You are on page 1of 60

Traceca Corridor

Traffic and Feasibility Studies - TNREG 9803

Module E :
Transport of crude oil and oil products on the Caspian Sea

Feasibility study for


the rehabilitation of Dubendi Oil Terminal (task E3)

April 2001

Report Cover Page

Project Title

: Traceca Corridor - Traffic and Feasibility Studies

Module E Title

: Transport of crude oil and oil products on the Caspian Sea

Project Number

: TNREG 9803

Module E Countries

: Azerbaijan, Kazakhstan and Turkmenistan

Local Operators

EC Consultant

Azerbaijan
Mr. Ikram Sadikov
Head of Transport Dept.
Ministry of Economy
Baku

Headquarters

Bceom Socit Franaise d'Ingnierie


Place des Frres Montgolfier
78286 Guyancourt Cedex, France

Kazakhstan

Project office

Mr. Talgat Abylgazin


General Director
Aktau Commercial Sea Port
Aktau

9 Sultanov Street, Appt. 67


Baku, Azerbaijan
Mr. Ph. Delaporte & Mr. A. Merrien
traceca@traffic.in-baku.com

seaport_akt@kaznet.kz
Sub-Consultant for Module E

Turkmenistan
Mr. Bekmyrat Gurbanmuradov
General Director
Turkmen Maritime Lines
Turkmenbashi

Port of Marseilles Authority, France


Mr. J.M. Bocognano
J.Bocognano@marseille-port.fr

turkmendeniz@online.tm

Date of report :

25 April 2001

Reporting period :

February to April 2001

Authors of report :

Andr Merrien and Jean-Michel Bocognano

EC Monitoring team
[name]

[signature]

[date]

[name]

[signature]

[date]

[name]

[signature]

[date]

EC Delegation
Tacis Bureau
[task manager]

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

Table of contents

1. Project synopsis for module E ......................................................................................................................4


2. Summary and conclusions...........................................................................................................................5
3. Oil flow projections.......................................................................................................................................7
4. Current condition of Dubendi Oil Terminal...................................................................................................8
4.1 General .................................................................................................................................................8
4.2 Navigation channel ...............................................................................................................................8
4.3 Breakwater............................................................................................................................................9
4.4 Piers......................................................................................................................................................9
4.5 Tank farms..........................................................................................................................................10
4.6 Rail-tank-car loading station ...............................................................................................................10
4.7 Waste Water Treatment Plant ............................................................................................................11
4.8 Oil pipe networks ................................................................................................................................11
4.9 Pump stations .....................................................................................................................................11
4.10 Power stations and electricity networks ..........................................................................................12
4.11 Administrative buildings ..................................................................................................................12
4.12 Miscellaneous deficiencies .............................................................................................................12
5. Rehabilitation plans....................................................................................................................................13
5.1
5.2
5.3
5.4

Short-term rehabilitation plan..............................................................................................................14


Medium-term rehabilitation plan .........................................................................................................15
Long-term rehabilitation plan ..............................................................................................................16
Investment costs.................................................................................................................................17

6. Ownership and operation schemes ...........................................................................................................17


7. Financial assessment ................................................................................................................................18
7.1
7.2
7.3
7.4

General ...............................................................................................................................................18
Computation of revenues....................................................................................................................19
Computation of operating expenses ...................................................................................................20
Financial results ..................................................................................................................................22

___________________

Annex 1:

Abbreviations & Acronyms, References and Staff List

Annex 2:

Photographs of Dubendi Oil Terminal

Annex 3:

Financial tables

Annex 4:

Maps and drawings

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

1. Project synopsis for module E


(Revised version, updated in April 2001)

Project Title

: Traceca Corridor - Traffic and Feasibility Studies

Module E Title

: Transport of crude oil and oil products on the Caspian Sea

Project Number

: TNREG 9803

Module E Countries

: Azerbaijan, Kazakhstan and Turkmenistan

Wider objective:

To promote adequate and safe transport of crude oil and oil products
on the Caspian Sea

Specific Objectives:

A traffic forecast for oil and oil products


The condition of existing infrastructure for oil transport
The feasibility of investments in Dubendi oil terminal
A brief pre-feasibility study for Aktau Oil Berths n4 & n5

Planned outputs:

A detailed traffic forecast


A detailed evaluation of the transport infrastructure (terminals and
vessels)
An overall feasibility study for rehabilitation of Dubendi oil terminal
A specific pre-feasibility study for Aktau Oil Berths n4 & n5

Project activities:

Preparation of supply demand analysis for crude oil and oil products
Preparation of traffic forecasts for crude oil and oil products
Evaluation of terminals in Aktau, Dubendi and Turkmenbashi
Evaluation of tanker fleet
Feasibility study for rehabilitation of Dubendi oil terminal
Brief pre-feasibility study for Aktau Oil Berths n4 & n5

Target group(s):

Ministries of Transport, Oil terminal operators, Tanker operators

Project start date:

15 March 2000 (Module E)

Expected completion date:

August 2001

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

2. Summary and conclusions


Dubendi Oil Terminal is currently the weakest node along the Traceca oil transportation route from the
eastern shore of the Caspian to the Black Sea, its throughput capacity being limited to approximately 4 million
tonnes per year. Since this route is strategically crucial for exports of Central Asian oil, as an alternative to
Russian itineraries, increase in oil flows through Dubendi may reasonably be expected. A wide range of
projections have been elaborated, the lowest ones being quite cautious:

Figures in million tonnes of oil through Dubendi Oil Terminal

in 2005 in 2010 in 2020

If Kazakh & Turkmen oils to be moved via the Main Export Pipeline are unloaded in
Dubendi port - ("high hypothesis")

12

17

If not (cross-Caspian pipeline, or any other option)


("low hypothesis")

Obviously the above figures can only be reached if improvement works are carried out at Dubendi Oil
Terminal, as well as on the other chain elements (the Aktau port, the tanker vessels, the railway lines from
Azerbaijan to Georgia and the Georgian ports). As far as Dubendi is concerned, this report proposes three
rehabilitation plans:
!

A short-term plan, allowing to increase the oil throughput up to 8 Mt per year, sufficient till 2020 in the low
hypothesis, only till 2006 in the high traffic hypothesis.

A medium-term rehabilitation plan, enabling to cope with 12 Mt per year, to be implemented by year 2010
in the optimistic hypothesis.

A long-term plan consistent with 18 Mt per year, needed by 2020 if traffic grows as fast as in the high
hypothesis.

It should be pointed out that the short-term plan covers vital items aiming at improving environmental
protection (upgrading the waste water treatment plant, supplying oil spill prevention equipment) and safety
(renewal of electricity networks, installation a modern fire-fighting system).
The related investment costs can be split up as follows:
Cost estimates in million USD

Short-term plan

Medium-term plan

Long-term plan

Total 3 plans

Infrastructures

7.270

7.790

2.890

17.950

Superstructures

3.730

11.080

11.620

26.430

Other equipment

1.710

1.050

0.105

2.865

Total

12.710

19.920

14.615

47.245

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

In order to evaluate the sustainability of the proposals a financial assessment has been performed,
1

considering the Dubendi Oil Terminal as a global "Cost and Profit Centre" . The results of the analysis are
summarised below:
!

In case no investment is undertaken and traffic is limited to 4 Mt per year, the terminal would yet be
profitable: annual cash-flows will always be positive and discounted global cash-flow should exceed 23
million USD. However, refraining from investing would entail unacceptable risks with regard to safety and
to environmental protection.

If traffic grows as fast as in the optimistic hypothesis, and provided that required investments are
implemented, the Internal Rate of Return would be close to15%. Nevertheless, although the global cashflow would be high (34 million USD), annual cash-flows would be negative till year 2007; if sufficient liquid
assets are not initially available to cancel cash needs, a loan should be contracted. The amount of this
2

loan should be around 12 million USD .


!

In case traffic growth is weak, as in the "low-case", and the short-term plan is implemented, the Internal
Rate of Return will be limited to 11%. The discounted global cash-flow would reach 25 million USD,
whereas annual cash-flows would almost always be on the positive side (a slight tariff increase or a very
limited loan would easily cancel the cash need).

The first conclusion of this study is that it would be unreasonable to leave the terminal in its current condition;
threats to workers' safety as well as against the environment are far above acceptable standards.
On the other hand, if Caspian TransCo receives reliable guarantees that Chevron will carry on increasing its
oil shipments via Dubendi, then the short-term improvement plan should be launched without hesitating. Even
if oil traffic doesn't exceed the 8 Mt threshold, the investment will be profitable.
Lastly, the most optimistic traffic option is also the one which may bring the highest benefits in terms of cashflow and of Rate of Return. The required 12 million USD loan should be easily granted, provided that a fair
agreement is reached between BISP, SOCAR and Caspian TransCo.

The sharing out of costs and benefits would have to be fairly discussed between BISP, SOCAR and Caspian TransCo,
under the control of the Government of Azerbaijan.

The EBRD might grant a loan to help finance the project. However, since private companies are involved in it (mainly
Chevron and Caspian TransCo), an EBRD loan would be limited to a small proportion of the project cost.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

3. Oil flow projections


Following oil flow projections regarding Traceca countries were elaborated in August 2000 for the needs of
the "Forecasts of Oil Flows" report:
Current and projected oil flows
(in million tonnes per annum)

1999

2005 2010

2020

Exports from Kazakhstan


To Russia and to Europe via the Druzhba pipeline system
To the Russian Orsk refinery
To Europe
via the CPC pipeline
via Aktau, Makhachkala and the Caucasian northern route
via Aktau, the Caspian Sea and the MEP
via Aktau, Dubendi and the Caucasian western route
To Asia via Iran

7,5
6,5

7,5
6,5

7,5
6,5

7,5
6,5

0,0
0,5
2,0
0,5

15,0
0,5
2,0
3,0
0,5

25,0
0,5
4,0
4,0
1,5

45,0
1,0
6,0
5,0
6,0

17,0

35,0

49,0

77,0

via the Caspian Sea and the MEP


via the Caspian Sea, Dubendi and the Caucasian western route
To Asia via Iran

0,5
2,5

1,0
1,0
4,0

2,0
2,0
16,0

3,0
3,0
24,0

Total Turkmenistan

3,0

6,0

20,0

30,0

1,9
3,9

5,0
5,0
5,0
2,0

7,0
7,0
20,0
4,0

8,5
8,5
36,0
9,0

5,8

17,0

38,0

62,0

Total Kazakhstan
Exports from Turkmenistan
To Europe

Exports from Azerbaijan


To Europe
via the Caucasian northern route
via the Caucasian western route
via the MEP
To Asia via the Caspian Sea and Iran
Total Azerbaijan

From the preceding it may be concluded that transit of crude oil through Dubendi port should grow, and that
growth will be sharper if Kazakh and Turkmen oil feeding the MEP are to be shipped onboard vessels to
cross the Caspian Sea:

Figures in million tonnes of oil through Dubendi Oil Terminal

in 2005 in 2010 in 2020

If Kazakh & Turkmen oils to be moved via the MEP are unloaded in Dubendi port

12

17

If not (cross-Caspian pipeline, or any other option)

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

4. Current condition of Dubendi Oil Terminal


4.1

General

In the Soviet times the Baku area was a major centre for oil processing. Baku refineries had a capacity of up
to 25 million tonnes of crude oil per year. They were processing not only oil extracted in the area but also
significant volumes brought from other parts of the Soviet Union, particularly Kazakhstan and Turkmenistan.
On the other hand large volumes of petroleum products were exported in direction of those two countries with
destinations as far as Siberia or even Kamchatka.
The terminal facilities of the Baku port were at one time handling inflows and outflows, particularly at pier
n20. However, to cope with increasing flows, at the beginning of the sixties it was decided to build a
dedicated oil terminal on the Absheron Peninsula in a site called Dubendi that is naturally well protected by
the Pirallachy island from the east and from the south (the island is connected to the mainland by an artificial
dike). Dubendi is at a distance of 47 km from Baku by land and 92 nautical miles by sea. Construction of the
port started in 1965.
Two kinds of flows are presently transiting by Dubendi:

Crude oil extracted in the region of the Absheron Peninsula, which reaches Dubendi by underwater
pipelines. It is shipped by rail to the SOCAR storage facilities in Sangachal, 60 km south of Baku, before
being forwarded by the AIOC pipeline to the Supsa port, on the Black Sea.

