You are on page 1of 207

The Cost Model Template

Introduction

You may change this template to suit your own taste, or your organisations conventions, as you wish. However, I suggest
as supplied, or there is a risk that the model will show incorrect calculations. You will need a reasonable level of familiarity
model works, although there are no macros.
Basic Features
At the bottom of the screen, tabs give access to the individual sheets i.e.

Header general information about the project.


Tasks the list of tasks with the base estimate, task contingency and project-wide contingency values. Also, when ea
StaffCosts the staff needed for the project, when they will be utilised, and their daily rates.
CapitalCosts items other than staff that will be purchased by the project, and when these costs will be incurred.
OngoingCosts depreciation of capital cost items, and the running costs for the system, such as operations, data pre
RiskAnalysis project-wide risks, how they will be managed, and the contingency allowance made.
Summary all the project costs, and the final total.
Cashflow billing details, and the monthly profit and loss predicted for the project.
PriceBreakdown allocation of the cost between different elements of the project.
EarnedValue tracking of the project as it proceeds.
Scratchpad an area for defining your own variables as input to the model.

In all the sheets:

Grey cells are the background, not usually changed.


White cells are for values or text to be input by the user.
Pale yellow cells are values calculated by the spreadsheet.
Blue cells are values carried forward from other sheets, or calculations that include such values.
Bright yellow cells highlight risk or contingency values between 20% and 40%. These default limits can be found in th
Bright red cells highlight risk or contingency values greater than 40%.

A red triangle in the corner of a cell shows that there is some help or other note appended. Hold the cursor over the cell to
Microsoft Excel, the size and position of these notes is somewhat unpredictable. If the note is not completely visible, rightmanipulate the notes window until the text is fully visible. If you no longer wish to see the notes, select Tools, Options,

There are a number of checks that the model is consistent. Failed checks are shown by red figures appearing, usually in t
heading, will describe the values being compared. For fuller details, select the cell, and select Format, Conditional Form
There are a number of features of the model that are not used by all projects, so are normally in hidden rows and columns
Row" (or "Column"), Unhide. Hidden text is blue by default, so you may like to change this to black. All the hidden featur
Excel Facilities You Can Use

Some features of Excel may be used to make working within the Cost Model easer. The Freeze Panes option under Win
in view while you are working on the Task Plan. From the Customise option under View, buttons can be added to the to
columns.
Removing Rows and Columns

The workbook contains more rows and columns than will be needed for all but the largest projects. Excess rows and colum
model is complete. However, this will sometimes affect other sheets containing copies of that information a problem usu
containing the copied information must also have the corresponding rows or columns removed. As a safety measure, whe
check that all the formulae for totals are correct.

If you wish to change a sheet, you will want to restore the gridlines and row/column headers this can be done by selectin
Header Sheet

Project Name. This should show the project phase, sub-section of the overall system, or option description if there ar

Estimate Date. This is filled in automatically by the spreadsheet to distinguish between different versions of the estim

Project Start Date. This is used by some other sheets in the model to give month-by-month breakdowns of effort and

Reference Number. Your own quotation number or proposal number, if relevant.

Currency. A three letter code, such as USD or GBP to indicate what currency is being used for the estimate.
10/18/2015
Page
1 of
207

Days Per Month. The number of working days in a month, taking account of holidays, illness,
and
company
overhead

Project Summary. An expansion of the Project Name giving more detail of what the estimate covers.

Signoff. The names of the estimators, reviewers, and those approving the estimate. This area can be altered in accor
organisation.

If you wish to change a sheet, you will want to restore the gridlines and row/column headers this can be done by selectin
Header Sheet

Project Name. This should show the project phase, sub-section of the overall system, or option description if there ar

Estimate Date. This is filled in automatically by the spreadsheet to distinguish between different versions of the estim

Project Start Date. This is used by some other sheets in the model to give month-by-month breakdowns of effort and

Reference Number. Your own quotation number or proposal number, if relevant.

Currency. A three letter code, such as USD or GBP to indicate what currency is being used for the estimate.

Days Per Month. The number of working days in a month, taking account of holidays, illness, and company overhead

Project Summary. An expansion of the Project Name giving more detail of what the estimate covers.

