Professional Documents
Culture Documents
HANDBOOK FOR
CONCRETE SEGMENTAL
AND CABLE-SUPPORTED BRIDGES
Published June 2008
by
Copyright 2008 by the American Segmental Bridge Institute. All Rights Reserved.
Printed in the United States of America. This book, or parts thereof may not be reproduced
in any form without permission of the publisher.
.)
Billinger Berger
lngeniEurbau GmbH
Bibliothek
1.0
1.1
Purpose
1.2
1.3
Structure Types
1.3.1
1.3.2
1.3.3
1.3.4
1.3.5
1.3.6
1.3.7
10
1.3.8
11
1.3.9
Heavy Segmental
13
1.3.9.1
13
15
17
2.0 Terminology
3.0
3.1
3.2
Introduction
Advantages of Segmental Span-by-Span Bridges
3.3
3.4
Special Considerations
3.5
Safety
18
3.6
Summary
20
17
)
Table of Contents, Chapters 1.0- 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
I of9
4.1
Overview
4.1.1
4.1.2
4.1.3
Segment Details
4.1.3.1
4.2.1
Forms
'
4.2.2
10
4.2.3
Geometry Control
13
4.3.4
13
4.3
Lifting Details
Typical Erection Cycle
4.3.1
Overview
14
14
4.3.2
Epoxy
15
4.3.3
Temporary PT
16
4.3.4
17
4.3.5
Grouting
18
4.4
19
4.4.1
20
4.4.2
Crane
Beam and Winch
4.4.3
Erection Gantry
22
4.4.4
Hauler
27
4.5
Special Topics
Surveying and Deflections
27
4.5.1
4.5.2
Pier Segments
28
4.5.2.1
21
27
Cast-in-Place
28
30
31
33
4.5.4
Mid-Span Closure
37
4.5.6
38
4.6
Engineering
38
4.6.1
Built-in Loads
38
4.6.2
Erection Loads
39
4.6.3
39
4.6.4
Temporary Post-Tensioning
39
Table of Contents, Chapters 1.0- 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
2 of9
5.0
5.1
5.2
3
3
6
6.0
6.1
6.2
6.3
6.4
6.5
6.6
6.7
Introduction
4
6
12
13
18
18
7.0
7.1
7.2
7.3
7.3.1
7.3.2
7.3.3
7.4
7.4.1
7.4.2
7.4.3
7.4.4
7.5.
7.5.1
7.5.2
7.5.3
7.5.4
7.6
7.7
7.8
7.8.1
7.8.2
7.9
Cable-Stayed Bridges
Introduction
Cable-Stayed Structure
Critical Construction Phases
Deck, Stay Cable Stresses
Unbalanced Loads
Other Critical Construction Loads
Geometry Control
Casting Curves
Geometry Control for Prescast Box Girder Segments
Geometry Control for Cast-in-Place Box Girders
Geometry Control for Cast-in-Place Flexible Decks
Stay-Cable System Quality Control
Stay-Cable Types
Bearing Plate, Recess Pipe Installation
Stay-Cable Pipe Installation
Installation of Other Stay-Cable Components
Control of Stay-Cable Forces
Fatigue Testing
Extradosed Bridges
Design Concept
Construction of Extradosed Bridges
Conclusion
References
3
3
3
5
5
11
13
14
14
15
20
20
20
20
20
22
23
24
26
26
26
28
29
29
29
)
Table of Contents, Chapters 1.0- 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
3 of9
8.0
8.1
8.2
8.3
8.4
8.5
Segmental Substructures
Introduction
Project Examples
Precasting Operations
Erection Operations
Summary
3
3
3
7
10
11
9.0
9.1
9.1.1
9.1.2
9.1.2.1
9.1.2.2
9.1.2.3
9.1.2.4
9.1.3
9.1.3.1
9.1.3.2
9.1.3.3
9.1.3.4
9.1.3.5
9.1.4
9.1.4.1
9.1.4.2
9.1.5
9.1.5.1
9.1.5.2
9.1.5.3
9.1.5.4
9.1.6
9.1.9.1
9.1.9.2
9.1.9.3
9.1.9.4
9.1.9.5
9.1.7
9.1.7.1
9.1.7.2
9.1.7.3
9.1.7.4
9.1.7.5
9.1.7.6
9.1.7.7
9.1.7.8
Segment Production
Security
Slip or Dock Conditions
Receiving/Delivery
Delivery of Segments
Material Deliveries
Site Preparation
Local Permits-Developer Fees
Grubbing and/or Clearing
Grading-Drainage, Runoff
Foundations
Procurement
Forms
Batch Plant
Steam Generator
Facilities
Office Trailer Locations
Form Locations
3
3
3
6
6
6
6
7
7
7
8
8
8
8
8
8
9
10
10
10
10
10
12
12
15
15
16
17
20
20
21
23
24
24
24
24
25
Table of Contents, Chapters 1.0 - 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
)
4 of9
')
9.1.8
9.1.9
9.2
9.2.1
9.2.2
9.3
9.4
9.5
9.6
9.7
9.8
9.9
9.10
9.11
9.12
9.13
9.14
9.14.1
9.14.2
9.14.3
9.14.4
9.14.5
Post Casting
Summary- Casting Yard Planning and Setup
Long Line and Short Line Forms
Long Line Casting Bed
Short Line Casting Bed
Match Casting
Casting Curve
Fabrication of Rebar Cage with Post-Tensioning Ducts and Hardware
Installation of Post-Tensioning Ducts
Handling the Prefabricated Rebar Cage
Rebar Cage in Casting Cell
Setting the Match Cast Segment
Placing Concrete
Finishing the Top Surface
Curing
Forms
~ ~')\A. "'-~
J fri ~.s
Crossover Construction
Grounding Requirements
LRT Conclusion
25
26
27
27
33
37
38
39
41
41
42
42
43
45
46
47
50
50
52
52
53
55
CHAPTER 10.0 PROCEDURES FOR HANDLING TRANSPORTING AND ERECTING PRECAST SEGMENTS
10.0
10.1
10.1.1
10.1.2
10.1.3
10.2
10.2.1
10.2.2
3
Methods of Lifting Precast Segments
3
Lifting Holes Cast in the Top Slab of Segments
3
Inserts Embedded in the Segment Webs and Protruding Above the Top Slab
4
Lifting Slings or C Hook Frame
5
Handling and Transporting of Precast Segments in Precast Yard
6
Handling precast segment from the new-cast position to the match-cast position 6
Handling and Transporting of Precast Segments from the Casting Area
to the Storage Area
10.3
10.3.1
10.3.1.1
10.3.1.2
10.3.1.3
10.3.2
10.3.2.1
10.3.2.2
10.3.2.3
10.3.3
10.4
10.4.1
Transporting Precast Segments from the Precast Yard to the Erection Site
Transporting Precast Segments via Water Using Barges
Loading
Transport
Unloading
Transporting Precast Segments Off-site via Land
Loading
Transport
Unloading
Transporting Precast Segments On-site via Land
Erection of Precast Segmental Bridges
Factors for the Selection of Precast Segmental Bridge Erection Methods
6
11
11
11
12
12
14
14
14
15
15
19
19
)
Table of Contents, Chapters 1.0- 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
5 of 9
CHAPTER 10.0 PROCEDURES FOR HANDLING TRANSPORTING AND ERECTING PRECAST SEGMENTS
Continued
10.4.2
10.4.2.1
10.4.2.1.1
10.4.2.1.2
10.4.2.1.3
10.4.2.1.4
10.4.2.1.5
10.4.2.1.6
10.4.2.2
10.4.2.2.1
10.4.2.2.2
10.4.2.2.3
10.4.2.2.4
10.4.2.3
21
22
22
24
25
27
28
29
30
30
32
34
36
37
11.0
11.1
11.1.1
11.1.1
11.1.2
11.1.2
11.1.3
11.1.3
11.1.4
11.1.4
11.1.5
11.1.5
11.1.6
11.1.6
11.1.7
11.1.7
11.1.8
11.1.8
11.2
11.3
11.4
11.5
11.6
11.7
Erection Details
Permanent Post-Tensioning
Anderson Technology Corporation- Transparent Sheathing
Anderson Technology Corporation- Super Corrosion Protective
(Supra Strand)
AVAR Post-Tensioning Systems for Segmental Bridge Construction
Single Plane/Multi Plane
AVAR Post-Tensioning Systems for Segmental Bridge Construction
Single Plane/Flat Anchorage
DYWIDAG-Systems International- DYWIDAG Post-Tensioning
Systems for Segmental Construction
DYWIDAG-Systems International- DYWIDAG Post-Tensioning
Systems for Segmental and CIP Construction
Freyssinet Post-Tensioning Systems- Freyssinet Post-Tensioning
Hardware for Segmental Bridges/G-Range Post-Tensioning Systems
Freyssinet Post-Tensioning Systems- Freyssinet F-Range Post-
3
3
4
Tensioning Systems
11
12
13
14
Table of Contents, Chapters 1.0 - 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
5
6
7
8
9
10
15
16
17
18
19
20
23
30
31
32
33
6 of9
CHAPTER 12.0 EPOXY JOINTING, DUCT COUPLER DEVICES, AND PREPACKAGED GROUT
12.0
Epoxy Jointing, Duct Coupler Devices, and Prepackaged Grout
Purposes of Epoxy
Types and Application of Epoxy
12.3
12.3.1
6
7
12.3.2
12.3.3
12.4
12.4.1
12.4.1
12.4.2
12.4.3
14
15
16
13.1
13.2
13.3
13.4
13.5
13.6
13.7
13.8
13.9
13.9.1
13.9.2
General
Casting Cell Geometry Control System
Tools Used for Geometry Control
Geometry Control of the First Pier Segment
Field Survey Checking During Erection
Systematic Error
Achieved Profiles
Pier Shaft Segments
Temperature Effects
Temperature Expansion and Contraction
Temperature Gradient
14.1
Bearings
14.1.1
14.1.2
14.1.3
Bearing Installation
14.1.4
14.1.5
Temperature Adjustment
14.2
14.2.1
14.2.2
14.2.3
14.2.4
14.2.5
14.2.5
14.2.6
14.2.6
14.2.7
14.2.7
Mortar Pads
Horizontal-Position of Bearings
Direction of Movement
Expansion Joints
,-'
9
10
13
3
3
7
12
13
13
14
15
15
15
15
18
3
3
3
6
6
6
6
7
7
8
9
10
12
13
14
15
16
17
Table of Contents,' Chapters 1.0 - 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
(
3
3
12.1
12.2
7 of9
15.0
Lessons Learned
15.1.0
General
15.2.0
15.2.1
Reinforcing Details
15.2.2
15.2.3
Cracking
15.2.4
15.2.5
15.2.6
15.2.7
15.2.8
15.2.9
Shear Lag
10
10
10
10
11
15.3.0
12
15.3.1
12
15.3.2
General
Equipment Requirements
15.3.3
Construction Loads
12
15.3.4
Truss Stability
13
15.3.5
14
15.3.6
15.3.7
Out-of-Balance Moments
14
15.3.8
14
15.3.9
15
12
14
15.3.10
15
15.3.11
15
15.3.12
16
15.3.13
Tendon Blockages
16
15.3.14
Tendon Pop-out
16
18
18
15.4.0
19
References
16.0
16.1
Motivation of Stakeholders
16.2
16.3
16.4
16.7
Preconstruction Conference
Engineering Submittals, Shop Drawings, RFis
Technical Workshops I Submittals I Format
Critical Issues early on at Precast Yard
16.8
16.5
16.6
4
4
5
5
Table of Contents, Chapters 1.0 - 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
8 of 9
16.9
16.10
16.11
16.12
16.13
16.14
16.15
16.16
16.17
16.18
16.19
16.20
Environmental Issues
Claims and Changes
Successful Project Ingredients
Summary
5
6
6
6
7
7
7
7
8
8
8
9
17.1
17.1.1
17.1.2
17.2
17.3
17.4
17.5
17.6
17.7
17.8
17.9
17.9.1
17.9.2
17.9.3
17.10
17.11
17.12
17.13
17.14
17.15
17.16
17.17
17.18
17.19
17.20
17.21
17.22
17.23
3
3
5
7
8
11
Recommended Practice for the Initial Inspection and Storage of Post-Tensioning Hardware 15
Recommended Practice for Inspection of Post-Tensioning Hardware
In the Reinforcement Cage
17
Recommended Practice for Resolution of Rebar Conflicts
18
Recommended Practice for Inspecting Post-Tensioning Hardware in the Form
20
Recommended Practice for Inspection of the Setting of Matchcast Segments
21
On-Site Hardware
21
Measuring Instruments
22
Observations in the Casting Cell
23
Recommended Practice for Concreting Segments
26
Recommended Practice for Inspection of Curing of Segments
28
Recommended Practice for Inspection of Stripping Forms and Bond Breaking
29
Recommended Practice for Inspection of Segment Handling in the Casting Yard 30
Recommended Practice for Inspection of Repairs Made to Segments
31
Recommended Practice for Inspection of Segment Storage
33
Recommended Practice for Inspection of Segments for Payment
34
Recommended Practice for Inspection of Segment Transportation
35
Recommended Practice for Inspection of Erection Equipment
36
Recommended Practice for Inspection of Falsework
37
Recommended Practice for the Inspection of Epoxy Joints
38
Recommended Practice for Tendon Stressing
40
Recommended Practice for Inspection of Grouting
40
Recommended Practice for Inspection of Cast-in-Place Segmental Structures
40
Table of Contents, Chapters 1.0 - 17.0 and Post-Tensioning Tendon Installation & Grouting Manual
9 of9
Chapter 3
Chapter 4
Chapter 5
Chapter 6
Chapter 7
Chapter 9
Chapter IO
Chapter 13
Geometry Control
Alan Moreton, Corven Engineering, Inc.
Lessons Learned
Chapter I5
Chapter I6
Acknowledgements
(First Edition)
"A Guide to the Construction of Segmental Bridges" developed by and for the Florida
Department of Transportation; October 1989, was used by the American Segmental Bridge
Institute Construction Practices Committee as a source document in the development of the
"Guidelines for Construction of Segmental Concrete Bridges" presented in this publication.
Contributions to the Handbook by individuals who were primary authors of chapters of this
section of the manual are acknowledged as follows:
Chapter 3
Chapter4
Chapter 5
Chapter 13
Segmental Substructures
- R. Kent Montgomery, FIGG
.J
DAVID GOODYEAR
Vice President
T. Y. Lin International
1115 W. Bay Drive NW, Suite 206
Olympia WA 98502
(360) 754-0544
Fax: (360)754-1714
e-mail: dgoodyear@tylin.com
e-mail: john.armeni@armeniconsulting.com
SEAN BUSH
PCL Civil Constructors, Inc.
2804 E. Jackson Street
Orlando, FL 32803
Cell: (407) 896-5960
(407) 896-5963
e-mail: sbush@pcl.com
ELIE H. HOMSI
Vice President Engineering Services
Flatiron Constructors, Inc.
100901-25 Frontage Road
Longmont CO 80504
(720) 49+8134
Fax (720) 494-8150
e-mail: ehomsi@flatironcorp.com
DAN CABELLO
IAN HUBBARD
Bayshore Concrete
Products Corporation
Parsons Brinckerhoff
Construction Services
POB230
Cape Charles, VA 23310
(757) 331-2300
(757) 331-2501
e'mail : dcabello@bcpcorp.com
RICCARDO CASTRACANI
DEAL/Rizzani de Eccher, USA
2999 NE 191st Street, Suite 901
Aventura, FL 33180
(305) 932-9700
Fax: (305) 932-9550
e-mail: rcastracani@rdeusanet
TOM DeHAVEN
FIGG
1585 Thomas Center Drive, Suite 106
Eagan, MN 55122
(651) 251-3444
Fax: (651) 251-3445
e-mail: tadfbi@aol.com
GOWEN DISHMAN
HNTB
c/o 3408 S. Lakeshore Drive
Lake Village, AR 71653
662-347-6506
gdishman@hntb.com
ANDREW A. GHOFRANI, P.E.
Design/Build Manager
Granite Construction, Inc.
585 W. Beach Street, Building #I
Watsonville, CA 95076
(831)728-7548
Fax: (831) 728-7513
e-mail: Andy.Ghofrani@gcinc.com
)
"
TAKAHIRO KAKUTA
PSM CONSTRUCTION
USA, INC.
111 Anza Blvd., Suite 415
Burlingame, CA 94010
(650) 344-9109
Fax: (650) 344-9199
e-mail : tkakuta@psmc-usa.com
KEEFER, MARK
VSL
282 Alpine Drive
Front Royal, VA 22630
Fax: (703) 451-0862
Mobile: (571) 437-3399
e~mail: mkeefer@structural.net
RICKLAIL
Southern Fonns. Inc.
445 Hales Bar Road
Guild, TN 3 7340
(423) 942-7000
Fax: (423) 942-1902
e-mail: rlail@southemfonns.com
FHWA
Office ofBridge Technology
lllBT, Room 3203, 400 7"' Street, SW
Washington, DC 20590
(202) 366-4589
Fax: (202) 366-3077
ARTIIUR PALMER
603 Hudson River Road
POBox248
Waterford, NY 12188
(H) 518-235-3647
(C) 518-810-6886
e-mail: arthur.palmer@parsons.com
e-mail: myintJwin@fhwa.dot.gov
RALPH SALAMIE
SCOTT MCNARY
McNary Bergeron & Associates
565 Burbank Street
Suite A
Broomfield, CO 80020
(CO .office only)
(860) 388-2267
Fax: 860-388-2268
e-mail: scott@mcnarybergeron.com
SAM! MEGALLY
PBS&J
9275 Sky Park Court, Suite 200
San Diego, CA 92123
(858) 514-1035
Fax: (858) 514-1001
e-mail: shmegally@pbsj.com
MARK MILICI
Dywidag Systems International, USA, Inc.
525 Wanaque Avenue, Suite LLI
Pompton Lakes, NJ 07442-1833
(973) 276-9222
Fax: (973) 276-9292
e-mail: mark.milici@dsiamerica.com
ALAN J. MORETON
e-mail: amoreton@corveneng.com
STEVE PABST
Kiewit Pacific
2200 Columbia House Blvd.
Vancouver, W A 98661
(360) 693-1478
Fax: (360) 693-5582
e-mail: ralph.salamie@kiewit.com
JIM SCHNEIDERMAN
PCL Civil Constructors, Inc.
3810 Northdale Blvd., Suite 200
Tampa, FL 33624
(813) 264-9500
Cell: (813) 781-0047
e-mail: jschneiderman@pcl.com
BEN SOULE
e-mail: bsoule@ibtengineers.com
EDWARD TRIPODI
ETIPTC
3430 Tumingwind Lane
Winter Garden, Fl. 34787
(612) 328-7778
e-mail: edtripodiptc@aol.com
JOHN WHITE
e-mail: jwhite@williamsfonn..com
CLIFFORD L. FREYERMUTH, Facilitator
ASBI
9201 N. 25th Avenue, Suite 150B
Phoenix, AZ 85021
(602) 997-9964
Fax: (602) 997-9965
e-mail: asbi@earthlink.net
)
2
DISCLAIMER
This publication is intended for the use of professionals competent in evaluating the
significance and limitation of its contents and who will accept responsibility for the
application of the materials it contains. American Segmental Bridge Institute makes no
warranty regarding the recommendations contained herein, including warranties of
quality, workmanship or safety, express or implied, further including, but not limited to,.
implied warranties or merchantability and fitness for a particular purpose.
THE
DAMAGES,
INCLUDING
CONSEQUENTIAL
DAMAGES,
BEYOND
Institute to any liability, direct or indirect, and those making such reference or quotation
shall waive any claims against the American Segmental Bridge Institute.
TABLE OF CONTENTS
CONSTRUCTION PRACTICES HANDBOOK FOR
CONCRETE SEGMENTAL AND CABLE-SUPPORTED BRIDGES
CHAPTER 1.0 INTRODUCTION AND OVERVIEW OF SEGMENTAL CONSTRUCTION
1.0
1.1
Purpose
1.2
1.3
Structure Types
1.3.1
1.3.2
1.3.3
1.3.4
1.3.5
1.3.6
1.3.7
10
1.3.8
11
1.3.9
Heavy Segmental
13
13
15
1.4
17
1 of 17
TABLE OF FIGURES
CONSTRUCTION PRACTICES HANDBOOK FOR
CONCRETE SEGMENTAL AND CABLE-SUPPORTED BRIDGES
CHAPTER 1.0 INTRODUCTION AND OVERVIEW OF SEGMENTAL CONSTRUCTION
Figure 1.1
Figure 1.2
Figure 1.3
Figure 1.4
Figure 1.5
Figure 1.6
Figure 1.7
Figure 1.8
Figure 1.9
Figure 1.10
Figure 1.11
Figure 1.12
Incremental Launching
10
Figure1.13
10
11
Figure 1.15
12
Figure 1.16
12
Figure 1.17
13
Figure 1.18
13
Figure 1.19
14
Figure 1.20
Figure 1.14
Figure 1.22
Figure 1.23
15
15
16
16
)
Chapter 1.0 Introduction and Overview of Segmental Construction
2ofl7
1.2
1.3
Structure Types
1.3.1
)
Chapter 1.0 Introduction and Overview of Segmental Construction
3 of 17
J
Chapter 1.0 Introduction and Overview of Segmental Construction
4 of 17
')
1.3.2
'.'
