CONTRACT NO.

:
PT PERUSAHAAN GAS NEGARA (Persero)
Tbk
DOC. NO.

PT. PETROTECHNINDO

PT. PRATIWI PUTRI SULUNG

CONTRACT PACKAGE NO. 11A :


PENGADAAN PAKET PEKERJAAN
UPGRADING TANGSI OFFTAKE STATION
PROJECT (CP-11A)

SCOPE OF WORK

REV.

02/12/20
14

ISSUED FOR BID

DATE

DESCRIPTIO
N

PAGE

PREPRD

CHKD

CONTRACTOR

APP
D

CHK
D

APPD

PMC

PGN

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

SCOPE OF WORK

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)


TABLE OF CONTENTS

DAFTAR ISI
1.

GENERAL.............................................................................................................. 4

2.

DEFINITIONS........................................................................................................ 6

3.

TERMINOLOGY AND ABBREVIATIONS.................................................................10

4.

SCOPE OF WORK................................................................................................ 11
4.1

GENERAL..................................................................................................... 11

4.2

INTENDED PURPOSES OF THE PROJECT.......................................................13

4.3

QUALITY....................................................................................................... 13

4.4

RISK............................................................................................................. 13

5.

ESSENTIAL OPERATION REQUIREMENTS............................................................13

6.

PERMANENT WORKS.......................................................................................... 14

7.

TEMPORARY WORKS.......................................................................................... 17

8.

PT. PRATIWI PUTRI SULUNG WORK ACTIVITIES...................................................17


8.1

GENERAL..................................................................................................... 17

8.2

The SITE...................................................................................................... 18

8.3

Survey and Soil Investigation......................................................................19

8.4

Detailed Engineering................................................................................... 21

8.4.1

Onshore Distribution Pipeline................................................................23

8.4.2

Tangsi Offtake Stations -2 (TS-2)..........................................................26

8.4.3 New Fire & Gas System, Additional Fire Extingusher and New Water
System Engineering ;......................................................................................... 31
8.4.4

CCTV System Engineering.....................................................................31

8.4.5

Power Distribution System Engineering................................................31

8.4.6 Electrical System Engineering (Grounding, Lightning Protection and


Lighting);........................................................................................................... 32

PT. Pratiwi Putri Sulung

Scope of Work
Page 2 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

8.4.7

Diesel Engine Generator System Engineering.......................................33

8.4.8

UPS System Engineering;......................................................................33

8.4.9 Instrumentation System (field instruments, flow computer, metering


station computer, marshalling rack), SCADA and Telephony Engineering.........34
8.4.10 Civil Engineering................................................................................... 34
8.4.11 Architectural Design Engineering..........................................................36
8.4.12 Building Utilities Engineering................................................................36
8.4.13 Instrument Air System Engineering.......................................................37
8.4.14 Utility Water System Engineering; Modification....................................37
9.

INDEPENDENT DESIGN VERIFICATION................................................................37

10.

PROCUREMENT............................................................................................... 38

10.1 GENERAL..................................................................................................... 38
10.2 FREE ISSUED MATERIALS............................................................................. 41
10.3 OFFTAKE STATION........................................................................................ 42
11.

CONSTRUCTION WORK................................................................................... 46

11.1 GENERAL..................................................................................................... 46
11.2 WORK SPACE ACQUISITION..........................................................................49
11.3 PERMIT, LICENSES, RETRIBUTION AND LEVIES............................................50
11.4 PIPELINE CONSTRUCTION............................................................................ 51
11.5 PIPE BRIDGES CONSTRUCTION....................................................................53
11.6 PIPELINE CROSSINGS................................................................................... 54
11.7 REINSTATEMENT.......................................................................................... 54
11.8 TANGSI OFFTAKE STATIONS.........................................................................55
12.

INSPECTION AND TESTING.............................................................................. 60

12.1.

ONSHORE DISTRIBUTION PIPELINE...........................................................60

12.2.

OFFTAKE STATION..................................................................................... 62

13.

CALIBRATION.................................................................................................. 66

13.1 Instrumentation........................................................................................... 66
13.2 Metering & Regulating System....................................................................66
14.

HEALTH, SAFETY AND ENVIRONMENT (HSE)...................................................66

15.

MIGAS CERTIFICATIONS................................................................................... 69

17.

COMMISSIONING............................................................................................. 70

18.

TRIAL OPERATION........................................................................................... 71

PT. Pratiwi Putri Sulung

Scope of Work
Page 3 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

19.

WARRANTY AND MAINTENANCE......................................................................72

20.

SPARE PARTS AND CONSUMABLES..................................................................73

21.

TRAINING........................................................................................................ 73

22.

DOCUMENTATION............................................................................................ 74

22.1 General........................................................................................................ 74
22.2 Deliverables for Design............................................................................... 75
22.3 Deliverables for Construction......................................................................75
22.4 Deliverables for Test.................................................................................... 77
22.5 Deliverables for As Built.............................................................................. 77
23.

TEMPORARY FACILITIES................................................................................... 78

23.2 Accommodation for EMPLOYERs Personnel.................................................80


23.3 Communication System for EMPLOYERs Personnel.....................................81
23.4

Ancillary Facilities............................................................................................ 83

23.5

Power............................................................................................................ 83

23.6

Transport........................................................................................................ 84

24.

ADMINISTRATION............................................................................................ 86

25.

PROGRAMMING AND PLANNING......................................................................86

26.

INTERFACE WITH OTHERS/BATTERY LIMIT.......................................................87

27.

EMPLOYERS UNDERTAKINGS..........................................................................87

28.

SCHEDULE FO WORK...................................................................................... 88

29.

ATTACHMENTS................................................................................................ 88

1. GENERAL
1.0 This document describes PT. Pratiwi Putri Sulung Scope of Work including but not
limited to survey and soil investigation, Existing facilities assessment, detailed engineering,
procurement, construction, inspection and testing, calibration, certification, training, precommissioning, commissioning, trial operation, and warranty of Upgrading Tangsi Station
Project (CP-11A).
2.0 PT. PRATIWI PUTRI SULUNG

PT. Pratiwi Putri Sulung

is

required

to

provide

and/or

do

whatever

is

Scope of Work
Page 4 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

inherently

or indispensably necessary to achieve the design, execution and completion of

the WORKS and the remedying

of all defects

requirements of PT. Pratiwi Putri Sulung.

therein, in full accordance

with the

This extends, but is not limited, to arranging

manufacturing, fabrication and such like activities, and for all procurement, shipping and
other transportation activities, all of which are deemed to be encompassed in the term
"construction/installation work" as used hereinafter.
3.0 Except where otherwise expressly stated, all of the requirements expressed

in or to be

reasonably implied from the CONTRACT are to be met by PT. PRATIWI PUTRI SULUNG.
This is so regardless of whether such requirements are expressed in the active voice as
something PT. PRATIWI PUTRI SULUNG must do, e.g. "... PT. Pratiwi Putri Sulung shall
..."or in the passive voice as something which must be done by PT. PRATIWI PUTRI
SULUNG. e.g. "... the Works shall be designed to allow ..." or in the imperative mood as a
direct instruction, e.g. "Provide the following ..."
4.0 Where items of WORK or topics are listed in the CONTRACT as examples of what is to be
done or addressed, such a list does not limit the work to be done solely to those items
listed. Such lists are to illustrate the type of work to be done or the topic to be addressed. not
the full range of what is to be done or addressed.
5.0 Except where otherwise expressly stated, the cost of meeting all of the requirements and
obligations expressed or reasonably implied in the CONTRACT are agreed to be included in
the Accepted Contract Amount.

This includes, in addition to the design, execution and

completion of the WORKS and the management

and administrative

work associated

therewith. such things as the cost of all licence and permits, utilities detection, protection and
relocation. demolition of structures, traffic management and diversions, temporary relocation
and reinstatement of existing facilities. environmental

protection. and implementation of

health and safety measures.


6.0 The EMPLOYER requires that the design and execution of the WORKS take into account the
nature of the environment within which the WORKS will be constructed. It is therefore
essential that PT. PRATIWI PUTRI SULUNG

liaises

effectively

with

all

officially

appointed Environmental Bodies, including Local/Municipal Authorities, Tol Road Authority,

PT. Pratiwi Putri Sulung

Scope of Work
Page 5 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

River and Canal Authority, Industrial Area and others having jurisdiction and/or utilities over
the areas in which the Works are located.
7.0 In addition,

planning and

execution

of the WORKS

requirements of Local/Municipal Authorities

shall take

into account the

to reduce the disruption to the normal

activities of areas adjacent to the Work Areas caused by the execution of the WORKS to a
level acceptable to such Authorities.
8.0 Where PT. PRATIWI PUTRI SULUNG is required to "define" something (for example, an
investigation or survey) then such definition must include everything necessary to ensure that
the investigation or survey generates the information necessary to enable PT. PRATIWI
PUTRI SULUNG to meet the requirements of the EMPLOYER.
9.0 PT. PRATIWI PUTRI SULUNG shall adhere strictly to the requirements is respect of health,
safety and enviromental aspects given in the CONTRACT including the custody and care of the
existing facilities alongside the working areas under CONTRACT PAKAGE NO. 11A. If the
existing facilities are damaged due to the responsibility of the CONTRACTOR, such damage shall
be rectified upon PT. PRATIWI PUTRI SULUNG receipt of the employers acceptance to PT.
PRATIWI PUTRI SULUNG proposed corrective action plan and in accordance with the
conditions of contract.
10.0

All information regarding tie-in, bridge crossing and road crossing locations in these broad

descriptions are approximate, and such things are to be precisely determined by PT. PRATIWI
PUTRI SULUNG during the detail design and execution of the works.

2. DEFINITIONS
For the definition of terms appearing within the documents forming the Dokumen Teknis
that are not specifically given herein, reference should be made to the Conditions of
Contract.
In addition to the definitions given within the Conditions of Contract, the following
definitions SHALL apply:
PROJECT

Upgrading Offtake Tangsi Station Pipeline Project (CP-11A)

Tangsi Offtake Station 1

The existing Offtake Station of Tangsi Cikarang, West Java

PT. Pratiwi Putri Sulung

Scope of Work
Page 6 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

(TS-1)
Tangsi Offtake Station 2

The New Offtake Station of Tangsi located next to the existing

(TS-2)

TS-1 as part of the development of Tangsi Offtake Station

Tangsi Offtake Station

The final development of TS-2 and all its facilities which built

(TOS)

in the existing area of TS-1

Cikarang Listrindo 1 (CL-

Existing MRS Station for elctricity power plant of PGNs

1)

customer of Cikarang Listrindo 1

EMPLOYER/PGN

PT Perusahaan Gas Negara (persero) Tbk.

PMC

PT. Petrochindo Utama (PTU) selected by the EMPLOYER to


carry out the duties assigned to him as Project Management
Consultant for the PROJECT

PT. PRATIWI PUTRI

A company selected by the EMPLOYER as PT. PRATIWI

SULUNG

PUTRI SULUNG to perform Engineering, Procurement and


Construction for the completion of the PROJECT.

SUB-CONTRACTOR

SUB-CONTRACTOR appointed by CONTRACTOR as the


Sub-CONTRACTOR for parts of the WORKS under the
PROJECT.

Supplier/Vendor

Supplier/Vendor appointed by the CONTRACTOR as the


Supplier for part of the WORKS under the PROJECT

Shall

Indicates requirements strictly to be followed in order to


conform to the requirements of the EMPLOYER, the project
specifictions, applicable standards and government rules and
regulations and from which no deviations is permitted

Should

Indicates that among several possibilities, one is recommended


as a certain course of action is preferred but not necessarily
required.

Responsible

Indicates that all cost to do and complete the activities/WORKS


shall be borne by PT. PRATIWI PUTRI SULUNG

MIGAS

PT. Pratiwi Putri Sulung

Directorate of Oil and Gas of Indonesia

Scope of Work
Page 7 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

DITMET

Directorate of Metrology of Indonesia

TRIAL OPERATION

Activities that shall be performed by PT. PRATIWI PUTRI


SULUNG to verify that the facilities can be operated under
stable conditions for the period of 14 (fourteen) days calculated
from the date of the accesptance of commissioning which
include, but not limited to the operation, maintenance, trouble
shooting and rectification of the pipeline, MRS, fire water
system and Diesel Engine Generator Set.

TAKING OVER

Taking Over Certificate (TOC) issued by EMPLOYER in

CERTIFICATE (TOC)

accordance with the provision in the contract Sub-Clouse 8


(Serah Terima) and Su-Clause 9.3 (Berita Acara Serah Terima
Seluruh Pekerjaan).

MECHANICAL

The certificate issued by the EMPLOYER when all elements of

COMPLATION

the PROJECT have been mechanically complated and ready for

CERTIFICATE

commissioning and in accordance with the provision in the


Contract Sub-Clouse 8.2 (Berita Acara Serah Terima)

FACTORY

Testng for individual system equipment performed in the

ACCEPTANCE TEST

manufacturers facilities for each system equipment according

(FAT)

to the requiremenst specification which have been approved by


the EMPLOYEER.

SPECIFICATION

Document forming the EMPLOYERs requirements as listed in


the Lampiran Penawaran in rescpect of the WORKS to be
performed by PT. PRATIWI PUTRI SULUNG under the
CONTRACT.

DRAWINGS

The EMPLOYERs drawings of the WORKS as listed in the


Lampiran Penawaran which consists of definitions drawings
and illustrative drawings.

SITE ACCEPTANCE

Inspection and Test for individual system equipment performed

TEST (SAT)

on SITE for each system equipment according to the


requirements specification which have been approved by the
EMPLOYER.

PT. Pratiwi Putri Sulung

Scope of Work
Page 8 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

MECHANICAL

Completion of pre-commissioning activity in which all

COMPLETION

elements of the PROJECT are to be mechanically completed


and ready for commissioning.

PERMANENT WORKS

The permanent works to be executed by PT. PRATIWI PUTRI


SULUNG under the contract.

TEMPORARY WORKS

All temporary works of every kinds (other than PT. Pratiwi


Putri Sulung equipment) required on SITE for the execution and
the completion of the PERMANENT WORKS and remedying
of any defects.

WORKS

The PERMANENT WORKS and TEMPORARY WORKS, or


either of them as appropriate including the responsibility for
undertaking works outside of the SITE if any as indicated in the
SPECIFICATION.

SITE

The places where the PERMANENT WORKS to be executed


and to which the Plant and Materials are to be delivered, and
any other places as may be specified in the CONTRACT as
forming part of the SITE.

The above definitions shall apply for every defined word when it is written with all
capital letters and/or when it is written with only the first letter is capital.

If there is any discrepancy regarding the definitions of the above words between this
Scope of Work and other documents under Bab X. Dokumen Teknis then the prevailing
definitions shall be as mentioned in the Conditions of Contract and in this Scope of Work.

3. TERMINOLOGY AND ABBREVIATIONS


The abbreviations in this document SHALL have the meaning as follows :
ATS

Automatic Transfer Switch

CCTV

Closed Circuit Television

CP

Cathodic Protection

DEG

Diesel Engine Generator

PT. Pratiwi Putri Sulung

Scope of Work
Page 9 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

FAT

Factory Acceptance Test

F&G

Fire and Gas

PHA

Process Hazard Analysis

I/O

Input I Output

LAN

Local Area Network

MDB

Main Power Distribution Board

MRS

Metering and Regulating System Power

PDB

Distribution Board

P&ID

Piping and Instrumentation Diagram

PLN

Perusahaan Listrik Negara (State Owned Public Electricity)


Transient Earth Clamp

TEC

Site Acceptance Test

SAT

Site Integrated Acceptance Test

SCADA

Supervisory Control and Data Acquisition

UPS

Uninterruptible Power Supply

4. SCOPE OF WORK
4.1 GENERAL
PT. PRATIWI PUTRI SULUNG SHALL perform the following activities as requirement
for this PROJECT.
The intended purpose of the PROJECT is to provide gas supply from TS-2 to CL-1 MRS
Stations, Cikarang Listrindo-2 (Future), ENKEI-Hyundai (Future) and to reinforce Bekasi
Distribution pipeline network. PT. PRATIWI PUTRI SULUNG shall be deemed to have
considered and taken due account all working restrictions and constraints that will apply inside
the existing offtake station and in interfacing with such station and other existing pipeline.
Such consideration shall include, as minimum with the existing facilities, such as tie-in works
and integrated commissioning works. The following are the existing facilities to be interfered
with the PROJECT:
i.
ii.
iii.

1 (one) existing TS-1 offtake station including its pipeline system


24 inch Rawa Maju Karawang main line.
12 inch distribution pipeline Tegalgede Distribusi Bekasi.

PT. Pratiwi Putri Sulung

Scope of Work
Page 10 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Under such existing conditions, PT. PRATIWI PUTRI SULUNG shall perform the WORKS as
follow (See PFD Doc. CP-11A-PTU-3275-PS-DG-002):
a.

b.

Development of Tangsi Offtake Station (TS-2)


Development new tangsi offtake station-2 as upgradaing of existing
Tangsi Offtake Station
Pipeline System Installation
Section-1 :
20 inch upstream pipeline systems (Approximately 200 meters)
including tie-in works by using hot tapping method to the existing 24
inch Rawa Maju Karawang main line.
Section -2 :
20 inch Tangsi Offtake Station-2 (TS-2) downstream pipeline system
(Approximately 2 km) to connect with the 16 inch existing CL-1
pipeline by using hot tapping method including future connection for
Cikarang Listrindo-2 (Future) and ENKE-Hyundai arae (Future).
Section-III :
Jumper line connection the existing 16 future connection at
downstream Tangsi Offtake Station-1 to existing 12 distribution
pipeline Tegal Gede Distribusi Bekasi (Approximately 210 Meters)
Remaining Items/Works
Valve Boxes, pipeline bridges, crossings, pipeline installation at
swampy area and others items/works to be developed by PT. PRATIWI
PUTRI SULUNG to complate the WORKS.

