You are on page 1of 10

MGE UPS SYSTEMS Ltd.

Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12

21 CN PROJECT
METRO NODE UPS SOLUTION
MGE Galaxy 3000 2 x 10 Kva UPS System
In line with the BT UPS Metro / Core Node UPS solution, we have pleasure in submitting our offer for the UPS
systems and associated work detailed in accordance with the BT contract number 658480. Based on the power
requirement details we have allowed for 2 x 10Kva UPS units operating in an N+N redundant system. Our offer
includes for an I/O Panel with castell interlock. Integral to the I/O panel are 2 x 4Way TP&N PDU fitted with 12 x
16 Amp MCBs all wired to terminals at the top of the of the panel at 32 Amps. The assumption is that the
maximum system load will be 8Kw (0.8Pf.). We have included for a 8Kw battery with each UPS having a battery
autonomy of 30Mins , 10 year design life to BS6290 Pt4. Our proposal includes for the following:

GALAXY 3000

Four Power ratings: 10 15 20 30 kVA


Three phase input and output
Parallel connection of up to four UPS.
On-line Double conversion (VFI).
Automatic and manual by-pass (built-in).
Power factor corrected rectifier.
Sealed or vented batteries.
Advanced communication options XML-web
(HTTP).

Galaxy 3000 implements a clean, high performance


IGBT rectifier/charger offering without any further
filtering:

Clean input current (THDi <3%)


High power factor >0.99
Total compatibility with engine generator sets
A reduction in electrical consumption

the Merlin Gerin Know How


Page 1 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12
2 x 10 kVA 30 Min (8kw) MGE Unitary Parallel 3000 UPS System
2 x 10 kVA, Galaxy 3000 UPS Module
2 x 8Kw, 30min battery 10 year design life- installed in matching battery cubicles
2 x Battery circuit breaker
1 x Floor mounted UPS input / output panel including intergral 2 x PDUS, 4 Way TPN
each fitted with 12 x 16Amp HRC MCBs wired to 32Amp terminals at the top of the
PDU.
2 x Battery build up on site (during normal working hours)
2 x DC Cable installation during normal working hours (Max 5m)
2 x AC Cable installation between UPS and I/O Panel (Max 5m)
1 x Plinths for UPS / battery cabinets, I/O Panel (500mm void , 40mm tile depth). Any
tile cutting and re-fitting is to be by others.
1 x Standard BT commissioning, 2 separate visit including load bank test

1 x Delivery to site and offloading and positioning (during normal working hours),
budget cost subject to a full site survey
1 x On site training for 6 BT personnel, to take place during load bank commissioning
1 x 5 Year Service Contract providing a 4 hour response for the 2 x 10Kva Installation
as per BT contract (Ref 658480), including yearly load bank/ battery impedance testing

Equipment Dimensions
QTY
2
2
1

ITEM
10 KVA UPS cabinet
Battery Cabinet
Floor standing UPS I/O Panel
inc PDUs

Unit height
Mm
1420
1600
2185

Unit depth
Mm
565
685
630

Unit width
Mm
655
850
1390

Weight
Kgs
210
450
350

OTHER USEFUL INFORMATION

All tile cutting and replacing is to be by others. Any plinths supplied will have adjustable feet
Please allow 550mm at the rear of the UPS
UPS are all bottom entry
The I/O Panel requires 2 x 63 three phase and neutral supplies.
I/O Panel has both top and bottom connection.
I/O Panel does not require rear access.
Max heat load from both UPSs running at max load will be no greater that 2KW.
Battery cabinet floor loading is approx 7.9Kn/m^2. UPS and I/O panel have reduced floor load figures compared to the
battery cabinet.
Lead time is currently 3-4 weeks from receipt of order
Installation time on site will be approx 1 week (depending on site conditions). A further 3 days once AC supply if
connected to the UPSs must be allowed for battery recharge. At the end of this period final commissioning including load
bank testing will be completed. This will take 1 day.
the Merlin Gerin Know How
Page 2 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12
Proposal to comprise the following:-

