Professional Documents
Culture Documents
I. INTRODUCTION
he BC Hydro transmission system, in a remote corner of
the province, had a sizeable addition brought into service
near the end of 2014. To spur economic activity in the region a
series of new transmission lines were constructed to
accommodate both non-utility generation and large industrial
loads. The main 287 kV transmission line to the area is very
long and had significantly more faults than anticipated in
months following the first energization. The protection
systems had been very dependable during all the faults in the
initial months and in the time since then as well. The security
of the relaying system has also been quite good. It was tested
though under a severe unintended operating condition for a
fault that occurred on January 7th 2015. This paper outlines
how multiple faults that day left the system in the unintended
operating configuration. This condition resulted in
approximately 1.7 pu voltage at multiple substations. Next the
paper will discuss how protection relaying in the region
responded while the system was operating in a critical state.
Three protection relays operated while there was no fault
2
cable is used for high speed protection and SCADA functions.
Tower construction, conductor data along with the line
parameters determined from the construction data are listed in
Appendix I. There is 35% series compensation at the BQN end
of line and 72% positive sequence shunt compensation using
two reactors at SKA and one at BQN. The shunt reactors at
SKA (2RX1 & 2RX2) are fixed and the one at BQN
(2RX231) is switchable.
2L102 is protected by modern microprocessor-based relays
with a high speed, sub-cycle, current differential scheme. The
line breakers are rated as having a three cycle interrupt time.
Therefore overall fault clearing time is less than four cycles
for all bolted faults. This speed is within the performance
target specified in NTL system planning studies.
4
RX22, TAT T1 tripped and
a
the overr-voltage starrted
2R
subbsiding.
Taable 1: Sequencce of Event on 07 January, 20
015
1
Time stamp
p
05:38:39.942
2
05:38:41.173
3
05:38:41.216
6
05:41:12.473
3
05:44:42.732
2
05:44:43.941
1
05:47:42.548
8
05:48:47.024
4
06:11:33.000
0
06:15:18.000
0
06:15:28.000
0
06:21:21.972
2
06:21:22.023
3
06:21:22.182
2
06:21:22.329
9
06:21:22.423
3
Event
2L102 initiial single-pole trip (C phase)) at
SKA and BQN
B
2L102 auto
o-reclose fail, three-pole trip
p at
SKA and BQN
B
2L102 open
n terminal logiic initiate transsfer
trips to 2L3
374 and 2L379
9
2L374 trip at BQN and RDC
R
2L379 trip at BQN, FKR and VOL
2L102 re-eenergized at botth ends
2L102 sing
gle-pole trip (C
C phase) at SK
KA
and BQN
2L102 auto
o-reclose fail, three-pole trip
p at
SKA and BQN
B
SKA 2L10
02 energization
n attempt fail due
d
to the persiistent fault
SKA 2L10
02 energization
n attempt fail due
d
to the persiistent fault
2L102 succcessful restoraation at SKA and
a
BQN
2L379 re-eenergized at BQ
QN
2L374 re-eenergized at BQ
QN and TAT
2L102 C-G
G fault initiatiion, 2.8 km fro
om
BQN
2L102 sing
gle-pole trip (C
C phase) at SK
KA
and BQN
BQN 287 kV bus C phase
p
experien
nce
over-voltag
ge (1.6 pu.)
BQN T3 PN tripped HV CBs, 2RX22 out
of service
BQN 287 kV bus C phase
p
experien
nce
higher overr-voltage (1.7 pu.)
p
TAT T1 PN
N tripped 2CB2, TAT T1 outt of
service
BQN 287 kV bus C ph
hase voltage drrop
u.
below 1 pu
BQN 2RX
X25 PN tripped
d bus CBs, BQ
QN
287 kV buss de-energized
5
IV. PROTECTION AND CONTROL DESCRIPTION
In two months following Northwest Transmission system
energization, 2L102 had several phase-to-ground faults and
the protection performed correctly during all faults. Previous
sections detailed how the system ended up in an undesirable
operational state on the morning of 7th January 2015.
The following protection section will detail the protection
operations in the NTL system that morning besides the 2L102
operations. It will also discuss the protection operations that
did not occur. Section V will discuss the measures taken to
quickly take action in the protection system to reduce the
chance of a high temporary over-voltage in the future.