It is planned that each (i) Work will be mechanically completed and commissioned according
to the following sequence:
a) Mechanical Completion of the pipeline, Offtake Station and all tie-ins including PreCommissioning Tests under the CONTRACT (SAT 1, 2 & 3).
b) Commissioning and Trial Operation of the entire gas pipeline system under the
CONTRACT (SAT 4).

4.2

INTENDED PURPOSES OF THE PROJECT


The intended purpose of the project is to provide a safe, robust, reliable, durable and costeffective means of transporting natural gas as follows:
a. Upgrading Tangsi Oftake Station by developing TS-2 and its facility. Development of
TS-2 shall be conducted in the Tangsi Offtake Station and shall be located next to the

PT. Pratiwi Putri Sulung

Scope of Work
Page 11 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

existing TS-1 by demolishing the existing regional office of Tangsi Offtake Station and
existing Tangsi warehouse building. Upgrading Tangsi Offtake Station Shall be
including modification some existing facilities.
b. Connection, interface and integration of the new facilities and equipment of TS-2 with
the existing TS-1 facilities.
c. Onshore pipeline distribution system 20 inch diameter, 16 inch diameter and 12 inch
diameter as describes above, including installation of valve box, tapping connection,
connection to future connections, future connection, bridges installation, cathodic
protection systems, etc.

4.3

QUALITY
PT. PRATIWI PUTRI SULUNG obligation is to ensure that the quality of design, materials and
workmanship is fit for purpose and that he/she estabilshes, implements, maintains and improves
a qualtity management system that will ensures and can verify and documents that the WORKS
are, in all respoects, designed, executed, and completed in accordance withh the CONTRACT.

4.4

RISK
PT. Pratiwi Putri Sulung obligation is to ensure that PT. PRATIWI PUTRI SULUNG
establishes implements, maintains and improves a risk managemengt system that will ensure
that the WORKS are designed, executed and completed in such a manner that risk is
competently identified and managed.

5. ESSENTIAL OPERATION REQUIREMENTS


The pipeline system to be provided as part of the WORKS shall be capable of operating nonstop (24 hours per day) from the date of Taking Over and such will provide:
a. Non-interruption of the gas distribution pipeline system operation, and
b. Safe operating condition throughout the entire gas distribution pipeline system and its
environment.

6. PERMANENT WORKS
The permanent WORKS under this contract that required to be designed, executed and
completed by the PT. PRATIWI PUTRI SULUNG, including, as the minimum, the following:

PT. Pratiwi Putri Sulung

Scope of Work
Page 12 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

1. Demolishing existing Tangsi regional office and warehouse, modification, addition,


reparation of existing facilities and develop Tangsi Offtake Station and its facilities as
part of the WORKS, include, as minimum (See Layout Drawing Tangsi Offtake Station
Doc. No. CP11A-PTU-3275-GA-DG-001)
2. The demolished equipment such as existing air conditioned units, existing pump units,
existing exhaust fan units and the like shall be hand overed and retruned to
EMPLOYERs designated area, PT. Pratiwi Putri Sulung shall coordinat with
PGN/PMC for the demolishion work to be executed
3. Demolish work and dispose removal materials.
4. A fully operational Offtake Station and its facilities which located within Tangsi Area.
(See Layout Drawing Tangsi Offtake Station Doc. No. CP11A-PTU-3275-GA-DG001)
5. A fully operational onshore gas distribution pipeline to be installed for project,
including pipeline of downstream and upstream TS-2, pipeline between upstream CL-1
and existing Bekasi Distribution Pipeline
6. 3 (three) hot tapping connections method: PT. PRATIWI PUTRI SULUNG shall
arrange and conduct assessment and investigation of the existing points which will be
tapped, including provide process and mechanical data. Based on the result of such
assessment and investigation, PT. PRATIWI PUTRI SULUNG shall provide hot
tapping procedure. The hot tapping activities shall be conducted only after PT.
PRATIWI PUTRI SULUNG received all required permits and approval from the
EMPLOYER for such activities. The hot tapping connections are as follow:
Hot Tapping-1 : 24 x 24 x 20
Hot Tapping at mainline 24 Rawamaju Karawang to connect 20 upstream

7.

pipeline TS-2
Hot Tapping-2 : 16 x 16 x 16
Hot Tapping at downstream 16 Tangsi Offtake Station-1 to connection to 16

upstream TS-2 Pipeline


Hot Tapping -3 : 12 x 12 x 12
Hot Tapping at 12 Bekasi Distribution line to connection jumperline to future

connectiom downstream TS-1.


Structural Bridge river crossings as follows :
For river crossing indicated by pipe bridge method, PT. PRATIWI PUTRI
SULUNG shall construct the structural bridges and install the pipeline and its
associate accessories. Cikarang kecil river pipe bridge shall be installed for 20
and 12 pipeline crosing side by side 12 pipeline space on pipebridge will be

used by EMPLOYER
The Stuctural bridge shall meet the Employers requirement as per Typical

PT. Pratiwi Putri Sulung

Scope of Work
Page 13 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Detail Drawing Bridge Pipeline Requirements.


8. Boring for road crossing as indicated in the list of pipeline crossings and special
construction method.
9. Valve boxes, the location of the new valve boxes shall be determined by PT. PRATIWI
PUTRI SULUNG during detail design subject to the EMPLOYERs approval.
10. Air Instrument System shall be provided to the TS-2 and also lined up to the existing
TS-1 as header connections only.
11. Fire and Gas and Fire Extingusher Systems shall be installed at Tangsi Offtake Station2. New fire and Gas panel convering the tangsi offtake station 2 shall be provided at the
control room and electrical room
12. PABX System including phone, fax, cables and its auxillaries as per telecomunication
and SCADA System.
13. Utility Water & Fire Water System shall be installed in TOS, completed with water
pond, Diesels and Electric Fire Pump, Jockey Pump, Fire Hydrant and Siamese
connections.
14. TS-2 shall be equipeed with Moveable Gantry crane with railway along long side of the
new offtake station.
15. PT. PRATIWI PUTRI SULUNG shall develop noise mapping for existing Tangsi
Offtake Station during detail design. The Noise level of gas pressure regulating process
from TS-2 shall be maximum 55 dB ( measured at 1 meter from the outside of building
wall).
16. All interfacing works to ensure interconnection, compability and interopability of this
new pipeline, offtake and system with the existing and/or future pipeline and systems.
17. All associated instrumentation, Local SCADA and telecommunication for the WORKS
including field instruments, cabling system, instrument grounding, etc.
18. New CCTV System for Tangsi Offtake Station as per closed circuit Television System
(See Specification Instrument Tangsi Offtake Station Doc. No. CP11A-PTU-3275-ICSP-005)
19. New Local SCADA shall be provided cover all Tangsi Offtake Station -2.
20. All associated cathodic protection systems for the pipeline systems. PT. PRATIWI
PUTRI SULUNG shall undertake soil investigation survey for the design purpose of
the cathodic protection system which will be installed for EMPLOYERs approval.
21. Build new buildings and modification existing control building and all associated civil
works for the PROJECT as indicated in the Layout Drawing Tangsi Offtake Station-2
22. All associated electrical works for the PROJECT.
23. New Diesel Engine Generator System for replacing the existing DEG. New Diesel
Engine Generator System shall cover electrical power system for Tangsi Offtake
Station-2 and convering TOS emergency electrical power requirements.
24. All associated piping system for the PROJECT.
25. All anciliary buildings and structures that are inherently necessary to ensure the proper
PT. Pratiwi Putri Sulung

Scope of Work
Page 14 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

operation of the WORKS, including addition, replacement and modification for Tangsi
Offtake Station, as required to complete the WORKS
26. All buildings and facilities required, whether new building or modification building for
operation and maintenance, as required in the EMPLOYERs data and drawings.
27. All testing requirements for all material and system equipped in the PROJECT.
28. All pre-commissioning and commissioning requirements to complete the PROJECT.

To ensure that the EMPOYER will be able to make full use of the facilities provided within the
Permanent Works upon taking over and that those Permanent Works fulfill all their functions,
PT. PRATIWI PUTRI SULUNG shall be responsible for Integrating, Pre-commissioning,
Testing, Commissioning, Trial Operation and Staff Training of the EMPLOYERs operational
personnel.
In respect of the distribution pipeline system installed under the Contract Package No. 11A, PT.
PRATIWI PUTRI SULUNG shall coordinate with and support the EMPLOYERs
operation/maintenance division and other PT. Pratiwi Putri Sulungs (if any) to be appointed by
the EMPLOYER, in the above activities.
Certain of PT. Pratiwi Putri Sulung personnel shall remain on-site for a period of 3 months after
Talking-Over in order to advise the operational staff on all operating maintenance aspects in
respect of Contract Package No. 11A and such as will allow them to achieve the intended gas
supply availability requirements.

7. TEMPORARY WORKS
The Temporary Works may depend on choices made by PT. PRATIWI PUTRI SULUNG,
including:

Temporary buildings, including offices, workshops, warehouses, medical and toilet

facilities, canteens, etc,


Temporary roads (including access roads) and associated temporary structures,
Temporary diversion of traffic including signalling and direction guidance

requirements,
Health and safety equipment and related facilities,
Temporary utilities including electric power supply,
Sanitary and drinking water supplies, waste and soil water plumbing and drainage, etc,
Temporary work areas, including that for additional construction space, material
storage, parking areas, fences, etc,

PT. Pratiwi Putri Sulung

Scope of Work
Page 15 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Temporary relocation and/or supports for existing utilities


Temporary communication link along the pipeline route and between the satellite

offices and main offices,


Supports and stabilization measures to facilitate excavation work,
Coffer dams, drainage and dewatering for earthworks,
Temporary scaffolding and false work for construction purposes,
Fire, smoke detection and fire extingusher facilities.

8. PT. PRATIWI PUTRI SULUNG WORK ACTIVITIES


8.1

GENERAL
PT. PRATIWI PUTRI SULUNG is required to provide and/or do whatever is inherently or
indispensably necessary to achieve the design, execution and completion of the WORKS and
the remedying of all defects therein, in full accordance with the requirements of the Contract.
This extends, but is not limited, to arranging detail survey, detail engineering design,
construction, installation, manufacturing, fabrication and such like activities, all of which are
deemed to be encompassed in the term construction/installation work as used hereinafter.
The design and construction/installation work shall follow a design requirements as detailed in
this Scope of Works.
PT. PRATIWI PUTRI SULUNG shall ensure that where necessary:

Full coordination is established with the authorities of existing and planned construction

of utility services,
Public information services, with advice issued in sufficient time, are provided where

disruptions to existing utility services are unavoidable,


Monitoring the environmental and social impacts of the carrying out of the WORKS,
Dealing with antiquities and liaison with relevant authorities,
The provision of power in whatever from necessary for the execution and completion of
the WORKS including power for Tests on Completion and Tests after Completion (if

any),
The provision of water necessary for the execution and completion of the WORKS

including adequate water treatment facilities for disposed water and its permits,
Setting up and running a system to ensure compliance with regulation and permitting
requirements governing the design, execution and completion of the WORKS.

PT. Pratiwi Putri Sulung

Scope of Work
Page 16 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

8.2

The SITE
1) Access to and possession, to the degree required, of Work Area shall be as is, which
includes existing structures and vegetation. Unless otherwise specified, the removal of
structures and vegetation and the preparation of the SITE for working, including any
road diversions and the like, shall be responsibility of PT. PRATIWI PUTRI SULUNG.
No existing access may be closed without an alternative access being provided.
2) None of the Work Areas shall be used for purposes other than for the execution of the
WORKS.
3) The EMPLOYER will not provide any working space to PT. PRATIWI PUTRI
SULUNG beyond that comprised within the Pipeline Route identified on the Illstrative
Drawings. PT. PRATIWI PUTRI SULUNG should prepare additional working space for
his own use if necessary, then all such additional working space shall be sourced and
obtained by him, entirely at his own cost.
4) PT. PRATIWI PUTRI SULUNG shall, at his own expense, source any quarries or
borrow pits that may be required, including arranging for and obtaining all necessary
permits where such are still not available. Except where stated otherwise, PT. PRATIWI
PUTRI SULUNG shall at his own expense arrange adequate off-SITE disposal of all
surplus excavated materials and disposal and removal of demolished work (existing
office, existing security guard hause, existing warehause, existing DEG Shelter, etc,
including arranging for and obtaining all necessary permits where such are still not
available.
5) The SITE (including Work Areas) shall be returned to the original neat and tidy
condition on completion of the WORKS. All holes shall be properly backfilled to the
original line and levels, all damages shall be properly repaired snd all evidences of
construction activities shall be removed.
6) The surface of earth slopes shall be shaped to ensure effective drainage.

8.3

Survey and Soil Investigation


1) Surveying all existing facilities and defining the oprational requirements for interfacing
the new facilities to be provided under the Contract with those existing facilities.
2) PT. PRATIWI PUTRI SULUNG may use EMPLOYERs Existing data survey report
which is attached, however PT. PRATIWI PUTRI SULUNG shall be totally responsible
for identifying and performing any and all other additional survey and soil investigation
activities necessary to complete the design. If additional survey and soil investigation

PT. Pratiwi Putri Sulung

Scope of Work
Page 17 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

are required, PT. PRATIWI PUTRI SULUNG shall conduct survey prior design work
and verify data survey provided by PGN, which covers, but not limited to the following
items:
Topograhic survey,
Soil test, (sondir, shallow boring & deep boring),
Test pit and utilities survey,
Traffic survey,
Soil resistivity survey,
Bathymetry survey,
Field and route survey,
Permit survey,
Cadastral survey.
3) The work shall be in accordance with the Survey Service Specificatiion and the
Cathodic Protection Construction Specification for Closed Interval Potential Survey
(CIPS). The CIPS survey works shall be done after commissioning.
4) The survey procedure shall be submitted by PT. PRATIWI PUTRI SULUNG to obtain
EMPLOYERs approval before commencing the activities.
5) The survey reports and associated documents/drawings shall be prepared by PT.
PRATIWI PUTRI SULUNG and submitted to EMPLOYER for review and approval.
6) PT. PRATIWI PUTRI SULUNG shall collect survey and soil investigation data which
are necessary to perform pipeline design and installation.
7) PT. PRATIWI PUTRI SULUNG shall be responsible for defining and implementing all
necessary SITE investigations, including a sampling and testing schedule, and crossing
points.
8) The purpose of the SITE investigations shall be to identify and quantify those
characetristics or properties of the materials found on or under the SITE for use in the
design and execution of the WORKS. The defiition of what investigation is required
shall take into account the data provided at bid stage and any assumptions or
conclusions drawn from such data with respect to the characteristics or properties of
materials.
9) Before the start of construction in each area of WORK, PT. PRATIWI PUTRI
SULUNG shall make a condition survey of all structures, utilities and other facilities
within the zone of potential influence of construction (deemed to be not greater than 25
m from the Pipeline Route or Work Area, as the case may be).
10) PT. Pratiwi Putri Sulung shall design the pipelines by considering the plan of PU
(Kementrian Pekerjaan Umum) of 10 (Ten) meters road widening alongside the inspeksi
kali malang and investigate the pipeline sections which will be affected by this road
widening. The design of pipeline construction shall refer to typical ditch details.
11) The condition survey shall include a visual inspection of the existing structures and
PT. Pratiwi Putri Sulung

Scope of Work
Page 18 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

facilities, noting the type of construction, the existing condition of the structural
elements, facades, interior finishes and pavement, and any existing damage. The
condition of the existing structures and facilities shall be documented in a written
report, including sketches and photgraphs. Measurements shall be made of the location,
length and width of any cracks, voids, differential settlement, lateral deflection, spilling,
leaks or other observed damage.
12) PT. PRATIWI PUTRI SULUNG shall review and refine the allignment sheet existing
data and survey report provided by the EMPLOYER for the route of the pipeline to a
width sufficient encompass influences of the topographic on the design or construction
of the pipeline and associated structures.
13) PT. PRATIWI PUTRI SULUNG is required to check, confirm and supplement for
necessary existing cadastral surveys of all properties within 25 m of the boundary of the
SITE.
14) PT. PRATIWI PUTRI SULUNG shall be responsible for defining, implementing and
updating as required a survey to idetify all permits that need to be obtained to allow the
WORKS to be designed, executed and completed.
15) PT. PRATIWI PUTRI SULUNG shall be responsible for developing the existing
utilities, taking into account all existing utilities that may be affected by the carrying out
of the WORKS.
16) The survey shall be regularly updated and include interrogation of the responsible
authorities, the study of available drawings, interpretation of known SITE conditions,
the use of utility location equipment and the digging of test pits and trenches. It must
culminate in trial trenches to be excavated at each open cut excavation if needed. The
intended purpose of this investigation is to ensure that all utilities that need to be
supported, protected or relocated by reason of the WORKS are identified in sufficient
time to allow the WORKS to progress as planned.

