Professional Documents
Culture Documents
By:
July, 2015
EXECUTIVE SUMMARY
This System Impact Study (SIS) is conducted for the 50 MW Felisa Solar Power
Project of Negros Ph Solar Inc. (NPSI) in Brgy. Felisa Bacolod City. The proposed
connection for this project is a direct connection to Bacolod 138 kV Substation.
This study was performed in accordance with the Philippines Grid Code (PGC) and
NGCP requirements. The purposes of this study are as follows:
1. Analyze the steady-state, stability, and short circuit conditions of the grid with
the project;
2. Determine any upgrades to the transmission system that would be required to
mitigate any adverse impacts that the project could otherwise pose on the
reliability and operating characteristics of the transmission system in
accordance with the PGC, NGCP standards and generally accepted
international transmission utility practices;
3. Determine any upgrades required to mitigate any degradation to transmission
transfer capability; and
4. Determine any upgrades required to mitigate any degradation to system
dynamic stability.
The primary area of concern of this study is the area around NGCPs Bacolod
Substation. Generated power from the proposed power plant will be transmitted to
Visayas grid through this substation.
In addition to the standard requirements of the PGC, the ERC had issued Resolution
No. 7 Series of 2013 imposing new requirements for intermittent power plants such
as this project. This proposed power plant should comply with those requirements,
compliance thereto should be demonstrated by field tests during testing and
commissioning.
STEADY STATE
Steady state thermal and voltage analyses were conducted to examine the comparative
system performance with and without the proposed project. The baseline performance is
based on the system without the proposed project. System performance was reevaluated with the project and compared with the baseline system. This approach
exposes the impact of the project on the system utilizing the criteria set by the PGC.
Steady state analysis was evaluated using a scenario where power plants at close
proximity to the project were dispatched to its maximum feasible levels for years 2016
and 2021. Peak load for 2016 and 2021 were respectively, 1,854.8 MW and 2,279.5
MW. Simulation at this dispatch scenario enabled the examination of the transmission
system to reliably operate with the proposed project integrated to the system.
Based on the steady state results the projects connection to the grid poses no
significant adverse impact on the reliability and operating characteristics of Visayas
grid. There was no significant voltage or thermal violations of reliability criteria
associated with the entry of the project considering its priority dispatch incentive
under the RE Law.
STABILITY
This evaluation consisted of application of faults on the system with the project using
peak base cases. The dynamic stability of the system during and after these faulted
conditions should conform to the requirements of the PGC. In addition, voltage,
frequency and power fluctuations or oscillations should dampen within the prescribed
period. Machine angle should also exhibit acceptable coherence.
In all tested fault conditions the project would pose no significant adverse impact on
the stability of the system.
FREQUENCY ASSESSMENT
Frequency assessment showed that the system frequency will not drop as low as
59.4 Hz with the outage of the proposed power plant. Automatic Load Dropping is
not expected during this loss-of-generation scenario.
SHORT CIRCUIT
Short-circuit analysis was conducted to determine the impact of the project on the
existing fault current levels in all substations. In this study, it was assumed that fault
duty of the circuit breakers installed in the system are as follows:
Volage Level
<69 kV
>69kV <138 kV
>230 kV
Rated Short
Circuit
Current (kA)
25
31.5
40
Simulation results indicate that the entry of the proposed project will not result to fault
levels beyond the fault duties of the existing circuit breakers.
CONCLUSION
This study revealed that the addition of NPSIs 50 MW Felisa Solar Power Project
has no significant impact on the reliability, stability and operating characteristics of
the Visayas power transmission system. The proposed power plant could be safely
and reliably integrated to Visayas grid.
TABLE OF CONTENTS
Executive Summary
Steady State
Stability
Frequency Assessment
Short Circuit
Conclusion
1. Background Information...................................................................................................... 8
2. Study Assumptions.............................................................................................................10
A.
Demand Forecast...................................................................................................... 10
B. Generation Expansions..................................................................................................10
C.
Transmission Expansions..........................................................................................12
D.
D.
Appendices
LIST OF TABLES
Table 1.
Table 4.
Table 7.
Table 19.
Table 20.
