Monthly Progress Report for the Month of January 2016 (Governance, Agriculture &

Governance.
Sr
.#

Pack
age
No.

Contract No

PERRA/ GOVKOHISTAN/
01/2007

PERRA/GOV/
KOHISTAN/06/
2008

District: KOHISTAN
Name Of Buildings

Police Station Dubair

Union
Council

Dubair

Covered Area (Sft)

No of
Buildings

5466.83

Name Of
contractor

M/S Arif Khan &


Bros.
Police Post Keru

Keru

1084.47

Police Post Jijal

Jijal

1375.25 (Inclusive
of Plinth protection)

Police Post Kayal

Kayal

C & W store Besham

Besham

Haji Bahadur
Sher & Sons

1375.25 (Inclusive
of Plinth protection)

-----

------

------

Date of Award of
Work

26/5/2007

Date of
VO issued if
Commencemen
any
t*

Date of
actual start

Date of
Handing
over of site

Completion
Date(as per
contract)

Variation
order in
pending

9/6/2007

Oct, 2007

Oct, 2007

8/6/2008

---do---

9/6/2007

12/3/2008

12/3/2008

8/6/2008

NA

29/1/2009

29/1/2009

29/1/2009

28/1/2010

NA

29/1/2009

29/1/2009

29/1/2009

28/1/2010

------

------

------

------

------

15/1/2009

------

Agriculture & Live stock Sector.

PERRA/AGRI04/ KOHISTAN/
11/2008

Tehsil Agriculture Office


Dassu
Dassu

2133.87

Tehsil
Agriculture
Office

1244.125

Staff
Residence
Quarter

557.81

Chowkidar
Residence

2133.87
2

PERRA/AGRITehsil Agriculture Office


03/KOHISTAN/10
Palas
/2008

Palas

1244.125
557.81
2133.87
1244.125

PERRA/AGRITehsil Agriculture Office


02/KOHISTAN/09
Pattan
/2008

Tehsil
Agriculture
Office
Staff
Residence
Quarter
Chowkidar
Residence
Tehsil
Agriculture
Staff
Office
Residence
Quarter

Pattan
557.81

Chowkidar
Residence

M/S Umer
Rehman & Co

23/01/2009

Not
applicable

6/2/2009

8/3/2009

23/01/2009

5/2/2010

M/S Shangla
Builders & Co.

26/05/2009

---------

4/2/2010

22/02/2010

4/2/2010

3/2/2011

M/S Riaz & CO

9/6/2009

---------

09/062009

Last week of
NOV 2009

9/6/2009

8/6/2010

PERRA/
LIVESTOCK.04/
KOHISTAN/08/
2008

VETERINARY
DISPENSARY DUBAIR
BALA

PERRA/
LIVESTOCK.03/
KOHISTAN/07/
2008

VETERINARY
DISPENSARY
SANAGAI

Dubair

1223.87

----------

M/S Riaz & CO

9/6/2009

------

9/6/2009

19-11-2009

9/6/2009

8/6/2010

SANAGAI

1223.87

----------

M/S Riaz & CO

9/6/2009

---------

9/6/2009

19-11-2009

9/6/2009

8/6/2010

1981.33

PERRA/
LIVESTOCK.02/
KOHISTAN/06/
2008

TEHSIL VETERINARY
HOSPITAL PATTAN

1250.00
Pattan
584.93

Office Residence(TVH
Dassu)

1981.33

Staff Residence(TVH
Dassu )

1250.00

PERRA/L.STK.05
/Kohistan/09/201 Office (TVH Shatyal)
0

Dassu

1981.33

Civil Veterinary
Dispensary Karang

1223.87

Civil Veterinary
Dispensary Seo

1223.87

Tehsil
Veterinary
Hospital
Staff
Residence

M/S Inayat Khan


& CO

9/6/2009

-------

9/6/2009

19-11-2009

9/6/2009

8/6/2010

work started

4/12/2010

17/12/2011

Chowkidar
quarter
Office
Residence(T
VH Dassu)
Staff
Residence(T
VH Dassu )
Office (TVH
Shatyal)
Civil
Veterinary
Dispensary
Karang
Civil
Veterinary
Dispensary
Seo

18/12/2010
Umer Rehman &
Co

26/04/2010

-----commencemen
t notice not
issued yet
18/12/2010

HEALTH SECTOR
Sr. Packa
# ge No.

