Professional Documents
Culture Documents
CONTRACT
: MRTCORP/KVMRT-SBK/ELE/V8/139
CONTRACTOR
DESCRIPTION
UNIT
Addition
: refer attachment
Sum
Addition
: refer attachment
Sum
3 TO P929
QTY
RATE
AMOUNT
355,602.77
299,515.00
56,087.77
REMARK
314,771.57
299,515.00
PROJECT
CONTRACT
: MRTCORP/KVMRT-SBK/ELE/V8/139
CONTRACTOR
DESCRIPTION
Ducts
Supplying , laying and jointing of the followig cables
ducts by open trech excavation including all excavation
works, backfilling with sand and compacted 150mm
layers on top; complete with all necessary concrete
encasement, blinding, bedding, haunching and surround
all necessary breaking up existing pavement, road cutting
etc disposal of surplus excavated material and reinstatment
of surfaces
2 way 100mm diameter PVC Duct 'class B'
Supplying, laying and jointing of the following HDPE (PN10)
ducts by Horizontal Direct Drilling method including
provision, assembly and removal on completion of all plant
equipment, resources and temporary works complete
with nylon draw rope, excavation of pit, backfilling,
disposal of surplus materials, breaking up existing pavement
and reinstatement of surface
2 ways 100mm diameter HDPE (PN10) ducts
Supplying, laying and jointing of the following sub ducts
through main ducts
3 Nos x 40mm diameter corrugated HDPE sub ducts
Cables
BQ REF
UNIT
QTY
RATE
AMOUNT
180
168.00
30,240.00
174
201.40
35,043.60
354
19.81
7,012.74
tatment
New Rate
pavement
New Rate
6A. 1/3 Add 1A
6A. 1/3 Add 1B
New Rate
m
m
m
m
345
95
269
237
21.60
22.52
30.29
18.00
7,452.00
2,139.40
8,148.01
4,266.00
New Rate
New Rate
m
m
630
100
41.52
83.04
26,157.60
8,304.00
nr
4,177.98
8,355.96
New Rate
nr
3,000.00
12,000.00
vy duty
149,119.31
Worst Scenario
25,704.00
35,043.60
7,012.74
6,334.20
2,139.40
8,148.01
3,626.10
22,233.96
7,058.40
8,355.96
10,200.00
135,856.37
PROJECT
CONTRACT
: MRTCORP/KVMRT-SBK/ELE/V8/139
CONTRACTOR
DESCRIPTION
Telecom Poles
Supply and install telecom poles complete with pipes/
ducts, connector, grip, stay wore and fixing accessories
to existing telecom pole including necessary footing,
excavation, backfilling and disposal of surplus excavated
materials
Standard telecom poles
Supply and install 2.00m GI riser complete with pipes/
ducts connector, gripm stay wire and fixing accessories
to existing telecom poles including necessary footing,
excavation, backfilling, and disposal of surplus excavated
materials
100mm diameter GI riser
Connection to existing cables
Connection of the following overhead cables to existing
including paying all connection fees and liasing with
authorities
Overhead cable; 10 pairs/0.5
Overhead cable; 20 pairs/0.5
Overhead cable; 50 pairs/0.5
Fibre Optic cables; 1 x 4C
Connection of the following underground cables to
existing including paying all connection fees and liasing
with authorities, location of existing cables, all necessary
excavation work, backfilling with approved material and
cable;
cable;
cable;
cable;
20 pairs/0.5
30 pairs/0.5
50 pairs/0.5
200 pairs/0.5
BQ REF
UNIT
QTY
RATE
AMOUNT
nr
11
756.23
8,318.53
nr
132.40
397.20
New Rate
6A. 1/6 Add. 1C
6A. 1/6 Add. 1D
11. 1/12 Add. 1D
nr
nr
nr
nr
2
2
2
2
124.20
236.31
378.17
627.39
248.40
472.62
756.34
1,254.78
xcavated
xcavated
ecessary
New Rate
New Rate
nr
nr
6
2
m
m
m
m
m
3597
613
135
735
200
897.00
1,794.00
5,382.00
3,588.00
36.00
13.20
108.00
22.00
32.00
129,492.00
8,091.60
14,580.00
16,170.00
6,400.00
surfaces
New Rate
6A. 1/8 Add. 1K
New Rate
6A. 1/8 Add. 1L
6A. 1/8 Add. 1M
195,151.47
Worst Scenario
8,318.53
397.20
211.14
472.62
756.34
1,254.78
3,049.80
110,068.20
8,091.60
12,393.00
16,170.00
6,400.00
167,583.21
PROJECT
CONTRACT
: MRTCORP/KVMRT-SBK/ELE/V8/139
CONTRACTOR
DESCRIPTION
BQ REF
UNIT
QTY
nr
41
RATE
276.39
AMOUNT
11,331.99
Worst Scenario
11,331.99
11,331.99
11,331.99
PROJECT
BQ REF
TM Services
Jalan Reko Overhead Cable
Ducts
Supplying, laying and jointing of the following
HDPE (PN10) ducts by Horizontal Direct Drilling
method including provision, assembly and
removal on completion of all plant, equipment
resources and temporary works complete with
nylon draw rope, excavation of pit, backfilling,
disposal of surplus materials, breaking up existing
pavement and reinstatement of surfaces
2 ways 100mm diameter HDPE (PN10) ducts
Sub Ducts
Supplying, laying and jointing of the following
sub ducts through man ducts
3Nos x 40mm diameter corrugated HDPE sub ducts
Cables
Supplying, installing and jointing of the following
overhead cables including cable joint and cable
terminations
Overhead cable; 20 pairs/0.5
Overhead cable; 50 pairs/0.5
Manholes
Standard telecommunication manholes construted
complete with all including all excavation concrete
brickwork,rendering, reinforcement, formwork,
heavy duty ductile, cover and frame, internal
fittings, hooks ladder and mild steel ladder, iron
anchor, cables bearers, end caps, post markers,
backfilling and disposal of surplus excavated
materials
Standard manhole type JC9C; depth to invert not
exceeding1.5m
Telecom poles
Supply and install telecom poles complete with
pipes/ducts, connector,grip, stay wire and fixing
accessories including necessary footing, excavation
backfilling, and disposal of surplus excavated
materials
Standard Telecom Poles
UNIT
OMISSION
QTY
RATE
AMOUNT
Worst Scenario
68
201.40
13,695.20
13,695.20
68
19.81
1,347.08
1,347.08
m
m
1282
1282
22.52
30.29
28,870.64
38,831.78
28,870.64
38,831.78
1282
nr
nr
39
62.26
79,817.32
79,817.32
4,177.98
8,355.96
8,355.96
756.23
29,492.97
29,492.97
200,410.95
200,410.95
st Scenario
PROJECT
BQ REF
6A.
6A.
6A.
6A.
1/8
1/8
1/8
1/8
Add.
Add.
Add.
Add.
1K
1L
1M
1A
UNIT
OMISSION
QTY
RATE
AMOUNT
nr
nr
nr
2
2
2
236.31
378.17
472.74
472.62
756.34
945.48
m
m
m
nr
1282
1282
1282
39
13.20
22.00
32.00
276.39
16,922.40
28,204.00
41,024.00
10,779.21
99,104.05
worst scenario
472.62
756.34
945.48
16,922.40
28,204.00
41,024.00
10,779.21
99,104.05