You are on page 1of 79

GOVRRNMENT OF ANDHRA PRADESH

ROADS & BUILDINGS DEPARTMENT

Detailed Cum Abstract Estimate

Name of work : Construction of High Level Bridge @


Km.21/200 of Butchi - Dagadarthi Road in SPS Nellore
District

Estimate Rs.

Circle :

(R&B) Circle Nellore

Division: (R&B) division Kavali


Sub Divisi (R&B) Sub division Kovur
Section:

(R&B) Section Allur

334.00 Lakhs

Name of work : Construction of High Level Bridge @ Km.21/200


of Butchi - Dagadarthi Road

General Abstract

1 Cost of Bridge work

1,80,49,933

2 Construction of approaches

40,69,492

Total:

2,21,19,426

LS Provisions:
3 LS Provision toward VAT a@ 5%

7,75,000

4 LS Provision toward Seigniorage charges

4,55,847

5 LS Provision toward Quality control @ 0.50%


6 LS Provision toward Road Safety interventions
7 LS Provision toward Avagahana Sadassulu

77,500
5,00,000
15,000

8 LS Provision toward Price adjustment

35,00,000

9 LS Provision toward Shifting of utilities

10,00,000

10 LS Provision toward

Widening the existing culvert on


dagadarthi side approaches

10,00,000

11 LS Provision toward Forming diversion road

5,00,000

12 LS Provision toward Guide posts,caustion boards,sign bo

4,00,000

13

LS Provision towards pre survey estimate preperation


of drawings , site plan, estimate, cross section details.

14 LS Provision toward conformatory bores for soil


15 LS Provision toward training works for vagu
13 LS Provision towards Land acquisition

2,00,000
10,00,000
8,00,000
10,00,000

14 LS Provision toward Contingenceis and rounding of

Grand Total:

57,227

3,34,00,000

Assistant Executive Engi


(R&B) Section Allur

Deputy Executive Engineer


(R&B) Sub Division, Kovur

Executive Engineer
(R&B) Division Kavali

DETAILED CUM ABSTRACT ESTIMATE


Name of work : Construction of High Level Bridge in Km.21/200 of Butchi - Dagadarthi Road
Sl
No
1

Description of item

Nos

Measurements
B

Rate
/per

Dismantalling the existing structures like culverts , bridges,


rataining walls and others comprising of masonary cement concrete
wood work steel work, including T&P and scafolding whereever
necessary sorting the dismantled material, disposal of unserviceable
material with a lead of 1000m and all lifts etc complete as per
MORT&H specification No.202.2.4 and as directed by the Engineer in
charge
Pavements
1 X 1
65.000
7.000
0.300
136.50
Cross walls
1 X 6
6.200
0.600
1.000
22.32
Long walls
1 X 2
65.000
0.400
1.000
52.00
210.82
Add for variations
0.180
### 146.00
cum cum
Earthwork excavation in soils upto SDR by mechanical means for
foundations of structures as per drawing and technical specification
including setting out, construction of shoring and bracing, removal of
stumps and other deleterious matter, dressing sides of bottom, back
filling the excavation earth to the extent required etc., complete
including seignioarge charges for finished item of work as per
MoRT&H specification 304(4th Revision) and as directed by the
Engineer-in-Charge
Raft Upto end of wing wall
1 X 1
70.240
10.800
2.700
1 X

65.660

3.000

1.050

206.83

Pucca aprons on D/S

1 X

5.000

1.050

344.72

For Toe walls quadrants

2 X

0.600

0.600

12.87

Toe wall straight portion

65.660
2xx5.68
9
4
6.000

0.600

0.600

8.64

Amount

30,806

###

Pucca aprons on U/S

Deduct portion of toe wall intercepted by raft apron

-1.25
###
380.00
### 24.00
cum cum

add for variations

Qty

72,000

Sand filling in foundation including cost, seignoirage and


conveyence of all materials to site and watering, tamping etc.,
complete for finshed item of work as per MoRT&H specification 304
(4th Revision) and as directed by the Engineer - in - Charge.
Under Raft upto end of wing wa 1 X

70.240

deduct portion intercepted by exg. Foundation

10.800

0.600

###
### 564.00
cum

304382238.xls

cum

2,57,184

Sl
No
4

Measurements
L
B
D
Vibrated cement concrete M 20 Grade Concrete using 40mm ,
20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in
position, Compacting , Vibrating and curing including all other
incidental and all other operational charges of T&P required etc.,
complete
as
including
dewatering
charges
per
MoRT&H
Specification 1500,1700, 2100 (4th Revision) for Raft foundation
Description of item

Lean concrete under Raft

Nos

Qty

1 X

70.240

11.700

0.150

###

Lean concrete under pucca apr 1 X

65.660

3.000

0.150

29.547

Lean concrete under pucca apr 1 X

65.660

5.000

0.150

49.245

Pucca apron U/S

1 X

65.660

3.000

0.300

59.094

Pucca apron D/S

1 X

65.660

5.000

0.300

98.490

Below aproach slab

1 X

4.140

6.600

0.150

4.099

Vibrated cement concrete M 20 Grade Concrete using 40mm ,


20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing, laying in
position,Compacting, Vibrating and curing including all other
incidental and all other operational charges of T&P required etc.,
complete as per MoRT&H Specification 1500,1700, 2200 (4 th Revision)
for Raft
Under abutments piers and win 1 X 1
70.240
11.700
1.500

Rate
/per

Amount

###
###
cum

###
cum

###

###
###
cum

###
cum

###

###
cum

6,45,632

Vibrated cement concrete M 20 Grade Concrete using 40mm ,


20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing, laying in
position,Compacting, Vibrating and curing including all other
incidental and all other operational charges of T&P required etc.,
complete including dewatering charges as per MoRT&H Specification
1500,1700, 2200 (4th Revision) for Sub structure below sill level
Abutment rectangular footings 1 X

10.100

2.900

0.600

Abutment triangular footings

(10.1+11.2) / 2

0.600

(0.60) / 2

2.490

2.600

0.600

--do-- traingular portion

2 X

(3.10+3.70) / 2

0.600

(0.60)/2

Pier Bottom footing

1 X

10.600

2.200

0.300

41.976

Pier top footing

1 X

10.000

1.600

0.300

28.800

1 X

Wing wall Rectangular footings 2

35.148
3.834
15.538
2.450

###
###
cum

304382238.xls

Sl
No
7

Description of item

Nos

Measurements
B

Qty

Amount

Vibrated cement concrete M 20 Grade Concrete using 40mm ,


20mm and 10mm size HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing, laying in
position,Compacting, Vibrating and curing including all other
incidental and all other operational charges of T&P required etc.,
complete as per MoRT&H Specification 1500,1700, 2200 (4 th Revision)
for Sub structure above sill level
Abutment rear traingle
1 X 2 (4.9+7.19) / 2 1.650
4.119
82.167
Abutment rectangle

9.190

0.700

4.119

52.995

Abutment front traingle

4.119

21.850

Wing wall rear traingle

4.119

50.630

--do--

4.140

(0.354) /2 1.270

3.720

Wing wall rectangle

4.140

0.500

5.389

44.621

Wing wall front triangle

4.140

(0.60) /2

5.389

26.770

--do-- --do--

4.119

3.690

Piers straight portion

###

--do-- cut and ease waters

8.400 (0.76+1.0) /2 4.119


(0.76x0.38+1.0x0.
50)
4.119
2x2

(9.19+10.10) / 2 (0.55)

/2

(2.49+4.14) /2
(0.354+1.50) /2

(0.70+0.55) /2
(0.60+0.141) /2

9.750
###
###
sqm

Rate
/per

###
sqm

###

###
cum

1,86,252

Vibrated reinforced cement concrete M 20 grade using 20mm


& 10mm HBG crushed stone aggregate (Coarse aggregate conforming
to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, seigniorage conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing
etc., including other incidental hire and operational charges of all T&P
as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as
per MoRT&H specification
1500,1600,1700 & 2200
(4th
revision ) and as directed by the Engineer-in-Charge Bed blocks and
backing wall
Bed blocks over piers St.portio 1 X 6
8.400
0.900
0.500
22.680
--do--Cut and ease waters

(0.90x0.45) /2

0.500

1.220

--do-- over abutments

8.282

0.750

0.500

6.212

Backing wall over abutments

8.400

0.310

0.350

1.823

--do--

2(9.182-8.4) /2 0.310 (0.65+0.12) 0.373

--do--

32.308
33.000
cum

304382238.xls

Sl
No
9

Measurements
L
B
D
Vibrated reinforced cement concrete M 25 grade using 20mm
& 10mm HBG crushed stone aggregate (Coarse aggregate conforming
to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, seigniorage conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing
etc., including other incidental hire and operational charges of all T&P
etc., complete as per approved drawings and as directed during
execution but excluding cost of steel and its fabrication charges for
finished item as per MoRT&H specification 1500,1600,1700 & 2200
(4th revision ) and as directed by the Engineer-in-Charge for Deck
slab
Description of item

Deck slab over spans


Kerbs over spans
Kerbs over wings

10

11

Nos

1 X
2 X
2 X

7
7
2

8.74
8.74
4.45

Qty

8.400
0.650
###
0.450
0.275
15.142
0.450(0.275-0.12) /21.240
###
say
###
cum

Vibrated reinforced cement concrete M 30 grade using 20mm &


10mm HBG crushed stone aggregate (Coarse aggregate conforming
to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, seigniorage conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing
etc., including all other incidental and operational charges of all T&P
etc., complete for finished item of work as per drawing BD/1-69( A) but
excluding cost of steel and its fabrication charges as per MoRT&H
specification
1500, 1600,1700, & 2702 (4 th Revision) and as
directed by the Engineer-in-Charge for wearing coat over Deck
slab.
1 X 7
8.740
7.500
(0.050+0.12)
Over slabs
1 x 2
4.450
7.500
(0.050+0.12)
Over approach slab
2
say

Rate
/per

Amount

###
cum

###

/2
34.320
/24.990
39.310
40.000
cum

###
cum

2,27,280

17.620
18.000
cum

###
cum

1,03,536

Vibrated reinforced cement concrete M.30 grade using 20mm


& 10mm HBG crushed stone aggregate (Coarse aggregate conforming
to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, seigniorage conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing
etc., including all other incidental and operational charges of all T&P
etc., complete for finished item of work as per Approved drawing but
excluding cost of steel and its fabrication charges as per MoRT&H
specification
1500, 1600,1700, & 2704 (4 th Revision) and as
directed by the Engineer-in-Charge for Approach slab.
Approach slab

304382238.xls

4.450

7.50

0.300
say

Sl
No
12

13

14

Measurements
Rate
Qty
/per
L
B
D
Construction of precast VRCC railing of M20 grade using HBG
crushed stone aggregate of size not exceeding 12 mm and fine
aggregate conforming to table 1000-2 true to line and grade,
tolerance of vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical posts not to exceed 2000mm, leaving
adequate space between vertical posts for expansion including cost,
seigniorage conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including
other incidental hire and operational charges of all T&P as per
approved drawings and as directed during execution but excluding
cost of steel and its fabrication charges as per approved drawings and
technical specifications for finished item of work as per MoRT&H
Specification 2703, 1500, 1600, 1700(4 th Revision)
2 x 7
8.740
###
Over spans
2 x 2
4.450
17.800
Over Wings
###
say
### 298.00
Rm Rm
Providing HYSD bars ( Fe-415 ) of diferent diameters, wrought and
put up bars of all diameters including cost and conveyance of steel to
site and all labour charges for fabrication of reinforcement including
cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over
lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions
of the Engineer-in-Charge and as per MoRT&H specification 1600
&2200 (4th revision) and as per I.S.1786 of 1985 for
R.C.C items
in Sub structure
33.000 /200kg/cum
6.600
Bed blocks and backing walls
441.310 /60kg/cum
26.479
add for skin friction @60
kgs/cum
0.330
Add
for
wastage
and
variations
33.409 ###
Mt
Mt
Description of item

