Professional Documents
Culture Documents
INFRASTRUCTURE DIVISION
TRACK AND RIGHT OF WAY DEPARTMENT
Technical Specifications
for
Mechanical Trackside Lubricator
for
Various Types of Rails
No. E-01-0019
June 2013
Contents
1
2
3
4
5
6
7
8
9
10
SCOPE
REFERENCE DOCUMENTS
DEFINITIONS
ISR SUPERSTRUCTURE AND LOCAL CONDITIONS
MECHNICAL TRACKSIDE LUBRICATOR - REQUIRMENTS
LUBRICANT FILLER EQUIPMENT - REQUIREMENTS
MANUFACTURE'S TECHNICAL DRAWINGS
MANUFACTURE
MARKING LABELING
MANUFACTURING QUALIFICATION MANAGEMENT
LIST OF DOCUMENTS TO BE SUBMITTED WITH BIDDER'S
11
PROPOSAL
LIST OF DOCUMENTS TO BE DELIVERED WITH EVERY
12
ISR ORDER
13 PACKING
14 WARRANTY AND TRAINING
APPENDIXES ISRAEL CLIMATE AND ENVIRONEMENTAL
APPENDIX A
CONDITIONS
APPENDIX B DSB 82-1 WHEEL PROFILE DRAWING
APPENDIX C RAIL HEAD PERMISSIBLE WEAR
APPENDIX D LUBRICANT REQUIREMENT
APPENDIX E ISR LOADING GAUGE
LIST OF DOCUMENTS TO BE SUBMITTED WITH
APPENDIX F
BIDDER'S PROPOSAL
2
2
2
2
3
4
4
5
5
5
6
7
7
8
9
10
11
12
14
1.
1.1
SCOPE
This technical specification pertains to the technical requirements for
mechanical trackside lubricators ("MTL") manufacturing, supply and
installation. To reduce friction and wear at wheel/rail interface by lubricant
the rail gauge side corner and rail gauge side face.
1.2
1.3
The MTLs shall be supplied with installation and adjustment tools for
efficiently assembled the MTLs to the rails.
2.
3.
DEFINITIONS
Gauge side face:
ISR:
4.
4.1
4.2
4.3
4.4
4.5
The MTL shall be designed for installation on rail types: 60E1, 60E2, 54E1
and 50E6 (rail types in accordance with EN13674-1).
4.6
The MTL shall be designed for efficient operation with ISR wheels type ISR using wheels of several diameters the wheels profile types are in
accordance with UIC 510-2, and DSB82-1 wheel type (IC3 trains) see
appendix B.
4.7
4.8
4.9
5.
5.1
5.2
The MTL shall apply lubricant to take effect in the active interface applied
in areas "A" and "B" of the rail throughout the intended length of the rail to
be lubricated.
5.3
The MTL shall work independently and do not require external energy
source, and shall provide uniform amount of lubricant direct to areas "A"
and "B" by each passing wheel.
5.4
5.5
The MTL pumping lubricant quantity per stroke shall be 0.1-0.15 gram.
5.6
The MTL shall be installed to the track without rail drilling and shall be
conformed to ISR nominal track gauge.
5.7
5.8
The MTL shall include a means of checking and adjusting the amount and
position of lubricant dispensed.
5.9
The means of adjusting the height of the lubricant application unit shall be
separate from the means of installing to the rail.
5.10 The MTL shall be on a safe distance from the on-track vehicles, in such a
way that it cannot be damaged as a result of rail maintenance work (see
ISR Loading Gauge appendix E).
5.11 The MTL components shall be designed and manufactured from materials
which the nature and main characteristics and chemical composite shall be
stated and their fluffiness to the requirements of the relevant standards and
could not be modified without approved by ISR.
5.12 The means shall be provided in the MTL to indicate the quantity of
lubricant remaining in the lubricant reservoir.
5.13 All parts which are non-metallic shall be made of hot weather resistant
materials, suitable for use at temperature of up to 70C and under high
corrosion conditions. Plastic parts shall be UV protected. Israel climate
condition should be considered (see appendix A).
5.14 The MTL reservoir shall be cleaned and corrosion protected before
painting. The painting shall be done with two layers - premier layer and
second layer. The second paint layer shall have high resistance to the
environment condition including UV sun radiation, and corrosion
environment, and high resistance to wear.