Signoff. The names of the estimators, reviewers, and those approving the estimate. This area can be altered in accor
organisation.
Tasks Sheet

Reference. A cross-reference to the requirements document, or whatever else you are working from. If there is no su
Task. A brief description of the estimatable entity.
Notes. Remarks, usually about how the estimate was made, or any reasons why the estimate, or the contingency allo
Base Days. Your estimate for this task, taking no account of risks.
Task Contingency. The percentage contingency that you are allowing to account for risks applicable only to this task.
Project Contingency. The estimate (with task contingency), plus the contingency to be added to account for risks app

The amount of project-level contingency estimated in terms of days is carried forward from the Risk Analysis. Adjust the pr
amount allowed is the same as this.

In the Task Plan area, show the effort to be expended every month for each task. A check column shows if the total assign

You can create subtotals for project phases, subsystems etc. by revealing all the hidden rows and columns. By default, the
In the normally-hidden column labelled Category, you should assign each task to one of the ten categories by entering a
Phase 1 could be assigned as A. Then the totals for Category A at the top will show the figures for Phase 1. The label for
StaffCosts Sheet

Enter all the staff roles, plus the name of the team member who will fill each role if this is known. Also enter the daily rate f
or copied from your organisations rate book if you have one. The Average Rate is calculated by taking the total number

Hidden columns to the right of the Rate column allow two further rates to be entered for each staff member. This allows i
boundary and rates are reviewed at each year end. Enter the expected new rate and the month at which it should be appli
In the Staff Plan area, show the effort to be expended every month for each task.

You can create subtotals for specific teams, types of staff etc. The procedure is the same as described for the creation of s
CapitalCosts Sheet

Reference. A reference number. This normally just starts at 1, but could be used to record manufacturers part numbe

Item. A brief description of the capital cost item. If the item is defined elsewhere (e.g. a suppliers quotation), then jus

Supplier. The name of the supplier of the item, if known.

Notes. Any further details, such as how the cost or item contingency has been determined.

Cost. The unit cost of the item.

Quantity. The number of the items that will be needed.

Base Cost. Cost x Quantity.

Item Contingency. The contingency allowance for this item.

Project Contingency. The cost inclusive of the project-wide contingency expressed in money terms, from the Risk An

Depreciation Start Date. The month at which the depreciation should start usually when the item is delivered.

Depreciation Years. The number of years over which the item should be depreciated usually one, three or five.

Monthly Allocations. The month or months within the project timescale in which the items cost will be incurred. This m
will be received, or when the bill will be paid.

Items can either be depreciated or included in the initial project costs but not both. In the totals section, the word Warning
depreciated amounts plus the values distributed over the project months.
The amount of project-level contingency estimated in terms of money is carried forward from the Risk Analysis. Adjust the
amount allowed is the same as this.
OngoingCosts Sheet

Items on this sheet are either staff (e.g. operations or data preparation staff) or other ongoing costs (e.g. hardware mainte
time should be calculated in days per year for each role, and the appropriate rate inserted. Other items should be entered
Hidden rows in the totals section allow the ongoing costs to be uprated annually. Enter a figure for
Annual
Inflation and th
10/18/2015
Page
2 of 207
capital costs) will be increased yearly.
RiskAnalysis Sheet

depreciated amounts plus the values distributed over the project months.
The amount of project-level contingency estimated in terms of money is carried forward from the Risk Analysis. Adjust the
amount allowed is the same as this.
OngoingCosts Sheet

Items on this sheet are either staff (e.g. operations or data preparation staff) or other ongoing costs (e.g. hardware mainte
time should be calculated in days per year for each role, and the appropriate rate inserted. Other items should be entered
Hidden rows in the totals section allow the ongoing costs to be uprated annually. Enter a figure for Annual Inflation and th
capital costs) will be increased yearly.
RiskAnalysis Sheet

Risk Number. A serial number to identify the risk.

Risk. A description of the risk to the project.

Cause. The circumstances under which this risk could occur.

Prevention. The steps that could be taken in advance to prevent the risk occurring.

Trigger. The conditions under which the risk management plan will be instigated.

Plan. The actions that will be taken to manage the risk if the trigger conditions occur.

Owner. The person who is most responsible for ensuring that the risk does not occur, and who will manage the proble
(e.g. a supplier).

Probability. The probability of the risk occurring estimated as low, medium or high.