Nos

Amount

42,018

###

Providing HYSD bars ( Fe-415 ) of diferent diameters, wrought and


put up bars of all diameters including cost and conveyance of steel to
site and all labour charges for fabrication of reinforcement including
cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over
lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions
of the Engineer-in-Charge and as per MoRT&H specification 1600
&2200 (4th revision) and as per I.S.1786 of 1985 for
R.C.C items
in Super structure
Deck slab as per Drq.No.BD/274
steel46.71 cum of
314.63cum =314.63 / 46.71 x
concrete = 2.887MT for over
qty of 314.63
Wearing coat 3Kgs/sqm = [7x8.74x7.50 + 2x4.45x7.50] x 3/1000
= [17.62x160/1000]
Approach slab @ 160kg/cum
= [11.70x140.16/1000]
Hand rails and posts @
11.70kg/Rm
Add horses of slab
Ad for wastage and variations
5%

304382238.xls

19.446
1.577
2.819
1.640
2.207
1.400
29.089

###

###

Sl
No

304382238.xls

Description of item

Nos

Measurements
B

Qty

Rate
/per

Mt

Mt

Amount

Sl
No
15

Measurements
B
D
Back filling behind Abutments with gravel including cost
,conveyance and seigniorage of all materials to site etc., complete as
per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No.
2200 (4th Revision) and as per Drawing and technical specifications for
finished item of work
Description of item

Filling abutments

Nos

2[1.65x6.292] /2

4.119

42.760

2 1.65 [6.292+7.0] /2

1.270

27.850

Wings

2.490 [4.0+7.0]/2 5.389

Deduct for filter media


Deduct approach slab

4.140

6.600

0.570
say

16

Qty

Rate
/per

###
###
-74.920
-31.150
###
### 450.00
cum cum

Amount

50,850

Providing and laying of filter media using 50% of 150 mm IRC


soling stone and 50 % of 40 mm HBG metal satisfying the
requirements laid down in clause 2504.2.2 of MoRT&H specifications to
athickness of not less than 600mm with smaller size towards the soil
and bigger size towards the wall and provided over the entire surface
behind the abutment, wing wall and return wall to the full height
compacted to a firm condition including cost and conveyance of all
metal seignorage charges ,and all labour charges as directed by the
departmental officers as per drawing and Technical specifications as
per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (4 th Revision)
for finished item of work.
2
For abutments
1 x 2[4.0+6.292]
/ 2 2+1.650.600
27.400
[4.119
For abutments

2[6.292+7.0]/2 [1.27]

0.600

10.130

Wings

2
2
2[2.49+4.14]
[5.389
/2
+1.500.600

44.500

Deduct approach slab

6.600

0.42

0.600

-3.330

Deduct approach slab portion

4.140

0.57

0.400

-3.780
74.920

say

304382238.xls

75.000
cum

###
cum

87,300

Sl
No
17

18

19

Description of item

Nos

Measurements
B

Qty

Rate
/per

Providing Mastic pad 2'. 0" x 4'. 0" (0.60 M x 1.20 M) of 1"
(25.40mm) for expansion joints including cost, conveyance and
placing in position and all labour charges for fixing etc., complete as
directed by the engineer in charge of the work.
1 x 8
8.400
0.6500
39.000
For Deck slab
1 x 8
7.500(0.05+0.12) / 2
4.490
Slab wearing coat joint
2
x
8
0.450
0.275
1.980
Kerb joints
2 x 7
8.740
0.05
6.120
Wearing coat sides
1 x 7
8.740
0.120
7.340
Wearing coat centre
2 x 2
4.450
0.050
0.890
Approach slab sides
2 x 1
4.450
0.120
1.070
centre
1
x
2
10.800
1.350
29.160
Construction joint in raft
2 x 2[2.60+3.20] /2 0.600
6.960
--do-- wings
2 x 2[3.20+0.50]/2 5.389
39.880
--do-###
say
### 805.00
sqm sqm

Amount

1,10,285

Providing Grouted Revetment with SS Revetment 225 mm thick


grouted with 0.20 cum of CC (1:4:8) including cost, seigniorage
charges and conveyance of materials to site and including labour
charges for packing the stones for revetment etc., complete for
finished item of work as per MoRT&H specification 2504 ( 4 th revision )
and as directed by the Engineer-in-Charge for quadrants
For Quadrants

2
{ x 5.389} /45.3892 + 0.225
5.3892

29.040

--do-- stright portion

41.150

6.00

5.389 x 2 0.225

70.190
71.000
cum

###
cum

1,13,103

12.870
8.640
21.510
22.000
cum

###
cum

35,046

Providing Rough stone dry packing with SS Revetment 225 mm


thick grouted with 0.20 cum of CC (1:4:8) including cost, seigniorage
charges and conveyance of materials to site and including labour
charges for packing the stones for revetment etc., complete for
finished item of work as per MoRT&H specification 2504 ( 4 th revision )
and as directed by the Engineer-in-Charge for Toe walls
for quadrants
--do-- stright portion

304382238.xls

2
2

x 22x x 5.389} / 0.600


4
x 2
6.00
0.600

0.600
0.600

Sl
No
20

Description of item

Nos

Measurements
B

Stright portion

x 5.389 / 5.389
4
x 2 0.150

19.360

6.000 5.389 x 2 0.150

27.440

say

Amount

46.800
47.000 450.00
cum cum

21,150

Providing weep holes in PCC/RCC for abutments , return walls and


wing walls with 100mm dia AC pipe extending through the full width of
the structure with slope of 1V :20H towards draining face complete as
per drawing and technical specifications no MORTH 2706,2200
Abutments
from
sill
Abutments
from sill
Abutments
from
Wing sill
walls
above
sill
Wing walls
above walls
sill
Wing
above
sill
Wing walls
above sill

@
@
@
@
@
@
@

1.0m
2.0m
3.0m
1.0m
2.0m
3.0m
4.0m

height
height
height
height
height
height
height

5
6
5
4
4
4
4

x
x
x
x
x
x
x

2
2
2
2
3
3
4

2.400
1.900
1.400
2.300
1.900
1.500
1.100
say

22

Rate
/per

Gravel backing behind revetment


with gravel including cost
,conveyance and seigniorage of all materials to site etc., complete as
per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No.
2200 (4th Revision) and as per Drawing and technical specifications for
finished item of work
Quadrants

21

Qty

24.000
22.800
14.000
18.400
22.800
18.000
17.600
###
### 87.00
Rm Rm

12,006

Providing and fixing of CI drainage spouts complete as per MORTH


specification and as per drawing No.BD1/1-69
2

14.000 874.00
Nos Each

12,236
###

304382238.xls

DETAILED CUM ABSTRACT ESTIMATE


Name of work : Forming approaches to the of High Level Bridge @ Km.21/200 of
Butchi - Dagadarthi Road
Forming Approaches
Measurements
Sl
Rate
Description of item
Nos
Qty
Amount
No
/per
L
B
D
1 Forming embankmentwith gravel including cost, seigniorage
charges and conveyance of all materials to work site and
spreading in uniform layers by approved means, on prepared
surface and compacting with vibratory roller to achieve the
desired density at OMC etc., complete for finished item of work
as per MoRT&H Specification 401& 407 (4th revision) and as
directed by the Engineer-in-charge.
Quantity as per separate sheet
2 Construction of Granular sub-base by providing
HBG
material confirming to Grading - III of MoRT&H Table 400-2
including cost, seigniorage charges and conveyance of all
materials to work site and spreading in uniform layers with
motor grader or by approved means, on prepared surface
mixing by mix in place method with Rotavator / approved
means at OMC and compacting with vibratory roller to achieve
the desired density etc., complete for finished item of work as
per MoRT&H Specification 401 (4th revision) and as directed
by the Engineer-in-charge.
Chennur side
1 X 1 145.000
7.300
0.200
Dagadarthi sdie

1 X 1 135.000

7.300

0.200

###
cum

3 Providing, Laying, Spreading and compacting graded HBG


crushed stone aggregate to Wet Mix macadem specification
including cost,seignorage of all materials and including
premixing the material with water at OMC in Mechanical mix
plant carriage of mixed material by tipper to site , laying in
uniform layers in base courses on well prepared surface and
compacting with Vibratory roller to acheive the desired density
etc., as directed by the Engineer-in-Charge and as per MoRT&H
specification.406
(4th revision)
finished item
of work. 0.250
Chennur side
1 X 1 for
145.000
7.300
1 X 1 135.000

7.300

0.250

###

211.70
197.10
408.80
6.40
415.20 ###
cum cum

add for variations

Dagadarthi sdie

###
cum

###

264.63
246.38
511.00

add for variations

2.00
513.00 ###
cum

304382238.xls

cum

###

Sl
No

Description of item

Nos

Measurements
B

Qty

Rate
/per

Amount

4 Providing and applying prime coat with bitumen Emulsion


(Medium settting) (Bulk) using Emulsion pressure distributor at
the rate of 0.60 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for
finished item of work as per MoRT&H Specification 503 (4th
revision) and as directed by the Engineer-in-Charge.
Chennur side

1 X 1 145.000

7.000

1015.00

Dagadarthi sdie

1 X 1 135.000

7.000

945.00
1960.00

add for variations

10.00
1970.00 29.00
sqm

57,130

sqm

5 Providing and applying tack coat with bitumen Emulsion


(Medium settting) (Bulk) using Emulsion pressure distributor at
the rate of 0.20 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for
finished item of work as per MoRT&H Specification 503 (4th
revision) and as directed by the Engineer-in-Charge.
for BM and SDBC
Chennur side
Dagadarthi sdie

1 X 2 145.000
1 X 2 135.000

7.000
7.000

2030.00
1890.00
3920.00
10.00
3930.00 10.40
sqm
sqm

add for variations

6 Providing 25 mm thick compacted Semi-Dense Bituminous


Concrete by hot mix plant using hard blasted granite crushed
aggregates of Grading -2 as per table 500-15 of specification
508 of MoRT&H (4th Revision), premixed with bituminous binder
60/70 grade @ 5% of mix and filler, transporting the hot mix to
work site, laying with mechanical paver finisher to the required
grade,
level
and
alignment,
rolling
with
smooth
wheeled,vibratory and tandem rollers to achieve the desired
compaction as per MoRT&H Specification 508 (4th Revision)
complete for finished item of work in all respects as directed by
Chennur
side
1 X 1 145.000
7.000
0.025
Engineer-in-charge
Dagadarthi sdie

1 X 1 135.000

7.000

0.025

40,872

25.38
23.63
49.00

add for variations

1.50
50.50 ###
cum

7 Providing 50mm thick compacted Bituminous concrete

304382238.xls

cum

###

Sl
No

Description of item

Nos

Measurements
B

Qty

Chennur side

1 X 1 145.000

7.000

0.050

50.75

Dagadarthi sdie

1 X 1 135.000

7.000

0.050

47.25

304382238.xls

Rate
/per

Amount

S.No Chainage Distance

Area

Average area Qty


Chennur side

1
2
3
4
5

20.875
20.900
20.950
21.005
21.020

1
2
3
4
5

21.090
21.105
21.150
21.200
21.225

25
50.000
55.000
15.000

15.000
45.000
50.000
25.000 0

4.325
13.594
36.340
36.920

Dagadarthi side
38.597
40.075
21.900
6.349

255.000 Total
Gross quantity=
Deduct for crust=
Net Quantity=
Add for variation of
levels

2.163
8.959
24.967
36.630
18.460

54.066
447.974
1373.171
549.449
0.000

39.336
30.987
14.124
3.1744

590.040
1394.431
706.208
79.360
5140.631

5140.631
651.525
4489.106
510.894
5000 Cu.m

COMPUTATION OF QUANTITY OF GRAVEL FORMATION


CS at
chainage [km]

Sl NO
1

20.875

20.900

20.950

21.005

21.020

CS area[m2] Average ares[m2] Distance [m]

Quantity[m3]

0.190
4.132

25.000

103.300

14.073

50.000

703.600

25.792

55.000

1418.600

31.513

15.000

472.700

8.074

20.071

31.513

31.513

2698.200

Bridge portion
6

10

21.090

21.105

21.150

21.200

21.225

36.554
36.554

15.000

548.300

27.497

45.000

1237.400

10.709

50.000

535.400

3.242

25.000

81.100

36.554

18.440

5.977

0.507
total:

2402.200
145+135 = 280

5100.400
or say

5100.000
cum

Seigniorage charges abstract


Metal:

For concrete items

2747.00

0.90

2472.30

Filter media

75.00

1.20

90.00

Revetment

93.00

1.20

111.60

GSB

415.20

1.28

531.46

WMM

513.00

1.32

677.16

SDBC

50.50

1.46

73.78
3956.30 50.00/M3

Sand

For concrete items


Sand fill

1395.55

0.45

628.00

456.00

1.20

547.20

197814.83

1175.20 40.00/M3

47007.9595

Gravel

Gravel fill

160.00

1.20

192.00 22.00/M3

4224.00

Gravel

Formation

5000

1.28

6400 22.00/M3

140800.00

Earth

Earth for foundations

3000.00

1.00

3000.00 22.00/M3

66000.05

455846.84
say

455847.00

Location of the Bridge


Central Point:

= Km.21.005

length of the Bridge outer to Outer of approach slab

= 70.240m.

