Professional Documents
Culture Documents
ITEM 2.1
2.1.1
COFFERDAM
GENERAL
2.1.1.1
DESCRIPTION
To ensure that all areas are free from the disturbance that the water will
cause to the constructions, this item shall contain but not limited to the
following works:
a. Excavation required for the construction of the weir
b. Disposal of the excavated material
c. Backfilling around the weir structure to the original ground level or as
required by the plans
d. Works to make sure that all areas are free from water at all times during
construction such as pumping and dewatering
e. Sheet piling (if necessary)
f. Construction and removal of temporary structures such as cofferdam,
pipes, canals and ditches.
g. Diversion of existing waterways
The Contractor shall submit to the Engineer a comprehensive plan and
construction methodology on how he proposes to achieve this task. This
shall include all the materials, labor, equipment, tools, pumping units, etc.
2.1.2
EXECUTION
MEASUREMENT/BASIS OF PAYMENT
ITEM 2.2
2.2.1
2.2.1.1
DESCRIPTION
The Work under this item includes providing all labor, materials, tools and
equipment necessary for clearing, grubbing, removing and disposing of all
vegetation and debris (including earthen materials incidentally removed
with vegetation and debris), and removing structures and obstructions
located within the limits shown on the plans or designated by the Engineer,
except such objects as are designated to remain in place or are to be
removed in accordance with other sections of these Specifications. The
Work shall also include the preservation from injury or defacement of all
vegetation and objects designated to remain
2.2.2
EXECUTION
2.2.2.1
CLEARING
Clearing shall consist of removing shrubs, and brush and disposal of all
debris including rubbish occurring within areas to be cleared. Stumps,
roots, brush, and other vegetation in the areas to be cleared shall be cut off
below the original ground surface.
2.2.2.2
HAND CLEARING
Bushes or trees shown on the Plans for removal and relocation shall be
removed and relocated as directed by the Engineer. Bushes and trees
designated for removal and relocation shall be carefully removed with
enough of the root wad kept intact to ensure the survival of the bush or tree
in its new locations. Bushes and trees designated for removal and
relocation that are damaged, or that do not survive as a result of the
transplanting, shall be replaced by the Contractor at its expense. The
relocated bush or tree shall be placed to original depth at a location as
directed by the Engineer.
2.2.2.5
GRUBBING
Grubbing shall consist of removal and disposal of stumps, roots larger than
seventy five (75) millimeters in diameter and matted roots from designated
grubbing areas. Logs and other organic or metallic debris and abandoned
concrete footings shall be removed.
2.2.2.6
STRIPPING
PRODUCTS
2.2.3.1
STORAGE PILES
Topsoil that is suitable for reuse shall be placed in storage piles convenient
to areas that are to receive application of topsoil. Topsoil shall be kept
separate from the other excavated materials and shall be free of roots,
stones larger than five (5) centimeters and other undesirable materials that
would interfere with the planting.
2.2.4
MEASUREMENT/BASIS OF PAYMENT
The area that is to be cleared and grubbed to be paid for will be the number of
square meter measure on the ground or site of the weir acceptably cleared in
conformity with the plans or as directed by the Engineer.
The accepted quantities, measured as prescribed above shall be paid for at the
contract unit price for each of the particular pay items listed and included in
the Bill of Quantities. The payment shall constitute full compensation for the
removal and disposal of cleared and grubbed materials including all labor,
equipment tools and incidentals necessary to complete the work prescribed in
this item.
ITEM 2.3
2.3.1
EARTH EXCAVATION
GENERAL
The excavation will generally refer to open excavation of foundation wet or dry
and in all sorts of soils.
2.3.1.1
DESCRIPTION
This item shall consist of the necessary excavation for foundations and
other structures indicated in the Plans, in accordance to these
specifications and in conformity with the lines, grades and dimensions
shown in the Drawings as indicated and established by the Engineer. The
Contractor shall be aware of obstructions such as pipes, conduits and
cables in the areas to be excavated. The Contractor shall verify the
existence and location of such obstructions before the start of excavation.
All excavated materials shall be disposed properly and deposited at
locations indicated by the Engineer.
2.3.1.2
NATURE of EXCAVATION:
2.3.1.2.1
Unclassified Excavation Unclassified excavation shall consist of
the excavation and disposal of all materials regardless of its nature, or
not classified and included in the Bill of Quantities under other pay
items.
EXECUTION
SHORING
Materials suitable and useful for back filling, plinth filling or levelling of
the plot or other use shall be stacked in convenient places but not in such
a way as to obstruct free movement of men, animals and vehicles or
encroach on the area required for constructional purposes.
