Annual Plan
Access to Programs and Data
End-User Computing
IT Control environment
IT General Controls
Computer Operations
IT General Controls
Company Name
ensive IT audit plan for the year XXXX
Activities
Internal Audit Plan Year XXXX
Monthly Review of physical access to information systems
and Data Centre December XXXX
Quarterly Review of Access administration
Review of end-user policies and procedures
Review of end-user computing + Backup of end-user
reports/data
Monthly Review of physical access to information systems
and Data Centre
Review of IT steering committee
Review of IT strategy
Review of IT policies and procedures
Review of Backup and Recovery Procedures - Back up and
DRP
Review of Anti-virus procedures
Review of incident and problem management -Helpdesk and
SLA
Monthly Review of physical access to information systems
and Data Centre
Review of Authorization, development, testing and approval
Review of Migration to the production environment
Review of Super-user activities
Monthly Review of physical access to information systems
and Data Centre
Quarterly Review of Access administration
Review of Identification and authentication
Review of controls over information
Timeline
13 January - 17 January
13 January - 17 January
20 January - 24 January
27 January - 31 January
3 Febraury - 7 February
3 February - 7 February
10 February - 14 February
17 February - 21 February
24 February - 28 February
3 March - 7 March
3 March - 7 March
10 March - 14 March
17 March - 21 March
24 March - 28 March
31 March - 4 April
7 April - 11 April
14 April - 18 April
21 April - 25 April
28 April - 2 May
5 May - 9 May
12 May - 16 May
5 May - 9 May
12 May - 16 May
19 May - 23 May
26 May - 30 May
Teasy Mobile M
Comprehensive IT audit plan
Sections
Entity Level Control Environment
Sub - Sections
IT Control environment
Responsible department
Review of IT strategy
IT
IT
IT
IT
Finance/IT
Timeline
13th to 20th January 2014