Professional Documents
Culture Documents
DIVISION 7
CONCRETE WORKS
SECTION 07100 - CONCRETE AND CONCRETE STRUCTURES...........2
SECTION 07200 - PRECAST CONCRETE PILES..............................33
SECTION 07250 - BORINGS FOR PILE BEARING CAPACITY............43
SECTION 07300 - CAST-IN-SITU PILE..........................................47
SECTION 07350 PILE DYNAMIC TESTING..................................63
SECTION 07400 - PRESTRESSED CONCRETE................................67
SECTION 07500 - REINFORCING STEEL.......................................83
SECTION 07600 - BRIDGE BEARINGS..........................................91
SECTION 07700 - WATERPROOFING.........................................101
SECTION 07800 - EXPANSION JOINT.........................................105
SECTION 07900 - BRIDGE DRAINAGE........................................112
-1-
-2-
Method of Measurement................................................................33
Basis of Payment...........................................................................33
-3-
1.
DESCRIPTION
This specification consists of the supply, transport and placing of concrete
mixes of different classes and concrete construction work in accordance with
the lines, grades, sections and other detail shown on the drawings or subject
to approval by the Engineer.
The figure below shows the applicable referencing of structural sections:
Figure
for
Payment
Reference only)
Item
(for
Water Roof:
RC Slab ;
Cross Beam;
Bearing ;
Cross Head ;
Prestreed Beam
& Concrete Form ;
Approach Slab:
Pier ;
Reinforcing
Steel ;
Box Culvert ;
Footing or
Pile Cap ;
Wing Wall ;
Apron ;
2.
REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied to
the works covered by this Specification.
TCVN 5438-04
TCVN 5439-04
TCVN 2682 92
TCVN 4029-85
TCVN 4030-03
TCVN 4031-85
TCVN 4032-85
testing
Cement. Test method for determination of fineness
Cements
Method
for
determinatoin
of
standard
workability
TCVN 6016-95
TCVN 6017-95
AASHTO M6
AASHTO M33
AASHTO M80
AASHTO M85
-4-
AASHTO M115
AASHTO M116
AASHTO M118
AASHTO M148
AASHTO M153
AASHTO M182
AASHTO T22
AASHTO T23
AASHTO T96
AASHTO T119
AASHTO T121
AASHTO T134
AASHTO T141
AASHTO T224
ASTM C31
ASTM C33
ASTM C39
ASTM C40
ASTM C87
ASTM C88
ASTM C91
ASTM C94
ASTM C109
ASTM C123
ASTM C136
ASTM C138
ASTM C143
ASTM C144
ASTM C150
ASTM C227
ASTM C287
ASTM C294
ASTM C295
ASTM C494
ASTM C827
ASTM C1017
ASTM C1077
-5-
3.
CONSTRUCTION REQUIREMENTS
General
(a)
(b)
(c)
(a)
(b)
(c)
(c)
Bagged cement shall bear the manufacturers name, cement type and
the date of manufacture and shall be stored in waterproof sheds or
other such temporary buildings used exclusively for the storage of
cement. Cement shall be stored in dry conditions on areas raised
above ground level. Storage capacity shall be sufficient to hold enough
cement for the largest units to be cast. Bags shall not be stored more
than 8 high and a free passage of at least one meter shall be left
between the cement and the side walls of the sheds.
(d)
(e)
3.1.2
-6-
the order in which they were delivered. Any delivery which has become
caked or otherwise adversely affected shall be removed from the Site
at the Contractors expense.
(f)
3.1.3
(a)
(b)
(a)
(b)
3.1.4
-7-
Compressive Strength
ASTM C40
Organic Impurities
ASTM C87
Mortar Strength
ASTM C88
Soundness
ASTM C123
ASTM C136
Sieve Analysis
(a) Fine aggregate shall consist of natural sand with hard, strong,
durable particles or other inert materials with similar
characteristics. Fine aggregate shall be clean and free from
extraneous materials, clay balls, organic matter or other
detrimental material in accordance with AASHTO M6.
The
maximum combined quantity of soluble chloride and sulphate in
fine aggregate shall not exceed 1,000 ppm.
(b) Fine aggregate shall be reasonably graded and shall meet the
grading requirements mentioned in Table 1.
(c) Fine aggregate shall be of such uniformity that the fineness
modulus as defined in AASHTO M6 shall not vary more than 0.20 in
either way from the fineness modulus of the representative
samples used in the mix designs.
Table 1 : Grading Requirements of Fine Aggregate
Sieve Size
(mm)
9.5
4.75
2.36
1.18
0.600
0.300
0.150
(a)
(b)
-8-
(c)
3.1.5
Admixtures
The use of any admixtures will require the approval of the Engineer. Each
type and each location or purpose shall be approved individually. Approval
will be dependent upon the submission of mix designs and satisfactory trial
mixes to demonstrate the function of the admixture.
3.2 Concrete Classes
(a)
(b)
(c)
Minimum Concrete
Strength at 28days
(150x300mm Cylinder)
(Mpa)
Maximum Size of Course
Aggregate (mm)
Minimum Cement Content
(kg/m3)
Maximum W/C Ratio (%)
Slump (mm)
C50
C35
C30
C30(for
bored
pile)
C25
C20
C10
50
35
30
30
25
20
10
20
20
20
20
20
25
40
450
380
350
350
330
280
175
30
50100
39.5
50100
45
50100
49.4
50
50100
55
50100
76
100
90100
100
90100
100
95100
25-60
25-60
25-60
130-170
25-75
Coarse Aggregate
Sieve Size
37.5mm
25.0mm
19.0mm
12.5mm
Volume 3 Technical Specification
100
100
100
90100
30-70
90100
30-70
90100
30-70
-9-
100
90-100
30-70
Location
Precast Girder (Super T)
CIP Deck Slab (incl Link Slab), Crossbeam of Super T
Abutment, Pier, Precast Concrete Plank for Super T
Bored Pile
Parapet, Pedestal of Lamp Post, Approach Slab
Sealing Concrete
Blinding Concrete
(a)
The Contractor shall submit his proposed mix designs to the Engineer
for his approval and prepare samples in order to Engineer checked
(c)
A new mix design shall be submitted to the Engineer for his approval if
there are any changes in characteristics or source of supply of any of
the component parts of the mix. Any delay due to such changes shall
be entirely the responsibility of the Contractor.
(d)
During the execution of the Works, the Engineer may require additional
tests to be made on the work mix to check compliance with the
approved Mix Design.
Water - Cement Ratio
3.2.2
(a)
The Contractors proposed water content and water cement ratio shall
be included in the mix designs, supported by trail mixes, submitted to
the Engineer for his approval. The water content shall be the least
amount that shall produce a workable homogeneous plastic mixture.
Excess water shall not be permitted and any batch containing such
excess shall be rejected.
(b)
The total water content for any batch of concrete shall include an
allowance for water contained in the aggregates. The Contractor shall
determine the water content of the aggregates before concrete
- 10 -
batching begins and admixture (if any). The water added to the mix
shall be adjusted for the water contained in the aggregates.
(c)
Frequent slump tests shall be carried out to ensure that the workability
of the concrete remains consistent.
3.2.3
After a mix design has been approved, the mix shall not be changed during
the progress of the work except as follows:
If it is found impossible to obtain concrete of the desired workability with the
mix proportions originally determined, changes in aggregate weights may be
made subject to the approval of the Engineer.
If it is found impossible to produce concrete of the minimum allowable
strength specified, the cement content may be increased subject to the
approval of the Engineer.
3.2.4
(a)
The amount of chloride in the concrete mass shall not exceed 1,000
ppm of the total concrete mass, or 6,000 ppm of the amount of cement
in the mix.
(b)
The amount of sulphate in the concrete shall not exceed 800 ppm of
the total concrete mass, or 5,000 ppm of the amount of the cement in
the mix.
(c)
3.2.5
Submittals
(a)
The Contractors submissions shall be made well before the start of any
concrete work on site. The Contractor shall bear in mind the time
required for submitting and gaining the approval of all constituents of
the mix and the time required to prepare mix designs and prove them
by trial mixes and subsequent cylinder tests. The Contractor shall also
allow sufficient time for the Engineer to review the submissions and to
conduct any additional trial mixes and tests that might be necessary.
(b)
Each mix design submittal shall include, but not be limited to, the
following:
(a)
Project identification;
(b)
(c)
(d)
(e)
Material proportions;
(f)
(g)
- 11 -
(i)
The saturated surface dry batch mass of the coarse and fine
aggregates in kilogram per cubic meter of concrete;
(j)
(k)
(l)
(m
)
Dosage of admixtures;
(n)
(o)
(p)
Bulk specific gravity (dry and saturated surface dry) of fine and
coarse aggregates;
(q)
(r)
(s)
(t)
(u)
(v)
(w
)
Design
(a)
(b)
- 12 -
The design shall be appropriate for such temporary works and shall
take into full consideration all temporary loading cases arising from
the procedures and work sequences, the prevailing conditions at the
site, in particular likely wind loading, and the nature of the existing
ground. The Contractor shall carry out all additional soils investigation
necessary to confirm his assumptions concerning the nature of the
existing ground.
(d)
Formwork and falsework shall be designed for vertical load and lateral
pressures in accordance with ACI 347 and, where appropriate, any
increased or re-adjusted loading that may result from pre-stressing
forces. If retarding admixtures are used, their effect shall be duly
considered during the calculation of the lateral pressures of the fresh
concrete. The formwork and falsework shall be designed and
constructed to ensure completed concrete surfaces comply with the
tolerances specified in ACI 347 or elsewhere in this specification.
(e)
The shop drawings and working drawings shall show the proposed
details of construction of members, spacing of bents, posts, studs,
walings, stringers, collars, bolts, wedges, bracing, rate of pour, and
the manufacturers recommended safe working capacity of all form
ties and column clasps. All assumptions, dimensions, material
properties and other data used in the structural analysis shall be
noted on the shop drawings. The Contractor shall furnish copies of
the design calculations to the Engineer for his consideration when
approving the Contractors proposals.