Detection. The difficulty of detecting if the trigger condition has occurred or not estimated as low, medium or high.

Impact. The impact on the project if the risk occurs estimated as low, medium or high.

Overall. A percentage that will be used to weight the maximum possible impact of the risk. This is automatically from

Method. An explanation of the amount of work that will be needed and/or the costs that will be incurred if the risk occ
Maximum Days and Maximum Cost.

Maximum Days. The additional person-days that will be needed if the risk occurs.

Weighted Days. The additional days that will be needed if the risk occurs, weighted by (a) the probability of it occurrin
on the project. Calculated as Maximum Days * Overall.

Maximum Cost. The additional cost that will be incurred if the risk occurs. This cost does not include the extra days e

Weighted Cost. The additional cost that will be incurred if the risk occurs, weighted by (a) the probability of it occurrin
impact on the project. Calculated as Maximum Cost * Overall.

Variables associated with the calculation of a suitable weighting for each risk can be found in the Scratchpad sheet and in
sheet. The algorithm is as follows:

a)
According to the user entry of L, M or H for Probability, Detection and Impact, assign a weighting value taken fro
respectively (default values are 1, 3 and 7).
b)
Place the weight in p_assessment, d_assessment or i_assessment for Probability, Detection and Impact respec
c)
Add the three weights and place in total_weight.
d)
Assess this total as a proportion of the maximum possible as held in max_weight (default = high_weight x 3 = 21).
e)
Allot a final weighting as this proportion of max_risk (default 75%) and place it in the Overall field.
f)
The Overall value is used to modify the maximum days and cost that are assigned to the risk, in order to obtain an a
Summary Sheet
Totals are shown quarterly. Monthly totals can simply be obtained from the other sheets.
Cashflow Sheet

To determine the project price, you can enter a markup on the cost, and the spreadsheet will determine the price (total of
price, which can be entered in the Total Income cell (the markup will remain blank).

Define the billing profile across the duration of the project such that the total comes to 100%. The sheet will determine the

Hidden rows can be used to enter interest earned or received. Enter the interest rate that you will pay for borrowed money
amounts. The rates will be applied monthly according to whether the cashflow is negative or positive.
PriceBreakdown Sheet

The Ref and Task columns are brought forward from the Tasks sheet. If rows have been added or removed from this, y
before using it. Check that the totals include all the relevant rows.
The sheet should be used as follows:

a)
Enter the price or cost that you wish to distribute among the various tasks in the cell labelled Cost to be Attributed (
Cashflow or Summary sheets e.g. Our_Price or Initial_Costs_Total.
b)
Enter T (no other value) into the Cost Element column for all tasks that you wish to be included in the price break
c)
The SUMIF function is used to determine totals for these values as Breakdown_Cost_Elements and for all other task
10/18/2015
Page 3 of 207
d)
The number of days for all tasks shown with a T is weighted by the value Breakdown_Other_Tasks/Breakdown_Co
e)
The weighted number of days is used to allocate the Breakdown_Price among the selected tasks.

This sheet is very likely to be altered, to incorporate the individual elements that you wish to break down or sum, or the am

The Ref and Task columns are brought forward from the Tasks sheet. If rows have been added or removed from this, y
before using it. Check that the totals include all the relevant rows.
The sheet should be used as follows:

a)
Enter the price or cost that you wish to distribute among the various tasks in the cell labelled Cost to be Attributed (
Cashflow or Summary sheets e.g. Our_Price or Initial_Costs_Total.
b)
Enter T (no other value) into the Cost Element column for all tasks that you wish to be included in the price break
c)
The SUMIF function is used to determine totals for these values as Breakdown_Cost_Elements and for all other task
d)
The number of days for all tasks shown with a T is weighted by the value Breakdown_Other_Tasks/Breakdown_Co
e)
The weighted number of days is used to allocate the Breakdown_Price among the selected tasks.

This sheet is very likely to be altered, to incorporate the individual elements that you wish to break down or sum, or the am
to use subtotals from the Tasks sheet, or to take more account of the capital costs.
EarnedValue Sheet

The Ref and Task columns are brought forward from the Tasks sheet. If rows have been added or removed from this, y
using it. Check that the totals include all the relevant rows.