8.4

Detailed Engineering
1) Certain PT. Pratiwi Putri Sulung Documents as specified in the Contract as being
required by the Employer to review. The submission of such documents and the
subsequent review thereof shall be carried out under the provisions of the Conditions of
Contract Desain Kontraktor.
2) PT. Pratiwi Putri Sulung obligation with respect to the design include the production of
a Design Manual, Plans for the management of the design process and the development
of the detail design and drawings into the detailed design, all such as will enable the
WORKS to be designed, procured, manufactured, constructed, installed, tested and

PT. Pratiwi Putri Sulung

Scope of Work
Page 19 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

commissioned in accordance with the Contract and to meet the requirements of the
EMPLOYER in the Scope of Work.
3) The ancillary work associated with those obligations includes planning, programming,
refinement, detailing, specifying, revising, quality control and verification and
documentation of the design and the administrative procedures associated therewith
through to and including production of As-built Drawings.
4) The design of WORKS, as contained in the detailed drawings, specifications and
procedures and all other documents to be prepared by PT. PRATIWI PUTRI SULUNG,
shall ensure that the WORKS are fir for their intended purposes. Inherent in the
intended purpose of the WORKS (and all component parts thereof) is that what is
designed and constructed is intrinsically safe, robust, reliable, durable and cost-effective
in operation.
5) The requirements with respect to the design given herein or elsewhere in the Scope of
Work are minimum requirements. Achievement thereof does not relieve PT. PRATIWI
PUTRI SULUNG of his obligation to comply with the fitness for purpose requirements
of the Contract.
6) The Plant and Materials within the completed Pipeline System shall allow optimum
operation at the given design condition specified in the EMPLOYERs requirements.
7) Adequate control measeures shall be installed to minimize the risks and hazards to
health, safety and the environment as far as is practicable.
8) The definition drawings are to be read as part of Specification and such drawings are
not intended to be used for construction purposes but to show specific Specification in
pictoral form and/or in a large sized tabular form. Such drawings show the minimum
requirements of the WORKS to be developed and carried out by PT. PRATIWI PUTRI
SULUNG for EMPLOYERs approval.
9) The illustrative drawings do not define the Specification, they serve to indicate design
solutions that could be acceptable to the Employer and which PT. PRATIWI PUTRI
SULUNG is free to adopt if he so chooses and adapt to suit the particular
circumstances.
10) It shall be the responsibility of PT. PRATIWI PUTRI SULUNG to determine if other
work beyond that shown on the definition drawings provided by EMPLOYER are
required to fulfill the Intended purpose of Contract Package No. 11 Upgrading Tangsi
Offtake Station and CL-2 Pipeline Project and to design, procure, fabricate, construct
and modificate all such additional facilities as may be rquired, all of which shall be
deemed to have been included in the Contract Proce stated in Surat Penunjukan
Pelaksana Pekerjaan.
11) The chainnages given in the Alignment Sheet provided by EMPLOYER are indicative
PT. Pratiwi Putri Sulung

Scope of Work
Page 20 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

only, and PT. PRATIWI PUTRI SULUNG shall determine the exact position of all
required pipeline system components from his own surveys prior to commencing design
work.
12) The suitability of the design to satisfy the Contract and be fit for purpose shall be
deemed to rest entirely with the PT. PRATIWI PUTRI SULUNG, notwithstanding
issuance of any approval notice.

8.4.1

Onshore Distribution Pipeline


1) Detailed Engineering of the PROJECT shall be in accordance with the Engineering
design performed by PT. PRATIWI PUTRI SULUNG and shall include, but not limited
to the followings:
Reviewing and verifying preliminary engineering specified in the Bid

Documents/Contract.
Performing survey as required in Section 8.3.
Reviewing and verifying requirements of pipes and materials excluding free

issue materials supplied by EMPLOYER.


Performing the Process Hazard Analysis (PHA) study.
Perfroming additional engineering required to complete the design.
Preparing calculation for bridge structure, bridge foundation and road crossing.
PT. PRATIWI PUTRI SULUNG shall design the pipeline bridges to withstand
the load of the pipeline. Dead load, live load, wind load, quake load and thermal
stress conditions shall be taken into account for the stress analysis of the bridge,
and weight of hydrostatic test water shall be considered as additional load fro

bridge design.
Confirming quantities of pipes, fittings and flanges.
Preparing construction procedures.
Preparing testing procedures.
Preparing Operations and Maintenances Manual and Procedures.
Preparing pre-Commissioning procedures.
Preparing Commissioning Manual and Procedures.
Preparing Trial Operation Procedures
Completing As-Built drawing.

2) Specifications and data sheets:


Pipe & Fitting Materials Specification and Data Sheet, except free issue

materials supplied by EMPLOYER.


Valve Specification and Data Sheet.
External and Internal Coating specification and data sheet.
Field Joint Coating Specification and Data Sheet.

PT. Pratiwi Putri Sulung

Scope of Work
Page 21 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Valve Coating Specification (for valve box application).


Painting System Specification (for above ground piping and structural steel).
Topography Survey Specification.
Survey and Soil Investigation Specification.
Civil and Structural Specification.
Steel Pipe Casing, Casing Spacer and End Seal Data Sheet.
Permanent Cathodic Protection System Specification.
Specification for Hydrostatic Test.
Other technical specifications or data sheets required to complete the detailed
design.

3) Design Calculations:
Road Crossing/Highway Crossing Calculation.
Hydrolic Analysis.
Horizontal Directional Drilling Calculation, if any.
Free Span Analysis, if required.
Pipe Stress and Flexibility Analysis.
Pipe Wall Thickness Calculation.
Bridge Structure and Foundation Calculations.
Buoyancy Control Design Calculation for construction in swampy area, if any.
Anchor block design and calculation.
Valve box design calculation.
Blowdown calculation.
Cathodic Protection Calculation.
Material Take Off.
Calculation of Anti-buoyancy Control.
Pipeline Lowering in analysis at limited space.
Electrical Load Calculation
Other technical calculation required to complete the detail design.
4) Procedures, which shall consist, but not limited, of following subjects:
Material handling, Transporation and Storage Procedure
SITE Clearing Procedure.
Cutting Pavement, Trenching and Backfilling Procedure.
Pipe Hauling and Stringing Procedure.
Pipe Line-up, Cutting, Beveling (with removing varnish) and Welding

Procedure.
Field Joint Coating Procedure.
Pipe Lowering Procedure.
Pipeline Crossing with Existing Utility Procedure.
Reinstatement Procedure
Crossing Procedure for all crossings (road, highway, river, waterway, etc.) and

teh method used (open cut, auger boring, others).


Construction and installation procedure for swampy area (if any).

PT. Pratiwi Putri Sulung

Scope of Work
Page 22 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Hot Tapping Procedure (including WPS).


Hydrostatic Test, Dewatering and Dry Procedure.
Pre-Commissioning & Commissioning Procedure.
Trial Operation Procedure.
Other procedures required to complete the Works.

5) Quality Assurance and Quality Control


Project Quality Plan
Inspection and Test Plan
WPS/PQR and weler certificate for pipeline and structure
Non Desctructive Examination Procedure
QA/QC General Requirement
QA/QC Manual
Procedure for NCR abd Disposition Plan
Material Receiving, Inspection and Storage Procedure
Procedure for Material Control and Taceability
Permits and Report form for construction work
Other quality assurance and quality control documents required to complete the
Works.
6) Design Drawings, which shall detail and describe regarding to this subjects:
Topography and Alignment Sheet (A3 size: Topography scale 1:500 and

8.4.2

elevation 1:100)
Crossings for all major crossing location (road crossings, river crossings, pipe

brdges, existing facilities, etc: A3 size)


Isometric Drawings (A3 size)
Permit Drawings
Obstacle Identification
Places where installation position will be changed extremely
Underground valves and boxes
Piping and Instrumentation Diagram
Hydrostatic Test Diagrams
Electrical Single Line Diagrams
Cathodic Protection
Topographical data, control monuments and crossing location
Adjacent property owners, if required
CP test locations
Marking post and warning sign locations
Bridge structures
And other drawings required to complete the detailed design

Tangsi Offtake Stations -2 (TS-2)


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design both of

PT. Pratiwi Putri Sulung

Scope of Work
Page 23 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

TS-2 and its facilities in accordance with the Project Specifications, and shall include,
but not limited to the followings:

Reviewing and verifying preliminary engineering specified in the Project


Specifications, Data Sheet, Drawings, Guidelines and another data have been

provided by EMPLOYER.
Reviewing and verifying requirements of pipes and materials excluding free

issue materials supplied by EMPLOYER.


Performing detailed engineering required to complete the design including

calculations, specifications, data sheets, drawings


Performing the Process Hazard Analysis (PHA) study
Preparing design drawings
Preparing detail equipment layout and station layout
Confirming quantities of pipes, fittings and flanges as Material Take Off (MTO).
Preparing construction and installtion procedure
Preparing test procedure
Preparing Operations and Maintenances Procedure
Preparing Pre-Commissioning Procedure
Preparing Commissioning Procedure
Preparing Trial Operation Procedure
Completing As-Built drawing

PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design
consisting of the following but not limited to:
1. Speifications and data sheets:
General Specification for Instrument
Metering and Regulating System
Piping and Fitting Materials
Valves
Insulation Joint
Fire and Gas System
Fire Extinguisher System
Fire Water System
Instrument Air System
General Electrical
Uninterruptible Power Supply
Power Distribution Board
Grounding and Lightning Protection
Electrical Cable
Cathodic Protection System
Filter
Diesel Engine Generator
Painting and Coating System
Survey and Soil Investigation
PT. Pratiwi Putri Sulung

Scope of Work
Page 24 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Civil and Structural


Shutdown Valve
Orifice Meter Data Sheet (Senior Orifice Fitting)
Flow Computer
Metering Station Computer, Instrumenation and Equipment
Design Control Logic and SAFE Chart
Pressure Control Valve
Loacl SCADA (RTU include network)
Other technical specifications or data sheets required to complete
the detailed design.

2. Design Calculations:
Pipe Stress Analysis (including MRS station)
Pipe wall thickness calculation
Line sizing
Equipment Sizing (Filters, Pumps, Compressor, etc.)
Sizing and strength calculation, filter element calculation
Structure and foundation calculation
Control valve sizing and noise calculation
Meter Sizing
Utility Requirement
Thermowell calculation
Material Take Off
Uncertainty calculation
Ipe support foundation calculation.. pipe
Noise calculation on surrounding location (outside Offtake and

MRS Shelter, outside panel wall, fence, etc.)


Other technical calculation required to complete the detailed
design.

3. Procedures, which shall consist of following subject as minimum:


Material handling, transportation and storage procedure
SITE clearing procedures
Mechanical equipment installation procedures
Civil /Structure installation procedures
General Electrical installation procedures, including testing

PT. Pratiwi Putri Sulung

procedures
General Instrumentation installation procedures, including

testing procedures
Pipe hauling procedures
Pipe cutting, beveling (with removing varnish (if any)) and

welding procedures
Welding Procedures (WPS), certified by MIGAS
NDT procedures

Scope of Work
Page 25 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Painting procedures
Pipeline crossing with existing utility procedures
Reinstatement procedures
Hot tapping procedure (including WPS if any)
Hydrostatic test procedures
Pre-Commissioning & commissioning Procedure
Other procedures required to complete the Works.

4. Quality Assurance and Quality Control:


Project Quality Plan
Inspection and Test Plan
WPS/PQR and welder certificat for piping and structure,

certified by MIGAS
Non Destructive Examination Procedure
QA/QC General Requirement
QA/QC Manual
Procedure for NCR and Disposition Plan
Material receiving, inspection and storage procedure
Procedure for material control and traceability
Permits and reports form for construction work
Other quality assurance and quality control documents required
to complete the Works.

5. Design Drawings, which shall detail and describe regarding to this


subjects, as minimum:
Offtake Station and MRS general arrangement and layout (A3)
Offtake Station and MRS Skid (permanent and temporary MRS)

PT. Pratiwi Putri Sulung

and pipe support drawing (A3)


Isometric drawing (A3)
Process Flow Diagram (PFD) and Heat and Material Balance
Piping and Instrumentation Diagram (P&ID)
Civil and Structures Detail Drawings
Fire Water System Diagram
SAFE (Safety Analysis Function Evaluation) Chart
Cause and Effect Diagram
Permit Drawings
Obstacle identification
Place where installation position will be change extremely
Hydrostatic Test diagrams
Diagram for SCADA connection with Metering Regulating

System
Adjacent property owners, if required
Marking post and warning sign locations
Instrument Hook Up Diagram
Instrument Logic Diagram
Scope of Work
Page 26 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Instrument Loop Diagram & Termination Diagram


And other drawings required to complete the detailed design

8.4.3
New Fire & Gas System, Additional Fire Extingusher and
New Water System Engineering ;
PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
Fire and Gas System, consisting of the following:
Fire and Gas Design Specification
Fire and Gas Design Calculation
Gas Clean Agent (FM200) Calculation
Gas Clean Agen (FM200) Layout Drawing
Single Line Diagram
Detector Layour and Coverage drawing
Equipment Data Sheet
Portable Extinguisher Data Sheet
Portable Extinguisher layout drawing
Provision for SCADA connections
Water pond requirement calculation
Fire hydrant layout, that consist of water pond, fire pumps, hydrant, fire

8.4.4

piping system, siamese connection and accessories


Fire & Gas schematic drawing
Wiring diagram
Equipment Sizing
Other engineering documents/drawings required to complete the design

CCTV System Engineering


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
CCTV System, consisting of the following:
CCTV Design Specification
CCTV Layout Drawing
CCTV Single Line Diagram
Equipment Data Sheet
Other engineering document/drawings required to complete the design

8.4.5

Power Distribution System Engineering.


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
Power Distribution System, consisting of the following:
Power Distribution System Specification
Electrical Power System Study:
o Load Flow

PT. Pratiwi Putri Sulung

Scope of Work
Page 27 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

o Short Circuit
o Motor Starting
o Harmonic Analysis
o Equipment and Cable Sizing
Single Line Diagram Drawing
Layout drawing
Design for Main Distribution Board (MDB) complete with Automatic
Transfer Switch (ATS) to accommodate the provision of diesel engine

generator
Provision for SCADA connection
Electrical Load Calculation (Including DEG selection)
Other engineering documents/drawings required to complete the design

8.4.6
Electrical System Engineering (Grounding, Lightning
Protection and Lighting);
PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
Electrical System, consisting of the following:
Verify existing capacity of power supply from PLN and DEG during

8.4.7

detail design
Grounding, Lightning Protection and Lighting system calculation and

study. The Grounding shall be jumpered to existing grounding system.


Single Line Diagram drawing
Hazardous Area Classification drawing
Equipment Layout drawing
Interconnection/wiring diagram
Lightning Protection Layout drawing
Cathodic Protection System
Equipment Data Sheet
Other engineering documents/drawings required to complete the design

Diesel Engine Generator System Engineering


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
industrial silent type Diesel Engine Generator System, consisting of the following:
Diesel Engine Generator Data Sheet and Specification
General Arrangement
Diesel Engine Generator Sizing
Fuel Tank Sizing and Design
Other engineering documents/drawings required to complete the design

8.4.8

UPS System Engineering;


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the

PT. Pratiwi Putri Sulung

Scope of Work
Page 28 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

industrial type UPS system and provided by vendor with proven satisfactory supply and
services that feeds the vital loads.
The load of UPS system shall consist of vital equipment related to SCADA, IT and
Telecom system, Metering & Regulationg instrument system. The unit shall be designed
to include 25% minimum margin applicable for future load growth.
PT. PRATIWI PUTRI SULUNG shall calculate the power requirement, battery and
rectifier sizing.
The design life of Industrial type UPS unit and the batteries shall be minimum 20
(twenty) years.
UPS system shall be designed as back-up power supply for 4 (four) hours of full load
operation.
PT. PRATIWI PUTRI SULUNG shall provide the following design documents during
detail design:
UPS Design Specification
UPS Data Sheet
Calculation Notes for the UPS unit including battery, rectifier and

inverter
Single Line Diagram of the UPS unit including the distribution unit
Interconnection/wiring diagram the US unit and Distribution Unit
Other engineering documents/drawings required to complete the design

Detail requirement of the UPS system shall refer to Equipment Specification of UPS
System.
PT. PRATIWI PUTRI SULUNG shall develop Equipment Data Sheet of UPS and
drawing for UPS Single Line Diagram based on existing data reference. PT. PRATIWI
PUTRI SULUNG shall perform survey to get the existing data on his own cost.

8.4.9
Instrumentation System (field instruments, flow
computer, metering station computer, marshalling rack),
SCADA and Telephony Engineering.
PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
Instrumentation System, consisting of the following:

PT. Pratiwi Putri Sulung

Equipment Data Sheet


Flow computer programming

Scope of Work
Page 29 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

8.4.10

System Architecture Drawing


Hook-up drawing
Wiring diagram
Instrument Wiring Connection List
Panel Arrangement
Loop drawing
Cable and Equipment Layout drawing
Equipment Sizing
Local SCADA connection
Local RTU programming
Acoustic Survey
Telephony system
Other engineering documents/drawings required to complete the design

Civil Engineering.
PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
Instrumentation System, consisting of the following:

Water pond for fire water system calculation


Foundation calculation
Movable Gantry Crane calculation
Structure calculation
Offtake and MRS Shelter and DEG shelter design drawing and
calculation. In designing the Offtake station and MRS shelter, PT.
PRATIWI PUTRI SULUNG shall consider the applicable regulation on
noise to surrounding environment (such as Decree of Environmental
Ministry).

PT. Pratiwi Putri Sulung

Layout drawing (include muster point and evacuation route)


Modification drawing of existing facility, that consist of:
o
o
o
o

Water chamber ponds repair after re-calculation


Drainage system
Main Gate and fence
Modification of Control Building (electrical room and control

o
o
o
o
o
o

room) for relocation / additional equipment, panel, etc.


Additional building prayer room and locker room
Replacement of exixting security guard house
Parking area for car and motorcycle complate with canopy
Pathway complate with canopy between main buildings
Drivver shelter
Other modification of the existing facility required to complete

Scope of Work
Page 30 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

the Works.