All other metallic parts shall be corrosion protected.
6.
6.1
6.2
The lubricant filler equipment shall enable filling the lubricator reservoir
efficiently. It shall include all means to pump lubricant from tanks (pails,
kegs, drums) with different sizes and capacities.
7.
7.1
7.2
The manufacturer shall submit, together with its proposal, a complete set of
technical drawings and material main characteristics of the lubricant filler
equipment.
The assembled lubricant filler equipment,
The operation of lubricant filler equipment drawing.
7.3
The manufacturer shall submit, together with its proposal, a complete set of
technical drawings and material main characteristics of the installation and
adjustment tools.
8.
8.1
MANUFACTURE
The MTL shall manufactured in accordance with the technical drawings
submitted by the manufacturer and approved by ISR, and must present a
clean surface, smooth and free from blow-holes, flaws, cracks, folds or
other faults.
9.
9.1
MARKING LABELING
Each MTL shall be inscribed with at least the following marks:
The manufacturer mark,
The last two figures of the manufacturing year,
The product identification type.
9.2
9.3
11.
11.12 The manufacturer shall declare in a signed document the estimate for the
MTL and it components life cycle.
11.13 The manufacturer shall submit the nature and main characteristics of the
metallic and non-metallic material and chemical composite for every
component.
11.14 The manufacturer shall submit 2 magnetic copies of all the manufacturing
technical drawings and the relevant technical descriptions of MTL and its
components, the lubricant filler equipment and the installation and
adjustment tool.
12.
12.1 Each order shall be delivered with certificate that each components has
manufactured according to technical drawings submitted and the
requirements of this technical specification.
13.
PACKING
13.1 The MTL components shall be packed in wooden boxes and will put in
container. The wooden box arrangement shall enable easy and safe
unpackaged and storage the goods.
13.2 The dimensions of the wooden shall be according to EN standard, to enable
maximum effective storage capacity in containers.
It shall be possible to put at least 3 wooden boxes one on the other.
Each package gross weight shall not exceed 1 tone.
Each package shall be labeled with the following details:
o Component name and type;
o Production batch number;
o Date of manufacture;
o Component barcode;
o Component quantity in box;
o Gross and net weight;
o Manufacturer recognition number or name;
o ISR recognition number;
o ISR order number;
o Ordinal number on the packing list.
The labeling shall be with black letters and shall be on 3 spots on the
package (one on top of the package and the two others on the sides).
A.2
Maximum Daily
Value*
560
260
143
350
A.3
A.4
Wet
22.0
7.9
1.7
SO4*
Dry
5.3
1.9
1.3
Average
71
21
84
100
Wet
7.0
2.0
1.4
10
Maximal
vertical wear
[mm]
13
14
17
Minimal
height of the
rail [mm]
140
145
155
11
Height of
the new rail
[mm]
153
159
172
Type of rail
(EN 13674-1)
50E6 (U-50)
54E1 (UIC-54)
60E1 (UIC-60), 60E2
unit
-
Test method
Visual
ISO 2049 or equivalent
ISO 6743-99
values
Homogenous
Homogenous
1 or 1.5
0.1 mm
290-340
Drop point
Flash point
Water content
% mass
Water resistance @ 40 C
Adhesion to sheet steel
(0.05 mm, 24 h @ 60 C)
Volatile components
Level
Stage
EN16028, Annex D
% mass
EN16028, Annex E
% mass
10
7% maximum
by weight for
NLGI No. 1
grease
Rating
Grade
150
200
1.0
0; 0
1
+15/-0
IRHD
150
mPas
400
mPas
4000
12
standard
mm
kg
DIN 51350-4
visual
EN16028, Annex B
13
0.8
Weld load not
less than 315kg
No corrosion
after 72 h
>60 after 28
days
14
The bidder shall supply technical description for the Lubricant filler
equipments. And the means to pump lubricant from tanks (pails, kegs,
drums) with different sizes and capacities.
F.2.
The bidder shall supply technical description for the installation and
adjustment tools.
F.3.
The bidder shall supply technical description for the nature and main
characteristics and chemical composite of the MTL components materials.
And stated their fluffiness to the requirements of the relevant standards.
F.4.
the bidder shall submit MTL reservoir paint parameters and painting
procedure.
F.5
the bidder shall submit the corrosion protection process for the metallic
parts.
15