You are on page 1of 11

SAT REPORT

PSS
11kV/415V substation

CLIENT
PROJECT NO
PSS
PROJECT NAME
(A)

: ADDC
:
: 01
:

CONSULTANT

CONTRACTOR
SHEET NO
DATE

:
: 1 of 8
:

General Check:

Sl.no
1
2
3
4
5
6
7
8
9
10

Description

Remarks

Earthing Circuit of Cubic


Label of Panels
Marking of equipment and terminals
Tightening of connection
Visual inspection of the panel and components
Voltage presence indication
Lamp Test
Scheme & Loop wiring verification check
MCBs rating as per drawing and working properly
SF6 Pressure Gauge
(B) Operation Check:

Sl.no
1
2
3
4
5

Description

Remarks

Mechanical opening and closing of C.B


Mechanical opening and closing of Ring Switch
C.B protection Trip indication
Mechanical opening and closing of Earth Switch
Pull to Trip Bar
(C) Interlock Check

Sl.no
1

Description

Remarks

Mechanical Interlock between CB & Ring Switch

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

Mechanical interlock between Earth Switch & Ring Switch

CLIENT
PROJECT NO
PSS
PROJECT NAME

: ADDC
:
: 01
:

CONTRACTOR
SHEET NO
DATE

CONSULTANT

:
: 2 of 8
:

NAME PLATE
Sl .No

Make & Type

Rated Voltage

Normal current

1) INSULATION RESISTANCE TEST BEFORE HI-POT


Test Connection
R: Y+B+E
Y: R+B+E
B: R+Y+E

Applied Test Voltage dc /1Min

Measured Resistance ()

Remarks

Leakage Current (mA)

Remarks

Measured Resistance ()

Remarks

2) DIELECTRIC TEST (for 1 minute)


Test Connection
R: Y+B+E
Y: R+B+E
B: R+Y+E
With Transformer CB ON

Applied Test Voltage ac /1Min

3) INSULATION RESISTANCE TEST AFTER HI-POT


Test Connection
R: Y+B+E
Y: R+B+E
B: R+Y+E

Applied Test Voltage dc /1Min


5kV

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

Test Equipment used:


INSTRUMENT NAME
SL. NO.
MAKE & MODEL
CALIB. DUE

CLIENT
PROJECT NO
PSS
PROJECT NAME

MEGGER

: ADDC
:
: 01
:

HIGH VOLTAGE TESTER

CONTRACTOR
SHEET NO
DATE

CONSULTANT

:
: 3 of 8
:

4) PROTECTION RELAY TEST


Relay Make/ Type
CT Ratio

SCHNEIDER ELECTRIC /
MICOM P124
100 / 1A

I>
I>>

t>
t>>

Transformer Rate

1500 kVA

Relay Sl. No.


Io >
Io >>

to >
to >>

(a)OVERCURRENT (I>)
Set
Value
(A)

APPLIED
CURRENT (A)

PICK UP CURRENT (A)


R-Y

Y-B

B-R

CALCULATED TIME
(sec)

MEASURED TIME (sec)


R-Y

Y-B

B-R

2 x Is
5 x Is
(b) OVERCURRENT (I>>)
Set
Value
(A)

APPLIED
CURRENT (A)

PICK UP CURRENT (A)


R-Y

Y-B

B-R

CALCULATED TIME
(sec)
Y-B

MEASURED TIME (sec)


R-Y

Y-B

B-R

2 x Is
(c) EARTH FAULT (Ie>)

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

Set
Value
(A)

APPLIED
CURRENT (A)

PICK UP
CURRENT (A)

CALCULATED TIME (sec)

MEASURED TIME (sec)

CALCULATED TIME (sec)

MEASURED TIME (sec)

2 x Is
5 x Is
(d) EARTH FAULT (Ie>>)
Set
Value
(A)

APPLIED
CURRENT (A)

PICK UP
CURRENT (A)

2 x Is

CLIENT
PROJECT NO
PSS
PROJECT NAME

Fault Record:
Record No
Fault

: ADDC
:
: 01
:

CONTRACTOR
SHEET NO
DATE

CONSULTANT

:
:

Threshold
Magnitude

Remarks:
Trip Test: Connected through (1) Primary Injection
1. Phase fault:

:
: 4 of 8
:

:
:

(2) Secondary Injection


2. Earth Fault :

Relay Final Setting:


In

: 1A

kVA

: 1500

CT Ratio

: 100/1 A

O/C Curve: IEC SI


I>
I>>

t>
t>>

E/F Curve: IEC SI


Ie>
Ie>>

t>
t>>

5) CT RATIO TEST

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

Injected Current (A)


RY / RN

PROTECTIO
N CT

YB / YN

BR / BN

--

--

--

--

--

E/F

--

--

---

----

--

--

---

CT RATIO
FOR
100 / 1 A

Measured Current (A)

--

---

----

--

--

POLARITY CHECKS:

R - Phase

CLIENT
PROJECT NO
PSS
PROJECT NAME

6)

Observations of Polarity Checks for Protection CT


Y - Phase

: ADDC
:
: 01
:

Remarks
B - Phase

CONTRACTOR
SHEET NO
DATE

CONSULTANT

:
: 5 of 8
:

