Professional Documents
Culture Documents
In this chapter we consider the automated equipment used in the processing of discrete parts in
large volumes. The equipment is often in the configuration of mechanically integrated tiow lines,
consisting of a number of workstations that perform the processing operations on the line. These
flow lines are called transfer machines or transfer lines. The methods used to transport parts
between stations are examined in this chapter as well as the other features that characterize these
production systems. We emphasize machining operations as the typical process carried out on these
systems, although the automated flow line concept is used in a variety of industries and processes.
Leave a reply
An automated flow line consists of several machines or workstations which are linked together by
work handling devices that transfer parts between the stations. The transfer of work parts occurs
automatically and the workstations carry out their specialized functions automatically. The flow line
can be symbolized as shown in Figure 4.1 using the symbols presented in Table 4.1. A raw work part
enters one end of the line and the processing steps are performed sequentially as the part moves
from one station to the next. It is possible to incorporate buffer storage zones into the flow line, either
at a single location or between every workstation.
the most appropriate means of production in cases of relatively stable product life ; high product
demand, which requires high rates of production; and where the alternative method of manufacture
would involve a large labor content. The objectives of the use of flow line automation are, therefore :
To reduce labor costs
To increase production rates
To reduce work-in-process
To minimize distances moved between operations
To achieve specialization of operations
To achieve integration of operations
Although Figure 4.1 shows the flow pattern of operations in a straight line, there are actually two
general forms that the work flow can take. These two configurations are in line and rotary.
In-line type
The in-line configuration consists of a sequence of workstations in a more-or-less straight-line
arrangement. The flow of work can take a few 90 turns, either for work piece reorientation, factory
layout limitations, or other reasons, and still qualify as a straight-line configuration. A common
pattern of work flow, for example, is a rectangular shape, which would allow the same operator to
load the starting workpieces and unload the finished workpieces. An example of an in-line transfer
machine used for metal-cutting operations is illustrated in Figure 4.2.
Rotary type
In the rotary configuration, the work parts are indexed around a circular table or dial. The work
stations are stationary and usually located around the outside periphery of the dial. The parts ride on
the rotating table and are registered or positioned, in turn, at each station for its processing or
assembly operation. This type of equipment is often referred to as an indexing machine or dial index
machine and the configuration is shown in Figure 4.3.
Selection
The choice between the two types depends on the application. The rotary type is commonly limited
to smaller workpieces and to fewer stations. There is generally not as much flexibility in the design of
the rotary configuration. For example, the dial-type design does not lend itself to providing for buffer
storage capacity. On the other hand, the rotary configuration usually involves a lower-cost piece of
equipment and typically requires less factory floor space.
a built-in storage capability to smooth out the effect of work stoppages at individual stations and
other irregularities.
The transfer mechanism of the automated flow line must not only move the partially completed work
parts or assemblies between adjacent stations, it must also orient and locate the parts in the correct
position for processing at each station. The general methods of transporting work pieces on flow
lines can be classified into the following three categories :
1. Continuous transfer
2. Intermittent or synchronous transfer
3. Asynchronous or power-and-free transfer
These three categories are distinguished by the type of motion that is imparted to the work piece by
the transfer mechanism. The most appropriate type of transport system for a given application
depends on such factors as :
Before discussing the three types of work transport system, we should try to clarify a possible source
of confusion. These transfer systems are used for both processing and assembly operations. In the
case of automatic assembly machines, we are referring to the mechanisms that transport the
partially completed assemblies between stations, not the feed mechanisms that present new
components to the assemblies at a particular station. The devices that feed and orient the
components are normally an integral part of the workstation. We take a closer look at these devices
in Chapter 7 when we discuss automatic assembly in more detail.Continuous transferWith the
continuous method of transfer, the work parts are moved continuously at constant speed. This
requires the work heads to move during processing in order to maintain continuous registration with
the work part. For some types of operations, this movement of the work heads during processing is
not feasible. It would be difficult, for example, to use this type of system on a machining transfer line
because of inertia problems due to the size and weight of the work heads. In other cases, continuous
transfer would be very practical. Examples of its use are in beverage bottling operations, packaging,
manual assembly operations where the human operator can move with the moving flow line, and
relatively simple automatic assembly tasks. In some bottling operations, for instance, the bottles are
transported around a continuously rotating drum. Beverage is discharged into the moving bottles by
spouts located at the drums periphery. The advantage of this application is that the liquid beverage
is kept moving at a steady speed and hence there are no inertia problems.Continuous transfer
systems are relatively easy to design and fabricate and can achieve a high rate of
production.Intermittent transferAs the name suggests, in this method the workpieces are
transported with an intermittent or discontinuous motion. The workstations are fixed in position and
the parts are moved between stations and then registered at the proper locations for processing. All
work parts are transported at the same time and, for this reason, the term synchronous transfer
system is also used to describe this method of work part transport. Examples of applications of the
intermittent transfer of work parts can be found in machining operations, press working operations
or progressive dies, and mechanized assembly. Most of the transfer mechanisms reviewed in
Section 4.3 provide the intermittent or synchronous type of work part transport.Asynchronous
transferThis system of transfer, also referred to as a power-and-free system, allows each work
part to move to the next station when processing at the current station has been completed. Each
part moves independently of other parts. Hence, some parts are being processed on the line at the
same time that others are being transported between stations. Asynchronous transfer systems offer
the opportunity for greater flexibility than do the other two systems, and this flexibility can be a great
advantage in certain circumstances. In-process storage of work parts can be incorporated into the
asynchronous systems with relative ease. Power-and-free systems can also compensate for line
balancing problems where there are significant differences in process times between stations.
Parallel stations or several series stations can be used for the longer operations, and single stations
can be used for the shorter operations. Therefore, the average production rates can be
approximately equalized. Asynchronous lines are often used where there are one or more manually
operated stations and cycle-time variations would be a problem on either the continuous or
synchronous transport systems. Larger work parts can be handled on the asynchronous systems. A
disadvantage of the power-and-free systems is that the cycle rates are generally slower than for the
other types.Pallet fixturesThe transfer system is sometimes designed to accommodate some sort of
pallet fixture. Work parts are attached to the pallet fixtures and the pallets are transferred between
stations, carrying the part through its sequence of operations. The pallet fixture is designed so that it
can be conveniently moved, located, and clamped in position at successive stations. Since the part
is accurately located in the fixture, it is therefore correctly positioned for each operation. In addition to
the obvious advantage of convenient transfer and location of work parts, another advantage of pallet
fixtures is that they can be designed to be used for a variety of similar parts.
The other method of work part location and fixturing does not use pallets. With this method, the
workparts themselves are indexed from station to station. When a part arrives at a station, it is
automatically clamped in position for the operation.
The obvious benefit of this transfer method is that it avoids the cost of pallet fixtures
TRANSFER MECHANISMS
There are various types of transfer mechanisms used to move parts between stations. These
mechanisms can be grouped into two types: those used to provide linear travel for in-line machines,
and those used to provide rotary motion for dial indexing machines.Linear transfer mechanisms
We will explain the operation of three of the typical mechanisms: the walking beam transfer bar
system, the powered roller conveyor system, and the chain-drive conveyor system. This is not a
complete listing of all types, but it is a representative sample.WALKING BEAM SYSTEMS. With the
walking beam transfer mechanism, the work parts are lifted up from their workstation locations by a
transfer bar and moved one position ahead. to the next station. The transfer bar then lowers the
parts into nests which position them more accurately for processing. This type of transfer device is
SYSTEM. This type of system is used in general stock handling systems as well as in automated flow
lines. The conveyor can be used to move pans or pallets possessing flat riding surfaces The rollers
can be powered by either of two mechanisms. The first is a belt drive, in which a flat moving belt
beneath the rollers provides the rotation of the rollers by friction. A chain drive is the second common
mechanism used to power the rollers. Powered roller conveyors are versatile transfer systems
because they can be used to divert work pallets into workstations or alternate tracks. We discuss
roller conveyor systems in Chapter 14.