[ This will be the 35.12m each on either side of km.21.005]


Providing a striaght portion of 300m on either side
Starting chainage of the striaght portion

21.005-70.24/2x1000
[-] 30/1000

= 21.005-0.03512-.015
= 21.005-0.05012
= km. 21.00488
say. Km 21.005
Ending of striaght portion

21.005+70.24/2x1000
+15/1000

= 21.005+0.05012
= 21.1051
say. 21.105
Starting of approach on Chennur side

= km.20.875

Ending of approach on Chennur side

= km.21.020

therefore the length of approach on Chennur side

= 21.020-20.875

[including 30mts striaght portion ]

= 0.145
or 145m

Ending of approach on Dagadarthi side

= km. 21.090

Ending of approach on Dagadarthi side

= km.21.225

therefore the length of approach on Dagadarthi side

= 21.225-21.090

[including 30mts striaght portion ]

= 0.135
or 135m

Name of work : Construction of High Level Bridge @ Km.21/200 of Butchi Dagadarthi Road
Sailient features of the Bridge

L.W.W

8.0 M clear spans 7 Nos as per Drawing No.


BD/1-74 & BD/2-74 suitably changed for 6.60
:
M clear span and Kerbs.
Total width = 6.60+(2.0x0.475) = 7.55 M

Sill level (or) Lowest bed level

: +98.331 M

Vertical clearence
(HFL to Bottom of slab)

: 0.900 M

H.F.L

: ,+102.050 M

Sill level to H.F.L

: 3.719 M

Sill level to Bottom of Slab

: 4.619 M

Sill level to bottom of Raft

: 0.60 M

Thickness of Raft

: 1500 mm

Thickness of Lean concrete

: 150 mm

10 Thickness of Sand cushion

: 600 mm

11 Thickness of Bed block

: 0.500 M

12 Bottom of Bed block level

: +102.45 M

13 Sill level to top of Abutment

: 4.119 M

14 Bottom level of Deck slab

: +102.950 M

15 Depth of Deck slab

: 0.650 M

Sailient features of the Bridge


16 Top level of Deck slab

: +103.600 M

17 Thickness of Wearing coat

: 120mm @ centre & 50mm @ edge

18 R.C.L

: +103.720 M

19 Length of Approach slab

: 4.450 M

20 Sill to R.C.L

: 5.389 M

21 Top of Raft level

: +97.731 M

22 Bottom of Raft level

: +96.381 M

23 Bottom of lean concrete

: +96.231 M

24 Bottom of Sand cushion level

: +95.631 M

Name of work : Construction of High Level Bridge @ Km.21/200 of Butchi - Dagadarthi Road
( 7 Vents x 8.00M Clear spans )
DESIGN OF RAFT FOUNDATIONS
Legth of wing wall from back of backing wall with earth slope 1V : 1H with revetment
225mm thick grouted in CC M-15 =( R.C.L - Sill ) [-] 0.55 [-] 0.70
= (103.72 - 98.331 ) [-] 1.25 = 5.389 [-] 1.25 = 4.139 or 4.14

Length of Raft up to Construction joint


Length of Raft up to construction joint = 7 x 8.0m + 6 x 0.76 +2 (0.70+1.65+0.20)
= 56.00 + 4.56 + 5.10 = 65.66 M
Width of Raft up to end of wing wall footing = 10.80 M
Width of Raft under Pier
= 10.80 M
Width of Raft for desing purpose
= 10.80 M

(I) LOADS ON THE RAFT


I Dead loads
(a) Hand rails @ 200 kgs/Rm [GOI drg. No.BD/5-69] Type II]
2 { 7x8.74 + 2[0.31+1.65+0.20} 0.20

26.20

86.67

7x8.74x7.50x0.65x2.50

745.63

2x7x8.74x0.45x0.275x2.50

37.86

Kerbs over wings up to construction joints


2x2[0.31+1.65+0.20] 0.45[0.275 - 0.12] 2.50

1.51

(b) Wearing coat

{7x8.74x2x0.31] 6.60 [0.12+0.05] } 2.50


2

(c) Deck slab [GOI drg. No.BD/2-74]


[d] Kerbs of slabs

[e] Bed blocks over abutments

2x8.282x0.75x0.50x2.50

15.53

[f] Backing walls

2x6.60x0.31x0.35x2.50

3.58

2.01

50.63

3.04

83.94

114.62

47.53

391.47

23.39

+ 2x2x [8.282 - 6.60] x 0.31[0.65+0.12] 2.50


2
[g] Bed blocks over piers

= 6 x 7.50 x 0.90 x 0.50 x 2.50

+ 6x2 x [0.90+0.45] x 0.50 x 2.50


2
Abutments, wings , Piers above sill level:
Abutment: Rear Triangle
Abutment: Rectangle
Abutment: front Triangle
Piers straight portion
Cut & ease waters

1x2 (4.0+6.292) x 1.65 x 4.119 x 2.40


2
2
1x2 x 8.282 x 0.70 x 4.119 x 2.40
1x2 (8.282+9.20) x 0.55 x 4.119 x 2.40
2
2
6 x 7.50 x (0.76+1.0) x 4.119 x 2.40
2
2 x 6 x (0.76x0.38+1.0+0.50) x 4.119 x 2.40
2x2

Wing walls Rear Triangle

2x2 (0.20+1.85) x [1.50+0.354] x 4.119 x 2.40


2
2

37.57

3.99

47.85

28.71

8.85

8.47

1x2 x9.20x2.90x0.60x2.40 =

76.84

Piers 1st footing

6x9.70x2.20x0.30x2.40 =

92.19

Piers 2nd footing

6x9.10x1.60x0.30x2.40 =

62.90

2x2x0.20x2.60x0.60x2.40 =

3.00

2x2 [3.10+3.10]/2 x [0.60+0.60]/2 x 2.40 =

5.88

Marked (A) 2 x [1.65+6.292] / 2 x 4.119 x 1.80 =

77.01

Marked (B) 2 x 1.65[6.292+7.0]/2 x 1.27 x 1.80 =

50.14

Marked (C) 2x4.0x0.20x0.60x1.80 =

1.73

+2 x [4.0+7.0] / 2 x 0.20 x 5.389 x 1.80 =

21.34

Total: =

2160.08

2x2 x 1.85 x [0.354] x 1.27 x 2.40


2
Rectangle

2x2 1.85 x 0.50 x 5.389 x 2.40

Front triangle

2x2 x 1.85 x (0.60] / 2 x 5.389 x 2.40


2x2 x [0.70+1.25] / 2 x (0.60+0.141] / 2 x 4.119 x 2.40

Abutments, wings , Piers Below sill level:


Abutment triangle footing

1x2x(9.20+10.40) x (0.60+0.60) x 2.40


2
2

Rectangular footing

Wing walls Rectangular footing


traingular footing
(i) Weight of earth

Stress due to Dead load = 2160.08 / 65.66x10.80 = 3.05 T/M2

(II) EFFECT OF LIVE LOAD


(a) IRC class TOR Tracked vehicle ( worst efect with single)
4.57

1.85

70 T

59.24 m

65.66 m
Essentricity = 65.66 / 2 (-) 1.85 (-) (4.57) / 2
= 32.83 (-) 1.85 (-) 2.285 = 28.695
Stress on Raft = 70 / (65.66 x 10.80)
= 0.10 -1 2.62

1 6 x 28.695
65.66
= 0.36T/m2 compression & 0.16 T/ M2 tension

Net stress : 3.05+0.36 = 3.41 T/M2


and 3.05 (-) 0.16 = 2.89T/M2
(b) IRC class TOR Tracked vehicle ( single vehicle for worst efect )
17T

17T

17T

17T

12T

12T

8T

1.85M

1.37M

3.05M

1.37M

2.13M

1.52M

3.96M

M
C.G of Loads from the first 17T Load
= 17(1.37+4.42+5.79) + 12(7.92+9.44) +( 8 x 13.4)
(4x17+2x12+8)
= 17x11.58+12x17.36+8x13.4
68+24+8
'= 196.86+208.33+107.20) / 100 = 5.124
Essentricity = 65.66 / 2 (-) 1.85 (-) 5.124 = 32.83 (-) 6.974 = 25.856
Stress = 100 / 65.66 x 10.80 1 6 x 29.856 / 65.66 = 0.14 ( 12.73)
= 0.52T/M2 compression & 0.24T/M2 Tension
Net stress = 3.05+0.52 = 3.57T/M2
& 3.05(-) 0.24 = 2.81 T/M2

Therefore IRC class 7 OR wheeled vihicles


governs design

6th
Span
6.56m

7th
Span
6.13m

2.81

2.85

2.92
P6

A2
3.70m

P5

2.95

3.03

3.05

5th
Span
6.56m

2.20m

P4

2.20m

4th
Span
6.56m

3.13

3.15

3.23
P3

2.20m

3rd
Span
6.56m

2.20m

P2

3.25

3.33

3.35

2nd
Span
6.56m

2.20m

P1

2.20m

1st
Span
6.13m

3.43

3.46

3.53
A1
3.70m

3.57

DISTRIBUTION FACTORS

65.66 M

Joint P1

Joint P6

DF for P1 A1

= (1/6.13)
(1/6.13+1/6.56)

= 0.163
(0.163+0.152)

= 0.52

DF for P1 P2

= (1/6.56)
(1/6.13+1/6.56)

=0.152
(0.163+0.152)

= 0.48

DF for P6 P5

= 0.48

DF for P6 A6

= 0.52

For the joints ie. P2,P3,P4,P5,


equal in between P2,P3,P4,P5

D.F for all the members = 0.50 since length of spans are

FIXED END MOVEMENTS


SPAN A1P1; FEM @ A1 =
FEM @ P1 =

SPAN P1 P2; FEM @ P1 =


FEM @ P2 =

SPAN P2P3; FEM @ P2 =

3.46X6.132 + [3.53-3.46] X 6.132


12
20
10.83 +(3.53-3.46 )x6.132
30
3.35x6.52 + [3.43-3.35] X 6.562
12
20
12.01 +(0.08 )x6.562
30
3.25x 6.562 + [3.33-3.25] X 6.562
12
20

=10.83+0.13=10.96Tm
=10.83+0.09=10.92Tm

=12.01+0.17=12.18Tm
=12.01+0.12=12.13Tm

=11.65+0.17=11.82Tm

FEM @ P3 =

SPAN P3P4; FEM @ P3 =


FEM @ P4 =
SPAN P4P5; FEM @ P4 =
FEM @ P5=

SPAN P5P6; FEM @ P5 =


FEM @ P6=

SPAN P6P7; FEM @ P6 =


FEM @ P7=

11.65 +(0.08 )x6.562


30
3.15x 6.562 + 0.80 X 6.562
12
20
11.30 +(0.08 )x6.562
30
3.05x 6.562 + 0.80 X 6.562
12
20
10.94 +(0.08 )x6.562
30
2.95x 6.562 + 0.80 X 6.562
12
20
10.58 +(0.08 )x6.562
30
2.85x 6.132 + 0.07 X 6.132
12
20
8.92 +(0.07 )x6.132
30