LIST OF FIGURES
Figure 1. Generation Capacity Additions in Visayas.............................................................. 11
Figure 2. Transmission Expansion Projects in Visayas..........................................................12
Figure 3. Low Voltage Withstand Capability Requirement for Large Photovoltaic Systems 16
Figure 4. Connection Scheme for the Project........................................................................ 17
Figure 5. Geographic Location of the Project.........................................................................18
Figure 6. Equivalent Model of the Grid in the Vicinity of the Project......................................20
Figure 7. Frequency Assessment, 2016 Peak Base Case.....................................................31
Figure 8. Frequency Assessment, 2021 Peak Base Case.....................................................31
1. BACKGROUND INFORMATION
Negros Ph Solar Inc. (NPSI) has embarked on developing this project by committing
significant resources and time to identify and secure key project specifics to ensure
project viability prior to applying for the various government permits and approvals.
This project has been under-development for the last 6 months with the proper site
selection and technical evaluation and local stakeholders engagement and
relationship building being developed to ensure project viability. The initial findings
are very optimistic. Necessary government permits were already secured.
This approach allows all the stakeholders, DOE, NGCP, Landowners, LGUs, etc. to
have better comfort and visibility that our Service Contract will crystalize into a real
project and not remain in development for years.
NPSI is a wholly owned Filipino corporation and was set up to fully focus on
developing the Philippine Solar market. The founder Ms. Maricel Montfort, a highly
successful native of Cadiz and currently residing in Bacolod and Manila, is a longstanding citizen who has had extensive working experience abroad and has returned
back to the Philippines to take an active part in improving the lives of the local
Filipinos through various infrastructure projects. Ms. Montfort is currently active with
several large infrastructure and social developments throughout the Philippines.
These include medical facilities, orphanages, water-treatment/purification projects
and land & property investments. Being a very successful business lady, she is able
to fully fund the professional and proper development of these projects.
NPSI has identified Bacolod City as a suitable site for the Solar project. Bacolod has
a stable climate with adequate sunlight throughout the year and minimal risk of
heavy typhoons or flooding. Land is plentiful and the local government agencies are
supportive of such an initiative.
NPSI has been actively developing the project for the last 6 months and focused on
securing the right land location and negotiating with the landowners to ensure terms
and conditions and commercially viable for the project. NPSI has actively engaged
the local LGUs and have planned for CSR activities for the area once the project
moves ahead.
Page 8
Land Status:
a) Identified and secured approximately 150 hectares with the landowners. Many
of the landowners are prominent local business people with good local
standing. Land Options have been signed for most of them and the rest will
be complete shortly and landowners are backing this project fully. NPSI has
very good relationships with all the landowners. In total NPSI aims to secure
approximately 280 hectares to build up to 200 MW.
b) NPSI had engaged professionals to conduct
Irradiation Studies
Flood studies
Topographical surveys
Soil studies
The site has ideal road access and is relatively flat with little flood risk. The
lands will not be an inconvenience any inhabitants. The landlords have
committed to ensure the site will be problem free and we will engage their
local individuals where possible.
c) The lands identified are outside the CARP jurisdiction and we have obtained
proper legal advice as well as advice from the local LGUs on the proper
procedure to ensure that the site is Solar ready. This has already been
factored in our evaluation.
d) The land titles have also been checked for any risk of foreclosure or
encumbrances being attached.
e) NPSI has also ensured that there are no sensitive or endangered trees on the
site and will not need any special approval or process.
This project proposes to connect to the grid through a direct connection to Bacolod
138 kV Substation. Direct connection had been preferred by NGCP to avoid
complicating the grid backbone protection system.
Page 9
2. STUDY ASSUMPTIONS
A. DEMAND FORECAST
Based on the 2013 Transmission Development Plan (TDP), there would relatively be
a significant increase in demand in Visayas Grid. Table 1 shows the demand
projections for the entire grid. Of greater interest for this proposed project is the
demand in Negros Island where the proposed facility will be injecting its power to the
grid. Bacolod Substation will be the main corridor of this project.
Table 1. Demand Projections for Visayas
B. GENERATION EXPANSIONS
Based on the Department of Energys list of proposed generators, the 2013
Transmission Development Plan identified the grid reinforcements needed to cater
the incoming generators. The status of generator development are classified by the
Department of Energy as Committed, Indicative and Prospective. The
generators considered in the study is shown in Figure 1, corresponding table is
shown in Table 2.
Page 10
Page 11
C. TRANSMISSION EXPANSIONS
Major developments in Negros island included in the 2013 TDP are as follows:
1. Negros-Panay Interconnection Uprating
2. Negros V Transmission Line Project
3. Visayas Substation Expansion I (Kabangkalan 1 x 50 MVA)
4. Visayas Substation Reliability I (Amlan 1 x 50 MVA, Bacolod 1 x 100 MVA and
Cadiz 1 x 50 MVA)
These proposed developments shown in Figure 2 as well as generation expansions
were included in the base cases and were considered in the assessments.