A. Duration of Over-Voltage Condition
The 2L102 line protection had single-phase tripping (SPT)
enabled on January 7th, which opens only the faulted phase
for any single-phase-to-ground fault. If the fault persists when
the open phase is closed (unsuccessful reclose), then the line
protection would open all phases with three-phase tripping
(3PT) logic, and send direct transfer trips to open entrance
breakers of RDC, FKR and VOL. The single-phase open
interval of the line is approximately 60 cycles (1 second). The
first phase-to-ground fault occurred at 5:38 AM and it was
persistent so, a direct transfer trip was sent to RDC, FKR, and
VOL taking them offline for the remainder of this time period.
During the 6:21 AM event 2L102 line protection detected the
single-phase-to-ground fault. During the approximately 1
second single-phase open (SPO) period, a number of addition
protection operations occurred, some unexpectedly.
B. BQN Transformer T3 Protection Operation
BQN T3 is a 10 MVA transformer with an HV delta
winding and an LV wye winding. The transformer serves a
fourth harmonic filter bank and the station service transformer
at BQN substation.
As shown in Figure 3, the voltage between Phase B and C
became very high (more 1.6 pu) during open pole period. It
saturated the delta winding of BQN T3 connected between the
two phases. Figure 6 shows the disturbance records from the
transformer differential relay. Three analog traces on top are
three-phase line currents processed by the 60-Hz digital filter
embedded in the relay. Two analog traces in the middle of the
figure are fifth harmonic frequency content relative to the
fundamental frequency in differential current measured by the
relay for the B and C phases. In bottom part of the figure,
digital traces are illustrating responses various relay elements
to the differential currents measured when the B-to-C winding
was overexcited by over-voltage. To illustrate distorted nature,
Figure 7 shows the unfiltered analog traces of the line currents
into the transformer. T3 primary (287 kV side) currents
demonstrate that, with harmonic distortion considered, these
currents were about 3 times the 20 Arms rated primary
current. Though not shown, negligible currents were coming
out of the transformer low-voltage windings confirming that
the high-side currents were transformer magnetizing currents.
In Figure 6 and Figure 7, Phase B and C line currents were
practically 180 out-of-phase which confirmed the saturation
6
filtered primary currents are shown in Figure 8 and the
unfiltered currents appear in Figure 9. The maximum
instantaneous currents (Phase B and C) were about 170 A
peak, due to severe harmonic distortion. As a comparison, the
rated primary current is 33 Arms (47 A peak).
Like BQN T3, a high percentage of 5th harmonic current
blocked the transformer from operating instantaneously when
it began to saturate from the high voltage. This event report
also shows the 5th harmonic current dropping below 35% and
tripping shortly afterwards. Compared to BQN T3, this
transformer took nearly 8 cycles longer to saturate to the point
where 5th harmonic current dropped below the inrush
threshold.
The unfiltered event report shows that the harmonic current
started to reduce while the fundamental current increased four
cycles after the relays event report was triggered. This aligns
with the tripping of BQN T3 and RX22 and the subsequent
voltage rise that was recorded in the area. The even higher
voltage drove the TAT transformer core deeper into saturation
causing the magnetizing flux to leak out of the core and setting
up eddy currents in the non-laminated parts of transformer. As
a result, the fifth harmonic current dropped relative to the
fundamental frequency component and contributed to
transformer tripping. Similar to other transmission and
distribution transformers in BC Hydro, the transformers in the
new NTL system were neither equipped with over-voltage nor
Volt-per-Hertz protection. Trips by the differential protection
saved the transformers from possible damage.
7
event with filtered currents and voltages. The clearing points
of various protections are easily identified with changes in
currents and voltages at the BQN terminal.
L g LT
L g LT
f
2
1
62.6 Hz
Lg LT (C g 2C m )
Lg LT
9
T
b) Linear Case without TAT T1
F
For this EMTP
P simulation, TAT
T
T1 (HV grounded-star
g
LV
L
groounded-star an
nd delta tertiaary) is assumeed to be out of
serrvice. The Phaase C phase-to
o-ground voltag
ge waveforms of
Figgure 15 (b) sh
how a dramattic reduction, compared to the
preeceding case, of the over-v
voltages during
g SPO. The beat
b
freequency of thee modulated waveform
w
is sim
milar to the case
witth TAT T1 an
nd BQN T3 ou
ut of service but
b the maximu
um
insstantaneous ov
ver-voltage on
nly marginally exceeds 1.0 pu.
Thhis case clearly
y demonstrates that TAT T1 must
m have play
yed
a ddominant role in
i producing th
he high temporrary over-voltag
ges
thaat occurred for the January 7, 06:21:21 SPO
O event.
