You are on page 1of 28

PROJECT

: PROJECT MASS RAPID TRANSIT LEMBAH KELANG : JAJARAN SUNGAI B


PACKAGE V8 : CONSTRUCTION AND COMPLETION OF VIADUCT GUIDE
ASSOCIATED WORKS FROM TAMAN MESRA TO KAJANG STATION

CONTRACT

: MRTCORP/KVMRT-SBK/ELE/V8/139

CONTRACTOR

: UEM CONSTRUCTION SDN BHD

VARIATION ORDER : VO No: 10382/VO/V8/034


DESCRIPTION
ITEM

: RELOCATION OF TM WORKS FROM PIER P893 TO P929

DESCRIPTION

UNIT

Relocation of TM Works from


Pier P893to P929
1

Addition

: refer attachment

Sum

Addition

: refer attachment

Sum

LANG : JAJARAN SUNGAI BULOH - KAJANG


ETION OF VIADUCT GUIDEWAY AND OTHER
TO KAJANG STATION

3 TO P929
QTY

RATE

AMOUNT

355,602.77
299,515.00

56,087.77

REMARK

314,771.57
299,515.00

PROJECT

: PROJECT MASS RAPID TRANSIT LEMBAH KELANG : JAJARAN SUNGAI BU


PACKAGE V8 : CONSTRUCTION AND COMPLETION OF VIADUCT GUIDEW
ASSOCIATED WORKS FROM TAMAN MESRA TO KAJANG STATION

CONTRACT

: MRTCORP/KVMRT-SBK/ELE/V8/139

CONTRACTOR

: UEM CONSTRUCTION SDN BHD

VALUATION OF VARIATION ORDER NO. 10377/VO/V8/034

RELOCATIONOF TM WORKS FROM PIER TO P929


TO EXECUTE RELOCATION OF TM WOTKS FROM PIER P893 TO P929 ALL IN ACCORDANCE WI
AUTHORITY APPROVED SHOP DRAWING
ITEM

DESCRIPTION
Ducts
Supplying , laying and jointing of the followig cables
ducts by open trech excavation including all excavation
works, backfilling with sand and compacted 150mm
layers on top; complete with all necessary concrete
encasement, blinding, bedding, haunching and surround
all necessary breaking up existing pavement, road cutting
etc disposal of surplus excavated material and reinstatment
of surfaces
2 way 100mm diameter PVC Duct 'class B'
Supplying, laying and jointing of the following HDPE (PN10)
ducts by Horizontal Direct Drilling method including
provision, assembly and removal on completion of all plant
equipment, resources and temporary works complete
with nylon draw rope, excavation of pit, backfilling,
disposal of surplus materials, breaking up existing pavement
and reinstatement of surface
2 ways 100mm diameter HDPE (PN10) ducts
Supplying, laying and jointing of the following sub ducts
through main ducts
3 Nos x 40mm diameter corrugated HDPE sub ducts
Cables

Supplying, installing and jointing of the following overhead


cables including cable joints and cable termination
Overhead cable; 10pairs/0.5
Overhead cable; 20pairs/0.5
Overhead cable; 50pairs/0.5
Fibre optic cable 1 x 4C
Supplying, laying and jointing of the following cables
through ducts including cable joints and cable termination
Jelly filled cable; 1 x 50 pairs/0.5
Jelly filler cable; 1 x 100 pairs/0.5
Manholes
Standard telecommunication manholes construted
complete with and including all excavation concrete,
brickwork, rendering, reinforcement, formwork, heavy duty
ductile cover and frame, internal fitting, hooks ladder and
mild steel ladder, iron anchor, cable bearers, end caps
post markers, backfilling and disposal of surplus
excavated materials
Standard manhole type JC9C; depth to invert not exceeding
1.5m
Standard manhole type JB30