2.3.2.3
BACKFILLING
All shoring and form work shall be removed after their necessity ceases
and trash of any sorts shall be cleaned out from the excavation. All space
between foundation masonry or concrete and sides of excavation shall be
refilled to the original surface with approved excavated materials in layers
fifteen (15) centimeter in thickness watered and rammed. The filling shall
be done after concrete or masonry is fully set and done in such a way as
not to cause undue thrust on any part of the structure. Where suitable
excavated materials is to be used for refilling it shall be brought from the
place where it is temporarily stacked and used in refilling.
No excavation of foundations shall be filled in or covered up until all
measurements of excavations, masonry concrete and other works below
ground level are jointly recorded. Black cotton soil shall not be used for
back filling or in plinth filling.
2.3.2.4
DEWATERING
MEASUREMENT/BASIS OF PAYMENT
The volume of excavation to be paid for will be the number of cubic meter
measure in the original position of material acceptably excavated in conformity
with the plans or as directed by the Engineer.
The accepted quantities, measured as prescribed above shall be paid for the
contract unit price for each of the particular pay items listed and included in
the Bill of Quantities. The payment shall constitute full compensation for the
removal and disposal of excavated materials including all labor, equipment
tools and incidentals necessary to complete the work prescribed in this item.
ITEM 2.4
2.4.1
ROCK EXCAVATION
GENERAL
2.4.1.1
DESCRIPTION
This item shall consist of the necessary rock excavation for foundations
and other structures indicated in the Plans, in accordance to these
specifications and in conformity with the lines, grades and dimensions
shown in the plans of as indicated and established by the Engineer. The
Contractor shall be aware of obstructions such as pipes, conduits and
cables in the areas to be excavated. The Contractor shall verify the
existence and location of such obstructions before the start of excavation.
All excavated materials shall be disposed properly and deposited at
locations indicated by the Engineer.
2.4.1.2
Nature of Excavation:
EXECUTION
BLASTING
2.4.2.3
EXCAVATION LIMITS
MEASUREMENT/METHOD OF PAYMENT
The volume of excavation to be paid for will be the number of cubic meter
measure in the original position of material acceptably excavated in
conformity with the plans or as directed by the Engineer.
The accepted quantities, measured as prescribed above shall be paid for
the contract unit price for each of the particular pay items listed and
included in the Bill of Quantities. The payment shall constitute full
compensation for the removal and disposal of excavated materials
including all labor, equipment tools and incidentals necessary to complete
the work prescribed in this item.
ITEM 2.5
2.5.1
HAULING OF MATERIALS
GENERAL
2.5.1.1
DESCRIPTION
EXECUTION
MEASUREMENT/BASIS OF PAYMENT
ITEM 2.6
2.6.1
2.6.1.1
DESCRIPTION
This work shall consist of the installation of rock dowels at the locations
and orientations designated in the Plans or by the Engineer.
The
Contractor shall select and construct the dowels and supply all materials,
equipment, and labor to test and install the dowels. The Engineer will
designate the orientation and minimum length of the dowel required.
2.6.2
SUBMITTALS
Not less than two weeks prior to commencing the rock doweling, the Contractor
shall submit in writing to the Engineer for approval:
The Contractor shall provide written evidence that the foreman and drill
operator have performed satisfactory work in similar capacities elsewhere. The
drill operator assisted by the foreman shall have installed rock dowels as
indicated in the Plan.
The Contractor shall submit a detailed plan for the rock doweling to include:
a. The proposed construction sequence and schedule.
b. The proposed drilling method and equipment.
c. The proposed drill hole diameter.
d. The proposed cement grout mix design
e. The proposed construction method for upwardly inclined anchors.
f. The proposed corrosion protection for the rock dowel system.
g. The calibration data for each load cell, test jack, pressure gauge and
master pressure gauge to be used in the proof testing.
h. The proposed stressing procedures and stressing equipment to proof test
the dowels.
Work shall not begin until the Engineer has approved the appropriate
submittals in writing.
2.6.3
MATERIAL REQUIREMENTS
EXECUTION
Work shall proceed according to the plan and schedule submitted by the
Contractor prior to the commencement of the work.
The Engineer shall specify the location, orientation, and minimum length of
each rock dowel. The rock dowel shall be installed within five degrees of the
specified angle. Unless otherwise specified, the angle of installation shall be
perpendicular to the rock face and inclined slightly downward. If the axis of
the rock dowel is not close to perpendicular to the rock face or within the angle
provided by the beveled washer, or the rock beneath the bearing plate is not
sound, a bearing pad approved by the Engineer shall be constructed at no
additional cost, so that the rock dowel is not bent when tensioned. In all
cases, at least three quarters of the bearing plate shall be in contact with the
rock face.