Building and civil structure drawing


Panel wall for reduce noise from MRS shelter
Movable Gantry Crane with railway :
Material handling equipment shall be provided to facilitate
handling, removal and replacement of any maintanable items.
All material construction for Movable Gantry Crane shall be
non-spark/spark resistance applicable for operation within
hazardous area
The Movable Gantry Crane shall be one type girder fixed height
All material handling equipment shall be design in accordance
with MIGAS regulations and applicable standards and codes
The Movable Gantry Crane shall be designed as railway
movable along long side of MRS building
The maximum capacity of material handling equipment shall be
5T and contractor to verify the wighest single equipment will be
handled in the MRS building for maintenance or operation
Minimum height of girder (under bottom) shall be 1.5 M from
the tallest equipment installed on MRS System
Clear span shall be 1 M (minimum) from outer side of
equipment
The railway for Movable Grantry Crane shall be flat with the
floor.

8.4.11

Other engineering documents/drawings required to complete the design.

Architectural Design Engineering.


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
Architectural Engineering, consisting of the following:

8.4.12

Exterior design drawing


Fence design
Gate design
Building and Structure painting
Other engineering documents/drawings required to complete the design.

Building Utilities Engineering.


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for

PT. Pratiwi Putri Sulung

Scope of Work
Page 31 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

building utility, consisting of the following:

8.4.13

Sanitation design and plumbing system (sewage, sanitary, clean water

system)
HVAC
Building Layout drawing
Other engineering documents/drawings required to complete the design.

Instrument Air System Engineering.


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
Instrument Air System, consisting of the following:

8.4.14

Equipment Specification and Data Sheet


Hook-up drawing
Wiring diagram
Equipment Sizing
Other engineering documents/drawings to complete the design

Utility Water System Engineering; Modification


PT. PRATIWI PUTRI SULUNG shall perform detailed engineering and design for the
Utility Water System. Existing utility water system is available which PT. PRATIWI
PUTRI SULUNG to connect with. The following shall be developed:

Plumbing system drawing


Equipment Specification and Data Sheet
Connection plan to existing system
Other engineering documents/drawings required to complete the design.

9. INDEPENDENT DESIGN VERIFICATION


Each Design Submission shall be accompanied by a Design Verification Certificate (DVC)
signed by and independent Design Verification Engineer (DVE) to ensure that the
EMPLOYERs entire Pipeline System has been properly designed in accordance with MIGAS
regulations, other Indonesian laws and regulations, and applicable safety-related standards and
codes, prior to the submission to the EMPLOYER. Each DVC shall:
a) Identify the Design Submission to which it relates, including all design calculations,
PT. Pratiwi Putri Sulung

Scope of Work
Page 32 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

key engineering drawings (process flow diagrams, piping & instrument diagrams,
alignment sheets, layout drawings, crossing/sectional drawings and other relevant
details),

simulation

procedures/results,

materials

specifications/data

sheets,

construction and transportation methodologies and their calculations, inspection and


testing plans/procedures and the like;
b) State that the design has been verified conceptually, analytically and arithmetically
c) Either state that the design complies with the relevant data provides by EMPLOYER
and Indonesian regulations and rules.
If the DVE (and/or DVE organization) was nominated at the bid stage, then such nomination
shall be deemed to be acceptable to the EMPLOYER. Where that was not the case, the name of
the proposed person and organization shall be submitted by PT. PRATIWI PUTRI SULUNG in
such time as to ensure that any adverse response thereto does not affect the Programme. If the
EMPLOYER is not satisfied with the proposed DVE, EMPLOYER shall give notice to that
effect to PT. PRATIWI PUTRI SULUNG within 28 days of PT. PRATIWI PUTRI SULUNG
submission stating the reasons. Should the EMPLOYER not give notice of dissatisfaction within
14 days, then EMPLOYER shall be deemed to be satisfied with PT. PRATIWI PUTRI
SULUNG nomination.

10.

PROCUREMENT
10.1

GENERAL

PT. PRATIWI PUTRI SULUNG SHALL be responsible for procurement of all materials and
equipments and for subcontract services including packing, shipping, transportation and
insurance to the site location(s), except free issued material supplied by EMPLOYER in Table1.
Regarding to these responsibilities, PT. PRATIWI PUTRI SULUNG shall perform, but not
limited to, the following procurement activities:
Prepare
and
issue
SUBCONTRACTOR(s)/VENDOR(s)

inquiry

packages

/SUPPLIER(s)

for

to
services,

permanently installed materials and equipment, including parts and tools


required for start up and pre-commissioning. (One un-priced copy of
those inquiry packages SHOULD be submitted to EMPLOYER for

PT. Pratiwi Putri Sulung

information).
Review SUBCONTRACTOR/VENDOR / SUPPLIER's Quotation
Scope of Work
Page 33 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

/Proposal on both technical and commercial viewpoint.


Perform
technical
evaluation
and
recommendation

of

SUBCONTRACTOR(s)/ VENDOR(s) /SUPPLIER(s) before issuance

Purchase Order.
Issue Purchase Order(s) for permanently installed materials and

equipment.
RESPONSIBLE for all custom clearance, duties and taxes on material

purchased by PT. PRATIWI PUTRI SULUNG.


Prepare a list of qualified SUBCONTRACTOR(s)/VENDOR(s)
/SUPPLIER(s) for services, materials and equipment supplied under this
PROJECT and submit to EMPLOYER for approval, in case the
SUBCONTRACTOR(s) /VENDOR(s)/ SUPPLIER(s) is different from

the CONTRACT.
Prepare a Procurement Plan including the milestone dates and progress

percentage schedule and issue to EMPLOYER for approval.


Coordinate, with SUBCONTRACTOR(s)/ VENDOR(s) /SUPPLIER (s),
the delivery of materials to meet the requirements and control delivery

schedules.
Report procurement status to EMPLOYER on bi-weekly basis.
Advise the EMPLOYER of the progress of material procurement and
provide status of all purchase orders issued, including those to be

prepared in the following month.


Obtain all required documentation, drawings, manuals, etc., from
SUBCONTRACTOR(s)/ VENDOR(s)/ SUPPLIER(s) as required for

Final Documentation and quality control.


Establish QMS (Quality Management System) to maintain quality
control, inspection procedures, schedules and ensure performance of all
purchased items

to the approved project

specifications, including

quality inspection and test witness.


Receive, load, transport and store all materials and equipments in a good

manner to prevent damage.


The rest of Free Issued material after construction shall be returned on

EMPLOYER warehouse by PT. PRATIWI PUTRI SULUNG.


Provide SUBCONTRACTOR/ VENDOR/ SUPPLIER's representatives

to direct, assist and certify proper on-site equipment installation.


At all times, keep and maintain detailed records of the materials and
equipments that have been purchased, received, stored and issued for

PT. Pratiwi Putri Sulung

Scope of Work
Page 34 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

construction and shall make such records available to the EMPLOYER

immediately on request.
Purchase of materials and equipments with or without the allowance to
proceed from the EMPLOYER will not relieve PT. PRATIWI PUTRI
SULUNG responsibility of liability

from obligations under

this

CONTRACT.
Provide materials and equipments with brand new and completed with
manufacturer certificate for each and shall be produced not later than 6

month prior CONTRACT.


Provide all equipments which sahll have local support for maintenance

and other services in Indonesia.


RESPONSIBLE to provide temporary storage of proper condition for

the materials and equipment until installation.


Prepare long lead material list which shall be submitted to EMPLOYER

for review in accordance with the schedule requirements.


Supply pipes, fittings, valves, flanges, gaskets, field joint coating, fiber
optic cable sub duct, liquid epoxy coating, cathodic protection system,
insulation joint, casing spacer & end seal, and other pipeline materials

except "Free Issue Material" listed in Table-1.


Supply all construction materials, bulks materials, and consumables
materials to achieve the requirement set forth in the specifications,

procedures and drawings.


Solely responsible to control and calculate the quantity of those materials

required to be used for the Works to accomplish the PROJECT.


Provide all shipping documents of all materials purchased by the PT.
PRATIWI PUTRI SULUNG. Such shipping documents shall include as a
minimum requirement as follows:
o a copy of latest revision of un-priced or priced purchase order

PT. Pratiwi Putri Sulung

document,
an original of the certificate of origin issued by the origin's

Chambers of Commerce- or Ministry of Trade and Industry,


an original of Certificate of Conformity issued by the Supplier/

o
o
o
o
o

Vendor,
an original of proforma/commercial invoice,
an original of the supplier's warranty certificate,
an original of bill of lading,
an original of packing list & weighing list,
an original of the ocean or inland marine insurance policy (as

Scope of Work
Page 35 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

applicable),
a copy of Factory Acceptance Test (FAT) Certificate (in an

approved format) and the Mill Certificate (if any),


a copy of Pemberitahuan lmpor Barang (PIB - Notification to
Import) and Surat Persetujuan Pengeluaran

Barang (SPPB -

Cargo Discharge approval) for permanent imported material.


a copy of Pemberitahuan lmpor Barang(PIB - Notification to
import) and Surat Persetujuan
Cargo

Discharge

approval)

Pengeluaran Barang (SPPBfor

temporary

imported

material/equipment and Pemberitahuan Ekspor Barang (PEB Notification to Export) after re-export of such temporary
imported material/equipment. an original of the

traceability

sheets,
a copy of customs clearance certificate and Tax Payment

Receipt, and
other related shipping documents as appropriate.

PT. PRATIWI PUTRI SULUNG SHALL refer to the following documents for
the detail requirements on procurement activities:

Doc. No. CP11A-PTU_3275-QC-PR-002 General Procurement and FAT


Requirement.

10.2

FREE ISSUED MATERIALS


PT. PRATIWI PUTRI SULUNG SHALL be fully responsible for executing inspection including
test tools and equipments, transportation, loading adn unloading (including lifting equipment,
etc), of the "Free Issue Materials" from EMPLOYER (locations see Table-1) to SITE location
including any insurance for those activities.
All of the EMPLOYER'S Free Issue Materials when first received by PT. PRATIWI PUTRI
SULUNG and being thereafter under effective control of PT. PRATIWI PUTRI SULUNG will
be accounted for by a Material Receiving Report (MRR).
The PT. PRATIWI PUTRI SULUNG SHALL prepare each MRR identifying the Materials
receipt from the EMPLOYER by identification numbers, description and quantity received
by PT. PRATIWI PUTRI SULUNG after joint receiving inspections made by the EMPLOYER
and PT. PRATIWI PUTRI SULUNG for verifying condition of Materials and a physical count

PT. Pratiwi Putri Sulung

Scope of Work
Page 36 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

of quantity made. Any discrepancies observed during such joint inspection shall be noted on an
Over, Short and Damage (OS&D) Report. Once PT. PRATIWI PUTRI SULUNG accept and
deliver the Free Issue Materials to his stockyard, if any damages found in the beveL coating,
etc., they SHALL be repaired by the PT. PRATIWI PUTRI SULUNG.
PT. PRATIWI PUTRI SULUNG SHALL be fully responsible for loading, transporting,
protecting, temporary storing, installing, inspecting and testing, and insuring all of the
EMPLOYER'S Free-Issue Materials after receipt of those Materials at such stockpile yards from
the EMPLOYER.
TABLE-1: FREE ISSUED MATERIAL

NO
1

ITEM
Ball Valve 16 #300

TOTAL
1 ea

EMPLOYERs
Stockpile Locations
+- 100 km
From Jakarta

PT. PRATIWI PUTRI SULUNG shall re-tagging all free issued material of valves based on
PFD and P & ID drawings
PT. PRATIWI PUTRI SULUNG shall collect all EMPLOYERs Free Issued Materials at such
stockpile yards designated by EMPLOYER within six (6) months after the commencement Date
of by any date informed by the EMPLOYER

10.3

OFFTAKE STATION
1. Metering & Regulating System (MRS) for Permanent MRS Station.
PT. PRATIWI PUTRI SULUNG shall supply Metering & Regulating System
include but not limited to: insulating joints, isolation valves, filters, shutdown
valve, sampling system, straightening vanes, orifice flowmeters, pressure
control valves, shutdown valves, check valves, fire water system, instrument
air system, pipes, fittings, all piping components, and special fittings (if any).
PT. PRATIWI PUTRI SULUNG/SUBCONTRACTOR shall have license as
PERUSAHAAN PERAKIT PEREKAYASA SISTEM METER MINYAK
DAN GAS BUMI issued by DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI.

PT. Pratiwi Putri Sulung

Scope of Work
Page 37 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Equipment for metering shall be listed in DAFTAR ALAT UKUR MINYAK


DAN GAS BUMI issued by DIREKTORAT JENDERAL MINYAK DAN
GAS BUMI.
2. Fire & Gas, Fire extinguisher and Fire Water System
PT. PRATIWI PUTRI SULUNG shall supply for new Fire & Gas and Fire
System for tangsi offtake station-2 and Extinguisher System for Tangsi
Offtake. This shall include but not limited to Smoke detectors, gas detectors,
flame detectors, heat detectors, alarm/control panels, manual push button
alarms,

strobe

lamps,

portable

extinguishers,

wheeled

extinguishers,

horns/sirens.
The Gas Clean Extingushing Agent system shall be completed with gas tanks,
pipes and accessories.
PT. PRATIWI PUTRI SULUNG shall develop and build Fire & Gas and Fire
Water System in accordance to NFPA standard, UL&FM and local regulation
requirement to protect the Tangsi Offtake Station from fire hazard occured at
the outside of the Station.
The Fire Water System shall include but not limited to Diesel fire water
pump(s), jockey pump, siamese connection(s), pipes, fittings, valves, fire
station, fire water pond and all the required construction materials and tools.
In the case the system is new system requirements, the new Fire Water System
for Fire & Gas and Fire Extinguisher, each system shall be originated from
year 1 (one) Manufacturers product/brand only.
3. Instrument Air System
PT. PRATIWI PUTRI SULUNG shall provide Instrument Air for pneumatic
actuated valves and cleaning purposes. The Instrument Air System shall
include but not limited to air compressors, air dryer, instrument air receivers,
pipes, fittings, valves and all the required construction materials and tools.
4. Utility Water; Modification
PT. PRATIWI PUTRI SULUNG shall provide Utility Water for cleaning and
sanitary purposes. The utility water system shall be designed in accordance
with the requirements of Decree of the Minister of Health No.
416/MENKES/PERIIXI 1990 for Clean Water Standard.
The Utility Water System shall include but not limited to deep wall pumps,
deep well, transfer pumps, filters, water metering equipment water tanks, pipes,

PT. Pratiwi Putri Sulung

Scope of Work
Page 38 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

fittings, valves and all the required constraction materials and tools
5. CCTV Camera; Addition
PT. PRATIWI PUTRI SULUNG shall supply and install CCTV System for TS2 (as additional system requirement).
PT. Pratiwi Putri Sulung shall provide new CCTV system and integrate with
the existing CCTV cameras.
6. Local SCADA
PT. PRATIWI PUTRI SULUNG shall supply new Local SCADA for Tangsi
Offtake Station-2
7. Power Distribution System
PT. PRATIWI PUTRI SULUNG shall provide new Power Distribution System
for Tangsi Offtake Station-2. This shall include but not limited to main
connection to PLN, main PDBs, lighting panels, power cables, cable
supporting systems, cable accessories, cable tagging system and accessories.
8. Uninterruptible Power Supply (UPS) System
PT. PRATIWI PUTRI SULUNG shall supply new the UPS system for Tangsi 2
Offtake Station included with the battery bank and the distribution unit in
accordance with the approved detail design Specification, Data Sheet and
Drawing.
9. Electrical System
PT. PRATIWI PUTRI SULUNG shall supply new Electrical System for the
Tangsi 2 Offtake Station, include but not limited to:
Grounding system for electrical system, instrument system and
telephony system completed with grounding rods, grounding cables,
spark gap (TEC Transient Earth Clamp), grounding fittings,

grounding bus bars, anti surge protection and accessories;


Lightning protection system completed with air terminals, down

conductors, lightning protection poles, and accessories;


Lighting system completed with flood light, indoor and outdoor
lighting, classiefied area lighting, emergency lighting, panels, lighting

poles, lighting switches and accessories;


Cathodic Protection System

10. Diesel Engine Generator System


PT. PRATIWI PUTRI SULUNG shall supply new Diesel Engine Generator
System for the backup power source of Tangsi Offtake Station for existing

PT. Pratiwi Putri Sulung

Scope of Work
Page 39 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

DEG replacement. This shall include but not limited to: Diesel Engine
Generator packages, remote battery chargers, fuel tank, cabling and
accessories. PT. PRATIWI PUTRI SULUNG shall verify during detail survey.
11. Instrumentation System
PT. PRATIWI PUTRI SULUNG shall supply new Instrumentation System for
Tangsi Offtake Station-2 and CL-2. This shall include but not limited to: flow
computers, metering station computers, alarm printers, marshalling rack, flow
computers cabinets, junction boxes, instrument wiring, instrument tagging,
cable supporting system, fitting tubing and valves, cable ties, cable lugs and
accessories, transmitters, indicators and gauges.
12. PABX System
PT. Pratiwi Putri Sulung shall supply new PABX system including phones
cables and its auxilliaries
13. Civil Structure
PT. PRATIWI PUTRI SULUNG shall supply Offtake Shelter, MRS shelter,
DEG Shelter, Fire Water Pump Shelter, etc. PT. PRATIWI PUTRI SULUNG
shall perform joint survey to define whether this scope will be modified or
shall be new designed one.
14. Civil
PT. PRATIWI PUTRI SULUNG shall supply civil material for the Offtake and
MRS stations.
Tthis shall include but not limited to: steel structures, shelters, concrete
structures, fences, gates, foundations, supports, brick wall, gravel, raised floors,
roofing, soil for enbankments and all the required construction materials and
tools.
15. Architectural Works
PT. PRATIWI PUTRI SULUNG shall supply Architectural works for the
Offtake and MRS Station. This shall include but not limited to: paintings,
roofing, furniture, outdoor decorations, planting, including any special
materials required to accomplish the WORKS.
16. Building Utilities
PT. PRATIWI PUTRI SULUNG shall supply Building Utilities for the Offtake
and MRS stations. This may include but not limited to: access road, pathway,

PT. Pratiwi Putri Sulung

Scope of Work
Page 40 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

canopy, drainage system, plumbing system including toiletries, piping,


ventilation and air conditioning system and accessories. PT. PRATIWI PUTRI
SULUNG shall perform joint survey to define whether this scope will be
modified or shall be new designed one.