Crude oil imported by tanker either (the bulk of it) from Aktau, Kazakhstan, from where it is mainly
shipped by Tengizchevroil, or from Okarem or Cheleken, Turkmenistan, where it is produced by Mobil
and Total. This oil is sent to Batumi port on the Black Sea by the Caspian TransCo Company.

Dubendi Oil Terminal mainly consists of a navigation channel, four piers sheltered by a breakwater as well as
onshore facilities: tank-farms, a rail-tank-car loading station, a waste water treatment plant, oil pipe networks,
pump stations, power stations, electricity and water networks, administrative buildings.
All infrastructures are owned by BISP whereas most unloading facilities, pipe systems and tank-farms belong
to SOCAR.
There is no bunkering station left in Dubendi. Tankers refuel in other ports of call.

4.2

Navigation channel

The navigation channel starts from the 10 m hydrographic contour line, and was initially dredged down to 10
m below the Caspian Sea chart datum. It is 100 m wide on the sea bed and stretches along 2.5 nautical
miles. Due to northern wave action the channel is subject to continuous siltation. Frequent dredging works
have been required to maintain water depths, however insufficient since a shoal currently reduces the depth

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

to 6.5 m in the vicinity of the breakwater head. The port basin was also initially dredged to 10 m, but siltation
3

has resulted in restricted depths: 9 m in the turning area, 8.5 m to 7.5 m along the berths .
The channel is marked with four port and four starboard buoys, which are highly corroded and partly not
working. In addition, two leading lines are marked by onshore beacons. The beacons in the first section are in
4

poor condition but still working, whilst beacons in the second section are out of operation .

4.3

Breakwater

The breakwater is of rubble mound type. Its total length is 1,035 m, consisting of a 250 m long root, a 540 m
long trunk section and a 245 m long head. The elevation of the top is 3 m above the Caspian chart datum.
The root section is protected with quarry stones, the trunk stretch is covered with 4.6 tonne concrete cubes
whilst the head part is protected with 10 to 15 tonne concrete cubes. The end of the breakwater head is
bordered by a sheet pile wall that reduces the structure width.
Due to the increase in the Caspian Sea level incoming waves are currently stronger than those which were
taken into account at the design phase; this is the reason why several parts of the armour layer and of the
cap failed, including at the head section, as shown on the attached photos. There is almost a breach between
connection with pier n2 and connection with pier n5.
The inner part of the breakwater is bordered with reinforced concrete piles supporting pipelines which are
generally severally damaged, except between the root and pier n1. Diver inspections revealed that piles are
damaged underwater too.
Floodlighting system along the breakwater is destroyed, as well as all water and electricity networks.

4.4

Piers

Four piers were constructed from 1972 to 1975, to allow berthing of tankers: pier n1, pier n2, pier n3 and
pier n5. Pier n4 was initially foreseen, close to pier n3, but finally not built. Piers n2 and n5 were never
used for oil traffic, they only accommodated tug boats, dredgers and other port vessels.
Each pier has two symmetrical berths, design capacity of each berth being 2.5 Mt per annum.
Pier n1 and pier n3 are operated by Caspian TransCo for unloading crude oil shipped from Aktau, Okarem
5

and Cheleken .
3

The CSC tanker fleet operating in the Caspian Sea consists of 33 tankers:

3 type Kafur Mamedov tankers:

12,300 dwt

Mean load draught: 8.00 m

9 type Absheron tankers:

7,400 dwt

Mean load draught: 5.3 m

5,500 dwt

Mean load draught: 4.15 m

al

21 type G Shikhlinskiy tankers:

The three largest tankers were recently purchased with the objective of reducing transportation costs. However this
acquisition didn't provide the expected benefit so far, since water depths in Aktau and Dubendi are not sufficient to
accommodate fully loaded 12,300 dwt tankers.
4

A specific project has been undertaken to upgrade navigation aids in Baku and Dubendi ports, to be implemented in
2001 under the Traceca programme. This project includes supply of radar equipment, Global Maritime Distress Safety
System, radio communication equipment, renewal of buoys, beacons, leading lights and lighthouses.

Pier n3 is also equipped for unloading refined oil products. However throughput of refined oil has fallen below a very
limited level in Dubendi (Baku city port has dedicated berths for unloading refined oil, originating from Turkmenbashi
refinery and mainly destined to Azerbaijan and to western Europe).

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

These piers are made of reinforced concrete piled structures consisting of berthing sections connected with
trestle bridges. They are equipped with fenders, bollards, oil unloading arms, oil pipelines, water pipes, valves
and lightening masts.
All concrete structures are highly deteriorated, cracked and show corroded steel bars, above sea water and
below water level as well.
Almost all fenders are simple rubber tyres which are not adequate.
Oil arms and pipes are in need of maintenance, although in working conditions.
Fire-fighting system is not suitable since it is only based on water, except a small foam equipment recently
installed on pier n3 - water is not adequate to fight hydrocarbon fires -. Moreover, there is no automated
system to give the alarm.
Other steel equipment (stairs, handrails, etc.) are very corroded and generally out of shape.
Electricity networks are such in poor condition that they are indeed dangerous.
Condition of pedestrian traffic on piers is very bad and somehow risky.
Lastly, access to pier n3, via a 220 m long rubble mound structure protected with 300 kg quarry stones, has
been damaged by wave action.

4.5

Tank farms

Two main tank farms are available. The first one borders the port basin and is used to store crude oil (16
tanks, total capacity 170,000 m3 - available current capacity is only 130,000 m3 because some tank bottoms
are obstructed with viscous products -), whereas the second one is on top of the hill (52 tanks, total capacity
260,000 m3); the latter was dedicated to refined products but is no longer used.
Current storage capacity for crude oil (130,000 m3) is a bit low: on the year 2000 traffic basis (3.5 Mt) it only
allowed an average "oil idle time" of 13 days. For the needs of the following project a more comfortable ratio
has been considered (20 days), entailing use of the upper tank farm for crude oil storage and extension of the
lower tank-farm.

4.6

Rail-tank-car loading station

Two pipelines allow transfer of crude oil from the lower tank farm to the RTC station, located a few kilometres
away, on top of the plateau. The station includes two blocks, each one being designed for 21 RTC at a time.
It is equipped with a complete and modern foam fire-fighting station.
The RTC loading station is recent and runs under satisfactory safety conditions.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

10

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

4.7

Waste Water Treatment Plant

The port has a Waste Water Treatment Plant (WWTP) built in 1970 for treating sanitary water, bilge water
6

from the tankers, and waste water from the land-based crude oil storage tanks . The original design capacity
of the WWTP was 1,500 to 2,000 tonnes of waste water per day. Since 1991 the WWTP has been operated
by the "28 of May" Company, the same Company that operates the port reception and oil transport facilities.
The WWTP staff and quality control laboratory are at the site. The laboratory is not capable of testing for
regulated parameters in the WWTP discharge. For complete analyses samples must be sent offsite. Analysis
of the sea water for phenols and other contaminants is according to Gost standards.
The WWTP features the following processes:
!

3 to 4 hours of settling in crude oil tanks (containing crude oil delivered from Aktau and Turkmenbashi, as
well as from Pirallachy Island, which now totals about 78.000 tonnes daily).

Draw off of water/oil emulsion (about 80 to 100 tonnes daily, depending on tanker traffic).

Two 5,000 tonne tanks for oil/water separation (about 17 to 20 tonnes of oil is returned to the crude oil
tanks).

Discharge of treated waste water to sea.

The WWTP is poorly maintained and operated. Significant bypassing is reported to occur.

4.8

Oil pipe networks

Except the rare lines which are still being used, all other pipelines are worn-out. Moreover, pipeline supports
which are standing along the breakwater are severely damaged.

4.9

Pump stations
7

There are three pump stations on the terminal: pump stations n27 and n62, serving the upper tank farm ,
and Caspian TransCo's pump station, serving the RTC loading facility. The latter is the only new and sound
one. The two others are operating but they are in need of overhaul.

6
7

The plant doesn't receive any ballast water since vessels arriving at the port are loaded with oil.
Crude oil is delivered to the lower tank farm by the use of vessel pumps. It may be underlined that unloading

operations are frequently delayed because of failures on vessel pumps.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

11

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

4.10 Power stations and electricity networks


The terminal is fed by two main transformers delivering 6 kV power to seven sub-transformers producing 0.4
kV power. All transformers and sub-transformers are in need of overhaul. Besides, the whole electricity
supply network is in advanced stage of deterioration and therefore dangerous with regard to risk of fire:
!

cable ways are not covered;

many connection boxes are no longer protected from dust and rain, and several cable connections are
not insulated;

earthening devices don't look efficient;

most supporting poles are corroded and about to collapse.

4.11 Administrative buildings


Though main building structures look sound, administrative buildings do not offer decent working conditions.
They need to be refurbished, they also need some modern office equipment and adequate improvements
allowing to centralise port operation control.

4.12 Miscellaneous deficiencies


Traffic of vehicles and pedestrians is not controlled according to international safety standards applicable to
oil terminals. All dangerous areas ought to be clearly marked and prohibited to non-authorised vehicles and
persons.
The general fire-fighting system is not adequate, especially because it does not include enough foam
systems (only pier n3 has a small foam tank). Furthermore, the water network is not well maintained and
outlets are difficult to locate.
There was no confirmation of the presence of appropriate oil spill prevention equipment, although a short old
boom guard for localising emergency oil spills in the process of unloading tankers could be seen. The "oil
refuse collector" ship carries out mechanical collection of oil and waste floating on the surface. The fire boat
is also supposed to be equipped with operational boom guards for localising oil spills in the berth areas. The
port evidently expects help to come from the port of Baku in the case of critical oil spills. There was no
indication that an Emergency Response Plan has been developed. The port has requested booms of the
Anakonda type as part of the rehabilitation project.
It may be added that Azerbaijan, as a member of the IMO (as well as all other riparian states of the Caspian), has
accepted the various requirements of the IMO concerning oil pollution preparedness, response and co-operation. These
include reporting procedures for vessels, emergency response plans, and international co-operation.
Port crude oil and petroleum product offloading and onloading facilities, which fall under the IMO directives on
preparedness, are in the process of improving facilities, developing Emergency Oil Spill Response Plans, and upgrading
equipment required to meet the terms of the plans. In general these ports should be prepared to handle US EPA Tier 1
and Tier 2 spills. The minimum requirements for Tier 1 (up to 10 tonnes) and Tier 2 (from 10 to 100 tonnes) spills are as
follows:

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

12

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

1.

Oil spill response vessel

2.

Rapid deployment boom system

3.

Permanently-moored boom

4.

Rope skimmer oil mop

5.

Portable power supply

6.

Sorbents

7.

Harbour compensators

8.

Harbour skimming system

9.