The dowels shall be handled and stored in such a manner as to avoid damage
or corrosion of the coating and the steel. Damage to the dowel steel as a result
of abrasion, cuts, nicks, welds, and weld splatter will be cause for rejection.
The dowels shall be protected from dirt, rust, and harmful substances. If
heavy corrosion or pitting is noted, the Engineer will reject the rock dowel.
The entire length of the rock dowel shall be encapsulated in cement grout for a
second level of corrosion protection. All exposed parts of the dowel, bearing
plate and nut on the surface shall be painted with approved corrosion
protection paint or epoxy patching compound.
The use of hand drills for advancing the anchor hole is not allowed without
written permission by the Engineer and demonstrated effectiveness by the
Contractor.
The drill hole shall be sized to provide a minimum of 50 millimeter of grout
cover around the bar. The Contractor shall flush the drill hole of all drill
cuttings and debris with compressed air prior to the installation of the rock
dowel. Holes drilled for rock dowels in which dowel installation is considered
by the Engineer to be impractical shall be re-drilled at the Contractors
expense.
The grout equipment shall produce a grout free of lumps and undispersed
cement. The pump shall be equipped with a pressure gauge near the discharge
end to monitor grout pressures. The grouting equipment shall be sized to
enable the grout to be pumped in one continuous operation. The grout shall
be injected from the lowest point of the drill hole. The quantity of the grout
and the grout pressures shall be recorded.
When the cement grout has reached final set, the Contractor shall install the
bearing plate, washers and nut. The end of the completed rock dowel shall be
trimmed to within 15 centimeters of the rock face.
At the discretion of the Engineer, up to 5 percent, but not less than three rock
dowels, of the installed rock dowels shall be proof tested. The Contractor shall
conduct the proof test, and the Engineer will interpret the results. The rock
dowel shall be tensioned to 11, 500 kilograms with a calibrated hollow-ram
hydraulic jack using a bar extension and coupler attached to the rock dowel
and held for 10 minutes. If no loss of load occurs over this time period, the
rock dowel is acceptable. The Engineer may require additional proof of testing
beyond the 5 percent maximum, if rock dowels fail the proof testing. All failed
rock dowels shall be replaced with an additional rock dowel installed in a
separate hole. No payment will be made for rock dowels that fail or for
additional proof testing.
2.6.5
MEASUREMENT/BASIS OF PAYMENT
Rock dowels will be measured per linear meter of rock dowel installed and
accepted.
The accepted quantity shall be paid for at the contract unit price and payment
shall be full compensation for furnishing and placing all materials, including
all labor, equipment, tools and incidentals necessary to complete the work
prescribed in this item.
ITEM 2.7
2.7.1
STONE MASONRY
GENERAL
2.7.1.1
DESCRIPTION
MATERIAL REQUIREMENTS
2.7.2.1
STONE
The stone shall be clean, hard and durable and shall be subjected to the
Engineers approval. Adobe stone shall not be used unless otherwise
specified.
Sizes and Shaped. Unless other sizes are shown on the plans, stones shall
have a thickness of not less than one and one half times their respective
thickness, and lengths of not less than one and one half times their
respective widths.
Dressing. The stone shall be dressed to remove any thin or weak portions.
Face stones shall be dressed to provide bed and joint lines that do not vary
more than twenty (20) millimeters from corners of the stones in excess
thirty (30) millimeters in radius. Bed surfaces of the face stones shall be
approximately normal to the face of the stones for about eighty (80)
millimeters and from this point may depart from a normal plane not to
exceed fifty (50) millimeters in three hundred (300) millimeters.
Finish for exposed Faces Face stones shall be pitched to line along the
beds and joints. The maximum projection of rock faces beyond the pitch
lines shall not be more than fifty (50) meters.
2.7.2.2
MORTAR
EXECUTION
2.7.3.1
Suitable equipment shall be provided for setting stones larger than those
that can be handled by two men. The rolling or turning of stones on the
walls will not be permitted. If a stone is loosened after the mortar has
taken initial set, it shall be removed, the mortar cleaned off, and the stone
is loosened after the mortar has taken initial set, it shall be removed, the
mortar cleaned off, and the stone re laid with fresh mortar.
2.7.3.2
CURING
If hot or dry weather, the masonry shall be satisfactory protected from the
sun and shall be kept wet for a period of at least three days after
completion.
2.7.4
MEASUREMENT/BASIS OF PAYMENT
The quantity to be paid for shall be the number of cubic meters of stone
masonry complete in place and accepted. Projections extending beyond the
faces of the walls shall not be included. In computing the quantity for payment,
the dimension used shall be those shown on the plans or ordered in writing by
the Engineer. No deductions shall be made for weep holes drain pipes or other
openings of less than one square meter in area.