11.

CONSTRUCTION WORK
11.1

GENERAL

1. The construction work SHALL be planned and executed so as to ensure that the
disruption to existing utility services is not such as to cause undue inconvenience
or to compromise safety. PT. PRATIWI PUTRI SULUNG shall ensure that where
necessary:
a) full coordination is established with the Toll Road operators and authorities of
existing and planned construction of utility services, and
b) public information services, with advice issued in sufficient time, are provided
where disruptions to existing utility services are unavoidable.
2. PT. PRATIWI PUTRI SULUNG is required to plan the design, execution
and completion of the WORKS in such a manner that the WORKS progress in an
orderly fashion, with due expedition and without delay.

The planning and

associated coordination is to include the identification of all external interfaces


within the design, execution and completion process. These include such diverse
aspects as complying with planning and building regulations, obtaining permits or
consents for operations on or under land or water,

traffic diversion, utility

protection and relocation. and coordination of design and construction with other
CONTRACTOR.
3. The Contract is an EPC contract. The primary motivation of such a contract is
"sole" source responsibility for design. construction and commissioning, and the
principal practical advantage thereof lies in the programming, planning and
coordination aspects of the design, execution and completion of the WORKS. PT.
PRATIWI PUTRI SULUNG planning and coordination obligations are imposed to

PT. Pratiwi Putri Sulung

Scope of Work
Page 41 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

ensure that this advantage is realized.


4. PT. PRATIWI PUTRI SULUNG obligation with respect to construction include a
requirement to:
a)

identify, prospect, survey, secure, extract, pay royalties for and transport
as the case may require, all natural materials needed to be brought to Site and
to ensure that they comply with the requirements of the CONTRACT, and

b)

ensure that any area on or in which PT. PRATIWI PUTRI SULUNG has
worked upon or acquired for the extraction of materials is reinstated and
rehabilitated, unless arrangements have been made for the further use of
such land.

5.

Within

the constraints given in

the Employer's Requirements and any

constraints that may be imposed by legislation or national or municipal


regulations, and by the incorporation in the CONTRACT of specific proposals
made by PT. PRATIWI PUTRI SULUNG in his bid (if any), PT. PRATIWI PUTRI
SULUNG is free to use whatever methods he considers to be appropriate to
construct the WORKS.
6.

Unless otherwise stated in the Employer's Requirements, installation and


application procedures for each product are required to be in accordance with the
appropriate manufacturer's

recommendations. PT. PRATIWI PUTRI SULUNG

SHALL, when so requested, furnish the EMPLOYER with printed

copies

of

such recommendations prior to installation or application.


7. PT. PRATIWI PUTRI SULUNG SHALL remedy any damage or defect (which
was attributable to PT. PRATIWI PUTRI SULUNG improper operation and
maintenance for construction related workmanship) within a reasonable time at the
risk and cost of the PT. PRATIWI PUTRI SULUNG.
8. The PT. PRATIWI PUTRI SULUNG shall be solely responsible for any
accident

or incident occurred attributable to PT. PRATIWI PUTRI SULUNG

construction workmanship. In such case, PT. PRATIWI PUTRI SULUNG SHALL


co-operate with the relevant landowner or property-owner in accordance with the

PT. Pratiwi Putri Sulung

Scope of Work
Page 42 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

agreed emergency response plan and procedures.


9. PT. PRATIWI PUTRI SULUNG SHALL be RESPONSIBLE for following
construction work. including but not limited to :

Construction I installation of the overall system under the PROJECT.

Supply labors, technicians, and engineer professionals, with sufficient skills and capability for
doing the work.

Provide all tools and special tools to do the work.

Provide spare parts, consumables and required tools during testing (individual and or
integrated), pre-commissioning, commissioning and trial operation.

Bear any taxes or levies to obtain all permits and licenses under this PROJECT.

Negotiating and making free and clear of any illegal houses or obstacles on the pipeline
route. All of the cost SHALL be borne by PT. PRATIWI PUTRI SULUNG.

Undertake and accomplish reinstatement and restoration for any damage of any existing
facilities due to access and work.

Complete installation, tie-in work, testing, pre-commiSSIOning, commissioning and trial


operation of this PROJECT. The work SHALL be performed in accordance with the Contract
Documents, including the approved construction procedures, drawings and specifications by
EMPLOYER.

Complete the work in accordance with the construction schedule submitted in its proposal and
approved by EMPLOYER.

Calculate the quantities of all materials required to accomplish the PROJECT.

Describe the progress of work, and the portion of the work forecasted to be completed and
SHALL be presented to EMPLOYER at regularly scheduled progress meeting.

PT. PRATIWI PUTRI SULUNG SHALL responsible for obtaining a proper Permit to Work
(PTW) from PGN's operating and maintenance team namely Strategic Business Unit (SBU)
before commencing the relevant work within or adjacent to the Site. Such Permit to Work shall
be issued by SBU strictly in accordance with its own Permit to Work System.

PT. Pratiwi Putri Sulung

Scope of Work
Page 43 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Provide security and safety arrangements for the protection of humans and properties during
construction period.

Carry out the proper disposal of liquid and solid wastes generated as a result of the construction
operations.

All recruitments stated in all Construction Specification document

11.2

WORK SPACE ACQUISITION

PT. PRATIWI PUTRI SULUNG SHALL provide all temporary work space not
specifically provided by the EMPLOYER as required, to survey, install and commission
the facilities as described in this document.
PT. PRATIWI PUTRI SULUNG SHALL provide proof of temporary work space
agreements with land owners to the EMPLOYER prior to commencing work.

11.3

PERMIT, LICENSES, RETRIBUTION AND LEVIES

PT. PRATIWI PUTRI SULUNG shall fully comply with and be totally responsible for
satisfying the requirements of Indonesian laws and regulations with regard to the
implementation of the WORKS, including obtaining permits, licenses and certificates
issued by relevant authorities. Further, insofar as it is within PT. PRATIWI PUTRI
SULUNG ability to do so, it is PT. PRATIWI PUTRI SULUNG responsibility to render
all assistance to the EMPLOYER to obtain operational permits, licenses and approvals
from all relevant authorities.
PT. PRATIWI PUTRI SULUNG shall be responsible to obtain all required permit
to accomplish the PROJECT, including but not limited to: surveying, liaising with
permitting agencies, site visits, photography, drawing preparation,

methodology

description/ procedures, work instructions, hot work permit, cover letters, works
progress schedules and reports, safety and environmental mitigation measures,
emergency response procedures and control procedures.
PT. PRATIWI PUTRI SULUNG SHALL be fully RESPONSIBLE in obtaining
necessary work permits from regulatory authorities for all personnel and equipment
involved in the PROJECT, including permits for performing construction activities,
PT. Pratiwi Putri Sulung

Scope of Work
Page 44 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

transporting of equipment and materials, permits and visas for PT. PRATIWI PUTRI
SULUNG Personnel, import and export of Goods, handling radioactive material,
treatment and disposal of liquids and water used for hydrostatic tests, and moving of its
equipment, personnel and PGN's operation.
Specifically, PT. PRATIWI PUTRI SULUNG SHALL be deemed to be fully aware that
compliance with all the requirements of MIGAS is fundamental to the successful
completion of both the WORKS and the PROJECT as a whole.
The EMPLOYER will appoint a third party inspection company certified by MIGAS to
review. inspect and verify whether or not the work undertaken by PT. PRATIWI
PUTRI SULUNG complies with MIGAS regulations and standards. PT. PRATIWI
PUTRI SULUNG shall be RESPONSIBLE for providing any and all services necessary
for obtaining MIGAS approvals and certificates including preparation of all necessary
specifications. procedures. plans and records as required by MIGAS or the third party
inspection company.
When a permit, in accordance with issuing authority regulations. has to be applied
for and issued to the EMPLOYER , PT. PRATIWI PUTRI SULUNG shall identify
the authority responsible for issuing the permit, prepare the application to the extent
possible and provide whatever documentation is required to support the application.
PT. PRATIWI PUTRI SULUNG shall then request the EMPLOYER to complete the
application and submit it to the relevant authority.
The Employer has PARTIALLY initiated the process of obtaining the Permits
for public road, river crossing and other facilities and infrastructures from the relevant
authorities as shown in Attachment-3 of this scope of works. PT. PRATIWI PUTRI
SULUNG shall continue and complete the process of obtaining such Permits under PT.
PRATIWI PUTRI SULUNG own cost. PT. PRATIWI PUTRI SULUNG is
RESPONSIBLE to initiate and proceed the permits that had not yet initiated by
EMPLOYER. When such permit is expired during Project completion period. PT.
PRATIWI PUTRI SULUNG is responsible to renew all permit required.
All cost for permits, licenses retributions and levies required shall be borne by PT.
PRATIWI PUTRI SULUNG.

PT. Pratiwi Putri Sulung

Scope of Work
Page 45 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

11.4

PIPELINE CONSTRUCTION

PT. PRATIWI PUTRI SULUNG shall do the works required to complete the overall
pipeline system. The work shall include but not limited to:

Responsible to obtain all permits, levies, retribution and licenses from

regulatory authorities to perform construction work.


Survey and stake the branch-line distribution alignment and SITE boundaries,

including soil investigation and soil resistivity test.


Perform test pit trenching to confirm existing utilities..
Clear the pipeline route from trees, illegal building, if necessary.
Transport and store all materials and equipment as required.
Construct temporary fences and warning marker during construction.
Cutting pavement, trenching, excavation up to the bottom of trench.
Install Soil Erosion control to control traffic during construction
Prepare proper person to control traffic during construction.
Ditch protection shall be installed to prevent the soil failure during

construction.
Opening dicth shall covered by temporary banner with environment picture and
PGN logo to avoid driver gaze on construction activity when drive the vehicle

which makes possibility of accident.


If required, the arrangement of ditch protection shall follow typcal Ditch Detail

Drawing (CP11A-PTU-3275-CV-DG-002).
Apply sand bedding and padding for stringing pipe, as required.
Construct sheeting with temporary support during trenching activity.
Prefrom qualification of welding procedures and welders.
Removing pipe coating (stripping) for above ground pipe installation (i.e; pipe

bridge crossing, piping on stations, etc).


Apply painting for above ground pipe/piping installation.
Cutting and beveling (with removing varnish) pipe prior to welding.
Hauling, stringing, alignment and welding the pipe.
NDT for welding joint by radiographic test, visual test and liquid penetrant

test/magnetic particle inspection for fillet weld and UT for Golden Joint.
Apply coating with heat shrink sleeve to welding joint and fitting.
Perform holiday inspection of completed coating.
Apply external and internal coating for fittings.
Apply external and internal coating for bare spool in the valves boxes.
Lowering pipe into ditch.
Repair damaged coating.
Perform traceability inspection.
Install dicth plugs as required

PT. Pratiwi Putri Sulung

Scope of Work
Page 46 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Install temporary cathodic protection.


Install permanent cathodic protection.
Install grounding cell around AC (Alternating Current) influence area.
Install permanent reference cell at the palce where it is difficult to put the

temporary reference electrode.


Backfill the ditch and compaction as required in Construction Specification for

Onshore Pipeline Construction (Doc. No. CP11A-PTU-3275-PL-CS-001).


Install block valves, venting pipe, and associated piping work including
support, valve box,foundations and vaults, apply liquid epoxy coating for

valves inside valve box for pipeline section.


Maintain temporary surface permanent to keep safety traffic
Insulating Joint as indicated in the piping and instrumentation diagram CP 11A

Tangsi Offtake Station -2 (Doc No. CP11A-PTU-3275-PS-DG-003)


Reinstatement and restoration of all damaged within the work area.
Install gas pipeline marking tape above pipe.
Install signs and markers.
Install accessories, including warning tape for all pipeline and concrete tile if

necessary
Install concrete slab above pipeline for river and road crossing (if required).
Tie-Ins work, including tie-in with existing piping facilities.
Collect and record as-built survey data.

11.5

PIPE BRIDGES CONSTRUCTION

PT. PRATIWI PUTRI SULUNG shall do the works required to complete the pipe
bridges construction. The work shall include but not limited to:

Facbricate & install bridges crossing including safety fence to avoid vehicle

accident.
Strip the external piping coating.
Painting the pipe and the bridge structures as specified.
Pipe installation/erection above the bridge.
Foundation (pilling and pilling test) pile cap work.
Install insulation joints at both end of pipe on bridge.
Construct and install anchor block for each pipeline bridge crossing, based on

stress analysis calculation approved by EMPLOYER.


Install pipe support and insulation material between pipe and supporting steel

structures (telepon sheet, etc).


All construction procedures and drawings shall be reviewed and approved by
EMPLOYER prior to release for construction.

PT. Pratiwi Putri Sulung

Scope of Work
Page 47 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

11.6

Reinstatement of all damaged within bridge construction area.

PIPELINE CROSSINGS

PT. PRATIWI PUTRI SULUNG shall do the works required to complete the crossing
construction. The work shall include but not limited to:

Determine the appropriate boring method for crossing, which shall use auger
boring, or better method with enough equipment capacity for pipe and depth
cover of pipe besed on approved calculation. For auger boring method, PT.
PRATIWI PUTRI SULUNG shall protect the external pipe coating by using
double wrapped Poly Ethylene coating or methode / materials approved by
EMPLOYER. PT. PRATIWI PUTRI SULUNG shall investigate the SITE and
soil condition prior to boring, and prepare the pit boring with adequate depth
and equipped with temporary shore structure to prevent soil erosion and land

sliding.
PT. PRATIWI PUTRI SULUNG shall install sacrificial cathodic protection

system at pipe casing with design lifetime 50 years.


PT. PRATIWI PUTRI SULUNG shall protect welding joint using special

shrink sleeve (ex: Dyrax or equivalent) for construction


PT. PRATIWI PUTRI SULUNG shall conduct a close coordination with permit

authorities during construction.


PT. PRATIWI PUTRI SULUNG shall prepare boring procedures, launching pit
and exit pit protection, equipment and facilities, and shall obtain the prior
consent from EMPLOYER before start of the crossing work.

11.7

REINSTATEMENT

PT. PRATIWI PUTRI SULUNG shall be responsible for reinstatement work within or
adjacent to the work areas used by the PT. PRATIWI PUTRI SULUNG.
The reinstatement requirements, including quality of material and workmanship shall
be subject to acceptance of Toll road operator, the EMPLOYER, Landowner, authorities
and other property owners.
Particularly for rigid pavement reinstatement, PT. PRATIWI PUTRI SULUNG shall

PT. Pratiwi Putri Sulung

Scope of Work
Page 48 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

replace entire segment of rigid pavement within or adjacent to the pipeline construction
area used by the PT. PRATIWI PUTRI SULUNG. The reinstatement requirements for
such replacement including quality of materials, workmanship and warranty shall be
subject to the acceptance of the local government authoriy or property owner.
PT. PRATIWI PUTRI SULUNG SHALL provide field-engineering services, including
manufacturer's representatives to ensure conformance with contract documents.
All of the above requirements are as detailed in Construction Specification for
Civil Structural (Doc. No. CP11A-PTU-3274-CV-CS-001).
PT. PRATIWI PUTRI SULUNG shall carry out reinstatement of all damaged within
crossing work area.
PT. PRATIWI PUTRI SULUNG shall gardening and planting the area with the proper
plants or crops. PT. PRATIWI PUTRI SULUNG Shall propose to EMPLOYER for the
kind of plants or crops for approval.

11.8

TANGSI OFFTAKE STATIONS

PT. PRATIWI PUTRI SULUNG shall do the works required to complete WORKS for
the upgrading tangsi offtake station . The work shall be but not limited to:
1) Permanent Metering & Regulating System
Fabricate the Offtake station and skid structure
Install all the mechanical and instruments equipments of Offtake
station as per approved P&ID
Install pipe support and steel structure for access and maintenance
Install the complete set of Offtake station to the relevant sites
2) Fire Water System
Install Fire Water System
Install Water Pond and Deep Well Pump
Install Fire Hydrant and accessories
Etc.
3) Install Utility Water System
Install Plumbing System
Install water tank
Etc.
4) Fire & Gas and Fire Extingusher System
Install conduit and cabling system

PT. Pratiwi Putri Sulung

Scope of Work
Page 49 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Install the equipments (detectors, panels, manual push buttons, strobes,

horns) as per approved drawings including necessary support


Install manual portable extinguishers.
Connect to Local SCADA system.
Etc.
5) Instrument Air System
Install air compressor pakage complate with air intake filter, air cooled

affter cooler, a liquid separator, and accessories


Install air instrument vessel
Installation of equipment, piping and auxillaries including provide air

instrument header for existing TS-1


Installation Local Control Panel
Connect and integrate to local SCADA System
Etc
6) CCTV Systems
Install new CCTV System for Offtake Station as per approved drawings.
Integrate existing CCTV cameras with new CCTV System
Etc.
7) Local SCADA and Telephony System
Install conduit, cabling system, equipment support and other necessary
equipments.
Install the equipments as per approved drawings.
Etc.
8) Power Distribution System
Connection to existing electricity power, if required performs new

connection to PLN.
New PDBs and lighting panels..
Install power cable from PDB to all new loads.
Install new power cable from existing local PDB to electrical apparatus

(lightings, switches, receptacles, etc.) including cable tagging.


