
plans.
Unit = cum
124

2609.00

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 450 cum (990 tonne)


a)

b)

Labour
Mate

day

1.120

185.07

207.28

L-12

Mazdoor skilled

day

6.000

206.99

1241.94

L-15

Mazdoor

day

22.000

177.07

3895.54

L-13

Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

Cement concrete batch mix plant @ 75 cum per hour

hour

6.000

2052.00

12312.00

P&M-068

Electric generator 100 KVA

hour

6.000

1698.00

10188.00

P&M-080

Paver finisher with electronic sensor

hour

6.000

3128.00

18768.00

P&M-034

Vibratory roller 8-10 t capacity

hour

8.000

1779.00

14232.00

P&M-059

889.92

P&M-060

Machinery

Water tanker6 KL capacity

hour

8.000

111.24

tonne.km

990 x L

2.68

Crushed stone coarse aggregate of 40 mm nominal


size @ 0.90 cum/cum of concrete conforming to table 2
of IRC: 74-1979.

cum

405.000

758.35

307133.37

M-055

Coarse Sand as per IS: 383 - 1970

cum

110.960

203.75

22608.59

M-004

Cement @ 150 kg/cum of concrete

tonne

67.500

5789.47

390789.47

M-081

cum

91.540

0.00

0.00

M-011

Tipper 10 T Capacity
Add 10 per cent of cost of carriage to cover cost of loading
and unloading
c) Material

Fly ash conforming to IS: 3812 ( Part II )

2651.62 Lead =1 km
& P&M-047
265.16

( Total fine aggregates = 450 x 0.45 = 202.50 cum To be


divided in ratio of 2 sand : 1.65 flyash. Refer table 4 of IRC:
74-1979).
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

79231.09
87154.20

Cost for 450cum = a+b+c+d+e

958696.17

Rate per cum = (a+b+c+d+e)/450

2130.44
say

Note

1.Depending upon approved designs, crushed stone


aggregates of nominal size 20mm can also be used as per
gradation given in table 2 of IRC: 74-1979.
2.The ratio of specific gravities of fly ash and sand has been
assumed to be 0.827.
3.The quantities of materials given in the analyses are for
estimating purposes. Actual quantities shall be as per job
mix formula.
4.Construction procedure as laid down in clause, of IRC: 741979 shall be followed.

6.6

Suggestive

Cement - Flyash Concrete Pavement.


Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement, coarse and fine aggregate conforming to IS 383,
maximum size of coarse aggregate not exceeding 25 mm,
replacing cement by fly ash to the extent of 15 per cent and
sand by 10 per cent, mixed in a batching and mixing plant as
per approved mix design, transported to site, laid with a fixed
form or slip form paver, spread, compacted and finished in a
continuous operation including provision of contraction,
expansion, construction and longitudinal joints, joint filler,
separation membrane, sealant primer, joint sealant,
debonding strip, dowel bar, tie rod, admixtures as approved,
curing compound, finishing to lines and grades as per
drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a)

Labour
125

2130.00

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

2.000

185.07

370.14

L-12

Mazdoor skilled

day

15.000

206.99

3104.85

L-15

Mazdoor

day

35.000

177.07

6197.45

L-13

Road Sweeper @ 1250 sqm per hour

hour

2.800

465.00

1302.00

P&M-031

Front end loader 1 cum bucket capacity

hour

18.000

1188.00

21384.00

P&M-017

Cement concrete batch mix plant @ 175 cum per hour


(effective output)
Electric generator 250 KVA

hour

6.000

4787.64

28725.84

P&M-067

hour

6.000

3237.00

19422.00

P&M-081

Slip form paver with electronic sensor

hour

6.000

2637.36

15824.16

P&M-006

Water tanker6 KL capacity

hour

36.000

111.24

4004.64

P&M-060

tonne.km

2415xL

4.32

10432.80

P&M-050
Lead= 1 km

Machinery

Add 10 per cent of cost of carriage to cover cost of loading


and unloading

1043.28

Concrete joint cutting machine .

hour

12.000

214.92

2579.04

P&M-083

Texturing machine .

hour

12.000

71.50

857.95

P&M-088

Crushed stone coarse aggregates of 25mm and


12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4.

cum

945.000

809.00

Sand as per IS: 383 and conforming to clause 602.2.4

cum

425.000

203.75

86595.61

M-004

Cement 43 grade

tonne

357.000

5789.47

2066842.11

M-081

Fly ash conforming to IS: 3812-1966 (Part-I)

tonne

109.000

0.00

0.00

M-011

32 mm mild steel dowel bars of grade S 240

tonne

9.450

48690.69

460126.98

M-126

16 mm deformed steel tie bars of grade S 415

tonne

1.170

46059.03

53889.07

M-082

sqm 3675.000

11.00

40418.14

M-164

Material

Separation Membrane of impermeable plastic sheeting


125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion
joint.
Joint sealant

764505.00 M-052 and


M-054

sqm

16.330

708.07

11562.79

M-141

kg

875.000

17.81

15580.69

M-120

kg

116.670

9.01

1050.96

M-097

Plastic sheath,1.25 mm thick for dowel bars

sqm

46.670

10.96

511.68

M-138

Curing compound

liter 1850.000

91.13

168585.65

M-090

kg 2070.000

112.77

233436.07

M-180

KL

167.07

36086.74

M-189

Sealant primer

Super plastisizer admixture IS marked as per 91031999 @ 0.5 per cent by weight of cement
Cost of water

216.000

Add 1 per cent of material for cost of miscellaneous


materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

39391.91

409383.15
450321.47

Cost for 1050cum = a+b+c+d+e

4953536.17

Rate per cum = (a+b+c+d+e)/1050

4717.65
say

Note

Remarks/
Input ref.

Mate

Transit truck agitator 5 cum capacity.

c)

Cost Rs

1.The quantities for cement, coarse aggregate and fine


aggregates are for estimating only .The exact quantities will
be as per mix design.
2.IRC: 68-1976 may be referred for guidelines on the design
of cement-fly ash concrete for rigid pavement construction.
*Calculation of cement, sand and fly ash.

126

4718.00

RCD/SOR
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Cement @ 400 kg/cum = 1050 x 400 = 420 tonnes. 15 per


cent of cement to be replaced by fly ash = 63 tonnes.
Balance cement = 357 tonnes. Quantity of fly ash = 63 x
specific gravity of fly ash /specific gravity of cement = 63 x
2.25/3.15 = 45 tonnes.
Sand @ 0.45 cum / cum of concrete = 1050 x 0.45 = 472.50
x 1.6 = 756 tonnes.10 per cent to be replaced by flyash.
Balance sand = 756 x 0.9 = 680.4 tonnes = 680.4 / 1.6 =
425 cum. Quantity of flyash = (756-680.4) x specific gravity
of fly ash/specific gravity of sand = 76.4 x 2.25 / 2.687 =
63.97 tonnes (say 64 tonnes)
Fly ash Total fly ash = 45 + 64 = 109 tonnes.

127

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Sr No

Ref. to
MoRTH
Spec.

7.1

702

Description

Unit

Cost Rs

Remarks/
Input ref.

Quantity

Rate Rs

day
day
day

0.040
0.250
0.500

185.07
206.99
177.07

7.40
51.75
88.54

L-12
L-15
L-13

sqm
sqm
sqm

1.000
1.000
2.000

77.51
77.51
60.75

77.51
77.51
121.50
5.53

M-107
M-106
M-108

Sub-Surface Drain with Geotextiles


Construction of sub surface drain 200 mm dia using geotextiles
treated with carbon black with physical properties as given in
clause 702.2.3 formed in to a stable network and a planar
geocomposite structure, joints wrapped with geotextile to prevent
ingress of soil, all as per clause 702 and approved drawings
including excavation and backfilling
Unit = Running metre
Taking output = one metre
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Material
Geonets, geomembrane and geotextile to make planar
geocomposite stable network for sub surface drain including
wrapping of joints with 160 mm over lapping with geotextile .
Geonets
Geomembrane
Geotextile
Add 2 per cent cost of material for miscellaneous items like
synthetic cord
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per metre = a+b+c+d

say

42.97
47.27
519.99
520.00

0.040
0.250
0.500

185.07
206.99
177.07

7.40
51.75
88.54

L-12
L-15
L-13

1.000
1.250

65.26
60.75

65.26
75.94
2.82

M-134
M-109

Note Surplus excavated material to be used at site. Hence seprate cost


for disposal not added.
7.2

702.4

Narrow Filter Sub-Surface Drain


Construction of a narrow filter sub- surface drain consisting of
porous or perforated pipe laid in narrow trench surrounded by a
geotextile filter fabric, with a minimum of 450 mm overlap of fabric
and installed as per clause 702.3 and 309.3.5 including excavation
and backfilling
Unit = Running metre length
Taking output = one metre
a) Labour
Mate
day
Mazdoor skilled
day
Mazdoor
day
b) Material
Perforated geosynthetic pipe 150 mm dia
metre
Geotextile filter fabric
sqm
Add 2 per cent cost of material for miscellaneous item like
synthetic cord
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per metre = a+b+c+d
say
Note Surplus excavated material to be used at site. Hence Separate cost
for disposal not added.

7.3

703

Laying Paving Fabric Beneath a Pavement Overlay


Providing and laying paving fabric with physical requirements as
per table 704-2 over a tack coat of paving grade Bitumen 80-100
penetration, laid at the rate of 1 kg per sqm over thoroughly
cleaned and repaired surface to provide a water resistant
membrane and crack retarding layer. Paving fabric to be free of
wrinkling and folding and to be laid before cooling of tack coat,
brooming and rolling of surface with pneumatic roller to maximise
paving fabric contact with pavement surface

Unit = sqm
127

29.17
32.09
352.97
353.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Taking output = 2800 sqm


a) Labour
Mate
Mazdoor
b) Machinery
Road sweeper 1250 sqm per hour
Pneumatic roller 14 tonnes 2000 sqm per hour
Bitumen pressure distributor 1750 sqm per hour
c) Material
Paving Fabric
Paving Bitumen 80-100
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 2800 sqm = a+b+c+d+e
Rate per sqm =(a+b+c+d+e)/2800

Rate Rs

day
day

0.800
20.000

185.07
177.07

148.06
3541.40

L-12
L-13

hour
hour
hour

2.240
1.400
1.680

465.00
1143.72
986.04

1041.60
1601.21
1656.55

P&M-031
P&M-037
P&M-004

sqm
tonne

2940.000
2.800

60.75
51344.59

178609.66
143764.85
33036.33
36339.97
399739.63
142.76
143.00

say
7.4

704

Cost Rs

Remarks/
Input ref.

Quantity

M-133
M-075

Laying Boulder Apron in Crates of Synthetic Geogrids


Providing, preparing and laying of geogrid crated apron 1 m x 5 m,
600 mm thick including excavation and backfilling with baffles at 1
metre interval, made with geogrids having characteristics as per
clause 704.2, joining sides with connectors/ring staples, top corners
to be tie tensioned, placing of suitable cross interval ties in layers of
300 mm connecting opposite side with lateral braces and tied with
polymer braids to avoid bulging, constructed as per clause 704.3.
filled with stone with minimum size of 200 mm and specific gravity
not less than 2.65, packed with stone spalls, keyed to the
foundation recess in case of sloping ground and laid over a layer of
geotextile to prevent migration of fines, all as per clause 704 and
laid as per clause 2503.3 and approved design.

Unit = cum
Taking output = 3.00 cum
a) Labour

b)

Mate

day

0.060

185.07

11.10

L-12

Mazdoor skilled

day

0.500

206.99

103.50

L-15

Mazdoor

day

1.500

177.07

265.61

L-13

Geo grids

sqm

21.000

77.51

1627.72

M-105

Connectors/ Staples

each

50.000

#VALUE!

#VALUE!

M-085

Material

Polymer braids

metre

20.000

#VALUE!

#VALUE!

M-140

Stones with minimum size of 200 mm

cum

3.450

343.79

1186.07

M-003

Stones spall for filling voids

cum

0.450

317.10

142.70

M-008

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 3 cum = a+b+c+d

#VALUE!

Rate per cum = (a+b+c+d)/ 3

#VALUE!
say

7.5

3100

Reinforced Earth Structures


Reinforced earth Structures have four main components as under:
a)
Excavation for foundation, foundation concrete and cement
concrete grooved seating in the foundation for facing elements
(facia material).
b)

Facia material and its placement.

c)
Assembling, joining with facing elements and laying of the
reinforcing elements.
d)
Earth fill with granular material which is to be retained by the
wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
128

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

7.5

3102

Description

Unit

(i)

Assembling, joining and laying of reinforcing elements.

With reinforcing element of steel / Aluminium strips /


polymeric strips.

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = Running Metre


Taking Output = 450 m
a)

Labour
Mate

day

0.360

185.07

66.63

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mazdoor skilled

day

3.000

206.99

620.97

L-15

metre

450*1.1

480.32

237758.96

M-154

metre

450*1.1

480.32

237758.96

M-153

metre

450*1.1

237.03

117328.88

M-157

metre

450*1.1

237.03

117328.88

M-156

5.Glass reinforced polymer/fibre reinforced polymer/polymeric metre


strips
@ Any one of the above alternative may be adopted as per
approved design.

450*1.1

480.32

237758.96

M-155

b)

Material

@ Reinforcement strips 60 mm wide 5 mm thick as per clause 3102.


1.Galvanised carbon steel strips
or
2.Copper Strips
or
3.Aluminium Strips
or
4.Stainless steel strips
or

Add 10 per cent of the cost of reinforcing strip towards accessories


like tie-strips, nuts and bolts and loops/lugs for joining reinforcing
elements with the facia pannels, overlaps, heat bonding or
extension.
Type 1.Galvanised carbon steel strips
1
c) Overhead charges @ 0.1 on (a+b)
d)

23950.90

Contractor's profit @ 0.1 on (a+b+c)

23950.90

Cost of 450 m = a+b+c+d

287410.77

Rate per metre =(a+b+c+d)/450

638.69
say

Type 2.Copper Strips


2
c) Overhead charges @ 0.1 on (a+b)
d)

23950.90

Contractor's profit @ 0.1 on (a+b+c)

23950.90

Cost of 450 m = a+b+c+d

287410.77

Rate per metre =(a+b+c+d)/450

638.69
say

Type 3.Aluminium Strips


3
c) Overhead charges @ 0.1 on (a+b)
d)

639.00

11907.89

Contractor's profit @ 0.1 on (a+b+c)

11907.89

Cost of 450 m = a+b+c+d

142894.67

Rate per metre =(a+b+c+d)/450

317.54
say

Type 4.Stainless steel strips


4
c) Overhead charges @ 0.1 on (a+b)
d)

639.00

318.00

11907.89

Contractor's profit @ 0.1 on (a+b+c)

11907.89

Cost of 450 m = a+b+c+d

142894.67

Rate per metre =(a+b+c+d)/450

317.54
say

129

318.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Type 5.Glass reinforced polymer/fibre reinforced polymer/polymeric


5
strips
c) Overhead charges @ 0.1 on (a+b)
d)

Contractor's profit @ 0.1 on (a+b+c)

23950.90
287410.77

Rate per metre =(a+b+c+d)/450

638.69
say

Remarks/
Input ref.

23950.90

Cost of 450 m = a+b+c+d

7.5(i)

Cost Rs

639.00

With reinforcing elements of synthetic geogrids


Unit = sqm
Taking output = 300 sqm
a)

b)

Labour
Mate

day

0.360

185.07

66.63

L-12

Mazdoor

day

6.000

177.07

1062.42

L-13

Mazdoor skilled

day

3.000

206.99

620.97

L-15

sqm

300.000

85.89

25767.05

Material
Synthetic Geogrids as per clause 3102.8 and approved
design and specifications.
Add 10 per cent of the cost of reinforcing elements (synthetic
geogrids) for accessories like tie-strips, nuts and bolts and
loops/lugs for joining reinforcing elements with the facia
pannels, overlaps and other protective elements for synthetic
geogrids.

2576.71

c)

Overhead charges @ 0.1 on (a+b)

3009.38

d)

Contractor's profit @ 0.1 on (a+b+c)

3310.31

Cost of 300 sqm of Synthetic geogrids = a+b+c+d

36413.46

Rate per sqm = (a+b+c+d)/ 300


7.5

3104

M-181

121.38
say

121.00

(ii) Facing elements of RCC


Unit = sqm
Taking output = 75 sqm
a)

b)

Labour
Mate

day

0.180

185.07

33.31

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

Mazdoor skilled

day

1.500

206.99

310.49

L-15

hour

6.000

535.00

3210.00

P&M-013

Pre-cast RCC M-35 facing elements of size as per design and cu.m
18 cm thick for 75 sqm. (Refer Item 12.8 (H))
HYSD steel @ 5 kg / sqm (Refer Item 12.6)
tonnes

13.500

3729.00

50341.50

0.380

69327.00

26344.26

Item 12.8 (H)


Case I
Item 13.6

Machinery
Light crane with lifting capacity upto 3 tonne

c)

Material

Add 2 per cent of cost of facia pannels, for all necessary temporary
form work, scaffolding and provision of loops/lugs for lifting of
pannels and joining the reinforcing elements.

1533.72

d)

Overhead charges @ 0.1 on (a+b)

408.50

e)

Contractor's profit @ 0.1 on (a+b+d)

449.35

Cost for 75 sqm = a+b+c+d+e

83162.33

Rate per sqm = (a+b+c+d+e)/ 75

1108.83
say

Note 1.The specification and construction details to be adopted shall be


as per section 3100 of MoRTH Specification.
2.Drainage arrangement shall be made as per approved design
and drawings.
3.The quantity of filler media shall be calculated as per approved
design and specifications and shall be priced separately.The rate
for same to be adopted from chapter 15.

130

1109.00

Ref. to
MoRTH
Spec.

Sr No

Description

Unit

4.Excavation for foundation including foundation concrete and


groove in the foundation for seating of bottom most facia panel and
capping beam to be calculated as per design and priced separately.
The rates for excavation and foundation concrete shall be taken
from the chapter 12 & 13 in bridge section.
5.The earth fill to be retained is not included in this analysis. The
same is to be worked out and provided separately complete as per
clause 305.
,

6.For compaction of Earthwork, attention is invited to clause 3105.5


of MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall and will
be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as per
approved design and specifications.
9.The market rate for supply of reinforcing elements and their
accessories are to be ascertained from reputed firms in the field of
earth reinforcement.
10.The earth fill material shall be clean, free draining, granular with
high friction and low cohesion, non-corrosive, coarse grained with
not 10 per cent of particles passing 75 micron sieve, free of any
deleterious matter, chlorides, salts, acids, alkalies, mineral oil,
fungus and microbes and shall be of specified PH value.
11.Capping beam is to be priced separately as per approved
design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.
12.The cost of reinforced earth retaining wall shall include following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial pannels and their erection .
(iv) Cost of reinforcing elements including their fixing and joining
with the facial pannels.
(v) Drainage arrangement including filter media as per approved
design and drawings.
13. The compacted earth filling to be retained shall form part of
embankment.

131

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Sr No
8.1

Ref. to
MoRTH
Spec.
408

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Cast in Situ Cement Concrete M20 Kerb


Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408

A.

Unit = Running metre


Taking output = 360 metre
Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60 metres/hour
Concrete mixer 0.48/0.28 cum capacity
Water tanker6 KL capacity
c) Material
Crushed stone aggregate 20 mm nominal size 59 per
cent
Coarse sand 30 per cent
Cement 11 per cent
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360
Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate
Mason
Mazdoor
b) Machinery
Kerb casting machine @ 60 metres/hour
Concrete batching and mixing plant @ 15 cum/hr.
Water tanker6 KL capacity
Tipper 5.5 cum capacity
c) Material
Crushed stone aggregate 20 mm nominal size 59 per
cent
Coarse sand 30 per cent
Cement 11 per cent
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 360 meter = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/360

day
day
day

0.720
2.000
16.000

185.07
234.29
177.07

133.25
468.58
2833.12

L-12
L-11
L-13

hour
hour
hour

6.000
12.000
5.000

279.72
211.68
111.24

1678.32
2540.16
556.20

P&M-029
P&M-009
P&M-060

cum

21.790

862.50

18793.92

M-053

cum
tonne
KL

10.900
5.700
30.000

203.75
5789.47
167.07

M-005
M-081
M-189

say

2220.92
33000.00
5012.05
6723.65
7396.02
81356.19
225.99
226.00

day
day
day

0.120
1.000
2.000

185.07
234.29
177.07

22.21
234.29
354.14

L-12
L-11
L-13

hour
hour
hour
hour

6.000
1.600
5.000
6.000

279.72
1704.24
111.24
873.00

1678.32
2726.78
556.20
5238.00

P&M-029
P&M-003
P&M-060
P&M-048

cum

21.790

862.50

18793.92

M-053

cum
tonne
KL

10.900
5.700
30.000

203.75
5789.47
167.07

2220.92
33000.00
5012.05
6983.68
7682.05
84502.56
234.73
235.00

M-004
M-081
M-189

say
8.2

408

Cast in Situ Cement Concrete M 20 Kerb with Channel

132

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Construction of cement concrete kerb with channel with top


and bottom width 115 and 165 mm respectively, 250 mm
high in M 20 grade PCC on M10 grade foundation 150 mm
thick, kerb channel 300 mm wide, 50 mm thick in PCCM20
grade, sloped towards the kerb, kerb stone with channel laid
with kerb laying machine, foundation concrete laid manually,
all complete as per clause 408
A

Using Concrete Mixer


Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

b)

c)

Labour
Mate

day

0.720

185.07

133.25

Mason

day

2.000

234.29

468.58

L-11

Mazdoor

day

16.000

177.07

2833.12

L-13

Machinery
Kerb casting machine @ 50 metres/hour for laying kerb
and channel
Concrete mixer 0.48/0.28

hour

6.000

279.72

1678.32

P&M-029

hour

16.000

211.68

3386.88

P&M-009

Water tanker6 KL capacity

hour

6.000

111.24

667.44

P&M-060

Material
Crushed stone aggregate 20 mm nominal size 60 per
cent
Coarse sand 30 per cent

cum

36.590

862.50

31558.95

M-053

cum

18.300

203.75

3728.71

M-005

Cement 10 per cent

tonne

9.010

5789.47

52163.16

M-081

KL

36.000

167.07

6014.46

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10263.29
11289.61

Cost for 300 metre = a+b+c+d+e

124185.76

Rate per metre = (a+b+c+d+e)/300


8.2

L-12

413.95
say

414.00

Using Concrete Batching and Mixing Plant


Unit = Running metre
Taking output = 300 metre length
Cement Concrete
Cement concrete of grade M20= 17.48 cum
Cement concrete of grade M10 for base = 23.18 cum
Total Concrete = 40.66 cum
a)

b)

c)

Labour
Mate

day

0.120

185.07

22.21

Mason

day

1.000

234.29

234.29

L-11

Mazdoor

day

2.000

177.07

354.14

L-13

Machinery
Kerb casting machine @ 50 metres/hour for laying kerb
and channel
Concrete batching and mixing plant @ 15 cum/hr.

hour

6.000

279.72

1678.32

P&M-029

hour

2.700

1704.24

4601.45

P&M-003

Water tanker6 KL capacity

hour

6.000

111.24

667.44

P&M-060

Tipper of 5.5 cum capacity

hour

6.000

873.00

5238.00

P&M-048

Material
Crushed stone aggregate 20 mm nominal size 60 per
cent
Coarse sand 30 per cent

cum

36.590

862.50

31558.95

M-053

cum

18.300

203.75

3728.71

M-004

Cement 10 per cent

tonne

9.010

5789.47

52163.16

M-081

KL

36.000

167.07

6014.46

M-189

Cost of water
d)

Overhead charges @ 0.1 on (a+b+c)

10626.11

133

L-12

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

128575.95

Rate per metre = (a+b+c+d+e)/300

428.59
say

801

Remarks/ Input
ref.

11688.72

Cost for 300 meter = a+b+c+d+e

8.3

Cost
Rs

429.00

Printing New Letter and Figures of any Shade


Printing new letter and figures of any shade with synthetic
enamel paint black or any other approved colour to give an
even shade
(i)

Hindi ( Matras commas and the like not to be measured


and paid for Half letter shall be counted as half )
Details for 100 letters of 16 cm height i.e. 1600 cm
Unit = per cm height per letter
a)

b)

Labour
Mate

day

0.120

185.07

22.21

L-12

Painter

day

2.000

223.29

446.58

L-18

Mazdoor

day

1.000

177.07

177.07

L-13

Litre

0.700

138.35

96.85

M-131

Material
Paint

c)

Overhead charges @ 0.1 on (a+b)

74.27

d)

Contractor's profit @ 0.1 on (a+b+c)

81.70

Cost for 1600 cm = a+b+c+d

898.67

Rate per cm height per letter = (a+b+c+ d)/1600

0.56
say

8.3

(ii)

0.60

English and Roman


Hyphens and the like not to be measured and paid for
Detail for 100 letters of 16 cm height. i.e.1600 cm
Unit = per cm height per letter
a)

b)

Labour
Mate

day

0.070

185.07

12.95

L-12

Painter Ist class

day

1.250

223.29

279.11

L-18

Mazdoor

day

0.500

177.07

88.54

L-13

Litre

0.500

138.35

69.18

M-131

Material
Paint

c)

Overhead charges @ 0.1 on (a+b)

44.98

d)

Contractor's profit @ 0.1 on (a+b+c)

49.48

Cost for 1600 cm = a+b+c+d

544.23

Rate per cm height per letter = (a+b+c +d)/1600

0.34
say

8.4

801

0.30

Retro-Reflectorised Traffic Signs


Providing and fixing of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm
below ground level as per approved drawing
Unit = Each
Taking output = one traffic sign

a)

b)

i)

Excavation for foundation

cum

0.216

179.00

38.66

item 3.13 (1) A

ii)

Cement concrete M15 grade

cum

0.120

4128.00

495.36

Item 12.8 (A)

iii)

Painting angle iron post two coats

sqm

0.430

39.00

16.77

Item 8.9

Mate

day

0.010

185.07

1.85

L-12

Mazdoor

day

0.250

177.07

44.27

L-13

kg

19.000

46.527

884.019

Labour (For fixing at site)

Material
Mild steel angle iron 75 x 75 x 6 mm
134

M-179 /1000

Sr No

Ref. to
MoRTH
Spec.

Description

(i)
( ii )

Unit

Aluminium sheeting fixed with encapsulated lens type


reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
90 cm equilateral triangle
or
60 cm equilateral triangle

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

17.68
sqm

0.350

7902.33

2765.81

M-061

sqm

0.156

7902.33

1232.76

M-061

sqm

0.283

7902.33

2236.36

M-061

sqm

0.480

7902.33

3793.12

M-061

sqm

0.270

7902.33

2133.63

M-061

60 cm x 60 cm square
or
90 cm high octagon
Machinery

sqm

0.360

7902.33

2844.84

M-061

sqm

0.672

7902.33

5310.36

M-061

Tractor-trolley

hour

0.010

171.02

1.71

or
( iii )

60 cm circular
or

( iv )

80 mm x 60 mm rectangular

(v)

60 cm x 45 cm rectangular
or

or

(vi )
( vii )
c)
(i)

90 cm equilateral triangle
d)

Overhead charges @ 0.1 on (a+b+c)

371.53

e)

Contractor's profit @ 0.1 on (a+b+c+d)

408.69

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

5046.36
say

( ii )

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

218.23
240.05

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

3191.37
say

( iii )

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

318.59
350.45
4405.72
say

d)

Overhead charges @ 0.1 on (a+b+c)

474.26

e)

Contractor's profit @ 0.1 on (a+b+c+d)

521.69
6289.39
say

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

308.32
339.15
4281.41
say

4281.00

60 cm x 60 cm square
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

379.44
417.38

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

5141.98
say

( vii )

6289.00

60 cm x 45 cm rectangular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


(vi )

4406.00

80 mm x 60 mm rectangular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


(v)

3191.00

60 cm circular

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)


( iv )

5046.00

60 cm equilateral triangle

5142.00

90 cm high octagon
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

625.99
688.59

Rate per traffic sign = ( i+ii+iii+a+b+c+d+e)

8125.26
say

135

8125.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Note

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

1.Any one area of aluminium sheeting given at (i) to (vii) may


be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
3. The depth of foundation and quantity of cement concrete
in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas.
This is applicable to all road signs and directions boards.

8.5

Direction and Place Identification Signs upto 0.9 sqm


Size Board.

801

Providing and erecting direction and place identification


retro-reflectorised sign as per IRC:67 made of high intensity
grade sheeting vide clause 801.3, fixed over aluminium
sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 x 45 x 60
cm, 60 cm below ground level as per approved drawing
Unit = sqm
Taking output = 0.9 sqm

a)

i) Excavation for foundation

cum

0.216

179.00

38.66

Item No. 3.13

ii) Cement concrete M15 grade

cum

0.120

4128.00

495.36

Item 12.8 (A)

iii) Painting angle iron post two coats

sqm

0.430

39.00

16.77

Item 8.9

Mate

day

0.010

185.07

1.85

L-12

Mazdoor

day

0.200

177.07

35.41

L-13

kg

19.000

46.527

884.02

M-179 /1000

sqm

0.900

7902.33

7112.09

M-061

Labour (For fixing at site)

b)

Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85
metres long
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

159.92

hour

0.020

171.02

901.64

Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e


Rate per sqm (for sign having area upto 0.9 sqm) =
(I+ii+iii+a+b+c+d+e)/0.90

10468.82
11632.03
say

Note

I) Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters

8.6

801

3.42
819.67

Direction and Place Identification Signs with size more


than 0.9 sqm size Board.
Providing and erecting direction and place identification
retro- reflectorised sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area exceeding 0.9
sqm supported on a mild steel angle iron post 75 mm x 75
mm x 6 mm, 2 Nos. firmly fixed to the ground by means of
properly designed foundation with M 15 grade cement
concrete45 cm x 45 cm x 60 cm, 60 cm below ground level
as per approved drawing
Unit = sqm
Taking output = 1.50 sqm

136

11632.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

a)

b)

Unit

Quantity

Rate Rs

Excavation for foundation

cum

0.430

179.00

76.97

Item No. 3.13

ii)

Cement concrete M15 grade

cum

0.240

4128.00

990.72

Item 12.8 (A)

iii)

Painting angle iron post 2 coats

sqm

0.860

39.00

33.54

Item 8.9

Mate

day

0.010

185.07

1.85

L-12

Mazdoor

day

0.300

177.07

53.12

L-13

kg

38.000

46.527

1768.04

M-179 /1000

sqm

1.500

7902.33

11853.49

M-061

Labour (For fixing at site)

Material

Aluminium sheeting fixed with encapsulated lens type


reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.

272.43

Machinery
Tractor-trolley

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

0.020

171.02

3.42

P&M-053

1395.24
1534.76

Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e


Rate per sqm ( for sign having area more than 0.9 sqm)
= ( i+ii+iii+a+b+c+d+e)/1.50

Note

Remarks/ Input
ref.

i)

Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85


metres long, 2 nos

c)

Cost
Rs

17983.57
11989.05
say

11989.00

i) Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters

8.7

802

Overhead Signs
Providing and erecting overhead signs with a corrosion
resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans
A

Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a)

Labour
Mate

day

0.240

185.07

44.42

L-12

Blacksmith

day

2.000

234.29

468.58

L-02

Mazdoor including for handling & fixing at site.

day

4.000

177.07

708.28

L-13

tonne

1.050

46239.26

48551.23

b)

Material
Aluminium alloy/galvanised steel including 5 per cent
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
and welding consumables

485.51

Add 15 per cent on cost of material for fabrication of trusses


as per approved design
c)

7355.51

Machinery
Crane 3 tonne capacity

hour

3.000

535.00

Truck

hour

0.500

773.00

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

P&M-013

386.50

P&M-057

6556.55
72122.08
say

1605.00
5960.50

Rate per tonne = (a+b+c+d+e)


8.7

M-060

Aluminium Alloy Plate for Over Head Sign


Unit = sqm

137

72122.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Taking output = 1 sqm


a)

Labour
Mate

day

0.020

185.07

3.70

L-12

Blacksmith

day

0.100

234.29

23.43

L-02

Mazdoor

day

0.150

177.07

26.56

L-13

sqm

1.000

1580.88

1580.88

b)

Material
Aluminium alloy plate,2 mm thick, fixed with high
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
ladders, pulleys, ropes etc
c) Overhead charges @ 0.1 on (a+b)
d)

0.54
163.51

Contractor's profit @ 0.1 on (a+b+c)

179.86

Rate per sqm = (a+b+c+d)

1978.48
say

Note

M-059

1978.00

1. The cost of excavation and foundation concrete for fixing


of vertical support system to be worked out separately as
per the approved drawing/design and to be included in the
estimate.
2. Lettering and arrow marks on sign board to be provided
separately as per actual requirement. Rates for these items
have been included separately in this chapter.

8.8

803

Painting Two Coats on New Concrete Surfaces


Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a)

Labour
Mate

day

0.120

185.07

22.21

L-12

Painter

day

2.000

223.29

446.58

L-18

Mazdoor

day

1.000

177.07

177.07

L-13

Litre

6.000

138.35

830.12

M-132

b)

Material

c)

Paint conforming to requirement of clause 803.3.


Add for scaffolding @ 1 per cent of labour cost where
required
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

6.46
148.24
163.07

Cost for 40 sqm = a+b+c+d

1793.75

Rate per sqm = (a+b+c+d)/40


8.9

803

44.84
say

45.00

Painting on Steel Surfaces


Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.030

185.07

5.55

L-12

Painter

day

0.450

223.29

100.48

L-18

Mazdoor

day

0.250

177.07

44.27

L-13

Litre

1.250

138.35

172.94

M-131

Material
Paint ready mixed approved brand.
Add @ 1 per cent on cost of material for scaffolding

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1.73
32.50
35.75

Cost for 10 sqm = a+b+c+d

393.22

Rate per sqm= (a+b+c+d)/10

39.32
138

Sr No

Ref. to
MoRTH
Spec.

8.10

803

Description

Unit

Quantity

Rate Rs
say

Cost
Rs

Remarks/ Input
ref.

39.00

Painting on Wood Surfaces


Providing and applying two coats of ready mix paint of
approved brand on wood surface after thorough cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.030

185.07

5.55

L-12

Painter

day

0.500

223.29

111.65

L-18

Mazdoor

day

0.200

177.07

35.41

L-13

Litre

1.500

138.35

207.53

M-131

Material
Paint ready mixed of approved brand.
Add @ 1 per cent on cost of material for scaffolding

2.08

c)

Overhead charges @ 0.1 on (a+b)

36.22

d)

Contractor's profit @ 0.1 on (a+b+c)

39.84

Cost for 10 sqm = a+b+c+d

438.28

Rate per sqm = (a+b+c+d)/10

43.83
say

8.11

44.00

Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on New Work

803

Painting lines, dashes, arrows etc on roads in two coats on


new work with ready mixed road marking paint conforming to
IS:164 on bituminous surface, including cleaning the surface
of all dirt, dust and other foreign matter, demarcation at site
and traffic control
(i)

Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.090

185.07

16.66

L-12

Painter

day

0.550

223.29

122.81

L-18

Mazdoor

day

1.550

177.07

274.46

L-13

Litre

1.480

138.35

204.76

M-132

Material
Road marking Paint as per IS :164

c)

Overhead charges @ 0.1 on (a+b)

61.87

d)

Contractor's profit @ 0.1 on (a+b+c)

68.06

Cost for 10 sqm = a+b+c+d

748.61

Rate per sqm= (a+b+c+d)/10


8.11

(ii)

74.86
say

75.00

12.95

L-12

Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.070

185.07

Painter

day

0.350

223.29

78.15

L-18

Mazdoor

day

1.350

177.07

239.04

L-13

Litre

1.480

138.35

204.76

M-132

Material
Road marking paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

53.49
58.84

Cost for 10 sqm = a+b+c+d

647.25

Rate per sqm = (a+b+c+d)/10

64.72
say

8.12

803

Painting Lines, Dashes, Arrows etc on Roads in Two


Coats on Old Work

139

65.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Painting lines, dashes, arrows etc on roads in two coats on


old work with ready mixed road marking paint conforming to
IS: 164 on bituminous surface, including cleaning the
surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control
(i)

Over 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.060

185.07

11.10

L-12

Painter Ist class

day

0.300

223.29

66.99

L-18

Mazdoor

day

1.250

177.07

221.34

L-13

Litre

0.900

138.35

124.52

M-132

Material
Road marking paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

42.39
46.63

Cost for 10 sqm = a+b+c+d

512.98

Rate per sqm = (a+b+c+d)/10


8.12

(ii)

51.30
say

51.00

12.95

L-12

Up to 10 cm in width
Unit = sqm
Taking output = 10 sqm
a)

b)

Labour
Mate

day

0.070

185.07

Painter Ist class

day

0.350

223.29

78.15

L-18

Mazdoor

day

1.350

177.07

239.04

L-13

Litre

0.900

138.35

124.52

M-132

Material
Road marking Paint

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

45.47
50.01

Cost for 10 sqm= a+b+c+d

550.15

Rate per sqm = (a+b+c+d)/10

8.13

803

55.01
say

55.00

Road Marking with Hot Applied Thermoplastic


Compound with Reflectorising Glass Beads on
Bituminous Surface
Providing and laying of hot applied thermoplastic compound
2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform and free from streaks and holes.
Unit = sqm
Taking output = 640 sqm
a)

b)

c)

Labour
Mate

day

0.500

185.07

92.54

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

Road marking machine @ 80 sqm per hour

hour

8.000

85.86

686.88

P&M-043

Tractor-trolley

hour

8.000

171.02

1368.14

P&M-053

Litre

2000.000

127.55

255097.14

M-118

kg

200.000

70.68

14135.96

M-152

Machinery

Material
Hot applied thermoplastic compound
Reflectorising glass beads

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

27173.48
29890.83

Cost for 640 sqm = a+b+c+d+e

328799.12

140

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per sqm = a+b+c+d+e)/640

Note

8.14

Cost
Rs

Remarks/ Input
ref.

513.75
say

514.00

1. A sealing primer may be applied in advance on cement


concrete pavement to ensure proper bonding. Any laitance
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
Kilometre Stone

804

Reinforced cement concrete M15grade kilometre stone of


standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i)

5th kilometre stone (precast)


Unit = Nos.
Taking output = 6 Nos.
cum

2.350

4128.00

9700.80

Item 12.8 (A)

kg

22.080

69.327

1530.74

Item 13.6 /1000

Excavation in soil for foundation

cum

1.680

179.00

300.72

Item No. 3.13

Painting two coats on concrete surface

sqm

9.850

45.00

443.25

Item 8.8

1800.000

0.30

540.00

Item 8.3

L-12

a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)
d)

e) Lettering on km post (average 30 letters of 10


cm height each)
Transportation and fixing
f)

g)

per cm per
letter

Labour
Mate

day

0.260

185.07

48.12

Mason

day

0.600

234.29

140.57

L-11

Mazdoor including loading/unloading

day

6.000

177.07

1062.42

L-13

hour

6.000

171.02

1026.11

P&M-053

Machinery
Tractor-trolley

h)

Overhead charges @ 0.1 on (f+g)

227.72

i)

Contractor's profit @ 0.1 on (f+g+h)

250.49

Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i

15270.95

Rate for each 5th km stone = (a+b+c+d+e+f+g+h+i)/ 6


8.14

(ii)

2545.16
say

2545.00

Ordinary kilometer stone (precast)


Unit = Nos.
Taking output = 14 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

d) Painting two coats on concrete surface


e) Lettering on km post ( average 12 letters of 10
cm height each)
Transportation and fixing
f)

g)

3.770

4128.00

15562.56

Item 12.8 (A)

kg

26.320

69.327

1824.69

Item 13.6 /1000

cum

2.770

179.00

495.83

Item No. 3.13

sqm
per cm per
letter

11.410

45.00

513.45

Item 8.8

1680.000

0.30

504.00

Item 8.3

L-12

Labour
Mate

day

0.320

185.07

59.22

Mason

day

1.000

234.29

234.29

L-11

Mazdoor

day

7.000

177.07

1239.49

L-13

hour

6.000

171.02

1026.11

P&M-053

Machinery
Tractor-trolley

h)

cum

Overhead charges @ 0.1 on (f+g)

255.91

i) Contractor's profit @ 0.1 on (f+g+h)


Cost for 14 Nos. ordinary km stone = (a+b+ c+d+e+f+g+h+i)

141

281.50
21997.05

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate for each ordinary km stone = (a+b+ c+d+e+f+g+h+j)


/14
8.14

(iii)

Cost
Rs

Remarks/ Input
ref.

1571.22
say

1571.00

Hectometer stone (precast)


Unit = Nos.
Taking output = 33 Nos.
a)

M-15 grade of concrete

b)

Steel reinforcement @ 5 kg per sqm

c)

Excavation in soil for foundation

cum

1.580

4128.00

6522.24

Item 12.8 (A)

kg

66.000

69.327

4575.58

Item 13.6 /1000

cum

1.390

179.00

248.81

Item No. 3.13

6.270

45.00

282.15

Item 8.8

330.000

0.30

99.00

Item 8.3

62.92

L-12

d) Painting two coats on concrete surface


sqm
e) Lettering on km post (average 1 letter of 10 cm per cm per
height each)
letter
Transportation and fixing
f)

g)

Labour
Mate

day

0.340

185.07

Mason

day

1.500

234.29

351.44

L-11

Mazdoor

day

7.000

177.07

1239.49

L-13

hour

6.000

171.02

1026.11

P&M-053

Machinery
Tractor-trolley

h)

Overhead charges @ 0.1 on (f+g)

268.00

i) Contractor's profit @ 0.1 on (f+g+h)


Cost for 33 Nos. Hectometer stone = (a+b+c+d+e+f+ g+h+i)

294.80
14970.53

Rate for each Hectometer stone = (a+b +c +d+e+f+


g+h+i) / 33

453.65
say

Note
8.15

805

454.00

The rate for excavation, cement concrete, steel


reinforcement, painting and lettering may be taken from
respective chapters.
Road Delineators
Supplying and installation of delineators (road way
indicators, hazard markers, object markers), 80-100 cm high
above ground level, painted black and white in 15 cm wide
strips, fitted with 80 x 100 mm rectangular or 75 mm dia
circular reflectorised panels at the top, buried or pressed into
the ground and conforming toIRC-79 and the drawings.
Unit = Each
Taking output= 30 Nos.
a)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor for fixing

day

1.000

177.07

177.07

L-13

each

30.000

451.08

13532.53

b)

Material
Cost of approved type of delineators from ISI certified
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation

1353.25

c)

Overhead charges @ 0.1 on (a+b)

1507.03

d)

Contractor's profit @ 0.1 on (a+b+c)

1657.73

Cost for 30 Nos. delineators = (a+b+ c+d)

18235.00

Rate per delineators = (a+b+c+d) /30

607.83
say

Note

8.16

806

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
Boundary pillar
Reinforced cement concrete M15 grade boundary pillars of
standard design as per IRC:25-1967, fixed in position
including finishing and lettering but excluding painting
142

608.00

M-091

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Unit = Each
Taking output = 57 Nos.
a)

M-15 grade of the boundary stone

b)

Steel reinforcement

c)

Excavation in soil

d)

Lettering, each 10 cm high

cum

1.250

4128.00

5160.00

Item 12.8 (A)

kg

79.800

69.327

5532.29

Item 13.6 /1000

cum

10.720

179.00

1918.88

Item No. 3.13

0.30

684.00

Item 8.3

per letter
per cm high

2280.000

Transportation and fixing


e)

f)

Labour
Mate

day

0.570

185.07

105.49

L-12

Mazdoor

day

14.250

177.07

2523.25

L-13

hour

6.000

171.02

1026.11

P&M-053

cum

11.970

317.10

3795.69

M-008

Machinery
Tractor-trolley

g)

Material
Stone spall

h)

Overhead charges @ 0.1 on (e+f+g)

745.05

i) Contractor's profit @ 0.1 on (e+f+g+h)


Cost for 57 Nos. boundary pillar = (a+b +c+d +e+ f+g+h+i )

819.56
22310.32

Rate for each boundary pillar = (a+b+c+d+e+ f+g+h+i)/57

Note

8.17

807

391.41
say

391.00

In case of soft ground, a proper foundation may be provided


as per approved design. In case foundation is required to be
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
G.I Barbed Wire Fencing 1.2 Metre High
Providing and fixing 1.2 metres high GI barbed wire fencing
with 1.8 m angle iron posts 40 mm x 40 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 9 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a)

Labour
Mate

day

0.090

185.07

16.66

L-12

Blacksmith

day

0.250

234.29

58.57

L-02

Mazdoor

day

2.000

177.07

354.14

L-13

kg

31.420

58.68

1843.61

M-063

kg

80.500

46.527

3745.45

M-179 /1000

b)

Material
Barbed wire 335 metres length @ 9.38 kg per 100
metres
MS angle iron 40 mm x 40mm x 6 mm, 23 metres in
length @ 3.5 kg per metre
Add for GI staple binding wire, drilling holes etc. @ 2 per
cent of the cost of material
c) Painting
Applying two coats of painting on exposed surface of
angle iron posts ( Rate as per item no. 8.9)
d) Overhead charges @ 0.1 on (a+b)
e)

111.78

sqm

2.110

39.00

82.29
613.02

Contractor's profit @ 0.1 on (a+b+d)

674.32

Cost for 30 metres fencing = a+b+c+d+e

7499.84

Rate per metre = (a+b+c+d+e)/30

249.99
say

143

250.00

Item 8.9

Sr No

Ref. to
MoRTH
Spec.

Description

Note
8.18

807

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Cost of excavation for foundation and foundation concrete to


be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
G.I Barbed Wire Fencing 1.8 Metre High
Providing and fixing 1.8 metres high GI barbed wire fencing
with 2.4 m angle iron posts 50 mm x 50 mm x 6 mm placed
every 3 metres center to center founded in M15 grade
cement concrete, 0.6 metre below ground level, every 15th
post, last but one end post and corner post shall be strutted
on both sides and end post on one side only and provided
with 12 horizontal lines and 2 diagonals interwoven with
horizontal wires, fixed with GI staples, turn buckles etc
complete as per clause 807
Unit = per running metre
Taking output = 30 metres
a)

b)

Labour
Mate

day

0.120

185.07

22.21

L-12

Blacksmith

day

0.400

234.29

93.72

L-02

Mazdoor

day

2.500

177.07

442.68

L-13

kg

40.150

58.68

2355.85

M-063

kg

152.000

46.527

7072.15

M-179 /1000

d)

Material
Barbed wire 428 metres length @ 9.38 kg per 100
metres
MS angle iron 50 mm x 50 mm x 6 mm,33.8 metres in
length @ 4.5 kg per metre
Add for GI staple, binding wire, drilling holes etc. @ 2
per cent of the cost of material
Painting
Applying two coats of painting on exposed surface of
angle iron posts
Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

c)

188.56

sqm

3.960

39.00

1119.27
12466.39

Rate per metre fencing = (a+b+c +d+e)/30

415.55
say

8.19

Suggest
ive

Item 8.9

1017.52

Cost for 30 metres fencing = a+b+c+d+e

Note

154.44

416.00

Cost of excavation for foundation and foundation concrete to


be added separately in the cost estimate as per approved
design. The rate for these items may be taken from
respective chapters.
Fencing With Welded Steel Wire Fabric 75 mm x 50 mm
Providing 1.20 metre high fencing with angle iron posts 50
mm x 50 mm x 6 mm at 3 metre center to center with 0.40
metre embedded in M15 grade cement concrete, corner, end
and every 10th post to be strutted, provided with welded
steel wire fabric of 75 mm x 50 mm mesh or 75 mm x 25 mm
mesh and fixed to iron posts by flat iron 50 x 5 mm and bolts
etc. complete in all respects.
Unit = Running metre
Taking output = 30 m
a)

b)

Labour
Mate

day

0.120

185.07

22.21

L-12

Welder

day

1.000

234.29

234.29

L-02

Mazdoor

day

2.000

177.07

354.14

L-13

i) Angle iron for posts 50 x 50 x 6 mm

kg

106.000

46.527

4931.90

M-179 /1000

ii) Runner flat 50 x 5 mm


iii) Welded steel wire fabric 75x50 mm mesh @ 4
kg/sqm,4 x 30 x 1.2 + 5 per cent wastage
OR
Welded steel wire fabric 75 x 25 mm mesh @ 7.75
kg/sqm, 7.75 x 30 x 1.2 + 5 per cent wastage

kg

26.000

46.527

1209.71

M-179 /1000

#VALUE!

M-191

Material

144

kg

151.000 input

kg

293.000

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Add 2.5 per cent of cost of material for drilling holes in


angles, flats, splitting angle at bottom, nuts and bolts and
welded consumables
c)

#VALUE!

hour

0.100

171.02

17.10

P&M-053

sqm

8.000

39.00

312.00

Item 8.9

Painting
Painting two coats including priming

e)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

f)

Contractor's profit @ 0.1 on (a+b+c+e)

#VALUE!

Cost for 30 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/30

Note

Remarks/ Input
ref.

Machinery
Tractor-trolley

d)

Cost
Rs

#VALUE!
say

#VALUE!

i) Adopt any one type of welded steel wire fabric 75 x 50 mm


or 75 x 25 mm as per approved design.
ii) The item of excavation and cement concrete in foundation
shall be measured and paid separately

8.20

808

Tubular Steel Railing on Medium Weight Steel Channel


( ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in
3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2
m centre to centre, complete as per approved drawings
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x
0.6
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x
0.6 x 0.3
iii) Painting of pipe
iv) Painting of channel section 6 nos,1.8 metres
each 0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)

b)

cum

1.296

179.00

231.98

Item No. 3.13

cum

0.648

4128.00

2674.94

Item 12.8 (A)

sqm

4.710

39.00

183.69

Item 8.9

sqm

2.160

39.00

84.24

Item 8.9

Mate

day

0.010

185.07

1.85

L-12

Mazdoor

day

0.250

177.07

44.27

L-13

Plumber

day

0.010

234.29

2.34

L-02

metre

30.000

172.29

5168.67

M-175

kg

99.360

46.527

4622.96

M-179 /1000

Material

Steel pipe 50 mm external dia as per IS:1239


Medium weight steel channel (ISMC series) 100 mm x
50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels
c)

92.46

Machinery
Tractor-trolley

hour

0.040

171.02

d)

Overhead charges @ 0.1 on (a+b+c)

1311.42

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1442.57

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e

808

P&M-053

15868.24

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10

8.21

6.84

1586.82
say

1587.00

Tubular Steel Railing on Precast RCC Posts, 1.2 m High


Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x
0.6 x 0.3
145

cum

1.296

179.00

231.98

Item No. 3.13

cum

0.648

4128.00

2674.94

Item 12.8 (A)

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

iii) RCC M - 20 for pre cast posts 6 nos of 1.8


metres each
iv) Painting of pipe
a)

b)

Rate Rs
5381.00

1721.92

Item 14.1(A)

sqm

4.710

39.00

183.69

Item 8.9

Mate

day

0.014

185.07

2.59

L-12

Mazdoor

day

0.350

177.07

61.97

L-13

Plumber

day

0.010

234.29

2.34

L-02

metre

30.000

172.29

5168.67

hour

0.250

171.02

Labour

Material
M-175

Machinery

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

42.75

P&M-053

527.83
580.62

Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e

11199.32

Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10


809

Remarks/ Input
ref.

0.320

Tractor-trolley

8.22

Cost
Rs

cum

Steel pipe 50 mm dia as per IS:1239


c)

Quantity

1119.93
say

1120.00

Reinforced Cement Concrete Crash Barrier


Provision of an Reinforced cement concrete crash barrier at
the edges of the road, approaches to bridge structures and
medians, constructed with M-20 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994
as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified
Unit = Linear metre
Taking output = 10 m
(i)

a)

M 20 grade concrete
cum

3.000

4128.00

12384.00

Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

HYSD steel reinforcement including dowel bars

tonne

0.280

46059.03

12896.53

M-082

Pre-moulded asphalt filler board

sqm

0.320

708.07

226.58

M-144

M 20 grade concrete
b)

c)

Material

d)

Overhead charges @ 0.1 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

1330.76
1463.83

Cost for 10 metre = a+b+c+d+e

28486.18

Rate per metre = (a+b+c+d+e)/10

2848.62
say

Note

8.23

810
A

Item 14.1(A)

Labour

i) Excavation and backfilling are incidental to work and not to


be measured separately.
ii) Rate for RCC M 20 may be taken from chapter on super
structure.
Metal Beam Crash Barrier
Type - A, "W" : Metal Beam Crash Barrier
Providing and erecting a "W" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of channel section
150 x 75 x 5 mm, 330 mm long complete as per clause 810

146

2849.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Unit = Running metre


Taking output = 4.5 metre length
a)

b)

Labour
Mate

day

0.060

185.07

11.10

L-12

Blacksmith

day

0.500

234.29

117.15

L-02

Mazdoor

day

1.000

177.07

177.07

L-13

hour

0.100

171.02

17.10

P&M-053

kg

41.210

46.527

1917.39

M-179 /1000

kg

88.560

46.527

4120.46

M-179 /1000

kg

16.240

46.527

755.60

M-179 /1000

kg

20.000

45.42

908.43

M-130

Machinery
Tractor-trolley

c)

Material
Corrugated sheet,3 mm thick, "W" beam section
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @
16.4 kg per metre
Nuts and bolts
Add 25 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c)
e)

1925.47
994.98

Contractor's profit @ 0.1 on (a+b+c+d)

1094.48

Cost for 4.5 metre = a+b+c+d+e

12039.24

Rate per metre = (a+b+c+d+e)/4.5


8.23

2675.39
say

2675.00

11.10

L-12

Type - B, "THRIE" : Metal Beam Crash Barrier


Providing and erecting a "Thrie" metal beam crash barrier
comprising of 3 mm thick corrugated sheet metal beam rail,
85 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 2 m high with 1.15 m below ground level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a space of channel section
150 x 75 x 5 mm, 546 mm long complete as per clause 810
Unit = Running metre
Taking output = 4.5 metre length
a)

b)

Labour
Mate

day

0.060

185.07

Blacksmith

day

0.500

234.29

117.15

L-02

Mazdoor

day

1.000

177.07

177.07

L-13

hour

0.100

171.02

17.10

P&M-053

kg

72.940

37.59

2741.84

M-088

kg

98.400

46.527

4578.29

M-179 /1000

kg

26.860

46.527

1249.72

M-179 /1000

kg

30.000

45.42

1362.65

M-130

Machinery
Tractor-trolley

c)

Material
Corrugated sheet,3 mm thick, "Thrie" beam section
railing,4.5 m in length
Channel post 150 x 75 x 5 mm, 2 m long,3 Nos @ 16.4
kg per metre
Spacer 150 x 75 x 5 mm channel 0.546 m long,3 Nos

Nuts and bolts


Add 15 per cent of the cost of material for fabrication, nuts,
bolts and washers etc.)
d) Overhead charges @ 0.1 on (a+b+c)
e)

1489.88
1174.48

Contractor's profit @ 0.1 on (a+b+c+d)

1291.93

Cost for 4.5 metre = a+b+c+d+e

14211.21

Rate per metre= (a+b+c+d+e)/4.5

3158.05
say

147

3158.00

Sr No

Ref. to
MoRTH
Spec.

Description

Note

8.24

811

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

In the case of median crash barrier, 'W' metal beam or thrie


beam section should be provided on both sides of the
vertical posts fixed in the median. Extra provision for metal
beam railing and spacer is required to be made when fixed
in the median depending on approved design.
Road Traffic Signals electrically operated

Note

8.25

Unit

Suggest
ive

Since it is a ready made item commercially produced and


erected by specialised firm in the electrical and electronic
field, rate may be taken based on market enquiry from firms
specialised in this field and ISI certified for the approved
design and drawing.
Flexible Crash Barrier, Wire Rope Safety Barrier
Providing and erecting a wire rope safety barrier with vertical
posts of medium weight RS Joist (ISMB series) 100 mm x 75
mm (11.50 kg/m), 1.50 m long 0.85 m above ground and
0.65 m below ground level, split at the bottom for better grip,
embedded in M 15 grade cement concrete 450 x 450 x 450
mm, 1.50 m center to center and with 4 horizontal steel wire
rope 40 mm dia and anchored at terminal posts 15 m apart.
Terminal post to be embedded in M 15 grade cement
concrete foundation 2400 x 450 x 900 mm (depth),
strengthened by a strut of RS joist 100 x 75 mm, 2 m long
at 450 C inclination and a tie 100 x 8 mm, 1.50 m long at the
bottom, all embedded in foundation concrete as per
approved design and drawing, rate excluding excavation and
cement concrete.
Unit = Running metre
Taking output = 15 metre
a) Labour

b)

Mate

day

0.120

185.07

22.21

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

Blacksmith

day

1.000

234.29

234.29

L-02

kg

190.000

46.527

8840.19

M-179 /1000

kg

46.000

46.527

2140.26

M-179 /1000

kg

188.400

46.527

8765.75

M-179 /1000

kg

65.000

29.76

1934.34

M-177

Material
i) RS Joist 100 x 75 mm - 16.5 m @ 11.5 kg per metre

ii) Struts - 2 Nos. for terminal posts,2 m long each 2 x 2


x 11.50
iii) Tie 2 Nos. of 8 mm steel plate,1.5 sqm each for
terminal posts @ 62.80 kg/sqm (2 x 1.5)
iv) Steel wire rope 40 mm, including 7.50 per cent
extra for fixing at ends 15 x 4 x 1.075 @ 1 kg per m
Add 5 per cent of cost of material for drilling, gripping, fixing,
fabrication and welding consumables
c) Painting
Applying 2 coats of painting on exposed surface
d)

1084.03

sqm

16.500

39.00

hour

0.250

171.02

2341.80

f)

Contractor's profit @ 0.1 on (a+b+d+e)

2575.98
28979.23
1931.95
say

The items of excavations and cement concrete works will be


measured and included separately as per the approved
designs and drawings.
Anti-Glare Devices in Median

P&M-053

Overhead charges @ 0.1 on (a+b+d)

Rate per m = (a+b+c+d+e+f)/15

Suggest
ive

42.75

e)

Cost for 15 m = a+b+c+d+e+f

8.26

Item 8.9

Machinery
Tractor-trolley

Note

643.50

Plantation

148

1932.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Plantation of shrubs and plants of approved species in the


median. apart from cutting off glare from vehicle coming from
opposite direction, these plants provide a pleasant
envoirenment and are eco-friendly. The rate for this item is
available in the chapter 11 on horticulture.
B

Anti-glare screen with 25 mm steel pipe framework fixed


with circular and rectangular vanes
Providing and erecting an anti - glare screen with 25 mm dia
vertical pipes fabricated and framed in the form of panels of
one metre length and 1.75 metre height fixed with circular
vane 250 mm dia at top and rectangular vane 600 x 300 mm
at the middle, made out of steel sheet of 3 mm thickness,
end vertical pipes of the panel made larger for embedding in
foundation concrete, applying 2 coats of paint on all exposed
surfaces, all as per approved design and drawings.
Unit = Running metre
Taking output = one metre
a)

b)

Labour
Mate

day

0.004

185.07

0.74

L-12

Mazdoor

day

0.100

177.07

17.71

L-13

metre

16.000

97.11

1553.73

M-174

kg

4.320

46.527

201.00

M-179 /1000

kg

4.800

46.527

223.33

M-179 /1000

Material

i) 25 mm steel pipe
ii) MS sheet for 600 x 300 x 3 mm rectangular vane,
one number @ 24kg/sqm
iii) MS sheet for 250 mm dia circular vane 3 mm thick,4
numbers @ 24 kg/sqm
Add 5 per cent cost of material for fabrication, welding,
bending, nuts, bolts etc
c) Painting
Applying 2 coats of painting on exposed surface
d)

Overhead charges @ 0.1 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+d)

98.90

sqm

1.830

39.00

2606.82
say

8.26

Item 8.9

230.50

Rate per metre = a+b+c+d+e


Note

71.37
209.54

2607.00

The items of excavation and cement concrete as per


approved design to be measured and paid separately
Anti-glare screen with rectangular vane of MS sheet
Providing and erecting anti - glare screen with rectangular
vanes of size 750 x 500 mm made from MS sheet, 3 mm
thick and fixed on MS angle 50 x 50 x 6 mm at an angle of
450 C to the direction of flow of traffic, 1.5 m center to
center, top edge of the screen 1.75 m above ground level,
vertical post firmly embedded in M-15 cement concrete
foundation 0.60 m below ground level, applying 2 coats of
paint on exposed faces, all complete as per approved design
and drawings
Unit = Running metre
Taking output = 1.50 metre
a)

b)

Labour
Mate

day

0.004

185.07

0.74

L-12

Mazdoor

day

0.100

177.07

17.71

L-13

i) Angle iron post,50 x 50 x 6 mm, length 2.35 m

kg

10.580

46.527

492.26

M-179 /1000

ii) MS sheet 3 mm thick @ 24 kg/sqm

kg

9.000

46.527

418.75

M-179 /1000

Material

Add 5 percent of cost of material for fabrication,nuts,bolts etc


c)

Tractor-trolley
d)

45.55

Machinery
hour

Painting

149

0.100

171.02

17.10

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Applying 2 coats of painting

sqm

Quantity
0.850

Rate Rs
39.00

Overhead charges @ 0.1 on (a+b+c)

99.21

f)

Contractor's profit @ 0.1 on (a+b+c+e)

109.13

Item 8.9

822.40
say

Suggest
ive

Remarks/ Input
ref.

1233.60

Rate per metre = (a+b+c+d+e+f)/1.50

8.27

33.15

e)

Cost for 1.5 m = a+b+c+d+e+f

Note

Cost
Rs

822.00

The items of excavation and cement concrete as per


approved design to be measured and paid separately. Rate
of painting has been analaysed separately in this chapter.
Street Lighting
Providing and erecting street light mounted on a steel
circular hollow pole of standard specifications for street
lighting, 9 m high spaced 40 m apart, 1.8 m overhang on
both sides if fixed in the median and on one side if fixed on
the footpath, fitted with sodium vapour lamp and fixed firmly
in concrete foundation.
Unit = Each
Taking output = one light
a)

b)

Labour
Mate

day

0.030

185.07

5.55

L-12

Mazdoor

day

0.500

177.07

88.54

L-13

Electrician

day

0.250

234.29

58.57

L-02

#VALUE!

#VALUE!

M-171

each

1.000

each

1.000

679.79

679.79

M-168

Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 9 m height above road
level

ii) Sodium vapour lamp


Add 5 per cent of cost of material for holder, electric cable,
insulation, ladder, scaffolding etc
c) Painting

(i)

For Fixing in Median


Providing two coats of alluminium paint over steel
circular hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel
circular hollow pipe with overhang on one side
For Fixing in Median

#VALUE!

sqm

5.750

39.00

224.25

Item 8.9

sqm

4.630

39.00

180.57

Item 8.9

d)

Overhead charges @ 0.1 on (a+b)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+d)

#VALUE!

Rate per light for fixing in Median= a+b+c+d+e

#VALUE!
say

(ii)

For fixing in Footpath


Rate per light for Fixing in Footpath = a+b+c+d+e

#VALUE!
say

Note

8.28

Suggest
ive

#VALUE!

#VALUE!

The items of excavation and cement concrete foundation will


be measured and included separately in the estimate as per
approved design and drawing. The rate for painting has
been analysed in this chapter.
Lighting on Bridges
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and
fitted with sodium vapour lamp
Unit = Each
Taking output = one light
a)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor

day

0.400

177.07

70.83

L-13

150

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Electrician
b)

day

0.200

each

1.000

each

1.000

Rate Rs

ii) Sodium vapour lamp 70 watt


Add 1 per cent of cost of material for holder, electric cable,
insulation, ladder, scaffolding etc
c) Painting
Providing two coats of alluminium paint over steel
circular hollow pipe
d) Overhead charges @ 0.1 on (a+b)

8.29

Suggest
ive

Remarks/ Input
ref.

234.29

46.86

#VALUE!

#VALUE!

M-170

679.79

679.79

M-168

L-02

#VALUE!

sqm

2.760

39.00

107.64

Item 8.9

#VALUE!

Contractor's profit @ 0.1 on (a+b+d)

#VALUE!

Rate per light = a+b+c+d+e

Note

Cost
Rs

Material
i) Steel circular hollow pole of standard specification for
street lighting to mount light at 5 m above deck level

e)

Quantity

#VALUE!
say

#VALUE!

2879.00

6794.44

The items of cement concrete to be measured and paid


separately as per approved design. The rate for painting has
already been analysed in this chapter.
Cable Duct Across the Road
Providing and laying of a reinforced cement concrete pipe
duct, 300 mm dia, across the road (new construction),
extending from drain to drain in cuts and toe of slope to toe
of slope in fills, constructing head walls at both ends,
providing a minimum fill of granular material over top and
sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m
thick layer of granular material free of rock pieces, outer to
outer distance of pipe at least half dia of pipe subject to
minimum 450 mm in case of double and triple row ducts,
joints to be made leak proof, invert level of duct to be above
higher than ground level to prevent entry of water and dirt,
all as per IRC: 98 - 1997 and approved drawings.

Case(i) Single row for one utility service


Unit = Running metre
Taking output = 20metres
a) Random Rubble masonry/Brick masonry in
cement mortar 1:6 for head wall both side
b) Labour

c)

d)

2.360

Mate

day

0.050

185.07

9.25

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

Mazdoor skilled

day

0.250

206.99

51.75

L-15

Reinforced Cement Concrete pipe 300 mm dia


Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 20 m)
Collar for joints 300 mm dia

metre

20.000

924.00

18480.00

M-151

153.00

1101.60

M-009

Cement mortar 1:2 for joints

Material

cum

7.200

each

9.000 input

cum

0.020

4247.00

hour

0.500

171.02

#VALUE!

M-083

84.94

Item 12.6 (B)

85.51

P&M-053

Machinery
Tractor-trolley

e)

Overhead charges @ 0.1 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 20 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/20


8.29

Item 12.7 ( B)

cum

#VALUE!
say

#VALUE!

Case(ii) Double row for two utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement
mortar 1:6 for head wall both sides.
b) Labour
Mate
151

cum

3.370

2879.00

9702.23

day

0.050

185.07

9.25

Item 12.7 ( B)

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Cost
Rs

Remarks/ Input
ref.

day

2.000

177.07

354.14

L-13

Mazdoor skilled

day

0.250

206.99

51.75

L-15

metre

40.000

924.00

36960.00

M-151

153.00

2203.20

M-009

Material
Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 40 m)

cum

14.400

Collar for joints 300 mm dia

each

18.000 input

#VALUE!

M-083

Cement mortar 1:2 for joints

cum

0.040

4247.00

169.88

Item 12.6 (B)

hour

1.000

171.02

171.02

P&M-053

Machinery
Tractor-trolley

8.29

Rate Rs

Mazdoor

Reinforced Cement Concrete pipe 300 mm dia

d)

Quantity

e)

Overhead charges @ 0.1 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 20 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/20

#VALUE!
say

#VALUE!

2879.00

12610.02

Case(iii) Triple rRow for three utility services


Unit = Running metre
Taking output = 20metres
a) Random Rubble brick/Brick masonry in cement
mortar 1:6 for head wall both sides.
b) Labour

c)

d)

4.380

Mate

day

0.160

185.07

29.61

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

Mazdoor skilled

day

1.000

206.99

206.99

L-15

Reinforced Cement Concrete pipe 300 mm dia


Granular soil with PI less than 6 for bedding and sides
of pipe (0.6 x 0.6 x 60 m)
Collar for joints 300 mm dia

metre

60.000

924.00

55440.00

M-151

cum

21.600

153.00

3304.80

M-009

each

27.000 input

#VALUE!

M-083

Cement mortar 1:2 for joints

cum

0.060

4247.00

254.82

Item 12.6 (B)

hour

1.500

171.02

256.53

P&M-053

Material

Machinery
Tractor-trolley

e)

Overhead charges @ 0.1 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 20 metre = a+b+c+d+e+f

#VALUE!

Rate per metre = (a+b+c+d+e+f)/20

#VALUE!
say

Note

8.30

Suggest
ive

Item 12.7 ( B)

cum

1.Inspection chamber at both ends is the responsibility of the


agency who is laying the duct. Hence not included.
2.The rates for stone masonry / brick masonry and cement
mortar to be adopted from respective clauses.
Highway Patrolling and Traffic Aid Post
It is proposed to locate one Traffic Aid Post every 50-60 km
of the highway.
The organisation and financial aspect are required to be
finalised in consultation with administrative and traffic
authorities .

152

#VALUE!