=
II I
II I I I
=
,.
I! l
''1''1'''1'1~
Figure 1.4- Erection of Cantilever N-ES with Segment Erector. Cantilever W-N 10 in the Foreground
5 of 17
1.3.3
of construction has been applied or considered in environmentally sensitive locations where construction
access is restricted to one or both ends of the bridge. A sketch of the erection scheme is shown in Figure
1.5, and a construction view of the Linn Cove Viaduct is presented in Figure 1.6.
)
Chapter 1.0 Introduction and Overview of Segmental Construction
6 of 17
. \
1.3.4
Construction of the precast segmental arch spans of the Natchez Trace Parkway Bridge in Tennessee is
illustrated by Figures 1.7 and 1.8. The arch spans range to 582 feet. Segment erection is supported by tiebacks to piers, or tie-backs anchored at ground anchors at the abutments. The Natchez Trace Parkway
Bridge deck was constructed utilizing balanced cantilever construction with spans ranging from 90 to 246
feet.
7 of 17
1.3.5
d)
8 of 17
1.3.6
9 ofl7
1.3.7
l
Figure 1.12 -Incremental Launching
10 of 17
Figure 1.14 -Launching Equipment for the Bellaire Beach Bridge, Tampa, FL
(Photo courtesy ofVSL)
1.3.8
11 ofl7
12ofl7
1.3.9
Heavy Segmental
13ofl7
)
Chapter 1.0 Introduction and Overview of Segmental Construction
14ofl7
Figure 1.20- Long Line Casting Form- San Francisco-Oakland East Bay Skyway Bridge
)
.. /
Figure 1.21 - 800- ton Segment Transporler- San Francisco Oakland East Bay Skyway Bridge
Chapter 1.0 Introduction and Overview of Segmental Construction
15 of 17
Figure 1.22- Segment Storage- San Francisco-Oak/and East Bay Skyway Bridge
Figure 1.23 - San Francisco-Oakland Skyway Bridge, Erection of First Segment, July 26, 2004
)
Chapter 1.0 Introduction and Overview of Segmental Construction
16 of 17
1.4
)
Chapter 1.0 Introduction and Overview of Segmental Construction
17 of 17
TABLE OF CONTENTS
)
Chapter 2.0- Terminology
Page I of 10
TABLE OF FIGURES
10
)
Chapter 2.0- Terminology
Page 2 of 10
2.0 Terminology
2.1 General Terminology
Anchorage Block- Build-out io the web, flange, or web-flange junction to provide area for one or more
tendon anchorages (Figure 2.2).
Balanced Cantilever Erection - This is an erection method where segments are erected alternatively on
either side of the pier in cantilever up to the point where a cast-io-place closure is made with the previous
cantilever or existing side span structure (Chapter 4.0)
Beam and Winch - Custom made erection equipment consisting of a longitudinal beam fitted with lifting
pulleys, tackle and winches which is attached to the end of a cantilever and lifts up the segments. After
erecting a segment, the equipment is advanced for erection of the next segment. This equipment is used
with balanced cantilever or progressive cantilever erection (Figure 4.3).
Box Girder or Box Pier- Box shaped structural member used for bridge superstructures and piers as shown
in Figure 2.2.
Cantilever Tendons - Longitudinal post tensioniog installed in the top slab of segmental bridges built io
balanced cantilever.
Cast-in-Place Segmental Bridge- A Bridge constructed with cast-in-place segments.
Casting Curve - This is the geometric profile to which the segments must be made in order to achieve the
required theoretical bridge profile after all final structural and time-dependent (creep and shrinkage)
deformations have taken place.
Closure - Cast-in-place concrete segment or segments used to complete a span.
Continuity Tendons- Longitudinal post tensioning installed in the bottom slab of segmental bridges built io
balanced cantilever.
Diabolo - Details for continuous duct placement through deviation saddles, and for connection at
diaphragms (Figure 2.3)
Deviation Saddle -Build-out in the web, flange, or web-flange junction to provide for change of direction
of an external tendon.
Deviation Trumpet- Detail for tendon connection of deviation saddles and diaphragms to provide tolerance
for angle of tendon connection (Figure 2.4).
External Tendon - Tendon located outside the flanges or webs of the structural member, generally inside
the box girder cell.
Erection Truss Span-bv-Span - This is a custom built truss which rests underneath a span on supports
connected to the pier and/or previously erected superstructure onto which a complete span of segments is
placed by crane or other device. Such trusses may be self launching to the next span or may be moved by
cranes.
Form Traveler - Equipment utilized for construction of Cast-in-Place segmental bridges. Major
components include the structural frames (horses), the upper work platform, the lower work platform, and
the trailing work platform. The form traveler is used to advance the forms from segment to segment. It
also supports the leading edge of the forms throughout the "form-rebar-pour" cycle.
Page 3 of 10
Launching Gantry - Custom built erection equipment which is used to take delivery of the segments, lift,
move and place them in their fmal erected locations in the superstructure. After completion of a cantilever
or span, the gantry is capable of launching itself forward into a position ready to construct the next
cantilever, or span.
Internal Tendon - Tendon located within the flanges or webs (or both) of the structural member.
Long Line Casting - Method of casting segments on a long casting bed which makes up the complete
cantilever or span between field closures.
Match Cast- Method of casting segments whereby a segment is cast against an existing segment to produce
a matching joint. When the segments are separated and re-assembled in the structure, the mating surfaces
fit together and reproduce the "as cast geometry."
Permanent Post Tensioning- Post tensioning that is required as part of the completed structure.
Pier Table- The portion of a cast-in-place segmental bridge that is built atop the piers prior to assembly of
the form travelers. In fact, a key factor in the pier table design process is the decision about whether to
only provide space for assembly of one form traveler or to provide adequate space for concurrent
fabrication of two form travelers.
Precast Segments - Box shaped precast concrete elements which can be assembled to form a bridge
superstructure or pier (see Figure 2.1).
Precast Segmental Bridge - A bridge constructed with precast segments. Common types described in
Article 1.3 of Chapter I.
Progressive Erection in Cantilever - Segments are erected in cantilever in one direction only from one pier
to the next using temporary intermediate piers or temporary cable stays or both to support the advancing
cantilever.
Segmental Constrnction - the fabrication and erection of a structural element (superstructure and/or
substructure) using individual elements, which may be either precast or cast-in-place. The completed
structural element acts as a monolithic unit under some or all design loads. Post-tensioning is typically used
to connect the individual elements. For superstructures, the individual elements are typically short (with
respect to the span length) box-shaped segments with monolithic flanges that comprise the full-width of the
structure.
Short Line Casting - Method of casting each segment in a special form called a casting cell using a fixed
bulkhead at one end and a previously cast segment at the other as shown in Figures 6.10, 6.11, and 6.12.
The form is only one segment long, hence the term "short line. 11
Span-bv-Span Erection - This is an erection method where all the segments for one span are placed on a
temporary support truss, aligned, jointed, and longitudinally post-tensioned together in one operation to
make a complete span. See Chapter 3.0.
Temporary Post Tensioning- Post tensioning installed solely for erection purposes.
Transverse Tendons- Post tensioning installed in the top deck and perpendicular to the centerline of the
bridge, typically to strengthen the cantilevered wings of the segments.
)
Chapter 2.0- Terminology
Page 4 of 10
Pier segment
/Jiitphl'tiltin
--...
....._......----- ...
-~~-~-~--r~---~
"'"' LugitudiJl.tJI
~antJJe:w::r
past-le;nsinning
T.rans1o>~r.se
Bearing pad
pede$lol ro:r
j30$l. t~.ti:'Oioning
.neoprt:nc or
1'ypicaJ ~~ecmeni.
pot bearings
,/'/_//
Pier
-tJ(tp
_/
Buxpicr
pu.-:t ~ten!tiouing
Shetu~
key
~"ace ancJUJ-t'
irl recess
Te.rnpur-a;-y
post-'-tensiPning
bli-ster
~~~~~~i~~~~~~~~s~;~~~:~~~:::J
l.lppcr P.ernrnncnt
posi- ten.-.ionif1C
;;tnchoru,t:fi: Mi.slcr
(Duttre!t.s) ror _
ftir lc:mporat'y
pu....r.-l.cnsionine bnr$
)
Chapter 2.0- Terminology
Page 5 of!O
f
N
--
-1~1: 1~1-
0
I
1-ijj'1-1
"""
'hE+:ifP=td
,.,.,
TYPE
~At DIABOLO
.....
...,'" . . .;r--l
I
t=f:::=;t:==L-+--.r.
~
E~
~~
lll-OI""'!,!;t.
t<>-~
'
FUTUR!tl'l>iOO!i
u~~-&~~1,
P.r.li."'!lr.~AII.S
..:.'1\
.....
!'-'
Jc:;lf
"'
b
~
0
II
.,
.....
'
!i
!.1.""""-
--1 -
---
""""
c---
- -- --- Twlo ..
\____/
..
'!YI>Ol~-
~~
SISEOOEO 1'EHOON
QIAI s
"'....,
...
P.T.HARDW!f
l<l!(,o.n.
~""'
~:.-.
... :
,. .~
e.
""
\
\_~"'A,__,..
\.._~,.. ....
~
~-~
SECTION:
O<TAII. 1
!!mU.
OIASOLO OETAILS
!l
-=
: !
: ~
: :
: :
'
... ,j
r-1 .;,\
i'
'
\J
-
!
'
!'
!
'
Page 7 of 10
2.2
Anchorage Assembly- An assembly of various hardware components which secures a tendon at its ends
after it has been stressed and, imparts the tendon force into the concrete (Figure 2.5).
Anticipated Set- The wedge set assumed to occur in the design calculation of the post-tensioning forces at
the time ofload transfer.
Bar- Post-tensioning bars are high strength steel bars, normally available from 5/8 to 2 1/2 inch diameter
and usually threaded with very coarse thread.
Bearing Plate - Any hardware that transfers the tendon force directly into a structure or the ground.
Bleed- The autogenous flow of mixing water within or its emergence from, newly placed grout, caused by
the settlement of the solid materials within the mass.
Bursting Force- Tensile forces in the concrete in the vicinity of the transfer or anchorage of prestressing
forces.
Coupler- A device used to transfer the prestressing force from one partial length prestressing tendon to
another. (Strand couplers are not permitted.)
Deviation Saddle - A concrete block build-out in a web, flange, or web-flange junction used to control the
geometry of, or to provide a means for changing direction of external, tendons.
Duct- Material forming a conduit to accommodate prestressing steel installation and provide an annular
space for the grout which protects the prestressing steel.
Effective Prestress - The stress or force remaining in the prestressing steel after all losses (short-term and
long-term) have occurred.
Family of Systems- Group of post-tensioning tendon assemblies of various sizes which use common
anchorage devices and design. All components within the family of systems shall be furnished by a single
supplier and shall have a common design with varying sizes.
Fluidity- A measure of time, expressed in seconds necessary for a stated quantity of grout to pass through
the orifice of a flow cone.
Grout- A mixture of cementitious materials and water with or without mineral additives or admixtures,
proportioned to produce a pumpable consistency without segregation of the constituents, when injected into
Heat Shrink- Heat welding techniques to make splices between sections of plastic duct, in accordance with
the duct manufacturers instructions. Heat shrink sleeves having unidirectional circumferential recovery
manufactured specifically for the size of the duct being coupled consisting of an irradiated and cross linked
high density polyethylene backing for external applications and linear-density polyethylene for internal
applications.
Inlet (also inlet pipe or grout injection port) - Tubing or duct used for injection of the grout into the duct.
Jacking Force - The force exerted by the device that introduces tension into the tendon.
Outlet (also ejection pipe or grout outlet vent or vent)- Tubing or duct to allow the escape of air, water,
grout and bleed water from the duct.
Page 8 ofiO
Post-tensioning- A method of prestressing where tensioning of the tendons occurs after the concrete has
reached a specified strength.
Pre-stressing Steel- The steel element of a post-tensioning tendon, which is elongated and anchored to
provide the necessary permanent prestressing force.
Post-Tensioning Scheme or Layout- The pattern, size and locations of post-tensioning tendons provided by
Prepackaged Grout- grout with anti-bleed, low permeability, and thixotropic characteristics
Post-tensioning System -An assembly of specific models of hardware, including but not limited to
anchorage assembly, local zone reinforcement, wedge plate, wedges, inlet, outlet, couplers, duct, duct
connections and grout cap, used to construct a tendon of a particular size and type. The entire assembly
must me'et the system pressure testing requirement. Internal and external systems are considered
independent of one another.
Pressure Rating - The estimated maximum pressure that water in a duct or in a duct component can exert
continuously with a high degree of certainty that failure of the duct or duct component will not occur
(commonly referred to as working pressure).
Set (Also Anchor Set or Wedge Set) - Set is the total movement of a point on the strand just behind the
anchoring wedges during load transfer from the jack to the permanent anchorages. Set movement is the
sum of slippage ofthe wedges with respect to the anchorage head and the elastic deformation of the anchor
components. For bars, set is the total movement of a point on the bar just behind the anchor nut at transfer
and is the sum of slippage of the bar and the elastic deformation of the anchorage components.
Special Anchorage Device- Anchorage device whose adequacy should be proven in standard acceptance
test. Most multiple anchorages and all bond anchorages are special anchorage device.
Strand- An assembly of several high strength steel wires wound together. Strands usually have six outer
wires helically wound around a single straight wire of a similar diameter.
Stressing Jacks and Gauges - Each jack will be equipped with a pressure gauge for deterruining the jacking
pressure. The pressure gauge will have an accurate reading gauge with a dial at least 6 inches in diameter.
Temporary Corrosion Protection- The introduction of a substance into the post-tensioning ducts
subsequent to installation and stressing of post-tensioned tendons and prior to grouting for purpose of
preventing or mitigating the initiation or propagation of corrosion of post-tensioned steel.
Tendon - A single or group of prestressing steel elements and their anchorage assemblies imparting
prestress forces to a structural member or the ground. Also, included are ducts, grouting attachments, grout
and corrosion protection filler materials or coatings.
Tendon Size - The number of individual strands of a certain strand diameter or the diameter of a bar.
Tendon Type- The relative location of the tendon to the concrete shape, internal or external.
Thixotropic - The property of a material that enables it to stiffen in a short time while at rest, but to acquire
a lower viscosity when mechanically agitated.
Transfer- The operation of imparting the force in a pre-tensioning anchoring device to the concrete.
Vacuum Grouting- grout injection used for repair of voids in ducts and anchorages after generating a
vacuum in the void space.
Page 9 of 10
Vacuum-assisted Grouting- normal grout injection after generating a vacuum in the duct containing the
tendon.
Wedge Plate- The hardware that holds the wedges of a multi-strand tendon and transfers the tendon force
to the anchorage assembly. (Commonly referred to as anchor head)
Wedge- A small conically shaped steel component placed around a strand to grip and secure it by wedge
action in a tapered hole through a wedge plate.
Wire- A single, small diameter, high strength steel member and, normally, the basic component of strand,
although some proprietary post-tensioning systems are made up of individual or groups of single wires.
Grout Inlet
Grout Outlet
Grout cap
Trumpet
Duct
Anchorage
3-part wedge
Strand
)
Chapter 2.0- Terminology
Page 10 of 10
TABLE OF CONTENTS
3.0
3.1
Introduction
3.2
3.3
3.4
Special Considerations
17
3.5
Safety
18
3.6
Summary
20
)
Chapter 3.0- Construction of Precast Segmental Span-by-Span Bridges
Page I of20
TABLE OF FIGURES
Figure 3.1
Figure 3.2
Figure 3.3
Figure 3.4
Figure 3.5
Figure 3.6
Figure 3.7
Figure 3.8
Figure 3.9
Figure 3.10
Figure 3.11
Figure 3.12
10
Figure 3.13
10
Figure 3.14
11
Figure 3.15
12
Figure 3.16
13
Figure 3.17
14
Figure 3.18
14
Figure 3.19
15
Figure 3.20
16
Figure 3.21
16
Figure 3.22
17
Figure 3.23
18
Figure 3.24
19
)
Chapter 3.0- Construction of Precast Segmental Span-by-Span Bridges
Page 2 of20
3.0
3.1
Introduction
Of all the types of segmental bridges, span-by-span bridges are possibly the simplest, and are often the
most cost effective. They are typically utilized for moderate span lengths up to approximately 150 feet,
although the construction method has been extended to spans upwards of 180 feet. For spans longer than
approximately 150 feet to 180 feet, other erection methods typically become more attractive. Even at span
lengths of 160 to 180 feet, span-by-span construction begins to lose much of its appeal. This is because the
erection trusses become larger and the construction method begins to lose cost effectiveness. Serious
consideration should be given to using span-by-span construction for any span length greater than 160 feet.
Span-by-span construction can be defined as construction where an entire span is erected and becomes selfsupporting, before erecting the next span. Typically, this involves supporting an entire span of precast
segments on a temporary erection truss. The segments are epoxy joined and the post-tensioning is stressed
to make the span self-supporting. The erection truss is then moved ahead to the next span and the erection
process repeated. The erection truss (or trusses) most often supports the segments under the wings, or
bottom soffit. Overhead erection trusses have also been utilized. Typical span-by-span construction can be
While many variations on the basic technique have been utilized, the common feature is that an entire span
is erected and becomes self-supporting, before erecting the next span.
Figure 3.1 - Underslung Erection Truss during Top-Down Erection of the Ernest Lyons Bridge
(Photo courtesy ofPCL Civil Constructors, Inc.)
Page 3 of20
Figure 3.2- Undendung Truss During Erection of the Mid Bay Bridge
(Photo courtesy of Figg Engineering Group)
Figure 3.3- Overhead Gantry during erection of the Seattle Sound Transit Project
(Photo courtesy of PCL Civil Constructors, Inc.)
Page 4 of20
Figure 3.4- Overhead Gantry during Erection of the C&D Canal Bridge
(Photo courtesy of Figg Engineering Group)
Page 5 of20
3.2
Of all the types of segmental construction, span-by-span constructed bridges are typically the most cost
effective. Historically, precast segmental span-by-span bridges have competed successfully in alternate
bids with cast-in-place concrete bridges, bulb-T bridges and steel bridges.
Most of the work associated with span-by span bridges is done in the precasting operations. The precasting
occurs in a casting yard and typically has no impact on highway or railway traffic occurring at the site of
the new bridge. Once the segments are cast, span-by-span bridges can be erected quickly. This minimizes
the time that construction impacts the site around the new bridge.
It should be noted that traffic can be maintained under the temporary erection trusses, once they are in
position for erection of a span. Typically the only restriction is that traffic is halted during the placement of
each segment, which takes only a small amount of time (typically 15-30 minutes). Although traffic can be
maintained under the trusses during erection, it should also be noted that care must be taken to protect
vehicular traffic from epoxy squeeze. This can be accomplished using various methods, the most common
of which is using tarps that hang underneath the segments during the epoxy operation. Examples of traffic
being maintained under and around spans being erected are illustrated in Figures 3.6 through 3.8.
Figure 3.6- Maintenance of Traffic for the Ernest Lyons Bridge Project
(Photo courtesy ofPCL Civil Constructors, Inc.)
)
Chapter 3.0- Construction of Precast Segmental Span-by-Span Bridges
Page 6 of20
Page 7 of20
Segmental superstructures are highly durable for the following reasons. First, the entire superstructure is
comprised of precast high performance concrete, cast in a controlled factory-like setting. Secondly the deck
is post-tensioned in the transverse direction, which minimizes cracking of this most exposed of bridge
structural elements. Finally, the superstructure is continuously post-tensioned in the longitudinal direction.
3.3
Closure Joint
Launching Truss
Page 8 of20
Figures 3.11 through 3.14. Typically, all but one segment is loaded onto the trusses before epoxy joining begins.
This is done because the truss deflections need to occur before the segments are epoxy joined, or else there is the
9 of20
Figure 3.12- Erecting Segments onto Trusses at Lee Roy Selmon Crosstown Expressway
(Photo courtesy ofPCL Civil Constructors, Inc.)
Figure 3.13- Erecting Segments onto Trusses at the Evans Crary Sr. Project
Chapter 3.0- Construction of Precast Segmental Span-by-Span Bridges
Page 10 of20
Page II of20
Page 12 of20
are sometimes prohibited until closure joints have been cured to a specified strength and final
stressing is complete. This is often a requirement because construction loads in adjacent spans can
cause vibration and movement to be transferred across the closure joint. If the closure joint has
not been properly cured, this vibration could jeopardize the structural integrity of the joint.
