Professional Documents
Culture Documents
In the beginning of this canal is a net door from U-girder of 100x40x3mm frame and
net from steel bar diameter (20mm) and spicing of 20cm c/c.
Construction joints must be considered after every 12m length of wall that they should
be put from foundation according maps.
For prevent the water loss the construction joints should be full from water proof
materials like bitumen or other materials.
The stone wall should be constructed from mountainous and hard stone.
The construction company can to change the stone masonry wall plastering with wall
pointing, a surface of the wall that isnt touch with water.
The construction works should be completed 100% with this volume of works
schedule and dont pay any cost for intractable extra works more them the offer work
volumes.
All volume of works is with their performance and should be have high quality.
During of the project work must not cut any tree, without governmental approval.
After the technical survey of the project, if the floods change the project damage the
site form and contracted project, maps and design dont match with site of the project
which was served technically before, the contractor company engineer is responsible to
9/22/2014
arrange the design and maps according to the site with consultation of ACTED
Engineer and taking of approval of related governmental department.
5.
6.
7.
8.
9.
10.
9/22/2014
11. For separations of the soil layer from concert layer plastic sheet should be use.
12. The shuttering should be checked before concrete pouring. (The shuttering planks
thickness should be at least 2.5cm and two sides of the planks should be smooth and
clean in order to prevent from concrete falling.
13. For providing from concrete bending should be use wooden timber in suitable
distances.
14. The shuttering surface should be in same level.
15. The concert should be use during one hour.
Plastering:
1.
2.
3.
4.
5.
6.
9/22/2014
7. Providing Indifference Contractor Company that use dirty sand, dont mix mortar well,
dont keep wet and seems slit or cracks, all less quantity works should be demolish
and they should be worked again.
8. Pointing works should be swell and beauty.
Carpentry works:
1. In the shuttering dont use from wooden boards more than 3 time.
2. The board that use for shuttering should has 2cm thickness and its surface should be
Sundry works:
1. Based on works volume this project should be completed 100% within 6months after the
signing of the contract.
2. For the normal progress of construction works and accurate supervision of the project the
contractor is responsible to employ a civil engineer to be present in the field till completion of
the project.
3. The project work will be implemented according to ACTED engineering department plan in
case of not progressing of the work according to plan the contractor will pay cash penalty
according to contract.
4. The contractor is responsible to provide work safety condition and all the labors should wear
hat, shoe, glasses and labor uniform as well as the labor shirt should be designed by companys
arm.
5. The respectable contractor is responsible to price each construction item in offer form
according to local market without benefit and clarify the benefit at the end of the offer both in
percentage and currency and add it in total price.
6. In case of forgetting any issue the respectable contractor can add it at end of the page and give
its prices in attached table.
9/22/2014