Page 12
The voltage limits adopted in this study were in compliance with the PGC which
requires that during normal and single outage contingency conditions, the voltage
should be within the range of 0.95 to 1.05 per unit. For the thermal limits, normal
thermal ratings shall not be violated under all-lines-in and single outage contingency
conditions. The steady state analysis was performed with both pre-contingency and
post-contingency solution parameters that allow adjustment of load tap-changing
transformers (LTCs), static var devices (SVDs) including switched capacitors and
phase angle regulators (PARs).
For short circuit studies, resulting three phase fault should not exceed the levels
shown in Table 3. These ratings are the standard fault duty rating of circuit breakers
connected to the grid.
Table 3. Power Circuit Breaker Fault Duty Rating
Voltage Level
<69 kV
25
>69kV <138 kV
31.5
>230 kV
40
Page 13
1. The Grid remains stable after any Single Outage Contingency for all
forecasted Load conditions; and
2. The Grid remains controllable after a Multiple Outage Contingency. In the
case of Grid separation, no total blackout should occur in any Island Grid.
In this study however, only stability under single outage contingency conditions were
evaluated.
Applied faults were cleared (normal clearing) in compliance with the requirements of
the PGC Section 4.5.2.3 as follows:
1. 85 ms for 500 kV;
2. 100 ms for 230 kV and 138 kV; and
3. 120 ms for voltages less than 138 kV
Delayed clearing were simulated in accordance with the requirements of the PGC
which states:
The circuit breaker fail protection shall be designed to initiate the tripping of
all the necessary electrically-adjacent circuit breakers and to interrupt the fault
current within the next 50 milliseconds, in the event that the primary protection
system fails to interrupt the fault current within the prescribed Fault Clearance
Time
In addition to the standard PGC requirements, the Energy Regulatory Commission
(ERC) had issued Resolution No. 7 series of 2013 entitled Resolution Adopting and
Approving Addendum to Amendment No. 1 of the Philippine Grid Code, Establishing
the Connection and Operational Requirements for Variable Renewable Energy
(VRE) Generating Facilities. Under Article II Section 2 of this addendum, additional
requirements for large photovoltaic generation systems were prescribed as follows:
1.) Section 2.1 Generating Unit Power Output
2.) Section 2.2 Frequency Withstand Capability
3.) Section 2.3 Reactive Power Capability
4.) Section 2.4 Performance During Network Disturbances
5.) Section 2.5 Voltage Control System
6.) Section 2.6 Active Power Control System; and
7.) Section 2.7 Power Quality
Page 14
Page 15
Page 16
Power Quality
With the proposed power plant connected to the system and under normal operating
state, the Flicker Severity and Total Harmonic Distortion at the connection point shall
not exceed the values prescribed by the PGC
The proposed power plant will demonstrate compliance with these requirements
through testing to be conducted pursuant to Section 3.2.3.
3. PROPOSED
CONNECTION
ARRANGEMENT AND
SYSTEM
MODELLING
In Figure 4 is shown the proposed connection for the project. This connection
consists of 138 kV transmission line directly connected to Bacolod 138 kV
Substation. The project will be equipped with a take-off substation at the power plant
site connected to a main bay at Bacolod Substation. The projects geographic
location is shown in Figure 5.
Proposed Power Plant
Page 17
Take-off Substation
The technical specifications used to model the proposed connection assets of NPSI
solar power plant project are shown in Table 5 to Table 7.
Table 5. Lumped Generator Specifications
Power
Capability
(MW)
Pmax
Pmin
50
Reactive Capability at
Full Dispatch (MVAR)
Qmax
0
Qmin
0
R Source
0
Remarks
X Source
99999
Refer to PSS/E
PV Modelling
Guide
Page 18
Description
Tap Ratio
Present
Tap
MVA
Rating
Tap
Steps
Grid
Transformers
22/138
D/Y
Center
65
R (pu)
X (pu)
based on
System
MVA
0.178620
Type
Length
Rate
(MVA)
NPSI take-off
138 kV tapping
3.5 km
196
R (pu)
X (pu)
0.001580 0.008740
B (pu)
0.002290
The grid model or base cases used in this study for years 2016 and 2021 were provided
by NGCP. Both base cases were derived from the Transmission Development Plan and
considered transmission line and generator expansion plans for the period covered. The
scenario represented was peak loading condition, maximizing dispatch of power plants
in the vicinity of the project. Off-peak scenarios were not considered in the assessment
since the proposed power plant is not expected to operate during off-peak.