The quantity of masonry, determined as provided, shall be paid for at the
contract unit price per cubic meter for stone masonry, which price and
payment shall be full compensation for furnishing and placing all materials,
including mortar for masonry, for all necessary excavation, and for all labor,
equipment, tools and incidentals necessary to complete the item.
ITEM 2.8
2.8.1
2.8.1.1
DESCRIPTION
SUBMITTALS
A copy of list of all reinforcing steel and bending diagrams shall be furnished to
the Engineer at the site of the work at least one week before the placing of
reinforcing steel is begun.
The Contractor shall be responsible for the accuracy of the lists and for
furnishing and placing all reinforcing steel in accordance with the details
shown on the plans.
2.8.3
MATERIAL REQUIREMENTS
Unless otherwise designated on the plans, or herein, all reinforcing steel shall
conform to the requirements of the following specifications:
Table 2.8.3: STEEL SPECIFICATION
ASTM A 615
AASHTO M 31
ASTM A 496
AASHTO M 225
ASTM A 185
AASHTO M 55
ASTM A 82
AASHTO M 32
ASTM A 184
AASHTO M 54
ASTM A 497
AASHTO M 221
Type A
AASHTO M 254
ASTM A 206
Bar reinforcement for concrete structures, except No. 2 bars shall be deformed
in accordance with AASHTO M 42, M31 and M53.
Dowel and tie bars shall conform to the requirements of AASHTO M31 or
AASHTO M42 except that rail steel should not be used for tie bars that are to
be bent and re-straightened during construction. Tie bars shall be free from
burring of other deformation restricting slippage in the concrete. A minimum of
one half ( 2
the length of each dowel bar shall be painted with one coat of
approved lead of tar paint before delivery to the site of the work.
The sleeves for dowel bars shall be metal of an approved design to cover fifty
(50) millimeters (2 inches), plus or minus six and three tenths (6.3) millimeters
of the dowel, with a closed end, and with suitable stop to hold the end of the
sleeve at least twenty five (25) millimeters (1 inch) from the end of the dowel
bar. Sleeves shall be of such design that they do not collapse during
construction.
Plastic coated dowel bar conforming to AASHTO M 254 may be used.
2.8.4
EXECUTION
2.8.4.1
ORDER LIST
Before materials are ordered, all order lists and bending diagrams shall be
furnished by the Contractor, for approval of the Engineer. The approval or
order lists and bending diagrams by the Engineer shall in no way relieve
the Contractor of responsibility for the correctness of such lists and
diagrams. Any expenses incident to the revisions of materials furnished
with the plans shall be borne by the Contractor.
Bar lists and bending diagrams for structures, which are included on the
Plans, do not have to be furnished by Contractor. When bar lists and
bending diagrams are included on the Plans, they are intended for
estimating approximate quantities. Contractor shall verify the quantity,
size, and shape of the bar reinforcement against those shown on the Plans
and make any necessary corrections before ordering.
2.8.4.2
PROTECTION OF MATERIALS
Steel reinforcement shall be stored above the surface of the ground upon
platforms, skids, or other supports and shall be protected as far as
practicable from mechanical injury and surface deterioration caused by
exposure to conditions producing rust. When placed in the work
reinforcement shall be free from dirt, detrimental rust, loose scale, paint,
grease, oil or other foreign materials. Reinforcement shall be free from
injuries effects such as cracks and laminations. Rust, surface scars,
surface irregularities of mill scale will not be caused for rejection, provided
the minimum dimensions are demonstrated.
2.8.4.3
BENDING
All reinforcing bars shall be bent cold except as shown on the Plans or as
permitted by the Engineer. Bars shall not be bent or straightened in a
manner that will cause damage to the bars. Irregularities in the bars shall
be caused for the rejection. Bars shall be bent around a circular pin having
the following diameter (db) in relation to the diameter of the bar (d):
Nominal Diameter (d), mm
10 to 20
6d
25 - 28
8d
32 and greater
10d
Bends and hooks in stirrups or ties may be bent to the diameter of the
principal bar enclosed therein.
2.8.4.4
The reinforcing bars shall be free from dirt, loose mill scale, paint, oil,
loose rust, or other foreign substance.
Steel reinforcement shall be accurately placed in the positions shown on
the plans or as required by the Engineer and firmly held at all intersection
during the placing and setting of concrete except where spacing is less
than three hundred (300) millimeters in each direction, in which case,
alternate intersections shall be tied. Ties shall be fastened on the inside.
Distance from the forms shall be maintained by means of stays, blocks,
ties, hangers, or other approved supports, so that it does not vary from the
position indicated on the plans by more than six (6) millimeters. Blocks for
holding reinforcement from contact with the forms shall be precast mortar
blocks of approved shapes and dimensions. Layers of bars shall be
separated by precast mortar blocks or by other equally suitable devices.