Page 13 of20
Closure Joints
Closure Joints
Temp. Supports
)
~
Page 14 of20
Stressing of the permanent post tensioning tendons is usually performed from a specially
fabricated stressing platform that is attached to the pier segment. The purpose of the stressing
platform is to provide a safe access for personnel to efficiently perform stressing operations.
The stressing platform is often equipped with chain-falls that are used to support the stressing
jacks from above. Figure 3.19 shows a stressing jack being supported from above by a chain-fall
during stressing operations.
Page 15 of20
)
Chapter 3.0- Construction of Precast Segmental Span-by-Span Bridges
Page 16 of20
It is also important to consider how and when construction materials and equipment are placed
inside the bridge structure. As with all segmental bridge construction, the span-by-span method
requires a significant portion of the work to take place from inside the bridge structure. This work
requires tools, equipment and materials to be transferred into and out of the bridge structure. Once
a span has been completed and the trusses have been advanced, it can be extremely difficult to
place bulky materials such as HOPE ducts, strand, temporary post-tensioning bars, etc. inside the
bridge structure.
It is often easiest to place construction materials inside the bridge through the open end of the
structure (leading edge of construction) when crews have access from the trusses and stressing
platforms. Likewise, it is always best to dispose of waste materials as each individual span is
completed rather than waiting until the end of the project when access is not readily available.
)
Chapter 3.0- Construction of Precast Segmental Span-by-Span Bridges
Page 17of20
Finally, a well thought out plan must be in place to remove the erection trusses after the fmal span
is complete. Many structures require that special erection sequences be used during the final span
to allow for removal of the trusses. If the fmal span to he erected is at an abutment, blockouts may
be required in the back wall to allow for permanent stressing or truss removal. Figure 3.23 shows
a typical situation in which the trusses must be removed from underneath the structure with very
little vertical clearance.
3.5
Safety
Safety is of paramount concern for all types of bridge construction. In addition to the typical
safety concerns on all construction projects, the span-by-span method of segmental bridge
construction has several unique safety challenges of its own.
As with all segmental construction, the leading edge of the structure during span-by span
construction is constantly changing. It is not uncommon for site conditions to change drastically
within one shift. For this reason, it is essential that strict procedures be in place to communicate
Once all segments have been epoxied together and all gaps have been closed, it is possible for
personnel to work inside the bridge and on the top deck without being tied off, provided that all
leading edges are properly delineated per OSHA guidelines. Figure 3.24 shows a typical situation
in which personnel are required to work near a leading edge (note all workers have harnesses and
Page 18of20
Figure 3.24- Personnel working near leading edge with safety harness
In addition to fall protection, another safety concern includes procedures for post-tensioning the
temporary and permanent post-tensioning tendons. Temporary post-tensioning bars and bar jacks
used during the epoxy squeeze operation are often heavy and awkward and must be lifted very
near the ceiling of the segment, many times in the corners. This activity is often very difficult and
can easily cause back injuries or muscle sprains if not well planned. If possible, temporary
stressing blocks should be designed to allow for easy access of personnel and equipment.
Permanent post-tensioning operations are performed using jacks with extremely high forces (in
excess of 500 tons). As a result, personnel working around this operation should be well trained in
the hazards associated with post-tensioning. For example, no personnel should be allowed directly
behind either end of the post-tensioning tendons when the stressing operation is taking place, in
case one or more strands should break. In addition, prior to starting the stressing operation, all
personnel in the area should be made aware that the operation is underway so that they know to
take the proper safety precautions. This is often communicated with a siren or an air horn.
In addition to the above mentioned concerns, thought should also be given as to how the leading
edge of the structure will be delineated after erection of a certain span is complete and the trusses
have been advanced forward. Several other crews are required to follow behind the erection crew
and it is important that the leading edges of the bridge structure be maintained until the permanent
traffic barrier or railing is in place.
Page 19 of20
3.6 Summary
Span-by-span constructed bridges are one of the most simple and cost effective forms of
segmental construction. They have successfully competed in alternate bids with cast-in-place
concrete bridges, bulb-T bridges and steel bridges. They are erected very rapidly. Due to the
speed of erection, and the fact that traffic can be maintained under the erection trusses (except
during times when segments are being placed on the truss), the use of span-by-span construction
can result in significant savings in maintenance of traffic costs and reduction in user delays. Spanby-span bridges incorporate high performance concrete and a biaxially, post-tensioned deck,
resulting in a very durable structure.
.)
Chapter 3.0- Construction of Precast Segmental Span-by-Span Bridges
Page 20 of20
TABLE OF CONTENTS
CONSTRUCTION PRACTICES HANDBOOK FOR
CONCRETE SEGMENTAL AND CABLE-SUPPORTED BRIDGES
CHAPTER 4.0 CONSTRUCTION OF PRECAST BALANCED CANTILEVER BRIDGES
4.0
Construction of Precast Segmental Balanced Cantilever Bridges
4.1
Overview
4.1.1
Basics of the Technique
4.1.2 Typical Segments Configurations
4.1.3 Segment Details
4.1.3.1 Cantilever Tendon Anchorages
4.1.3.2 Continuity Anchors
4.1.3.3 Temporary Post-Tensioning
4.1.3.4 Permanent Ducts
4.1.3.5 Web Keys
4.1.3.6 Flange Keys
4.2
Casting Yard and Transportation
4.2.1
Forms
4.2.2 Detailing and Workmanship
4.2.3 Geometry Control
4.3.4 Lifting Details
4.3
Typical Erection Cycle
4.3.1
Overview
4.3.2 Epoxy
4.3.3 Temporary PT
4.3.4 Tendon Installation and Jacking
4.3.5 Grouting
4.4
Erection Equipment and Methods
4.4.1
Crane
4.4.2 Beam and Winch
4.4.3 Erection Gantry
4.4.4 Hauler
4.5
Special Topics
4.5.1
Surveying and Deflections
4.5.2 Pier Segments
4.5.2.1 Cast-in-Place
4.5.2.2 Precast Pier Segment
4.5.2.3 Precast Shell
4.5.3 Expansion Joints
4.5.4 Mid-Span Closure
4.5.6 Temporary Access Openings
4.6
Engineering
4.6.1
Built-in Loads
4.6.2 Erection Loads
4.6.3 Cambers and Deflections
4.6.4 Temporary Post-Tensioning
3
3
3
4
5
6
7
7
7
9
9
9
9
10
13
13
14
14
15
16
17
18
19
20
21
22
27
27
27
28
28
30
31
33
37
38
38
38
39
39
39
Page I of39
TABLE OF FIGURES
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 2 of39
4.0
4.1
Overview
4.1.1
procedures. In balanced cantilever construction, erection progresses outwards from a central pier,
until adjacent cantilevers meet at mid-span. Segment erection generally progresses by erecting
symmetric pairs of segments, with one segment of each pair secured on opposite ends of the
previously completed structure with post-tensioning bars. Each pair of segments is then stressed
against the structure with cantilever tendons. These tendons are located in the top flanges of the
segments, and run from one cantilever tip to the other. As segments are added, the cantilever
tendons become progressively longer. A typical sequence for a three-span bridge is illustrated in
Figure 4.1.
_S!Wp:4
-- E:rt!ff $/tM;{'fi""""'
-_nilt;gl)'l>l6?s~l
- f'f,m r~s~
-_s.wr_.""IIJ ~ww~rml$~
rrlr :_=rrr
- ll~_.. t~'n!rrn
t>W!/.w tt~-ftod!
:
ttt
r:cn'!f_&H L#!!J!!t.f~- ~
-a
Jiwr"U
$1~ f'oiimrnmt~liNu-PY
- FI-e i~r"'y'p'J
:-~...""...J."--L--L...L..J_L.
~-F<r<-..r
StC(J~7-
~-~~
)
/
Page 3 of39
-sr<;ge 8
~ il--1~lf{lml$i,p{"'
l~"'!'f Slf~$
w
/l_>jld{W<J,
!flo/!""!- ~-futtirpiy Pt
~f=<-.1'~---~ll/ffr(""""
1 1
1 1
Si'tJJ1!:_l
rr. .
- itl<trfilti.r<sr"-:""u!JC:.., ,j"
'SltJIJlt
ro
.kmi>li U'"""--.oopl",quwo
I I
----
f
------
~folft>l"'_,lfilii-Tll,,dl~Col>ik>JIIff'r
'
Balanced cantilever spans are generally considered in situations where span-by-span erection is
impractical. Span lengths greater than 150' are typically prohibitive for span-by-span
construction, while precast balanced cantilever construction is effective for span lengths from !50'
to 450', and has been implemented for spans in excess of 500' in response to special
circumstances. Balanced cantilever construction is well adapted for alignments with tight
curvature. Erection gantries used for span-by-span erection, and particularly underslung gantries,
may not be able to simultaneously place an entire span when the transverse offsets due to
curvature are significant. With balanced cantilever erection, segments are placed individually,
bringing more flexibility and extended reach.
4.1.2
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 4 of39
~ooro
MULTI-CElL BOX
G
,_
14
SECTION A-A
~Rib
14
SECTION 8-8
SECTION
\~
7rJ
Closure Strip
\~
c-c
7r D
SECTION D-D
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 5 of39
I-rAlignment.KeY.
/[i:JpS1Bb-Csntii8Wif
/6
T~[JC/0~ DtJCts
~---SymmoiJicai.Aba'!f
!
0
~-
,,J-'
Top. SJab.-CBntuever./(
Tendoh AnchOii!ge
Tempgrory_pT Ba_~ \
; BottOin Slab_ ContiiJrilty
Tenrt_on Anchorage
\
\
co
!
Bottom SJab Continu;ty..!
-Tencjon Duct$
L AfignYTJentKey
4.1.3.1
These anchor the cantilever tendons that permanently secure each pair of tendons to the cantilever.
They are typically located in the top flange, in close proximity to the web/flange junction. There are
several different configurations for locating the cantilever tendons, illustrated in Figure 4.4.
Considerations for choosing the location of an anchorage include the maximum tendon size, thickness
of the top flange, interference with web stirrups, and cost and complexity of the forms. An additional
consideration that is growing in importance is the role of grouting and anchorage protection. This area
has seen new developments in recent years, and it is important that the anchorages are detailed to
accommodate the project grouting, inspection and anchorage protection requirements.
Page 6 of39
Top Slab
CantflwtJf Tendrm
Blister~
Bottom Slab
~
Swtlrm A-A
'--Cont!ooffy Tendon
Top Slab
Cantllwer Tendon
Bottom Slob
Contlnufty
Tendon
Bllste~
--\L~====.=~
~
Section A-A "--Continuity Tendon
OOUBl CART/lEVER TENDONS. FACE ANCHORED
Top Slob
ContiiENer Tendon
Contlfwer Tendon
Contloolfy Tendon
4.1.3.2
Continuity Anchors.
When two cantilevers are joined, continuity tendons are stressed across the completed construction
joint. At this stage, there is no access to the segment face, so the continuity tendons are anchored in
internal blisters. These are concentrated in the bottom flange, at the web/flange interface. Often there
are a limited number of continuity tendons in the top flange as well.
4.1.3.3
Temporary post-tensioning.
During a typical erection cycle, the segments are secured against the cantilever with post-tensioning
bars until the permanent tendons have been stressed. The various methods of accommodating these
bars are discussed below, but it is important that they are anticipated from the earliest stages.
4.1.3.4
Permanent ducts.
Precast segments for balanced cantilever construction are notable for the number of holes on the face
of the segment. Because each cantilever tendon stretches from end to end of the cantilever, segments
near the pier must accommodate nearly one set of tendons for each segment in the cantilever. Figure
4.5 illustrates a typical longitudinal post-tensioning layout, showing the concentration of tendons in the
top flange near the pier, and in the bottom flange near mid-span.
Page 7 of39
PLAN VlEW
Balanced cantilever construction relies primarily on internal tendons, and attention to detail in the
planning stages can simplify construction. In some cases, the contractor is permitted to adjust
tendon layout and local details provided the post-tensioning force and eccentricity is maintained.
Some typical considerations include:
I.
Proper spacing of the ducts. Duct spacing is governed by the requirements of the
AASHTO Specifications. and deserves careful attention. Ducts that are spaced
too closely together are at an increased risk of a pull-through failure where
transverse deviations occur. Ducts should be spaced at least one duct diameter
apart. This limitation is generally increased, due to practical considerations. Duct
holes in the bulkhead need W' or more between them to facilitate bulkhead
manufacture and segment production.
Ducts should be straight across all joints. When the segments are match-cast, an
important consideration is alignment of the ducts across the segment joint. This is
generally achieved by inserting a short, rigid mandrel in the ducts that cross the
joint. When a duct is curved, a smooth transition is difficult to achieve, and can
lead to unwanted kinks at the joint. It is frequently necessary to include tendons
that run at a slight angle to the bridge axis. This is easily accommodated- it is
only a curve that is to be avoided.
Page 8 of39
4.1.3.5
3.
4.
Web keys.
Shear keys are indentations along the mating faces of the webs. Their purpose is to ensure the transfer
of shear across the segment joint. As such, they should cover as much of the web as is achievable.
4.1.3.6
Flange keys.
Alignment keys are generally located in the top and bottom flanges of the segment. They are distinct
from web keys, in that they are not explicitly designed to transfer global shear across the joint. Rather,
their primary function is to ensure a proper fit-up between segments when they are erected in the field.
They are also important in transferring local shear in the top flange at the joints. Balanced cantilever
segments typically have large portions of the top and bottom flanges reserved for longitudinal ducts, so
consideration should be given in design and construction to accommodating both ducts and alignment
keys.
4.2
4.2.1 Forms
As for most precast segmental construction, the casting cell bulkhead is a critical part of the set up.
The basics of the bulkhead are covered elsewhere in this handbook, but there are a few features
specific to balanced cantilever bridges that are worth noting.
When span lengths are over 200 feet, it is frequently more cost effective to use a variable depth
superstructure. This helps to provide peak shear and bending capacity where it is needed most. At
the same time, it adds a layer of complexity to casting operations. Forms created for variable
depth segments need to accommodate changes in depth, and to do so without interrupting the
casting schedule. Common solutions include two-piece bulkheads, where the bulkhead can be
lengthened or shortened by bolting together different pieces, adjustable soffit tables, and
adjustable core forms. While one set of forms can accommodate a range of depths, it may be
economical to have one set of forms that can accommodate the deepest segments, and another set
to accommodate the shallowest. In this case, it is important to analyze the workflow to ensure the
forms work together without interruption.
While the fixed bulkhead is an important part of any casting cell, for a balanced cantilever bridge
it takes on additional significance as the template for all longitudinal post-tensioning. All tendon
ducts are secured to pre-existing holes in the bulkhead. This means that the bulkhead must include
a hole at every location where a tendon crosses the joint- not just for that particular joint, but for
all joints. It is beneficial to standardize and re-use duct locations in a post-tensioning layout, to
Page 9 of39
Balanced cantilever designs make use of internal blisters for anchoring continuity tendons and
temporary PT. While it is good to standardize the blister locations whenever possible, it is likely
that the locations of internal blisters will vary. Core forms should be able to accommodate the
addition or removal of an internal blister on a regnlar basis.
)
Chapter 4.0 -Construction of Precast Segmental Typical Balanced Cantilever Bridges
Pagel0of39
Figure4.7
-~"'=.,"
"""""'<!It~~~
Figure4.8
Fif!ure 4.9
Page II of 39
the duct is contained entirely within the toe of the blister, and it is important that the duct
placement in the yard matches this requirement, when applicable.
HALF SE:Cr/ON
Figure4.10
Figure 4.11
These examples of common critical details do not constitute an exhaustive list. It is important that
good engineering judgment be used in developing segment details, and that critical details are
clearly shown in the plans and accurately implemented in the casting yard. Specific requirements
for many of these details are given in AASHTO Specifications, their successful implementation
begins with careful detailing during design.
J
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 12of39
misalignments.
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 13 of39
Page 14of39
4.3.2 Epoxy
Epoxy is now required for all segment joints, and has always been an AASHTO requirement for
joints with internal tendons. In many jurisdictions, epoxy is required on both faces of the
segments to be joined. The main purposes of the epoxy are to provide a strong, impermeable seal
at the joint to prevent corrosion in the tendons, and to lubricate the joint during installation. For
balanced cantilever construction, the epoxy can enter many of the empty ducts when the segments
are stressed together if adequate measures to protect the duct are not taken. It is important to swab
the ducts after erecting each segment, otherwise the epoxy can block the duct and hinder tendon
installation for subsequent segments.
_)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 15 of39
4.3.3 Temporary PT
Temporary PT is generally a necessary part of a typical erection cycle. In most cases, the
temporary PT will take the form of high-strength bars placed near the top and bottom flanges. The
purpose of the temporary bars is twofold. First, they provide a means of securing the new segment
to the cantilever, so that it may be released from the lifting equipment. Second, it provides a means
of compressing the wet epoxy. The epoxy should be compressed to a minimum of 40 psi during
the cure time, which can vary depending on product and temperature. The post-tensioning bars
should provide a minimum compression both while the segment is supported only by the bars, and
when the cantilever tendons have been stressed.
There are three main methods of incorporating the temporary PT into the segment. The first is via
small blisters cast on the interior of the box girder. They are typically located as shown in figure
4.16. This option allows easy access to both ends of the bars, so the bars can be removed andreused on later cycles. To be re-used, the bars must be stressed to a fairly low level, typically 50%
of their ultimate strength. This method is very efficient during construction, and requires a limited
quantity of bars. However, the forms and casting operations see a small impact due to the
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 16 of39
Stresslrq
!A"'
Block--out
1'CWp("
(lypJ
\
'Lr
m
ry
Post-Tenslonlrq
Bar
INTERNAL TO CROSS-SECTION
SECTION A-A
The third method consists of using a bracket attached to the segment to anchor the bars. This
functions much like the first option, but eliminates the blisters from the interior. However, careful
attention must be paid to proper detailing of the brackets to avoid local spalling. Some operations
are added to the typical cycle to secure the brackets in place for each segment.
Page 17of39
4.3.5 Grouting
There is a growing recognition of the important role that grouting procedures play in the long-term
performance of segmental bridges. For a balanced cantilever bridge, it is beneficial to refine the
typical grouting operations.
As noted above, tendons are installed and stressed on a daily basis during cantilever erection.
However, it is generally best to wait until the entire cantilever is complete before grouting any of
the cantilever tendons. This is because there is often an empty duct directly adjacent to each
tendon when it is installed. If that tendon were grouted, there would be a risk of the grout crossing
over to the empty duct. This would result in blockages when later tendons are installed if the
empty ducts are not swabbed clear with each grouting operation
Depending on erection speed and local conditions, the allowable period for leaving a stressed
tendon ungrouted may be exceeded. In this case, a corrosion inhibitor can be used to extend the
period before grouting. In all cases, care should be taken to assure that water is not allowed to
stand in the ducts during cantilever erection. In cases where roadway grade does not provide
convenient drain points, grout inlets can be used to verify conditions in ungrouted tendons and
blow out standing water if necessary.
Cantilever tendons are often very long and flat, with little variation in elevation other than
roadway grade. This means that there are few high or low points where grout vents would be
required. For longer tendons, it is worthwhile to install supplemental grout vents along the length
of the tendons to improve grouting results.
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 18 of39
4.4
Up-front cost
Operating height
Lifting capacity
Terrain I Access
Required safety factors (for example, when crossing a railway)
Erection sequence
Loads on the structure
Structure capacity
tl
,I
=
II
llil
!)
I I I I I I I I
"'TJ,
I I I
'I'
I II
mg
".1/1".1/1".1/1".1/1".1/i'-.l/1\l/
\1/ ~l/l\l/l\l/1"-1ffil/l".l/l".l/l".l/l),._
tL
C::J
C::J
C:J
JJ avERHEMJ GANTF
)
Chapter 4.0 -Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 19 of39
4.4.1 Crane
Under the right circumstances, cranes can be used to place segments at the cantilever tips. This
can be a very cost-effective option, as cranes are readily available. It also allows the possibility of
erecting multiple cantilevers at once, offering savings on schedule.
However, the main constraint on crane erection is access. Balanced cantilever bridges are often
selected in response to inaccessible terrain, be it over a highway, water, or an environmentally
sensitive area. Since the crane will be used to place the segments in their final position, it must
have access along the entire alignment.
In some cases, this can be avoided by using a light crane positioned on the bridge deck. A ground
based crane can be used to place segments on the deck, typically at the pier. The deck mounted
crane then picks up the segments and carries it out to the tip. This technique was used on the
Sound Transit balanced cantilever spans (Figure 4.21), and is generally only available for
relatively light sections.
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 20 of39
of this is the San Francisco-Oakland Bay Bridge Approaches, pictured in Figure 4.22.
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 21 of39
Some considerations for beam and winch systems include the access and the height. For a fixed
system, access is required at every location along the alignment to deliver segments to the tip. In
addition, hoisting segments over significant heights can be time consuming, and have a negative
impact on the erection cycle.