(f)
(g)
(h)
- 13 -
railing.
3.3.2
Construction of Formwork
(a)
(b)
Wooden boards shall be cut accurately to shape and fixed such that
there are no openings after the wetting of the formwork prior to
placing concrete.
(c)
(d)
(f)
All exposed sharp edges shall be chamfered using triangular fillets not
less than 2 cm by 2 cm in size, unless otherwise directed by the
Engineer. The triangular fillets or chamfer strips shall be milled from
clear, straight grain lumber and shall have a finished surfaced on all
sides. Curved surfaces shall be formed of plywood, metal, or other
suitable material.
(g)
- 14 -
(j)
(k)
(l)
Tolerances
Spacing of reinforcement
Within 10mm
Concrete
cover
Superstructure
Concrete
structure
cover
for
for
other
- 15 -
Within 5 mm
Within 10mm
(n)
3.3.3
(a)
Formwork/Falsework
Pre-tensioned T beams
- / 85%
- / 100%
14 days / 80%
Floor slabs
14 days / 70%
Columns
2 days / 70%
1 day / 70%
To enable finishing, forms used for parapets, barriers, and exposed vertical surfaces
shall be removed between 24 hours and 48 hours after casting, depending on
weather conditions.
- 16 -
3.4 Concreting
3.4.1
General
(a)
(b)
(c)
(d)
(e)
The batching of concrete shall not begin until such time as all the
equipment and labour required for batching, transporting, placing,
compacting, finishing and curing the concrete is in place in
accordance with the Contractors approved method statement.
Batching
(a)
(b)
The Contractor shall submit his method statement for the batching
and mixing of concrete to the Engineer for his approval. The
statement shall include the location of the batching and mixing plant,
the type or types of mixers and machines to be used, arrangements
for the storage of aggregates and the batching and mixing of concrete
and transporting concrete from the batching plant to the site.
(c)
The type of mixer shall be a drum mixer. Mixers of less than 0.5 cubic
meter capacity shall not be used to batch structural concrete. The
use of continuous mixers will not be permitted.
(d)
The batching plant shall include separate bins for the bulk cement,
fine aggregate and for each size of coarse aggregate, a weighing
3.4.2
- 17 -
(g)
(a)
(b)
(c)
(2) Water
(a)
(b)
(3) Aggregates
(a)
(b)
3.4.3
(a)
When mixed batches are hauled to the mixer, bulk cement shall be
transported either in waterproof compartments or between the fine
and coarse aggregates. Where cement is placed in contact with moist
- 18 -
(c)
(d)
Any arrangements for the cooling of the mixing water as and the
handling of admixtures shall be subject to approval by the Engineer.
(e)
(f)
The volume of concrete mixed per batch shall not exceed the mixers
nominal capacity as shown on the manufacturers standard rating
plate on the mixer. Water shall be added as required by clause 3.4.2
(2)b above.
(g) Mixing shall continue for the minimum times shown below after all the
water has been added.
mixers having a capacity of 1.5
m3 or less
minimum
seconds
60
minimum
seconds
90
minimum
minutes
1.5
each
additional
capacity or fraction
be increased
15 seconds
by
minimum
seconds
70
500
liter
Mixing time shall be measured from the time all materials, except
water, are in the drum.
(i)
- 19 -
time the lock is released. If the timing device fails, the Contractor
may continue operations for up to 24 hours while it is being repaired,
provided he furnishes an approved timepiece equipped with minute
and second hands. After 24 hours the mixer shall not be used until
repairs are made.
(j)
(k)
Concrete that is not in place within one hour of the time when
ingredients were charged into the mixing drum, or concrete that has
developed an initial set, shall be rejected.
3.4.4
Concrete Consistency
The concrete slump shall be determined by the Contractors trial mixes and
shall be measured in accordance with AASHTO T119.
3.4.5
Pumping
(a)
(b)
(c)
(d)
3.4.6
(a)
(b)
Concrete shall be placed gently in position and shall not have a free
fall of more than 1.5m to avoid segregation of the materials and
displacement of the reinforcement.
(c)
(d)
- 20 -
(e)
Pipes or chutes may be allowed for small sections and bottom dump
buckets or other suitable vessels may be allowed for large sections to
convey the concrete as near as possible to its final position.
All concrete shall be placed and compacted in even layers with each
batch and each layer merged with the previous one.
(i)
(j)
(k)
(l)
Concreting in any one part or section of the work shall be carried out
in one continuous operation and no interruption of work will be
allowed.
(o)
(p)
After a beam, wall or column has been cast, an interval of one hour
shall be allowed before casting the continuous slab. The same applies
for all abrupt changes in sections.
(q)
- 21 -
(r)
(s)
3.4.7
(a)
(b)
(d)
(e)
Bottom opening skips shall be straight sided, smooth and fitted with
externally operated bottom opening double doors and overlapping
canvas flaps.
(a)
(b)
3.4.8
- 22 -
(c)
(d)
3.4.9
(a)
The Contractor shall carry out the work in such a manner that the
placing of concrete in any particular section of the structure shall be
executed without any interruption whatsoever from the beginning to
the end of the operation. If interruptions occur, no fresh concrete
shall be deposited on or against the concrete placed before the
interruption such time as the concrete is sufficiently set to permit the
formation of a construction joint.
(b)
(c)
3.5 Joints
3.5.1
General
(a)
(b)
(c)
3.5.2
Construction Joints
(a)
(b)
(c)
All joints which are exposed to view shall be carefully finished true to
line and elevation. After the header board has been removed, laitance
shall be removed from the surface by washing with water under
pressure or by sandblasting to expose clean, well bonded aggregate.
After the surface has been prepared, the concrete shall be left
- 23 -
3.5.3
After the header board has been removed, laitance shall be removed
from the surface by washing with water under pressure or by
sandblasting to expose clean, well bonded aggregate. When the
concrete has been cured for the normal period, the second pour shall
be bonded to the first pour by the application of a two-component
liquid polysulphide polymer epoxy resin concrete adhesive to the
concrete joint surface. The epoxy concrete adhesive shall be subject
to approval by the Engineer.
(b)
(c)
d)
(e)
- 24 -
The joint between the deck slab and the coping shall be de-bonded using an
approved elastic material which shall allow movement between the slab and
the coping. The Contractor shall submit his proposal for the provision and
placing of the de-bonding layer to the Engineer for his approval.
3.6 Concrete Finishing
3.6.1
(b)
(c)
The types of surface finishes and necessary form works are as follows:
No particular requirements
for finishing
Class F2
Formed
Finish
Class F3
Class F4
Unformed
Finish
Class U1
Class U2
Class U3
3.6.2
Formworks
Sawn Formwork for
unexposed concrete
surfaces
Wrought Formwork of
steel or plywood or
timber.
Lined Formwork using
material approved by the
Engineer to be of the
same type and obtained
from one source
throughout for any one
structure.
-
(a)
- 25 -
Any concrete the surface of which has been treated before being
inspected by the Engineer will be liable to rejection.
3.6.3
Fixing of Ironwork
All brackets, lag-bolts and other ironwork for which holes have been boxed
out or left in the concrete of a structure shall be carefully grouted into their
correct positions.
3.6.4
Reconstruction of Faulty Work
In the event any members or portion of the work proves, after removal of
the formwork, to be of inferior workmanship or to be in any way
whatsoever defective, or should crushing tests on samples taken from the
work show that the concrete used therein is of inferior Quality, such work
shall, at the discretion of the Engineer, be cut out and replaced.
3.7 Curing
(a)
(b)
(c)
(c)
(d)
When forms are removed before the end of the 7-day curing period,
specified curing procedures shall be applied by the Contractor and
continued until the end of the 7-day period as specified.
3.7.1
- 26 -
3.7.2
(b)
(c)
- 27 -
(b)
The Contractor shall provide and install all pre-cast elements complete,
furnishing all materials, labour and equipment and performing all
required work as required by drawings, as specified herein, other
applicable Specification Sections and as may be required by the
Engineer.
(c)
The pre-cast constituents and component work shall include, but not be
limited to, the supply and installation of the pre-cast elements,
necessary grout and grouting and all appurtenances required for their
proper installation.
3.8.1
Materials
(a)
(b)
3.8.2
(a)
(b)
(d)
To ensure proper bond to the deck slab, the top surface of girders in
contact with deck slabs shall be given a rough exposed aggregate
finish. At approximately the time of initial set, all laitance shall be
removed with a coarse wire to expose the concrete aggregate.
(e)
(f)
All pre-cast members shall be lifted and supported only at the points
indicated on the drawings or as may be otherwise approved by the
Engineer.
(g)
- 28 -
items.
3.9 Quality Control of Concrete
3.9.1
General
(a)
(b)
(a)
3.9.2
(i)
(ii)
(iii
)
(iv
)
(v)
(vi
)
(b)
(c)
(d)
(e)
He shall ensure completion of the batch ticket, which shall include the
detail below, the recording of the apparent water/cement ratio, and
the time discharge are completed; furnishing a copy of each batch
ticket at the time of placement.
Concrete supplier
Ticket serial number
Date and truck number
- 29 -
Contractor
Structure or location of placement
Mix-design and concrete class
Component quantities and concrete total volume
Moisture corrections for aggregate moisture
Total water in mix at plant
Time of batching
Time at which discharge must be completed
(g)
(h)
The provision of copies of work sheets and test results as they are
completed.
3.9.3
(a)
(b)
(c)
(d)
(e)
The Contractor shall bear all expenses for obtaining, cutting out or
sampling all specimens and/or component parts for testing.
Compressive Strength Testing
(a)
3.9.4
(c)
- 30 -
OK
Alternative 2
stop placing
concrete
and rectifyAlternative
any
1
defect
Remove and replace the defective
concrete without waiting the results of
28-day test by the responsibility of the
Contractor
if No
OK
Countermeasure
s to be taken
Acceptance
of the Lot
3.10
Testing frequencies
Test Description
Test Frequency
Remar
k
Article 3
- 31 -
c
2
b
c
3.11
of
3.11.1
Strengths
(a)
(b)
(c)
If the results of the 28-day tests do not satisfy the minimum technical
requirements the Contractor shall conduct such additional test as
may be required by the Engineer.