Sr No
8.31

Ref. to
MoRTH
Spec.
Suggest
ive

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Items Related to Underpass/ Subway/ Overhead Bridge/


Overhead Foot Bridge
The items involved for underpass/ subway/ overhead bridge/
overhead foot bridge are earthwork, plain cement concrete,
plastering, painting, information sign etc. The rates for these
items are available in respective chapters which can be
adopted for the quantities derived from the approved
designs and drawings

8.32

Suggest
ive

Traffic Control System and Communication System


Providing a traffic control centre and communication system
including telecommunication facilities and related
accessories, CCTV, radar, vehicle detection camera, central
computer system
These are specialised item of telecommunication system
and are the commercial products. The designer is required
to contact the manufacturers to ascertain market prices. In
case of civil works required to be executed for these
installations, pricing may be done as per rates in relevant
chapters for quantities derived as per approved design and
drawing.
As regards the locations where such devices are required to
be installed, the traffic control authority should be consulted
to finalise the location

8.33

Suggest
ive

Gantry Mounted Variable Message Sign Board


Providing and erecting gantry mounted variable message
sign board electronically operated capable of flashing the
desired message over a designed support system of
aluminium alloy or galvanised steel, erected as per approved
design and drawings and with lateral clearance as per
clause 802.3
(i)

Gantry Support System


Unit = tonne
Taking output=1 tonne
a)

b)

c)

Labour
Mate

day

0.120

185.07

22.21

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

Blacksmith

day

1.000

234.29

234.29

L-02

tonne

1.050

46239.26

48551.23

Material
Alluminium alloy/galvanised steel including 5 per cent
wastage
Add 15 per cent of cost of material for fabrication and
erection.
Add 1 per cent of cost of material for nuts, bolts and
welding
Machinery
Truck 10 tonne

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7282.68
485.51

hour

1.000

773.00

6347.34
69820.70
say

(ii)

773.00
5770.31

Rate per tonne = a+b+c+d+e


8.33

Message Display
Message display board 6 sqm electronically operated with
complete electronic fitments for flashing the pre-determined
messages.
This is a specilised commercial product and the lumpsum
rate including erection at site is required to be as certained
from the market and including in the rate analysis. The size
of the board will vary depending upon specific location.

153

M-060

69821.00

P&M-057

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

The rate for the gantry mounted variable sign would be the
addition of cost of gantry support system as per approved
design determined at (i) above and the cost of message
display board as certained from the market at (ii) above

154

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Sr No
8.34

Ref. to
MoRTH
Spec.
Suggest
ive

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Traffic Impact Attenuators at Abutments and Piers


A

With Scrap Tyres


Provision and installation of traffic attenuators at
abutment/pier of flyovers bridges using scrap tyres of size
100 x 20 retrieved from trucks laid in 2 rows and 4 tiers, one
above the other and tied with 20 mm wire rope as per
approved design and drawings.
Unit = sqm
Taking output = 20sqm
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

1.500

177.07

265.61

L-13

Blacksmith

day

0.250

234.29

58.57

L-02

each

80.000

59.20

4736.38

M-161

kg

150.000

29.76

4463.85

M-176

Material
Scrap tyres of size 900 x 20
20 mm steel wire rope

Add 1 per cent of cost of wire rope for clamps etc.


c)

44.64

Machinery
Tractor-trolley

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3.000

171.02

1110.66
12217.27

Rate per sqm = (a+b+c+d+e)/20


B

P&M-053

1009.69

Cost for 20 sqm = a+b+c+d+e

8.34

513.05

610.86
say

611.00

Using Plastic/Steel Barrel, Filled with Sand


Provision and installation of traffic impact attenuator at
abutment/pier of flyovers bridges using plastic/steel barrels
0.60 m dia and 1.0 m in height, filled with sand in three rows
and tied with20 mm steel wire rope as per approved design
and drawings
Unit = sqm
Taking output = 20sqm
a)

b)

Labour
Mate

day

0.130

185.07

24.06

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

Blacksmith

day

0.250

234.29

58.57

L-02

each

50.000

Steel barrels

each

50.000

90.84

4542.17

M-172

Sand

cum

8.000

203.75

1630.04

M-004

kg

15.000

29.76

446.39

M-176

Material
Plastic barrels
or

20 mm steel wire rope


Add 1 per cent of cost of wire rope for clamps etc.
c)

4.46

Machinery
Tractor-trolley

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.000

171.02

757.89
833.68

Cost for 20 sqm = a+b+c+d+e

9170.50

Rate per sqm = (a+b+c+d+e)/20

458.53
say

8.34

342.04

With HI - DRO cell Sandwich (Patented)


(In this patented HI - DRO cell system, water gets
discharged from plastic tubes on impact over a predetermined time, thus absorbing the energy)

155

459.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Providing and installing a patentend HI - DRO cell system as


a traffic impact attenuators, using plastic tubes 50 cm dia,
1.2 m in height, 25 mm opening at the top, placed in three
rows, filled with water and tied with a 20 mm steel wire rope
Unit = sqm
Taking output = 10sqm
a)

b)

Labour
Mate

day

0.100

185.07

18.51

L-12

Mazdoor

day

2.500

177.07

442.68

L-13

each

40.000

#VALUE!

M-139

Material
Plastic tubes 50 cm dia,1.2 m high

#VALUE!

Cost of water

KL

12.000

167.07

2004.82

M-189

20 mm steel wire rope

kg

100.000

29.76

2975.90

M-176

Add 1 per cent of cost of wire rope for clamps etc.


c)

29.76

Machinery
Tractor-trolley

hour

2.000

171.02

342.04

P&M-053

Water tanker6 KL capacity

hour

2.000

111.24

222.48

P&M-060

d)

Overhead charges @ 0.1 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 10 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/10

#VALUE!
say

8.35

Suggest
ive

#VALUE!

Road Markers/Road Stud with Lense Reflector


Road Markers/Road Stud with plastic body of
RPM/ASA/HIPS as per clause 804.2.1 of MORTH,
fitted with lense reflectors, installed in concrete
or asphaltic surface by drilling hole 30 mm upto
a depth of 60 mm and bedded in a suitable
bituminous grout or epoxy mortar, all as per BS
873 part 4:1973)

Unit = Nos
Taking output = 50Nos
a)

b)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

each

50.000

167.01

8350.30

M-062

Material
plastic body of RPM/ASA/HIPS 100 x 100 mm fitted
with lense reflectors

Add 10 per cent of cost of material for fixing and installation


c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

835.03
936.98
1030.68

Cost for 50 studs = a+b+c+d

11337.46

Rate per studs = (a+b+c+d)/50


8.36

Suggest
ive

226.75
say

227.00

Traffic Cone
Provision of red fluorescent with white reflective sleeve traffic
cone made of low density polyethylene (LDPE)
material
with a square base of 390 x 390 x 35 mm and a height of
770 mm, 4 kg in weight, placed at 1.5 m interval, all as per
BS 873
Unit = Running metre
Taking output = 68 Nos.
a)

b)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor

day

0.500

177.07

88.54

L-13

each

68.000

394.70

26839.51

Material
Traffic cones with 150 mm reflective sleeve
156

M-186

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Unit

Quantity

Rate Rs

hour

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

0.100

171.02

2964.37
32608.11

Rate per metre = (a+b+c+d+e)/68

479.53
say

Roadside Amenities
A

Rest areas
Providing plainly furnished accommodation for rest rooms,
dormitories, restaurants, stalls, shops, petrol pump,
telephone booth, first aid room, traffic aid post, police
assistance booth, including electricity, toilet and sewerage
system
Pricing may be done based on current plinth area rates
approved by PWD/CPWD/MES for a particular zone. Area is
required to be assessed for specific location as per actual
site conditions

Parking areas and bus laybyes for trucks, buses and


light vehicles
Pricing of parking areas may be done for the quantities of
various items based on the approved dimensions and
pavement design for a particular terrain and soil. Rates for
items may be from respective chapters.
Lawn
Providing a lawn planted with grass and its maintenance
Pricing of lawn may be done as per rates given in the
chapter on horticulture for the quantities as per approved
dimensions in the drawings

8.38

Suggest
ive

Rumble Strips
Provision of 15 nos rumble strips covered with premix
bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking
paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings

8.39

Suggest
ive

Policeman Umbrella
Provision of a 2 m high (floor to roof) umbrella for traffic
policeman at road crossings, where necessary, installed on a
raised platform, built on a central support of a steel pipe 100
mm dia, roof made of 25 mm dia steel pipe to provide
covered area of 3 sqm, roofed with CGI sheets, all steel
parts to be given 2 coats of paint
Unit = each
Taking output = one number
Earthwork
Cement Concrete
brick masonry or

Quantities of these items to be


calculated as per approved design and
cost added as per rates of these items
given in chapter 3 and 13

stone masonry

cum
cum
cum
cum

Painting
a)

17.10
2694.88

Cost for 68 Nos. = a+b+c+d+e

8.37

Remarks/ Input
ref.

Machinery
Tractor-trolley

Suggest
ive

Cost
Rs

sqm

2.500

Mate

day

0.090

Mazdoor

day

1.000

Blacksmith

day

1.000

Welder

day

0.250

Labour

157

480.00

P&M-053

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity

Material
Steel pipe 100 mm dia

metre

3.500

Steel pipe 25 mm dia

metre

10.000

kg

8.000

hour

0.500

CGI sheets
Add 25 per cent of cost of material for fabrication
Add 2 per cent of cost of material for welding consumables,
J-hooks, washers etc.
c) Machinery
Tractor-trolley
d)

Overheads @ per cent on (a+b+c)

e)

Contractors Profit@ per cent on (a+b+c+d)

Rate per policeman umbrella = a+b+c+d+e


8.40

suggesti
ve

High Mast Pole Lighting at Interchanges and Flyovers


Providing and erecting a high mast pole lighting with 30 m
high hot dip galvanised mast designed to withstand forces
exerted with wind speeds of 180 km per hour with 3 seconds
gust, as per IS:875 (Part 3) - 1978, fitted with a base flange,
door at the base of mast with heavy duty internal lock,
lantern carriage, suitable winching arrangement for safe
working load of 750 kg and high powered electrically driven
power tools for raising and lowering of lantern carriage,
flexible 8 core electric cable, lightening conductor, earthing
terminal, and fixing 2 nos aviation obstruction lights on top of
the mast, all complete as per approved design and drawings
This is a specialised work and is generally done by firms
who specialise in such jobs. The detailed designs and
estimates are submitted by the firms along with their tender
for checks by the Department. The cost of this work is
required to be worked out based on approved design,
drawings and estimate of the lowest tender. A separate
contract for this work is concluded as the contractors for
road and bridge works generally donot undertake such jobs.

8.41

Toll Plaza
The construction, operation and maintenance of Toll Plaza
can be broken into separate items of work as under based
on the approved design and drawings:a)
Provision of toll collection service lane to separate
different categories of vehicles for purpose of toll collection.
This involves considerable increase in carriage way width
b)
Provision of 2.5 m wide separators for different toll
collection service lanes for safety
c) Toll booths with integrated roof cover
d) Barrier gates for individual lanes
e)
Provision of building to provide facility to toll plaza
personnel
f) Toll plaza office equipment and furniture
g)
Water supply, electricity, sanitation, septic-tank system
and drainage
h)
Telephone, intercomes, wireless communication
system
i) High mast lighting
j) Pavement marking
k) Overhead signs
l) Fixed message signs (Advance)
m) Variable message signs
n) Traffic cones and pylons
o) First aid post
p) Traffic aid post and security

158

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

The quantities for the above mentioned items may be


calculated from the approved design and drawings and their
rates adopted from respective chapters of the Standard Data
Book
8.42

Safety Devices and Signs in Construction Zones


Provision and fixing of traffic signs for limited period at
suitable locations in construction zone comprising of warning
zone, approach transition zone, working zone and terminal
transition zone with a minimum distance of 60 cm from the
edge of the kerb in case of kerbed roads and 2 to 3 m from
the edge of the carriageway in case of un-kerbed roads, the
bottom edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 60 mm x 60 mm x 6 mm angle
iron post, founded and installed as per approved design and
drawings, removed and disposed of after completion of
construction work, all as per IRC:SP:55-2001
Unit = each
Taking output = one sign post
Following types of signs are required to be fixed in
construction zones for safety of traffic
a) Diversion one km ahead
b)

Traffic sign ahead

c)

Road ahead closed

d)

Men at work

e)

Road narrow

f)

Single file traffic

g)

Right lane diverted

h)

Left lane diverted

i)

Right lane closed

j) Left lane closed


k) Median closed
l) Diversion to other carriageway
m) Traffic signal ahead
n) Two way traffic
o) Un - even road
p) Slippery road
q) Loose chippings
r) Dual carriageway ends
s) Diversion
t) Do not enter
u) Road closed
v) Stop
w) Slow
x) One way
y) Give way
z)

Overtaking prohibited

aa)

Speed limit

bb)

Weight limit

cc)

Height and length limit

dd)

No stopping or standing

ee)
Any other warning or regulatory safety sign as per
site requirement and consistent with IRC:SP:55-2001 and
IRC:67
The rate for traffic signs are already worked out and given
elsewhere in this chapter. The same may be adopted.
8.43

suggesti
ve

Portable Barricade in Construction Zone

159

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Installation of a steel portable barricade with horizontal rail


300 mm wide, 2.5 m in length fitted on a 'A' frame made with
45 x 45 x 5 mm angle iron section, 1.5 m in height,
horizontal rail painted (2 coats) with yellow and white stripes,
150 mm in width at an angle of 450 C, 'A' frame painted with
2 coats of yellow paint, complete as per IRC:SP:55-2001
Unit = each
Taking output = one steel portable barricade
a)

b)

Labour
Mate

day

0.020

185.07

Mazdoor

day

0.250

Painter

day

0.500

Welder

day

L-12

177.07

44.27

L-13

223.29

111.65

L-18

0.250

234.29

58.57

L-02

kg

25.000

46.527

1163.18

M-179 /1000

kg

15.000

46.527

697.91

M-179 /1000

litre

0.500

138.35

69.18

M-131

Material
Angle iron 45 x 45 x 5 mm
MS sheet 300 mm wide,2.5 m long and 2.6 mm thick

Paint
Add 2 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b)
d)

3.70

37.22
218.57

Contractor's profit @ 0.1 on (a+b+c)

240.42

Rate per barricade = a+b+c+d

2644.67
say

8.44

suggesti
ve

2645.00

Permanent Type Barricade in Construction Zone


A

With steel components


Construction of a permanent type barricade made of steel
components, 1.5 m high from road level, fitted with 3
horizontal rails 200 mm wide and 4 m long on 50 x 50 x 5
mm angle iron vertical support, painted with yellow and white
strips, 150 mm in width at an angle of 45 0 C, complete as
per IRC:SP:55-2001
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.050

185.07

9.25

L-12

Mazdoor

day

0.300

177.07

53.12

L-13

Painter

day

0.600

223.29

133.97

L-18

Welder

day

0.300

234.29

70.29

L-02

kg

15.000

46.527

697.91

M-179 /1000

kg

50.000

46.527

2326.37

M-179 /1000

litre

1.000

138.35

138.35

M-131

Material
Angle iron 50 x 50 x 5 mm,2 m long,2 Nos.

MS sheet of 12 SWG,3 Nos of 200 mm width and 4 m


length
Paint
Add 1 per cent of cost of steel for welding consumables,
nuts & bolts and drilling holes
c) Overhead charges @ 0.1 on (a+b)
d)

30.24
345.95

Contractor's profit @ 0.1 on (a+b+c)

380.55

Rate per barricade = a+b+c+d

4186.01
say

8.44

With wooden components


Construction of a permanent type barricade made of wooden
components, 1.5 m high from road level, fitted with 3
horizontal planks 200 mm wide and 3.66 m long on 100 x
100mm wooden vertical post, painted with yellow and white
strips, 150 mm in width at an angle of 45 0 C, complete as
per IRC:SP:55-2001
Unit = each
160

4186.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Taking output = one barricade


a)

b)

Labour
Mate

day

0.050

185.07

9.25

L-12

Mazdoor

day

0.300

Painter

day

0.600

177.07

53.12

L-13

223.29

133.97

Carpenter

day

L-18

0.600

234.29

140.57

L-04

cum

0.180

31666.24

5699.92

M-185

Material
Timber

Add 1 per cent of cost of timber for nuts & bolts, nails, etc.

57.00

c)

Overhead charges @ 0.1 on (a+b)

609.38

d)

Contractor's profit @ 0.1 on (a+b+c)

670.32

Rate per barricade = a+b+c+d

7373.55
say

8.44

7374.00

With bricks
Construction of a permanent type barricade made with brick
work in mud mortar, 1.5 m high, 4 m long, 600 mm thick,
plastered with cement mortar 1:6, painted with yellow and
white strips
Unit = each
Taking output = one barricade
a)

b)

Labour
Mate

day

0.240

185.07

44.42

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

Painter

day

1.000

223.29

223.29

L-18

Mason

day

2.000

234.29

468.58

L-11

each

Material
1800.000

4.33

7791.43

M-079

kg

22.000

5.789

127.37

M-081 /1000

Sand

cum

0.090

203.75

18.34

M-005

Paint

litre

1.250

138.35

172.94

M-131

Brick
Cement

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

937.76
1031.53

Rate per barricade = a+b+c+d

11346.86
say

8.45

suggesti
ve

11347.00

Drum Delineator in Construction Zone


Provision of metal drum/empty bitumen drum delineator, 300
mm in diameter, 800 mm high, filled with earth for stability,
painted in circumferential strips of alternate black and white
100 mm wide fitted with reflectors 3 Nos of 7.5 cm dia, all as
per IRC:SP:55-2001
Unit = each
Taking output = one drum delineator
a)

b)

Labour
Mate

day

0.020

185.07

3.70

L-12

Mazdoor

day

0.250

177.07

44.27

L-13

Painter

day

0.250

223.29

55.82

L-18

Material
Steel drum 300 mm dia 1.2 m high/empty bitumen
drum
Paint

each

1.000

90.84

90.84

M-172

litre

0.500

138.35

69.18

M-131

c)

Overhead charges @ 0.1 on (a+b)

26.38

d)

Contractor's profit @ 0.1 on (a+b+c)

29.02

Rate per drum delineator = a+b+c+d

319.21
say

8.46

suggesti
ve

Flagman

161

319.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost
Rs

Remarks/ Input
ref.

Positioning of a smart flagman with a yellow vest and a


yellow cap and a red flag 600 x 600 mm securely fastened to
a staff 1 m in length for guiding the traffic
Unit = each
Taking output = one flagman
a)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

each

1.000

34.46

34.46

M-099

each

1.000

22.52

22.52

M-196

b)

Material

c)

Flag of red color cloth 600 x 600 mm


Wooden staff for fastening of flag 25 mm dia, one m
long
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

24.15
26.56

Rate per flagman = a+b+c+d

292.16
say

162

292.00

CHAPTER-9
PIPE CULVERTS
Sr No

Ref. to
MoRTH
Spec.

9.1

408

Description

Unit

Cost Rs

Remarks/
Input ref.

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate
Mason
Mazdoor
b) Material
40mm Aggregate at site
Sand at site
Cement at site
Cost of water
c) Machinery
Concrete mixer0.4/ 0.28 cum
Generator set 33 KVA
Water tanker6 KL capacity
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Note

9.2

Quantity Rate Rs

2900

day
day
day

0.640
1.000
15.000

185.07
234.29
177.07

118.44
234.29
2656.05

L-12
L-11
L-13

cum
cum
tonne
KL

13.800
6.900
3.300
18.000

758.35
203.75
5789.47
167.07

10465.29
1405.91
19105.26
3007.23

M-055
M-005
M-081
M-189

hour
hour
hour

6.000
6.000
3.000

211.68
342.36
111.24

P&M-009
P&M-079
P&M-060

say

1270.08
2054.16
333.72
4065.04
4471.55
49187.02
3279.13
3279.00

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .

Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
1000 mm dia
a)

Labour
Mate
Mason
Mazdoor
b) Material
Sand at site
Cement at site
RCC pipe NP-4 /prestressed concrete pipe including
collar at site
Granular material passing 5.6 mm sieve for bedding
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre = (a+b+c+d)/12.5

day
day
day

0.180
0.500
4.000

185.07
234.29
177.07

33.31
117.15
708.28

cum
tonne
metre

0.070
0.050
12.500

203.75
5789.47
4395.60

14.26
289.47
54945.00

M-005
M-081
M-149

cum

4.500

153.00

688.50
5679.60
6247.56
68723.13
5497.85
5498.00

M-009

say
Note

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.2

1200 mm dia
a) Labour
162

L-12
L-11
L-13

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Mate
Mason
Mazdoor
b) Material
Sand at site
Cement at site
RCC pipe NP-4/prestressed concrete pipe including
collar at site
Granular material passing 5-6 mm sieve for class
bedding
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 12.5 metres = a+b+c+d
Rate per metre= (a+b+c+d)/12.5
Note

9.3

2900

Quantity Rate Rs

Cost Rs

Remarks/
Input ref.

day
day
day

0.280
1.000
6.000

185.07
234.29
177.07

51.82
234.29
1062.42

L-12
L-11
L-13

cum
tonne
metre

0.090
0.070
12.500

203.75
5789.47
5319.60

18.34
405.26
66495.00

M-005
M-081
M-150

cum

5.000

153.00

765.00

M-009

say

6903.21
7593.53
83528.88
6682.31
6682.00

66.63

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete and masonry works in head walls and
parapets .
Unit = metre

Taking output = 12.5 metres ( 10 pipes of 2.5 m length


each in two rows.)
1000 mm dia
a)

b)

Labour
Mate

day

0.360

185.07

Mason

day

1.000

234.29

234.29

L-11

Mazdoor

day

8.000

177.07

1416.56

L-13

cum

0.140

203.75

28.53

M-005

Material
Sand at site
Cement at site

tonne

0.100

5789.47

578.95

M-081

RCC pipe NP-4/prestressed concrete pipe including


collar at site
Granular material passing 5.6 mm sieve for bedding

metre

25.000

4395.60

109890.00

M-149

cum

12.500

153.00

1912.50

M-009

c)

Overhead charges @ 0.1 on (a+b)

11412.74

d)

Contractor's profit @ 0.1 on (a+b+c)

12554.02

Cost for 12.5 metres = a+b+c+d

138094.21

Rate per metre = (a+b+c+d)/12.5


Note

L-12

11047.54

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .

say

11048.00

0.560

185.07

103.64

2. The rate analysis does not include excavation, cement


/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3

1200 mm dia
a)

Labour
Mate

day

Mason

day

2.000

234.29

468.58

L-11

Mazdoor

day

12.000

177.07

2124.84

L-13

163

L-12

Sr No

Ref. to
MoRTH
Spec.

Description
b)

Unit

Quantity Rate Rs

Remarks/
Input ref.

Material
Sand at site

cum

0.180

203.75

36.68

M-005

Cement at site

tonne

0.140

5789.47

810.53

M-081

metre

25.000

5319.60

132990.00

M-150

cum

13.750

153.00

2103.75

M-009

c)

RCC pipe NP-4 /prestressed concrete pipe including


collar at site
Granular material passing 5-6 mm sieve for class
bedding
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13863.80
15250.18

Cost for 12.5 metres = a+b+c+d

167751.99

Rate per metre= (a+b+c+d)/12.5


Note

Cost Rs

13420.16

1. In case of cement craddle bedding, quantity of PCC M15


is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

164

say

13420.00

CHAPTER- 10
MAINTENANCE OF ROADS
Sr No

Ref. to
MoRTH
Spec.

10.1

3002

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Restoration of Rain Cuts


Restoration of rain cuts with soil, moorum, gravel or a
mixture of these, clearing the loose soil, benching for 300
mm width, laying fresh material in layers not exceeding 250
mm and compacting with plate compactor or power rammers
to restore the original alignment, levels and slopes
Unit = cum
Taking output = 10 cum
a) Labour
Mate
Mazdoor
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour
Tipper ( L is average lead in km for borrow earth)

day
day

0.080
2.000

185.07
177.07

14.81
354.14

L-12
L-13

197.12

P&M-026

hour

0.130

1516.32

tonne.km

12 x L

2.27

hour

0.500

142.99

Add 10 per cent of cost of carriage towards loading and


unloading charges.
Plate compactor
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 cum = a+b+c+d
Rate per cum = (a+b+c+d)/10
Note

10.2

3003

27.22 Lead =1 km &


P&M-058
2.72
P&M-086

say

71.50
66.75
73.43
807.68
80.77
81.00

Only 75 per cent of fresh material has been provided as 25


per cent can be retrieved at site from earth that is flown
down the slope in the form of slurry and deposited at the foot
of the rain cuts
Maintenance of Earthen Shoulder (filling with fresh soil)
Making up loss of material/ irregularities on shoulder to the
design level by adding fresh approved soil and compacting it
with appropriate equipment.
Unit = sqm
Taking output = 100 sqm
Assuming average thickness of filling to be 150 mm
Quantity of fresh material = 15 cum
a) Labour
Mate
Mazdoor
b) Machinery
Excavator1.0 cum bucket capacity @ 60 cum per hour
Tipper ( L is average lead in km for borrow earth)
Add 10 per cent of cost of transportation to cover cost of
loading and unloading
Plate compactor @ 25 sqm per hour
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 100 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)100

10.3

3003

day
day

0.180
4.500

185.07
177.07

33.31
796.82

L-12
L-13

hour

0.250

1516.32

379.08

P&M-026

tonne.km

24xL

2.27

54.43 Lead =1 km &


P&M-058
5.44

hour

12.000

142.99

P&M-086

say

1715.90
298.50
328.35
3611.83
36.12
36.00

185.07
177.07

18.51
442.68

L-12
L-13

Maintenance of Earth Shoulder (stripping excess soil)


Stripping excess soil from the shoulder surface to achieve
the approved level and compacting with plate compactor
Unit = sqm
Taking output = 100 sqm
Assuming average depth of stripping as 75 mm
Quantity of earth cutting involved = 7.5 cum
a) Labour
Mate
Mazdoor
b) Machinery

day
day

165

0.100
2.500

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Plate compactor @ 25 sqm per hour


c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 100 sqm = a+b+c+d
Rate per sqm on = (a+b+c+d)100

hour

Quantity
4.000

Rate Rs

Cost Rs

142.99

say
Note
10.4

3004.2

Remarks/
Input ref.

571.97
103.32
113.65
1250.11
12.50
13.00

P&M-086

The earth stripped from earthen shoulders to be dumped on


the side slopes locally for disposal.
Filling Pot-holes and Patch Repairs with open-Graded
Premix surfacing, 20mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 511, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 10250 sqm (205 cum)(405 tonne)
a) Labour
Mate

b)

c)

Day

3.760

185.07

695.86

L-12

Mazdoor

Day

90.000

177.07

15936.30

L-13

Mazdoor skilled

Day

4.000

206.99

827.96

L-15

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

HMP 100-110 TPH Capacity

hour

6.000

33841.00

203046.00

P&M-022

Tipper 10 tonnes capacity

hour

45.000

873.00

39285.00

P&M-048

Smooth wheeled roller 8-10 tonnes

hour

12.000

665.00

7980.00

P&M-044

cum

184.500

756.00

139482.00

M-052

cum

92.250

655.60

60479.38

M-051

tonne

14.970

51344.59

768628.53

M-075

tonne

2.460

45849.96

112790.90

M-077

Machinery

Material
Crushed stone aggregates nominal size 13.2mm @
0.18 cum per 10 sqm
Crushed stone aggregates nominal size 11.2mm @
0.09 cum/10 sqm
Bitumen 80/100 @ 14.6 kg per 10 sqm

d)

Bitumen emulsion for tack coat including vertical sides


of pot hole.
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

135091.45
148600.59

Cost for 10250 sqm = a+b+c+d+e

1634606.53

Rate per sqm = (a+b+c+d+e)/10250


10.5

3004.2

159.47
say

159.00

Filling Pot-holes and Patch Repairs with Bituminous


concrete, 40mm.
Removal of all failed material, trimming of completed
excavation to provide firm vertical faces, cleaning of surface,
painting of tack coat on the sides and base of excavation as
per clause 503, back filling the pot holes with hot bituminous
material as per clause 504, compacting, trimming and
finishing the surface to form a smooth continuous surface, all
as per clause 3004.2
Unit = Sqm
Taking out put = 4900 sqm (196 cum)(450 Tonnes)
a)

b)

Labour
Mate

Day

2.920

185.07

540.40

L-12

Mazdoor

Day

70.000

177.07

12394.90

L-13

Mazdoor skilled

Day

3.000

206.99

620.97

L-15

Air compressor 250 cfm

hour

6.000

293.76

1762.56

P&M-001

HMP 100-110 TPH Capacity

hour

6.000

33841.00

203046.00

P&M-022

Tipper 10 tonnes capacity

hour

45.000

873.00

39285.00

P&M-048

Machinery

166

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Smooth wheeled roller 8-10 tonnes


c)

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

hour

12.000

665.00

7980.00

P&M-044

I) Bitumen

tonne

22.500

51344.59

1155253.29

M-075

ii) Bitumen emulsion for tack coat .

tonne

1.180

45849.96

54102.95

M-077

20-10mm 35 per cent

cum

99.750

1087.74

108501.75

M-045

10-5 mm 23 per cent

cum

65.550

743.09

48709.29 M-025,M-040

5mm and below 40 per cent

cum

114.000

217.00

24738.00

M-030

tonne

8.620

4427.31

38163.39

M-188

Material

iii) Aggregates
Grading I - 19mm(Nominal size)

Filler 2 per cent by weight of aggregate


Add 5 per cent for wastage

1908.17

or
Grading-II 13mm (Nominal size)
13.2-10 mm 30 per cent

cum

85.500

910.00

77805.00

M-044

10-5 mm 25 per cent

cum

71.250

743.09

52944.88

M-025

5 mm and Below43 per cent

cum

122.550

217.00

26593.35

M-030

tonne

8.620

4427.31

38163.39

M-188

Filler 2 per cent


Add 5 per cent for wastage

1908.17

Any one of the above alternatives of aggregate i.e. 19mm or


13mm nominal size may be adopted as per approved
design.
10.5

(i)

for grading I Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

169700.67
186670.74

Cost for 4900 cum = a+b+c+d+e

2053378.09

Rate per cum = (a+b+c+d+e)/4900

419.06
say

419.00

#VALUE!
10.5

(ii)

for grading II Material


d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

167240.09
183964.10

Cost for 4900 cum = a+b+c+d+e

2023605.06

Rate per cum = (a+b+c+d+e)/4900

412.98
say

413.00

#VALUE!
Note
10.6

3004.3.3

For detailed working of quantities of aggregates, refer item


5.8 of chapter 5
Crack Filling
Filling of crack using slow - curing bitumen emulsion and
applying crusher dust in case crack are wider than 3mm.
Unit = Running Meter
Taking out put = 500m
a)

b)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

Kg

33.000

45.85

1513.05

M-077

cum

0.020

211.23

4.22

M-021

Material
Slow-curing bitumen emulsion
Stone crusher dust

c)

Overhead charges @ 0.1 on (a+b)

170.17

d)

Contractor's profit @ 0.1 on (a+b+c)

187.19

Cost for 500sqm = a+b+c+d

2059.11

Rate per meter = (a+b+c+d+e)/500

4.12
say

10.7

3004.4

Dusting

167

4.10

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Applying crusher dust to areas of road where bleeding


of excess bitumen has occurred.
Unit = Sqm
Taking output = 3500 sqm
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

cum

6.250

211.23

1320.16

M-021

Material
Stone crusher dust finer than 3mm with not more
than 10 per cent passing 0.075 sieve.

c)

Overhead charges @ 0.1 on (a+b)

168.91

d)

Contractor's profit @ 0.1 on (a+b+c)

185.80

Cost for 3500sqm = a+b+c+d

2043.81

Rate per meter = (a+b+c+d)/3500

0.58
say

10.8

(A)
3004.3.2

Fog Seal

(B)
3004.3.4

Crack Prevention courses.


(i)
(ii)
(iii)
(iv)

10.8

10.8

0.60

sqm

43.00

Item 5.17

Stress Absorbing Membrane (SAM) crack width less than 6


mm
Stress Absorbing Membrane (SAM) with crack width 6 mm to
9 mm
Stress Absorbing Membrane (SAM) crack width above 9 mm
and cracked area above 50 per cent

sqm

67.00

sqm

82.00

sqm

110.00

Item 5.21
Case-I
Item 5.21
Case-II
Item 5.21
Case-IV

Bitumen Impregnated Geotextile

sqm

149.00

Item 5.21
Case-IV

Item 5.15
Case-I
Item 5.15
Case-II
Item 5.15
Case-III

Slurry Seal

(C)
3004.5
(i)

5 mm thickness

sqm

72.00

(ii)

3 mm thickness

sqm

51.00

(iii)

1.5 mm thickness

sqm

31.00

(D)
3004.6

Surface Dressing for maintenance works.


(i)

19 mm nominal chipping size

sqm

98.00

(ii)

13 mm nominal size chipping

sqm

79.00

Item 5.9
Case-I
Item 5.9
Case-II

The above mentioned items have already been included in


chapter 5.
10.9

3005.1

Repair of Joint Grooves with Epoxy Mortar


Repair of spalled joint grooves of contraction joints,
longitudinal joints and expansion joints in concrete
pavements using epoxy mortar or epoxy concrete
Unit = running metre
Taking output = 10 metres
a)

b)

c)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

0.500

177.07

88.54

L-13

Chiseller

day

0.500

185.07

92.54

L-05

Material
Epoxy primer

kg

2.500

9.01

22.52

M-097

Epoxy compound with accessories for preparing epoxy


mortar
Machinery

kg

10.000

282.81

2828.09

M-095

hour

0.050

293.76

14.69

Air compressor 250 cfm for cleaning

168

P&M-001

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Unit

Quantity

Rate Rs

Cost Rs
305.38
335.91

Cost for 10 metres = a+b+c+d+e

3695.06

Rate per metre = (a+b+c+d+e)/10

369.51
say

10.10

3005.2

Remarks/
Input ref.

370.00

Repair of old Joints Sealant


Removal of existing sealant and re sealing of contraction,
longitudinal or expansion joints in concrete pavement with
fresh sealant material
Unit = running metre
Taking output = 10 metres
a)

b)

c)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

0.500

177.07

88.54

L-13

Primer

kg

0.250

90.84

22.71

M-146

Sealant

kg

1.000

17.81

17.81

M-120

hour

0.050

293.76

14.69

P&M-001

Material

Machinery
Air compressor 250 cfm for cleaning

d)

Overhead charges @ 0.1 on (a+b+c)

15.11

e)

Contractor's profit @ 0.1 on (a+b+c+d)

16.63

Cost for 10 metres = a+b+c+d+e

182.88

Rate per metre = (a+b+c+d+e)/10

18.29
say

10.11

3000

18.30

Hill Side Drain Clearance


Removal of earth from the choked hill side drain and
disposing it on the valley side manually
Unit = running metre
Taking output = 10 metres
Assuming muck causing choking of drain to be 0.2 cum per
metre, quantity of earth to be removed for 10 metres = 2
cum
a) Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

b)

Overhead charges @ 0.1 on (a+b)

c)

Contractor's profit @ 0.1 on (a+b)

19.19
21.11

Cost for 10 metres = a+b+c

232.17

Rate per metre = (a+b+c)/10


10.12

3000

23.22
say

23.20

Land Slide Clearance in soil


Clearance of land slides in soil and ordinary rock by a bulldozer D 80 A-12, 180 HP and disposal of the same on the
valley side
Unit = cum
Taking output = 100 cum
a)

b)

Labour
Mate

day

0.040

185.07

7.40

L-12

Mazdoor

day

1.000

177.07

177.07

L-13

hour

1.670

3135.24

5235.85

P&M-014

Machinery
Dozer 80 HP @ 60 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

542.03
596.24

Cost for 100 cum = a+b+c+d

6558.59

Rate per cum = (a+b+c+d)/100

65.59
say
169

66.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

10.13

3000

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Land Slide clearance involves pushing of loose earth slided


on the road surface from hill face on the valley side. Since
no cutting of original ground is involved, the output of dozer
has been taken as 60 cum per hour for soil, ordinary rock
and blasted hard rock. However, if there are objection to
disposing of earth on valley side, additional resources for its
disposal shall be considered as per site conditions.
Landslide Clearance in Hard Rock Requiring Blasting
Clearing of land slide in hard rock requiring blasting for 50
per cent of the boulders and disposal of the same on the
valley side.
Unit = cum
Taking output = 100 cum
a)

b)

c)

Labour
Mate

day

0.090

185.07

16.66

L-12

Mazdoor

day

1.500

177.07

265.61

L-13

Driller

day

0.750

206.99

155.24

L-06

Blaster

day

0.070

289.31

20.25

L-03

Dozer D 80 A-12,180 HP @ 60 cum per hour

hour

1.670

3135.24

5235.85

P&M-014

Air compressor 250 cfm with two jack hammer

hour

2.500

293.76

734.40

P&M-001

kg

17.500

112.77

1973.49

M-104

each

70.000

14.27

998.63

M-094 /100

Machinery

Materials
Gelatine 80 per cent @ 35 kg per 100 cum

c)

Electric Detonators @ 1 Detonator for 2 Gelatine sticks


of 125 gms each
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

940.01
1034.01

Cost for 100 cum = a+b+c+d+e

11374.16

Rate per cum = (a+b+c+d+e)/100

113.74
say

Note
10.14

3000

114.00

Credit for the rock if found acceptable as construction


material shall be afforded
Snow Clearance on Roads with Dozer
Snow clearance from road surface by a bull- dozer 165 Hp
and disposing it on the valley side
Unit = cum
Taking output = 5000 cum
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

hour

5.880

3135.24

18435.21

Machinery
Dozer D 80 A-12,180 HP @ 850 cum per hour

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1880.42
2068.46

Cost for 5000 cum = a+b+c+d

22753.03

Rate per cum = (a+b+c+d)/5000

4.55
say

Note

10.15

3000

i) Labour provided will not be cutting the snow. They will be


guiding the dozer operator on the alignment of the road as
entire surface gets covered with snow and the edges of the
road are not visible and for changing the blade angle. Also
they will keep a watch on the hill side for any eventuality of
avalanches, slide etc
Snow Clearance on Roads with Snow Blowers
Snow clearance from road surface by a snow blower and
disposing on the valley side.
Unit = cum

170

4.60

P&M-014

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 3600 cum


a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

#VALUE!

P&M-087

Machinery
Snow blower equipment 140 HP @ 600 cum per hour

hour

6.000 Value

c)

Overhead charges @ 0.1 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 3600 cum (a+b+c+d)

#VALUE!

Rate per cum = (a+b+c+d)/3600

#VALUE!
say

171

#VALUE!

CHAPTER-11

HORTICULTURE
Sr No

Ref. to
MoRTH
Spec.

11.1

307

Description

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Cost Rs

day
day

0.040
1.000

185.07
177.07

L-12
L-13

say

7.40
177.07
18.45
20.29
223.21
14.88
14.90

Spreading of Sludge Farm Yard Manure or/and good


Earth
Spreading of sludge farm yard manure or/ and good earth in
required thickness (cost of sludge, farm yard manure or/and
good earth to be paid for separately)
Unit = cum
Taking output = 15 cum
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.1 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 15 cum= a+b+c
Rate per cum = (a+b+c)/15

11.2

307

Grassing with ' Doobs' Grass


Grassing with 'Doobs' grass including watering and
maintenance of the lawn for 30 days or more till the grass
forms a thick lawn free from weeds and fit for moving
including supplying good earth if needed

(i)

Unit = sqm
Taking output = 100 sqm
In rows 15 cm apart in either direction
a)

Labour
Mate
Mazdoor for grassing
Mazdoor for maintenance for 30 days
b) Machinery
Water tanker6 KL capacity
c) Material
Doob grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm= (a+b+c+d+e)/100
11.2

(ii)

In rows 7.5 cm apart in either direction


a) Labour
Mate
Mazdoor for grassing.
for maintenance for 30 days
b) Machinery
Water tanker6 KL capacity
c) Material
Doob grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/100

day
day
day

0.170
0.750
1.000

185.07
177.07
177.07

31.46
132.80
177.07

L-12
L-13
L-13

hour

0.500

111.24

55.62

P&M-060

kg

100.000

3.04

M-112

say

304.00
70.10
77.10
848.15
8.48
8.50

day
day
day

0.220
1.250
1.000

185.07
177.07
177.07

40.72
221.34
177.07

L-12
L-13
L-13

hour

0.750

111.24

83.43

P&M-060

kg

200.000

3.04

608.00
113.06
124.36
1367.97
13.68
13.70

M-112

say
Note

11.3

307

In the case of horticulture one mate has been provided for


every 10 mazdoors as maintenance of grass and plants
require more care.
Making Lawns including Ploughing and Dragging with
'Swagha' Breaking of Clod
Making lawns including ploughing and breaking of clod,
removal of rubbish, dressing and supplying doobs grass
roots and planting at 15 cm apart, including supplying and
spreading of farm yard manure at rate of 0.18 cum per 100
sqm
Unit = sqm
Taking output = 100 sqm

171

Sr No

Ref. to
MoRTH
Spec.

Description
Labour
Mate
Mazdoor for preparation of ground
Mali for fetching doobs grass roots and grassing at 15
cm apart
b) Machinery
Water tanker6 KL capacity
Tractor with filler
c) Material
Supply of farm yard manure at site of work
Fine grass
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 sqm = a+b+c+d+e

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

day
day
day

0.150
0.500
1.000

185.07
177.07
206.99

27.76
88.54
206.99

L-12
L-13
L-09

hour
hour

0.500
0.010

111.24
171.02

55.62
1.71

P&M-060
P&M-053

cum
kg

0.180
100.000

528.65
3.04

95.16
304.00
77.98
85.77
943.52

M-167
M-113

a)

Rate per sqm = (a+b+c+d+e)/100


11.4

307

9.44
say

9.40

Maintenance of Lawns or Turfing of Slopes


Maintenance of lawns or Turfing of slopes (rough grassing)
for a period of one year including watering etc
Unit = sqm
Taking output = 100 sqm
a)

Labour
Mali

b)

Water tanker6 KL capacity


c)

day

10.000

206.99

2069.90

L-09

hour

15.000

111.24

1668.60

P&M-060

KL

90.000

167.07

15036.14

M-189

Machinery
Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1877.46
2065.21

Cost for 100 sqm = a+b+c+d+e

22717.31

Rate per sqm = (a+b+c+d+e)/100


11.5

307

227.17
say

227.00

Turfing Lawns with Fine Grassing including Ploughing,


Dressing
Turfing lawns with fine grassing including ploughing,
dressing including breaking of clods, removal of rubbish,
dressing and supplying doobs grass roots at 10 cm apart,
including supplying and spreading of farm yard manure at
rate of 0.6 cum per 100 sqm
Unit = sqm
Taking output = 100 sqm
a)

b)

c)

Labour
Mate

day

0.250

185.07

46.27

L-12

Mazdoor for preparation of ground

day

1.000

177.07

177.07

L-13

Mali for fetching doobs grass roots hedges and


grassing at 10 cm apart
Machinery

day

1.500

206.99

310.49

L-09

Water tanker6 KL capacity

hour

0.500

111.24

55.62

P&M-060

Tractor with tiller

hour

0.010

171.02

1.71

P&M-053

cum

0.600

528.65

317.19

M-167

kg

100.000

3.04

304.00

M-113

Material
Supply of farm yard manure at site of work @ 0.6 cum
per 100 sqm
Fine grass

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

121.23
133.36

Cost for 100 sqm = a+b+c+d+e

1466.93

Rate per sqm = (a+b+c+d+e)/100

14.67

172

Sr No

Ref. to
MoRTH
Spec.

11.6

307

Description

Unit

Quantity

Rate Rs

Cost Rs

say

14.70

Remarks/
Input ref.

Maintenance of Lawns with Fine Grassing for the First


Year
Maintenance of lawns with fine grassing for the first year
including watering etc
Unit = sqm
Taking output = 100 sqm
a)

Labour
Mali

b)

Water tanker6 KL capacity


c)

day

10.000

206.99

2069.90

L-09

hour

20.000

111.24

2224.80

P&M-060

KL

60.000

167.07

10024.09

M-189

Machinery
Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1431.88
1575.07

Cost for 100 sqm = a+b+c+d+e

17325.74

Rate per sqm = (a+b+c+d+e)/100

173.26
say

11.7

307

173.00

Planting and Maintaining of Permanent Hedges


(a)

Planting permanent hedges including digging of


trenches
Planting permanent hedges including digging of trenches, 60
cm wide and 45 cm deep, refilling the excavated earth mixed
with farmyard manure, supplied at the rate of 4.65 cum per
100 metres and supplying and planting hedge plants at 30
cm apart
Unit = Running metre
Taking output = 100metre
a)

b)

Labour
Mate

day

1.400

185.07

259.10

L-12

Mazdoor for digging of trench 60 cm wide and 45 cm


deep
Mazdoor for refilling the excavated earth mixed with
cow dung, preparation of ground and digging of plant,
from the nursery carriage to site and planting in
position

day

10.000

177.07

1770.70

L-13

day

4.000

177.07

708.28

L-13

hour

0.500

111.24

55.62

P&M-060

Machinery
Water tanker6 KL capacity

c)

Material
Cost of hedge plants 2 rows at 30 cm apart

each

2x340

22.80

15504.00

M-116

Supply of farm yard manure at site of work

cum

4.670

528.65

2468.80

M-167

Pesticide

kg

0.250

56.39

14.10

M-136

Cost of water

KL

3.000

167.07

501.20

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2128.18
2341.00

Cost for 100 metres = a+b+c+d+e

25750.97

Rate per metre = a+b+c+d+e)/100

257.51
say

(b)

258.00

Maintenance of hedge for one year


Unit = Running metre
Taking output = 100 m
a)

b)

Labour
Mate

day

3.000

185.07

555.21

L-12

Mazdoor

day

30.000

177.07

5312.10

L-13

hour

5.000

111.24

556.20

P&M-060

Machinery
Water tanker6 KL capacity

c)

Material

173

Sr No

Ref. to
MoRTH
Spec.

Description
Manure sludge/Farm yard manure
Pesticide
Cost of water
Cost of hedge plants @ 10 per cent casualty
d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

cum

2.000

528.65

1057.30

M-167

kg

0.500

56.39

28.19

M-136

KL

30.000

167.07

5012.05

M-189

each

68.000

22.80

1550.40

M-116

1407.14
1547.86

Cost for 100 metres = a+b+c+d+e

17026.45

Rate per metre = a+b+c+d+e)/100

170.26
say

11.8

307
(a)

170.00

Planting and Maintaining of Flowering Plants and


Shrubs
Planting flowering plants and shrubs in central verge
Unit = Running metres 200 plants and 800 shrubs in two
rows in one km length of road where width of verge is
3m and above.
Taking output = 1000 metres
a)

b)

Labour
Mate

day

1.200

185.07

222.08

L-12

Mazdoor

day

12.000

177.07

2124.84

L-13

hour

6.000

111.24

667.44

P&M-060

Plants

each

200.000

23.94

4787.19

M-100

Shrubs

each

800.000

11.40

9120.00

M-166

Manure sludge/Farm yard manure

cum

63.640

528.65

33643.29

M-167

Pesticide

kg

0.500

56.39

28.19

M-136

Cost of water

KL

36.000

167.07

6014.46

M-189

Machinery
Water tanker6 KL capacity

c)

Material

d)

Overhead charges @ 0.1 on (a+b+c)

5660.75

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6226.82

Rate per Km = (a+b+c+d+e)


11.8

(b)

68495.06
say

68495.00

Maintenance of flowering plants and shrubs in central


verge for one year
Unit = km
Taking output = one km
a)

b)

Labour
Mate

day

36.000

185.07

6662.52

L-12

Mazdoor

day

365.000

177.07

64630.55

L-13

hour

90.000

111.24

10011.60

P&M-060

Machinery
Water tanker6 KL capacity

c)

Material
Manure Sludge / farm yard manure at site

cum

10.000

528.65

5286.50

M-167

Cost of water

KL

180.000

167.07

30072.28

M-189

Plants

each

20.000

23.94

478.72

M-100

Shrubs

each

80.000

11.40

912.00

M-166

kg

1.500

56.39

84.58

M-136

Replacement of casualties @ 10 per cent

Pesticides
d)

Overhead charges @ 0.1 on (a+b+c)

11813.87

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12995.26

Rate per Km for one year = (a+b+c+d+e)

142947.88
say

11.9

307

Planting of Trees and their Maintenance for one Year

174

142948.00

Sr No

Ref. to
MoRTH
Spec.

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Mate

day

1.700

185.07

314.62

L-12

Mazdoor for planting

day

2.000

177.07

354.14

L-13

Mazdoor for maintenance for one year

day

15.000

177.07

2656.05

L-13

hour

2.000

111.24

222.48

P&M-060

Sapling 2 m high 25 mm dia

each

10.000

17.54

175.42

M-160

Farm yard manure

cum

0.940

528.65

496.93

M-167

Description
Planting of trees by the road side (Avenue trees) in 0.60 m
dia holes, 1 m deep dug in the ground, mixing the soil with
decayed farm yard/sludge manure, planting the saplings,
backfilling the trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
Taking output = 10 trees
a)

b)

Labour

Machinery
Water tanker6 KL capacity

c)

Material

Pesticide

kg

0.500

56.39

28.19

M-136

Cost of water

KL

12.000

167.07

2004.82

M-189

d)

Overhead charges @ 0.1 on (a+b+c)

625.27

e)

Contractor's profit @ 0.1 on (a+b+c+d)

687.79

Cost for 10 trees = a+b+c+d+e

7565.71

Rate per trees = (a+b+c+d+e)/10

756.57
say

11.10

308

757.00

Renovation Lawns including, Weeding, Forking the


Ground, Top Dressing with Forked Soil
Renovation lawns including, weeding, forking the ground,
top dressing with forked soil, watering and maintenance the
lawns, for 30 days or more, till the grass forms a thick lawn,
free from weeds, and fit for moving and disposal of rubbish
as directed, including supplying good earth, if needed but
excluding the cost of well decayed farm yard manure
Unit = sqm
Taking output = 100 sqm
a)

b)

Labour
Mate

day

0.120

185.07

22.21

L-12

Mazdoor

day

3.000

177.07

531.21

L-13

hour

0.500

111.24

55.62

P&M-060

KL

3.000

167.07

501.20

M-189

Machinery
Water tanker6 KL capacity

c)

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

111.02

e)

Contractor's profit @ 0.1 on (a+b+c+d)

122.13

Cost for 100 sqm = a+b+c+d+e

1343.39

Rate per sqm = (a+b+c+d+e) / 100


11.11

308.2

13.43
say

13.40

528.65

528.65

Supply at Site Well Decayed Farm Yard Manure


Supply at site of work well decayed farm yard manure, from
any available source, approved by the engineer in charge
including screening and stacking
Unit = cum
Taking output = one cum
a)

Material
a) Cost of well decayed farm yard manure duly
screened, loading, carriage, unloading and
stacking at site

cum

1.000

b)

Overhead charges @ 0.1 on (a)

52.87

c)

Contractor's profit @ 0.1 on (a+b)

58.15
175

M-167

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per cum = (a+b+c)

Cost Rs

Remarks/
Input ref.

639.67
640.00

11.12

308.20

Supply at Site of Work/ Store-Deoiled Neem Cake


Supply at site of work/ store-deoiled neem cake duly packed
in used gunny bags
Unit = quintal
Taking output = one quintal
a) Cost, carriage, loading, unloading and stacking in
store/site
b) Overheads@ per cent on (a)
c)

quintal

1.000

Contractors profit@ per cent on (a+b)

Rate per quintal = a+b+c


11.13

308.2

VALUE

Supplying Sludge
Supplying sludge duly stacked at site/ store
Unit = cum
Taking output = one cum
a) Cost of sludge including carriage, loading,
unloading and stacking at site
b) Overheads@ per cent on (a)
c)

cum

1.000

Contractors profit@ per cent on (a+b)

Rate per cum = a+b+c


11.14

New

VALUE

Half Brick Circular Tree Guard, in 2nd Class Brick,


internal diametre 1.25 metres, and height 1.2 metres,
above ground and 0.20 metre below ground
Half brick circular tree guard, in 2nd class brick, internal
diametre 1.25 metres, and height 1.2 metres, above ground
and 0.20 metre below ground, bottom two courses laid dry,
and top three courses in cement mortar 1:6 (1 cement 6
sand) and the intermediate courses being in dry honey comb
masonry, as per design complete
Unit = Each
Taking output = one tree guard
a)

b)

Labour
Mate

day

0.050

185.07

9.25

L-12

Mason

day

0.250

234.29

58.57

L-11

Mazdoor

day

0.250

177.07

44.27

L-13

Brick 2nd class including carriage

each

230.000

4.33

995.57

M-079

Cement mortar 1:6

cum

0.025

2107.00

52.68

Item 12.6
(D)

Material

c)

Overhead charges @ 0.1 on (a+b)

116.03

d)

Contractor's profit @ 0.1 on (a+b+c)

127.64

Rate per tree Guard = a+b+c+d

1404.01
say

1404.00
#VALUE!

Edging with 2nd class bricks, laid dry lengthwise, including


excavation, refilling, consolidation, with a hand packing and
spreading nearly surplus earth within a lead of 50 metres
Unit = Metre
Taking output= 10 metres
a)

b)

Labour
Mate

day

0.002

185.07

0.37

L-12

Mason

day

0.050

234.29

11.71

L-11

Mazdoor

day

0.050

177.07

8.85

L-13

each

50.000

4.33

216.43

M-079

Material
Brick 2nd class including carriage

176

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

c)

Overhead charges @ 0.1 on (a+b)

23.74

d)

Contractor's profit @ 0.1 on (a+b+c)

26.11

Cost for 10 metre = a+b+c+d

28.72
say

New

Remarks/
Input ref.

287.21

Rate per metre = (a+b+c+d)/10


11.16

Cost Rs

28.70

Making Tree Guard 53 cm dia and 1.3 m High as per


Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 1.3 m high as per design
from empty bitumen drum, slit suitably to permit sun and air,
(supplied by the department at stock issue rate) including
providing and fixing 2 nos MS sheet rings 50 x 0.5 mm with
rivets, complete in all respect
Unit = Each
Taking output = one tree guard
a)

b)

Labour
Mate

day

0.020

185.07

3.70

L-12

Blacksmith

day

0.150

234.29

35.14

L-02

Mazdoor

day

0.070

177.07

12.39

L-13

each

1.000

90.84

90.84

M-172

kg

0.650

46.53

30.24

each

22.000

5.64

124.05

M-179 /
1000
M-158

Material
Empty bitumen drum
MS sheet 50 x 0.5 mm
Rivets 6 mm dia and 10 mm in length

c)

Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

29.64
32.60

Rate for each tree guard = a+b+c+d


11.17

New

358.61
say

359.00

0.040

185.07

7.40

L-12

0.200

234.29

46.86

L-02

0.200

177.07

35.41

L-13

Making Tree Guard 53 cm dia and 2 Metre High as per


Design from Empty Bitumen Drums
Making tree guard 53 cm dia and 2 metres high as per
design from empty bitumen drums, slit suitably to permit sun
and air, ( supplied by the department at stock issue rate)
including providing and fixing four legs 40 cm long of 30 x 3
mm MS riveted to tree guard and providing and fixing 2 nos
MS sheet rings 50 x 0.5 mm with rivets complete in all
respects
Unit = Each
Taking output = one tree guard
a)

Labour
Mate
Blacksmith

day

Mazdoor
b)

Material
Empty bitumen drum

each

1.500

90.84

136.27

M-172

MS sheet50 x 0.5 mm

kg

0.650

46.53

30.24

each

50.000

5.64

281.93

M-179 /
1000
M-158

kg

1.300

46.53

60.49

Rivets 6 mm dia and 10 mm in length


MSplate30 x 3 mm
c)

Overhead charges @ 0.1 on (a+b)

59.86

d)

Contractor's profit @ 0.1 on (a+b+c)

65.85

Rate for each tree guard = a+b+c+d

724.30
say

11.18

New

Wrought Iron and Mild Steel Welded Work

177

724.00

M-179 /
1000

Sr No

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

185.07

83.28

L-12

234.29

468.58

L-02

2.500

177.07

442.68

L-13

quintal

1.050

4652.73

4885.37

M-179 /10

quintal

0.050

-1550.91

(77.55)

M-179/10/3

Unit

Quantity

Rate Rs

Mate

day

0.450

Blacksmith/ welder for cutting to design and shape and


jointing
Mazdoor for fixing and helper for Blacksmith/welder

day

2.000

day

Angle, tees, channels etc


Deduct the cost of scrap

Wrought iron and mild steel welded work (using angles,


square bars, tees and channel grills, grating frames, gates
and tree guards of any size and design etc. including cost of
screens and welding rods or bolts and nuts complete fixed in
position but without the cost of excavation and concrete for
fixing which will be paid separately
Unit = quintal
Taking output = one quintal
a)

b)

Labour

Material

Add 5 per cent of cost of material for welding rods and other
welding accessories
c) Overhead charges @ 0.1 on (a+b)
d)

240.39
604.28

Contractor's profit @ 0.1 on (a+b+c)

664.70

Rate per quintal = a+b+c+d


11.19

New

7311.73
say

7312.00

Tree Guard with MS Iron


Providing and fixing MS iron tree guard 60 cm dia and 2
metre high above ground level formed of 4 Nos (25 x 6 mm)
and 8 Nos (25 x 3 mm) vertical MS riveted to 3 Nos (25 x 6
mm) iron rings in two halves, bolted together with 8 mm dia
and 30 mm long bolts including painting two coats with paint
of approved brand over a coat of priming, complete in all
respects.
Unit = Each
Taking output = one tree guard
a)

b)

c)

Labour
Mate

day

0.050

185.07

9.25

L-12

Blacksmith

day

0.250

234.29

58.57

L-02

Mazdoor

day

0.250

177.07

44.27

L-13

MS iron 25 x 6 mm

kg

19.200

46.527

893.32

MS iron 25 x 3 mm

kg

9.600

46.527

446.66

M-179 /
1000
M-179 /
1000

hour

0.040

171.02

6.84

P&M-053

sqm

1.770

39.00

69.03

Item 8.9

Material

Add 5 per cent of cost of material for riveting, bolting


and welding accessories
Machinery
Tractor-trolley

d)

Painting
Painting two coats including priming

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

145.89
160.48

Rate per tree guard =a+b+c+d+e+f

1834.32
say

Note

1 The items of excavation and concreting to be measured


and paid separately as per design .
2 . Rate of painting may be adopted from the chapter as
Traffic signs.

11.20

New

Tree Guard with MS Angle Iron and Steel Wire

178

1834.00

Sr No

Ref. to
MoRTH
Spec.

Cost Rs

Remarks/
Input ref.

185.07

9.25

L-12

234.29

58.57

L-02

0.250

234.29

58.57

L-02

day

0.250

177.07

44.27

L-13

MS angle 30 x 30 x 3 mm

kg

13.500

46.53

628.12

MS iron 25 x 3 mm

kg

18.000

46.53

837.49

Steel wire 3 mm dia

kg

6.000

30.28

181.69

M-179 /
1000
M-179 /
1000
M-192

Description

Unit

Quantity

Rate Rs

Mate

day

0.050

Blacksmith

day

0.250

Welder

day

Mazdoor

Providing and fixing tree guard 0.60 metre square, 2.00


metre high fabricated with MS angle iron 30 x 30 x 3 mm,
MS iron 25 x 3 mm and steel wire3 mm dia welded and
fabricated as per design in two halves bolted together
Unit = Each
Taking output = one tree guard
a)

b)

c)

Labour

Material

Tractor-trolley
d)

82.36

Add 5 per cent of cost of material for riveting, bolting


and welding accessories
Machinery
hour

0.040

171.02

6.84

P&M-053

sqm

1.500

39.00

58.50

Item 8.9

Painting
Painting two coats including priming

e)

Overhead charges @ 0.1 on (a+b+c)

f)

Contractor's profit @ 0.1 on (a+b+c+e)

190.72
209.79

Rate per tree guard = a+b+c+d+e+f


11.21

New

2366.17
say

2366.00

Compensatory Afforestation
Planting trees as compensatory afforestation at the rate of
290 trees per hectare at a spacing of 6 m by grubbing and
leveling the ground upto a depth of 150 mm, digging holes
0.9 m dia, 1 m deep, mixing farm yard/sludge manure with
soil, planting of sapling 2 m high with 25 cm dia stem,
backfilling the hole and watering
Unit = Hectare
Taking output = one hectare
a)

Labour

i) Planting
Mate

day

2.500

185.07

462.68

L-12

Mazdoor

day

25.000

177.07

4426.75

L-13

Mate

day

5.000

185.07

925.35

L-12

Mazdoor

day

50.000

177.07

8853.50

L-13

Dozer 80 HP @ 1000 sqm/hour

hour

10.000

2028.78

20287.80

P&M-015

Water tanker6 KL capacity (for planting)

hour

3.000

111.24

333.72

P&M-060

Water tanker6 KL capacity (for maintenance)

hour

25.000

111.24

2781.00

P&M-060

Sapling 1 to 1.5 m high 2 cm dia stem

each

290.000

14.03

4069.78

Add 10 per cent of sapling

each

29.000

14.03

406.98

Decayed farm yard/sludge manure (planting)

cum

60.900

528.65

32194.79

M-160 x
0.8
M-160 x
0.8
M-167

Decayed farm yard/sludge manure (maintenance)

cum

4.000

528.65

2114.60

M-167

Pesticides for planting

kg

0.500

56.39

28.19

M-136

Pesticides for maintenance

kg

1.500

56.39

84.58

M-136

Cost of water

KL

18.000

167.07

3007.23

M-189

ii) For Maintenance for one year

b)

c)

d)

Machinery

Material

Overhead charges @ 0.1 on (a+b+c)

7997.69
179

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Unit

Quantity

Rate Rs

Contractor's profit @ 0.1 on (a+b+c+d)

8797.46

Rate per hectare = a+b+c+d+e

96772.10
say

Note

Cost Rs

Cost of fencing to be provided as per size of plot and


approved design, measured and paid separately

180

96772.00

Remarks/
Input ref.

CHAPTER-12

FOUNDATIONS
Sr No

Ref. to
MoRTH
Spec.

12.1

304

Description

Unit

Quantity

Rate Rs

Cost Rs

Excavation for Structures


Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I

Ordinary soil
Unit = cum
Taking output = 10 cum

A
(i)

Manual Means
Depth upto 3 m
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

0.14

185.07

25.91

day

3.50

177.07

619.75
161.41
80.71
887.78
88.78

say

Note

89.00

1. Cost of dewatering may be added where required upto, 10


percent of labour cost assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.

12.1 (I) A

(ii)

Depth 3 m to 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

0.18

185.07

33.31

day

4.50

177.07

796.82
207.53
103.77
1141.43
114.14

say

12.1 (I) A

Note

Cost of dewatering may be added where required upto 15 per


cent of labour cost. Assessment for dewatering shall be done
as per actual ground conditions.

(iii)

Depth above 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

0.24

185.07

44.42

day

6.00

177.07

1062.42
276.71
138.35
1521.90
152.19

say

Note

12.1 (I)

B
(i)

114.00

1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
180

152.00

day

0.32

185.07

59.22

day

8.00

177.07

1416.56

hour

6.00

1516.32

9097.92

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

2643.43

c) Overhead charges @ 0.25 on (a+b)


d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240

1321.71
14538.84
60.58
say

Note

12.1 (I) B

(ii)

61.00

Cost of dewatering upto 5 per cent of (a+b) may be added,


where required. Assessment for dewatering shall be made as
per site conditions..
Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity

day

0.32

185.07

59.22

day

8.00

177.07

1416.56

hour

6.00

1516.32

9097.92
2643.43

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1321.71
14538.84

Cost for 210 cum = a+b+c+d

69.23

Rate per cum = (a+b+c+d)/210


say

12.1 (I) B

Cost Rs

Note

Cost of dewatering upto 7.5 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions..

(iii)

Depth above 6m

69.00

Unit = cum
Taking output = 180 cum
a)

b)

Labour
Mate

day

0.40

185.07

74.03

Mazdoor

day

10.00

177.07

1770.70

hour

6.00

1516.32

9097.92

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.25 on (a+b)

2735.66

d)

Contractor's profit @ 0.1 on (a+b+c)

1367.83
15046.14

Cost for 180 cum = a+b+c+d

83.59

Rate per cum = (a+b+c+d)/180


say

Note

84.00

1. Cost of dewatering upto 10 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side slopes.

12.1

II

Ordinary Rock (not requiring blasting)

Manual Means

(i)

Depth upto 3 m
Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.20

185.07

37.01

Mazdoor

day

5.00

177.07

885.35

b)

Overhead charges @ 0.25 on (a)

230.59

c)

Contractor's profit @ 0.1 on (a+b)

115.30
1268.25

Cost for 10 cum = a+b+c

126.83

Rate per cum = (a+b+c)/10


say

Note

12.1(II)

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
Mechanical Means
181

127.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Unit = cum
Taking output = 180 cum
a)

b)

Labour
Mate

day

0.24

185.07

44.42

Mazdoor

day

6.00

177.07

1062.42

hour

6.00

1516.32

9097.92

Machinery
Hydraulic excavator 1.0 cum bucket capacity

2551.19

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1275.59
14031.54

Cost for 180 cum = a+b+c+d

77.95

Rate per cum = (a+b+c+d)/180


say

Note

78.00

1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.

12.1

III

Hard Rock ( requiring blasting )

Manual Means
Unit = cum
Taking output = 10 cum
a)

b)

Labour
Mate

day

0.35

185.07

64.77

Driller

day

0.50

206.99

103.50

Blaster

day

0.25

289.31

72.33

Mazdoor

day

8.00

177.07

1416.56

hour

1.00

293.76

293.76

3.50

112.77

394.70

14.00

14.27

199.73

Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling.

c)

Material
Blasting Material

kg

Detonator electric

each

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

636.34
318.17
3499.84

Cost for 10 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/10

349.98
say

Note

12.1

IV

350.00

Cost of dewatering @ 10 percent of (a+b) may be added,


where required. Assessment for dewatering shall be made as
per site conditions.
Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum

Mechanical Means
a)

Labour
Mate

day

0.20

185.07

37.01

Mazdoor

day

5.00

177.07

885.35

hour

6.00

293.76

1762.56

b)

Machinery

c)

Air Compressor 250 cfm with 2 leads of pneumatic


breaker
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

671.23
335.62
3691.77

Cost for 10 cum = a+b+c+d

369.18

Rate per cum = (a+b+c+d)/10


say

Note

1. Cost of dewatering upto10 per cent of (a+b), may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
182

369.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

2.In case of rock, foundation beyond3 m is not dug and hence


not included.
12.1

Marshy Soil
Unit = cum
Taking output = 10 cum
Depth upto 3 m

Manual means
a)

b)

Labour
Mate/Supervisor

day

0.40

185.07

74.03

Mazdoor

day

10.00

177.07

1770.70

hour

2.67

171.02

456.62

Machinery
Tractor-trolley for removal.

