Professional Documents
Culture Documents
1.0
SHEET
OF 4
1OF 10
SCOPE
The scope shall include complete ash handling system comprising
bottom ash handling system, fly ash handling system, bottom ash
storage silo, fly ash storage silo and equipment below silo. The ash
handling system and equipment to be supplied shall be as per the
system description and flow diagram enclosed. The ash handling
system shall be complete in all respects with all mechanical, civil,
structural, electrical and instrumentation.
The extent of supply under the contract includes all items shown in
the drawings, not with standing the fact that such items may have
been omitted from the specifications or schedules. Similarly the
extent of supply also includes all items mentioned in the
specification and / or schedule not with standing the fact that such
items may have been omitted in the drawings.
2.0
SYSTEM DESCRIPTION
Independent ash removal systems are proposed, one for bottom
ash( submerged scraper chain conveyor, clinker grinder and belt
conveyor system) and another for fly ash(pressure pneumatic
conveying system). The descriptions of ash handling systems are
furnished below:
2.1
2.1.1
( 2 x 77 MW Units )
( Refer flow diagram No. TCE.4084A-570-FD-1007 & plot plan
drawing No. TCE.4084A -100-GA-1001)
Bottom ash generated shall be collected in the dry type refractory
lined bottom ash hopper. Bottom ash from refractory lined ash
hopper shall be conveyed to the silo as shown in the flow diagram.
Bottom ash collected in the silo shall be loaded into the open trucks
through feeder for further disposal by others. Clinker
grinders( 1w+1s), belt conveyors from the outlet of clinker grinder to
the common conveyor shall be Unitwise.The conveyor to Bottom
Ash silo and the bottom ash silo are common for both the units.
SECTION: D 1.8
SHEET
OF 4
2OF 10
SECTION: D 1.8
SHEET
OF 4
3OF 10
below each fly ash hopper which shall be used during maintenance
of the ash transmitter vessel.
Three (3) reciprocating compressors, one standby,one operating for
two units during normal operation and two operating for both units
during rapid evacuation shall be provided to meet the conveying air
requirements of fly ash handling system of 2 x 77 MW Units .
2.3
2.3.1
2.3.2
3.0
SYSTEM CAPACITY
3.1
3.1.1
The minimum rate of generation of bottom ash shall be considered
as 20 % of total ash generated from worst coal. The rated capacity of the
scraper conveyor for each unit shall be based on 150 % margin over bottom
ash generation rate based on Imported worst coal. Accordingly, the capacities
of clinker grinder and all belt conveyors shall be determined. Clinker grinder
and belt conveyors shall be common for both the units.
SECTION: D 1.8
TITLE
4OF 10
3.1.2
The rated capacity of disposal equipment below the ash silo shall
be 30 TPH.
3.2
3.2.1
The rate of generation of fly ash shall be considered as 90 % of total
ash generated from the Imported worst coal. Normally the fly ash
conveying system shall operate continuously with time gaps
between cycles. However, the capacity of fly ash handling system
shall be designed to clear the ash collected in 8 hours in about 4
hours time considering imported worst coal and Indian coal.
Accordingly all the equipment shall be sized.
3.2.2
The rated capacity of disposal equipment below fly ash silo shall be
30 TPH.
4.0
4.1
(b)
Bottom ash
(i)
(ii)
: 1600 kg/cu.m
Fly ash
(i)
(ii)
4.2
800 kg/cu.m
500-800
: Abrasive
:
1600 kg/cu.m
The pneumatic handling system for fly ash shall be of dense phase
and the velocity of air ash mixture shall not exceed 10 m/s.
SECTION: D 1.8
SHEET
OF 4
5OF 10
4.3
4.4
High and low level probes shall be provided in each ash hopper for
measuring the evacuation rate during PG test.
4.5
In case vent valves are provided for the transmitter vessels this vent
connection shall be provided above the highest ash level in the
hopper.