=11.65+0.12=11.77Tm

=11.30+0.17=11.47Tm
=11.30+0.12=11.42Tm

=10.94+0.17=11.11Tm
=10.94+0.12=11.06Tm

=10.58+0.17=10.75Tm
=10.58+0.12=10.70Tm

=8.92+0.13=9.05 Tm
=8.92+0.09=9.01 Tm

MOVEMENT - DISTRIBUTION CHART

Joint

A1

P1

P2

P3

P4

P5

P6

Member

A1P1

P1A1 P1P2

P2P1 P2P3

P3P2 P3P4

P4P3 P4P5

P5P4 P5P6

P6P5 P6A2

A2P6

D.F

--

0.52 0.48

0.50 0.50

0.50 0.50

0.50 0.50

0.50 0.50

0.48 0.52

--

FEM

-10.96

10.92 -12.18

12.13 -11.82

11.77 -11.47

11.42 -11.11

11.06 -10.75

10.7 -9.05

9.01

Balance

--

0.66 0.60

-0.15 -0.16

-0.15 -0.15

-0.15 -0.06

-0.15 -0.16

-0.79 -0.86

--

0.3 -0.08

-0.07 -0.08

-0.07 -0.08

-0.07 -0.4

-0.08 -

Carry over 0.33


FEM

-10.63

Balance

--

Carry over 0.02


FEM

-10.61

Balance

--

Carry over 0.01


FEM

-10.6

Balance

--

Carry over -FEM

-10.6

Balance

--

Carry over --

-- -0.08
11.58 -11.66

12.28 -12.06

11.55 -11.7

0.04 0.04

-0.11 -0.11

+0.08 +0.07

0.02 0.04

-0.06 0.04

-- -0.05

10.84 -11.31

9.83 -9.91

+0.08 +0.07

0.24 0.23

0.04 0.04

0.04 0.12

0.04 0.02

0.12 --

8.58
-0.02

12.19 -12.13

11.57 -11.81

11.32 -11.16

11.12 -11.06

9.99 -9.87

8.6

0.03 0.02

-0.03 -0.03

0.12 0.12

-0.08 -0.08

-0.03 -0.03

-0.06 -0.06

--

0.01 0.06

-0.01 -0.04

0.06 -0.01

-0.04 -0.03

-0.02 --

11.65 -11.67

12.17 -12.1

11.68 -11.73

11.3 -11.25

11.05 -11.12

9.91 -9.93

0.01 0.01

-0.03 -0.04

0.03 0.02

-0.02 -0.03

0.04 0.03

0.01 0.01

--

-0.02 -0.01

0.01 0.02

-0.01 --

0.02 --

--

11.08 -11.09

9.94 -9.92

8.57

-0.01 -0.01

---

-- -0.02

-- -0.02

--

0.02

11.66 -11.68

12.14 -12.12

11.69 -11.72

11.29 -11.26

0.01 0.01

-0.01 -0.01

0.02 0.01

-0.02 -0.01

-- --

--

11.67 -11.67

0.01

-10.6

Balance

--

-- --

--

-0.01

Carry over --

-- --

--

--

-10.6

-0.43

11.62 -11.67

FEM

Total FEM

11.2 -11.35

A2

11.67 -11.67

--

12.13 -12.12

12.13 -12.13

-0.01

8.57

-- --

-- --

-- --

11.27 -11.27

11.09 -11.09

9.93 -9.93

0.01 --

-- --

-- --

-- --

--

--

-- --

-- --

-- --

--

11.71 -11.72

--

0.01 --

-0.03

11.72 -11.72

11.27 -11.27

11.09

-11.09

9.93

-9.93

8.57

8.57

Mix. FEM = 12.13 Tm

Max. FEM = 12.13 T.m


For VCC M-15 grade concrete maximum permissible tensile stress in bending
= 0.40 Mpa Table No. 10 of IRC 21-2000(IRC Bridge code section III = 40 T/ m 2
M
I

F
Y

E
R

Therefore

M
I/Y

M
Z

Therefore

m
F

Bd2
6

M
f

B = Width of Raft 1m considered


f = 40 T/m2 ; M = 12.13 T.m
d = Thickness of Raft =

6M / Bf

6x12.13 / 1.0 x 40

Provide 1.35 M thick Raft in VCC M-15 over 150mm thick CC M-15
lean concrete bed over 600mm thick sand cushion
Stress on Soil

= 3.57 + (1.35+0.15) 2.40+0.6 x 1.80 = 3.57 +3.60 +1.08 = 8.25 T/ m 2


However a S.B.C of 9.00 T / M2 is recommended from soil tests results

n bending

= 40 T/ m 2

= 1.35M

0mm thick CC M-15

= 8.25 T/ m 2

sts results

HYDRAULIC - CALCULATIONS
DISCHARGE CALCULATIONS
Statement showing the GLs on the stream
Sl No

CS @ Chainage

G.L

H.F.L

1 500 m U/S

+99.064

+102.59

2 250 m U/S

+98.634

+102.32

3 At site of crossing

+98.331

+102.05

4 250 m D/S

+98.201

+101.765

5 500 m D/S

+97.989

+101.51

Bed level slope calculations:


Bed level @ 500m U/S

=99.064

Bed level @ 500m D/S

=97.989

Diference in bed level in 1000m

=1.075

Bed slope = 1.075 / 1000 = 0.001075


Rugocity coefect = n = 0.045 for widening, some pools, and shoals,
clean , inefective slope and sections of the stream

AREA - VELOCITY METHOD


C/S @ 500 M U/S
Ch
(m)
0.000

G.L
(m)

M.F.L
(m)

101.480

Dif.
(m)

102.590

Area of
Mean.Dif Distance flow A
1
(m)
'D' (m)
(m2)

1.110

0.005

101.885

102.590

0.705

0.010

101.869

102.590

0.721

0.015

101.909

102.590

0.681

0.020

101.991

102.590

0.599

0.025

100.710

102.590

1.880

0.030

99.064

102.590

3.526

0.035

99.714

102.590

2.876

0.040

100.075

102.590

2.515

0.045

102.446

102.590

0.144

0.050

102.366

102.590

0.224

0.055

101.663

102.590

0.927

Wetted
Bed level perimetr
int; Dif e
'x' (m)
x2+d2-P
(m)

0.907

5.000

4.54

0.405

5.020

0.713

5.000

3.56

0.016

5.000

0.701

5.000

3.51

0.040

5.000

0.640

5.000

3.20

0.082

5.000

1.240

5.000

6.20

1.281

5.160

2.703

5.000

13.51

1.646

5.260

3.201

5.000

16.00

0.650

5.040

2.696

5.000

13.48

0.361

5.010

1.330

5.000

6.65

2.371

5.530

0.184

5.000

0.92

0.080

5.000

0.576

5.000

2.88

0.703

5.050

55.000

74.43

56.07

Hydraulic mean depth R = A / P = 74.45 / 56.07 = 1.328


Velocity 'V' = R2/3 S

Velocity 'V' = 1.3282/3 X 0.0010751/2

1/2

0.045

Velocity 'V' = 1.2082x 0.03279 = 0.88m /Sec


0.045

Discharge AV = 74.45x0.88 = 65.52 cumsec

AREA - VELOCITY METHOD


C/S @ 250 M U/S
Ch
(m)

G.L
(m)

M.F.L
(m)

Dif.
(m)

0.000

101.575

102.320

0.745

0.005

101.515

102.320

0.805

0.010

101.483

102.320

0.837

0.015

101.397

102.320

0.923

0.020

101.364

102.320

0.956

0.025

101.289

102.320

1.031

0.030

99.142

102.320

3.178

0.035

98.634

102.320

3.686

0.040

99.945

102.320

2.375

0.045

99.847

102.320

2.473

0.050

100.770

102.320

1.550

0.055

101.734

102.320

0.586

0.060

101.655

102.320

0.665

0.065

101.562

102.320

0.758

0.070

101.801

102.320

0.519

0.075

102.135

102.320

0.185

0.077

102.320

0.080

102.550

102.320

Area of
Mean.Dif Distance flow A
1
(m)
'D' (m)
(m2)

Wetted
Bed level perimetr
int; Dif e
'x' (m)
x2+d2-P
(m)

0.775

5.000

3.88

0.060

5.000

0.821

5.000

4.11

0.032

5.000

0.880

5.000

4.40

0.068

5.000

0.939

5.000

4.70

0.033

5.000

0.993

5.000

4.97

0.075

5.000

2.105

5.000

10.52

2.147

5.440

3.432

5.000

17.16

0.508

5.030

3.031

5.000

15.15

1.311

5.170

2.424

5.000

12.12

0.098

5.000

2.012

5.000

9.93

0.923

5.080

1.068

5.000

5.34

0.964

5.090

0.625

5.000

3.13

0.079

5.000

0.711

5.000

3.56

0.093

5.000

0.638

5.000

3.19

0.239

5.010

0.352

5.000

1.76

0.334

5.010

0.092

2.200

0.20

0.185

2.210

77.200

104.12

0.000

--

-78.04

Hydraulic mean depth R = A / P = 104.12 / 78.04 = 1.334


Velocity 'V' = R2/3 S

Velocity 'V' = 1.3282/3 X 0.0010751/2

1/2

0.045

Velocity 'V' = 1.212x 0.03279 = 0.88m /Sec


0.045

Discharge AV = 104.12x0.88 = 91.63 cumsec

AREA - VELOCITY METHOD


C/S @ Site of crossing
Ch
(m)

G.L
(m)

M.F.L
(m)

Dif.
(m)

20.975

101.376

102.050

0.674

21.000

101.204

102.050

0.846

21.025

101.122

102.050

0.928

21.030

100.141

102.050

1.909

21.035

99.570

102.050

2.480

21.040

99.394

102.050

2.656

21.045

99.239

102.050

2.811

21.050

99.025

102.050

3.025

21.055

98.331

102.050

3.719

21.060

98.807

102.050

3.243

21.065

98.874

102.050

3.176

21.070

98.902

102.050

3.148

21.075

98.962

102.050

3.088

21.080

100.100

102.050

1.950

Area of
Mean.Dif Distance flow A
1
(m)
'D' (m)
(m2)
0.760

25.000

19.00

0.172

25.000

0.887

25.000

22.18

0.082

25.000

1.419

5.000

7.09

0.981

5.100

2.195

5.000

10.97

0.571

5.030

2.568

5.000

12.84

0.176

5.000

2.734

5.000

13.67

0.155

5.000

2.918

5.000

14.59

0.214

5.000

3.372

5.000

16.86

0.694

5.050

3.481

5.000

17.41

0.476

5.020

3.210

5.000

16.05

0.076

5.000

3.162

5.000

15.81

0.028

5.000

3.118

5.000

15.59

0.060

5.000

2.519

5.000

12.60

1.138

5.130

50.000

146.39

0.958

25.000

23.96

0.277

25.000

0.723

25.000

18.09

0.193

25.000

175.000

267.18

Total from 21.030 to 21.080


21.100

100.953

102.050

1.097

21.125

101.230

102.050

0.820

21.150

101.423

102.050

0.627

Wetted
Bed level perimetr
int; Dif e
'x' (m)
x2+d2-P
(m)

50.230

175.35

Hydraulic mean depth R = A / P = 267.18 / 175.35 = 1.5237m


Velocity 'V' = R2/3 s

Velocity 'V' = 1.52372/3 x 0.0010751/2

1/2

0.045

Velocity 'V' = 1.324x 0.03274 = 0.963m /Sec


0.045

Discharge AV = 104.12x0.88 = 0.963 cumsec

Discharge = 267.18 x 0.963 =257.29


Considering only efective channel flow from Ch. 21.03 to 21.080
Hydraulic mean depth = R = 146.39 / 50.23 = 2.9144
Velocity 'V' = 2.9142/3 X 0.0010751/2
0.045

Velocity 'V' = 2.0403x 0.03274 = 1.4844m/Sec


0.045

Discharge = 146.39 x 1.4844 = 217.30 cum sec

AREA - VELOCITY METHOD


C/S @ 250M D/S
Ch
(m)

G.L
(m)

M.F.L
(m)

Dif.
(m)

0.000

100.455

101.765

1.310

5.000

101.342

101.765

0.423

10.000

101.280

101.765

0.485

15.000

100.462

101.765

1.303

20.000

98.877

101.765

2.888

25.000

98.201

101.765

3.564

30.000

98.315

101.765

3.450

35.000

98.970

101.765

2.795

40.000

100.629

101.765

1.136

45.000

101.293

101.765

0.472

50.000

100.558

101.765

1.207

Area of
Mean.Dif Distance flow A
1
(m)
'D' (m)
(m2)

Wetted
Bed level perimetr
int; Dif e
'x' (m)
x2+d2-P
(m)

0.867

5.000

4.33

0.887

5.080

0.454

5.000

2.27

0.020

5.000

0.894

5.000

4.47

0.818

5.070

2.096

5.000

10.48

1.585

5.250

3.226

5.000

16.13

0.676

5.050

3.507

5.000

17.54

0.114

5.010

3.123

5.000

15.61

0.655

5.040

1.966

5.000

9.83

1.659

5.270

0.804

5.000

4.02

0.664

5.040

0.839

5.000

4.20

0.735

5.050

50.000

88.88

50.86

Hydraulic mean depth R = A / P = 88.88 / 50.86 = 1.7475m


Velocity 'V' = R2/3 S

Velocity 'V' = 11.74752/3 X 0.0010751/2

1/2

0.045

Velocity 'V' = 1.4508x 0.03274 = 1.056m /Sec


0.045

Discharge AV = 88.88x1.056 = 93.86 cumsec

AREA - VELOCITY METHOD


C/S @ 500M D/S
Ch
(m)

