Professional Documents
Culture Documents
Summary
The Magnus platform, UK northern North Sea, has been producing
since 1983 with all 20 original slots now occupied. Additional infill
and extend-reach-drilling (ERD) production targets were identified and a means of access was required while maintaining base
field production. Platform modification was selected because of
significant commercial advantage over alternative developments.
The Magnus jacket was modified to permit running of four additional large conductors into which two smaller casings could be
installed respectively.
A tapered jacket profile necessitated preinstalled conductor
guide frames to build to 4 inclination at seabed, requiring initial
use of the large conductor as a conduit for drilling assemblies.
Custom-manufactured and specialist equipment was designed and
procured to enable successful underreaming to 54 in. and installation of 46-in. conductor. Drilling-assembly design and initial pilothole profile were deemed critical to subsequent success in running
rigid open-ended 46-in. conductor. Well-critical structural cement
was pumped to seabed by use of a 16-in. inflatable packer and inner
string. Unguided installation of two 185/8-in. casing strings inside
46-in. conductor was then achieved. The 185/8-in. casing strings
were cemented in place using light cement to preserve (shallow)
casing-shoe integrity. High-resolution multishot gyro surveys and
a newly developed gamma-wipe survey technique were used to
obtain critical 185/8-in. relative-shoe-orientation information before
subsequent kickoff.
Two wells were batch set successfully to the 133/8-in. casing
shoe by means of one conductor. Modification of existing wellhead technology for close proximity has proved successful. Access
to additional Magnus resources by means of an otherwise full
template has been delivered by this conductor-sharing-wellhead
(CSW) technology.
Introduction
Magnus is the most northerly currently operated field on the UK
Continental Shelf (Fig. 1). Discovered in 1974, Magnuss first
production was established in 1983. Continual field development
has resulted in more than 90 penetrations including exploration,
appraisal, and development wells.
In 1995, production from a now full well template plateaued
and a program of well-intervention work was commenced to offset
rapid decline of 60% per annum (Day et al. 1998). An enhancedoil-recovery (EOR) program was later adopted, using water-alternating-gas injection to maintain field output. Extensive subsurface
work focused on EOR mechanisms across discrete reservoir panels
and identified multiple new injection and off-take points that would
be required to optimize field production from each respective area
124
Rationale
Needed to support and guide the curvature
of new well conductors to seabed
125
A-annulus outlets
B-annulus outlets
C-annulus outlets
Fig. 5CSW alignment simulation illustrating relative orientations of wellhead housings at the A, B, and C annuli outletvalve levels; note staggered outlet-valve orientations by level
to permit access to and operation of all valves.
126
this end a 42-in. retro-fit conductor shoe was designed and manufactured (Fig. 9). This shoe would be run if dogleg severity was
surveyed to exceed 1/30 m at any point in the initial pilot hole.
Suspension of the shoe inside an open-ended 46-in. conductor joint
would be achieved by means of a 133/8-in. inflatable packer made
up to a 133/8-in. shear-out sub, and the complete assembly could
be run and retrieved on drillpipe. The 42-in. retro-fit shoe was not
deployed on the first MEP well because of a surveyed pilot-hole
profile of dogleg severity less than 1/30 m.
Fig. 6The 46-in. CSW installed; picture shows intermediate housing lowermost (complete with C-annulus side outlet
valves) and dual compact housings uppermost (complete with
A- and B-annulus side outlet valves); note close proximity of
conductor deck steel.
E8: PMEP1
E7: NWMP
MSL: 57 m
Fig.10
Hordland: 1017 m
(989 m)
Fig. 10CSW well-design illustration showing batch-set 133/8-in.-casing strings cemented back inside conductor-sharing 185/8-in.
conduit strings.
inflatable packer also afforded the capability to maintain inflatable-element pressure if a leaking packer was observed. A 46-in.
conductor was suspended by the blocks to mitigate the risk of
becoming locked in the slips as the cement set.
Unguided Conductor Conduits. To reduce drilling complexity, dual 185/8-in. conduits were planned to protrude 5 and 10 m
from the 46-in.-conductor shoe only, vertically staggered to aid
subsequent kickoff from each well. Placement of 185/8-in.-casing
shoes deeper by means of continued drilling was not required by
the Magnus casing design (Fig. 10). To this end, a single 42-in.
cleanout run was carried out through the 46-in.-conductor shoe,
into which both 185/8-in.-conduit strings could be run.
