The below table shows the data collected as per survey done by
NMCs Zonal Health officer.
Survey Data
Families not having individual 9395
toilets
Families
going
for
open 5593
defecation
Applications sanctioned by zonal 1128
committee
.
Survey Data
52 (610 Seats)
29
To be Repaired
In Working Condition
To be Constructed (Proposed)
21
2
7 (70 Seats)
Budget required
defecation Free
Item
for
making
Number of Units
Construction of IHHT
5593
Construction
of 21(Repaired)
Community Toilet
+7(New)
Construction of Public 88
Toilet
Total
O and M Cost
Nagpur
Open
Total
Budget
Required
8.95 Crores
42 lakh
150000
1.32 Crores
10.69 Crore
2 crores per
year