Professional Documents
Culture Documents
Case is a petition for certoriari, assailing the decision of the Court of Appeals which
affirmed,with modifications, ruling by the RTC granting the complaint for Specific
Performance anddamages filed by Lacap against RP
Dist. Eng. Of Pampanga issued an invitation to bid dated Jan 27, 1992 where Lacap
and twoother contractors were pre-qualified
Being the lowest bidder, Lacap won the bid for concreting of a certain baranggay,
andthereafter undertook the works and purchased materials and labor in connection
with
On Oct 29, 1992, Office of the Dist. Eng conducted final investigation of end product
and fountit 100% completed according to specs. Lacap thereafter sought the
payment of the DPWH
DPWH withheld payment on the grounds that the CoA disapproved final release of
funds dueto Lacaps license as contractor having expired
Dist. Eng sought the opinion of DPWH legal. Legal then responded to Dist. Eng that
theContractors License Law (RA 4566) does not provide that a contract entered into
by acontractor after expiry of license is void and that there is no law that expressly
prohibits or declares void such a contract
DPWH Legal Dept, through Dir III Cesar Mejia, issued First Indorsement on July 20
1994recommending that payment be made to Lacap. Despite such
recommendation, no paymentwas issued
On July 3, 1995, respondent filed the complaint for Specific Performance and
Damagesagainst petitioner before the RTC.14
On September 14, 1995, petitioner, through the Office of the Solicitor General
(OSG), filed aMotion to Dismiss the complaint on the grounds that the complaint
states no cause of actionand that the RTC had no jurisdiction over the nature of the
action since respondent did notappeal to the COA the decision of the District Auditor
to disapprove the claim.
On August 5, 1996, the OSG filed its Answer invoking the defenses of nonexhaustion of administrative remedies and the doctrine of non-suability of the State
Following trial, the RTC rendered on February 19, 1997 a decision ordering DPWH to
payLacap for the contract of the project, 12% interest from demand until fully paid,
and the costs of the suit
upon conviction, be sentenced to pay afine of not less than five hundred pesos but
not more than five thousand pesos.
The "plain meaningrule" or verba legis in statutory construction is that if the statute
is clear, plain and free fromambiguity, it must be given its literal meaning and
applied without interpretation. The wordings of R.A. No. 4566 are clear. It does not
declare, expressly or impliedly, as void contracts entered into bya contractor whose
license had already expired. Nonetheless, such contractor is liable for paymentof
the fine prescribed therein. Thus, respondent should be paid for the projects he
completed. Suchpayment, however, is without prejudice to the payment of the fine
prescribed under the law.