At the end of each month (or selected time-period), and for each task, you should enter the figures for the Budgeted Cost
progress has been made. Also enter the Actual Cost of Work Produced (ACWP) usually the time booked by project team
project reporting package if you are using one.
Red numbers in the SV, CV, SPI and CPI columns indicate a cost or schedule overrun.
The Estimate At Completion (EAC) is calculated as the actual costs to date plus the cost of the remaining work assuming

actual costs to date = ACWS_Total;

remaining work = Budget at Completion (BAC) minus the Earned Value to date (BCWP_Total);

current rate of productivity = CPI.


Scratchpad Sheet

This is used to create variables specific to a particular Cost Model. The variables can be used in formulae elsewhere in the
may be derived from other values in the model. Some examples are:

currency exchange rates;

on-site allowances;

daily expenses (e.g. travel abroad);

number of days for a project phase;

number of days for a project subsystem;

staff rates.

To create a variable, enter its name, its value or formula, and a comment about what it represents. To define the name to E
to the clipboard, select the Value cell, and then paste the name into the Name field on the toolbar (where the cell positio
Name, Define. The latter sequence can also be used to remove names.

There are some hidden rows containing values that are built in to the default Cost Model. These may be changed but shou
Diagrams

It is sometimes easier to create a new worksheet, carrying forward the figures that you wish to show in a diagram. These f
worksheets. Select the appropriate cells in the new sheet, and choose the Chart icon from the Microsoft Excel toolbar. Th
clicking on any element you wish to change.
Copyright Paul Coombs 2002.

10/18/2015

Page 4 of 207

10/18/2015

Page 5 of 207

with the template


er the way the

oject.

quired.

ented feature in
ent, then
omments.

in question, or its

e by Format,

ames to remain
etion of rows and

moved once the


The sheets
umns you should

project.

10/18/2015
your

Page 6 of 207

project.

your

ur own.

any days to add.


cell) so the

timated.

s labelled A to J.
he tasks for
Phase 1.

may be imported
taff costs.

crosses a year

hen the bill for it

ual the

te cell) so the

for each. Staff

depreciation 10/18/2015
of

Page 7 of 207

te cell) so the

for each. Staff

depreciation of

outside the project

pact entries.
entries for

and (c) its impact

nd (c) its relative

sk Analysis

_weight

e decided on a

or credit

kdown sheet

en from the

10/18/2015

al. You may wish

Page 8 of 207

kdown sheet

en from the

al. You may wish

ue sheet before

g how much
mported from a

e:

may be static or

the Name cell


, select Insert,

e other
ltered by right

10/18/2015

Page 9 of 207

10/18/2015

Page 10 of 207

COST MODEL
Project Name
Estimate Date

18-Oct-15

Project Start Date

18-Oct-15

Reference Number
Currency

USD

Days Per Month

19

Project Summary

Signoff
Role

10/18/2015

Name

Signature

Page 11 of 207

TASKS
0
Base Total

0 Days

Task Contingency

0.0%

0 Days

Total with Task Contingency

Project Contingency

GRAND TOTAL
Ref

Task

0
Base
Days

Task Cont.
%
Days

0
0
0
0
0
0
0
0
0
0

10/18/2015

0 Check

Project
Cont.
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Staff Profile
0

Check

Total
Notes

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 12 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 13 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 14 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 15 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 16 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 17 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 18 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 19 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 20 of 207

Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17
0

10/18/2015

Page 21 of 207

10/18/2015

Page 22 of 207

10/18/2015

Page 23 of 207

10/18/2015

Page 24 of 207

10/18/2015

Page 25 of 207

10/18/2015

Page 26 of 207

10/18/2015

Page 27 of 207

10/18/2015

Page 28 of 207

10/18/2015

Page 29 of 207

Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18
0

10/18/2015

Page 30 of 207

10/18/2015

Page 31 of 207

10/18/2015

Page 32 of 207

10/18/2015

Page 33 of 207

10/18/2015

Page 34 of 207

10/18/2015

Page 35 of 207

10/18/2015

Page 36 of 207

10/18/2015

Page 37 of 207

10/18/2015

Page 38 of 207

STAFF COSTS
0
Total
Oct-15 Nov-15 Dec-15 Jan-16
Total
Days

Average
Rate
0

Check From Tasks sheet


Role

Name

0
Days

Rate
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

Cost
(USD)