Individual response pits

10. Capacity for installation & commissioning of equipment


11. Spare parts and maintenance

5. Rehabilitation plans
Rehabilitation plans have been developed to cope with the projected increase of oil flows, to improve the
environmental protection at the port and to comply with safety requirements. Two hypotheses of oil flows
8

have been considered, based on the former traffic projections :


in 2005

in 2010

in 2020

High hypothesis

12

17

Low hypothesis

Figures in Mt

Rehabilitation plans have been adjusted accordingly:


!

A short-term rehabilitation plan allowing an annual flow of 4 to 8 Mt, sufficient till 2020 in the "low-traffic"
hypothesis, till 2006 only in the "high-traffic" case.

A medium-term rehabilitation plan allowing an annual flow of 8 to 12 Mt, to be launched in 2005 in the
"high-traffic" case.

A long-term rehabilitation plan allowing an annual flow of 12 to 18 Mt, to be launched in 2010 in the "hightraffic" case.

Without any investment DOT capacity would be limited to approximately 4 Mt per annum - or reduced in case the
breakwater carries on failing -.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

13

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

5.1

Short-term rehabilitation plan

a. Infrastructures
As far as infrastructures are concerned, the short-term plan includes:
!

Rehabilitation of the root section and of the trunk section of the breakwater (total length 790 m) by
placement of heavier blocks on the armour layer and by widening the capping berm. This will require
preliminary wave studies and hydraulic tests.

Rehabilitation of pier n1 and pier n3 by repair of reinforced-concrete piles, slabs and beams (removal of
damaged concrete, sealing of new steel bars, injection of resin and projection of cement mortar),
replacement of fenders, bollards, stairs and handrails.

b. Superstructures
Regarding superstructures the short-term plan covers:
!

Road repair works on top of the breakwater, up to pier n1, on the access causeway to pier n3 as well as
in both tank-farm areas (including drainage systems and cable ditches).

Improvement works in the lower tank-farm (cleaning-out of tank bottoms and repair of floating roofs in
blocks 13a and 14).

Conversion of tanks in the upper tank-farm to provide an additional storage capacity of 120,000 t of crude
oil (blocks n4, n7 and n11).

Improvement of oil pipes and oil arms serving pier n1 and pier n3, as well as oil pipes in both tankfarms.

Overhaul of internal pump stations n27 and n62.

Rehabilitation of the Waste Water Treatment Plant.

Complete renovation of the electricity system, from the main transformers (including cables, cable ways,
connection boxes, earthening devices and floodlighting poles).

c. Other equipment
In the short-term plan rehabilitation of other equipment covers:
!

A preliminary in-door refurbishment of buildings in the lower and the upper port areas.

Renewal of the boiler unit and its connected utilities (electricity supply and steam pipes) .

Supply of a first set of environmental protection equipment (an oil boom, a rapid deployment boom

system, an oil skimmer and an oil-refuse collector).


!

Installation of a new fire-fighting system, including a sea-water pump, an upgraded water network, a foam
production station and an automated alarm system.

The boiler produces steam which is used to heat up crude oil pipes.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

14

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

Installation of notice boards and signs informing port workers and visitors about the safety rules they
have to follow and prohibiting access to designated areas.

5.2

Medium-term rehabilitation plan

a. Infrastructures
As far as infrastructures are concerned, the medium-term plan includes:
!

Dredging of the navigation channel and of the port basin down to 10 m below CD, to allow 12,000 dwt oil
carriers to enter the port with full tanks

10

Rehabilitation of the head section of the breakwater (245 m long) by placement of heavier blocks on the
armour layer and by strengthening the sheet pile wall, on the basis of the results of wave studies and
hydraulic tests to be performed during the course of the first phase.

Rehabilitation of pier n2 by repair of reinforced-concrete piles, slabs and beams (removal of damaged
concrete, sealing of new steel bars, injection of resin and projection of cement mortar), placement of
fenders, bollards, stairs and handrails.

Rehabilitation of the berths dedicated to port vessels (tug boats, pilot vessels, fire fighting vessel,
pollution fighting units).

Reconstruction of slope protections along the western shore of the port basin (quarry stone revetment).

b. Superstructures
Regarding superstructures, the medium-term plan covers:
!

Road repair works on top of the breakwater, from pier n1 up to pier n2, as well as in both tank-farm
areas (including drainage systems and cable ditches).

Renovation of oil tanks 13b, in the lower tank-farm.

Extension of block 14, in the lower tank-farm, to increase oil storage capacity by 120,000 m3.

Complete overhaul of tanks in the upper tank-farm (tanks n4, n7 and n11).

Improvement of oil pipes and oil arms serving pier n2, as well as pipes in both tank-farms.

Electricity networks on the breakwater, on pier n2, on the port-vessel berth and in the extended tankblock 14 (including cables, cable ways, connection boxes, earthening devices and floodlighting poles).

c. Other equipment
In the medium-term plan rehabilitation of other equipment includes:
!

Completion of building refurbishment in the lower and the upper port areas, including installation of
computerised systems to centralise port operations.

Supply of a second set of environmental protection equipment (an oil boom, a second vessel for boom
deployment, a second oil skimmer and another oil-refuse collector).

10

This only make sense if consistent deepening works are undertaken in Aktau port.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

15

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

5.3

Completion of the fire-fighting system with additional foam equipment for pier n2 and in the tank-farms.

Long-term rehabilitation plan

a. Infrastructures
As far as infrastructures are concerned, the long-term plan includes:
!

Dredging works in the vicinity of pier n5, down to 10 m below CD, to allow 12,000 dwt oil carriers to berth
along this pier with full loads.

Rehabilitation of pier n5 by repair of reinforced-concrete piles, slabs and beams (removal of damaged
concrete, sealing of new steel bars, injection of resin and projection of cement mortar), reconstruction of
collapsed concrete slabs, placement of fenders, bollards, stairs and handrails.

b. Superstructures
Regarding superstructures, the long-term plan covers:
!

Road repair works on top of the breakwater, from pier n2 up to pier n5, as well as in both tank-farm
areas (including drainage systems and cable ditches).

Renovation of oil tanks of blocks 13a and 14, in the lower tank-farm.

Complete overhaul of oil tanks of blocks 6, 8, 9 and 12, in the upper tank-farm.

Placement of oil pipes and oil arms serving pier n5.

Final upgrading of oil pipes in both tank-farms.

Extension of electricity networks on the breakwater and on pier n5 (including cables, cable ways,
connection boxes, earthening devices and floodlighting poles).

c. Other equipment
In the long-term plan this item simply deals with the supply of a third set of oil-spill prevention equipment: an
oil boom, a skimmer, an oil-mop rope and a oil-refuse collector.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

16

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

5.4

Investment costs

Investment costs have been estimated according to current regional prices supplied by the Contractor's local
partners and also with reference to recent civil works performed in Azerbaijan. The details provided at the first
page of Annex 3 can be summarised as follows:
(cost estimates in thousands USD)

Short-term plan

Medium-term plan

Long-term plan

Total 3 plans

7,270

7,790

2,890

17,950

B. Superstructures

3,730

11,080

11,620

26,430

C. Other equipment

1,710

1,050

105

2,865

12,710

19,920

14,615

47,245

A. Infrastructures

Total A + B + C

6. Ownership and operation schemes


All infrastructures of DOT are owned by BISP (the channel, the breakwater and the piers), whereas
superstructures belong to SOCAR (the pipes, the oil arms, the pumps and the tanks). BISP also owns the
pilot boats, the tug boats and the navigation aids.
Caspian TransCo is the terminal operator

11

. For the operation of DOT Caspian TransCo has signed

agreements with CSC, with BISP as well as with SOCAR. The Consultant understood that tariffs are often
adjusted according traffic levels and to other miscellaneous parameters.
Each entity has its own staff working at the terminal: approximately 40 employees from BISP, 180 to 200 from
SOCAR (including 20% assigned to the underwater supply pipeline, which is out of the scope of this report),
and around 20 from Caspian TransCo.

11

Caspian TransCo is in charge of arranging multi-modal transportation of oil from the eastern side of the Caspian Sea
to the Black Sea port of Batumi, via Dubendi, in line with the terms of the Protocol signed in July 1999 by Officials of
Kazakhstan, Azerbaijan and Georgia, within the framework of the Inogate programme.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

17

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

7. Financial assessment

7.1

General

The objectives of the financial assessment are to evaluate the capacity of DOT to be self-supporting and to
bear the load of the improvement works which are required to comply with safety requirements, to protect the
environment and to cope with the projected increase of oil throughput. In this chapter DOT is considered as a
global "cost and profit centre", the sharing out of investment costs being to be agreed upon by negotiations
between BISP, SOCAR and Caspian TransCo.
Financial projections have been made according to three families of hypotheses:
1. No investment is undertaken and traffic is therefore limited to 4 Mt per year throughout the whole study
period (20 years).
2. Investments are carried out to cope with the low traffic hypothesis (4 Mt in year 2005, 6 Mt in year 2010
and 8 Mt in year 2020). The content of the investment programme is that of the "short term plan",
amounting to USD 12.7 million.
3. Investments are carried out to cope with the high traffic hypothesis (7 Mt in year 2005, 12 Mt in year 2010
and 17 Mt in year 2020). In this case the content of the investment programme covers the short-term
plan (USD 12.7 million), the medium-term plan (USD 19.9 million) and the long-term plan (USD 14.6
million), resulting in a total investment of USD 47.2 million.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

18

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

7.2

Computation of revenues

DOT revenues have firstly been computed on the basis of current tariff rates and without considering any
loan or any grant. As a second stage, increased tariffs and loans have been taken into account in order to
reach more satisfactory financial results.
Sources of revenues are split into vessel dues, cargo dues and oil storage dues.
Vessel dues
Standard tanker tariffs at Dubendi Port are displayed in the following table.

Unit Rates

"Kafur Mamedov"
tankers

"Absheron"
tankers

"Gal Shikhlinskiy"
tankers

Vessel size (m3)

28,780

19,228

14,350

Standard oil load (t)


Unit

6,500
Sub-total

5,000
Sub-total

3,500
Sub-total

(1000 Manats)

(1000 Manats)

(1000 Manats)

Registration

(Manats)

lump sum

10

10

10

Sailing

lump sum

40

40

40

Channel

130

m3

3,741

2,499

1,865

Vessel

80

m3

2,302

1,538

1,148

Berth

120

m3

3,453

2,307

1,722

Mooring

lump sum

880

440

440

Tug-boat

340

m3

9,785

6,537

4,879

Total in thousands Manats

20,212

13,372

10,104

Total in USD per call *

4,500

3,000

2,250

Total in USD per tonne of oil *

0.69

0.59

0.64

* Using an exchange rate of 1 USD for 4,500 Manats

In the following an average standard rate of USD 0.65 per tonne of oil has been accounted for. Yet, it has
also been considered that CSC tankers simply pay a lump sum of USD 1000 per call, whichever type of
tanker calls at the port.
Cargo dues cover transfer of oil from ships to storage tanks. They are based on a rate of USD 0.60 per
tonne of oil.
Oil storage dues have been rounded at USD 0.90 per tonne of oil.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

19

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

7.3

Computation of operating expenses

Operating expenses include labour cost, maintenance costs, energy consumption costs, overhead expenses,
financial charges - in case of loans -, as well as depreciation of facilities.
a. Labour cost
At the end of year 2000 total staff involved in operation of DOT was 210 (including BISP, SOCAR and
Caspian TransCo personnel). The average overall cost of a terminal employee was about USD 130 per
month including salary, pension fund, social charges and vacation, whilst that of an engineer was USD 220
per month. As a whole it can be considered that the average unit cost is close to USD 160 per month, i.e.
USD 1920 per year. On this basis the total annual labour cost amounts to USD 400,000.
In the future this cost should vary, under the impact of several factors: traffic increase, improvement in
productivity and rise of salaries.
Impact of traffic increase
Part of the employees are involved in administrative tasks or in activities which will not be altered by
variations of traffic. It has been assumed that only one third of the number of employees should increase with
the traffic. In 2000 it is considered that 140 people are a fixed number, not depending on the traffic level, and
70 are a variable number - with a productivity of 50,000 t/year per employee -. The latter workforce is likely to
vary together with the traffic level.
Impact of improvement in productivity
Rehabilitation of the terminal should entail improved productivity, thanks to renewed equipment and to
computerised management of operations. It is assumed that productivity will increase at an average rate of
3% per year in the coming 20 years (in the "no investment" case productivity is supposed to remain stable),
which leads to the following results:

Productivity (tonnes/year):

Year 2000
50,000

Staff

Year 2005
58,000

Year 2010
67,200

Year 2015
77,900

Year 2020
90,300

Year 2000

Year 2005

Year 2010

Year 2020

Traffic for the "no investment" case (Mt/year)

3.5

Staff in the "no investment" case

210

220

220

220

High traffic hypothesis (Mt/year)

3.5

12

17

Variable staff

70

120

180

190

Fixed staff

140

140

140

140

Staff in the high traffic hypothesis

210

260

320

330

Low traffic hypothesis (Mt/year)

3.5

Variable staff

70

70

90

90

Fixed staff

140

140

140

140

Staff in the low traffic hypothesis

210

210

230

230

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

20

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

Impact of rise of salaries


On the basis of a yearly increase of 2% the annual cost of an employee will vary as follows:
!