The use of pebbles, pieces of broken stone or brick, metal pipe and wooden
blocks shall not be permitted. Unless otherwise shown in the plans or
required by the Engineer, the minimum distance between bars shall be
forty (40) millimeters. Reinforcement in any member shall be placed and
concrete begins. Concrete placed in violation of this provision may be
rejected and removal may be required. If fabric reinforcement is shipped in
SPLICING
Grade 40 Min.
Lap
Grade 60 Min.
Lap
Tension
24 bar diam.
36 bar diam.
300 mm
Compression
20 bar diam.
24 bar diam.
300 mm
In lapped splices, the bars shall be placed in contact and wired together.
Lapped splices will not be permitted at locations where the concrete
sections is sufficient to provide minimum clear distance of one and one
third the maximum size of coarse aggregate between the splice and the
nearest adjacent bar. Welding of reinforcing steel shall be done only if
detailed on the plans or if authorized by the Engineer in writing. Spiral
reinforcement shall be spliced by lapping at least one and a half turns or
by butt welding unless otherwise shown on the plans.
2.8.4.6
WELDING OF SPLICES
MEASUREMENT/BASIS OF PAYMENT
The quantity of reinforcing steel to be paid for will be the final quantity placed
and accepted in the completed structure.
No allowance will be made for tie-wires, separators, wire and other materials
used in fastening the reinforcing steel in place. If bars are substituted upon the
ITEM 2.9
2.9.1
This item specifies the requirements for the design, construction and removal
of formwork required to produce the finished concrete to the shape, lines and
dimensions shown on the Plans.
2.9.1.1
DESCRIPTION
MATERIAL REQUIREMENTS
The type and condition of formwork sheeting and lining, and the ability of the
formwork and its supports to withstand distortion caused by the placement
and compaction of the concrete, and the standard of workmanship used in the
formwork construction shall be such that the finished surfaces of the concrete
will conform to the requirements of the specifications and Plans.
Form lumber shall be stress graded or merchantable and shall be of non
staining species and dressed on concrete forming side if to be used for exposed
EXECUTION
2.9.3.1
FORMWORK DESIGN
FORM CONSTRUCTION
REMOVAL OF FORMS
Clear span less than three (3) meters seven (7) days
Clear span three (3) meters to six (6) meters fourteen (14)
Clear span over six (6) meters twenty one (21) days.
days
b.
Slabs
-
columns,
control
joints,
grooves
and
all
Shoring
All trenches and other excavations shall be properly sheeted and
braced, to furnish working conditions acceptable to the Engineer.
Bracing shall be so arranged as not to place any strains on portions of
completed work until the general construction has proceeded far
enough to provide ample strength in the opinion of the Engineer.
2.9.4
MEASUREMENT/BASIS OF PAYMENT
The quantities measured as arranged above shall be paid for at the contract
unit price of the pay item that is contained within the Bill of Quantities.
Payment shall be the reimbursement for all materials, labor, equipment, tools,
and incidentals necessary to complete the work prescribed in this item.
ITEM 2.10
2.10.1 GENERAL
Concrete shall be composed of Portland cement, fine aggregate, coarse
aggregate, water and admixtures as specified for the work except as otherwise
authorized in writing by the Engineer. Ready mix concrete shall be permitted,
provided it can be placed within the time requirements specified and complies
with all of the provisions hereinafter specified.
2.10.1.1 DESCRIPTION
This item shall consist of furnishing, placing, and finishing concrete in
concrete/ reinforced concrete structures in accordance with this
specification and conforming to the lines, grades, and dimension shown on
the plans.
a.
b.
c.
2.10.2 SUBMITTALS
Samples of constituent materials and of concrete as placed shall be subjected
to laboratory tests. The Contractor shall submit samples of materials as
directed by the Engineer for his approval and all materials incorporated shall
conform to the approved samples. The Contractor shall design the concrete
mixes for all classes of concrete as will be define in this specification and
submit his proposal together with the test results of the strength of all classes
of the concrete mix design for the approval of the Engineer. The design of the
concrete mixes and the concrete strength test shall be made in the field
SPECIFICATION
Portland Cement
Masonry Cement
FINE AGGREGATES
mass percent of
millimeters (No.
percent each of
not be allowed
Sieve Size
9.5 mm (
3
8
Percent Passing
in )
100
4.75 mm ( No. 4 )
95 100
1.18 mm ( No. 16 )
45 80
0.30 mm ( No. 50 )
5 30
0 10
2.10.3.2.2
COURSE AGGREGATES
DESIGNATION
MASS
PERCENT
PASSING
STANDARD
mm
ALTERNATE
U.S. Standard
GRADING
A
GRADING
B
GRADING
C
75.0
3 in
100
63.0
2 in
90 100
100
100
50.0
2 in
90 100
95 100
37.5
1 in
25 60
35 75
25.0
1 in
0 15
35 70
19.0
in
0 10
12.5
in
05
05
10 30
4.75
No. 4
05
2.10.3.2.3
AGGREGATE TESTS
No aggregate shall be used until advice has been received that it has
satisfactory passed all tests to the satisfaction of the Engineer, at
which time written approval shall be given for its use.
