Marginal Field Development

The Sea Swift Conductor Supported Platform (CSP)

Ken Crawford

Page 1

Agenda

Our Company
Our Services
Offshore Structures for Marginal Field Development
utilising a MOPU development solution

Page 2

Our Engineering Solutions


Delivering Your Vision
Exceptional Innovation in Offshore Engineering Solutions

Concept, design, procurement and installation


Offshore systems, products and technical support services
Offshore Structures
Riser Systems
Hydraulic Systems
Service & Rental

Page 3

Our Company
Structured for Your Success
Global Track Record and Experience

Operational experience and on-ground representation in Asia Pacific, Africa, Europe,


Middle East, North Sea and USA
Worked completed for over 110 customers in 32 countries

Growing Team

Degree Qualified Engineers to PHD level


Affiliation with Cambridge University
Experienced hands-on Offshore Field Engineers
Offer practical solutions to offshore challenges

Page 4

Our Commitment
To Your Success
Innovative, Robust and Reliable Solutions
to Drilling and Platform Requirements

Innovation: based on hands on experience

Safety: first before all else

Service & Quality: responsive and tailored to customer needs

Cost Control: delivering reduced platform costs. Lower installation costs, minimum
drilling downtime, simplified critical path and reduced intervention costs

Page 5

Our Company
Structured for your Success
Project
Management

Offshore
Installation
&
Operations

Analysis &
Engineering

Fabrication
& Testing

Procurement

Page 6

Our Innovation
Bringing Your Specification to Life

Offshore Structures
Sea Swift Conductor Supported
Platform
Subsea Drilling Templates
Subsea Protective Structures
Wellhead Tower
Tension Decks
Bespoke Offshore Structures
Design, Procure, Supply, Install

Page 7

Our Innovation
Bringing Your Specification to Life

Riser Systems

Riser Analysis
Subsea Riser Systems
Surface Riser Systems
Pipeline Riser
VIV Suppression Systems
Connectors
Tie-back Engineering
Centralisers

Page 8

Our Innovation
Bringing Your Specification to Life

Hydraulic Systems

Hydraulic Power Unit


Wellhead Control Panel
Spare Parts
Image Based Information System
System Appraisal / Troubleshooting
Fluid Analysis

Page 9

Our Innovation
Bringing Your Specification to Life

Service & Rental

SUREgrip Tension Ring


PROten Riser Tensioning System
Rig Floor Tensioning System
Conductor / Riser Tensioning Unit
Cement Top Up System
Aquascope Subsea Camera
Trash Caps
Conductor Tie-back Rental Tools

Page 10

Offshore Structures
Sea Swift Conductor Supported Platform

Page 11

Offshore Structures
MOPU Wellbay Modules

Bespoke wellbay modules designed to be


used in conjunction with a MOPU

Quick and low cost solution for rapid


development of normally uneconomical
fields

Attaching the wellbay module to the hull of


the FPSO removes the need for a NUI or
standard jacket

Systems are designed to be either fitted to


new build rigs or retrofit to existing rigs

Allows multiple wells to be tied back to an


FPSO

Page 12

Offshore Structures
Tension Decks

Bespoke tension decks designed for


explorations and development drilling

Systems are designed to be either fitted to


new build rigs or retrofit to existing rigs

Allows multiple wells to be drilled at one


single location

Can provide up to 1500 Tones of tension


across 6 individual well slots

Page 13

Offshore Structures
Sea Swift Conductor Supported Platforms

Typically NUI platforms using well conductors as


structural members.

Designed to current API and Verification body


rules.

Designed for installation by standard cantilever


Jack-up and supply vessel. No need specialist
vessel assistance.

Conductors can be drilled and cemented or piled.

Three main applications

Normally Unmanned Installation

Pre drill wellhead platform

Slot addition wellhead platform

Page 14

Sea Swift CSP


Component Montage

Page 15

Sea Swift CSP


Configurable Topsides

Page 16

Sea Swift CSP


Conductors

Typically 36 or 30 diameter Grade X52.


Premium fatigue grade connectors (e.g. National Oilwell Varco XLC-S
connectors) with excellent strength and fatigue performance.
Pile or drill conductors.
Four conductors will form the main structural support to the platform and
will be effectively fixed within the subsea structures via use of grout.
Corrosion protection will be provided.

Page 17

Sea Swift CSP


Subsea Structures
Example of 4 Well Sea Swift

Overall dimensions of approximately: H: 13.6m W: 6.9m L: 8.1m

4 wells in a 2 x 2 array @ 6m x 4.8m spacing plus a central running slot


which can also be used as a well slot (future requirement).

Approximate weight 160 Tonnes.

4 x 42 O/D leg sleeves, and an arrangement of smaller tubular sections


interconnecting bracing members.

The subsea structure will be located at or just above the seabed and
initially supported on a central support pile. This can also accommodate
an additional well if required in the future.

All required cement grouting equipment, installation cameras, subsea


gyrocompass location fittings and guides for the export riser and subsea
power umbilical cable.

Conductors will be grouted within the sleeves.

Page 18

Sea Swift CSP


Riser Guide

Offers support/protection to the export riser and umbilical


cable.
Approximate weight will be 2.5 Tonnes
Locates over two well conductors.
Installed either following or during the installation of the 4
well conductors and prior to installation of the topsides
module.
Incorporates guide modules for the export riser and the
subsea power umbilical cable.
Will be installable using AEL patented technology.

