Professional Documents
Culture Documents
Slabs
One Way Slabs
Introduction
Reinforced concrete building construction
commonly has floor slabs, beams, girders and
columns continuously placed to form a
monolithic system.
11/16/2014
Introduction
B1,B2, and B3 are supported on the Girders
B4,B5, and B6 are supported on the Columns
G1,G2, and G3 are supported on the Columns
Types of Slabs
One-Way Slabs
Solid Slabs
Ribbed Slabs (Ribbed Joist floor)
Long Span
>2
Short Span
11/16/2014
Types of Slabs
Two-Way Slabs
Solid Slabs
Ribbed Slabs (Ribbed Joist floor)
Types of Slabs
Flat Slabs
11/16/2014
Example S1
A one-way single span reinforced concrete
slab has a simple span of 5.0 m. The service
live load is 15 kN/m2, the dead load is 10
kN/m2 (including self weight) and 28 MPa
concrete is specified for use with steel with a
yield stress equal to 420 MPa. Design the slab,
following the provisions of the ACI code.
Example S1
First determine the thickness of the slab:
From Table 9.5a of the ACI code
h=
l
5
=
= 0.250 m
20 20
0.0123857 * 420
28
11/16/2014
Example S1
As = 0.0123857 *1000 * 217.5 = 2693.89 mm 2
Use 525
d = 250 20 12.5 = 217.5 mm
2454.37 * 420
= 43.31 mm c = 50.96 mm
0.85 * 28 *1000
217.5 50.96
t = 0.003
= 0.00980 = .90
50.96
3694.51
=
= 0.0113 > min
186 *1000
M u = 181.70 kN - m
a=
Example S2
A reinforced concrete slab is built integrally
with its supports and consists of two equal
spans, each with clear span of 4.5 m. The
service live load is 5 kN/m2, and 28 MPa
concrete (Density =23.5 kN/m3) is specified for
use with steel with a yield stress equal to 420
MPa. Design the slab, following the provisions
of the ACI code.
CE 432 1st Semester 14/15
Dr. Nadim Shbeeb
11/16/2014
Example S2
First determine the thickness of the slab:
From Table 9.5a of the ACI code
4.5
l
h=
=
= 0.161 m
28 28
Use h=165 mm, thus
DL = 23.5 * .165 = 3.88 kN/m 2
wu = 1.2 * 3.88 + 1.6 * 5 = 12.656 kN/m 2
Example S2
8.3.3 As an alternate to frame analysis, the following approximate
moments and shears shall be permitted for design of continuous
beams and one-way slabs (slabs reinforced to resist flexural stresses
in only one direction), provided (a) through (e) are satisfied:
(a) There are two or more spans;
(b) Spans are approximately equal, with the larger of two
adjacent spans not greater than the shorter by more than 20
percent;
(c) Loads are uniformly distributed;
(d) Un-factored live load, L, does not exceed three times unfactored dead load, D; and
(e) Members are prismatic.
11/16/2014
Example S2
wln2 1
At interior support : M =
= *12.656 * 4.52 = 28.476 kN.m
9
9
wl 2 1
At midspan : + M = n = *12.656 * 4.52 = 18.306 kN.m
14 14
wl 2 1
At exterior support : M = n = *12.656 * 4.52 = 10.679 kN.m
24 24
1
24
1
9
1
14
Example S2
0.005 = 0.0181
d=
M u _ Interior
f yb(1 0.59
fy
f c'
= 70.40 mm
)
As = bd = 693.733 mm 2
Use 514 Each m
CE 432 1st Semester 14/15
Dr. Nadim Shbeeb
11/16/2014
Example S2
d = 165 50 7 = 108 mm
1 769.69 * 420
c=
= 15.98 mm
0.85 0.85 * 28 *1000
108 15.98
t = 0.003
= 0.0173 = .90
15.98
769.69
=
= 0.0071 > min
108 *1000
M u _ Interior = 29.44 kN - m
Similarly
As _ midspan = 437 mm 2 (Use 314 per m)
As _ Exteroir = 360 mm 2 (Use 314 per m)
CE 432 1st Semester 14/15
Dr. Nadim Shbeeb
Example S2
Shear Consideration
wu ln
wu d
2
12.656 * 4.5
1
= 1.15 *
12.656 * .108 = 31.38 kN < Vc
2
2
Vu = 1.15
11/16/2014
Reinforcement Details
Straight bars
L1/5
Bent bars
L /5
L1/3
L2/3
L1
L2
L1/3
L1/7
L2/3
L1/5
L2/3
L2/3
L2/4
L1
L2/4
L2
Ribbed Slab
2.5 cm
3.5 cm
9 cm
7 cm
14, 18 ,24 , 32 cm
2 cm
20 cm
36 cm
20 cm
12-15 cm
Shrinkage and
Temperature
Main
Reinforcement
40 cm
CE 432 1st Semester 14/15
Dr. Nadim Shbeeb
11/16/2014
Ribbed Slab
Design as T-beam
52 cm
7 cm
14,18, 24,32 cm
12 cm
0.5 m
6.5 m
B4
B3
0.5 m
B1
0.5 m
3.0 m
0.5 m
10
11/16/2014
Ribbed Slab
2.5 cm
3.5 cm
9 cm
7 cm
18cm
2 cm
20 cm
15 cm
20 cm
To estimate bw assume:
Cover =25 mm,
Stirrups 8,
Main reinforcement 2 20,
distance between reinforcement=30mm
h=
l
3
= = 18.75 cm
16 16
bw = 2 * (25 + 8 + 20) + 30
= 136mm Use 150mm
Ribbed Slab
2.5 cm
3.5 cm
9 cm
7 cm
18cm
2 cm
20 cm
15 cm
20 cm
To estimate DL:
1
0.73
= 1.34 kN/m 2
Rib : (0.15 + 0.19) * 0.18 * 24 = 0.73 kN/m =
2
0.55
: 0.020 * 22 = 0.44 kN/m 2
1
1
Block: 0.55* 0.2 *.15 = 1.36 kN/m 2
hf: 0.07* 24 = 1.68 kN/m 2
11
11/16/2014
Ribbed Slab
DLSlab=1.8+.625+.77+.44+1.36+1.68=8.02 kN/m2
Assume Partitions DL=2.35 kN/m2
DLTotal=10.37 kN/m2
LL=2.0 kN/m2
Ribbed Slab
Design as T-beam
Mu =
wu l 2 8.81 * 3.52
=
= 13.17 kN.m
8
8
13.17 * 10 6
70
0.9 * 420 * ( 215 )
2
= 193 .563 mm 2
193.563
= 0.006 > min
150 * 215
193 .563 420
a=
= 8.28 mm < h f
0.85 21 550
12
11/16/2014
Ribbed Slab
Use 214
307.88 * 420
= 13.17 mm
0.85 * 21* 550
a 13.17
c= =
= 15.49 mm
1 0.85
a=
215 15.49
= 0.0386 > 0.005
15.49
307.88
w =
= 0.00955
150 * 215
13.17
M u = 0.9 307.88 420 (215
)
2
= 24.26 kN.m > Mu
t = 0.003
Ribbed Slab
2.5 cm
3.5 cm
9 cm
7 cm
18 cm
2 cm
20 cm
15 cm
20 cm
214
18
13