575.34

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

287.67
3164.35

Cost for 10 cum = a+b+c+d

316.44

Rate per cum = ( a+b+c+d)/ 10


say

Note

316.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1-IA (ii) to (iii) for ordinary soil

12.1 (V)

Mechanical Means
a)

b)

Labour
Mate

day

0.08

185.07

14.81

Mazdoor for dressing sides, bottom and backfilling

day

2.00

177.07

354.14

hour

0.17

1516.32

257.77

hour

0.45

873.00

392.85

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 cum
per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.25 on (a+b)

254.89

d)

Contractor's profit @ 0.1 on (a+b+c)

127.45
1401.91

Cost for 10 cum = a+b+c+d

140.19

Rate per cum = (a+b+c+d)/10


say

Note

140.00

1. Cost of dewatering @ 20 percent of (a+b) may be added,


where required
2. Shoring & strutting @ 10 percent of (a+b), where required
may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1-IB (ii) to (iii) for ordinary soil

VI

Back Filling in Marshy Foundation Pits


Unit : Cum
Taking Output : 6 cum
a)

b)

Labour
Mate

day

0.12

185.07

22.21

Mazdoor for dressing sides, bottom and backfilling

day

3.00

177.07

531.21

hour

2.00

171.02

342.04

Machinery
Tractor-trolley for transportation

223.86

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

111.93
1231.25

Cost for 6 cum = a+b+c+d

205.21

Rate per cum = (a+b+c+d)/6

183

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.2

304

Cost Rs
205.00

Filling Annular Space Around Footing in Rock


Unit = cum
Taking out put = 1 cum

12.3

VALUE

Lean cement concrete 1:3:6 nominal mix. Rate may be taken


as per item 12.4.
Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum

304

Taking output = 1 cum


a)

b)

Labour
Mate

day

0.01

185.07

1.85

Mazdoor

day

0.30

177.07

53.12

cum

1.20

109.09

130.90

Material
Sand (assuming 20 per cent voids)

46.47

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

23.23
255.58

Rate per cum = a+b+c+d


say

12.4

2100

256.00

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a)

b)

Labour
Mate

day

0.64

185.07

Mason

day

1.00

234.29

234.29

Mazdoor

day

15.00

177.07

2656.05

40 mm Aggregate

cum

13.50

758.35

10237.78

coarse Sand

cum

6.75

203.75

1375.34

tonne

3.45

5789.47

19973.68

18.00

167.07

3007.23

Material

cement
Cost of water
c)

KL

Machinery
Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Water tanker 6 KL capacity

hour

2.00

111.24

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

5143.69
56580.61
3772.04

Rate per cum = (a+b+c+d+e)/15


say

12.5

1300

222.48
10287.38

Cost for 15 cum = a+b+c+d+e

Note

118.44

3772.00

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per
Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum
a)

b)

Material
Bricks Ist class

each

2500.00

4.33

10821.43

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)

cum

1.20

3333.00

3999.60

day

0.48

185.07

88.83

Labour
Mate

184

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Mason

day

4.00

234.29

937.16

Mazdoor

day

8.00

177.07

1416.56

c)

Overhead charges @ 0.25 on (a+b)

4315.90

d)

Contractor's profit @ 0.1 on (a+b+c)

2157.95
23737.43

Cost for 5 cum = a+b+c+d

4747.49

Rate per cum (a+b+c+d)/5


say

12.6

Subanalysis

Cost Rs

4747.00

(i)

Rate for Brick Work in C. M. 1:2 in foundation

5049.00

(ii)

Rate for Brick Work in C. M. 1:3 in foundation

4747.00

(iii)

Rate for Brick Work in C. M. 1:4 in foundation

4542.00

(iv)

Rate for Brick Work in C. M. 1:6 in foundation

4343.00

(A)

Cement Mortar 1:3 (1 cement : 3 sand)


Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.51

5789.47

2952.63

cum

1.05

203.75

213.94

Mate

day

0.04

185.07

7.40

Mazdoor

day

0.90

177.07

Cement
Sand
b)

Labour

say

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(B)

159.36
3333.00

Cement Mortar1:2 (1cement :2 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.672

5789.47

3890.53

cum

0.933

203.75

190.17

Mate

day

0.04

185.07

7.40

Mazdoor

day

0.90

177.07

159.36

Cement
Sand
b)

Labour

say

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(C)

4247.00

Cement Mortar1:4 (1cement :4 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.40

5789.47

2315.79

cum

1.12

203.75

228.20

Mate

day

0.04

185.07

7.40

Mazdoor

day

0.90

177.07

Cement
Sand
b)

Labour

say

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(D)

159.36
2711.00

Cement Mortar1:6 (1cement :6 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.288

5789.47

1667.37

cum

1.337

203.75

272.45

Mate

day

0.04

185.07

7.40

Mazdoor

day

0.90

177.07

159.36

Cement
Sand
b)

Labour

185

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

say

Total Material and Labour = (a+b)


12.7

1400

Rate Rs

Cost Rs
2107.00

Stone Masonry Work in Cement Mortar 1:3 in Foundation


complete as per Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum

1405.4

(A)

Square Rubble Coursed Rubble Masonry (first sort)


a)

Material
Stone

cum

5.50

360.24

1981.32

Through and bond stone

each

35.00

6.06

211.97

cum

1.50

3333.00

4999.50

Mate

day

0.66

185.07

122.15

Mason

day

7.50

234.29

1757.18

Mazdoor

day

9.00

177.07

1593.63

(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)
b)

Labour

2666.44

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1333.22
14665.40

Cost for 5 cum = a+b+c+d

2933.08

Rate per cum (a+b+c+d)/5


say

1405.3

(B)

2933.00

Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a)

Material
Stone

cum

5.50

359.72

1978.45

Through and bond stone

each

35.00

6.06

211.97

cum

1.55

3333.00

5166.15

Mate

day

0.62

185.07

114.74

Mason

day

6.00

234.29

1405.74

Mazdoor

day

9.00

177.07

1593.63

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)
b)

Labour

c)

Overhead charges @ 0.25 on (a+b)

2617.67

d)

Contractor's profit @ 0.1 on (a+b+c)

1308.84
14397.19

Cost for 5 cum = a+b+c+d

2879.44

Rate per cum (a+b+c+d)/5


say

Note

12.8

1500,
1700 &
2100

2879.00

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry works.
Plain/Reinforced Cement Concrete in Open Foundation
complete as per Drawing and Technical Specifications.

PCC Grade M15


Unit = cum
Taking output = 15 cum
a)

Material
tonne

4.13

5789.47

23910.53

Coarse sand

cum

6.75

203.75

1375.34

40 mm Aggregate

cum

8.10

758.35

6142.67

20 mm Aggregate

cum

4.05

862.50

3493.13

10 mm Aggregate

cum

1.35

655.60

885.06

day

0.86

185.07

159.16

Cement

b)

Labour
Mate
186

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 63 KVA

hour

6.00

361.80

2170.80

Machinery

2887.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1731.98

11257.90
5628.95
61918.44

Cost for 15 cum = a+b+c+d+e+f

4127.90

Rate per cum = (a+b+c+d+e+f)/15


say

Note

12.8

Cost Rs

4128.00

Needle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
PCC Grade M20
Unit : cum
Taking output = 15 cum
a)

Material
tonne

5.16

5789.47

29873.68

Coarse sand

cum

6.75

203.75

1375.34

40 mm Aggregate

cum

5.40

758.35

4095.11

20 mm Aggregate

cum

5.40

862.50

4657.51

10 mm Aggregate

cum

2.70

655.60

1770.13

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

3277.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

1965.92
12778.48
6389.24

Contractor's profit @ 0.1 on (a+b+c+d+e)

70281.66

Cost for 15 cum = a+b+c+d+e+f

4685.44

Rate per cum = (a+b+c+d+e+f)/15


say

12.8

C
Case I

4685.00

RCC Grade M20


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.21

5789.47

30163.16

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Cement

b)

c)

Labour

Machinery

187

Sr No

Ref. to
MoRTH
Spec.

Description

d)

Unit

Concrete mixer (cap. 0.40/0.28 cum)

hour

Generator 33 KVA

hour

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Rate Rs

6.00

211.68

1270.08

6.00

342.36

2054.16

1977.65
12854.73
6427.36
70701.00

Cost for 15 cum = a+b+c+d+e+f

4713.40

Rate per cum = ( a+b+c+d+e+f )/15


say

12.8 C

Cost Rs

3297.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 4 per cent on (a+b+c)

e)

Quantity

4713.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a) Material
tonne

41.66

5789.47

241189.47

Coarse Sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

6.00

2488.00

14928.00

6.00

1698.00

10188.00

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

Loader 1 cum capacity

hour

6.00

Transit Mixer 4 cum capacity for lead upto 1 km.

hour
tonne.km

Lead beyond 1 km, L-lead in km

7128.00

15.00

854.55

12818.25

300L

4.32

1296.00

234.36

1406.16

hour

Concrete Pump

3236.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

1188.00

15528.58
100935.74
50467.87

Contractor's profit @ 0.1 on (a+b+c+d+e)

555146.58

Cost for 120 cum = a+b+c+d+e+f

4626.22

Rate per cum = ( a+b+c+d+e+f )/120


say

12.8

D
Case I

4626.00

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.99

5789.47

34678.95

Coarse sand

cum

6.75

203.75

1375.34

40 mm Aggregate

cum

5.40

758.35

4095.11

20 mm Aggregate

cum

5.40

862.50

4657.51

10 mm Aggregate

cum

2.70

655.60

1770.13

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

188

Sr No

Ref. to
MoRTH
Spec.

Description

d)

Unit

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Rate Rs

2023.25
13994.13
6997.07
76967.72

Cost for 15 cum = a+b+c+d+e+f

5131.18

Rate per cum = ( a+b+c+d+e+f )/15


say

12.8 D

Cost Rs

3597.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 3.75 per cent of (a+b+c)

e)

Quantity

5131.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a)

Material
tonne

47.95

5789.47

277605.26

Coarse sand

cum

54.00

203.75

11002.74

40 mm Aggregate

cum

43.20

758.35

32760.89

20 mm Aggregate

cum

43.20

862.50

37260.09

10 mm Aggregate

cum

21.60

655.60

14161.02

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

234.36

1406.16

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

hour

Concrete Pump

3539.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

15922.50
110130.63
55065.31

Contractor's profit @ 0.1 on (a+b+c+d+e)

605718.44

cost of 120 cum = a+b+c+d+e+f

5047.65

Rate per cum = (a+b+c+d+e+f)/120


say

12.8

E
Case I

5048.00

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.05

5789.47

35026.32

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)

189

3621.00

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

2036.42

Formwork @ 3.75 per cent of a+b+c.

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

14085.21
7042.60
77468.64

cost of 15 cum = a+b+c+d+e+f

5164.58

Rate per cum (a+b+c+d+e+f )/15


say

12.8 E

Cost Rs

5165.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit: cum
Taking Output = 120 cum
a)

Material
Cement

b)

c)

tonne

48.38

5789.47

280094.74

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

6.00

2488.00

14928.00

6.00

1698.00

10188.00

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

Loader 1 cum capacity 1 cum

hour

6.00

Transit Mixer 4 cum capacity for lead upto 1 km.

hour
tonne.km

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

hour

Concrete Pump

7128.00

15.00

854.55

12818.25

300L

4.32

1296.00

6.00

234.36

1406.16

3560.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3.75 per cent on cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

1188.00

16016.99
110784.16
55392.08

Contractor's profit @ 0.1 on (a+b+c+d+e)

609312.88

cost of 120 cum = a+b+c+d+e+f

5077.61

Rate per cum (a+b+c+d+e+f )/120


say

12.8

F
Case I

5078.00

PCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.08

5789.47

35200.00

Coarse sand

cum

6.75

203.75

1375.34

40 mm Aggregate

cum

5.40

758.35

4095.11

20 mm Aggregate

cum

5.40

862.50

4657.51

10 mm Aggregate

cum

2.70

655.60

1770.13

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost
of material, labour and machinery

190

3632.00
1906.60

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

14095.23
7047.62
77523.78

cost of 15 cum = a+b+c+d+e+f

5168.25

Rate per cum (a+b+c+d+e+f )/15


say

12.8 F

Cost Rs

5168.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a)

Material
tonne

48.60

5789.47

281368.42

Coarse sand

cum

54.00

203.75

11002.74

40 mm Aggregate

cum

43.20

758.35

32760.89

20 mm Aggregate

cum

43.20

862.50

37260.09

10 mm Aggregate

cum

21.60

655.60

14161.02

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

6.00

2488.00

14928.00

6.00

1698.00

10188.00

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

Loader 1 cum capacity

hour

6.00

Transit Mixer 4 cum capacity for lead upto 1 km.

hour
tonne.km

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

hour

Concrete Pump

7128.00

15.00

854.55

12818.25

300L

4.32

1296.00

6.00

234.36

1406.16

3570.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

1188.00

14992.71
110838.97
55419.48

Contractor's profit @ 0.1 on (a+b+c+d+e)

609614.32

cost of 120 cum = a+b+c+d+e+f

5080.12

Rate per cum (a+b+c+d+e+f )/120


say

12.8

G
Case I

5080.00

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.10

5789.47

35315.79

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)

191

3640.00
1910.79
14126.17

Sr No

Ref. to
MoRTH
Spec.

Description
f)

Unit

Quantity

Rate Rs

7063.08

Contractor's profit @ 0.1 on (a+b+c+d+e)

77693.93

cost of 15 cum = a+b+c+d+e+f

5179.60

Rate per cum = (a+b+c+d+e+f)/15


say

12.8 G

Case II

Cost Rs

5180.00

Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.80

5789.47

282526.32

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

6.00

234.36

1406.16

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead
in Kilometer

hour

Concrete Pump

3580.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

15034.29
111146.38
55573.19

Contractor's profit @ 0.1 on (a+b+c+d+e)

611305.10

cost of 120 cum = a+b+c+d+e+f

5094.21

Rate per cum (a+b+c+d+e+f )/120


say

12.8

H
Case I

5094.00

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
Cement

b)

c)

d)

tonne

6.33

5789.47

36647.37

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 3 per cent on a+b+c

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3729.00
1677.76
14400.81
7200.40
79204.44

cost of 15 cum = a+b+c+d+e+f

5280.30

Rate per cum = (a+b+c+d+e+f)/15


192

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.8 H

Cost Rs
5280.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit ; cum
Taking Output = 120 cum
a)

Material
tonne

50.64

5789.47

293178.95

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader1 cum capacity

hour

6.00

1188.00

7128.00

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

6.00

234.36

1406.16

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead
in Kilometer

hour

Concrete Pump

3669.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

13206.12
113352.49
56676.25

Contractor's profit @ 0.1 on (a+b+c+d+e)

623438.72

cost of 120 cum = a+b+c+d+e+f

5195.32

Rate per cum = (a+b+c+d+e+f)/120


say

Note:

5195.00

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.

WELL FOUNDATION
12.9

1200

Providing and Constructing Temporary Island 16 m


diameter for Construction of Well Foundation for 8m dia.
Well.
A

Assuming depth of water 1.0 m and height of island to be


1.25 m including Royality for earth @ Rs. 3768.00 for
each Island.
Unit = 1 No
Taking output = 1 No.
a)

b)

c)

Material
Earth (compacted)

cum

251.20

25.1

6305.12

Sand bags

each

750.00

1.73

1298.57

Mate

day

0.40

185.07

74.03

Mazdoor for filling sand bags, stitching and placing

day

15.00

177.07

2656.05

hour

20.00

784.62

15692.40

Labour

Machinery
Crane with grab 1 cum capacity

392.31

Consumables @ 2.5 per cent of (c) above


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6604.62
3302.31
36325.41

Rate per No. (a+b+c+d+e)


say

Note

It is assumed that earth will be available within the working


space of crane with grab bucket.
193

36325.00

Sr No

Ref. to
MoRTH
Spec.

12.9

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Assuming depth of water 4.0 m and height of island 4.5 m


including Royality for earth @ Rs. 13565.00 for each
Island.
Unit = 1No
Taking output = 1 No
a)

b)

c)

Material
Earth (compacted)

cum

904.32

25.10

22698.43

Sand bags

each

Wooden ballies 8" Dia and 9 m long

each

6000.00

1.73

10388.57

95.00

49.23

Wooden ballies 2" Dia for bracing

metre

4676.82

190.00

17.81

3383.23

Labour
Mate

day

5.60

185.07

1036.39

Mazdoor for piling 8" dia ballies for piling 8" dia ballies

day

18.00

177.07

3187.26

Mazdoor for bracing with 2" dia ballies

day

12.00

177.07

2124.84

Mazdoor for filling sand bags, stitching and placing

day

110.00

177.07

19477.70

hour

50.00

784.62

39231.00

Machinery
Crane with grab 1 cum capacity

2655.11

Consumables and other arrangements for piling ballies @ 2.5


per cent of (a+b+c).
d) Overhead charges @ 0.25 on (a+b+c)

27214.84

e)

13607.42

Contractor's profit @ 0.1 on (a+b+c+d)

149681.62

Rate per No. (a+b+c+d+e)


say

Note

12.9

149682.00

For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
Providing and constructing one span service road to
reach island location from one pier location to another
pier location including Royality for earth @ Rs. 225.00 per
m for service Road.
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a)

b)

c)

Material
Earth

cum

450.00

25.10

11295.00

Sand bags

each

300.00

1.73

519.43

Mate

day

0.24

185.07

44.42

Mazdoor for filling sand bags, stitching and placing

day

6.00

177.07

1062.42

Front end Loader 1 cum capacity

hour

27.00

1188.00

32076.00

Tipper 5.5 cum capacity

hour

28.00

873.00

24444.00

Labour

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

17360.32
8680.16
95481.74

Cost for 30 m (a+b+c+d+e)

3182.72

Rate per m (a+b+c+d+e)/30


say

12.10

1200 &
1900

3183.00

Providing and Laying Cutting Edge of Mild Steel weighing


40 kg per metre for Well Foundation complete as per
Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a)

Material
Structural steel in plates, angles, etc including 5 per
cent wastage
Nuts & bolts

194

tonne
Kg

1.05

46527.33

48853.70

20.00

45.42

908.43

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

(for cutting, bending, making holes, joining, welding and


erecting in position)
Mate

day

1.32

185.07

244.29

Fitter

day

5.50

238.29

1310.60

Blacksmith

day

5.50

234.29

1288.60

Welder

day

5.50

234.29

1288.60

Mazdoor

day

16.50

177.07

2921.66

b)

Quantity

Rate Rs

Labour

4976.21

Electrodes, cutting gas and other consumables @ 10 per cent


of cost of (a) above
c) Overhead charges @ 0.25 on (a+b)
d)

15448.02
7724.01

Contractor's profit @ 0.1 on (a+b+c)

84964.11

Rate per MT (a+b+c+d)


say

12.11

1200,
1500 &
1700

Cost Rs

84964.00

Plain/Reinforced Cement Concrete, in Well Foundation


complete as per Drawing and Technical Specification.
Unit = 1 cum
Taking output = 1 cum
A

Well curb

(i)

RCC M20 Grade

Case I

Same as for 12.8 (C) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
3297.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


formwork @ 20 per cent of the cost of concrete

659.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

989.10

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

494.55
5440.05

Rate perm (a+b+c+d+e+f)


say

12.11 A (i)

3234.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 20 per cent of the cost of concrete

646.80

e)

Overhead charges @ 0.25 on (a+b+c+d)

970.20

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

485.10
5336.10

Rate perm (a+b+c+d+e+f)


say

12.11 A

5440.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(ii)

5336.00

RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.75 per cent.

Case I

Using Concrete Mixer


3621.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

724.20

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1086.30
543.15
5974.65

Rate perm (a+b+c+d+e+f)


say

12.11 A
(ii)

5975.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3560.00
712.00
1068.00
534.00
5874.00

Rate perm (a+b+c+d+e+f)

195

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.11 A

(iii)

Cost Rs
5874.00

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.0 per cent.

Case I

Using Concrete Mixer


3729.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

745.80
1118.70
559.35
6152.85

Rate perm (a+b+c+d+e+f)


say

12.11 A
(iii)

Case II With Batching Plant, Transit Mixer and Concrete Pump


3859.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

771.80
1157.70
578.85
6367.35

Rate perm (a+b+c+d+e+f)


say

Note.

12.11

Well steining
PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
2887.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

288.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

793.93

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

396.96
4366.59

Rate perm (a+b+c+d+e+f)


say

(ii)

6367.00

If curb concrete is carried out within steel liner, cost of


formwork shall be excluded.

(I)

Case I

12.11 B

6153.00

4367.00

PCC M20 Grade


Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


3277.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

327.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

901.18

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

450.59
4956.46

Rate perm (a+b+c+d+e+f)


say

12.11 B

(iii)

4956.00

RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


3297.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

329.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

906.68

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

453.34
4986.71

Rate perm (a+b+c+d+e+f)


say

196

4987.00

Sr No
12.11 B
(iii)

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Case II With Batching Plant, Transit Mixer and Concrete Pump


3234.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

323.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

889.35

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

444.68
4891.43

Rate perm (a+b+c+d+e+f)


say

12.11 B

(iv)

Case I

Same as for 12.8 (D) except for formwork which shall be @


10 per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
3597.00

d)

formwork @ 10 per cent of the cost of concrete

359.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

989.18

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

494.59
5440.46

Rate perm (a+b+c+d+e+f)


say

5440.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


3538.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


formwork @ 10 per cent of the cost of concrete

353.80

e)

Overhead charges @ 0.25 on (a+b+c+d)

972.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

486.48
5351.23

Rate perm (a+b+c+d+e+f)


say

'12.11 B

4891.00

PCC M25 Grade

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 B
(iv)

Cost Rs

(v)

5351.00

RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


3621.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

362.10

e)

Overhead charges @ 0.25 on (a+b+c+d)

995.78

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

497.89
5476.76

Rate perm (a+b+c+d+e+f)


say

12.11 B
(v)

3560.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

356.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

979.00

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

489.50
5384.50

Rate perm (a+b+c+d+e+f)


say

'12.11 B

5477.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(vi)

5385.00

PCC M30 Grade


Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

3632.00

formwork @ 10 per cent of the cost of concrete

363.20

e)

Overhead charges @ 0.25 on (a+b+c+d)

998.80

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

499.40
5493.40

Rate perm (a+b+c+d+e+f)

197

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.11 B
(vi)

5493.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


3569.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

356.90

e)

Overhead charges @ 0.25 on (a+b+c+d)

981.48

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

490.74
5398.11

Rate perm (a+b+c+d+e+f)


say

'12.11 B

Cost Rs

(vii)

5398.00

RCC M30 Grade


Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


3640.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

364.00
1001.00
500.50
5505.50

Rate perm (a+b+c+d+e+f)


say

12.11 B
(vii)

Case II With Batching Plant, Transit Mixer and Concrete Pump


3580.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

358.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

984.50

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

492.25
5414.75

Rate perm (a+b+c+d+e+f)


say

'12.11 B

5506.00

(viii)

5415.00

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Case I

Using Concrete Mixer


3729.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

372.90

formwork @ 10 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1025.48
512.74
5640.11

Rate perm (a+b+c+d+e+f)


say

12.11 B
(viii)

Case II With Batching Plant, Transit Mixer and Concrete Pump


3859.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

385.90

formwork @ 10 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1061.23
530.61
5836.74

Rate perm (a+b+c+d+e+f)


say

'12.11 B

5640.00

(ix)

5837.00

RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

51.60

5789.47

298736.84

Coarse Sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

Cement

198

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
cum

10 mm Aggregate

kg

Admixture
b)

c)

Rate Rs

43.20

655.60

28322.05

206.00

112.77

23230.84

0.84

185.07

155.46

Mate

day

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Machinery
Batching Plant

hour

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

854.55

12818.25

4.32

1296.00

234.36

1406.16

Transit Mixer 4 cum capacity for lead beyond 1 km.


Concrete Pump

6.00

hour

15.00

tonne.km

300xL

hour

6.00
3909.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 10 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)

46899.26
128972.96
64486.48

Contractor's profit @ 0.1 on (a+b+c+d+e)

cost of 120 cum = a+b+c+d+e+f

709351.30
5911.26

Rate per cum = (a+b+c+d+e+f)/120


say

12.11 C

Cost Rs

Labour

Transit Mixer 4 cum capacity for lead upto 1 km.

f)

Quantity

5911.00

Bottom Plug
Concrete to be placed using tremie pipe

(i)
Case I

Note: 10% extra cement to be added where under water


concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.55

5789.47

32131.58

Coarse sand

cum

6.75

203.75

1375.34

40 mm Aggregate

cum

5.40

758.35

4095.11

20 mm Aggregate

cum

5.40

862.50

4657.51

10 mm Aggregate

cum

2.70

655.60

1770.13

Kg

18.60

112.77

2097.54

Mate

day

0.90

185.07

166.56

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Light Crane 3 tonnes capacity for handling tremie pipe

hour

6.00

535.00

3210.00

Cement

Admixture
b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3782.00
2509.33

14807.55
7403.77
81441.50

cost of 15 cum = a+b+c+d+e

5429.43

Rate per cum = (a+b+c+d+e)/15


say

12.11 C
(i)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump

199

5429.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Unit ; cum
Taking Output = 120 cum
a)

Material
tonne

44.40

5789.47

257052.63

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Kg

148.80

112.77

16780.33

Mate

day

0.88

185.07

162.86

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

6.00

2488.00

14928.00

6.00

1698.00

10188.00

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

Loader 1 cum capacity

hour

6.00

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer


Concrete Pump

1188.00

7128.00

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

1406.16

3508.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

18655.04

109880.08
54940.04
604340.45

cost of 120 cum = a+b+c+d+e

5036.17

Rate per cum = (a+b+c+d+e)/120


say

'12.11 C

(ii)
Case I

5036.00

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.99

5789.47

34678.95

Coarse sand

cum

6.75

203.75

1375.34

40 mm Aggregate

cum

5.40

758.35

4095.11

20 mm Aggregate

cum

5.40

862.50

4657.51

10 mm Aggregate

cum

2.70

655.60

1770.13

Kg

21.60

112.77

2435.85

Mate

day

0.90

185.07

166.56

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Light Crane of 3 tonnes capacity for handling tremie pipe

hour

6.00

535.00

3210.00

Cement

Admixture
b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

200

3974.00
2653.61

15565.04
7782.52

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

85607.70

cost of 15 cum = a+b+c+d+e

5707.18

Rate per cum = (a+b+c+d+e)/15


say

12.11 C
(ii)

Cost Rs

5707.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

47.88

5789.47

277200.00

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

Cement

43.20

655.60

28322.05

Kg

172.80

112.77

19486.84

Mate

day

0.88

185.07

162.86

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

6.00

234.36

1406.16

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

hour

Concrete Pump

3698.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

19797.74

115879.22
57939.61
637335.73

cost of 120 cum = a+b+c+d+e

5311.13

Rate per cum = (a+b+c+d+e)/120


say

'12.11 C

(iii)
Case I

5311.00

PCC Grade M30


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

Material
tonne

6.08

5789.47

35200.00

Coarse sand

cum

6.75

203.75

1375.34

40 mm Aggregate

cum

5.40

758.35

4095.11

20 mm Aggregate

cum

5.40

862.50

4657.51

10 mm Aggregate

cum

Cement

2.70

655.60

1770.13

Kg

21.60

112.77

2435.85

Mate

day

0.90

185.07

166.56

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Light Crane of 3 tonnes capacity for handling tremie pipe

hour

6.00

535.00

3210.00

Admixture
b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)

201

4009.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

2679.67

Add 5 per cent of cost of material and labour towards cost of


forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

15701.81
7850.91
86359.97

cost of 15 cum = a+b+c+d+e

5757.33

Rate per cum = (a+b+c+d+e)/15


say

12.11 C
(iii)

Cost Rs

5757.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.64

5789.47

281600.00

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Kg

172.80

112.77

19486.84

Mate

day

0.88

185.07

162.86

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

6.00

2488.00

14928.00

6.00

1698.00

10188.00

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

Loader 1 cum capacity

hour

6.00

Transit Mixer 4 cum capacity for lead upto 1 km.

hour
tonne.km

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

hour

Concrete Pump

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

7128.00

15.00

854.55

12818.25

300L

4.32

1296.00

6.00

234.36

1406.16

3735.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

1188.00

20017.74

117034.22
58517.11
643688.23

cost of 120 cum = a+b+c+d+e

5364.07

Rate per cum = (a+b+c+d+e)/120


say

'12.11 C

(iv)
Case I

5364.00

PCC Grade M35


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

Material
tonne

6.29

5789.47

36415.79

Coarse sand

cum

6.75

203.75

1375.34

40 mm Aggregate

cum

5.40

758.35

4095.11

20 mm Aggregate

cum

5.40

862.50

4657.51

10 mm Aggregate

cum

Cement

2.70

655.60

1770.13

Kg

21.60

112.77

2435.85

Mate

day

0.90

185.07

166.56

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

hour

6.00

211.68

1270.08

Admixture
b)

c)

Labour

Machinery
Concrete mixer (cap. 0.40/0.28 cum)
202

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Generator 33 KVA

hour

6.00

342.36

2054.16

Light Crane of 3 tonnes capacity for handling tremie pipe

hour

6.00

535.00

3210.00

4090.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2740.46

16020.96
8010.48
88115.27

cost of 15 cum = a+b+c+d+e

5874.35

Rate per cum = (a+b+c+d+e)/15


say

12.11 C
(iv)

Cost Rs

5874.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

50.28

5789.47

291094.74

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Kg

172.80

112.77

19486.84

Mate

day

0.88

185.07

162.86

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

6.00

234.36

1406.16

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

hour

Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3814.00
20492.47

119526.59
59763.30
657396.25

cost of 120 cum = a+b+c+d+e

5478.30

Rate per cum = (a+b+c+d+e)/120


say

12.11

Intermediate plug

(i)

Grade M20 PCC

5478.00

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Case I

Using Concrete Mixer


3782.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

945.50
472.75
5200.25

Rate per cum = (a+b+c+d+e)


say

12.11 D
(i)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump

203

5200.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

3508.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

877.00
438.50
4823.50

Rate per cum = (a+b+c+d+e)


say

'12.11 D

(ii)

Cost Rs

4824.00

Grade M25 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.

Case I

Using Concrete Mixer


3974.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

993.50
496.75
5464.25

Rate per cum = (a+b+c+d+e)


say

12.11 D
(ii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3698.00
924.50
462.25
5084.75

Rate per cum = (a+b+c+d+e)


say

'12.11 D

(iii)

Case I

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

4009.00

d)

Overhead charges @ 0.25 on (a+b+c)

1002.25

e)

Contractor's profit @ 0.1 on (a+b+c+d)

501.13
5512.38
say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

933.75
466.88
5135.63
say

Top plug

(i)

Grade M15 PCC

5512.00

3735.00

Rate per cum = (a+b+c+d+e)


12.11

5085.00

Grade M30 PCC

Rate per cum = (a+b+c+d+e)


12.11 D
(iii)

5464.00

5136.00

Same as Item 12.8(a) excluding formwork


Case I

Using Concrete Mixer


2887.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

721.75

e)

Contractor's profit @ 0.1 on (a+b+c+d)

360.88
3969.63

Rate per cum = (a+b+c+d+e)


say

3970.00

Same as Item 12.8(b) excluding formwork


Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

3277.00

d)

Overhead charges @ 0.25 on (a+b+c)

819.25

e)

Contractor's profit @ 0.1 on (a+b+c+d)

409.63
4505.88

Rate per cum = (a+b+c+d+e)

204

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

Same as Item 12.8 (d)


Case I

excluding formwork
3597.00

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

899.25
449.63
4945.88

Rate per cum = (a+b+c+d+e)


say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

884.50
442.25
4864.75
say

(iv)

4946.00

3538.00

Rate per cum = (a+b+c+d+e)


'12.11 E

4506.00

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 E
(iii)

Cost Rs

4865.00

Grade M30 PCC


Same as Item 12.8(f) excluding formwork

Case I

Using Concrete Mixer


3632.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

908.00

e)

Contractor's profit @ 0.1 on (a+b+c+d)

454.00
4994.00

Rate per cum = (a+b+c+d+e)


say

12.11 E
(iv)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

3569.00

d)

Overhead charges @ 0.25 on (a+b+c)

892.25

e)

Contractor's profit @ 0.1 on (a+b+c+d)

446.13
4907.38

Rate per cum = (a+b+c+d+e)


say

12.11

F
(i)
Case I

4994.00

4907.00

Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.12

5789.47

29642.11

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

1956.81

Form Work @ 4 per cent of a+b+c


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12719.25
6359.63
69955.89

cost of 15 cum = a+b+c+d+e

4663.73

Rate per cum = (a+b+c+d+e)/15


say

205

4664.00

Sr No
12.11 F (i)

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

40.92

5789.47

236905.26

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

6.00

2488.00

14928.00

6.00

1698.00

10188.00

1188.00

7128.00

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

Loader (capacity 1 cum)

hour

6.00

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

Formwork @ 4 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

99821.85

e)

Contractor's profit @ 0.1 on (a+b+c+d)

49910.92
549020.15

cost of 120 cum = a+b+c+d+e

4575.17

Rate per cum = (a+b+c+d+e)/120


say

12.11 F

(ii)
Case I

1406.16
15357.21

4575.00

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.05

5789.47

35026.32

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

2036.42

Form Work @ 3.75 per cent of a+b+c


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14085.21
7042.60
77468.64

cost of 15 cum = a+b+c+d+e

5164.58

Rate per cum = (a+b+c+d+e)/15


say

12.11 F
(ii)

5165.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
Cement
Coarse sand
206

tonne

48.40

5789.47

280210.53

cum

54.00

203.75

11002.74

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

Cost Rs

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader (capacity 1 cum)

hour

6.00

1188.00

7128.00

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

16021.33

d)

Overhead charges @ 0.25 on (a+b+c)

110814.19

e)

Contractor's profit @ 0.1 on (a+b+c+d)

55407.10
609478.06

cost of 120 cum = a+b+c+d+e

5078.98

Rate per cum = (a+b+c+d+e)/120


say

12.11 F

(iii)
Case I

1406.16

Formwork @ 3.75 per cent of ( a+b+c)

5079.00

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.10

5789.47

35315.79

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

1910.79

Formwork @ 3.5 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14126.17
7063.08
77693.93

cost of 15 cum = a+b+c+d+e

5179.60

Rate per cum = (a+b+c+d+e)/15


say

12.11 F
(iii)

5180.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.79

5789.47

282468.42

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Cement

b)

Labour

207

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Unit

Quantity

Rate Rs

Cost Rs

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader (capacity 1 cum)

hour

6.00

1188.00

7128.00

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

1406.16
15032.27

Formwork @ 3.5 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

111131.40
55565.70
611222.70

cost of 120 cum = a+b+c+d+e

5093.52

Rate per cum = (a+b+c+d+e)/120


say

12.11 F

(iv)
Case I

5094.00

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.33

5789.47

36647.37

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.86

185.07

159.16

Mason

day

1.50

234.29

351.44

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

1677.76

Formwork @ 3 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14400.81
7200.40
79204.44

cost of 15 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/15

5280.30
say

12.11 F
(iv)

5280.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

50.64

5789.47

293178.95

Coarse sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader (capacity 1 cum)

hour

6.00

1188.00

7128.00

hour

15.00

854.55

12818.25

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.

208

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Lead beyond 1 Km, L - lead in Kilometer


Concrete Pump

Quantity

Rate Rs

tonne.km

300L

4.32

hour

6.00

234.36

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

56676.25
623438.72
5195.32

Rate per cum = (a+b+c+d+e)/120


say

(v)

1406.16

113352.49

cost of 120 cum = a+b+c+d+e

'12.11 F

1296.00

13206.12

Formwork @ 3 per cent of (a+b+c)

Note

Cost Rs

5195.00

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

52.20

5789.47

302210.53

Coarse Sand

cum

54.00

203.75

11002.74

20 mm Aggregate

cum

64.80

862.50

55890.13

10 mm Aggregate

cum

43.20

655.60

28322.05

206.00

112.77

23230.84

0.84

185.07

155.46

Cement

kg

Admixture
b)

c)

Labour
Mate

day

Mason

day

3.00

234.29

702.87

Mazdoor

day

18.00

177.07

3187.26

Machinery
Batching Plant

hour

2488.00

14928.00

Generator 100 KVA

hour

6.00

1698.00

10188.00

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity for lead beyond 1 km.
Concrete Pump

d)

Formwork @ 3 per cent on cost of concrete i.e. cost of


material, labour and machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6.00

hour

15.00

854.55

12818.25

tonne.km

300.L

4.32

1296.00

hour

6.00

234.36

1406.16
14173.99
121660.07
60830.03
669130.37

cost of 120 cum = a+b+c+d+e

5576.09

Rate per cum = (a+b+c+d+e)/120


say

12.12

Section
1200

5576.00

Sinking of 6 m external diameter well (other than


pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.50 m per hour.
a)

Labour
Mate

day

0.12

185.07

22.21

Sinker ( skilled )

day

1.00

206.99

206.99

209

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Sinking helper ( semi-skilled )


b)

Quantity

Rate Rs

day

2.00

180.07

360.14

hour

2.00

1176.12

2352.24

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

235.22
794.20

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

397.10
4368.10

Rate per metre = (a+b+c+d)


say

12.12 A

(ii)

Cost Rs

4368.00

Beyond 3m upto 10m depth


Rate of sinking = 0.33 m per hour.
a)

b)

Labour
Mate

day

0.15

185.07

27.76

Sinker

day

1.25

206.99

258.74

Sinking helper ( semi-skilled )

day

2.50

180.07

450.18

hour

3.00

1176.12

3528.36

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b)

352.84
1154.47

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

577.23
6349.57

Rate per metre = (a+b+c+d)


say

12.12 A

(iii)
a

12.12 A

(iv)
a
b

12.12 A

(v)

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

6668.00

12th m

5%

7001.00

13th m

5%

7351.00

14th m

5%

7719.00

15th m

5%

8105.00

16th m

5%

8510.00

17th m

5%

8936.00

18th m

5%

9383.00

19th m

5%

9852.00

20th m

5%

10345.00

Total Cost from 10m upto 20m

83870.00

Avg Rate per metre

8387.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge

21st m

7.5%

11121.00

13345.00

22nd m

7.5%

11955.00

14346.00

23rd m

7.5%

12852.00

15422.00

24th m

7.5%

13816.00

16579.00

25th m

7.5%

14852.00

17822.00

26th m

7.5%

15966.00

19159.00

27th m

7.5%

17163.00

20596.00

28th m

7.5%

18450.00

22140.00

29th m

7.5%

19834.00

23801.00

30th m

7.5%

21322.00

25586.00

Total Cost from 20m upto 30m

157331.00

188796.00

Avg Rate per metre

15733.00

18880.00

Beyond 30m upto 40 m

210

6350.00

Sr No

Ref. to
MoRTH
Spec.

Description
a
b

12.12

Unit

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

Quantity

(a)

Rate Rs

Cost Rs

(b)Including
20% for
Kentledge

31st m

10%

23454.00

28145.00

32nd

10%

25799.00

30959.00

33rd m

10%

28379.00

34055.00

34th m

10%

31217.00

37460.00

35th m

10%

34339.00

41207.00

36th m

10%

37773.00

45328.00

37th m

10%

41550.00

49860.00

38th m

10%

45705.00

54846.00

39th m

10%

50276.00

60331.00

40th m

10%

55304.00

66365.00

Total Cost from 30m upto 40m

373796.00

448556.00

Avg Rate per metre

37380.00

44856.00

Clayey Soil ( 6m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.33 m per hour.
a)

b)

Labour
Mate

day

0.15

185.07

27.76

Sinker ( skilled )

day

1.50

206.99

310.49

Sinking helper ( semi-skilled )

day

2.25

180.07

405.16

hour

3.00

1176.12

3528.36

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b)

352.84
1156.15

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

578.07

Rate per metre = (a+b+c+d)

6358.82
say

12.12 B

(ii)

6359.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.30

185.07

55.52

Sinker

day

3.00

206.99

620.97

Sinking helper ( semi-skilled )

day

4.50

180.07

810.32

hour

6.00

1176.12

7056.72

hour

2.00

513.00

1026.00

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

808.27

c)

Overhead charges @ 0.25 on (a+b)

2594.45

d)

Contractor's profit @ 0.1 on (a+b+c)

1297.22
14269.47

Rate per metre = (a+b+c+d)


say

12.12 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a) (b)Including for


dewatering @
5% of cost, if
required

11th m

5%

14982.00

15731.00

12th m

5%

15731.00

16518.00

211

14269.00

Sr No

12.12 B

12.12 B

12.12

Ref. to
MoRTH
Spec.

Description

(iv)

Unit

Rate Rs

13th m

5%

16518.00

17344.00

14th m

5%

17344.00

18211.00

15th m

5%

18211.00

19122.00

16th m

5%

19122.00

20078.00

17th m

5%

20078.00

21082.00

18th m

5%

21082.00

22136.00

19th m

5%

22136.00

23243.00

20th m

5%

23243.00

24405.00

Total Cost from 10m upto 20m

188447.00

197870.00

Avg Rate per metre

18845.00

19787.00

Cost Rs

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering of the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(a)

(c)Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

21st m

7.5%

24986.00

31233.00

32795.00

22nd m

7.5%

26860.00

33575.00

35254.00

23rd m

7.5%

28875.00

36094.00

37899.00

24th m

7.5%

31041.00

38801.00

40741.00

25th m

7.5%

33369.00

41711.00

43797.00

26th m

7.5%

35872.00

44840.00

47082.00

27th m

7.5%

38562.00

48203.00

50613.00

28th m

7.5%

41454.00

51818.00

54409.00

29th m

7.5%

44563.00

55704.00

58489.00

30th m

7.5%

47905.00

59881.00

62875.00

Total Cost from 20m upto 30m

353487.00

441860.00

463954.00

Avg Rate per metre

35349.00

44186.00

46395.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Quantity

(a)

(b) Including (b)Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

52696.00

63235.00

66397.00

32nd

10%

57966.00

69559.00

73037.00

33rd m

10%

63763.00

76516.00

80342.00

34th m

10%

70139.00

84167.00

88375.00

35th m

10%

77153.00

92584.00

97213.00

36th m

10%

84868.00

101842.00

106934.00

37th m

10%

93355.00

112026.00

117627.00

38th m

10%

102691.00

123229.00

129390.00

39th m

10%

112960.00

135552.00

142330.00

40th m

10%

124256.00

149107.00

156562.00

Total Cost from 30m upto 40m

839847.00

1007817.00

1058207.00

Avg Rate per metre

83985.00

100782.00

105821.00

Soft Rock (6m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a)

Labour
Mate

day

0.92

185.07

170.26

Sinker ( skilled )

day

3.00

206.99

620.97

212

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

Sinking helper ( semi-skilled )

day

20.00

180.07

3601.40

Diver

day

0.50

206.99

103.50

hour

4.00

1176.12

4704.48

hour

3.50

513.00

1795.50

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

650.00

Add for dewatering @ of 5 per cent of (a+b), if required

582.31
3057.10

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1528.55
16814.07

Rate per metre = (a+b+c+d)


say

12.12

Cost Rs

16814.00

Hard Rock (6m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

4.00

112.77

451.08

Electric Detonators

each

18.00

14.27

256.79

Mate

day

1.56

185.07

288.71

Driller

day

2.00

206.99

413.98

Blaster

day

0.25

289.31

72.33

Mazdoor

day

12.00

177.07

2124.84

Mazdoor (Skilled)

day

4.00

206.99

827.96

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.

hour

6.00

1176.12

7056.72

Hire & running charges of compressor with pneumatic


breaker/Jack hammer for drilling.

hour

2.00

513.00

1026.00

Labour

Machinery

590.53

Dewatering @ 5 per cent of cost of (b+c), if required.

808.27

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3479.30
1739.65
19136.16

Rate per metre = (a+b+c+d+e)


say

12.13

Section
1200

19136.00

Sinking of 7 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.30 m per hour.
a)

b)

Labour
Mate

day

0.15

185.07

27.76

Sinker ( skilled )

day

1.25

206.99

258.74

Sinking helper ( semi-skilled )

day

2.50

180.07

450.18

hour

3.25

1176.12

3822.39

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

213

382.24

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

1235.33

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

617.66
6794.29

Rate per metre = (a+b+c+d)


say

12.13 A

(ii)

Cost Rs

6794.00

Beyond 3m upto 10m depth


Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

0.18

185.07

33.31

Sinker

day

1.50

206.99

310.49

Sinking helper ( semi-skilled )

day

3.00

180.07

540.21

hour

4.50

1176.12

5292.54

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

529.25
1676.45

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

838.23
9220.48

Rate per metre = (a+b+c+d)


say

12.13 A

(iii)
a

12.13 A

(iv)
a
b

12.13 A

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

9682.00

12th m

5%

10166.00

13th m

5%

10674.00

14th m

5%

11208.00

15th m

5%

11768.00

16th m

5%

12356.00

17th m

5%

12974.00

18th m

5%

13623.00

19th m

5%

14304.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre

12177.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

(a)

(b)Including
20% for
Kentledge

21st m

7.5%

16145.00

19374.00

22nd m

7.5%

17356.00

20827.00

23rd m

7.5%

18658.00

22390.00

24th m

7.5%

20057.00

24068.00

25th m

7.5%

21561.00

25873.00

26th m

7.5%

23178.00

27814.00

27th m

7.5%

24916.00

29899.00

28th m

7.5%

26785.00

32142.00

29th m

7.5%

28794.00

34553.00

30th m

7.5%

30954.00

37145.00

Total Cost from 20m upto 30m

228404.00

274085.00

Avg Rate per metre

22840.00

27409.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

15019.00
121774.00

(a)

(b)Including
20% for
Kentledge

31st m

10%

34049.00

40859.00

32nd

10%

37454.00

44945.00

214

9220.00

Sr No

12.13

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

33rd m

10%

41199.00

49439.00

34th m

10%

45319.00

54383.00

35th m

10%

49851.00

59821.00

36th m

10%

54836.00

65803.00

37th m

10%

60320.00

72384.00

38th m

10%

66352.00

79622.00

39th m

10%

72987.00

87584.00

40th m

10%

80286.00

96343.00

Total Cost from 30m upto 40m

542653.00

651183.00

Avg Rate per metre

54265.00

65118.00

Cost Rs

Clayey Soil ( 7m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(I)

Depth below bed level upto 3.0 M


Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

0.18

185.07

33.31

Sinker ( skilled )

day

1.50

206.99

310.49

Sinking helper ( semi-skilled )

day

3.00

180.07

540.21

hour

4.50

1176.12

5292.54

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

529.25
1676.45

d)

Overhead charges @ 0.25 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+c)

838.23
9220.48

Rate per metre = (a+b+c+d)


say

12.13 B

(ii)

9220.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.26

185.07

48.12

Sinker

day

2.00

206.99

413.98

Sinking helper ( semi-skilled )

day

4.00

180.07

720.28

hour

6.00

1176.12

7056.72

hour

3.25

513.00

1667.25

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

872.40
2694.69

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1347.34
14820.77

Rate per metre = (a+b+c+d)


say

12.13 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

(b) Including
for dewatering
@ 5% of cost,
if required

11th m

5%

15562.00

16340.00

12th m

5%

16340.00

17157.00

13th m

5%

17157.00

18015.00

14th m

5%

18015.00

18916.00

15th m

5%

18916.00

19862.00

16th m

5%

19862.00

20855.00

17th m

5%

20855.00

21898.00

18th m

5%

21898.00

22993.00

215

14821.00

Sr No

12.13 B

Ref. to
MoRTH
Spec.

Description

(iv)
a
b
c

12.13 B

19th m

5%

20th m

5%

Cost Rs

24143.00

24143.00

25350.00
205529.00

Avg Rate per metre

19574.00

20553.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

( c) Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

31st m

7.5%

25954.00

32443.00

34065.00

32nd

7.5%

27901.00

34876.00

36620.00

33rd m

7.5%

29994.00

37493.00

39368.00

34th m

7.5%

32244.00

40305.00

42320.00

35th m

7.5%

34662.00

43328.00

45494.00

36th m

7.5%

37262.00

46578.00

48907.00

37th m

7.5%

40057.00

50071.00

52575.00

38th m

7.5%

43061.00

53826.00

56517.00

39th m

7.5%

46291.00

57864.00

60757.00

40th m

7.5%

49763.00

62204.00

65314.00

Total Cost from 30m upto 40m

367189.00

458988.00

481937.00

Avg Rate per metre

36719.00

45899.00

48194.00

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

22993.00

Rate Rs

195741.00

Beyond 30m upto 40 m

Quantity

Total Cost from 10m upto 20m

(v)

12.13

Unit

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

( c) Including (b) Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

54739.00

65687.00

68971.00

32nd

10%

60213.00

72256.00

75869.00

33rd m

10%

66234.00

79481.00

83455.00

34th m

10%

72857.00

87428.00

91799.00

35th m

10%

80143.00

96172.00

100981.00

36th m

10%

88157.00

105788.00

111077.00

37th m

10%

96973.00

116368.00

122186.00

38th m

10%

106670.00

128004.00

134404.00

39th m

10%

117337.00

140804.00

147844.00

40th m

10%

129071.00

154885.00

162629.00

Total Cost from 30m upto 40m

872394.00

1046873.00

1099215.00

Avg Rate per metre

87239.00

104687.00

109922.00

0.58

185.07

107.34

Soft Rock ( 7m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

Sinker ( skilled )

day

4.00

206.99

827.96

Sinking helper ( semi-skilled )

day

10.00

180.07

1800.70

Diver

day

0.75

206.99

155.24

hour

4.50

1176.12

5292.54

hour

3.75

513.00

1923.75

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
216

721.63

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

505.38

Add for dewatering @ of 5 per cent of (a+b), if required

2833.63

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1416.82
15584.99

Rate per metre = (a+b+c+d)


say

12.13

Cost Rs

15585.00

Hard Rock ( 7m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

7.00

112.77

789.40

Electric Detonators

each

30.00

14.27

427.98

Mate

day

1.60

185.07

296.11

Driller

day

2.00

206.99

413.98

Blaster

day

0.25

289.31

72.33

Mazdoor

day

18.00

177.07

3187.26

Mazdoor (Skilled)

day

4.00

206.99

827.96

Diver

day

0.50

206.99

103.50

hour

6.00

1176.12

7056.72

hour

2.00

513.00

1026.00

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

649.19
873.19

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3930.91
1965.45
21619.98

Rate per metre = (a+b+c+d+e)


say

12.14

Section
1200

21620.00

Sinking of 8 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.18

185.07

33.31

Sinker ( skilled )

day

1.50

206.99

310.49

Sinking helper ( semi-skilled )

day

3.00

180.07

540.21

hour

4.00

1176.12

4704.48

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

470.45
1514.73
757.37
8331.04

Rate per metre = (a+b+c+d)


say

12.14 A

(ii)

Beyond 3m upto 10m depth


Rate of sinking @ 0.20 m/hour
217

8331.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

Unit

Quantity

Rate Rs

Labour
Mate

day

0.25

185.07

46.27

Sinker

day

1.75

206.99

362.23

Sinking helper ( semi-skilled )

day

3.50

180.07

630.25

hour

5.00

1176.12

5880.60

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

588.06
1876.85

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

938.43
10322.68

Rate per metre = (a+b+c+d)


say

12.14 A

(iii)
a

12.14 A

(iv)
a
b

12.14 A

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

10839.00

12th m

5%

11381.00

13th m

5%

11950.00

14th m

5%

12548.00

15th m

5%

13175.00

16th m

5%

13834.00

17th m

5%

14526.00

18th m

5%

15252.00

19th m

5%

16015.00

20th m

5%

16816.00

Total Cost from 10m upto 20m

136336.00

Avg Rate per metre

13634.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge

21st m

7.5%

18077.00

21692.00

22nd m

7.5%

19433.00

23320.00

23rd m

7.5%

20890.00

25068.00

24th m

7.5%

22457.00

26948.00

25th m

7.5%

24141.00

28969.00

26th m

7.5%

25952.00

31142.00

27th m

7.5%

27898.00

33478.00

28th m

7.5%

29990.00

35988.00

29th m

7.5%

32239.00

38687.00

30th m

7.5%

34657.00

41588.00

Total Cost from 20m upto 30m

255734.00

306880.00

Avg Rate per metre

25573.00

30688.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

Cost Rs

(a)

(b) Including
20% for
Kentledge

31st m

10%

38123.00

45748.00

32nd

10%

41935.00

50322.00

33rd m

10%

46129.00

55355.00

34th m

10%

50742.00

60890.00

35th m

10%

55816.00

66979.00

36th m

10%

61398.00

73678.00

37th m

10%

67538.00

81046.00

38th m

10%

74292.00

89150.00

218

10323.00

Sr No

12.14

Ref. to
MoRTH
Spec.

Description

Unit

39th m

10%

40th m

10%

Quantity

Rate Rs

81721.00

98065.00

89893.00

107872.00

Total Cost from 30m upto 40m

607587.00

729104.00

Avg Rate per metre

60759.00

72910.00

Cost Rs

Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.22

185.07

40.72

Sinker ( skilled )

day

2.00

206.99

413.98

Sinking helper ( semi-skilled )

hour

3.50

180.07

630.25

5.50

1176.12

6468.66

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

646.87
2050.12

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1025.06
11275.64

Rate per metre = (a+b+c+d)


say

12.14 B

(ii)

11276.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.32

185.07

59.22

Sinker

day

2.50

206.99

517.48

Sinking helper ( semi-skilled )

day

4.50

180.07

810.32

hour

6.00

1176.12

7056.72

hour

3.50

513.00

1795.50

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

885.22
2781.11

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1390.56
15296.12

Rate per metre = (a+b+c+d)


say

12.14 B

(iii)
a
b

12.14 B

(iv)

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

(b) Including
for dewatering
@ 5% of cost,
if required

11th m

5%

16061.00

16864.00

12th m

5%

16864.00

17707.00

13th m

5%

17707.00

18592.00

14th m

5%

18592.00

19522.00

15th m

5%

19522.00

20498.00

16th m

5%

20498.00

21523.00

17th m

5%

21523.00

22599.00

18th m

5%

22599.00

23729.00

19th m

5%

23729.00

24915.00

20th m

5%

24915.00

26161.00

Total Cost from 10m upto 20m

202010.00

212110.00

Avg Rate per metre

20201.00

21211.00

Beyond 20m upto 30 m

219

15296.00

Sr No

Ref. to
MoRTH
Spec.

Description
a
b
c

12.14 B

Rate Rs

Cost Rs

(c)Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

31st m

7.5%

26784.00

33480.00

35154.00

32nd

7.5%

28793.00

35991.00

37791.00

33rd m

7.5%

30952.00

38690.00

40625.00

34th m

7.5%

33273.00

41591.00

43671.00

35th m

7.5%

35768.00

44710.00

46946.00

36th m

7.5%

38451.00

48064.00

50467.00

37th m

7.5%

41335.00

51669.00

54252.00

38th m

7.5%

44435.00

55544.00

58321.00

39th m

7.5%

47768.00

59710.00

62696.00

40th m

7.5%

51351.00

64189.00

67398.00

Total Cost from 30m upto 40m

378910.00

473638.00

497321.00

Avg Rate per metre

37891.00

47364.00

49732.00

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

Quantity

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

(v)

12.14

Unit

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

(c ) Including (b) Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

56486.00

67783.00

71172.00

32nd

10%

62135.00

74562.00

78290.00

33rd m

10%

68349.00

82019.00

86120.00

34th m

10%

75184.00

90221.00

94732.00

35th m

10%

82702.00

99242.00

104204.00

36th m

10%

90972.00

109166.00

114624.00

37th m

10%

100069.00

120083.00

126087.00

38th m

10%

110076.00

132091.00

138696.00

39th m

10%

121084.00

145301.00

152566.00

40th m

10%

133192.00

159830.00

167822.00

Total Cost from 30m upto 40m

900249.00

1080298.00

1134313.00

Avg Rate per metre

90025.00

108030.00

113431.00

0.68

185.07

125.85

Soft Rock ( 8m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a)

b)

Labour
Mate

day

Sinker ( skilled )

day

4.00

206.99

827.96

Sinking helper ( semi-skilled )

day

12.00

180.07

2160.84

Diver

day

1.00

206.99

206.99

hour

5.00

1176.12

5880.60

hour

3.75

513.00

1923.75

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

780.44

Add for dewatering @ of 5 per cent of (a+b), if required

595.32
3125.44

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1562.72
17189.90

Rate per metre = (a+b+c+d)


220

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.14

Cost Rs
17190.00

Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

8.00

112.77

902.17

Electric Detonators

each

32.00

14.27

456.52

Mate

day

1.09

185.07

201.73

Driller

day

2.00

206.99

413.98

Blaster

day

0.25

289.31

72.33

Mazdoor

day

20.00

177.07

3541.40

Mazdoor (Skilled)

day

4.00

206.99

827.96

hour

6.00

1176.12

7056.72

hour

2.00

513.00

1026.00

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

657.01
505.74

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3915.39
1957.69
21534.62

Rate per metre = (a+b+c+d+e)


say

12.15

Section
1200

21535.00

Sinking of 9 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.19

185.07

35.16

Sinker ( skilled )

day

1.50

206.99

310.49

Sinking helper ( semi-skilled )

day

3.25

180.07

585.23

hour

4.00

1176.12

4704.48

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

470.45
1526.45

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

763.23
8395.48

Rate per metre = (a+b+c+d)


say

12.15 A

(ii)

8395.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.27

185.07

49.97

Sinker

day

1.75

206.99

362.23

Sinking helper ( semi-skilled )

day

4.00

180.07

720.28

Machinery

221

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

hour

Quantity
5.50

Rate Rs
1176.12

646.87

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1031.00
11341.01
say

(iii)
a

12.15 A

12.15 A

(iv)

6468.66

2062.00

Rate per metre = (a+b+c+d)


12.15 A

Cost Rs

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

11908.00

12th m

5%

12503.00

13th m

5%

13128.00

14th m

5%

13784.00

15th m

5%

14473.00

16th m

5%

15197.00

17th m

5%

15957.00

18th m

5%

16755.00

19th m

5%

17593.00

20th m

5%

18473.00

Total Cost from 10m upto 20m

149771.00

Avg Rate per metre

14977.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge

21st m

7.5%

19858.48

23830.00

22nd m

7.5%

21348.00

25618.00

23rd m

7.5%

22949.00

27539.00

24th m

7.5%

24670.00

29604.00

25th m

7.5%

26520.00

31824.00

26th m

7.5%

28509.00

34211.00

27th m

7.5%

30647.00

36776.00

28th m

7.5%

32946.00

39535.00

29th m

7.5%

35417.00

42500.00

30th m

7.5%

38073.00

45688.00

Total Cost from 20m upto 30m

280937.48

337125.00

Avg Rate per metre

28094.00

33713.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

(a)

(b) Including
20% for
Kentledge

31st m

10%

41880.30

50256.00

32nd

10%

46068.00

55282.00

33rd m

10%

50675.00

60810.00

34th m

10%

55743.00

66892.00

35th m

10%

61317.00

73580.00

36th m

10%

67449.00

80939.00

37th m

10%

74194.00

89033.00

38th m

10%

81613.00

97936.00

39th m

10%

89774.00

107729.00

40th m

10%

98751.00

118501.00

Total Cost from 30m upto 40m

667464.30

800958.00

Avg Rate per metre

66746.00

80096.00

222

11341.00

Sr No
12.15

Ref. to
MoRTH
Spec.

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Clayey Soil ( 9m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.24

185.07

44.42

Sinker ( skilled )

day

2.25

206.99

465.73

Sinking helper ( semi-skilled )

day

3.75

180.07

675.26

hour

5.75

1176.12

6762.69

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

676.27

c)

Overhead charges @ 0.25 on (a+b)

2156.09

d)

Contractor's profit @ 0.1 on (a+b+c)

1078.05
11858.50

Rate per metre = (a+b+c+d)


say

12.15 B

(ii)

11859.00

Beyond 3m upto 10m depth


Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

0.34

185.07

62.92

Sinker

day

2.50

206.99

517.48

Sinking helper ( semi-skilled )

day

5.00

180.07

900.35

hour

6.50

1176.12

7644.78

hour

3.75

513.00

1923.75

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

956.85
3001.53

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1500.77
16508.43

Rate per metre = (a+b+c+d)


say

12.15 B

12.15 B

(iii)

Beyond 10 m upto 20 m

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add for dewatering @ 5 per cent of cost, if required.

(iv)

(a)

(b) Including
for dewatering
@ 5% of cost,
if required

11th m

5%

17333.00

18200.00

12th m

5%

18200.00

19110.00

13th m

5%

19110.00

20066.00

14th m

5%

20066.00

21069.00

15th m

5%

21069.00

22122.00

16th m

5%

22122.00

23228.00

17th m

5%

23228.00

24389.00

18th m

5%

24389.00

25608.00

19th m

5%

25608.00

26888.00

20th m

5%

26888.00

28232.00

Total Cost from 10m upto 20m

218013.00

228912.00

Avg Rate per metre

21801.00

22891.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering on the cost, if required

223

16508.00

Sr No

Ref. to
MoRTH
Spec.

Description
c

12.15 B

(v)
a
b
c

12.15

Unit

Quantity
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

Rate Rs

Cost Rs

( c) Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

31st m

7.5%

28905.00

36131.00

37938.00

32nd

7.5%

31073.00

38841.00

40783.00

33rd m

7.5%

33403.00

41754.00

43842.00

34th m

7.5%

35908.00

44885.00

47129.00

35th m

7.5%

38601.00

48251.00

50664.00

36th m

7.5%

41496.00

51870.00

54464.00

37th m

7.5%

44608.00

55760.00

58548.00

38th m

7.5%

47954.00

59943.00

62940.00

39th m

7.5%

51551.00

64439.00

67661.00

40th m

7.5%

55417.00

69271.00

72735.00

Total Cost from 30m upto 40m

408916.00

511145.00

536704.00

Avg Rate per metre

40892.00

51115.00

53670.00

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

( c) Including (b) Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

60959.00

73151.00

76809.00

32nd

10%

67055.00

80466.00

84489.00

33rd m

10%

73761.00

88513.00

92939.00

34th m

10%

81137.00

97364.00

102232.00

35th m

10%

89251.00

107101.00

112456.00

36th m

10%

98176.00

117811.00

123702.00

37th m

10%

107994.00

129593.00

136073.00

38th m

10%

118793.00

142552.00

149680.00

39th m

10%

130672.00

156806.00

164646.00

40th m

10%

143739.00

172487.00

181111.00

Total Cost from 30m upto 40m

971537.00

1165844.00

1224137.00

Avg Rate per metre

97154.00

116584.00

122414.00

Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

0.76

185.07

140.65

Sinker ( skilled )

day

4.00

206.99

827.96

Sinking helper ( semi-skilled )

day

14.00

180.07

2520.98

Diver

day

1.20

206.99

248.39

hour

6.50

1176.12

7644.78

hour

4.00

513.00

2052.00

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

969.68

Consumables in sinking @ 10 per cent of (b)


Add for dewatering @ of 5 per cent of (a+b), if required

1440.44

c)

Overhead charges @ 0.25 on (a+b)

3961.22

d)

Contractor's profit @ 0.1 on (a+b+c)

1980.61
21786.71

Rate per metre = (a+b+c+d)


say

12.15

Hard Rock ( 9m dia well )


Unit = Running Meter
224

21787.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

10.00

112.77

1127.71

Electric Detonators

each

40.00

14.27

570.65

Mate

day

1.17

185.07

216.53

Driller

day

2.00

206.99

413.98

Blaster

day

0.25

289.31

72.33

Mazdoor

day

22.00

177.07

3895.54

Mazdoor (Skilled)

day

4.00

206.99

827.96

Diver

day

1.00

206.99

206.99

hour

7.00

1176.12

8232.84

hour

2.50

513.00

1282.50

Labour

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

757.43
563.33

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

4541.95

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2270.97
24980.71

Rate per metre = (a+b+c+d+e)


say

12.16

1200

24981.00

Sinking of 10 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.20 m / hour
a)

b)

Labour
Mate

day

0.20

185.07

37.01

Sinker ( skilled )

day

1.50

206.99

310.49

Sinking helper ( semi-skilled )

day

3.50

180.07

630.25

hour

5.00

1176.12

5880.60

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

588.06
1861.60
930.80
10238.81

Rate per metre = (a+b+c+d)


say

12.16 A

(ii)

10239.00

Beyond 3m upto 10m depth


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.31

185.07

57.37

Sinker

day

2.00

206.99

413.98

Sinking helper ( semi-skilled )

day

4.25

180.07

765.30

hour

5.75

1176.12

6762.69

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)
225

676.27

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

2168.90

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1084.45
11928.96

Rate per metre = (a+b+c+d)


say

12.16 A

(iii)
a

12.16 A

(iv)
a
b

12.16 A

12.16

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

12525.00

12th m

5%

13151.00

13th m

5%

13809.00

14th m

5%

14499.00

15th m

5%

15224.00

16th m

5%

15985.00

17th m

5%

16784.00

18th m

5%

17623.00

19th m

5%

18504.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre

15753.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge

21st m

7.5%

20886.00

25063.00

22nd m

7.5%

22452.00

26942.00

23rd m

7.5%

24136.00

28963.00

24th m

7.5%

25946.00

31135.00

25th m

7.5%

27892.00

33470.00

26th m

7.5%

29984.00

35981.00

27th m

7.5%

32233.00

38680.00

28th m

7.5%

34650.00

41580.00

29th m

7.5%

37249.00

44699.00

30th m

7.5%

40043.00

48052.00

Total Cost from 20m upto 30m

295471.00

354565.00

Avg Rate per metre

29547.00

35457.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

19429.00
157533.00

(v)

Cost Rs

(a)

(b) Including
20% for
Kentledge

31st m

10%

44047.00

52856.00

32nd

10%

48452.00

58142.00

33rd m

10%

53297.00

63956.00

34th m

10%

58627.00

70352.00

35th m

10%

64490.00

77388.00

36th m

10%

70939.00

85127.00

37th m

10%

78033.00

93640.00

38th m

10%

85836.00

103003.00

39th m

10%

94420.00

113304.00

40th m

10%

103862.00

124634.00

Total Cost from 30m upto 40m

702003.00

842402.00

Avg Rate per metre

70200.00

84240.00

Clayey Soil (10m dia. Well )


Unit = Running Meter
Taking output = 1 cum

226

11929.00

Sr No

Ref. to
MoRTH
Spec.

Description
(i)

Unit

Quantity

Rate Rs

Cost Rs

Depth below bed level upto 3.0 M


Rate of sinking 0.18m/hour.
a)

b)

Labour
Mate

day

0.25

185.07

46.27

Sinker ( skilled )

day

2.50

206.99

517.48

Sinking helper ( semi-skilled )

day

5.50

180.07

990.39

hour

6.00

1176.12

7056.72

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

705.67
2329.13

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1164.56
12810.21

Rate per metre = (a+b+c+d)


say

12.16 B

(ii)

12810.00

Beyond 3m upto 10m depth


Rate of sinking 0.15m/hour.
a)

b)

Labour
Mate

day

0.40

185.07

74.03

Sinker

day

3.00

206.99

620.97

Sinking helper ( semi-skilled )

day

5.50

180.07

990.39

hour

6.00

1176.12

7056.72

hour

4.00

513.00

2052.00

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

910.87
2926.24

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1463.12
16094.34

Rate per metre = (a+b+c+d)


say

12.16 B

(iii)
a
b

12.16 B

(iv)
a
b
c

16094.00

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

(b) Including
for dewatering
@ 5% of cost,
if required

11th m

5%

16899.00

17744.00

12th m

5%

17744.00

18631.00

13th m

5%

18631.00

19563.00

14th m

5%

19563.00

20541.00

15th m

5%

20541.00

21568.00

16th m

5%

21568.00

22646.00

17th m

5%

22646.00

23778.00

18th m

5%

23778.00

24967.00

19th m

5%

24967.00

26215.00

20th m

5%

26215.00

27526.00

Total Cost from 10m upto 20m

212552.00

223179.00

Avg Rate per metre

21255.00

22318.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

( c) Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

31st m

7.5%

28181.00

35226.00

36987.00

32nd

7.5%

30295.00

37869.00

39762.00

227

Sr No

12.16 B

12.16

Ref. to
MoRTH
Spec.

Description

(v)

Unit

Rate Rs

Cost Rs

33rd m

7.5%

32567.00

40709.00

42744.00

34th m

7.5%

35010.00

43763.00

45951.00

35th m

7.5%

37636.00

47045.00

49397.00

36th m

7.5%

40459.00

50574.00

53103.00

37th m

7.5%

43493.00

54366.00

57084.00

38th m

7.5%

46755.00

58444.00

61366.00

39th m

7.5%

50262.00

62828.00

65969.00

40th m

7.5%

54032.00

67540.00

70917.00

Total Cost from 30m upto 40m

398690.00

498364.00

523280.00

Avg Rate per metre

39869.00

49836.00

52328.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Quantity

(a)

( c) Including (b) Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

59435.00

71322.00

74888.00

32nd

10%

65379.00

78455.00

82378.00

33rd m

10%

71917.00

86300.00

90615.00

34th m

10%

79109.00

94931.00

99677.55

35th m

10%

87020.00

104424.00

109645.20

36th m

10%

95722.00

114866.00

120609.30

37th m

10%

105294.00

126353.00

132670.65

38th m

10%

115823.00

138988.00

145937.40

39th m

10%

127405.00

152886.00

160530.30

40th m

10%

140146.00

168175.00

176583.75

Total Cost from 30m upto 40m

947250.00

1136700.00

1193535.15

Avg Rate per metre

94725.00

113670.00

119354.00

Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a)

b)

Labour
Mate

day

0.86

185.07

159.16

Sinker ( skilled )

day

4.00

206.99

827.96

Sinking helper ( semi-skilled )

day

16.00

180.07

2881.12

Diver

day

1.40

206.99

289.79

hour

7.00

1176.12

8232.84

hour

4.25

513.00

2180.25

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

1041.31

Consumables in sinking @ 10 per cent of (b)

572.72

Add for dewatering @ 5 per cent of cost, if required

4046.29

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2023.14
22254.57

Rate per metre = (a+b+c+d)


say

12.16

22255.00

Hard Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a)

Material
Kg

Gelatine 80 per cent


228

11.00

112.77

1240.48

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
each.

Electric Detonators
b)

c)

Quantity

Rate Rs

44.00

14.27

627.71

Labour
Mate

day

1.27

185.07

235.04

Driller

day

2.00

206.99

413.98

Blaster

day

0.25

289.31

72.33

Mazdoor

day

24.00

177.07

4249.68

Mazdoor (Skilled)

day

4.00

206.99

827.96

hour

8.50

1176.12

9997.02

hour

3.00

513.00

1539.00

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

576.80

Consumables in sinking @ 10 per cent of cost of (b+c).