Install new control cable for alarm indication from existing PDB to

marshalling rack.
Connect to Local SCADA system.
Etc.
9) Electrical System
Install distribution power supply for offtake station
Install grounding system for electrical system, instrument system and
telephony system completed with grounding rods, grounding cables,
grounding fittings, grounding bus-bars, spark gap (TEC Transient Earth

PT. Pratiwi Putri Sulung

Clamp), anti surge protection, and accessories for new facillities.


Install lightning protection system completed with air terminals, down

Scope of Work
Page 50 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

conductors, accessories and connect to existing lightning pole.


Install lighting system for new facillities completed with conduits, trays,
trenching, flood light, indoor and outdoor lighting, classified area
lighting, emergency lighting, panels, lighting poles, lighting switches,

equipment support and accessories.


Connect and interface with existing electrical systems.
Etc.
10) Diesel Engine Generator System
Install the new Diesel Engine Generator sets as per approved documents.
Install cabling to PDB system.
Install control cable from generator local control panel to marshalling

rack.
Install control cable from remote battery charger to generator auxiliary

terminal.
Connect to Local SCADA systems
Etc.
11) UPS System
Install the new UPS Unit included with the battery and distribution unit in
accordance with the approved construction drawing including the

necessary support and rack system.


Install power cabling to PDB unit, if required
Install control cable to the marshalling Cabinet
Connect to Local SCADA system.

12) Instrumentation System


Install and connect instrument cable from field instruments to junction
boxes and/or

from junction boxes to marshalling

rack and from

marshalling rack to flow computers cabinets& Local SCADA.


Install field instruments, junction boxes and supports.
Install hook up tubing and fittings for related field instruments.
Install LAN cable to accommodate communication from flow computers

to station computers
Install trenching, tray or conduit for cabling system
Install cable tagging
Interconnection between flow computers with local SCADA HMI display.
Install flow computers & SCADA cabinet, marshalling cabinet.
Install flow computers & SCAD, station computers& HMI display

including the required software to operate the system


Install printers
Programming for the SCADA system.
Install power cable, data cable, grounding & instrument cable.

PT. Pratiwi Putri Sulung

Scope of Work
Page 51 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Etc.
13) Civil Works
PT. PRATIWI PUTRI SULUNG SHALL construct all civil works at
station. The civil works comprises of but not limited to demolishing of
existing office of Tangsi station, Modification of existing Control
Building, new development Tangsi-2 MRS building, new development
DEG

shelter,

demolishing

existing

security guard

house,

new

development security guard house, new development of prayer room and


locker room, modification of gate and fence as indicated in the Tangsi
Offtake Layout drawing, new development of water pond for Fire Water
System, modification for improving drainage system and biopory of
Tangsi Offtake Station, existing Warehause demobilish access road and
parking area, addition or modification of access road/pathway install
canopy for items indicated in the layout drawing , new development of

driver shelter.
Construct all foundations for all new building and shelter ( inluding piling
test for piling work), existing Control building (modification), fences, etc.
The foundation type SHALL be in accordance with Soil Investigation
Report performed by PT. PRATIWI PUTRI SULUNG or data provided by

emplyer. The method for piling work shall be approved by Employer.


Construct pipe support, fences around the offtake station.
Construct the cable trench and cable entrance to all buildings.
Construct shelter for Diesel Engine Generators equipments.
Construct all structure and steel structures for new and modification

buildings
Construct walkway/personnel access around and to connect buildings.
Install deep well and water pond for fire water system
Install noise attenuation wall, if required
NDT for butt weld by radiographic test, visual test and penetrant test /

magnetic particle inspection for fillet weld (refer to AWS D1.1)


Etc.

14) Architectural Works


Construct exterior works according to the approved documents (roofing

PT. Pratiwi Putri Sulung

works, painting works, floor tiling works, etc).


Doors and windows installation complete with accessories.
Construct a landscape.
Etc.

Scope of Work
Page 52 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

15) Building Utilities


PT. PRATIWI PUTRI SULUNG shall review and if required modified

perimeter ditch around building and Offtake Station.


PT. PRATIWI PUTRI SULUNG shall design, install and perform

Inspection and testing on appropriate sewage system.


Modification and repair drainage system for Tangsi Offtake station.
Construct clean water system including water pump, water wells, water

piping and accessories, which may applicable.


Install toiletries and septic tank for guard house.
Repair and install addition biopory system for Tangsi Offtake station.
Install HVAC, including for modification control building, guard hause

and prayer room


Etc.
16) Access Road
Modification and construction the access road, parking area for Tangsi
Offtake Station.
17) Fencing and Gate
Temporary fence

during

construction

shall

be

provided

with

environmentally banner.
Etc
18) Water Supply
PT. PRATIWI PUTRI SULUNG shall drill deep wells for water supply,
and ensure it to the minimum standards of water quality.
Well testing shall be performed no less than 36 hours
19) Others
PT. PRATIWI PUTRI SULUNG shall plant the Tangsi Offtake Station with
the proper plants or crops. PT. PRATIWI PUTRI SULUNG shall propose to
EMPLOYER for the kind of plants or crops for approval.

12.

INSPECTION AND TESTING


12.1.

ONSHORE DISTRIBUTION PIPELINE

PT. PRATIWI PUTRI SULUNG shall be RESPONSIBLE for the complete all system up
to full and final acceptance of the installed and tested system. The testing shall

include but not be limited to hydrostatic test, NOT, and Holiday Test.
PT. PRATIWI PUTRI SULUNG shall submit:

PT. Pratiwi Putri Sulung

Scope of Work
Page 53 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Inspection

and

Test

Plan (ITP)

to

EMPLOYER for

review

and

approval.PT. PRATIWI PUTRI SULUNG shall refer to QA/QC Specification

for the detailed requirements.


Inspection and Test Plan (ITP) to EMPLOYER in full compliance to
MIGAS requirement

EMPLOYER reserves the right to carry out of inspections at any time during the
procurement/construction of PT. PRATIWI PUTRI SULUNG work.
PT. PRATIWI PUTRI SULUNG shall provide EMPLOYER with a complete set of
detailed drawings and procedures, which will be used by EMPLOYER as guidance
during manufacturing, fabrication and testing of equipment. PT. PRATIWI PUTRI
SULUNG shall refer to QA/QC Specification for the detailed requirements.

PT. Pratiwi Putri Sulung

Scope of Work
Page 54 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

PT. PRATIWI PUTRI SULUNG SHALL carry out the

inspection, testing and

pre commissioning of the pipeline facilities as follows:

Preparation of inspection, testing and pre-commissioning procedures of all


pipeline distribution facilities and submit to EMPLOYER for review and

approval.
Perform NDT by using X- ray for each weld joint,
Perform NDT 100% for golden joint (X-ray, Ultrasonic Test, and MT/PT)
Perform holiday test,
PT. PRATIWI PUTRI SULUNG SHALL minimize the number of golden joint.
Perform hydrostatic tests of completed sections of the pipeline
distribution including the supply of test water;

locate and repair leaks;

dewatering, swabbing, drying and purging. The work SHALL be in accordance


with the Specification Hydrostatic Testing Onshore Pipeline, Spool and MRS

(CP11A-PTU-3275-CM-CS-001).
Gauging pig inspection shall be done for each pipeline section to detect any

defect in the pipeline sections.


Caliper pig inspection shall only be performed for 20 inch for the following

pipeline Section-2
Perform commissioning of cathodic protection system. And CIPS
Calibration of instruments to be used in the system/facilities pre -

commissioning and testing.


Stand-by supervisors and labors to cope with damages and unexpected troubles.
Reporting for testing and pre-commissioning to EMPLOYER for obtaining

approval and acceptance.


Supporting EMPLOYER to prepare report for any and all services
necessary for obtaining MIGAS approval and certificate.

12.2.

OFFTAKE STATION

PT. PRATIWI PUTRI SULUNG shall be responsible for the complete all system up to
full and final acceptance of the installed and tested system. The testing SHALL
include but not be limited to hydrostatic test, NDT(by using X-ray), loop test, continuity
test, function test, FAT, and SAT.
PT. PRATIWI PUTRI SULUNG shall submit Inspection and Test Plan (ITP) to
EMPLOYER for review and approval.

PT. Pratiwi Putri Sulung

Scope of Work
Page 55 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

EMPLOYER reserves the right to carry out of inspections at any time during the
procuremen construction of PT. PRATIWI PUTRI SULUNG 's work.
When ready, and unless a provision to the contrary is explicitly stated herein, every
system shall undertake a stand-alone Factory Acceptance Test in order to demonstrate
its ability to fulfill its functionalities as per specifications.
PT. PRATIWI PUTRI SULUNG shall provide all calibration, test and simulation
equipments that are required to demonstrate the correct operation of the system.
Certificates of the test equipment shall be traceable to National and International
Standards and shall be provided and included as part of the official test Report.
PT. PRATIWI PUTRI SULUNG shall obtain from the Manufacturer records of all tests
performed as part of the Manufacturers standard factory testing and quality control
procedures. PT. PRATIWI PUTRI SULUNG shall provide Product Certification of
device and equipment, supplied by Manufacturers.
PT. PRATIWI PUTRI SULUNG shall submit copies of the Manufacturers test records
and Product Certification during FAT. They shall be part of the Factory Acceptance Test
Report.
PT. PRATIWI PUTRI SULUNG shall provide EMPLOYER with a complete set of
detailed drawings and procedures, which will be used by EMPLOYER as guidance
during manufacturing, fabrication and testing of equipment.
PT. PRATIWI PUTRI SULUNG shall demonstrate during FAT the standard and
specific, hardware and software functionalities and performance as defined in the
approved detailed functional design of the individual system.
PT. PRATIWI PUTRI SULUNG shall submit to EMPLOYER a complete test schedule
and FAT Procedures for the Factory Acceptance Test (FAT), at least thirty (30) days
prior to the test being performed, for EMPLOYER review and approval.
The original signed copy of the Factory Acceptance Test Report shall be submitted
officially to EMPLOYER no later than seven (7) days after completion of the test,
with two complete copies of the Report with attachments.
PT. Pratiwi Putri Sulung

Scope of Work
Page 56 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

If, for any reason, the EMPLOYER waives any part of the inspection, the waiver does
not relieve PT. PRATIWI PUTRI SULUNG from the responsibility to repairs at his
own expense to any defects found later on site within the site commissioning and/or
warranty period.
FAT shall be performed per system and held in PT. PRATIWI PUTRI SULUNG/
SUBCONTRACTOR facilities

as

per

required

in the

each

specification

document.
SAT shall be performed per system and held in site as per required in the each
specification document.
EMPLOYER shall witness for such testing, and PT. PRATIWI PUTRI SULUNG
shall provide access, administration arrangement (VISA assistance), room space for
EMPLOYER's representative during FAT, SAT and SlAT.
PT. PRATIWI PUTRI SULUNG shall refer to QA/QC Specification for the detailed
requirements.
PT. PRATIWI PUTRI SULUNG shall carry out the inspection, testing and precommissioning of the Offtake station facilities as follows:

Preparation of inspection, testing and pre-commissioning procedures of

MRS station facilities and submit to EMPLOYER for review and approval.
Perform NOT for each weld joint on MRS system and skid,
Perform holiday test,
Perform hydrostatic tests of MRS sections including the supply of test
water; locate and repair leaks; dewatering, drying and purging. The work
SHALL be in accordance with the Construction Specification Hydrostatic

Testing (CP11A-3275-TPU-CM-CS-001).
Calibration of instruments to be used in the system/facilities pre

commissioning and testing.


Stand-by supervisors and labors to cope with damages and unexpected

troubles.
Reporting for testing and pre-commissioning to EMPLOYER for obtaining

approval and acceptance.


Perform cable test, loop test,
Perform pneumatic test before nitrogen purging,

PT. Pratiwi Putri Sulung

Scope of Work
Page 57 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Perform test for Local SCADA connection


Supporting EMPLOYER to report to related parties for testing.
Perform load test for Gantry Crane
Other test specified refer to Construction Specification
The following tests are required to be witnessed by EMPLOYER
No

Description

Linepipe FAT

Ball Valves (Include Shut Down and HCV) FAT

Filter AND Pressure Vessel FAT

Diesel Engine Generator Sets FAT

Local SCADA System FAT

Uninterruptible Power Supply FAT

Pressure Control Valve FAT

Metering and Regulating (MRS) System FAT

F&G System FAT

10

Instrument Air Package FAT

11

Electrical Distribution Panel FAT

12

SAT 1, 2, 3,& 4

PT. PRATIWI PUTRI SULUNG shall responsible on MIGAS and DITMET attendance
to witnessing the metering system FAT, SAT and commissioning.

13.

CALIBRATION
13.1

Instrumentation

All field instrumentation SHALL be calibrated by Directorate of Metrology or any


party appointed by Directorate of Metrology. PT. PRATIWI PUTRI SULUNG SHALL
provide the

calibration procedures and SHALL be submitted to EMPLOYER for

review and approval.

PT. Pratiwi Putri Sulung

Scope of Work
Page 58 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

13.2

Metering & Regulating System

PT. PRATIWI PUTRI SULUNG shall calibrate the Metering and Regulating System.
The system SHALL include but not limited to orifice meters, transmitters, gauges, flow
computers, flow recorders.
Calibration SHALL be conducted with the presence of and shall be certified and
validated by Directorate of Metrology and with MIGAS.
PT. PRATIWI PUTRI SULUNG shall provide the calibration procedures and shall be
submitted to EMPLOYER for review and approval.

14.

HEALTH, SAFETY AND ENVIRONMENT (HSE)


EMPLOYER is fully committed to maintaining high levels of safety, occupational
health and environmental protection throughout the WORKS. PT. PRATIWI PUTRI
SULUNG shall comply strictly with these requirements PT. PRATIWI PUTRI
SULUNG shall ensure that all provisions of his site safety procedures are being
properly met or exceeded with no unacceptable harm to the environment.
PT. PRATIWI PUTRI SULUNG shall provide and funish the employees with the
proper and necessary Personel Protective Equipment (PPE). The PPE standard
requirement should be in accordance with ANSI/SNI and or an equal, and should be
approved by EMPLOYER/PMC representative prior to commencement.
Nevertheless, PT. PRATIWI PUTRI SULUNG shall also consider HSE aspects within
his design consideration of the permanent plant and facilities of the CP 11A: Upgrading
Tangsi Offtake Station Project.
PT. PRATIWI PUTRI SULUNG shall adhere strictly to the requirements of the
EMPLOYER in respect of health and safety matters as are particularly expressed in the
EMPLOYER's "PGN's Guideline on Safety, Occupational Health and Environmental
Management System ( Pedoman Sistem Keselamatan dan Kesehatan

Kerja Serta

Pengelolaan Lingkungan) No. P-001/0.18".


During

PROJECT

PT. Pratiwi Putri Sulung

implementation

PT. PRATIWI PUTRI SULUNG

SHALL

Scope of Work
Page 59 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

also refer to EMPLOYER's Operating Procedures as follow:


a. SOP EMPLOYER No. 0-003/0.38 - lzin Kerja (Permit To Work);
b. SOP EMPLOYER No. 0-004/0.38 Pengelolaan dan Pemantauan
Lingkungan (Environmental Management and Monitoring);
c. SOP EMPLOYER No. 0-005/0.38 Pengelolaan B3 dan Limbah B3
(Hazardous and poisonous Waste Management);
d. SOP EMPLOYER No. 0-006/0.38 Pre Start-Up and Safety Review;
e. SOP EMPLOYER No. 0-007/0.38 Analisa Bahaya Proses (Process
f.

Hazard Analysis);
SOP EMPLOYER No. 0-008/0.38 Analisa Keselamatan Kerja (Job

Safety Analysis);
g. SOP EMPLOYER No. 0-010/0.38 Lock Out Tag Out;
h. SOP EMPLOYER No. 0-012/0.38 Risk Containment Audit (RCA);
i. SOP EMPLOYER No. 0-002/0.38 Tanggap Gawat Darurat
j.

(Emergency Response Plan);


SOP EMPLOYER No. 0-014/0.38 Investigasi Insiden dan Pelaporan

(Incident Investigation and Reporting);


k. SOP EMPLOYER No. 0-019/0.18 Pelaksanaan Pekerjaan;
l. SOP EMPLOYER No. 0-020/0.38 Evaluasi Kinerja KONTRAKTOR;
m. SOP EMPLOYER No. 0-021/0.38 Laporan Unjuk Kerja (SHE
Performance Report);
n. Work Instruction EMPLOYER No. I-002/0.38 Ijin Kerja Panas;
o. Work Instruction EMPLOYER No. I-003/0.38 Ijin Kerja Dingin;
p. Work Instruction EMPLOYER No. I-004/0.38 Ijin Kerja Memasuki
Ruang Terbatas;
q. Work Instruction EMPLOYER No. I-005/0.38 Ijin Kerja Radiografi;
r. Work Instruction EMPLOYER No. I-006/0.38 Ijin Kerja Listrik;
s. Work Instruction EMPLOYER No. I-007/0.38 Ijin Kerja
t.