CHAIN-DRIVE CONVEYOR SYSTEM. Figure 4.5 illustrates this type of transfer system. Either a
chain or a flexible steel belt is used to transport the work carriers. The chain is driven by pulleys in
either an over-and-under configuration, in which the pulleys turn about a horizontal axis, or an
around-the-corner configuration, in which the pulleys rotate about a vertical axis.
This general type of transfer system can be used for continuous, intermittent, or non synchronous
movement of work parts. In the non synchronous motion, the work parts are pulled by friction or ride
on an oil film along a track with the chain or belt providing the movement. It is necessary to provide
some sort of final location for the work parts when they arrive at their respective stations.
BUFFER STORAGE
Automated flow lines are often equipped with additional features beyond the basic transfer
mechanisms and workstations. For example, the idea of using a buffer storage capacity between
stations was introduced in Section 4.1. It is not uncommon for production flow lines to include
storage zones for collecting banks of work parts along the line. One example of the use of storage
zones would be two intermittent transfer systems, each without any storage capacity, linked together
with a work part inventory area. It is possible to connect three, four, or even more lines in this
manner. Another example of work part storage on flow lines is the asynchronous transfer line. With
this system, it is possible to provide a bank of work parts for every station on the line.
There are two principal reasons for the use of buffer storage zones. The first is to reduce the effect of
individual station breakdowns on the line operation. The continuous or intermittent transfer system
acts
as a single integrated machine. When breakdowns occur at the individual stations or when
preventive maintenance is applied to the machine, production must be halted. In many cases, the
proportion of time the line spends out of operation can be significant, perhaps reaching 50% or
more. Some of the common reasons for line stoppages are :
Defective work parts or components at assembly stations, which require that the feed
mechanism be cleared
When a breakdown occurs on an automated flow line, the purpose of the buffer storage zone is to
allow a portion of the line to continue operating while the remaining portion is stopped and under
repair. For example, assume that a 20-station line is divided into two sections and connected by a
parts storage zone which automatically collects parts from the first section and feeds them to the
second section. If a station jam were to cause the first section of the line to stop, the second section
could continue to operate as long as the supply of parts in the buffer zone lasts. Similarly, if the
second section were to shut down, the first section could continue to operate as long as there is
room in the buffer zone to store parts. Hopefully, the average production rate on the first section
would be about equal to that of the second section. By dividing the line and using the storage area,
the average production rate would be improved over the original 20-station flow line. A quantitative
analysis of the effect of adding buffer inventory zones will be presented in Chapter 5. Figure 4.10
illustrates the case of two processing lines separated by a storage buffer.
assembly line on which all the stations are mechanized except one. The manual station requires the
operator to perform an alignment of two components and the time required tends to vary from cycle
to cycle. For the transfer system in this line, we must choose between a synchronous system with no
parts storage capacity and an asynchronous system which allows a float of parts ahead of each
station. To illustrate this difference in operation, let us consider the following example.
EXAMPLE 4.2
Assume that we have collected data on the operation and found the following distribution of
operation times for a total of 100 cycles: 7 s; two occurrences, or 29; 8 s; 10%: 9 s; 18%; 10 s; 38%;
11s; 20% and 12 s; 12%. This gives an average of 10 s. If this manual operation were used on the
synchronous machine. the line would have to be set up with cycle time of 12 s to allow the operator
time to finish all assemblies. This would give a production rate of 300 units/h from the line. If the
cycle time
were adjusted to 11 s, the cycle rate would increase to 327 per hour. but the operator
would be unable to complete 12% of the assemblies. Thus, the actual production rate of completed
assemblies would be only 288 units/h. If the cycl time were decreased to 10 s, the cycle rate would
increase to 360 per hour. However, the operator would be unable to complete the assemblies
requiring 11 s and 12 s. The actual production rate would suffer a decrease to 245 units/h.
With the asynchronous transfer system. the line could be arranged to collect a bank of work parts
immediately before and after the manual station. Thus, the operator would be allowed a range of
times to complete the alignment process. As long as the operators average time were compatible
with the cycle time of the transfer system, the flow line would run smoothly. The line cycle time could
be set at 10 s and the production rate would be 360 good assemblies per hour.
The disadvantages of buffer storage on flow lines are increased factory floor space. higher inprocess inventory, more material handling equipment, and greater complexity of the overall flow line
system. The benefits of buffer storage are often great enough to more than compensate for these
disadvantages.
Controlling an automated flow line is a complex problem, owing to the sheer number of sequential
steps that must be carried out. There are three main functions that are utilized to cont,l the operation
of an automatic transfer system. The first of these is an operational requirement, the second is a
safety requirement, and the third is dedicated to improving quality.
1. Sequence control. The purpose of this function is to coordinate the sequence of actions of
the transfer system and its workstations. The various activities of the automated flow line
must be carried out with split-second timing and accuracy. On a metal machining transfer
line, for example, the work parts must be transported, located, and clamped in place before
the work heads can begin to feed. Sequence control is basic to the operation of the flow line.
2. Safety monitoring. This function ensures that the transfer system does not operate in an
unsafe or hazardous condition. Sensing devices may be added to make certain that the
cutting tool status is satisfactory to continue to process the work part in the case of a
machining-type transfer line. Other checks might include monitoring certain critical steps in
the sequence control function to make sure that these steps have all been performed and in
the correct order. Hydraulic or air pressures might also be checked if these are crucial to the
operation of automated flow lines.
3. Quality monitoring. The third control function is to monitor certain quality attributes of the
work part. Its purpose is to identify and possibly reject defective work parts and assemblies.
The inspection devices required to perform quality monitoring are sometimes incorporated
into existing processing stations. In other cases, separate stations are included in the line for
the sole purpose of inspecting the work part.
It is possible to extend the notion of quality monitoring and to incorporate a control loop into the flow
line as illustrated in Figure 4.11. An inspection station would be used to monitor certain quality
characteristics of the part and to feed back information to the preceding workstations so that
adjustments in the process could be made.
The traditional means of controlling the sequence of steps on the transfer system has been to use
electromechanical relays. Relays are employed to maintain the proper order of activating the work
heads, transfer mechanism, and other peripheral devices on the line. However, owing to their
comparatively large size and relative unreliability, relays have lost ground to other control devices,
such as programmable controllers and computers. These more modern components offer
opportunities for a higher level of control over the flow line, particularly in the areas of safety
monitoring and quality monitoring.
the failures are random and infrequent, it may be better to continue to operate the machine and lock
out the affected assembly from further operations. If the assembly machine were stopped,
production would be lost at all other stations while the machine is down. Deciding whether it is better
to stay in operation or stop the line must be based on the probabilities and economics of the
particular case. The point is that there are alternative control strategies to choose between,
instantaneous control and memory control.
1. Instantaneous control. This mode of control stops the operation of the flow line immediately
when a malfunction is detected. It is relatively simple, inexpensive, and trouble-free.
Diagnostic features are often added to the system to aid in identifying the location and cause
of the trouble to the operator so that repairs can be quickly made. However, stopping the
machine results in loss of production from the entire line, and this is the systems biggest
drawback.
2. Memory control. In contrast to instantaneous control, the memory system is designed to
keep the machine operating. It works to control quality and/or protect the machine by
preventing subsequent stations from processing the particular work part and by segregating
the part as defective at the end of the line. The premise upon which memory-type control is
based is that the failures which occur at the stations will be random and infrequent. If,
however, the station failures result from cause (a work head that has gone out of alignment,
for example) and tend to repeat, the memory system will not improve production but, rather,
degrade it. The flow line will continue to operate, with the consequence that bad parts will
continue to be produced. For this reason, a counter is sometimes used so that if a failure
occurs at the same station for two or three consecutive cycles, the memory logic will cause
the machine to stop for repairs.
