Professional Documents
Culture Documents
ACCOMPLISHMENT REPORT
as of ____________________________, 2015
A. PROJECT DATA
Project Title
Loction
Contractor
Project Manager
Original Contract Amount
:
:
: Php
: Php
:
:
:
:
Starting Date
Original Completion Date
Revised Completion Date
Remaining Time
B. WORK PROGRESS
% Completed
Previous
This Period
To Date
D.
Scheduled
Previous
Actual
Slippage
This Period
To Date
Material Cost
Labor Cost
Equipment Cost
Prepared by :
Project Engineer
MAGV/2K4/CONSTRUCTION
302121138.xls / project data (REA-EGBP)
Checked/Verified by :
Noted by :
RENE E. ABAD
Construction Div. Head
Contractor
MAGV/2K4/CONSTRUCTION
302121138.xls / project data (REA-EGBP)
CDC-ECMD
CDC-ECMD
Project
Location
Date Started
Date of Completion
Report No.
Remaining Days
:
:
:
:
ITEM
ACTIVITIES/DESCRIPTION
TOTAL
APPROVED
QUANTITY
ACCOMPLISHMENT (%)
UNIT
UNIT
COST
Prepared by :
MAGV/2K4/CONSTRUCTION
302121138.xls / Physical Accomplishment (REA-E)
AMOUNT
% WT.
0.00
0.0%
Checked by :
Noted by :
RENE E. ABAD
PREVIOUS
THIS PERIOD
0.000%
0.000%
TOTAL TO DATE
Less Programmed
Slippage (+)
TOTAL TO DATE
0.000%
Project
Location
Date Started
Date of Completion
Report No.
Remaining Days
:
:
:
:
ITEM
ACTIVITIES/DESCRIPTION
MAGV/2K4/CONSTRUCTION
302121138.xls / Physical Accomplishment (REA-E)
TOTAL
APPROVED
UNIT
UNIT
QUANTITY
COST
Project Engineer, CDC - ECMD
ACCOMPLISHMENT (%)
AMOUNT
% WT.
PREVIOUS
THIS PERIOD
TOTAL TO DATE
ACCOMPLISHMENT REPORT
as of ____________________________, 2015
A. PROJECT DATA
Project Title
Loction
Contractor
Project Manager
Original Contract Amount
:
:
: Php
: Php
:
:
:
:
Starting Date
Original Completion Date
Revised Completion Date
Remaining Time
B. WORK PROGRESS
% Completed
Previous
This Period
To Date
D.
Scheduled
Previous
Actual
Slippage
This Period
To Date
Material Cost
Labor Cost
Equipment Cost
Prepared by :
Project Engineer
MAGV/2K4/CONSTRUCTION
302121138.xls / project data (REA) (MMP)
Checked/Verified by :
MELQUIADES M. PINEDA
Project Engineer
Noted by :
RENE E. ABAD
Construction Div. Head
Contractor
MAGV/2K4/CONSTRUCTION
302121138.xls / project data (REA) (MMP)
CDC-ECMD
CDC-ECMD
Project
Location
Date Started
Date of Completion
Report No.
Remaining Days
:
:
:
:
ITEM
ACTIVITIES/DESCRIPTION
TOTAL
APPROVED
QUANTITY
ACCOMPLISHMENT (%)
UNIT
UNIT
COST
AMOUNT
% WT.
PREVIOUS
THIS PERIOD
TOTAL TO DATE
4.00%
4.00%
Prepared by :
MAGV/2K4/CONSTRUCTION
302121138.xls / Physical Accomplishment (RE (MM
0.00
8.0%
Checked by :
Noted by :
MELQUIADES M. PINEDA
RENE E. ABAD
0.000%
Err:522
TOTAL TO DATE
Less Programmed
Slippage (+)
0.000%
Project
Location
Date Started
Date of Completion
Report No.
Remaining Days
:
:
:
:
ITEM
ACTIVITIES/DESCRIPTION
MAGV/2K4/CONSTRUCTION
302121138.xls / Physical Accomplishment (RE (MM
TOTAL
APPROVED
UNIT
UNIT
QUANTITY
COST
Project Engineer, CDC - ECMD
ACCOMPLISHMENT (%)
AMOUNT
% WT.
PREVIOUS
THIS PERIOD
TOTAL TO DATE