Year 2000: USD 1920

Year 2005: USD 2120

Year 2010: USD 2340

Year 2015: USD 2580

Year 2020: USD 2850

b. Maintenance costs
Annual maintenance costs can be estimated as ratios of investment costs, and following ratios have been
applied to planned investments:
!

0.5% for the breakwater;

0.2% for the other infrastructure items;

5% for the superstructures and the other equipment.

As far as existing facilities are concerned, a yearly lump sum of 1 million USD has been taken into account.
c. Energy consumption costs
From the Inogate Ref. 1 report the cost of energy spent to unload a tanker and to pump its oil into storage
tanks is around USD 0.12 per tonne of oil.
d. Overhead expenses
Part of administrative and management costs of BISP, SOCAR and Caspian TransCo is to be incorporated
into the terminal operating expenses. For this purpose DOT turnover has been considered as the key
parameter, it has been multiplied by 0.15 to compute global overhead expenses.
e. Financial charges
Each time it is assumed that a loan will be needed, following standard conditions are applied: 4-year grace
delay, 10-year repayment period and 8% financial charges (interest rate plus commitment fees plus fixed
fees).
f. Depreciation of facilities
It has be considered that rehabilitation works will be amortised within 20 years. No depreciation is accounted
for existing facilities.

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

21

Transport of crude oil and oil products on the Caspian Sea - European Commission Tacis-Traceca Programme
____________________________________________________________________________________________________________

7.4

Financial results

Details of financial computations are in the attached Annex 3, from page 2 through page 8. They are
summarised in the table below.

Discounted
cash-flow
at 10%
(million USD)

Internal Rate of
Return
(%)

Maximum need in
cash-flow
(million USD)

23.5

0
0
11.55

0
0.45
0

34.2
56.9
37.0

14.6
25.4
19.0

8.2 (in 2006)


4.9 (in 2002)
0

0
0
0.4

0
0.03
0

24.5
25.3
24.6

11.2
12.2
11.3

0.3 (in 2005)


0
0

Hypothesis

Table in
Annex 3

Loan
(million
USD)

No investment

REF

High traffic
High traffic
High traffic

HH1
HH2
HH3

Low traffic
Low traffic
Low traffic

LH1
LH2
LH3

Tariff Rise
(USD/t)

Note: gross operating profits are clearly positive in all cases, even in the "no investment" hypothesis.
Comments:
!

In the "no investment" case cash-flows are always positive (average USD 2.4 million per year),
discounted cash-flow being USD million 23.5. DOT is globally quite profitable.

In the two other cases cash-flows are sometimes negative at the beginning of the time period; this is the
reason why additional tests have been carried out, firstly with increased tariffs, then with loans.

In the "high traffic" hypothesis a significant rise of tariff (USD 0.45 per tonne of oil) is not sufficient to
cancel the need in cash-flow. A USD 11.55 million loan can solve the problem.

In the "low traffic" hypothesis a very slight increase of tariff (USD 0.03 per tonne of oil) cancels the
negative cash-flows. The same result can be obtained with a very limited loan (USD 400,000).

Internal Rates of Return are satisfactory in all cases, although a bit on the edge in the "low traffic"
hypothesis. Investments are profitable.

Enclosures: Annex 1 to Annex 4

________________________________________________________________________
Feasibility Study for the Rehabilitation of Dubendi Oil Terminal - April 2001

22

Annex 1
Abbreviations & Acronyms, References and Staff List

Abbreviations and Acronyms

AIOC
BISP
BSL
CD
CPC
CSC
DOT
dwt
EBRD
IMDG
IMO
Inogate
km
kV
m
MARPOL
MEP
Mt
RTC
SOCAR
t
Traceca
USD
V
WWTP

Azerbaijan International Oil Corporation


Baku International Sea Port
Baltic Sea Level
Chart Datum
Caspian Pipeline Consortium (from western Kazakhstan to Novorossiysk)
Caspian Shipping Company
Dubendi Oil Terminal
dead weight tonnage
European Bank for Reconstruction and Development
International Maritime Dangerous Goods Code
International Maritime Organisation
Interstate Oil and Gas Transmission to Europe (a European Commission programme)
kilometre
kilo Volts
metre
International Convention for Prevention of Marine Pollution
Main Export Pipeline (from Baku to Ceyhan)
Million tonnes
Rail Tank Car
State Oil Company of Azerbaijan Republic
metric tonne
Transport Corridor Europe-Caucasus-Asia
United States dollar
Volt
Waste Water Treatment Plant

References

1. Trans-Caucasian Multi-Modal Oil Transport System (Inogate 97.04, January 2000)


2. Complementary Feasibility Studies for Oil and Gas Transport from the Caspian Sea Region (Inogate 97.01)
3. Hydrocarbon Potential Assessment (Inogate 97.02)
4. Priority Emergency Investment in Oil and Gas Infrastructures (Inogate 97.03)
5. Feasibility Study for Oil and Gas Pipe-Lines across the Caspian Sea (Inogate 96.01)
6. Black Sea Oil Investment (Lloyds Shipping Economist, April 2000)
7. Restituer le potentiel de la mer Caspienne (Ptrole et Gaz Informations, April 2000)
8. The Caspian Sea: legal status and international security (Umirserik Kasenov)
9. Lexploitation des hydrocarbures de la mer Caspienne (Ptrole et Techniques, February 2000)
10. EIA Caspian Sea Region Report (Energy Information Administration, December 1998)
11. Caucase, le grand jeu ptrolier (Courrier International, October 1999)
12. Seminar: Les enjeux rgionaux de la mer Caspienne (Centre Franais du Commerce Extrieur, September 1999)
13. Caucase, les grandes manuvres russes (LExpress, November 1999)

Staff list

1. BENEFICIARIES & COUNTERPARTS


Ministry of Economics of Azerbaijan
Mr. Ikram Sadikov, Head of Transport Department
Mr. Hussein Gubadov, Head of Fuel and Energy Department
Baku International Sea Trade Port
Mr. Soltan Kazimov, Chief Engineer
Mr. Rafail Mirgulamov, Commercial Manager
Aktau Commercial Sea Port
Mr. Abylgazin, General Director
Mr. Glock, Deputy General Director
Turkmen Maritime Lines
Mr. Bekmyrat Gurbanmuradov, General Director
Mr. Murad Atayev, Deputy General Director

2. TACIS
Co-ordinators
Mr. Marc Graille, Tbilisi
Mr. Erzhan Zhumali, Astana
Mr. Emilio Valli, Astana
Mr. Boris Smolin, Baku
Mr. Mahir Kazimov, Baku
Mr. Mukhamet Gulychev, Ashgabad
Mr. Michael Wilson, Ashgabad
Monitor
Mr. Pieter Melissen, Tashkent

3. CONSULTANT & SUB-CONSULTANTS


BCEOM

Mr. Andr Merrien, Port Engineer


Mr. Robert Gould, Environmentalist
PORT OF MARSEILLES AUTHORITY

Mr. Jean-Michel Bocognano, Port Engineer


Mr. Patrick Durel, Port Economist
Mr. Christian Montfort, Oil Traffic Expert
Mr. Marcel Immel, Oil Superstructure Expert
Mr. Michel Peronnet, Oil Process Expert
CASPMORNIIPROEKT, BAKU

Mrs. Tamilla Bagirova, Director


Mr. Fazil Gahramanov, Chief Engineer
AZQIPRONEFTECHIM, BAKU

Mr. Valeriy Aleksandrov, Chief Engineer

4. OTHER STAFF MET

EBRD

Mr. Christopher Ousey, London


Mrs. Lala Gouliyeva, Baku
Mr. Rufat Imamverdiyev, Baku
Mr. Kanat Aubakirov, Almaty
Mr. Batyr Hudaynazarov, Ashgabad

Kaztransoil

Mr. Kairgeldi Kabyldin, Astana

Kazakh Petroleum Association

Mr. Edward Verona, Almaty

Investconsulting

Mr. Kadyr Baikenov, Almaty

SOCAR

Mr. Gahraman Narimanogly, Baku

SOCAR

Mr. Vagif Abbasov, Baku

AIOC

Mr. Roger Davis, Baku

AIOC

Mr. Gary Reichow, Baku

Azerneftyag

Mr. Adil Ragimov, Baku

Caspian Shipping Company

Mr. Elshad Khalykov, Baku

Azerbaijan State Railways

Mr. Musa Panahov, Baku

Caspian TransCo Inc.

Mr. Nazih Elbeyli, Baku

Caspian TransCo Inc.

Mr. Bekir Vural, Baku

Caspian TransCo Inc.

Mr. Aydin Saral, Baku

Caspian TransCo Inc.