1791.18

d)

Overhead charges @ 0.25 on (a+b+c)

5392.80

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2696.40
29660.37

Rate per metre = (a+b+c+d+e)


say

12.17

1200

Cost Rs

29660.00

Sinking of 11 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A

Sandy Soil

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.21

185.07

38.86

Sinker ( skilled )

day

1.50

206.99

310.49

Sinking helper (semi-skilled)

day

3.30

180.07

594.23

hour

6.00

1176.12

7056.72

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

705.67
2176.49
1088.25

Cost for 0.5m = a+b+c+d

11970.71

Rate per metre = (a+b+c+d)/0.50

23941.42
say

12.17 A

(ii)

23941.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.13 m/hour
a)

b)

Labour
Mate

day

0.32

185.07

59.22

Sinker

day

2.00

206.99

413.98

Sinking helper (semi-skilled)

day

4.50

180.07

810.32

hour

4.00

1176.12

4704.48

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b+c)

d)

Contractor's profit @ 0.1 on (a+b+c+d)

470.45
1614.61
807.31
8880.36

Cost for 0.5m = a+b+c+d

17760.72

Rate per metre = (a+b+c+d)/0.50

229

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.17 A

(iii)
a

12.17 A

12.17 A

12.17

(iv)

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

18649.00

12th m

5%

19581.00

13th m

5%

20560.00

14th m

5%

21588.00

15th m

5%

22667.00

16th m

5%

23800.00

17th m

5%

24990.00

18th m

5%

26240.00

19th m

5%

27552.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre

23456.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.
7.5%

31100.00

37320.00

7.5%

33433.00

40120.00

23rd m

7.5%

35940.00

43128.00

24th m

7.5%

38636.00

46363.00

25th m

7.5%

41534.00

49841.00

26th m

7.5%

44649.00

53579.00

27th m

7.5%

47998.00

57598.00

28th m

7.5%

51598.00

61918.00

29th m

7.5%

55468.00

66562.00

30th m

7.5%

59628.00

71554.00

Total Cost from 20m upto 30m

439984.00

527983.00

Avg Rate per metre

43998.00

52798.00

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

(a)

(b) Including
20% for
Kentledge

31st m

10%

65591.00

78709.00

32nd

10%

72150.00

86580.00

33rd m

10%

79365.00

95238.00

34th m

10%

87302.00

104762.00

35th m

10%

96032.00

115238.00

36th m

10%

105635.00

126762.00

37th m

10%

116199.00

139439.00

38th m

10%

127819.00

153383.00

39th m

10%

140601.00

168721.00

40th m

10%

154661.00

185593.00

Total Cost from 30m upto 40m

1045355.00

1254425.00

Avg Rate per metre

104536.00

125443.00

Clayey Soil (11 m dia. Well )


Unit = Running Meter
Taking output = 0.50 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a)

(b)Including
20% for
Kentledge

22nd m

(i)

(a)

21st m

(v)

28930.00
234557.00

Labour

230

Cost Rs
17761.00

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

Mate

day

0.26

185.07

48.12

Sinker ( skilled )

day

2.50

206.99

517.48

Sinking helper (semi-skilled)

day

4.00

180.07

720.28

hour

5.00

1176.12

5880.60

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

588.06
1938.63

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

969.32

Cost for 0.5m = a+b+c+d

10662.48

Rate per metre = (a+b+c+d)/0.50

21324.97
say

12.17 B

(ii)

Cost Rs

21325.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.08 m/hour
a)

b)

Labour
Mate

day

0.43

185.07

79.58

Sinker

day

3.50

206.99

724.47

Sinking helper (semi-skilled)

day

5.75

180.07

1035.40

hour

6.00

1176.12

7056.72

hour

4.25

513.00

2180.25

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

923.70

c)

Overhead charges @ 0.25 on (a+b)

3000.03

d)

Contractor's profit @ 0.1 on (a+b+c)

1500.01
16500.16

Cost for 0.5m = a+b+c+d

33000.32

Rate per metre = (a+b+c+d)/0.50


say

12.17 B

12.17 B

(iii)

Beyond 10 m upto 20 m

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add for dewatering @ 5 per cent of cost, if required.

(iv)

33000.00

(a) (b)Including for


dewatering @
5% of cost, if
required

11th m

5%

34650.00

36383.00

12th m

5%

36383.00

38202.00

13th m

5%

38202.00

40112.00

14th m

5%

40112.00

42118.00

15th m

5%

42118.00

44224.00

16th m

5%

44224.00

46435.00

17th m

5%

46435.00

48757.00

18th m

5%

48757.00

51195.00

19th m

5%

51195.00

53755.00

20th m

5%

53755.00

56443.00

Total Cost from 10m upto 20m

435831.00

457623.00

Avg Rate per metre

43583.00

45762.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(a)

(c)Including (b)Including
25% for
5% for
Kentledge dewatering, if
required

21st m

7.5%

57787.00

72234.00

75846.00

22nd

7.5%

62121.00

77651.00

81534.00

23rd m

7.5%

66780.00

83475.00

87649.00

231

Sr No

12.17 B

Ref. to
MoRTH
Spec.

Description

(v)

Unit

24th m

7.5%

71789.00

25th m

7.5%

26th m

7.5%

27th m

7.5%

28th m
29th m
30th m

Cost Rs
94223.00

77173.00

96466.00

101289.00

82961.00

103701.00

108886.00

89183.00

111479.00

117053.00

7.5%

95872.00

119840.00

125832.00

7.5%

103062.00

128828.00

135269.00

7.5%

110792.00

138490.00

145415.00

Total Cost from 20m upto 30m

817520.00

1021900.00

1072995.00

Avg Rate per metre

81752.00

102190.00

107300.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

(a)

(c ) Including (b)Including
20% for
5% for
Kentledge dewatering, if
required

31st m

10%

121871.00

146245.00

153557.00

32nd

10%

134058.00

160870.00

168914.00

33rd m

10%

147464.00

176957.00

185805.00

34th m

10%

162210.00

194652.00

204385.00

35th m

10%

178431.00

214117.00

224823.00

36th m

10%

196274.00

235529.00

247305.00

37th m

10%

215901.00

259081.00

272035.00

38th m

10%

237491.00

284989.00

299238.00

39th m

10%

261240.00

313488.00

329162.00

40th m

10%

287364.00

344837.00

362079.00

1942304

2330765

2447303

194230.00

233077.00

244730.00

0.95

185.07

175.82

Avg Rate per metre


C

Rate Rs
89736.00

Total Cost from 30m upto 40m


12.17

Quantity

Soft Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a)

b)

Labour
Mate

day

Sinker ( skilled )

day

4.25

206.99

879.71

Sinking helper (semi-skilled)

day

18.00

180.07

3241.26

Diver

day

1.50

206.99

310.49

hour

8.00

1176.12

9408.96

hour

4.50

513.00

2308.50

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

1171.75

Consumables in sinking @ 10 per cent of (b)

c)

Add for dewatering @ 5 per cent of cost of (b), if


required
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

644.46
4535.23
2267.62

Cost for 0.5m = a+b+c+d

24943.79
49887.57

Rate per metre = (a+b+c+d)/0.50


say

12.17

49888.00

Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a)

Material
Kg

Gelatine 80 per cent


232

12.00

112.77

1353.25

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
each.

Electric Detonators
b)

c)

Quantity

Rate Rs

48.00

14.27

684.78

Labour
Mate

day

1.35

185.07

249.84

Driller

day

2.00

206.99

413.98

Blaster

day

0.25

289.31

72.33

Mazdoor

day

26.00

177.07

4603.82

Mazdoor (Skilled)

day

4.00

206.99

827.96

hour

10.00

1176.12

11761.20

hour

3.50

513.00

1795.50

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

677.84

Consumables in sinking @ 10 per cent of cost of (b+c).

1972.46

d)

Overhead charges @ 0.25 on (a+b+c)

6103.24

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3051.62
33567.82

Cost for 0.5m = a+b+c+d

67135.63

Rate per metre = (a+b+c+d)/0.50


say

12.18

1200

Cost Rs

67136.00

Sinking of 12 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A

Sandy Soil

(i)

I) Depth below bed level upto 3.0 M


Rate of sinking @ 0.05 m/hour
a)

b)

Labour
Mate

day

0.22

185.07

40.72

Sinker ( skilled )

day

1.75

206.99

362.23

Sinking helper (semi-skilled)

day

4.00

180.07

720.28

hour

6.00

1176.12

7056.72

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

705.67
2221.40

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1110.70
12217.73

Cost for 0.25m = a+b+c+d

48870.91

Rate per metre = (a+b+c+d)/0.25


say

12.18 A

(ii)

48871.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.038 m/hour
a)

b)

Labour
Mate

day

0.37

185.07

68.48

Sinker

day

2.50

206.99

517.48

Sinking helper (semi-skilled)

day

4.75

180.07

855.33

hour

6.50

1176.12

7644.78

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

764.48
2462.64
1231.32
13544.49

Cost for 0.25m = a+b+c+d

233

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

54177.98

Rate per metre = (a+b+c+d)/0.25


say

12.18 A

(iii)
a

12.18 A

12.18 A

(iv)

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

56887.00

12th m

5%

59731.00

13th m

5%

62718.00

14th m

5%

65854.00

15th m

5%

69147.00

16th m

5%

72604.00

17th m

5%

76234.00

18th m

5%

80046.00

19th m

5%

84048.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre

71552.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.

(b)Including
20% for
Kentledge

7.5%

94869.00

113843.00

22nd m

7.5%

101984.00

122381.00

23rd m

7.5%

109633.00

131560.00

24th m

7.5%

117855.00

141426.00

25th m

7.5%

126694.00

152033.00

26th m

7.5%

136196.00

163435.00

27th m

7.5%

146411.00

175693.00

28th m

7.5%

157392.00

188870.00

29th m

7.5%

169196.00

203035.00

30th m

7.5%

181886.00

218263.00

Total Cost from 20m upto 30m

1342116.00

1610539.00

Avg Rate per metre

134212.00

161054.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

(a)

(b)Including
20% for
Kentledge

31st m

10%

200075.00

240090.00

32nd

10%

220083.00

264100.00

33rd m

10%

242091.00

290509.00

34th m

10%

266300.00

319560.00

35th m

10%

292930.00

351516.00

36th m

10%

322223.00

386668.00

37th m

10%

354445.00

425334.00

38th m

10%

389890.00

467868.00

39th m

10%

428879.00

514655.00

40th m

10%

471767.00

566120.00

Avg Rate per metre


Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i)

(a)

21st m

(v)

88250.00
715519.00

Total Cost from 30m upto 40m


12.18

Cost Rs

Depth below bed level upto 3.0 M


Rate of sinking @ 0.04 m/hour
234

3188683

3826420

318868.00

382642.00

54178.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

Unit

Quantity

Rate Rs

Labour
Mate

day

0.30

185.07

55.52

Sinker ( skilled )

day

3.00

206.99

620.97

Sinking helper (semi-skilled)

day

4.50

180.07

810.32

hour

6.25

1176.12

7350.75

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

735.08
2393.16

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1196.58
13162.37

Cost for 0.25m = a+b+c+d


Rate per metre = (a+b+c+d)/0.25

52649.47
say

12.18 B

(ii)

Cost Rs

52649.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.03 m/hour
a)

b)

Labour
Mate

day

0.48

185.07

88.83

Sinker

day

3.75

206.99

776.21

Sinking helper (semi-skilled)

day

6.00

180.07

1080.42

hour

8.33

1176.12

9797.08

hour

4.50

513.00

2308.50

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

1210.56
3815.40

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1907.70

Cost for 0.25m = a+b+c+d

20984.71

Rate per metre = (a+b+c+d)/0.25

83938.82
say

12.18 B

12.18 B

(iii)
a

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add for dewatering @ 5 per cent of cost, if required.

(iv)

83939.00

Beyond 10 m upto 20 m

(a) (b)Including for


dewatering @
5% of cost, if
required

11th m

5%

88136.00

12th m

5%

92543.00

92543.00
97170.00

13th m

5%

97170.00

102029.00

14th m

5%

102029.00

107130.00

15th m

5%

107130.00

112487.00

16th m

5%

112487.00

118111.00

17th m

5%

118111.00

124017.00

18th m

5%

124017.00

130218.00

19th m

5%

130218.00

136729.00

20th m

5%

136729.00

143565.00

Total Cost from 10m upto 20m

1108570.00

1163999.00

Avg Rate per metre

110857.00

116400.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(a)

(c)Including (b)Including
25% for
5% for
Kentledge dewatering, if
required

21st m

7.5%

146984.00

183730.00

192917.00

22nd

7.5%

158008.00

197510.00

207386.00

235

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

23rd m

7.5%

169859.00

212324.00

222940.00

24th m

7.5%

182598.00

228248.00

239660.00

25th m

7.5%

196293.00

245366.00

257634.00

26th m

7.5%

211015.00

263769.00

276957.00

27th m

7.5%

226841.00

283551.00

297729.00

28th m

7.5%

243854.00

304818.00

320059.00

29th m

7.5%

262143.00

327679.00

344063.00

30th m

7.5%

281804.00

352255.00

369868.00

2079399

2599250

2729213

207940.00

259925.00

272921.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.18 B

(v)
a

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

(a)

(c ) Including (b)Including
20% for
5% for
Kentledge dewatering, if
required

31st m

10%

309984.00

371981.00

390580.00

32nd

10%

340982.00

409178.00

429637.00

33rd m

10%

375080.00

450096.00

472601.00

34th m

10%

412588.00

495106.00

519861.00

35th m

10%

453847.00

544616.00

571847.00

36th m

10%

499232.00

599078.00

629032.00

37th m

10%

549155.00

658986.00

691935.00

38th m

10%

604071.00

724885.00

761129.00

39th m

10%

664478.00

797374.00

837243.00

40th m

10%

730926.00

877111.00

920967.00

Avg Rate per metre


C

Cost Rs

Beyond 30m upto 40 m

Total Cost from 30m upto 40m


12.18

Rate Rs

4940343

5928411

6224832

494034.00

592841.00

622483.00

Soft Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a)

b)

Labour
Mate

day

1.06

185.07

196.17

Sinker ( skilled )

day

4.50

206.99

931.46

Sinking helper (semi-skilled)

day

20.00

180.07

3601.40

Diver

day

1.75

206.99

362.23

hour

10.00

1176.12

11761.20

hour

4.75

513.00

2436.75

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

1419.80
780.89

Add for dewatering @ 5 per cent, if required

5372.47

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2686.24
29548.60

Cost for 0.25m = a+b+c+d

118194.42

Rate per metre = (a+b+c+d)/0.25


say

12.18

Hard Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m

(i)

Depth in hard rock strata upto 3 m


Rate of sinking @ 0.020 m/hour

236

118194.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit

Electric detonator

c)

Rate Rs

Kg

14.00

112.77

1578.79

each.

56.00

14.27

798.90

Labour
Mate

day

1.44

185.07

266.50

Driller

day

2.00

206.99

413.98

Blaster

day

0.25

289.31

72.33

Mazdoor

day

28.00

177.07

4957.96

Mazdoor (Skilled)

day

4.50

206.99

931.46

hour

12.50

1176.12

14701.50

hour

4.00

513.00

2052.00

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required.

837.68

Consumables in sinking @ 10 per cent of (c).

1759.12

d)

Overhead charges @ 0.25 on (a+b+c)

7092.55

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3546.28
39009.05

Cost for 0.25m = a+b+c+d+e

156036.18

Rate per metre = (a+b+c+d+e)/0.25


say

12.19

1200

Cost Rs

Material
Gelatine80 per cent

b)

Quantity

156036.00

Sinking of Twin D Type well (other than pneumatic


method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A

Sandy Soil

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.20

185.07

37.01

Sinker ( skilled )

day

1.25

206.99

258.74

Sinking helper (semi-skilled)

day

3.75

180.07

675.26

hour

5.50

1176.12

6468.66

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

646.87

c)

Overhead charges @ 0.25 on (a+b)

2021.64

d)

Contractor's profit @ 0.1 on (a+b+c)

1010.82
11118.99

Rate per metre = (a+b+c+d)


say

12.19 A

(ii)

11119.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.30

185.07

55.52

Sinker

day

1.50

206.99

310.49

Sinking helper (semi-skilled)

day

4.00

180.07

720.28

hour

5.88

1176.12

6915.59

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

691.56
2173.36

Overhead charges @ 0.25 on (a+b)


237

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

1086.68

Contractor's profit @ 0.1 on (a+b+c)

11953.47

Rate per metre = (a+b+c+d)


say

12.19 A

(iii)
a

12.19 A

(iv)
a
b

12.19 A

12.19

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

12551.00

12th m

5%

13179.00

13th m

5%

13838.00

14th m

5%

14530.00

15th m

5%

15257.00

16th m

5%

16020.00

17th m

5%

16821.00

18th m

5%

17662.00

19th m

5%

18545.00

20th m

5%

157875.00

Avg Rate per metre

15788.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b)Including
20% for
Kentledge

21st m

7.5%

20932.00

25118.00

22nd m

7.5%

22502.00

27002.00

23rd m

7.5%

24190.00

29028.00

24th m

7.5%

26004.00

31205.00

25th m

7.5%

27954.00

33545.00

26th m

7.5%

30051.00

36061.00

27th m

7.5%

32305.00

38766.00

28th m

7.5%

34728.00

41674.00

29th m

7.5%

37333.00

44800.00

30th m

7.5%

40133.00

48160.00

Total Cost from 20m upto 30m

296132.00

355359.00

Avg Rate per metre

29613.00

35536.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

(a)

(b)Including
20% for
Kentledge

31st m

10%

44146.00

52975.00

32nd

10%

48561.00

58273.00

33rd m

10%

53417.00

64100.00

34th m

10%

58759.00

70511.00

35th m

10%

64635.00

77562.00

36th m

10%

71099.00

85319.00

37th m

10%

78209.00

93851.00

38th m

10%

86030.00

103236.00

39th m

10%

94633.00

113560.00

40th m

10%

104096.00

124915.00

Total Cost from 30m upto 40m

703585.00

844302.00

Avg Rate per metre

70359.00

84430.00

Clayey Soil (Twin D Type Well )


Unit = Running Meter
Taking output = 1 meter

(i)

19472.00

Total Cost from 10m upto 20m

(v)

Cost Rs

Depth below bed level upto 3.0 M

238

11953.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Rate of sinking @ 0.16 m/hour


a)

b)

Labour
Mate

day

0.26

185.07

48.12

Sinker ( skilled )

day

2.50

206.99

517.48

Sinking helper (semi-skilled)

day

4.00

180.07

720.28

hour

6.25

1176.12

7350.75

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

735.08

c)

Overhead charges @ 0.25 on (a+b)

2342.92

d)

Contractor's profit @ 0.1 on (a+b+c)

1171.46

Rate per metre = (a+b+c+d)

12886.09
say

12.19 B

(ii)

12886.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.45

185.07

83.28

Sinker

day

3.25

206.99

672.72

Sinking helper (semi-skilled)

day

6.00

180.07

1080.42

hour

6.67

1176.12

7844.72

hour

4.50

513.00

2308.50

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

1015.32
3251.24

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1625.62
17881.82

Rate per metre = (a+b+c+d)


say

12.19 B

12.19 B

(iii)

Beyond 10 m upto 20 m

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add for dewatering @ 5 per cent of cost, if required.

(iv)
a
b
c

17882.00

(a) (b)Including for


dewatering @
5% of cost, if
required

11th m

5%

18776.00

19715.00

12th m

5%

19715.00

20701.00

13th m

5%

20701.00

21736.00

14th m

5%

21736.00

22823.00

15th m

5%

22823.00

23964.00

16th m

5%

23964.00

25162.00

17th m

5%

25162.00

26420.00

18th m

5%

26420.00

27741.00

19th m

5%

27741.00

29128.00

20th m

5%

29128.00

30584.00

Total Cost from 10m upto 20m

236166.00

247974.00

Avg Rate per metre

23617.00

24797.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(c)Including (b)Including
25% for
5% for
Kentledge dewatering, if
required

21st m

7.5%

31313.00

39141.00

41098.00

22nd

7.5%

33661.00

42076.00

44180.00

23rd m

7.5%

36186.00

45233.00

47495.00

239

Sr No

12.19 B

12.19

Ref. to
MoRTH
Spec.

Description

(v)

Unit

Rate Rs

Cost Rs

24th m

7.5%

38900.00

48625.00

51056.00

25th m

7.5%

41818.00

52273.00

54887.00

26th m

7.5%

44954.00

56193.00

59003.00

27th m

7.5%

48326.00

60408.00

63428.00

28th m

7.5%

51950.00

64938.00

68185.00

29th m

7.5%

55846.00

69808.00

73298.00

30th m

7.5%

60034.00

75043.00

78795.00

Total Cost from 20m upto 30m

442988.00

553738.00

581425.00

Avg Rate per metre

44299.00

55374.00

58143.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Quantity

(a)

(c ) Including (b)Including
20% for
5% for
Kentledge dewatering, if
required

31st m

10%

66037.00

79244.00

83206.00

32nd

10%

72641.00

87169.00

91527.00

33rd m

10%

79905.00

95886.00

100680.00

34th m

10%

87896.00

105475.00

110749.00

35th m

10%

96686.00

116023.00

121824.00

36th m

10%

106355.00

127626.00

134007.00

37th m

10%

116991.00

140389.00

147408.00

38th m

10%

128690.00

154428.00

162149.00

39th m

10%

141559.00

169871.00

178365.00

40th m

10%

155715.00

186858.00

196201.00

Total Cost from 30m upto 40m

1052475.00

1262969.00

1326116.00

Avg Rate per metre

105248.00

126297.00

132612.00

159.16

Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a)

b)

Labour
Mate

day

0.86

185.07

Sinker ( skilled )

day

4.50

206.99

931.46

Sinking helper (semi-skilled)

day

15.00

180.07

2701.05

Diver

day

1.50

206.99

310.49

hour

8.33

1176.12

9797.08

hour

6.00

513.00

3078.00

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

1287.51

Consumables in sinking @ 10 per cent of (b)

708.13

Add for dewatering @ 5 per cent, if required

4743.22

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2371.61
26087.69

Rate per metre = (a+b+c+d)


say

12.19

26088.00

Hard Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a)

Material
Kg

Geletine80 per cent


240

10.00

112.77

1127.71

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
each.

Electric detonators
b)

c)

Quantity

Rate Rs

40.00

14.27

570.65

Labour
Mate

day

1.34

185.07

247.99

Driller

day

2.00

206.99

413.98

Blaster

day

0.25

289.31

72.33

Mazdoor

day

25.00

177.07

4426.75

Mazdoor (Skilled)

day

4.25

206.99

879.71

hour

10.00

1176.12

11761.20

hour

3.00

513.00

1539.00

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required.

967.05

Consumables in sinking @ 10 per cent of (b).

1426.72

d)

Overhead charges @ 0.25 on (a+b+c)

5858.27

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2929.14
32220.50

Rate per metre = (a+b+c+d+e)


say

12.20

1200

Cost Rs

32220.00

Pneumatic sinking of wells with equipment of approved


design, drawing and specifications worked by competent
and trained personnel and comprising of compression
and decompression chambers, reducers, two air locks
separately for men and plant & materials, arrangement
for supply of fresh air to working chambers, check
valves, exhaust valves, shafts made from steel plates of
riveted construction not less than 6 mm thick to
withstand an air pressure of 0.50 MPa, controlled blasting
of hard rock where required, staircases and 1 m wide
landing plateforms with railing, arrangement for
compression and decompression, electric lighting of 50
V maximum, proper rooms for rest and medical
examinations and compliance with safety precautions as
per IS:4138, all as per clause1207.6 of MoRTH
Specifications.

Unit - 1 cum
Taking output = 5 cum
a)

Material
M35 grade RCC corbel provided for supporting of
equipment (Dimensions as per ground conditions). Rate
may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel

Cum

8.00

3669.00

29352.00

tonne

0.48

46059.03

22108.33

Blasting material
Kg

1.50

112.77

169.16

each

6.00

14.27

85.60

Medical Officer

day

0.50

0.00

0.00

Para medical personnel

day

1.00

0.00

0.00

Mate

day

1.86

185.07

344.23

Driller

day

1.00

206.99

206.99

Blaster

day

0.50

289.31

144.66

Mazdoor (for cutting, blasting, cleaning, removal of


Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)

day

30.00

177.07

5312.10

day

10.00

206.99

2069.90

Diver

day

4.00

206.99

827.96

Gelatine 80 per cent


Electric detonators
b)

c)

Labour

Machinery

241

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

(i) Induction, deinduction and erection of plant and


equipment including all components and
accessories for pneumatic method of well sinking.

6.00

Rate Rs
Value

L.S

Induction and deinduction


Usage of plant and equipment for pneumatic method of
well sinking
Air compressor 250 cfm, 2 nos.

hour
hour

Hire and running charges of crane of 15 tonne capacity

hour

Motorised barge of 20 tonne capacity

hour

Boat to carry atleast 20 persons

hour

Cost Rs
#VALUE!

100000.00

L.S

Erection at site and commissioning

Note

hour

Quantity

150000.00
6.00

3834.00

23004.00

2x6

293.76

3525.12

6.00

770.04

4620.24

6.00

142.56

855.36

6.00

142.56

855.36

Electric generating set 33 KVA

hour

6.00

342.36

2054.16

Tipper 10 tonne capacity

hour

6.00

873.00

5238.00

d)

Overhead charges @ 0.25 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 5 cum = a+b+c+d+e (see notes below)

#VALUE!

Rate per cum = (a+b+c+d+e)/5

#VALUE!

1.The cost of induction, deinduction and erection of


equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of individual wells will be
added to the cost indicated at (1) above to arrive at the final
rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.

12.21

1207

Sand Filling in Wells complete as per Drawing and


Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a)

Material
cum

1.20

109.09

Mate

day

0.01

185.07

1.85

Mazdoor

day

0.30

177.07

53.12

Sand (assuming 20 per cent voids )


b)

Labour

46.47

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

23.23
255.58

Rate per cum (a+b+c+d)


say

12.22

1200 &
1900

130.90

256.00

Providing Steel Liner 10 mm thick for Curbs and 6 mm


thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a)

Material
i) Structural steel including 5 per cent wastage

b)

Labour

242

tonne

1.05

46527.33

48853.70

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Mate

day

1.24

185.07

229.49

Fitter

day

6.00

238.29

1429.74

Blacksmith

day

5.00

208.99

1044.95

Welder

day

5.00

234.29

1171.45

Mazdoor

day

10.00

177.07

1770.70

c)

Electrodes, cutting gas and other consumables @ 5 per


cent on cost a (a) above.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2442.69
14235.68
7117.84
78296.23

Rate for per MT (a+b+c+d)


say

12.23

1100 &
1700

Cost Rs

78296.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a)

Materials
cum

6.62

5478.00

36264.36

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.

hour

6.00

5023.08

30138.48

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

535.00

267.50

hour

6.00

Rate included
in piling rig

Loader I cum bucket capacity.

hour

0.30

1188.00

356.40

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.30

873.00

261.90

300.00

2.24

673.49

PCC Grade M35


Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

kg

Labour
Mate/Supervisor

day

0.14

185.07

25.91

Mazdoor

day

3.50

177.07

619.75
8085.86

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

4042.93
80736.57

Cost for 15 m = a+b+c+d+d+e

5382.44

Rate per metre (a+b+c+d+e)/15


say

12.24
1100,160
0 & 1700

5382.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a)

Materials
PCC Grade M35

cum

7.85

5478.00

43002.30

hour

6.00

5023.08

30138.48

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

Machinery( for boring and construction )


Hire and running charges of hydraulic piling rig with
power unit and complete accessories including shifting
from one bore location to another.
243

Sr No

Ref. to
MoRTH
Spec.

c)

Description

Unit

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

535.00

hour

6.00

Rate included
in piling rig

Loader I cum bucket capacity.

hour

0.40

1188.00

475.20

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.40

873.00

349.20

350.00

2.24

785.74

kg

Quantity

Rate Rs

Labour
day

0.16

185.07

29.61

Mazdoor

day

4.00

177.07

708.28
8188.50

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

4094.25
88039.07
8803.91

Rate per metre (a+b+c+d+e)/10


say

1100 &
1700

267.50

Mate/Supervisor

Cost for 10 m = a+b+c+d+d+e

12.25

Cost Rs

8804.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a)

Materials
cum

10.17

5478.00

55711.26

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.

hour

6.00

5023.08

30138.48

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

535.00

267.50

hour

6.00

Rate included
in piling rig

Loader I cum bucket capacity.

hour

0.50

1188.00

594.00

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.50

873.00

436.50

PCC Grade M35


Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

kg

385.00

2.24

Mate/Supervisor

day

0.18

185.07

33.31

Mazdoor

day

4.50

177.07

796.82
8282.73

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

4141.37
101266.28

Cost for 9 m = a+b+c+d+d+e

11251.81

Rate per metre (a+b+c+d+e)/9


say

12.26

1100 &
1700

864.32

Labour

11252.00

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a)

Materials
cum

PCC Grade M35


Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b)

Materials Pile shoes


244

17.66

5478.00

96741.48

Sr No

Ref. to
MoRTH
Spec.

Description

c)

d)

Unit

Quantity

Rate Rs

i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

iii) Steel helmet and cushion block on top of casing head


during driving
Machinery

Kg

50.00

51.16

2558.23

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit and
accessories..

hour

6.00

5023.08

30138.48

Hiring and running charges for light crane 5 tonnes


lifting capacity for lowering reinforcement and handling
steel casing.
Labour

hour

0.50

599.40

299.70

Mate/Supervisor

day

0.12

185.07

22.21

Mazdoor

day

3.00

177.07

531.21

e)

Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

11803.22
5901.61
161659.19

Cost for 40 m = a+b+c+d+e

4041.48

Rate per metre (a+b+c+d+e)/40


say

Note

Cost Rs

4041.00

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.

12.27

1100 &
1700

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a)

Materials
cum

PCC Grade M35

23.55

5478.00

129006.90

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b)

Materials Pile shoes


i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

50.00

51.16

2558.23

c)

iii) Steel helmet and cushion block on top of casing head


during driving
Machinery

Kg

hour

6.00

5023.08

30138.48

hour

0.50

599.40

299.70

hour

0.50

535.00

267.50

d)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering
reinforcement cage.
Labour
Mate/Supervisor

day

0.16

185.07

29.61

Mazdoor

day

4.00

177.07

708.28

e)

Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

11916.21
5958.11
194546.07

Cost for 30 m = a+b+c+d+e

6484.87

Rate per metre (a+b+c+d+e)/30


say

245

6485.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Unit

Quantity

Rate Rs

Cost Rs

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.

12.28

1100 &
1700

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a)

Materials
PCC Grade M35

cum

22.61

5478.00

123857.58

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

iii) Steel helmet on top of casing head during driving

Kg

50.00

51.16

2558.23

c)

Machinery
hour

6.00

5023.08

30138.48

hour

0.50

599.40

299.70

d)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
Labour
Mate/Supervisor

day

0.18

185.07

33.31

Mazdoor

day

4.50

177.07

796.82

e)

Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

11872.40
5936.20
189155.76

Cost for 20 m = a+b+c+d+e

9457.79

Rate per metre (a+b+c+d+e)/20


say

Note

12.29

1100 &
1700

9458.00

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a)

Materials
cum

RCC Grade M35

11.78

5195.00

61197.10

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes

Kg

240.00

56.39

13532.53

b) M.S. shoes

Kg

105.00

42.08

4418.43

246

Sr No

Ref. to
MoRTH
Spec.

Description

c)

d)

Unit

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

Quantity

Rate Rs

30.00

51.16

1534.94

785.16

4710.96

Crane20 t capacity

hour

6.00

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

Mate/Supervisor

day

0.12

185.07

22.21

Mazdoor

day

3.00

177.07

531.21

Value

#VALUE!

e)

Overhead charges @ 0.25 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!
#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e+f)/60


say

12.30

1100 &
1700

#VALUE!

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.

Cost for 60 m = a+b+c+d+e+f

Note

Cost Rs

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials
cum

RCC Grade M35

22.08

5195.00

114705.60

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes

Kg

160.00

56.39

9021.68

b) M.S. shoes

Kg

70.00

42.08

2945.62

Kg

40.00

51.16

2046.59

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane 40 T capacity

hour

6.00

1166.40

6998.40

hour

6.00

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.16

185.07

29.61

Mazdoor

day

4.00

177.07

708.28

Value

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 50 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/50


say

Note

12.31

1100 &
1700

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials

247

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
cum

RCC Grade M35

Quantity

Rate Rs

Cost Rs

31.40

5195.00

163123.00

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

c)

d)

a) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

b) M.S. shoes @ 35 Kg per pile of 15 m

Kg

70.00

42.08

2945.62

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

50.00

51.16

2558.23

1176.12

7056.72

Crane 50 t capacity.

hour

6.00

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

Mate/Supervisor

day

0.20

185.07

37.01

Mazdoor

day

5.00

177.07

885.35

Value

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 40 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/40


say

Note

12.32

1100&17
00

#VALUE!

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)

cum

5.40

5195.00

28053.00

b ) Material Pile shoes

c)

a) C I shoes

kg

240.00

56.39

13532.53

b) M. S shoes

kg

105.00

42.08

4418.43

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

hour

6.00

627.48

3764.88

hour

6.00

Mate/Supervisor

day

0.12

185.07

Mazdoor

day

3.00

177.07

Crane 10 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Value

22.21
531.21
#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 60 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/60


say

Note

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.

248

#VALUE!

Sr No
12.33

Ref. to
MoRTH
Spec.

Description

1100
&1700

Unit

Quantity

Rate Rs

Cost Rs

Driven precast vertical M35 grade R.C.C. Piles excluding


Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)

cum

12.50

5195.00

64937.50

b ) Material Pile shoes

c)

a) C I shoes

kg

160.00

56.39

9021.68

b) M. S shoes

kg

70.00

42.08

2945.62

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

hour

6.00

785.16

4710.96

hour

6.00

Mate/Supervisor

day

0.16

185.07

29.61

Mazdoor

day

4.00

177.07

708.28

Crane 20 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Value

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

Cost for 50 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/50

#VALUE!
say

Note

12.34

1100
&1700

#VALUE!

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 13.11( F ) (IV)
b ) Material

cum

22.50

5195.00

116887.50

Pile shoes

c)

a) C I shoes

kg

160.00

56.39

9021.68

b) M. S shoes

kg

70.00

42.08

2945.62

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

hour

6.00

785.16

4710.96

hour

6.00

Mate/Supervisor

day

0.18

185.07

33.31

Mazdoor

day

4.50

177.07

796.82

Crane 20 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

e)

Value

#VALUE!

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.

#VALUE!

Overhead charges @ 0.25 on (b+c+d)

#VALUE!

249

Sr No

Ref. to
MoRTH
Spec.

Description
f)

Unit

Quantity

Rate Rs

#VALUE!

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

Cost for 40 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/40


say

Note

12.35

1100,
1900

Cost Rs

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven Vertical Steel Piles complete as per Drawing and &
Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a)

Materials

b)

Structural steel including 5 per cent wastage @ 82.20


kg/m
Machinery

c)

tonnes

6.04

46527.33

281025.09

Crane 10 T capacity

hour

6.00

627.48

3764.88

Vibrating Pile driving hammer complete with power unit


and other accessories.

hour

6.00

Mate/Supervisor

day

0.12

185.07

Mazdoor

day

3.00

177.07

Value

Labour
531.21
#VALUE!

d)

Overhead charges @ 0.25 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e)/70


say

1100
&1900

22.21

Add 0.5 per cent of (a+b+c) for providing steel


helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and other
imponderables during installation.

Cost for 70 m = a+b+c+d+e

12.36

#VALUE!

#VALUE!

Driven Vertical Steel Piles complete as per Drawing and &


Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a)

Materials

b)

Structural steel including 5 per cent wastage @92.50


kg/m
Machinery

c)

tonnes

5.83

46527.33

271254.35

Crane 10 T capacity

hour

6.00

627.48

3764.88

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

Mate/Supervisor

day

0.14

185.07

25.91

Mazdoor

day

3.50

177.07

619.75

Value

Add 0.5 per cent of (a+b+c) for providing steel


helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

#VALUE!

d)

Overhead charges @ 0.25 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!

Cost for 60 m = a+b+c+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/60


say

12.37

1100

#VALUE!

Pile Load Test on single Vertical Pile in accordance with


IS:2911(Part-IV)
Unit = 1 MT
250

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Taking output = 1 MT

Note

12.38

1100,
1500
&1700

a) Initial and routine load test

tonne

1.00

300.00

300.00

b) Lateral load test

tonne

1.00

5000.00

5000.00
5300.00

Although, this item is incidental to work and is not required to


be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

RCC Grade M20


Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

5.12

5789.47

29642.11

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.90

185.07

166.56

Mason

day

1.50

208.99

313.49

Mazdoor for concreting

day

20.00

177.07

3541.40

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

1962.67

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12757.35
6378.67
70165.42

Cost for 15 cum = a+b+c+d+e

4677.69

Rate per metre (a+b+c+d+e)/15


say

12.38A

(ii)

4678.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

5.12

5789.47

29642.11

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.16

185.07

29.61

Mason

day

0.38

208.99

79.42

Mazdoor for concreting

day

2.50

177.07

442.68

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

Batching Plant @ 20 cum/hour

hour

0.75

2488.00

1866.00

Generator 100 KVA

hour

0.75

1698.00

1273.50

Loader (capacity 1 cum)

hour

1188.00

891.00

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) Material, b) Labour and c) Machinery
251

hour

2.00

854.55

1709.10

tonne.km

37.5L

4.32

162.00

hour

0.75

234.36

175.77
1934.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Quantity

Rate Rs

12571.03
6285.51
69140.66

Cost for 15 cum = a+b+c+d+e

4609.38

Rate per metre (a+b+c+d+e)/15


say

Note
12.38

Cost Rs

4609.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M25
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

5.99

5789.47

34678.95

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.90

185.07

166.56

Mason

day

1.50

208.99

313.49

Mazdoor for concreting

day

20.00

177.07

3541.40

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2164.14
14066.93
7033.46
77368.10

Cost for 15 cum = a+b+c+d+e

5157.87

Rate per metre (a+b+c+d+e)/15


say

12.38B

(ii)

5158.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

5.99

5789.47

34678.95

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.16

185.07

29.61

Mason

day

0.38

208.99

79.42

Mazdoor for concreting

day

2.50

177.07

442.68

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

Batching Plant @ 20 cum/hour

hour

0.75

2488.00

1866.00

Generator 125 KVA

hour

0.75

2307.00

1730.25

Loader (capacity 1 cum)

hour

1188.00

891.00

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)


252

hour

2.00

854.55

1709.10

tonne.km

37.5L

4.32

162.00

hour

0.75

234.36

175.77
2153.75
13999.36
6999.68

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

76996.50

Cost for 15 cum = a+b+c+d+e

5133.10

Rate per metre (a+b+c+d+e)/15


say

Note
12.38

Cost Rs

5133.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M30
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

6.10

5789.47

35315.79

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.90

185.07

166.56

Mason

day

1.50

208.99

313.49

Mazdoor for concreting

day

20.00

177.07

3541.40

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

2189.62

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14232.51
7116.25
78278.79

Cost for 15 cum = a+b+c+d+e

5218.59

Rate per metre (a+b+c+d+e)/15


say

'12.38C

(ii)

5219.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

6.10

5789.47

35315.79

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.16

185.07

29.61

Mason

day

0.38

208.99

79.42

Mazdoor for concreting

day

2.50

177.07

442.68

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

Batching Plant @ 20 cum/hour

hour

0.75

2488.00

1866.00

Generator 100 KVA

hour

0.75

1698.00

1273.50

Loader (capacity 1 cum)

hour

1188.00

891.00

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

1709.10

tonne.km

37.5L

4.32

162.00

hour

0.75

234.36

175.77
2160.95
14046.19
7023.09
77254.03

Cost for 15 cum = a+b+c+d+e

5150.27

Rate per metre (a+b+c+d+e)/15


253

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

Note
12.38

Cost Rs
5150.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M35
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

6.33

5789.47

36647.37

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.90

185.07

166.56

Mason

day

1.50

208.99

313.49

Mazdoor

day

20.00

177.07

3541.40

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

2242.88

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14578.72
7289.36
80182.95

Cost for 15 cum = a+b+c+d+e

5345.53

Rate per metre (a+b+c+d+e)/15


say

'12.38D

(ii)

5346.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

6.33

5789.47

36647.37

Coarse sand

cum

6.75

203.75

1375.34

20 mm Aggregate

cum

8.10

862.50

6986.27

10 mm Aggregate

cum

5.40

655.60

3540.26

Mate

day

0.16

185.07

29.61

Mason

day

0.38

208.99

79.42

Mazdoor for concreting

day

2.50

177.07

442.68

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

Batching Plant @ 20 cum/hour

hour

0.75

2488.00

1866.00

Generator 125 KVA

hour

0.75

2307.00

1730.25

Loader (capacity 1 cum)

hour

1188.00

891.00

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

1709.10

tonne.km

37.5L

4.32

162.00

hour

0.75

234.36

175.77
2232.49
14511.15
7255.58
79811.34

Cost for 15 cum = a+b+c+d+e


Rate per metre (a+b+c+d+e)/15

5320.76
say

254

5321.00

Sr No
12.39

Ref. to
MoRTH
Spec.
1100&17
00

Description

Unit

Quantity

Rate Rs

Cost Rs

Levelling Course for Pile cap


Providing and laying of PCC M15 levelling course 100mm
thick below the pile cap.
Unit = cum
Taking output = 15 cum
a)

Material
tonne

4.13

5789.47

23910.53

Coarse sand

cum

6.75

203.75

1375.34

40 mm aggregate

cum

8.10

758.35

6142.67

20 mm Aggregate

cum

4.05

862.50

3493.13

10 mm Aggregate

cum

1.35

655.60

885.06

Mate

day

0.86

185.07

159.16

Mason

day

1.50

208.99

313.49

Mazdoor

day

20.00

177.07

3541.40

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

Generator 33 KVA

hour

6.00

342.36

2054.16

Cement

b)

c)

Labour

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10786.25
5393.13
59324.40

Cost for 15 cum = a+b+c+d+e

3954.96

Rate per metre (a+b+c+d+e)/15


say

12.40

1600

3955.00

Supplying, Fitting and Placing un-coated HYSD bar


Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a)

Material
tonne

1.05

46059.03

48361.98

Kg

6.00

62.52

375.14

day

0.40

185.07

74.03

Blacksmith

day

2.00

234.29

468.58

Mazdoor

day

6.00

177.07

1062.42

HYSD bars including5 per cent overlaps and wastage


Binding wire
b)
Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

12585.54

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

6292.77
69220.46

Rate per MT (a+b+c+d)


say

12.41

1600

69220.00

Supplying, fitting and placing un-coated Mild steel


reinforcement complete in foundation as per drawing and
technical specification
Unit = 1 MT
Taking output = 1 MT
a)

Material
tonne

1.05

48690.69

51125.22

Kg

6.00

62.52

375.14

day

0.43

185.07

79.58

Blacksmith

day

2.25

234.29

527.15

Mazdoor

day

6.50

177.07

1150.96

MS bars including 5 per cent overlaps and wastage


Binding wire
b)
Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate

13314.51

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

6657.26
73229.82

Rate for per MT (a+b+c+d)

255

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

256

Cost Rs
73230.00

CHAPTER-12

FOUNDATIONS
Sr No

Ref. to
MoRTH
Spec.

12.1

304

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation for Structures


Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with approved material.
I

Ordinary soil
Unit = cum
Taking output = 10 cum

A
(i)

Manual Means
Depth upto 3 m
a) Labour
Mate
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

0.14

185.07

25.91

L-12

day

3.50

177.07

619.75

L-13

161.41
80.71
887.78
88.78
say

Note

89.00

1. Cost of dewatering may be added where required upto, 10


percent of labour cost assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding marshy soil.
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.

12.1 (I) A

(ii)

Depth 3 m to 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

0.18

185.07

33.31

L-12

day

4.50

177.07

796.82

L-13

207.53
103.77
1141.43
114.14
say

12.1 (I) A

Note

Cost of dewatering may be added where required upto 15 per


cent of labour cost. Assessment for dewatering shall be done
as per actual ground conditions.

(iii)

Depth above 6 m
a) Labour
Mate/Supervisor
Mazdoor
b) Overhead charges @ 0.25 on (a)
c) Contractor's profit @ 0.1 on (a+b)
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

day

0.24

185.07

44.42

L-12

day

6.00

177.07

1062.42

L-13

276.71
138.35
1521.90
152.19
say

Note

12.1 (I)

B
(i)

114.00

1. Cost of dewatering may be added where required upto 20


per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
Mechanical Means
Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
257

152.00

day

0.32

185.07

59.22

L-12

day

8.00

177.07

1416.56

L-13

hour

6.00

1516.32

9097.92

P&M-026

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

1321.71
14538.84
60.58
say

12.1 (I) B

(ii)

61.00

Cost of dewatering upto 5 per cent of (a+b) may be added,


where required. Assessment for dewatering shall be made as
per site conditions..
Depth 3 m to 6 m
Unit = cum
Taking output = 210 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity
c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

day

0.32

185.07

59.22

L-12

day

8.00

177.07

1416.56

L-13

hour

6.00

1516.32

9097.92

P&M-026

2643.43
1321.71
14538.84

Cost for 210 cum = a+b+c+d

69.23

Rate per cum = (a+b+c+d)/210


say

12.1 (I) B

Remarks/
Input ref.

2643.43

c) Overhead charges @ 0.25 on (a+b)


d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Note

Cost Rs

Note

Cost of dewatering upto 7.5 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions..

(iii)

Depth above 6m

69.00

Unit = cum
Taking output = 180 cum
a)

b)

Labour
Mate

day

0.40

185.07

74.03

L-12

Mazdoor

day

10.00

177.07

1770.70

L-13

hour

6.00

1516.32

9097.92

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.25 on (a+b)

2735.66

d)

Contractor's profit @ 0.1 on (a+b+c)

1367.83
15046.14

Cost for 180 cum = a+b+c+d

83.59

Rate per cum = (a+b+c+d)/180


say

Note

84.00

1. Cost of dewatering upto 10 per cent of (a+b) may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side slopes.

12.1

II

Ordinary Rock (not requiring blasting)

Manual Means

(i)

Depth upto 3 m
Unit = cum
Taking output = 10 cum
a)

Labour
Mate

day

0.20

185.07

37.01

L-12

Mazdoor

day

5.00

177.07

885.35

L-13

b)

Overhead charges @ 0.25 on (a)

230.59

c)

Contractor's profit @ 0.1 on (a+b)

115.30
1268.25

Cost for 10 cum = a+b+c

126.83

Rate per cum = (a+b+c)/10


say

Note

12.1(II)

Cost of dewatering upto 10 per cent of labour cost may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
Mechanical Means
258

127.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit = cum
Taking output = 180 cum
a)

b)

Labour
Mate

day

0.24

185.07

44.42

L-12

Mazdoor

day

6.00

177.07

1062.42

L-13

hour

6.00

1516.32

9097.92

P&M-026

Machinery
Hydraulic excavator 1.0 cum bucket capacity

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2551.19
1275.59
14031.54

Cost for 180 cum = a+b+c+d

77.95

Rate per cum = (a+b+c+d)/180


say

Note

78.00

1.Cost of dewatering upto 10 per cent of (a+b), may be


added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond 3 m is not dug and
hence not included.

12.1

III

Hard Rock ( requiring blasting )

Manual Means
Unit = cum
Taking output = 10 cum
a)

b)

Labour
Mate

day

0.35

185.07

64.77

L-12

Driller

day

0.50

206.99

103.50

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

8.00

177.07

1416.56

L-13

hour

1.00

293.76

293.76

P&M-001

3.50

112.77

394.70

M-104

14.00

14.27

Machinery
Air Compressor 250 cfm with 2 jack hammer for drilling.

c)

Material
Blasting Material

kg

Detonator electric

each

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

636.34
318.17
3499.84

Cost for 10 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/10

349.98
say

Note

12.1

IV

199.73 M-094/100

350.00

Cost of dewatering @ 10 percent of (a+b) may be added,


where required. Assessment for dewatering shall be made as
per site conditions.
Hard Rock ( blasting prohibited )
Unit = cum
Taking output = 10 cum

Mechanical Means
a)

Labour
Mate

day

0.20

185.07

37.01

L-12

Mazdoor

day

5.00

177.07

885.35

L-13

hour

6.00

293.76

1762.56

b)

Machinery

c)

Air Compressor 250 cfm with 2 leads of pneumatic


breaker
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

671.23
335.62
3691.77

Cost for 10 cum = a+b+c+d

369.18

Rate per cum = (a+b+c+d)/10


say

Note

1. Cost of dewatering upto10 per cent of (a+b), may be


added, where required. Assessment for dewatering shall be
made as per site conditions.
259

369.00

P&M-001

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

2.In case of rock, foundation beyond3 m is not dug and hence


not included.
12.1

Marshy Soil
Unit = cum
Taking output = 10 cum
Depth upto 3 m

Manual means
a)

b)

Labour
Mate/Supervisor

day

0.40

185.07

74.03

L-12

Mazdoor

day

10.00

177.07

1770.70

L-13

hour

2.67

171.02

456.62

Machinery
Tractor-trolley for removal.

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

287.67
3164.35

Cost for 10 cum = a+b+c+d

316.44

Rate per cum = ( a+b+c+d)/ 10


say

Note

P&M-053

575.34

316.00

1. Cost of dewatering @ 30 per cent of (a), may be added,


where required Assessment for dewatering shall be made as
per site conditions.
2. Shoring & strutting 15 per cent of (a), where required may
be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item12.1-IA (ii) to (iii) for ordinary soil

12.1 (V)

Mechanical Means
a)

b)

Labour
Mate

day

0.08

185.07

14.81

L-12

Mazdoor for dressing sides, bottom and backfilling

day

2.00

177.07

354.14

L-13

hour

0.17

1516.32

257.77

P&M-026

hour

0.45

873.00

392.85

P&M-048

Machinery
Hydraulic excavator 1.0 cum bucket capacity @ 60 cum
per hour
Tipper 5.5 cum capacity, 4 trips per hour.

c)

Overhead charges @ 0.25 on (a+b)

254.89

d)

Contractor's profit @ 0.1 on (a+b+c)

127.45
1401.91

Cost for 10 cum = a+b+c+d

140.19

Rate per cum = (a+b+c+d)/10


say

Note

140.00

1. Cost of dewatering @ 20 percent of (a+b) may be added,


where required
2. Shoring & strutting @ 10 percent of (a+b), where required
may be added
3. It is assumed that Marshy Soil will be available upto 3 m
depth only. For deeper excavation below 3 m depth, refer
analysis in item 12.1-IB (ii) to (iii) for ordinary soil

VI

Back Filling in Marshy Foundation Pits


Unit : Cum
Taking Output : 6 cum
a)

b)

Labour
Mate

day

0.12

185.07

22.21

L-12

Mazdoor for dressing sides, bottom and backfilling

day

3.00

177.07

531.21

L-13

hour

2.00

171.02

342.04

P&M-053

Machinery
Tractor-trolley for transportation

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

223.86
111.93
1231.25

Cost for 6 cum = a+b+c+d

205.21

Rate per cum = (a+b+c+d)/6

260

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.2

304

Cost Rs

Remarks/
Input ref.

205.00

Filling Annular Space Around Footing in Rock


Unit = cum
Taking out put = 1 cum

12.3

VALUE

Lean cement concrete 1:3:6 nominal mix. Rate may be taken


as per item 12.4.
Sand Filling in Foundation Trenches as per Drawing &
Technical Specification
Unit = cum

304

Taking output = 1 cum


a)

b)

Labour
Mate

day

0.01

185.07

1.85

L-12

Mazdoor

day

0.30

177.07

53.12

L-13

cum

1.20

109.09

130.90

Material
Sand (assuming 20 per cent voids)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

46.47
23.23
255.58

Rate per cum = a+b+c+d


say

12.4

2100

M-006

256.00

PCC 1:3:6 in Foundation


Plain cement concrete 1:3:6 nominal mix in foundation with
crushed stone aggregate 40 mm nominal size mechanically
mixed, placed in foundation and compacted by vibration
including curing for 14 days.
Unit = cum
Taking output = 15 cum
a)

b)

Labour
Mate

day

0.64

185.07

118.44

L-12

Mason

day

1.00

234.29

234.29

L-11

Mazdoor

day

15.00

177.07

2656.05

L-13

40 mm Aggregate

cum

13.50

758.35

10237.78

M-055

coarse Sand

cum

6.75

203.75

1375.34

M-005

tonne

3.45

5789.47

19973.68

M-081

18.00

167.07

3007.23

M-189

Material

cement
Cost of water
c)

KL

Machinery
Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Water tanker 6 KL capacity

hour

2.00

111.24

222.48

P&M-060

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10287.38
5143.69
56580.61

Cost for 15 cum = a+b+c+d+e

3772.04

Rate per cum = (a+b+c+d+e)/15


say

Note
12.5

1300

3772.00

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.
Brick Masonry Work in Cement Mortar 1:3 in Foundation
complete excluding Pointing and Plastering, as per
Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum
a)

b)

Material
Bricks Ist class

each

2500.00

4.33

10821.43

Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)

cum

1.20

3333.00

3999.60

day

0.48

185.07

88.83

M-079
Item 12.6
(A)

Labour
Mate

261

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

day

4.00

234.29

937.16

L-11

Mazdoor

day

8.00

177.07

1416.56

L-13

c)

Overhead charges @ 0.25 on (a+b)

4315.90

d)

Contractor's profit @ 0.1 on (a+b+c)

2157.95
23737.43
4747.49

Rate per cum (a+b+c+d)/5


say

Subanalysis

Remarks/
Input ref.

Mason

Cost for 5 cum = a+b+c+d

12.6

Cost Rs

4747.00

(i)

Rate for Brick Work in C. M. 1:2 in foundation

5049.00

(ii)

Rate for Brick Work in C. M. 1:3 in foundation

4747.00

(iii)

Rate for Brick Work in C. M. 1:4 in foundation

4542.00

(iv)

Rate for Brick Work in C. M. 1:6 in foundation

4343.00

(A)

Cement Mortar 1:3 (1 cement : 3 sand)


Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.51

5789.47

2952.63

M-081

cum

1.05

203.75

213.94

M-005

Mate

day

0.04

185.07

7.40

L-12

Mazdoor

day

0.90

177.07

159.36

L-13

Cement
Sand
b)

Labour

say

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(B)

3333.00

Cement Mortar1:2 (1cement :2 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.672

5789.47

3890.53

M-081

cum

0.933

203.75

190.17

M-005

Mate

day

0.04

185.07

7.40

L-12

Mazdoor

day

0.90

177.07

159.36

L-13

Cement
Sand
b)

Labour

say

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(C)

4247.00

Cement Mortar1:4 (1cement :4 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.40

5789.47

2315.79

M-081

cum

1.12

203.75

228.20

M-005

Mate

day

0.04

185.07

7.40

L-12

Mazdoor

day

0.90

177.07

159.36

L-13

Cement
Sand
b)

Labour

say

Total Material and Labour = (a+b)


Subanalysis
(Addl.)

(D)

2711.00

Cement Mortar1:6 (1cement :6 sand)

Unit = 1 cum
Taking output = 1 cum
a)

Materials
tonne

0.288

5789.47

1667.37

M-081

cum

1.337

203.75

272.45

M-005

Mate

day

0.04

185.07

7.40

L-12

Mazdoor

day

0.90

177.07

159.36

L-13

Cement
Sand
b)

Labour

262

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

say

Total Material and Labour = (a+b)


12.7

1400

Rate Rs

Cost Rs

Remarks/
Input ref.

2107.00

Stone Masonry Work in Cement Mortar 1:3 in Foundation


complete as per Drawing and Technical Specifications.
Unit = cum
Taking output = 5 cum

1405.4

(A)

Square Rubble Coursed Rubble Masonry (first sort)


a)

Material
Stone

cum

5.50

360.24

1981.32

M-169

Through and bond stone

each

35.00

6.06

211.97

M-182

cum

1.50

3333.00

4999.50

Mate

day

0.66

185.07

122.15

L-12

Mason

day

7.50

234.29

1757.18

L-11

Mazdoor

day

9.00

177.07

1593.63

L-13

(35no.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)
b)

Labour

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2666.44
1333.22
14665.40

Cost for 5 cum = a+b+c+d

2933.08

Rate per cum (a+b+c+d)/5


say

1405.3

(B)

Item 12.6
(A)

2933.00

Random Rubble Masonry


( coursed/uncoursed )
Unit = cum
Taking output = 5 cum
a)

Material
Stone

cum

5.50

359.72

1978.45

M-148

Through and bond stone

each

35.00

6.06

211.97

M-182

cum

1.55

3333.00

5166.15

Mate

day

0.62

185.07

114.74

L-12

Mason

day

6.00

234.29

1405.74

L-11

Mazdoor

day

9.00

177.07

1593.63

L-13

(35nos.x0.24mx0.24mx0.39m = 0.79 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6 A sub-analysis)
b)

Labour

c)

Overhead charges @ 0.25 on (a+b)

2617.67

d)

Contractor's profit @ 0.1 on (a+b+c)

1308.84
14397.19

Cost for 5 cum = a+b+c+d

2879.44

Rate per cum (a+b+c+d)/5


say

Note

12.8

1500,
1700 &
2100

Item 12.6
(A)

2879.00

The labour already considered in cement mortar has been


taken into account while proposing labour for masonry works.
Plain/Reinforced Cement Concrete in Open Foundation
complete as per Drawing and Technical Specifications.

PCC Grade M15


Unit = cum
Taking output = 15 cum
a)

Material
tonne

4.13

5789.47

23910.53

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm Aggregate

cum

8.10

758.35

6142.67

M-055

20 mm Aggregate

cum

4.05

862.50

3493.13

M-053

10 mm Aggregate

cum

1.35

655.60

885.06

M-051

day

0.86

185.07

159.16

L-12

Cement

b)

Labour
Mate
263

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Unit

Quantity

Rate Rs

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 63 KVA

hour

6.00

361.80

2170.80

P&M-019

Machinery

2887.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1731.98

11257.90
5628.95
61918.44

Cost for 15 cum = a+b+c+d+e+f

4127.90

Rate per cum = (a+b+c+d+e+f)/15


say

12.8

Remarks/
Input ref.

Mason

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery

Note

Cost Rs

4128.00

Needle Vibrator is an item of minor T & P which is already


included in overhead charges. Hence not added in rate
analysis of cement concrete works.
PCC Grade M20
Unit : cum
Taking output = 15 cum
a)

Material
tonne

5.16

5789.47

29873.68

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm Aggregate

cum

5.40

758.35

4095.11

M-055

20 mm Aggregate

cum

5.40

862.50

4657.51

M-053

10 mm Aggregate

cum

2.70

655.60

1770.13

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

3277.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

1965.92
12778.48
6389.24

Contractor's profit @ 0.1 on (a+b+c+d+e)

70281.66

Cost for 15 cum = a+b+c+d+e+f

4685.44

Rate per cum = (a+b+c+d+e+f)/15


say

12.8

C
Case I

4685.00

RCC Grade M20


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.21

5789.47

30163.16

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Cement

b)

c)

Labour

Machinery

264

Sr No

Ref. to
MoRTH
Spec.

Description

d)

Unit

Concrete mixer (cap. 0.40/0.28 cum)

hour

Generator 33 KVA

hour

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Rate Rs

Remarks/
Input ref.

6.00

211.68

1270.08

P&M-009

6.00

342.36

2054.16

P&M-079

1977.65
12854.73
6427.36
70701.00

Cost for 15 cum = a+b+c+d+e+f

4713.40

Rate per cum = ( a+b+c+d+e+f )/15


say

12.8 C

Cost Rs

3297.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 4 per cent on (a+b+c)

e)

Quantity

4713.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a) Material
tonne

41.66

5789.47

241189.47

M-081

Coarse Sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

6.00

2488.00

14928.00

P&M-002

6.00

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

234.36

1406.16

P&M-050
Lead= 1
km
P&M-007

Lead beyond 1 km, L-lead in km

hour

Concrete Pump

3236.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

15528.58
100935.74
50467.87

Contractor's profit @ 0.1 on (a+b+c+d+e)

555146.58

Cost for 120 cum = a+b+c+d+e+f

4626.22

Rate per cum = ( a+b+c+d+e+f )/120


say

12.8

D
Case I

4626.00

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.99

5789.47

34678.95

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm Aggregate

cum

5.40

758.35

4095.11

M-055

20 mm Aggregate

cum

5.40

862.50

4657.51

M-053

10 mm Aggregate

cum

2.70

655.60

1770.13

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

265

Sr No

Ref. to
MoRTH
Spec.

Description

d)

Unit

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Rate Rs

Remarks/
Input ref.

2023.25
13994.13
6997.07
76967.72

Cost for 15 cum = a+b+c+d+e+f

5131.18

Rate per cum = ( a+b+c+d+e+f )/15


say

12.8 D

Cost Rs

3597.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 3.75 per cent of (a+b+c)

e)

Quantity

5131.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a)

Material
tonne

47.95

5789.47

277605.26

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

40 mm Aggregate

cum

43.20

758.35

32760.89

M-055

20 mm Aggregate

cum

43.20

862.50

37260.09

M-053

10 mm Aggregate

cum

21.60

655.60

14161.02

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

hour

Concrete Pump

3539.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.75 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

15922.50
110130.63
55065.31

Contractor's profit @ 0.1 on (a+b+c+d+e)

605718.44

cost of 120 cum = a+b+c+d+e+f

5047.65

Rate per cum = (a+b+c+d+e+f)/120


say

12.8

E
Case I

5048.00

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.05

5789.47

35026.32

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)

266

3621.00

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

14085.21
7042.60
77468.64

cost of 15 cum = a+b+c+d+e+f

5164.58

Rate per cum (a+b+c+d+e+f )/15


say

12.8 E

Remarks/
Input ref.

2036.42

Formwork @ 3.75 per cent of a+b+c.

e)

Cost Rs

5165.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Unit: cum
Taking Output = 120 cum
a)

Material
Cement

b)

c)

tonne

48.38

5789.47

280094.74

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

6.00

2488.00

14928.00

P&M-002

6.00

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

1698.00

10188.00

P&M-080

Loader 1 cum capacity 1 cum

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

hour

Concrete Pump

3560.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 3.75 per cent on cost of concrete i.e.
cost of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

16016.99
110784.16
55392.08

Contractor's profit @ 0.1 on (a+b+c+d+e)

609312.88

cost of 120 cum = a+b+c+d+e+f

5077.61

Rate per cum (a+b+c+d+e+f )/120


say

12.8

F
Case I

5078.00

PCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.08

5789.47

35200.00

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm Aggregate

cum

5.40

758.35

4095.11

M-055

20 mm Aggregate

cum

5.40

862.50

4657.51

M-053

10 mm Aggregate

cum

2.70

655.60

1770.13

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost
of material, labour and machinery

267

3632.00
1906.60

Sr No

Ref. to
MoRTH
Spec.

Description
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

14095.23
7047.62
77523.78

cost of 15 cum = a+b+c+d+e+f

5168.25

Rate per cum (a+b+c+d+e+f )/15


say

12.8 F

Cost Rs

5168.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit : cum
Taking Output = 120 cum
a)

Material
tonne

48.60

5789.47

281368.42

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

40 mm Aggregate

cum

43.20

758.35

32760.89

M-055

20 mm Aggregate

cum

43.20

862.50

37260.09

M-053

10 mm Aggregate

cum

21.60

655.60

14161.02

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

6.00

2488.00

14928.00

P&M-002

6.00

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead


in Kilometer

hour

Concrete Pump

3570.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.50 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

14992.71
110838.97
55419.48

Contractor's profit @ 0.1 on (a+b+c+d+e)

609614.32

cost of 120 cum = a+b+c+d+e+f

5080.12

Rate per cum (a+b+c+d+e+f )/120


say

12.8

G
Case I

5080.00

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.10

5789.47

35315.79

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)

268

3640.00
1910.79
14126.17

Sr No

Ref. to
MoRTH
Spec.

Description
f)

Unit

Quantity

Rate Rs

77693.93
5179.60

Rate per cum = (a+b+c+d+e+f)/15


say

Case II

Remarks/
Input ref.

7063.08

Contractor's profit @ 0.1 on (a+b+c+d+e)

cost of 15 cum = a+b+c+d+e+f

12.8 G

Cost Rs

5180.00

Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.80

5789.47

282526.32

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead
in Kilometer

hour

Concrete Pump

3580.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

15034.29
111146.38
55573.19

Contractor's profit @ 0.1 on (a+b+c+d+e)

611305.10

cost of 120 cum = a+b+c+d+e+f

5094.21

Rate per cum (a+b+c+d+e+f )/120


say

12.8

H
Case I

5094.00

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
Cement

b)

c)

d)

tonne

6.33

5789.47

36647.37

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Formwork @ 3 per cent on a+b+c

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3729.00
1677.76
14400.81
7200.40
79204.44

cost of 15 cum = a+b+c+d+e+f

5280.30

Rate per cum = (a+b+c+d+e+f)/15


269

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.8 H

Cost Rs

Remarks/
Input ref.

5280.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit ; cum
Taking Output = 120 cum
a)

Material
tonne

50.64

5789.47

293178.95

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead
in Kilometer

hour

Concrete Pump

3669.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost of
material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)
f)

13206.12
113352.49
56676.25

Contractor's profit @ 0.1 on (a+b+c+d+e)

623438.72

cost of 120 cum = a+b+c+d+e+f

5195.32

Rate per cum = (a+b+c+d+e+f)/120


say

Note:

5195.00

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.

WELL FOUNDATION
12.9

1200

Providing and Constructing Temporary Island 16 m


diameter for Construction of Well Foundation for 8m dia.
Well.
A

Assuming depth of water 1.0 m and height of island to be


1.25 m including Royality for earth @ Rs. 3768.00 for
each Island.
Unit = 1 No
Taking output = 1 No.
a)

b)

c)

Material
Earth (compacted)

cum

251.20

25.1

6305.12

M-092

Sand bags

each

750.00

1.73

1298.57

M-159

Mate

day

0.40

185.07

74.03

L-12

Mazdoor for filling sand bags, stitching and placing

day

15.00

177.07

2656.05

L-13

hour

20.00

784.62

15692.40

Labour

Machinery
Crane with grab 1 cum capacity

392.31

Consumables @ 2.5 per cent of (c) above


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6604.62
3302.31
36325.41

Rate per No. (a+b+c+d+e)


say

Note

It is assumed that earth will be available within the working


space of crane with grab bucket.
270

36325.00

P&M-012

Sr No

Ref. to
MoRTH
Spec.

12.9

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Assuming depth of water 4.0 m and height of island 4.5 m


including Royality for earth @ Rs. 13565.00 for each
Island.
Unit = 1No
Taking output = 1 No
a)

b)

c)

Material
Earth (compacted)

cum

904.32

25.10

22698.43

M-092

Sand bags

each

Wooden ballies 8" Dia and 9 m long

each

6000.00

1.73

10388.57

M-159

95.00

49.23

4676.82

Wooden ballies 2" Dia for bracing

metre

M-194

190.00

17.81

3383.23

M-193

Labour
Mate

day

5.60

185.07

1036.39

L-12

Mazdoor for piling 8" dia ballies for piling 8" dia ballies

day

18.00

177.07

3187.26

L-13

Mazdoor for bracing with 2" dia ballies

day

12.00

177.07

2124.84

L-13

Mazdoor for filling sand bags, stitching and placing

day

110.00

177.07

19477.70

L-13

hour

50.00

784.62

39231.00

P&M-012

Machinery
Crane with grab 1 cum capacity

2655.11

Consumables and other arrangements for piling ballies @ 2.5


per cent of (a+b+c).
d) Overhead charges @ 0.25 on (a+b+c)

27214.84

e)

13607.42

Contractor's profit @ 0.1 on (a+b+c+d)

149681.62

Rate per No. (a+b+c+d+e)


say

Note

12.9

149682.00

For other well diameters rate can be worked out on the basis
of cross-sectional area of well. The diameter of the island
shall be in the conformity with clause 1203.2 of MoRTH
specifications.
Providing and constructing one span service road to
reach island location from one pier location to another
pier location including Royality for earth @ Rs. 225.00 per
m for service Road.
Assuming span length 30 m, width of service road 10m and
depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a)

b)

c)

Material
Earth

cum

450.00

25.10

11295.00

M-092

Sand bags

each

300.00

1.73

519.43

M-159

Mate

day

0.24

185.07

44.42

L-12

Mazdoor for filling sand bags, stitching and placing

day

6.00

177.07

1062.42

L-13

Front end Loader 1 cum capacity

hour

27.00

1188.00

32076.00

P&M-017

Tipper 5.5 cum capacity

hour

28.00

873.00

24444.00

P&M-048

Labour

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

17360.32
8680.16
95481.74

Cost for 30 m (a+b+c+d+e)

3182.72

Rate per m (a+b+c+d+e)/30


say

12.10

1200 &
1900

3183.00

Providing and Laying Cutting Edge of Mild Steel weighing


40 kg per metre for Well Foundation complete as per
Drawing and Technical Specification.
Unit = 1 MT
Taking output = 1 MT
a)

Material
Structural steel in plates, angles, etc including 5 per
cent wastage
Nuts & bolts

271

tonne
Kg

1.05

46527.33

48853.70

M-179

20.00

45.42

908.43

M-130

Sr No

Ref. to
MoRTH
Spec.

Unit

(for cutting, bending, making holes, joining, welding and


erecting in position)
Mate

day

1.32

185.07

244.29

L-12

Fitter

day

5.50

238.29

1310.60

L-08

Blacksmith

day

5.50

234.29

1288.60

L-02

Welder

day

5.50

234.29

1288.60

L-02

Mazdoor

day

16.50

177.07

2921.66

L-13

b)

Quantity

Rate Rs

d)

4976.21
15448.02
7724.01

Contractor's profit @ 0.1 on (a+b+c)

84964.11

Rate per MT (a+b+c+d)


say

1200,
1500 &
1700

Cost Rs

Labour

Electrodes, cutting gas and other consumables @ 10 per cent


of cost of (a) above
c) Overhead charges @ 0.25 on (a+b)

12.11

Remarks/
Input ref.