KELANG : JAJARAN SUNGAI BULOH - KAJANG


PLETION OF VIADUCT GUIDEWAY AND OTHER
A TO KAJANG STATION

P929 ALL IN ACCORDANCE WITH THE

BQ REF

UNIT

QTY

RATE

AMOUNT

180

168.00

30,240.00

6A. 1/2 Add 1A

174

201.40

35,043.60

6A. 1/2+1 Add 1A

354

19.81

7,012.74

tatment

New Rate

pavement

New Rate
6A. 1/3 Add 1A
6A. 1/3 Add 1B
New Rate

m
m
m
m

345
95
269
237

21.60
22.52
30.29
18.00

7,452.00
2,139.40
8,148.01
4,266.00

New Rate
New Rate

m
m

630
100

41.52
83.04

26,157.60
8,304.00

6A. 1/5 Add 1A

nr

4,177.98

8,355.96

New Rate

nr

3,000.00

12,000.00

vy duty

149,119.31

Worst Scenario

25,704.00

35,043.60

7,012.74

6,334.20
2,139.40
8,148.01
3,626.10

22,233.96
7,058.40

8,355.96
10,200.00

135,856.37

PROJECT

: PROJECT MASS RAPID TRANSIT LEMBAH KELANG : JAJARAN SUNGAI


PACKAGE V8 : CONSTRUCTION AND COMPLETION OF VIADUCT GUID
ASSOCIATED WORKS FROM TAMAN MESRA TO KAJANG STATION

CONTRACT

: MRTCORP/KVMRT-SBK/ELE/V8/139

CONTRACTOR

: UEM CONSTRUCTION SDN BHD

VALUATION OF VARIATION ORDER NO. 10377/VO/V8/034

RELOCATIONOF TM WORKS FROM PIER TO P929


TO EXECUTE RELOCATION OF TM WOTKS FROM PIER P893 TO P929 ALL IN ACCORDANCE
AUTHORITY APPROVED SHOP DRAWING
ITEM

DESCRIPTION
Telecom Poles
Supply and install telecom poles complete with pipes/
ducts, connector, grip, stay wore and fixing accessories
to existing telecom pole including necessary footing,
excavation, backfilling and disposal of surplus excavated
materials
Standard telecom poles
Supply and install 2.00m GI riser complete with pipes/
ducts connector, gripm stay wire and fixing accessories
to existing telecom poles including necessary footing,
excavation, backfilling, and disposal of surplus excavated
materials
100mm diameter GI riser
Connection to existing cables
Connection of the following overhead cables to existing
including paying all connection fees and liasing with
authorities
Overhead cable; 10 pairs/0.5
Overhead cable; 20 pairs/0.5
Overhead cable; 50 pairs/0.5
Fibre Optic cables; 1 x 4C
Connection of the following underground cables to
existing including paying all connection fees and liasing
with authorities, location of existing cables, all necessary
excavation work, backfilling with approved material and

compaction, breaking up existing pavement road cutting


etc and reinstatement of surface (Connection measured
per joint)
Jelly filled cable; 1 x 50 pairs/0.5
Jelly filled cable; 1 x 100 pairs/0.5
Removal of existing cables amd associated works
Dismantling, disconnecting and removal of the
following existing overhead cables including recording,
stacking and labeling of recovery of the same: complete
witl all necessary work, etc and reinstatement of surfaces
returning and delivery of recovery to Authorities
Drop wire
Overhead
Overhead
Overhead
Overhead

cable;
cable;
cable;
cable;