G.L
(m)

M.F.L
(m)

Dif.
(m)

10.000

101.757

10.660

101.510

101.510

0.000

15.000

99.890

101.510

1.620

20.000

98.003

101.510

3.507

25.000

98.103

101.510

3.407

30.000

97.989

101.510

3.521

35.000

99.088

101.510

2.422

40.000

100.157

101.510

1.353

45.000

101.357

101.510

0.153

50.000

101.348

101.510

0.162

Area of
Mean.Dif Distance flow A
1
(m)
'D' (m)
(m2)

Wetted
Bed level perimetr
int; Dif e
'x' (m)
x2+d2-P
(m)

0.810

4.340

3.52

1.620

4.630

2.564

5.000

12.82

1.887

5.340

3.457

5.000

17.29

0.100

5.000

3.464

5.000

17.32

0.114

5.000

2.972

5.000

14.86

1.099

5.120

1.888

5.000

9.44

1.069

5.110

0.753

5.000

3.77

1.200

5.140

0.158

5.000

0.79

0.009

5.000

39.340

79.81

40.34

Hydraulic mean depth R = A / P = 79.81 / 40.34 = 1.9784m


Velocity 'V' = R2/3 S

Velocity V' = 1.97842/3 X 0.0010751/2

1/2

0.045

Velocity 'V' = 1.576x 0.03274 = 1.147m /Sec


0.045

Discharge AV = 79.81x1.47 = 91.54 cumsec

Catchmetn Area Method


Catchment area = M = 8.25 Sq Km
RYVEs Formula = Q = CM

2/3

C = 8.50 therefore Q = 8.50 x 8.25

2/3

= 8.5x4.06 = 34.54 cumsec

Comparision of Discarge

(I) Discharge by C.A. method


(II) Discharge by A.V. Method

34.540 M3/sec

a) CS @

500m

U/S

65.520 M3/sec

b) CS @

250m

U/S

91.630 M3/sec

c) CS at site of crossing considering only


=
portion of flow as efective channel flow

217.300 M3/sec

d) CS @

250m

D/S

93.860 M3/sec

e) CS @

500m

D/S

91.540 M3/sec

As seen from the above discharges the discharge of site of


crossing is 217.30 cumsec being the heighest of all cross sections and is
considered for design purpose, since there was no proper course for the stream
and the entire vagu site and adjoining fields becomes sheet of water, the water
from the fields flowing through the causeway. Hence the discharge at the site of
crossing if felt more reasonable as the efective water flow is about 50M/i as per
local enquiry. Hence the design discharge is taken as 217.30 cum/ secs ie. at the
site of crossing.
Velocity at Site of crossing
Depth of flow at the site of crossing
Lowest Bed level
HFL at the site of crossing
therefore depth of flow =
d'
Assuming an efflux of 0.15 = 'x'

=
=
=
=

0.953 m/sec
+98.331 m
+102.05 m
3.719 m

Head due to afflux = V2d2 / (d+x)2 2g


1.0562 x 3.7192 / (0.953+0.15)2 2x9.81

0.166m

Therefore total head = 0.15 +0.166 = 0.316m


Velocity of approach =

0.90

2gh

19.62x 0.316

0.90 x

2.24m/sec

But restricting the velocity to the velocity at the site of crossing


ie.0.953m/sec (or) 1.0m/sec non siting and non scouring velocity,
Then LWW =

Discharge / d x V
217.36 / 3.719 x 1.00 =

58.430

This tallies roughly to the efective water flow width of 50m at the site and hence
7Vents of 8.0M clear span giving a LWW of 56M has been provided.

SCOUR DEPTH CALCULATIONS


Since a L.W.W of 56M on par with efective water flow is provided, there will not
be any scour than the L.B.L.
More over bottom of lean concrete is at a total depth of 0.60+1.35 0.15 = 2.10M
depth below the L.B.L. Hence the scour may not extend to that extent
However the following scour calculations have been made for the purpose of
scour calculations, the design discharge is increased by 30%
Therefore Discharge = 217.30 x 1.30 = 282.49cumsecs
Discharge / m cum of LWW = 282.49 / 56 = 5.044 cumsecs = D b
Therefore Normal Scour depth

D1 =

1.34

/3

/3

Db2
KSf

KSf = Assumed silt factor = 1.00


Therefore

5.004
1.34
1.00

D (or) dsm
1

=1.34 x (25.442)1/3
= 1.34 x 2.94 = 3.94m
For Raft foundations, the depth should not be less than 1.27 dsm for cut of walls
1.27dsm = 1.27 x 3.94 = 5.004m
Therefore Level of cutof wall = HFL (-) 5.004 = +102.05 (-) 5.004 = +97.046 m
Bottom level of lean concrete is at lower level than Max. Scour. Hence there
is no need for cut of walls.
But however pucca apron of 300mm thick in VCC M-15 over 150mm thick for a
width of 3.0m on U/S and 5.0m
on D/S may be provided for safety purpose.

Name of work : Construction of High Level Bridge @ Km.21/200 of Butchi - Dagadarthi Road
QUARRY CHART

HBG metal

Gravel
Proposed HLB

4/6

13/4
Butchi Dagadarthi road

21/2

27/6

202/4

NH-5

0/0

RCC pipes
183/6
4/8
Sand
+0.20CT
0/0
River Pennar

Kovur town rd

Weighted average leads


Name of work : Construction of High Level Bridge @ Km.21/200 of Butchi - Dagadarthi
Road
For HBG Metal Source:
Elemanchipadu quarry at km 4/6 of Butchi
Dagadarthi road with 0.80KMCT
Car track
Buthci Dagadarthi road

0.80

km

km 4.60

km 21.20

For Sand Mortor: River Pennar Km 1/4 of NBB road with 0.20KMCT
Car track
0.20
km
Kovur town road
km 0.00
to km 4.80
NH-5
km 183.600 to km 202.400
Buthci Dagadarthi road
km 27.600
to km 21.200

For Gravel: KM 13/4 of the road with 0.20KMCT


Car track
0.20
B_D road
km 13.40
to

km
km 21.20

For RCC Pipes KM 183/6 of NH-5


Factory to junction
NH-5
km 183.60
B_D road
km 27.60

to
to

km 202.40
km 21.10

For Bitumen : Chennai


City lead
NH-5
B_D road

to
to

km 202.40
km 21.10

km 0.00
km 27.60

0.88
16.60
17.48
18.00
kms

0.22
4.80
18.80
6.60
30.42
31.00
kms

0.22
7.80
8.02
8.00
kms
0.40
18.80
6.40
25.60
26.00
kms

5.00
202.40
6.40
213.80
214.00
kms

ROAD METAL RATES

Name of work : Construction of High Level Bridge @ Km.21/200 of Butchi - Dagadarthi Road

Sl.
No

Description of
Meterial

Lead in
Kms

Conve
yance

A) FOR ROAD WORKS

Machin
Deduct
e
stacking
Initial cost
charges Toal Cost
crushin
less stacking
for
per Cum
charge
g
conve
s
yance
charges
Blastin
g

60 to 63 mm IRC and MoRTH


HBG metal

18.00

222.00

351.30

70.00

87.83

-8.70

722.43

50 to 55 mm IRC and MoRTH


HBG metal

18.00

222.00

381.30

70.00

95.33

-8.70

759.93

40 to 45 mm IRC and MoRTH


HBG metal

18.00

222.00

491.30

70.00

122.83

-8.70

897.43

18.00

222.00

86.30

52.50

0.00

-8.70

352.10

18.00

222.00

31.05

0.00

0.00

-8.70

244.35

6 150 mm soling stone HBG metal

18.00

222.00

73.30

70.00

0.00

-8.70

356.60

40 to 45 mm IRC and MoRTH


HBG M/C metal

18.00

222.00

491.30

70.00

122.83

-8.70

897.43

25 to 27 mm IRC and MoRTH


HBG M/C metal

18.00

222.00

821.30

70.00

205.33

-8.70

1309.93

19 to 22 mm IRC and MoRTH


HBG M/C metal

18.00

222.00

836.30

70.00

209.08

-8.70

1328.68

12 to 14 mm IRC and MoRTH


HBG M/C metal

18.00

222.00

681.30

70.00

170.33

-8.70

1134.93

9.5 to 11.20 mm IRC and MoRTH


HBG M/C metal

18.00

222.00

551.30

70.00

137.83

-8.70

972.43

5 to 7 mm IRC and MoRTH


HBG M/C metal

18.00

222.00

421.30

70.00

105.33

-8.70

809.93

2.36 to 5 mm IRC and MoRTH


HBG M/C metal

18.00

222.00

225.30

70.00

56.33

-8.70

564.93

4 SS Revetment work 300mm

10

Quarry spall(Field picked metal)


Av. Of rate 25mm & 40mm

304382238.xls

11

HBG Stone chips 2.36mm


and below

18.00

222.00

216.30

0.00

0.00

-8.70

429.60

8.00

142.00

50.50

0.00

0.00

-5.50

187.00

13 40 mm SS-5 HBG M/C metal

18.00

222.00

491.30

70.00

122.83

-8.70

897.43

14 25 mm SS-5 HBG M/C metal

18.00

222.00

821.30

70.00

205.33

-8.70

1309.93

15 20 mm SS-5 HBG M/C metal

18.00

222.00

836.30

70.00

209.08

-8.70

1328.68

16 12 mm SS-5 HBG M/C metal

18.00

222.00

681.30

70.00

170.33

-8.70

1134.93

17 10 mm SS-5 HBG M/C metal

18.00

222.00

551.30

70.00

137.83

-8.70

972.43

18 6 mm SS-5 HBG M/C metal

18.00

222.00

421.30

70.00

105.33

-8.70

809.93

19 Sand for Mortar

31.00

268.80

169.50

0.00

0.00

-5.50

432.80

20 Sand for Filling

31.00

268.80

54.50

0.00

0.00

-5.50

317.80

21 HYSD Steel

0.00

44000.00

22 6mm Mild Steel

0.00

43000.00

23 Mild Steel

0.00

43000.00

24 Cement

0.00

5900.00

12 Gravel

25

Bitumen VG_10 (80/100)


rares wef from 01-07-2013

214.00

642.00

43414.38 ST:2%

868.29

44924.67

26 Bitumen VG_30 (60/70)

214.00

642.00

44329.74 ST:2%

886.59

45858.33

27 Bitumen emulsion [01-07-2013]

214.00

642.00

38985.00 ST:2%

779.70

40406.70

304382238.xls

304382238.xls

DATAS
Quantity

Description of Item

Rate

per

Amount

Earthwork excavation in soils upto SDR by mechanical means for foundations of


structures as per drawing and technical specification including setting out, construction
of shoring and bracing, removal of stumps and other deleterious matter, dressing sides
of bottom, back filling the excavation earth to the extent required etc., complete
including seignioarge charges for finished item of work as per MoRT&H specification
304(4th Revision) and as directed by the Engineer-in-Charge

Unit : Cum

Page 323 of MoRT&H SDB

Taking out put = 240 Cum


(A) Labour
0.32 day

Mate

188.00

day

60.16

8.00 day

Mazdoor unskilled

146.00

day

1168.00
1228.16

(B) Machinery
240.00 cum

Rate as per G.O. Ms No 10, Dt 26/7/2005

13.00

cum

3120.00

cum

0.00

(C) Seigniorage charges


240.00 Cum

Seigniorage charges

[c] Over head charges @ 20% on (A) + (B)


(D) Total of (A) + (B)+( C)+(D)
(E) Add Contractors Profit at 10% on (E)
Cost per 240 cum (E)+(F)
Rate for 1 cum

869.63
5217.79
521.78
5739.57
23.91
23.91

Rate to be adopted

24.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Dismantalling the existing structures like culverts , bridges, rataining walls and others
comprising of masonary cement concrete wood work steel work, including T&P and
scafolding whereever necessary sorting the dismantled material, disposal of
unserviceable material with a lead of 1000m and all lifts etc complete as per MORT&H
specification No.202.2.4 and as directed by the Engineer in charge
Unit = cum

Page 345,346 of MoRT&H SDB

Taking output = 1.25cum


(A) Labour
0.03 day

Mate

188.00

day

5.64

0.08 day

Mazdoor

146.00

day

11.68
17.32

(B) Material
0.27 Hrs

Tractor trailor

345.00

cum

93.15

(C)
20.00 %

Add for Over head charges @ 20% on (A)+(B)

(D) Total of (A) + (B)+( C)


(E) Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)

22.09
132.56
13.26
145.82
145.82

Or say

146.00
1 cum

Quantity

Description of Item

Rate

per

Amount

Sand filling in foundation including cost, seignoirage and conveyence of all materials to
site and watering, tamping etc., complete for finshed item of work as per MoRT&H
specification 304 (4th Revision) and as directed by the Engineer - in - Charge.