Tolerance requirements
Production-rate requirements
Reliability of individual stations and transfer mechanisms, as well as overall reliability of the
line
Ease of maintenance
In developing the concept for a mechanized flow line, there are two general approaches that can be
considered. The first is to use standard machine tools and other pieces of processing equipment at
the workstations and to connect them with standard or special material handling equipment. The
material handling hardware serves as the transfer system and moves, feeds, and ejects the work
between the standard machines. The line of machines is sometimes referred to as a link line. The
individual machines must either be capable of operating on an automatic cycle or they must be
manually operated. There may also be fixturing and location problems at the stations which are
difficult to solve without some form of human assistance during the cycle. A firm will often prefer the
link line because it can be made up from machine tools that are already in the plant, these machine
tools can be reused when the production run is finished, and there is less debugging and
maintenance. These flow lines can also be engineered by personnel within the firm, perhaps with the
aid of material handling experts. The limitation of these flow lines is that they favor simpler workpiece
shapes and smaller sizes since the work handling equipment is less sophisticated and more generalpurpose. Greater future use of industrial robots as material handling devices will increase the
attractiveness of the link line. This type of flow line is used in such processes as plating and finishing
operations, press-working, rolling mill operations, gear manufacturing, and a variety of machining
operations.
The alternative approach to developing an automated line is to turn the problem over to a machine
tool builder specializing in the fabrication of transfer lines, assembly machines, or other flow line
equipment. Using the customers blueprints and specifications, the builder will submit a proposal for
the line. Typically, several machine tool builders will be asked to make proposals. Each proposed
design will be based on the machine components comprising the builders product line as well as the
ingenuity and experience of the engineer preparing the proposal.
or transfer system, and work heads for performing the -various processing or assembly
operations. These standard components will be fabricated into the special configuration required for
the customers product. Several examples of these standard transferline components are pictured in
Figures 4.16 and 4.17. For metal-cutting transfer lines, the work heads consist of the feed
mechanism, spindle, and power source. The work heads must then be fitted with special tools to
carry out the particular process. These work heads do not have a frame or worktable. Instead, they
are attached to the transfer system frame, which has been specially adapted for the work part. When
a flow line has been fabricated using this building-block principle, it is sometimes referred to as a
unitized flow line. The standard machine tool components all go together and act as a single
mechanical unit.
Single-station machine
These mechanized production machines perform several operations on a single work part which is
fixtured in one position throughout the cycle. The operations are performed on several different
surfaces by work heads located around the piece. The available space surrounding a stationary
workpiece limits the number of machining heads that can be used. This limit on the number of
operations is the principal disadvantage of the single-station machine. Production rates are usually
low to medium.
Rotary indexing machine
To achieve higher rates of production, the rotary indexing machine performs a sequence
of machining operations on several workparts simultaneously. Parts are fixtured on a horizontal
circular table or dial, and indexed between successive stations. An example of a dial indexing
machine is shown in Figure 4.12.
Trunnion machine
This machine, shown in Figure 4.13. uses a vertical drum mounted on a horizontal axis, so it is a
variation of the dial indexing machine. The vertical drum is called a trunnion. Mounted on it are
several fixtures which hold the workparts during processing.
Trunnion machines are most suitable for small workpieces. The configuration of the machine, with a
vertical rather than a horizontal indexing dial, provides the opportunity to perform operations on
opposiJe sides of the workpart. Additional stations can be located on the outside periphery of the
tnmnion if this is required. The trunnion-type machine is appropriate for workparts in the medium
production range.
Transfer machine
The most highly automated and versatile of the machines is the transfer line, illustrated in Figures
4.2 and 4.15. The workstations are arranged in a straight-line flow pattern and parts are transferred
automatically from station to station. The transfer system can be synchronous or asynchronous,
workparts can be transported with or without pallet fixtures, buffer storage can be incorporated into
the line operation if desired, and a variety of different monitoring and control features can be used to
manage the line. Hence, the transfer machine offers the greatest flexibility of any of the machines
discussed. The transfer line can accommodate larger workpieces than the rotary-type indexing
systems. Also, the number of stations, and therefore the number of operations, which can be
included on the line is greater than for the circular arrangement. The transfer line has traditionally
been used for machining a single product in high quantities over long production runs. More recently,
transfer machines have been designed for ease of changeover to allow several different but similar
workparts to be produced on the same line. These attempts to introduce flexibility into transfer line
PROBLEMS
4.1. For the eight-slotted driven member of the Geneva mechanism in Figure 4.8, determine the
proportion of each complete revolution of the driver that motion is being imparted to the driven
member. Express this in degrees. How many degrees of rotation represent dwell ?
4.2. A Geneva mechanism with a six-slotted driven member is used in a dial-type assembly machine.
The longest assembly operation takes exactly 1s to complete, so the driven member must be in a
stopped (dwell) position for this length of time.
(a) At what rotational speed must the driver be turned to accomplish this 1-s dwell ?
(b) How much time will be required to index the dial to the next position ?
(c) Determine the ideal production rate of the assembly machine if each index of the dial produces a
completed work part.
4.3. A certain transfer line performs a sequence of machining and assembly operations. One of the
assembly operations near the end of the line is performed manually. The distribution of operation
times for the manual station is given in the following table.
Operation time (s)
15
2.7
16
6.1
17
12.1
18
25.9
19
32.1
20
10.9
21
6.9
100.0
uses a synchronous (intermittent) transfer system, determine the cycle rate and
actual production rate per hour if the transfer system were set to index parts at each of the following
intervals : once every 22 s. 21 s, 20 s, 19 s, 18 s. Time taken to move parts is negligible.
(b) If an asynchronous parts transfer system were used on this line to accumulate a float of parts
before the manual station, at what cycle rate should the system be operated ?
Determine the corresponding production rate.
transcend the manufacturing processes at individual stations. What is the effect of the number of
workstations on the performance of the line How much improvement can he obtained by using one
or more buffer storage zones? What is the effect of component quality on the operation of an
automated assembly machine? How will the use of manual workstations affect the line? These are
questions that can he analyzed using a systems approach.
In addition to the reliability problem, another systems design problem is one of properly balancing the
line. ln line balancing. the objective is to spread the total work load as evenly as possible among the
stations in the line. The problem is normally associated with the design of manual assembly lines. lt
is also a consideration in automated flow lines, but the reliability problem usually predominates We
will consider line balancing in Chapter 6. The reliability of the line will be the principal concern of the
present chapter.
$60.00/h or $l.00/min to operate the transfer line. Cutting tools are estimated to cost $0.15/work part.
Using the foregoing data, it is desired to compute the following measures of line performance :
(a) Production rate.
(b) Number of hours required to meet a demand of 1500 units/week.
(c) Line efficiency.
(d) Cost per unit produced.
Solution:
(a) The average production time per piece can be calculated from Eq. (5.1).
The average production rate for the line would be
determined by Eq. (5.3).
However, correcting for the scrap rate of 5%, the
actual production rate of good poducts is
(b) To compute the number of hours required to
produce 1500 units/week (we assume that this means 1500 good units plus scrap rather than 1500
with 5% scrap included), we divide the production rate of 35.625 units/h into the 1500-unit
requirement :
(c) The line efficiency is found by taking the ratio of the ideal cycle
time to the average productive time, according to Eq. (5.5).
. . . , n.
Since the parts are not removed when a station jam occurs, it is possible (although not probable) that
the part will jam at every station. The expected number of line stops per part passing through the line
can be obtained merely by summing up the probabilities p, over the n stations. Since each of the n
stations is processing a part each cycle, this expected number of line stops per part passing through
the line is equal to the frequency of line stops per cycle. Thus,
If the probabilities p are all equal, p1 = p2 = . . . =
pn = p, then
EXAMPLE 5.2
In a 10-station transfer line, the probability that a station breakdown will occur for a given work part is
equal to 0.01. This probability is the same for all 10 stations. Determine the frequency of line stops
per cycle on this flow line using the upper-bound approach.
Solution :
The value of F can be calculated from Eq. (5.10).
This is the value of F used in Example 5.1.
Lower-bound approach
The lower-bound approach gives an estimate of the lower limit on the expected number of line stops
per cycle. In this approach we assume that the station breakdown results in the destruction or
damage of the workpiece. For example, a drill or tap breaks off in the part during processing. The
broken tool must be replaced at the workstation and the work part must be removed from the line for
subsequent rework or scrap. Accordingly, the part cannot proceed to the next stations for further
processing.