To reduce the tendency of the second unguided 185/8-in.-conduit
string to hang up on the initial 185/8-in.-conduit string, semiflush
connections were used on non-centralized pipe. The initial conduit
string was run to protrude 5 m outside the 46-in. conductor shoe,
a minimum of 8 m off hole bottom to negate any chance of the
first 185/8-in. string hanging up on hole fill, leading to buckling
and ensuing occupation of greater space inside the 46-in. conductor. The second 185/8-in.-conduit string was then run to 10 m
outside the 46-in.-conductor-shoe depth with an eccentric shoe to
aid running against the initial conduit. A stab-in circulating casing-running tool was also used throughout dual 185/8-in. running
operations to maintain the capability to wash and rotate casing at
any stage in the operation.
Dual Unguided 185/8-in.-Conduit Cementing. Both 185/8-in.conduit strings needed to be cemented uncentralized (to reduce
running risk) and by means of a 57-m air gap with a low formationfracture strength. Extensive Magnus offset drilling has resulted in a
well-constrained fracture gradient of 1.26 SG at the conductor-shoe
depth of 380 m measured depth below rotary table (MDBRT). The
185/8-in.-conduit cement did not carry structural loads. All well
and tree loads were transferred to the 46-in. conductor (Fig. 10).
Subsequent hole sections were drilled using a diverter, so a 60-psi
128
Fig. 11Example plan view showing CSW profiles in the vicinity of the 46-in. conductors; for planning purposes, both
46-in. conductor and internal unguided 185/8-in. conduits were
assigned well paths. Green dots represent conductor locations
at surface (46-in. conductor in center and 185/8-in. conduits on
either side).
Fig. 12Typical traveling-cylinder, or anticollision, plot illustrating allowable deviations from plan of less than 1 m at 600-m MDBRT.
(b)
Planned exit from 18 5/8?
It was expected that the most likely outcome would be that the
casing strings would be touching for the majority of the section
and hence the actual center-to-center distance would be close to
the minimum separation. This was generally found to be the case,
as illustrated in Fig. 17. Little change in relative orientation of
(c)
Image of twisted 18 5/8?
(d)
Possible collision if 18 5/8?
relative orientation unknown
EOUs
Twisted 18
1 5/8 ?
Fig. 13Illustration of unknown 185/8-in.-conduit paths inside 46-in. conductor when installed unguided; conventional gyro-survey
accuracies would lead to significantly overlapping ellipses of uncertainty (EOUs) (A) preventing derivation of two distinct paths.
Incorrect allocation of well target in the event of an unknown twist (C) could lead to a collision (D).
130
Gravity Toolface
(GT F_RT)
190
(DEG)
190
46
46
CutAway
Conclusion
MEP conductor installation necessitated the use of 46-in. conductor deviated from vertical, which in turn led to the installation
of open-ended conductor and running of dual unguided 185/8-in.
conduits. The nonstandard operation incorporated use of multiple items of custom-manufactured equipment and required use
of novel cementing and surveying techniques. Use of unguided
conduits has been demonstrated to be feasible, provided that new
cementing and surveying methods are developed.
Acknowledgments
The authors thank BP EOC and partners Nippon Oil Exploration
& Production UK Limited, ENI UK Limited, and Energy North
Sea Limited for permission to print this paper. Thanks are also
conveyed to all team members of the MEP for helping to deliver
the first slot-sharing well pair ahead of schedule despite inherent
challenges.
References
Anchaboh, L., de Lange, F.P.A., van Beelen, C.J., and Tan, R.K.W. 2001.
Conductor Sharing WellheadsMore For Less. Paper SPE 68699 presented at the SPE Asia Pacific Oil and Gas Conference and Exhibition,
Jakarta, 1719 April. doi: 10.2118/68699-MS.
Day, S., Griffin, T., and Martins, P. 1998. Redevelopment and Management
of the Magnus Field for Post-Plateau Production. Paper SPE 49130
Centre-Centre Distance
Distance
.8
Min 1s
Metres
Max 1s
Min 2s
.6
Max 2s
Min 3s
.4
Max 3s
Min physical
Max physical
.2
0
50
100
150
200
250
300
350
400
Measured Depth
Fig. 1646-in. starter head with dual 185/8-in. landing plate and
18-in. mandrel hanger installed; center-to-center separation
of conductor-sharing 185/8-in. strings is 23 in.
March 2011 SPE Drilling & Completion
Fig. 17Plot showing variation in gyro-surveyed center-tocenter separation between 185/8-in. conduits inside 46-in. conductor with depth; physical limits of conductor inside diameter
and minimum 185/8-in. center-to-center separation when touching are included.
131
Centre-Centre Direction
Direction
90
Min 1s
Degrees
Max 1s
0
Min 2s
-180
0
50
100
150
200
250
300
350
400
Measured Depth
Fig. 18Plot showing variation in relative orientation of gyrosurveyed 185/8-in. well paths with depth.
132