In stating requirements for most materials, reference has been made
to AASHTO and ASTM Standard Specification for material. Those
Specifications, in turn, include reference to the respective AASHTO
and ASTM methods of sampling and testing. In such instances the
following methods of sampling and testing will govern:
TEST METHOD
2.10.3.2.4
SPECIFICATION
AASHTO T 11
AASHTO T 19
AASHTO T 27
Resistance to Abrasion of
Small Size Coarse
Aggregate by Use of the Los
Angeles Machine
AASHTO T 96
Soundness of Aggregate by
Use of Sodium Sulfate of
Magnesium Sulfate
AASHTO T 104
WATER
METAL REINFORCEMENT
(ASTM A 615)
AASHTO M 31
ASTM A 616
ASTM A 617
ASTM 187
(ASTM A 82)
AASHTO M 32
(ASTM A 185)
(ASTM A 185)
AASHTO M 55
RUBBER SEAL
ADMIXTURES
SPECIFIED
COMPRESSIVE
STRENGTH AT
28 DAYS, Fc
(PSI)
2500
0.642
0.554
3000
0.576
0.465
3500
0.510
0.399
4000
0.443
0.354
2.10.4.3
CONSISTENCY
BATCHING
When batches are hauled to the mixer, bulk cement shall be transported
either in waterproof compartments or between the fine and course
aggregates. When cement is placed in contact with moist aggregates,
batches will be rejected unless mixed within one half () hours of such
contact. Sacked cement may be transported on top of the aggregates.
Batches shall be delivered to the mixer separate and intact. Each batch
shall be dumped cleanly into the mixer without loss, and, when more
than one batch is carried on the truck, without spilling of material from
one batch into another.
2.10.4.8
2.10.4.9.1
CURING CONCRETE
The Contractor shall protect all concrete work against injury from
outside elements and defacement of any nature during construction
operations. All concrete, particularly exposed surfaces shall be treated
immediately after concreting or cement finishing is completed, and
shall be provided with continuous moist curing for at least seven (7)
days regardless of the ambient air temperature. Walls and vertical
surfaces may be covered with continuously saturated burlap or by
other approved means. Horizontal surfaces, slabs, and other items
shall be inundated with pool of water to a depth of one and 2 tenths
(1.2) centimeter and kept continuously wet with the use of sprinklers.
Finished surfaces and slabs shall be protected from the direct rays of
the sunlight to prevent shrinking and cracking.
The curing method shall be one or more of the following:
a. Water Method The concrete shall be kept continuously wet by the
application of water for a minimum period of seven (7) days after
the concrete has been placed.
b. Curing Compound Surfaces exposed to the air may be cured by
the application of an impervious membrane approved by the
Engineer.
c. Waterproof Membrane Method The exposed finished surfaces of
concrete shall be sprayed with water, using a nozzle that so
atomizes the flow that a mist and not a spray are formed until the
concrete has set, after which a curing membrane of waterproof
paper or plastic sheeting shall be placed.
d. Forms-in-Place Method Formed surfaces of concrete may be cured
by retaining the form in place. The forms shall remain in place for a
minimum period of seven (7) days after the concrete has been
placed, except that for members over fifty (50) centimeters in least
dimension, the forms shall remain in place for a minimum period
of five (5) days.
e. Curing Cast-in-Site Concrete All newly placed concrete cast-in
into the structures shall be cured by the water method, the formsin-place method, or as permitted herein, by the curing compound
method.
f. Curing Pre-Cast Concrete Piles All newly placed concrete for precast concrete piles, conventionally reinforced or pre-stressed shall
be cured by the Water Method as described in subsection Curing
Concrete, except that the concrete shall be kept under moisture for
at least fourteen (14) days. All the option of the Contractor, steam
curing maybe used in which case the steam curing provisions of
DPWH SS subsection 407.3.8 (6) curing pre-cast concrete shall
apply except that the concrete shall be kept wet for at least seven
(7) days including the holding and steaming period.