Equivalent model of the grid in the vicinity of the project is shown in Figure 6.
Page 19
Proposed 50 MW
Solar Power Plant
The 50 MW generator was modeled as lumped unit using PVGU1 in the dynamic
stability study while the electrical controls was modelled as PVEU1. Parameters for
the models are shown in Table 8 and Table 9 respectively. Other system dynamics
data were provided by NGCP.
Page 20
Page 21
Monitored Element
MVA
Rating
1
2
3
4
5
6
196.00
108.04
196.00
196.00
196.00
196.00
Peak Load
Condition
Without
Silay Solar
MVA
%
N/A
84.91
78.59
84.72
43.22
132.92
67.82
15.33
7.82
10.64
5.43
With
Silay
Solar
MVA
50.90
93.47
93.26
152.74
24.71
20.00
%
25.97
86.51
47.58
77.93
12.61
10.20
196.00
20.20
10.31
14.44
7.37
392.00
34.56
8.82
24.32
6.20
108.00
196.00
49.57
47.40
45.90
24.18
44.02
57.33
40.76
29.25
392.00
95.44
24.35
90.28
23.03
Monitored Element
MVA
Rating
1
2
3
4
5
6
7
8
196.00
108.04
196.00
196.00
196.00
196.00
Peak Load
Condition
Without
Silay Solar
MVA
%
N/A
69.60
64.42
69.45
35.43
97.69
49.84
6.03
3.08
6.37
3.25
With
Silay
Solar
MVA
50.94
89.32
89.09
147.09
21.93
20.68
%
25.99
82.67
45.45
75.05
11.19
10.55
196.00
27.08
13.82
27.58
14.07
392.00
42.82
10.92
43.22
11.03
EB Magalona-Barotac Viejo
9 138 kV
10 Barotac Viejo-Dingle 138 kV
Barotac Viejo-Concepcion
11 138 kV
108.00
196.00
47.90
27.67
44.35
14.12
47.02
27.41
43.54
13.98
392.00
82.62
21.08
82.69
21.09
Page 22
MVA
Rating
196.00
108.04
196.00
196.00
196.00
196.00
Without
Silay Solar
MVA
%
N/A
165.96 153.61
164.93
84.15
212.78 108.56
55.29
28.21
51.14
26.09
Wit
h
Silay Solar
MVA
%
50.97
26.01
182.54 168.96
181.44
92.57
232.55 118.65
65.46
33.40
61.64
31.45
196.00
85.03
43.38
57.49
29.33
392.00
64.93
16.56
54.67
13.95
108.00
196.00
98.30
94.75
91.02
48.34
69.33
116.50
64.19
59.44
392.00
190.35
48.56
180.17
45.96
1
2
3
4
5
6
7
MVA
Ratin
g
Without
196.00
108.04
196.00
196.00
196.00
196.00
Silay Solar
MVA
%
N/A
136.01 125.89
135.04
68.90
176.62
90.11
82.25
41.96
82.65
42.17
196.00
103.25
52.68
Wit
h
Silay Solar
MVA
%
50.94
26.09
89.32 161.45
89.09
88.37
147.09 114.34
21.93
31.33
20.68
30.98
27.58
52.95
392.00
71.39
18.21
43.22
18.36
108.00
196.00
109.71
101.44
101.58
51.76
47.02
27.41
98.89
51.70
392.00
163.85
41.80
82.69
41.80
Page 23
Without
Silay Solar
(kV)
3 [NPHS_HI 138.000]
227601
138.0
COLON
0
227700
SAMBOAN
138.00
235500
BACOLOD
69.000
235501
BACOLOD
69.000
237100
PONDOL
138.00
237101
PONDOL
138.00
237200
AMLAN HI
138.00
237201 AMLAN
SP
138.00
237300 MAB
138.0
HI
0
237400
KABANKAL
138.00
237500
BACOLOD
138.00
237800
EBMAG1
138.00
237801
EBMAG2
138.00
247100 BTC VIEJ 138.00
247200
138.0
DINGLE
0
247700
CNCPCION
138.00
(p.u.)
N/A
Wit
h
Silay Solar
(p.u.
