You are on page 1of 1

Activity

ID

Activity
Description

Orig Rem
Dur Dur

Predecessors

Early
Start

Early
Finish

17DEC10
01:00

23DEC10
07:59

17
18
0 6 12 18 0 6 12 18 0

DEC
19
20
21
6 12 18 0 6 12 18 0 6 12 18 0

22
6 12 18 0

23
24
6 12 18 0 6 12

Hot Tap Work


Subtotal

151

151

0 HT020*

17DEC10
01:00

17DEC10
08:59

48

48

0 HT010*

17DEC10
09:00

19DEC10
08:59

0 HT030*

19DEC10
09:00

19DEC10
16:59

HT040 Erect Spark Containment Habitat

18DEC10
02:00*

18DEC10
03:59

HT050 Perform lamination check/UT test

0 HT040*

18DEC10
04:00

18DEC10
05:59

HT060 Perform Ovality on hot tap location

0 HT050*

18DEC10
06:00

18DEC10
13:59

HT070 Submit UT Test/MPI result to consultant/client

0 HT060*

18DEC10
14:00

18DEC10
21:59

65

65

0 HT070*

18DEC10
22:00

21DEC10
14:59

0 HT080*

HT110 Crane and welding machine into position

0 HT320*

21DEC10
01:00

21DEC10
02:59

HT100 Operation line check/gas test

0 HT090*

21DEC10
15:00

21DEC10
15:59

Operation line check/gas test

HT120 Clamp split tee for 6" hot tap

0 HT100*,
HT110

21DEC10
16:00

21DEC10
16:59

Clamp split tee for 6" hot tap

HT130 Check with operation on flow parameter

0 HT120*

21DEC10
17:00

21DEC10
17:59

Check with operation on flow parameter

HT140 Fit-up/tack weld split tee on existing pipe

0 HT130*

21DEC10
18:00

21DEC10
18:59

Fit-up/tack weld split tee on existing pipe

HT150 Fit-up inspection(contractor/consultant/client)

0 HT140*

21DEC10
19:00

21DEC10
19:59

Fit-up inspection(contractor/consultant/client)

HT160 Welding(root run on branch section)

0 HT150*

21DEC10
20:00

21DEC10
20:59

HT170 Welding(root run on longitudinal section)

0 HT160*

21DEC10
21:00

21DEC10
21:59

HT180 NDT for both roots (MPI)

0 HT170*

21DEC10
22:00

21DEC10
23:59

HT190 Full fillet welding on circumstance existing pip

0 HT180*

22DEC10
00:00

22DEC10
03:59

HT200 Cap butt welds

0 HT190*

22DEC10
04:00

22DEC10
09:59

HT210 Pneumatic test on comp pad

0 HT200*

22DEC10
10:00

22DEC10
10:59

HT220 Install hot tap valve/blind for hydrotest

0 HT210*

22DEC10
11:00

22DEC10
11:59

HT230 Hydrotest split tee/valve

0 HT220*

22DEC10
12:00

22DEC10
13:59

HT240 Inspect hot tap machine prior to drilling

0 HT230*

22DEC10
14:00

22DEC10
14:59

Inspect hot tap machine prior to drilling

HT250 Hot tap drilling by tapping contractor

0 HT240*

22DEC10
15:00

22DEC10
16:59

Hot tap drilling by tapping contractor

HT260 Close HT valve/Depressurise/drain the tapping

0 HT250*

22DEC10
17:00

22DEC10
17:59

HT270 Remove hot tap cutter

0 HT260*

22DEC10
18:00

22DEC10
18:59

HT280 Install vent blind

0 HT270*

22DEC10
19:00

22DEC10
19:59

HT290 1st PSSR-Contractor/Consult/Client clear punches

0 HT280*

22DEC10
20:00

22DEC10
23:59

HT300 Touch-up paint on hot tap nozzle

0 HT290*

23DEC10
00:00

23DEC10
03:59

HT310 House keeping

0 HT300*

23DEC10
04:00

23DEC10
07:59

Work Pack 010


Tie-in 200
Procurement
HT020 Hot tap material received

17DEC10
00:59*

Hot tap material received

Off Site Fabrication


HT010 Fabriate Hot tap split tee
HT030 Blast & Paing Hot tap split tee
HT320 Delivery to site

Fabriate Hot tap split tee


Blast & Paing Hot tap split tee
Delivery to site

Preliminary Activities

HT080 Approve to weld on hot tap location


HT090 Hot work permit received

Erect Spark Containment Habitat


Perform lamination check/UT test
Perform Ovality on hot tap location
Submit UT Test/MPI result to consultant/client
Approve to weld on hot tap location

21DEC10
14:59

Hot work permit received

Execution
Crane and welding machine into position

Welding(root run on branch section)


Welding(root run on longitudinal section)
NDT for both roots (MPI)
Full fillet welding on circumstance existing pip
Cap butt welds
Pneumatic test on comp pad
Install hot tap valve/blind for hydrotest
Hydrotest split tee/valve

Close HT valve/Depressurise/drain the tapping


Remove hot tap cutter
Install vent blind

Post Activities

Start Date
Finish Date
Data Date
Run Date

17DEC10 00:00
23DEC10 07:59
17DEC10 00:00
04JAN11 07:28

Early Bar

HTAP

Critical Activity

House keeping

Date

Hot Tapping Work


Classic Schedule Layout

Primavera Systems, Inc.

Touch-up paint on hot tap nozzle

Sheet 1 of 1

Float Bar
Progress Bar

1st PSSR-Contractor/Consult/Client clear punches

Revision

Checked

Approved

You might also like