Professional Documents
Culture Documents
Submitted to:
Engineer Muhammad Mohsin
Lecturer, MNS UET Multan
Submitted by:
Rashid Ali (2012-BT-Civil-09)
Amir Shehzad (2012-BT-Civil-17)
Imtiaz Faiz (2012-BT-Civil-23)
Saif-ur-Rehman (2012-BT-Civil-39)
Abstract
DEAPARTMENT
5 OF CIVIL ENGINEERING TECHNOLOGY
MNS UET MULTAN
5
Acknowledgement
DEAPARTMENT
5 OF CIVIL ENGINEERING TECHNOLOGY
MNS UET MULTAN
5
Table of Contents
DEAPARTMENT
5 OF CIVIL ENGINEERING TECHNOLOGY
MNS UET MULTAN
5
Introduction
Primavera is a Project Management software developed by Oracle. Which is used for globally
prioritizing, planning, managing, and executing projects, programs, and portfolios. Latest version of
Primavera available in market is 15.1. which is an upgrade of Primavera P6 Version 8.1. There are no
Versions 9 to 14 because Oracle changed their naming convention with the release of 15.1 so the name
is the same as the year of the release. Before Primavera, Software like Primavera P3, Microsoft Project,
Sure Trak and Asta Power project were used. But Primavera P6 is advanced and more reliable Project
Management Software, hence it is Preferred.
Purpose:
The purpose of planning is to have a clear image in our mind that what will be done and when will be
done? The ultimate process of planning is to build a model that allows us to predict which activities and
resources are critical to the timely completion of the project.
By doing planning we can have clear idea about availability of resources, their excess or
shortage. Once we get the idea of shortage, we can then implement the strategies to make sure that
these activities and resources are managed properly. And hence ensuring that project will be delivered
on time as well as within budget. Both of these parameters are very important to measure the success of
any project.
When we open Primavera, the following window appears showing all existing organizational structures
and their Projects.
Purpose of Planning
The ultimate purpose of planning is to build a model that enables you to predict which activities and
resources are critical to the timely completion of the project. Strategies may then be Implemented to
ensure that these activities and resources are managed properly, thus ensuring that the project will
be delivered both On Time and Within Budget.
Cost
Other project management functions that are not traditionally managed with planning and
scheduling software but may have components
reflected in the
schedule include:
Document Management andControl,
Quality Management,
Contract Management,
Issue Management,
Risk Management,
Industrial Relations, and
Accounting.
The development of Enterprise Project Management systems has resulted in the inclusion of many
of these functions in project planningand scheduling software.
Primavera includes modules for:
Issue Management,
Risk Management, and
DEAPARTMENT
5 OF CIVIL ENGINEERING TECHNOLOGY
MNS UET MULTAN
5
Document Management.
Planning Cycle
The planning cycle is an integral part of managing a project. A software package suchas Primavera
makes this activity much easier .
Enter the breakdown structure of the project deliverables orproducts into the software. This is
often called a Work Breakdown Structure(WBS) or Product Breakdown Structure (PBS),
DEAPARTMENT
5 OF CIVIL ENGINEERING TECHNOLOGY
MNS UET MULTAN
5
Break a project down into the work required to create the deliverables and enter these into the
software as Activities under the
appropriate WBS,
Assign durations, constraints, predecessors and successorsof the activities and then calculate
the start and finish date
of all the activities,
Assign resources and/or costs, which represent people, equipment or materials, to the activities
and calculate the project resource
requirements and/or cash flow.
Optimize the project plan,
Set Baseline Dates and Budgets to compare progress against
Record the consumption of resources and/or costs and re-estimate the resources and/or costs
required to finish the project.
Produce management reports
Activity types:
Task Dependent
Resource Dependent
Level of Effort
Start Milestone / Finish Milestone
WBS Summary
DEAPARTMENT
5 OF CIVIL ENGINEERING TECHNOLOGY
MNS UET MULTAN
5
Has a duration which is determined by a group of activities that share a common WBS level.
The Activity's duration will equal the overall duration of activities assigned to the same WBS
level.
Resources that drive activity dates cannot be assigned to WBS summary activities.
Creating calendars:
Constraints:
Definition:
A Constraint is a restriction imposed on the start or finish date of an activity It may or may not
override logic, depending on the Constraint Type Should be used sparingly, only to represent
external factors that are not within the control of the organization, e.g. easements, ADOT ROW,
etc..
DEAPARTMENT
5 OF CIVIL ENGINEERING TECHNOLOGY
MNS UET MULTAN
5
Constraint Types:
Start on :
imposes a start date. Can delay an early start or accelerate a late start to satisfy the imposed date.
Unlike the mandatory start constraint, doesnt violate logic.
Start on or after :
Also known as "Start no earlier than".Affects only early dates. Limits the earliest time an activity
can begin so that early start date cannot be earlier than the constraint date. Logic however, may
cause the early start to occur later.
Start on or before :
Also known as "Start no later than".Affects only late dates. Limits the latest date it can start. When
calculating a schedule, it is used in the backward pass only if the calculated late start date will be
later than the imposed date. This constraint may decrease total float.
Finish on:
Similar to the "Start on". Imposes a finish date. The finish on constraint can delay an early finish or
accelerate a late finish to satisfy the imposed date.
Finish on or after :
"Finish no earlier than". Limits the earliest time it can finish so that the finish of an activity is not
scheduled before the imposed date.
Finish on or before :
"Finish no later than". Limits the latest time it can be finished. The finish on or before constraint
affects only late dates. Reduces Total Float.
As late as possible :
Pushes the activity to start as late as possible without delaying its successors, if it has available
float.
sets early and late dates equal to the date you specify. Overrides logic..Do not Use..!!!!
DEAPARTMENT
5 OF CIVIL ENGINEERING TECHNOLOGY
MNS UET MULTAN
5