General Description
The project requirement based on the load requirement details is for, 2 (two) three phase input / three phase
output UPS system rated at 10kVA for 30 minutes. MGE will offer its well proven Galaxy 3000 range, rated at
20kVA (power factor 0.8 lagging). The Galaxy PW UPS modules are designed for either unitary operation or can
be connected in parallel with another module to provide a fully redundant (N+N) parallel UPS system. This UPS is
a double conversion true on-line UPS as set out in IEC 62040-3 and EN 50091-3 standard for UPS topology.
All commissioning and testing of the UPS installation has been costed based on standard BT Commissioning
including load bank hire, attendance is to be during normal working hours.
2 off

MGE Galaxy 3000 - 10kVA UPS module

3 phase input 3 phase output, high efficiency double conversion (true on-line) static UPS systems, incorporating
rectifier / temperature compensated charger with walk-in circuit, IGBT inverter with PWM, automatic static bypass
switch, manual maintenance bypass switches and input / output isolating switches and built in harmonic filtration.
UPS Ratings:
Input Mains 1
Input Mains 2
Output:
Heat loss
Cable Connection:
Colour:
Standard Communication:

2 off

10kVA at a power factor of 0.8 lagging


400V 3 Phase, 50Hz, ( 17 Amps Battery Recharge)
400V 3 Phase & N , 50Hz ( 15Amps)
400V 3 Phase & N, 50Hz, (15 Amps)
Aprox 1.1 Kw at full load including filter losses
Bottom Entry
Light grey / white (RAL 9002)
Volt free contacts as standard see compliance statement
EPO facility as standard

MGE battery protection circuit breaker (BCB)

Battery protection circuit breaker fitted within the UPS cubicle


2 off

SECI Card Agent

To provide Volt Free connectivity to the BT PEMP Alarm network which is running . Alarm cable installation, final
connection and testing is to be by others.
2 off

10kva, 30 minute end of life, sealed lead acid type stationary battery system.

Mounted internally within a matching battery cubicle. As per the BT specification the battery has been designed to
give full autonomy at the end of the 5 year warranty period. The battery system is supplied with all necessary interbattery connections and insulators. BCB will be mounted internally within the Battery cubicle
Battery type:

VRLA sealed Lead Acid with design life of 10-years BS 6290 part 4 1997.
the Merlin Gerin Know How
Page 3 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12

1 off
One -

UPS Input / Output Panel, including external Wrap around bypass.


single section floor standing UPS Input/Output Panel to BSEN 60439-1
Form 4 Type 2 and fitted with:1 63amp triple pole and neutral link switch isolator (Rectifier Supply
Main Isolator)
2 63amp triple pole and neutral link fuse switch complete with 32amp
HRC fuses (UPS 1 & 2 Rectifier Supply)
1 63amp triple pole and neutral link switch isolator (Mains Switch for
Bypass Supply)
2 63amp triple pole and neutral link fuse switch complete with 32amp
HRC fuses (UPS 1 & 2 Bypass Supply)
1 63amp four pole switch isolator complete with Castell lock and KSS
switch (Overall Maintenance Bypass)
2 63amp four pole 2-position and off changeover switch (UPS 1 and UPS 2
System Output/Loadbank)
2 63amp triple pole and neutral link fuse switches complete with 32amp
HRC fuses (PDU 1 and PDU 2)
2 4way triple pole and neutral link MCB Board each fitted with 12-16amp single
pole Type C MCBs wired to 32amp terminals
Each MCB Board will also be fitted with 1-multi function meter
and 3-indicator lamps
Paint finish:
RAL 7032
A main earth bar and screw fixed engraved labels are included
Dimensions 2185mm high x 1390mm wide x 630mm deep

The Panel has been quoted as a single section. Should there be a site that requires
the Panel to be delivered in two sections, then this will mean an extra cost, for re connecting
and testing.
1 off

Set of Steel Plinths (Optional)

Set of steel plinths for 2 X UPS, 2 x Battery Cabinets, 1 X I/O Panel . Plinths to be 500mm to the top of the tile with
a tile locator designed for a 40mm tile. The plinths will be complete with adjustable feet. Please note that the tile
locator should not be used as a load support. Floor depth and tile thickness are to be confirmed before ordering,
all tile cutting and installation is to be by others.
2 off