(d)
If the concrete does not comply with the specifications, the Engineer
may order the Contractor to remove the defective concrete and
replace it with concrete of the specified Quality. All additional testing
and remedial work shall be at the expense of the Contractor.
(e)
(a)
3.11.2
Pier
Bearing
- 32 -
Wing wall
Apron
Approach
Concrete
Top Level
Center
Position
Dimension
Verticality
Top Grade
Pile cap
10 mm
column
5 mm
Pedestal
2.5 mm
5 mm
5 mm
Slab
5 mm
Railing
-
5 mm
5 mm
5 mm
5 mm
5 mm
1/300
10 to +50 mm*
1/ 300
1 in 200
2.5 mm
5 mm
1/500
3 mm in 3
5 mm
in 3 m
-
in 3 m
-
m (1/1000)
-
Irregularities
Wall Flatness
4.
(b)
At the discretion of the Engineer a payment of 90% of the bill item may
be included in a certificate for concrete which has been completed in an
otherwise satisfactory manner but for which the final curing is not
complete or the test for the 28 days compressive strength could not be
completed.
(c)
- 33 -
Pay Item
07100-01
07100-02
07100-03
07100-04
07100-05
07100-06
07100-07
Description
Concrete Class C50 MPa
Concrete Class C 35 MPa
Concrete Class C 30 MPa
Concrete Class C 25 MPa
Concrete Class C 20 MPa
Concrete Class C 10 MPa
Blinding crush stone
- 34 -
Unit
m3
m3
m3
m3
m3
m3
m3
Reference Standards.....................................................................36
Materials for Piling........................................................................36
Supply of Material........................................................................................... 36
Concrete......................................................................................................... 36
Reinforcing Steel............................................................................................. 36
3. CONSTRUCTION REQUIREMENTS........................................37
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
Submittals....................................................................................37
Requirement of Pile Works.............................................................37
Casting, Curing and Finishing........................................................38
Handling.......................................................................................38
Pilot Piles.....................................................................................38
Driving and Pile Construction.........................................................39
Pile installation by static pressing method (TCVN 286-20003 section 6)
40
Pile Splicing..................................................................................42
Defective Piles..............................................................................43
Pile Records..................................................................................43
- 35 -
1.
2.
DESCRIPTION
(a)
(b)
MATERIAL REQUIREMENTS
Supply of Material
The Contractor shall submit to the Engineer for his approval, samples of the
material to be provided and the names of the manufacturers and suppliers
who will supply the materials required for pile construction. The Quality of
the material provided shall be certified by the supplier, and samples shall
be tested under the supervision of the Engineer, at the Contractors
expenses.
2.2.2
Concrete
The concrete class to be used for pre-cast piles shall be as indicated on the
drawings and shall comply with the requirements of Specification Concrete and Concrete Structures.
2.2.3
Reinforcing Steel
The reinforcement steel to be used for pre-cast piles shall be as indicated
on the drawings and shall comply with the requirements of Specification Reinforcing Steel.
- 36 -
3.
CONSTRUCTION REQUIREMENTS
3.1 Submittals
The Contractors proposed method statement for pre-cast concrete piles
shall be submitted to the Engineer for his approval well before the start of
pile driving. The method statement shall include but not necessarily limited
to the following:
1
10
11
12
13
14
15
- 37 -
the Engineer.
(b)
(b)
(c)
Special care shall be taken to place the concrete to produce a pile free
from any air pockets, honeycombing or other defects.
(d)
(e)
(f)
Curing of concrete piles shall be in accordance with Specification Concrete and Concrete Structures.
(g)
(h)
Each face of the pile shall not deviate by more than 6 mm over a
length 3 m determined by using straight edge placed on each face.
(i)
(j)
Piles shall not be driven less than 28 days after casting or such reduced
time as may be approved by the Engineer.
3.4 Handling
(a)
(b)
Concrete piles shall only be lifted by slinging from the lifting holes or in
positions which have been submitted to and approved by the Engineer.
(c)
(d)
- 38 -
Test piles shall be driven with the same hammer, driving cap, and dolly
and packing materials that are used for driving foundation piles.
(c)
The Contractor shall keep a complete driving record of each test pile in
a form acceptable to the Engineer and complete with all data on the
piles including, but not limited to, hammer speed, operating stroke,
blows per 30 cm and final resistance.
(d)
Permanent piling works shall not commence until the construction and
records of the test piles have been approved by the Engineer.
(b)
(c)
(d)
All excavation for piled foundations shall be complete before the piles
are driven. The excavation shall be to such an elevation as to
compensate for possible uplift or subsidence of the surrounding earth.
(e)
(f)
The methods used for driving piles shall not subject them to excessive
and undue abuse that produces crushing and spalling of the concrete.
Manipulation of piles to force them into proper position, if considered
by the Engineer too excessive, will not be permitted.
(g)
(h)
(i)
The driving head shall keep the pile and the hammer on the same axis
to provide a driving surface normal to the top of the pile. The helmet,
dolly and any packing shall be in sound condition.
(j)
The hammer blow shall be in line with the pile axis and the impact
surface shall be flat and at a right angle to the pile and hammer axis.
- 39 -
(k)
(l)
(m) The Contractor shall temporarily suspend pile driving operations and
report to the Engineer whenever the following conditions occur:
* There is a sudden change in the penetration rate of the pile.
* The pile has been suddenly deflected or otherwise moved.
* The top of the pile has been seriously damaged.
(n)
All piles pushed up by the driving of adjacent piles or any other cause
shall be re-driven.
(o)
(p)
When water jets are approved for use, the number of jets and the
nozzle volume and pressure shall be sufficient to freely erode the
material adjacent to the pile. The plant shall have sufficient capacity to
deliver at all times a pressure equivalent to at least 690 kPa at two
19mm (3/4 inch) jet nozzles. The jets shall be shut off before the
required penetration is reached and the piles shall be driven solely by
hammers to final penetration as required by the Engineer. Water jets
shall not be used during penetration of the bearing stratum.
(TCVN 286-20003
- power of the equipment shall not be less than 1.4 times the maximum
pressing force in the design;
- pressing force of the equipment must be applied on the central axis of
the pile when pressing from the pile top and act uniformly on the sides of
the pile when pressing to the side, the pressing force shall not create
lateral force on the pile;
- the equipment must have valid testing certificates for the pressure meter
and the oil valve and a jack adjustment table issued by the relevant
Authority.;
- 40 -
- pile pressing equipment must ensure the operation condition and labour
safety during the construction.
- 41 -
(b)
(c)
(d)
The splice joint shall not be closer than eight (8) meters to the
underside of the pile cap.
(e)
(f)
Curing and finishing of extensions shall be the same as for the original
- 42 -
pile.
3.9 Defective Piles
(a)
(b)
(c)
3.10
Pile Records
(a)
(b)
- 43 -
4.
(b)
Measurements shall be made from the tip (bottom of the steel shoe
plate of the pile) to the cut-off line indicated on the drawings or as may
be approved by the Engineer. Portions of piles cast deeper than
required through over-driving procedures shall not be measured for
payment.
(c)
All the tests that may be required by the Engineer for approval of the
works, or the equipment, shall not be measured for separate payment,
and shall be considered as incidental work and shall be deemed
included in the rates and unit price of the piles.
(b)
Pay
Item
Description
Uni
t
07200-1
lm
- 44 -
General.........................................................................................46
Depth of Bores..............................................................................46
Method of Boring...........................................................................46
Sampling, Testing and Boring Logs.................................................47
Sampling and Testing......................................................................................47
Testing frequencies......................................................................................... 47
Boring Logs..................................................................................................... 47
Method of Measurement................................................................48
Basis of Payment...........................................................................48
- 45 -
1.
DESCRIPTION
This specification describes the requirements and procedures for Soil
Investigation in locations as may be required by the Engineer or required
by the Contractor for information to confirm pile driving conditions or
foundation bearing capacity.
2.
REFERENCE STANDARDS
The following Standards in their latest edition shall be particularly applied
to the works covered by this specification.
22TCN-2592000
ASTM D422
ASTM D854-06
ASTM D1586
ASTM D2113-06
ASTM D2166
ASTM D2216
ASTM D2487-06
ASTM D2974
ASTM D4318
3.
3.1 General
As may be required by the Contractor, subject to the approval of the
Engineer, or as may be required by the Engineer, the Contractor shall
carry out drilling and sampling for soil investigations at the selected
locations to obtain necessary subsurface data, information and/or
samples for testing.
The methods and procedures for soil investigation shall be in accordance
with the Vietnamese, AASHTO or ASTM standards listed above as may be
appropriate.
3.2 Depth of Bores
Soil test drilling shall be taken to the depth as required by the Engineer or
as necessary to establish the required foundation information. In the case
of structural foundations the test drilling shall generally be sufficient to
prove continuity of the bearing stratum.
3.3 Method of Boring
(a)
- 46 -
(b)
(a)
(b)
(c)
The static ground water level shall be recorded for each hole.
(d)
Rock cores shall be taken when and where required by the Engineer.
The full core shall be recovered and stored in core boxes for
inspection by the Engineer.
(e)
(a)
(b)
(c)
All boring logs shall contain, but not be limited to, the following
information and data:
3.4.2
1
2
3
4
5
6
7
8
9
10
Structure name
Bore position and code number
Reduced level of top of the bore
Date and time of boring
Diameter of bore
Type of plant used
Depth to which bore was cased
Depth to base of each stratum from the surface
Description of strata
Depth and results of standard penetration testing tests (if
required)
11 Depth of any split-spoon sampling (if required)
12 Static water level
13 Remarks
(d)
(e)
- 47 -
4.
(b)
Unit
meter
No.
Note.
Where provision has been made in the Bills of Quantities for work included in this
specification to be paid for against a Provisional Sum, payment shall be
determined in accordance with the appropriate requirements of the Conditions of
Contract.