Description

84964.00

Plain/Reinforced Cement Concrete, in Well Foundation


complete as per Drawing and Technical Specification.
Unit = 1 cum
Taking output = 1 cum
A

Well curb

(i)

RCC M20 Grade

Case I

Same as for 12.8 (C) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
3297.00 Item 12.8
(C)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


formwork @ 20 per cent of the cost of concrete

659.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

989.10

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

494.55
5440.05

Rate perm (a+b+c+d+e+f)


say

12.11 A (i)

3234.00 Item 12.8


(C)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 20 per cent of the cost of concrete

646.80

e)

Overhead charges @ 0.25 on (a+b+c+d)

970.20

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

485.10
5336.10

Rate perm (a+b+c+d+e+f)


say

12.11 A

5440.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

(ii)

5336.00

RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.75 per cent.

Case I

Using Concrete Mixer


3621.00 Item 12.8
(E)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

724.20

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1086.30
543.15
5974.65

Rate perm (a+b+c+d+e+f)


say

12.11 A
(ii)

5975.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3560.00 Item 12.8


(E)
712.00
1068.00
534.00
5874.00

Rate perm (a+b+c+d+e+f)

272

DIR used
item

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.11 A

(iii)

Cost Rs

Remarks/
Input ref.

5874.00

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be@ 20
per cent of the cost of concrete instead of 3.0 per cent.

Case I

Using Concrete Mixer


3729.00 Item 12.8
(H) Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

745.80
1118.70
559.35
6152.85

Rate perm (a+b+c+d+e+f)


say

12.11 A
(iii)

Case II With Batching Plant, Transit Mixer and Concrete Pump


3859.00 Item 12.8
(H)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 20 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

771.80

578.85
6367.35
say

Note.

Well steining
PCC M15 Grade
Same as for 12.8 (A) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
2887.00 Item 12.8
(A)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

288.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

793.93

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

396.96
4366.59

Rate perm (a+b+c+d+e+f)


say

12.11 B

(ii)

6367.00

If curb concrete is carried out within steel liner, cost of


formwork shall be excluded.

(I)

Case I

DIR used
item

1157.70

Rate perm (a+b+c+d+e+f)

12.11

6153.00

4367.00

PCC M20 Grade


Same as for 12.8 (B) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


3277.00 Item 12.8
(B) PCC

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

327.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

901.18

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

450.59
4956.46

Rate perm (a+b+c+d+e+f)


say

12.11 B

(iii)

4956.00

RCC M20 Grade


Same as for 12.8 (C) except for formwork which shall be @
10 per cent of the cost of concrete instead of 4 per cent.

Case I

Using Concrete Mixer


3297.00 Item 12.8
(C)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

329.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

906.68

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

453.34
4986.71

Rate perm (a+b+c+d+e+f)


say

273

4987.00

Sr No
12.11 B
(iii)

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

3234.00 Item 12.8


(C)

d)

formwork @ 10 per cent of the cost of concrete

323.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

889.35

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

444.68
4891.43

Rate perm (a+b+c+d+e+f)


say

(iv)

Case I

Same as for 12.8 (D) except for formwork which shall be @


10 per cent of the cost of concrete instead of 4 per cent.
Using Concrete Mixer
3597.00 Item 12.8
(D)

d)

formwork @ 10 per cent of the cost of concrete

359.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

989.18

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

494.59
5440.46

Rate perm (a+b+c+d+e+f)


say

5440.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


3538.00 Item 12.8
(D)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


formwork @ 10 per cent of the cost of concrete

353.80

e)

Overhead charges @ 0.25 on (a+b+c+d)

972.95

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

486.48
5351.23

Rate perm (a+b+c+d+e+f)


say

'12.11 B

4891.00

PCC M25 Grade

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 B
(iv)

Remarks/
Input ref.

Case II With Batching Plant, Transit Mixer and Concrete Pump


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 B

Cost Rs

(v)

5351.00

RCC M25 Grade


Same as for 12.8 (E) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


3621.00 Item 12.8
(E)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

362.10

e)

Overhead charges @ 0.25 on (a+b+c+d)

995.78

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

497.89
5476.76

Rate perm (a+b+c+d+e+f)


say

12.11 B
(v)

3560.00 Item 12.8


(E)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

356.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

979.00

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

489.50

say

(vi)

DIR used
item

5384.50

Rate perm (a+b+c+d+e+f)


'12.11 B

5477.00

Case II With Batching Plant, Transit Mixer and Concrete Pump

5385.00

PCC M30 Grade


Same as for 12.8 (F) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

3632.00 Item 12.8


(F)

formwork @ 10 per cent of the cost of concrete

363.20

e)

Overhead charges @ 0.25 on (a+b+c+d)

998.80

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

d)

499.40
5493.40

Rate perm (a+b+c+d+e+f)

274

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.11 B
(vi)

Remarks/
Input ref.

5493.00

Case II With Batching Plant, Transit Mixer and Concrete Pump


3569.00 Item 12.8
(F)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

356.90

e)

Overhead charges @ 0.25 on (a+b+c+d)

981.48

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

490.74
5398.11

Rate perm (a+b+c+d+e+f)


say

'12.11 B

Cost Rs

(vii)

5398.00

RCC M30 Grade


Same as for 12.8 (G) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3.5 per cent.

Case I

Using Concrete Mixer


3640.00 Item 12.8
(G)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

364.00
1001.00
500.50
5505.50

Rate perm (a+b+c+d+e+f)


say

12.11 B
(vii)

Case II With Batching Plant, Transit Mixer and Concrete Pump


3580.00 Item 12.8
(G)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

formwork @ 10 per cent of the cost of concrete

358.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

984.50

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

492.25
5414.75

Rate perm (a+b+c+d+e+f)


say

'12.11 B

5506.00

(viii)

5415.00

RCC M35 Grade


Same as for 12.8 (H) except for formwork which shall be @
10 per cent of the cost of concrete instead of 3 per cent.

Case I

Using Concrete Mixer


3729.00 Item 12.8
(H) Case I

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

372.90

formwork @ 10 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

1025.48
512.74
5640.11

Rate perm (a+b+c+d+e+f)


say

12.11 B
(viii)

Case II With Batching Plant, Transit Mixer and Concrete Pump


3859.00 Item 12.8
(H)

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

385.90

formwork @ 10 per cent of the cost of concrete

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

530.61
5836.74
say

(ix)

DIR used
item

1061.23

Rate perm (a+b+c+d+e+f)


'12.11 B

5640.00

5837.00

RCC M40 Grade


Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

51.60

5789.47

298736.84

M-081

Coarse Sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

Cement

275

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
cum

10 mm Aggregate

kg

Admixture
b)

c)

Rate Rs

43.20

655.60

28322.05

M-051

206.00

112.77

23230.84

M-180

0.84

185.07

155.46

L-12

day

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Machinery
Batching Plant

hour

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

854.55

12818.25

P&M-049

4.32

1296.00

234.36

1406.16

Lead= 1 ,
P&M-050
P&M-007

Concrete Pump

6.00

hour

15.00

tonne.km

300xL

hour

6.00
3909.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
d)
Formwork @ 10 per cent on cost of concrete i.e. cost
of material, labour and machinery
e) Overhead charges @ 0.25 on (a+b+c+d)

46899.26
128972.96
64486.48

Contractor's profit @ 0.1 on (a+b+c+d+e)

cost of 120 cum = a+b+c+d+e+f

709351.30
5911.26

Rate per cum = (a+b+c+d+e+f)/120


say

Remarks/
Input ref.

Mate

Transit Mixer 4 cum capacity for lead beyond 1 km.

12.11 C

Cost Rs

Labour

Transit Mixer 4 cum capacity for lead upto 1 km.

f)

Quantity

5911.00

Bottom Plug
Concrete to be placed using tremie pipe

(i)
Case I

Note: 10% extra cement to be added where under water


concreting is involved
PCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.55

5789.47

32131.58

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm Aggregate

cum

5.40

758.35

4095.11

M-055

20 mm Aggregate

cum

5.40

862.50

4657.51

M-053

10 mm Aggregate

cum

2.70

655.60

1770.13

M-051

Kg

18.60

112.77

2097.54

M-180

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Light Crane 3 tonnes capacity for handling tremie pipe

hour

6.00

535.00

3210.00

P&M-013

Cement

Admixture
b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3782.00
2509.33

14807.55
7403.77
81441.50

cost of 15 cum = a+b+c+d+e

5429.43

Rate per cum = (a+b+c+d+e)/15


say

12.11 C
(i)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump

276

5429.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Unit ; cum
Taking Output = 120 cum
a)

Material
tonne

44.40

5789.47

257052.63

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Kg

148.80

112.77

16780.33

M-180

Mate

day

0.88

185.07

162.86

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

6.00

2488.00

14928.00

P&M-002

6.00

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

hour

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer


Concrete Pump

3508.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

18655.04

109880.08
54940.04
604340.45

cost of 120 cum = a+b+c+d+e

5036.17

Rate per cum = (a+b+c+d+e)/120


say

'12.11 C

(ii)
Case I

5036.00

PCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.99

5789.47

34678.95

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm Aggregate

cum

5.40

758.35

4095.11

M-055

20 mm Aggregate

cum

5.40

862.50

4657.51

M-053

10 mm Aggregate

cum

2.70

655.60

1770.13

M-051

Kg

21.60

112.77

2435.85

M-180

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe

hour

6.00

535.00

3210.00

P&M-013

Cement

Admixture
b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3974.00
2653.61

15565.04
7782.52

277

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Remarks/
Input ref.

85607.70

cost of 15 cum = a+b+c+d+e

5707.18

Rate per cum = (a+b+c+d+e)/15


say

12.11 C
(ii)

Cost Rs

5707.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

47.88

5789.47

277200.00

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

Cement

43.20

655.60

28322.05

M-051

Kg

172.80

112.77

19486.84

M-180

Mate

day

0.88

185.07

162.86

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

hour

Concrete Pump

3698.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

19797.74

115879.22
57939.61
637335.73

cost of 120 cum = a+b+c+d+e

5311.13

Rate per cum = (a+b+c+d+e)/120


say

'12.11 C

(iii)
Case I

5311.00

PCC Grade M30


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

Material
tonne

6.08

5789.47

35200.00

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm Aggregate

cum

5.40

758.35

4095.11

M-055

20 mm Aggregate

cum

5.40

862.50

4657.51

M-053

10 mm Aggregate

cum

Cement

2.70

655.60

1770.13

M-051

Kg

21.60

112.77

2435.85

M-180

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe

hour

6.00

535.00

3210.00

P&M-013

Admixture
b)

c)

Labour

Machinery

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)

278

4009.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

15701.81
7850.91
86359.97

cost of 15 cum = a+b+c+d+e

5757.33

Rate per cum = (a+b+c+d+e)/15


say

12.11 C
(iii)

Remarks/
Input ref.

2679.67

Add 5 per cent of cost of material and labour towards cost of


forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Cost Rs

5757.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.64

5789.47

281600.00

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Kg

172.80

112.77

19486.84

M-180

Mate

day

0.88

185.07

162.86

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

6.00

2488.00

14928.00

P&M-002

6.00

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

hour

Concrete Pump

3735.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

20017.74

117034.22
58517.11
643688.23

cost of 120 cum = a+b+c+d+e

5364.07

Rate per cum = (a+b+c+d+e)/120


say

'12.11 C

(iv)
Case I

5364.00

PCC Grade M35


Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a)

Material
tonne

6.29

5789.47

36415.79

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm Aggregate

cum

5.40

758.35

4095.11

M-055

20 mm Aggregate

cum

5.40

862.50

4657.51

M-053

10 mm Aggregate

cum

Cement

2.70

655.60

1770.13

M-051

Kg

21.60

112.77

2435.85

M-180

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

hour

6.00

211.68

1270.08

P&M-009

Admixture
b)

c)

Labour

Machinery
Concrete mixer (cap. 0.40/0.28 cum)
279

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Remarks/
Input ref.

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Light Crane of 3 tonnes capacity for handling tremie pipe

hour

6.00

535.00

3210.00

P&M-013

4090.00

Per Cum Basic Cost of Labour, Material & Machinery


(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2740.46

16020.96
8010.48
88115.27

cost of 15 cum = a+b+c+d+e

5874.35

Rate per cum = (a+b+c+d+e)/15


say

12.11 C
(iv)

Cost Rs

5874.00

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

50.28

5789.47

291094.74

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Kg

172.80

112.77

19486.84

M-180

Mate

day

0.88

185.07

162.86

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Cement

Admixture
b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

P&M-050
Lead= 1
km

6.00

234.36

1406.16

P&M-007

Transit Mixer 4 cum capacity, lead beyond 1 Km, L lead in Kilometer

hour

Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c)
Add 5 per cent of cost of material and labour towards cost of
forming sump, protective bunds, chiselling and making
arrangements for under water concreting with tremie pipe.
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3814.00
20492.47

119526.59
59763.30
657396.25

cost of 120 cum = a+b+c+d+e

5478.30

Rate per cum = (a+b+c+d+e)/120


say

12.11

Intermediate plug

(i)

Grade M20 PCC

5478.00

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Case I

Using Concrete Mixer


3782.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

945.50
472.75
5200.25

Rate per cum = (a+b+c+d+e)


say

12.11 D
(i)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump

280

5200.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

3508.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

877.00
438.50
4823.50

Rate per cum = (a+b+c+d+e)


say

'12.11 D

(ii)

Cost Rs

4824.00

Grade M25 PCC


Same as in bottom plug concrete, excluding cost of forming
sump, protective bunds, chiseling etc.

Case I

Using Concrete Mixer


3974.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

993.50
496.75
5464.25

Rate per cum = (a+b+c+d+e)


say

12.11 D
(ii)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3698.00
924.50
462.25
5084.75

Rate per cum = (a+b+c+d+e)


say

'12.11 D

(iii)

Case I

Same as in bottom plug concrete, excluding cost of forming


sump, protective bunds, chiseling etc.
Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

4009.00

d)

Overhead charges @ 0.25 on (a+b+c)

1002.25

e)

Contractor's profit @ 0.1 on (a+b+c+d)

501.13
5512.38
say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

933.75
466.88
5135.63
say

Top plug

(i)

Grade M15 PCC

5512.00

3735.00

Rate per cum = (a+b+c+d+e)


12.11

5085.00

Grade M30 PCC

Rate per cum = (a+b+c+d+e)


12.11 D
(iii)

5464.00

5136.00

Same as Item 12.8(a) excluding formwork


Case I

Using Concrete Mixer


2887.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

721.75

e)

Contractor's profit @ 0.1 on (a+b+c+d)

360.88
3969.63

Rate per cum = (a+b+c+d+e)


say

3970.00

Same as Item 12.8(b) excluding formwork


Case I

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

3277.00

d)

Overhead charges @ 0.25 on (a+b+c)

819.25

e)

Contractor's profit @ 0.1 on (a+b+c+d)

409.63
4505.88

Rate per cum = (a+b+c+d+e)

281

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

Same as Item 12.8 (d)


Case I

3597.00

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

899.25
449.63
4945.88
say

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

4946.00

3538.00
884.50
442.25
4864.75

Rate per cum = (a+b+c+d+e)


say

(iv)

4506.00

excluding formwork

Rate per cum = (a+b+c+d+e)

'12.11 E

Remarks/
Input ref.

Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

12.11 E
(iii)

Cost Rs

4865.00

Grade M30 PCC


Same as Item 12.8(f) excluding formwork

Case I

Using Concrete Mixer


3632.00

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

908.00

e)

Contractor's profit @ 0.1 on (a+b+c+d)

454.00
4994.00

Rate per cum = (a+b+c+d+e)


say

12.11 E
(iv)

Case II Using Batching Plant, Transit Mixer and Crane/concrete


pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

3569.00

d)

Overhead charges @ 0.25 on (a+b+c)

892.25

e)

Contractor's profit @ 0.1 on (a+b+c+d)

446.13
4907.38

Rate per cum = (a+b+c+d+e)


say

12.11

F
(i)
Case I

4994.00

4907.00

Well cap
RCC Grade M20
Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

5.12

5789.47

29642.11

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

1956.81

Form Work @ 4 per cent of a+b+c


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12719.25
6359.63
69955.89

cost of 15 cum = a+b+c+d+e

4663.73

Rate per cum = (a+b+c+d+e)/15


say

282

4664.00

Sr No
12.11 F (i)

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

40.92

5789.47

236905.26

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

6.00

2488.00

14928.00

P&M-002

6.00

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

Generator 100 KVA

hour

1698.00

10188.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

P&M-050
Lead= 1
km
P&M-007

Formwork @ 4 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

99821.85

e)

Contractor's profit @ 0.1 on (a+b+c+d)

49910.92
549020.15

cost of 120 cum = a+b+c+d+e

4575.17

Rate per cum = (a+b+c+d+e)/120


say

12.11 F

(ii)
Case I

1406.16
15357.21

4575.00

RCC Grade M25


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.05

5789.47

35026.32

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

2036.42

Form Work @ 3.75 per cent of a+b+c


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14085.21
7042.60
77468.64

cost of 15 cum = a+b+c+d+e

5164.58

Rate per cum = (a+b+c+d+e)/15


say

12.11 F
(ii)

5165.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
Cement
Coarse sand
283

tonne

48.40

5789.47

280210.53

M-081

cum

54.00

203.75

11002.74

M-004

Sr No

Ref. to
MoRTH
Spec.

Description

b)

c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

P&M-050
Lead= 1
km
P&M-007

16021.33

d)

Overhead charges @ 0.25 on (a+b+c)

110814.19

e)

Contractor's profit @ 0.1 on (a+b+c+d)

55407.10
609478.06

cost of 120 cum = a+b+c+d+e

5078.98

Rate per cum = (a+b+c+d+e)/120


say

12.11 F

(iii)
Case I

1406.16

Formwork @ 3.75 per cent of ( a+b+c)

5079.00

RCC Grade M30


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.10

5789.47

35315.79

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

1910.79

Formwork @ 3.5 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14126.17
7063.08
77693.93

cost of 15 cum = a+b+c+d+e

5179.60

Rate per cum = (a+b+c+d+e)/15


say

12.11 F
(iii)

5180.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

48.79

5789.47

282468.42

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Cement

b)

Labour

284

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

1296.00

hour

6.00

234.36

1406.16

P&M-050
Lead= 1
km
P&M-007

15032.27

Formwork @ 3.5 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

111131.40
55565.70
611222.70

cost of 120 cum = a+b+c+d+e

5093.52

Rate per cum = (a+b+c+d+e)/120


say

12.11 F

(iv)
Case I

5094.00

RCC Grade M35


Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a)

Material
tonne

6.33

5789.47

36647.37

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

1677.76

Formwork @ 3 per cent of (a+b+c)


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14400.81
7200.40
79204.44

cost of 15 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/15

5280.30
say

12.11 F
(iv)

5280.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material
tonne

50.64

5789.47

293178.95

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

L-12

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Cement

b)

c)

Labour

Machinery
Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader (capacity 1 cum)

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity for lead upto 1 km.

285

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Lead beyond 1 Km, L - lead in Kilometer


Concrete Pump

Quantity

Rate Rs

tonne.km

300L

4.32

hour

6.00

234.36

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

56676.25
623438.72
5195.32

Rate per cum = (a+b+c+d+e)/120


say

'12.11 F

(v)

1406.16

P&M-050
Lead= 1
km
P&M-007

113352.49

cost of 120 cum = a+b+c+d+e

Note

1296.00

Remarks/
Input ref.

13206.12

Formwork @ 3 per cent of (a+b+c)


d)

Cost Rs

5195.00

Where ever concrete is carried out using batching plant,


transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
RCC M40 Grade
Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a)

Material
tonne

52.20

5789.47

302210.53

M-081

Coarse Sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

206.00

112.77

23230.84

M-180

0.84

185.07

155.46

L-12

Cement

kg

Admixture
b)

c)

Labour
Mate

day

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Machinery
Batching Plant

hour

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader 1 cum capacity

hour

6.00

1188.00

7128.00

P&M-017

Transit Mixer 4 cum capacity for lead upto 1 km.


Transit Mixer 4 cum capacity for lead beyond 1 km.
Concrete Pump

d)

Formwork @ 3 per cent on cost of concrete i.e. cost of


material, labour and machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

6.00

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300.L

4.32

1296.00

P&M-050
Lead= 1
km

hour

6.00

234.36

1406.16

P&M-007

14173.99
121660.07
60830.03
669130.37

cost of 120 cum = a+b+c+d+e

5576.09

Rate per cum = (a+b+c+d+e)/120


say

12.12

Section
1200

5576.00

Sinking of 6 m external diameter well (other than


pneumatic method of sinking) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.50 m per hour.
a)

Labour
Mate

day

0.12

185.07

22.21

L-12

Sinker ( skilled )

day

1.00

206.99

206.99

L-15

286

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Sinking helper ( semi-skilled )


b)

Quantity

Rate Rs

day

2.00

180.07

360.14

hour

2.00

1176.12

2352.24

L-14

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

P&M-075

235.22
794.20
397.10
4368.10

Rate per metre = (a+b+c+d)


say

(ii)

Remarks/
Input ref.

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

12.12 A

Cost Rs

4368.00

Beyond 3m upto 10m depth


Rate of sinking = 0.33 m per hour.
a)

b)

Labour
Mate

day

0.15

185.07

27.76

L-12

Sinker

day

1.25

206.99

258.74

L-15

Sinking helper ( semi-skilled )

day

2.50

180.07

450.18

L-14

hour

3.00

1176.12

3528.36

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

352.84
1154.47
577.23
6349.57

Rate per metre = (a+b+c+d)


say

12.12 A

(iii)
a

12.12 A

(iv)
a
b

12.12 A

(v)

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

6668.00

12th m

5%

7001.00

13th m

5%

7351.00

14th m

5%

7719.00

15th m

5%

8105.00

16th m

5%

8510.00

17th m

5%

8936.00

18th m

5%

9383.00

19th m

5%

9852.00

20th m

5%

10345.00

Total Cost from 10m upto 20m

83870.00

Avg Rate per metre

8387.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge

21st m

7.5%

11121.00

13345.00

22nd m

7.5%

11955.00

14346.00

23rd m

7.5%

12852.00

15422.00

24th m

7.5%

13816.00

16579.00

25th m

7.5%

14852.00

17822.00

26th m

7.5%

15966.00

19159.00

27th m

7.5%

17163.00

20596.00

28th m

7.5%

18450.00

22140.00

29th m

7.5%

19834.00

23801.00

30th m

7.5%

21322.00

25586.00

Total Cost from 20m upto 30m

157331.00

188796.00

Avg Rate per metre

15733.00

18880.00

Beyond 30m upto 40 m

287

6350.00

P&M-075

Sr No

Ref. to
MoRTH
Spec.

Description
a
b

12.12

Unit

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

Quantity

(a)

Rate Rs

Cost Rs

Remarks/
Input ref.

(b)Including
20% for
Kentledge

31st m

10%

23454.00

28145.00

32nd

10%

25799.00

30959.00

33rd m

10%

28379.00

34055.00

34th m

10%

31217.00

37460.00

35th m

10%

34339.00

41207.00

36th m

10%

37773.00

45328.00

37th m

10%

41550.00

49860.00

38th m

10%

45705.00

54846.00

39th m

10%

50276.00

60331.00

40th m

10%

55304.00

66365.00

Total Cost from 30m upto 40m

373796.00

448556.00

Avg Rate per metre

37380.00

44856.00

Clayey Soil ( 6m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.33 m per hour.
a)

b)

Labour
Mate

day

0.15

185.07

27.76

L-12

Sinker ( skilled )

day

1.50

206.99

310.49

L-15

Sinking helper ( semi-skilled )

day

2.25

180.07

405.16

L-14

hour

3.00

1176.12

3528.36

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

352.84
1156.15
578.07

Rate per metre = (a+b+c+d)

6358.82
say

12.12 B

(ii)

P&M-075

6359.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.30

185.07

55.52

L-12

Sinker

day

3.00

206.99

620.97

L-15

Sinking helper ( semi-skilled )

day

4.50

180.07

810.32

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

2.00

513.00

1026.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

808.27

c)

Overhead charges @ 0.25 on (a+b)

2594.45

d)

Contractor's profit @ 0.1 on (a+b+c)

1297.22
14269.47

Rate per metre = (a+b+c+d)


say

12.12 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a) (b)Including for


dewatering @
5% of cost, if
required

11th m

5%

14982.00

15731.00

12th m

5%

15731.00

16518.00

288

14269.00

Sr No

12.12 B

12.12 B

12.12

Ref. to
MoRTH
Spec.

Description

(iv)

Unit

Rate Rs

13th m

5%

16518.00

17344.00

14th m

5%

17344.00

18211.00

15th m

5%

18211.00

19122.00

16th m

5%

19122.00

20078.00

17th m

5%

20078.00

21082.00

18th m

5%

21082.00

22136.00

19th m

5%

22136.00

23243.00

20th m

5%

23243.00

24405.00

Total Cost from 10m upto 20m

188447.00

197870.00

Avg Rate per metre

18845.00

19787.00

Cost Rs

Remarks/
Input ref.

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering of the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(a)

(c)Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

21st m

7.5%

24986.00

31233.00

32795.00

22nd m

7.5%

26860.00

33575.00

35254.00

23rd m

7.5%

28875.00

36094.00

37899.00

24th m

7.5%

31041.00

38801.00

40741.00

25th m

7.5%

33369.00

41711.00

43797.00

26th m

7.5%

35872.00

44840.00

47082.00

27th m

7.5%

38562.00

48203.00

50613.00

28th m

7.5%

41454.00

51818.00

54409.00

29th m

7.5%

44563.00

55704.00

58489.00

30th m

7.5%

47905.00

59881.00

62875.00

Total Cost from 20m upto 30m

353487.00

441860.00

463954.00

Avg Rate per metre

35349.00

44186.00

46395.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Quantity

(a)

(b) Including (b)Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

52696.00

63235.00

66397.00

32nd

10%

57966.00

69559.00

73037.00

33rd m

10%

63763.00

76516.00

80342.00

34th m

10%

70139.00

84167.00

88375.00

35th m

10%

77153.00

92584.00

97213.00

36th m

10%

84868.00

101842.00

106934.00

37th m

10%

93355.00

112026.00

117627.00

38th m

10%

102691.00

123229.00

129390.00

39th m

10%

112960.00

135552.00

142330.00

40th m

10%

124256.00

149107.00

156562.00

Total Cost from 30m upto 40m

839847.00

1007817.00

1058207.00

Avg Rate per metre

83985.00

100782.00

105821.00

Soft Rock (6m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a)

Labour
Mate

day

0.92

185.07

170.26

L-12

Sinker ( skilled )

day

3.00

206.99

620.97

L-15

289

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

20.00

180.07

3601.40

L-14

Diver

day

0.50

206.99

103.50

L-07

hour

4.00

1176.12

4704.48

P&M-075

hour

3.50

513.00

1795.50

P&M-063

Machinery

Consumables in sinking @ 10 per cent of (b)

650.00

Add for dewatering @ of 5 per cent of (a+b), if required

582.31

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3057.10
1528.55
16814.07

Rate per metre = (a+b+c+d)


say

Remarks/
Input ref.

Sinking helper ( semi-skilled )

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

12.12

Cost Rs

16814.00

Hard Rock (6m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

4.00

112.77

Electric Detonators

each

18.00

14.27

Mate

day

1.56

185.07

288.71

L-12

Driller

day

2.00

206.99

413.98

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

12.00

177.07

2124.84

L-13

Mazdoor (Skilled)

day

4.00

206.99

827.96

L-15

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.

hour

6.00

1176.12

7056.72

P&M-075

Hire & running charges of compressor with pneumatic


breaker/Jack hammer for drilling.

hour

2.00

513.00

1026.00

P&M-063

Machinery

590.53
808.27

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3479.30
1739.65
19136.16

Rate per metre = (a+b+c+d+e)


say

Section
1200

M-104

256.79 M-094/100

Labour

Dewatering @ 5 per cent of cost of (b+c), if required.

12.13

451.08

19136.00

Sinking of 7 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 7 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking = 0.30 m per hour.
a)

b)

Labour
Mate

day

0.15

185.07

27.76

L-12

Sinker ( skilled )

day

1.25

206.99

258.74

L-15

Sinking helper ( semi-skilled )

day

2.50

180.07

450.18

L-14

hour

3.25

1176.12

3822.39

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

290

382.24

P&M-075

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Unit

Quantity

Rate Rs

617.66
6794.29
say

(ii)

Remarks/
Input ref.

1235.33

Rate per metre = (a+b+c+d)


12.13 A

Cost Rs

6794.00

Beyond 3m upto 10m depth


Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

0.18

185.07

33.31

L-12

Sinker

day

1.50

206.99

310.49

L-15

Sinking helper ( semi-skilled )

day

3.00

180.07

540.21

L-14

hour

4.50

1176.12

5292.54

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

529.25
1676.45
838.23
9220.48

Rate per metre = (a+b+c+d)


say

12.13 A

(iii)
a

12.13 A

(iv)
a
b

12.13 A

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

9682.00

12th m

5%

10166.00

13th m

5%

10674.00

14th m

5%

11208.00

15th m

5%

11768.00

16th m

5%

12356.00

17th m

5%

12974.00

18th m

5%

13623.00

19th m

5%

14304.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre

12177.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour).

(a)

(b)Including
20% for
Kentledge

21st m

7.5%

16145.00

19374.00

22nd m

7.5%

17356.00

20827.00

23rd m

7.5%

18658.00

22390.00

24th m

7.5%

20057.00

24068.00

25th m

7.5%

21561.00

25873.00

26th m

7.5%

23178.00

27814.00

27th m

7.5%

24916.00

29899.00

28th m

7.5%

26785.00

32142.00

29th m

7.5%

28794.00

34553.00

30th m

7.5%

30954.00

37145.00

Total Cost from 20m upto 30m

228404.00

274085.00

Avg Rate per metre

22840.00

27409.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

15019.00
121774.00

(a)

(b)Including
20% for
Kentledge

31st m

10%

34049.00

40859.00

32nd

10%

37454.00

44945.00

291

9220.00

P&M-075

Sr No

12.13

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

33rd m

10%

41199.00

49439.00

34th m

10%

45319.00

54383.00

35th m

10%

49851.00

59821.00

36th m

10%

54836.00

65803.00

37th m

10%

60320.00

72384.00

38th m

10%

66352.00

79622.00

39th m

10%

72987.00

87584.00

40th m

10%

80286.00

96343.00

Total Cost from 30m upto 40m

542653.00

651183.00

Avg Rate per metre

54265.00

65118.00

Cost Rs

Remarks/
Input ref.

Clayey Soil ( 7m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(I)

Depth below bed level upto 3.0 M


Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

0.18

185.07

33.31

L-12

Sinker ( skilled )

day

1.50

206.99

310.49

L-15

Sinking helper ( semi-skilled )

day

3.00

180.07

540.21

L-14

hour

4.50

1176.12

5292.54

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

d)

Overhead charges @ 0.25 on (a+b)

e)

Contractor's profit @ 0.1 on (a+b+c)

529.25
1676.45
838.23
9220.48

Rate per metre = (a+b+c+d)


say

12.13 B

(ii)

P&M-075

9220.00

Beyond 3m upto 10m depth


Rate of sinking = 0.17 m per hour.
a)

b)

Labour
Mate

day

0.26

185.07

48.12

L-12

Sinker

day

2.00

206.99

413.98

L-15

Sinking helper ( semi-skilled )

day

4.00

180.07

720.28

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

3.25

513.00

1667.25

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

872.40
2694.69
1347.34
14820.77

Rate per metre = (a+b+c+d)


say

12.13 B

(iii)
a
b

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

(b) Including
for dewatering
@ 5% of cost,
if required

11th m

5%

15562.00

16340.00

12th m

5%

16340.00

17157.00

13th m

5%

17157.00

18015.00

14th m

5%

18015.00

18916.00

15th m

5%

18916.00

19862.00

16th m

5%

19862.00

20855.00

17th m

5%

20855.00

21898.00

18th m

5%

21898.00

22993.00

292

14821.00

Sr No

12.13 B

Ref. to
MoRTH
Spec.

Description

(iv)
a
b
c

12.13 B

19th m

5%

20th m

5%

Cost Rs

Remarks/
Input ref.

24143.00

24143.00

25350.00
205529.00

Avg Rate per metre

19574.00

20553.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

( c) Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

31st m

7.5%

25954.00

32443.00

34065.00

32nd

7.5%

27901.00

34876.00

36620.00

33rd m

7.5%

29994.00

37493.00

39368.00

34th m

7.5%

32244.00

40305.00

42320.00

35th m

7.5%

34662.00

43328.00

45494.00

36th m

7.5%

37262.00

46578.00

48907.00

37th m

7.5%

40057.00

50071.00

52575.00

38th m

7.5%

43061.00

53826.00

56517.00

39th m

7.5%

46291.00

57864.00

60757.00

40th m

7.5%

49763.00

62204.00

65314.00

Total Cost from 30m upto 40m

367189.00

458988.00

481937.00

Avg Rate per metre

36719.00

45899.00

48194.00

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

22993.00

Rate Rs

195741.00

Beyond 30m upto 40 m

Quantity

Total Cost from 10m upto 20m

(v)

12.13

Unit

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

( c) Including (b) Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

54739.00

65687.00

68971.00

32nd

10%

60213.00

72256.00

75869.00

33rd m

10%

66234.00

79481.00

83455.00

34th m

10%

72857.00

87428.00

91799.00

35th m

10%

80143.00

96172.00

100981.00

36th m

10%

88157.00

105788.00

111077.00

37th m

10%

96973.00

116368.00

122186.00

38th m

10%

106670.00

128004.00

134404.00

39th m

10%

117337.00

140804.00

147844.00

40th m

10%

129071.00

154885.00

162629.00

Total Cost from 30m upto 40m

872394.00

1046873.00

1099215.00

Avg Rate per metre

87239.00

104687.00

109922.00

0.58

185.07

107.34

L-12

Soft Rock ( 7m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a)

b)

Labour
Mate

day

Sinker ( skilled )

day

4.00

206.99

827.96

L-15

Sinking helper ( semi-skilled )

day

10.00

180.07

1800.70

L-14

Diver

day

0.75

206.99

155.24

L-07

hour

4.50

1176.12

5292.54

P&M-075

hour

3.75

513.00

1923.75

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
293

721.63

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2833.63
1416.82
15584.99

Rate per metre = (a+b+c+d)


say

12.13

Remarks/
Input ref.

505.38

Add for dewatering @ of 5 per cent of (a+b), if required


c)

Cost Rs

15585.00

Hard Rock ( 7m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a)

b)

c)

Material
Gelatine 80 per cent

Kg

7.00

112.77

Electric Detonators

each

30.00

14.27

Mate

day

1.60

185.07

296.11

L-12

Driller

day

2.00

206.99

413.98

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

18.00

177.07

3187.26

L-13

Mazdoor (Skilled)

day

4.00

206.99

827.96

L-15

Diver

day

0.50

206.99

103.50

L-07

hour

6.00

1176.12

7056.72

P&M-075

hour

2.00

513.00

1026.00

P&M-063

Machinery

649.19
873.19

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3930.91
1965.45
21619.98

Rate per metre = (a+b+c+d+e)


say

Section
1200

M-104

427.98 M-094/100

Labour

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

12.14

789.40

21620.00

Sinking of 8 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 8 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.18

185.07

33.31

L-12

Sinker ( skilled )

day

1.50

206.99

310.49

L-15

Sinking helper ( semi-skilled )

day

3.00

180.07

540.21

L-14

hour

4.00

1176.12

4704.48

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

470.45
1514.73
757.37
8331.04

Rate per metre = (a+b+c+d)


say

12.14 A

(ii)

Beyond 3m upto 10m depth


Rate of sinking @ 0.20 m/hour
294

8331.00

P&M-075

Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

Unit

Quantity

Rate Rs

Mate

day

0.25

185.07

46.27

L-12

Sinker

day

1.75

206.99

362.23

L-15

Sinking helper ( semi-skilled )

day

3.50

180.07

630.25

L-14

hour

5.00

1176.12

5880.60

Machinery

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

588.06
1876.85
938.43
10322.68

Rate per metre = (a+b+c+d)


say

(iii)
a

12.14 A

(iv)
a
b

12.14 A

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

10839.00

12th m

5%

11381.00

13th m

5%

11950.00

14th m

5%

12548.00

15th m

5%

13175.00

16th m

5%

13834.00

17th m

5%

14526.00

18th m

5%

15252.00

19th m

5%

16015.00

20th m

5%

16816.00

Total Cost from 10m upto 20m

136336.00

Avg Rate per metre

13634.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge

21st m

7.5%

18077.00

21692.00

22nd m

7.5%

19433.00

23320.00

23rd m

7.5%

20890.00

25068.00

24th m

7.5%

22457.00

26948.00

25th m

7.5%

24141.00

28969.00

26th m

7.5%

25952.00

31142.00

27th m

7.5%

27898.00

33478.00

28th m

7.5%

29990.00

35988.00

29th m

7.5%

32239.00

38687.00

30th m

7.5%

34657.00

41588.00

Total Cost from 20m upto 30m

255734.00

306880.00

Avg Rate per metre

25573.00

30688.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

Remarks/
Input ref.

Labour

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

12.14 A

Cost Rs

(a)

(b) Including
20% for
Kentledge

31st m

10%

38123.00

45748.00

32nd

10%

41935.00

50322.00

33rd m

10%

46129.00

55355.00

34th m

10%

50742.00

60890.00

35th m

10%

55816.00

66979.00

36th m

10%

61398.00

73678.00

37th m

10%

67538.00

81046.00

38th m

10%

74292.00

89150.00

295

10323.00

P&M-075

Sr No

12.14

Ref. to
MoRTH
Spec.

Description

Unit

39th m

10%

40th m

10%

Quantity

Rate Rs

81721.00

98065.00

89893.00

107872.00

Total Cost from 30m upto 40m

607587.00

729104.00

Avg Rate per metre

60759.00

72910.00

Cost Rs

Remarks/
Input ref.

Clayey Soil ( 8m dia. Well )


Unit = Running Meter.
Taking output = 1 meter

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.22

185.07

40.72

L-12

Sinker ( skilled )

day

2.00

206.99

413.98

L-15

Sinking helper ( semi-skilled )

hour

3.50

180.07

630.25

L-14

5.50

1176.12

6468.66

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

646.87
2050.12
1025.06
11275.64

Rate per metre = (a+b+c+d)


say

12.14 B

(ii)

P&M-075

11276.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.32

185.07

59.22

L-12

Sinker

day

2.50

206.99

517.48

L-15

Sinking helper ( semi-skilled )

day

4.50

180.07

810.32

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

3.50

513.00

1795.50

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

885.22
2781.11
1390.56
15296.12

Rate per metre = (a+b+c+d)


say

12.14 B

(iii)
a
b

12.14 B

(iv)

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

(b) Including
for dewatering
@ 5% of cost,
if required

11th m

5%

16061.00

16864.00

12th m

5%

16864.00

17707.00

13th m

5%

17707.00

18592.00

14th m

5%

18592.00

19522.00

15th m

5%

19522.00

20498.00

16th m

5%

20498.00

21523.00

17th m

5%

21523.00

22599.00

18th m

5%

22599.00

23729.00

19th m

5%

23729.00

24915.00

20th m

5%

24915.00

26161.00

Total Cost from 10m upto 20m

202010.00

212110.00

Avg Rate per metre

20201.00

21211.00

Beyond 20m upto 30 m

296

15296.00

Sr No

Ref. to
MoRTH
Spec.

Description
a
b
c

12.14 B

Rate Rs

Cost Rs

Remarks/
Input ref.

(c)Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

31st m

7.5%

26784.00

33480.00

35154.00

32nd

7.5%

28793.00

35991.00

37791.00

33rd m

7.5%

30952.00

38690.00

40625.00

34th m

7.5%

33273.00

41591.00

43671.00

35th m

7.5%

35768.00

44710.00

46946.00

36th m

7.5%

38451.00

48064.00

50467.00

37th m

7.5%

41335.00

51669.00

54252.00

38th m

7.5%

44435.00

55544.00

58321.00

39th m

7.5%

47768.00

59710.00

62696.00

40th m

7.5%

51351.00

64189.00

67398.00

Total Cost from 30m upto 40m

378910.00

473638.00

497321.00

Avg Rate per metre

37891.00

47364.00

49732.00

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required

(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

Quantity

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required

(v)

12.14

Unit

(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

(c ) Including (b) Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

56486.00

67783.00

71172.00

32nd

10%

62135.00

74562.00

78290.00

33rd m

10%

68349.00

82019.00

86120.00

34th m

10%

75184.00

90221.00

94732.00

35th m

10%

82702.00

99242.00

104204.00

36th m

10%

90972.00

109166.00

114624.00

37th m

10%

100069.00

120083.00

126087.00

38th m

10%

110076.00

132091.00

138696.00

39th m

10%

121084.00

145301.00

152566.00

40th m

10%

133192.00

159830.00

167822.00

Total Cost from 30m upto 40m

900249.00

1080298.00

1134313.00

Avg Rate per metre

90025.00

108030.00

113431.00

0.68

185.07

125.85

L-12

Soft Rock ( 8m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a)

b)

Labour
Mate

day

Sinker ( skilled )

day

4.00

206.99

827.96

L-15

Sinking helper ( semi-skilled )

day

12.00

180.07

2160.84

L-14

Diver

day

1.00

206.99

206.99

L-07

hour

5.00

1176.12

5880.60

P&M-075

hour

3.75

513.00

1923.75

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)

780.44

Add for dewatering @ of 5 per cent of (a+b), if required

595.32

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3125.44
1562.72
17189.90

Rate per metre = (a+b+c+d)


297

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.14

Cost Rs

Remarks/
Input ref.

17190.00

Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

8.00

112.77

Electric Detonators

each

32.00

14.27

Mate

day

1.09

185.07

201.73

L-12

Driller

day

2.00

206.99

413.98

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

20.00

177.07

3541.40

L-13

Mazdoor (Skilled)

day

4.00

206.99

827.96

L-15

hour

6.00

1176.12

7056.72

P&M-075

hour

2.00

513.00

1026.00

P&M-063

Machinery

657.01
505.74

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3915.39
1957.69
21534.62

Rate per metre = (a+b+c+d+e)


say

Section
1200

M-104

456.52 M-094/100

Labour

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

12.15

902.17

21535.00

Sinking of 9 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 9 m.
A
(i)

Sandy Soil
Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a)

b)

Labour
Mate

day

0.19

185.07

35.16

L-12

Sinker ( skilled )

day

1.50

206.99

310.49

L-15

Sinking helper ( semi-skilled )

day

3.25

180.07

585.23

L-14

hour

4.00

1176.12

4704.48

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

470.45
1526.45
763.23
8395.48

Rate per metre = (a+b+c+d)


say

12.15 A

(ii)

P&M-075

8395.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.27

185.07

49.97

L-12

Sinker

day

1.75

206.99

362.23

L-15

Sinking helper ( semi-skilled )

day

4.00

180.07

720.28

L-14

Machinery

298

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

hour

Quantity
5.50

Rate Rs
1176.12

646.87

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1031.00
11341.01
say

(iii)
a

12.15 A

12.15 A

(iv)

6468.66

2062.00

Rate per metre = (a+b+c+d)


12.15 A

Cost Rs

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

11908.00

12th m

5%

12503.00

13th m

5%

13128.00

14th m

5%

13784.00

15th m

5%

14473.00

16th m

5%

15197.00

17th m

5%

15957.00

18th m

5%

16755.00

19th m

5%

17593.00

20th m

5%

18473.00

Total Cost from 10m upto 20m

149771.00

Avg Rate per metre

14977.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge

21st m

7.5%

19858.48

23830.00

22nd m

7.5%

21348.00

25618.00

23rd m

7.5%

22949.00

27539.00

24th m

7.5%

24670.00

29604.00

25th m

7.5%

26520.00

31824.00

26th m

7.5%

28509.00

34211.00

27th m

7.5%

30647.00

36776.00

28th m

7.5%

32946.00

39535.00

29th m

7.5%

35417.00

42500.00

30th m

7.5%

38073.00

45688.00

Total Cost from 20m upto 30m

280937.48

337125.00

Avg Rate per metre

28094.00

33713.00

(v)

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

(a)

(b) Including
20% for
Kentledge

31st m

10%

41880.30

50256.00

32nd

10%

46068.00

55282.00

33rd m

10%

50675.00

60810.00

34th m

10%

55743.00

66892.00

35th m

10%

61317.00

73580.00

36th m

10%

67449.00

80939.00

37th m

10%

74194.00

89033.00

38th m

10%

81613.00

97936.00

39th m

10%

89774.00

107729.00

40th m

10%

98751.00

118501.00

Total Cost from 30m upto 40m

667464.30

800958.00

Avg Rate per metre

66746.00

80096.00

299

11341.00

Remarks/
Input ref.
P&M-075

Sr No
12.15

Ref. to
MoRTH
Spec.

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Clayey Soil ( 9m dia. Well )


Unit = Running Meter.
Taking output = 1 cum

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.24

185.07

44.42

L-12

Sinker ( skilled )

day

2.25

206.99

465.73

L-15

Sinking helper ( semi-skilled )

day

3.75

180.07

675.26

L-14

hour

5.75

1176.12

6762.69

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

676.27

c)

Overhead charges @ 0.25 on (a+b)

2156.09

d)

Contractor's profit @ 0.1 on (a+b+c)

1078.05
11858.50

Rate per metre = (a+b+c+d)


say

12.15 B

(ii)

P&M-075

11859.00

Beyond 3m upto 10m depth


Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

0.34

185.07

62.92

L-12

Sinker

day

2.50

206.99

517.48

L-15

Sinking helper ( semi-skilled )

day

5.00

180.07

900.35

L-14

hour

6.50

1176.12

7644.78

P&M-075

hour

3.75

513.00

1923.75

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

956.85
3001.53
1500.77
16508.43

Rate per metre = (a+b+c+d)


say

12.15 B

12.15 B

(iii)

Beyond 10 m upto 20 m

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add for dewatering @ 5 per cent of cost, if required.

(iv)

(a)

(b) Including
for dewatering
@ 5% of cost,
if required

11th m

5%

17333.00

18200.00

12th m

5%

18200.00

19110.00

13th m

5%

19110.00

20066.00

14th m

5%

20066.00

21069.00

15th m

5%

21069.00

22122.00

16th m

5%

22122.00

23228.00

17th m

5%

23228.00

24389.00

18th m

5%

24389.00

25608.00

19th m

5%

25608.00

26888.00

20th m

5%

26888.00

28232.00

Total Cost from 10m upto 20m

218013.00

228912.00

Avg Rate per metre

21801.00

22891.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering on the cost, if required

300

16508.00

Sr No

Ref. to
MoRTH
Spec.

Description
c

12.15 B

(v)
a
b
c

12.15

Unit

Quantity
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

Rate Rs

Cost Rs

Remarks/
Input ref.

( c) Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

31st m

7.5%

28905.00

36131.00

37938.00

32nd

7.5%

31073.00

38841.00

40783.00

33rd m

7.5%

33403.00

41754.00

43842.00

34th m

7.5%

35908.00

44885.00

47129.00

35th m

7.5%

38601.00

48251.00

50664.00

36th m

7.5%

41496.00

51870.00

54464.00

37th m

7.5%

44608.00

55760.00

58548.00

38th m

7.5%

47954.00

59943.00

62940.00

39th m

7.5%

51551.00

64439.00

67661.00

40th m

7.5%

55417.00

69271.00

72735.00

Total Cost from 30m upto 40m

408916.00

511145.00

536704.00

Avg Rate per metre

40892.00

51115.00

53670.00

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
(a)

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

( c) Including (b) Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

60959.00

73151.00

76809.00

32nd

10%

67055.00

80466.00

84489.00

33rd m

10%

73761.00

88513.00

92939.00

34th m

10%

81137.00

97364.00

102232.00

35th m

10%

89251.00

107101.00

112456.00

36th m

10%

98176.00

117811.00

123702.00

37th m

10%

107994.00

129593.00

136073.00

38th m

10%

118793.00

142552.00

149680.00

39th m

10%

130672.00

156806.00

164646.00

40th m

10%

143739.00

172487.00

181111.00

Total Cost from 30m upto 40m

971537.00

1165844.00

1224137.00

Avg Rate per metre

97154.00

116584.00

122414.00

Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a)

b)

Labour
Mate

day

0.76

185.07

140.65

L-12

Sinker ( skilled )

day

4.00

206.99

827.96

L-15

Sinking helper ( semi-skilled )

day

14.00

180.07

2520.98

L-14

Diver

day

1.20

206.99

248.39

L-07

hour

6.50

1176.12

7644.78

P&M-075

hour

4.00

513.00

2052.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

969.68

Consumables in sinking @ 10 per cent of (b)


Add for dewatering @ of 5 per cent of (a+b), if required

1440.44

c)

Overhead charges @ 0.25 on (a+b)

3961.22

d)

Contractor's profit @ 0.1 on (a+b+c)

1980.61
21786.71

Rate per metre = (a+b+c+d)


say

12.15

Hard Rock ( 9m dia well )


Unit = Running Meter
301

21787.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a)

b)

c)

Material
Gelatine 80 per cent

Kg

10.00

112.77

Electric Detonators

each

40.00

14.27

Mate

day

1.17

185.07

216.53

L-12

Driller

day

2.00

206.99

413.98

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

22.00

177.07

3895.54

L-13

Mazdoor (Skilled)

day

4.00

206.99

827.96

L-15

Diver

day

1.00

206.99

206.99

L-07

hour

7.00

1176.12

8232.84

P&M-075

hour

2.50

513.00

1282.50

P&M-063

Machinery

757.43
563.33

Consumables in sinking @ 10 per cent of cost of (b).


d)

Overhead charges @ 0.25 on (a+b+c)

4541.95

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2270.97
24980.71

Rate per metre = (a+b+c+d+e)


say

1200

M-104

570.65 M-094/100

Labour

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.

12.16

1127.71

24981.00

Sinking of 10 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Diameter of well - 10 m.
A

Sandy Soil

(i)

Depth below bed level upto 3.0 M


Rate of sinking 0.20 m / hour
a)

b)

Labour
Mate

day

0.20

185.07

37.01

L-12

Sinker ( skilled )

day

1.50

206.99

310.49

L-15

Sinking helper ( semi-skilled )

day

3.50

180.07

630.25

L-14

hour

5.00

1176.12

5880.60

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

588.06
1861.60
930.80
10238.81

Rate per metre = (a+b+c+d)


say

12.16 A

(ii)

P&M-075

10239.00

Beyond 3m upto 10m depth


Rate of sinking 0.17 m / hour
a)

b)

Labour
Mate

day

0.31

185.07

57.37

L-12

Sinker

day

2.00

206.99

413.98

L-15

Sinking helper ( semi-skilled )

day

4.25

180.07

765.30

L-14

hour

5.75

1176.12

6762.69

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)
302

676.27

P&M-075

Sr No

Ref. to
MoRTH
Spec.

Description
c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

Unit

Quantity

Rate Rs

2168.90
1084.45
11928.96

Rate per metre = (a+b+c+d)


say

12.16 A

(iii)
a

12.16 A

(iv)
a
b

12.16 A

12.16

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

12525.00

12th m

5%

13151.00

13th m

5%

13809.00

14th m

5%

14499.00

15th m

5%

15224.00

16th m

5%

15985.00

17th m

5%

16784.00

18th m

5%

17623.00

19th m

5%

18504.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre

15753.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b) Including
20% for
Kentledge

21st m

7.5%

20886.00

25063.00

22nd m

7.5%

22452.00

26942.00

23rd m

7.5%

24136.00

28963.00

24th m

7.5%

25946.00

31135.00

25th m

7.5%

27892.00

33470.00

26th m

7.5%

29984.00

35981.00

27th m

7.5%

32233.00

38680.00

28th m

7.5%

34650.00

41580.00

29th m

7.5%

37249.00

44699.00

30th m

7.5%

40043.00

48052.00

Total Cost from 20m upto 30m

295471.00

354565.00

Avg Rate per metre

29547.00

35457.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement, and Labour etc.

19429.00
157533.00

(v)

Cost Rs

(a)

(b) Including
20% for
Kentledge

31st m

10%

44047.00

52856.00

32nd

10%

48452.00

58142.00

33rd m

10%

53297.00

63956.00

34th m

10%

58627.00

70352.00

35th m

10%

64490.00

77388.00

36th m

10%

70939.00

85127.00

37th m

10%

78033.00

93640.00

38th m

10%

85836.00

103003.00

39th m

10%

94420.00

113304.00

40th m

10%

103862.00

124634.00

Total Cost from 30m upto 40m

702003.00

842402.00

Avg Rate per metre

70200.00

84240.00

Clayey Soil (10m dia. Well )


Unit = Running Meter
Taking output = 1 cum

303

11929.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description
(i)

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Depth below bed level upto 3.0 M


Rate of sinking 0.18m/hour.
a)

b)

Labour
Mate

day

0.25

185.07

46.27

L-12

Sinker ( skilled )

day

2.50

206.99

517.48

L-15

Sinking helper ( semi-skilled )

day

5.50

180.07

990.39

L-14

hour

6.00

1176.12

7056.72

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

705.67
2329.13
1164.56
12810.21

Rate per metre = (a+b+c+d)


say

12.16 B

(ii)

P&M-075

12810.00

Beyond 3m upto 10m depth


Rate of sinking 0.15m/hour.
a)

b)

Labour
Mate

day

0.40

185.07

74.03

L-12

Sinker

day

3.00

206.99

620.97

L-15

Sinking helper ( semi-skilled )

day

5.50

180.07

990.39

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

4.00

513.00

2052.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

910.87
2926.24
1463.12
16094.34

Rate per metre = (a+b+c+d)


say

12.16 B

(iii)
a
b

12.16 B

(iv)
a
b
c

16094.00

Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.

(a)

(b) Including
for dewatering
@ 5% of cost,
if required

11th m

5%

16899.00

17744.00

12th m

5%

17744.00

18631.00

13th m

5%

18631.00

19563.00

14th m

5%

19563.00

20541.00

15th m

5%

20541.00

21568.00

16th m

5%

21568.00

22646.00

17th m

5%

22646.00

23778.00

18th m

5%

23778.00

24967.00

19th m

5%

24967.00

26215.00

20th m

5%

26215.00

27526.00

Total Cost from 10m upto 20m

212552.00

223179.00

Avg Rate per metre

21255.00

22318.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

( c) Including (b) Including


25% for
5% for
Kentledge dewatering, if
required

31st m

7.5%

28181.00

35226.00

36987.00

32nd

7.5%

30295.00

37869.00

39762.00

304

Sr No

12.16 B

12.16

Ref. to
MoRTH
Spec.

Description

(v)

Unit

Rate Rs

Cost Rs

33rd m

7.5%

32567.00

40709.00

42744.00

34th m

7.5%

35010.00

43763.00

45951.00

35th m

7.5%

37636.00

47045.00

49397.00

36th m

7.5%

40459.00

50574.00

53103.00

37th m

7.5%

43493.00

54366.00

57084.00

38th m

7.5%

46755.00

58444.00

61366.00

39th m

7.5%

50262.00

62828.00

65969.00

40th m

7.5%

54032.00

67540.00

70917.00

Total Cost from 30m upto 40m

398690.00

498364.00

523280.00

Avg Rate per metre

39869.00

49836.00

52328.00

Remarks/
Input ref.

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Quantity

(a)

( c) Including (b) Including


20% for
5% for
Kentledge dewatering, if
required

31st m

10%

59435.00

71322.00

74888.00

32nd

10%

65379.00

78455.00

82378.00

33rd m

10%

71917.00

86300.00

90615.00

34th m

10%

79109.00

94931.00

99677.55

35th m

10%

87020.00

104424.00

109645.20

36th m

10%

95722.00

114866.00

120609.30

37th m

10%

105294.00

126353.00

132670.65

38th m

10%

115823.00

138988.00

145937.40

39th m

10%

127405.00

152886.00

160530.30

40th m

10%

140146.00

168175.00

176583.75

Total Cost from 30m upto 40m

947250.00

1136700.00

1193535.15

Avg Rate per metre

94725.00

113670.00

119354.00

Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a)

b)

Labour
Mate

day

0.86

185.07

159.16

L-12

Sinker ( skilled )

day

4.00

206.99

827.96

L-15

Sinking helper ( semi-skilled )

day

16.00

180.07

2881.12

L-14

Diver

day

1.40

206.99

289.79

L-07

hour

7.00

1176.12

8232.84

P&M-075

hour

4.25

513.00

2180.25

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

1041.31

Consumables in sinking @ 10 per cent of (b)

572.72

Add for dewatering @ 5 per cent of cost, if required


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4046.29
2023.14
22254.57

Rate per metre = (a+b+c+d)


say

12.16

22255.00

Hard Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a)

Material
Kg

Gelatine 80 per cent


305

11.00

112.77

1240.48

M-104

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
each.

Electric Detonators
b)

c)

Quantity

Rate Rs

44.00

14.27

627.71 M-094/100

Labour
day

1.27

185.07

235.04

L-12

Driller

day

2.00

206.99

413.98

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

24.00

177.07

4249.68

L-13

Mazdoor (Skilled)

day

4.00

206.99

827.96

L-15

hour

8.50

1176.12

9997.02

P&M-075

hour

3.00

513.00

1539.00

P&M-063

Machinery

576.80

Consumables in sinking @ 10 per cent of cost of (b+c).

1791.18

d)

Overhead charges @ 0.25 on (a+b+c)

5392.80

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2696.40
29660.37

Rate per metre = (a+b+c+d+e)


say

1200

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

12.17

Cost Rs

29660.00

Sinking of 11 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 0.50 m
Diameter of well - 11 m.
A

Sandy Soil

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.21

185.07

38.86

L-12

Sinker ( skilled )

day

1.50

206.99

310.49

L-15

Sinking helper (semi-skilled)

day

3.30

180.07

594.23

L-14

hour

6.00

1176.12

7056.72

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

705.67
2176.49
1088.25

Cost for 0.5m = a+b+c+d

11970.71

Rate per metre = (a+b+c+d)/0.50

23941.42
say

12.17 A

(ii)

P&M-075

23941.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.13 m/hour
a)

b)

Labour
Mate

day

0.32

185.07

59.22

L-12

Sinker

day

2.00

206.99

413.98

L-15

Sinking helper (semi-skilled)

day

4.50

180.07

810.32

L-14

hour

4.00

1176.12

4704.48

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b+c)

d)

Contractor's profit @ 0.1 on (a+b+c+d)

470.45
1614.61
807.31
8880.36

Cost for 0.5m = a+b+c+d

17760.72

Rate per metre = (a+b+c+d)/0.50

306

P&M-075

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

12.17 A

(iii)
a

12.17 A

12.17 A

12.17

(iv)

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

18649.00

12th m

5%

19581.00

13th m

5%

20560.00

14th m

5%

21588.00

15th m

5%

22667.00

16th m

5%

23800.00

17th m

5%

24990.00

18th m

5%

26240.00

19th m

5%

27552.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre

23456.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.
7.5%

31100.00

37320.00

7.5%

33433.00

40120.00

23rd m

7.5%

35940.00

43128.00

24th m

7.5%

38636.00

46363.00

25th m

7.5%

41534.00

49841.00

26th m

7.5%

44649.00

53579.00

27th m

7.5%

47998.00

57598.00

28th m

7.5%

51598.00

61918.00

29th m

7.5%

55468.00

66562.00

30th m

7.5%

59628.00

71554.00

Total Cost from 20m upto 30m

439984.00

527983.00

Avg Rate per metre

43998.00

52798.00

Beyond 30m upto 40 m


Add 10 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

(a)

(b) Including
20% for
Kentledge

31st m

10%

65591.00

78709.00

32nd

10%

72150.00

86580.00

33rd m

10%

79365.00

95238.00

34th m

10%

87302.00

104762.00

35th m

10%

96032.00

115238.00

36th m

10%

105635.00

126762.00

37th m

10%

116199.00

139439.00

38th m

10%

127819.00

153383.00

39th m

10%

140601.00

168721.00

40th m

10%

154661.00

185593.00

Total Cost from 30m upto 40m

1045355.00

1254425.00

Avg Rate per metre

104536.00

125443.00

Clayey Soil (11 m dia. Well )


Unit = Running Meter
Taking output = 0.50 meter
Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a)

(b)Including
20% for
Kentledge

22nd m

(i)

(a)

21st m

(v)

28930.00
234557.00

Labour

307

Cost Rs
17761.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

b)

Unit

Quantity

Rate Rs

day

0.26

185.07

48.12

L-12

Sinker ( skilled )

day

2.50

206.99

517.48

L-15

Sinking helper (semi-skilled)

day

4.00

180.07

720.28

L-14

hour

5.00

1176.12

5880.60

Machinery

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

P&M-075

588.06
1938.63
969.32

Cost for 0.5m = a+b+c+d

10662.48

Rate per metre = (a+b+c+d)/0.50

21324.97
say

(ii)

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

12.17 B

Cost Rs

21325.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.08 m/hour
a)

b)

Labour
Mate

day

0.43

185.07

79.58

L-12

Sinker

day

3.50

206.99

724.47

L-15

Sinking helper (semi-skilled)

day

5.75

180.07

1035.40

L-14

hour

6.00

1176.12

7056.72

P&M-075

hour

4.25

513.00

2180.25

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay
Consumables in sinking @ 10 per cent of (b)

923.70

c)

Overhead charges @ 0.25 on (a+b)

3000.03

d)

Contractor's profit @ 0.1 on (a+b+c)

1500.01
16500.16

Cost for 0.5m = a+b+c+d

33000.32

Rate per metre = (a+b+c+d)/0.50


say

12.17 B

12.17 B

(iii)

Beyond 10 m upto 20 m

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add for dewatering @ 5 per cent of cost, if required.

(iv)

33000.00

(a) (b)Including for


dewatering @
5% of cost, if
required

11th m

5%

34650.00

36383.00

12th m

5%

36383.00

38202.00

13th m

5%

38202.00

40112.00

14th m

5%

40112.00

42118.00

15th m

5%

42118.00

44224.00

16th m

5%

44224.00

46435.00

17th m

5%

46435.00

48757.00

18th m

5%

48757.00

51195.00

19th m

5%

51195.00

53755.00

20th m

5%

53755.00

56443.00

Total Cost from 10m upto 20m

435831.00

457623.00

Avg Rate per metre

43583.00

45762.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(a)

(c)Including (b)Including
25% for
5% for
Kentledge dewatering, if
required

21st m

7.5%

57787.00

72234.00

75846.00

22nd

7.5%

62121.00

77651.00

81534.00

23rd m

7.5%

66780.00

83475.00

87649.00

308

Sr No

12.17 B

Ref. to
MoRTH
Spec.

Description

(v)

Unit

24th m

7.5%

71789.00

25th m

7.5%

26th m

7.5%

27th m

7.5%

28th m
29th m
30th m

Cost Rs
94223.00

77173.00

96466.00

101289.00

82961.00

103701.00

108886.00

89183.00

111479.00

117053.00

7.5%

95872.00

119840.00

125832.00

7.5%

103062.00

128828.00

135269.00

7.5%

110792.00

138490.00

145415.00

Total Cost from 20m upto 30m

817520.00

1021900.00

1072995.00

Avg Rate per metre

81752.00

102190.00

107300.00

Remarks/
Input ref.

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

(a)

(c ) Including (b)Including
20% for
5% for
Kentledge dewatering, if
required

31st m

10%

121871.00

146245.00

153557.00

32nd

10%

134058.00

160870.00

168914.00

33rd m

10%

147464.00

176957.00

185805.00

34th m

10%

162210.00

194652.00

204385.00

35th m

10%

178431.00

214117.00

224823.00

36th m

10%

196274.00

235529.00

247305.00

37th m

10%

215901.00

259081.00

272035.00

38th m

10%

237491.00

284989.00

299238.00

39th m

10%

261240.00

313488.00

329162.00

40th m

10%

287364.00

344837.00

362079.00

1942304

2330765

2447303

194230.00

233077.00

244730.00

0.95

185.07

175.82

L-12

Avg Rate per metre


C

Rate Rs
89736.00

Total Cost from 30m upto 40m


12.17

Quantity

Soft Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a)

b)

Labour
Mate

day

Sinker ( skilled )

day

4.25

206.99

879.71

L-15

Sinking helper (semi-skilled)

day

18.00

180.07

3241.26

L-14

Diver

day

1.50

206.99

310.49

L-07

hour

8.00

1176.12

9408.96

P&M-075

hour

4.50

513.00

2308.50

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

1171.75

Consumables in sinking @ 10 per cent of (b)

c)

Add for dewatering @ 5 per cent of cost of (b), if


required
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

644.46
4535.23
2267.62

Cost for 0.5m = a+b+c+d

24943.79
49887.57

Rate per metre = (a+b+c+d)/0.50


say

12.17

49888.00

Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a)

Material
Kg

Gelatine 80 per cent


309

12.00

112.77

1353.25

M-104

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
each.

Electric Detonators
b)

c)

Quantity

Rate Rs

48.00

14.27

684.78 M-094/100

Labour
day

1.35

185.07

249.84

L-12

Driller

day

2.00

206.99

413.98

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

26.00

177.07

4603.82

L-13

Mazdoor (Skilled)

day

4.00

206.99

827.96

L-15

hour

10.00

1176.12

11761.20

P&M-075

hour

3.50

513.00

1795.50

P&M-063

Machinery

677.84

Consumables in sinking @ 10 per cent of cost of (b+c).

1972.46

d)

Overhead charges @ 0.25 on (a+b+c)

6103.24

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3051.62
33567.82

Cost for 0.5m = a+b+c+d

67135.63

Rate per metre = (a+b+c+d)/0.50


say

1200

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost (c), if required.

12.18

Cost Rs

67136.00

Sinking of 12 m external diameter well ( other than


pneumatic method of sinking ) through all types of strata
namely sandy soil, clayey soil and rock as shown against
each case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 0.25 m
Diameter of well - 12 m.
A

Sandy Soil

(i)

I) Depth below bed level upto 3.0 M


Rate of sinking @ 0.05 m/hour
a)

b)

Labour
Mate

day

0.22

185.07

40.72

L-12

Sinker ( skilled )

day

1.75

206.99

362.23

L-15

Sinking helper (semi-skilled)

day

4.00

180.07

720.28

L-14

hour

6.00

1176.12

7056.72

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

705.67
2221.40
1110.70
12217.73

Cost for 0.25m = a+b+c+d

48870.91

Rate per metre = (a+b+c+d)/0.25


say

12.18 A

(ii)

P&M-075

48871.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.038 m/hour
a)

b)

Labour
Mate

day

0.37

185.07

68.48

L-12

Sinker

day

2.50

206.99

517.48

L-15

Sinking helper (semi-skilled)

day

4.75

180.07

855.33

L-14

hour

6.50

1176.12

7644.78

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.

764.48

Consumables in sinking @10 per cent of (b)


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2462.64
1231.32
13544.49

Cost for 0.25m = a+b+c+d

310

P&M-075

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

54177.98

Rate per metre = (a+b+c+d)/0.25


say

12.18 A

(iii)
a

12.18 A

12.18 A

(iv)

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

56887.00

12th m

5%

59731.00

13th m

5%

62718.00

14th m

5%

65854.00

15th m

5%

69147.00

16th m

5%

72604.00

17th m

5%

76234.00

18th m

5%

80046.00

19th m

5%

84048.00

20th m

5%

Total Cost from 10m upto 20m


Avg Rate per metre

71552.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour.

(b)Including
20% for
Kentledge

7.5%

94869.00

113843.00

22nd m

7.5%

101984.00

122381.00

23rd m

7.5%

109633.00

131560.00

24th m

7.5%

117855.00

141426.00

25th m

7.5%

126694.00

152033.00

26th m

7.5%

136196.00

163435.00

27th m

7.5%

146411.00

175693.00

28th m

7.5%

157392.00

188870.00

29th m

7.5%

169196.00

203035.00

30th m

7.5%

181886.00

218263.00

Total Cost from 20m upto 30m

1342116.00

1610539.00

Avg Rate per metre

134212.00

161054.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

(a)

(b)Including
20% for
Kentledge

31st m

10%

200075.00

240090.00

32nd

10%

220083.00

264100.00

33rd m

10%

242091.00

290509.00

34th m

10%

266300.00

319560.00

35th m

10%

292930.00

351516.00

36th m

10%

322223.00

386668.00

37th m

10%

354445.00

425334.00

38th m

10%

389890.00

467868.00

39th m

10%

428879.00

514655.00

40th m

10%

471767.00

566120.00

Avg Rate per metre


Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i)

(a)

21st m

(v)

88250.00
715519.00

Total Cost from 30m upto 40m


12.18

Cost Rs

Depth below bed level upto 3.0 M


Rate of sinking @ 0.04 m/hour
311

3188683

3826420

318868.00

382642.00

54178.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

Unit

Quantity

Rate Rs

Mate

day

0.30

185.07

55.52

L-12

Sinker ( skilled )

day

3.00

206.99

620.97

L-15

Sinking helper (semi-skilled)

day

4.50

180.07

810.32

L-14

hour

6.25

1176.12

7350.75

Machinery

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

P&M-075

735.08
2393.16
1196.58
13162.37

Cost for 0.25m = a+b+c+d


Rate per metre = (a+b+c+d)/0.25

52649.47
say

(ii)

Remarks/
Input ref.