2.10.4.9
ACCEPTANCE OF CONCRETE
2.10.4.9.1
STRENGTH OF CONCRETE
SLUMP
MEASUREMENT/BASIS OF PAYMENT
The quality of concrete to be paid shall be the quality shown in the Bill of
Quantity unless charges in design are made in which case the quality shown
in the Bill of Quantity will be adjusted by the amount of the change for the
purpose of payment. No deduction will be made for the volume occupied by
pipes less than one hundred one (101) millimeters or four (4) inches in
diameter or for reinforcing steel, anchors, weep holes or expansion materials.
The accepted qualities of structural concrete completed in place will be paid
for at the contract unit price for cubic meter as indicated in the Bill of
Quantities.
Pay Item and Description
Unit of Measurement
Structural Concrete
Cubic Meter
Such prices and payment shall be full compensation for furnishing all
materials, including metal water stops, joints, joint filers, weep holes, and
rock backing and timber bumpers; for all form and false work; for mixing,
placing, furnishing, and curing and concrete; and for all labor, materials,
equipment, tools, and incidentals necessary to complete the item, except that
reinforcing steel shall be paid for at the contract unit price per kilograms for
reinforcing steel metal pipes and drains, metal conduits and ducts, and metal
expansion angles shall be paid for as structural steel that when the proposal
does not include an item for structural steel these miscellaneous metal parts
shall be paid for as reinforcing steel.
ITEM 2.11
2.11.1
2.11.1.1
DESCRIPTION
This item includes the supply, furnishing and installation of stainless steel
intake and flushing gates.
2.11.2
CONTRACTORS SCOPE
The Contractors scope for this work item shall be the following:
a. The Contractor shall supply, install, test and commission a fully operational
weir intake, desander intake, desander flushing, head ponds drain gates as
reflected in the Plans are in accordance with the provisions of these
Specifications or as instructed by the Engineer.
b. The Contractor shall construct the framing of the Inlet Portal gate slots and
other related steel works and concrete embedded works.
2.11.3
RELATED STANDARD
MATERIAL REQUIREMENTS
The gates shall be made of A36 steel. All materials shall be new and shall be
meet the required ultimate strength, limit of elasticity, ductility, hardness,
durability, suitability for the intended service and best engineering practice.
All materials shall comply with the latest applicable standard of ASTM unless
otherwise specified or approved by the Engineer.
The lifting mechanism of the intake and flushing gates shall be supplied and
installed by approved supplier.
Gate lifting mechanism shall consist of a steel-bodied and steel-mounted
gate with steel faced wedges and wedge blocks. Side wedges shall be
adjustable. Top and bottom wedges shall withstand seating and unseating
heads.
Frames shall be circular or rectangular flanged frames to connect with wall
thimbles and provide for openings of the shape and dimensions specified.
Each extension stem shall be the same material and the same size as the
stem of the gate it operates. Brackets and stem guides shall be made of steel
and fully adjustable. The guide block shall be bushed where it contacts the
extension stem.
The gate should be capable of withstanding the seating, unseating, and
operating heads. A seating head and an unseating head equal to the
difference between the top of levee elevation and the closed gate elevation
should be used in design. All components should be adequate to withstand all
stresses encountered during installation or operation without breakage or
deleterious deformation.
Each gate should meet leakage requirements of the AWWA. AWWA
specifications maintain that leakage under seating head should not exceed
one tenths (0.1) gallons per minute per foot of perimeter. Under the design
unseating heads, leakage should not exceed two tenths (0.2) gallons per
a.
ASTM A 123 for plain and fabricated material, and assembled products.
b.
2.11.4 EXECUTION
2.11.4.1
TESTING
After installation the Contractor shall test each gate for satisfactory
operation and water tightness against maximum operating pressure
insofar as practicable. If an electric or hydraulic operator is used, limit
switches shall be adjusted following the manufacturers instructions.
A field leakage test shall be perform by the Contractor after installation of
the gates. The manufacturer shall be notified of the test so as to allow
sufficient time to enable a representative of the manufacturer to be
present at the test site. After all adjustments have been made and the
mechanism properly lubricated, each gate slide shall be operated through
one complete cycle as a final check on proper operation before starting the
leakage test.
2.11.5
MEASUREMENT/BASIS OF PAYMENT
ITEM 2.12
ITEM 2.13
2.13.1 GENERAL
2.13.1.1
DESCRIPTION
This item shall cover supply, fabrication and installation of metal railings
and other steel works as shown on the Plans including labor, materials,
equipment and tools necessary to complete the works.
2.13.2 MATERIAL REQUIREMENTS
The structural adequacy of the metal stair design is the responsibility of the
designer or professional of record.
a. Railing assembly shall withstand a minimum concentrated load of two
hundred (200) pounds or ninety and seven tenths (90.7) kilogram applied
vertically downward or horizontally in any direction, but not
simultaneously, at any point on the top rail.
Codes may vary in method of application and magnitude of load.
