Professional Documents
Culture Documents
2
Today’s Agenda
• Design Overview
• Client Goals and Challenges
• Application Engineering
Process
• Construction
• System Transition
• Success Factors
• Questions
Design Overview – Project Timeline
July 2008
January 2005 Corbalis Rated at 225 MGD
Construction Begins
June 2004
Final Design Complete
March 2003
Engineering Design Report
October 2002
Expansion Capacity Study
(Plant Rated at 150 MGD)
Design Overview – Control System
Scope of Work
OWS/LOP
-Replace existing -Add new controls
control system to support the new
hardware and “Process Train”
software along with other
plant upgrades
- Install new fiber
Controller
Controller
optic network
-Integrate existingField
control logic
Field
associated withInstruments
existing process
Instruments
equipment into new control system
SCADA System
Overview - Corbalis SCADA Components
Local Programmable
Operator Panels Logic Controllers Operator
Workstations
Overview – SCADA Network Redundancy
2 Hr. Back-up
No Data from
UPS time for SCADA
DYNAC Equipment and
Chem. Bldg. @ OWS
Instruments.
LOP Used this OWS
to Control
Process LOP
LOP
6-Pair Fiber
Locally
PLC
PLC
MES
MES
Chem. Bldg.
X
UPS
X Corbalis DYNAC
OWS
SCADA “Ring” MES
MES
MES
MES
No Data from
Chem. Bldg. @
HES – Hirschman Ethernet Switch Facility Support Center this OWS
LOP – Local Operator Panel
OWS – Operator Workstation
PLC - Programmable Logic Controller
UPS – Uninterruptible Power Supply
Design Challenges
• Develop an understanding of
the existing system
• Avoid Technology
Obsolescence
• Ensure a “smooth” system
transition with minimal
downtime
• Develop drawings and
documents that clearly indicate
scope of work
Design Challenges
• Develop an understanding
of the existing system
- Consistent communication with
Fairfax Water staff
- Reviewing documentation
- “Walking” the system
- Taking time “on site” – no shortcuts
here.
Design Challenges
• Avoiding Technology
Obsolescence
– $200k Allowance
– Contractor restricted on
releasing computers for order
Design Challenges
Step-by-step procedures
Outage durations
Contingency plans
Critical Design Documents
Comm.
Cables
Vendor Panels
UPS
Piping (or Process) &
Instrumentation Diagram (P&ID)
Existing vs.
New Instr.
Vendor
Where signals Control Panels
are wired
Control Loop #s and
Description
Strategies
PLC
Logic
LOP/OWS
Functions
Alarms and
Monitoring
Applications Engineering (AE)
• Major Components:
– HMI System
– PLC Systems
– Data Historian
– Plant Reports
– Data Network
AE Project Goals
• Moving Water
• Running on Multiple Computer Systems
• Interfacing to Different Generations of
Equipment
• Integration of “Vendor
Systems”
Application Engineering Process-
Collaboration During Development
• Frequent Communications
– Daily informal meetings
– Weekly formal meetings
• Teamwork
• Operator awareness of I/O
transition
• Developer’s on-site office
Success Factors
• No major shutdowns or
disturbances
• New system has been
embraced by operations
• Accessibility to developer
minimized need for formal
training
• Engineer’s Work Plan has
evolved into programming
standards
Standards
Certification
Education & Training
Publishing
Conferences & Exhibits