Some specialized equipment has been built to overcome these difficulties. Specialized lifters are
able to move along the deck to hoist segments at an accessible location. They then deliver the
segment to the cantilever tip for erection. These are generally custom built to suit a specific
project. An example is the lifter used in the Dallas High-5 project, shown in Figure 4.23 below. It
should be noted that this method may present some engineering challenges during erection, since
the loaded hauler will occupy many different positions. Supplemental methods of reducing
demand on the substructure, such as tie-downs or counterweights may be necessary.
\'
Page 22 of39
The impact of schedule may also be a deciding factor in selecting an overhead gantry. Where the
structure is relatively long and there is a reasonable repetitiveness of spans, a gantry can be a fast
and efficient means of erecting cantilevers. However, gantries are restrictive, in that they impose a
linear erection sequence on the project. It is not possible for a single gantry to erect on multiple
piers, as would be the case with crane erection.
With many of the gantries currently being designed and/or fabricated overseas, other issues should
be considered including lead time, import challenges, quality control issues, design criteria and
standards, replacement parts and equipment training.
~ -~
Rear Support
II..
'---'
F """"-"
cp
L'-'
A! Two-Spans l..ong
Slobllriy Arm-.
j
.....,_,
T~/1'-
-J/I'W\1"
."\\.
'---'
"-Rear Support
]),_
1)'---F""-"
.....,_,
L'-'
B! Less Than Two-Spont>
Loll(/
After the pier segment is in place, either by setting it if precast or by casting it in place, the
overhead gantry is positioned as shown in Figure 4.24 to begin typical segment erection. The
gantry rests on two supports and is, therefore, statically determinate. The center support is
anchored on the pier segment where the cantilever is being erected while the rear support is tied
down at some point on the previous cantilever. The segments to be erected are either transported
from the rear of the gantry along the completed structure or lifted directly from below depending
on the conditions of ground or barge access at the site. In the former case, the gantry supports
must be transversely spaced such that a segment, when rotated 90 to the bridge, may pass
between them. A trolley which generally rides on the upper or secondary chords of the launching
girder is used to transport the segment and to position it for erection.
Page 23 of39
\
Figure 4.25- Segment Rotated 90" between Truss Chords, Otay River Bridge
After erection of a particular cantilever is completed and any span closures are made, the gantry is
launched to begin cantilever erection on the following pier. The exact sequence involved depends
largely on the gantry being used and the span configuration of the bridge under construction. If the
gantry is of sufficient size relative to the forward span length, shown in Figure 4.24A, it may be
possible to place the pier segment for the next cantilever without changing the longitudinal
positioning of the gantry. If the nose section of the gantry is shorter than the forward span length
as shown in Figure 4.24B, some sort of two-stage launch or temporary intermediate bent must be
used.
After the pier segment is in position, the gantry can be advanced until the central support is located
over the pier segment. The support is then anchored to the pier to begin the next cycle of typical
segment erection on the new cantilever.
The method by which a launching gantry advances relative to the bridge depends on the overall
design of the gantry and the particular construction application. In some designs, the gantry is
supported on temporary front and rear supports, and then prepared to launch by freeing the
primary (center) support. The gantry rolls over the front (nose) support by means of a trolley fixed
to the support. It may also roll over a similar trolley on the rear support, which has typically
already been advanced and reattached to the deck near the center support. Alternately, for this type
of gantry the rear support may be attached to the launching gantry itself. In this instance the rear
support would actually roll over the completed deck on rubber tires or a rail system. In other
gantry designs that feature two moveable primary supports, the gantry is supported on temporary
supports only long enough to advance the two primary supports along the completed deck. Once
the primary supports are repositioned and reengaged, the gantry rolls over trolleys fixed to those
supports.
Chapter 4.0 -Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 24 of39
The evolution of launching gantries has recently been towards girders whose total lengths are
equal or slightly greater than twice the typical span length (Figure 4.24A). This has been made
possible largely due to the more efficient use of materials than the first-generation gantries, and
due to a recognition that additional bridge reinforcing and associated labor is more expensive over
the course of a large project than additional gantry length. As is demonstrated in the schematics in
Figure 4.24A, the longer girders offer the advantage of ensuring that loads transmitted to the
superstructure remain over the piers or at ]east in the very near vicinity. Pier segment p1acement
and girder advancement operations are simplified by allowing the simultaneous placement of the
typical segments of a cantilever and the pier segment at the following cantilever pier location.
Page 25 of39
As a practical matter, the tendency is to size a gantry based on twice the "typical" span length.
This keeps the gantry to a reasonable length to facilitate erection and launching operations for the
majority of spans. For span lengths in excess of the typical span, special, though not necessarily
complex, procedures will need to be carried out to allow the gantry to be launched from one pier
segment to another.
!
Chapter 4.0 -Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 26 of39
4.4.4 Hauler
In some cases. a specialized segment hauler may be used to transport segments at the erection site.
This is sometimes used to deliver segments over the completed structure to the erection gantry.
When this is the case. it is advantageous to match the width of the hauler to the webs of the box
girder. The loaded hauler places significant concentrated loads on the bridge. and local bending of
the top flange should be minimized. Care should be taken to limit the path taken by the hauler to
avoid overloading the structure.
Surveys should be carried out on a daily basis, and should always be performed before or near
sunrise to avoid tip deflections associated with differential temperatures. The survey data should
be used to compare the projected position of the cantilever tip to the target position for that stage.
Note that the target position may vary from day to day as the structure is loaded -it will not
necessarily coincide with the final alignment.
Page 27 of39
The construction engineer plays an important role in this effort. The construction engineer should
calculate the deflected shape of the cantilever at multiple phases during erection. This may
include the completion of each cycle, before and after stressing PT, and before and after major
shifting major equipment (such as launching an erection gantry). These deflections can be
combined with the actual casting data by the site personnel, and compared against the daily
surveys.
in general use.
4.5.2.1 Cast in Place.
In this case, the entire segment is cast as part of the substructure. The great advantage of this
method is in weight. Since the segments with a thickened diaphragm can be the heaviest of the
project, using a cast-in-place pier segment can reduce the heaviest load for transportation and
erection equipment. This frees the designer to use a larger diaphragm, which is often
advantageous in seismic regions with heavy column reinforcement that must be continuous into
J
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 28 of39
Figure 4.30- First Precast Segment Supported Prior to Casting Closure ]oint,
Otay River Bridge.
Page 29 of39
.~
There are two main advantages to precasting the pier segments. The first is that the exacting rebar
placement and concrete operations take place in the casting yard, where the conditions are much
more controlled. The second is in segment placement during erection. The need to have a CIP
joint between the pier and first typical segment is eliminated, greatly enhancing the erection speed
of a typical cantilever.
In most cases, a precast pier segment is supported on bearings. This means that structure stability
is an important consideration during construction. The large unbalanced loads that are a necessary
part of balanced cantilever erection can be difficult to accommodate with a bearing connection in
the absence of a gantry designed to provide stability. Supplemental towers, tie-downs, brackets,
or combination are needed to provide global stability, as shown in Figure 4.33. The cost of these
stability structures can become substantial as the unbalanced loads increase.
)
Chapter 4.0 -Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 30of39
I I
I
I
X
X
i
i
I
V'-'"'P{rl Frame
I
Tomp Foollrg
DHJJXIWAHY TENSION TIES
Page31 of39
This method brings with it both the advantages and drawbacks of conventional methods. The
chief advantage is the ability to create a monolithic connection with the pier, while still
maintaining a match-cast joint at the pier segment. This provides the global stability of a CIP pier
table, without sacrificing the speed of segment erection.
However, many of the challenges of CIP work remain. It is necessary to have continuous rebar
between the precast shell and the CIP diaphragm. This often means a large number of rebar
couplers on the interior face of the shell. Complex rebar and higher-strength concrete must be
placed on site. An additional consideration is the degree of grade and crossfall. The precast shells
must be supported accurately in order to set the alignment correctly for the entire cantilever.
Placing the segment and tying the supplemental rebar can be a challenge when the segment is at a
steep angle to the vertical column steel. In situations where these challenges can be met, the
precast shell method can offer an advantage in erection speed.
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 32 of39
Figure 4.36- Installation of Supplemental Rebar Inside Precast Shell, Dallas High-S
This is achieved by blocking the two halves of the hinge together during cantilever erection. The
two hinge halves are effectively treated as a single segment, and temporary cantilever tendons are
installed through them to erect the remainder of the cantilevered segments. Once closure has been
cast for that span, the temporary tendons holding the hinge together are severed, and the blocking
removed.
It should be noted that this method often requires tightly congested post-tensioning and
reinforcement in the hinge segments. If this method is adopted, constructability should be an
important consideration at every stage of design and construction.
Page 33 of 39
\
'
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 34 of39
The second method is the mid-span hinge. In this method, the joint is located in the middle of the
completed span, between two adjacent cantilevers. Continuity is created by steel beams that cross
the joint, and are anchored in both sides. There are several possible configurations for the support
of these beams, but they are all intended to transfer moment as well as shear, while allowing
longitudinal movement. Transfer of moment is important, because without moment continuity the
angle break under creep redistribution and live load would be unacceptable. The beam
configuration for the Otay River Bridge is showo in Figure 4.39 below.
)
This method enjoys some advantages due to its compatibility with the balanced cantilever erection
sequence. After an entire cantilever is erected, the beams can be lifted into position, and pushed
back into the completed box girder. The adjacent cantilever is then built, and the beam is pushed
back across the expansion joint and secured in its final position.
This method does require special diaphragm segments, whose purpose is to anchor the steel beams
to the concrete box girder. As with any diaphragm segment, weight is an important consideration.
Beam installation is performed inside the concrete box girder, which can limit the space available
for work. A generous allowance for construction tolerances for all of the various components
(beam, segment, bearing, geometry) will help to avoid placement problems in the field.
The beams serve as an important structural member, and their long term performance should be
considered during design. This would include issues such as access and bearing replacement.
Awareness of the maintenance requirements should persist during construction, when the long
term impact of proposed modifications should be weighed against any gains to constructability.
)
Chapter 4.0- Construction of Precast Segmental Typical Balanced Cantilever Bridges
Page 35 of39
The third method is to place the expansion joint at the columns. This can be achieved by building
the spans adjacent to the expansion joint on falsework, when that option is available. However,
balanced cantilever construction is often selected to avoid the need for falsework. In these cases,
temporary post-tensioning can be used to erect the spans adjacent to the expansion joint in
balanced cantilever.
With this method, the pier segments at the expansion joints are blocked and secured together to
create a monolithic pier segment. The segments on either side of the joint are equipped with ducts
for temporary cantilever tendons. These spans can be built out from the expansion joint pier in
typical balanced cantilever fashion, held in place by the temporary tendons. Once continuity has
been achieved on both sides, the temporary tendons are cut, and the blocking removed. This
method is generally applicable only for shorter spans.
Page 36 of39
Page 37 of39
4.6
Engineering
Construction engineering is an important feature of balanced cantilever construction. While
construction schematics are typically included in a design, the wide variation in schedule, methods
and equipment available make it unlikely that the contractor's chosen method will match the
assumed conditions. Listed below are some of the tasks typically associated with construction
engineering for a precast balanced cantilever bridge.
Page 38 of39
Page 39 of39
\,
/
'
TABLE OF CONTENTS
5.0
5.1
Introduction
5.2
Construction Methods
Page I of28
TABLE OF FIGURES
Figure 5.2
Figure 5.3
Lahn Bridge
Figure 5.4
Figure 5.5
Figure 5.6
Figure 5.7
Figure 5.8
Figure 5.9
11
Figure 5.10
11
12
Figure 5.12
12
Figure 5.13
14
Figure 5.14
14
Figure 5.15
15
Figure 5.16
15
Figure 5.11
Figure 5.17
16
Figure 5.18
16
Figure 5.19
17
Figure 5.20
17
Figure 5.21
18
Figure 5.22
20
Figure 5.23
21
Figure 5.24
The launching rams [G2] have pushed the traveler forward to the
leading edge of construction. The front bogey assembly
[G4] is on the main rails
Figure 5.25
22
Rear tie-down system for one main frame [G3], rear bogy
assembly [H1], rear tie-down bars, and pull-down ram [H2]
23
Figure 5.26
25
Figure 5.27
26
Figure 5.28
27
Figure 5.29
Abutment Segment
28
/
Page 2 of28
5.0
5.1
Fll(EQ POINT
When two opposing free cantilever structures are attached as a single structure and erected at the same
step, it is termed "balanced cantilever construction method" as shown in Figure 5.2.
1-----"---l_
FORM TRAVElER
--'---_-.....,._'r-_--'-_
_,_L
_j,
Page 3 of28
In basic terms, cast-in-place (c.i.p) construction denotes a construction process where the segments are
progressively cast on site at their final position in the structure. In comparison precast construction the
segments are prefabricated at a casting plant, either on site or at a remote facility, transported to the
project site and erected as a completed unit in the final position.
With cast-in-place construction the bridge segments are built in place, in progressive increments; one
segment at a time. The manufacturing switches from a controlled enviromnent (a casting yard) to the
superstrocture itself. The segment forms cantilever from the previously cast segment and remain in
place until the new concrete segment has achieved sufficient strength so that it can be post-tensioned
and permanently held in place to the previous segments cast behind it.
The application to cast-in-place reinforced concrete bridges took place for the first time with the
constroction of a 68 meter span bridge across the Rio de Peixe in Brazil in 1930. However, the
cantilevering method for reinforced concrete never gained popularity due to excessive deflection and
heavy reinforcing.
Dr. Ulrich Finsterwalder of the firm Dyckerhoff & Widmann AG (DSI International) successfully
applied post-tensioning to a cast-in-place concrete bridge using the balanced cantilever method
with constroction of the Lalm Bridge at Balduinstein in Germany in 1950-1951, after World War II
(see Figure 5.3). The bridge is fixed at both ends and has a span length of203.65 feet (62.09m).
This bridge is considered the pioneer of modern long span segmental concrete bridge constroction.
\,
deep valleys and rivers where placing temporary supports is not possible of cost prohibitive. The only
drawback of the system is the time required for superstructure construction. While the time required
for constroction of a typical segment (usually about 5 days, however this can vary considerably
depending on the learning curve) is much longer than precast segmental construction, this should be
considered in the context of the longer span lengths for which cast-in-place balanced cantilever
construction is used. The span length for cast-in-place segmental bridges is a function of several
different factors; the economical range is about 70 to 250m (230 to 820ft) with major cost factors
being the large pier tables and the specialized equipment required to construct the segments. At the
beginning of superstructure construction, there is a learning curve for the construction crew which
results in a much slower pace of construction. The learning curve effect may be particularly apparent
during construction of the first pier table. Sufficient consideration should be incorporated in the
project schedule for the learning curve of the first pier table and initial segment casting cycle.
Page 4 of28
d}
)
Chapter 5.0- Construction of Cast-in-Place Balanced Cantilever Bridges
Page 5 of28
5.2
Construction Methods
In cast-in-place balanced cantilever construction, a starter segment is first constructed over a pier
colwnn as shown in Figure 5.5 and Figure 5.6. The starter segment over the pier is called a piertable. From this starting point, the bridge can be built from a single pier or multiple piers at the
same time using form-travelers moving toward mid-span. At mid-span, the two adjacent cantilever
tips are connected to make a continuous structure with a closure pour segment. Typically a formtraveler or steel strong backs are attached to both cantilever tips to prevent differential movement
during the closure pour. These attachments can also correct any horizontal misalignment as well as
elevation ofboth tips (see Figure 5.7).
-~
/
Page 6 of28
Page 7 of28
In classical cantilever bridge construction, segments are placed symmetrically from the pier table with
typical segment lengths ranging from 10'-0" to 16'-0". Segment lengths longer than 16'-0" are rarely
used due to longer segments producing large out ofbalance loads during construction. In addition, 16'0" segment form-travelers are widely available on the market, and can often be reused without ordering
a new one. In special cases, cantilevering with form-travelers longer than 16'-0" has been
accomplished.
The cantilevering process is not possible without the use of a specialized piece of equipment; a form
traveler. The form travelers are a self-launching structural system that is supported off the leading
cantilever tip and is used to support the segment formwork and weight of the newly cast segment. The
form traveler remains in place until the new segment has gained sufficient strength to be posttensioned to the previous cantilever segments where the segment will remain in its final structural
position. Provisions are made that allow the form traveler to move forward, at an increment of one
segment length at a time, as the cantilever is constructed. A detailed discussion of form travelers is
provided in this chapter
The balanced cantilever method of construction is the most common technique for cast-in-place
segmental bridges. Several advantages have contributed to the success of the balanced cantilever
method. One of the most important advantages is the repetitive cycle that is used to construct each
segment, which leads to efficient and rapid construction of the superstructure. This method is very
feasible for long span bridges which are located high above the ground, eliminating the use of
extensive falsework. Access from the ground is only necessary for construction of the abutments and
piers. Several creative and cost saving methods for constructing the superstructure are available when
terrain under the structure is inaccessible or particularly difficult to build from.
Long span balanced cantilever bridges require post-tensioning for support during construction and
under service loading after the structure is completed. During construction the cantilever am1
increases in length with the casting of each additional segment and large tension stresses are applied to
the top deck of the segment. The stresses are smallest at the cantilever tip and increase to a maximum
adjacent to the pier. A series of post-tensioning tendons, called cantilever tendons, are located in the
top deck to resist the tension and keep the cantilever tip from sagging. These tendons tie back a newly
cast segment to the existing structure and must be stressed from the leading cantilever tip each time a
new segment is cast. This concept is best illustrated with the diagram provided in Figure 5.8. The
majority of tendons are located at the point of maximum stress and decrease at the end of a completed
cantilever ann. Each cantilever tendon passes through a thin metal conduit, referred to as a duct, that
stretches from one end of the cantilever tip to the other; each tendon is located in a separate duct. The
cantilever tendons increase in length with the addition of new segments and reach their maximum with
a completed cantilever.
When two adjacent cantilever arms are connected with a closure segment a span is complete and
continuity is provided from pier to pier. After continuity is achieved a redistribution of stresses takes
place reducing the values applied during construction. The span must withstand the self-weight of the
structure combined with design loads such as vehicles, temperature, future overlays and snow. Large
tension stresses are now applied to the bottom deck of the cross-section. The stresses are smallest
adjacent to the pier and increase to a maximum at mid-span. Continuity tendons are located in the
bottom slab to balance the tension stresses. Higher concentrations of continuity tendons are required at
the location of maximum tensile stress and decrease towards the piers. Continuity tendons are stressed
at concrete anchor blocks inside the box segment after the closure pour is made. Figure 5.8A
illustrates this principle.
Page 8 of28
Bottom
slab of
closure
A pair of
continuity tendons
is anchored at a
concrete block cast
existing structure
Maximum number of
tendons is at the point
of maximum stress
Page 9 of28
Major construction loads considered in cantilever construction are as follows (see Figure 5.9):
Form-travelers
Construction equipment
Construction materials
Windloads
Seismic loads
For horizontally curved superstructures, out of balance loads also occur in the transverse direction. For
this reason, a three-dimensional structural model is required for horizontally curved structures.
Columns, footings, and foundations are critical elements of the cantilever structure to be checked and
designed for construction loads. In addition to serviceability and strength, the stability of the overall
structure must be checked. Due to large out of balance loads, it is common practice to provide
temporary supports to resist out of balanced forces. Temporary supports provide the required structural
stability during construction as shown in Figure 5.10. Stability during construction may also be
provided by double-walled piers as shown in Figure 5.11, or by a monolithic connection between the
pier and superstructure as shown in Figure 5.12.
\,
Page 10 of28
II#/
Figure 5.10- Temporary Supports During Construction, Puyallup River Bridge, Washington
Page II of28
Figure 5.11- Double-Walled Pier Superstructure Connection, Lower Screwtail Bridge, Arizona
Figure 5.12 -Jl1onolithic Column Superstructure Connection, Tsable River Bridge, Vancouver, BC
Page 12 of28
Construction Sequence
Segment dead load is a large source of out of balance moment during construction of the substructure.
These loads can be reduced using an asymmetrical pier-table as shown in Figure 5.13. The same result
may be obtained by using a symmetrical pier table and construction of one-half segment on one side of the
pier table as shown in Figure 5.5 and 5.14. The difference in cantilever length is about half of one typical
segment length. In turn. full segment lengths will be constructed on each side of the pier table, producing
out-of-balance loads at each stage of about half the segment. In addition, the out-of-balance load due to the
form-traveler is also reduced, due to a shorter lever arm.
Once the pier table has been placed, cured and formwork removed the assembly of the first traveler can
take place on top of the pier table. It typically takes approximately 2 weeks to assemble the first traveler for
one end of the cantilever and another 2 weeks to assemble and attach all of the associated soffit, side and
ceiling forms with hardware to the traveler prior to beginoing the initial casting cycle. The casting of the
initial segment takes another 2 to 3 weeks (depending on the amount of reinforcing steel and posttensioning to be installed). Once the first segment has been cast and the traveler is advanced out on the
cantilever at this point in time this will provide sufficient room on top of the pier table to allow the
assembly of the second traveler on the opposite end of the cantilever. Again, the similar time of2 weeks
must be allowed to assemble the second traveler and another 2 weeks to attach all of the associated forms
and hardware prior to the beginoing of the casting cycle.