Page 19

Sea Swift CSP


Typical Topsides Facilities Equipment

Production Test & Manifolds, piping and valves


Wellhead control panel and Hydraulic Power Unit (HPU)
Platform control interface
Pig launcher
Flare / Emergency Vent Boom
Emergency personnel shelter (located within designated Safe Area)
Electrical Equipment Room (located within designated Safe Area)
Chemical injection package
Platform Control System
Multiphase flow meter
Sump tank and pump
ESP Control Transformers
Vent scrubber and pump
CCTV
Service water pump
Emergency Lighting
Diesel driven crane and diesel tank
Life escape devices e.g. life buoys
Platform Safety Equipment

Page 20

Sea Swift CSP


Delivery of the Complete Solution

Project
Management

Offshore
Installation
&
Operations

Analysis &
Engineering

Fabrication
& Testing

Procurement

Page 21

Sea Swift CSP


Project Management

Dedicated Project Team


Structural & Fatigue Analysis
Process simulations
Topsides Facilities Equipment Analysis
Mechanical
- Instrument & Control
- Electrical & Power
- Piping
- Telecommunication
- Technical Safety
- Detailed Design
Production of BOD
Development of design specifications & key documents

Page 22

Sea Swift CSP


Analysis & Engineering

FEED Study / Review & verification of FEED design documents


Structural & Fatigue Analysis
Process simulations
Topsides Facilities Equipment Analysis
Mechanical
- Instrument & Control
- Electrical & Power
- Piping
- Telecommunication
- Technical Safety
- Detailed Design
Production of BOD
Development of design specifications & key documents

Page 23

Sea Swift CSP


Procurement
Sub contractor evaluation and selection:
Sub contractor audits and final selection of sub contractors driving down costs where possible

Procurement of long lead items

Conductor joints and connectors


Structural sections and subsea structure cans
Pig Launcher
Topside facilities equipment & Piping
WHCP / HPU

Page 24

Sea Swift CSP


Fabrication
Sub contractor evaluation and selection:
Sub contractor audits and final selection of
sub contractors driving down costs where
possible

Procurement of long lead items


Conductor joints and connectors
Structural sections such as the subsea
structure cans
Topside facilities equipment & Piping

Platform and riser Installation equipment


fabrication
QA, QC
Installation of facilities equipment
Riser pre-fabrication
Platform FAT
Full Aquaterra management team on site to
manage fabrication

Manufacturing phase:

Delivery of complete solution

Topsides module fabrication and painting


Subsea structure fabrication and painting
Platform ancillaries fabrication and painting

Page 25

Sea Swift CSP


Example Schedule

Page 26

Sea Swift CSP

Page 27

Sea Swift CSP

Page 28

Sea Swift CSP

Page 29

Sea Swift CSP

Page 30

Sea Swift CSP


Seme Development - General Platform Configuration

26m Water Depth


Four 30 Conductors run to 50m below mudline
Provision for 5 wells (3 initial + 2 optional)
25 year design life. Minimal processing facilities - will incorporate
manifolds, multi-phase analyser/meter, utilities and a pig launcher.
6m x 4.8m well spacing with additional centre running / support slot
One subsea structure approximately
H: 13.6m W: 6.9m L: 8.1m
Weight: Approximately 160T
Topside 3 deck levels approximately
H: 9.5m W: 12m L: 15m
Weight (including process equipment): Approx. 260T
(based on current understanding of requirements)
Crude transported to shore via a 15km long, 8 pipeline to a 12,000BPD
capacity onshore facility.
Power will be supplied via one combined subsea power and fibre optic
data communication cable.
Umbilical and Riser guides.
Access via boat landing and ladder
Page 31

Sea Swift CSP

Page 32

Sea Swift CSP


Installation
1.
2.
3.
4.
5.

6.
7.
8.
9.
10.

Pick up and Hang off Subsea Structure


Drill Centre Slot Conductor
Pickup & Install Lower Subsea Structure
Pickup and Install Upper Subsea Structure
Drill and Run Four Environmental Conductors

Attach riser guides and boat access ladder as conductor ran

Cut conductors to height as each is drilled


Space Out & Grout Lower Subsea Structure to Depth
Space Out & Grout Upper Subsea Structure to Depth
Pick up and Hang-off Topside Structure
Transfer and Set Down Topside Structure
Complete Hook Up & Commissioning

Page 33

Sea Swift CSP


Installation

Page 34

Sea Swift CSP


Gallery

Page 35

Sea Swift CSP


Gallery

Page 36

Sea Swift CSP


Gallery

Page 37

Sea Swift CSP


Gallery

Page 38

Sea Swift CSP


Gallery

Page 39

Sea Swift CSP


Gallery

Page 40

Sea Swift CSP


Gallery

Page 41

Sea Swift CSP


Gallery

Page 42

Sea Swift CSP


Gallery

Page 43

Sea Swift CSP


Gallery

Page 44

Sea Swift CSP


Gallery

Page 45

Sea Swift CSP


Gallery

Page 46

Sea Swift CSP


Gallery

Page 47

Sea Swift CSP


Gallery

Page 48

Sea Swift CSP


Installation
1.

Drill Centre Hole. Pick up and Install Lower Subsea Structures

Page 49

Sea Swift CSP


Installation
2.

Pick up and Install Upper Subsea Structures

Page 50

Sea Swift CSP


Installation
3.

Pick up Topside and Boat Landing Structures

Page 51

Sea Swift CSP


Installation
4.

Commence Drilling Operations

Page 52

Sea Swift CSP


Installation
5.

Prepare Cement Hoses

Page 53

Sea Swift CSP


Installation
6.

Spaceout and Secure Subsea Structures

Page 54

Sea Swift CSP


Installation
7.

Position & Install Topsides

Page 55

Sea Swift CSP


Installation
8.

Complete Hook-up and Commissioning

Page 56