Mr. Ardic Durdu, Baku

Chevron

Mr. Haver Kambaizadeh, Baku

BP Amoco

Mr. Falk Mamedov, Baku

Elf Petroleum

Mr. Jean-Franois Daganaud, Baku

Total Oil

Mr. Patrick Lantigner, Baku

Entrepose Construction Company

Mr. Franck Le Baron, Baku

Bouygues Offshore Construction Company

Mr. Olivier Clausin, Baku

Annex 2
Photographs of Dubendi Oil Terminal (23)

fig-9.jpg (832x532x16M jpeg)

fig-8.jpg (832x544x16M jpeg)

fig-7.jpg (1752x1162x16M jpeg)

fig-6.jpg (1752x1182x16M jpeg)

fig-5.jpg (1764x1182x16M jpeg)

fig-4.jpg (796x544x16M jpeg)

fig-3.jpg (884x596x16M jpeg)

fig-23.jpg (1752x1162x16M jpeg)

fig-22.jpg (836x540x16M jpeg)

fig-2.jpg (992x393x16M jpeg)

fig-16.jpg (840x548x16M jpeg)

fig-15.jpg (2020x1332x16M jpeg)

fig-14.jpg (2020x1328x16M jpeg)

fig-12.jpg (832x532x16M jpeg)

fig-11.jpg (816x520x16M jpeg)

fig-10.jpg (840x540x16M jpeg)

fig-1.jpg (995x395x16M jpeg)

fig-21.jpg (540x824x16M jpeg)

fig-20.jpg (1536x2048x16M jpeg)

fig-19.jpg (1536x2048x16M jpeg)

fig-18.jpg (1532x1556x16M jpeg)

fig-17.jpg (540x844x16M jpeg)

fig-13.jpg (544x840x16M jpeg)

Annex 3
Financial Tables (8 sheets)

TABLE REF : situation of reference (no investment, traffic limited to 4 Mt per year)
DUBENDI OIL TERMINAL

PROJECTED PROFIT & LOSS STATEMENT AND CASH-FLOW


UNIT

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

TRAFFIC FORECAST : SITUATION OF REFERENCE


TOTAL TONNAGE

1000 t

NUMBER OF CALLS

unit

STAFF

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

4000

667

667

667

667

667

667

667

667

667

667

667

667

667

667

667

667

667

667

667

667

667

667

220

220

220

220

220

220

220

220

220

220

220

220

220

220

220

220

220

220

220

220

220

220

PROJECTED PROFIT AND LOSS STATEMENT


OPERATING REVENUES
Port dues on vessels
Handling of oil (ship->tank)
Storage of oil (tank->outside)
Additionnal revenue

unit
$/call
$/Ton
$/Ton
$/Ton

Tariff
1000
0,60
0,90

Base

Rate

TOTAL REVENUES
OPERATING EXPENSES
Salaries
Maintenance:
Old facilities
New facilities infrastructures
New facilities superstructures
Energy consumption
Overheads
Financial charges
Former Amortization
New Amortization

lump sum
5%
0
0,12
15%

$/Ton
Op. Rev

in 1000 $

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

6667

422

433

444

455

466

476

486

495

505

515

526

537

548

560

571

582

593

605

616

627

627

627

1000

1000

1000

1000

1000

1000

480
1000
0

0
480
1000
0

0
480
1000
0

0
480
1000
0

0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

480
1000
0

obsolete
0

TOTAL EXPENSES

2902

2913

2924

2935

2946

2956

2966

2975

2985

2995

3006

3017

3028

3040

3051

3062

3073

3085

3096

3107

3107

3107

GROSS OPERATING PROFIT

3764

3753

3742

3731

3720

3711

3701

3691

3682

3672

3661

3649

3638

3627

3616

3605

3593

3582

3571

3560

3560

3560

PROJECTED CASH-FLOW
INCOMES
Gross operating profit
Amortization
Grants
Loan

in 1000 $

3764
0

3753
0

3742
0

3731
0

3720
0

3711
0

3701
0

3691
0

3682
0

3672
0

3661
0

3649
0

3638
0

3627
0

3616
0

3605
0

3593
0

3582
0

3571
0

3560
0

3560
0

3560
0

3764

3753

3742

3731

3720

3711

3701

3691

3682

3672

3661

3649

3638

3627

3616

3605

3593

3582

3571

3560

3560

3560

1280

1276

1272
0

1269
0

1265
0

1262
0

1258
0

1255
0

1252
0

1248
0

1245
0

1241
0

1237
0

1233
0

1229
0

1226
0

1222
0

1218
0

1214
0

1210
0

1210
0

1210
0

TOTAL OUTCOMES

1280

1276

1272

1269

1265

1262

1258

1255

1252

1248

1245

1241

1237

1233

1229

1226

1222

1218

1214

1210

1210

1210

CASH FLOW
Cumulative cash-flow

2484
2484

2477
4962

2470
7431

2463
9894

2455
12349

2449
14798

2443
17241

2436
19677

2430
22107

2423
24531

2416
26947

2409
29355

2401
31756

2394
34150

2386
36537

2379
38916

2372
41287

2364
43651

2357
46008

2349
48358

2349
50707

2349
53056

2484

2252

2041

1850

1677

1521

1379

1250

1134

1028

931

844

765

693

628

570

516

468

424

384

349

317

0
0

0
0

0
0

0
0

0
0

0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

TOTAL INCOMES
OUTCOMES
Taxes on profit
Foreign loan refunding
Investments

Annual cash flow discounted

Gross prof.

34%

10%

1,10

Total cash flow discounted :

FOREIGN LOAN CHARGES


Loan
Reimbursement
Remaining
Interest

23506

IN 1000 $
0

-2-

TABLE HH 1 : high traffic hypothesis, no increase in tariff, no loan


DUBENDI OIL TERMINAL

PROJECTED PROFIT & LOSS STATEMENT AND CASH-FLOW


UNIT

2001

1000 t

4000

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

TRAFFIC FORECAST : HIGH HYPOTHESIS


TOTAL TONNAGE
NUMBER OF CALLS

unit

STAFF

4750

5500

6250

7000

8000

9000

10000

11000

12000

12500

13000

13500

14000

14500

15000

15500

16000

16500

17000

17000

17000

667

792

917

1042

1167

1333

1500

1667

1833

2000

2083

2167

2250

2333

2417

2500

2583

2667

2750

2833

2833

2833

220

230

240

251

261

272

284

295

307

319

320

321

321

322

323

324

325

326

327

328

328

328

PROJECTED PROFIT AND LOSS STATEMENT


OPERATING REVENUES
Port dues on vessels
Handling of oil (ship->tank)
Storage of oil (tank->outside)
Additionnal revenue

Unit
$/call
$/Ton
$/Ton
$/Ton

tariff
1000,00
0,60
0,90
0,00

Base

Rate

TOTAL REVENUES
OPERATING EXPENSES
Salaries
Maintenance:
Old facilities
New facilities infrastructures
New facilities superstructures
Energy consumption
Overheads
Financial charges
Former Amortization
New Amortization

lump sum

Op. Rev

0,50%
5,0%
0,120
15%

in 1000 $

667
2400
3600
0

792
2850
4275
0

917
3300
4950
0

1042
3750
5625
0

1167
4200
6300
0

1333
4800
7200
0

1500
5400
8100
0

1667
6000
9000
0

1833
6600
9900
0

2000
7200
10800
0

2083
7500
11250
0

2167
7800
11700
0

2250
8100
12150
0

2333
8400
12600
0

2417
8700
13050
0

2500
9000
13500
0

2583
9300
13950
0

2667
9600
14400
0

2750
9900
14850
0

2833
10200
15300
0

2833
10200
15300
0

2833
10200
15300
0

6667

7917

9167

10417

11667

13333

15000

16667

18333

20000

20833

21667

22500

23333

24167

25000

25833

26667

27500

28333

28333

28333

422

455

488

520

553

591

630

668

707

745

764

783

802

821

841

860

879

898

917

936

936

936

1000

1000

480
1000
0

570
1188
0

1000
37
270
660
1375
0

1000
37
270
750
1563
0

1000
37
270
840
1750
0

1000
56
573
960
2000
0

1000
76
875
1080
2250
0

1000
76
875
1200
2500
0

1000
76
875
1320
2750
0

1000
83
1168
1440
3000
0

1000
90
1460
1500
3125
0

1000
90
1460
1560
3250
0

1000
90
1460
1620
3375
0

1000
90
1460
1680
3500
0

1000
90
1460
1740
3625
0

1000
90
1460
1800
3750
0

1000
90
1460
1860
3875
0

1000
90
1460
1920
4000
0

1000
90
1460
1980
4125
0

1000
90
1460
2040
4250
0

1000
90
1460
2040
4250
0

1000
90
1460
2040
4250
0

635

635

635

1133

1630

1630

1630

1995

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

obsolete
5%

TOTAL EXPENSES

2902

3212

4464

4774

5084

6312

7540

7949

8357

9431

10299

10503

10707

10911

11116

11320

11524

11728

11932

12136

12136

12136

GROSS OPERATING PROFIT

3764

4704

4703

5643

6583

7021

7460

8718

9976

10569

10534

11163

11793

12422

13051

13680

14310

14939

15568

16198

16198

16198

PROJECTED CASH-FLOW
INCOMES
Gross operating profit
Amortization
Grants
Loan

5%

TOTAL INCOMES
OUTCOMES
Taxes on profit
Foreign loan refunding
Investments-infra
Investments-super+equipment

Gross prof.

34%

TOTAL OUTCOMES
ANNUAL CASH FLOW
Cumulative cash-flow
Annual cash flow discounted

10%

34183

Situation of reference
ANNUAL CASH FLOW REF
Cumulative cash-flow ref
DIFFERENTIAL :
ANNUAL CASH FLOW DIF
Annual cash flow discounted

10%

Total cash flow discounted

10%

FOREIGN LOAN CHARGES


Loan
Reimbursement
Remaining
Interest

IN 1000 $

1,10

in 1000 $

3764
0

4704
0

4703
635

5643
635

6583
635

7021
1133

7460
1630

8718
1630

9976
1630

10569
1995

10534
2360

11163
2360

11793
2360

12422
2360

13051
2360

13680
2360

14310
2360

14939
2360

15568
2360

16198
2360

16198
2360

16198
2360

3764

4704

5338

6278

7218

8154

9090

10348

11606

12564

12894

13523

14153

14782

15411

16040

16670

17299

17928

18558

18558

18558

1280

1599

1599
0

1918
0

2387
0
3900
6050

2964
0

3392
0
1450
5850

3594
0
1450
5850

3582
0

3795
0

4009
0

4223
0

4437
0

4651
0

4865
0

5079
0

5293
0

5507
0

5507
0

5507
0

3650
2700

2238
0
3900
6050

2536
0

3650
2700
7630

7949

1599

1918

12188

12337

2536

2964

10692

10894

3582

3795

4009

4223

4437

4651

4865

5079

5293

5507

5507

5507

-3866
-3866

-3245
-7111

3739
-3372

4359
987

-4971
-3984

-4184
-8167

6553
-1614

7384
5770

914
6684

1671
8355

9312
17667

9728
27395

10143
37538

10558
48096

10974
59070

11389
70459

11804
82264

12220
94484

12635
107119

13051
120169

13051
133220

13051
146270

-3866

-2950

3090

3275

-3395

-2598

3699

3789

426

709

3590

3410

3232

3058

2890

2726

2569

2418

2273

2134

1940

1764

2484
2484

2477
4962

2470
7431

2463
9894

2455
12349

2449
14798

2443
17241

2436
19677

2430
22107

2423
24531

2416
26947

2409
29355

2401
31756

2394
34150

2386
36537

2379
38916

2372
41287

2364
43651

2357
46008

2349
48358

2349
50707

2349
53056

-6350

-5722

1269

1896

-7426

-6633

4111

4948

-1516

-753

6896

7319

7742

8165

8587

9010

9433

9856

10278

10701

10701

10701

-6350

-5202

1049

1425

-5072

-4118

2320

2539

-707

-319

2659

2565

2467

2365

2261

2157

2053

1950

1849

1750

1591

1446

IRR

14,6%

0
0

0
0

0
0

0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

10676

Rate of return :

0
8,0%

0
0

0
0

-3-

TABLE HH 2 : high traffic hypothesis, increased tariff (+ USD 0.45 per tonne), no loan
DUBENDI OIL TERMINAL

PROJECTED PROFIT & LOSS STATEMENT AND CASH-FLOW


UNIT

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

TRAFFIC FORECAST : HIGH HYPOTHESIS


TOTAL TONNAGE
NUMBER OF CALLS

1000 t

4000

4750

5500

6250

7000

8000

9000

10000

11000

12000

12500

13000

13500

14000

14500

15000

15500

16000

16500

17000

17000

17000

unit

667

792

917

1042

1167

1333

1500

1667

1833

2000

2083

2167

2250

2333

2417

2500

2583

2667

2750

2833

2833

2833

220

230

240

251

261

272

284

295

307

319

320

321

321

322

323

324

325

326

327

328

328

328

STAFF

PROJECTED PROFIT AND LOSS STATEMENT


OPERATING REVENUES
Port dues on vessels
Handling of oil (ship->tank)
Storage of oil (tank->outside)
Additionnal revenue