Typically one working cycle can be accomplished in one week after the learning curve has passed. It is
noted that the cycle can vary and is dependent on many variables. ) .. Pier tables are normally constructed
in three to four months. One advantage to this type of construction is the repetition of activities over and
over until the bridge is completed. Over the course of these cycles, the contractor has the opportunity to
correct and improve procedures. The minimum pier table length is approximately 32 feet.
However, NRS ofNorway has designed a special form-traveler which can accommodate a minimum length
pier-table of 10'-0" as shown in Figure 5.16.
The weight of a typical form-traveler including formwork ranges from 160 to 180 kips for a single cell box,
and can reach 280 kips for wider twin cell boxes. The single cell box consists of two traveler frames while
a two-cell box has three frames .
.Form travelers are usually obtained from subcontractors, and are provided with a detailed checklist of the
steps involved in operation of the form traveler. This checklist must be consistently observed during the
construction process.
Form traveler installation and operation on the 1-895 Bridge over the James River in Virginia is illustrated
in Figure 5.17 through 5.21. The main span length is 672 feet.
Page 13 of28
)'
Page 14 of 28
Figure 5.15- Deck Reinforcement and Tendon Ducts, Wakota Bridge, Minnesota
(photo courtesy ofParsons)
lC'..V(M\1:1)
(3m MIN}
P!iASE_1
{CO_NS_T/WCl'fMWlE!lSj
PHASE3
(SPunllltl OF TIIAVELERS)
PHASE4
(READY FOR NORWJ. PROCEot/RE)
Page 15 of28
Page 16 of28
Page 17of28
Page 18 of28
Page 19 of28
~
,...,
.~ --
------
!"~:-.:.:
\
'
'
~\
\
\
'
''
:'
!
!
[g
Traveler Components
~- Primary structural system
1. front truss
~main frame or rails not shown in this view
E. Bottom platform
4. front suspension bars
~bottom platform framework and side work
platform
6. exterior wall formwork
6.
F..
supporting framework
overhang formwork and work platform
Work platforms
1. upper work platform
Figure 5.22- End view of traveler looking from the leading end of construction
Bottom Platform
Bottom platform carries the concrete weight for the bottom slab and walls, and provides a safe staging area
to work from. The bottom platform is held in place on the trailing end to the previous segment with a set of
4 high strength bars that pass through sleeves in the bottom slab. The leading edge is supported with 4 bars
suspended from the inside spreader beams. It is noted that when the bottom platform is ready to be moved
ahead the trailing end must be released from the existing segment or else it would be restrained from
moving. A secondary set of bars, one each side, are suspended from the rear truss and connected to the
bottom platform allowing it to move freely during launching to the next position.
)
Chapter 5.0- Construction of Cast-in-Place Balanced Cantilever Bridges
Page 20 of28
l~
::! ~
__________________________
------------------ ::::{.,
,,,,
'
!
!
!
------::::::::::::::::::::::::J'
Next segment
to be cast
Traveler Components
A. Primary structural system
I. front truss
2. main frame
3. rear truss
F.
Workplatforms
I. upper work platform witb post-tensioning
jack in place
2. lower work platform
3. rear trailing platform
G. Launching system
1. main rails and rear tie-down bars
2. hydraulic launching cylinders
3. rear bogey assembly
4. front bogey
H. Tie-down system
1. rear tie-down bars through concrete slab
2. pull-down ram to release tie-down bars
Interior formwork assembly supports the concrete load between the web walls. Two high strength bars are
suspended from a set of spreader beams. These bars are connected to a framework running longitudinally
inside the box segment. The rear end of the frame is tied down to the previous segment with 2 bars similar
to the bottom platform. The interior beams are a two-part system: they provide vertical support for the
crown form and provide a rail for the interior wall support. The interior walls are supported on a frame
suspended on rollers that slide independently along the interior beams. When the form traveler is launched
to the next position it is necessary to leave the interior wall forms at the previous location. The web walls
Chapter 5.0- Construction of Cast-in-Place Balanced Cantilever Bridges
Page 21 of28
of the segment contain heavy vertical reinforcing that can only be installed from the interior of the girder,
which would not be possible with the wall panels in place. When reinforcing installation is completed the
interior wall panels can be advanced forward on the roller assembly.
Cantilever Formwork Assembly
Cantilever formwork assembly supports the cantilevered portion of the top deck outside each web wall and
provides access for construction activities such as post-tensioning of the transverse tendons. Two bars on
the front end of the traveler are suspended from a spreader beam and connected to the front end of a frame
running longitudinally under the overhang. The cantilever assembly includes a system for supporting the
exterior web wall form. The trailing end of the assembly is supported at two locations. It is tied down to
the previous segment and is suspended from the rear truss with a high strength bar.
Launching System
The complete traveler assembly is supported on a pair of rails located directly above the girder web walls
for direct load transfer into the superstructure. The rails provide a smooth surface to roll the traveler
forward removing any irregularities of the concrete deck. Launching the form traveler system forward is a
two step process: first the rails are 'pulled' forward 5.0m to the next segment position stopping just short of
the leading edge at the cantilever tip, next the complete assembly is 'pushed' forward 5.0m over the rails.
Details of the launching components are provided in Figure 5.24. The system is moved forward in 900mm
increments with a set of hydraulic cylinders pinned between the main frame of the traveler and rails. The
traveler and rails are launched with the same set of cylinders. The length of the launching cylinders limits
the distance traveled with each increment.
)
Chapter 5.0- Construction of Cast-in-Place Balanced Cantilever Bridges
Page 22 of28
Tie-Down System
When the traveler is advanced to the next segment position, 5.0m away, it must be restrained from tipping
over. The rear tie-down system is the main structural support that will restrain any tipping forces during
concrete placement. Details of this system are provided in Figure 5.25. The rear tie-down assembly is
restrained with 4 high strength bars, one set for each main frame. The tie-down bars are preloaded to a
specified force to prevent the traveler from moving during concrete placement. The front end of the
traveler must be lifted off the rails so it will not roll forward. Located at the front edge of the cantilever tip
and below the front bogey is the front leveling ram. This rani lifts the front rollers off the rails and supports
the traveler weight during concrete placement.
With the traveler secured, adjustments are made to set the segment formwork to the correct elevation.
Elevations are calculated with the geometry control manual by determining the segment number and
construction step at that particular phase in construction. The project surveyor under strict tolerances
surveys the new position. Adjusting the length of the front suspension bars changes the leading formwork
position. Center hole jacks are used to make large adjustments and turning the appropriate nut with a
wrench can set final elevation. Additional task-specific operations are required to complete casting cycles
that are not directly related to operation of the form traveler; these activities are discussed later in this
report.
Page 23 of28
The following steps summarize the launching process; (the numbered components are referenced in
Figures 5. 22 and 5.23):
I.
Launch the main rails to next 5.0m segment position, flush with tip of cantilever [Gl]
2.
Tie down rear end of rails with high strength bars [Gl]
3.
Lower front leveling ram so that front bogey rollers are in contact with rails [G4]
4.
Release all rear ties of the bottom platform and top deck form support [C3, D2]
5.
Actuate rear pull-down ram to engage safety clamp and release 8 tiedown bars [HZ]
6.
7.
Launch traveler forward, install and pre-load 8 tiedown bars at next segment position [HI]
8.
Install and stress rear ties of bottom platform, overhang and iop deck form [C3, D2]
9.
Interior form system is left behind and rolled forward later to facilitate reinforcing installation
[Dl]
Work Platforms
An upper wmk platform is suspended from the front truss by a series of high strength bars and a lower
work platform is supported from a fixed channel support to the bottom platform. The work platforms
provide access for construction of segment bulkheads, post-tensioning from the leading edge and access to
the traveler components. Figure 5.26 provides an end view of the traveler.
Page 24 of28
-~
I
Page 25 of28
Overnight: Cure
elevations. Cast
new segment with
concrete to achieve
sufficient strength
Day I: Stress
transverse tendons
in top slab. Stress
cantilever tendons.
Day I: Release
formwork and
traveler tie-down
s. Launch main
~lo ~ no n~o;,;~n
Day4:
Install
longitudinal
tendon ducts and
tendons. Install
Day 4: Advance
interior formwork,
install wall ties and
rebar in top slab
Day 3: Install
bulkhead. Install
rebar in bottom
slab and web
walls.
Day2:
Advance and
anchor form
traveler to existing
concrete at next
segment position.
Survey new segment
elevations.
that the transverse tendons must be stressed prior to stripping the traveler formwork. The traveler
formwork must be stripped before the traveler assembly can be launched forward. As a result, the first step
can not begin until the new segment concrete has reached sufficient strength so it will not crack under the
large compressive force from post-tensioning.
The curing of concrete thus becomes a time sensitive activity that has the potential to delay the critical path
of the project. High early strength concrete is typically used to avoid a potential delay. Since it is critical
that the proper concrete strength has been achieved prior to post-tensioning and launching the traveler test
cylinders were used to verify the in-place strength.
Day I of the casting cycle begins with the post-tensioning crew (4 members) stressing the transverse
tendons while the form traveler crew (4 members) simultaneously releases the formwork and traveler
tiedown bars preparing to advance to the next segment. The cantilever tendons are stressed at this time if
they terminate at this location.
Day 2 the traveler crew (4 of 8 members, crew is divided between the each traveler) advances the form
traveler to the next segment position, trim the exterior wall form to the new height and align the formwork
to the correct elevation with the assistance of the project surveyor. A carpenter installs the prefabricated
bulkheads on the segment face.
Day 3 the reinforcing crew (5 members) begins installation of the bottom slab and web walls of the box
girder. All reinforcing steel for the segments is tied in place as the form traveler bracing and framework
did not provide enough space to lift a preassembled cage into place.
Day 4 when the reinforcing installation is completed on the bottom slab and walls, the crew begins
installation on the top deck. In addition, the longitudinal and transverse post-tensioning ducts and tendon
strands are installed, but left unstressed. Coordination of the different crews is essential in the confined
area of the segment. The interior walls are rolled out, cut to the correct dimensions and form ties are
installed.
Day 5 consists of final preparations for casting of the segment and placement of the concrete. The day
begins early: the project engineer determines the final elevation of the new segment with any required
corrections. The project surveyor must then check the final position within an hour of sunrise to eliminate
any false readings caused by thermal movement of the cantilever. Concrete is typically placed in the
following sequence: outside comer of the bottom slab and web wall, bottom slab, web walls and top deck
Chapter 5.0- Construction of Cast-in-Place Balanced Cantilever Bridges
Page 26 of28
\_)
as illustrated in Figure 5.28. The concrete is consolidated with internal concrete vibrators. Field personnel
must exercise careful quality control when placing the concrete. The first placement at the outside corner
must be delivered with a low slump to 'plug' the bottom of the open wall form from the added pressure of
placing the web walls above. Subsequent concrete placed must have a high slump to be placed in the
congested areas of reinforcing steel and post-tensioning ducts.
Page 27 of28
Abutment Segments
Situated at each end of the bridge is an Abutment Segment. Abutment segments make the fmal connection
between a completed cantilever and the abutment substructure. The segment depth at this point in the
structure is typically constant. The abutment segments usually contain massive thick diaphragms situated
over the bridge bearings to transfer the vertical load of the end span and provide anchorage for the
continuity tendons. This area of the abutment segment usually contains a high concentration of reinforcing
steel take require significant time to construct. Abutment segments are typically constructed in three
separate lifts: bottom slab, web walls and diaphragm, top slab and deck overhang supported on shoring.
Abutment segments are supported on steel falsework that remains in place until a closure segment is cast
connecting to the end cantilever. Figure 5.29 shows an abutment segment under construction with the
falsework in place.
Page 28 of28
TABLE OF CONTENTS
6.0
6.1
Introduction
6.2
6.3
6.4
12
6.5
13
6.6
Summary
18
6.7
Reference
18
Page I ofl8
TABLE OF FIGURES
Figure 6.1
Figure 6.2
Figure 6.3
Figure 6.4
Figure 6.5
Figure 6.6
Figure 6.7
Figure 6.8
Figure 6.9
10
Figure 6.10
11
Figure 6.11
11
Figure 6.12
12
Figure 6.13
13
Figure 6.14
14
Figure 6.15
14
Figure 6.16
15
Figure 6.17
Launch Bearing
16
Figure 6.18
16
Figure 6.19
17
Figure 6.20
17
Page 2 of 18
6.0
6.1
Introduction
Generally, construction of incremental launching segmental bridges consists of manufacturing of a
bridge superstructure by segments in a fabrication area set up behind one of the abutments. A new
segment is match-cast against the preceding segment. After the concrete is hardened and launch
prestressing is installed in the newly cast segment, the whole superstructure is moved forward by
the length of one segment to clear the casting cell for casting a new segment. The superstructure
moves on the piers, and segment fabrication continues until the first segment reaches the abutment
The incremental launching method has been successfully used in dozens of long and short bridges
in Europe, Japan, and other parts of the world, although its application is limited in the North
America. The incremental launching method is generally economical for prestressed concrete
bridges of medium span, ranging from I 00 feet to more than 200 feet. It is applicable to longer
spans with temporary piers that halve the spans during construction. Launching from the opposite
abutments is sometimes adopted in the longest bridges in order to diminish the thrust force.
Launching from the opposite abutments also permits halving the construction duration by working
in two casting yards, although the equipment cost doubles.
Chapter 6.0- Incremental Launching of Segmental Bridges
Page 3 of 18
A schematic view of the standard arrangement for an incrementally launched bridge is shown in
the Fignre 6.2.
Launching Nose
Temporary
Pier
6.2
Most of the work associated with the incremental launching method is done in a casting yard set
behind one of the abutments. Because the superstructure moves forward on the piers, construction
is carried out without falsework and is not affected by the conditions under the bridge. Additional
consideration is not necessary to pass over obstacles such as buildings and rivers. Because no
impact at all is given to the clearances of highway or railway traffic crossing below the bridge,
traffic is uninterrupted during construction.
Page 4 of 18
Examples of traffic being maintained below the spans being launched are illustrated in Fignres 6.3
and 6.4. In the bridge of Figure 6.4 (launched in downtown Milan, Italy), No.340 trains passed
under the bridge everyday without any speed restrictions. The electrified lines have also been kept
in service.
There are many advantages to incremental launching segmental bridges which include:
I.
b.
c.
d.
e.
f.
2.
Steel cages are partially prefabricated within the casting yard or in the workshop.
Preassembly can be fractioned at different levels (web panels, deck slab panels,
etc.) or integral. The full utilization of personnel is permitted by parallel (rather
than serial) activities which are performed at short distance from one another.
Site industrialization can be adapted to the bridge length and dimension. The
specialized construction equipment (a launching nose and a hydraulic thrust
system) can be reused on different projects if designed on modular bases. The
casting cell is also generally designed with standard components.
Mechanized and concentrated fabrication generally needs a crew of a constant
number of workers (usually 10 to 15 people) throughout the segmental
construction. Yard industrialization reduces the time required for each activity.
Ahnost all materials are delivered to one place, which simplifies transportation
issues. Handling of materials inside the small yard is easy and labor-saving.
Generally a standard tower crane assists the casting yard for enhanced efficiency
of handling.
Workers do not need to be transported to several locations. Construction risks
for workers are also minimized as the casting cell is rigidly supported on the
ground instead of being, e.g., suspended at the tip of a cantilever, and no activity
takes place on the superstructure.
g. Sheltered fabrication is uninterrupted by bad weather. Construction during
winter in cold regions is possible with heat insulation if other conditions allow.
Improved workmanship and quality
a. The geographically concentrated fabrication makes clean and efficient
management of construction and labor possible.
b.
c.
d.
The factory-like conditions and repetitive works expedite workmanship and high
quality work environment. A high rate of progress can be attained by training
the team with the use of mechanization. Working rhythm can be coordinated to
the construction of one deck segment per week to use weekend for curing of
concrete. Although the deck segments are generally as long as one-half of the
span, alternative organizations with shorter segments are also possible for higher
repetitiveness.
The mechanized fabrication enables precise control of geometry and the
concrete cover, thus further enhancing quality of construction.
3.
Improved safety
a. Little work is done at the final bridge position. Most operation is performed on
b.
the ground, much simpler and safer than operation in the air.
Little or no interference to the clearance of highway or railroad traffic crossing
below bridges.
c.
Construction behind an abutment minimizes the impact to the third parties and
surrounding environment.
Page 5 of 18
6.3
15 for high-speed railway bridges, mostly because of deflection limitations in service. Spans with
equal or almost equal length (except the end ones) are preferable in order to maximize the number
of equal segments.
The most suitable cross-section is the single-cell box section. Double-cell box sections have also
been used although construction is somewhat more complicated with respect to shuttering and
launch supports. A double-cell fish-belly section has been used in Italy for a 2700-feet-long bridge
with architectural board-marked finishing of surface.
Figure 6.5 shows the double-cell segment extraction from the highly industrialized casting yard.
The cleanliness and order of the yard are evident in the photograph. Above the deck, the rollcompacting unit expels the bleeding water from the upper concrete layer of the deck slab to
diminish the W/C ratio and increase the local strength.
Three-cell and four-cell cross-sections have also been successfully launched. Figure 6.4 shows a
three-cell section launched on two support aligmnents.
Page 6 of 18
Figure 6.6 shows a four-cell voided slab launched in Italy on three support alignments. This highly
skewed, varying-width simply-supported span was launched onto a railroad with the help of a steel
temporary pier that avoided overturning. In this case the three launching noses were inexpensive
prestressed concrete blocks fixed to the front deck end with prestressing bars and braced to each
other with steel angles. The central launch alignment also acted as a plan guide.
Double-T beams (ribbed slabs) have been launched on short spans or onto arches. In this case the
span between the spandrel colunms is generally short. In spite of their simplicity, the ribbed slabs
are hard to launch due to the raised location of the cross-sectional centroid.
Page 7 ofl8
The incremental launching method is normally used for straight bridges or bridges curved with
constant radius - either horizontally or vertically throughout the bridge. Bridges with variable
curvature have been launched with wide launch bearings and lateral temporary piers in the most
delicate cases. Launching from both abutments with central closure permits the use of two
different curvatures like "S" curve. The superstructure should be of constant depth. Minor
adjustment in the vertical alignment of the launch surface is attained by temporarily attaching
shims to formwork. An example of incremental launching of a bridge with plan curvature is
illustrated in Figures 6.7. Because of the unique character of construction, it is highly
recommended that the attention should be paid at the early design phase to the possible use of the
incremental launching method.
6.3.2 Post-tensioning
Almost every section of the superstructure receives alternating bending moment and shear forCe
from its own weight as it is launched forward. Mid-span sections which usually receive only
positive bending moment also have to resist negative moment and shear force during launch.
These cyclic changes prevent use of the final tendons during launch and require launch tendons
laid out centrically rather than eccentrically.
There are several ways to provide launch tendons and make them coordinate with final tendons.
The principles are broadly classable to two, as described below and illustrated in Figure 6.8.
1.
Launch tendons required during launch are decided first, compensated by continuous
final tendons installed on completion oflaunch to resist the rest of dead load and live load.
Launch tendons are usually laid out straight in both the top slab and bottom slab, and they
provide centroidal prestress force as a whole. Continuous final tendons are provided by
parabolic internal tendons in the webs or polygonal external tendons.
2.
Final tendons required against the service loads are determined first either with internal
tendons or external tendons. Temporary launch tendons compensate the eccentricity of
the final tendons during launch. Temporary launch tendons are removed on completion of
Page 8 of 18
launch. In some bridges, the removed tendons were repositioned and reused as part of
fmal tendons. An example of launch external tendons and final external tendons is shown
in Figure 6.9.
Approach (I) is usually more effective as it permits progressive introduction of launch
prestressing; it is also less restraining on the yard organization. The temporary launch prestressing
of approach (2) needs an additional cost. The operations of tendon releasing and repositioning are
expensive and time-consuming; however, the high level of launch prestressing (both permanent
and antagonist tendons are present) may diminish the web thickness and increase the crosssectional efficiency.
..
_-..__
!during Launch
~..
--
--/
Final
;
I
--
"" -
"
'!'
-- /T'-.,
Ten~ons
__......-u
1'
Launch Tendons
-- --
--
-- -rPermanent
~ern aI Tendons
Page 9 of 18
Yard operations are limited to the segment arrangement along the support/launch rails, the
joint sealing, and the introduction of post-tensioning in the new sections of the superstructure.
The construction duration can be half of that required for cast-in-place, although with
additional labor costs and a precast yard because of these additional activities.
of the approaches of bridges where longer central spans are built by balanced-cantilever
construction (with or without stay-cables), and construction of the superstructure of arch bridges
(Figure 6.11 ).
