Final project Structural design and test of wing

Project mode: Group 4 members


Each group will design, build, and test a structural configuration for a wing construction. The goal is to design, analyze, build and test
a wing structure that will carry the heaviest load, have the minimum weight possible while meeting given specifications and predicted
behavior from analysis. All wing structures will be gradually loaded until they fail.
Specifications:
1. Structure construction: Semi-monocoque3
2. Structural elements to be used: ribs, spars, stringers, and/or skin
3. Materials of construction: free4
4. Wing geometry:
Airfoil:
MAC
AR
Taper ratio
Twist angle
Dihedral angle

NACA
0.16
5.0
1.0
0
0

2424
m

5. Flight level
h 0 m

3
4

Selected section can be single/multi cell


Materials and material properties related to the analysis must be used in the analysis and included in the final report

Projects
AE Structural design

6. Design speed
V 100 km/h
7. The construction must be accompanied by a documented report of design, analysis, and construction.
8. Supports and loading configuration are depicted in Fig. 15.
9. Grading will be based on the maximum loading to weight ratio (Lmax/W) (20%), accuracy of reported results (25%), project
report (40%), and delivery (15%) as presented in table 1.1.
Table 1.1. Evaluation parameters
Grade
Parameter

Lmax
W

Lmax
W

0.9 to 0.99

0.8 to 0.89

0.7 to 0.79

0.1 to 0.69

95 to 100%

90 to 94.99%

85 to 89.99%

80 to 84.99%

> 79.99%

Documentation is
well written and the
project is well
explained, it meets
all of the
specifications

Documentation or
project lacks of fair
in writing or
explanation, it
meets most of the
specifications

Documentation
and project lacks of
a fair explanation,
it meets most of the
specifications

Documentation
and project lacks of
a fair explanation,
it meets some of
the specifications

Documentation
poorly written and
the project is not
well explained

max

(20%)
Accuracy of analytical
and experimental results
(25%)
Project report (40%)
- Front page
- Index
- Introduction
- Materials
- Procedure
- Results
- Conclusions
5

10

Loading will be done using an angle of attack = 0

Projects
AE Structural design

References

Report delivery (15%)

Delivery was on
time

Delivery was 0 - 6
hours overdue

Delivery was 6 - 12
hours overdue

Delivery was 12 18 hours overdue

Delivery was 18 24 hours overdue6

Penalties:
1. Dimensions: Length/chord tolerance of +/- 4mm, and thickness tolerance of+/-2 mm are allowed; 0.5 points in final grade will
be deducted due to tolerance violations.
2. Loading to weight ratio: Values less than n = 4.4 will be automatically graded 0 (zero).

100

10

150

100

150

Figure 1: Wing loading schematic, Dimensions in mm