Unit
$/call
$/Ton
$/Ton
$/Ton

tariff
1000,00
0,60
0,90
0,45

Base

Rate

TOTAL REVENUES
OPERATING EXPENSES
Salaries
Maintenance:
Old facilities
New facilities infrastructures
New facilities superstructures
Energy consumption
Overheads
Financial charges
Former Amortization
New Amortization

in 1000 $

667
2400
3600
1800

792
2850
4275
2138

917
3300
4950
2475

1042
3750
5625
2813

1167
4200
6300
3150

1333
4800
7200
3600

1500
5400
8100
4050

1667
6000
9000
4500

1833
6600
9900
4950

2000
7200
10800
5400

2083
7500
11250
5625

2167
7800
11700
5850

2250
8100
12150
6075

2333
8400
12600
6300

2417
8700
13050
6525

2500
9000
13500
6750

2583
9300
13950
6975

2667
9600
14400
7200

2750
9900
14850
7425

2833
10200
15300
7650

2833
10200
15300
7650

2833
10200
15300
7650

8467

10054

11642

13229

14817

16933

19050

21167

23283

25400

26458

27517

28575

29633

30692

31750

32808

33867

34925

35983

35983

35983

422

455

488

520

553

591

630

668

707

745

764

783

802

821

841

860

879

898

917

936

936

936

1000

1000

480
1270
0

570
1508
0

1000
37
270
660
1746
0

1000
37
270
750
1984
0

1000
37
270
840
2223
0

1000
56
573
960
2540
0

1000
76
875
1080
2858
0

1000
76
875
1200
3175
0

1000
76
875
1320
3493
0

1000
83
1168
1440
3810
0

1000
90
1460
1500
3969
0

1000
90
1460
1560
4128
0

1000
90
1460
1620
4286
0

1000
90
1460
1680
4445
0

1000
90
1460
1740
4604
0

1000
90
1460
1800
4763
0

1000
90
1460
1860
4921
0

1000
90
1460
1920
5080
0

1000
90
1460
1980
5239
0

1000
90
1460
2040
5398
0

1000
90
1460
2040
5398
0

1000
90
1460
2040
5398
0

635

635

635

1133

1630

1630

1630

1995

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

TOTAL EXPENSES

3172

3533

4835

5196

5557

6852

8148

8624

9100

10241

11143

11381

11619

11856

12094

12332

12570

12808

13045

13283

13283

13283

GROSS OPERATING PROFIT

5294

6521

6806

8033

9260

10081

10902

12543

14183

15159

15315

16136

16956

17777

18597

19418

20239

21059

21880

22700

22700

22700

lump sum

Op. Rev

0,50%
5,0%
0,120
15%

obsolete
5%

PROJECTED CASH-FLOW
INCOMES
Gross operating profit
Amortization
Grants
Loan

5%

TOTAL INCOMES
OUTCOMES
Taxes on profit
Foreign loan refunding
Investments-infra
Investments-super+equipment

Gross prof.

34%

TOTAL OUTCOMES
ANNUAL CASH FLOW
Cumulative cash-flow
Annual cash flow discounted

10%

56901

Situation of reference
ANNUAL CASH FLOW REF
Cumulative cash-flow ref
DIFFERENTIAL :
ANNUAL CASH FLOW DIF
Annual cash flow discounted

10%

Total cash flow discounted

10%

FOREIGN LOAN CHARGES


Loan
Reimbursement
Remaining
Interest

IN 1000 $

in 1000 $

5294
0

6521
0

6806
635

8033
635

9260
635

10081
1133

10902
1630

12543
1630

14183
1630

15159
1995

15315
2360

16136
2360

16956
2360

17777
2360

18597
2360

19418
2360

20239
2360

21059
2360

21880
2360

22700
2360

22700
2360

22700
2360

5294

6521

7441

8668

9895

11214

12532

14173

15813

17154

17675

18496

19316

20137

20957

21778

22599

23419

24240

25060

25060

25060

1800

2217

2314
0

2731
0

3428
0
3900
6050

4265
0

4822
0
1450
5850

5154
0
1450
5850

5207
0

5486
0

5765
0

6044
0

6323
0

6602
0

6881
0

7160
0

7439
0

7718
0

7718
0

7718
0

3650
2700

3148
0
3900
6050

3707
0

3650
2700
8150

8567

2314

2731

13098

13378

3707

4265

12122

12454

5207

5486

5765

6044

6323

6602

6881

7160

7439

7718

7718

7718

-2856
-2856

-2046
-4902

5127
225

5937
6162

-3203
2959

-2164
795

8825
9620

9908
19529

3691
23220

4700
27920

12468
40388

13010
53397

13551
66948

14093
81041

14634
95675

15176
110851

15717
126569

16259
142828

16801
159628

17342
176971

17342
194313

17342
211655

-2856

-1860

4237

4460

-2188

-1344

4982

5085

1722

1993

4807

4560

4318

4082

3854

3633

3421

3217

3022

2836

2578

2343

2484
2484

2477
4962

2470
7431

2463
9894

2455
12349

2449
14798

2443
17241

2436
19677

2430
22107

2423
24531

2416
26947

2409
29355

2401
31756

2394
34150

2386
36537

2379
38916

2372
41287

2364
43651

2357
46008

2349
48358

2349
50707

2349
53056

-5340

-4523

2657

3474

-5659

-4613

6383

7472

1261

2277

10052

10601

11150

11699

12248

12797

13346

13895

14444

14993

14993

14993

-5340

-4112

2196

2610

-3865

-2864

3603

3834

588

966

3875

3716

3553

3389

3225

3063

2904

2749

2598

2451

2229

2026

IRR

25,4%

0
0

0
0

0
0

0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

33395

Rate of return :

0
8,0%

0
0

0
0

-4-

TABLE HH 3 : high traffic hypothesis, no tariff increase, loan (USD 11.55 million)
DUBENDI OIL TERMINAL

PROJECTED PROFIT & LOSS STATEMENT AND CASH-FLOW


UNIT

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

TRAFFIC FORECAST : HIGH HYPOTHESIS


TOTAL TONNAGE
NUMBER OF CALLS

1000 t

4000

4750

5500

6250

7000

8000

9000

10000

11000

12000

12500

13000

13500

14000

14500

15000

15500

16000

16500

17000

17000

17000

unit

667

792

917

1042

1167

1333

1500

1667

1833

2000

2083

2167

2250

2333

2417

2500

2583

2667

2750

2833

2833

2833

220

230

240

251

261

272

284

295

307

319

320

321

321

322

323

324

325

326

327

328

328

328

STAFF

PROJECTED PROFIT AND LOSS STATEMENT


OPERATING REVENUES
Port dues on vessels
Handling of oil (ship->tank)
Storage of oil (tank->outside)
Additionnal revenue

Unit
$/call
$/Ton
$/Ton
$/Ton

tariff
1000,00
0,60
0,90

Base

Rate

TOTAL REVENUES
OPERATING EXPENSES
Salaries
Maintenance:
Old facilities
New facilities infrastructures
New facilities superstructures
Energy consumption
Overheads
Financial charges
Former Amortization
New Amortization

in 1000 $

667
2400
3600
0

792
2850
4275
0

917
3300
4950
0

1042
3750
5625
0

1167
4200
6300
0

1333
4800
7200
0

1500
5400
8100
0

1667
6000
9000
0

1833
6600
9900
0

2000
7200
10800
0

2083
7500
11250
0

2167
7800
11700
0

2250
8100
12150
0

2333
8400
12600
0

2417
8700
13050
0

2500
9000
13500
0

2583
9300
13950
0

2667
9600
14400
0

2750
9900
14850
0

2833
10200
15300
0

2833
10200
15300
0

2833
10200
15300
0

6667

7917

9167

10417

11667

13333

15000

16667

18333

20000

20833

21667

22500

23333

24167

25000

25833

26667

27500

28333

28333

28333

422

455

488

520

553

591

630

668

707

745

764

783

802

821

841

860

879

898

917

936

936

936

1000

1000

480
1000
0

570
1188
320

1000
37
270
660
1375
612

1000
37
270
750
1563
612

1000
37
270
840
1750
612

1000
56
573
960
2000
924

1000
76
875
1080
2250
924

1000
76
875
1200
2500
863

1000
76
875
1320
2750
802

1000
83
1168
1440
3000
740

1000
90
1460
1500
3125
648

1000
90
1460
1560
3250
556

1000
90
1460
1620
3375
463

1000
90
1460
1680
3500
371

1000
90
1460
1740
3625
278

1000
90
1460
1800
3750
186

1000
90
1460
1860
3875
94

1000
90
1460
1920
4000
62

1000
90
1460
1980
4125
31

1000
90
1460
2040
4250
0

1000
90
1460
2040
4250
0

1000
90
1460
2040
4250
0

635

635

635

1133

1630

1630

1630

1995

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

2360

TOTAL EXPENSES

2902

3532

5076

5386

5696

7236

8464

8812

9159

10171

10947

11059

11171

11282

11394

11506

11617

11790

11963

12136

12136

12136

GROSS OPERATING PROFIT

3764

4384

4091

5031

5971

6097

6536

7855

9174

9829

9886

10608

11329

12051

12773

13494

14216

14877

15537

16198

16198

16198

9886
2360

10608
2360

11329
2360

12051
2360

12773
2360

13494
2360

14216
2360

14877
2360

15537
2360

16198
2360

16198
2360

16198
2360

lump sum

Op. Rev

0,50%
5,0%
0,120
15%

obsolete
5%

PROJECTED CASH-FLOW
INCOMES
Gross operating profit
Amortization
Grants
Loan

5%

TOTAL INCOMES
OUTCOMES
Taxes on profit
Foreign loan refunding
Investments-infra
Investments-super+equipment

Gross prof.

34%

TOTAL OUTCOMES
ANNUAL CASH FLOW
Cumulative cash-flow
Annual cash flow discounted

10%

36989

Situation of reference
ANNUAL CASH FLOW REF
Cumulative cash-flow ref
DIFFERENTIAL :
ANNUAL CASH FLOW DIF
Annual cash flow discounted

10%

Total cash flow discounted

10%

FOREIGN LOAN CHARGES


Loan
Reimbursement
Remaining
Interest

IN 1000 $
11 550
11 550
8,0%

3764
0

4384
0

4091
635

5031
635

5971
635

6097
1133

in 1000 $

6536
1630

7855
1630

9174
1630

9829
1995

4000

3650

3900

7764

8034

4726

5666

10506

7230

8166

9485

10804

11824

12246

12968

13689

14411

15133

15854

16576

17237

17897

18558

18558

18558

1391
0

1710
0

2030
0
3900
6050

2073
0
3900
6050

2222
765

2671
765

3119
765
1450
5850

3342
1155
1450
5850

3361
1155

3607
1155

3852
1155

4097
1155

4343
1155

4588
1155

4834
390

5058
390

5283
390

5507
0

5507
0

5507
0

1280

1491

3650
2700

3650
2700

7630

7841

1391

1710

11980

12023

2987

3436

11184

11797

4516

4762

5007

5252

5498

5743

5224

5448

5673

5507

5507

5507

134
134

194
328

3335
3663

3955
7618

-1474
6144

-4793
1350

5179
6529

6049
12578

-380
12198

27
12225

7730
19955

8206
28161

8682
36843

9159
46002

9635
55637

10111
65748

11353
77101

11789
88890

12225
101114

13051
114165

13051
127215

13051
140266

134

176

2756

2972

-1007

-2976

2923

3104

-177

11

2980

2876

2766

2653

2537

2421

2471

2332

2199

2134

1940

1764

2484
2484

2477
4962

2470
7431

2463
9894

2455
12349

2449
14798

2443
17241

2436
19677

2430
22107

2423
24531

2416
26947

2409
29355

2401
31756

2394
34150

2386
36537

2379
38916

2372
41287

2364
43651

2357
46008

2349
48358

2349
50707

2349
53056

-2350

-2284

865

1493

-3930

-7242

2736

3613

-2810

-2396

5314

5797

6281

6765

7249

7732

8981

9424

9868

10701

10701

10701

-2350

-2076

715

1121

-2684

-4497

1544

1854

-1311

-1016

2049

2032

2001

1960

1909

1851

1955

1865

1775

1750

1591

1446

IRR

19,0%

7650
612

11550
612

11550
924

765
10785
924

765
10020
863

765
9255
802

1155
8100
740

1155
6945
648

1155
5790
556

1155
4635
463

1155
3480
371

1155
2325
278

1155
1170
186

390
780
94

390
390
62

390
0
31

0
0
0

0
0
0

0
0
0

13482

Rate of return :