20 pairs/0.5
30 pairs/0.5
50 pairs/0.5
200 pairs/0.5

AH KELANG : JAJARAN SUNGAI BULOH - KAJANG


OMPLETION OF VIADUCT GUIDEWAY AND OTHER
ESRA TO KAJANG STATION

TO P929 ALL IN ACCORDANCE WITH THE

BQ REF

UNIT

QTY

RATE

AMOUNT

nr

11

756.23

8,318.53

6A. 1/6 Add. 1A

nr

132.40

397.20

New Rate
6A. 1/6 Add. 1C
6A. 1/6 Add. 1D
11. 1/12 Add. 1D

nr
nr
nr
nr

2
2
2
2

124.20
236.31
378.17
627.39

248.40
472.62
756.34
1,254.78

xcavated

6A. 1/5 Add. 1E

xcavated

ecessary

New Rate
New Rate

nr
nr

6
2

m
m
m
m
m

3597
613
135
735
200

897.00
1,794.00

5,382.00
3,588.00

36.00
13.20
108.00
22.00
32.00

129,492.00
8,091.60
14,580.00
16,170.00
6,400.00

surfaces

New Rate
6A. 1/8 Add. 1K
New Rate
6A. 1/8 Add. 1L
6A. 1/8 Add. 1M

195,151.47

Worst Scenario

8,318.53

397.20

211.14
472.62
756.34
1,254.78

3,049.80

110,068.20
8,091.60
12,393.00
16,170.00
6,400.00

167,583.21

PROJECT

: PROJECT MASS RAPID TRANSIT LEMBAH KELANG : JAJARAN SUNGAI


PACKAGE V8 : CONSTRUCTION AND COMPLETION OF VIADUCT GUID
ASSOCIATED WORKS FROM TAMAN MESRA TO KAJANG STATION

CONTRACT

: MRTCORP/KVMRT-SBK/ELE/V8/139

CONTRACTOR

: UEM CONSTRUCTION SDN BHD

VALUATION OF VARIATION ORDER NO. 10377/VO/V8/034

RELOCATIONOF TM WORKS FROM PIER TO P929


TO EXECUTE RELOCATION OF TM WOTKS FROM PIER P893 TO P929 ALL IN ACCORDANCE WI
AUTHORITY APPROVED SHOP DRAWING
ITEM

DESCRIPTION

BQ REF

Dismantling , disconnecting and removal of the


following existing Telecom cables and its
associated work services including cable ducts
pipes, manhole and the like; including carefully
exposed, get out, recording, stacking and
labeling of recovery of the same; complete with
all necessary excavation work to any depth,
breaking up exisitng pavement, road cutting, etc
and reinstatement of surfaces; returning delivery
of recovery
Standard Telecom Poles

6A. 1/11 Add. 1A

: JAJARAN SUNGAI BULOH - KAJANG


N OF VIADUCT GUIDEWAY AND OTHER
AJANG STATION

N ACCORDANCE WITH THE

UNIT

QTY

nr

41

RATE

276.39

AMOUNT

11,331.99

Worst Scenario

11,331.99

11,331.99

11,331.99

PROJECT

: PROJECT MASS RAPID TRANSIT LEMBAH KELANG : JAJARAN SUNGAI BUL


PACKAGE V8 : CONSTRUCTION AND COMPLETION OF VIADUCT GUIDEWA
ASSOCIATED WORKS FROM TAMAN MESRA TO KAJANG STATION

SUB-CONTRACT WORKS : CONSTRUCTION< COMPLETION,TESTING AND COMMISIONING OF


RELOCATION (TELECOMUNICATION WORKS)
PMRTLK-JAJARAN SUNGAI BULOH-KAJANG
BILL NO. 6A (TELECOMMUNICATION WORKS)
Jalan Reko Overhead Cable Work (IFC Drawings)
ITEM
DESCRIPTION

BQ REF

TM Services
Jalan Reko Overhead Cable
Ducts
Supplying, laying and jointing of the following
HDPE (PN10) ducts by Horizontal Direct Drilling
method including provision, assembly and
removal on completion of all plant, equipment
resources and temporary works complete with
nylon draw rope, excavation of pit, backfilling,
disposal of surplus materials, breaking up existing
pavement and reinstatement of surfaces
2 ways 100mm diameter HDPE (PN10) ducts

6A. 1/2 Add 1A

Sub Ducts
Supplying, laying and jointing of the following
sub ducts through man ducts
3Nos x 40mm diameter corrugated HDPE sub ducts