- 48 -
Reference Standards.....................................................................50
Materials for Piling........................................................................50
Concrete......................................................................................................... 50
Reinforcing Steel............................................................................................. 50
Temporary Casings.......................................................................................... 50
Permanent Casings......................................................................................... 51
Bentonite and Bentonite Slurry (Drilling Fluid)................................................51
Submittals....................................................................................................... 51
3. CONSTRUCTION REQUIREMENTS........................................52
3.1
3.1.1
3.1.2
3.1.3
3.1.4
3.1.5
3.1.6
3.2
3.3
3.4
3.5
3.5.1
3.5.2
3.5.3
3.6
3.6.1
3.6.2
3.6.3
3.6.4
3.6.5
3.6.6
3.7
3.8
3.8.1
3.8
Boring........................................................................................... 52
Boring Near Recently Cast Piles......................................................................52
Stability of Pile Excavation using Drilling Fluid................................................53
Spillage and Disposal......................................................................................53
Pumping from Bored Holes..............................................................................53
Cleanliness of Pile Bases.................................................................................53
Inspection....................................................................................................... 53
Final Pile Toe Level........................................................................53
Reinforcement..............................................................................54
Concreting....................................................................................54
Extraction of Casing......................................................................56
Workability of Concrete...................................................................................56
Concrete level................................................................................................. 56
Water Level..................................................................................................... 56
Quality Control of Piling.................................................................56
General........................................................................................................... 56
Testing of Materials for Drilling Fluid...............................................................56
Piling............................................................................................................... 57
Integrity Testing of Piles..................................................................................58
Sonic Testing................................................................................................... 59
Core Testing.................................................................................................... 59
Positional Tolerance......................................................................61
Reporting......................................................................................61
Daily Piling Records......................................................................................... 61
Testing frequencies.......................................................................61
Method of Measurement................................................................63
Basis of Payment...........................................................................63
- 49 -
1.
DESCRIPTION
The work under this Specification Section consists of the construction of
Cast-in-Situ piles using the reverse circulation drilling method, crab type
hammers, and steel casing or any other earth drill method approved by the
Engineer, in accordance with this specification and in conformity with the
drawings or as may be required by the Engineer.
The work to be performed as specified in this Specification Section shall be
carried out after any required sub-soil investigations have been completed
by the Contractor in accordance with this specification, the drawings, or as
may be required by the Engineer.
2.
MATERIAL REQUIREMENTS
OCMA DFCP4
API S13A
TCVN 326-04 or
22TCN 257-2000
Concrete
- 50 -
2.2.4
Permanent Casings
(2) Mixing
(a)
(b)
2.2.6
(a)
(b)
- 51 -
CONSTRUCTION REQUIREMENTS
3.1 Boring
3.1.1
(a)
Piles shall not be bored so close to piles which have recently been
cast and which contain workable or unset concrete such that a flow of
concrete could be induced from or damage caused to any of the piles.
(b)
- 52 -
3.1.2
Fluid
(a)
Where the use of drilling fluid is approved for maintaining the stability
of a bore, the level of the fluid in the excavation shall be maintained
so that the fluid pressure always exceeds the pressures exerted by
the soils and external groundwater or at not less than 1m above the
level of the external groundwater. An adequate temporary casing
may be required in conjunction with the method to ensure stability of
the strata near ground level until concrete has been placed.
(b)
3.1.3
For a boring without casing, the diameter of the boring hole for a
representative number of piles will be measured by calipers prior to
the placing of concrete into it. The Contractors Quality Control
personnel shall do the measurement using approved equipment.
(b)
- 53 -
During pile boring, the Contractor shall produce a boring log indicating
approximate depths and types of the various earth layers found in the
bore. Based on the existing conditions of boring, the Engineer might
require the Contractor to provide disturbed samples for visual
analysis.
(c)
The Contractor shall immediately notify the Engineer if, during the
installation of piles, the ground conditions are different from those
indicated on the drawings or observed in the prebore.
(d)
The Engineer will confirm the final pile toe level after his inspection of
the earth layers penetrated by the pile.
(e)
The Contractor shall prepare for carrying out sampling and tests to
check bottom soils and excavation geometry.
3.3 Reinforcement
(a)
(b)
(c)
(d)
3.4 Concreting
(a)
- 54 -
commencement of concreting.
(b)
(c)
(d)
(e)
(f)
During and after concreting care shall be taken to avoid damage to the
concrete due to pumping and dewatering operations.
(g)
The hopper and pipe of the tremie shall be clean and watertight
throughout. The pipe shall extend to the base of the pile and a sliding
plug or barrier shall be placed in the pipe to prevent direct contact
between the first charge of concrete and the water. The pipe shall at
all times penetrate the concrete that has previously been placed and
shall not be withdrawn from the concrete until completion of
concreting. At all times a sufficient quantity of concrete shall be
maintained within the pipe to ensure that the concrete pressure
exceeds the water pressure. The tremie pipe shall be kept at least 2.0m
but never more than 5.0m. under the concrete level. The internal
diameter of the tremie pipe shall not be less than 150mm for concrete
made with 20mm aggregate and not less than 200 mm for concrete
made with 40mm aggregate. It shall be so designed that external
projections are minimized, allowing the tremie to pass through
reinforcing cages without causing damage. The internal face of the
pipe of the tremie shall be free from projections.
(h)
(i)
(j)
- 55 -
Workability of Concrete
(b)
(c)
(d)
3.5.3
Water Level
The Contractor shall submit to the Engineer for his approval suitable
proposals for dealing with groundwater levels higher than the required pile
head casting level shown on the drawings prior to placing concrete. The
pile head shall not be left below the groundwater level unless approved
precautions are taken.
3.6 Quality Control of Piling
3.6.1
General
The Contractor shall comply with his approved Quality Assurance Plan.
3.6.2
Testing of Materials for Drilling Fluid
(a)
(b)
- 56 -
The Contractor shall submit to the Engineer for his approval the
method proposed for the sampling and checking of contaminated
bentonite and for the cleaning of the base of the bore. In the event of
a change in the established working pattern, tests for shear strength
and pH value shall be reintroduced for a period if required.
Property to be
measured
Density
Viscosity
3.6.3
Range of results at
20o C
Less than 1.10g/ml
30-90s or Less than
20 cP
Test method
Mud density balance
Marsh cone method
Fann viscometer *
Shear strength(10
minute gel
strength)
Shearometer
Fann viscometer
PH
9.5-12
pH indicator strips or
electrical pH meter
Ensuring proper storage and handling of all the materials for pile
fabrication.
(b)
(c)
- 57 -
(d)
(e)
(f)
Proper preparation and performance for piles (including the Test Piles
if required according to the drawings or by the Engineer) as stated in
this specification.
(g)
(h)
3.6.4
(b)
The length of steel tubing shall extend to the limits indicated on the
drawings.
(c)
(d)
(e)
The top of the tube shall be provided with a screw type plug, to
prevent the intrusion of foreign materials into the tube.
(f)
(g)
(h)
- 58 -
(i)
When required by the Engineer, the Contractor shall fill all tubes with
an expansive grout, acceptable to the Engineer, which is capable of
displacing any water in the tubes. The grout shall be continuously
injected into the tubes from the bottom of the tube to the top.
3.6.5
Sonic Testing
(a)
Test shall not be carried out until the pile concrete has gained its 28
days characteristic strength.
(b)
(c)
3.6.6
The contractor shall submit his proposal for conducting static load tests to
the Engineer for this approval.
Unless otherwise directed by the Engineer the test load shall be applied in
the following sequence:
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
- 59 -
(i)
For acceptance, the total pile top displacement under 1.5 times pile
working load and after its subsequent removal shall not exceed the
following values:
Loaded
Unloaded
(b)
(c)
After the completion of loading tests, all equipment and load used
shall be removed from the site.
(d)
- 60 -
3.6.7
Core Testing
(a)
(b)
The inclination of the pile shall not deviate more than 1:100 from the
required vertical alignment.
c)
After completion of all piling work and prior to casting the pile top into the
pile cap or foundation, the top of the reinforcement cage shall be no more
than 150 mm above and no more than 75 mm below the correct position
and the top of the concrete shall be within 25 mm of the correct elevation.
d)
The bottom of the shaft excavation shall be normal to the axis of the pile
within 60 mm per meter of pile diameter
e)
Where a casing is used, its outside diameter shall not be less than the
shaft diameter shown on the Drawings. The diameter of cast in-situ piles
shall be at least 97% of the specified diameter
3.8 Reporting
3.8.1
The Contractor shall furnish the Engineer with a detailed daily record of
soils encountered during excavation and construction of the piles.
The Contractor shall keep records of the installation of each pile and shall
submit two signed copies of these records to the Engineer not later than
24 hours after the pile was installed. The signed records shall be as
indicated in the following table.
Table 1 Records of pile borings:
(a)
(b)
- 61 -
(c)
Pile type
(d)
(e)
(f)
(g)
(h)
(i)
Date of concreting
(j)
(k)
Working level
(l)
(m)
Toe level
(n)
(o)
(p)
(q)
Vertical of borehole
(r)
(s)
(t)
(u)
Concrete mix
(v)
(w)
(x)
(y)
Test Description
Test
Frequency
Remark
- 62 -
4.
Table 2; Table
3
Table 4
Table 5
all
expenses
- 63 -
resulting
from
the
Contractor's
previsions
submersible pumps;
for
pumps
and
dewatering
by
10
11
Pay Item
07300
01
07300 - 02
07300
03
07300
04
07300
05
07300
06
07300
07
Description
Unit
lm
lm
lm
each
Nos
Nos
Ultrasonic Test
section
- 64 -
Tender documents
Contract Package 1A
- 65 -
Pile DynamicTesting
Tender documents
Contract Package 1A
1. DESCRIPTION...................................................................67
2. EQUIPMENT AND MATERIAL REQUIREMENTS.......................67
3. SPECIALIST......................................................................68
4. REPORTING RESULTS........................................................68
5. METHOD OF PAYMENT.......................................................69
6. BASIS OF PAYMENT..........................................................69
- 66 -
Pile DynamicTesting
1.