4000

3650

4000

7650
320

3900
7650
612

-5-

TABLE LH 1 : low traffic hypothesis, no increase in tariff, no loan


DUBENDI OIL TERMINAL

PROJECTED PROFIT & LOSS STATEMENT AND CASH-FLOW


UNIT

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

TRAFFIC FORECAST : LOW HYPOTHESIS


TOTAL TONNAGE
NUMBER OF CALLS

1000 t

4000

4000

4000

4000

4000

4400

4800

5200

5600

6000

6200

6400

6600

6800

7000

7200

7400

7600

7800

8000

8000

8000

unit

667

667

667

667

667

733

800

867

933

1000

1033

1067

1100

1133

1167

1200

1233

1267

1300

1333

1333

1333

220

217

214

212

209

213

217

221

225

229

229

229

229

229

229

229

229

229

229

229

229

229

STAFF

PROJECTED PROFIT AND LOSS STATEMENT


OPERATING REVENUES
Port dues on vessels
Handling of oil (ship->tank)
Storage of oil (tank->outside)
Additionnal revenue

Unit
$/call
$/Ton
$/Ton
$/Ton

tariff
1000,00
0,60
0,90

Base

Rate

TOTAL REVENUES
OPERATING EXPENSES
Salaries
Maintenance:
Old facilities
New facilities infrastructures
New facilities superstructures
Energy consumption
Overheads
Financial charges
Former Amortization
New Amortization

in 1000 $

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

733
2640
3960
0

800
2880
4320
0

867
3120
4680
0

933
3360
5040
0

1000
3600
5400
0

1033
3720
5580
0

1067
3840
5760
0

1100
3960
5940
0

1133
4080
6120
0

1167
4200
6300
0

1200
4320
6480
0

1233
4440
6660
0

1267
4560
6840
0

1300
4680
7020
0

1333
4800
7200
0

1333
4800
7200
0

1333
4800
7200
0

6667

6667

6667

6667

6667

7333

8000

8667

9333

10000

10333

10667

11000

11333

11667

12000

12333

12667

13000

13333

13333

13333

422

428

433

438

443

462

480

499

518

537

548

560

571

583

594

606

617

628

640

651

651

651

1000

1000

480
1000
0

480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
18
135
480
1000
0

1000
37
270
528
1100
0

1000
37
270
576
1200
0

1000
37
270
624
1300
0

1000
37
270
672
1400
0

1000
37
270
720
1500
0

1000
37
270
744
1550
0

1000
37
270
768
1600
0

1000
37
270
792
1650
0

1000
37
270
816
1700
0

1000
37
270
840
1750
0

1000
37
270
864
1800
0

1000
37
270
888
1850
0

1000
37
270
912
1900
0

1000
37
270
936
1950
0

1000
37
270
960
2000
0

1000
37
270
960
2000
0

1000
37
270
960
2000
0

318

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

TOTAL EXPENSES

2902

2908

2913

2918

3394

4031

4198

4365

4531

4698

4784

4869

4955

5040

5126

5211

5297

5382

5467

5553

5553

5553

GROSS OPERATING PROFIT

3764

3759

3754

3749

3273

3302

3802

4302

4802

5302

5550

5798

6045

6293

6541

6789

7037

7285

7533

7780

7780

7780

5550
635

5798
635

6045
635

6293
635

6541
635

6789
635

7037
635

7285
635

7533
635

7780
635

7780
635

7780
635

lump sum

Op. Rev

0,50%
5,0%
0,120
15%

obsolete
5%

PROJECTED CASH-FLOW
INCOMES
Gross operating profit
Amortization
Grants
Loan

3764
0

5%

TOTAL INCOMES
OUTCOMES
Taxes on profit
Foreign loan refunding
Investments-infra
Investments-super+equipment

Gross prof.

34%

3759
0

3754
0

3749
0

3273
318

3302
635

in 1000 $

3802
635

4302
635

4802
635

5302
635

3764

3759

3754

3749

3590

3937

4437

4937

5437

5937

6185

6433

6680

6928

7176

7424

7672

7920

8168

8415

8415

8415

1280

1278

1276
0

1275
0
3650
2700

1113
0
3650
2700

1123
0

1293
0

1463
0

1633
0

1803
0

1887
0

1971
0

2055
0

2140
0

2224
0

2308
0

2393
0

2477
0

2561
0

2645
0

2645
0

2645
0

TOTAL OUTCOMES

1280

1278

1276

7625

7463

1123

1293

1463

1633

1803

1887

1971

2055

2140

2224

2308

2393

2477

2561

2645

2645

2645

ANNUAL CASH FLOW


Cumulative cash-flow

2484
2484

2481
4965

2478
7443

-3876
3567

-3872
-305

2814
2509

3144
5654

3474
9128

3804
12932

4134
17067

4298
21365

4461
25826

4625
30451

4789
35240

4952
40192

5116
45307

5279
50587

5443
56030

5606
61636

5770
67406

5770
73176

5770
78946

2484

2255

2048

-2912

-2645

1748

1775

1783

1775

1753

1657

1564

1474

1387

1304

1225

1149

1077

1008

943

858

780

2484
2484

2477
4962

2470
7431

2463
9894

2455
12349

2449
14798

2443
17241

2436
19677

2430
22107

2423
24531

2416
26947

2409
29355

2401
31756

2394
34150

2386
36537

2379
38916

2372
41287

2364
43651

2357
46008

2349
48358

2349
50707

2349
53056

Annual cash flow discounted

10%

24489

Situation of reference
ANNUAL CASH FLOW REF
Cumulative cash-flow ref
DIFFERENTIAL :
ANNUAL CASH FLOW DIF
Annual cash flow discounted

10%

Total cash flow discounted

10%

FOREIGN LOAN CHARGES


Loan
Reimbursement
Remaining
Interest

IN 1000 $

-6338

-6328

365

702

1038

1375

1711

1882

2053

2224

2395

2566

2737

2908

3079

3250

3421

3421

3421

-4762

-4322

227

396

533

641

726

726

720

709

694

676

655

633

609

584

559

508

462

IRR

11,2%

0
0

0
0

0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0

0
0

0
0

983

Rate of return :

0
8,0%

0
0

0
0

-6-

TABLE LH 2 : low traffic hypothesis, slight tariff increase (+ USD 0.03 per tonne), no loan
DUBENDI OIL TERMINAL

PROJECTED PROFIT & LOSS STATEMENT AND CASH-FLOW


UNIT

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

TRAFFIC FORECAST : LOW HYPOTHESIS


TOTAL TONNAGE
NUMBER OF CALLS

1000 t

4000

4000

4000

4000

4000

4400

4800

5200

5600

6000

6200

6400

6600

6800

7000

7200

7400

7600

7800

8000

8000

8000

unit

667

667

667

667

667

733

800

867

933

1000

1033

1067

1100

1133

1167

1200

1233

1267

1300

1333

1333

1333

220

217

214

212

209

213

217

221

225

229

229

229

229

229

229

229

229

229

229

229

229

229

STAFF

PROJECTED PROFIT AND LOSS STATEMENT


OPERATING REVENUES
Port dues on vessels
Handling of oil (ship->tank)
Storage of oil (tank->outside)
Additionnal revenue

Unit
$/call
$/Ton
$/Ton
$/Ton

tariff
1000,00
0,60
0,90
0,03

Base

Rate

TOTAL REVENUES
OPERATING EXPENSES
Salaries
Maintenance:
Old facilities
New facilities infrastructures
New facilities superstructures
Energy consumption
Overheads
Financial charges
Former Amortization
New Amortization

in 1000 $

667
2400
3600
120

667
2400
3600
120

667
2400
3600
120

667
2400
3600
120

667
2400
3600
120

733
2640
3960
132

800
2880
4320
144

867
3120
4680
156

933
3360
5040
168

1000
3600
5400
180

1033
3720
5580
186

1067
3840
5760
192

1100
3960
5940
198

1133
4080
6120
204

1167
4200
6300
210

1200
4320
6480
216

1233
4440
6660
222

1267
4560
6840
228

1300
4680
7020
234

1333
4800
7200
240

1333
4800
7200
240

1333
4800
7200
240

6787

6787

6787

6787

6787

7465

8144

8823

9501

10180

10519

10859

11198

11537

11877

12216

12555

12895

13234

13573

13573

13573

422

428

433

438

443

462

480

499

518

537

548

560

571

583

594

606

617

628

640

651

651

651

1000

1000

480
1018
0

480
1018
0

1000
0
0
480
1018
0

1000
0
0
480
1018
0

1000
18
135
480
1018
0

1000
37
270
528
1120
0

1000
37
270
576
1222
0

1000
37
270
624
1323
0

1000
37
270
672
1425
0

1000
37
270
720
1527
0

1000
37
270
744
1578
0

1000
37
270
768
1629
0

1000
37
270
792
1680
0

1000
37
270
816
1731
0

1000
37
270
840
1782
0

1000
37
270
864
1832
0

1000
37
270
888
1883
0

1000
37
270
912
1934
0

1000
37
270
936
1985
0

1000
37
270
960
2036
0

1000
37
270
960
2036
0

1000
37
270
960
2036
0

318

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

TOTAL EXPENSES

2920

2926

2931

2936

3412

4051

4220

4388

4557

4725

4811

4898

4984

5071

5157

5243

5330

5416

5503

5589

5589

5589

GROSS OPERATING PROFIT

3866

3861

3856

3851

3375

3414

3924

4435

4945

5455

5708

5961

6214

6467

6720

6973

7226

7478

7731

7984

7984

7984

5708
635

5961
635

6214
635

6467
635

6720
635

6973
635

7226
635

7478
635

7731
635

7984
635

7984
635

7984
635

lump sum

Op. Rev

0,50%
5,0%
0,120
15%

obsolete
5%

PROJECTED CASH-FLOW
INCOMES
Gross operating profit
Amortization
Grants
Loan

5%

3866
0

3861
0

3856
0

3851
0

3375
318

3414
635

in 1000 $

3924
635

4435
635

4945
635

5455
635

3866

3861

3856

3851

3692

4049

4559

5070

5580

6090

6343

6596

6849

7102

7355

7608

7861

8113

8366

8619

8619

8619

1315

1313

1311
0

1309
0
3650
2700

1147
0
3650
2700

1161
0

1334
0

1508
0

1681
0

1855
0

1941
0

2027
0

2113
0

2199
0

2285
0

2371
0

2457
0

2543
0

2629
0

2715
0

2715
0

2715
0

TOTAL OUTCOMES

1315

1313

1311

7659

7497

1161

1334

1508

1681

1855

1941

2027

2113

2199

2285

2371

2457

2543

2629

2715

2715

2715

ANNUAL CASH FLOW


Cumulative cash-flow

2552
2552

2548
5100

2545
7645

-3808
3837

-3805
31

2888
2920

3225
6145

3562
9707

3899
13606

4235
17841

4402
22243

4569
26812

4736
31548

4903
36451

5070
41521

5237
46758

5404
52162

5571
57733

5738
63471

5905
69375

5905
75280

5905
81185

2552

2317

2103

-2861

-2599

1794

1821

1828

1819

1796

1697

1601

1509

1420

1335

1254

1176

1102

1032

965

878

798

2484
2484

2477
4962

2470
7431

2463
9894

2455
12349

2449
14798

2443
17241

2436
19677

2430
22107

2423
24531

2416
26947

2409
29355

2401
31756

2394
34150

2386
36537

2379
38916

2372
41287

2364
43651

2357
46008

2349
48358

2349
50707

2349
53056

TOTAL INCOMES
OUTCOMES
Taxes on profit
Foreign loan refunding
Investments-infra
Investments-super+equipment

Annual cash flow discounted

Gross prof.

