PROJECT PROPOSAL
I.
PROGRAM TITLE
:
:
:
:
:
OFW
Magnitude
Magnitude
Proportion
Labor Force
5272
OFW
121
2.30%
Household
4099
OFC (Household)
118
2.88%
Population
19101
OFC Members
711
3.72%
Although many OFWs were successful in rearing their families towards a decent family living,
some have failed due to financial mismanagement and cases of maltreatment. They finally
decided to settle in the country though gripped with uncertainties on how to reintegrate with
the community and how to aptly raise the family.
With the foregoing, the municipal government through its Municipal Poverty Reduction Action
Team has identified Reintegration Program for OFWs of the National Reintegration Center for
OFWs (NRCO) of the DOLE through the Livelihood Development Assistance Program as one of
its Bottom-up Budgeting Projects. Also included in the target beneficiaries are the OFW Family
Circles (OFCs).
III. OBJECTIVES
In general, it has the objective of reintegrating returning OFWs in the community and assists
OFW Family Circles (OFCs) in a livelihood intervention to improve their economic well-being.
Specifically, its objective is to provide livelihood goods and/or materials to beneficiaries as
inputs in their livelihood undertakings.
Time Frame
Expected Output
Concerned
Agency
December, 2015
PESO Bato
Verification
of
the
submitted
Project
Proposal and Fund
allocation from the
National Reintegration
Center
for
OFWs
(NCRO)
Identification
of
beneficiaries
and
Profiling
of
beneficiaries
January, 2016
DOLE-NCRO
/
PESO Bato / OK
sa Bato
January, 2016
Beneficiaries identified
and profiled by the PESO
through CBMS with the
assistance of OFW at
Kapamilya sa Bato
PESO Bato / OK
sa Bato
January, 2016
DOLE-NCRO
Conduct of Small
Business Management
Training & Financial
Awareness Seminar
and
Preparation of
Individual Business Plan
2nd week of
February, 2016
Business management
training and financial
awareness seminar
conducted; Individual
Business Pan prepared
DOLE-NCRO
PESO Bato
OK sa Bato
Preparation of
supporting documents
3rd week of
February, 2016
PESO-Bato
Preparation
submission of
Proposal
and
Project
summary of profile of
target beneficiaries,
summary of tools and
equipment, work and
financial plan and
canvass sheet.
VIII.
Submission of
supporting documents
to the NCRO
January 2016
PESO-Bato
March, 2016
DOLE-NCRO
Procurement Process
BAC, LGU-Bato
Awarding Livelihood
Development
Assistance Program
goods and/or materials
June, 2016
DOLE-NCRO
PESO-Bato
Liquidation of Fund
July, 2016
Fund liquidated
DOLE-NCRO
PESO-Bato
Monitoring and
Evaluation
Project implementation
monitored and evaluated
DOLE-NCRO
PESO-Bato
BUDGETARY REQUIREMENTS:
No. of project beneficiaries
50
P 500,000.00
As part of the marketing plan, product or service description shall be clearly identified as to its
uniqueness compared to other existing livelihood undertakings. It shall also include target
market or customers. Accessibility to major material requirements and the skills needed for the
Project shall also be given consideration. Marketing Plan shall also include pricing scheme or
strategy. In cases the product is high compared to competitors, corresponding advantages of
the product must be carefully explained to customers.
Production Plan shall be carefully identified. It shall include steps on how a livelihood
undertaking will operate and who are the persons involved in business operation. Personnel
must be clearly identified in an Organizational Plan. It must state their corresponding role and
duties in business operation and the salaries they shall be receiving each and every paying
period.
Sales and revenue forecast must also be considered in the business plan preparation to allow
comparison and assessment on the monthly or annual operation of a business.