Tender documents
Contract Package 1A
DESCRIPTION
The work shall consist of furnishing all materials, equipment, and labour
necessary for conducting high-strain dynamic tests on drilled and cast-in-place
piles. 2% of all completed piles shall be selected for testing as approved by the
Engineer. The Contractor shall appoint an Independent Specialist to conduct all
testing and shall supply materials, equipment and labour as specified, for work
prior to, during, and after the tests all to the approval of the Engineer. Testing
procedures shall conform to ASTM D4945-89 unless noted otherwise. The shaft
used for the test will be instrumented and tested by the Independent Specialist,
as approved by the Engineer, meeting requirements outlined in the ASTM D494589 specification as well as those outlined below.
2.
The Contractor shall supply all labour, materials and equipment required to
prepare and dynamically load the test pile, and return the pile to a condition
suitable for use in the finished structure. The Contractors equipment and
methods shall include but not be limited to:
The extension of the pile top if a permanent casing has not been used to
construct the pile. The extension shall be formed of a thin walled casing or
equivalent and shall be at least equal to two and a half (2 ) pile
diameters such that the extended pile head can be readily accessed by
the testing engineer at the time of the test. If the pile top is below grade,
the Contractor shall remove the surrounding soil to expose the pile top in a
safe working environment.
A flat, level, and sound concrete top to the pile perpendicular to the
vertical axis of the pile. The top of the concrete should be level with or
above the casing. Prior to the test, four windows approximately 150mm.
by 150mm. shall be provided in each quadrant of the casing.
A drop weight in the range of one and half to two percent (1.5% to 2%) of
the anticipated pile capacity to be approved by the Engineer.
A guide allowing variable drop heights typically between 2 to 3m to be
approved by the Engineer.
A shaft top cushion consisting of new sheets of plywood with total
thickness between 50mm. and 150mm. to be approved by the Engineer.
A steel striker plate at least 50mm. thick and an area between 70% and
90% of the area of the pile top, but not less than the area of the impacting
surface of the drop weight, shall be placed on top of the plywood cushion.
Where reinforcement protrudes above the top of the pile the Contractor
may:
- 67 -
Pile DynamicTesting
Tender documents
Contract Package 1A
SPECIALIST
b)
c)
Calibrated Accelerometer
4.
REPORTING RESULTS
The Specialist shall promptly submit a report of the testing results to the
Engineer for approval. The field results from at least one (CAPWAP) analysis
(case Pile Wave Analysis Program) shall be submitted. The CAPWAP analysis
shall be performed by an experienced and qualified Engineer. The report shall
also provide the following:
Wave Equation analysis results obtained
a)
prior to testing
b)
c)
d)
- 68 -
Pile DynamicTesting
5.
Tender documents
Contract Package 1A
METHOD OF PAYMENT
The quantity to be paid for shall be the number of bored piles tested and
accepted. Any item indicated and not otherwise described hereto shall be
considered subsidiary to the work item and shall not be paid for separately.
6.
BASIS OF PAYMENT
Payment shall be made for each test together with the relevant report accepted
by the Engineer at the contract price shown below. The payment shall constitute
full compensation for the cost of Pile Dynamic Testing, the cost of appointing an
Independent Specialist, all instrumentation, testing and testing equipment,
analysis and reporting, tools, labour and all other incidentals necessary to
complete the work prescribed in this Item.
Payment will be made under:
Pay
Number
Item
07350 01
Description
Unit
PDA tests
Nos
- 69 -
Pile DynamicTesting
Tender documents
Contract Package 1A
- 70 -
Pile DynamicTesting
Tender documents
Contract Package 1A
TABLE OF CONTENTS
1. DESCRIPTION...................................................................72
2. MATERIAL REQUIREMENTS................................................72
2.1
2.2
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5
2.2.6
2.2.7
Reference Standards.....................................................................72
Material for Prestressed Concrete..................................................72
General Requirement......................................................................................72
Prestressing Steel............................................................................................ 72
Anchorages for post tensioning.......................................................................73
Ducts (Sheath)................................................................................................ 74
Grout for Ducts................................................................................................ 74
Concrete......................................................................................................... 75
Submittals....................................................................................................... 75
3. CONSTRUCTION REQUIREMENTS........................................76
3.1
3.2
3.2.1
3.2.2
3.2.3
3.3
3.4
3.5
3.6
3.6.1
3.6.2
3.7
3.8
3.9
3.9.1
3.9.2
3.10
3.11
3.12
3.13
3.14
General.........................................................................................76
Sampling and Testing....................................................................77
Grouting Trials................................................................................................. 77
Site Flow Tests................................................................................................. 78
Testing of Pre-cast Pre-stressed Members.......................................................78
Placing Steel.................................................................................78
Pretensioning Method...................................................................78
Post-tensioning Method.................................................................79
Grouting.......................................................................................80
Plant for Grouting............................................................................................ 80
Grouting of Ducts and Sheathing....................................................................80
Protection of Prestressing Anchorages...........................................81
Superstructure Construction..........................................................82
Curing........................................................................................... 83
General........................................................................................................... 83
Steam Curing.................................................................................................. 83
Handling, Transport and Storage....................................................84
Marking of Precast Prestressed Members.......................................84
Erection of Pre-cast Beams............................................................84
Tolerances for Pre-stressed Concrete Structures.............................85
Testing frequencies.......................................................................85
Method of Measurement................................................................87
Basis of Payment...........................................................................87
- 71 -
Prestressed Concrete
1.
2.
Tender documents
Contract Package 1A
DESCRIPTION
(a)
(b)
The work shall include the supply and installation of any items
necessary for the particular pre-stressing system to be used, including
but not limited to ducts, anchorage assemblies and grout used for
pressure grouting ducts.
(c)
MATERIAL REQUIREMENTS
22TCN 272-05
AASHTO LRFD
ASTM A421-91
ASTM A416-99
General Requirement
All materials to be furnished and used, but not covered in this specification,
shall conform to the requirements stipulated in other applicable
specifications.
2.2.2
Prestressing Steel
(a) High tensile strength steel wire shall be stress relieved and shall
conform to the requirements of ASTM A421-91 or equivalent for Uncoated Stress Relieved Steel Wire for Pre-stressed Concrete
(b) High tensile steel strand with low-relaxation shall be weld free and
stress relieved after stranding and shall conform to the requirements
of ASTM A416-99 or equivalent Steel Strand, Un-coated Seven Wire
Stress Relieved Strand for Prestressed Concrete
(c) Testing of pre-stressing reinforcement shall be in accordance with the
- 72 -
Prestressed Concrete
Tender documents
Contract Package 1A
(a)
(b)
(c)
- 73 -
Prestressed Concrete
Tender documents
Contract Package 1A
(e)
(f)
(g)
2.2.4
Ducts (Sheath)
(a)
(b)
(c)
2.2.5
Ducts shall have grouting connections at each end and shall have
vent/drains at all intermediate high and low points, subject to the
approval of the Engineer.
Grout for Ducts
(b)
- 74 -
Prestressed Concrete
(c)
Tender documents
Contract Package 1A
2.2.6
Concrete
(a)
(b)
The maximum size of aggregate for use in the manufacture of prestressed concrete shall be 25 millimeters.
(c)
2.2.7
Temporary works
Temporary fixing/stabilizing method of the supports and closures
during erection operations
Travelling forms, suspended false-work or scaffolding, girder erection
gantries
Form-work and false-work
Dimensions and complete descriptions of all devices, joints, bearings,
and anchorages not specified or detailed in the Specifications
Pre-stressing
Method and timing of the insertion of pre-stressing cables.
Post-tensioning or Pre-tensioning hardware, jointing, jacking, grouting
equipment, and men and materials of any kind
Vertical alignment and deflection control measures with calculations
- 75 -
Prestressed Concrete
Tender documents
Contract Package 1A
Grouting
Statement for grouting of ducts
Erection of members
Equipment for all machinery, devices, labor and material which are to
be used for erection
Methods of tie-down and closure of superstructures during erection
Cross Beam
Installation and pre-stressing methods of cross beam
Deck Slab
Fabrication and Installation methods of Concrete Form Works
Installation methods of Cast in Situ Slab on the Concrete Form Works
3.
CONSTRUCTION REQUIREMENTS
3.1 General
(a)
(b)
- 76 -
Prestressed Concrete
Tender documents
Contract Package 1A
Grouting Trials
(a)
Where full scale trials are required they shall begin at least 21 days
before the planned commencement of the fixing of ducts for prestressing in the permanent works unless otherwise specified in the
Contract.
(b)
The trials shall incorporate all relevant details of ducts, vents, duct
supports, pre-stressing anchorages and couplers, pre-stressing
strands and grout inlets and outlets. Tendons shall be sufficiently
tensioned such that the strands within the duct take up a
representative alignment. All systems, methods and materials shall
be those proposed for the permanent works and shall have been
submitted to the Engineer as part of the Contractors detailed method
statement.
(c)
(e)
After the grout strength has reached 17 Mpa, at least three samples,
each one of 1 meter long, shall be cut from the grouted duct at the
locations chosen by the Engineer. Each of the samples shall be
sectioned longitudinally by cutting with a high speed abrasive cutting
wheel, friction saw or similar.
The sectioned samples shall be
delivered to the Engineer, who will assess the acceptability of the
grouting trials particularly in respect of the presence and location of
any voids in the samples.
(f)
- 77 -
Prestressed Concrete
(g)
Tender documents
Contract Package 1A
3.2.2
Fluidity of the grout shall be tested on site at the time of mixing using the
Marsh Cone Test to ensure practicality of pumping and minimize the risk of
blockage during grouting operation. A target flow time of 10-15 seconds
shall be achieved.
3.2.3
Testing of Pre-cast Pre-stressed Members
Where required by the Engineer, one or more beams may be subjected to a
loading test. The Contractor shall obtain the prior approval of the Engineer
for the detailed arrangements for testing. The cost of tests and records
shall be included in the unit prices.