AC cable installation

MGE will install AC cable between the UPS and I/O panel, this is based on the cable run being under the raised
floor with a max cable length of 5m. This includes for suitable containment if required. MGE has not included for
the supplies to the I/O panel from the main LV panel or for any distribution supplies from the I/O panel to the
equipment racks.
the Merlin Gerin Know How
Page 4 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12
2 off

DC Power cabling and control cabling

MGE will install all DC power cabling and control cabling between the battery system, battery isolators and the
battery circuit breaker to the UPS system, assuming a maximum of a 5 metre cable run
1 off

Delivery to site

The nett service includes delivery to site of the complete UPS system including battery.
1 off

Offloading and Positioning


Offloading and positioning on the above equipment is assuming one visit to site with easy access without
obstruction, on a normal working weekday during normal working hours.
Cost will depend on the access
The price will be based on a single visit provided the site is ready for installation.

1 off

Commissioning / start-up services


MGE will provide commissioning by our own fully trained engineers when the system is fully installed and
ready to work. Price is based on specification as set out in the BT Planning and Maintenance Guidance
For UPS Systems document PWR/ACS/D010.
The commissioning includes the following works:

Provision of method statement


Load bank testing
Visual checks
Cable installation checks
Setting and programming of the UPS system (off load)
Operational checks
Where available the load will be transferred onto the UPS

The fixed price will include the cost of travel and expenses for a standard commissioning on a normal working day
during normal working hours. Outside these hours costs will be chargeable at our current rate
1 off

Site Services
MGE will provide the following site services in connection with the supply, delivery, installation and testing
of the UPS system.

Attendance at periodic site meetings if required


Assistance with project implementation
Dedicated project manager.
Supervision of delivery, off-loading and positioning of UPS and battery systems

the Merlin Gerin Know How


Page 5 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12
1 off.

Maintenance Manuals and Record Drawings


Following completion of the installation, testing and commissioning, MGE will provide copies of all
drawings, manuals and test results in a mutually agreed format.

1 off

MGE SystemSure BT Maintenance Contract to cover 2 x 10Kva Unitary UPS Installation


MGE can offer the following 5 year service contract in line with BT Specification to cover

All parts used

All labour & travel for call-out and maintenance visits

Guaranteed 4 hour response time to site in the event of an emergency call-out which covers 24hrs a
day, 365 days a year.

Annual UPS Maintenance visit, attendance during normal working hours i.e. Monday to Friday 9am 5pm, excluding public holidays.

Annual battery maintenance visit during including impedance or AC Load bank test- to be carried out
during normal working hours

Access to 24 helpline managed by senior engineers / managers

1 off UPS Training


On site training for up to a maximum of 6 BT personnel to a first line standard on the installed equipment. All
training will be carried out by a fully qualified MGE Engineer. Certification will be issued to the attendees on
completion of the course.

We trust that this quotation meets with your approval. Should you require any further information please do not
hesitate to contact the undersigned.
Yours faithfully
MGE UPS SYSTEMS LTD
Richard Irwin
Mobile Tel 0788 4475192
Richard.irwin@mgeups.com

the Merlin Gerin Know How


Page 6 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12

Terms and Conditions


Offer is made in line with the agreed Terms and Conditions between MGE UPS Systems and BT as set out in
Term Contract 658480.
Price Structure
The prices quoted are nett :

Exclude all VAT and taxes.


Include delivery, off-loading and positioning as detailed
Excludes all cabling unless specified within our quotation
Excludes all switchgear except for battery circuit breakers (BCBs) unless stated above.
BT Alarm connection and testing is to be by others

All prices are quoted in Pounds Sterling (GBP) and remain valid for 30 days from date of quotation.
Payment Terms:
All prices to be quoted are nett/nett. Payment for 100% of the invoiced value will be required within 42 days of
date of invoice (Standard BT Terms) . No retention will be acceptable on the purchase of these goods and services
Despatch (Ex-works)
Our despatch time for this equipment is currently: 3-4 working weeks from order being received. A firm delivery
date will be confirmed on acceptance of order.
Defects liability
The product defects liability will be as per the agreed BT 5 Year warranty from date of installation subject to a
warranty / maintenance agreement being taken at time of order. This warranty may be void should the
maintenance regime not be adhered to.
Validity
Unless withdrawn previously this quotation is open for acceptance within 30 days form today's date.
Scope of Works
This quotation is based on supply of goods and cabling as specified. Any additional works or costs arising due to
delays on site that are not the result of MGE will be chargeable as appropriate.
Conditions:
This quotation is submitted in line with MGE UPS Systems Ltd Terms and conditions of Sale unless otherwise
modified below. (E.& O.E.)