H-33

Contract No

PERRA/
KOHISTAN/33/
2009

Name Of Buildings

BHU Goshali

Union
Council

Goshali

Covered Area (Sft)

No of
Buildings

1896.30

Main Building

1741.96

Type III
Residence

650.95

Type V
Residence
Block A

650.95

Type V
Residence
Block B

196.434

Guard Room

1896.30

Main Building

1741.96
2

H-51

PERRA/
KOHISTAN/51/
2009

BHU Bataira

Bataira

650.95

196.434

Type V
Residence
Block B
Guard Room

1896.30

Main Building

650.95

1741.96
3

H-4

PERRA/
KOHISTAN/04/
2009

BHU Sharakot

Sharakot

650.95

650.95

H-34

PERRA/
KOHISTAN/34/
2009

BHU Jijal

Jijal

Type III
Residence
Type V
Residence
Block A

Type III
Residence
Type V
Residence
Block A

Name Of
contractor

M/S Manawar
Shah & Brothers

M/S Zardad &


Brothers

M/S Shah Nawaz


& Sons

Date of
Handing
over of site

Completion
Date(as per
contract)

NA(date of decision for salvage


20/06/2009
material) 11/6/2009
25/05/200911/6/2009

10/6/2010

Date of Award of
Work

2/10/2009

25/05/2009

Type V
Residence
Block B

196.434

Guard Room

1896.30

Main Building

1741.96

Type III
Residence

650.95

Type V
Residence
Block A

650.95

Type V
Residence
Block B

196.434

Guard Room

M/S Haji Bahadur


Sher & Sons

28/05/2009

Date of
VO issued if
Commencemen
any
t*

Date of
actual start

NA

9/10/2009
(Date of letter 15/10/2009
of EDO Health)

9/10/2009

NA

11/6/2009 (date
of decision for
22/06/2009
salvage
material)

1/6/2009

work on only
02x
21/07/2009(Date
NA
of letter of DRU
Buildings
office)
actually
started on

8/10/2010

10/6/2010

10/6/2010(Tentative)

H-27

PERRA/
KOHISTAN/27/
2009

BHU Soyal Dara

1896.30

Main Building

1741.96

Type III
Residence

Kareen
196.434

Guard Room

1896.30

Main Building

1741.69
650.95
6

H-35

PERRA/
KOHISTAN/35/
2009

BHU Ranolia

Ranolia

M/S Munawar
shah & Brothers

2/7/2009

NA

11/06/2009
(Date of letter
of Salvage
material)

Not started
yet.

11/6/2009

10/6/2010

M/S Munawar
shah & Brothers

6/7/2009

NA

01/11/2009(Dat
e of leaving of
IDPs refer MM
of 11/11/2009)

1/11/2009

1/11/2009

31/10/2010

Type III
Residence
Type V
Residence
BlockA

650.95

Type V
Residence
BlockB

196.434

Guard Room

1896.30
1741.96

H-45

8 H-89

22 H-124

23 H-22

PERRA/
KOHISTAN/45/
2009

PERRA/
KOHISTAN/89/
2009

BHU Karang

RHC SHATYAL

PERRA/KOHISTA EMOC Center at (RHC


N/124/2011
Dassu)

PERRA/
KOHISTAN/22/
2009

BHU Gabrial

Karang

SHATYAL

650.95

Type III
Residence
Type V
Residence
Block1

650.95

Type V
Residence
Block2

196.434

Guard Room

3257.715

Main Building

196.43

Guard Room

M/S Munawar
shah & Brothers

2/6/2009 (Date
communicated
by DRU officials
through E-mail)

NA

M/S SULTAN
MEHMOOD

24/02/2010

Not
available

29/03/2010

29/10/2011

N.A

M/S Saeed-UrRehman &


Brothers

27/07/2010

M/S Zardad &


Brothers

22/02/2010

Al rehman
Main Building construction and
co

Dassu

Karang

Main Building

1896.30

Main Building

1741.96

Type III
Residence

650.95

Type V
Residence
Block A

650.95

Type V
Residence
Block B

196.434

11/6/2009((Date
of letter of
28/06/2009
decision for
salvage material)

11/6/2009

10/6/2010

29/03/2010

15/03/2010

28/03/2011

29/10/2011

18/2/2012

17/2/2012

28/10/2012

NA

NA

9/4/2015

19/3/2015

26/7/2011

NA

21/04/2010

21/04/2011

7/4/2010

20/04/2011

Guard Room

Note: The data described above is based on lastest possible record available

WATSAN SECTOR
1

PERRA/
WATSAN01/KOHISTAN/07 PHED Residence Dassu
/2008

DASSU

--------

--------

SOCIAL SECTOR
1

----

PERRA/S.P-01- Women Developmentl


KOHISTAN/14/20 Center & Social Welfare
Complex Kohistan
10

Dassu

-----

-----

-----

-----

-----

-----

-----

-----

-----

016 (Governance, Agriculture & Livestock, Health & Watsan Sectors)

Present EOT status

Awarded
Extension expired
on 07/01/2010

Bid
Cost/Contra
ct Amount
(Rs. Million)

Status

Defect Liability
Certificate Status

Outstanding payment
due to the contractor if
any

87

87

Roof treatment Completed.

NA

Nil

Work Sttoped

94

94

Finishing work in progress

NA

NA

Work in progress.