Again, let p1 be the probability that a part will jam at a particular station i. Then, considering a given
work part as it proceeds through the line, p1 is the probability that the part will jam at station 1, and
(1- p1) is the probability that the part will not jam at station i and thus be available for subsequent
processing. The quantity p2(1- p1) is the probability that this given part will jam at station 2.
Generalizing, the quantity
is the probability that the given part will jam at any
station i. Summing all these probabilities from i = 1through n would give the probability or what has
previously been called the frequency of line stops per cycle. There is an easier way to determine this
frequency.
The probability that a given part will pass through all n stations without a line stop associated with its
processing is given by
Therefore, the frequency of line stops per cycle is provided by
if the probabilities pi that a part will jam at a
particular station are all equal, p1 = p2 . . . = pn = p. then
We might be tempted to view this frequency, F, as
the probability of a line stop per cycle, except that it is possible, in the upper-bound approach, for the
frequency of line stops per cycle to exceed unity. A probability greater than l cannot be interpreted.
With the lower-bound approach, the number of work parts coming off the line will be less than the
number starting. If the pans are removed from the line when a breakdown occurs, they are not
available to be counted as part of the output of the line. Therefore, the production-rate formula given
by Eq. (5.3) must be amended to reflect this reduction in output. Using the lower-bound approach,
the production-rate formula becomes
where F not only stands for the frequency of line stops but also the frequency of
pars removal. If no rework is performed, F is the scrap rate. Therefore, the term (1 F) represents
the yield of the transfer machine. Tp is interpreted to mean the average cycle time of the machine.
EXAMPLE 5.3
Compute the value of F using the lower-bound approach for the data of Example 5.2. Also compute
the production rate.
Solution:
From Eq. (5. l2) the value of F is
Although the value of F is smaller as calculated by the lowerbound approach, the difference is small. This difference grows as the value of p and the number of
workstations increase.
To compute the production rate, we must adjust Eq. (5.3), as indicated in the previous discussion, by
the value of F, Production time Tp was calculated in Example 5.1 as 1.6 min. Therefore, the
production rate
This is somewhat below the 35.6 pieces/h obtained
in Example 5.1, where the scrap rate was 0.05 rather than the 0.0956 computed here. We can
reason that the 5% scrap rate probably represents a mixture of the two cases assumed by the upperand lower-bound approaches. When breakdowns occur, the work parts are sometimes removed from
the line and other times they are not, The upper- and lower-bound approaches, as their names imply,
provide upper and lower limits on the frequency of downtime occurrences. However, these two
approaches also generate upper and lower limits on the production rate, assuming that station
breakdowns are the sole cause of scrap. Of course, the 5% scrap figure may also include other
conditions, such as poor quality of the work parts.
Some comments and observations
Determining whether the upper- or the lower-bound approach is more appropriate for a particular
transfer line requires knowledge about the operation of the line. The operator may be required to use
judgment in each breakdown to determine whether the work part should be removed. lf pans are
sometimes removed and sometimes not, the actual frequency of breakdowns will fall somewhere
between the upper and lower bounds. Of the two approaches, the upper-bound approach is
preferred, certainly for convenience of calculation and probably for accuracy also.
There are other reasons why line stops occur which are not directly related to workstations (e.g.,
transfer mechanism failure, schedule tool changes for all stations, preventive maintenance, product
changeover, etc.). These other factors must be taken into consideration when determining line
performance.
The biggest difficulty in using Eqs. (5.9) through (5.12) lies in determining the values of p1 for the
various stations. Perhaps the best approach is to base the values of p1 on previous historical data
and experience with similar workstations.
There are a number of general truths about the operation of transfer lines which are revealed by the
equations of Sections 5.1 and 5.2. First, the line efficiency decreases
substantially as the number of stations increases. It is not uncommon for large transfer lines
consisting of up to 100 stations to be down more than 50% of the time. lt is doubtful that such lines
achieve the return on investment which their owners anticipated from them. The influence of the
number of stations on line efficiency is dramatically displayed in Figure 5.3 for several assumed
values of station breakdown probabilities.
PARTIAL AUTOMATION
There are many examples of How lines in industry that contain both automated and manually
operated workstations. These cases of partially automated production lines occur for two main
reasons. First, mechanization of a manually operated How line is often introduced gradually.
Automation of the simpler manual operations is carried out initially, and the transition toward a fully
automated line is accomplished progressively. A long
period of time may elapse before the transformation has been completed. Meanwhile, the line
operates as a partially automated system. The second reason for partial automation is based strictly
on economics. Some manual operations are difficult to automate and it may be uneconomical to do
so. Therefore, when the sequence of workstations is planned for the flow line, certain stations are
designed to be manually operated while the rest are designed to be automatic. Examples of
operations that are often difficult to automate are processes requiring alignment or special human
skills to carry out. Many assembly operations fall into this category. Also, inspection operations often
create problems when automation is being considered to substitute for a human operator. Defects in
a work part that can be easily perceived by a human inspector are sometimes extremely difficult to
identify by an automatic inspection device. Another problem is that the automatic device can only
check the defects for which it was designed, whereas a human operator is capable of sensing a
variety of unforeseen imperfections in the part.
To analyze the performance of a partially automated How line, we will build on the developments of
the previous sections. Our analysis will be confined to the operation of a system without buffer
storage. Later in this section we will speculate on the improvements that would result if in-process
inventory banks were used for the manual workstations. The ideal cycle time Tc will be detennined
by the slowest station in the line, which generally will be one of the manual stations. We assume that
breakdowns occur only at the automatic stations and that the reasons for breakdowns are as varied
as they are for a completely automated system (e.g., tool failures, defective components, electrical
and mechanical malfunctions, etc.). Breakdowns do not occur at the manual stations because the
human operators are flexible enough, we assume, to adapt to the kinds of variations and disruptions
that cause an automatic workhead to stop. This, of course, is not always true, but our analysis will be
based on this assumption. Let p equal the probability of a station breakdown for an automatic work
head. The values of p may
be different for different stations, but we will leave to the reader the task of generalizing on our
particular case of equal p for all stations.
Since n is the total number of workstations on the line, let na equal the number of automatic stations
and no equal the number of manual operator stations. The sum of na and no must be n. ln our
previous discussion of costs in Section 5.1, CL was used to represent the cost to operate the line,
including labor, capital, and overhead. For a partially automated system, we must separate this term
into several components. Let Co equal the operator cost per manual station. This is a labor cost in
$/minute which applies to each manually operated workstation. The cost per automatic workstation in
$/minute will be denoted by Cas This cost will often vary for different stations, depending on the level
of sophistication of the mechanism. We can allow for these differences in Cas, with little difficulty, as
will be shown in a subsequent example. The last cost component of CL is the cost per minute of the
automatic transfer mechanism which will be used for all stations, manual and automatic, to transport
the work parts. Let this cost be symbolized by Cat. It is not a cost per station, but rather a cost that
includes all n stations. Combining these costs. the total line cost CL is given by
To figure the average production time, the ideal
cycle time is added to the average downtime per cycle as follows :
By using no (the number of automatic workstations),
we are consistent with our assumption that breakdowns do not occur at manual stations. Equation
(5.14) is based on the upper- bound approach of Section 5.2.
By substituting Eqs. (5.13) and (5, 14) into Eq. (5.8), we obtain the cost per unit produced :
EXAMPLE 5.4
A proposal has been made to replace one of the current manual stations with an automatic work
head on a 10-station transfer line, The current system has six automatic work heads and four manual
stations. The current cycle time is 30 s. The bottleneck station is the manual station that is the
candidate for replacement. The proposed automatic station would allow the cycle time to be reduced
to 24 s. The new station is costed at $0.25/min. Other cost data for the existing line :
We assume that the downtime distributions of all stations within a stage are the same, and that the
average downtimes of stages I and 2 are Td1 and Td2.