Page 10 of 18
Figure 6.10- Transverse Shift of the First Half of a Twin-Box Section on Launch Completion
(Photo courtesy of Marco Rosignoli)
~
~2\IV\1\1\)1
L..,l-~:1.....,11
Jlll
[_ _ _----,..__.,....--_ _ _]
]1
Figure 6.11 -Incremental Launching with Balanced Cantilever and Arch Construction
Cable-stayed bridges can be built by incrementally launching the continuous superstructure onto
temporary piers and by permanently suspending it from a tower on launch completion. Figure 6.12
shows a cable-stayed bridge built by incremental launching in Italy. At the launch completions,
the crossbeams that anchor the stay-cables are generally located above the temporary piers. Also
this bridge was launched onto railways in service without any interference.
Page II ofl8
6.4
yard, and pre-sizing the launch equipment. Optimum organization depends on the length of the
bridge, the number and length of segments, and the construction schedule. All these parameters
The casting yard is usually set behind one abutment. In the case of settlement or no embankment
is available, the formwork is supported by temporary supports. If the bridge has a longitudinal
gradient, it is preferable for the superstructure to be launched from the lower elevation, so that no
braking equipment is necessary during launching.
If the number of segments is large and enough space is available, it is convenient to create rebar
cage preassembly area. The rebar cage preassembly area is usually set behind the casting cell and
a gantry crane carries the rebar cage to the casting cell. Length of segments between 35 feet and
I 00 feet is generally economical. It depends on the location of construction joints, typical span
length, concrete volume, available space, and so on. Longer segments shorten construction period,
but expands the casting cell. It is desirable for construction joints to be located at section of low
bending moment. A half of a span with construction joints at the span quarters is a common
conclusion for length of segments.
A representative working cycle for typical incremental launching segmental bridges with a boxsection consists of following steps:
I.
2.
3.
4.
5.
6.
7.
8.
9.
Page 12 of 18
One full construction cycle typically takes about one week to ten days. One week is generally
preferred to cure the deck slab concrete during weekend. In this case, a complete span is cast every
two weeks. When the bridge is very long, it may be convenient to divide the production into two
areas although this increases the total length of the casting yard. Therefore, a higher level of
industrialization is generally preferred.
")
Accurate setting of the formwork is very important so that the sliding bottom surface is smooth
and maintains the launching direction accurately. Forrnwork is of steel or plywood panels, selected
depending on the number of cycles, i.e. the number of segments. The launching surfaces are
generally match-cast onto neoprene-Teflon plates placed onto stiff stainless-steel extraction rails.
Load deflections of the extraction rails must be minimized.
Two persons are generally necessary at every pier during launching to insert low-friction plates
between the launching bearings and the superstructure. On completion of launch, temporary
bearings are replaced by permanent bearings after lifting the superstructure with hydraulic jacks.
Continuous final tendons, either external or internal, are installed and prestressed afterward.
6.5
commonly used launching systems are pulling launching and friction launching.
Chapter 6.0- Incremental Launching of Segmental Bridges
Page 13 of 18
webs of the cross-section. A launcher is composed of vertical jacks and horizontal pistons. After
the superstructure is hoisted from bearing blocks by vertical jacks, horizontal pistons push the
superstructure forward. The thrust force is transferred by friction between the vertical jacks and
the concrete bottom surface. Then, the superstructure is lowered onto the bearing blocks again by
retracting the vertical jacks, and the longitudinal pistons are finally retracted to repeat this cycle.
Chapter 6.0- Incremental Launching of Segmental Bridges
Page 14ofl8
In the case of two-cell cross-sections, the friction launchers can also be placed in axial position as
)
Figure 6.16- Axial Friction Launching System
(Photo courtesy of Marco Rosigno/i)
the webs. The top of the launching bearings are covered by polished stainless steel sheet.
Launch pads are inserted between the superstructure and the launching bearings. The launch pads
are made of sandwiched neoprene sheets and steel sheets. A Teflon plate is glued to the bottom
surface of the pads. The pads are continuously fed until the designated launching length is reached
(Figure 6.17 and 6.18). Contact of the stainless steel sheet and the Teflon plate reduces friction to
2-4%. The edges of the launching bearings are rounded so that the sliding plates can be inserted
without difficulty. On completion of the whole launch, launch bearings are replaced by permanent
bearings. Some types of bearings are used as launch bearing as well as permanent bearings. An
Page 15 of 18
Lateral guides are necessary to maintain the correct plan arrangement of the superstructure during
launch. They are placed beside the launching bearings surfaced with rollers or stainless steel
(Figure 6.20). It is important to have locking devises to support the superstructure horizontally
between subsequent launches, especially when launch is performed in an inclined elevation.
Page 16ofl8
a pier ahead of it. Three ways usually employed to mitigate this negative moment are:
attach a light weight steel launching nose to the front end of the superstructure to reduce
sectional force in the cantilever
use temporary cable-stay system to support the cantilever from above
place temporary piers between permanent piers to reduce the span length during launch
Page 17ofl8
6.6
Summary
Incremental launching method is one of the most industrialized and effective forms of segmental
construction. Large numbers of segmental concrete bridges have been successfully competed by
incremental launching all around the world. Recent development of high-strength concrete, lightweight concrete~ and precast technologies can reduce launching weight and further reduce
construction period. Further expansion of application is expected.
6.7
References
(I) Rosignoli, M., "LAUNCHED BRIDGES: Prestressed concrete bridges built on the ground and
launched into their fmal position", American Society of Civil Engineers, ASCE Press, 1998.
(2) Rosignoli, M., "BRIDGE LAUNCHING", Thomas Telford, 2002.
<)
Chapter 6.0- Incremental Launching of Segmental Bridges
Page 18 of 18
CHAPTER 7
~
-'\
.. )
'~
7.5.4
7.6
7.7
7.8
7.8.1
7.8.2
7.9
TABLE OF FIGURES
Figure 7.1
Figure 7.2
Figure 7.3
Figure 7.4
Figure 7.5
Figure 7.6
Figure 7.7
Figure 7.8
Figure 7.9
Figure 7.10
Figure 7.11
Figure 7.12
Figure 7.13
Figure 7.14
I of29
2 of29
<)
Introduction
Cable-stayed bridges have been increasingly successful for spans as short as 300 ft (91 m) and as
long as 3340 ft (1018 m). Modern bridges use multiple stay cable cables for ease of erection and to
reduce the weight of the bridge decks. In addition, cable-stayed structures must now resist dynamic
effects due to the loss of a stay cable, and this condition is easier to satisfy with close stay cable
spacing. The structures are, therefore, highly indeterminate and, as a result, construction phases
are more critical than for conventional bridges. The final state of stresses in the structure depends
greatly on the accuracy of construction.
Following the initial choice of material for a cable stayed bridge superstructure, the next decision to
be made by the designer is the method of construction for the bridge. Assuming concrete has been
selected, there are two main choices for construction: cast-in-place with traveling forms or precast
segmental construction.
Precast Segmental Construction can be used very efficiently under the following conditions:
Superstructure segments are often heavy (130-300 t) unless the superstructure is divided into
twin box girders. In the case of heavy segments, easy access to the site must exist, preferably
by barge. Precast segments can be erected by a floating crane for low-level bridges. For high
level bridges, it is easier to use a "beam and winch" system where the segments are lifted
off barges with a winch system on the deck. The segments can also be delivered from the top
if their weight is not excessive and erected with a derrick or crane on the deck.
Manufacturing large precast segments requires a significant initial investment for casting
yard, moulds and lifting equipment. This investment can be justified if a sufficient number
of segments have to be built.
This is the reason why most precast concrete cable-stayed bridges are relatively long bridges
or bridges where the cross section for the approach spans superstructure has been extended
into the main span (e.g. James River Bridge, C&D Canal Bridge, Maumee River Bridge).
7.2
Cable-Stayed Structure
The structure is made of three main components: Pylon, Deck, and Stay Cables. It can be
assimilated to a triangular truss, with the deck acting as the bottom chord. The stay cables are
stressed at the time of erection in order to balance the weight of the deck. For subsequent loading
conditions, the stay cables act as passive structural members like the pylon and the deck.
Fignre 7.1 Triangle Structure: Deck-Pylon-Stay Cable
Pylon
Stay Cable
F
Deck
;---1
c:ti.IIJ~~:I::d~
1
3 of29
Such a structure is often assimilated as a beam on elastic supports. The stay cables can be modeled
as springs which are pre-compressed at the time of erection to provide adequate support to the deck
without excessive bending. The amount of "pre-compression" of these springs will be essential in
determining the stresses in the structure at the end of construction. Usually the designer balances
the dead load shear with the stay cable forces to limit bending stresses in the superstructure.
However, stay cable forces can be adjusted to counteract bending due to long-term creep,
superimposed dead loads or live loads.
')
AL
j j Uniform Load P
2K
I Stay
I
vis;,.
I Stay
I Stay
$22
4000 Ft4
2 2 2 2
2 2 2 2 ?
2 2 2 2$
r" 3oo Ft 4
Chapter 7 -Cable-Stayed Bridges
4of29
Rigid superstructures provide for a better distribution of the loads among the previously erected
stay cables, which also reduces the negative moment in the deck when pouring or lifting segments.
Segment lengths are also normally shorter for precast segments to limit the segment weights and/
or allow for trucking the segments. In this case, the stay cable spacing is divided into two or three
segments, allowing for re-stressing of the stay cable in-between lifts and further reduction of the
moments in the deck. Stay cable forces and deck bending moments during construction are also
more critical with heavier erection equipment such as cranes on deck.
Figure 7.5 Typical Erection Phases
1) Lift Segment
3) Lift Segment
2) Restress Stay
5 of29
Figure 7.7
Photos Courtesy of
Figg & Muller Engineers
6of29
7 of29
With flexible superstructures, the segments can be as long as 35ft (10.7 m), corresponding to the
stay cable spacing. In this case, the deck moment and stresses in the previously installed stay cables
must be reduced. For instance, the stay cable can be connected to the traveling form and partially
stressed prior to pouring the segment. Alternatively, the stay cable spacing and segment length can
be reduced. For instance, the stay cable spacing and segment length were reduced to 17'6" for the
Dame Point Bridge in Florida to facilitate construction operations.
8 of29
Figure 7.11
Dame Point Bridge, Florida
9 of29
10 of29
7.3.2
Unbalanced Loads
The overall stability of tbe partially completed bridge is critical. Cable stayed structures are usually
built by tbe balanced cantilever method and the cantilevers can reach exceptional lengths. This
makes tbe occurrence of dissymmetrical wind conditions on each side of the pylon more likely.
Also, unsymmetrical dead loads result in critical moments in pylons and foundations.
The main loads to be considered for overall stability during construction are:
Unbalanced segment
Unbalanced dead load
Unbalanced horizontal and vertical wind
Unbalanced construction loads.
At ultimate conditions, tbe dynamic effects due to the loss of a segment and/or erection equipment
on one cantilever must be taken into account.
Load combinations for checking stability during construction can be found in AASHTO LRFD,
Art. 5.14.2.3.2. Horizontal and vertical wind loads during construction should be developed through
wind tunnel testing or analytical wind studies.
Figure 7.15 Unbalanced Loads
QE
)
DL-1%
DL+ 1%
,.
< 20B
8;;. 101-1
IWr >
Chapter 7 -Cable-Stayed Bridges
l!.5Wvl
II of29
~ +
____ ,
----
_..J
t t t '
Figure 7.18 Horizontal Yawing
Temp.
Stay
Temp.
Stay
CD
Section
\J
12 of29
Unbalanced loads are also critical for stay cable anchorages at the pylon. With saddles, sufficient
friction must be provided between stay cables and saddle pipes to resist the unbalanced loads with
an acceptable safety factor as mentioned in the PTI Recommendations for Stay Cable Design,
Testing and Installation, 5th Edition (PTI Recommendations),Art. 5.7.2.2.
F+DF
PlanView
Figure 7.25
Shear Lag During Construction
r-1
I
I
/
L_]
Entrainment effects must also be accounted for, especially when the backstay cables are anchored
in a previously erected back span. Sufficient compression must be provided to prevent joint
opening behind the stay cable anchorages.
13 of29
Stay cable vibration may occur during construction when the periods of vibrations of the stay
cables and the partially completed deck are similar.
Stay cable cables are also sensitive to wind/rain-induced vibrations during construction and in
service (see PTI Recommendations, Art. 5.2).
These vibrations must be studied carefully at the design stage; and wind tunnel tests should be
performed to evaluate counter measures, which could include:
Hydraulic dampers at deck level.
Specially designed stay cable pipes with helix or dimples to limit the influence
of rain on stay cable vibrations.
Steel ropes connecting stay cable cables to change their vibration frequency.
The overall sequence of construction influences final stresses in the structure. The sequence of
closing the bridge in the side spans and central span cannot be altered without a structural check:
Secondary moments due to post-tensioning and moment redistribution due to concrete creep are
influenced by this sequence.
In summary, all construction phases must be thoroughly checked before the start of erection. The
analysis should take into account actual erection conditions and actual equipment loads. At the
design stage, the feasibility of construction should be checked by analyzing one erection scheme;
and the specifications should clearly outline the tolerances for deviating from this scheme.
\ Side Span
'
~Pylon
eoo'
[! [J_IP-
_ ..
3
t.-
14 of29
']
If any of these factors differs from design assumptions, new curves must be developed.
Figure 7.29 Cast In-Place Bridge
(Intermediate Cambers)
=:::::::-~
Casting Curve
Final Profile
Casting Curve = Final Profile + Camber
Casting cannot start until casting curves are developed, which requires knowledge of the final
erection scheme, actual construction loads, and actual material characteristics. If creep tests are
required, they should be made at the beginning of the project so as not to delay casting. Segment
weights should be monitored at the site by checking member diruensions and concrete unit weight
or weighing segments (if the segments are precast).
In summary, it is essential to develop actual casting curves rapidly at the beginning of construction
to avoid delays. These curves must be produced using a time-dependent software that takes into
account the effects of concrete creep and shrinkage, steel relaxation, and actual construction phases
and schedule.
Wet-Cast
Segment
Match-Cast
Segment
;.
sw,
..
NW,;, SWA.~I
11
cAs Cast
NW.41
BenchMark
(Elevation)
__-,
1
East Rivet o 'r-+""==="-:''---'--'""_'f".l.i_-_p,L'-.1._ ,
Line
-0----
Fi
;E.;.
F;..
E,
'
NEl SE.il
NEAL
Fixed
Bulkhead
_...(.;:
'
;---;1
~~~I
o--- - -
15 of29
The as-cast set of data is then transformed into the reference system of the erection site by a simple
matrix operation.
Figure 7.31 Coordinate Transformation
I x; ,Y; I =
As-Cast Coordinates
Coordinate
I X;, Y; 1 =Erection
Yj
.L.__L_ _ _ __ , _ _
It should be noted that a systematic error of only 0.001 feet on elevation measurements in the
casting cell would result in significant discrepancies at the end of a long cantilever. The first
segment of the cantilever must be placed accurately to avoid offsets at the cantilever end.
Deflections of the structure at each stage are obtained from the general time-dependent computer
program. Adding these values to the as-cast survey marker elevations provides expected elevations
at each stage of erection.
Similarly, the geometry of the pylon must be controlled during construction to verify that the
maximum out-of-plumb and out-of-straight-line values assumed in the design for this compression
member are not exceeded.
Pylon - Construction Tolerances
Figure 7.32 Out-of-Plumb
I
I
ITG~-- 20"''Q
R"' 2DOH
I
I
The elevation of the cantilever end should be plotted at each phase against theoretical figures.
Instant movements of deck and pylon should be measured when lifting a segment or stressing a stay
cable and checked against theoretical figures. Interpretation of the results would give indications on
the actual stiffness of the structure.
Deck Deformations During Construction
16 of29
Bending of the overall cantilever can be checked by plotting actual and theoretical elevations at
each joint at a given erection phase. Mter each deck survey, the verticality of the pylon should be
checked. If the pylon is out of position, it means that the structure is subjected to unbalanced loads;
and the deck survey would be affected by this condition.
It is imperative to check that the last erected segment is not warped. This is simply done by
comparing readings of the 4 elevation survey markers after erection and in the casting cell.
Figure 7.36 Segment Shape Control
aa
A, B, C, D: Elevation Markers
The accuracy of the stay cable jacking force can also be checked by measuring variations of
elevations of the same survey marker during a full erection cycle (segments lifting, stay cable
stressing andre-stressing). Comparing the result with theoretical figures allows determination of
a gain or loss of elevation for the full cycle. Loss of elevation could indicate a deficit of effective
stay cable force or excessive downward deformation, for instance, because of additional segment
weight. Since the total deck movement includes an equal number of upward and downward
deflections, the influence of the actual structure stiffness on the results is reduced.
The thermal gradients within the superstructure and between concrete deck and stay cables can
affect stay cable forces. The nominal stay cable forces given in the design normally do not
account for thermal effects. One solution consists of verifying and adjusting the stay cable forces
early in the morning if the stay cable has to be stressed during the day-time in order to satisfy the
contractor's operations. It is more practical to estimate the gradients at the time of stressing, for
instance, with thermo-couples. At each stage of erection, a correction of stay cable force can be
computed to account for loss due to thermal gradients. During the daytime, thermal gradients
create a downward deflection of the cantilever. When the gradient dissipates, the cantilever deflects
back up and it results into a loss of stay cable force. Therefore, when stressing during daytime, an
increase of stay cable jacking forces is required.
Figure 7.37 Thermal Effect Stay Force Correction
t.F = AE x t.L
F - t.F
(Gradient)
17 of29
Plotting of the cantilever end elevations at each phase gives a good indication of the actual stiffness
of the structure.
The deck deflects up and down under stay cable stressing and segment lifting. The amplitude of the
deflections increases with the length of the cantilever.
If the bridge is stiffer than assumed, the cantilever tip elevation will seem high after lifting a
segment. After stressing a stay cable, the elevation of the cantilever will seem low.
Modifying the stay cable forces to bring the deck to the theoretical elevation at each phase could
result into unacceptable stresses in the superstructure. This explains why a cable stayed bridge with
a rigid type superstructure cannot be erected following theoretical elevations only. In this case the
erection should be governed by stay cable forces with a tolerance not exceeding +1- 5%.
If cantilever tip elevations are low after stressing and lifting a segment, this is an indication that the
whole cantilever is aimed low or is deflecting excessively.
Figure 7 38 Plot Cantilever Tip
~0--
Stress Stay
&"< &
Lift Segment
Bridge Instrumentation:
Important information can be obtained by placing thermo-couples and strain gauges along the deck section.
However, precautions must be taken to obtain valid results:
o Gauges must have the proper accuracy to detect long-term strains.
o Gauges must be installed properly and must not be disturbed during concrete pours.
o They have to be distributed across the width and depth of the section so that
"average" axial stresses can be estimated.
o A "zero" reading must be taken just after erecting or pouring a segment. Effects of
creep/shrinkage of concrete must be dissociated by testing shrinkage separately.
The concrete modulus of elasticity has to be estimated to convert strains into stresses.
Figure 7 39 Instrumentation
~
I
Strain Gauge
Strain Gauge + Thermocouple
18 of29
"J
EFFECT
-8MM
+10% DL
-10% CONCRETE E
-10% INITIAL F-STAY
-10MM
-44MM
DECK GRADIENT 10 C0
-30MM
TEMPERATURE DECK -5 C0
-2MM
GRADIENT STAY/DECK 5 C0
-12MM
E STAY -13%
-11MM
)
Other geometry discrepancies due to additional segment weight or inaccurate stay cable jacking
forces must be corrected by re-stressing the stay cables. Usually several stay cables along the
cantilever have to be re-stressed to avoid excessive stresses in the deck or stay cables. Re-stressing
the stay cables is a complex operation because the system is highly undetermined. The designer
needs to calculate the jacking forces for each stay cable and re-check the stresses in the structure at
each stressing operation. If the geometry discrepancy was due to additional weight, the stay cable
forces will be adjusted higher and the designer needs to verify that allowable stay cable forces are
not exceeded for the bridge in service. It is advisable to provide some additional stay cable capacity
at the design stage to account for such construction variations.
Figure 7.41 Stay Restressing
V1
F1
A2 1 F2
A3t F3
A22 F2
A:52 F3
= A13
A23 F2
A33 F3
V3
= A11
V2 = A12 F,
F1
19of29
<J
Chapter 7 -Cable-Stayed Bridges
20 of29
Great accuracy is required when placing the guide pipe as it will dictate the stay cable alignment.
Installation tolerances are provided In the PTI recommendations,Art. 5.9. The vertical and
horizontal angles are especially critical, as offsets would create bending stresses in the stay cable.
The anchorage adjustable nuts or shims are in contact with the bearing plate. The bearing area
must be perfectly flat to avoid stress concentrations and deformation of the anchorage socket or
adjustable nut.
