Professional Documents
Culture Documents
3, AUGUST 2007
937
same time, the power supply from the large central power plants
responsible for reactive power and voltage control and maintaining power system stability has to be reduced to keep the active power balance in the grids. In several European countries,
there are also plans for substituting such central power plants by
large offshore wind farms [1], [2].
Therefore, this paper focuses on maintaining short-term
voltage stability of the large wind power systems with a
possible lack of reactive-power and voltage control due to displacement of domestic power plants [1][3]. In such situations,
stable and reliable operation of the large wind power systems
may rely on strong ac connections to the neighboring power
systems with a sufficient amount of such control.
This paper is inspired by a stability investigation performed
by the Danish TSO, Energinet.dk, for the Western Danish wind
power system being in (almost) island ac operation. The investigation is carried out for a realistic case study where the strong ac
connections to the UCTE synchronous area were out of service
for a period. This paper gives a brief introduction to the Western
Danish wind power system and outlines the main outcomes of
the investigation performed. The results presented in this paper
might particularly be addressed to the operators of power systems that are in island ac operation and with plans for massive
incorporation of wind powerGreat Britain, Ireland, Tasmania,
etc. [4], [5].
I. INTRODUCTION
Manuscript received August 29, 2006; revised December 14, 2006. Paper no.
TPWRS-00586-2006.
V. Akhmatov is with Siemens Wind Power A/S, DK-7330 Brande, Denmark
(e-mail: vladislav.akhmatov@siemens.com).
P. B. Eriksen is with Energinet.dk, Transmission System Operator of Denmark, Fjordvejen 1-11, DK-7000 Fredericia, Denmark (e-mail: pbe@energinet.
dk).
Digital Object Identifier 10.1109/TPWRS.2007.901283
938
TABLE II
WIND TECHNOLOGY BY INSTALLED WIND POWER IN DENMARK
TABLE I
KEY FIGURES OF THE WESTERN DANISH POWER SYSTEM
In dynamic stability investigations, the Danish TSO, Energinet.dk, uses the simulation tool PowerFactory from the
supplier DigSilent, Gmaringen, Germany. The transmission
system model contains all the 400-kV and 150-kV substations,
the transmission lines and transformers in Western Denmark
and part of Northern Germany, the distribution transformers
and equivalents of the underlying distribution networks with
distributed generation and consumption. Furthermore, Energinet.dk has implemented detailed, unit-specific, dynamic
models of all the central power plants, the offshore wind farm
Horns Rev A, and the HVDC links. In this investigation, the
distributed wind turbines are represented as fixed-speed wind
turbine equivalents. The models of distributed combined heat
and power (CHP) units relevant for this investigation are given
by suitable generic equivalents [3].
The models applied by Energinet.dk are partly validated from
measured events in the transmission system (see the Appendix).
III. MOTIVATION
The UCTE synchronous area provides about two thirds of
the short-circuit capacity of the Western Danish transmission
AKHMATOV AND ERIKSEN: LARGE WIND POWER SYSTEM IN ALMOST ISLAND OPERATION
system. The strong 400-kV ac connections to Northern Germany account for about 80% of the active power transport
between Western Denmark and the UCTE synchronous area.
This underlines the importance of these 400-kV ac connections
for reliability and stability of the Western Danish wind power
system.
In summer 2006, the 400-kV substation at Wilster in Northern
Germany was planned for renovation. Thus, one of the two
400-kV ac connections to the UCTE system was planned to
be out of service. During the planned period of renovation, the
400-kV system of Western Denmark would be connected to the
UCTE system through a single 400-kV tie (see Fig. 1).
Operational situations in which this 400-kV tie could also
be out of service (forced) were also taken into consideration.
The 220-kV ac connections to Northern Germany were still in
service. In that case, the Western Danish wind power system
would be in almost island ac operation.
Stability of the Western Danish wind power system may not
be jeopardized despite such an unusual operational situation.
The Danish TSO, Energinet.dk, performed a voltage stability
investigation to specify the arrangements needed to maintain
stable operation of the Western Danish wind power system.
A. Grid Disturbance
The grid disturbance for this investigation is a three-phase,
short-circuit fault applied to a 400-kV line in the Western Danish
system. The fault duration is 100 ms, and the fault is cleared
by tripping the line. The investigation is carried out for several
400-kV lines subject to such a short-circuit fault.
This paper presents the results for a three-phase fault on the
400-kV line between the substations Tjele and Ferslev, shown
in Fig. 1, which is among the most critical events.
939
Fig. 2. Voltage at 400-kV substation Tjele when the 400-kV tie to the UCTE
area is in service. Number of domestic central power plants in operation is a
parameter of the investigation.
B. Success Criterion
The success criterion must be formulated to see if the goal of
the investigation is reached. For this investigation, the success
criterion consists of the following requirements.
1) Voltage in the transmission system must be re-established
within a specified range and stabilized, e.g., all possible
voltage fluctuations must be damped out.
2) Since the wind turbines have prioritized access to the
grid, all the possible alternatives without reduction of the
power generation from the wind turbines must be taken
into account and investigated before such reduction can
be proposed.
For Western Denmark, this means that a certain number of
central power plants must be in operation to maintain short-term
voltage stability, although reduction of the power supply from
wind turbines (for example, by ordering some of the wind turbines to stop during a critical period) would have a positive effect on voltage stability.
Note that the use of more central power plants to stabilize
operation of the Western Danish wind power system without reducing the wind power generation or increasing the power consumption results in increased export to the Nordel area through
the HVDC links.
C. The 400-kV Tie to Germany in Service
Simulation results illustrating short-term voltage stability of
the Western Danish system with the number of domestic central
power plants in operation as a parameter of the investigation are
shown in Fig. 2.
When the 400-kV ac tie to Northern Germany is in service,
the German power plants contribute to the voltage reestablishment in the Western Danish wind power system. However,
maintaining short-term voltage stability does not seem possible
without use of domestic central power plants.
This investigation has shown that at least three domestic central power plants must be in operation to maintain short-term
voltage stability.
Note that the grid voltage recovers when at least two central
power plants are in operation. The third power plant is required
940
AKHMATOV AND ERIKSEN: LARGE WIND POWER SYSTEM IN ALMOST ISLAND OPERATION
941
Fig. 4. Specified voltage profile for the fault-ride-through test according to the
Danish Grid Codes [8], [12].
Fig. 5. Area of the Danish transmission system validated from the described
event at the 150-kV line between substations Herning and Sdr. Felding.
942
Fig. 6. Voltage and current in three phases at the 150-kV substation Karlsgrde, the on-land connection point of the Horns Rev A wind farm. (a) Measured. (b)
Simulated.
AKHMATOV AND ERIKSEN: LARGE WIND POWER SYSTEM IN ALMOST ISLAND OPERATION
943