the Merlin Gerin Know How


Page 7 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12

Galaxy 3000 Technical Specification


Standard features

Options

on-line double conversion and PFC rectifier

J-BUS/MOD-BUS, SNMP, AS400, U-Talk/ASCII, USB,

Battery monitoring and intermittent-recharge system

SHUT/HID communications cards

Colour graphical display

MultiSlot communications expansion module

Relay communications card

Solution-Pac and Management-Pac software packages

ECO mode

backfeed protection

Choice of four colours

Integrated long backup-time battery charger

Automatic and maintenance bypasses

isolation transformer

Enhanced EMC (level B)

General characteristics
Rated power (kVA)
Active power (kW)
Normal AC input

10

15

20

30

12

16

24

2.1

power factor = 0,8

1.5

Heat loss
rated voltage

380 - 400 - 415 V 3-phase

voltage range

250 V minimum to 440 V maximum (1)

frequency

50 / 60 Hz

frequency range

47 63 Hz

power factor

> 0,99

current distortion

< 3 % (2)

Voltage

380 - 400 - 415 V +/- 10%, 3-phase + neutral

frequency

50 / 60 Hz +/- 8%

voltage (steady state)

380 - 400 - 415 V +/- 1%, 3-phase + neutral

Bypass AC input

Output
frequency

50 ou 60 Hz +/-1%

synchronization range

adjustable from 0,25 Hz to 4 Hz

voltage transients

+/- 3% for 0 to 100% and 100 to 0% load step changes

voltage distortion

THDU < 2% ph-ph and ph-n for linear loads


THDU < 3% ph-ph and ph-n for non-linear loads

crest factor

up to 3:1

permissible overload

120% for 1,5 min; 150% for 1 second

double-conversion mode

up to 90%

ECO mode

up to 97%

Colour

RAL 9002 or metallised grey, blue or green

storage temperature range

-10 to +45C

Efficiency

Environment

ambient temperature

0 to 40C, 20 to 25C recommended, 0 to 30C continuous

noise level (dBA)

< 50

degree of protection

IP 215 as defined by IEC 529

< 50

< 53

< 53

the Merlin Gerin Know How


Page 8 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12
Standards
construction and safety

IEC 62040-1, IEC 60950, EN 50091-1

design and manufacture

ISO 9001, ISO 14001, IEC 60146

performance and topology

IEC 62040-3, EN 50091-3

EMC

IEC 62040-2, EN 50091-2 level B, EN 55011/022 level B

Immunity

IEC 61000-4-2/3/4/5

harmonic disturbances

IEC 61000-3-2/4

Certification

TV, CE

(1): 323 to 440 V at Pn; (2): for source THDU <2%; (3): backup time for linear loads with power factor = 0,8 / for standardised non-linear load.

Galaxy 3000 dimensions and weights


Kva
Rated power

Electrical Charecteristics
Rated power (kVA)
Active power (kW)
Normal AC input

Normal AC input current


Charge A C input current
Bypass Input Current
Output Current

10

15

20

width (mm)

655

670

height (mm)

1420

1600

depth (mm)

565

weight (kg)

330

30

685
380

470

570

10

15

20

30

power factor = 0,8

12

16

24

@ 400v

16

23

30

45

@ 400v

20

27

31

46

@ 400v

15

22

29

44

@ 400v

15

22

29

44

the Merlin Gerin Know How


Page 9 of 10

MGE UPS SYSTEMS Ltd.


Orion House
171-177 High Street
Wealdstone
HARROW
HA3 5EA
Tel: 0 20 88 61 40 40
Fax 0 20 88 61 28 12
For Your Notes:

the Merlin Gerin Know How


Page 10 of 10

You might also like