You are on page 1of 2

Installation Integrity 2006 WLL

H.V.A.C Commissioning Management START-UP COMMISSIONING INSPECTION TEST SHEET


Operating and Maintenance Manuals (Air Handling Unit with Recovery Fan)
Testing and Balancing www.i2ime.com
Contract Integrated District Cooling Plant @ The Pearl, Qatar Ref QA-PCA01a
Client CAT International Qatar W.L.L Date
Plant reference AHU- (Supply Fan) Job ref
Location / area serving Sheet 1 of 2
FAN FAN - MOTOR HUMIDIFIER RECOVERY FAN & MOTOR
Manufacturer Manufacturer Capacity kg/h Manufacturer (Fan)
Type / Make Frame size Power kW Fan Capacity
Size Serial no. Manufacturer (Motor)
Serial no. Power kW HEATER Serial no.
Ordered duty Air Volume l/s Electrical supply volts / phase / hertz Capacity kW Power kW
External Static Press Pa Motor current (FLA) amps Electrical supply volts / phase / hertz Electrical supply volts / phase / hertz
Service Factor Motor current (FLA) amps
Pre-start up Inspection Y/N Notes Start up Inspection Y/N Notes
Item Mechanical: Item Mechanical:
1 Equipment matches the submittal data 1 Motor rotation correct During Start-up.
2 Mounting checked (shipping bolts removed) 2 Outdoor air damper open
3 Alignment by Millwright or installer 3 Supply air damper wide open
4 Pulleys aligned and belt tension correct 4 Fire / Smoke damper open
5 Equipment guards installed 5 Balance dampers open
6 Fan rotates freely Electrical:
7 Fun & Motor lubricated per MFG recommendations 6 Electrical interlocks verified
8 Smoke and fire dampers (or combination) in place 7 Status indicators verified (Local / Remotes)
9 Smoke detectors are installed (if applicable) 8 Motor Amps - Rated ____ Actual ____
10 Air Temp sensor, and filter diff. pressure gauge correct location 9 Motor Volts - Rated ____ Actual ____
11 Duct insulation provided 10 VFD (if any) settings to match motor were applicable
12 Balanced dampers installed, positioned and locked 11 VFD (if any) vendor representative onsite
13 Access doors for all dampers installed (Ducts and Plenums) START-UP DATA:
14 Condensate lines provided and clear @ 12.5 Hz @25.0 Hz @ 37.5 Hz @ 50.0 Hz
15 Cooling coil clean and clear - piping correct connection Measured Amps
16 Ductwork flexible connectors installed Measured Votage
17 Ductwork sealed as required and leak tested STATIC PARAMETER
18 Sound Attenuator installed Intake Air Static Pressure : Pa
19 Louvers (outdoor) installed Supply Air Static Pressure: Pa
20 Start-up Filters Installed. External Static Pressure: Pa
Electrical: Deficiency Corrected:
21 Electrical connections / termination complete (MCC Sign-off)
22 Isolator switch installed & terminated :
- Supply Fan
- Heater
- Humidifier
- Recovery Fan
23 Overload protection in place (sized correctly)
24 AHU internal lightings complete and functional.
Others:
25 Equipment manufacturers submittal, performance data,
fan curves, dimensions, as-built drawings. * indicates unobtanable ** indicates not stated *** not applicable
WITNESS
Vendor / Installer Representative i2i Representative BAYTUR Representative KEO Representative
Name: Name: Name: Name:
Date: Date: Date: Date:
Signature: Signature: Signature: Signature:
Installation Integrity 2006 WLL
H.V.A.C Commissioning Management START-UP COMMISSIONING INSPECTION TEST SHEET
Operating and Maintenance Manuals (Air Handling Unit with Recovery Fan)
Testing and Balancing www.i2ime.com
Contract Integrated District Cooling Plant @ The Pearl, Qatar Ref QA-PCA01a
Client CAT International Qatar W.L.L Date
Plant reference AHU- (Return Fan) Job ref
Location / area serving Sheet 2 of 2
FAN FAN-MOTOR
Manufacturer Manufacturer
Type / Make Frame size
Size Serial no.
Serial no. Power kW
Ordered duty Air Volume l/s Electrical supply volts / phase / hertz
External Static Press Pa Motor current (FLA) amps
Service Factor
Pre-start up Inspection Y/N Notes Start up Inspection Y/N Notes
Item Mechanical: Item Mechanical:
1 Equipment matches the submittal data 1 Motor rotation correct During Start-up.
2 Mounting checked (shipping bolts removed) 2 Return air damper open
3 Alignment by Millwright or installer 3 Extract air damper wide open
4 Pulleys aligned and belt tension correct 4 Fire / Smoke damper open
5 Equipment guards installed 5 Balance dampers open
6 Fan rotates freely Electrical:
7 Fun & Motor lubricated per MFG recommendations 6 Electrical interlocks verified
8 Smoke and fire dampers (or combination) in place 7 Status indicators verified (Local / Remotes)
9 Smoke detectors are installed (if applicable) 8 Motor Amps - Rated ____ Actual ____
10 Air Temp sensor, and filter diff. pressure gauge correct location 9 Motor Volts - Rated ____ Actual ____
11 Duct insulation provided 10 VFD (if any) settings to match motor were applicable
12 Balanced dampers installed, positioned and locked 11 VFD (if any) vendor representative onsite
13 Access doors for all dampers installed (Ducts and Plenums) START-UP DATA:
14 Sound attenuator installed @ 12.5 Hz @25.0 Hz @ 37.5 Hz @ 50.0 Hz
15 Ductwork flexible connectors installed Measured Amps
16 Ductwork sealed as required and leak tested Measured Votage
17 Louvers(extract) installed STATIC PARAMETER
18 Start-up Filters Installed. Return Air Static Pressure : Pa
Exhaust Air Static Pressure: Pa
Electrical: External Static Pressure: Pa
19 Electrical connections / termination complete (MCC Sign-off) Deficiency Corrected:
20 Isolator switch installed & terminated :
- Return Fan
- Recovery Fan
21 Overload protection in place (sized correctly)
22 AHU internal lightings complete and functional.
* indicates unobtanable ** indicates not stated *** not applicable
WITNESS
Vendor / Installer Representative i2i Representative BAYTUR Representative KEO Representative
Name: Name: Name: Name:
Date: Date: Date: Date:
Signature: Signature: Signature: Signature:

You might also like