Labour

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

12.18 B

Cost Rs

52649.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.03 m/hour
a)

b)

Labour
Mate

day

0.48

185.07

88.83

L-12

Sinker

day

3.75

206.99

776.21

L-15

Sinking helper (semi-skilled)

day

6.00

180.07

1080.42

L-14

hour

8.33

1176.12

9797.08

P&M-075

hour

4.50

513.00

2308.50

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1210.56
3815.40
1907.70

Cost for 0.25m = a+b+c+d

20984.71

Rate per metre = (a+b+c+d)/0.25

83938.82
say

12.18 B

12.18 B

(iii)
a

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add for dewatering @ 5 per cent of cost, if required.

(iv)

83939.00

Beyond 10 m upto 20 m

(a) (b)Including for


dewatering @
5% of cost, if
required

11th m

5%

88136.00

12th m

5%

92543.00

92543.00
97170.00

13th m

5%

97170.00

102029.00

14th m

5%

102029.00

107130.00

15th m

5%

107130.00

112487.00

16th m

5%

112487.00

118111.00

17th m

5%

118111.00

124017.00

18th m

5%

124017.00

130218.00

19th m

5%

130218.00

136729.00

20th m

5%

136729.00

143565.00

Total Cost from 10m upto 20m

1108570.00

1163999.00

Avg Rate per metre

110857.00

116400.00

Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering on the cost, if required

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(a)

(c)Including (b)Including
25% for
5% for
Kentledge dewatering, if
required

21st m

7.5%

146984.00

183730.00

192917.00

22nd

7.5%

158008.00

197510.00

207386.00

312

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

23rd m

7.5%

169859.00

212324.00

222940.00

24th m

7.5%

182598.00

228248.00

239660.00

25th m

7.5%

196293.00

245366.00

257634.00

26th m

7.5%

211015.00

263769.00

276957.00

27th m

7.5%

226841.00

283551.00

297729.00

28th m

7.5%

243854.00

304818.00

320059.00

29th m

7.5%

262143.00

327679.00

344063.00

30th m

7.5%

281804.00

352255.00

369868.00

2079399

2599250

2729213

207940.00

259925.00

272921.00

Total Cost from 20m upto 30m


Avg Rate per metre
12.18 B

(v)
a

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

(a)

Remarks/
Input ref.

(c ) Including (b)Including
20% for
5% for
Kentledge dewatering, if
required

31st m

10%

309984.00

371981.00

390580.00

32nd

10%

340982.00

409178.00

429637.00

33rd m

10%

375080.00

450096.00

472601.00

34th m

10%

412588.00

495106.00

519861.00

35th m

10%

453847.00

544616.00

571847.00

36th m

10%

499232.00

599078.00

629032.00

37th m

10%

549155.00

658986.00

691935.00

38th m

10%

604071.00

724885.00

761129.00

39th m

10%

664478.00

797374.00

837243.00

40th m

10%

730926.00

877111.00

920967.00

Avg Rate per metre


C

Cost Rs

Beyond 30m upto 40 m

Total Cost from 30m upto 40m


12.18

Rate Rs

4940343

5928411

6224832

494034.00

592841.00

622483.00

Soft Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a)

b)

Labour
Mate

day

1.06

185.07

196.17

L-12

Sinker ( skilled )

day

4.50

206.99

931.46

L-15

Sinking helper (semi-skilled)

day

20.00

180.07

3601.40

L-14

Diver

day

1.75

206.99

362.23

L-07

hour

10.00

1176.12

11761.20

P&M-075

hour

4.75

513.00

2436.75

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

1419.80
780.89

Add for dewatering @ 5 per cent, if required


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

5372.47
2686.24
29548.60

Cost for 0.25m = a+b+c+d

118194.42

Rate per metre = (a+b+c+d)/0.25


say

12.18

Hard Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m

(i)

Depth in hard rock strata upto 3 m


Rate of sinking @ 0.020 m/hour

313

118194.00

Sr No

Ref. to
MoRTH
Spec.

Description
a)

Unit

Electric detonator

c)

Rate Rs

Kg

14.00

112.77

each.

56.00

14.27

1578.79

M-104

798.90 M-094/100

Labour
day

1.44

185.07

266.50

L-12

Driller

day

2.00

206.99

413.98

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

28.00

177.07

4957.96

L-13

Mazdoor (Skilled)

day

4.50

206.99

931.46

L-15

hour

12.50

1176.12

14701.50

P&M-075

hour

4.00

513.00

2052.00

P&M-063

Machinery

837.68

Consumables in sinking @ 10 per cent of (c).

1759.12

d)

Overhead charges @ 0.25 on (a+b+c)

7092.55

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3546.28
39009.05

Cost for 0.25m = a+b+c+d+e

156036.18

Rate per metre = (a+b+c+d+e)/0.25


say

1200

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent, if required.

12.19

Cost Rs

Material
Gelatine80 per cent

b)

Quantity

156036.00

Sinking of Twin D Type well (other than pneumatic


method of sinking) through all types of strata namely
sandy soil, clayey soil and rock as shown against each
case, complete as per drawing and technical
specifications. Depth of sinking is reckoned from bed
level.
Unit = Running Meter
Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A

Sandy Soil

(i)

Depth from bed level upto 3.0 M


Rate of sinking @ 0.18 m/hour
a)

b)

Labour
Mate

day

0.20

185.07

37.01

L-12

Sinker ( skilled )

day

1.25

206.99

258.74

L-15

Sinking helper (semi-skilled)

day

3.75

180.07

675.26

L-14

hour

5.50

1176.12

6468.66

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

646.87

c)

Overhead charges @ 0.25 on (a+b)

2021.64

d)

Contractor's profit @ 0.1 on (a+b+c)

1010.82
11118.99

Rate per metre = (a+b+c+d)


say

12.19 A

(ii)

P&M-075

11119.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.17 m/hour
a)

b)

Labour
Mate

day

0.30

185.07

55.52

L-12

Sinker

day

1.50

206.99

310.49

L-15

Sinking helper (semi-skilled)

day

4.00

180.07

720.28

L-14

hour

5.88

1176.12

6915.59

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @10 per cent of (b)

c)

691.56
2173.36

Overhead charges @ 0.25 on (a+b)


314

P&M-075

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Unit

Quantity

Rate Rs

1086.68

Contractor's profit @ 0.1 on (a+b+c)

11953.47

Rate per metre = (a+b+c+d)


say

12.19 A

(iii)
a

12.19 A

(iv)
a
b

12.19 A

12.19

Beyond 10m upto 20m


Add 5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
11th m

5%

12551.00

12th m

5%

13179.00

13th m

5%

13838.00

14th m

5%

14530.00

15th m

5%

15257.00

16th m

5%

16020.00

17th m

5%

16821.00

18th m

5%

17662.00

19th m

5%

18545.00

20th m

5%

157875.00

Avg Rate per metre

15788.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 20 per cent of cost for Kentledge including supports,
loading arrangement and Labour.

(a)

(b)Including
20% for
Kentledge

21st m

7.5%

20932.00

25118.00

22nd m

7.5%

22502.00

27002.00

23rd m

7.5%

24190.00

29028.00

24th m

7.5%

26004.00

31205.00

25th m

7.5%

27954.00

33545.00

26th m

7.5%

30051.00

36061.00

27th m

7.5%

32305.00

38766.00

28th m

7.5%

34728.00

41674.00

29th m

7.5%

37333.00

44800.00

30th m

7.5%

40133.00

48160.00

Total Cost from 20m upto 30m

296132.00

355359.00

Avg Rate per metre

29613.00

35536.00

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 20 per cent of cost for Kentledge including supports,


loading arrangement, and Labour etc.

(a)

(b)Including
20% for
Kentledge

31st m

10%

44146.00

52975.00

32nd

10%

48561.00

58273.00

33rd m

10%

53417.00

64100.00

34th m

10%

58759.00

70511.00

35th m

10%

64635.00

77562.00

36th m

10%

71099.00

85319.00

37th m

10%

78209.00

93851.00

38th m

10%

86030.00

103236.00

39th m

10%

94633.00

113560.00

40th m

10%

104096.00

124915.00

Total Cost from 30m upto 40m

703585.00

844302.00

Avg Rate per metre

70359.00

84430.00

Clayey Soil (Twin D Type Well )


Unit = Running Meter
Taking output = 1 meter

(i)

19472.00

Total Cost from 10m upto 20m

(v)

Cost Rs

Depth below bed level upto 3.0 M

315

11953.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Rate of sinking @ 0.16 m/hour


a)

b)

Labour
Mate

day

0.26

185.07

48.12

L-12

Sinker ( skilled )

day

2.50

206.99

517.48

L-15

Sinking helper (semi-skilled)

day

4.00

180.07

720.28

L-14

hour

6.25

1176.12

7350.75

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Consumables in sinking @ 10 per cent of (b)

735.08

c)

Overhead charges @ 0.25 on (a+b)

2342.92

d)

Contractor's profit @ 0.1 on (a+b+c)

1171.46

Rate per metre = (a+b+c+d)

12886.09
say

12.19 B

(ii)

P&M-075

12886.00

Beyond 3m upto 10m depth


Rate of sinking @ 0.15 m/hour
a)

b)

Labour
Mate

day

0.45

185.07

83.28

L-12

Sinker

day

3.25

206.99

672.72

L-15

Sinking helper (semi-skilled)

day

6.00

180.07

1080.42

L-14

hour

6.67

1176.12

7844.72

P&M-075

hour

4.50

513.00

2308.50

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic chisel attachment for
cutting hard clay.
Consumables in sinking @ 10 per cent of (b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

1015.32
3251.24
1625.62
17881.82

Rate per metre = (a+b+c+d)


say

12.19 B

12.19 B

(iii)

Beyond 10 m upto 20 m

Add 5 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add for dewatering @ 5 per cent of cost, if required.

(iv)
a
b
c

17882.00

(a) (b)Including for


dewatering @
5% of cost, if
required

11th m

5%

18776.00

19715.00

12th m

5%

19715.00

20701.00

13th m

5%

20701.00

21736.00

14th m

5%

21736.00

22823.00

15th m

5%

22823.00

23964.00

16th m

5%

23964.00

25162.00

17th m

5%

25162.00

26420.00

18th m

5%

26420.00

27741.00

19th m

5%

27741.00

29128.00

20th m

5%

29128.00

30584.00

Total Cost from 10m upto 20m

236166.00

247974.00

Avg Rate per metre

23617.00

24797.00

Beyond 20m upto 30 m


Add 7.5 per cent for every additional meter depth of sinking
over the rate of sinking for the previous meter
Add 5 per cent of cost for dewatering on the cost, if required
(a)

Add 25 per cent of cost for Kentledge including supports,


loading arrangement and Labour ).

(c)Including (b)Including
25% for
5% for
Kentledge dewatering, if
required

21st m

7.5%

31313.00

39141.00

41098.00

22nd

7.5%

33661.00

42076.00

44180.00

23rd m

7.5%

36186.00

45233.00

47495.00

316

Sr No

12.19 B

12.19

Ref. to
MoRTH
Spec.

Description

(v)

Unit

Rate Rs

Cost Rs

24th m

7.5%

38900.00

48625.00

51056.00

25th m

7.5%

41818.00

52273.00

54887.00

26th m

7.5%

44954.00

56193.00

59003.00

27th m

7.5%

48326.00

60408.00

63428.00

28th m

7.5%

51950.00

64938.00

68185.00

29th m

7.5%

55846.00

69808.00

73298.00

30th m

7.5%

60034.00

75043.00

78795.00

Total Cost from 20m upto 30m

442988.00

553738.00

581425.00

Avg Rate per metre

44299.00

55374.00

58143.00

Remarks/
Input ref.

Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking


over the rate of sinking for the previous meter

Add 5 per cent of cost for dewatering, if required

Add 20 per cent of cost for Kentledge including supports,


loading arrangement and Labour).

Quantity

(a)

(c ) Including (b)Including
20% for
5% for
Kentledge dewatering, if
required

31st m

10%

66037.00

79244.00

83206.00

32nd

10%

72641.00

87169.00

91527.00

33rd m

10%

79905.00

95886.00

100680.00

34th m

10%

87896.00

105475.00

110749.00

35th m

10%

96686.00

116023.00

121824.00

36th m

10%

106355.00

127626.00

134007.00

37th m

10%

116991.00

140389.00

147408.00

38th m

10%

128690.00

154428.00

162149.00

39th m

10%

141559.00

169871.00

178365.00

40th m

10%

155715.00

186858.00

196201.00

Total Cost from 30m upto 40m

1052475.00

1262969.00

1326116.00

Avg Rate per metre

105248.00

126297.00

132612.00

Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a)

b)

Labour
Mate

day

0.86

185.07

159.16

L-12

Sinker ( skilled )

day

4.50

206.99

931.46

L-15

Sinking helper (semi-skilled)

day

15.00

180.07

2701.05

L-14

Diver

day

1.50

206.99

310.49

L-07

hour

8.33

1176.12

9797.08

P&M-075

hour

6.00

513.00

3078.00

P&M-063

Machinery
Hire & running charges of crane with grab bucket of
0.75 cum capacity and accessories.
Air compressor with pneumatic breakers

1287.51

Consumables in sinking @ 10 per cent of (b)

708.13

Add for dewatering @ 5 per cent, if required


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4743.22
2371.61
26087.69

Rate per metre = (a+b+c+d)


say

12.19

26088.00

Hard Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a)

Material
Kg

Geletine80 per cent


317

10.00

112.77

1127.71

M-104

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
each.

Electric detonators
b)

c)

Quantity

Rate Rs

40.00

14.27

570.65 M-094/100

Labour
day

1.34

185.07

247.99

L-12

Driller

day

2.00

206.99

413.98

L-06

Blaster

day

0.25

289.31

72.33

L-03

Mazdoor

day

25.00

177.07

4426.75

L-13

Mazdoor (Skilled)

day

4.25

206.99

879.71

L-15

hour

10.00

1176.12

11761.20

P&M-075

hour

3.00

513.00

1539.00

P&M-063

Machinery

967.05

Consumables in sinking @ 10 per cent of (b).

1426.72

d)

Overhead charges @ 0.25 on (a+b+c)

5858.27

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2929.14
32220.50

Rate per metre = (a+b+c+d+e)


say

1200

Remarks/
Input ref.

Mate

Hire & running charges of crane with grab bucket of


0.75 cum capacity and accessories.
Hire & running charges of compressor with pneumatic
breaker/Jack hammer or drill
Dewatering @ 5 per cent of cost of (b+c), if required.

12.20

Cost Rs

32220.00

Pneumatic sinking of wells with equipment of approved


design, drawing and specifications worked by competent
and trained personnel and comprising of compression
and decompression chambers, reducers, two air locks
separately for men and plant & materials, arrangement
for supply of fresh air to working chambers, check
valves, exhaust valves, shafts made from steel plates of
riveted construction not less than 6 mm thick to
withstand an air pressure of 0.50 MPa, controlled blasting
of hard rock where required, staircases and 1 m wide
landing plateforms with railing, arrangement for
compression and decompression, electric lighting of 50
V maximum, proper rooms for rest and medical
examinations and compliance with safety precautions as
per IS:4138, all as per clause1207.6 of MoRTH
Specifications.

Unit - 1 cum
Taking output = 5 cum
a)

Material
M35 grade RCC corbel provided for supporting of
equipment (Dimensions as per ground conditions). Rate
may be adopted vide Item 12.8 (H)
HYSD bar reinforcement in corbel

Cum

8.00

3669.00

29352.00

Item 12.8
(H)

tonne

0.48

46059.03

22108.33

M-082

169.16

M-104

Blasting material
Kg

1.50

112.77

each

6.00

14.27

Medical Officer

day

0.50

0.00

Para medical personnel

day

1.00

Mate

day

1.86

Driller

day

1.00

206.99

Blaster

day

0.50

Mazdoor (for cutting, blasting, cleaning, removal of


Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter
for air lock, carrying out mechanical and electrical
operations and repairs and other skilled jobs.)

day

30.00

day

Diver

day

Gelatine 80 per cent


Electric detonators
b)

c)

85.60 M-094/100

Labour

Machinery

318

0.00

L-16

0.00

0.00

L-19

185.07

344.23

L-12

206.99

L-06

289.31

144.66

L-03

177.07

5312.10

L-13

10.00

206.99

2069.90

L-15

4.00

206.99

827.96

L-07

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

(i) Induction, deinduction and erection of plant and


equipment including all components and
accessories for pneumatic method of well sinking.

6.00

Rate Rs
Value

L.S

Induction and deinduction


Usage of plant and equipment for pneumatic method of
well sinking
Air compressor 250 cfm, 2 nos.

hour

Cost Rs
#VALUE!

Remarks/
Input ref.
P&M-082

100000.00

L.S

Erection at site and commissioning

Note

hour

Quantity

150000.00
6.00

3834.00

23004.00

P&M-038

hour

2x6

293.76

3525.12

P&M-001

Hire and running charges of crane of 15 tonne capacity

hour

6.00

770.04

4620.24

P&M-072

Motorised barge of 20 tonne capacity

hour

6.00

142.56

855.36

P&M-066

Boat to carry atleast 20 persons

hour

6.00

142.56

855.36

P&M-066

Electric generating set 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Tipper 10 tonne capacity

hour

6.00

873.00

5238.00

P&M-048

d)

Overhead charges @ 0.25 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Cost for 5 cum = a+b+c+d+e (see notes below)

#VALUE!

Rate per cum = (a+b+c+d+e)/5

#VALUE!

1.The cost of induction, deinduction and erection of


equipment shall be divided by the total quantity of pneumatic
sinking for all the wells of a particular bridge to arrive at the
per cum rate on account of this item.
2.Cost of pneumatic sinking per cum of individual wells will be
added to the cost indicated at (1) above to arrive at the final
rate of pneumatic sinking per cum.
3.The cost of induction and deinduction will depend upon the
distance involved for shifting of equipment which may be
assessed in individual cases as per actual ground conditions
at the time of making of cost estimates.
4.In case pneumatic sinking is involved on a dry bed, the
provision of barge and boat may be omitted.
5.The necessity and dimensions of the corbel will be as per
actual ground conditions.
6.Small equipments like welding sets, pumps, vibrators,
pneumatic tools, portable lamps, fire extinguishers, hose
pipes etc., have not been included as the same are covered
as items of minor T&P under overhead charges.
7.Depth of sinking shall be restricted to 30 m.

12.21

1207

Sand Filling in Wells complete as per Drawing and


Technical Specifications.
Unit = 1 cum
Taking output = 1 cum
a)

Material
cum

1.20

109.09

Mate

day

0.01

185.07

1.85

L-12

Mazdoor

day

0.30

177.07

53.12

L-13

Sand (assuming 20 per cent voids )


b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

46.47
23.23
255.58
say

1200 &
1900

M-006

Labour

Rate per cum (a+b+c+d)


12.22

130.90

256.00

Providing Steel Liner 10 mm thick for Curbs and 6 mm


thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a)

Material
i) Structural steel including 5 per cent wastage

b)

Labour

319

tonne

1.05

46527.33

48853.70

M-179

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

day

1.24

185.07

229.49

L-12

Fitter

day

6.00

238.29

1429.74

L-08

Blacksmith

day

5.00

208.99

1044.95

L-01

Welder

day

5.00

234.29

1171.45

L-02

Mazdoor

day

10.00

177.07

1770.70

L-13

c)

Electrodes, cutting gas and other consumables @ 5 per


cent on cost a (a) above.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2442.69
14235.68
7117.84
78296.23
say

1100 &
1700

Remarks/
Input ref.

Mate

Rate for per MT (a+b+c+d)


12.23

Cost Rs

78296.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a)

Materials
cum

6.62

5478.00

36264.36 Item 12.11


(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.

hour

6.00

5023.08

30138.48

P&M-036

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

535.00

267.50

P&M-013

hour

6.00

Rate included
in piling rig

Loader I cum bucket capacity.

hour

0.30

1188.00

356.40

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.30

873.00

261.90

P&M-048

300.00

2.24

673.49

M-071

PCC Grade M35


Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

kg

Labour
Mate/Supervisor

day

0.14

185.07

25.91

L-12

Mazdoor

day

3.50

177.07

619.75

L-13

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

8085.86
4042.93
80736.57

Cost for 15 m = a+b+c+d+d+e

5382.44

Rate per metre (a+b+c+d+e)/15


say

12.24
1100,160
0 & 1700

5382.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a)

Materials
PCC Grade M35

cum

7.85

5478.00

43002.30 Item 12.11


(C) iv

hour

6.00

5023.08

30138.48

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

Machinery( for boring and construction )


Hire and running charges of hydraulic piling rig with
power unit and complete accessories including shifting
from one bore location to another.
320

P&M-036

Sr No

Ref. to
MoRTH
Spec.

c)

Description

Unit

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

535.00

hour

6.00

Rate included
in piling rig

Loader I cum bucket capacity.

hour

0.40

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.40

kg

Quantity

Rate Rs

P&M-013

1188.00

475.20

P&M-017

873.00

349.20

P&M-048

350.00

2.24

785.74

M-071

Labour
Mate/Supervisor

day

0.16

185.07

29.61

L-12

Mazdoor

day

4.00

177.07

708.28

L-13

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

8188.50
4094.25
88039.07
8803.91

Rate per metre (a+b+c+d+e)/10


say

1100 &
1700

Remarks/
Input ref.

267.50

Cost for 10 m = a+b+c+d+d+e

12.25

Cost Rs

8804.00

Bored cast-in-situ M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a)

Materials
cum

10.17

5478.00

55711.26 Item 12.11


(C) iv

Hire and running charges of hydraulic piling rig with


power unit and complete accessories including shifting
from one bore location to another.

hour

6.00

5023.08

30138.48

P&M-036

Hire and running charges of light crane for lowering


reinforcement cage
Hire and running charges of Bentonite pump

hour

0.50

535.00

267.50

P&M-013

hour

6.00

Rate included
in piling rig

Loader I cum bucket capacity.

hour

0.50

1188.00

594.00

P&M-017

Tipper 5.5 cum capacity for disposal of muck from pile


bore hole
Bentonite

hour

0.50

873.00

436.50

P&M-048

864.32

M-071

PCC Grade M35


Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)

c)

Machinery( for boring and construction )

kg

385.00

2.24

Labour
Mate/Supervisor

day

0.18

185.07

33.31

L-12

Mazdoor

day

4.50

177.07

796.82

L-13

d)

Overhead charges @ 0.25 on (b+c)

e)

Contractor's profit @ 0.1 on (b+c+d)

8282.73
4141.37
101266.28

Cost for 9 m = a+b+c+d+d+e

11251.81

Rate per metre (a+b+c+d+e)/9


say

12.26

1100 &
1700

11252.00

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 750 mm
Unit = Running meter
Taking output = 40 metre
a)

Materials
cum

PCC Grade M35


Rate for concrete may be adopted same as for bottom plug
vide item no. 12.11( C ) (IV)
b)

Materials Pile shoes


321

17.66

5478.00

96741.48 Item 12.11


(C) iv

Sr No

Ref. to
MoRTH
Spec.

Description

c)

d)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

M-124

iii) Steel helmet and cushion block on top of casing head


during driving
Machinery

Kg

50.00

51.16

2558.23

M-173

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit and
accessories..

hour

6.00

5023.08

30138.48

P&M-085

Hiring and running charges for light crane 5 tonnes


lifting capacity for lowering reinforcement and handling
steel casing.
Labour

hour

0.50

599.40

299.70

P&M-070

Mate/Supervisor

day

0.12

185.07

22.21

L-12

Mazdoor

day

3.00

177.07

531.21

L-13

e)

Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

11803.22
5901.61
161659.19

Cost for 40 m = a+b+c+d+e

4041.48

Rate per metre (a+b+c+d+e)/40


say

Note

Cost Rs

4041.00

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.

12.27

1100 &
1700

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a)

Materials
cum

PCC Grade M35

23.55

5478.00

129006.90 Item 12.11


(C) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b)

Materials Pile shoes


i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

M-124

50.00

51.16

2558.23

M-173

c)

iii) Steel helmet and cushion block on top of casing head


during driving
Machinery

Kg

hour

6.00

5023.08

30138.48

P&M-085

hour

0.50

599.40

299.70

P&M-070

hour

0.50

535.00

267.50

P&M-013

d)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
Hire and running charges for light crane for lowering
reinforcement cage.
Labour
Mate/Supervisor

day

0.16

185.07

29.61

L-12

Mazdoor

day

4.00

177.07

708.28

L-13

e)

Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

11916.21
5958.11
194546.07

Cost for 30 m = a+b+c+d+e

6484.87

Rate per metre (a+b+c+d+e)/30


say

322

6485.00

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.

12.28

1100 &
1700

Driven cast-in-place vertical M35 grade R.C.C. Pile


excluding Reinforcement complete as per Drawing and &
Technical Specification
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a)

Materials
PCC Grade M35

cum

22.61

5478.00

123857.58 Item 12.11


(C) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

M-080

ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m

Kg

70.00

66.31

4641.36

M-124

iii) Steel helmet on top of casing head during driving

Kg

50.00

51.16

2558.23

M-173

c)

Machinery
hour

6.00

5023.08

30138.48

P&M-085

hour

0.50

599.40

299.70

P&M-070

d)

Hire and running charges of piling rig Including double


acting pile driving hammer complete with power unit and
accessories.
Hiring and running charges for light crane 5 tonnes
lifting capacity for lowering reinforcement and handling
steel casing.
Labour
Mate/Supervisor

day

0.18

185.07

33.31

L-12

Mazdoor

day

4.50

177.07

796.82

L-13

e)

Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

11872.40
5936.20
189155.76

Cost for 20 m = a+b+c+d+e

9457.79

Rate per metre (a+b+c+d+e)/20


say

Note

12.29

1100 &
1700

9458.00

1.The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
2.In case steel lining is included in the design for driven castin-situ pile and is planned to be retained, the same may be
included in the rate analysis. In case the temporary steel
casing used during casting is planned to be removed, an
additional cost @ 0.50 per cent of cost of concrete may be
provided to cover its usage.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 500 mm
Unit = Running Meter
Taking output = 60 m
a)

Materials
cum

RCC Grade M35

11.78

5195.00

61197.10 Item 12.11


(F) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes

Kg

240.00

56.39

13532.53

M-080

b) M.S. shoes

Kg

105.00

42.08

4418.43

M-125

323

Sr No

Ref. to
MoRTH
Spec.

Description

c)

d)

Unit

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

Quantity

Rate Rs
51.16

1534.94

M-173

785.16

4710.96

P&M-073

#VALUE!

P&M-092

Crane20 t capacity

hour

6.00

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

Mate/Supervisor

day

0.12

185.07

22.21

L-12

Mazdoor

day

3.00

177.07

531.21

L-13

Value

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.

#VALUE!

e)

Overhead charges @ 0.25 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!
#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e+f)/60


say

12.30

1100 &
1700

Remarks/
Input ref.

30.00

Cost for 60 m = a+b+c+d+e+f

Note

Cost Rs

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 750 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials
cum

RCC Grade M35

22.08

5195.00

114705.60 Item 12.11


(F) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes

Kg

160.00

56.39

9021.68

M-080

b) M.S. shoes

Kg

70.00

42.08

2945.62

M-125

Kg

40.00

51.16

2046.59

M-173

c)

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery
Crane 40 T capacity

hour

6.00

1166.40

6998.40

P&M-074

hour

6.00

#VALUE!

P&M-092

d)

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour
Mate/Supervisor

day

0.16

185.07

29.61

L-12

Mazdoor

day

4.00

177.07

708.28

L-13

Value

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 50 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/50


say

Note

12.31

1100 &
1700

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Pile Diameter = 1000 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials

324

#VALUE!

Sr No

Ref. to
MoRTH
Spec.

Description

Unit
cum

RCC Grade M35

Quantity

Rate Rs

31.40

5195.00

Cost Rs

Remarks/
Input ref.

163123.00 Item 12.11


(F) iv

Rate for concrete may be adopted same as for bottom


plug vide item no. 12.11( F ) (IV)
b ) Material Pile shoes

c)

d)

a) C.I. shoes for the pile

Kg

160.00

56.39

9021.68

M-080

b) M.S. shoes @ 35 Kg per pile of 15 m

Kg

70.00

42.08

2945.62

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

50.00

51.16

2558.23

M-173

1176.12

7056.72

P&M-011

#VALUE!

P&M-092

Crane 50 t capacity.

hour

6.00

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

Mate/Supervisor

day

0.20

185.07

37.01

L-12

Mazdoor

day

5.00

177.07

885.35

L-13

Value

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 40 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/40


say

Note

12.32

1100&17
00

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 300 mm x 300 mm
Unit = Running Meter
Taking output = 60 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)

cum

5.40

5195.00

28053.00 Item 12.11


(F) iv

b ) Material Pile shoes

c)

a) C I shoes

kg

240.00

56.39

13532.53

M-080

b) M. S shoes

kg

105.00

42.08

4418.43

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

M-173

hour

6.00

627.48

3764.88

P&M-071

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.12

185.07

Mazdoor

day

3.00

177.07

Crane 10 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Value

L-12

531.21

L-13

#VALUE!

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

#VALUE!

Cost for 60 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/60


say

Note

22.21

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.

325

#VALUE!

Sr No
12.33

Ref. to
MoRTH
Spec.

Description

1100
&1700

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Driven precast vertical M35 grade R.C.C. Piles excluding


Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 500 mm x 500 mm
Unit = Running Meter
Taking output = 50 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 12.11( F ) (IV)

cum

12.50

5195.00

64937.50 Item 12.11


(F) iv

b ) Material Pile shoes

c)

a) C I shoes

kg

160.00

56.39

9021.68

M-080

b) M. S shoes

kg

70.00

42.08

2945.62

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

M-173

hour

6.00

785.16

4710.96

P&M-073

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.16

185.07

29.61

L-12

Mazdoor

day

4.00

177.07

708.28

L-13

Crane 20 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

Value

e)

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.
Overhead charges @ 0.25 on (b+c+d)

#VALUE!

f)

Contractor's profit @ 0.1 on (b+c+d+e)

#VALUE!

#VALUE!

Cost for 50 m = a+b+c+d+e+f

#VALUE!

Rate per metre (a+b+c+d+e+f)/50

#VALUE!
say

Note

12.34

1100
&1700

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding
Reinforcement complete as per Drawing and & Technical
Specification
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a)

Materials

RCC Grade M-35


Rate for concrete may be adopted same as for bottom
plug vide item no. 13.11( F ) (IV)
b ) Material

cum

22.50

5195.00

116887.50 Item 12.11


(F) iv

Pile shoes

c)

a) C I shoes

kg

160.00

56.39

9021.68

M-080

b) M. S shoes

kg

70.00

42.08

2945.62

M-125

c) Steel helmet and cushion block on top of pile head


during driving.
Machinery

Kg

30.00

51.16

1534.94

M-173

hour

6.00

785.16

4710.96

P&M-073

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.18

185.07

33.31

L-12

Mazdoor

day

4.50

177.07

796.82

L-13

Crane 20 tonne capacity


Vibrating Pile driving hammer complete with power unit
and accessories.
d ) Labour

e)

Value

Add 1 per cent of (a+b+c) for carriage of piles from


casting yard to work site and stacking, and other
imponderables during installation.

#VALUE!

Overhead charges @ 0.25 on (b+c+d)

#VALUE!

326

Sr No

Ref. to
MoRTH
Spec.

Description
f)

Unit

Quantity

Rate Rs

#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e+f)/40


say

12.35

1100,
1900

Remarks/
Input ref.

#VALUE!

Contractor's profit @ 0.1 on (b+c+d+e)

Cost for 40 m = a+b+c+d+e+f

Note

Cost Rs

#VALUE!

The quantity of concrete required to be removed above the


designed top level of concrete, if any, will be provided for in
the rate analysis.
Driven Vertical Steel Piles complete as per Drawing and &
Technical Specification
Section of the pile - H Section steel column 400 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 70 m
a)

Materials

b)

Structural steel including 5 per cent wastage @ 82.20


kg/m
Machinery

c)

tonnes

6.04

46527.33

281025.09

Crane 10 T capacity

hour

6.00

627.48

3764.88

P&M-071

Vibrating Pile driving hammer complete with power unit


and other accessories.

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.12

185.07

Mazdoor

day

3.00

177.07

Value

Labour
L-12

531.21

L-13

#VALUE!

d)

Overhead charges @ 0.25 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!
#VALUE!

Rate per metre (a+b+c+d+e)/70


say

1100
&1900

22.21

Add 0.5 per cent of (a+b+c) for providing steel


helmet on top of pile head during driving, stacking of
piles at site, providing anti-corrosion treatment and other
imponderables during installation.

Cost for 70 m = a+b+c+d+e

12.36

M-179

#VALUE!

Driven Vertical Steel Piles complete as per Drawing and &


Technical Specification
Section of the pile - H Section steel column 450 x 250 mm
(ISHB Series)
Unit = Running Meter
Taking output = 60 m
a)

Materials

b)

Structural steel including 5 per cent wastage @92.50


kg/m
Machinery

c)

tonnes

5.83

46527.33

271254.35

Crane 10 T capacity

hour

6.00

627.48

3764.88

P&M-071

Vibrating Pile driving hammer complete with power unit


and accessories.
Labour

hour

6.00

#VALUE!

P&M-092

Mate/Supervisor

day

0.14

185.07

25.91

L-12

Mazdoor

day

3.50

177.07

619.75

L-13

Value

Add 0.5 per cent of (a+b+c) for providing steel


helmet and cushion block on top of pile head during
driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

#VALUE!

d)

Overhead charges @ 0.25 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!
#VALUE!

Cost for 60 m = a+b+c+d+e

#VALUE!

Rate per metre (a+b+c+d+e)/60


say

12.37

1100

Pile Load Test on single Vertical Pile in accordance with


IS:2911(Part-IV)
Unit = 1 MT
327

#VALUE!

M-179

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Taking output = 1 MT

Note

12.38

1100,
1500
&1700

a) Initial and routine load test

tonne

1.00

300.00

300.00

b) Lateral load test

tonne

1.00

5000.00

5000.00
5300.00

Although, this item is incidental to work and is not required to


be included in BOQ of contract, the same is required to be
added in the estimate to assess cost of work.
Cement Concrete for Reinforced Concrete in Pile Cap
complete as per Drawing and Technical Specification

RCC Grade M20


Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

5.12

5789.47

29642.11

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

208.99

313.49

L-10

Mazdoor for concreting

day

20.00

177.07

3541.40

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

1962.67

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12757.35
6378.67
70165.42

Cost for 15 cum = a+b+c+d+e

4677.69

Rate per metre (a+b+c+d+e)/15


say

12.38A

(ii)

4678.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

5.12

5789.47

29642.11

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-004

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.16

185.07

29.61

L-12

Mason

day

0.38

208.99

79.42

L-10

Mazdoor for concreting

day

2.50

177.07

442.68

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2488.00

1866.00

P&M-002

Generator 100 KVA

hour

0.75

1698.00

1273.50

P&M-080

Loader (capacity 1 cum)

hour

1188.00

891.00

P&M-017

P&M-049

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) Material, b) Labour and c) Machinery
328

hour

2.00

854.55

1709.10

tonne.km

37.5L

4.32

162.00

hour

0.75

234.36

Lead =1
km & P&M050
175.77 P&M-007
1934.00

Sr No

Ref. to
MoRTH
Spec.

Description
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Unit

Quantity

Rate Rs

6285.51
69140.66
4609.38

Rate per metre (a+b+c+d+e)/15


say

12.38

Remarks/
Input ref.

12571.03

Cost for 15 cum = a+b+c+d+e

Note

Cost Rs

4609.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M25
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

5.99

5789.47

34678.95

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

208.99

313.49

L-10

Mazdoor for concreting

day

20.00

177.07

3541.40

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

2164.14
14066.93
7033.46
77368.10

Cost for 15 cum = a+b+c+d+e

5157.87

Rate per metre (a+b+c+d+e)/15


say

12.38B

(ii)

5158.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

5.99

5789.47

34678.95

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-004

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.16

185.07

29.61

L-12

Mason

day

0.38

208.99

79.42

L-10

Mazdoor for concreting

day

2.50

177.07

442.68

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2488.00

1866.00

P&M-002

Generator 125 KVA

hour

0.75

2307.00

1730.25

P&M-018

Loader (capacity 1 cum)

hour

1188.00

891.00

P&M-017

P&M-049

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

1709.10

tonne.km

37.5L

4.32

162.00

hour

0.75

234.36

Lead =1
km & P&M050
175.77 P&M-007
2153.75
13999.36
6999.68

329

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

5133.10

Rate per metre (a+b+c+d+e)/15


say

12.38

Remarks/
Input ref.

76996.50

Cost for 15 cum = a+b+c+d+e

Note

Cost Rs

5133.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M30
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

6.10

5789.47

35315.79

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

208.99

313.49

L-10

Mazdoor for concreting

day

20.00

177.07

3541.40

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

2189.62

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14232.51
7116.25
78278.79

Cost for 15 cum = a+b+c+d+e

5218.59

Rate per metre (a+b+c+d+e)/15


say

'12.38C

(ii)

5219.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

6.10

5789.47

35315.79

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-004

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.16

185.07

29.61

L-12

Mason

day

0.38

208.99

79.42

L-10

Mazdoor for concreting

day

2.50

177.07

442.68

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2488.00

1866.00

P&M-002

Generator 100 KVA

hour

0.75

1698.00

1273.50

P&M-080

Loader (capacity 1 cum)

hour

1188.00

891.00

P&M-017

P&M-049

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

1709.10

tonne.km

37.5L

4.32

162.00

hour

0.75

234.36

Lead =1
km & P&M050
175.77 P&M-007
2160.95
14046.19
7023.09
77254.03

Cost for 15 cum = a+b+c+d+e

5150.27

Rate per metre (a+b+c+d+e)/15


330

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

Note
12.38

Cost Rs

Remarks/
Input ref.

5150.00

The value of a, b and c may be taken as applicable i.e. either


using concrete mixer or batching plant.
RCC Grade M35
Unit = cum
Taking output = 15 cum

(i)

Using Concrete Mixer


a)

Material
tonne

6.33

5789.47

36647.37

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

208.99

313.49

L-10

Mazdoor

day

20.00

177.07

3541.40

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator (capacity 33 KVA)

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

2242.88

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

14578.72
7289.36
80182.95

Cost for 15 cum = a+b+c+d+e

5345.53

Rate per metre (a+b+c+d+e)/15


say

'12.38D

(ii)

5346.00

Using Batching Plant, Transit Mixer and Concrete Pump


a)

Material
tonne

6.33

5789.47

36647.37

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-004

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.16

185.07

29.61

L-12

Mason

day

0.38

208.99

79.42

L-10

Mazdoor for concreting

day

2.50

177.07

442.68

L-13

Mazdoor for breaking pile head, bending bars, cleaning


etc.
Machinery

day

1.00

177.07

177.07

L-13

Batching Plant @ 20 cum/hour

hour

0.75

2488.00

1866.00

P&M-002

Generator 125 KVA

hour

0.75

2307.00

1730.25

P&M-018

Loader (capacity 1 cum)

hour

1188.00

891.00

P&M-017

P&M-049

Cement

b)

c)

Labour

0.75

Transit Mixer ( capacity 4.0 cu.m )


Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

d)

Formwork @ 4 per cent on cost of concrete i.e. cost of


a) Material, b) Labour and c) Machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

hour

2.00

854.55

1709.10

tonne.km

37.5L

4.32

162.00

hour

0.75

234.36

Lead =1
km & P&M050
175.77 P&M-007
2232.49
14511.15
7255.58
79811.34

Cost for 15 cum = a+b+c+d+e


Rate per metre (a+b+c+d+e)/15

5320.76
say

331

5321.00

Sr No
12.39

Ref. to
MoRTH
Spec.
1100&17
00

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Levelling Course for Pile cap


Providing and laying of PCC M15 levelling course 100mm
thick below the pile cap.
Unit = cum
Taking output = 15 cum
a)

Material
tonne

4.13

5789.47

23910.53

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

40 mm aggregate

cum

8.10

758.35

6142.67

M-055

20 mm Aggregate

cum

4.05

862.50

3493.13

M-053

10 mm Aggregate

cum

1.35

655.60

885.06

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

208.99

313.49

L-10

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Cement

b)

c)

Labour

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

10786.25
5393.13
59324.40

Cost for 15 cum = a+b+c+d+e

3954.96

Rate per metre (a+b+c+d+e)/15


say

12.40

1600

3955.00

Supplying, Fitting and Placing un-coated HYSD bar


Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a)

Material
tonne

1.05

46059.03

48361.98

M-082

Kg

6.00

62.52

375.14

M-072

day

0.40

185.07

74.03

L-12

Blacksmith

day

2.00

234.29

468.58

L-02

Mazdoor

day

6.00

177.07

1062.42

L-13

HYSD bars including5 per cent overlaps and wastage


Binding wire
b)
Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

12585.54
6292.77
69220.46

Rate per MT (a+b+c+d)


say

12.41

1600

69220.00

Supplying, fitting and placing un-coated Mild steel


reinforcement complete in foundation as per drawing and
technical specification
Unit = 1 MT
Taking output = 1 MT
a)

Material
tonne

1.05

48690.69

51125.22

M-126

Kg

6.00

62.52

375.14

M-072

day

0.43

185.07

79.58

L-12

Blacksmith

day

2.25

234.29

527.15

L-02

Mazdoor

day

6.50

177.07

1150.96

L-13

MS bars including 5 per cent overlaps and wastage


Binding wire
b)
Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13314.51
6657.26
73229.82

Rate for per MT (a+b+c+d)

332

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs
say

333

Cost Rs
73230.00

Remarks/
Input ref.

RCD/SOR

CHAPTER-13

SUB-STRUCTURE
Sr No
13.1

Ref. to
MoRTH
Spec.

Description

1300 &
2200

Unit

Quantity

Rate Rs

Remarks/
Input ref.

Brick masonry work in 1:3 in sub-structure complete


excluding pointing and plastering, as per drawing and
Technical Specifications
Unit = cum
Taking output = 1 cum
a) Material
Bricks Ist class
Cement mortar 1:3 (Rate as in Item 12.6 A subanalysis)
b) Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of material
and labour
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum (a+b+c+d)

each
cum

day
day
day

500.00
0.24

4.33
3333.00

0.06
0.80
0.80

185.07
234.29
177.07

say
13.2

Cost Rs

1300 &
2200

Pointing with cement mortar (1:3 ) on brick work in


substructure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6 )
Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per 10 sqm (a+b+c+d)

cum

0.03

3333.00

day
day
day

0.04
0.50
0.50

185.07
234.29
177.07

2164.29
M-079
799.92 Item 12.6 (A)

11.10
187.43
141.66
165.22

L-12
L-11
L-13

867.40
433.70
4770.72
4771.00

99.99 Item 12.6 (A)

b)

say
13.3

13.4

Note
1300 &
2200

Scaffolding is already included in item 13.1


Plastering with cement mortar (1:3 ) on brick work in
sub-structure as per Technical Specifications
Unit = 10 sqm
Taking output = 10 sqm
a) Material
Cement mortar 1:3 (Rate as in Item 12.6)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per 10 sqm (a+b+c+d)

Note

1.Scaffolding is already included in item no. 13.1


2.The number of masons and Mazdoors already catered in
the cement mortar have been taken into account while
providing these categories in brick masonry, pointing and
plastering.

1400 &
2200

Stone masonry work in cement mortar 1:3 for


substructure complete as per drawing and Technical
Specifications
Random Rubble Masonry
( coursed/uncoursed )
Unit = cum
Taking output = 1 cum
a) Material
Stone
Through and bond stone
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 12.6)
b) Labour
Mate
Mason
Mazdoor
Add for scaffolding @ 5 per cent of cost of a)
Material and b) Labour
c) Overhead charges @ 0.25 on (a+b)

d)

cum

0.144

3333.00

day
day
day

0.04
0.50
0.50

185.07
234.29
177.07

7.40
117.15
88.54
78.27
39.13
430.48
430.00

479.95 Item 12.6 (A)


L-12
L-11
L-13

say

7.40
117.15
88.54
173.26
86.63
952.92
953.00

359.72
42.39

M-148
M-182

cum
No

1.00
7.00

359.72
6.06

cum

0.33

3333.00

day
day
day

0.10
1.20
1.20

185.07
234.29
177.07

1099.89 Item 12.6 (A)


18.51
281.15
212.48
100.71
528.71

Contractor's profit @ 0.1 on (a+b+c)

264.36

Rate per cum (a+b+c+d)

2907.92
say

253

L-12
L-11
L-13

2908.00

L-12
L-11
L-13

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

13.4

Description
B

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Coursed rubble masonry (first sort )


Unit = cum
Taking output = 1 cum
a) Material
Stone

cum

1.10

359.72

395.69

M-148

Through and bond stone

each

7.00

6.06

42.39

M-182

cum

0.30

3333.00

Mate

day

0.12

185.07

22.21

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

1.50

177.07

265.61

L-13

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6)
b)

c)

Add for scaffolding @ 5 per cent of cost of material


and labour
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

L-12

103.86
545.27
272.64

Rate per cum (a+b+c+d)


13.4

999.90 Item 12.6 (A)

Labour

2999.00
say

2999.00

Ashlar masonry ( first sort )


Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone

cum

1.11

360.24

399.87

M-169

Through and bond stone

each

7.00

6.06

42.39

M-182

cum

0.33

3333.00

Mate

day

0.20

185.07

37.01

Mason

day

2.50

234.29

585.73

L-11

Mazdoor

day

2.50

177.07

442.68

L-13

(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)


Cement mortar 1:3 (Rate as in Item 12.6)
b)

c)

Add for scaffolding @ 5 per cent of cost of a)


Material and b) Labour
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

684.49
342.24
3764.67
say

13.5

L-12

130.38

Rate per cum (a+b+c+d)


Note

1099.89 Item 12.6 (A)

Labour for masonry work

3765.00

The labour already considered in the cement mortar have


been taken into account while providing these categories in
the stone masonry works.
Plain/Reinforced cement concrete in sub-structure
complete as per drawing and Technical Specifications

1500,
1700 &
2200

Unit = cum
Taking output = 1 cum
A

PCC Grade M15

(p) Height upto 5m


Same as Item 12.8 (A) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (A)
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

2887.00 Item 12.8 (A)

10.00

288.70
793.93
396.96

Rate per cum (a+b+c+d+e+f)

4366.59
say

13.5

4367.00

PCC Grade M20

(p) Height upto 5m


Same as Item 12.8 (B) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (B)
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3277.00 Item 12.8 (B)


PCC
10.00

327.70
901.18
450.59

Rate per cum (a+b+c+d+e+f)

4956.46
say

254

4956.00

Sr No
13.5

RCD/SOR

Ref. to
MoRTH
Spec.

Description
C

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

PCC Grade M25

(p) Height upto 5m


Same as Item 12.8 (D) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.75 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3597.00 Item 12.8 (D)

10.00

359.70
989.18
494.59

Rate per cum (a+b+c+d+e+f)

5440.46
say

13.5 C
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3538.00 Item 12.8 (D)

10.00

353.80
972.95
486.48

Rate per cum (a+b+c+d+e+f)

5351.23
say

13.5 C

5440.00

5351.00

(q) Height 5m to 10m


Same as Item 12.8 (D) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.75 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3597.00 Item 12.8 (D)

12.00

431.64

2.00

71.94
1025.15
512.57

Rate per cum (a+b+c+d+e+f)

5638.30
say

13.5 C
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3538.00 Item 12.8 (D)

12.00

424.56

2.00

70.76
1008.33
504.17

Rate per cum (a+b+c+d+e+f)

5545.82
say

13.5 C

(r)

5638.00

5546.00

Height above 10m


Same as Item 12.8 (D) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.75 per cent of cost of
material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3597.00 Item 12.8 (D)

15.00

539.55

4.00

143.88
1070.11
535.05

Rate per cum (a+b+c+d+e+f)

5885.59
say

255

5886.00

Sr No
13.5 C
(r)

RCD/SOR

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (D) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

15.00

530.70

4.00

141.52
1052.56
526.28
5789.05
say

Remarks/
Input ref.

3538.00 Item 12.8 (D)

Rate per cum (a+b+c+d+e+f)


13.5

Cost Rs

5789.00

PCC Grade M30

(p) Height upto 5m


Same as Item 12.8 (F) upto 5 m height with the only change
that the provision of form work shall be 10 per cent instead
of 3.50 per cent of cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3632.00 Item 12.8 (F)

10.00

363.20
998.80
499.40

Rate per cum (a+b+c+d+e+f)

5493.40
say

13.5 D
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3569.00 Item 12.8 (F)

10.00

356.90
981.48
490.74

Rate per cum (a+b+c+d+e+f)

5398.11
say

13.5 D

5493.00

5398.00

(q) Height 5m to 10m


Same as Item 12.8 (F) with the following changes: (i) Add 2
per cent of cost of material, Labour and machinery
excluding form work to cater for extra lift. (ii) The provision of
form work shall be 12 per cent instead of 3.50 per cent of
cost of material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3632.00 Item 12.8 (F)

12.00

435.84

2.00

72.64
1035.12
517.56

Rate per cum (a+b+c+d+e+f)

5693.16
say

13.5 D
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3569.00 Item 12.8 (F)

12.00

428.28

2.00

71.38
1017.17
508.58

Rate per cum (a+b+c+d+e+f)

5594.41
say

13.5 D

(r)

5693.00

Height above 10m


Same as Item 12.8 (F) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 3.50 per cent of cost of
material, labour and machinery

256

5594.00

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

15.00

544.80

4.00

145.28
1080.52
540.26
5942.86
say

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (F) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

15.00

535.35

4.00

142.76
1061.78
530.89
5839.78
say

5943.00

3569.00 Item 12.8 (F)

Rate per cum (a+b+c+d+e+f)


13.5

Remarks/
Input ref.

3632.00 Item 12.8 (F)

Rate per cum (a+b+c+d+e+f)


13.5 D
(r)

Cost Rs

5840.00

RCC Grade M20

(p) Height upto 5m


Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3297.00 Item 12.8 (C)

10.00

329.70
906.68
453.34

Rate per cum (a+b+c+d+e+f)

4986.71
say

13.5 E
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3234.00 Item 12.8 (C)

10.00

323.40
889.35
444.68

Rate per cum (a+b+c+d+e+f)

4891.43
say

13.5 E

4987.00

4891.00

(q) Height 5m to 10m


For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 12 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3297.00 Item 12.8 (C)

12.00

395.64

2.00

65.94
939.65
469.82

Rate per cum (a+b+c+d+e+f)

5168.05
say

13.5 E
(q)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift

257

5168.00

3234.00 Item 12.8 (C)

12.00

388.08

2.00

64.68

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

460.85
5069.30
say

(r)

Remarks/
Input ref.

921.69

Rate per cum (a+b+c+d+e+f)


13.5 E

Cost Rs

5069.00

Height above 10m


Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of
material, labour and machinery.

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3297.00 Item 12.8 (C)

15.00

494.55

4.00

131.88
980.86
490.43

Rate per cum (a+b+c+d+e+f)

5394.72
say

13.5 E
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (C) Case II
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3234.00 Item 12.8 (C)

15.00

485.10

4.00

129.36
962.12
481.06

Rate per cum (a+b+c+d+e+f)

5291.63
say

13.5

5395.00

5292.00

RCC Grade M25

(p) Height upto 5m


Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3621.00 Item 12.8 (E)

10.00

362.10
995.78
497.89

Rate per cum (a+b+c+d+e+f)

5476.76
say

13.5 F
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3560.00 Item 12.8 (E)


DIR used item

10.00

356.00
979.00
489.50

Rate per cum (a+b+c+d+e+f)

5384.50
say

13.5 F

5477.00

5385.00

(q) Height 5m to 10m


For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 11.8 per cent of cost of material, labour and
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift

258

3621.00 Item 12.8 (E)

11.80

427.28

1.80

65.18

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

514.18
5656.00
say

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II

5656.00

3560.00 Item 12.8 (E)


DIR used item

d) formwork

e)

Add 11.8 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

11.80

420.08

1.80

64.08
1011.04
505.52

Rate per cum (a+b+c+d+e+f)

5560.72
say

13.5 F

(r)

Remarks/
Input ref.

1028.36

Rate per cum (a+b+c+d+e+f)


13.5 F
(q)

Cost Rs

5561.00

Height above 10m


For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case I
d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3621.00 Item 12.8 (E)

15.00

543.15

4.00

144.84
1077.25
538.62

Rate per cum (a+b+c+d+e+f)

5924.86
say

13.5 F
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (E) Case II

5925.00

3560.00 Item 12.8 (E)


DIR used item

d) formwork

e)

Add 15 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

15.00

534.00

4.00

142.40
1059.10
529.55

Rate per cum (a+b+c+d+e+f)

5825.05
say

13.5

5825.00

RCC Grade M30

(p) Height upto 5m


Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3640.00 Item 12.8 (G)

10.00

364.00
1001.00
500.50

Rate per cum (a+b+c+d+e+f)

5505.50
say

13.5 G
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5506.00

3580.00 Item 12.8 (G)

10.00

358.00
984.50
492.25

Rate per cum (a+b+c+d+e+f)

5414.75
say

259

5415.00

Sr No
13.5 G

RCD/SOR

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

e)

Add 11.5 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3640.00 Item 12.8 (G)

11.50

418.60

1.60

58.24
1029.21
514.61

Rate per cum (a+b+c+d+e+f)

5660.66
say

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 11.5 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

11.50

411.70

1.60

57.28
1012.25
506.12
5567.35
say

(r)

5661.00

3580.00 Item 12.8 (G)

Rate per cum (a+b+c+d+e+f)


13.5 G

Remarks/
Input ref.

(q) Height 5m to 10m


For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

13.5 G
(q)

Cost Rs

5567.00

Height above 10m


For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case I
d) formwork

e)

Add 14 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3640.00 Item 12.8 (G)

14.00

509.60

3.50

127.40
1069.25
534.63

Rate per cum (a+b+c+d+e+f)

5880.88
say

13.5 G
(r)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (G) Case II
d) formwork

e)

Add 14 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3580.00 Item 12.8 (G)

14.00

501.20

3.50

125.30
1051.63
525.81

Rate per cum (a+b+c+d+e+f)

5783.94
say

13.5

5881.00

5784.00

RCC Grade M35

(p) Height upto 5m


Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 10 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3729.00 Item 12.8 (H)


Case I
10.00

372.90
1025.48
512.74

Rate per cum (a+b+c+d+e+f)

5640.11
say

13.5 H
(p)

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
260

5640.00

3859.00 Item 12.8 (H)

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.
DIR used item

d) formwork
Add 10 per cent of cost of material, labour and
machinery (a+b+c) for Formwork

261

10.00

385.90

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Unit

Quantity

Rate Rs

Remarks/
Input ref.

1061.23
530.61

Rate per cum (a+b+c+d+e+f)

5836.74
say

13.5 H

Cost Rs

(q) Height 5m to 10m

5837.00
5412.00

For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 11 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3729.00 Item 12.8 (H)


Case I
11.00

410.19

1.40

52.21
1047.85
523.92

Rate per cum (a+b+c+d+e+f)

5763.17
say

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

13.5 H
(q)

e)

Add 11 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3859.00 Item 12.8 (H)

11.00

424.49

1.40

54.03
1084.38
542.19

Rate per cum (a+b+c+d+e+f)

5964.08
say

13.5 H

(r)

Height above 10m

5964.00
5530.00

For height, above 10m, add 3 per cent of cost as above


excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case I
d) formwork

e)

Add 13 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

3729.00 Item 12.8 (H)


Case I
13.00

484.77

3.00

111.87
1081.41
540.71

Rate per cum (a+b+c+d+e+f)

5947.76
say

13.5 H
(r)

5763.00

Case With Batching Plant, Transit Mixer and Concrete Pump


II
Per Cum Basic Cost of Labour, Material & Machinery
(a+b+c) of Item 12.8 (H) Case II
d) formwork

e)

Add 13 per cent of cost of material, labour and


machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and
machinery excluding formwork to cater for extra lift
Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

5948.00

3859.00 Item 12.8 (H)

13.00

501.67

3.00

115.77
1119.11
559.56

Rate per cum (a+b+c+d+e+f)

6155.11
say

6155.00
5707.00

Note

The basic components of this analysis are the same as


those of items 13.8 (A to H). The only changes are as under:
a)
Ramps/Stairs: Extra expenditure on structures which
are more than 5 m high @ 2 per cent of cost for height upto
10 m and 4 per cent for heights above 10 m will be involved
for approaching the work spot by providing higher ramp/stair
case for use by the working parties.
b) The above mentioned percentages have been suitably
modified for different categories as cost for various
categories varies, whereas effort for access for same height
will be similar. As the cost of richer concrete is comparatively
more, the percentage to be added has been reduced to
maintain the same cost for extra efforts.

262

Sr No
13.6

RCD/SOR

Ref. to
MoRTH
Spec.

Description

Section
1600 &
2200

Supplying, fitting and placing HYSD bar reinforcement in


sub-structure complete as per drawing and Technical
Specifications

Unit

263

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage
Binding wire
b)
Labour for cutting, bending, shifting to site, tying
and placing in position
Mate

tonne

1.05

46059.03

48361.98

M-082

kg

6.00

62.52

375.14

M-072

day

0.34

185.07

62.92

L-12

Blacksmith

day

2.00

234.29

468.58

L-02

Mazdoor

day

6.50

177.07

1150.96

L-13

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

12604.90
6302.45

Rate for per MT (a+b+c+d)


13.7

1600 &
2200

69326.93
say

69327.00

Supplying, fitting and placing Mild steel reinforcement


complete in sub-structure as per drawing and Technical
Specification
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage
Binding wire
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate

tonne

1.05

48690.69

51125.22

M-126

kg

6.00

62.52

375.14

M-072

day

0.28

185.07

51.82

L-12

Blacksmith

day

1.50

234.29

351.44

L-02

Mazdoor

day

5.50

177.07

973.89

L-13

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

13219.38
6609.69

Rate for per MT (a+b+c+d)


13.8

2706 &
2200

72706.57
say

72707.00

Providing weep holes in Brick masonry/Plain/


Reinforced concrete abutment, wing wall/ return wall
with 100 mm dia AC pipe, extending through the full
width of the structure with slope of 1V :20H towards
drawing foce. Complete as per drawing and Technical
Specifications
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent )

metre

31.50

50.28

1583.73

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp

each.

30.00

24.33

729.88

M-123

each.

10.00

5.03

50.28

M-056/10

cum

0.05

3333.00

Mate

day

0.03

185.07

5.55

Mason

day

0.50

234.29

117.15

L-11

Mazdoor

day

0.25

177.07

44.27

L-13

collar for AC pipe (average) taking 10% of above pipe


rate
Cement mortar 1:3 (Rate as in Item 12.6)
b)

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

L-12

674.38
337.19
3709.07

Rate per No. (a+b+c+d)/30

123.64
say

13.9

166.65 Item 12.6 (A)

Labour

Cost for 30 m = a+b+c+d

Note

M-056

124.00

1. In case of stone masonry, the size of the weep hole shall


be 150 mm x 80 mm or circular with 150 mm diameter.
2. For structure in stone masonry, the weep holes shall be
deemed to be included in the item of stone masonry work
and shall not be paid separately.
Back filling behind abutment, wing wall and return wall
complete as per drawing and Technical Specification

710.1.4.
of
IRC:78
& 2200

Unit = cum
Taking output = 10 cum
A

Granular material
a)

b)

Labour
Mate

day

0.28

185.07

51.82

L-12

Mazdoor

day

7.00

177.07

1239.49

L-13

cum

12.00

153.00

1836.00

M-009

hour

2.50

142.99

357.48

P&M-086

Material
Granular material

c)

Machinery
Plate compactor/power rammer
264

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description

Unit

Water Tanker

hour

265

Quantity
0.05

Rate Rs
111.24

Cost Rs
5.56

Remarks/
Input ref.
P&M-060

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description
d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Unit

Quantity

Rate Rs

436.29
4799.23

Rate per cum = (a+b+c+d+e)/10

479.92
say

b)

Labour
Mate

day

0.28

185.07

51.82

L-12

Mazdoor for filling, watering, ramming etc.

day

7.00

177.07

1239.49

L-13

cum

12.00

109.09

1309.04

M-006

Plate compactor/power rammer

hour

2.50

142.99

357.48

P&M-086

Water Tanker

hour

0.06

111.24

6.67

P&M-060

Material
Sand

c)

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

741.13

e)

Contractor's profit @ 0.1 on (a+b+c+d)

370.56

Cost for 10 cum of sandy backfill = a+b+c+d+e

4076.20

Rate per cum = (a+b+c+d+e)/10

407.62
say

710.1.4.
of
IRC:78
and
2200

480.00

Sandy material
a)

13.10

Remarks/
Input ref.

872.59

Cost for 10 cum of granular backfill = a+b+c+d+e

13.9

Cost Rs

408.00

Providing and laying of Filter media with granular


materials/stone crushed aggregates satisfying the
requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm
with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface
behind abutment, wing wall and return wall to the full
height compacted to a firm condition complete as per
drawing and Technical Specification.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate

day

0.32

185.07

59.22

L-12

Mazdoor for filling, watering, ramming etc.

day

7.00

177.07

1239.49

L-13

Mazdoor (Skilled)

day

1.00

206.99

206.99

L-15

7356.00

M-012

b)

Material
cum

12.00

613.00

c)

Filter media of stone aggregate conforming to clause


2504.2.2. of MoRTH specifications.
Machinery
Water Tanker of 6 KL capacity

hour

0.06

111.24

d)

Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

12194.02

Rate per cum = (a+b+c+d+e)/10

1219.40
say

2000,
1000 &
2200

P&M-060

1108.55

cost for 10 cum of Fiter Media = a+b+c+d+e

13.11

6.67
2217.09

1219.00

Supplying, fitting and fixing in position true to line and


level cast steel rocker bearing conforming to IRC: 83(Pt.1) section IX and clause 2003 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a)

Labour
Mate

day

0.06

185.07

11.10

L-12

Mazdoor (Skilled)

day

0.50

206.99

103.50

L-15

Mazdoor

day

1.00

177.07

177.07

L-13

each.

1.00

55883.28

55883.28

b)

Material

c)

Cast steel rocker bearing assembly of 250 tonne


design load capacity duly painted complete with all its
components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts, lifting arrangements,
grease and other consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

558.83

14183.44
7091.72

cost for 250 tonnes capacity bearing = a+b+c+d

78008.94

Rate per tonne capacity = (a+b+c+d)/250

312.04
say

266

312.00

M-065

Sr No
13.12

RCD/SOR

Ref. to
MoRTH
Spec.
2000 ,
1000 &
2200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Supplying, fitting and fixing in position true to line and


level forged steel roller bearing conforming to IRC:
83(Pt.-1) section IX and clause 2003 of MoRTH
specifications complete including all accessories as per
drawing and Technical Specifications.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis
a)

b)

Labour
Mate

day

0.06

185.07

11.10

L-12

Mazdoor

day

1.00

177.07

177.07

L-13

Mazdoor (Skilled)

day

0.50

206.99

103.50

L-15

each.

1.00

37256.21

37256.21

Material
Forged steel roller bearing of 250 tonne design load
capacity duly painted complete with all its components
as per drawing and specifications
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts, lifting arrangements,
grease and other consumables.

372.56

c)

Overhead charges @ 0.25 on (a+b)

9480.11

d)

Contractor's profit @ 0.1 on (a+b+c)

4740.06

cost for 250 tonnes capacity bearing = a+b+c+d

52140.61

Rate per tonne capacity = (a+b+c+d)/250

208.56
say

13.13

2000 &
2200

M-067

209.00

Supplying, fitting and fixing in position true to line and


level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per
drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE)
and clause 2004 of
MoRTH Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this analysis
a)

b)

Labour
Mate

day

0.06

185.07

11.10

L-12

Mazdoor

day

1.00

177.07

177.07

L-13

Mazdoor (Skilled)

day

0.50

206.99

103.50

L-15

each.

1.00

#VALUE!

#VALUE!

M-069

Material
PTFE sliding plate bearing assembly of 80 tonnes
design load capacity duly painted complete with all its
components as per drawing and Technical
Specifications
Add 1 per cent for foundation anchorage bolts and
consumables.

267

#VALUE!

Sr No

RCD/SOR

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

c)

Overhead charges @ 0.25 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

cost for 80 tonnes capacity bearing = a+b+c+d

#VALUE!
say

2000 &
2200

Remarks/
Input ref.

#VALUE!

Rate per tonne capacity = (a+b+c+d)/80


13.14

Cost Rs

#VALUE!

Supplying, fitting and fixing in position true to line and


level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96
mm for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a)

b)

Labour
Mate

day

0.06

185.07

11.10

L-12

Mazdoor

day

1.00

177.07

177.07

L-13

Mazdoor (Skilled)

day

0.50

206.99

103.50

L-15

19200.00

0.50

9623.13

M-066

Material
Elastomeric bearing assembly consisting of 7 layers of
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete
with all components as per drawing and Technical
Specifications.

cucm

c)

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts and consumables.
Overhead charges @ 0.25 on (a+b)

96.23

d)

Contractor's profit @ 0.1 on (a+b+c)

1251.38

cost for 19200cc of elastomeric bearing = a+b+c+d

13765.17

2502.76

Rate per cc of elastomeric bearing = (a+b+c+d)/19200

0.72
say

13.15

2000 &
2200

0.72

Supplying, fitting and fixing in position true to line and


level sliding plate bearing with stainless steel plate
sliding on stainless steel plate with mild steel matrix
complete including all accessories as per drawing and
Technical Specifications.
Unit: one tonne capacity
Considering the sliding bearing of 80 tonnes design capacity
for this analysis.
a) Labour
Mate

day

0.04

185.07

7.40

L-12

Mazdoor

day

0.75

177.07

132.80

L-13

Mazdoor (Skilled)

day

0.35

206.99

72.45

L-15

each.

1.00

22579.27

22579.27

b)

Material

c)

Supply of sliding plate bearing of 80 tonne design


capacity complete as per drawings and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for
foundation anchorage bolts and consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

2877.21

cost for 80 tonnes of capacity bearing = a+b+c+d

31649.36

225.79
5754.43

Rate per tonne Capacity =(a+b+c+d) / 80

395.62
say

268

396.00

M-070

Sr No
13.16

RCD/SOR

Ref. to
MoRTH
Spec.
2000 &
2200

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Supplying, fitting and fixing in position true to line and level


POT-PTFE bearing consisting of a metal piston supported by
a disc or unreinforced elastomer confined within a metal
cylinder, sealing rings, dust seals, PTFE surface sliding
against stainless steel mating surface, complete assembly to
be of cast steel/fabricated structural steel, metal and
elastomer elements to be as per IRC: 83 part-I & II
respectively and other parts conforming to BS: 5400, section
9.1 & 9.2 and clause 2006 of MoRTH Specifications
complete as per drawing and approved Technical
Specifications.
Unit: one tonne capacity

387.20

Considering a Pot bearing assembly of 250 tonne capacity


for this analysis.
a) Labour

b)

Mate

day

0.08

185.07

14.81

L-12

Mazdoor

day

1.50

177.07

265.61

L-13

Mazdoor (Skilled)

day

0.50

206.99

103.50

L-15

each.

1.00

31752.36

31752.36

Material
Pot type bearing assembly consisting of a metal piston
supported by a disc, PTFE pads providing sliding
surfaces against stainless steel mating together with
cast steel assemblies/fabricated structural steel
assemblies duly painted with all components as per
clause 2006 and complete as per drawings and
Technical Specifications.

c)

Add 1 per cent of cost of bearing assembly for


foundation anchorage bolts and consumables.
Overhead charges @ 0.25 on (a+b)

8113.45

d)

Contractor's profit @ 0.1 on (a+b+c)

4056.72

317.52

cost for 250 tonnes capacity bearing = a+b+c+d

44623.96

Rate per tonne capacity = (a+b+c+d)/250

178.50
say

269

178.00

M-068

CHAPTER-14

SUPER-STRUCTURE
Sr No
14.1

Ref. to
MoRTH
Spec.