3.3 Placing Steel
All steel reinforcement shall be accurately placed in the position shown on
the drawings and rigidly held in place during placing and setting of the
concrete. Distance from the forms shall be maintained by stays, formwork
spacers, ties, hangers, or other approved support. Formwork spacers for
holding units from contact with the forms shall be of approved material,
shape and dimensions. Layers of reinforcement shall be separated by
suitable wire spacers. Wooden blocks shall not be used.
3.4 Pretensioning Method
(a)
(b)
(c)
(d)
- 78 -
Prestressed Concrete
Tender documents
Contract Package 1A
Engineer.
3.5 Post-tensioning Method
(a)
(b)
(c)
Each anchorage device shall be set square to the line of action of the
corresponding post-tensioning tendon and shall be securely fixed in
position and gradient to prevent movement during the placing and
compaction of concrete.
(d)
(e)
(f)
(g)
The Contractor shall establish the datum point for measuring extension
and jack pressure to the satisfaction of the Engineer. Allowance shall
be made for the friction in the jack and anchorage for pull-in of the
tendon during anchorage.
(h)
The tendons shall be stressed at a gradual and steady rate until the
required extension and tendon load are reached or are approved by the
Engineer. The sequence of stressing shall be as shown on the drawings
or directed by the Engineer.
(i)
The force in the tendons shall be obtained from readings on a load cell
or pressure gauge incorporated in the equipment and the extension of
the tendons measured. The extension of the tendons under the
approved total forces shall be within the limits given below of the
agreed calculated extension.
Transverse
Segments:
Tendons
Longitudinal
Segments
Tendons
- 79 -
for
5%
Prestressed Concrete
Tender documents
Contract Package 1A
5%
(j)
If the measured extensions are not within the specified tolerance then
the Contractor shall submit to the Engineer his method of rectifying the
discrepancy.
(k)
When the pre-stressing force has been applied to the satisfaction of the
Engineer, the tendons shall be anchored. The force exerted by the
tensioning apparatus shall then be decreased gradually and steadily so
as to avoid shock to the tendon or anchorage.
(l)
(m) Unless otherwise agreed by the Engineer, tendons shall not be cut less
than 2 days after stressing.
3.6 Grouting
3.6.1
(a)
(b)
(c)
The pressure gauges shall be calibrated before they are first used in
the Works, and thereafter as required by the Engineer. All equipment
shall be thoroughly cleaned and washed with clean water at least
once every 3 hours during the grouting operations and at the end of
use for each day.
(d)
(a)
3.6.2
- 80 -
Prestressed Concrete
Tender documents
Contract Package 1A
(b)
(c)
(d)
(e)
(f)
The Contractor shall keep full records of grouting including the date
when each duct was grouted, the proportion of the grout and any
admixtures used, the pressure, details of any interruptions and
topping up required. Copies of these records shall be supplied to the
Engineer within 3 days of completing grouting.
(b)
(c)
The anchorage recess shall then be filled with an approved nonshrinkage mortar. The mortar shall not contain aluminium powder,
iron particles, chlorides, sulphates, fluorides or nitrates.
(d) Where the protection will form part of the exposed works, the
anchorage recess shall be filled with concrete of the same quality and
colour as that of the adjacent concrete and shall be applied and cured
in accordance with these specifications or as may be required by the
- 81 -
Prestressed Concrete
Tender documents
Contract Package 1A
Engineer.
(e)
(b)
(c)
(d)
(e)
(f)
- 82 -
Prestressed Concrete
Tender documents
Contract Package 1A
(g)
(h)
3.9 Curing
3.9.1
General
The casting bed for any unit cured with steam shall be completely
enclosed to prevent steam from escaping and exclude the outside
atmosphere.
(b)
Two to four hours after placing concrete and after the concrete has
undergone initial set, the first application of steam shall be made. If
retarding admixtures have been used, the duration before application
of the steam shall be increased to four to six hours.
(c)
Water curing methods shall be used from the time the concrete is
placed until steam is first applied.
(d)
(e)
(f)
- 83 -
Prestressed Concrete
Tender documents
Contract Package 1A
3.11
(b)
(c)
3.12
- 84 -
Prestressed Concrete
Tender documents
Contract Package 1A
and work at the Ong Nhieu river where temporary bridging may be
used. The statement shall include full details of the equipment to be
used to handle beams and to incorporate them into the structure. The
method statement shall be accompanied by full structural calculations
and appropriate workshop drawings for each stage of the procedure.
The calculations shall be appropriate for such temporary works and
shall take into full consideration all temporary loading cases arising
from the procedures, the prevailing conditions at the site, in particular
likely wind loading, and the nature of the existing ground. The
Contractor shall carry out all additional soils investigation necessary to
confirm his assumptions concerning the nature of the existing ground.
The calculations and drawings shall be certified and stamped by a
qualified structural engineer experienced in the preparation of such
details.
The details shall include consideration of the effect of each stage of the
procedure on the completed permanent works on which the gantry is to
be mounted and operated. The procedures for lifting and transferring
the beams into position and the order of erection of the beams shall be
such that the eccentricity of loading on the completed permanent
works (supporting piers and the foundations) is minimized.
When beams are being placed in position they shall be braced against
overturning before being released by the crane or other lifting devices.
Beams shall be prevented from moving laterally during the placing of
in-situ concrete.
The lifting and placing of beams will not be permitted to commence
until such time as the Contractors method statement, calculations and
shop drawings have been reviewed and approved by the Engineer.
3.13
The tolerances listed in Table 1 are the allowable deviations for pre-stressed
concrete structures. These tolerances will be included in assessments for the
acceptance of work.
Table 1 Acceptance Tolerances of Pre-stressed concrete structures
Tolerance
Length
5 mm
Center Location
5 mm
10 mm
5 mm
10 mm
Compressive Strength
Refer
06100
- 85 -
subsection
Prestressed Concrete
Tender documents
Contract Package 1A
5 mm
Bowing
3.14
Testing frequancies
c
2
Test Description
Test Frequency
- 86 -
Article
Article
Article
Article
Remark
products
4.3
4.5
4.6
4.7; 4.8; 4.9
Article 5
Article
Article
Article
Article
2.1
2.2
2.3
2.4
Article 2.5
Article 2.6; 2.7
Article 2.8
Article 2.9
Prestressed Concrete
Tender documents
Contract Package 1A
+ Tensioning
+ Epoxy liquid
During construction period:
Constrcution for reinforcement &
precast prestressed reinforcement
Tightening of steel wire ropes bed,
formwork, falsework
Tightening of steel wire ropes work
c
4.
Article 2.10
Article 2.11
Chapter III
Chapter IV
Chapter V (Include
Pretensioning
Method
&
Posttensioning Method)
Chapter VI
Chapter VII
(b)
(c)
Payment for Tendons of Post Tensioning Members shall include the work
of tensioning, grouting, anchorages, ducts and all required testing for
materials.
- 87 -
Prestressed Concrete
Tender documents
Contract Package 1A
Pay
Item
07400-01
Nos
07400-02
Nos
07400-03
Nos
07400-04
Nos
07400-05
Nos
07400-06
Nos
Description
- 88 -
Unit
Prestressed Concrete
Tender documents
Contract Package 1A
1. DESCRIPTION...................................................................90
2. MATERIAL REQUIREMENTS................................................90
2.1
2.2
2.2.1
2.2.2
2.2.3
2.2.4
Reference Standards.....................................................................90
Material for Reinforcing Steel........................................................90
Reinforcing Bars.............................................................................................. 90
Spiral Reinforcement Steel..............................................................................91
Substitution of different size...........................................................................91
Welded Steel Wire Fabric.................................................................................91
3. CONSTRUCTION REQUIREMENTS........................................91
3.1
3.2
3.3
3.4
3.4.1
3.4.2
3.5
3.6
3.6.1
3.6.2
3.6.3
3.7
3.7
Method of Measurement................................................................95
Basis of Payment...........................................................................95
- 89 -
Reinforcing Steel
1.
Tender documents
Contract Package 1A
DESCRIPTION
This Specification Section describes the requirements and provisions for the
supply, bending, fabrication and placing of steel reinforcement of the type,
size, shape and grade required in accordance with the drawings as specified
or as may be required by the Engineer.
2.
MATERIAL REQUIREMENTS
AASHTO M31
AASHTO T68
AASHTO
M164M
AASHTO M232
ASTM A82
ASTM A153
ASTM A615
ASTM A185
ASTM A615
ACI 315
Reinforcing Bars
All reinforcing steel bars shall be deformed billet steel and shall meet the
requirements of AASHTO M31 (ASTM A615), Grade 60 or equivalent,
except for plain round reinforcing bars which shall be provided in
accordance with AASHTO M31 (ASTM A615), Grade 40 or equivalent as
called for in the reinforcing schedule. Testing shall be in accordance with
AASHTO T68. Unit stress calculations for bars having an area differing by
6 percent or more from the nominal bar area shall be made using the
measured bar area.
- 90 -
Reinforcing Steel
2.2.2
Tender documents
Contract Package 1A
(b)
2.2.4
Welded steel wire fabric shall comply with the requirements of ASTM A185
and shall be as indicated on the drawings. Welded fabric shall be placed
as recommended by the Concrete Reinforcing Steel Institute (CRSI) Manual
of Standard Practices.
3.
CONSTRUCTION REQUIREMENTS
- 91 -
Reinforcing Steel
Tender documents
Contract Package 1A
(b)
In the event a reinforcement steel sample under test fails to meet the
specification requirements at any time, or the Engineer considers that
samples which were presented to him for test were not truly
representative, or if it becomes apparent that reinforcement steel
which has not been approved has been used on the Works, the
Engineer may instruct the Contractor to break out and remove
completely all such sections of the work already constructed using
such suspect reinforcement steel.
(c)
All testing of reinforcement steel bars shall meet the requirements and
specification limits of the ASTM/AASHTO designation for the particular
size, and grade of steel.
Bending
Bar reinforcement shall be cut and bent to the shapes shown on the
Drawings. Fabrication tolerances shall be in accordance with ACI 315. All
bars shall be bent cold, unless otherwise permitted.
Bars partially
embedded in concrete shall not be field bent except as shown on the
drawings or as specifically permitted.