Governing code should be checked for specific requirements. Most codes
require a two hundred (200) pound minimum concentrated load applied in
any direction at any point on the top rail.
b. Railing assembly shall withstand a minimum uniform load of fifty (50)
pounds per foot or two hundred ninety eight (298) kilograms per meter
applied horizontally or vertically downward, but not simultaneously, on the
top rail.
Some codes have requirements for uniform loading on the top rails. Most
codes require a fifty (50) pounds per foot minimum uniform load. Uniform
loads are not to be applied concurrently with concentrated loads.
c. Guard intermediate rails, balusters, panel fillers, posts or cables shall be
designed for a uniform load of not less than fifty (50) pounds per square
foot applied horizontally over the gross area of the guard of which they are
part. Reactions due to this loading need not be added to the loading
specified for the main supporting members of the guard.
d. Railing frame components and cable hardware shall be designed to
withstand loads encountered without excessive deflection or distortion
when cables are tensioned to conform to building code requirements.
2.13.2.1
Materials shall be delivered on the job site in good condition and properly
protected against damage to finished surfaces.
Materials shall be stored in a location and in a manner to avoid damage and
in a clean, dry location away from uncured concrete and masonry. Stacking
shall be done in a way, which will prevent bending. Cover with waterproof
2.13.3 EXECUTION
2.13.3.1
PREPARATION
INSTALLATION
RECTIFICATION OF DAMAGES
Remove stained or otherwise defective work and replace with material that
meets specification requirements.
In case of damaged finish and defective components, the contractor in all
instances will have to make good the necessary repairs at his own expense
and as directed by the Engineer.
2.13.4 MEASUREMENT/BASIS OF PAYMENT
The quantities measured as arranged above shall be paid for at the contract
unit price of the pay item that is contained within the Bill of Quantities.
Payment shall be the reimbursement for all materials, labor, equipment,
tools, and incidentals necessary to complete the work prescribed in this item.
ITEM 2.14
2.14.1 GENERAL
2.14.1.1
SCOPE
This item includes all materials, labor, equipment and performance of all
operations necessary to complete all plastering works for both interior and
exterior surfaces of masonry and concrete indicated on Plans and
specifications herein. It shall serve as a guide for the minimum
requirements for the system and application of Portland cement plaster.
2.14.2 MATERIAL REQUIREMENTS
Where products and or systems are specified they shall be installed in
accordance with the Building Code and/or manufacturers requirements.
Do not proceed with lathing or plastering until all products or finish samples
are approved unless permitted by the Engineer.
Cement and water shall conform to the specification indicated in the item
Concreting Works somewhere in this specification.
Materials shall be delivered in their original bags with labels intact and
legible.
Storage and protection of all materials are the responsibility of the
Contractor.
2.14.2.1
a. Cold Weather
- Do not use frozen material.
- Do not mix materials or apply cement plaster when ambient
temperature is less than thirty (35) degrees Fahrenheit or one and six
tenths (1.6) degrees Centigrade.
b. Hot Weather
- Protect cement plaster from uneven and excessive evaporation during
hot, windy, and dry weather.
- Moist curing after each coat of cement plaster with water if ambient
temperature is more than seventy five (75) degrees or twenty four (24)
degrees Centigrade. Moist cure for forty eight (48) hours after
application of coats.
- Hot, or dry, or windy weather the cement plaster should be moistened
down and then covered with a single sheet of polyethylene plastic.
- Moist curing is required at the start and end of work day.
- For humidity higher than seventy five (75) percent, moist curing is not
required.
2.14.2.2
GENERAL MIX
Withhold ten (10) mixing of water until mixing is almost complete then add
as needed to produce necessary consistency. Keep water to a minimum.
2.14.3 EXECUTION
a. Cement Plaster Directly Over a Concrete Surface
- Concrete surface must be clean of dust, loose particles, oil, and other
foreign matter which would affect a bond of cement plaster to concrete.
- Apply a liquid bonding agent to concrete surface per manufacturers
standards.
- Test bond of cement plaster to concrete surface.
- Cement plaster must be applied with sufficient force (by hand or machine)
to develop full adhesion between plaster and the substrate.
- Cement plaster base coat must be rodded off to a true flat plane. Even and
level with screeds. Follow this by wood floating the surface. Fill all voids and
dress surface for acrylic finish.
All items to be attached so that they are level, plumb and true, and create a
proper screed and depth for the cement plaster. Attach building paper, lath,
and accessories per standards and code.
2.14.4 MEASUREMENT/BASIS OF PAYMENT
The quantities measured as arranged above shall be paid for at the contract
unit price of the pay item that is contained within the Bill of Quantities.
Payment shall be the reimbursement for all materials, labor, equipment,
tools, and incidentals necessary to complete the work prescribed in this item.