-X
dwF
I. 2c<. 4A
21 of29
Figure 7.46 Steel Pipe Erection with Highline, Maumee River Bridge, Ohio
Photo Courtesy ofBilfinger & Berger
Chapter 7- Cable-Stayed B1idges
22 of29
--..._,
)
./)
Figure 7.47
PE Pipe Erection with Messenger Cable
James River Bridge, Virginia
Figure 7.48
PE Pipe Supported with Strands
Puente de Ia Unidad, Mexico
Photo Courtesy of VSL Mexico
23 of29
- - -'v- "'----'-~v
- 3/8"
IlL =
Strand
av
In -< (
Deck Movement
liH
y
/
/
o<.
..-''-'/~
4L
= 4H
oln o<
I
I
I
Pylon Movement
24 of29
Small stay cable force adjustments or stressing of short stay cables, must be performed by using the
anchorage ring nut and a multiple strand jack. This is required when elongations are so short (less
than 15 mm) that this would result into overlap of the wedge bite marks on the stay cable strands.
heam111 plate
an~;ho~age
L!O\:>;.
n = strand number
Total -Force: n x F,~
1'110110Sflilflt1 j&l;k
' t . .,
~~~~::ffi'::.=:=_~~~
~~-- . --J
25 of29
~')
26 of29
Extradosed bridges have been used economically for spans between 100 m and 200 m. Spans up
to 270m have been reached in Japan by using hybrid girders (concrete close to the pier and steel
central span).
Following are some interesting features of extradosed bridges
Reduced concrete box girder depth and lowered vertical profile
Variable depth box girders replaced with constant depth box girders resulting into
standardization of precasting operations, reduction of precast segment weights.
Reduced pylon height compared to cable-stayed bridges, lower vertical clearance required.
Simplified cable testing requirements (low stress variations, no fatigue)
Higher cable allowable stresses (-30%) compared to stay cables.
27 of29
28 of29
7.9 Conclusion
"j
The construction phases of a cable-stayed bridge are critical. Important decisions need to be made at
the site in a timely manner to avoid construction delays. The presence of a team knowledgeable in
the design of the structure at the site during construction is therefore essential.
References
FIP Congress 1986-New Delhi, Cable Stayed Bridges, Keynote Lecture by Fritz Leonhardt
Pouts Haubanes, Pr. Rene Walter-1985
Construction and Design of Prestressed Concrete Segmental Bridges, Podolny-Muller-1982
Construction and Design of Cable Stay Cable Bridges, 2nd edition-Podolny-Scalzi-1986
PTI Recommendations for Stay Cable Design, Testing and Installation, Fifth Edition
AASHTO LRFD Bridge Design Specifications
Bridge Name
Location
Date
Main
Span(Ft)
Benton
Washington
1957
170
CIP
Sacramento River
California
1977
180
CIP
Pasco-Kennewick
Washington
1978
981
East Huntington
West Virginia
1985
900
Sunshine Skyway
Florida
1987
1200
Dame Point
Florida
1989
1300
James River
Virginia
1990
630
Neches River
Texas
1991
640
Talmadge Memorial
Georgia
1991
llOO
Cochrane
Alabama
1992
780
C&DCanal
Delaware
1995
750
Sydney Lanier
Georgia
2000
1250
Maumee River
Ohio
2007
612.5
Penobscot Narrows
Maine
2007
ll61
La Plata River
Puerto Rico
2008
525
Pomeroy Mason
Ohio
2008
675
Superstructure Type
29 of29
\J
TABLE OF CONTENTS
CONSTRUCTION PRACTICES HANDBOOK FOR
CONCRETE SEGMENTAL AND CABLE-SUPPORTED BRIDGES
CHAPTER 8.0 SEGMENTAL SUBSTRUCTURES
8.0
Segmental Substructures
8.1
Introduction
8.2
Project Examples
8.3
Precasting Operations
8.4
Erection Operations
10
8.5
Summary
11
I ofl7
TABLE OF FIGURES
GUIDELINES FOR CONSTRUCTION OF SEGMENTAL CONCRETE BRIDGES
CHAPTER 8.0 SEGMENTAL SUBSTRUCTURES
Figure 8.1
Figure 8.2
Figure 8.3
Figure 8.4
Figure 8.5
Figure 8.6
Figure 8.7
Figure 8.8
Figure 8.9
Figure 8.10
Figure 8.11
10
Figure 8.12
10
Figure 8.1
12
Figure 8.1
13
Figure 8.1
14
Figure 8.1
15
Figure 8.1
16
Figure 8.1
17
r)
Chapter 8.0- Segmental Substructures
2 of!?
8.0
Segmental Substructures
8.1
Introduction
The development of precast segmental piers, extends the use of segmental technology to bridge
substructures. The frrst use of precast segmental piers in the United States was likely the Seven
Mile Bridge, built in 1982 and located in the Florida Keys. Since 1982, over a dozen bridges
utilizing precast segmental piers have been successfully constructed, allowing bridge substructures
to utilize the benefrts of precast!prestressed concrete. These benefrts include increased rates of
construction, economy and durability. In many cases where site preparations, deep foundations or
extensive repetition of common piers provide lead time for precasting piers, conventional cast-inplace foundations can be re-designed to precast segmental piers for a significant project savings.
8.2
Project Examples
As pointed out in the introduction, many projects have utilized precast segmental piers. These
projects are diverse and range from projects completed in the early 1980's to projects currently
under construction.
Many of these projects utilize simple hollow rectangular piers. This is the case for the VarinaEnon Bridge, the James Burrows Edwards (Wando) Bridge, the Chesapeake and Delaware Canal
Bridge, the Garcon Point Bridge, and the Hoover Darn Bypass Colorado River Bridge.
Other structures have utilized a variety of shapes selected to meet structural, aesthetic and other
project requirements. Among these structures are the Sunshine Skyway, Linn Cove Viaduct,
Albemarle Sound Bridge and U.S. 183 Austin Bridge.
Of interest is the James Burroughs Edwards Bridge over the Wando River. The construction
sequence for the main span of the superstructure called for temporary piers in the side span. The
contractor elected to use precast segments for these piers, that were later disassembled after
construction of the main span and utilized for permanent piers elsewhere in the project. This
innovative use of segmental piers resulted in a significant reduction of materials and construction
cost.
Another project of note is the Linn Cove Viaduct on the Blue Ridge Parkway in North Carolina.
This project utilized hexagonal piers with concave surfaces to fulfrll the aesthetic requirements.
Black iron oxide was added to the concrete mix that has allowed the piers to weather to the same
color as the surrounding rock outcroppings.
The Linn Cove Viaduct also utilized a unique construction placement for the piers. No heavy
equipment was allowed on the terrain below the structure. Therefore, the superstructure was built
forward in progressive placement until a pier location was reached. The pier column segments
were then delivered across the completed portion of the superstructure and placed in final position
from above.
Precast segments are also utilized in the Hoover Darn Bypass Colorado River Bridge. The
contractor elected to use precast segments for the pier columns and the spandrel columns on the
concrete arches. The colunros are engineered to slightly taper toward the pier caps. The tallest of
the colunros is about 300 ft tall. The temporary pylons which support stay-cable system during the
arch erection are precast as well. Because of their temporary nature, epoxy coating is not provided
between the pylon segments.
3 ofl7
4 of 17
5 of 17
Figure 8. 7- Hoover Dam Bypass Colorado River Bridge Precast Column Erection
6 of 17
8.3
Precasting Operations
While there can be variations in precasting procedures based on the contractor's preferences, the
basic operations can be sunnnarized as:
Precast column segments are typically a constant cross-section. Therefore, the reinforcing is very
simple and is typically comprised of a series of transverse sets and a series of vertical straight bars.
The transverse sets have typically been ties consisting of smaller bars sizes. Tie requirements with
current design codes have increased the density of ties, but the resulting reinforcing bar cages
remain modular and readily tied in assembly jigs off line.
~J
Chapter 8.0- Segmental Substructures
7 ofl7
match-cast to assure a precise fit for when they are epoxy joined during erection. The bottom
segments are typically cast first and casting proceeds upwards with the top segments being cast
last. The first segment in each column is simply cast in the forms at ground level. The next
segment is match-cast on top of the first segment. The first segment is then taken to storage, the
second segment placed in the bottom position and the third segment cast on top of the second.
This cycle is repeated until the casting of all segments in a column is complete. The last segment
is a pier cap segment and will typically have a solid section and special reinforcing to
accommodate the bearings and distribute the bearing and post-tensioning forces to the overall
cross-section.
The set-up for a match-cast pour most often follows the following sequence. The core form
(forming the interior void) is installed above and overlapping the match-cast segment. The
reinforcing cage is then installed, along with the post-tensioning ducts. The exterior form is then
installed. The form and match cast segment are then surveyed into plumb positions. If there was a
deviation in the as-built plumbness from the last match-cast pour, the next pour will not be set
perfectly, plumb. Instead, forms for the next pour will be offset to compensate for the previous asbuilt survey and allow the column as a whole to track a vertical line. Note that two orthogonal
faces must be monitored to assure plumbness in both directions.
8 ofl7
)
/
storage is usually a nominal 2500 psi. Therefore, minimum strength for handling is readily
achieved overnight and most contractors elect not to steam column segments.
The precasting operations for precast column segments are very straightforward and a segment per
day can typically be produced in each form bed. The limiting factor is the time needed for the
concrete to achieve minimum strength for handling. It typically does not take a full day for a
three to four person crew to set up and pour a segment when the reinforcing cage is pre-tied.
9 ofl7
8.4
Erection Operations
Erection of precast columns proceeds very quickly. As noted, there can be variations based on the
contractor's means and methods, but the sequence that follows represents typical colwnn erection
operations.
The first operation is to place and plumb the first segment on the footing. Typically a keyway,
slightly larger than the segment cross-section is cast into the top of the footing. The first segment
is placed partially down into the keyway, but a minimum joint of I to 2 inches is left between the
segment and the bottom of the keyway. The segment is plumbed by survey and shimmed off the
bottom the keyway to maintain the desired geometry. Accuracy required for this operation is a
function of the height of the colunm, since any error in setting will be projected to the top of the
column. Post-tensioning ducts between the footing and the segment are coupled. Finally, high
strength grout is poured into the keyway to join the segment to the footing.
10ofl7
After curing the grout joint, erection of the remainder of the segments can proceed. The segments
are epoxy joined by placing epoxy on the top ofthe last segment just prior to setting the next
segment. The segments are simply set atop the previous segment, as geometry has been
established in the precasting operation.
The segments are placed until either stability becomes questionable, or the contact time
for the epoxy is approaching the spec limit. At this time vertical post-tensioning is applied to
the column to achieve a minimum uniform pressUre of 40 psi for epOxy squeeze,_ or the
minimum stress required for stability, whichever is greater. During erection, intermediate post-
tensioning is most-often achieved with post-tensioning bars. These bars can be temporary, or
become part of the permanent post-tensioning system. Note that for shorter colwnns, the entire
column can often be erected without an intermediate stressing operation.
After all the segments in a column are erected, the permanent vertical post-tensioning is stressed.
While either bars or strand tendons are acceptable, strand tendons are most often used for the
major permanent post-tensioning. These tendons typically have both anchorages located in the pier
cap segment and loop down throngh the footing. They are double end stressed from the pier cap.
Tendons internal to the concrete cross-section are typically utilized. However, tendons external to
the cross-section and running in the interior void can also be used if part of the design (these are
typically unbonded tendons, and require a different design basis than internal tendons). In either
case the tendons are grouted after installation for corrosion protection.
Five pages of detail drawings for precast box piers developed for use with the AASHTO-PCIASBI Standard Segments are included in Figures 8.13 through 8.17. A detail drawing of the
tendon loop connection of precast segmental piers to the foundation is presented in Figure 8.18.
8.5
Summary
Precast segmental substructures can be a very efficient solution when ever there is volume
production of standard pier shapes. Precasting can also be the best solution for unique sections
that require high quality concrete or geometry control, and when there is a long lead time for deep
foundations that allows the contractor to fabricate pier sections in parallel with foundation work.
The major advantage of precasting piers is the speed of erection, which surpasses any available
option.
Contractor re-design of conventional foundations to precast segmental foundations is often an
option. Given current design codes and standards, precast pier sections are most efficient in low to
moderate seismic areas or for tall columns controlled by wind forces, where the major
reinforcement can be post-tensioning. In high seismic areas, the high density of confmement
reinforcing required by current codes and the ductility requirements for plastic hinge design make
precast box sections less practical. However, current trends in code requirements that base design
on system response instead of section ductility will favor post-tensioned precast segmental
columns, so future use of this design option should become increasingly popular.
11 of 17
IL;
Figure 8.13- Span-by-Span and Balanced Cantilever Construction Spans 100' to 200'
~Box Pier Segment Dimensions
12 of I 7
lj__,__ ~---f'iii,------j---i--l-----.,.....~--
Figure 8.14- Span-by-Span and Balanced Cantilever Construction Spans 100' to 200'
-Box Pier Cap Segment Dimensions
13 of!?
-r-
---~~
-1..-
-----
:-:
=======
Figure 8.15- Span-by-Span and Balanced Cantilever Construction Spans 100' to 200'
-Precast Box Pier Details I
14ofl7
Figure 8.16- Span-by-Span and Balanced Cantilever Construction Spans 100' to 200'
-Precast Box Pier Details II
\J
Chapter 8.0- Segmental Substructures
l5ofl7
<
>
!I!
.il
I"JJ1'1J
.v~,.w
Figure 8.17- Span-by-Span and Balanced Cantilever Construction Spans 100' to 200'
- Precast Box Pier Details Ill
()
Chapter 8.0- Segmental Substructures
16 of 17
"o~vrm
SPRAY PAltrr
wrfHZiflC
AFTER WElDING
OETAIL3
STEEl (;lAMP~-/
BARBED FITIING ---__., ~
j'.
PEPJPE~j/
OETAILZ
")
Chapter 8.0- Segmental Substructures
17ofl7
/)
TABLE OF CONTENTS
CONSTRUCTION PRACTICES HANDBOOK FOR
CONCRETE SEGMENTAL AND CABLE..SUPPORTED BRIDGES
CHAPTER 9.0 PRODUCTION OF PRECAST SEGMENTS
9.0
9.1
9.1.1
9.1.2
9.1.2.1
9.1.2.2
9.1.2.3
9.1.2.4
9.1.3
9.1.3.1
9.1.3.2
9.1.3.3
9.1.3.4
9.1.3.5
9.1.4
9.1.4.1
9.1.4.2
9.1.5
9.1.5.1
9.1.5.2
9.1.5.3
9.1.5.4
9.1.6
9.1.9.1
9.1.9.2
9.1.9.3
9.1.9.4
9.1.9.5
9.1.7
9.1.7.1
9.1.7.2
9.1.7.3
9.1.7.4
9.1.7.5
9.1.7.6
9.1.7.7
9.1.7.8
9.1.8
9.1.9
9.2
9.2.1
9.2.2
9.3
9.4
9.5
9.6
9.7
9.8
9.9
9.10
9.11
9.12
9.13
9.14
9.14.1
9.14.2
9.14.3
9.14.4
9.14.5
Segment Production
Casting Yard Planning and Setup
Introduction
Location
Acreage
Utilities
Existing Buildings
Water Access
Existing Site Conditions
Soil Conditions
Drainage/Storm Water Plan
Wetlands Issues
Securi1y
Slip or Dock Conditions
Receiving/Delivery
Delivery of Segments
Material Deliveries
Site Preparation
Local Permits-Developer Fees
Grubbing and/or Clearing
GradingDrainage, Runoff
Foundations
Procurement
Fonns
Batch Plant
Steam Generator
Cranes (Gantry Cranes, Tower Cranes and Segment Haulers)
Auxiliary Equipment
Facilities
Office Trailer Locations
Form Locations
Rebar Jig Locations
Warehouse, Material Storage location
Steam Generator Location, Piping Requirements
Portable Toilet Locations
Temporary Fuel Storage
Trash, Scrap, Recyclables
Post Casting
Summary- Casting Yard Planning and Setup
long line and Short line Forms
long line Casting Bed
Short line Casting Bed
Match Casting
Casting Curve
Fabrication of Rebar Cage with Post-Tensioning Ducts and Hardware
Installation of Post-Tensioning Ducts
Handling the Prefabricated Rebar Cage
Rebar Cage in Casting Cell
Setting the Match Cast Segment
Placing Concrete
Finishing the Top Surface
Curing
Forms
Special Situations - Elevated light Rail Construction
Rail Construction
LRT Electlification
Crossover Construction
Grounding Requirements
LRT Conclusion
3
3
3
6
6
6
6
7
7
7
8
8
8
8
8
8
9
10
10
10
10
10
12
12
15
15
16
17
20
20
21
23
24
24
24
24
25
25
26
27
27
33
37
38
39
41
41
42
42
43
45
46
47
50
50
52
. 52
53
55
I of 55
TABLE OF FIGURES
-)
Figure 9.10
Figure 9.11
Figure 9.12
Figure 9.13
Figure
Figure
Figure
Figure
Figure
Figure
9.14
9.15
9.16
9.17
9.18
9.19
Figure 9.20
Figure 9.21
Figure 9.22
Figure 9.23
Figure 9.24
Figure 9.25
Figure 9.26
Figure 9.27
Figure 9.28
Figure 9.29
Figure 9.30
Figure 9.31
Figure 9.32
Figure 9.33
Figure 9.34
Figure 9.35
Figure 9.36
Figure 9.37
Figure 9.38
Figure 9.39
Figure 9.40
Figure 9.41
Figure 9.42
Figure 9.43
Figure 9.44
Figure 9.45
Figure 9.46
Figure 9.47
Figure 9.48
Figure 9.49
4
5
7
9
11
12
13
14
16
18
21
22
23
24
25
25
26
28
29
29
30
31
32
32
33
34
34
35
35
36
36
37
38
39
40
41
44
44
46
47
48
49
49
50
51
51
52
53
54
55
~,
J
2 of 55
9.0
Segment Production
9.1
9.1.1 Introduction
Essential features of a casting yards utilizing short line forming are shown in Figures 9.la aod 9.lb.
The plaoning and decisions made at the start of a project can set the tone for the remainder of the
job. Many preliminary decisions regarding the location and setup of a casting yard for a
segmental bridge project should have been made during the bidding process. One or more
potential locations should have been examined for acreage, existing site conditions, requirements
for site preparation, required equipment, site access both in and out, and site clean up at the end of
the project.
Once the project has been awarded, the preliminary decisions have to be expanded to ensure a
smooth and efficient start up. This chapter will outline the several "incidentals" that tend to be
overlooked before the first casting cell arrives on site. As with most construction projects time is
always the driving factor. This means ahnost innnediately after award, long lead items need to be
ordered. This can be anything from casting cells to batch plants to steam generators aod cranes.
The idea behind segmental bridges is to have the segments themselves waiting at the casting yard
to deliver as required by the erector.
The most obvious long lead item is the casting cells. These can take anywhere from twelve weeks
to six months for delivery, depending on the number offorms required and the complexity of the
segments. It is during this time that the casting yard needs to be fmalized and prepared to accept
the casting cells for erection upon their delivery. Site preparations can be as simple as
clearing/grubbing, and leveling and grading, or may include drainage installation, consideration of
wet land issues, zonage requirements, utility installation, and docking issues if delivery is to be by
water.
Another item that requires early consideration is personnel for the project. Project Managers
aod/or Plant Managers are typically known at the outset of a project. However, the supporting cast
will take time to assemble. The supporting cast will include the QA/QC inspectors, Surveyors,
Form Crews, Reinforcing Steel Cage Crews, Crew for Transverse Post-Tensioning and Grouting,
Finishers, Operators, aod the many auxiliary employees required to complete the daily work.
3 of 55
=Fm~,
I
I
I
I
4 of 55
~.
il~
~l
,Ji
= ! !! ~
= = = ! ii i
! i! !i i
'
~
i;====l:~i
' "
:3:
"
!E5
~~~
--
!'=<!
'
:I
!!
i==i
ii i
::
!!
!
j
~=~
!!
"'-
" '
!!
=!
' 00-
ii
!i
=!
~~
1"'';;
ii==:!
' '
!! !! ~
=f" '
"
'
!!
!==
~ '1:;
l [/
1"'-
1~
'
ii
~~
Ftif4i
e;;;:
!!
i
!r==l!
==!
~.
'
'\!!
~
b' \z v~
IJI ~~ i!
m_~
F\ ~
lllrl i(~
-4
i
!
!
bd
h
i!
'E5
IS
'E=!
=!
!
=
" '
;,
!
E=!'
'
~~
i! !
!=
v
~~nt
!!
~-!'=<!
'\
. '.JI. Ill
I
'\,_l!J
1"'~
!!
=~~
m1
'
ii
" ''
'
" '
'
J!!
,.,.._.
Iii M~/
[ ~-~
~~.~ n~
!!
==
eel~
!!
==
li~
i==i~
!!
~
~
i
~SIY.b~
\ ..
5 of 55
9.1.2 Location
9.1.2.1 Acreage
Minimum Size Based on Size/Quantity of Segments
The property size required depends on a variety of factors, including: segment length and width,
the gantry crane width ( determines storage area aisle layout), amount of space between stored
segments for work crews, whether the segments will be stacked, hatching needs, and shipping area
layout are factors that require consideration. IdentifY the various work stations and the anticipated
footprint for each component of the casting yard. Assumptions concerning space requirements
should be conservative, and all assumptions should be clearly stated in preparation of a bid.