(kV)
)
1.0142 139.95
136.80
0.9913
0.9903
136.66
137.31
0.9950
0.9917
136.85
70.46
1.0212
1.0196
70.35
70.46
1.0212
1.0196
70.35
138.48
1.0035
1.0017
138.23
138.48
1.0035
1.0017
138.23
137.99
0.9999
0.9984
137.78
137.99
0.9999
0.9984
137.78
138.86
1.0062
1.0042
138.58
139.35
1.0098
1.0078
139.08
140.18
1.0158
1.0143
139.97
140.90
1.0210
1.0213
140.94
141.06
141.20
1.0222
1.0232
1.0211
1.0217
140.91
140.99
140.03
1.0147
1.0134
139.85
141.51
1.0254
1.0244
141.37
Without
Silay Solar
(kV)
3 [NPHS_HI 138.000]
138.0
227601 COLON
0
227700
SAMBOAN
138.00
235500
BACOLOD
69.000
System Impact Study for Negros Ph Solar Inc.s
50 MW Felisa Solar Power Project
(p.u.)
N/A
Wit
h
Silay Solar
(p.u.
(kV)
)
1.0055 138.75
1.0093
139.28
1.0066
138.91
0.9987
137.82
0.9918
136.87
1.0074
69.51
1.0044
69.30
Page 24
235501
BACOLOD
69.000
237100
PONDOL
138.00
237101
PONDOL
138.00
237200
AMLAN HI
138.00
237201 AMLAN
SP
138.00
237300 MAB
138.0
HI
0
237400
KABANKAL
138.00
237500
BACOLOD
138.00
237800
EBMAG1
138.00
237801
EBMAG2
138.00
247100 BTC VIEJ 138.00
247200
138.0
DINGLE
0
247700
CNCPCION
138.00
1.0074
69.51
1.0044
69.30
1.0033
138.46
1.0003
138.04
1.0033
138.46
1.0003
138.04
0.9991
137.88
0.9963
137.49
0.9991
137.88
0.9963
137.49
1.0032
138.44
0.9999
137.99
1.0052
138.72
1.0019
138.26
1.0084
139.16
1.0056
138.77
1.0183
140.53
1.0164
140.26
1.0215
1.0233
140.97
141.22
1.0197
1.0216
140.72
140.98
1.0107
139.48
1.0098
139.35
1.0330
142.55
1.0320
142.42
Without
Silay Solar
Mi
n
3 [NPHS_HI 138.000]
138.0
227601 COLON
0
227700
SAMBOAN
138.00
235500
BACOLOD
69.000
235501
69.000
Max
N/A
0.975
4
0.974
3
0.997
0
0.997
0.997
1
1.004
3
1.032
6
1.032
Wit
h
Silay Solar
Min
0.9961
Max
1.0242
0.9748
0.9958
0.9694
1.0035
1.0006
1.0006
1.0304
1.0304
BACOLOD
237100
PONDOL
138.00
237101
PONDOL
138.00
237200 AMLAN
HI
138.00
237201 AMLAN
SP
138.00
237300 MAB
138.0
HI
0
237400
KABANKAL
138.00
237500
BACOLOD
138.00
237800
EBMAG1
138.00
237801
EBMAG2
138.00
247100 BTC VIEJ 138.00
System Impact Study for Negros Ph Solar Inc.s
50 MW Felisa Solar Power Project
0
0.989
9
0.988
9
0.988
9
0.988
9
0.994
3
0.997
2
0.992
7
0.999
5
0.994
1
1.006
0
6
1.006
8
1.006
9
1.003
2
1.003
2
1.014
1
1.020
8
1.023
5
1.027
7
1.027
0
1.027
7
0.9883
1.0066
0.9874
1.0067
0.9874
1.0028
0.9874
1.0028
0.9893
1.0125
0.9939
1.019
0.9961
1.0242
0.9974
1.0287
0.9976
1.0273
1.0046
1.0276
Page 25
247200
DINGLE
247700
CNCPCION
138.0
0
1.0045
1.0210
1.0033
1.0203
138.00
1.0149
1.0282
1.0140
1.0280
Monitored
Substations
Mi
n
3 [NPHS_HI 138.000]
227601
138.0
COLON
0
227700
SAMBOAN
138.00
235500
BACOLOD
69.000
235501
BACOLOD
69.000
237100
PONDOL
138.00
237101
PONDOL
138.00
237200
AMLAN HI
138.00
237201 AMLAN
SP
138.00
237300 MAB
138.0
HI
0
237400
KABANKAL
138.00
237500
BACOLOD
138.00
237800
EBMAG1
138.00
237801
EBMAG2
138.00
247100 BTC VIEJ 138.00
247200
138.0
DINGLE
0
247700
CNCPCION
138.00
Max
Min
0.9612
0.999
9
1.0132
0.9973
0.982
1.0042
0.9716
0.964
1.0245
0.9574
0.964
0.988
8
0.987
9
0.987
9
0.987
9
0.980
5
0.980
1
0.967
5
0.990
1
0.968
9
1.005
4
0.994
1
1.022
1
1.0245
0.9574
1.0067
0.9862
1.0067
0.9853
1.0027
0.9853
1.0027
0.9853
1.01
0.9838
1.0153
0.9777
1.0199
0.9613
1.0279
0.9866
1.0287