96

96

NA

NA

Handed Over

96

96

NA

NA

Handed Over

0.000

------

------

Issues/Remarks

10.047

-----do----------

Over all
Facility wise
Physical
Progress(%)

23.645

------do----Stipulated time
expired.contractor
has not applied for
extension.

Physical
Progress
(%)

------

------

Work order not issued.

42.00

14.251

NA

30.00

35.40

30.000

100
NA

86

100

NA

NA

Masonry work above plinth


beam in progress

--------

-------

Steel fabrication and


formwork preparing for slab
and Beams.

--------

-------

100.00

Boundary wall completed

Roof Slab Completed.

54.000

Roof Slab Completed.

54.00
54.000

--------

------

Handed Over

--------

------

work stopped by the


contractor due to non
availibility of Funds.

Boundary wall completed

54.000

13.504

work stopped
by the contractor since due to
non availibility of Funds.

Boundry wall completed

100

Not apply for EOT

Rcc Roof slab Completed.

Roof Slab Completed.

Not applicable

5.305

29.32

29.32

Super structure RCC


columns and Brick
masonary upto R.B
completed. Site vanished in
flood.

Not applicable

5.622

2.36

2.36

excavation completed and


site vanished in flood.

Not apply for EOT

Existing site is totally


vanished in flood.

--------

-------

work stopped by contractor

--------

NA

NA

Shutrring for Roof


beam and slab in
progress

NA

NA

30.00

steel cutting and binding for


roof slab.

29.32

-------

steel cutting and binding for


roof slab.

0.00
14.00
35.00

32.355

-------

steel cutting and binding for


roof slab.

30.00

Not applicable

--------

30.00

13.086

The route leading to the site


has been vanished and hence
the site is not accesable.

--------

20.00

20.00

plinth beam
completed and super
structure masonary in
progress

NA

NA

0.00

0.00

--------

NA

NA

0.00

0.00

--------

NA

NA

Work stopped by the


contractor due to non
availibility of Funds.

Present EOT status

Not apply for EOT

Eot Submitted To
NESPAK

Bid
Cost/Contra
ct Amount
(Rs. Million)

31.365

Physical
Progress
(%)

Status

25.00

Rcc Columns in ground


floor completed.

15.73

P.B casted.Class "E"


concrete under floor
completed.

6.00

15.92

shuttring and steel


cutting and binding for
raft foundation.

0.67

Demolition completed.

0.67

Demolition completed.

62.000

Trusess in progress

62.00

Trusess in progress

Defect Liability
Certificate Status

Outstanding payment
due to the contractor if
any

----------

------

work stopped by the


contractor due to non
availibility of Funds.

--------

------

Work Stoped

Issues

Trusess completed

27.250

80.00

61.00
Trusess completed

80.00

Eot Submitted To
NESPAK

Eot Submitted To
NESPAK

29.565

29.134

46

Trusess in progress

30

Block masonary in
G/floor floor completed

60

Plaster work in progress

54

50.00

PGI sheets in progress.

54

PGI sheets in progress.

54

PGI sheets in progress.

48.00

G-floor and F-floor exterior


and interior plaster work
completed

48.00

G-floor and F-floor exterior


and interior plaster work
completed

40.00

37.79

steel cutting and binding for


roof beam in progress.

1.00

Excavation in progress.

0.85

site clearence completed

---------

------------

Work stopped due to Snow

---------

----------

work stopped by the


contractor due to non
availibility of Funds.

Not applicable yet

Not apply for EOT

0.00

work not started yet

0.00

work not started yet

25.821

30.147

0.00

work not started yet

48.00

plaster work completed

33.78

Plaster work in progress

35.00

plaster work completed

35.00

35.00

40.55

plaster work completed

plaster work completed

---------

---------

--------

------

. Status of Termination is not


held in this office.

work stopped by the


contractor due to non
availibility of Funds.

Ground floor slab has been


casted in september 2010.

27.01
0.00

Not apply for EOT

31.409

29.97

work not started yet.

19.25

29.97

R.B casted.

11.04

Block masonry completed


upto plinth level.

52.00
Not available

19.457

Not apply for EOT

Not apply for EOT

2.784

49.880

8.603

60.00

60.00

False ceiling work and


Bath tiles in Progress
Slab completed

53.00

Block masonary for Super


structure completed.

53.00

Block masonary up to roof


Beam Completed.

53.00

Block masonary up to roof


Beam Completed.

30.00

Masonry work above plinth


beam in progress

66.00

---------

Site not accsesable after


Floods 2010.

---------

---------

Work Stopped

N.A

N.A

Work in progress

----------

------

Work stopped due to Snow

---------

---------

Lintel beam completed.

50.00

53.00

---------

Roof beam completed

53.00
6.00

N.A

R.B casted.

66.00

Plinth protection Work


completed.

Work Stopped

-----

-----

-----

-----

-----

-----

Work order not issued.