Over the long run, both stages must have equal efficiencies. For example, if the efficiency of stage I
would tend to be greater than the stage 2 efficiency, the inventory in the storage buffer would tend to
build up until its capacity b is reached. Thereafter, stage l would eventually be blocked when it tried
to outproduce stage 2. Similarly, if the efficiency of stage 2 is greater, the buffer inventory would
become depleted, thus starving stage 2. Accordingly, the efficiencies of the two stages would tend to
equalize over time.
The overall line efficiency for the two stages can be expressed as
where Eo is the line efficiency without buffer
storage. The value of Eo was given by Eq. (5.l6), but we will write it below to explicitly define the twostage system efficiency when b = 0 :
The term D1h(b) appearing in Eq. (5.25 represents
the improvement in efficiency that results from adding buffer capacity (b > 0).
D1 is the proportion of total time that stage 1 is down. However, Buzacott defines D1 as
Note that the form of this equation is different from
the case given by Eq. (5.6) when we were considering the How line to be an integral mechanism,
uncomplicated by the presence of buffer stocks.
The term h(b) is the ideal proportion of the downtime D1 (when stage 1 is down) that stage 2 could
be up and operating within the limits of buffer capacity b. Buzacott [2] presents equations for
evaluating h(b) using a Markov chain analysis. The equations cover several different downtime
distributions and are based on the assumption that the probability of both stages being down at the
same time is negligible. Four of these equations are presented in Table 5.l.
In sample calculations, the author has found that Eq. (5.21) tends to overestimate line efficiency. This
is because of the assumption implicit in the computation of h(b) that both stages will not be broken
down at the same time. Another way of stating this assumption is this: During the downtime of stage
l, stage 2 is assumed to always be operating. However, it is more realistic to believe that during the
downtime of stage 1, stage 2 will be down a certain portion of the time, this downtime determined by
the efficiency of stage 2. Hence, it seems more accurate to express the overall line efficiency of a
two~stage line as follows, rather than by Eq. (5.21) :
where E2 represents the efficiency of stage 2 by Eq.
(5.l7). In work subsequent to the research documented in reference [2], Buzacott develops a more
exact solution to the two-stage problem than that provided by Eq. (5.2l). This is reported in reference
5 and seems to agree closely with the results given by Eq. (5.29).
EXAMPLE 5.5
This example will illustrate the use of Eq. (5.29) and Table 5.l to calculate line efficiency for a transfer
line with one storage buffer. The line has I0 workstations, each with a probability of breakdown of
0.02. The cycle time of the line is I min, and each time a breakdown occurs, it takes exactly 5 min to
make repairs. The line is to be divided into two stages by a storage bank so that each stage will
consist of five stations. We want to compute the efficiency of the two-stage line for various buffer
capacities.
Solution :
First, let us compute the efficiency of the line with no buffer capacity.
By Eq. (5.16),
and L represents me leftover units, the number by which b exceeds BTd/Tc. Enally, let r
= F1/F1, as given by Eq_ (5.20).
With these definitions and assumptions, we can express the relationships for two theoretical
downtime distributions as developed by Buzacott [2]:
1. Constant repair distribution. Each downtime occurrence is assumed to require a constant require
time Td.
2.
Geometric repair distribution. This downtime distribution assumes that the probability that repairs are
completed during any cycle is independent of the time since repairs began. Define the parameter K :
Therefore,
E = 0.50 + 0.25 ( 0.952 ) ( 0.6667 ) = 0.6587
A 32% increase in line efficiency results when the buffer capacity equals 100. Comparing this to the
case when b = 10, we can see the law of diminishing returns operating.
When the storage capacity is infinite (b = ),
pt
Station
pt
0.01
0.03
0.02
10
0.01
0.01
11
0.02
0.03
12
0.02
0.02
13
0.02
0.04
14
0.31
0.01
15
0.33
0.01
16
0.31
We want to consider the relative performances when the line is separated into two, three, or four
stages.
Solution:
First, the performance of the line can be determined for the single-stage case (no storage buffer)
From the table, the frequency of downtime occurrences is given by Eq. (5.9) :
Stations
Fk
Ek
1-5
0.09
0.5814
6-10
0.10
0.5556
11-16
0.11
0.5319
The third stage, with the lowest efficiency, determines the overall three-stage line efficiency Eoo =
0.5319.
Finally, for four stages the division would be the following :
Stage
Stations
Fk
Ek
1-4
0.07
0.6410
5-8
0.08
0.6098
9-12
0.08
0.6998
13-16
0.07
0.6410
The resulting line efficiency for the four-stage configuration would be Eoo = 0.6098
The example shows the proper approach for dividing the line into stages. lt also shows how the line
efficiency continues to increase as the number of storage banks is increased. However, it can be
seen that the rate of improvement in efficiency drops off as more stage buffers are added. In the
foregoing calculations we assumed an infinite buffer capacity. For realistic capacities, the efficiency
would be less as was illustrated in Example 5.5.
The maximum possible efficiency would be achieved by using an infinite storage bank between every
workstation. Station 6 would be the bottleneck stage. We leave it for the reader to figure out the line
efficiency for the I6-stage case.
Simulation has become a much more familiar tool for the analyst to use to study transfer lines and
other production systems. Simulation software packages have become available that are much
easier to use, yet provide more capabilities to investigate system performance. These languages
include SLAM ll (Pritsker & Associates, Inc., West Lafayette, Indiana), SIMAN (Systems Modeling
Corporation, State College, Pennsylvania), SEE WHY (Istel lnc., Burlington, Massachusetts), and
several improved versions of GPSS. Animated graphics capabilities are becoming more common on
simulation languages such as these, permitting the user to visualize more clearly the operation of the
flow line (or other system). Although the equations presented in this chapter are useful as long as the
assumptions underlying them are valid, there are many flow line systems whose complexities are
beyond the assumed conditions of these models. Asynchronous transfer lines are good examples of
production systems in this category. Robot cells, flexible manufacturing systems, automated material
handling systems, and other systems that we cover later in this book are also sometimes too
complex to submit to analytic mathematical models. Computer simulation, especially with animated
graphics, can be used to assess the performance of these complex production systems and to
identify their design flaws and operating problems.
PROBLEMS
5.1. An eight-station rotary indexing machine operates with an ideal cycle time of 20 s. The
frequency of line stop occurrences is 0.06 stop/cycle on the average. When a stop occurs, it takes an
average of 3 min to make repairs. Determine the following :
(a) Average production time Tp
(b) Average production rate Rp
(c) Line efficiency E
(d) Proportion of downtime D
5.2. Assume that the frequency of line stop occurrences in Problem 5.1 is due to random mechanical
and electrical failures on the line. Suppose, in addition to the foregoing reasons for line stops, that
the workstation tools must be reset and/or changed at regular intervals. It takes an average of 4 min
to inspect and adjust or change the tools at all eight stations. This procedure is performed every 200
cycles. Recompute Tp, Rp, E, and D with these additional data for the indexing machine.
5.3. Component costs associated with the operation of the indexing machine of Problem 5.2 are as
follows :
cost of raw workpart = $0.35/workpiece
cost to operate the line = $0.50(min
cost of disposable tooling = $0.02/workpiece
Compute the average cost per workpiece produced off the rotary indexing machine.
5.4. In the operation of a certain 15-station transfer line, the ideal cycle time is 0.58 min. Breakdowns
occur at a rate of once every 10 cycles, and the average downtime per breakdown ranges between 2
and 9 min, with an average of 4.2 min. The plant in which the transfer line is located works an 8-h
day, 5 days per week. How many parts will the line be capable of producing during an average
week ?
5.5. The following data apply to a 12-station in-line transfer machine :
p = 0.01 (all stations have an equal probability of failure)
Tc = 0.3 min
Td = 3.0 min
Using the upper-bound approach, compute the following for the transfer machine:
(a) F, the frequency of line stops.
(b) Rp, the average production rate.
(c) E, the line efficiency.
5.6. Solve Problem 5.5 using the lower-bound approach. What proportion of workparts are removed
from the transfer line?