10%

34%

25336

Situation of reference
ANNUAL CASH FLOW REF
Cumulative cash-flow ref
DIFFERENTIAL :
ANNUAL CASH FLOW DIF
Annual cash flow discounted

10%

Total cash flow discounted

10%

FOREIGN LOAN CHARGES


Loan
Reimbursement
Remaining
Interest

IN 1000 $

67

71

75

-6271

-6260

439

783

1126

1469

1812

1986

2161

2335

2509

2684

2858

3032

3207

3381

3555

3555

3555

67

65

62

-4712

-4276

273

442

578

685

768

766

757

744

727

707

684

660

634

608

581

528

480

IRR

12,2%

0
0

0
0

0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0
0

0
0

0
0

0
0

1830

Rate of return :

0
8,0%

0
0

0
0

-7-

TABLE LH 3 : low traffic hypothesis, no increase in tariff, loan (USD 0.4 million)
DUBENDI OIL TERMINAL

PROJECTED PROFIT & LOSS STATEMENT AND CASH-FLOW


UNIT

2001

2002

2003

2004

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

TRAFFIC FORECAST : LOW HYPOTHESIS


TOTAL TONNAGE
NUMBER OF CALLS

1000 t

4000

4000

4000

4000

4000

4400

4800

5200

5600

6000

6200

6400

6600

6800

7000

7200

7400

7600

7800

8000

8000

8000

unit

667

667

667

667

667

733

800

867

933

1000

1033

1067

1100

1133

1167

1200

1233

1267

1300

1333

1333

1333

220

217

214

212

209

213

217

221

225

229

229

229

229

229

229

229

229

229

229

229

229

229

STAFF

PROJECTED PROFIT AND LOSS STATEMENT


OPERATING REVENUES
Port dues on vessels
Handling of oil (ship->tank)
Storage of oil (tank->outside)
Additionnal revenue

Unit
$/call
$/Ton
$/Ton
$/Ton

tariff
1000,00
0,60
0,90
0,00

Base

Rate

TOTAL REVENUES
OPERATING EXPENSES
Salaries
Maintenance:
Old facilities
New facilities infrastructures
New facilities superstructures
Energy consumption
Overheads
Financial charges
Former Amortization
New Amortization

in 1000 $

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

667
2400
3600
0

733
2640
3960
0

800
2880
4320
0

867
3120
4680
0

933
3360
5040
0

1000
3600
5400
0

1033
3720
5580
0

1067
3840
5760
0

1100
3960
5940
0

1133
4080
6120
0

1167
4200
6300
0

1200
4320
6480
0

1233
4440
6660
0

1267
4560
6840
0

1300
4680
7020
0

1333
4800
7200
0

1333
4800
7200
0

1333
4800
7200
0

6667

6667

6667

6667

6667

7333

8000

8667

9333

10000

10333

10667

11000

11333

11667

12000

12333

12667

13000

13333

13333

13333

422

428

433

438

443

462

480

499

518

537

548

560

571

583

594

606

617

628

640

651

651

651

1000

1000

480
1000
0

480
1000
0

1000
0
0
480
1000
0

1000
0
0
480
1000
0

1000
18
135
480
1000
0

1000
37
270
528
1100
32

1000
37
270
576
1200
32

1000
37
270
624
1300
32

1000
37
270
672
1400
32

1000
37
270
720
1500
32

1000
37
270
744
1550
29

1000
37
270
768
1600
26

1000
37
270
792
1650
22

1000
37
270
816
1700
19

1000
37
270
840
1750
16

1000
37
270
864
1800
13

1000
37
270
888
1850
10

1000
37
270
912
1900
6

1000
37
270
936
1950
3

1000
37
270
960
2000
0

1000
37
270
960
2000
0

1000
37
270
960
2000
0

318

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

635

TOTAL EXPENSES

2902

2908

2913

2918

3394

4063

4230

4397

4563

4730

4812

4895

4977

5059

5142

5224

5306

5388

5471

5553

5553

5553

GROSS OPERATING PROFIT

3764

3759

3754

3749

3273

3270

3770

4270

4770

5270

5521

5772

6023

6274

6525

6776

7027

7278

7529

7780

7780

7780

5521
635

5772
635

6023
635

6274
635

6525
635

6776
635

7027
635

7278
635

7529
635

7780
635

7780
635

7780
635

lump sum

Op. Rev

0,50%
5,0%
0,120
15%

obsolete
5%

PROJECTED CASH-FLOW
INCOMES
Gross operating profit
Amortization
Grants
Loan

5%

TOTAL INCOMES
OUTCOMES
Taxes on profit
Foreign loan refunding
Investments-infra
Investments-super+equipment

Gross prof.

34%

3764
0

3759
0

3754
0

3749
0

3273
318

3270
635

in 1000 $

3770
635

4270
635

4770
635

5270
635

400

3764

3759

3754

3749

3990

3905

4405

4905

5405

5905

6156

6407

6658

6909

7160

7411

7662

7913

8164

8415

8415

8415

1280

1278

1276
0

1275
0
3650
2700

1113
0
3650
2700

1112
0

1282
0

1452
0

1622
0

1792
40

1877
40

1962
40

2048
40

2133
40

2219
40

2304
40

2389
40

2475
40

2560
40

2645
0

2645
0

2645
0

TOTAL OUTCOMES

1280

1278

1276

7625

7463

1112

1282

1452

1622

1832

1917

2002

2088

2173

2259

2344

2429

2515

2600

2645

2645

2645

ANNUAL CASH FLOW


Cumulative cash-flow

2484
2484

2481
4965

2478
7443

-3876
3567

-3472
95

2793
2888

3123
6011

3453
9465

3783
13248

4073
17321

4239
21560

4405
25964

4570
30535

4736
35271

4902
40172

5067
45239

5233
50472

5399
55871

5564
61435

5770
67205

5770
72976

5770
78746

2484

2255

2048

-2912

-2372

1734

1763

1772

1765

1727

1634

1544

1456

1372

1291

1213

1139

1068

1001

943

858

780

2484
2484

2477
4962

2470
7431

2463
9894

2455
12349

2449
14798

2443
17241

2436
19677

2430
22107

2423
24531

2416
26947

2409
29355

2401
31756

2394
34150

2386
36537

2379
38916

2372
41287

2364
43651

2357
46008

2349
48358

2349
50707

2349
53056

Annual cash flow discounted

10%

24564

Situation of reference
ANNUAL CASH FLOW REF
Cumulative cash-flow ref
DIFFERENTIAL :
ANNUAL CASH FLOW DIF
Annual cash flow discounted

10%

Total cash flow discounted

10%

FOREIGN LOAN CHARGES


Loan
Reimbursement
Remaining
Interest

IN 1000 $
400
400

-6338

-5928

344

681

1017

1353

1650

1823

1996

2169

2342

2515

2688

2861

3034

3208

3421

3421

3421

-4762

-4049

214

384

522

631

700

703

700

691

678

662

644

623

600

577

559

508

462

IRR

11,3%

0
0

400
0

400
32

400
32

400
32

400
32

40
360
32

40
320
29

40
280
26

40
240
22

40
200
19

40
160
16

40
120
13

40
80
10

40
40
6

40
0
3

0
0

0
0

0
0

1058

Rate of return :

400
0

8,0%

0
0

0
0

-8-

Dubendi Oil Terminal Rehabilitation - Investment cost estimates


Costs estimates in thousands USD
Short term

Medium term

Long term

Total 3 terms

A. Infrastructures
A1. Detailed design, tender docs & works supervision

470

A2. Dredging works


Dredging of navigation channel
Dredging of port basin
Sub-total A2
A3. Breakwater works
Rehabilitation of the root section
Rehabilitation of the trunk section
Rehabilitation of the head section

490

190

1150

700
500
1 200

400
400

700
900
1 600

1 500
2 500
Sub-total A3

4 000

A4. Berth works


Rehabilitation of pier n1
Rehabilitation of pier n2
Rehabilitation of pier n3
Rehabilitation of pier n5
Rehabilitation of port-vessels berth

1 500
2 500
3 000
7 000

3 000
3 000

1 600
2 000
1 200
2 300
Sub-total A4

2 800

800
2 800
300

2 300

7 270

7 790

2 890

17 950

250

700

750

1 700

50
10
30
40
130

30
20
30

20
20
30

80

70

100
50
90
40
280

A5. Shore protections inside the port basin


Total A

1 600
2 000
1 200
2 300
800
7 900
300

B. Superstructures
B1. Detailed design, tender docs & works supervision
B2. Road works
Road on top of the breakwater
Roads in lower tank-farm area
Roads in upper tank-farm area
Access road to pier n3
Sub-total B2
B3. Lower tank-farm
Block n13a
Block n13b
Block n14
Extension of block 14

30

1 000
1 500

20
Sub-total B3

B4. Upper tank-farm


Block n4
Block n6
Block n7
Block n8
Block n9
Block n11
Block n12

1 500

50

1 500
3 000

100

2 000

2 500

2 000
100

2 000
2 000
2 000

100

2 000

Sub-total B4

300

6 000

1 000
7 000

Sub-total B5
B6. Rehabilitation of the Waste Water Treatment Plant

150
500
50
700
300

50
500
250
800

50
500
250
800

B5. Pipes and pumps


Pipes & pumps in the berthing areas
Pipes & pumps in the lower tank-farm
Pipes & pumps in the upper tank-farm

1 030
1 500
1 520
1 500
5 550
2 100
2 000
2 100
2 000
2 000
2 100
1 000
13 300
250
1 500
550
2300
300

B7. Electricity networks

2 000

500

500

3 000

Total B

3 730

11 080

11 620

26 430

C1. Detailed design, tender docs & works supervision

110

70

185

C2. Refurbishment and equipment of buildings


In lower area
In upper area
Sub-total C2
C3. Boiler unit in upper storage area

80
100
180
220

150
180
330

C. Other equipment

C4. Supply of environmental protection equipment


C5. Supply & installation of safety equipment
Total C
Total A + B + C

-1-

230
280
510
220

200

150

1 000

500

100

450

1 710

1 050

105

2 865

12 710

19 920

14 615

47 245

1 500

Annex 4
Maps and Drawings

!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!
!

Traceca map
Global "oil map"
Dubendi Channel and port layout
Dubendi Marine and land facilities
Piers n1 & n2 Oil transfer scheme
Pier n3 Oil transfer scheme
Existing power supply scheme
Directory scheme for power supply
Piping and power supply diagrams
Short-term flow diagram
Medium-term flow diagram
Long-term flow diagram
Breakwater head
Breakwater root and trunk
Pier cross-section
Pier longitudinal section
Port-vessel berth

You might also like