3.4.2
Hooks and Bend Dimensions
The dimensions of hooks and the diameters of bends measured on the
inside of the bar shall be as shown on the drawings. When the dimensions
of hooks or the diameter of bends are not shown, they shall be in
accordance with Division I, Article 8.23 of the AASHTO Standard
Specifications for Construction of Roads and Bridges or ACI 318 Building
Code Requirements for Reinforced Concrete
3.5 Fixing of Reinforcement Steel
(a)
- 92 -
Reinforcing Steel
Tender documents
Contract Package 1A
end of all tying wires shall be turned into the main body of the concrete
and not allowed to project towards the surface. Spacing blocks shall be
of pre-cast concrete of a strength at least equal to that of concrete
being placed. They shall be as small as practicable and shall be
securely fixed in position by means of wires cast into them. They shall
be soaked with water immediately prior to concreting.
(b)
(c)
(d)
(e)
(f)
(g)
(h)
(i)
- 93 -
Reinforcing Steel
Tender documents
Contract Package 1A
shown on the drawings and splices for 16mm or smaller bars, splicing of
bars will not be permitted without the approval of the Engineer. Splices shall
be staggered as far as possible.
3.6.1
Lapped Splices
Lapped splices shall be of the lengths shown on the drawings. If not
shown on the Drawings, the length of lapped splices shall be no less than
35 bar diameters. The bars in lapped splices shall be placed and wired in
such as manner as to maintain the minimum concrete cover and the
minimum spacing between the bars as detailed in this specification.
3.6.2
Welded Splices
Welded splices shall be used only if specified on the drawings or if
approved by the Engineer. Where approved welding shall conform to the
Structural Welding Code, Reinforcing Steel, AWS D1.4 of the American
Welding Society and applicable special provisions.
Welding of
reinforcement steel will be allowed if the chemical composition of the steel
exceeds the percentages shown in Table 1.
Mechanical Coupler
(a)
(b)
- 94 -
Reinforcing Steel
Tender documents
Contract Package 1A
4.
Test Description
TCVN 1561-1: 2008: Steel
concrete - Plain bar.
Material testing: (for material
approval)
Sampling & method for testing
Other testing & frequency for
testing
TCVN 1561-2: 2008: Steel
concrete - Ribbed bar.
Material testing: (for material
approval)
Sampling & method for testing
Other testing & frequency for
testing
Test Frequency
Remark
for reinforcement of
Article 11.3.2.2
Article 11.3.3
for
reinforcement
of
Article 8; 9
Article 12.3.3
(b)
(c)
When laps are made for splices for the convenience of the Contractor,
in addition to those indicated on the drawings the extra steel shall not
be included for payment.
(d)
For computing the weight of reinforcement steel bars for payment, The
Contractor shall be comply with the Standard Unit Weight Table
- 95 -
Reinforcing Steel
Tender documents
Contract Package 1A
provided according with table 2 TCVN 1651-1: 2008 (for plain bar) &
table 2 TCVN 1651-2:2008 (for ribbed bar)
Cross section
area mm2, An
6
8
10
12
14
16
18
20
22
25
28
32
36
40
28.3
50.3
78.5
113
154
201
254.5
314
380
490.9
615.8
804.2
1017.9
1256.6
Tolerance (%)
8
8
6
6
5
5
5
5
5
4
4
4
4
4
An = 0.7854 x d2
Unit weight per length = 7.85 x 10-3 x An
Cross section
area mm2, An
6
8
10
12
14
16
18
20
22
25
28
32
28.3
50.3
78.5
113
154
201
254.5
314
380.1
491
616
804
- 96 -
Tolerance (%)
8
8
6
6
5
5
5
5
5
4
4
4
Reinforcing Steel
Tender documents
Contract Package 1A
4
36
1017.9
7.99
4
40
1257
9.86
50
1964
15.42
4
If diameter of Ribbed bar is greater than 50mm, it is recommended to have
agreement between Manufacturer and Purchaser, and tolerance allowable for
each ribbed bar must be 4%
An = 0.7854 x d2
Unit weight per length = 7.85 x 10-3 x An
Pay Item
Description
Unit
07500-01
Reinforcing Steel
- 97 -
Ton
Reinforcing Steel
Tender documents
Contract Package 1A
Reference Standards.....................................................................99
Submittals..................................................................................100
3. ELASTOMERIC BEARINGS................................................101
3.1
3.2
3.2.1
3.2.2
3.2.3
General.......................................................................................101
Materials.....................................................................................101
Elastomeric Materials....................................................................................101
Internal Steel Laminates...............................................................................102
Laminated Elastomeric Bearing Pads............................................................102
4. MECHANICAL BEARINGS..................................................104
4.1
5. DOWELS........................................................................105
6. BEARING INSTALLATION..................................................105
7. TESTING OF BEARINGS....................................................106
7.1
7.2
7.3
Method of Measurement..............................................................108
Basis of Payment.........................................................................108
- 98 -
Waterproofing
1.
Tender documents
Contract Package 1A
DESCRIPTION
This Specification Section describes the requirements and procedures for the
supply and installation of bridge bearing pads as indicated on the drawings,
or as may be directed by the Engineer.
2.
MATERIAL REQUIREMENTS
ASTM A123
ASTM A570
ASTM A615
ASTM C881
ASTM C1107
ASTM D412
ASTM D429
ASTM D518
ASTM D746
ASTM D1149
ASTM D2240
ASTM D3182
ASTM D3183
ASTM D3184
ASTM D3185
ASTM D3186
ASTM D3187
ASTM D3188
ASTM D3189
- 99 -
Waterproofing
Tender documents
Contract Package 1A
ASTM D3190
ASTM D3192
ASTM D3192
ASTM D4014
SAE 1020
2.2 Submittals
The Contractor shall prepare and submit the following to the Engineer for
his approval. The Contractor shall obtain the approval of the Engineer
before beginning fabrication of the bearings.
(a)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
Once the Engineer has approved these methods, they shall not be
changed without prior approval by the Engineer.
100
Waterproofing
3.
Tender documents
Contract Package 1A
ELASTOMERIC BEARINGS
3.1 General
(e)
(f)
(g)
The total out to out thickness of a bearing pad shall not be less than
the thickness indicated on the Drawings nor more than 6 mm greater
than that thickness. Variation of total thickness within an individual
bearing pad shall not exceed 3 mm.
(h)
The length and width of a bearing pad shall not vary more than 3 mm
from the dimensions indicated on the Drawings.
(i)
The bond between the elastomer and the steel laminate shall be such
that, when a sample is tested for separation, failure shall occur within
the elastomer and not between the elastomer and the steel.
3.2 Materials
(a)
(b)
3.2.1
Elastomeric Materials
101
Waterproofing
3.2.2
Tender documents
Contract Package 1A
The internal steel laminates for the laminated elastomeric bearing pads shall be
rolled carbon steel sheets complying with ASTM A 570 or AASHTO N183 (ASTM
A36).
3.2.3
ASTM Standard
Physical Properties
Value
D2240
D412
60 5
175
425
D573, 70 HR.
@ 100oC
D395.
Method B
+ 15
- 15
- 40
35
Ozone
D1149
D429, A
D429, B
D429, B
No
Cracks
80% R(Z1)
2.8kg
7 kg
ASTM Standard
Physical Properties
Low
Temperature
Test-Durometer
Change
Bearing or sample to be exposed for
96 hrs. @-28 oC, 2 oC. (The specimen
102
60 Duro
Waterproofing
Tender documents
Contract Package 1A
+ 15(Z2)
No cracks
-0, +3 mm
-0, +6 mm
0, + 3 mm
Compression
35 kgs/sq.cm
5%
103
56 kgs./sq.cm
7%
Waterproofing
4.
Tender documents
Contract Package 1A
(c)
In addition, shear resistance of the bearing shall not exceed 2.1 kg/cm 2
for 60 durometer, Table No. 1 compounds at 25% strain of the total
effective rubber thickness after an extended four-day ambient
temperature of -28 oC.
(d)
MECHANICAL BEARINGS
(a)
(b)
(b)
(c)
(d)
All bearing devices and components shall be stored at the work site in
an area that provides protection form environmental and physical
damage.
(e)
104
Waterproofing
5.
Tender documents
Contract Package 1A
DOWELS
(a)
(b)
(c)
(d)
6.
BEARING INSTALLATION
(a)
(b)
(c)
(d)
(e)
Any devices such as steel packs used to hold bearings level whilst
being fixed, must be removed so that the bearing seats only on its
mortar bedding.
(f)
105
Waterproofing
Tender documents
Contract Package 1A
1:400
Plan position
7.
Laterally
3mm
Longitudinally
6mm
Center/Center Spacing
3mm
TESTING OF BEARINGS
The testing of selected bearings shall be arranged with the Engineer prior to
their inclusion in the Works. The testing shall be done at an independent
testing facility approved by the Engineer.
(2)
(3)
106
Waterproofing
Tender documents
Contract Package 1A
(2)
(b)
(c)
(d)
107
Waterproofing
8.
Tender documents
Contract Package 1A
(e)
(f)
(b)
(b)
Description
Elastomeric
Type
Unit
(600 350
07600-01
Bearing
78) mm
07600-02
07600-03
Non-shrinkage mortar
07600-05
07600-06
Sq.m
07600-07
Bitument
Cu.m
set
Set
Cu.m
Ton
108
Waterproofing
Tender documents
Contract Package 1A
TABLE OF CONTENTS
1. DESCRIPTION.................................................................110
2. MATERIAL REQUIREMENTS..............................................110
2.1
2.2
2.3
2.4
Reference Standards...................................................................110
Deck Waterproofing Membrane....................................................110
Bituminous Waterproofing Membrane...........................................110
Submittals..................................................................................111
3. CONSTRUCTION REQUIREMENTS......................................111
3.1
3.2
3.3
3.3.1
3.3.2
Method of Measurement..............................................................112
Basis of Payment.........................................................................112
109
Waterproofing
1.
Tender documents
Contract Package 1A
DESCRIPTION
The work under this Specification Section consists of the supply, transport
and installation of waterproofing membranes in accordance with the
information, procedures and details stated in this Specification Section and in
conformance with the drawings, and as required by the Engineer.