5.7. A circular indexing machine performs 10 assembly operations at 10 separate stations. The total
cycle time, including transfer time between stations, is 10 s. Stations break down with a
probability p = 0.007, which can be considered equal for all 10 stations. When these work stoppages
occur, it takes an average of 2 min to correct the fault. Parts are not normally removed from the
machine when these stops occur. Compute the proportion of downtime, the efficiency, and the
production rate of this circular indexing machine.
5.8. A transfer machine has six stations as follows:
Station
Operation
pi
Load part
0.78
0.02
0.01
0.90
0.04
1.42
Mill flats
0.01
1.42
Unload part
0.45
1.25
The time to transfer between stations = 0.28 min. If the part stops due to a jam in the line, it is
removed as defective. It takes an average of 8 min to determine the fault.and correct the problem
and remove the part. Also, there is a scheduled tool change every 40 parts which takes 6 min to
complete. There are 20,000 parts to be started onto the transfer machine.
(a) How many defective parts will be removed from the line?
(b) How many total hours will be consumed in the manufacturing process?
(c) Find the proportion of downtime.
(d) Find the rate of production of acceptable parts.
5.9. In Problem 5.8, the cost of operating the transfer machine is $60/h, as estimated by the
accounting department of the company. It is proposed that a computer and sensors be installed to
aid in diagnosing breakdowns when they occur. The anticipated savings are 2 min off the 8 min to
identify and correct the fault when it occurs. The computer will have no effect on tool changes. The
estimated cost of installing the monitoring system is $11,000. How many units must the system
produce in order to pay for the computer?
5.10. A 23-station transfer line has been logged for 5 days (a total of 2400 min). During this time,
there were a total of 158 downtime occurrences on the line. Ihe accompanying table identifies the
type of downtime occurrence, how many occurrences, and how much total time for the type of
occurrence.
Number of
Total minutes
Type of occurrence
occurrences
lost
132
793
104
520
21
189
26
84
78
The transfer line performs a sequence of machining operations, the longest of which takes 0.42 min.
The transfer mechanism takes 0.08 min to index a part from one station to the next position.
Assuming no parts removal when the line jams, determine the following characteristics for this line
for the 5-day period:
(a) How many parts are produced.
(b) Downtime proportion.
(c) Production rate and production time.
(d) Frequency rate p associated with the transfer mechanism breakdowns.
5.11. An eight-station transfer line has the following operations at each station; also given are the
processing time and the frequency of line stops for each station. During the observation period there
were 2000 parts completed.
Station
Process
Breakdowns
Load part
0.40
Mill top
0.85
22
Mill sides
1.10
31
0.60
47
0.40
0.90
58
0.75
84
Unload part
0.50
Also influencing the cycle time is the operation of the transfer mechanism, which takes 0.15 min
each cycle. When breakdowns occur it takes an average of 7.00 min to make repairs and get the line
operating again. Assume that the upper-bound approach is operative in your analysis for the
following :
(a) Determine the average production time per piece and the hourly production rate for this transfer
line.
(b) What is the uptime efficiency of the line and the proportion downtime?
(c) How many hours were required to produce the 2000 parts?
5.12. In Problem 5.11, if the lower-bound approach were used instead of the upper-bound approach,
and if the frequency of breakdowns in the lower-bound approach F = 0.10, determine the following
(assuming that the process times, transfer time, and average downtime per occurrence are the same
in Problem 5.11) :
(a) How many raw workparts would have started on the line in order to complete the 2000 parts?
(b) How many parts would have been removed from the line as damaged due to breakdowns if 2000
parts were completed?
(c) How many hours would have been required to produce the 2000 completed parts?
5.13. The APSCIM Machine & Foundry operates an automated transfer line with 12 stations. The
line is considered to have an efficiency that is unacceptably low. Figure P5.13 is a report of a study
on the current line operations. APSCIM would like to improve the efficiency by making the following
changes in the line :
First, change over from the current electromechanical relaytype controls to a programmable
controller. In addition to controlling the line in the same way as before, the new controller would
reduce the average downtime by diagnosing the malfunction, thus allowing repairs to be made more
quickly. It is expected that the average downtime per occurrence will be reduced by 25% using this
diagnostic system.
Second, divide the current line consisting of 12 stations into two stages, each consisting of six
stations. An in-process storage buffer would be used between the stages so that each stage could
operate as an independent transfer line. This is expected to improve the overall production rate and
line efficiency.
Determine the following :
(a) The parameters of the line performance as it currently operates (without the improvements).
These should include the ideal cycle time, the frequency of line stops, the line efficiency, and the
average hourly production rate.
(b) The effect of the two changes in the line operation described above. Determine the effect of both
of the changes together rather than each change separately. Your analysis should result in an
assessment of the line performance for each stage (ideal cycle time, the frequency of line stops, the
line efficiency, and the average hourly production rate). Also, determine the overall performance of
the two-stage system. In your analysis, assume the upper-bound approach. Make any other
additional assumptions necessary to solve the problem.
5.14. A 14-station transfer line has been logged for a total of 2400 min. The following table identifies
the type of downtime occurrence, how many occurrences, and how much time was lost for each
type.
Type of occurrence
Number
70
400
45
300
25
150
The ideal cycle time for the line is 0.50 min, including transfer time between stations. Half of the
downtime occurrences for tool changes and failures (35 occurrences and 200 min) involve cases
where the part was damaged and has to be removed from the line. The other downtime occurrences
follow the assumptions of the upper-bound approach. Determine the following characteristics of the
line operation.
(a) How many acceptable parts were produced during the 2400-min period?
(b) What were the line efficiency and downtime proportion?
(c) What was the average actual production rate of acceptable parts in parts per hour?
(d) Determine the frequency p associated with the transfer system failures?
5.15. A partially automated flow line has a mixture of mechanized and manual workstations. There
are a total of si stations and the overall theoretical cycle time is 1.0 min. This includes a transfer
time of 6 s. The six stations possess characteristics as follows :
Station
Type
pg
Manual
30
Automatic
15
0.01
Automatic
20
Automatic
25
0.01
Manual
54
Manual
30
0.02
Cost of the transfer mechanism is $0.10/min to operate. Cost to run each of the automatic
workheads is figured at $0.12/min for each of the three automatic stations. Labor cost to operate
each of the manual stations is $0.15/min for each of stations 1, 5, and 6. It has been proposed to
substitute an automatic workhead for the current manual station 5. The cost of this workhead will be
0.25/min and its breakdown rate p will be 0.02, but its process time will be only 30 s compared to 54
s for the cunent line. The average downtime per breakdown of the cunent and proposed
configuration is 3.0 min. Should the proposal be accepted ?
5.16. A manual flow line has six stations. The time required to process the part at each station is 1.0
min. The parts are transfened by hand from one station to the next, and an additional 12 s is lost
each cycle due to lack of operator discipline. Hence, the current cycle time on the line is 1.2 min.Ibe
following two proposals have been made:.First, install a mechanized transfer system to pace the line.
Second, automate one or more of the workstations on the line, resulting in a partially or fully
automated line. This requires installation of the mechanized transfer system in the first proposal. The
transfer system alone will bring discipline to the line and cause the cycle time to be reduced to 1.0
min. All six stations are candidates for automation ; however, there are differences in the reliability
with which the automated stations would operate. This is manifested in the value of p, the probability
of a station failure. These probability values am given in the following table.
Station
Probability p
Station
Probability p
0.01
0.04
0.02
0.05
0.03
0.06
The average downtime = 3 min when any of these automated stations break down. The ideal cycle
time for each automated station is 20 s. The cost of the automated transfer mechanism (which
serves all six stations) = $0.10/min. The cost per operator on the line = $0.20/min; and the cost per
automated workstation = $0.25/min. Determine if either or both of the proposals should be accepted.
If the second proposal is accepted, how many stations should be automated? Use cost per piece as
the criterion for your determinations.
5.17. A 16-station automatic transfer line has the following operating characteristics:
Tc = 0.75 min
Td = 3.0 min
p = 0.01 for all workstations
A proposal has been submitted to place a storage buffer between stations 8 and 9 to improve the
overall efficiency of the transfer line. What is the current line efficiency (use the upper-bound
approach), and what is the maximum possible efficiency that would result from use of a storage
buffer?