Staff Profile

Total Days

Check

USD
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 39 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 40 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 41 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 42 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 43 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 44 of 207

0
0
0

10/18/2015

0
0
0

Page 45 of 207

Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17
0

10/18/2015

Page 46 of 207

10/18/2015

Page 47 of 207

10/18/2015

Page 48 of 207

10/18/2015

Page 49 of 207

10/18/2015

Page 50 of 207

10/18/2015

Page 51 of 207

10/18/2015

Page 52 of 207

Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18
0

10/18/2015

Page 53 of 207

10/18/2015

Page 54 of 207

10/18/2015

Page 55 of 207

10/18/2015

Page 56 of 207

10/18/2015

Page 57 of 207

10/18/2015

Page 58 of 207

10/18/2015

Page 59 of 207

CAPITAL COSTS
0
Base Total

Item Contingency
Total with Item Contingency

0.0%

0
0

Project Contingency

Total Capital Costs (USD)

Ref

Item

10/18/2015

Supplier

Notes

Cost
(USD)

Qty.

Base
Cost

Item Cont.
%
USD

Page 60 of 207

10/18/2015

Page 61 of 207

10/18/2015

Page 62 of 207

10/18/2015

Page 63 of 207

USD
0
Initial
Costs
0

Depreciated
Costs
0
0 Warning!
Included in Project Costs

Total
Cost
(USD)
()
0

Check

Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

Depreciate
From
Years

Page 64 of 207

10/18/2015

Page 65 of 207

10/18/2015

Page 66 of 207

10/18/2015

Page 67 of 207

Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

Page 68 of 207

10/18/2015

Page 69 of 207

10/18/2015

Page 70 of 207

10/18/2015

Page 71 of 207

Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18


0
0
0
0
0
0
0

10/18/2015

Page 72 of 207

10/18/2015

Page 73 of 207

10/18/2015

Page 74 of 207

10/18/2015

Page 75 of 207

ONGOING COSTS
0
Total

Ref

Item

2016

2017

2018

2019

2020

Depreciation of Capital Costs

Other Ongoing Costs

Total Ongoing Costs

Rate
(USD)

Total
Days

Total
Days
(USD)
0
2015

STAFF
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

2015

2016

2017

2018

2019

2020

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 76 of 207

0
0
0
Total (Days)

Total (USD)
Ref

Item
OTHER COSTS

0
0
0

0
Total
USD
(USD)
0
2015

2016

2017

2018

2019

2020

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

Page 77 of 207

Total

10/18/2015

Page 78 of 207

RISK ANALYSIS
0
Risks Estimated in Terms of Days
Risks Estimated in Terms of Cost (USD)

10/18/2015

Page 79 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 80 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 81 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 82 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 83 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 84 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 85 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 86 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 87 of 207

RISK NUMBER

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 88 of 207

RISK NUMBER

10

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 89 of 207

RISK NUMBER

11

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 90 of 207

RISK NUMBER

12

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 91 of 207

RISK NUMBER

13

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 92 of 207

RISK NUMBER

14

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 93 of 207

RISK NUMBER

15

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 94 of 207

RISK NUMBER

16

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 95 of 207

RISK NUMBER

17

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 96 of 207

RISK NUMBER

18

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 97 of 207

RISK NUMBER

19

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 98 of 207

RISK NUMBER

20

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 99 of 207

RISK NUMBER

21

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 100 of 207

RISK NUMBER

22

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 101 of 207

RISK NUMBER

23

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 102 of 207

RISK NUMBER

24

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 103 of 207

RISK NUMBER

25

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 104 of 207

RISK NUMBER

26

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 105 of 207

RISK NUMBER

27

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 106 of 207

RISK NUMBER

28

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 107 of 207

RISK NUMBER

29

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 108 of 207

RISK NUMBER

30

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 109 of 207

RISK NUMBER

31

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 110 of 207

RISK NUMBER

32

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 111 of 207

RISK NUMBER

33

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 112 of 207

RISK NUMBER

34

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 113 of 207

RISK NUMBER

35

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 114 of 207

RISK NUMBER

36

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 115 of 207

RISK NUMBER

37

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 116 of 207

RISK NUMBER

38

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 117 of 207

RISK NUMBER

39

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 118 of 207

RISK NUMBER

40

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 119 of 207

RISK NUMBER

41

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 120 of 207

RISK NUMBER

42

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 121 of 207

RISK NUMBER

43

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 122 of 207

RISK NUMBER

44

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 123 of 207

RISK NUMBER

45

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 124 of 207

RISK NUMBER

46

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 125 of 207

RISK NUMBER

47

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 126 of 207

RISK NUMBER

48

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 127 of 207

RISK NUMBER

49

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 128 of 207

RISK NUMBER

50

Definition
Risk

Cause

Management
Prevention

Trigger

Plan

Owner
Assessment
Probability

Detection

Impact

Overall

11%

Contingency Allowance
Method

Maximum Days
Maximum Cost (USD)