Unit = cum

Page 422 of MoRT&H SDB

Taking output = 1 cum


(A) Labour
0.01 day

Mate

188.00

day

1.88

0.30 day

Mazdoor

146.00

day

43.80
45.68

(B) Material
1.20 Cum

Sand for filling

317.80

cum

381.36

(C)
20.00 %

Add for Over head charges @ 20% on (A)+(B)

(D) Total of (A) + (B)+( C)


(E) Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)

85.41
512.45
51.25
563.70
563.70

Or say

564.00
1 cum

Quantity

Description of Item

Rate

per

Amount

Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for
foundations

Unit = cum

Page 331 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.64 nos

Mate

188.00

day

120.32

1.00 nos

Mason

193.40

day

193.40

Mazdoor

146.00

day

2190.00

15.00 nos

Total

2503.72

(B) Material
13.50

cum

Cost of 40mm SS-5 HBG M/C metal

6.75

cum

Sand at site

3.45

MT

Cement at site

897.43

cum

432.80

cum

2921.40

5900.00

MT

20355.00

Total

12115.31

35391.71

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 35 KVA

620.00

hr

3720.00

2.00 hr

Water tanker 6 KL capacity

345.00

hr

690.00

Total

6480.00

Add for Over head charges @ 20% on (A)+(B)+( C)

8875.09

(D)
20.00 %

(E) Total of (A) + (B)+( C)+(D)


(F) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum

53250.52
5325.05
58575.57
3905.04
3905.04

Rate to be adopted

3905.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

161.68

Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as including dewatering charges per MoRT&H
Specification 1500,1700, 2100 (4th Revision) for Lean concrete

Unit = cum

Page 335 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.86 nos

Mate

188.00

day

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

3371.78

(B) Material
8.10 cum

Cost of 40mm SS-5 HBG M/C metal

897.43

cum

7269.18

4.05 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

cum

5381.15

1.35 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

cum

1312.78

6.75 cum

Sand at site

432.80

cum

2921.40

4.13 MT

Cement at site

5900.00

MT

24367.00

Total

41251.51

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

6.00 hr

Generator set 35 KVA


Dewatering charges

15.00 cum

hr

2070.00

620.00

hr

3720.00

120.00

cum

1800.00
7590.00

(D) Form work


4.00 %

Form work @ 4% on (A)+(B)+( C)

52213.29

Cum

2088.53

(E)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)+(D)

(F) Total of (A) + (B)+( C)+(D)+(E)


(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum

10860.36
65162.18
6516.22
71678.40
4778.56
4778.56

Rate to be adopted

4779.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

161.68

Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as including dewatering charges per MoRT&H
Specification 1500,1700, 2100 (4th Revision) for Raft

Unit = cum

Page 335 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.86 nos

Mate

188.00

day

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

3371.78

(B) Material
8.10 cum

Cost of 40mm SS-5 HBG M/C metal

897.43

cum

7269.18

4.05 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

cum

5381.15

1.35 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

cum

1312.78

6.75 cum

Sand at site

432.80

cum

2921.40

4.13 MT

Cement at site

5900.00

MT

24367.00

Total

41251.51

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

6.00 hr

Generator set 35 KVA


Dewatering charges

15.00 cum

hr

2070.00

620.00

hr

3720.00

120.00

cum

1800.00
7590.00

(D) Form work


4.00 %

Form work @ 4% on (A)+(B)+( C)

52213.29

Cum

2088.53

(E)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)+(D)

(F) Total of (A) + (B)+( C)+(D)+(E)


(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum

10860.36
65162.18
6516.22
71678.40
4778.56
4778.56

Rate to be adopted

4779.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing, laying in
position,Compacting, Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification
1500,1700, 2200 (4th Revision) for Sub structure below sill level

Unit = cum

Page 335,455 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.86 nos

Mate

188.00

day

161.68

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

3371.78

(B) Material
8.10 cum

Cost of 40mm SS-5 HBG M/C metal

897.43

cum

7269.18

4.05 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

cum

5381.15

1.35 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

cum

1312.78

6.75 cum

Sand at site

432.80

cum

2921.40

4.13 MT

Cement at site

5900.00

MT

24367.00

Total
5.00 %

Dewatering charges

41251.51
on A+B

44623.29

2231.16

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 35 KVA

620.00

hr

3720.00
5790.00

(D) Form work


10.00 %

Form work @ 10% on (A)+(B)+( C)

50413.29

Cum

5041.33

(E)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)+(D)

(F) Total of (A) + (B)+( C)+(D)+(E)


(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum

11090.92
68776.70
6877.67
75654.37
5043.62
5043.62

Rate to be adopted

5044.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing, laying in
position,Compacting, Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification
1500,1700, 2200 (4th Revision) for Sub structure above sill level

Unit = cum

Page 335,455 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.86 nos

Mate

188.00

day

161.68

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

3371.78

(B) Material
8.10 cum

Cost of 40mm SS-5 HBG M/C metal

897.43

cum

7269.18

4.05 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

cum

5381.15

1.35 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

cum

1312.78

6.75 cum

Sand at site

432.80

cum

2921.40

4.13 MT

Cement at site

5900.00

MT

24367.00

Total

41251.51

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 35 KVA

620.00

hr

3720.00
5790.00

(D) Form work


10.00 %

Form work @ 10% on (A)+(B)+( C)

50413.29

Cum

5041.33

(E)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)+(D)

(F) Total of (A) + (B)+( C)+(D)+(E)


(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum

11090.92
66545.54
6654.55
73200.09
4880.01
4880.01

Rate to be adopted

4880.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including other incidental hire and operational charges of all T&P as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication
charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (4th
revision ) and as directed by the Engineer-in-Charge for Bed blocks & Backing walls

Unit = cum

Page 472,457 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.86 nos

Mate

188.00

day

161.68

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

3371.78

(B) Material
8.10 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

5.40 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

6.75 cum

Sand at site

5.12 MT

Cement at site

cum

10762.31
5251.12

432.80

cum

2921.40

5900.00

MT

30208.00

Total

49142.83

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 35 KVA

620.00

hr

3720.00

Total

5790.00

(D) Form work


10.00 %

Form work @ 10% on (A)+(B)+( C)

58304.61

Cum

5830.46

(E)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)+(D)

(F) Total of (A) + (B)+( C)+(D)+(E)


(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum

12827.01
76962.08
7696.21
84658.29
5643.89
5643.89

Rate to be adopted

5644.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including other incidental hire and operational charges of all T&P etc., complete as per
approved drawings and as directed during execution but excluding cost of steel and its
fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 &
2200 (4th revision ) and as directed by the Engineer-in-Charge for Deck slab

Unit = cum

Page 472 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.86 nos

Mate

188.00

day

161.68

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

3371.78

(B) Material
8.10 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

5.40 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

6.75 cum

Sand at site

6.05 MT

Cement at site

cum

10762.31
5251.12

432.80

cum

2921.40

5900.00

MT

35695.00

Total

54629.83

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 35 KVA

620.00

hr

3720.00

Total

5790.00

(D) Form work


20.00 %

Form work @ 20% on (A)+(B)+( C)

63791.61

Cum

12758.32

(E)
6.00 %

Add for Over head charges @ 6% on (A)+(B)+( C)+(D)

(F) Total of (A) + (B)+( C)+(D)+(E)


(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum

4593.00
81142.93
8114.29
89257.22
5950.48
5950.48

Rate to be adopted

5950.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per drawing BD/1-69( A) but excluding cost of steel and its
fabrication charges as per MoRT&H specification
1500, 1600,1700, & 2702 (4th
Revision) and as directed by the Engineer-in-Charge for wearing coat over Deck slab.

Unit = cum

Page 477,492 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.90 nos

Mate

188.00

day

169.20

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

3066.00

21.00 nos

Total

3525.30

(B) Material
8.10 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

cum

10762.31

5.40 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

cum

5251.12

6.75 cum

Sand at site

432.80

cum

2921.40

6.10 MT

Cement at site

5900.00

MT

35990.00

Total

54924.83

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 35 KVA

620.00

hr

3720.00

2.25 nos

Labour for cleaning deck slab concrete

146.00

day

5790.00
328.50

(D)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)

(E) Total of (A) + (B)+( C)+(D)


(F) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum M 30 Concrete

12913.73
77482.36
7748.24
85230.60
5682.04
5682.04

Rate to be adopted

5682.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

161.68

Vibrated reinforced cement concrete M.30grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per Approved drawing but excluding cost of steel and its
fabrication charges as per MoRT&H specification
1500, 1600,1700, & 2704 (4th
Revision) and as directed by the Engineer-in-Charge for Approach slab.

Unit = cum

Page 340,501 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.86 nos

Mate

188.00

day

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

3371.78

(B) Material
8.10 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

cum

10762.31

5.40 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

cum

5251.12

6.75 cum

Sand at site

432.80

cum

2921.40

6.10 MT

Cement at site

5900.00

MT

35990.00

Total

54924.83

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 35 KVA

620.00

hr

3720.00

Total

5790.00

(D) Form work


2.00 %

Form work @ 2% on (A)+(B)+( C)

64086.61

Cum

1281.73

(E)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)+(D)

(F) Total of (A) + (B)+( C)+(D)+(E)


(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum M 25 Concrete

13073.67
78442.01
7844.20
86286.21
5752.41
5752.41

Rate to be adopted

5752.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Construction of precast VRCC railing of M20 grade using HBG crushed stone aggregate
of size not exceeding 12 mm and fine aggregate conforming to table 1000-2 true to line
and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre
spacing between vertical posts not to exceed 2000mm, leaving adequate space between
vertical posts for expansion including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including other incidental hire and operational charges of all T&P as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication
charges as per approved drawings and technical specifications for finished item of work
as per MoRT&H Specification 2703, 1500, 1600, 1700(4th Revision)

Unit = 1 RM

Page 472,497 of MoRT&H SDB

Hand rails without foot paths


Material
M20 grade VRCC
No. of vertical end posts = 2 x 0.30x 0.20 x0.77 =

0.0924 cum

Internal vertical posts = 3x0.18x0.20x0.77 =

0.0832 cum

hand rail in2 tier =6.74-(2x0.3+3x0.18)=5.60 RM


quantity of RCC = 2x5.60x0.115x0.165 =

0.2125 cum

Total Concrete =

0.3881 cum

VRCC M 20 Grade
(A) Labour
0.86 nos

Mate

188.00

day

161.68

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

3371.78

(B) Material
8.10 cum

Cost of 12mm SS-5 HBG M/C metal

1134.93

cum

9192.93

5.40 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

6.75 cum

Sand at site

432.80

cum

2921.40

5.12 MT

Cement at site

5900.00

MT

30208.00

5251.12

Total

47573.45

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 35 KVA

620.00

hr

3720.00

Total

5790.00

(D) Form work


12.00 %

Form work @ 12% on (A)+(B)+( C)

56735.23

Cum

6808.23

(E)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)+(D)

12708.69

(F) Total of (A) + (B)+( C)+(D)+(E)

76252.15

(G) Add Contractors Profit at 10% on (F)

7625.22

Cost per 15 cum (F)+(G)

83877.37

Rate for 1 cum

5591.82

Cost of Railing for one side


0.3881 Cum

Cost per
Cost per 1 RM =

6.74 RM =

5591.82

cum

2170.19
321.99
321.99

Quantity

Description of Item

Rate

per

Rate to be adopted

Amount
322.00
1 RM

Hand rails without foot paths (Output =12.719 RM)