0.9627
1.0301
1.0046
1.0168
0.9975
1.0371
1.0217
Max
1.015
5
1.010
7
1.002
8
1.019
5
1.019
5
1.004
6
1.004
6
1.000
3
1.000
3
1.007
5
1.012
5
1.015
5
1.026
2
1.025
9
1.027
5
1.015
4
1.035
5
Page 26
Substation
3 [NPHS_HI 138.000]
23750 [BACOLO
0
D
138.00]
23550 [BACOLO
1
D
69.000]
23550 [BACOLO
0
D
69.000]
23780
0
[EBMAG1 138.00]
23780
1
[EBMAG2 138.00]
24710
0
[BTC VIEJ 138.00]
24770 [CNCPCI
0
ON
138.00]
24720
138.00
0
[DINGLE
]
23740 [KABANK
0
AL
138.00]
23730
138.00
0
[MAB HI
]
23720 [AMLAN
0
HI
138.00]
23720 [AMLAN
1
SP
138.00]
23710
0
[PONDOL 138.00]
22770 [SAMBOA
0
N
138.00]
22760
138.00
1
[COLON
]
Peak Load
Condition
Without
With
Silay Solar
Silay Solar
2016
2021
2016
2021
13,540.0
N/A
13,807.40
N/A
0
8,279.20
10,118.2
0
10,118.2
0
6,700.4
0
Table 19. Short Circuit MVA at Power Plant S/S (Peak Loading)
Short Circuit MVA and X/R
at Solar 69kV Bus
Peak Load Condition
2016
2021
MVA
X/R
MVA
X/R
1,650.15 4.8616 1,618.19 4.43667
Page 27
6. STABILITY ASSESSMENT
Stability analysis assessed the impact of the project to the transient stability performance
of the grid. The analysis was based on the assumptions and methodology described in
the previous sections. The stability plots are included in the Appendices.
These three phase faults were later isolated at normal and delayed clearing times.
As a stability criteria, for the transient stability assessment, parameters namely,
machine angle, bus voltages, bus frequency and generator power swing during and
after the system disturbance should have acceptable damping and coherence.
System Impact Study for Negros Ph Solar Inc.s
50 MW Felisa Solar Power Project
Page 28
The results of the stability simulation indicated acceptable response of the system
parameters with the proposed facility integrated, damping mostly within the first ten
(10) seconds after the application of fault. The summary of dynamic stability
simulations is shown in Table 20 for scenarios with the power plant.
Applied Fault
Normal
Clearing
Delayed
Clearing
Normal
Clearing
Delayed
Clearing
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
BUS FAULTS
1. Bus Fault at NPHS_HI 138 kV Bus (3)
2. Bus Fault at BACOLOD 138 kV Bus (237500)
3. Bus Fault at EBMAG1 138 kV Bus (237800)
4. Bus Fault at EBMAG2 138 kV Bus (237801)
5. Bus Fault at KABANKAL 138 kV Bus (237400)
6. Bus Fault at MAB HI 138 kV Bus (237300)
7. Bus Fault at AMLAN SP 138 kV Bus (237201)
with
Page 29
69 kV Line
with
Tripping
7. Fault at Bacolod 138/69 kV Transformer (T1)
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
Stable
with
Tripping
8. Fault at Kabankalan-Mabinay HI 138 kV Line with
Tripping
9. Fault at Amlan HI-Mabinay HI 138 kV Line with
Tripping
7. FREQUENCY ASSESSMENT
Frequency assessment evaluates if the loss of the proposed power plant will not cause
the frequency to drop below 59.4 Hz frequency limit set by PGC. For 2016 and 2021
base cases, the frequency will not fall as low as 59.4 Hz. The outage of the proposed
power plant will not result to Automatic Load Dropping (ALD). Figure 7 and Figure 8
shows the results of frequency assessments for 2016 and 2021 base cases respectively.
Page 30
Page 31
Page 32
APPENDICES