Description

1500
&1600
1700

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Cement

tonne

5.12

5789.47

29642.11

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Furnishing and Placing Reinforced/ Prestressed cement


concrete in super-structure as per drawing and Technical
Specification
A

RCC Grade M20

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)

for 15
cum

48921.00

For formwork and staging add the following:


14.1A Case
I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

48921.00

for 15
20.00

9784.20
14676.30
7338.15

Cost for 15 cum = a+b+c+d+e+f

80719.65

Rate per cum = (a+b+c+d+e+f)/15

5381.31
say

14.1A Case
I (i)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

48921.00
25.00

12230.25
15287.81
7643.91

Cost for 15 cum = a+b+c+d+e+f

84082.97

Rate per cum = (a+b+c+d+e+f)/15

5605.53
say

14.1A
Case I (i)

(r)

for 15

48921.00
30.00

14676.30

e)

Overhead charges @ 0.25 on (a+b+c+d)

15899.33

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

7949.66

Cost for 15 cum = a+b+c+d+e+f

87446.29

Rate per cum = (a+b+c+d+e+f)/15

5829.75
say

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)


(p)

5606.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A Case
I

5381.00

Height 5m to 10m

Height upto 5m

268

5830.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

for 15
25.00

12230.25
15287.81
7643.91
84082.97

Rate per cum = (a+b+c+d+e+f)/15

5605.53
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

48921.00
30.00

14676.30
15899.33
7949.66

Cost for 15 cum = a+b+c+d+e+f

87446.29

Rate per cum = (a+b+c+d+e+f)/15

5829.75
say

(r)

5830.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

for 15

48921.00
35.00

17122.35

e)

Overhead charges @ 0.25 on (a+b+c+d)

16510.84

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8255.42

Cost for 15 cum = a+b+c+d+e+f

90809.61

Rate per cum = (a+b+c+d+e+f)/15


14.1A

5606.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A
Case I (ii)

Remarks/
Input ref.

48921.00

Cost for 15 cum = a+b+c+d+e+f

14.1A Case
I (ii)

Cost Rs

6053.97
say

6054.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

40.92

5789.47

236905.26

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1A Case
II

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)
269

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

383931.00

for 120

383931.00
20.00

76786.20

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

115179.30
57589.65

Cost for 120 cum = a+b+c+d+e+f

633486.15

Rate per cum = (a+b+c+d+e+f)/120

5279.05
say

14.1A
Case II (i)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

383931.00
25.00

95982.75
119978.44
59989.22

Cost for 120 cum = a+b+c+d+e+f

659881.41

Rate per cum = (a+b+c+d+e+f)/120

5499.01
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

383931.00
30.00

115179.30
124777.58
62388.79

Cost for 120 cum = a+b+c+d+e+f

686276.66

Rate per cum = (a+b+c+d+e+f)/120

5718.97
say

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

383931.00
25.00

95982.75
119978.44
59989.22

Cost for 120 cum = a+b+c+d+e+f

659881.41

Rate per cum = (a+b+c+d+e+f)/120

5499.01
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

383931.00
30.00

115179.30
124777.58
62388.79

Cost for 120 cum = a+b+c+d+e+f

686276.66

Rate per cum = (a+b+c+d+e+f)/120

5718.97
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

383931.00
35.00

134375.85
129576.71
64788.36

Cost for 120 cum = a+b+c+d+e+f

712671.92

Rate per cum = (a+b+c+d+e+f)/120

5938.93
say

5719.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

5499.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A Case
II (ii)

5719.00

(ii) For T-beam & slab, 25-35 per cent of (a+b+c)


(p)

14.1A Case
II (ii)

5499.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1A Case
II

5279.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1A
Case II (i)

Cost Rs

RCC Grade M25

Case I Using Concrete Mixer


Unit = 1 cum
270

5939.00

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Cement

tonne

5.99

5789.47

34678.95

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.86

185.07

159.16

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Taking output = 15 cum


a)

b)

c)

Material

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)

for 15
cum

53958.00

For formwork and staging add the following:


14.1B Case
I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

53958.00

for 15
20.00

10791.60
16187.40
8093.70

Cost for 15 cum = a+b+c+d+e+f

89030.70

Rate per cum = (a+b+c+d+e+f)/15

5935.38
say

14.1B
Case I (i)

(q)

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

53958.00
25.00

13489.50
16861.88
8430.94

Cost for 15 cum = a+b+c+d+e+f

92740.31

Rate per cum = (a+b+c+d+e+f)/15

6182.69
say

14.1B
Case I (i)

(r)

6183.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

53958.00
30.00

16187.40
17536.35
8768.18

Cost for 15 cum = a+b+c+d+e+f

96449.93

Rate per cum = (a+b+c+d+e+f)/15

6430.00
say

14.1B Case
I

5935.00

Height 5m to 10m

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

for 15

6430.00

53958.00
25.00

13489.50

e)

Overhead charges @ 0.25 on (a+b+c+d)

16861.88

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8430.94

Cost for 15 cum = a+b+c+d+e+f

92740.31

Rate per cum = (a+b+c+d+e+f)/15

6182.69
say

271

6183.00

Sr No
14.1B Case
I (ii)

Ref. to
MoRTH
Spec.

Description
(q)

Unit

Quantity

Rate Rs

for 15

53958.00
30.00

16187.40

e)

Overhead charges @ 0.25 on (a+b+c+d)

17536.35

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8768.18

Cost for 15 cum = a+b+c+d+e+f

96449.93

Rate per cum = (a+b+c+d+e+f)/15

6430.00
say

(r)

6430.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

for 15

53958.00
35.00

18885.30

e)

Overhead charges @ 0.25 on (a+b+c+d)

18210.83

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

9105.41

Cost for 15 cum = a+b+c+d+e+f

100159.54

Rate per cum = (a+b+c+d+e+f)/15


14.1B

Remarks/
Input ref.

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1B Case
I (ii)

Cost Rs

6677.30
say

6677.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

47.95

5789.47

277605.26

M-081

Coarse sand

cum

54.20

203.75

11043.49

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.84

185.07

155.46

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

18.00

177.07

3187.26

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1B Case
II

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)

for 120

424671.00
20.00

84934.20

e)

Overhead charges @ 0.25 on (a+b+c+d)

127401.30

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

63700.65
700707.15

Rate per cum = (a+b+c+d+e+f)/120

5839.23
say

(q)

1406.16

424671.00

Cost for 120 cum = a+b+c+d+e+f

14.1B Case
II (i)

1296.00 Lead =1 km
& P&M-050

Height 5m to 10m

272

5839.00

P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

for 120
25.00

106167.75
132709.69
66354.84
729903.28

Rate per cum = (a+b+c+d+e+f)/120

6082.53
say

(r)

d)

Formwork and staging 30 per cent of (a+b+c)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

424671.00
30.00

127401.30
138018.08
69009.04

Cost for 120 cum = a+b+c+d+e+f

759099.41

Rate per cum = (a+b+c+d+e+f)/120

6325.83
say

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

25.00

106167.75
132709.69
66354.84
729903.28

Rate per cum = (a+b+c+d+e+f)/120

6082.53
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

424671.00
30.00

127401.30
138018.08
69009.04

Cost for 120 cum = a+b+c+d+e+f

759099.41

Rate per cum = (a+b+c+d+e+f)/120

6325.83
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

424671.00

for 120
35.00

148634.85
143326.46
71663.23

Cost for 120 cum = a+b+c+d+e+f

788295.54

Rate per cum = (a+b+c+d+e+f)/120


C

6326.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

6083.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1B
Case II (ii)

6326.00

424671.00

for 120

Cost for 120 cum = a+b+c+d+e+f

14.1B
Case II (ii)

6083.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum

14.1B Case
II

Remarks/
Input ref.

424671.00

Cost for 120 cum = a+b+c+d+e+f

14.1B Case
II (i)

Cost Rs

6569.13
say

6569.00

RCC Grade M 30

Case I Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a)

Material
Cement

tonne

6.10

5789.47

35315.79

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

273

Sr No

Ref. to
MoRTH
Spec.

Description
b)

c)

Cost Rs

Quantity

Rate Rs

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

21.00

177.07

3718.47

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)

for 15
cum

54779.00

For formwork and staging add the following:


14.1C Case
I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

54779.00
20.00

10955.80
16433.70
8216.85

Cost for 15 cum = a+b+c+d+e+f

90385.35

Rate per cum = (a+b+c+d+e+f)/15

6025.69
say

14.1C
Case I (i)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

54779.00

for 15
25.00

13694.75
17118.44
8559.22

Cost for 15 cum = a+b+c+d+e+f

94151.41

Rate per cum = (a+b+c+d+e+f)/15

6276.76
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

54779.00
30.00

16433.70
17803.18
8901.59

Cost for 15 cum = a+b+c+d+e+f

97917.46

Rate per cum = (a+b+c+d+e+f)/15

6527.83
say

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

25.00

13694.75
17118.44
8559.22
94151.41

Rate per cum = (a+b+c+d+e+f)/15

6276.76
say

(q)

6528.00

54779.00

for 15

Cost for 15 cum = a+b+c+d+e+f

14.1C Case
I (ii)

6277.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C Case
I

6026.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1C
Case I (i)

Remarks/
Input ref.

Unit

6277.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

for 15

54779.00
30.00

16433.70

e)

Overhead charges @ 0.25 on (a+b+c+d)

17803.18

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

8901.59

274

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost for 15 cum = a+b+c+d+e+f

6527.83
say

(r)

6528.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

54779.00

for 15
35.00

19172.65

e)

Overhead charges @ 0.25 on (a+b+c+d)

18487.91

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

9243.96

Cost for 15 cum = a+b+c+d+e+f

101683.52

Rate per cum = (a+b+c+d+e+f)/15


14.1C

Remarks/
Input ref.

97917.46

Rate per cum = (a+b+c+d+e+f)/15


14.1C Case
I (ii)

Cost Rs

6778.90
say

6779.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump.


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

48.79

5789.47

282468.42

M-081

Coarse sand

cum

54.60

203.75

11124.99

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.88

185.07

162.86

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

19.00

177.07

3364.33

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader

hour

6.00

1188.00

7128.00

P&M-017

12818.25

P&M-049

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c) for
120 cum
For formwork and staging add the following:
14.1C Case
II

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

hour

15.00

854.55

tonne.km

300L

4.32

hour

6.00

234.36

429801.00

for 120

429801.00
20.00

85960.20
128940.30
64470.15

Cost for 120 cum = a+b+c+d+e+f

709171.65

Rate per cum = (a+b+c+d+e+f)/120

5909.76
say

14.1C Case
II (i)

(q)

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

5910.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

429801.00

for 120
25.00

107450.25
134312.81
67156.41

Cost for 120 cum = a+b+c+d+e+f

738720.47

Rate per cum = (a+b+c+d+e+f)/120

6156.00
say
275

6156.00

Sr No
14.1C Case
II (i)

Ref. to
MoRTH
Spec.

Description
(r)

Unit

Quantity

Rate Rs

for 120

429801.00
30.00

128940.30

e)

Overhead charges @ 0.25 on (a+b+c+d)

139685.33

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

69842.66

Cost for 120 cum = a+b+c+d+e+f

768269.29

Rate per cum = (a+b+c+d+e+f)/120

6402.24
say

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120
25.00

107450.25
134312.81
67156.41
738720.47

Rate per cum = (a+b+c+d+e+f)/120

6156.00
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

429801.00
30.00

128940.30
139685.33
69842.66

Cost for 120 cum = a+b+c+d+e+f

768269.29

Rate per cum = (a+b+c+d+e+f)/120

6402.24
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

429801.00

for 120
35.00

150430.35
145057.84
72528.92

Cost for 120 cum = a+b+c+d+e+f

797818.11

Rate per cum = (a+b+c+d+e+f)/120


D

6402.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

14.1

6156.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C Case
II (ii)

6402.00

429801.00

Cost for 120 cum = a+b+c+d+e+f

14.1C Case
II (ii)

Remarks/
Input ref.

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1C Case
II

Cost Rs

6648.48
say

6648.00

RCC/PSC Grade M35

Case I Using Concrete Mixer.


Unit = 1 cum
Taking output = 15 cum
a)

b)

c)

Material
Cement

tonne

6.33

5789.47

36647.37

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

Mate

day

0.90

185.07

166.56

L-12

Mason

day

1.50

234.29

351.44

L-11

Mazdoor

day

21.00

177.07

3718.47

L-13

hour

6.00

211.68

1270.08

P&M-009

6.00

342.36

2054.16

P&M-079

Labour

Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA

hour

Basic Cost of Labour, Material & Machinery (a+b+c)


276

for 15
cum

56110.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost Rs

For formwork and staging add the following:


14.1D Case
I

(i)

For solid slab super-structure, 18-28 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 18 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

56110.00

for 15
18.00

10099.80
16552.45
8276.23

Cost for 15 cum = a+b+c+d+e+f

91038.48

Rate per cum = (a+b+c+d+e+f)/15

6069.23
say

14.1D
Case I (i)

(q)

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 23 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

56110.00

for 15
23.00

12905.30
17253.83
8626.91

Cost for 15 cum = a+b+c+d+e+f

94896.04

Rate per cum = (a+b+c+d+e+f)/15

6326.40
say

14.1D
Case I (i)

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

56110.00
28.00

15710.80
17955.20
8977.60

Cost for 15 cum = a+b+c+d+e+f

98753.60

Rate per cum = (a+b+c+d+e+f)/15

6583.57
say

(ii)

For T-beam & slab, 23-33 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 23 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15
23.00

12905.30
17253.83
8626.91
94896.04

Rate per cum = (a+b+c+d+e+f)/15

6326.40
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

56110.00
28.00

15710.80
17955.20
8977.60

Cost for 15 cum = a+b+c+d+e+f

98753.60

Rate per cum = (a+b+c+d+e+f)/15

6583.57
say

(r)

6326.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D Case
I (ii)

6584.00

56110.00

Cost for 15 cum = a+b+c+d+e+f

14.1D Case
I (ii)

6326.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D Case
I

6069.00

6584.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 33 per cent of (a+b+c)

56110.00

for 15
33.00

18516.30

e)

Overhead charges @ 0.25 on (a+b+c+d)

18656.58

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

9328.29

277

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Cost for 15 cum = a+b+c+d+e+f

6840.74
say

(iii)
(p)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

56110.00
38.00

21321.80
19357.95
9678.98

Cost for 15 cum = a+b+c+d+e+f

106468.73

Rate per cum = (a+b+c+d+e+f)/15

7097.92
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

56110.00
48.00

26932.80
20760.70
10380.35

Cost for 15 cum = a+b+c+d+e+f

114183.85

Rate per cum = (a+b+c+d+e+f)/15

7612.26
say

(r)

7098.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 48 per cent of (a+b+c)

14.1D
Case I (iii)

6841.00

For box girder and balanced cantilever, 38-58 per cent of


cost of concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 38 per cent of (a+b+c)

14.1D
Case I (iii)

Remarks/
Input ref.

102611.16

Rate per cum = (a+b+c+d+e+f)/15


14.1D Case
I

Cost Rs

7612.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 58 per cent of (a+b+c)

for 15

56110.00
58.00

32543.80

e)

Overhead charges @ 0.25 on (a+b+c+d)

22163.45

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

11081.73

Cost for 15 cum = a+b+c+d+e+f

121898.98

Rate per cum = (a+b+c+d+e+f)/15

8126.60
say

8127.00

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

b)

c)

Material
Cement

tonne

50.64

5789.47

293178.95

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

Mate

day

0.88

185.07

162.86

Mason

day

3.00

234.29

702.87

L-11

Mazdoor

day

19.00

177.07

3364.33

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
278

440389.00

1296.00 Lead =1 km
& P&M-050
1406.16

P&M-007

Sr No
14.1D Case
II

Ref. to
MoRTH
Spec.

Description

Unit

(i)

For solid slab super-structure, 18-28 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 18 per cent of (a+b+c)

Quantity

Rate Rs

440389.00

for 120
18.00

79270.02

e)

Overhead charges @ 0.25 on (a+b+c+d)

129914.76

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

64957.38

Cost for 120 cum = a+b+c+d+e+f

714531.15

Rate per cum = (a+b+c+d+e+f)/120

5954.43
say

14.1D Case
II (i)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

440389.00
23.00

101289.47
135419.62
67709.81

Cost for 120 cum = a+b+c+d+e+f

744807.90

Rate per cum = (a+b+c+d+e+f)/120

6206.73
say

(r)

for 120

440389.00
28.00

123308.92

e)

Overhead charges @ 0.25 on (a+b+c+d)

140924.48

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

70462.24

Cost for 120 cum = a+b+c+d+e+f

775084.64

Rate per cum = (a+b+c+d+e+f)/120

6459.04
say

(ii)

For T-beam & slab, 23-33 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 23 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

23.00

101289.47
135419.62
67709.81
744807.90

Rate per cum = (a+b+c+d+e+f)/120

6206.73
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

440389.00
28.00

123308.92
140924.48
70462.24

Cost for 120 cum = a+b+c+d+e+f

775084.64

Rate per cum = (a+b+c+d+e+f)/120

6459.04
say

(r)

6207.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D
Case II (ii)

6459.00

440389.00

for 120

Cost for 120 cum = a+b+c+d+e+f

14.1D
Case II (ii)

6207.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1D Case
II

5954.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 23 per cent of (a+b+c)

14.1D Case
II (i)

Cost Rs

6459.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 33 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Cost for 120 cum = a+b+c+d+e+f

for 120

440389.00
33.00

145328.37
146429.34
73214.67
805361.38

279

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per cum = (a+b+c+d+e+f)/120


(iii)
(p)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

440389.00
38.00

167347.82
151934.21
75967.10

Cost for 120 cum = a+b+c+d+e+f

835638.13

Rate per cum = (a+b+c+d+e+f)/120

6963.65
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

440389.00
48.00

211386.72
162943.93
81471.97

Cost for 120 cum = a+b+c+d+e+f

896191.62

Rate per cum = (a+b+c+d+e+f)/120

7468.26
say

(r)

for 120

440389.00
58.00

255425.62

e)

Overhead charges @ 0.25 on (a+b+c+d)

173953.66

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

86976.83

Cost for 120 cum = a+b+c+d+e+f

956745.10

Rate per cum = (a+b+c+d+e+f)/120


E

7468.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 58 per cent of (a+b+c)

14.1

6964.00

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 48 per cent of (a+b+c)

14.1D Case
II (iii)

6711.00

For box girder and balanced cantilever, 38-58 per cent of


cost of concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 38 per cent of (a+b+c)

14.1D Case
II (iii)

Remarks/
Input ref.

6711.34
say

14.1D Case
II

Cost Rs

7972.88
say

7973.00

PSC Grade M-40

Case 1 Using concrete mixer.


Unit = 1 cum
Taking output = 15 cum
a)

Material
Cement

tonne

6.45

5789.47

37342.11

M-081

Coarse sand

cum

6.75

203.75

1375.34

M-005

20 mm Aggregate

cum

8.10

862.50

6986.27

M-053

10 mm Aggregate

cum

5.40

655.60

3540.26

M-051

kg

25.80

112.77

2909.49

M-180

Mate

day

0.96

185.07

177.67

L-12

Mason

day

2.00

234.29

468.58

L-11

Mazdoor

day

22.00

177.07

3895.54

L-13

Concrete mixer (cap. 0.40/0.28 cum)

hour

6.00

211.68

1270.08

P&M-009

Generator 33 KVA

hour

6.00

342.36

2054.16

P&M-079

Admixture @ 0.4 per cent of cement


b)

c)

Labour

Machinery

Basic Cost of Labour, Material & Machinery (a+b+c)

for 15
cum

For formwork and staging add the following:


14.1E Case
I

(i)

For solid slab super-structure, 20-30 per cent of (a+b+c)

(p)

Height upto 5m

280

60020.00

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 20 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

for 15

60020.00
20.00

12004.00
18006.00
9003.00

Cost for 15 cum = a+b+c+d+e+f

99033.00

Rate per cum = (a+b+c+d+e+f)/15

6602.20
say

14.1E
Case I (i)

(q)

for 15

60020.00
25.00

15005.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

18756.25

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

9378.13

Cost for 15 cum = a+b+c+d+e+f

103159.38

Rate per cum = (a+b+c+d+e+f)/15

6877.29
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 15

60020.00
30.00

18006.00
19506.50
9753.25

Cost for 15 cum = a+b+c+d+e+f

107285.75

Rate per cum = (a+b+c+d+e+f)/15

7152.38
say

(ii)

For T-beam & slab, 25-35 per cent of (a+b+c)

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

for 15
25.00

15005.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

18756.25

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

9378.13
103159.38

Rate per cum = (a+b+c+d+e+f)/15

6877.29
say

(q)

for 15

60020.00
30.00

18006.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

19506.50

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

9753.25

Cost for 15 cum = a+b+c+d+e+f

107285.75

Rate per cum = (a+b+c+d+e+f)/15

7152.38
say

(r)

6877.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1E Case
I (ii)

7152.00

60020.00

Cost for 15 cum = a+b+c+d+e+f

14.1E Case
I (ii)

6877.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 30 per cent of (a+b+c)

14.1E Case
I

6602.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 25 per cent of (a+b+c)

14.1E
Case I (i)

Cost Rs

7152.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

for 15

60020.00
35.00

21007.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

20256.75

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

10128.38

Cost for 15 cum = a+b+c+d+e+f

111412.13

Rate per cum = (a+b+c+d+e+f)/15

7427.48
say
281

7427.00

Remarks/
Input ref.

Sr No
14.1E

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Cement

tonne

51.60

5789.47

298736.84

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

kg

206.40

112.77

23275.94

M-180

Mate

day

0.94

185.07

173.97

Mason

day

3.50

234.29

820.02

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Case II Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a)

Material

Admixture @ 0.4 per cent of cement


b)

c)

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for 120


cum
For formwork and staging add the following:
14.1E Case
II

(i)
(p)

469528.00

For solid/voided slab super-structure, 18-28 per cent of


(a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 cum
d)

Formwork and staging 18 per cent of (a+b+c)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

469528.00
18.00

84515.04
138510.76
69255.38

Cost for 15 cum = a+b+c+d+e+f

761809.18

Rate per cum = (a+b+c+d+e+f)/120

6348.41
say

14.1E Case
II (i)

(q)

for 120

469528.00
23.00

107991.44

e)

Overhead charges @ 0.25 on (a+b+c+d)

144379.86

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

72189.93

Cost for 120 cum = a+b+c+d+e+f

794089.23

Rate per cum = (a+b+c+d+e+f)/120

6617.41
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

469528.00
28.00

131467.84
150248.96
75124.48

Cost for 120 cum = a+b+c+d+e+f

826369.28

Rate per cum = (a+b+c+d+e+f)/120

6886.41
say

(ii)

6617.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1E Case
II

6348.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 23 per cent of (a+b+c)

14.1E Case
II (i)

1296.00 Lead =1 km
& P&M-050
1406.16 P&M-007

For T-beam & slab inclduing launching of precast girders by


launching truss upto 40 m, 23-33 per cent of cost of
concrete (a+b+c)
282

6886.00

Sr No

Ref. to
MoRTH
Spec.

Description
(p)

Unit

Quantity

Rate Rs

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 23 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

469528.00
23.00

107991.44
144379.86
72189.93

Cost for 120 cum = a+b+c+d+e+f

794089.23

Rate per cum = (a+b+c+d+e+f)/120

6617.41
say

14.1E Case
II (ii)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

469528.00
28.00

131467.84
150248.96
75124.48

Cost for 120 cum = a+b+c+d+e+f

826369.28

Rate per cum = (a+b+c+d+e+f)/120

6886.41
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

469528.00
33.00

154944.24
156118.06
78059.03

Cost for 120 cum = a+b+c+d+e+f

858649.33

Rate per cum = (a+b+c+d+e+f)/120

7155.41
say

(iii)
(p)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

469528.00

for 120
38.00

178420.64
161987.16
80993.58

Cost for 120 cum = a+b+c+d+e+f

890929.38

Rate per cum = (a+b+c+d+e+f)/120

7424.41
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

469528.00
48.00

225373.44
173725.36
86862.68

Cost for 120 cum = a+b+c+d+e+f

955489.48

Rate per cum = (a+b+c+d+e+f)/120

7962.41
say

(r)

7424.00

Height 5m to 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 48 per cent of (a+b+c)

14.1E Case
II (iii)

7155.00

For cast-in-situ box girder, segment construction and


balanced cantilever, 38-58 per cent of cost of concrete.
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 38 per cent of (a+b+c)

14.1E Case
II (iii)

6886.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 33 per cent of (a+b+c)

14.1E Case
II

6617.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 28 per cent of (a+b+c)

14.1E
Case II (ii)

Cost Rs

7962.00

Height above 10m

Basic Cost of Labour, Material & Machinery (a+b+c)


cum
d) Formwork and staging 58 per cent of (a+b+c)

for 120

469528.00
58.00

272326.24

e)

Overhead charges @ 0.25 on (a+b+c+d)

185463.56

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

92731.78

Cost for 120 cum = a+b+c+d+e+f

1020049.58
283

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per cum = (a+b+c+d+e+f)/120


14.1F

Cost Rs

Remarks/
Input ref.

8500.41
say

8500.00

323052.63

M-081

PSC Grade M-45


Unit = 1 cum
Taking output = 120 cum
a)

Material
Cement

tonne

55.80

5789.47

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

kg

223.20

112.77

25170.50

M-180

Mate

day

0.94

185.07

173.97

Mason

day

3.50

234.29

820.02

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Admixture @ 0.4 per cent of cement


b)

c)

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1F

(i)
(p)

for 120

495738.00
16.00

79318.08

e)

Overhead charges @ 0.25 on (a+b+c+d)

143764.02

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

71882.01

Cost for 120 cum = a+b+c+d+e+f

790702.11

Rate per cum = (a+b+c+d+e+f)/120

6589.18
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

495738.00

for 120
21.00

104104.98
149960.75
74980.37

Cost for 120 cum = a+b+c+d+e+f

824784.10

Rate per cum = (a+b+c+d+e+f)/120

6873.20
say

(r)

6589.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 21 per cent of (a+b+c)

14.1F (i)

1406.16

495738.00

For solid slab/voided slab super-structure, 16-26 per cent


of cost of concrete (a+b+c)
Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 16 per cent of (a+b+c)

14.1F (i)

1296.00 Lead =1 km
& P&M-050

6873.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 26 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

495738.00
26.00

128891.88
156157.47
78078.74

Cost for 120 cum = a+b+c+d+e+f

858866.09

Rate per cum = (a+b+c+d+e+f)/120

7157.22
say

284

7157.00

P&M-007

Sr No
14.1F

Ref. to
MoRTH
Spec.

Description

Unit

(ii)

For T-beam & slab including launching of precast girders by


launching truss upto 40 m span, 21-31 per cent of cost of
concrete.

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 21 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Quantity

Rate Rs

495738.00

for 120
21.00

104104.98
149960.75
74980.37

Cost for 120 cum = a+b+c+d+e+f

824784.10

Rate per cum = (a+b+c+d+e+f)/120

6873.20
say

14.1F (ii)

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

495738.00
26.00

128891.88
156157.47
78078.74

Cost for 120 cum = a+b+c+d+e+f

858866.09

Rate per cum = (a+b+c+d+e+f)/120

7157.22
say

(r)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

495738.00
31.00

153678.78
162354.20
81177.10

Cost for 120 cum = a+b+c+d+e+f

892948.07

Rate per cum = (a+b+c+d+e+f)/120

7441.23
say

(iii)

For cast-in-situ box girder, segmental construction and


balanced cantilever, 36-56 per cent of cost of concrete.

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 36 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120
36.00

178465.68
168550.92
84275.46
927030.06

Rate per cum = (a+b+c+d+e+f)/120

7725.25
say

(q)

for 120

495738.00
46.00

228039.48

e)

Overhead charges @ 0.25 on (a+b+c+d)

180944.37

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

90472.19

Cost for 120 cum = a+b+c+d+e+f

995194.04

Rate per cum = (a+b+c+d+e+f)/120

8293.28
say

(r)

7725.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 46 per cent of (a+b+c)

14.1F (iii)

7441.00

495738.00

Cost for 120 cum = a+b+c+d+e+f

14.1F (iii)

7157.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 31 per cent of (a+b+c)

14.1F

6873.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 26 per cent of (a+b+c)

14.1F (ii)

Cost Rs

8293.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 56 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

Cost for 120 cum = a+b+c+d+e+f

for 120

495738.00
56.00

277613.28
193337.82
96668.91
1063358.01

285

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per cum = (a+b+c+d+e+f)/120


14.1

Cost Rs

Remarks/
Input ref.

8861.32
say

8861.00

340421.05

M-081

PSC Grade M-50


Unit = 1 cum
Taking output = 120 cum
a)

Material
Cement

tonne

58.80

5789.47

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

kg

235.20

112.77

26523.75

M-180

Mate

day

0.94

185.07

173.97

Mason

day

3.50

234.29

820.02

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader

hour

6.00

1188.00

7128.00

P&M-017

hour

15.00

854.55

12818.25

P&M-049

tonne.km

300L

4.32

6.00

234.36

Admixture @ 0.4 per cent of cement


b)

c)

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

hour

Basic Cost of Labour, Material & Machinery (a+b+c) for


120 cum
For formwork and staging add the following:
14.1G

(i)

For cast-in-situ box girder, segmental construction and


balanced cantilever, 35-55 per cent of cost of concrete

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

514460.00
35.00

180061.00
173630.25
86815.13
954966.38

Rate per cum = (a+b+c+d+e+f)/120

7958.05
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

514460.00

for 120
45.00

231507.00
186491.75
93245.88

Cost for 120 cum = a+b+c+d+e+f

1025704.63

Rate per cum = (a+b+c+d+e+f)/120

8547.54
say

(r)

7958.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 45 per cent of (a+b+c)

14.1G (i)

1406.16

514460.00

Cost for 120 cum = a+b+c+d+e+f

14.1G (i)

1296.00 Lead =1 km
& P&M-050

8548.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 55 per cent of (a+b+c)

514460.00

for 120
55.00

282953.00

e)

Overhead charges @ 0.25 on (a+b+c+d)

199353.25

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

99676.63

Cost for 120 cum = a+b+c+d+e+f

1096442.88

Rate per cum = (a+b+c+d+e+f)/120

9137.02
say
286

9137.00

P&M-007

Sr No
14.1

Ref. to
MoRTH
Spec.

Description
H

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Cement

tonne

63.50

5789.47

367631.58

M-081

Coarse sand

cum

54.00

203.75

11002.74

M-004

20 mm Aggregate

cum

64.80

862.50

55890.13

M-053

10 mm Aggregate

cum

43.20

655.60

28322.05

M-051

kg

254.00

112.77

28643.85

M-180

Mate

day

0.94

185.07

173.97

Mason

day

3.50

234.29

820.02

L-11

Mazdoor

day

20.00

177.07

3541.40

L-13

Batching Plant @ 20 cum/hour

hour

6.00

2488.00

14928.00

P&M-002

Generator 100 KVA

hour

6.00

1698.00

10188.00

P&M-080

Loader

hour

6.00

1188.00

7128.00

P&M-017

12818.25

P&M-049

PSC Grade M- 55
Unit = 1 cum
Taking output = 120 cum
a)

Material

Admixture @ 0.4 per cent of cement


b)

c)

Labour
L-12

Machinery

Transit Mixer ( capacity 4.0 cu.m )


Transit Mixer 4 cum capacity lead upto1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Basic Cost of Labour, Material & Machinery (a+b+c) for
120 cum
For formwork and staging add the following:
14.1H

(i)

For cast-in-situ box girder, segmental construction and


balanced cantilever, 35-55 per cent of cost of concrete

(p)

Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 35 per cent of (a+b+c)

hour

15.00

854.55

tonne.km

300L

4.32

hour

6.00

234.36

for 120

543791.00
35.00

190326.85

e)

Overhead charges @ 0.25 on (a+b+c+d)

183529.46

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

91764.73
1009412.04

Rate per cum = (a+b+c+d+e+f)/120

8411.77
say

(q)

e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

for 120

543791.00
45.00

244705.95
197124.24
98562.12

Cost for 120 cum = a+b+c+d+e+f

1084183.31

Rate per cum = (a+b+c+d+e+f)/120

9034.86
say

(r)

8412.00

Height 5m to 10m
Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 45 per cent of (a+b+c)

14.1H (i)

1406.16

543791.00

Cost for 120 cum = a+b+c+d+e+f

14.1H (i)

1296.00 Lead =1 km
& P&M-050

9035.00

Height above 10m


Basic Cost of Labour, Material & Machinery (a+b+c)
cum
d) Formwork and staging 55 per cent of (a+b+c)
e)

Overhead charges @ 0.25 on (a+b+c+d)

f)

Contractor's profit @ 0.1 on (a+b+c+d+e)

543791.00

for 120
55.00

299085.05
210719.01
105359.51

Cost for 120 cum = a+b+c+d+e+f

1158954.57

Rate per cum = (a+b+c+d+e+f)/120

9657.95
say

287

9658.00

P&M-007

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

tonne

1.05

46059.03

48361.98

M-082

Kg

8.00

62.52

500.19

M-072

day

0.44

185.07

81.43

L-12

Blacksmith

day

3.00

234.29

702.87

L-02

Mazdoor

day

8.00

177.07

1416.56

L-13

1.Where ever concrete is carried out using batching plant, transit


mixer, concrete pump, admixers conforming IS: 9103 @ 0.4 per
cent of weight of cement may be added for achieving desired
slump of concrete.
2. Cement provided for various components of the super
structure is for estimating purpose only. Actual quantity of cement
will be as per approved mix design. Similarly, the provision for
coarse and fine aggregates is for estimating purpose and the
exact quantity shall be as per the mix design.
3. The items like needle and surface vibrators are part of minor T
& P which is already covered under the overhead charges. As
such these items have not been added separately in the rate
analysis.

14.2

1600

Supplying, fitting and placing HYSD bar reinforcement in


super-structure complete as per drawing and technical
specifications
Unit = 1 MT
Taking output = 1 MT
a)

Material
HYSD bars including 5 per cent for laps and wastage
Binding wire

b)
Labour for cutting, bending, tying and placing in
position
Mate

Basic Cost of Labour & Material (a+b)


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

51064.00
12765.76
6382.88

Rate per MT = a+b+c+d


14.3

1800

70211.67
say

70212.00

High tensile steel wires/strands including all accessories for


stressing, stressing operations and grouting complete as
per drawing and Technical Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight = 0.377
MT)
a) Material

b)

H.T. Strand @ 9.42 kg/m including 2 per cent for wastage


and extra length for jacking

tonne

0.385

62418.78

24031.23

M-119

Sheathing duct ID 66 mm along with 5 per cent extra


length 40 x 1.05 = 42 m.

metre

42.00

61.80

2595.56

M-165

Tube anchorage set complete with bearing plate,


permanent wedges etc

each

2.00

34.35

68.71

M-187

Cement for grouting including 3 per cent wastage @ 3.00


kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)

tonne

0.125

5789.47

723.68

M-081

Add 0.50 per cent cost of material for Spacers, Insulation


tape and miscellaneous items
Labour

137.10

i) For making and fixing cables, anchorages


Mate

day

0.16

185.07

29.61

L-12

Blacksmith

day

1.00

234.29

234.29

L-02

Mazdoor

day

3.00

177.07

531.21

L-13

Mate/Supervisor

day

0.05

185.07

9.25

L-12

Prestressing operator / Fitter

day

0.25

238.29

59.57

L-08

Mazdoor

day

1.00

177.07

177.07

L-13

Mate/Supervisor

day

0.05

185.07

9.25

L-12

Mason

day

0.25

234.29

58.57

L-11

ii) For prestressing

iii) For grouting

288

Sr No

Ref. to
MoRTH
Spec.

Description

Quantity

Rate Rs

day

1.00

177.07

177.07

L-13

Stressing jack with pump

hour

2.50

116.10

290.25

P&M-040

Grouting pump with agitator

hour

1.00

112.77

112.77

M-111

Generator 33 KVA.

hour

3.50

342.36

1198.26

P&M-079

Mazdoor
c)

Machinery

d)

Overhead charges @ 0.25 on (a+b+c)

7610.86

e)

Contractor's profit @ 0.1 on (a+b+c+d)

3805.43

Cost for 0.377 MT (a+b+c+d+e)

41859.76

Rate per MT = (a+b+c+d+e)/0.377

111033.84
say

Note
14.4

2702

Cost Rs

Remarks/
Input ref.

Unit

111034.00

Cost of HT steel has been taken for delivery at site. Hence


carriage has not been considered.
Providing and laying Cement concrete wearing coat M-30
grade including reinforcement complete as per drawing and
Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a)

Material

b)

Cement concrete M30 Grade Refer relevant item of


concrete in Item 14.1 excluding formwork
HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Labour
Mazdoor for cleaning deck slab concrete surface.

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

cum

1.00

3582.00

3582.00 Item 14.1(C)

tonne

0.075

51064.00

3829.80 Item 14.2 A


DIR used item

day

0.15

177.07

10227.75
say

515 &
2702

L-13

929.80

Rate per cum (a+b+c+d)


14.5

26.56
1859.59

10228.00

Mastic Asphalt
Providing and laying 12 mm thick mastic asphalt wearing
course on top of deck slab excluding prime coat with paving
grade bitumen meeting the requirements given in table 50029, prepared by using mastic cooker and laid to required
level and slope after cleaning the surface, including
providing antiskid surface with bitumen precoated fine
grained hard stone chipping of 9.5 mm nominal size at the
rate of 0.005cum per 10 sqm and at an approximate spacing
of 10 cm center to center in both directions, pressed into
surface when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface, all
complete as per clause 515.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum) assuming a
density of 2.3 tonnes/cum.
a) Labour

b)

Mate

day

0.49

185.07

90.68

L-12

Mazdoor

day

11.00

177.07

1947.77

L-13

Mazdoor (Skilled)

day

1.25

206.99

258.74

L-15

Machinery

289

Sr No

Ref. to
MoRTH
Spec.

Description

c)

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mechanical broom @ 1250 sqm per hour

hour

0.06

465.00

27.90

P&M-031

Air compressor 250 cfm

hour

0.06

293.76

17.63

P&M-001

Mastic cooker 1 tonne capacity

hour

6.00

54.81

328.86

P&M-030

Bitumen boiler 1500 litres capacity

hour

6.00

182.52

1095.12

P&M-005

Tractor for towing and positioning of mastic cooker and


bitumen boiler
Material

hour

1.00

171.02

171.02

P&M-053

tonne

0.204

52269.11

10662.90

M-074

cum

0.39

211.23

82.38

M-021

tonne

0.36

4427.31

1593.83

M-188

cum

0.55

655.60

360.58

M-051

0.036 #VALUE!

#VALUE!

M-142

Base mastic (without coarse aggregates) = 60 per cent


Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a specific
case)

d)

i) Bitumen 80/100 or 60/70 @ 10.2 per cent by weight of


mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of mix =
2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium carbonate content not
less than 80 per cent by weight @ 17.92 per cent by
weight of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 per
cent by weight of mix = 2 x 40/100 = 0.8 MT = 0.8/1.456 =
0.55
v) Pre-coated stone chips of 9.5 mm nominal size for skid
resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by weight =
0.036 x 1.456 x 2/100 = 0.001048MT = 1.05kg
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

cum
kg

1.05

52.27

#VALUE!
#VALUE!

Cost for 72.46 sqm = a+b+c+d+e

#VALUE!

Rate per sqm = (a+b+c+d+e)/72.46

#VALUE!
say

Note

54.88 M-074/1000

#VALUE!

1.The rates for 6 mm or any other thickness may be worked out


on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and paid
separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only. Actual
design is required to be done for each case.
5.The quantity of bitumen works out 17 per cent of the mastic
asphalt blocks without aggregates and falls within the standards
laid down by MoRTH Specifications.

14.6

2703,
1500,
1600 &
1700

Construction of precast RCC railing of M30 Grade,


aggregate size not exceeding 12 mm, true to line and grade,
tolerance of vertical RCC post not to exceed 1 in 500, centre
to centre spacing between vertical post not to exceed 2000
mm, leaving adequate space between vertical post for
expansion, complete as per approved drawings and
technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a)

Material
i) M30 Grade Reinforced Cement Concrete
No. of vertical posts = (12 + 2)2 = 28 Nos., External area of
vertical post 0.25x0.275 = 0.069sqm, Concrete in Vertical
posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x
24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm,
Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total
Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD /
202).

290

cum

4.092

3582.00

14657.54 Item 14.1(C)


DIR used
item

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Add 5 per cent of above cost for form work for casting in
casting yard.
ii) HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.

b)

Add 5 per cent of (a) for handling and fixing of precast


panels in position
Overhead charges @ 0.25 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

Quantity

Rate Rs

tonne

0.865

51064.00

2978.04
15634.71
7817.35
85990.88
1791.48
say

2703,
1500,
1600 &
1700

44170.36 Item 14.2 A


DIR used item

Rate per metre (a+b+c)/48

14.7

Remarks/
Input ref.

732.88

Rate for 48 m (a+b+c)

Note

Cost Rs

1791.00

1.Quantities of material have been adopted from standard plans


of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of 24 m
span.
Construction of RCC railing of M30 Grade in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of
vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical post not to exceed 2000 mm,
leaving adequate space between vertical post for expansion,
complete as per approved drawings and technical
specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a)

Material
i) M30 Grade Reinforced Cement Concrete

cum

4.092

3582.00

14657.54 Item 14.1(C)

No. of vertical posts = (12 + 2)2 = 28 Nos., External area of


vertical post 0.25x0.275 = 0.069sqm, Concrete in vehicle
posts = 0.069 x 28 = 1.932 cum, Hand rail in 3 tiers = 3 x
24 = 72 m, External area = 0.170 x 0.175 = 0.03 sqm,
Concrete in hand rails = 0.03 x 72 = 2.16 cum, Total
Concrete = 1.932 + 2.16 = 4.092 cum. (Refer MoRTH SD /
202).
Add 12 per cent of above cost for form work.
ii) HYSD bar reinforcement Rate as per item No
14.2(Excluding OH & CP)

1758.91
tonne

0.865

51064.00

44170.36 Item 14.2 A

refer MoRTH SD / 202.


b)

Overhead charges @ 0.25 on (a)

c)

Contractor's profit @ 0.1 on (a+b)

15146.70
7573.35

Rate for 48 m (a+b+c)

83306.86

Rate per metre (a+b+c)/48


Note

14.8

2703.2 &
1900

1735.56
say

1736.00

1. Quantities of material have been adopted from standard plans


of MoRTH vide drawing no. SD/202.
2. 48 m length is the total linear length adding both sides of 24 m
span.
Providing, fitting and fixing mild steel railing complete as
per drawing and Technical Specification
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a)

Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT

tonne

2.946

46527.33

137069.52

M-179

2) MS Flat = 0.964 x 1.05 = 1.012 MT

tonne

1.012

46527.33

47085.66

M-179

3) MS bars = 0.17 x 1.05 = 0.180 MT

tonne

0.18

46527.33

8374.92

M-179

4) MS bolts, nuts and washers

tonne

0.15

45421.67

6813.25 M-130*1000

Add @ 5 per cent of cost of material for painting one shop


coat with red oxide primer and three coats of synthetic
enamel paint and consumables to safeguard against
weathering and corrosion.

9967.17

Add for cost of concrete for fixing vertical posts in the


performed recess @ 1 per cent of cost of material.

1993.43

291

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Add for electricity charges, welding and drilling equipment,


electrodes and other consumables @ 1 per cent of cost of
material.
b)

Labour
Mate

day

2.80

185.07

518.20

L-12

Mazdoor (Skilled)

day

30.00

206.99

6209.70

L-15

Mazdoor

day

40.00

177.07

7082.80

L-13

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

56777.02
28388.51
312273.62

Rate per metre (a+b+c+d)/100

3122.74
say

2705

Remarks/
Input ref.

1993.43

Cost for 100 m steel railing = a+b+c+d

14.9

Cost Rs

3123.00

Drainage Spouts complete as per drawing and Technical


specification
Unit = 1 No.
Taking output = 1 No.
a)

b)

Material
Corrosion resistant Structural steel including 5 per cent
wastage
GI pipe 100mm dia

Kg

4.00

46.53

186.11 M-087/1000

metre

6.00

50.28

301.66

M-056

GI bolt 10 mm Dia

each

6.00

11.07

66.41

M-110

Galvanised MS flat clamp

each

2.00

11.07

22.14

M-101

Mate

day

0.02

185.07

3.70

L-12

Skilled (Blacksmith, welder etc.)

day

0.02

234.29

4.69

L-02

Mazdoor

day

0.02

177.07

3.54

L-13

Mate

day

0.01

185.07

1.85

L-12

Mason

day

0.01

234.29

2.34

L-11

Mazdoor

day

0.20

177.07

35.41

L-13

Labour

For fabrication

For fixing in position

c)

Add @ 5 per cent of cost of material and labour for


electrodes, cutting gas, sealant, anti-corrosive bituminous
paint, mild steel grating etc.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

31.39

164.81
82.41

Rate per metre (a+b+c+d)

906.47
say

Note

906.00

1. In case of viaducts in urban areas, the drainage spouts should


be connected with suitably located pipelines to discharge the
surface run-off to drains provided at ground level.
2. In case of bridges, sufficient length of G.I Pipe shall be
provided to ensure that there is no splashing of water from the
drainage spout on the structure.

14.10

2700

PCC M15 Grade leveling course below approach slab


complete as per drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding
formworks
Rate per cum

14.11

1500,16
00,1700
& 2704

Reinforced cement concrete approach slab including


reinforcement and formwork complete as per drawing and
Technical specification
Unit = 1 cum
Taking output = 1 cum
a)

Material

292

cum

1.00

3970.00
say

3970.00 Item 12.8 (A)


3970.00

Sr No

Ref. to
MoRTH
Spec.

Description
Cement concreteM30 Grade Refer relevant item of
concrete in item 12.8(G)by using batching plant, excluding
formwork i.e. per cum basic cost (a+b+c) (Excluding OH &
CP)

Unit

Quantity

Rate Rs

cum

1.00

3580.00

( Refer relevant item of concrete in item No. 13.8 (G)


except that form work may be added at the rate of 2 per
cent of cost against 3.5 per cent provided in the
foundation concrete.

b)

HYSD bar reinforcement Rate as per item No


14.2(Excluding OH & CP)
Overhead charges @ 0.25 on (a)

c)

Contractor's profit @ 0.1 on(a+b)

tonne

0.05

51064.00

1600

Item 12.8
(G)

2553.20 Item 14.2 A


1551.20
775.60
8531.60

say

14.12

3580.00

Remarks/
Input ref.

71.60

Rate per cum (a+b+c)


Note

Cost Rs

8532.00

The grade of reinforced cement concrete may be adopted as


M30 for severe conditions and M25 for moderate conditions.
Providing anti-corrosive treatment to HYSD reinforcement
with Fusion Bonded Epoxy Coating (FBEC)
Unit = 1 MT
Taking output = 1 MT
To be taken as per the prevailing market rates.

Note

14.13

1800 &
2300

VALUE

Contractors generally do not have expertise for this item . The


job is therefore, got done from specialised firms who have the
expertise in the field of construction chemicals. The prevailing
rate in the market is required to be ascertained from the market
and added in the cost estimate. Detailed guidelines in this regard
have been issued by MoRTH vide their circular no. RW/NH34041/44/91-S&R dated 21.3.2000.
Precast - pretensioned Girders
Providing, precasting, transportation and placing in position
precast pretensioned concrete girders as per drawing and
technical specifications
Unit = 1 cum
Taking output = 1 cum
Grade of concrete - M40
a)

Material
Cement

tonne

0.47

5789.47

2721.05

M-081

Coarse sand

cum

0.45

20 mm Aggregate

cum

0.54

203.75

91.69

M-004

862.50

465.75

10 mm Aggregate

cum

M-053

0.36

655.60

236.02

Admixture @ 0.4 per cent of cement

M-051

Kg

1.88

112.77

212.01

M-180

HYSD steel .

tonne

0.10

46059.03

4605.90

M-082

HT strand with 5 per cent as wastage and extra length for


anchoring
LDO for steam curing

tonne

0.06

62418.78

3745.13

M-119

Litre

37.00

#VALUE!

#VALUE!

M-122

Add consumables such as binding wire, foam, packing


tape, shuttering oil, HDPE pipe for unbonding of strand,
bolt & nuts etc @ 1 per cent of material cost
b)

#VALUE!

Labour

(i) Cutting, bending, making reinforcement cage, placing in


position, binding etc. complete
Taking quantity of steel 100 Kg/cum of concrete including
laps and wastage
Mate

day

0.06

185.07

Mazdoor (Skilled)

day

0.35

Mazdoor

day

1.40

(ii) Cable cutting and threading in position including binding


by insulation tape with HDPE pipes etc., prestessing and
cutting of extra length of HT strand after de-stressing.
Taking quantity of HT strand 60 Kg/cum
293

11.10

L-12

206.99

72.45

L-15

177.07

247.90

L-13

Sr No

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.02

185.07

3.70

L-12

Mazdoor (Skilled)

day

0.14

206.99

28.98

L-15

Mazdoor

day

0.50

177.07

88.54

L-13

Mate

day

0.12

185.07

22.21

L-12

Mazdoor (Skilled)

day

1.00

206.99

206.99

L-15

Mazdoor

day

2.00

177.07

354.14

L-13

day

0.03

185.07

5.55

L-12

Mazdoor (Skilled)

day

0.05

206.99

10.35

L-15

Mazdoor

day

0.60

177.07

106.24

L-13

Mate

day

0.01

185.07

1.85

L-12

Mazdoor

day

0.35

177.07

61.97

L-13

day

0.01

185.07

1.85

L-12

day

0.25

177.07

44.27

L-13

Mate

day

0.01

185.07

1.85

L-12

Mazdoor (Skilled)

day

0.06

206.99

12.42

L-15

Mazdoor

day

0.24

177.07

42.50

L-13

Generator 100 KVA

hour

0.05

1698.00

84.90

P&M-080

Batching Plant @ 20 cum/hour

hour

0.05

2488.00

124.40

P&M-002

Transit Mixer 4 cum capacity

hour

0.10

854.55

85.46

P&M-049

Concrete Pump stationary

hour

0.05

234.36

11.72

P&M-007

Crane 35 tonne capacity

hour

0.10

784.62

78.46

P&M-012

Trailor 30 tonne capacity

hour

0.10

1864.08

186.41

P&M-089

Loader

hour

0.05

1188.00

59.40

P&M-017

117.69

P&M-012

(iii) Erection and dismantling of shuttering


Taking shuttering area 10 sqm/cum of concrete

(iv) Concreting by Batching plant and stationary concrete


pump
Mate

(v) Steam curing and manual curing

(vi) Handling of precast girder, stacking in stockyard and


again loading in trailor
Mate
Mazdoor
(vii) Placement of girders in position over pier caps
including placement of sand jacks, channel, levelling etc.

c)

Machinery

i) At casting yard

ii) For transportation and placement at site


Crane 35 tonne capacity
Trailer 30 tonne capacity for transporting to site.

hour

0.15

784.62

tonne.km

2.5xL

2.27

hour

0.15

1864.08

5.67 Lead =1 km
& P&M-090

(L - Lead in Kilometer)
Trailor 30 tonne capacity during placement.

#VALUE!

d)

Cost of formwork, steam curing arrangement, pretensioning


arrangement etc @ 5 per cent of cost material, labour and
machinery
Overhead charges @ 0.25 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

1700 &
1800

P&M-089

#VALUE!

Rate per cum = (a+b+c+d+e)


14.14

279.61

#VALUE!
say

#VALUE!

#VALUE!

M-117

47.51

M-183

Providing and fixing Helical pipes in voided concrete slabs


Unit = 1 RM
Taking output = 1 RM
a)

Material
Helical pipes 600mm diameter

metre

1.00

#VALUE!

Tie rods 20mm diameter

each

1.00

47.51

Consumables for sealing joints etc.@ 5 per cent of cost of


material
b) Labour
Mate

#VALUE!

day
294

0.01

185.07

1.85

L-12

Sr No

Ref. to
MoRTH
Spec.

Description

Quantity

Rate Rs

Fitter

day

0.05

238.29

11.91

L-08

Mazdoor

day

0.20

177.07

35.41

L-13

c)

Overhead charges @ 0.25 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Rate per cum (a+b+c+d)

#VALUE!
say

14.15

800

#VALUE!

Crash Barriers
The rate analysis for rigid crash barrier in reinforced cement
concrete, semi-rigid crash barrier with metal beam and flexible
crash barrier with wire ropes have been made and included in
chapter-8 on Traffic and Transportation.

14.16

Cost Rs

Remarks/
Input ref.

Unit

800

Per m

VALUE

Painting on concrete surface


Providing and applying 2 coats of water based cement paint
to unplastered concrete surface after cleaning the surface of
dirt, dust, oil, grease, efflorescence and applying paint @ of
1 litre for 2 sqm.
Unit = sqm
Taking output = 10 sqm
a)

Labour
Mate

day

0.01

185.07

1.85

L-12

Painter

day

0.25

223.29

55.82

L-18

Mazdoor (Skilled)

day

0.25

206.99

51.75

L-15

Litres

5.00

75.18

375.90

M-190

b)

Material

c)

Water based paint of approved quality for cement concrete


surface
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

121.33
60.67

Cost for 10 sqm (a+b+c+d)

667.32

Rate per sqm (a+b+c+d)/10

66.73
say

14.17

2604

67.00

Burried Joint
Providing and laying a burried expansion joint, expansion
gap being 20 mm, covered with 12 mm thick, 200 mm wide
galvanised weldable structural steel plate as per IS: 2062,
placed symmetrical to centre line of the joint, resting freely
over the top surface of the deck concrete, welding of 8 mm
dia. 100 mm long galvanised nails spaced 300 mm c/c along
the centre line of the plate, all as specified in clause 2604.
Unit = Running meter
Taking output = 12 m
a)

Labour
Mate

day

0.02

185.07

3.70

L-12

Mazdoor

day

0.40

177.07

70.83

L-13

Mazdoor (Skilled)

day

0.20

206.99

41.40

L-15

kg

237.50

46.24

b)

Material

c)

Galvanised M.S plate 200 mm wide,12 mm thick @ 94.20


kg/sqm including 5 per cent wastage
Add 1 per cent of cost of steel plate cutting, welding
consumables and galvanised nails.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

109.82
2801.89
1400.95

Cost for 12 m = (a+b+c+d)

15410.41

Rate per m = (a+b+c+d)/12

1284.20
say

Note

14.18

2605

10981.82 M-060/1000

Guidelines laid down vide the MoRTH circular No. RW/NH34059/1/96-S&R dated 30.11.2000 and subsequent corrigendum
dated 25.01.2001 may be reffered for expansion joints.
Filler joint

295

1284.00

Sr No

Ref. to
MoRTH
Spec.

Description
(i)

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.04

185.07

7.40

L-12

Mazdoor

day

0.50

177.07

88.54

L-13

Mazdoor (Skilled)

day

0.50

206.99

103.50

L-15

kg

55.00

481.39

26476.19

Providing & fixing 2 mm thick corrugated copper plate in


expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a)

Labour

Cutting, bending, carrying & fixing etc.

b)

Material
Copper plate - 12m long x 250 mm wide

M-086

Area = 12 x 0.25 = 3 sqm


Weight = 3 x 0.002 x 8900 = 53.4 kg
Wastage @ 2.5 per cent = 1.33 kg/54.73 kg say = 55 kg.
c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

6668.91
3334.45

Cost for 12 m = (a+b+c+d)

36678.98

Rate per m = (a+b+c+d)/12

3056.58
say

14.18

(ii)

3057.00

Providing & fixing 20 mm thick compressible fibre board in


expansion joint complete as per drawing & Technical
Specification.
Unit = Running meter
Taking output = 12 m
a)

Labour

For carrying, placing & fixing.

b)

Mate

day

0.01

185.07

1.48

L-12

Mazdoor

day

0.10

177.07

17.71

L-13

Mazdoor (Skilled)

day

0.10

206.99

20.70

L-15

sqm

3.00

603.53

1810.60

Material

20 mm thick compressible fibre board 12 m long x 25 cm


deep.
Area = 12 x 0.25 = 3 sqm
c)

Overhead charges @ 0.25 on (a+b)

462.62

d)

Contractor's profit @ 0.1 on (a+b+c)

231.31

Cost for 12 m = (a+b+c+d)

2544.42

Rate per m = (a+b+c+d)/12


14.18

(iii)

M-084

212.04
say

212.00

Providing and fixing in position 20 mm thick premoulded


joint filler in expansion joint for fixed ends of simply
supported spans not exceeding 10 m to cater for a
horizontal movement upto 20 mm, covered with sealant
complete as per drawing and technical specifications.
Unit = Running meter
Taking output = 12 m
a)

Labour
Mate

day

0.01

185.07

1.85

L-12

Mazdoor

day

0.20

177.07

35.41

L-13

Mazdoor (Skilled)

day

0.10

206.99

20.70

L-15

sqm

3.60

708.07

2549.05

b)

Material

c)

Premoulded joint filler 12 m long,20 mm thick and 300 mm


deep.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

651.75
325.88

Cost for 12 m = (a+b+c+d)

3584.65

Rate per m = (a+b+c+d)/12

298.72
say
296

299.00

M-141

Sr No
14.18

Ref. to
MoRTH
Spec.

Description
(iv)

Unit

Providing and filling joint sealing compound as per


drawings and technical specifications with coarse sand and
6 per cent bitumen by weight
Unit = Running meter
Taking output = 12 m
12m long x 100 mm wide x 10mm deep recess

297

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Sr No

Ref. to
MoRTH
Spec.

Description
a)

b)

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.02

185.07

3.70

L-12

Mazdoor

day

0.50

177.07

88.54

L-13

Mazdoor (Skilled)

day

0.10

206.99

20.70

L-15

cum

0.012

203.75

2.45

M-005

cum

0.001

52269.11

52.27

M-074

Labour

Material
Sand

Volume 12 x 0.1 x 0.01 = 0.012 cum


Weight 0.012 x 1400 = 16.8kg
Bitumen
16.8 x 0.06 = 1 kg
c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

41.91
20.96

Cost for 12 m = (a+b+c+d)

230.52

Rate per m = (a+b+c+d)/12

19.21
say

Note

19.20

For arriving at the final rate of filler joints per m


length and per cm depth of joint filling compound,
the rates at Sl. No. i), ii), iii) & iv) shall be added

14.19

2600

Asphaltic Plug joint


Providing and laying of asphaltic plug joint to provide for
horizontal movement of 25 mm and vertical movement of 2
mm, depth of joint varying from 75 mm to 100 mm, width
varying from 500 mm to 750 mm (in traffic direction),
covered with a closure plate of 200mm x 6mm of weldable
structural steel conforming to IS: 2062, asphaltic plug to
consist of polymer modified bitumen binder, carefully
selected single size aggregate of 12.5 mm nominal size and
a heat resistant foam caulking/backer rod, all as per
approved drawings and specifications.

Unit = Running meter


Taking output = 12 m
a)

b)

Labour
Mate

day

0.052

185.07

9.62

L-12

Mazdoor

day

1.00

177.07

177.07

L-13

Mazdoor (Skilled)

day

0.30

206.99

62.10

L-15

cum

0.75

756.00

567.00

M-052

Polymer modified bitumen

kg

77.50

53.32

4132.36 M-078/ 1000

Galvanised structural steel plate 200 mm wide,6 mm thick,


12 m long (2.4 sqm) @ 47.10 kg/sqm including 5 per cent
wastage
Add 1 per cent for welding and foam caulking/backer rod
and other incidentals.
Machinery

kg

113.00

38.63

4365.70

Material
Crushed stone aggregate 12.5 mm nominal size

c)

93.14

Mastic cooker 1 tonne capacity

hour

1.00

54.81

54.81

P&M-030

Smooth 3-wheeled steel roller 8-10 capacity

hour

0.50

665.00

332.50

P&M-044

d)

Overhead charges @ 0.25 on (a+b+c)

2448.57

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1224.29

Cost for 12 m asphalt plug joint = (a+b+c+d+e)

13467.16

Rate per m = (a+b+c+d+e)/12

1122.26
say

Note

14.20

2606

M-103

The nominal size of aggregates shall be 12.5 mm for depth of


joint upto 75 mm and 20 mm for joints of depth more than 75
mm.
Elastomeric Slab Steel Expansion Joint

298

1122.00

Sr No

Ref. to
MoRTH
Spec.

Description

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.06

185.07

11.10

L-12

Mazdoor

day

1.00

177.07

177.07

L-13

Mazdoor (Skilled)

day

0.50

206.99

103.50

L-15

metre

12.00

19422.70

233072.41

Providing and laying of an elastomeric slab steel expansion


joint, catering to right or skew (less than 20 deg., moderately
curved with maximum horizontal movement upto 50 mm,
complete as per approved drawings and standard
specifications to be installed by the manufacturer/supplier
or their authorised representative ensuring compliance to
the manufacturer's instructions for installation and clause
2606 of MoRTH specifications for road & bridge works.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour

Material
Supply of elastomeric slab seal expansion joint assembly
manufactured by using chloroprene, elastomer for
elastomeric slab unit conforming to clause 915.1 of IRC: 83
(part II), complete as per approved drawings and standard
specification conforming to clause 2606 of MoRT&H
Specification

c)

Add 5 per cent of cost of material for anchorage


reinforcement, welding and other incidentals.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

11653.62
61254.43
30627.21

Cost for 12 m = (a+b+c+d)

336899.34

Rate per m = (a+b+c+d)/12


14.21

2600

M-093

28074.95
say

28075.00

Compression Seal Joint


Providing and laying of compression seal joint consisting of
steel armoured nosing at two edges of the joint gap suitably
anchored to the deck concrete and a preformed chloroprene
elastomer or closed cell foam joint sealer compressed and
fixed into the joint gap with special adhesive binder to cater
for a horizontal movement upto 40 mm and vertical
movement of 3 mm.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.036

185.07

6.66

L-12

Mazdoor

day

0.60

177.07

106.24

L-13

Mazdoor (Skilled)

day

0.30

206.99

62.10

L-15

kg

446.00

38.63

17231.00

Material
1. Galvanised angle sections 100mm x 100mm of 12mm
thickness weldable structural steel as per IS: 2062, 2 nos.
of 12 m length each @ 17.7 kg/m and 5 per cent wastage.
Add 5 per cent of cost of above for structural steel for
anchorage, welding and other incidentals.
Preformed continuous chloroprene elastomer or closed cell
foam sealing element with high tear strength, vulcanised in
a single operation for the full length of a joint to ensure
water tightness.

870.30
metre

12.00

#VALUE!

#VALUE!

#VALUE!

c)

Add 1 per cent of cost of sealing element for lubricantcum-adhesive and other consumables.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

#VALUE!

Cost for 12 m = (a+b+c+d)

#VALUE!

Rate per m = (a+b+c+d)/12

#VALUE!
say

299

M-103

#VALUE!

M-143

Sr No

Ref. to
MoRTH
Spec.

Description
Note

Cost Rs

Remarks/
Input ref.

Unit

Quantity

Rate Rs

Mate

day

0.05

185.07

9.25

L-12

Mazdoor

day

1.00

177.07

177.07

L-13

Mazdoor (Skilled)

day

0.25

206.99

51.75

L-15

metre

12.00

6043.69

72524.32

1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.

14.22

3. The anchoring bars of the expansion joint assembly shall be


welded to the main reinforcement of the deck.
Strip Seal Expansion Joint

2607

Providing and laying of a strip seal expansion joint catering


to maximum horizontal movement upto 70 mm, complete as
per approved drawings and standard specifications to be
installed by the manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's
instructions for installation.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour

Material
Supply of complete assembly of strip seal expansion joint
comprising of edge beams, anchorage, strip seal element
and complete accessories as per approved specifications
and drawings.

c)

Add 5 per cent of cost of material for anchorage


reinforcement, welding and other incidentals.
Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

3638.12
19100.13
9550.06

Cost for 12 m = (a+b+c+d)

105050.70

Rate per m = (a+b+c+d)/12

8754.22
say

Note

14.23

2600

M-178

8754.00

1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
Modular Strip / Box Seal Joint
Providing and laying of a modular strip Box seal expansion
joint including anchorage catering to a horizontal movement
beyond 70 mm and upto 140mm, complete as per approved
drawings and standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.056

185.07

10.36

L-12

Mazdoor

day

1.00

177.07

177.07

L-13

Mazdoor (Skilled)

day

0.40

206.99

82.80

L-15

metre

12.00

21404.46

256853.52

Material
Supply of a modular strip/box seal joint assembly
comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and control
system, all steel sections protected against corrosion and
installed by the manufacturer or his authorised
representative.

c)

Overhead charges @ 0.25 on (a+b)

64280.94

d)

Contractor's profit @ 0.1 on (a+b+c)

32140.47

Cost for 12 m Modular strip/box seal joint = (a+b+c+d)


300

353545.15

M-127

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Quantity

Rate Rs

Rate per m = (a+b+c+d)/12

14.24

Remarks/
Input ref.

29462.10
say

Note

Cost Rs

29462.00

1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be
welded to the main reinforcement of the deck.
Modular Strip / Box Seal Joint

2600

Providing and laying of a modular strip box seal expansion


joint catering to a horizontal movement beyond 140mm and
upto 210mm, complete as per approved drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised representative
ensuring compliance to the manufacturer's instructions for
installation.
Unit = Running meter
Taking output = 12 m
a)

b)

Labour
Mate

day

0.07

185.07

12.95

L-12

Mazdoor

day

1.25

177.07

221.34

L-13

Mazdoor (Skilled)

day

0.50

206.99

103.50

L-15

metre

12.00

#VALUE!

#VALUE!

M-128

Material
Supply of a modular box/box seal joint assembly containing
3 modules/cells and comprising of edge beams, two central
beams, chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.

c)

Overhead charges @ 0.25 on (a+b)

#VALUE!

d)

Contractor's profit @ 0.1 on (a+b+c)

#VALUE!

Cost for 12 m Modular strip/box seal joint = (a+b+c+d)

#VALUE!

Rate per m = (a+b+c+d)/12

#VALUE!
say

Note

1. The installation shall be done by the manufacturer or his


authorised representative to the satisfaction of the Engineer.
2. The concreting for joining the expansion joint assembly with
the deck has not been included in this analysis as the same is
catered in the quantities of RCC deck.
3. The anchoring bars of the expansion joint assembly shall be
welded to the main reinforcement of the deck.

301

#VALUE!

CHAPTER - 15

RIVER TRAINING AND PROTECTION WORKS


Sr No

Ref. to
MoRTH
Spec.

15.1

2503

Description

*
Note
2503

*
Note

15.3

2503

Quantity Rate Rs

Cost Rs

Remarks/
Input ref.

Providing and laying boulders apron on river bed for


protection against scour with stone boulders weighing not
less than 40 kg each complete as per drawing and Technical
specification.
A

15.2

Unit

Boulder Laid Dry Without Wire Crates.


Unit = cum
Taking output = 1 cum
a) Material
Stone
Stone Spalls
b) Labour
Mate
Mason
Mazdoor *
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum = (a+b+c+d)
Including excavation for trimming for preparation of bed.
Nominal excavation required for preparation of bed has been taken
into account while making provision for labour.
Boulder Apron Laid in Wire Crates
Providing and laying of boulder apron laid in wire crates made with
4mm dia GI wire conforming to IS: 280 & IS:4826 in 100mm x
100mm mesh (weaved diagonally) including 10 per cent extra for
laps and joints laid with stone boulders weighing not less than 40
kg each.
Unit = cum
Taking output = 3 mx1.5mx1.25m = 5.63 cum
a) Material
4mm GI wire crates woven in mesh size of 100 mm x 100 mm.
Stone
Stone Spalls
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5.63 cum = a+b+c+d
Rate per cum = (a+b+c+d)/5.63
Including excavation for trimming for preparation of bed.
Readymade woven wire crate rolls have been considered in the
rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.
Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)
Providing and laying of apron with cement concrete blocks of size
0.5x0.5x0.5 m cast in-situ and made with nominal mix of M-15
grade cement concrete with a minimum cement content of 250
kg/cum as per IRC: 21-2000.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) including OH &
CP
Add 2 per cent of cost to account for excavation for preparation of
bed, nominal surface reinforcement and filling of granular material
in recesses between blocks.
Rate per cum

cum
cum

1.00
0.20

343.79
317.10

343.79
63.42

M-003
M-008

day
day
day

0.04
0.35
0.75

185.07
234.29
177.07

L-12
L-11
L-13

say

7.40
82.00
132.80
157.35
78.68
865.45
865.00

sqm
cum
cum

22.00
5.63
1.13

73.09
343.79
317.10

1608.03
1935.53
358.32

M-102
M-003
M-008

day
day
day

0.18
1.50
*3.00

185.07
206.99
177.07

33.31
310.49
531.2
1194.2
597.11
6568.23
1166.65
1167.00

L-12
L-15
L-13

say

cum

1.00

4128.00

82.56

say

300

4128.00 Item 12.8 (A)

4210.56
4211.00

Sr No

Ref. to
MoRTH
Spec.

15.4

2504

Description

Unit

Quantity Rate Rs

Remarks/
Input ref.

Providing and laying Pitching on slopes laid over prepared


filter media including boulder apron laid dry in front of toe of
embankment complete as per drawing and Technical
specifications
A

Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg
Stone spalls of minimum 25 mm size
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Rate per cum = (a+b+c+d)

cum
cum

1.00
0.20

343.79
317.10

343.79
63.42

M-003
M-008

day
day
day

0.04
0.35
0.75

185.07
234.29
177.07

7.40
82.00
132.80
157.35
78.68
865.45
865.00

L-12
L-11
L-13

say
15.4

Cost Rs

Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in cement


concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A)

cum

1.00

4128.00

Add 2 per cent of cost to account for nominal surface


reinforcement and filling of granular material in recesses between
blocks.