6A. 1/2+1 Add. 1A

Cables
Supplying, installing and jointing of the following
overhead cables including cable joint and cable
terminations
Overhead cable; 20 pairs/0.5
Overhead cable; 50 pairs/0.5

6A. 1/3 Add. 1A


6A. 1/3 Add. 1B

Overhead cable; 200 pairs/0.5

6A. 1/3 Add. 1C

Manholes
Standard telecommunication manholes construted
complete with all including all excavation concrete
brickwork,rendering, reinforcement, formwork,
heavy duty ductile, cover and frame, internal
fittings, hooks ladder and mild steel ladder, iron
anchor, cables bearers, end caps, post markers,
backfilling and disposal of surplus excavated
materials
Standard manhole type JC9C; depth to invert not
exceeding1.5m

6A. 1/5 Add. 1A

Telecom poles
Supply and install telecom poles complete with
pipes/ducts, connector,grip, stay wire and fixing
accessories including necessary footing, excavation
backfilling, and disposal of surplus excavated
materials
Standard Telecom Poles

6A. 1/5 Add. 1E

AJARAN SUNGAI BULOH - KAJANG


F VIADUCT GUIDEWAY AND OTHER
NG STATION
COMMISIONING OF UTILITIES

UNIT

OMISSION
QTY
RATE

AMOUNT

Worst Scenario

68

201.40

13,695.20

13,695.20

68

19.81

1,347.08

1,347.08

m
m

1282
1282

22.52
30.29

28,870.64
38,831.78

28,870.64
38,831.78

1282

nr

nr

39

62.26

79,817.32

79,817.32

4,177.98

8,355.96

8,355.96

756.23

29,492.97

29,492.97

200,410.95

200,410.95

st Scenario

PROJECT

: PROJECT MASS RAPID TRANSIT LEMBAH KELANG : JAJARAN SUNGAI BU


PACKAGE V8 : CONSTRUCTION AND COMPLETION OF VIADUCT GUIDEW
ASSOCIATED WORKS FROM TAMAN MESRA TO KAJANG STATION

TION< COMPLETION,TESTING AND COMMISIONING OF UTILITIES


TION (TELECOMUNICATION WORKS)

K-JAJARAN SUNGAI BULOH-KAJANG


6A (TELECOMMUNICATION WORKS)
Overhead Cable Work (IFC Drawings)
ITEM
DESCRIPTION

BQ REF

Connecting of the following overhead cables to


existing including paying all connection fees
and liasing with authorities
8
9
10

Overhead cable; 20 pairs/0.5


Overhead cable; 50 pairs/0.5
Overhead cable; 200 pairs/0.5

6A. 1/6 Add. 1C


6A. 1/6 Add. 1D
6A. 1/6 Add. 1E

Dismantling, disconnecting and removal of the


following existing overhead cables including
recording, stacking and labelling of recovery of
the same; complete with all necessary work, etc
and reinstatement of surfaces; returning and
delivery of recovery to Authorities
11
12
13
14

Overhead cable; 20 pairs/0.5


Overhead cable; 50 pairs/0.5
Overhead cable; 200 pairs/0.5
Standard Telecom Poles

6A.
6A.
6A.
6A.

1/8
1/8
1/8
1/8

Add.
Add.
Add.
Add.

1K
1L
1M
1A

JAJARAN SUNGAI BULOH - KAJANG


OF VIADUCT GUIDEWAY AND OTHER
ANG STATION

UNIT

OMISSION
QTY
RATE

AMOUNT

nr
nr
nr

2
2
2

236.31
378.17
472.74

472.62
756.34
945.48

m
m
m
nr

1282
1282
1282
39

13.20
22.00
32.00
276.39

16,922.40
28,204.00
41,024.00
10,779.21

99,104.05

worst scenario

472.62
756.34
945.48

16,922.40
28,204.00
41,024.00
10,779.21

99,104.05

You might also like