Penggalian;
Work Instruction EMPLOYER No. I-010/0.38 Komunikasi,
Konsultasi dan Partisipasi Keselamatan, Kesehatan Kerja dan

Pengelolaan Lingkungan serta Energi;


u. Work Instruction EMPLOYER No. I-011/0.38 Identifikasi Bahaya,
Penilaian Resiko dan Bentuk Pengendaliannya;
v. Work Instruction EMPLOYER No. I-012/0.38 Penanganan
Tumpahan Material B3.
w. Work Instruction EMPLOYER No. 077700.K/ KK.03/PROYEK/2013
Bekerja Aman Dalam Galian
x. Work Instruction EMPLOYER No. 102800.K/ KK.02/PROYEK/2013
Keselamatan Bekerja Radiografi.
y. Work Instruction EMPLOYER No. 111500.K/ KK.03/PROYEK/2013
PT. Pratiwi Putri Sulung

Scope of Work
Page 60 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Keselamatan Bekerja Blasting


z. Analisis Mengenai Dampak

Lingkungan

(AMDAL)

Kegiatan

Pipanisasi Gas Bumi Labuhan Maringgai (Lampung) Perairan


P.Damar (Kep.Seribu) Muara Tawar (Muara Bekasi) Bekasi
(Tegalgede) Karawang (Walahar) Tahun 2005.
PT. PRATIWI PUTRI SULUNG SHALL ensure that procedures are in place during the
execution of the WORKS for the control of health and safety that:
a) Comply with acceptable international or national standards for health and
safety applicable to the construction industry in general and the gas industry in
particular. including any specific standards imposed by the EMPLOYER;
b) Encourage the establishment and maintenance of a responsible approach to the
welfare and safety of those employed by PT. PRATIWI PUTRI SULUNG and
the EMPLOYER during the course of the design, execution and completion of
the WORKS;
c) Protect those members of the public that may be affected by the execution of
the WORKS;
d) allow the Employer's Personnel to monitor and audit implementation and
success of the procedures. and
e) ensure a lost time injury and fatality rate that is As Low As Reasonably
Possible (ALARP), with a zero target rate for lost time injuries and fatalities
being the aim, and where the actual number of fatalities per one million man
working hours shall not exceed 0.075.
For the detail requirements on HSE, PT. PRATIWI PUTRI SULUNG shall also refer to
Safety, Health. Environmental and Security Management System Requirements (Doc.
No. CP11-PTU-3275-HS-PR-003).
PT. PRATIWI PUTRI SULUNG shall conduct training for all PT. PRATIWI PUTRI
SULUNG 's supervisors and workers related with safety and environment. The training
shall be witnessed by EMPLOYER.

15.

MIGAS CERTIFICATIONS
PT. PRATIWI PUTRI SULUNG shall be fully RESPONSIBLE in obtaining the
certificate from DITMET and MIGAS for the metering system and other equipment as

PT. Pratiwi Putri Sulung

Scope of Work
Page 61 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

required . all cost for such certifications shall be borne by PT. PRATIWI PUTRI
SULUNG.
PT. PRATIWI PUTRI SULUNG shall be fully responsible to provide the required
documents for THIRD PARTY in obtaining the SKPP and SKIP Certificates relesed by
MIGAS (refer to keputusan Dirjen MIGAS No. 84.K/38/DJM/1998)

16.

MECHANICAL COMPLETION
Pre-commissioning tests required to be carried out by PT. PRATIWI PUTRI SULUNG
after completion of all construction/installation work for each work phase for the
Project shall cover appropriate inspections and non-operational tests for the installed
works to verify that the Works are mechanically complete in accordance with the
Specification before starting Commissioning.
Mechanical completion shall be conducted by PT. PRATIWI PUTRI SULUNG
including pre-commissioning test (SAT 1, 2 and 3) as follows:

Preparation of testing and pre-commissioning procedures of all pipeline

distribution facilities and submit to EMPLOYER for approval.


Perform hydrostatic tests of completed sections of the pipeline system
including the supply of test water; locate and repair leaks; dewatering,
swabbing, gauging pig inspection, loacte and test any defects, caliper pig
inspection before and after the hydrostatic test, drying and

purging. The

work shall be in accordance with the Construction Specification Hydrostatic

Testing (Doc. No. CP11A-PTU-3275-CM-CS-001).


Clean-up the line route and construction sites.
Calibration of instruments to be used in the system/facilities pre-

commissioning and testing.


Stand-by supervisors and labors to cope

troubles.
Reporting for testing and pre-commissioning to EMPLOYER for obtaining

with damages and unexpected

approval andacceptance.
Supporting EMPLOYER to report to related parties for testing.
Nitrogen Purging
Perform pre-commissioning per system :
- Perform test for instrument air system
- Perform test and fine tuning for pressure control valves,

PT. Pratiwi Putri Sulung

Scope of Work
Page 62 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

17.

Perform test shut down valve,


Perform test for CCTV system all features function,
Perform test for automatic swicthing from main power to

backup power system


Perfom test for fire and gas activeation and its associated

equipment,
Perform test for lighting commissioning for the duration of

24 haurs,
Perform test for cathodic protections
Perform test for any others systems

COMMISSIONING
Upon the successful of mechanical completion, PT. PRATIWI PUTRI SULUNG shall
perform commissioning for all supplied system under the PROJECT under
EMPLOYER supervision in accordance to commissioning and trial operation
document.
The commissioning activities shall be conducted within 14 days including, but not
limited to the following:

18.

Perform gas-in along the pipeline,


Standby supervisors and labors for troubleshooting activities,
Reporting for commissioning to EMPLOYER for approval

TRIAL OPERATION
PT. PRATIWI PUTRI SULUNG shall
Offtake Station, MRS, diesel

perform Trial

Operation for

Pipeline,

engine generator, fire water system, air instrument

system, local SCADA system, and other system supplied by PT. PRATIWI PUTRI
SULUNG for 14 (fourteen) days period starting from Commissioning completion.
During the Trial Operation period for Offtake and MRS Stations, PT. PRATIWI
PUTRI SULUNG shall provide operators to monitor and operate the system in 24
hours under EMPLOYER supervision.
And for diesel engine generator, fire and gas system, fire water system, air instrument
system, local SCADA system, and other system supplied by PT. PRATIWI PUTRI

PT. Pratiwi Putri Sulung

Scope of Work
Page 63 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

SULUNG. PT. PRATIWI PUTRI SULUNG SHALL provide operator(s) on call basis
(maximum 3 hours after failure reported) during the Trial Operation period.
During the Trial Operation for pipeline system, PT. PRATIWI PUTRI SULUNG
SHALL provide operators to perform:

Leakage inspection on weekly basis, and


Cathodic Protection inspection on monthly basis

PT. PRATIWI PUTRI SULUNG shall provide the proper equipments and tools to
facilitate the inspection. PT. PRATIWI PUTRI SULUNG

shall

provide

Trial

Operation Procedure for EMPLOYER's review and approval.


PT. PRATIWI PUTRI SULUNG shall be RESPONSIBLE of any trouble shooting and
rectification during this Trial Operation period with no additional cost to EMPLOYER.

19.

WARRANTY AND MAINTENANCE

PT. PRATIWI PUTRI SULUNG shall warrant the supplied equipment and systems
comprised within the PROJECT by remedying any defects (if any) within the
Defects Notification Period for the duration of 365 days after Taking Over
Certificate issued by EMPLOYER. PERFORMANCE CERTIFICATE will be
issued by EMPLOYER under the supervision of the Conditions of Contract Sub-

Clause 9.1 [Perbaikan Cacat Mutu].


PT. PRATIWI PUTRI SULUNG shall execute all works required to remedy defects
or damage to work provided and installed by PT. PRATIWI PUTRI SULUNG
which is attributable to:
a. The design of Works for which PT. PRATIWI PUTRI SULUNG is responsible.
b. Plant, materials or workmanship not being in accordance with the Contract,
including but not limited to:
i.
Parts / equipment changes

due

to factory defect,

improper

transportation, and mishandling,


ii.
Packing, shipping, loading and unloading cost.
iii.
Installation cost
iv.
Transportation cost
c. Improper operation or maintenance which was attributable to matters for which
PT. PRATIWI PUTRI SULUNG is responsible.
d. Failure by PT. PRATIWI PUTRI SULUNG to comply with any other

PT. Pratiwi Putri Sulung

Scope of Work
Page 64 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

obligations.

Throughout the entirety of the Defects Notification Period PT. PRATIWI PUTRI
SULUNG shall at his own cost promptly remedy any defects that are found in the
WORKS such that there is no disruption whatsoever to the EMPLOYER's gas
distribution operations. All necessary tools, parts and labor for remedying defects
shall be provided by the PT. PRATIWI PUTRI SULUNG. The parts to be used for
remedial work shall be additional to the spare parts required for operating and
maintaining the EMPLOYER's gas distribution operations for a period of 12

months from the date of Final Taking Over.


During Defects Notification period, PT. PRATIWI PUTRI SULUNG

shall

provide list of personnel of its SUB-CONTRACTOR(s) whom, on behalf of PT.


PRATIWI PUTRI SULUNG, shall be able to be contacted by and provide service

to EMPLOYER for emergency service within 3 hours maximum response time.


PT. PRATIWI PUTRI SULUNG shall develop a Maintenance Concept based on
providing high system availability. A Maintenance Plan shall be prepared which
defines the maintenance requirements, logistics and support, staff skills and
organization necessary for the Engineering and Maintenance systems to achieve the
service availability specified..

20.

SPARE PARTS AND CONSUMABLES


PT. PRATIWI PUTRI SULUNG SHALL supply spare parts, recommended
consumables and required tools during testing (individual and or integrated), precommissioning, commissioning and trial operation.
PT. PRATIWI PUTRI SULUNG SHALL supply spare parts and required tools for
operation and maintenance.
Spare Part and all tools necessary for operating and maintaining the EMPLOYERS
gas distribution operaion for a period 24 mounths (as per attachment 2) from the date of
taking-over must be deposited with the EMPLOYER prior to the issue of the takingover certificate together with all necessary tools to enable the EMPLYER to carry out
work on the palnt and equipment for the design life of the distribution pipeline system .
if it subsequently observed that the deposite spare part are or will be inadequate in

PT. Pratiwi Putri Sulung

Scope of Work
Page 65 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

quantity, PT. PRATIWI PUTRI SULUNG sahall ensure that sufficient addition spare
part are provided in adequate time to avoid disruption to the EMPLOYERS gas
distribution operations.

21.

TRAINING
PT. PRATIWI PUTRI SULUNG SHALL provide training for EMPLOYER personnel
for all system under the PROJECT,

including the operation and maintenance of

individual system equipment. The training SHALL assume that operators have no
experience of operating a gas pipeline.
PT. PRATIWI PUTRI SULUNG SHALL provide training at the center of expertise (for
supervisors) and local training (for operator level). The local training SHALL utilize the
installed facilities. PT. PRATIWI PUTRI SULUNG SHALL develop training syllabus
and training module.
The number of man days required for EMPLOYERin each training SHALL be as
follows:
Tabel 2. Training Requirements for Material / Equipment
Center of expertise
ltem(s)

MRS

Duration
(working
day(s))
5

F&G

Fire Water System

PDB

N/A

N/A

Diesel Engine
Generator

N/A

N/A

N/A

N/A

N/A

N/A

UPS
lnstument Air
System

No. of
trainee(s)

Local
No. of
trainee(s)

Duration
(working day(s))

PT. PRATIWI PUTRI SULUNG shall provide allowance, transportation and


PT. Pratiwi Putri Sulung

Scope of Work
Page 66 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

accommodation for the training participant based on EMPLOYER 's standard.


Trainers shall provide certification for training program. Trainers shall be qualified and
certified as instructor by MANUFACTURER.

22.

DOCUMENTATION
22.1

General

Certain

PT. Pratiwi Putri Sulung

CONTRACT as

Documents

are

specified

in

being required by the EMPLOYER for review.

the
The

submission of such documents and the subsequent review thereof shall be


carried out under the provisions of Conditions of Contract Sub-Clause 5.1

[Desain Kontraktor].
PT. Pratiwi Putri Sulung Documents for review are to be submitted in such time
as will allow the WORKS to progress as planned, taking into account the
EPMLOYER ' s review period and the possible need to resubmit documents

where non compliance with the requirements of the CONTRACT are observed.
PT. Pratiwi Putri Sulung Documents shall be submitted in a manner that allows
for the transmitted data to be stored on a computer server and input into a
database for monitoring the subject and status of submissions. Where the
editorial integrity of the content of the document is of concern, the document
may be provided in a protected for mat.

In such cases, a version of the

document that allows the contents to be accessed and used by the Employer's
personnel is also to be provided.

In addition, paper hardcopies shall be

provided where stipulated.

22.2

Deliverables for Design

All Design Submissions to be submitted to the EMPLOYER for review shall be


presented in 3 (three) hard paper copies and 1 (one) CD-ROM for editable copy.
The Design Submission shall contain all of the design assumptions, loading conditions,
analytical methods, design codes and calculations necessary to determine whether, with
respect the subject matter of the Design Submission, the CONTRACT has been
complied with. At each stage of the design process the documentation to be submitted

PT. Pratiwi Putri Sulung

Scope of Work
Page 67 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

shall be the updated versions of the previous issue of the documentation insofar as it is
applicable and required by the EMPLOYER at the relevant design stage
All final or issued for construction documents shall be submitted in 3 (three) sets of
hardcopies, 1(one) original and 2 (two) copies and 2 (two) of softcopies on DVD
(editable format).

22.3

Deliverables for Construction

PT. PRATIWI PUTRI SULUNG shall submit construction report completed with
photographs and video as the evidence.
PT. PRATIWI PUTRI SULUNG shall provide 50 technically perfect, digital color
photographs of the Works each month from the Commencement Date until the issue of
the Final Taking Over Certificate for the whole of Works. The photographs shall be
taken in such locations and at such a time or times as the EMPLOYER shall generally
direct. The photographs shall be taken with a tripod-mounted digital camera and
shall, unless agreed otherwise, be in 35 mm x 35 mm (full frame) format; the resolution
shall be not less than 16 megapixels.
Enlargements of 10 color photographs are also to be provided (5 copies of each). The
photographs for enlargement shall be selected from time to time by the EMPLOYER.
The area of each enlargement shall not exceed 1,000,000 mm2 . Each month, PT.
PRATIWI PUTRI SULUNG shall provide 2 copies of a short edited video (lasting
between 3 and 5 minutes) to demonstrate the progress being made for all major and/or
critical activities (where the content is to be agreed each month in advance with the
EMPLOYER and which shall be of finished quality suitable for distribution to the
news media for immediate showing.
In addition, PT. PRATIWI PUTRI SULUNG shall takes and submits perfect
photographs which are showing but not limited to:

The Site condition before and after construction activities.


Every welded joint condition,
Off-set and depth of pipe,
Backfilling condition of each compaction layer.
Etc.

PT. Pratiwi Putri Sulung

Scope of Work
Page 68 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

and which are indicated with project name, date, site address, PT. Pratiwi Putri
Sulung name, supervisor name, etc. on each site on daily basis.
PT. PRATIWI PUTRI SULUNG shall provide digital Video documentation i n HD
1080 format. The Video shall be stored in DVD disc format playable in standard DVD
players.
All rights related to the photographs and videos, including copyright, shall be vested in
EMPLOYER.

22.4

Deliverables for Test

PT. PRATIWI PUTRI SULUNG shall submit documents described below, as a


minimum :
a)
b)
c)
d)
e)

Factory Acceptance Test procedure


Site acceptance test procedure
Site Integrated Acceptance Test procedure
Pre-commissioning and Commissioning procedure
Trial Operation

Those documents shall be submitted for approval 30 days prior the testing.

22.5

Deliverables for As Built

All specifications, data sheets, procedures, calculations and drawings being utilized for
purchasing, construction or fabrication shall be reviewed and approved by
EMPLOYER.
As-Built documentation containing all the above specifications, data sheets,
procedures, calculations and drawings shall be assembled as job-books and submitted
to EMPLOYER. PT. PRATIWI PUTRI SULUNG shall submit the As-Built document
list to EMPLOYER for approval prior issuance of the original document.
The As-Built Documents SHALL comprise :
a) Drawings of the Permanent Works as installed (including a 'family tree' index
incorporating all dawings from suppliers and sub PT. Pratiwi Putri Sulungs),
indicating all changes made to the original drawings issued for construction/

PT. Pratiwi Putri Sulung

Scope of Work
Page 69 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

installation purposes;
b) Specifications of the Permanent Works as installed, indicating all changes made
to the original specifications issued for constructions/ installations purposes.
c) All variations and change orders issued by the EMPLOYER during the
execution of the WORKS.
d) A full report on all non-conformities identified and corrective measures taken.
e) All construction records and deliverables developed by PT. PRATIWI PUTRI
SULUNG and / or its SUBCONTRACTOR(s) including all test results.
f) Operation and maintenance documentation, including all applicable
product indformation required to operate and maintain the system.
g) All project documentation prepared by PT. PRATIWI PUTRI SULUNG and its
sub PT. Pratiwi Putri Sulung(s) (procurement/ sub-contracting documents), and.
h) All health, safety and environmental reports, records and statstics.
All documents shall be submitted in 4 (four) sets of hardcopies as 1 (one) original,
3(three) paper copies, and 4 (four) sets of editable softcopies (native files) and scanned
hardcopies (PDF format) compiled in CD/DVD.
All bespoke software provided for operating and maintaining the completed WORKS
(that is, software especially written or standard software customized by specialists),
together with all licenses and supporting documentation relating thereto (including
"Helps" files and the likes), shall be provided by PT. PRATIWI PUTRI SULUNG to
complete the As-Built documents submission data.

23.