Metering core- Y-Phase

Make/Type
CT Ratio

Sl .No
VA/Cl

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

Ratio Test
Core No. Ref
S1-S2

CT Ratio (A)

Primary injected current (A)

Secondary measured current (A)

7) Earth Fault Indicator:


Make/Type
Set trip level
Pick up Value
Reset time

:
:
:
: 4 hrs

Test Equipment used:


INSTRUMENT NAME
SL. NO.
MAKE & MODEL
CALIB. DUE

TRIP LEVEL: 25, 50, 100 A


Serial No.
Supply
LED Indicaton

SEC IN KIT

:
:
:

MULTIMETER

8) Earth Resistance ():


TRM Body
Transformer body
Transformer neutral
Test Equipment used:
INSTRUMENT NAME
SL. NO.
MAKE & MODEL
CALIB. DUE

CLIENT
PROJECT NO
PSS
PROJECT NAME

: ADDC
:
: 01
:

DIGITAL GROUND TESTER


DGT/SP/01
Megger & DET4TC2

CONSULTANT

CONTRACTOR
SHEET NO
DATE

:
: 6 of 8
:

9) Transformer Test Report

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

Name Plate Details


Sl.No
Year of Manufacture
Rating KVA
Type of Cooling
Frequency (Hz)
Rated Voltage (kV)
Impedance Normal Tap (%)
Temperature Rise Oil/Winding 0C
Vector Group Symbol
Rated Current (A)
Oil Weight (Lit)
Total Weight (Kg)

SIEMENS TRANSFORMERS LLC


10003214
2014
1500
ONAN
50
11 / 0.415
5.75
45 / 55
Dyn11
78.7 / 2086.8
861
4350

(a) Visual Check:


Sl.No
01
02
03
04
05
06
07
08
09
10

Description

Remarks

Installing according to drawing


No Oil leakage & Oil Level position correct
All drain valves are fully closed
No visible cracks or breaks to bushing
All bushing connections are fully tightened
Main tank grounding correct
Neutral grounding is correct (fixed, tightened & insulated)
Pressure relief valve are correctly installed
Earthing of cable boxes and other removable parts
Winding temperature are correctly installed

CLIENT
PROJECT NO
PSS

: ADDC
:
: 01

CONSULTANT

Tested by ( for spaceage)


Name:
Signature:
Date:

CONTRACTOR
SHEET NO
DATE

:
: 7 of 8
:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

PROJECT NAME

(b) Insulation Resistance Test


Winding
Ref

Voltage in dc
(V)

HV to Earth
HV to LV
LV to Earth

5000
2500
1000

15sec

Insulation Resistance (G)


60sec

Polarisation Index (PI) Value =


(60Sec/ 15Sec)

(c) Winding Resistance


H.V Side
Taps

Resistance ()
1V-1W

1U-1V

1W-1U

1
2
3
4
5
L.V Side ()
Taps
2u-2v

2v-2w

Resistance ()
2w-2u

2u-2n

2v-2n

2w-2n

(d) Magnetising Current Test

As per the test result attached

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

CLIENT
PROJECT NO
PSS
PROJECT NAME

: ADDC
:
: 01
:

CONTRACTOR
SHEET NO
DATE

CONSULTANT

:
: 8 of 8
:

(e) Magnetising Core Balance test


Applied Voltage
r-n

y-n
-

b-n

r-n

y-n

b-n

Remarks

Measured Voltage

(f) Turns Ratio Test

As per the test result attached


(g) Vector Group Test

As per the test result attached


(h) Functional Checks of Supervisory Equipments:
Sl.No
01
02
03
04
05
06

Checks
Vertical Oil Level Switch
Oil Temperature Indicator
Pressure relief valve
OTI Alarm Setting Temperature (
OTI Trip Setting Temperature (
OTI alarm/trip contacts

Remarks

C)
C)

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

SNAG LIST

CLIENT
PROJECT NO
PSS
PROJECT NAME

: ADDC
:
: 01
:

CONSULTANT

CONTRACTOR
SHEET NO
DATE

:
: 9 of 9
:

MDB TESTING
(A) General Check:
Sl.no
1
2
3
4
5
6
7
8
9
10

Description

Remarks

Earthing Circuit of Cubic


Label of Panels
Marking of equipment and terminals
Tightening of connection
Visual inspection of the panel and components
Check function of CBs draw out rack
Check selector switches
Check manual operation of CBs
MCBs rating as per drawing and working properly
Check Fuses
(B) Operation Check:

Sl.no
1
2
3
4
5

Description

Remarks

Verify CBs open/close manual


Simulate external control signal and verify CBs open/close automatically
Verify operation of all selector switches and push buttons
Verify operation of all instrumentation, ammeters, voltmeters, lamps etc.
Verify operation of safety shutdowns, UVR, ELR

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

SAT REPORT
PSS
11kV/415V substation

7
8
9
10
11

Verify test, rack in and rack out position


Verify spring charge status and indication
Verify auto and manual status
Verify CBs open, on and trip status
Verify remote start and stop commands

Tested by ( for spaceage)


Name:
Signature:
Date:

Witnessed by (ADDC)

You might also like