10/18/2015

Weighted Days
Weighted Cost

Page 129 of 207

COST SUMMARY
0
Total (USD)

Q1

2015
Q3

Q2

Q4

Total

Q1

2016
Q3

Q2

Q4

Total

Q1

2017
Q3

Q2

Q4

Staff Costs

Capital Costs

Total Initial Cost

Ongoing Costs

Total Project Cost

10/18/2015

Page 207 of 130

17
Total

Q1

2018
Q3

Q2

Q4

Total

Q1

2019
Q3

Q2

Q4

Total

Q1

2020
Q3

Q2

Q4

Total

10/18/2015

Page 207 of 131

CASHFLOW
0
Total

Check

Oct-15

Nov-15

Dec-15

Jan-16

Feb-16

Mar-16

Apr-16

May-16

Jun-16

Jul-16

Staff Costs (USD)

Capital Costs (USD)

Total Costs (USD)

Billing Schedule

0.00%

Markup

Income (USD)

Gross Profit (USD)

Cashflow

Margin

10/18/2015

0.00%

Page 132 of 207

Aug-16

Sep-16

Oct-16

Nov-16

Dec-16

Jan-17

Feb-17

Mar-17

Apr-17

May-17

Jun-17

Jul-17

Aug-17

Sep-17

Oct-17

0
0

10/18/2015

Page 133 of 207

Nov-17

Dec-17

Jan-18

Feb-18

Mar-18

Apr-18

May-18

Jun-18

Jul-18

Aug-18

Sep-18

0
0

10/18/2015

Page 134 of 207

PRICE BREAKDOWN
0

Ref

Cost Elements
Other Tasks

0
0

Total
Check from Tasks sheet

0
0

Cost
Element?

Days

Task
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

USD
Cost Actually Attributed
Cost to be Attributed

0
0

Weighted
Days
Cost
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 135 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 136 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 137 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 138 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 139 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 140 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 141 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 142 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 143 of 207

EARNED VALUE
0
BAC
Ref

Name
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

EAC

BCWS BCWP ACWP

SV

SPI

CV

CPI

Oct-15
BCWS BCWP ACWP

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 144 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 145 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 146 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 147 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 148 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 149 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 150 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 151 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 152 of 207

Nov-15
Dec-15
Jan-16
Feb-16
Mar-16
Apr-16
May-16
BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 153 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 154 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 155 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 156 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 157 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 158 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 159 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 160 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 161 of 207

May-16
Jun-16
Jul-16
Aug-16
Sep-16
Oct-16
Nov-16
BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 162 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 163 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 164 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 165 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 166 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 167 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 168 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 169 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 170 of 207

Nov-16

Dec-16
Jan-17
Feb-17
Mar-17
Apr-17
May-17
ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 171 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 172 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 173 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 174 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 175 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 176 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 177 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 178 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 179 of 207

Jun-17
Jul-17
Aug-17
Sep-17
Oct-17
Nov-17
Dec-17
BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 180 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 181 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 182 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 183 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 184 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 185 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 186 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 187 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 188 of 207

Dec-17
Jan-18
Feb-18
Mar-18
Apr-18
May-18
Jun-18
BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 189 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 190 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 191 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 192 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 193 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 194 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 195 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 196 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 197 of 207

Jun-18

Jul-18
Aug-18
Sep-18
ACWP BCWS BCWP ACWP BCWS BCWP ACWP BCWS BCWP ACWP
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 198 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 199 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 200 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 201 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 202 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 203 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 204 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 205 of 207

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

10/18/2015

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 206 of 207

SCRATCHPAD
0
Name

10/18/2015

Value 1

Value 2

Comment

Page 207 of 207

You might also like