4.6
The movements of the fly ash hoppers, due to the expansion shall
be considered and the Contractor shall include suitable expansion
joints as necessary in the fly ash pipe lines. The expansion joints
shall be of stainless steel construction.
4.7
The radius of 900 bends shall be minimum 5 times the pipe diameter.
4.8
Fluidising pads in fly ash silos, ESP hoppers and other vessels shall
be preferably of woven stainless steel and should withstand
temperature upto 170C.
4.9
Ash silos shall be provided with access ladder inside the silos and
external staircase from ground level to different platforms.
4.10
4.11
The motor rating for all the equipment shall have a margin of 10%
over the BKW. The service factor for selection of gearboxes,
resilient couplings, flexible couplings, brakes etc., shall be 1.5
minimum on the motor rating.
4.12
The type of high speed coupling between motor and gear box shall
be as follows :
(a)
: Resilient type
(b)
4.13
The emission level at the outlet of the bag filter shall be limited to
100 mg / cu.m
SECTION: D 1.8
SHEET
OF 4
6OF 10
5.0
5.1
Layout Requirements
5.1.1
5.1.2
The layout of water piping for the ash handling system shall ensure
that all valves are located so as to be conveniently accessible. All
the water piping from the pump house to bottom ash hopper area,
scraper feeder, fly ash storage silo area shall be routed in the
overhead pipe rack only. In no case, the water pipes shall run in
the trench.
5.1.3
5.1.4
5.1.5
5.1.6
5.1.7
5.1.8
5.1.9
SECTION: D 1.8
SHEET
OF 4
7OF 10
5.1.10
5.2
Maintenance Requirements
5.2.1
5.2.2
5.2.3
5.2.4
5.2.5
5.2.6
6.0
6.1
6.2
Operation philosophy
A microprocessor based PLC system with one (1) no. PC shall be
provided for the safe operation, control and monitoring of the entire
ash handling plant from the ash handling system control room. This
PC shall be used during start-up and commissioning. Suitable, RS
485 MODBUS links shall be provided to the main control room DCS
SECTION: D 1.8
SHEET
OF 4
8OF 10
for start / stop operation and monitoring of the plant during normal
operations. However, fly ash silo unloading system and bottom ash
silo unloading system shall be operated from the respective control
panel provided locally with the equipment / system with the
indication in the AHS control room and DCS.
6.3
6.3.1
The microprocessor based PLC shall be configured with hot backup redundancy for CPU,Power supply and communication ports for
PLC-DCS link. However, the IO cards, IO racks, rack power supply
shall be non-redundant. The system shall provide for sequencing of
automatic start-up / shutdown, bringing standby equipment into
operation on failure of main equipment and manual intervention
(auto / manual) facility for all the equipment from PLC. The PLC
shall be provided with one (1) no. operating cum programming
stations to perform operation and software changes. The input
/output modules shall be configured in non-redundant mode.
6.3.2
6.3.3
6.3.4
6.4
6.5
SECTION: D 1.8
SHEET
OF 4
9OF 10
6.5.1
6.5.2
6.5.3
6.5.4
Individual pair shielded and overall shield twisted pair copper cables
shall be used for analog signals and overall shielded cables shall be
used for digital signals. Individual and overall screened triplex shall
be used for RTDs. All the cables shall be armoured. The wire size
shall be 0.5 sqmm and the color coding shall be as per IEC. The
insulation including overall sheath shall be FRLS quality.
6.5.5
6.5.6
6.6
1.0
1.1
1.2
1.3
1.4
SECTION: D 1.8
(b)
(c)
(d)
(e)
(f)
1.5
SHEET
OF 4
OF 10
10
1.6
1.7
2.0
2.1
2.2
Fly ash piping layout from fly ash hoppers to fly ash silo.
Seal Water Piping
Compressed air piping
Water piping for fly ash collection system (to blower
and dust conditioner)
All pumps
Transmitter vessel
Fly ash valves
Pipe fittings
Dust conditioner
Rotary feeder
Clinker grinder
Blowers
Air Compressors
Fly ash collectors
Sump / drain pumps