Professional Documents
Culture Documents
Acceptance
Testing
by Scott Martorano, CFPS
Posted: August 1, 2008
Although sometimes used interchangeably, these terms are
distinct. Understanding each one will help ensure that a
buildings fire protection features operate as designed.
Since the early 1980s, automatic sprinkler systems have gradually increased in
complexity. Advances in sprinkler technology have lead to the development of
extended coverage, residential, quick-response and ESFR sprinklers, to name a
few. The most common sprinkler system to be installed is still the basic wet pipe
system. However, dry systems, preaction, deluge and foam water sprinkler
systems have seen steady growth as well.
All of these systems must be put through acceptance testing by the installing
contractor to ensure proper operation, but individual acceptance testing may not
verify interconnections and operation with other building fire protection systems.
In buildings where the sprinkler systems are intended to work with other fire
protection systems such as fire alarm systems or smoke- control systems a
more complete commissioning program may be the more appropriate method to
ensure the owners expectations are met.
While advances in technology have greatly improved fire-protection-system
capabilities, the individual system components and related building designs have
become more complex. This has resulted in more-demanding acceptance testing,
a more-challenging installation process, and, in some cases, difficult long-term
system maintenance for many sprinkler systems. This can be especially true if
the sprinkler system requires interconnection and operation with other fire
protection systems.
Many times in newly constructed buildings, automatic sprinkler systems are
treated as autonomous within the structures overall fire protection scheme
during the design, construction and long-term operation. In some cases, the
building owner may consider this acceptable. In other cases, the building owner
may seek assurance that the buildings fire protection features work together as
intended when the building was designed.
Flow control
sprinkler system.
All photos
c ourtesy of Viking
Corp.
The contractor must notify the Authority Having Jurisdiction, who will then decide
if they wish to witness the testing or not. The contractor then conducts the
individual system acceptance and operational testing described in NFPA 13. The
specific item tested will vary depending on what type of sprinkler system is
installed, but may include all or some of the following:
1. Flushing the underground pipe.
2. Hydrostatic test.
3. The air test for dry systems (non-interlock preaction or double interlock
preaction systems).
4. The system operational test.
5. Submitting the contractors material and test certificate.
Multiple sprinkler
system risers.