TEMPORARY FACILITIES
PT. PRATIWI PUTRI SULUNG SHALL provide the following temporary facilities for
EMPLOYER's representatives during the construction period until the Completion of
Whole of the work.
23.1. Office
a) These offices are intended to accommodate all activities for the whole project.
The provision of temporary facilities for EMPLOYERs personnel as required
by EMPLOYER as follows:
PT. PRATIWI PUTRI SULUNG shall provide offices for the sole use
of the EMPLOYERs Personnel at every location where PT. PRATIWI

PT. Pratiwi Putri Sulung

Scope of Work
Page 70 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

PUTRI SULUNG establishes an administration office for PT. Pratiwi


Putri Sulung own personnel along the route of the pipeline.such office
for the EMPLOYERs Personnel shall be made available for the same

period as PT. PRATIWI PUTRI SULUNG office are available.


The EMPLOYERs Office shall include security guards (24 hours),
office boys and cleaning services in order for the EMPLOYERs
Personnel to adequately perfrom the daily Inspection and examintaion
of the WORK and the auditing of PT. PRATIWI PUTRI SULUNG

activities.
Fitted means fixtures necessary to enable the space provided to

function as an office ready for immediate occupancy.


For each EMPLOYERs office, furnishings include desks with 4
lockable drawers each (including 2 desks for secretaries), swivel chairs,
visitors chairs, conference table (for 20 persons), coat stands, tables

and filling cabinet appropriate to the number of occupants.


For each EMPLOYERs office, equipped means provided with
standard office equipment, specifically: fully equipped PPE (Personal
Protective Equipment) for supervisors (25) and visitors (10), Fire
Extinguisher, first aid kit, safety signs, whiteboards (1 per 2 occupants
space), 2 notice board with drawing-pins, photocopy machine (XEROX
or equivalent) for A3 size including supply of photocopy papers and
reguler maintenance, filling trays (3 per occupant space), drawing file
cabinet (maximum A0 size), paper punches, steples and wastepaper

baskets (1 each occupant space).


For each EMPLOYERs Office, the offices are to include a fully
equipped kitchen suitable for the preparation of hot and cold drinks,
and to be equipped with 1refrigerator, 1 microwave oven, 1 cupboard,
coffe cups and dishware adequate to the number occupants, and the
like. Toilet facilities are to comply with regulatory requirements. A

room with seating and a telephone is to be provided for drivers.


Each private office shall be equipped with a locakbel door with a safe
locking device, a window, 4 wall sockets (2 pin type), fluorescent
lighting fixtures, 3 locakable filing cabinets and the like.

PT. Pratiwi Putri Sulung

Scope of Work
Page 71 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

Table.3. EMPLOYER Office

EMPLOYER Office
Occupa
nts
25

Area

Sapace Provision

Open-Plan Office ( 150 m2 )


3 Private Offic ( @ 9 m2 )
Reception Area
Meeting Room for 30 occupants
( min. 45 m2 )
Prayer Room
Pantry
Toilets
Drivers Room

250 m2

b) Communication Equipment
PT. PRATIWI PUTRI SULUNG shall provide for the use of the
EMPLOYERs personnel during the course of the Contract of the
communication and IT Services, including all necessary ancillary. The
telephones and fax machines shall be restricted to calls within
Indonesia, and PT. PRATIWI PUTRI SULUNG shall pay the telephone

and fax bill for such calls.


PT. PRATIWI PUTRI SULUNG shall also establish Internet
connections and pay the running cost of Internet connections.

c) Drinking Water
Chilled and hot, potable water is to be made available at those
EMPLOYERs offices provided by the PT. PRATIWI PUTRI
SULUNG. Potable water is defined as water which is safe and suitable
for drinking without receiving any further form of treatment. A supply
of potable water bottled by a reputable and registered water supplier is
to be provided.

23.2 Accommodation for EMPLOYERs Personnel


PT. PRATIWI PUTRI SULUNG shall at PT. Pratiwi Putri Sulung own cost provide
comfortable living accommodation, for up to 3 of EMPLOYERs Personnel to the same
standard as four star hotel.

PT. Pratiwi Putri Sulung

Scope of Work
Page 72 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

The accommodation shall be located in a convenient position relative to the location of


each EMPLOYERs SITE office in which each respective EMPLOYERs Personnel is
assigned to work.

23.3 Communication System for EMPLOYERs Personnel


a) A Communication System (i.e. Mobile Telephone as shown on Table 4.) shall
be provided for the EMPLOYERs personnel up to a maximum number of 6
users for SITE Office provided that the maximum monthly bills shall not be
more than Rp. 300,000,-/month for each Mobile Telephone. In addition, PT.
PRATIWI PUTRI SULUNG shall provide Mobile Phone Vouchers @ Rp.
100,000,-/month for another 13 (thirteen) Employers personnel for SITE
communication and ccordination.
b) The intended purpose of the Communication System is to provide the
EMPLOYERs personnel with convenient and dedicated means of oral
communication between each other during the construction period. This is to
allow them to discharge their duties and obligations properly from the date of
commencement of mobilization by the PT. PRATIWI PUTRI SULUNG, until
such time as PT. PRATIWI PUTRI SULUNG has completed the Whole of the
Works.
Table.4. Communication System
Item
Fixed Telephone
Mobile Telephone
Internet Connections
Computer
Equipment

UPS
PT. Pratiwi Putri Sulung

General Description of Equipment


Standard PABX Telephone System for No. of
handset and lines shown.
Samsung Galaxy Grand or equivalent
Minimum speed of 2 Mbps IX connection, SLA
98% or better
Server (HP Proliant ML310e G8 or equivalent, 4
GB, (IP), 1x Quad-Core Intel Xeon E3-1220 v3,,
Memory 4 GB PC3-12800EDDR3
Registered DIMMS, HP NC105i PCI Express
Gigabit, HP E200 8 Internal Port Smart Array
SAS/SATA, HP Half-Height SATA DVD-ROM,
Tower Standard 5U, Keyboard & Mouse
included, 2TB SATA 7.2K)
UPS for Workstations with 600 VA capacity

EMPLOYE
R
2 ( 1 lines )
6 ea
Min. 2 lines
Min. 2

10
Scope of Work
Page 73 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

UPS
Desk Top Computer

Notebook Computer

Colour multifunction
printer ( A4 dan A3 )
Laser Jet Colour
Printer ( A4 )
External Hard Disk

PT. Pratiwi Putri Sulung

UPS for Server with 1.5 kVA


Processor : Min. Intel Core i7 Processor
4 GB DDR3 PC12800 MHz DDR3 Memory
Clock Speed : Min. 2.20 GHz, Cache 8MB
Hard Drive : Min. 1 TB Serial ATA 7200

RPM
Optical Drive : DVD+RW
Video : Min. 1 GB GDDR 3 (discrete. No

onboard)
Networking : Integrated 10/100 Mbps LAN
Keyboard : Standard Keyboard
Input Device : Optic Scroll Mouse
Interface provide : 4x USB 2.0
Monitor : Min. LCD 23 inch LED Wide

Screen
Operating System : Genuine Microsoft

Windows 7 Professional 64 bit


Software : Genuine Microsoft Office, Full

Version anti-virus
Processor : Min. Intel Core i7 Processor
Min. 4 GB DDR3 PC 12800 Memory
Clock Speed : Min. 2.40 GHz, Cache 6 MB
Hard Drive : Min. 500 GB Serial ATA 7200

RPM
Optical Drive : DVD+RW
Video : Min. 1 GB GDDR 3
Networking : Integrated 10/100 Mbps LAN
Keyboard : Standard Keyboard
Input Device : Separate Wireless Optic Scroll

Mouse
Interface provide : 4x USB 2.0
Monitor : 14 inch HD
Operating System : Genuine Microsoft

Windows 7 Professional 64 bit


Software : Genuine Microsoft Office, Full

Vesion anti-virus
Copying, Scanning, faxing, email, (Xerox
WorkCentre TM 7220/7225 or equivalent
HP 2550 N or equivalent
1 Tera Byte Capacity

2
10

1
1
5

Scope of Work
Page 74 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

(Portable)
USB Flash Disk
LED TV Training
Monitor
Multi-media Portable
Projector
Global Positioning
System (GPS)
Digital Camera

23.4

32 GB High Speed
40 inch minimum (colour with flat screen)

5
1

3D with camera

Water Proof Garmin with colour display, camera


and Bluetooth
Canon ixus 16 Megapixels or equivalent

1
3

Ancillary Facilities
a) Services to all offices and buildings provided for the use of the EMPLOYERs
personnel shall include signage, car parking, standard voltage electricity,
lighting, telephone lines, Internet connections, air conditioning, sewage
disposal and waste disposal and the like. The buildings shall be cleaned daily
and regularly maintained.
b) Sanitary facilities shall be supplied with consumables such as lavatory paper,
disinfectant, soap, detergent and paper towels.
c) Signage shall clearly identify the offices and buildings and shall match in style,
size colours and materials the signage used on the EMPLOYERs existing
facilities in Jakarta.

23.5

Power
a) Provide all the electrical power required for the execution, testing and
commissioning of the WORKS, including the power required for the temporary
facilities for the EMPLOYERs personnel.
b) Where the provision of electrical power involves arrangements for power to be
supplied in whole or part from any national electrical generating or distribution
company or government organization, then should such a power fail in any
calender month for:
A cummulative period of 10 hours, or
On more than three occasions of duration greater than 30 minutes, then
PT. PRATIWI PUTRI SULUNG shall thereafter, and until the issue of
the Final Taking-Over Certificate, provide standby power-generating
equipment which can be brought on line within 10 minutes.

PT. Pratiwi Putri Sulung

Scope of Work
Page 75 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

23.6

Transport
a) Transport shall be provided for the EMPLOYERs Personnel for the proper
monitoring, supervision and auditing of the design, execution and completion
of the WORKS and the discharge of those obligations as may be required under
the Contract that require the transportation of the Engineers assistants.
b) Included in such duties is the inspection and auditing of the design and
execution of the WORKS from 28 days after the Commencement Date or such
other period as may be agreed, until such time as PT. PRATIWI PUTRI
SULUNG has completed the Whole of Work.
c) As a minimum, transport is to include the following types of vehicles:
Type A: Estate car, minimum of 7 seats, 4 passenger-door, engine

capacity not less than 2000cc, automatic transmission.


Type B: Micro Bus, minimum capacity of 10 passengers.
Type C: sport Utility Vehicle, minimum of 5 seats, 5 door, long wheel
base, high and low gear ratios, engine capacity not less than 2500cc,

automatic transmission.
Type D: luxury jeep type, 4-wheel drive, minimum of 5 seats, 4-door,

engine capacity not less than 3000cc.


d) The vehicles are to be provided for the exclusive use of the EMPLOYERs
Personnel, and all vehicles are to be air conditioned and equipped with first aid
kit and portable extingusihers. The vehicles are, unless agreed otherwise, have
no distinguished marks other than the number plate, name of the manufacturer
and model details, and to be new when first porvided. Each vehicle is to be
replaced with a new vehicle when it accumulates 150,000km. Vehicles are to be
provided with fuel, lubricants, and are to be comprehensively insured for any
driver.
e) Vehicles are to maintained in a safe, clean and reliable condition for the
duration of their use in the service of the EMPLOYERs Personnel, and
repaired whenever necessary to do so. In the event that such vehicles are not
available for use by reason of their being under repair, broken down or in for
service, equivalent transport is to be provided by PT. PRATIWI PUTRI
SULUNG until such time as the repairs are complete & the original vehicles
are back in use.
f) Properly licensed, including certified safety driving licensed, drivers are to be
provided for all vehicles.
g) The requirements of Vehicles Months given in Table 4 shall be indicative and

PT. Pratiwi Putri Sulung

Scope of Work
Page 76 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

PT. PRATIWI PUTRI SULUNG shall provide such services during the period.
h) Once supplied, vehicles and drivers are to be available for use at all times
during the following periods:
Normal working hours and such other times when PT. PRATIWI
PUTRI SULUNG is working.
When requested by the EMPLOYER for emergency situations, and
When requested by the EMPLOYER for the discharge of the duties of

the EMPLOYERs Personnel outside normal working hours.


Table.5. Vehicle Month

Class

Type
Type
Type
Type

23.7

A
B
C
D

Number
to be
Provide
d

Average Driver
Requirements over the
period required
(HOURS/VEHICLE/MONTH
)

3
0
0
0

250
N/A
N/A
N/A

Average
Distance
Requiremenets
over the
periode
required
(KM/MONTH)
5000
N/A
N/A
N/A

Duration of Requirements
The temporary offices and the equipment therein , including all temporary
facilities and services for the EMPOYERs personnel stated herein, are to be
provided and maintened by PT. PRATIWI PUTRI SULUNG until 28 days after
the date of the issuance of the Final Taking-Over Certificate. There after, except
where stated otherwise, all offices and equipment provided for the use of the
EMPLOYERs personnel shall revert to PT. PRATIWI PUTRI SULUNG. When
offices revert to PT. PRATIWI PUTRI SULUNG they shall be removed and the
site there of reisnstated.

24.

ADMINISTRATION
Administrative requirements include provision of PT. Pratiwi Putri Sulung Documents,
attendance at meetings, liaison with authorities, the management of external interfaces,
and the specific requirements with respect to the structure of PT. PRATIWI PUTRI

PT. Pratiwi Putri Sulung

Scope of Work
Page 77 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

SULUNGSs organization.
PT. PRATIWI PUTRI SULUNG is required to ibtain permits and approvals necessary
for completing the WORKS including temporary works and facilities from landowners,
property owners, and local governments and communities. PT. PRATIWI PUTRI
SULUNG shall carry out its permit surveys for such purpose.

25.

PROGRAMMING AND PLANNING


PT. PRATIWI PUTRI SULUNG is required to plan the design, execution and
completion of the WORKS in such a manner that the WORKS progress in and orderly
fashion, with due expedition and without delay. The planning and associated
coordination is to include the identification of all external interface within the design,
execution and completion process. These include such diverse aspects as complying
with planning and building regulations, obtaining permits or consents for operations on
or under lan or water, traffic diversion, utility protection and relocation, and
coordination of design and construction with other PT. PRATIWI PUTRI SULUNGs.
PT. PRATIWI PUTRI SULUNG shall be responsible for obtaining at PT. Pratiwi Putri
Sulung own cost all permits necessary for the design, execution and completion of the
WORKS with the exception of the permits to be obtained in sufficient time to allow the
WORKS to progress as planned. In addition, PT. PRATIWI PUTRI SULUNG is
responsible to assist the EMPLOYER in the acquisition of those permits to be obtained
by the EMPLOYER including to bear all associated cost as describes in clause 27,
EMPLOYERs undertakings
PT. PRATIWI PUTRI SULUNG shall be fully responsible for obtaining a proper
Permit to Work (PTW) from EMPLOYERs operating and maintenance team namely
Strategic Business Unit (SBU) before commencing the relevant work within or adjacent
to the SITE. Such Permit to Work shall be issued by SBU strictly in accordance with its
own Permit to Work System.

26.

INTERFACE WITH OTHERS/BATTERY LIMIT


PT. PRATIWI PUTRI SULUNG is required to design and complete all interfaces with
the work being undertaken under the other contractd and with the existing pipeline

PT. Pratiwi Putri Sulung

Scope of Work
Page 78 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

systems as is necessary to complete the Works as shown on the Drawings and defined
in the Contract.
The interface shall be undertaken by PT. PRATIWI PUTRI SULUNG as follows:
a)
b)
c)
d)
e)

27.

With the existing 24 inch distribution pipeline Rawa Maju - Kerawang


With the existing 16 inch distribution pipeline Cikarang Listrindo -1.
With the existing 12 inch distribution pipeline Tegal Gede Bekasi.
With the existing electrical system
With the existing utility water system

EMPLOYERS UNDERTAKINGS
a) Provide the SITE (including securing usage of the Onshore Pipeline Route for
the pipeline and acquiring the land for the pipeline stations, ground beds,
rectifier station areas and cathodic protection cabling areas).
b) Provide such data for the SITE and the area adjacent to the SITE as may
already be in the EMPLOYERs hands, including, where available, topography
survey

data,

Environmental

Management

and

Monitoring

Procedure

(UKL/UPL) and reports, soil investigation surveys and the like. This data shall
be treated as information only, PT. PRATIWI PUTRI SULUNG shall be
responsible to verify such data and conduct additional survey if they think
necessary for the designing the WORKS.
c) Obtain and maintain the following permits, licenses and certificates:
Land Compesation for Onshore Pipeline Route
Equipment Operational Safety Worthines Certificate (SKPP), e.g.
Pressure Vessel, Rotating Equipment, Storage Tanks, Pipeline, PSV,

Electrical Equipment, and


Supply at the EMPLOYERs cost, all natural gas necessary for
completing the commissioning of the entire Pipeline System, excluding
such natural gas required for PT. PRATIWI PUTRI SULUNG remedy
work where required.

28.

SCHEDULE OF WORK
PT. PRATIWI PUTRI SULUNG shall complete and commision the WORKS according
with the Time for Completion of the Works stated in the Contract and as shown in
Project Contract Master Schedule, Doc. No. CP11A-PTU-3275-GA-SC-001

PT. Pratiwi Putri Sulung

Scope of Work
Page 79 of 80

UPGRADING TANGSI OFFTAKE STATION PROJECT (CP-11A)

29.

ATTACHMENTS
1.List of Pipeline Crossings and Special ContsructionMethod
2.Spare Part List
3.Permit Initiation Status by EMPLOYER.
4.Existing Data
I.
Civil
II.
Electrical
III.
Instrument
IV.
Utility

PT. Pratiwi Putri Sulung

Scope of Work
Page 80 of 80