C. EMTP Non-L
Linear Analysiss with TAT T1
F
Figure 16 com
mpares the EM
MTP simulatio
on with the no
onlinnear effects to
o the recorded
d data from the digital faault
reccorder (DFR) at
a the BQN en
nd of the 2L37
79. The DFR 287
2
kV
V instantaneou
us C Phase voltage
v
(phase-to-ground) are
dissplayed in solid lines while the
t simulated values
v
are sho
own
as dotted lines. A Phase C-to-g
ground fault occcurred on 2L1
102
neaar BQN at T = 0 and the Phase C of the linee at BQN open
ns 3
cyccles later and
d SKA Phase C opens one--half cycle latter.
Wiithin 1.5 cyclees, Phase C-to
o-ground voltag
ge at BQN go
oes
intto a high TOV,, with an initiaal 2 cycles of an
a over-voltagee of
aroound 1.67 pu followed
f
by a TOV of abou
ut 1.6 pu. At T =
200 ms BQN T3
3 protection op
pens 2CB2 and
d 2CB3 and trrips
botth T3 as well as 2RX22. There is an immeediate increasee in
TO
OV on Phase C to about 1.71 pu, which peersists until TA
AT
T1 trips off.
10
abssorption abovee its rating, thee internal heatiing due to enerrgy
lossses may resu
ult in thermall runaway off the zinc ox
xide
com
mponents and the arrester faiils.
Disadvaantages:
This solution
n prevented a repeat of the January 7th high
temporary over-voltage event with
hout additio
onal
investment in
n hardware and
d communicatiions.
Disadvantages:
11
if tthe 2L379 terrminal breakerrs at FKR are open, this
trannsformer willl not be coonnected to the system.
Connsequently, ann operating orrder can probaably prevent
anyy problem created by the additioon of this
auttotransformer, if Alternative 2 is implementted.
V
VII. CONCLUSSIONS
A. Effeects of Single-P
Pole Tripping iin Radial Systeems
Overr-voltage mitiggation shouldd be a primaary planning
priorityy when consideering using a single-pole tripping scheme
in a reemote or radiial system. It is important for system
plannerrs to consider tthe system ressonance frequeency under a
variety of intentiional and unintentional operating
configuurations when specifying equuipment such aas line shunt
reactorss and transform
mers
TP Simulation
n of 23 MW of
o Generation on
Figgure 18: EMT
2L
L379 and Singlee-Phase Trip.
C. Equipment Replacement
R
F
For this option
n, the existing TAT
T
T1 would
d be replaced by
b a
dellta-grounded star
s
transformeer, the same as BQN T3. As
dessigned, single--line to ground
d faults on 2L102 would ressult
in SPO and all otther faults wou
uld result in 3PO
O.
Addvantages:
During SPO
O, the voltagee waveforms on the 287 kV
system wou
uld be similar to Case 6, having
h
negligiible
temporary ov
ver-voltage.
A STATCO
OM that wou
uld reduce thee power quallity
problem in the distributio
on voltages at TAT during the
period of thee SPO
Disadvantages:
12
VIII. APPENDIX I
A. 2L102 Construction
Figure I-1 shows a typical steel-Y type monopole tower for
this flat-configuration circuit. The average height of the
conductor above ground at the tower is 15.0 m. Each phase
comprises a bundle of two 2B-1590 KCMIL ASCR Lapwing
conductors in a 45.7 cm arrangement.
1.
2.
3.
4.
5.
IX. REFERENCES
F. Iliceto, E. Cinieri and A. Di Vita, Overvoltages Due to
Open-Phase Occurrence in Reactor Compensated EHV
Lines, IEEE Transactions on Power Apparatus and
Systems, Vol. PAS-103, No. 3, March 1984, pp. 474-482.
Marta Val Escudero and Miles Refern, Effects of
Transmission Line Construction on Resonance in Shunt
Compensated EHV Lines, Presented at the International
Conference on Power Systems Transients (IPST05),
Montreal, Canada, June 19-23, 2005, Paper No. IPST0509.
M. Nagpal, Terry Martinich, Amitpal Bimbhra and Dave
Sydor, Damaging Open-Phase Overvoltage Disturbance
on a Shunt-Compensated 500 kV Line Initiated by
Unintended Trip, IEEE Transactions on Power Delivery,
Vol. 30, No. 1, February 2015.
M. Nagpal, Terry Martinich, Amitpal Bimbhra, Dave
Sydor and Jerry Wen, Damaging Open Pole OverVoltage Disturbance Initiated by Personnel Incident,
Western Protective Relaying Conference in October 2013,
Spokane, WA, USA.
Terry Martinich, M. Nagpal and S. Manuel, Analysis of