5.18. If the capacity of the storage buffer in Problem 5.17 is to be 10 workparts, calculate the line
efficiency and the average production rate of the two-stage transfer line. Assume that downtime
(Td = 3.0 min) is a constant.
5.19. Solve Problem 5.18 assuming that downtime is geometrically distributed.
5.20. In the transfer line of Problem 5.19, suppose that it is mom technically feasible to place the
storage buffer between stations 6 and 7. Using a storage buffer capacity of 10 workparts, calculate
the line efficiency and the average production rate. Assume that downtime is constant.
5.21. Solve Problem 5.20 but assume that downtime is geometrically distributed.
5.22. A synchronous transfer line has 20 stations and operates with an ideal cycle time of 0.5 min. All
stations have an equal probability of breakdown, p = 0.01. When breakdowns occur, the average
downtime is 5.0 min and the upper-bound approach applies. A proposal has been made to divide the
line into two independent stages, each stage having 10 stations, with a buffer storage zone between
the stations. The proposal indicates that each stage could operate independently to increase
production rate of the overall line. It has been decided that the storage capacity will be
25 units.1be cost to operate each station is $4.80/6 per station. Installation of the buffer storage zone
would increase the line operating cost by $12.00/h. Ignore material and tooling costs in this problem.
(a) Determine the average production rate per hour and the cost per unit of production for the current
20-station line.
(b) Calculate the average production rate per hour and the cost per unit for the proposed two-stage
system.
5.23. A certain 16-station transfer line can be conveniently divided into a two-stage line with a buffer
storage zone between the eighth and ninth workstations. He probability of a failure at any station is
p = 0.01. The ideal cycle time is 1.0 min and the downtime on the line is 10.0 min every time a
linestop occurs. He downtime should be considered to be constant, and the upper-bound approach
should be assumed. The cost of installing the buffer storage zone is a function of its capacity. The
cost = $0.6b/h = $0.01b/min, where b = the buffer capacity. However, the storage buffer can only be
built to hold increments of 10 (i.e., capacity = 10 or 20 or 30, etc.). He cost to operate the line is $120
per hour. Material costs and tooling costs should be ignored. Based on cost per unit of product,
determine the capacity of the buffer zone that will minimize the product cost.
5.24. The operation of a certain 20-station line is very poor and the management is looking to
improve the lines performance. The ideal cycle time is 48 s, and the uptime efficiency is only 40%.
The average downtime per occurrence is 3.0 min. Assume that the frequency of breakdowns is equal
for all stations and that the repair time distribution is constant. One of the altematives under
consideration is to divide the line into two equal stages by means of a storage buffer. Each stage
would have 10 workstations. The company can install a buffer with a 15-unit capacity in the line for
$14,000. The present unit cost of production is $4.00 per unit produced (this ignores material and
tooling costs). How many units will have to be produced in order for the $14,000 investment in the
storage buffer to pay for itself?
It turns out that the products design has a significant impact on the ease with which its assembly
can be automated. We begin our chapter with this topic.
items (screw, lock washer, and nut) to perform the fastening operation. Fourth, a sense of touch is
required to make sure that the nut is started properly onto the screw thread. Each of these four
problems makes automation of the operation difficult. All four problems together make it nearly
impossible. As a consequence, attempts at assembly automation have led to an examination of the
methods specified by the designer to fasten together the various components of a product.
The first and most general lesson, obvious from the example above, is that the methods traditionally
used for manual assembly are not necessarily the best methods for automated assembly. Human
beings are the most dexterous and intelligent machines : able to move to different positions in the
workstation, able to adapt to unexpected problems and new situations during the work cycle, capable
of manipulating and coordinating multiple objects simultaneously, and able to make use of a wide
range of senses in performing work. For assembly automation to be achieved, fastening procedures
must be devised and specified during product design that do not require all of these human
capabilities.
The first three types involve the same methods of work part transport described in Section 4.2. In the
stationary base part system, the base part (to which the other components are added is placed in a
The dial-type machine is shown in Figure 7.1. In the typical application, base parts are loaded onto
fixtures or nests that are attached to the circular dial. Components are added and/or fastened at the
various work stations located around the periphery of the dial. The dial indexing machine is the most
common system in this category. It operates with a synchronous or intermittent motion, where the
cycle consists of the process time plus indexing time. Several of the mechanisms describe in Section
4.3 can be used to provide this motion. Although less common, dial-type assembly machines are
sometimes designed to use a continuous motion rather than an intermittent motion.
The in-line assembly machine consists of a series of automatic work stations located along an in-line
transfer system. It is the automated version of the manual assembly line. Continuous, synchronous,
or asynchronous transfer systems can be used with the in-line configuration.
The operation of dial-type and in-line assembly systems is similar to the operation of their
counterparts described in Chapter 4 for machining (and other processing) operations. Sub
assemblies at various stages of completion are processed simultaneously at separate work stations.
For synchronous transfer of work between stations, the ideal cycle time equals the operation time at
the slowest station plus the transfer time between stations. The production rate, at 100% up time, is
the reciprocal of the ideal cycle time. Owing to jams of the components at the workstations and other
malfunctions, the system will probably not operate at 100% up time. We will analyze the operation of
these automated assembly systems in a subsequent section of this chapter.
Hopper. This is the container into which the components are loaded at the work station. A
separate hopper is used for each component type. The components are usually loaded into
the hopper in bulk. This means that the parts are randomly oriented initially in the hopper.
Parts feeder. This is a mechanism that removes the components from the hopper one at a
time for delivery to the assembly work head. The hopper and parts feeder are often
combined into one operating mechanism. The vibratory bowl feeder, pictured in Figure 7.3, is
a very common example of the hopper-feeder combination.
intervals that are consistent with the cycle time of the assembly work head. The placement
device physically places the component in the correct location at the workstation for the
assembly operation by the work head. These elements are sometimes combined into a
single operating mechanism in other cases, they are two separate devices. Several types of
escapement and placement devices are pictured in Figure 7.5.
The elements of the parts delivery system are illustrated schematically in Figure 7.6. A parts selector
is illustrated in the diagram. Improperly oriented parts are fed back into hopper. In the case of a parts
orientor, improperly oriented parts are reoriented an proceed to the feed track. A more detailed
description of the various elements of the delivery system is provided in reference [3].
One of the recent developments in the technology of parts feeding and deliver systems is the
programmable parts feeder [5,7]. The programmable parts feeder is capable of feeding components
of varying geometries with only a few minutes required to make the adjustments (change the
program) for the differences. This type of feeder would possess the flexibility to be used in batch
production assembly systems. Most parts feeder are designed as fixed automated systems for highproduction assembly.
selector and the orientor will be combined. Let us define 9 to be the proportion of components that
pass through the selector-orientor process and are correctly oriented for delivery into the feed track.
Hence the effective rate of delivery of components from the hopper into the feed track will be f. The
remaining proportion, (1 ), will be a circulated back into the hopper. Obviously, the delivery
rate f of components to the work head must be sufficient to keep up with the cycle rate of the
assembly machine.
Assuming that the delivery rate of components f is greater than the cycle rate Rc of the assembly
machine, a means of limiting the size of the queue in the feed track must be established. This is
generally accomplished by placing a sensor (e.g., limit switch, optical sensor, etc.) near the top of the
feed track, which is used to turn off the feeding mechanism when the feed track is full. This sensor is
referred to as the high-level sensor, and its location defines the active length Lf2 of the feed track. If
the length of a component in the feed track is Lc, the number of parts that can be held in the feed
track is nf2 = Lf2/Lc. The length of the components must be measured from a point on a given
component to the corresponding point on the next component in the queue to allow for possible
overlap of parts. The value of nf2 is the capacity of the feed track.
Another sensor is placed along the feed track at some distance from the first sensor and is used to
restart the feeding mechanism-again. Defining the location of this low- level sensor as Lf1, the
number of components in the feed track at this point is nf1 = Lf1/Lc.
