You are on page 1of 8

TITLE

SEWAGE DRAINAGE PIPES

Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012
Page: 1 of 5

CANYON VIEWS DEVELOPMENTS


DEFENCE HOUSING AUTHORITIES PHASE II (EXT)
ISLAMABAD, PAKISTAN

METHOD STATEMENT FOR


SEWAGE DRAINAGE PIPES

METHOD STATEMENT FOR


CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)

00

For the initial issue &


approval

10th June,
2012

Ab.Maje
ed

Rev
No

Details For Revision

DATE

Prepared
By

TITLE

SEWAGE DRAINAGE PIPES

Checke
d
By

Approva
ls

Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012
Page: 2 of 5

METHOD STATEMENT FOR


CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)

Table of Contents
1. OBJECTIVE.......................................................................................................... 3
2. SCOPE................................................................................................................. 3
3. REFERECNES...................................................................................................... 3
4. ABBREVATIONS.................................................................................................. 3
5. RESPONSIBILITIES............................................................................................ 3
6. EQUIPMENT........................................................................................................ 4
7. PROCEDURE....................................................................................................... 4
8. MATERIAL........................................................................................................... 5
9. SAFETY EQUIPMENT........................................................................................ 5
10. SAFETY CHECKS............................................................................................ 5
11. MANPOWER.................................................................................................... 5

TITLE

SEWAGE DRAINAGE PIPES

Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012

METHOD STATEMENT FOR


CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)

Page: 3 of 5

1. OBJECTIVE
1.1-

The main objective of this method of statement is to provide


guidance for the formwork Fixing & Removal for construction
of houses as per specification of this particular project.

2. SCOPE
2.1
This method statement covers inspection and quality
monitoring of
construction activities for houses based on approved
engineering principles.

3. REFERECNES
3.1
3.2
I
3.3
3.4

Project Specifications Pages # 36-41


Cement
Recommended i.e. BS12 or ASTM C150 TYPE
Sand
Aggregate

Approved quarries
Approved quarries

4. ABBREVATIONS
4.1
4.2
4.3
4.4

PM
QA & QC
HSE
RFI

Project Manager
Quality Assurance & Quality Control
Health Safety & Environment.
Request for Inspection

5. RESPONSIBILITIES
5.1
Project Manager is responsible to
ensure that the
construction activities
for the building are conducted according to this method
of statement, latest
METHOD STATEMENT FOR
CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)

approved construction drawings & project specification


will be followed in
true later in sprit.
5.2
Construction Manager is responsible for the implementation
of method of
Statement

TITLE

SEWAGE DRAINAGE PIPES

Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,

METHOD STATEMENT FOR


CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)

2012
Page: 4 of 5

6. EQUIPMENT
6.1
6.2
6.3
6.4
material.
6.5
6.6

Mixer Machine
Block manufacturing machine
NET(Jali) for screening of material
Measuring pan (DAGA0 for measurement of exact quantity of
Hand shovel
Mortar pan if required
Hessian cloth

6.7
7. PROCEDURE

7.1
Shop drawing for sewage drainage pipes approved by
Engineer
7.2
Material must be approved by Engineer
Procedure
Following procedure will be followed
RFI(request for inspection shall be sent to engineer for approval
7.3
7.4
7.5
7.6

Laying of pipes
Maintain slope level of pipe to 1%
Hydro testing for piping, for 2 hours\
Approval for casing

METHOD STATEMENT FOR


CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)

TITLE

SEWAGE DRAINAGE PIPES

Doc No:TIJ-SWDR09
Rev:
00
Date: 10thJune,
2012
Page: 5 of 5

METHOD STATEMENT FOR


CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)

7.7
Removing of mould after manufacturing blocks must be with
due care
7.8
Curing of concrete manufactured blocks shall be ensured in
order to
achieve required compressive strength
7.9
Minimum crushing strength of 1000 PSI average of three
units tested or 850
psi per individual unit.
7.10
Proper Cleaning of Platform where blocks are manufactured.
7.11
After hardening of concrete blocks, concrete blocks will be
picked from
platform to another place nearby platform.
7.12
Concrete blocks will be properly stacked and will be covered
with hessian
cloth to maintain the moisture for longer time.

8. Material
8.1
8.2
8.3

Ordinary Portland cement approved by Engineer.


Sand approved by Engineer
Aggregate approved by Engineer

9.1
9.2
9.3
9.4
9.5

Safety helmet
Safety shoes
Gloves
Safety Glasses
Dust Mask

9. Safety Equipment

10.

Safety Checks

10.1
Safety Engineer will make ensure that working area is safe
and accordance
with project site regulations

11.
11.1
11.2
11.3
11.4

MANPOWER
QC Engineer
Lab Technician
Foreman
Labor

METHOD STATEMENT FOR


CONSTRUCTION OF REMAINING WORKS ALMA-1
TOWNHOUSES
(58UNITS)

You might also like