Professional Documents
Culture Documents
MBEG 1134
Question
Answer
Introduction
Concurrent delay is two or more occurrences that operate at the same time to
delay the progress of the Works. Where the delays in question act on different
activities, the matter is easily resolved by inputting the delays, one at a time, into
the contractors programme and checking the results as the process continues 1.
However, not all of those events enable the contractor to claim an extension of
time or to claim loss and expense2.
SESSION 2014/2015
MBEG 1134
a construction projects by which they can resolve issues and avoid disputes. The
Protocol defines true concurrent delays as the occurrence of two or more delays
events at the same time, one an employer risk event, the other a contractor risk
event and the effects of which are felt at the same time.5
In analysing concurrent delays, each delay should be assessed separately and its
impact on other activities and the project date for completion calculated. Much
will turn on the quality of planning and programming, and record keeping. Not
only will there often be several delay events running in parallel, but there may be
parallel critical paths to contend with and periods of acceleration and/or
mitigation to take into account. The contract conditions will also have to be taken
into account on the analysis technique used6.
Devlin Approach
5 The Society of Construction Law, U.K., Delay & Disruption Protocol, 2002
6 Gibson R., Technical Papers : Dispute Resolution 03, Gibson Consulting Limited, May 2010
7 Ramsey V. & Furst S., Keating on Construction Contracts, 9th Ed., Sweet & Maxwell, 2015
8 [1950] 1 All England 1033
2
SEMESTER 2
SESSION 2014/2015
MBEG 1134
If a breach of contract is one of two causes of a loss, both causes cooperating and both of approximately equal efficacy, the breach is
sufficient to carry judgment for the loss.....
9 Adrian Williamson QC, Concurrency In Construction Delays, Keating Chambers, UK, 2005
10 [1987] 3 9 BLR 106
3
SEMESTER 2
SESSION 2014/2015
MBEG 1134
In both City Inn Limited v Shepherd Construction Limited 11 and John Doyle
Construction Limited v Laing Management (Scotland) Ltd 12, Drummond Young LJ,
when talking about concurrency in respect of extensions of time and loss,
supported the proposition of the dominant or proximate cause approach, which
was said to derive from Leyland Shipping Company Limited v Norwich Union Fire
Insurance Society Limited13 and other insurance cases14.
The Burden of Proof Approach contends that if there are two causes and the
claimant is in breach of contract, it is for the claimant to show that the loss was
caused otherwise than by his breach15.
SESSION 2014/2015
MBEG 1134
This approach has the great advantage that it can be applied equally to both
claim and counterclaim. There can only be one dominant cause of any particular
period of delay. If the dominant cause is the contractual responsibility of the
Employer, the Contractor gets loss and expense and does not pay liquidated
damages. If the dominant cause is the contractual responsibility of the
Contractor, his claim for loss and expense fails and he must pay liquidated
damages for the period of delay17.
Conclusion
Keating defined three type of approaches to justify the concurrent delays which is
The Devlin Approach, The Dominant Cause Approach and Burden of Proof
Approach. The Devlin Approach which contends that if there are two causes
operating together and one is a breach of contract, then the party responsible for
the breach will be liable for the loss. The Dominant Cause Approach contends
that if there are two causes, the effective, dominant cause is to be the deciding
factor. Lastly, The Burden of Proof Approach; which contends that if there are two
causes and the claimant is in breach of contract, it is for the claimant to show
that the loss was caused otherwise than by his breach.
17 Adrian Williamson QC, Concurrency In Construction Delays, Keating Chambers, UK, 2005
5
SEMESTER 2
SESSION 2014/2015