82.56

4210.56

Rate per cum


15.5

2504

4128.00 Item 12.8 (A)

say

4211.00

735.60

Providing and laying Filter material underneath pitching in


slopes complete as per drawing and Technical specification
Unit = cum
Taking output = 1 cum
a)

Material
cum

1.20

613.00

Mate

day

0.05

185.07

9.25

L-12

Mazdoor (Skilled)

day

0.25

206.99

51.75

L-15

Mazdoor *

day

1.00

177.07

177.07

L-13

Graded stone aggregate of required size


b)

M-012

Labour

c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

243.42
121.71
1338.80

Rate per cum = (a+b+c+d)


say

1339.00

Includes Mazdoor required for trimming of slope to proper profile


and preparation of bed.
15.6

700 &
2504

Geotextile Filter
Laying of a geotextile filter between pitching and embankment
slopes on which pitching is laid to prevent escape of the
embankment material through the voids of the stone
pitching/cement concrete blocks as well as to allow free movement
of water without creating any uplift head on the pitching.
Unit = sqm
Taking output = 10 sqm.
a)

Labour

Mate

day

0.02

185.07

3.70

L-12

Mazdoor

day

0.30

177.07

53.12

L-13

Mazdoor (Skilled)

day

0.10

206.99

20.70

L-15

b)

Material

301

Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Permeable synthetic geotextile including 5 per cent for overlap


and wastage
c) Overhead charges @ 0.25 on (a+b)

sqm

d)

Quantity Rate Rs
11.00

85.89

M-181

127.79
1405.68

Rate per sqm = (a+b+c+d)/10

140.57
say

2504.4

944.79

Remarks/
Input ref.

255.58

Contractor's profit @ 0.1 on (a+b+c)

Cost for 10 sqm = a+b+c+d

15.7

Cost Rs

141.00

Toe protection
A toe wall for toe protection can either be in dry rubble masonry in
case of dry rubble pitching or pitching with stones in wire crates or
it can be in PCC M15 nominal mix if cement concert block have
been used for pitching . Rates for toe wall can be adopted from
respective clauses depending upon approved design. The rate for
excavation for foundation, dry rubble masonry and PCC M15 have
been analysed and given in respective chapters.

15.8

2505

Providing and laying Flooring complete as per drawing and


Technical specifications laid over cement concert bedding.
A

Rubble stone laid in cement mortar 1:3


Unit = cum
Taking output = 1 cum
a)
Cement mortor 1:3 (Rate as in Item 12.6 sub-analysis)
excluding OH & CP
b)
Add for cement concrete bedding (M15 Nominal mix)
vide Item 12.8 (A) excluding OH & CP . Quantity shall be
adopted as per design ( Assume Rubble stone Flooring
thickness 300mm and cement concrete bedding thickness
100mm)

cum

0.33

3333.00

1099.89 Item 12.6 (A)

cum

0.33

2887.00

952.71 Item 12.8 (A)

Add 1 per cent of cost to account for excavation for preparation of


bed.
c) Material

20.53

Stone

cum

1.00

343.79

343.79

M-003

Stone Spalls

cum

0.20

317.10

63.42

M-008

Mate

day

0.08

185.07

14.81

L-12

Mason

day

0.50

234.29

117.15

L-11

Mazdoor (for laying stones, filling of quarry spalls)

day

1.50

177.07

265.61

L-13

d)

Labour

e)

Overhead charges @ 0.25 on (a+c+d)

f)

Contractor's profit @ 0.1 on (a+c+d+e)

476.16
238.08
3592.14

Rate per cum = (a+b+c+d+e+f)


say
15.8

Includes cement mortar for laying and filling of joints.

Cement Concrete blocks Grade M15


Concrete Grade M15 block. (Rate as per item No. 12.8 (A)
including OH & CP.
Add for cement concrete bedding (M15 Nominal mix) vide Item
12.8 (A) including OH & CP. Quantity shall be adopted as per
design ( Assume Cement Concrete blocks thickness 300mm and
cement concrete bedding thickness 100mm)

cum

1.00

4128.00

4128.00 Item 12.8 (A)

cum

0.33

4128.00

1362.24 Item 12.8 (A)

Add 1 per cent of cost to account for excavation for preparation of


bed.
Rate per cum

54.90
5545.14
say

15.9

2506

Dry Rubble Flooring


Construction of dry rubble flooring at cross drainage works for
relatively less important works.
Unit = cum
Taking output = 1 cum
a)

Material

302

3592.00

5545.00

Sr No

Ref. to
MoRTH
Spec.

Unit

Stone

cum

1.00

343.79

343.79

M-003

Stone Spalls

cum

0.20

317.10

63.42

M-008

Mate

day

0.10

185.07

18.51

L-12

Mason

day

0.50

234.29

117.15

L-11

mazdoor

day

1.50

177.07

265.61

L-13

b)

Quantity Rate Rs

Labour

4.01

Add 1 per cent of (b) for trimming and preparation of base.


c)

Overhead charges @ 0.25 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

203.12
101.56

Rate per cum = (a+b+c+d)

1117.16
say

15.10

2507.2
A

Rate same as per item No. 12.7 (A)

cum

1.00

Note

15.11

2507.2

2933.00

2933.00 Item 12.7 (A )

including OH & CP
say

Rate per cum


B

1117.00

Curtain wall complete as per drawing and Technical


specification
Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort)

15.10

Cost Rs

Remarks/
Input ref.

Description

Cement concrete Grade M15


Concrete Grade M15 Rate as per item No. 12.8 (A) including OH &
CP
Rate per cum

cum

1.00

4128.00

2933.00

4128.00 Item 12.8 (A)

say

4128.00

Other items like excavation for foundation, filling behind wall, filter
media, weep holes etc. shall be added separately as per approved
design.
Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less than 40
kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a)

Material

Stone

cum

1.00

343.79

343.79

M-003

Stone Spalls

cum

0.20

317.10

63.42

M-008

Mate

day

0.05

185.07

9.25

L-12

Mason

day

0.25

234.29

58.57

L-11

Mazdoor
Add 1 per cent of cost of (a+b)
for trimming and preparation of
bed.
c) Overhead charges @ 0.25 on (a+b)

day

1.00

177.07

177.07

L-13

b)

d)

Labour

6.52
164.66
82.33

Contractor's profit @ 0.1 on (a+b+c)

905.61

Rate per cum = (a+b+c+d)


15.12

2503.3

say

906.00

Gabian Structure for Retaining Earth


Providing and construction of a gabian structure for retaining earth
with segments of wire crates of size 7 m x 3 m x 0.6 m each
divided into 1.5 m compartments by cross netting, made from 4
mm galvanised steel wire @ 32 kg per 10 sqm having minimum
tensile strength of 300 Mpa conforming to IS:280 and galvanizing
coating conforming to IS:4826, woven into mesh with double twist,
mesh size not exceeding 100 x 100 mm, filled with boulders with
least dimension of 200 mm, all loose ends to be tied with 4 mm
galvanised steel wire
Unit = cum
Taking output = 7 x 3 x 0.6 = 12.60 cum
a)

Labour

Mate

day

0.28

185.07

51.82

L-12

Mazdoor

day

5.00

177.07

885.35

L-13

303

Sr No

Ref. to
MoRTH
Spec.

Quantity Rate Rs

Unit

Mazdoor (Skilled)

day

2.00

206.99

413.98

L-15

b) Material
Galvanised steel wire crates of mesh size 100 mm x 100 mm
woven with 4mm dia. GI wire in rolls of required size.
Stone boulders with least dimension of 200 mm

sqm

61.00

73.09

4458.63

M-102

cum

12.60

343.79

4331.75

M-003

Stone spalls of minimum size 25 mm

cum

2.52

317.10

799.09

M-008

c)

Overhead charges @ 0.25 on (a+b)

2735.16

d)

Contractor's profit @ 0.1 on (a+b+c)

1367.58
15043.36

Cost for 12.60 cum (a+b+c+d)

1193.92

Rate per cum (a+b+c+d)/12.60


Note

15.13

Cost Rs

Remarks/
Input ref.

Description

say

1194.00

Readymade woven wire crate rolls have been considered in the


rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.
Gabian Structure for Erosion Control, River Training Works
and Protection works

2503.3

Providing and constructing gabian structures for erosion control,


river training works and protection works with wire crates of size 2
m x 1 m x 0.3 m each divided into 1m compartments by cross
netting, made from 4 mm galvanised steel wire @ 32 kg per 10
sqm having minimum tensile strength of 300 Mpa conforming to
IS:280 and galvanizing coating conforming to IS:4826, woven into
mesh with double twist, mesh size not exceeding 100 mm x 100
mm, filled with boulders with least dimension of 200 mm, all loose
ends to be securely tied with 4 mm galvanised steel wire.
Unit = cum
Taking output = 2 x 1 x 0.3 x 10 Nos. = 6.00 cum
a)

Labour

Mate

day

0.14

185.07

25.91

L-12

Mazdoor

day

2.50

177.07

442.68

L-13

Mazdoor (Skilled)

day

1.00

206.99

206.99

L-15

Galvanised steel wire crates of mesh size 100 mm x 100 mm


woven with 4mm dia. GI wire in rolls of required size to cover 6.00
cum.

sqm

65.00

73.09

4751.00

M-102

Stone boulders with least dimension of 200 mm

cum

6.00

343.79

2062.74

M-003

Stone spalls of minimum size 25 mm

cum

1.20

317.10

380.52

M-008

b)

Material

c)

Overhead charges @ 0.25 on (a+b)

1967.46

d)

Contractor's profit @ 0.1 on (a+b+c)

983.73

Cost for 6.00 cum (a+b+c+d)

10821.02
1803.50

Rate per cum (a+b+c+d)/6.00


say
Note

Readymade woven wire crate rolls have been considered in the


rate analysis. In case readymade rolls are not available, GI wire
4mm dia. @ 32 kg per 10 sqm may be provided. In that case 2 per
cent of the cost of GI wire may be added for weaving the wire
crates.

304

1804.00

CHAPTER-16

REPAIR AND REHABILITATION


Sr No

Ref. to
MoRTH
Spec.

16.1

2809

Description

Unit

Tractor-trolley.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10
2809

Rate Rs

day
day

0.06
1.00

185.07
177.07

11.10
177.07

L-12
L-13

hour

1.00

293.76

293.76

P&M-001

hour

0.50

171.02

P&M-053

say

85.51
170.23
73.77
811.44
81.14
81.00

day
day

0.03
0.75

185.07
177.07

5.55
132.80

L-12
L-13

hour
hour

0.75
0.40

293.76
171.02

220.32
68.41
128.12
55.52
610.73
61.07
61.00

P&M-001
P&M-053

say
2807

Guniting concrete surface with cement mortar applied with compressor after
cleaning surface and spraying with epoxy complete as per Technical
Specification
Unit = Sq m
Taking output = 1 sqm
Assuming thickness 25 mm
a) Material
Cement
Graded sand
Wire mesh 50mm x 50mm size of 3mm wire
Epoxy
Accelerator compound for guniting @ 4 per cent of weight of cement

kg
cum
kg
kg
kg

16.00
0.04
2.00
0.67
0.64

5.789
203.75
30.28
282.81
112.77

Add 2 per cent of cost of material for miscellaneous consumables like


nozzles, wire brush, cotton waste etc.
b)

c)

Labour
Mate
Mason
Mazdoor
Machinery
Compressor with guniting equipment along with accessories

2800

92.63 M-081/1000
8.15
M-005
60.56
M-192
189.48
M-095
72.17
M-180
8.46

day
day
day

0.01
0.04
0.14

185.07
234.29
177.07

1.85
9.37
24.79

hour

0.10

Value

#VALUE!

d)

Overhead charges @ 0.3 on (a+b+c)

#VALUE!

e)

Contractor's profit @ 0.1 on (a+b+c+d)

#VALUE!

Rate per sqm = (a+b+c+d+e)


16.4

Remarks/
Input ref.

Removal of existing asphaltic wearing coat comprising of 50 mm thick


asphaltic concert laid over 12 mm thick mastic asphalt including disposal with
all lift and lead upto 1000 m.
Unit = Sq m
Taking output = 10 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Air Compressor 250 cfm with pneumatic breaker.
Tractor-trolley.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = (a+d+c+d)
Rate per sqm = (a+b+c+d)/10

16.3

Cost Rs

Removal of existing cement concrete wearing coat including its disposal


complete as per Technical Specification without causing any detrimental effect
to any part of the bridge structure and removal of dismantled material with all
lifts and lead upto 1000 m
Unit = Sq m ( Thickness 75 mm)
Taking output = 10 sqm
a) Labour
Mate
Mazdoor
b) Machinery
Air Compressor 250 cfm with pneumatic breaker/jack hammer along with
accessories.

16.2

Quantity

L-12
L-11
L-13
P&M-076

#VALUE!
say

#VALUE!

5.64

5.64

Providing and inserting nipples with approved fixing compound after drilling
holes for grouting as per Technical Specifications including subsequent
cutting/removal and sealing of the hole as necessary of nipples after
completion of grouting with Cement/Epoxy
Unit = Number
Taking output = 1 No.
a) Material
Nipples

each
305

1.00

M-129

Cement, fixing compound and consumables @ 15 per cent of cost of nipple


b)

0.85

Labour
Mate

day

0.01

185.07

1.85

L-12

Mazdoor (Skilled) labour for drilling

day

0.08

206.99

16.56

L-15

Mazdoor (Skilled) labour for fixing nipple and sealing inlets

day

0.08

206.99

16.56

L-15

Mazdoor for cutting and removing of nipples

day

0.04

177.07

7.08

L-13

Add 10 per cent of labour cost for drilling holes etc


c)

Overhead charges @ 0.3 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

4.21
15.82
6.86

Rate per No. = (a+b+c+d)

75.42
say

16.5

Sealing of cracks/porous concrete by injection process


nipples/Grouting complete as per Technical Specification.

2806

Cement Grout
Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage
Admixtures (anti shrinkage compound) @ 20 per cent of cost of cement
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Machinery
Grout pump with agitator and accessories
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per kg = (a+b+c+d+e)

kg

1.10

5.79

day
day
day

0.08
0.10
0.10

185.07
206.99
177.07

14.81
20.70
17.71

L-12
L-15
L-13

hour

0.10

112.77

11.28
21.64
9.38
103.15
103.00

M-111

say
B

Cement Mortar (1:1) Grouting


Unit = kg
Taking output = 1 kg
a) Material
Cement including 10 per cent wastage
Sand including 10 per cent wastage
Admixtures (anti shrinkage compound)

75.00

through

kg
kg

0.55
0.55

5.79
0.14

day
day
day

0.08
0.10
0.10

185.07
206.99
177.07

14.81
20.70
17.71

L-12
L-15
L-13

hour

0.10

112.77

M-111

say

11.28
20.52
8.89
97.79
98.00

@ 20 per cent of cost of cement

Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Machinery
Grout pump with agitator and accessories
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per kg = (a+b+c+d+e)

6.37 M-081/1000
1.27

3.18 M-081/1000
0.07 M-005/1500
0.64

b)

16.6

2800

Patching of damaged concrete surface with polymer concrete and curing


compounds, initiator and promoter, available in present formulations, to be
applied as per instructions of manufacturer and as approved by the Engineer.

Unit = sqm
Taking output = 10 sqm for an average thickness of 25mm.
a)

b)

Labour
Mate
Mazdoor (Skilled)
Mazdoor
Material
Pre-packed polymer concrete based on epoxy system complete with curing
compound, intiator and promoter including 5 per cent wastage.

Machinery
Grout pump with agitator and accessories
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10

day
day
day

0.06
0.75
0.75

185.07
206.99
177.07

11.10
155.24
132.80

L-12
L-15
L-13

kg

315.00

#VALUE!

#VALUE!

M-145

2.00

112.77

225.54
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

M-111

c)

hour

say

306

Note

This item is a proprietory item available in market as pre-packed polymer concrete


and is required to be applied as per instructions of the manufacturer.

307

16.7

2803

Sealing of crack / porous concrete with Epoxy Grout by injection through


nipples complete as per clause 2803.1.
Unit = kg
Taking output = 1 kg
a)

Material
Epoxy including 10 per cent wastage
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Machinery
Epoxy Injection gun
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per kg = (a+b+c+d+e)

kg

1.10

282.81

311.09

M-095

day
day
day

0.08
0.10
0.10

185.07
206.99
177.07

14.81
20.70
17.71

L-12
L-15
L-13

hour

0.10

Value

#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

P&M-078

say
16.8

2804

Applying epoxy mortar over leached, honey combed and spalled concrete
surface and exposed steel reinforcement complete as per Technical
Specification
Unit = sqm
Taking output = 10 sqm
Assume average 10mm thickness of epoxy mortar
a) Material
Epoxy resin-hardener mix for prime coat
Epoxy mortar
Epoxy resin -hardener mix for seal coat.
Add 3 per cent cost of material for other consumables like acetone etc and to
cover wastage.
Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10

kg
kg
kg

2.50
2.20
2.00

481.82
169.69
481.82

1204.56
373.31
963.65
76.25

M-098
M-096
M-098

day
day
day

0.04
0.50
0.50

185.07
206.99
177.07

L-12
L-15
L-13

say

7.40
103.50
88.54
845.16
366.23
4028.58
402.86
403.00

b)

16.9

2807

Removal of defective concrete, cleaning the surface thoroughly, applying the


shotcrete mixture mechanically with compressed air under pressure,
comprising of cement, sand, coarse aggregates, water and quick setting
compound in the proportion as per clause 2807.1., sand and coarse
aggregates conforming to IS: 383 and table 1 of IS: 9012 respectively, water
cement ratio ranging from 0.35 to 0.50, density of gunite not less than 2000
kg/cum, strength not less than 25 Mpa and workmanship conforming to clause
2807.6.
unit: sqm
Taking output = 10 sqm, 40 mm average thickness.
a) Labour
Mate
Mazdoor
Mazdoor (Skilled)
b) Machinery
Air compressor 250 cfm
Shotcreteing equipment
water tanker 6 KL capacity
c) Material
Cement
Sand
Coarse aggregate of size 4.75mm
Quick setting compound
Water
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 10 sqm = a+b+c+d+e
Rate per sqm = (a+b+c+d+e)/10

day
day
day

0.04
0.50
0.50

185.07
177.07
206.99

7.40
88.54
103.50

L-12
L-13
L-15

hour
hour
hour

1.00
1.00
0.02

293.76
Value
111.24

293.76
#VALUE!
2.22

P&M-001
P&M-076
P&M-060

kg
cum
cum
kg
KL

120.00
0.15
0.15
2.50
0.10

5.789
203.75
261.00
99.20
167.07

694.74 M-081/1000
30.56
M-005
39.15
M-024
247.99
M-147
16.71
M-189
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

say
16.10

2800

Applying pre-packed cement based polymer mortar of strength 45 Mpa at 28


days for replacement of spalled concrete
Unit = sqm
Taking output = 10 sqm
Assumed thickness - 10 mm
a) Material
Acrylic polymer bonding coat

Litre
308

1.40

129.48

181.27

M-057

pre-packed cement based polymer mortar of strength 45 Mpa at 28 days

b)

Add 3 per cent of (a ) above for wastage.


Labour

kg

12.00

#VALUE!

#VALUE!
#VALUE!

309

M-145

Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
16.11

2805

day
day
day

0.04
0.50
0.50

185.07
206.99
177.07

L-12
L-15
L-13

say

7.40
103.50
88.54
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

481.82

3854.58

M-098

Eproxy bonding of new concrete to old concrete


Unit = sqm
Taking output = 10 sqm
a)

Material
Epoxy resin with pot life not less than 60-90 minutes and satisfying testing as
per clause 2803.9

kg

8.00

Add 3 per cent of (a ) above for wastage.

115.64

b)

Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 sqm = a+b+c+d
Rate per sqm = (a+b+c+d)/10
16.12

2810

day
day
day

0.04
0.50
0.50

185.07
206.99
177.07

L-12
L-15
L-13

say

7.40
103.50
88.54
1250.90
542.05
5962.60
596.26
596.00

Providing external prestressing with high tensile steel wires/strands including


drilling for passage of prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per drawing and Technical
Specification
Span assumed: 25 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 1 MT
Assume 12.7mm dia. Strand in 12T13 system. Weight-9.42 kg/m of cable.
a)

Material
HTS strand including 5 per cent wastage and extra length for jacking

tonne

1.05

62418.78

65539.72

M-119

HDPE pipes 75mm dia including 5 per cent wastage

metre

112.00

152.45

17074.37

M-114

kg

Cement for grouting


Tube anchorage set complete with bearing plate, permanent wedges etc
Epoxy
MS plates for deviator (where deviator blocks are not provided)

b)

400.00

5.789

each

8.00

34.35

kg

6.00

tonne

2.10

274.83

M-187

282.81

1696.85

M-095

46527.33

97707.40

M-179

Add 20 per cent cost of material for other materials like lead sheet, sleeves,
deviator fixtures etc.
Labour

i) For making holes in the structure .


Mate
Mazdoor Semi-skilled)
Mazdoor
ii) For making and fixing anchorages for cables and placement of cables .
Mate
Blacksmith
Mazdoor
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor
iv) For grouting
Mate/Supervisor
Mason
Mazdoor
c) Machinery
Stressing jack with pump
Grouting pump with agitator
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate per MT = (a+b+c+d+e)

310

2315.79 M-081/1000

36921.79

day
day
day

0.24
3.00
3.00

185.07
180.07
177.07

44.42
540.21
531.21

L-12
L-14
L-13

day
day
day

0.44
3.00
8.00

185.07
234.29
177.07

81.43
702.87
1416.56

L-12
L-02
L-13

day
day
day

0.13
0.70
2.65

185.07
238.29
177.07

24.06
166.80
469.24

L-12
L-08
L-13

day
day
day

0.13
0.70
2.65

185.07
234.29
177.07

24.06
164.00
469.24

L-12
L-11
L-13

hour
hour

4.00
1.35

116.10
112.77

464.40
152.24
68034.45
29481.59
324297.52

say

324298.00

P&M-040
M-111

16.13

2810

Providing external prestressing with high tensile steel wires/strands including


drilling for passage of prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per drawing and Technical
Specification
Span assumed: 50 m
No. of cables: 4 no.
No. of anchorages : 8 no.
Unit = MT
Taking output = 3.10 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of cable.
a)

Material
HTS strand including 5 per cent wastage and extra length for jacking

tonne

3.10

62418.78

193498.21

HDPE pipes 90mm dia including 5 per cent wastage

metre

Cement for grouting


Tube anchorage set complete with bearing plate, permanent wedges etc

tonne
each

Epoxy
MS plates for deviator (where deviator blocks are not provided)

kg
tonne

224.00

152.45

34148.74

M-115

1.01
8.00

5789.47
34.35

5847.37
274.83

M-081
M-187

10.00
7.00

282.81
46527.33

2828.09
325691.33

M-095
M-179

Add 20 per cent cost of material for other materials like lead sheet, sleeves,
deviator fixtures etc.
b) Labour
i) For making holes in the structure .
Mate
Mazdoor Semi-skilled)
Mazdoor
ii) For making and fixing anchorages for cables and placement of cables .
Mate
Blacksmith
Mazdoor
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor
iv) For grouting
Mate/Supervisor
Mason
Mazdoor
c) Machinery
Stressing jack with pump
Grouting pump with agitator
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 3.10 MT = a+b+c+d+e
Rate per MT = (a+b+c+d+e)/3.10
16.14

2810

M-119

112457.71

day
day
day

0.08
8.00
8.00

185.07
180.07
177.07

14.81
1440.56
1416.56

L-12
L-14
L-13

day
day
day

1.28
7.00
25.00

185.07
234.29
177.07

236.89
1640.03
4426.75

L-12
L-02
L-13

day
day
day

0.20
1.00
4.00

185.07
238.29
177.07

37.01
238.29
708.28

L-12
L-08
L-13

day
day
day

0.26
1.50
5.00

185.07
234.29
177.07

48.12
351.44
885.35

L-12
L-11
L-13

hour
hour

7.00
3.00

116.10
112.77

P&M-040
M-111

say

812.70
338.31
206202.41
89354.38
982898.17
317063.93
317064.00

Providing external prestressing with high tensile steel wires/strands including


drilling for passage of prestessing steel, all accessories for stressing and
stressing operation and grouting complete as per drawing and Technical
Specification
Span assumed: 100 m
No. of cables: 6 no.
No. of anchorages : 12 no.
Unit = MT
Taking output = 9.28 MT
Assume 12.7mm dia. Strand in 19T13 system. Weight-14.73 kg/m of cable.
a)

Material
HTS strand including 5 per cent wastage and extra length for jacking

tonne

9.28

62418.78

579246.24

M-119

HDPE pipes 90 mm dia including 5 per cent wastage


Cement for grouting

metre
tonne

672.00
3.04

152.45
5789.47

102446.23
17600.00

M-115
M-081

Tube anchorage set complete with bearing plate, permanent wedges etc

each

12.00

34.35

412.24

M-187

kg

14.00

282.81

3959.33

M-095

tonne

20.00

46527.33

930546.67

M-179

Epoxy
MS plates for deviator (where deviator blocks are not provided)
Add 20 per cent cost of material for other materials like lead sheet, sleeves,
deviator fixtures etc.
311

326842.14

b) Labour
i) For making holes in the structure .
Mate

day

312

1.72

185.07

318.32

L-12

16.15

2808

Mazdoor Semi-skilled)
Mazdoor
ii) For making and fixing anchorages for cables and placement of cables .

day
day

18.00
25.00

180.07
177.07

3241.26
4426.75

L-14
L-13

Mate
Blacksmith
Mazdoor
iii) For prestressing
Mate/Supervisor
Fitter
Mazdoor
iv) For grouting
Mate/Supervisor
Mason
Mazdoor
c) Machinery
Stressing jack with pump
Grouting pump with agitator
d) Overhead charges @ 0.3 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 9.28 MT = a+b+c+d+e
Rate per MT = (a+b+c+d+e)/9.28

day
day
day

4.00
20.00
80.00

185.07
234.29
177.07

740.28
4685.80
14165.60

L-12
L-02
L-13

day
day
day

0.30
1.50
6.00

185.07
238.29
177.07

55.52
357.44
1062.42

L-12
L-08
L-13

day
day
day

1.00
5.00
20.00

185.07
234.29
177.07

185.07
1171.45
3541.40

L-12
L-11
L-13

hour
hour

10.00
10.00

116.10
112.77

P&M-040
M-111

say

1161.00
1127.71
599187.86
259648.07
2856128.81
307772.50
307773.00

P&M-084
L-12
L-15
L-13
M-195

Replacement of Bearings complete as per Technical Specification


Unit = No
Taking output = 3 No.
Lifting of superstructure span by jacking up from below i.e. by placing the jacks on
pier/abutment caps for span length of 30m.
a)

Lifting of span
i) Hire charges for jack of 40 tonne lifting capacity.
Mate
Mazdoor (Skilled)
Mazdoor
v) Wooden packing
b) Replacement of bearing
Cost of bearing.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of repair of 3 bearings = a+b+c+d
Rate of repair per bearing = (a+b+c+d)/3

16.16

Note

The work entails replacement of all the bearings on one side of the span.

2808

Rectification of Bearings as per Technical Specifications

each
day
day
day
cum

3.00
0.64
4.00
12.00
0.15

758.16
185.07
206.99
177.07
#VALUE!

2274.48
118.44
827.96
2124.84
#VALUE!

each

3.00

55883.28

say

167649.83
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

M-065

Unit = 1 No
Taking output = 3 No.
a) Lifting of superstructure span by jacking up from below i.e. by placing the
jacks on pier/abutment caps for span length of 30m.
i) Hire charges for jack of 40 tonne lifting capacity.
ii) Mate
iii) Mazdoor (Skilled)
iv) Mazdoor
v) Wooden packing
b) Cost of parts to be replaced for 3 bearings.
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of repair of 3 bearings = a+b+c+d
Rate of repair per bearing = (a+b+c+d)/3

each

3.00

758.16

2274.48

P&M-084

day
day
day
cum
each

0.64
4.00
12.00
0.15
3.00

185.07
206.99
177.07
#VALUE!
#VALUE!

118.44
827.96
2124.84
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!
#VALUE!

L-12
L-15
L-13
M-195
M-064

say
Note
16.17

The rectification of 3 bearings included in this analysis are on the same side of the
span.
Replacement of Expansion Joints complete as per drawings
Unit -1 RM
Taking output = 12 RM
a)

Material
Epoxy for bonding new concrete to old concrete @ 0.8 kg/sqm
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i)

b)

Labour

313

kg
cum

9.60
3.60

282.81
4298.00

2714.97
M-095
15472.80 Item 14.1(C)

Removal of old expansion joint including breaking of concrete, cutting of lugs and
shifting of broken material etc.
Mate
Mazdoor
Mazdoor (Skilled)
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for replacement of 12 RM = a+b+c+d

day
day
day

0.26
6.00
0.50

185.07
177.07
206.99

L-12
L-13
L-15

say

48.12
1062.42
103.50
5820.54
2522.23
27744.57
2312.05
2312.00

Rate per RM = (a+b+c+d)/12


Note

16.18

The rate for the installation of new expansion joints may be taken from the chapter
on superstructure. Broken concrete will have to be replaced which has been
included in this analysis.
Replacement of Damaged Concrete Railing.
Unit = RM
Taking output = 10 RM
a) Labour
Labour for dismantling old railing and disposal of dismantled material.
Mate
Mazdoor
b) Machinery
Tractor-trolley for disposal of dismantled material
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10

Note
16.19

day
day

0.20
5.00

185.07
177.07

37.01
885.35

L-12
L-13

hour

1.00

171.02

P&M-053

say

171.02
328.01
142.14
1563.54
156.35
156.00

The rate for the provision of new railing may be adopted from the chapter on
superstructure.
Replacement of Crash Barrier.
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled material.
Mate
Mazdoor
b) Machinery
Tractor-trolley for disposal of dismantled material
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10

Note
16.20

day
day

0.40
10.00

185.07
177.07

74.03
1770.70

L-12
L-13

hour

1.00

171.02

P&M-053

say

171.02
604.72
262.05
2882.52
288.25
288.00

The rate for the construction of new crash barrier may be adopted from chapter 8 on
Traffic and Transportation.
Replacement of Damaged Mild Steel Railing
Unit = RM
Taking output = 10 M
a) Labour
Labour for dismantling old railing and disposal of dismantled material.
Mate
Mazdoor
b) Machinery
Tractor-trolley for disposal of dismantled material
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 10 m = a+b+c+d
Rate per metre = (a+b+c+d)/10

16.21

day
day

0.16
4.00

185.07
177.07

29.61
708.28

L-12
L-13

hour

1.00

171.02

P&M-053

say

171.02
272.67
118.16
1299.74
129.97
130.00

185.07

7.40

Repair of Crash Barrier


Repair of concrete crash barrier with cement concert of M-30 grade by cutting and
trimming the damaged portion to a regular shape, cleaning the area to be repaired
thoroughly, applying cement concert after erection of proper form work.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent of the volume of
concrete .This will require 0.30 cum of concrete.
a)

Manpower*
Mate

day
314

0.04

L-12

Mazdoor

day

1.00

177.07

cum

0.30

4298.00

177.07

L-13

* For dismantling and trimming the surface to a regular shape and removal of
damaged material.
b)

Material
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i)

1289.40 Item 14.1(C)


DIR used item

This may be priced based on the rate given the chapter of superstructure.
c)

Overhead charges @ 0.3 on (a)

442.16

d)

Contractor's profit @ 0.1 on (a+c)

191.60

Cost for 10 m = a+b+c+d

2107.64

Rate per m = (a+b+c+d)/10

210.76
say

16.22

211.00

Repair of RCC Railing


Carrying out repair of RCC M30 railing to bring it to the original shape.
Unit = Running meter.
Taking output = 10 M.
It is assumed that damage is to the extent of 10 per cent .
a)

b)

Material
M-30 grade cement concrete excluding OH & CP (Rate as per items 14.1 C (i)

cum

0.10

4298.00

429.80 Item 14.1(C)

HYSD bar reinforcement Rate as per item No 14.2(Excluding OH & CP)

tonne

0.013

51064.00

663.83 Item 14.2 A


DIR used item

Labour*
Mate

day

0.016

185.07

2.96

L-12

mazdoor

day

0.20

177.07

35.41

L-13

say

339.60
147.16
1618.77
161.88
162.00

* For dismantling and trimming the surface to a regular shape and removal of
damaged material.
c) Overhead charges @ 0.3 on (b)
d) Contractor's profit @ 0.1 on (b+c)
Cost for 10 m = a+b+c+d
Rate per m = (a+b+c+d)/10

16.23

Repair of Steel Railing


Repair of steel railing to bring it to the original shape
It is assumed that the damage to the steel railing is to the extent of 10 per cent .
Unit = Running meter.
Taking output = 10 M.
a)

Material
Mild steel ISMC series
Flat iron
MS Bolt and nuts
Add 5 per cent of cost of material for painting.
b) Labour
Mate
Mazdoor (Skilled)
Mazdoor
c) Overhead charges @ 0.3 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost of repair for10m = a+b+c+d
Cost of meter = (a+b+c+d)/10

kg
kg
kg

29.00
10.00
1.00

46.53
46.53
45.42

day
day
day

0.016
0.20
0.20

185.07
206.99
177.07

say

315

1349.29 M-179/1000
465.27 M-179/1000
45.42
M-130
93.00
2.96
41.40
35.41
609.83
264.26
2906.85
290.68
291.00

L-12
L-15
L-13

Sub - Analysis_B

Sr No

Ref. to
MoRTH
Spec.

3.1

301

Description

Unit

Quantity

Rate Rs

Cost Rs

Remarks/
Input ref.

Excavation in Soil by Manual Means .

SUB ANA
-B (1)

Excavation for roadway in soil using manual means


including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000
metres.Including royality @ Rs. 24.00 per cum but
excluding the cost of watering , rolling & compaction
Note In case there is a situation where the crosssection is of cut and fill and cut earth is required
to be used in embankment in the immediate
vicinity, the item of carriage in the truck shall be
omitted.
Unit = cum
Taking output = 120 cum
a)

Labour
Mate

c)

Mazdoor
Machinery
Truck 5.5 cum capacity
Overhead charges @ 0.1 on (a+b)

d)

Contractor's profit @ 0.1 on (a+b+c)

b)

day

1.800

185.07

333.13

L-12

day

45.000

177.07

7968.15

L-13

hour

10.000

0.00

0.00
830.13

P&M-057

913.14

Cost of 120 cum = a+b+c+d

10044.54

Rate per cum = (a+b+c+d)/120


Royality @ Rs. 24.00 per Cum
Rate per cum
3.1

301

SUB ANA
-B (2)

say

108.00

Excavation in Soil by Manual Means .


Excavation for roadway in soil using manual means
including loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000
metres.
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
Royality @ Rs. 24.00 per Cum
Rate per cum

3.2

83.70
24.00

301

SUB ANA
-B

Excavation in Ordinary Rock by Manual Means


Excavation in ordinary rock using manual means
including loading in a truck and carrying of excavated
material to embankment site with in all lifts and leads
upto 1000 metres (including royality @ Rs. 24.00 per
cum but excluding watering, rolling & compaction)
Unit = cum
Taking output = 120 cum

RCD/SOR_2nd Edition

day
day

1.800
45.000

185.07
177.07

333.13
7968.15

L-12
L-13

hour
hour
hour

10.000
1.500
0.800

773.00
665.00
111.24

7730.00
997.50
88.99

P&M-057
P&M-044
P&M-060

KL

4.800

167.07

801.93
1791.97
1971.17

M-189

say

21682.83
180.69
24.00
205.00

Sub - Analysis_B
a)

Labour
Mate
Mazdoor
b) Machinery
c) Overhead charges @ 0.1 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Royality @ Rs. 24.00 per Cum
Rate per cum

day
day

2.800
70.000

185.07
177.07

518.20
12394.90

say

1291.31
1420.44
15624.85
130.21
24.00
154.21
154.00

L-12
L-13

Note In case there is a situation where the cross-section is


of cut and fill and cut earth is required to be used in
embankment in the immediate vicinity, the item of
carriage in the truck shall be omitted.
3.2

301

SUB ANA
-B

Excavation in Ordinary Rock by Manual Means


Excavation in ordinary rock using manual means
including loading in a truck and carrying of excavated
material to embankment site with in all lifts and leads
upto 1000 metres (including royality @ Rs. 24.00 per
cum, watering, rolling & compaction - from immediate
vicinity)
Unit = cum
Taking output = 120 cum
a) Labour
Mate
Mazdoor
b) Machinery
Truck 5.5 cum capacity
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 120 cum = a+b+c+d
Rate per cum = (a+b+c+d)/120
Royality @ Rs. 24.00 per Cum
Rate per cum

3.6

301

SUB ANA
-B

2.800
70.000

185.07
177.07

518.20
12394.90

L-12
L-13

hour
hour
hour

10.000
1.500
0.800

773.00
665.00
111.24

7730.00
997.50
88.99

P&M-057
P&M-044
P&M-060

KL

4.800

167.07

M-189

say

801.93
2253.15
2478.47
27263.13
227.19
24.00
251.19
251.00

Excavation in Soil using Hydraulic Excavator CK


90 and Tippers with Disposal upto 1000 metres.
Excavation for roadwork in soil with hydraulic
excavator of 0.9 cum bucket capacity including
cutting and loading in tippers, trimming bottom and
side slopes, in accordance with requirements of
lines, grades and cross sections, and transporting to
the embankment location within all lifts and lead upto
1000m (including royality @ Rs. 24.00 per cum,
watering, rolling & compaction)
Unit = cum
Taking output = 360 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @
60 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)

RCD/SOR_2nd Edition

day
day

day
day

0.080
2.000

185.07
177.07

14.81
354.14

L-12
L-13

hour

6.000

1516.32

9097.92

P&M-026

hour
hour
hour

16.000
4.500
2.400

873.00
665.00
111.24

13968.00
2992.50
266.98

P&M-048
P&M-044
P&M-060

KL

14.400

167.07

2405.78
2910.01
3201.01

M-189

Sub - Analysis_B
Cost for 360 cum = a+b+c+d
Rate per cum = (a+b+c+d)/360
Royality @ Rs. 24.00 per Cum
Rate per cum
3.7

301

SUB ANA
-B

Excavation in Ordinary Rock using Hydraulic


Excavator CK-90 and Tippers with Disposal upto
1000 metres.
Excavation for roadway in ordinary rock with
hydraulic excavator of 0.9 cum bucket capacity
including cutting and loading in tippers, transporting
to embankment site within all lifts and lead upto 1000
m, trimming bottom and side slopes in accordance
with requirements of lines, grades and cross sections
(including royality @ Rs. 24.00 per cum , watering,
rolling & compaction)
Unit = cum
Taking output = 240 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity
@ 36 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 240 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/240
Royality @ Rs. 24.00 per Cum
Rate per cum

3.10
SUB ANA
-B

say

35211.15
97.81
24.00
121.81
122.00

301

day
day

0.080
2.000

185.07
177.07

14.81
354.14

L-12
L-13

hour

6.000

1516.32

9097.92

P&M-026

hour
hour
hour

11.000
3.000
1.600

873.00
665.00
111.24

9603.00
1995.00
177.98

P&M-048
P&M-044
P&M-060

KL

9.600

167.07

M-189

say

1603.85
2284.67
2513.14
27644.51
115.19
24.00
139.19
139.00

Excavation in Marshy Soil


Excavation for roadway in marshy soil with hydraulic
excavator 0.9 cum bucket capacity including cutting
and loading in tippers and disposal with in all lifts and
lead upto 1000 metres, trimming of bottom and side
slopes in accordance with requirements of lines,
grades and cross sections (including royality @ Rs.
24.00 per cum , watering, rolling & compaction)
Unit = cum
Taking output = 300 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator 0.90 cum bucket capacity
@ 50 cum per hour
Tipper 5.5 cum capacity, 4 trips per hour.
Smooth wheel roller @ 70 cum per hour
Water Tanker @ 6.0 KL capicity
c) Materials
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)

day
day

0.080
2.000

185.07
177.07

14.81
354.14

L-12
L-13

hour

6.000

1516.32

9097.92

P&M-026

hour
hour
hour

13.640
3.750
2.000

873.00
665.00
111.24

11907.72
2493.75
222.48

P&M-048
P&M-044
P&M-060

KL

12.000

167.07

2004.82
2609.56
2870.52

M-189

Cost for 300 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/300
Royality @ Rs. 24.00 per Cum
Rate per cum
say
3.16

305

RCD/SOR_2nd Edition

Construction of Embankment
obtained from Borrowpits

with Material

31575.72
105.25
24.00
129.25
129.00

Sub - Analysis_B
SUB ANA
-B

Construction of embankment with approved material


obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to required
slope and compacting to meet requirement of table
300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic Excavator1 cum bucket capacity @
60 cum per hour
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover
cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour
Motor grader for grading @ 100 cum per hour
Water tanker6 KL capacity
Smooth wheel roller 8-10 tonnes @ 70 cum per
hour
c) Material
Cost of water
Compensation & Royality for earth taken from
private land
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100

day
day

0.040
1.000

185.07
177.07

7.40
177.07

L-12
L-13

hour

1.670

1516.32

2532.25

P&M-026

tonne.km

160 x L

2.68

428.54
42.85

P&M-047

hour

0.500

3135.24

1567.62

P&M-014

hour

1.000

2519.00

2519.00

P&M-032

hour
hour

4.000
1.430

111.24
665.00

444.96
950.95

P&M-060
P&M-044

KL
cum

24.000
100.000

167.07
25.10

4009.64
2510.00

M-189
M-092

say

1519.03
1670.93
18380.25
183.80
184.00

Compensation for earth will vary from place to place


and will have to be assessed realistically as per
particular ground situation. In case earth is available
from Govt. land, compensation for earth will not be
required. The position is required to be clearly stated
in the cost estimate.
3.17

305

SUB ANA
-B

Construction of Embankment with Material


Deposited from Roadway Cutting
Construction of embankment with approved
materials deposited at site from roadway cutting and
excavation from drain and foundation of other
structures graded and compacted to meet
requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour
Motor grader for grading @ 100 cum per hour
Water tanker6 KL capacity
Smooth wheel roller 8-10 tonnes @ 56 cum per
hour
c) Material
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Rate for 100 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/100

day
day

0.020
0.500

185.07
177.07

3.70
88.54

hour

0.500

3135.24

1567.62

P&M-014

hour

1.000

2519.00

2519.00

P&M-032

hour
hour

4.000
1.430

111.24
665.00

444.96
950.95

P&M-060
P&M-044

KL

24.000

167.07

4009.64
958.44
1054.28
11597.13
115.97

say

RCD/SOR_2nd Edition

116.00

L-12
L-13

M-189
M-189
M-092

Sub - Analysis_B
In case the earth cutting is done by dozer and
pushed for filling in the embankment, the input of
dozer in the cost of embankment shall be deleted as
the same is already provided in the cost of
excavation. However, if the earth is dumped by
tippers from roadway cutting, the input of dozer for
spreading is required to be provided.
3.18

305

Construction of Subgrade and Earthen Shoulders

SUB ANA
-B

Construction of sub-grade and earthen shoulders


with approved material obtained from borrow pits
with all lifts & leads, transporting to site, spreading,
grading to required slope and compacted to meet
requirement of table No. 300-2
Unit = cum
Taking output = 100 cum
a) Labour
Mate
Mazdoor
b) Machinery
Hydraulic excavator1 cum bucket capacity @
60 cum per hour
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover
cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour
Motor grader for grading @ 50 cum per hour
Water tanker with 6 km lead
Smooth wheel roller 8-10 tonnes @ 56 cum per
hour
c) Material
Cost of water
Compensation & Royality for earth taken from private
land
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)

day
day

0.040
1.000

185.07
177.07

7.40
177.07

L-12
L-13

hour

1.670

1516.32

2532.25

P&M-026

tonne.km

175xL

2.68

468.72
46.87

P&M-047

hour

0.500

3135.24

1567.62

P&M-014

hour

2.000

2519.00

5038.00

P&M-032

hour
hour

4.000
1.790

111.24
665.00

444.96
1190.35

P&M-060
P&M-044

KL
cum

24.000
100.000

167.07
25.10

4009.64
2510.00

M-189
M-092

1799.29
1979.22

Cost for 100 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/100
3.19

SUB ANA
-B

305.3.4

say

21771.39
217.71
218.00

Compacting Original Ground


Compacting original ground supporting subgrade
Case-I Loosening of the ground upto a level of 500 mm
below the sub-grade level, watered, graded and
compacted in layers to meet requirement of table
300-2 for sub-grade construction.
Unit = cum
Taking output = 600 cum
a) Labour
Mate
Mazdoor
b) Machinery
Tractor with ripper attachment
Motor grader for grading
Water tanker 6 KL capacity
Smooth wheel roller 8-10 tonnes @ 56 cum per
hour
c) Material
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)
Cost for 600 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/600

RCD/SOR_2nd Edition

day
day

0.120
3.000

185.07
177.07

22.21
531.21

L-12
L-13

hour
hour
hour
hour

9.000
6.000
4.000
10.710

285.12
2519.00
111.24
665.00

2566.08
15114.00
444.96
7122.15

P&M-055
P&M-032
P&M-060
P&M-044

KL

24.000

167.07

4009.64
2981.02
3279.13
36070.40
60.12

M-189

say

60.00

Sub - Analysis_B
3.19

Compacting original ground supporting


embankment
Case-II Loosening, leveling and Compacting original ground
supporting embankment to facilitate placement of
first layer of embankment, scarified to a depth of 150
mm, mixed with water at OMC and then compacted
by rolling so as to achieve minimum dry density as
given in Table 300-2 for embankment construction.

SUB ANA
-B

Unit = cum
Taking output = 600 cum
a)

b)

c)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor

day

2.000

177.07

354.14

L-13

Machinery
Tractor with ripper attachment

hour

6.000

285.12

1710.72

P&M-055

Smooth wheel roller 8-10 tonnes @ 56 cum per


hour
Water tanker6 KL capacity

hour

10.710

665.00

7122.15

P&M-044

hour

4.000

111.24

444.96

P&M-060

KL

24.000

167.07

4009.64

M-189

Material
Cost of water

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

1365.64
1502.21

Cost for 600 cum = (a+b+c+d+e)

16524.26

Rate per sqm = (a+b+c+d+e)/600

27.54
say

5.11

512

Sub Analysis
for Type
'B"

28.00

Close Graded Premix Surfacing/Mixed Seal


Surfacing
Mechanical means using HMP of appropriate
capacity not less than 75 tonnes/hour.
Case I Providing, laying and rolling of close-graded premix
surfacing material of 20 mm thickness composed of
11.2 mm to 0.09 mm (Type-a) or 13.2 mm to 0.09
mm (Type-b)
aggregates using penetration grade
bitumen to the required line, grade and level to serve
as wearing course on a previously prepared base,
including mixing in a suitable plant, laying and rolling
with a Smooth wheeled roller 8-10 tonne capacity,
and finishing to required level and grade.

Unit = sqm
Taking output = 10250 sqm (205 cum)
a) Labour

b)

Mate

day

0.840

185.07

155.46

L-12

Mazdoor working with HMP, road sweeper,


paver and roller
Skilled mazdoor for checking line & levels

day

16.000

177.07

2833.12

L-13

day

5.000

206.99

1034.95

L-15

i) HMP of appropicate capacity - 75 t per hour

hour

6.000

33841.00

203046.00

P&M-022

ii) Electric Generator Set 250 KVA

hour

6.000

3237.00

19422.00

P&M-081

iii) Front end loader 1 cum bucket capacity

hour

6.000

1188.00

7128.00

P&M-017

tonne.km

450 x L

2.68

Machinery

iv) Tipper 10 tonne capacity


Add 10 per cent of cost of carriage to cover cost of
loading and unloading
v) Paver finisher hydrostatic with sensor
attachment
iv) Smooth wheeled8-10 tonnes weight
c)

Material

Type - B

RCD/SOR_2nd Edition

1205.28 Lead =1 km &


P&M-047
120.53

hour

6.000

3128.00

18768.00

P&M-034

hour

6.000

665.00

3990.00

P&M-044

Sub - Analysis_B
Bitumen @ 19 kg per 10 sqm

d)

Stone crushed aggregates 13.2 mm to 0.09


mm @ 0.27 cum per 10 sqm
Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

tonne

19.480

52269.11

1018202.19

M-074

cum

276.750

624.00

172692.00

M-042

144859.75
159345.73

Cost for 10250 sqm = a+b+c+d+e

1752803.01

Rate per sqm = (a+b+c+d+e)/10250

171.01
For Type 'B'

say

171.00

With Smooth wheel Roller


4.9

404

Water Bound Macadam

SUB ANA
-B

Providing, laying, spreading and compacting stone


aggregates of specific sizes to water bound
macadam specification including spreading in
uniform thickness, hand packing, rolling with 3
wheeled steel/ vibratory roller 8-10 tonnes in stages
to proper grade and camber, applying and brooming
requisite type of screening/ binding Materials to fill up
the interstices of coarse aggregate, watering and
compacting to the required density.
By Manual Means
A

Unit = cum
Taking output = 360 cum
a)

b)

Labour
Mate

day

10.080

185.07

1865.51

L-12

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

250.000

177.07

44267.50

L-13

Smooth 3 wheeled steel roller @ 30cum/hour

hour

12.000

665.00

7980.00

P&M-044

Water tanker 6 KL capacity

hour

24.000

111.24

2669.76

P&M-060

cum

435.600

465.37

202714.48

Type A 13.2 mm for grading-I @ 0.27 cum per


10 sqm
OR

cum

97.200

624.00

60652.80 M-042

Crushable type such as Moorum or Gravel for


grading-I @ 0.30 cum per 10 sqm

cum

108.000

119.64

12921.35

M-007

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Machinery

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading-I

4.9A
(i)

Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10
sqm for compacted thickness of 100 mm

M-039

Stone Screening

Binding material
Binding Material @ 0.08cum per 10 sqm for
grading I material
Cost of water
4.9A (i)

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

29689.04

e)

Contractor's profit @ 0.1 on (a+b+c+d)

32657.94

Cost for 360 cum = a+b+c+d+e

359237.39

Rate per cum = (a+b+c+d+e)/360

997.88
say

998.00

OR
4.9A (i)

Using Scrining Type-A (13.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 360 cum = a+b+c+d+e

RCD/SOR_2nd Edition

34806.75
38287.43
421161.73

Sub - Analysis_B
Rate per cum = (a+b+c+d+e)/360
4.9A

1169.89
say

1170.00

232136.59

Grading-II
(ii)

Aggregate
cum

435.600

532.91

Type A 13.2 mm for grading-II@ 0.12 cum per


10 sqm
OR

cum

57.600

624.00

35942.40 M-042

Crushable type such as Moorum or Gravel for


grading II &III @ 0.22 cum per 10 sqm
OR

cum

105.590

119.64

12633.01

Type B11.2 mm for grading-III @ 0.18 cum per


10 sqm
Binding material

cum

86.400

503.00

43459.20 M-041

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Grading-II 63 mm to 45 mm /Grading-III 53 mm
to 22.4 mm@ 0.91 cum per 10 sqm for
compacted thickness of 75 mm

M-038

Stone Screening

Binding Material @ 0.06cum per 10 sqm for


grading II material
Cost of water
4.9A (ii)

M-007

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

32602.42

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35862.66

Cost for 360 cum = a+b+c+d+e

394489.24

Rate per cum = (a+b+c+d+e)/360

1095.80
say

1096.00

OR
4.9A (ii)

Using Scrining Type-A (13.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

35277.93

e)

Contractor's profit @ 0.1 on (a+b+c+d)

38805.72

Cost for 360 cum = a+b+c+d+e

426862.89

Rate per cum = (a+b+c+d+e)/360

1185.73
say

4.9A (ii)

1186.00

Using Scrining Type-B (11.2mm agg.)


(c)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36029.61
39632.57

Cost for 360 cum = a+b+c+d+e

435958.22

Rate per cum = (a+b+c+d+e)/360


4.9A

1211.00
say

1211.00

240542.91

Grading-III
(iii)

Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per
10 sqm for compacted thickness of 75 mm

cum

435.600

552.21

M-036

Type B 11.2 mm for grading-III @ 0.18 cum per


10 sqm
OR

cum

86.400

503.00

43459.20 M-041

Crushable type such as Moorum or Gravel for


grading II &III @ 0.22 cum per 10 sqm

cum

105.590

119.64

12633.01

M-007

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening

Binding material
Binding Material @ 0.06cum per 10 sqm for
grading II material
Cost of water
4.9A (iii)

RCD/SOR_2nd Edition

Using Scrining Crushable type such as Moorum or Gravel

Sub - Analysis_B
(a)

d)

Overhead charges @ 0.1 on (a+b+c)

33443.05

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36787.35

Cost for 360 cum = a+b+c+d+e

404660.89

Rate per cum = (a+b+c+d+e)/360

1124.06
say

1124.00

OR
4.9A (iii)

Using Scrining Type-B (11.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36870.24
40557.26

Cost for 360 cum = a+b+c+d+e

446129.86

Rate per cum = (a+b+c+d+e)/360

1239.25
say

1239.00

0.680

185.07

125.85

L-12

( Anyone of the aggregate grading, screening and


binding material may be used as per design)
4.9
SUB ANA
-B

By Mechanical Means:
B

Unit = cum
Taking output = 360 cum
a)

Labour
Mate

day

Mazdoor skilled

day

2.000

206.99

413.98

L-15

Mazdoor

day

15.000

177.07

2656.05

L-13

Motor grader 110 HP @ 50cum/hr. for spreading

hour

7.200

2519.00

18136.80

P&M-032

Smooth 3 wheeled steel roller @ 30cum/hr.

hour

12.000

665.00

7980.00

P&M-044

Water tanker 6 KL capacity

hour

24.000

111.24

2669.76

P&M-060

cum

435.600

465.37

202714.48

Type A 13.2 mm for grading-I @ 0.27 cum per


10 sqm
OR

cum

97.200

624.00

60652.80 M-042

Crushable type such as Moorum or Gravel for


grading-I @ 0.30 cum per 10 sqm
Binding material

cum

108.000

119.64

12921.35

M-007

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

b)

Machinery

c) Material ( Refer table 400 - 7, 8 & 9 )


Grading - I

4.9B
(i)

Aggregate
Grading-I 90 mm to 45 mm@ 1.21cum per 10
sqm for compacted thickness of 100 mm

M-039

Stone Screening

Binding Material @ 0.08cum per 10 sqm for


grading I material
Cost of water
4.9B (i)

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

27167.61

e)

Contractor's profit @ 0.1 on (a+b+c+d)

29884.37

Cost for 360 cum = a+b+c+d+e

328728.07

Rate per cum = (a+b+c+d+e)/360

913.13
say

913.00

OR
4.9B (i)

Using Scrining Type-A (13.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

32285.32

e)

Contractor's profit @ 0.1 on (a+b+c+d)

35513.86

Cost for 360 cum = a+b+c+d+e

RCD/SOR_2nd Edition

390652.42

Sub - Analysis_B
Rate per cum = (a+b+c+d+e)/360
4.9B

1085.15
say

1085.00

232136.59

Grading - II
(ii)

Aggregate
cum

435.600

532.91

Type A 13.2 mm for grading-II@ 0.12 cum per


10 sqm
OR

cum

57.600

624.00

35942.40 M-042

Crushable type such as Moorum or Gravel for


grading II &III @ 0.22 cum per 10 sqm
OR

cum

105.590

119.64

12633.01

Type B11.2 mm for grading-III @ 0.18 cum per


10 sqm
Binding material

cum

86.400

503.00

43459.20 M-041

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Grading-II 63 mm to 45 mm /Grading-III 53 mm
to 22.4 mm@ 0.91 cum per 10 sqm for
compacted thickness of 75 mm

M-038

Stone Screening

Binding Material @ 0.06cum per 10 sqm for


grading II material
Cost of water
4.9B (ii)

M-007

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

30080.99

e)

Contractor's profit @ 0.1 on (a+b+c+d)

33089.08

Cost for 360 cum = a+b+c+d+e

363979.93

Rate per cum = (a+b+c+d+e)/360

1011.06
say

1011.00

OR
4.9B (ii)

Using Scrining Type-A (13.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

32756.49
36032.14

Cost for 360 cum = a+b+c+d+e

396353.58

Rate per cum = (a+b+c+d+e)/360

1100.98
say

4.9B (ii)

1101.00

Using Scrining Type-B (11.2mm agg.)


(c)

d)

Overhead charges @ 0.1 on (a+b+c)

33508.17

e)

Contractor's profit @ 0.1 on (a+b+c+d)

36858.99

Cost for 360 cum = a+b+c+d+e

405448.91

Rate per cum = (a+b+c+d+e)/360

1126.25
say

1126.00

240542.91

Grading - III

4.9B
(iii)

Aggregate
Grading-III 53 mm to 22.4 mm@ 0.91 cum per
10 sqm for compacted thickness of 75 mm

cum

435.600

552.21

M-036

Type B11.2 mm for grading-III @ 0.18 cum per


10 sqm
OR

cum

86.400

503.00

43459.20 M-041

Crushable type such as Moorum or Gravel for


grading II &III @ 0.22 cum per 10 sqm

cum

105.590

119.64

12633.01

M-007

cum

28.800

119.64

3445.69

M-007

KL

144.000

167.07

24057.82

M-189

Stone Screening

Binding material
Binding Material @ 0.06cum per 10 sqm for
grading II material
Cost of water

RCD/SOR_2nd Edition

Sub - Analysis_B
4.9B (iii)

Using Scrining Crushable type such as Moorum or Gravel


(a)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

30921.62
34013.78

Cost for 360 cum = a+b+c+d+e

374151.57

Rate per cum = (a+b+c+d+e)/360

1039.31
say

1039.00

OR
4.9B (iii)

Using Scrining Type-B (11.2mm agg.)


(b)

d)

Overhead charges @ 0.1 on (a+b+c)

e)

Contractor's profit @ 0.1 on (a+b+c+d)

34348.81
37783.69

Cost for 360 cum = a+b+c+d+e

415620.55

Rate per cum = (a+b+c+d+e)/360


4.10

405

1154.50
say

1155.00

769.89
413.98
18061.14

Crushed Cement Concrete Sub-base / Base

SUB ANA
-B

Breaking and crushing of material obtained by


breaking damaged cement concrete slabs to size
range not exceeding 75 mm as specified in table
400.7 transporting the aggregates obtained from
breaking of cement concrete slabs at a lead of L km.,
laying and compacting the same as sub base/ base
course, constructed as WBM to clause 404 except
the use of screening or binding Material.
Unit = cum
Taking output =360 cum
a) Labour
Mate
Mazdoor skilled
Mazdoor for crushing broken cement concrete
pavement/slabs into aggregate
b) Machinery
Motor Grader,110 HP @ 50 cum/hr.
Smooth 3 wheeled steel roller @ 30cum/hr.
Front end loader 1 cum bucket capacity
Tipper 10 tonne capacity
Add 10 per cent of cost of carriage to cover
cost of loading and unloading
Water tanker 6 KL capacity with 5 km lead @ 1
trip per hour
c) Material
Material available from dismantled concrete slab
after crushing / breaking and only carriage is
required to be provided
Cost of water
d) Overhead charges @ 0.1 on (a+b+c)
e) Contractor's profit @ 0.1 on (a+b+c+d)

day
day
day

4.160
2.000
102.000

185.07
206.99
177.07

hour
hour
hour
tonne.km

6.000
12.000
6.000
720 x L

2519.00
665.00
1188.00
2.68

1. It is assumed that dismantling of concrete


slab/pavement has been considered separately.
Hence same is not added in this analysis. Only
labour for crushing the dismantled slab into
aggregate has been added. Carriage from stock pile
to work site has been provided with a lead of L km.
Note 2. In case of breaking of slabs is done locally without
involvement of transportation, the provision of tipper,
front end loader and loading/unloading charges may
be deleted.
4.12

406

RCD/SOR_2nd Edition

Wet Mix Macadam

15114.00
P&M-032
7980.00
P&M-044
7128.00
P&M-017
1928.45 Lead =1 km &
P&M-047
192.84

hour

12.000

111.24

1334.88

P&M-060

KL

72.000

167.07

12028.91
6495.21
7144.73

M-189

Cost for 360 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/360
With Smooth 3 wheeled Steel Roller

L-12
L-15
L-13

78592.04
218.31
say

218.00

Sub - Analysis_B
SUB ANA
-B

Providing, laying, spreading and compacting graded


stone aggregate to wet mix macadam specification
including premixing the Material with water at OMC
in mechanical mix plant carriage of mixed Material by
tipper to site, laying in uniform layers with paver in
sub- base / base course on well prepared surface
and compacting with vibratory roller to achieve the
desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate
Mazdoor skilled
Mazdoor
b) Machinery
Wet mix plant of 75 tonne hourly capacity
Electric generator 125 KVA
Front end loader 1 cum capacity
Paver finisher
Smooth 3 wheeled steel roller @ 8-10 tonnes.
Water tanker 6 KL capacity
Tipper

c)

d)
e)

day
day
day

0.480
2.000
10.000

185.07
206.99
177.07

hour
hour
hour
hour
hour
hour
tonne.km

6.600
6.000
6.000
6.000
12.000
3.000
495 x L

2454.00
2307.00
1188.00
1420.00
665.00
111.24
2.68

cum
cum
cum
KL

89.100
118.800
89.100
18.000

723.00
794.46
239.00
167.07

Add 10 per cent of cost of carriage to cover


cost of loading and unloading
Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent
22.4 mm to 2.36 mm @ 40 per cent
2.36 mm to 75 micron@ 30 per cent
Cost of water
Overhead charges @ 0.1 on (a+b+c)
Contractor's profit @ 0.1 on (a+b+c+d)

Cost for 225 cum = a+b+c+d+e


Rate per cum = (a+b+c+d+e)/225
say

88.83
413.98
1770.70

L-12
L-15
L-13

16196.40
P&M-094
13842.00
P&M-018
7128.00
P&M-017
8520.00
P&M-035
7980.00
P&M-044
333.72
P&M-060
1325.81 Lead =1 km &
P&M-047
132.58

64419.30
94381.37
21294.90
3007.23
24083.48
26491.83

M-034
M-031
M-022
M-189

291410.14
1295.16
1295.00

1. Though vibratory roller is required only for 3 hours


as per norms, the same is required to be available at
site for 6 hours to match with other machines. The
usage rates of vibratory roller may be multiplied with
a factor of 0.65.
Note 2. As three wheeled smooth steel rollers are
commonly in use, the same has been provided as an
alternative which can be used if the thickness of
individual layer does not exceed 100 mm.
12.5

1300

SUB ANA
-B

Brick Masonry Work in Cement Mortar 1:2 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class
Cement mortar 1:2 (Rate as in Item 12.6 B subanalysis)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

each
cum

2500.00
1.20

4.33
4247.00

day
day
day

0.48
4.00
8.00

185.07
234.29
177.07

say

RCD/SOR_2nd Edition

10821.43
M-079
5096.40 Item 12.6 (B)

88.83
937.16
1416.56
4590.10
2295.05
25245.53
5049.11
5049.00

L-12
L-11
L-13

Sub - Analysis_B
12.5

1300

SUB ANA
-B

Brick Masonry Work in Cement Mortar 1:4 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class
Cement mortar 1:4 (Rate as in Item 12.6 C subanalysis)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

each
cum

2500.00
1.20

4.33
2711.00

day
day
day

0.48
4.00
8.00

185.07
234.29
177.07

say
12.5

1300

SUB ANA
-B

88.83
937.16
1416.56
4129.30
2064.65
22711.13
4542.23
4542.00

L-12
L-11
L-13

Brick Masonry Work in Cement Mortar 1:6 in


Foundation complete excluding Pointing and
Plastering, as per Drawing and Technical
Specifications.
Unit = cum
Taking output = 5 cum
a) Material
Bricks Ist class
Cement mortar 1:6 (Rate as in Item 12.6 D
sub-analysis)
b) Labour
Mate
Mason
Mazdoor
c) Overhead charges @ 0.25 on (a+b)
d) Contractor's profit @ 0.1 on (a+b+c)
Cost for 5 cum = a+b+c+d
Rate per cum (a+b+c+d)/5

each
cum

2500.00
1.20

4.33
2107.00

day
day
day

0.48
4.00
8.00

185.07
234.29
177.07

say

RCD/SOR_2nd Edition

10821.43
M-079
3253.20 Item 12.6 (C)

10821.43
M-079
2528.40 Item 12.6 (D)

88.83
937.16
1416.56
3948.10
1974.05
21714.53
4342.91
4343.00

L-12
L-11
L-13

CHAPTER-1
CARRIAGE OF MATERIALS
Sr No

Ref. to
MoRTH
Spec.

Description

Unit

Loading and Unloading of Stone


Boulder/ Stone aggregates/Sand/
Kanker/Moorum

1.1

Quantity Rate Rs Cost Rs

Remarks
/ Input
ref.

cum

Placing tipper at loading point, loading


with front end loader, dumping,
turning for return trip, excluding time
for haulage and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i)
Positioning of tipper at loading
point
ii)
Loading by front end loader 1

1 Min
13 Min

cum bucket capacity @ 25 cum per


hour
iii)
Maneuvering, reversing,
dumping and turning for return
iv)
Waiting time, unforeseen
contingencies etc
Total
a)

b)

2 Min
4 Min
20 Min

Machinery
Tipper 5.5 tonnes capacity

hour

0.330

Front end-loader 1 cum bucket


capacity @ 25 cum/hour
Overhead charges @ 0.1 on (a)

hour

0.330

873.00
1188.00

822.96
149.63

Unloading will be by tipping.

Loading
and
Unloading
Boulders by Manual Means

P&M-017

74.81

Rate per cum = (a+b+c)/ 5.5


1.2

P&M-048

392.04
68.01

c)
Contractor's profit @ 0.1 on
(a+b)
Cost for 5.5 cum = a+b+c
Note

288.09

say

150.00

of

Unit = cum
Taking output = 5.5 cum
a)

b)

Labour
Mate

day

0.110

185.07

20.36

L-12

Mazdoor for loading and unloading

day

0.750

177.07

132.80

L-13

hour

0.750

873.00

654.75

P&M-048

Machinery
Tipper 5.5 tonne capacity

c)
Overhead charges @ 0.1 on
(a+b)
d)
Contractor's profit @ 0.1 on
(a+b+c)
Cost for5.5 cum = a+b+c+d

80.79
88.87
977.57

Rate per cum = (a+b+c+d)/5.5


Note
1.3

177.74

Unloading will be by tipping.

say

178.00

Loading and Unloading of Cement


or Steel by Manual Means and
Stacking.
Unit = tonne
Taking output = 10 tonnes
a)

b)

Labour
Mate

day

0.080

185.07

14.81

L-12

Mazdoor for loading and unloading

day

2.000

177.07

354.14

L-13

hour

2.000

773.00

1546.00

Machinery
Truck 10 tonne capacity

c)
Overhead charges @ 0.1 on
(a+b)
d)
Contractor's profit @ 0.1 on
(a+b+c)
Cost for10 tonnes = a+b+c+d

191.49
210.64
2317.08

Rate per tonnes = (a+b+c+d)/10

231.71
say

1.4

Cost of Haulage Excluding Loading


and Unloading
Haulage of materials by tipper excluding
cost of loading, unloading and stacking.

232.00

P&M-057

Unit = t.km
Taking output 10 tonnes load and lead
10 km = 100 t.km

(i)

Surfaced Road
Speed with load : 25 km / hour.
Speed while Returning empty :35 km / hour.
a)

Machinery.
Tipper 10 tonne capacity
Time taken for onward haulage with
load
Time taken for empty return trip.

b)

hour

0.400

873.00

349.20

P&M-048

hour

0.290

873.00

253.17

P&M-048

Overhead charges @ 0.1 on (a)

60.24

c)
Contractor's profit @ 0.1 on
(a+b)
cost for 100 t km = a+b+c

66.26
728.87

Rate per t.km = (a+b+c)/100


1.4

(ii)

7.29
say

7.30

Unsurfaced Graveled Road


Speed with load: 20 km / hour
Speed for empty return trip :30 km / hour
a)

Machinery
Tipper 10 tonnes capacity
Time taken for onward haulage with
load
Time taken for empty return trip

b)

hour

0.500

873.00

436.50

P&M-048

hour

0.330

873.00

288.09

P&M-048

Overhead charges @ 0.1 on (a)

72.46

c)
Contractor's profit @ 0.1 on
(a+b)
Cost for 100 t .km = a+b+c

79.70
876.75

Rate per t.Km = (a+b+c)/100


1.4

(iii)

8.77
say

8.80

Katcha Track and Track in River


Bed/Nallah Bed and Choe Bed
Speed with load :10 km / hour
Speed while returning empty:15 km / hour
a)

Machinery
Tipper 10 tonnes capacity

b)

Time taken for onward haulage

hour

1.000

873.00

873.00

P&M-048

Time taken for empty return trip

hour

0.670

873.00

584.91

P&M-048

Overhead charges @ 0.1 on (a)

145.79

c)
Contractor's profit @ 0.1 on
(a+b)
Cost for 100 t .km = a+b+c

160.37
1764.07

Rate per t.Km = (a+b+c)/100

17.64
say

17.60

You might also like