The Contractor shall apply bituminous membranes and deck waterproofing
membranes to all surfaces as indicated on the drawings, including but not
limited to wing walls, retaining walls, abutment walls, and similar
foundations, and to the bridge decks.
2.
MATERIAL REQUIREMENTS
(b)
The Contractor shall provide to the Engineer evidence that the applier
of the material is a qualified, experienced applier and is approved by
the manufacturer to apply his materials.
(c)
(d)
110
Waterproofing
Tender documents
Contract Package 1A
Asphalt: Asphalt for mop coat shall be in accordance with ASTM D449,
Type III.
(f)
(g)
2.4 Submittals
The Contractor shall submit to the Engineer three samples of each type of
the materials he proposes to use in accordance with pertinent requirements
of the Specifications.
For bituminous mastic and primer, one-pint containers shall be submitted.
The Contractor shall submit to the Engineer certification that materials to be
provided comply with the requirements of this specification.
3.
CONSTRUCTION REQUIREMENTS
The Contractor shall deliver products to the job site in their original
unopened containers clearly labelled with the manufacturers name,
brand designation, type and class as applicable.
(b)
The Contractor shall store products in an approved dry area and shall
protect them from contact with soil and from exposure to the elements.
Products shall be kept dry at all times.
(c)
(b)
3.3 Application
3.3.1
111
Waterproofing
3.3.2
Tender documents
Contract Package 1A
(b)
(b)
Description
Waterproofing Membrane
-
112
Unit
m2
Waterproofing
Tender documents
Contract Package 1A
1. DESCRIPTION.................................................................114
2. MATERIAL REQUIREMENTS..............................................114
2.1
2.2
2.3
Reference Standards...................................................................114
Submittals..................................................................................117
Approval of Materials..................................................................117
3. CONSTRUCTION REQUIREMENTS......................................117
3.1
3.2
3.3
Method of Measurement..............................................................119
Basis of Payment.........................................................................119
- 113
Expansion joint
1.
Tender documents
Contract Package 1A
DESCRIPTION
This Specification Section describes the requirements for expansion and
fixed joints as indicated on the drawings, including pre-moulded joint filler
and joint sealer. The Contractor shall furnish all required materials and
install expansion joints, fixed joints, pre-moulded joint filler and joint sealer
in accordance with the details indicated on the drawings and as specified
herein. This work shall include the supply and installation or application of
all necessary hardware including anchor bolts and studs, sealants,
adhesives, epoxies, and other accessories.
2.
MATERIAL REQUIREMENTS
AASHTO
M297
AASHTO
M183
ASTM A123
ASTM D395
ASTM D412
ASTM D471
ASTM D994
Preformed
Expansion
(Bituminous Type)
ASTM D1149
ASTM D2240
ASTM D6690
(a)
Joint
Filler
for
Concrete
Physical Properties
Requirements
ASTM D412
Tensile strength
126kg/cm2
(min. )
ASTM D412
Elongation at break
400%
ASTM D2240
Hardness (Durometer A)
50 5
ASTM D395
Compression set
(Method B) 22 hours at 70 oC
20%, max.
ASTM D1149
Ozone resistance:
No cracks
- 114
Expansion joint
Tender documents
Contract Package 1A
Oil deterioration:
Volume increase after immersion in
ASTM Oil # 3 for 70 hours @ 100 C
120%, max.
(b)
(c)
The sealant for sealing joints between the expansion joint units,
along the edges of the expansion joint, and the bolts and plugs shall
be a high solid, one-part polyurethane based sealant that cures
quickly, without shrinkage, into a rubber with high elongation
characteristics and excellent recovery Sealant shall be capable of
bonding to concrete, steel, and neoprene without the use of a
primer. When cured, the sealant shall possess excellent abrasion
resistance and shall resist attack by salt, oil, and road chemicals.
The sealant to be used shall meet the requirements of the
manufacturer of the neoprene expansion joint.
(d)
When test specimens are cut from the finished product a 10-percent
variation in Physical Properties will be allowed.
(e)
The flexible epoxy for filling voids around the nut fasteners shall
consist of a black two-component flexible epoxy sealant having the
following physical properties:
Base Material:
Weight/Liter(mixed
materials):
1.05 kg/liter
Mixing Time:
Pot Life:
Initial Cure:
4 hours @ 24C
Final Cure:
48 hours @ 24C
Shelf Life:
12
months
minimum
(components separate)
Hardness
Durometer:
Shore
A 80 + 10
(f)
(g)
- 115
Expansion joint
Tender documents
Contract Package 1A
Epoxy Resin
Color:
Concrete Grey
Weight/Liter
Materials):
% Solids Content:
98 % minimum by weight
Mixing Time:
Pot Life:
Initial Cure:
4 hours @ 24C
Final Cure:
48 hours @ 24 C
Shelf Life:
Tensile Strength:
211 kg/cm2
Elongation:
7% @ 24 C
Water Absorption:
1. 0% maximum
(h)
(i)
Anchor bolts for joint seals shall be hot dip galvanized in accordance
with ASTM A153 commercial grade bolts set in epoxy mortar in holes
cored in the deck in accordance with approved shop drawings.
(j)
(k)
- 116
Expansion joint
Tender documents
Contract Package 1A
2.2 Submittals
(a)
(b)
(c)
CONSTRUCTION REQUIREMENTS
- 117
Expansion joint
Tender documents
Contract Package 1A
(c)
After coating the seat area with the specified sealant adhesive, the
joint shall be positioned over the anchor bolts and the nuts securely
tightened. All loose or long anchor bolts shall be corrected in a
manner approved by the Engineer.
(d)
All joints between units, around connecting bolts, and cavity plugs
shall be carefully sealed with sealant in a neat workmanlike manner
to keep out water and protect against corrosion. Neoprene surfaces
to be in contact with sealant shall be buffed at the plant or wire
brushed prior to installation to provide a bonding surface for the
sealant.
(e)
Prior to filling the space in the bolt wells, the Engineer shall inspect
the anchor bolts and the tightening of the nuts to the
manufacturers specified torque. Any wells sealed without the
Engineers approval shall be opened and resealed after approval at
the Contractors expense.
(f)
(b)
The filler for each joint shall be furnished in a single piece for the full
depth and width required for the joint. When the use of more than
one piece is required for a joint, the abutting ends shall be fastened
securely and held accurately to shape by stapling or other positive
fastening means.
(b)
- 118
Expansion joint
4.
Tender documents
Contract Package 1A
(b)
(b)
(c)
Pre-moulded Joint Filler and Joint Sealer shall not be paid separately.
They shall be deemed to be included in the unit price of Expansion
Joint with full compensation for all materials, labour, tools,
equipment and appurtenances and execution of all work and any
incidentals required for the complete finishing and installation of
pre-moulded joint filler and joint sealer.
Pay
Description
Item
07800-01 Expansion joint
- 119
Unit
lm
Expansion joint
Tender documents
Contract Package 1A
120
Expansion joint
Tender documents
Contract Package 1A
Reference Standards...................................................................122
Drain Pipes.................................................................................122
Catch pit and Grating...................................................................122
Fixing Brackets............................................................................122
Submittals..................................................................................122
Delivery, Storage and Handling....................................................122
Installation..................................................................................123
Method of Measurement..............................................................123
Catch pits and gratings.................................................................................123
Drainage Pipe................................................................................................ 123
Basis of Payment........................................................................................... 123
121
Bridge drainage
1.
Tender documents
Contract Package 1A
DESCRIPTION
This work consists of the provision and installation of the bridge drainage
system. Work shall be in accordance with the drawings subject to the approval
of the Engineer.
2.
MATERIAL REQUIREMENTS
ASTM A53
coated,
ASTM A48
JIS G 5501
JIS G 3442
JIS G 3101
122
Bridge drainage
Tender documents
Contract Package 1A
directly on the ground. The inside of pipes and fittings shall be kept free of dirt
and debris.
2.7 Installation
Drainage catch pits and gratings shall be installed complete at the locations
indicated on the drawings. Catch pits shall be cast into the structure or cast
into a previously formed box out as detailed in the Contractors method
statement. Where the catch pits are to be cast into a box out all relevant
details shall be subject to the approval of the Engineer. Where catch pits are
secured into box outs using concrete, the concrete shall be at least equal in
strength to the concrete in the surrounding structure and all box out faces
shall be prepared as required for construction joints. The inside faces of the
catch pit shall be painted in accordance with specification 08800 Painting
table 1, system for aggressive conditions subject to the approval of the
Engineer.
All pipes and fittings shall be installed to the locations, lines and grades
indicated in the drawings. Cutting of pipe shall be avoided. Where pipes are
cut the cut end shall be cleaned and trimmed and painted in accordance with
specification 08800 Painting immediately after cutting. All joints shall be
properly and securely made to ensure no leakage of water.
All pipe brackets shall be located and securely fixed in place before pipes are
installed.
3.
Drainage catch pits, frames and gratings inclusive of all fittings shall be
measured for payment by the number of drainage sets of each type,
constructed and installed in accordance with the requirements of the drawings
and approved by the Engineer.
3.1.2
Drainage Pipe
Drainage piping shall be measured for payment by linear meters along the
centre and between intersections of the centre of the pipe for the steel drain
piping of the diameter and type required by the drawings. The measurement
by linear metre shall include all fixtures and fittings including pipe covers,
tees, pipe connectors, brackets and all necessary fitting, supports and
accessories indicated on the drawings or otherwise required. All rates shall
include protective coatings, and shall be for all items constructed, installed
and approved by the Engineer.
3.1.3
Basis of Payment
Payment shall be made in accordance with the applicable unit prices of the pay
items of the Bill of Quantities listed below, and shall include all labor,
equipment and incidentals necessary to install drainage catch pits, frames and
gratings and all piping and fittings.
Volume 3 Technical Specification
123
Bridge drainage
Pay Item
07900-01
07900-10
Tender documents
Contract Package 1A
Pipe DN200
Description
Unit
lm
No.
124
Bridge drainage