Material
M20 grade VRCC
No. of vertical end posts = 2 x 0.30x 0.20 x0.77 =

0.0924 cum

Internal vertical posts = 6x0.18x0.20x0.77 =

0.1663 cum

hand rail in2 tier =12.719-(2x0.3+6x0.18)=11.04 RM


quantity of RCC = 2x11.04x0.115x0.165 =

0.4189 cum

Total Concrete =

0.6776 cum

Cost of Railing for one side


0.6776 Cum

Cost per

12.719 RM =

5591.82

cum

Cost per 1 RM =

3789.02
297.90
297.90

Rate to be adopted

298.00
1 RM

Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700,
2100,2700 (4th Revision) for levelling course

Unit = cum

Page 335,500 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.86 nos

Mate

188.00

day

1.50 nos

Mason

193.40

day

290.10

Mazdoor

146.00

day

2920.00

20.00 nos

Total

161.68

3371.78

(B) Material
8.10 cum

Cost of 40mm SS-5 HBG M/C metal

897.43

cum

7269.18

4.05 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

cum

5381.15

1.35 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

cum

1312.78

6.75 cum

Sand at site

432.80

cum

2921.40

4.13 MT

Cement at site

5900.00

MT

24367.00

Total

41251.51

Machinery
6.00 hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00 hr

Generator set 33 KVA

620.00

hr

3720.00
5790.00

(D)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)

(E) Total of (A) + (B)+( C)+(D)


(F) Add Contractors Profit at 10% on (F)
Cost per 15 cum (E)+(F)
Rate for 1 cum

10082.66
60495.95
6049.60
66545.55
4436.37
4436.37

Rate to be adopted

4436.00

Quantity

Description of Item

Rate

per

Amount
1 Cum

Quantity

Description of Item

Rate

per

Amount

Providing Grouted Revetment with SS Revetment 225 mm thick grouted with 0.20 cum
of M-15 including cost, seigniorage charges and conveyance of materials to site and
including labour charges for packing the stones for revetment etc., complete for finished
item of work as per MoRT&H specification 2504 ( 4th revision ) and as directed by the
Engineer-in-Charge for quadrential revetment.

Cost of M-15

Page 331,522 of MoRT&H SDB

Taking output = 15 cum


(A) Labour
0.64 nos

Mate

188.00

day

120.32

1.00 nos

Mason

193.40

day

193.40

Mazdoor

146.00

day

2190.00

15.00 nos

Total

2503.72

(B) Material
8.10 cum

Cost of 40mm SS-5 HBG M/C metal

897.43

cum

7269.18

4.05 cum

Cost of 20mm SS-5 HBG M/C metal

1328.68

cum

5381.15

1.35 cum

Cost of 10mm SS-5 HBG M/C metal

972.43

cum

1312.78

432.80

cum

2921.40

5900.00

MT

24367.00

6.75

cum

Sand at site

4.13

MT

Cement at site
Total

41251.51

Machinery
6.00

hr

Concrete mixer 0.4/0.28 cum

345.00

hr

2070.00

6.00

hr

Generator set 33 KVA

620.00

hr

3720.00

2.00

hr

Water tanker 6 KL capacity

345.00

hr

Total

690.00
6480.00

Cost per 15 cum

50235.23

Rate for 1 cum

3349.02

Cost of Grouted Revetment


Unit = Cum
Taking output = 1 cum
(A) Labour
0.04 nos

Mate

188.00

day

7.52

0.35 nos

Mason

193.40

day

67.69

0.75 nos

Mazdoor for laying stones, filling quarry spalls

146.00

day

109.50

Total

184.71

(B) Material
0.20 cum

Cost of CC(1:4:8)

1.00 cum

Cost of SS Revetment 300 mm


Total

3349.02

cum

352.10

cum

669.80
352.10
1021.90

(C)
20.00 %

Add for Over head charges @ 20% on (A)+(B)

(D) Total of (A) + (B)+( C)


(E) Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)

241.32
1447.93
144.79
1592.72
1592.72

Rate to be adopted

1593.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Gravel backing behind revetment


with gravel including cost ,conveyance and
seigniorage of all materials to site etc., complete as per Clause 710.1.4 of IRC : 78and
as per MoRT&H Specification No. 2200 (4th Revision) and as per Drawing and technical
specifications for finished item of work
Unit = cum

Page 462 of MoRT&H SDB

Taking output = 10 cum


(A) Labour
0.28 nos

Mate

188.00

day

52.64

7.00 nos

Mazdoor

146.00

day

1022.00

Total

1074.64

(B) Material
12.00 cum

Cost of Granular material

187.00

cum

Total

2244.00
2244.00

Machinery
2.50 hr

Plate compactor/Power rammer/road roller

0.05 hr

Water tanker 6 KL capacity


Total

30.00

hr

75.00

345.00

hr

17.25
92.25

(D)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)

(E) Total of (A) + (B)+( C)+(D)


(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum

682.18
4093.07
409.31
4502.38
450.24
450.24

Rate to be adopted

450.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of
40 mm HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H
specifications to athickness of not less than 600mm with smaller size towards the soil
and bigger size towards the wall and provided over the entire surface behind the
abutment, wing wall and return wall to the full height compacted to a firm condition
including cost and conveyance of all metal seignorage charges ,and all labour charges
as directed by the departmental officers as per drawing and Technical specifications as
per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (4th Revision) for finished item
of work.
Unit = cum

Page 463 of MoRT&H SDB

Taking output = 10 cum


(A) Labour
0.32 nos

Mate

188.00

day

60.16

7.00 nos

Mazdoor for filling watering, ramming etc

146.00

day

1022.00

1.00 nos

Mazdoor skilled

193.40

day

193.40

Total

1275.56

(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
6.00 cum

Cost of 150mm size IRC soling stone (HBG)

356.60

cum

2139.60

6.00 cum

Cost of 40mm size IRC HBG metal

897.43

cum

5384.58

Total

7524.18

Machinery
0.06 hr

Water tanker 6 KL capacity


Total

345.00

hr

20.70
20.70

(D)
20.00 %

Add for Over head charges @ 20% on (A)+(B)+( C)

(E) Total of (A) + (B)+( C)+(D)


(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum

1764.09
10584.53
1058.45
11642.98
1164.30
1164.30

Rate to be adopted

1164.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

830.00
188.00
146.00

day
day
day

365.20
564.00
876.00
1805.20

44000.00
43000.00

MT
MT

46200.00
258.00
46458.00

Providing HYSD bars ( Fe-415 ) of diferent diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for sub structure
of R.C.C items.

Unit = MT
Taking output = 1 MT
(A)
0.44
3.00
6.00

Labour
nos
nos
nos

(B) Material
1.05 MT
6.00 Kg

Page 489,490 of MoRT&H SDB

Mate
Black smith
Mazdoor
Total
HYSD bars including overlaps
Binding wire
Total

(C)
20.00 %
Add for Over head charges @ 20% on (A)+(B)
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

9652.64
57915.84
5791.58
63707.42
63707.42
63707.00
1 MT

Quantity

Description of Item

Rate

per

Amount

188.00
188.00
146.00

day
day
day

82.72
564.00
1168.00
1814.72

44000.00
43000.00

MT
MT

46200.00
344.00
46544.00

Providing HYSD bars ( Fe-415 ) of diferent diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision)
and as per I.S.1786 of 1985 for
Super
structure of R.C.C items.

Unit = MT
Taking output = 1 MT
(A)
0.44
3.00
8.00

Labour
nos
nos
nos

(B) Material
1.05 MT
8.00 Kg

Page 489,490 of MoRT&H SDB

Mate
Black smith
Mazdoor
Total
HYSD bars including overlaps
Binding wire
Total

(C)
20.00 %
Add for Over head charges @ 20% on (A)+(B)
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

9671.74
58030.46
5803.05
63833.51
63833.51
63834.00
1 MT

Quantity

Description of Item

Rate

per

Amount

Providing weep holes in PCC/RCC for abutments , return walls and wing walls with
100mm dia AC pipe extending through the full width of the structure with slope of 1V :
20H towards draining face complete as per drawing and technical specifications no
MORTH 2706,2200

Cement mortor [1:3]

Unit = 30.00Rm

0.51

Mt

cement

3400.00

mt

1734.00

1.05

cum

sand

432.80

cum

454.44

0.04

nos

Mate

145.00

each

5.80

0.90

nos

Mazdoor

101.00

each

90.90
2285.14

Materilals
31.50

Rm

cost of 100mm dia AC pipes including 5% wastage

35.00

Rm

1102.50

10.00

nos

collor for AC pipe

15.00

No

150.00

30.00

nos

MS clamp

8.00

No

240.00

0.05

cum

cement mortor [1:3]

2285.14

cum

114.26
1606.76

Labour
0.03

nos

Mate

145.00

each

4.35

0.50

nos

Mason

136.70

each

68.35

0.25

nos

Mazdoor

101.00

each

25.25
97.95
1704.71

0.20

over head charges@20%

3311.46

662.29
2367.00

rate per 1Rm


(F) Add Contractors Profit at 10% on (E)
Rate per Cum

78.90
7.89
86.79
86.79

Rate per 1Rm

87.00
1Rm

Quantity

Description of Item

Rate

per

Amount

42500.00

mt

170.00

151.00

cum

302.00
66.00

Providing and fixing of CI drainage spouts complete as per MORTH specification and as
per drawing No.BD1/1-69

Taking out put : 1No


4.00

kg

Structural steel

2.00

nos

100mm dia 1m lomg GI pipe

6.00

nos

100mm dia GI bolt

11.00

each

2.00

nos

Galvonised MS flat clamp

25.00

each

50.00
588.00

Labour
0.02

nos

Mate

188.00

each

3.76

0.02

nos

skilled black smith

193.40

each

3.87

0.02

nos

Mazdoor

146.00

each

2.92

0.01

nos

Mate

188.00

each

1.88

0.01

nos

skilled black smith

193.40

each

1.93

0.20

nos

Mazdoor

146.00

each

29.20

cost of material and labour


elecrtodes etc

613.56

Labour fixation in position

0.05

30.68
74.24
662.24

0.20

over head charges@20%

662.24

(F) Add Contractors Profit at 10% on (E)

794.69

132.45
794.69
79.47

Rate per Cum

874.16
874.16

Rate per 1Rm

874.00
1Rm

Providing Mastic pad 2'. 0" x 4'. 0" (0.60 M x 1.20 M) of 1"
(25.40mm) for expansion joints including cost, conveyance and
placing in position and all labour charges for fixing etc., complete as
directed by the engineer in charge of the work.

1.00

sqm

Rate of mastic pads


Rate per one sqm

805.00

sqm

805.00
805.00
/sqm

Quantity

Description of Item

Rate

per

Amount

Construction of Granular sub-base by providing HBG material confirming to Grading - III


of MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all
materials to work site and spreading in uniform layers with motor grader or by approved
means, on prepared surface mixing by mix in place method with Rotavator / approved
means at OMC and compacting with vibratory roller to achieve the desired density etc.,
complete for finished item of work as per MoRT&H Specification 401 (4th revision) and
as directed by the Engineer-in-charge.
Unit = cum
Taking output = 300 cum

Page 95 of MoRT&H SDB

(A) Labour
0.40 day

Mate

188.00

day

75.20

2.00 day

Mazdoor skilled

193.40

day

386.80

8.00 day

Mazdoor unskilled

146.00

day

1168.00

Total

1630.00

(B) Machinery
6.00 hr
12.00 hr

Motor grader 3.35M Blade @50 cum/Hr


Tractor with Rotavator

2600.00

hr

15600.00

345.00

hr

4140.00

6.00 hr

Vibratory roller 8T

1550.00

hr

9300.00

3.00 hr

Water tanker 6 KL

345.00

hr

Total
(C) Material
255.00 cum
129.00 cum

Coarse graded Granular sub-base material as per


9.5mm
to 4.75mm
@ 66%
Table 400-2
of MORT&H
(Average rate of 9.5-11.2mm & 5-7mm HBG M/C
2.36mm and below @34%
metal)
(Rate of 2.36mm & below HBG metal)
Total

1035.00
30075.00

782.43

Cum

199519.65

429.60

Cum

55418.40
254938.05
286643.05

5% Total of (A) + (B)+( C)+(D)

17198.58
303841.63

(F) Add Contractors Profit at 10% on (E)


Cost per 300 cum (E) + (F)
Rate per 1 cum

30384.16
334225.80
1114.09
1114.09

Rate to be adopted

1114.00
1 Cum

Quantity

Description of Item

Rate

per

Amount

90.24

Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to
Wet Mix macadem specification including cost,seignorage of all materials and including
premixing the material with water at OMC in Mechanical mix plant carriage of mixed
material by tipper to site , laying in uniform layers in base courses on well prepared
surface and compacting with Vibratory roller to acheive the desired density etc., as
directed by the Engineer-in-Charge and as per MoRT&H specification.406 (4th revision)
for finished item of work.