The rate at which the quantity of parts in the buffer will be reduced when the high-level sensor is
actuated = Rc, where Rc is the theoretical cycle rate of the assembly machine. On average, the rate at
which the quantity of parts will increase upon actuation of the low-level sensor is f Re. However,
the rate of increase will not be uniform due to the random nature of the feeder-selector operation.
Accordingly, the value of nf1 must be made large enough to virtually eliminate the probability of a
stock out after the low-level sensor has turned on the feeder.
EXAMPLE 7.1
The cycle time for a given assembly work head = 0.2 min. The parts feeder has a feed rate = 20
components/min. The probability that a given component fed by the feeder will pass through the
selector is = 0.3. The number of parts in the feed track corresponding to the low-level sensor
is nf1 = 6. The capacity of the feed track is nf2 = 18 parts.
(a) Determine how long it will take for the supply of parts in the feed track to go from nf2 tonf1.
(b) Determine how long it will take on average for the supply for parts to go from nf1 to nf2.
Solution:
(a) The rate of depletion of parts in the feed track, starting from nr2, will be Rc = 1/0.2 = 5
parts/min. The time to deplete is
(b) The rate of parts increase in the feed track, once the
low-level sensor has been reached, is
f Rc = (20)(0.3) 5
=6 5
The probability of the first event is the product of the fraction defective rate for the station,qi,
multiplied by the probability that a defect will cause the station to stop, mi. This product is the same
as the term pi, of Section 5.2, the probability that a part will jam at station i. For an assembly
machine,
In this case where the component is defective and
causes a station jam, the defective component will be cleared and the next component will be
allowed to feed and be assembled. We assume that this next component is not defective the
probability of two consecutive defects is very small, equal to q2.
The second possible event, when the component is defective but does not cause a station jam, has
a probability given by
With this outcome, a bad part is joined to the existing assembly, perhaps
rendering the entire assembly defective.
To calculate production rate we must first determine the frequency of downtime occurrences per
cycle, F. If each station jam results in a machine downtime occurrence, F can be found by taking the
expected number of station jams per cycle. Making use of Eq. (7.1), this value is given by
where
Tc = ideal cycle time
Td = average downtime per occurrence
For the case of equal mi and equal qi,
From the average production time per assembly, we
obtain the production rate from Eq. (5.3), repeated here for convenience :
yield. While the yield of good product is an important issue in any automated production line, we see
that it can be explicitly included in the formulas for assembly machine performance by means
of q and m.
EXAMPLE 7.2
A 10-station in-line assembly machine has a 6-s ideal cycle time. The base part is automatically
loaded prior to the first station, and components are added at each of the stations. The fraction
defect rate at each of the 10 stations is q = 0.01, and the probability that a defect will jam is m = 0.5.
When a jam occurs, the average downtime is 2 min. Determine the average production rate, the yield
of good assemblies, and the up time efficiency of the assembly machine.
Solution :
The average production cycle time is
The production rate is therefore
EXAMPLE 7.3
Let us examine how the performance measures in Example 7.2 are affected by variations in qand m.
First, for m = 0.5, determine the production rate, yield, and efficiency for three levels of q : q = 0, q =
0.01, and q = 0.02. Second, for q = 0.01, determine the production rate, yield, and efficiency for three
levels of m: m = 0.2, m = 0.5, and m = 0.8. Computations similar to those in Example 7.2 provide the
following results :
other words, it does not consider the yield of good product from the assembly machine. The cost to
operate the assembly machine using instantaneous control is $ 60/h or $ 1.00 / min. Because of its
greater complexity, the cost of operating the memory control is $ 1.10 / min. Other costs are
negligible.
Solution:
We will compute the average production time, yield, and cost for instantaneous control first.
PROBLEMS
7.1. A feeder selector device at one of the stations of an automated assembly machine has a feed
rate f = 25 parts / min and provides a throughput of one part in four ( = 0.25 ). The ideal cycle time
of the assembly machine is 10 s. The low-level sensor on the feed track is set at 10 parts, and the
high-level sensor is set at 20 parts.
(a) How long will it take for the supply of parts to be depleted from the high-level sensor to the lowlevel sensor once the feederselector device is turned off ?
(b) How long will it take for the parts to be resupplied from the low-level sensor to the high-level
sensor, on average, after the feeder-selector device is turned on ?
(c) What proportion of the time that the assembly machine is operating will the feeder selector device
be turned on ? Turned off ?
7.2. Do Problem 7.1 but use a feed rate f = 32 parts / min. Note the importance of tuning the feederselector rate to the cycle rate of the assembly machine.
7.3. A dial indexing machine has six stations that perform the following assembly operations to the
base part ( also given are element times, and q and m values for the components added ) :
= 0.5 for all stations. Downtime per occurrence for defective parts is 2 min. Determine the
yield of assemblies that are free of defective components. the proportion of assemblies that contain
at least one defective component, the average production rate, and the up time efficiency.
7.9. An eight-station automatic assembly machine has an ideal cycle time of 10 s. Downtime is
caused by defective parts jamming at the individual assembly stations. The average downtime per
occurrence is 3.0 min. The fraction defect rate is 1.0% and the probability that a defective part will
jam at a given station is 0.6 for all stations. The cost to operate the assembly machine is $90.00/h
and the cost of components being assembled is $0.60/unit assembly. Ignore other costs.
(a) Determine the yield of good assemblies.
(b) Determine the average production rate of good assemblies.
(c) What proportion of assemblies will have at least one defective component ?
(d) Determine the unit cost of the assembled product.
7.10. A synchronous assembly machine has eight stations and must produce at a rate of 400
completed assemblies per hour. Average downtime per jam is 2.5 min. When a breakdown occurs,
all subsystems (including the feeder) stop. The frequency of breakdowns of the machine is once
every 50 parts. One of the eight stations is an automatic assembly operation that uses a feederselector. The components fed into the selector can have any of five possible orientations, each with
equal probability, but only one of which is correct for passage into the feed track to the assembly
work head. Parts rejected by the selector are fed back into the hopper. What minimum rate must the
feeder deliver components to the selector during system up time in order to keep up with the
assembly machine ?
7.11. An automated assembly machine has four workstations. The first station presents the base
part for the assembly, and the other three stations add parts to the base. The ideal cycle time for the
machine is 15 s and the average downtime when a jam results from a defective part is 3.0 min. The
fraction defective rates and probabilities that a defective part will jam the station are given in the
following table.
Workstation
Part identification
q
0.01
Base
1.0
Bracket
0.02
1.0
Pin
0.03
1.0
Retainer
0.04
0.5
Quantities of 100,000 for each of the bases, brackets, pins, and retainers are used to stock the
assembly line for operation.
(a) Determine the proportion of good product to total product coming off the line.
(b) Determine the production rate of good product coming off the line during steady-state operation.
(c) With the quantities of components given above, determine the total number of final assemblies
that will be produced. Of the total, how many will be good product, and how many will be products
that contain at least one defective component ?
(d) Of the number of defective assemblies determined in part (c), how many will have defective base
parts? How many will have defective brackets? How many will have defective pins ? How many will
have defective retainers ?
7.12. A six-station automatic assembly machine has an ideal cycle time of 6 s. At stations 2 through
6, parts feeders deliver components to be assembled to a base part which is added at the first
station. Each of stations 2 through 6 is identical and the five components are identical. That is, the
completed product consists of the base part plus the five components. The base parts have zero
defects, but the other components are defective at a rate q. When an attempt is made to assemble a
defective component to the base part, the machine stops (m = 1.0 ). It takes an average of 2.0 min to
make repairs and start the machine up after each stoppage. Since all components are identical, they
are purchased from a supplier who can control the fraction defect rate very closely. However, the
supplier charges a premium for better quality. The cost per component is determined by the following
equation :
jams resulting from defective components. However, the actual delivery of finished assemblies is far
below that designed production rate. Analyze the problem and determine the following :
(a) The designed average production rate that the foreman alluded to.
(b) The proportion of assemblies coming off the system that contain one or more defective
components.
(c) The problem that limits the assembly system from achieving the expected production rate.
(d) The production rate that the system is actually achieving. State any assumptions that you make in
determining your answer.