Unit = cum

Page 110,111 of MoRT&H SDB

Taking output = 225 cum


(A) Labour
0.48 nos.

Mate

188.00

day

2.00 nos.

Mazdoor skilled

193.40

day

386.80

Mazdoor

146.00

day

1460.00

10.00 nos.

Total

1937.04

(B) Machinery
6.60 hr

Wet mix plant of 60 tonne hr. capacity

1320.00

hr

8712.00

6.00 hr

Electric generating set 125 KVA

1090.00

hr

6540.00

6.00 hr

front end loader 1 cum capacity

1320.00

hr

7920.00

6.00 hr

Mechanical Paver finisher 100 TPH

1090.00

hr

6540.00

3.90 hr

Vibratory roller 8-10 T

1550.00

hr

6045.00

3.00 hr

Water tanker

345.00

hr

1035.00

Total

36792.00

(C) Material
89.10 cum

45 to 22.40mm IRC HBG metal @ 30%

1178.68

cum

105020.39

962.18

cum

114306.98

(Av. Of 40-45, 25-27, 19-22mm )


118.80 cum

22.4 to 2.36mm IRC HBG metal @ 40%

(Av. Of 19-22, 12-14, 9.5-11.2, 5-7mm and 2.36mm & below)


89.10 cum

2.36mm to 75 micron @ 30% (2.36mm & below)


Total

429.60

cum

38277.36
257604.73

(D)
5.00 %

Add for Over head charges @ 5% on (A)+(B)+( C)

(E) Total of (A) + (B)+( C)+(D)


(F) Add Contractors Profit at 10% on (E)
Cost per 225 cum (E) + (F)
Rate per 1 cum

14816.69
311150.46
31115.05
342265.51
1521.18
1521.18

Rate to be adopted per 1 cum

1521.00
Cum

Quantity

Description of Item

Rate

per

Amount

Providing and applying prime coat with bitumen Emulsion (Medium settting) (Bulk)
using Emulsion pressure distributor at the rate of 0.60 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of work as
per MoRT&H Specification 503 (4th revision) and as directed by the Engineer-in-Charge.

unit = sqm

Page 124 of MoRT&H SDB

Taking output = 3500 sqm


(A) Labour
0.08 nos

Mate

188.00

day

15.04

2.00 nos

Mazdoor

146.00

day

292.00

Total

307.04

(B) Machinery
2.80 hr

Mechanical broom Hydraulic @ 1250 sqm/hr.

290.00

hr

812.00

2.80 hr

Air compressor 250 cfm

370.00

hr

1036.00

2.00 hr

Emulsion pressure distributor @1750 sqm/hr

600.00

hr

1200.00

1.00 hr

Water tankar 6Kl

hr

Total

0.00
3048.00

(C) Material
2.10 MT

Bitumen Emulsion @ 0.60 Kgs/sqm


Total

40406.70

MT

84854.07
84854.07

(D)
5.00 %

Add for Over head charges @ 5% on (A)+(B)+( C)

(E) Total of (A) + (B)+( C)+(D)


(F) Add Contractors Profit at 10% on (E)
Cost per 3500 sqm (E) + (F)
Rate per 1 sqm

4410.46
92619.57
9261.96
101881.53
29.11
29.11

Rate to be adopted

29.00
1 Sqm

Quantity

Description of Item

Rate

per

Amount

Providing and applying tack coat with bitumen Emulsion (Medium settting) (Bulk) using
Emulsion pressure distributor at the rate of 0.20 kgs per sqm on the prepared
bituminous/granular surface cleaned with mechanical broom for finished item of work as
per MoRT&H Specification 503 (4th revision) and as directed by the Engineer-in-Charge.
unit = sqm

Page 124 of MoRT&H SDB

Taking output = 3500 sqm


(A) Labour
0.08 nos

Mate

188.00

day

15.04

2.00 nos

Mazdoor

146.00

day

292.00

Total

307.04

(B) Machinery
2.80 hr

Mechanical broom Hydraulic @ 1250 sqm/hr.

290.00

hr

812.00

2.80 hr

Air compressor 250 cfm

370.00

hr

1036.00

2.00 hr

Emulsion pressure distributor @1750 sqm/hr

600.00

hr

1200.00

Total

3048.00

(C) Material
0.70 MT

Bitumen Emulsion @ 0.20 Kgs/sqm

40406.70

MT

Total

28284.69
28284.69

(D)
5.00 %

Add for Over head charges @ 5% on (A)+(B)+( C)

31332.69

1581.99

(E) Total of (A) + (B)+( C)+(D)

33221.72

(F) Add Contractors Profit at 10% on (E)

3322.17

Cost per 3500 sqm (E) + (F)

36543.89

Rate per 1 sqm

10.44
10.44

Rate to be adopted

10.40
1 Sqm

Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant


using hard blasted granite crushed aggregates of Grading -2 as per table 500-15 of
specification 508 of MoRT&H (4th Revision), premixed with bituminous binder 60/70
grade @ 5% of mix and filler, transporting the hot mix to work site, laying with
mechanical paver finisher to the required grade, level and alignment, rolling with
smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per
MoRT&H Specification 508 (4th Revision) complete for finished item of work in all
respects as directed by Engineer-in-charge
Unit = cum

Page 135,136,137 of MoRT&H SDB

Taking output = 195 cum (450 tonnes.)


(A) Labour
0.84

nos.

14.00

nos.

5.00

nos.

Mate
Mazdoor working with HMP, Mechanical broom,
paver,roller,asphalt cutter and assistance for
setting
outlines,levels
and layout
of construction.
Skilled Mazdoor
for checking
line and
levels.

188.00

day

157.92

193.40

day

2707.60

146.00

day

Total

730.00
3595.52

(B) Machinary
11.00

hr

Hot mix plant 40 to 60 TPH

15525.00

hr

170775.00

6.00

hr

6.00

hr

Mechanical Paver finisher @ 100 TPH

1090.00

hr

6540.00

Generator 250 KVA

1550.00

hr

9300.00

6.00

hr

3.90

hr

Front end loader 1 cum capacity


Power road roller 8 tonne for initial break down
rolling
Vibratory roler 8 tonne for intermediate rolling
Finish rolling with 6-8 tonne smooth wheeled
tandem roller.

1320.00

hr

7920.00

540.00

hr

2106.00

3.90

hr

3.90

hr

1550.00

hr

6045.00

1035.00

hr

4036.50

Quantity

Description of Item

Rate

per

Total

Amount
206722.50

(C) Material
22.50

M.T

(I) Bitumen @ 5% by weight of mix

45858.33

MT

1031812.53

(ii) Aggregate
For Grading II
162.450

cum

9.50mm to 4.75mm HBG m/c chips @ 57%

782.43

cum

127105.75

116.850

cum

4.75mm and below @ 41%

497.27

cum

58105.42

5.70

cum

Filler @ 2% of weight of aggregates.

429.60

cum

Total

2448.72
1219472.42

(D)
5.00

Add for Over head charges @ 5% on (A)+(B)+( C)

71489.52

(E) Total of (A) + (B)+( C)+(D)

1501279.96

(F) Add Contractors Profit at 10% on (E)

150128.00

Cost per 195 cum (E) + (F)

1651407.96

Rate per 1 cum

8468.76
8468.76

Rate to be adopted

8469.00
1 Cum

Forming embankmetn with gravel including cost, seigniorage charges and conveyance
of all materials to work site and spreading in uniform layers by approved means, on
prepared surface and compacting with vibratory roller to achieve the desired density at
OMC etc., complete for finished item of work as per MoRT&H Specification 401& 407
(4th revision) and as directed by the Engineer-in-charge.
Unit = cum
Taking output = 300 cum
(A) Labour
0.40 day

Mate

188.00

day

2.00 day

Mazdoor skilled

193.40

day

386.80

8.00 day

Mazdoor unskilled

146.00

day

1168.00

Total

75.20

1630.00

(B) Machinery
6.00 hr

Vibratory roller 8T

1550.00

hr

9300.00

3.00 hr

Water tanker 6 KL

345.00

hr

1035.00

Total

10335.00

(C) Material
384.00 cum

Gravel

187.00

71808.00

(D)
5.00 %

Add for Over head charges @ 5% on (A)+(B)+( C)

(E) Total of (A) + (B)+( C)+(D)


(F) Add Contractors Profit at 10% on (E)
Cost per 300 cum (E) + (F)
Rate per 1 cum

4188.65
87961.65
8796.17
96757.82
322.53
322.53

Rate to be adopted

323.00
1 Cum

Name of work : Construction of High Level Bridge @ Km.21/200 of Butchi - Dagadarthi Road

CERTIFICATES
1)
2)
3)
4)
5)

Certified that the leads provided in the lead statement are the shortest
Certified that the distances noted herein are correct
Certified that the quarries are the nearest and are having sufficient yield
Certified that the routes shown are the nearest
Certiified that the description of the variety of materials noted are correct
to the best of my knowledge

Name of work : Construction of High Level Bridge @ Km.21/200 of Butchi Dagadarthi Road

CERTIFICATE
1)

Certified that I have inspected the Bithci Dagadarthi road km


21/2 in SPSR Nellore district on ---------------------------- and the
provisions provided in the estimate are necessary and
adequate as per the field conditions

Superintending Engineer (R&B)


Nellore

FIELD PARTICULARS OF BRIDGE CHECK LIST


[ To be Submitted by the field staf ]

1) SITE PLAN

2) LS OF ROAD

Site plan with chainage , distance , bearings of


road and stream with proposed alignment.
Alternative alignments, showing the apporaches
to be straight for a length of 100m on the both
sides of the bridge duly avoiding curve in bridge
:
portion. The skew angle of the bridge if any, to
be marked in the site plan with respect to the
direction (ie. Flow direction to be marked clearly
on the up stream side of the bridge with an arrow
mark)
The chainage of the proposed road and existing
road with possible position of piers and
abutments to be marked on the LS along with
bores showing various soil strata met. The :
proposed gradients also to be marked on the LS
duly showing approach length of 500mts on both
sides

Site plan based on


total station survey
is enclosed

Yes

3) LS OF STREAM

LS of stream both on U/S and D/S for a distance


of 500m from the center of the bridge for bed :
slope calculation of the stream.

Yes

CROSS
4) SECTIONS
OF STREAM

Five cross sections [ Normal to stream] one at


the site of crossing, two on U/S and two on D/S
side at a distance of 250m and 500m resp. The
:
sill leel of the stream to be marked on lowest bed
level of the cross sections recommended by the
Superintending Engineer

Yes

5) DISCHARGE

Discharge calculations by A-V method at all five


cross sections of the stream. Discharge
calculations by C-A method with rain fall data :
and also the original topo map for verifying the
catchment area

Enclosed

Calculations fo linear water way and requirement


:
of LWW from the site condition

Enclosed

7) MFL

The MFL to be marked on all the cross sections of


the stream and also on the LS of the road. The
MFL spread width should be matched both in the :
site plan and cross sections at the site of
crossing, if not reasons should explained.

Yes

8) SCOUR DEPTH

Calculations of scour depth, type of foundations


and proposed foundation levels, type of bed :
material in the stream for silt factor calculations

Enclosed

Test results of sub soil with SBC calculations from


(R&B) test centers recommended SBC from the :
Superintending Engineer

Enclosed

6)

9)

LINEAR
WATERWAY

SUB SOIL
RESULTS

// 2 //
10) CERTIFICATES

Separate certificate for each item of earth work,


metal, sand, quarry of metal and bitumen :
supported by lead distances

Enclosed
Crust as in existing

11) DESIGN CRUST

Design crust proposed along with CBR value and


:
traffic intensity in CVPD

road is sufficient
and is proposed

12)

Typical cross sections of he existing road and proposed road on


both sides fo approaches

Enclosed

13)

Certificate of the inspection and adequacy of provisions made in


the estimate

Enclosed

14)

Superintending Engineer's report specific recommendations for


LWW and type of foundations etc.,

Enclosed

You might also like