Workstation placement should have some flexibility without impacting work flow and production
efficiency.
Zoning Restrictions
The property being considered should be discussed with local building officials to determine
property usefulness. Due to the temporary nature ofthe casting yard, a zoning modification may
be feasible in consideration of bringing jobs to the local economy.
9.1.2.2 Utilities
Since the casting yard setup is usually on the critical path of every project, the property's utilities
(including locations, sizes, and rated capacities) are necessary information before making any
negotiations or commibnents. An assessment of the existing utilities and anticipated casting yard
needs is vital to ascertaining initial setup costs and scheduling impacts.
Existing
Electrical- The contractor's kilowatt requirements are necessary before discussions with the local
utility company can start. If a batch plant will be setup, it's highly probable that a transformer
addition or upgrade will be necessary. This can be a long-lead item, so the need must be identified
early.
Water- The contractor must determine the precise casting yard needs before existing water
supply can be deemed acceptable. The batch plant needs, truck washout area, steam generator, and
sprinkler system requirements for any new buildings. Every work station and task should be
evaluated.
Telephone- The contractor, subcontractors, engineering and inspection firms all require a phone
system with multiple telephone lines.
Internet- Internet service may be required for the casting yard's efficient operation, remote
monitoring and possible web cameras.
Required to be Installed
Once the contractor has successfully obtained the low-bid award, the list of utility upgrades must
be documented and each item addressed and managed. The list of utility upgrades should be
included in the casting yard schedule to ensure completion is monitored.
Chapter 9.
O~Production
of Precast Segments
6of55
.~~
7 of 55
9.1.3.4 Security
Security needs and public safety are high priorities when considering a casting yard site. Local
unemployment and crime statistics could alert the contractor to potential problems. The town
board or city council members and the local chamber of commerce are good business alliances.
Evaluate all the data and implement conservative measures to provide a safe and secure
environment.
9.1.4 Receiving/Delivery
9.1.4.1 Delivery of Segments
Segment delivery is the primary determining factor for establishing the casting yard's distance
from and allowable travel route to the project. Once the segment takeoff is complete, this shipment
aspect must be developed. The maximum size and weight of the segments will affect the proper
truck/trailer combination for delivery. The contractor can evaluate his existing fleet or discuss the
project with a reputable trailer manufacturer or local trucking company. The state and local
agencies responsible for transportation permits will need to be contacted. These agencies will
evaluate allowable axle loads, axle layouts, and height or width restrictions within their
jurisdiction. The contractor should convey the number of legally permitted loads anticipated and
shipments per day. If multiple jurisdictions are involved, the contractor will need to negotiate an
acceptable criterion. Also, discuss scheduling, signage, escorts, police details, convoy allowances,
hours of operation, bridge survey requirements and restrictions, and any upcoming construction
projects along the intended route.
8 of 55
9 of 55
9.1.5.4 Foundations
Choose the best soil bearing locations on the property for the foundations, especially for the forms
and batch plant. Consideration should be given to whether the foundations are temporary or
permanent. Be sure to contact Dig Safe prior to commencing sitework.
For Offices
Unless the contractor anticipates a long project, a level area with stable soils or slab-on-grade will
suffice for temporary office trailers. Determine the total area required to house the project staff.
If a wood frame structure, pre-engineered metal building, or masonry building is planoed, the soil
bearing capacity will determine foundation requirements. If the structure will combine office and
production, make sure proper firewall separations are incorporated into the design and the
financial implications are determined upfront.
For Forms
Determine soil bearing capacity and stability prior to receiving form layout and loads. Reviewing
all the data and cost analyses will determine the type of foundation and any impact on scheduling.
Since this activity is always on the critical path, the initial planning must be thorough.
i\J
Chapter 9. 0- Production of Precast Segments
10of55
Once the marine haulout facility is operational, maintaining and repairing infrastructure is
extremely important, so perform periodic inspections to maintain a good structural status and
functionality. To accomplish this task a maintenance program should be in effect with a detailed
maintenance schedule.
II of 55
To the extent feasible, existing structures on the property could be used for office space, QC lab,
material storage, and casting operations. The climate and project length will determine the
investment cost-benefits of modifications. The cost factor of re-modification should be considered
if the property needs to be restored back to its original condition.
Employee Parking
Assign a suitable parking space with capacity for all employees and anticipated visitors. Use the
appropriate barriers and signage depending on proximity to work areas and security level. Choose
the site carefully; many aspects of casting yard operation are harmful to automobiles.
9.1.6 Procurement
9.1.9.1 Forms
Purchasing precast segmental casting cells may determine the profitability of the casting yard
operation. The contractor and casting machine manufacturers should thoroughly discuss what is
included in the "Form Package." Items not included are unwelcome and expensive surprises
during the erection of the casting inachines.
12 of 55
Long line casting cells require a large footprint for the forms. The soffit is the full length of the
cantilever and is built to the profile of the bridge. Details of the soffit form provide for geometry
control. Side forms and soffit forms must permit adjustment for the deflection that will occur.
Short line casting cells require much less area than long line machines. Horizontal and vertical
adjustments are required for a short line machine. Geometry control requires the use of highly
skilled staff and technical instruments.
Typical segment machines are the most critical production item in the casting yard. Therefore, it is
critical to make sure the forms allow yard personnel to quickly and efficiently cast one segment
per machine per day.
Constant depth casting cells are the easiest forms to "turn" every day. The soffit width, and the
web wall depth are constant. Segment length may vary, requiring that the match cast segment be
moved on the soffit or that a soffit extension be used.
Variable depth casting cells require the most changes to the forms to cast each segment. Changes
in segment height and soffit width require additional time to prepare the casting machine for the
next pour. In order to cast one segment per machine per day, the panels in the core form should be
as light as possible so that the panels can be installed by hand. It is also recommended that an
additional soffit be purchased to allow crews to assemble a day ahead to decrease change-over
time each morning.
All typical segments have rolling soffits and mandrels. High capacity rollers or crane wheels are
used to position both pieces. The track and embeds to hold the rollers should be included in the
form package.
Soffits for the typical segments must adjust for horizontal curves and tight geometry control.
Discuss both horizontal and vertical hydraulic options. Manual adjustment of the soffit and
positioning frame generally requires too much time. Some casting cells come with two soffits and
positioning frames, while others come with two soffits and one moveable positioning frame that
13of55
Due to the large quantity of segments to be cast per cell, skin thickness of the forms is important.
Steel for most soffit, web, and wing panels should be at least 1/4-inch thick.
Placement of bracing for the web and wing supports requires base plates to be anchored to the
foundation. The base plates and embeds should be included in the form package.
Stripping the wing walls is generally performed by lowering/rotating the web and wing forms
away from the segment. Make sure the forms will be able to move beyond any drain blockouts or
enlarged wing tips without having to physically remove panels. Determine whether the forms can
be moved manually or if additional hydraulics are required
Shear keys can be fabricated from different materials. The most durable and costly shear key is
machined from solid steel bar. Machined steel bar shear keys will withstand the abuse from the
rebar cage dragging across them, and can be cost effective if used many times. Bent steel plate
and ultra high molecular weight Polyethylene are other materials that may be used for shear keys.
Both materials work well but are more susceptible to damage from rebar cages and misuse.
The core form must be carefully detailed to ensure that a segment is cast every day. The ability to
rapidly configure the core for deviation segments, top blocks and bottom blocks is criticaL Check
with the form manufacturer to determine if removing a "pour by" panel will provide the deviation
segment or if it is necessary to remove the core web panel and replace it with a panel that has the
deviation blockout built in. Make sure all panels in the core have a slight draft (slope)
incorporated to facilitate stripping. The core form may be retracted using hydraulics, moved
manually, or a combination ofboth methods.
Pier, expansion, and abutment segments require more time to set up for casting. The recess area of
these forms should be fabricated to facilitate stripping. Split Piers require a rolling soffit to move
the half segments individually.
14 of 55
. !
15of55
The steam generator size and output capacity will be determined by quantity of forms, form
layout, and maximum concrete cubic yardage cast per day. In colder climates the concrete cubic
yardage quantity should include the matchcast segments, since their temperature must be similar to
concrete placement temperature. A 1,000,000-5,000,000 BTU unit will service most casting yard
applications, with larger custom units available. The manufacturer will provide a piping design to
optimize the unit; any variation on this design will drastically affect performance. The units can be
outfitted with a variety of options ranging from simple manual controls to sophisticated
computerized systems using thermocouples at each form. The latter can be progranuned to start
the unit after concrete preset, provide the correct ramp-up to optimum temperature, and ramp
down the unit for proper release strength. Some computerized systems can be operated from the
QC lab. Carefully weigh the cost benefits for each option, especially whether or not the equipment
can be expensed over multiple projects. Also, check the hardness of the local water in case a water
softener is needed as mineral deposits can gradually fill the steam lines and plug valves.
allow a reduced heat source and form insulation techniques to achieve accelerated curing.
Fogging and water sprinkler methods should be used to maintain a humid environment. A fine fog
mist is frequently applied through a system of nozzles or sprayers to raise the relative humidity of
the air over tlatwork, thus slowing evaporation from the surface. Formwork can be economically
insulated with commercial blanket or batt insulation that has a tough moisture proof covering.
When insulated formwork is used, care should be taken to ensure that concrete temperatures do
not become excessive.
Other options to investigate are electrical, hot oil, microwave and infrared curing methods which
have been available for accelerated concrete curing use for several years. Electrical heating is
especially useful in cold-weather concreting. Hot oil may be circulated under steel forms to heat
the concrete. Portable hydronic heaters may be used to thaw subgrades as well as to heat concrete
!.,)
16 of 55
Examine strongback and rigging needs carefully for safety and efficient operation. A site-specific
safety manual and mandatory employee safety training is a key component of a successful project.
When evaluating a gantry crane consider the following:
Lifting Capacity - Determine the maximum segment weight prior to selecting a crane. Also,
make sure the crane will handle other uses or projects in the future.
Overall Height- Identify any casting yard problems associated with the crane's height.
Wheelbase- This criterion will establish the storage area Jane width. Decide on how
segments will be stored and the maximize Jane capacity.
Maxlinum Hook Height- Determine the maximum height a segment will have to be lifted
above the ground, making sure to add the strongback and rigging. To lift a segment over
segments in storage or lift a segment over a segmental form, these items will determine the
hook height necessary.
Turning Radius - Carefully determine cas.ting yard component layout using radius data.
Traveling Speed- Useful information for unaerstanding task timefrarne and critical
coordination factors.
Drive Train- Casting yards typically have rough terrain; consider cost-benefits of all-wheel
drive.
Every aspect of the casting, storage, and shipping operations will be controlled by the above
factors. The particular aspects of the project requirements must be considered, any areas left
unchecked could be costly. Review all federal, state, and local safety ordinances.
http://www. osha. gov/SLTC/cranehoistsafetv/
Purchase
Regardless of the type of crane selected, there are many foreign and domestic manufacturers.
Check product availability, service requirements, setup requirements (secondary crane), and
include a manufacturer's list of recommended replacement parts in the contract. For smaller
projects, a used crane might be suitable, especially a manufacturer's reconditioned unit.
Lease
A new or used crane can be leased making the payments fully tax deductible operating expenses.
For a larger crane size and relatively short duration, this option might be preferable.
The rough terrain aspects of a casting yard are the perfect environment for telescopic forklifts.
There are a number of manufacturers which produce telescopic boom forklifts. Their versatility is
enhanced by numerous attachments applicable to casting yards (buckets, work platforms, rigid and
extendable booms). Check maximum load height, load charts, specialized maneuverability
options, precise load placement controls and ease of operation.
)
Chapter 9. 0- Production of Precast Segments
17 of 55
)
Figure 9.9- Tall Segmental Forms May Require an Aerial Personnel Lift
Front-end Loaders
Front-end loaders are excellent all-around machines, especially with quick-disconnect bucket and
options. This machine can keep the batch plant aggregate bins full, and by adding forks can load
and unload tractor trailers. Front-end loaders may be used to keep the storage area and
construction roads flat. Finally, they will move the air compressor, post-tensioning and grouting
equipment around the storage area. With a variety of manufacturers and equipment sizes, frontend loaders are a versatile machine that is a strong asset to the casting yard.
Compressors
There are many uses for compressors in the casting yard, including air tools at the segmental
forms, batch plant needs, QC lab, and sandblasting needs. Since using air tools will increase labor
productivity, a centrally located compressor with a suitably sized holding tank is warranted. After
the casting yard layout has been determined, locate air supply line routes to each work zone.
Determine where you will be sandblasting segment joints, etc., and whether it will be at one
location or whether a trailer-mounted compressor should be purchased. Review all OSHA, state,
and local ordinances regarding installation requirements.
18 of 55
Survey Equipment
A one-second accuracy theodolite is used for centerline checks and elevation readings with a
builder's level capable of reading to 0.001-foot using an invar rod. Project specifications should be
carefully reviewed for requirements. Monopod setups for the instruments are normally used. In
certain applications a station that covers the entire project may be advantageous.
Winches, Screeds, Vibrators
Winches are a popular method for moving the matchcast segment to and from the casting position
along the rails provided by the form manufacturer. Usually a pulley system is utilized on the
opposite side of the form so that only one winch per segmental form is needed. The winch size is
based on segment weight and coefficient of fiction of the rollers running along the rails, with an
appropriate safety factor.
Screed manufacturers produce a variety of screeds that operate on air, gas, diesel, and electric.
Each has benefits if used with manufacturer's recommendations. Carefully review the specific
needs of your casting operation. It is important to remember that the concrete should already have
been vibrated using other methods. The screed's purpose is to level and consolidate the top
surface only.
Two types of vibrators can be used in precast segmental (internal and external). Typically, only
handheld internal vibrators are used, preferably in 18" maximum lifts. If the contractor is casting
complex segments or congested rebar configurations, the additionai use of external vibrators can
ensure proper consolidation and an aesthetic form finish. A small roller screed or air screed system
to finish the deck surface is desirable.
Generator
Generators come in a variety of sizes to assist startup and daily casting operations. Many casting
yards are setup in remote areas where a small generator will be necessary to get the workers
started. Have the electrical contractor estimate total kilowatt usage of the batch plant, casting yard,
and office needs. This information can be used to evaluate back-up generator requirements. To
ensure productivity in rural areas (especially areas subject to frequently black/brown outs), a large
back-up generator can eliminate project delays.
Sandblast Equipment
The chief usage of the casting yard sandblaster is for light cleaning of the segmental matchcast
joints prior to shipment. The joint faces must not be altered by this process. Depending on
contractor preference, this task can be accomplished by a stationary or mobile setup. Review the
project specifications and epoxy joint adhesive manufacturer's recommendation for required
surface preparation to determine sandblasting equipment, compressor capacity, and sandblast
material's composition and grit size.
Computers
Desktops and/or laptops serve many uses at the casting yard. The most vital usage is maintaining
the daily geometry control software input/output to keep casting on target. The batch plant will
have its own computer, tracking hatching operations and material usage. Office staff will be
coordinating submittal status of a host of startup submittals for casting yard layout, equipment,
materials, concrete mix designs and ongoing shop drawing approvals. Field personnel will be
monitoring material inventory and purchasing requirements. The proper computer systems,
software, and well-thought-out networking and internet linking requirements will promote a
successful operation.
19 of 55
Lab Equipment
The concrete specifications will detail the AASHTO, PC!, and ASTM standards to be followed
during the approval and day-to-day casting operations. Since most projects are of short duration
concentrate the on-site lab focus on the daily aspects of quality control. Specialized testing by an
AASHTO-Certified Laboratory will be required for petrographic analysis of the course and fine
aggregates, alkali-silica reaction tests, modulus of elasticity test, and creep and shrinkage tests;
visiting the AASHTO website will list local certified labs.
Prioritize the lab setup depending on the casting yard requirements. Usually the concrete mix
design is the first task. Determine post-tensioning and grouting testing requirements. Some
projects will require plant certification by PC! or NPCA. Both organizations will be helpful in
concrete lab setup, preparing a quality control procedures manual, and addressing QC personnel
certifications. The website address for each organization is as follows:
htto://www.aashto.org/
htto://www.aci int.org/
htto://www.astrn.org/
9.1. 7 Facilities
9.1.7.1 OfficeTrailerlocations
Unless the property has an existing office space that can be economically configured to the project
needs, explore the availability of mobile office trailers which come in a variety of sizes and
accommodations. Also, these trailers can be grouped together easily with stairs and decks to
Troubleshooting and quick resolutions are key components of a well-run casting yard. The office
complex should be suitable for all parties; in proximity to each other, close to the center of the
casting yard, and near the QC lab.
Inspectors
Inspectors should have sufficient office space to review plans and specifications, each should have
a desk, chair, locking file cabinet, phone and fax on larger projects, mobile radios, computers and
web access might be required. The larger and/or more complex projects will require detailed task
assignments and close monitoring by senior staff.
Surveyors/Engineers
These staff members will require everything listed above plus the use of custom computer setups
with specialized software depending on project specifics. A 'Geometry Control Manual' should be
issued to monitor daily operations. The precaster's surveyor and the inspector's surveyor should
each have their own geometry control programs to be able to make independent checks against
each others set up numbers.
QA/QC Personnel
The ASCE Manual of Professional Practice "Quality in the Constructed Project" defines and
discusses Quality Assurance and Quality Control as follows:
(J
Chapter 9. 0- Production of Precast Segments
20 of 55
A 'Quality Control Manual' and 'Repair Procedures Manual' should be issued to provide daily
operational procedures.
9.1. 7.2 Form Locations
Each segmental form will require some servicing by crane and material handlers on a daily basis,
thus, the casting yard layout needs to accommodate many tasks. Casting yard layouts will be
controlled by the choice of equipment purchased.
21 of 55
()
Chapter 9. 0- Production of Precast Segments
22 of 55
Casting yard layout is based on workflow efficiencies obtained by creating an assembly line
enviromnent. Rebar jig assemblies can be constmcted of wood or steel depending on a variety of
factors. A mioirnum of two rebar jigs is recommended for each casting form. Typical rebar jig
assemblies must operate in a simple manner for daily cycling requirements. However, these jigs
must adapt to the versatility of the casting form they serve. Prior to fabrication of rebar jigs
analyze every segment configuration requirement to ensure smooth transitions. Most pier and
expansion joint segments can be pre-tied to the top ofthe webs. This will accelerate the casting
process, especially when the piers are starter segments for each span.
23 of 55
24 of 55
temperature extremes, and hours of operation anticipated minus minimum tank pressure capacity
)
Figure 9.14- Storage Yard Layout
Once casting is complete there is still much work to be done to the segments before they are ready
for delivery and erection. Once the concrete has reached a predetermined strength the transverse
tendons require stressing and grouting. Inevitably, some cosmetic work will be required to ensure
the segments meet appearance requirements. This cosmetic work could range from rubbing the
segment and lightly grinding the edges to any structural repairs that may be necessary. The final
step is to lightly sandblast the faces to remove any laitance, dirt, debonding agents, etc. before
segments are delivered for erection.
25 of 55
To avoid multiple handling of the segments, much of this work can be done in the storage yard.
Ideally, the segments of the same span should be stored together. This makes it easier to track
spans that are ready for delivery, as well completion of the fmish work a span at a time without
frequent relocation of crews and equipment.
The key to setting up the yard is leaving enough space between segments to allow a scissor lift or
man lift to maneuver between the ends of the segments and to have access to the transverse
tendons with a stressing jack and pump. The crew will also need to get to the ends of the
segments for grouting. The equipment being used will dictate the amount of room required
between the segments.
erection.
As with most segmental construction projects, the casting schedule is driven by the sequence of
erection. It is helpful to designate a row or series of rows in the storage yard layout for individual
spans. This will make finishing much more efficient and will allow the loading crews to locate
segments more quickly at time of delivery.
The overall purpose in setting up the storage yard is efficiency. The more efficient the yard crew
and equipment operators are, the less money it costs to run the yard. Since there is never
unlimited access to equipment there is a risk of having a crew waiting for the crane to address their
needs. If the yard is organized, it will not be necessary for workmen to spend time looking for
segments at time of delivery. Efficiency is the key to a well-run yard.
26 of 55
\J
Upon award of the project, write purchase orders to all of the vendors who have been working
with a letter of intent. These vendors should be able to move directly into production, thus
delivering the material more quickly than would be possible without the early commitments from
the successful contractor.
9.2
9.2.1
The long line method refers to casting all the segments of a run by moving the form from one
segment to the next without moving any segment.
all segments of a span, when the deck has been designed to be erected span by span, or
all the segments of one cantilever arm or both cantilever arms on either side of a pier when
the deck has been designed to be erected using the balanced cantilever method. When both
arms are cast at the same time, the pier segment is also cast in the long line bed. This
a bottom form or soffit which is fixed and has the same total length as the entire casting run.
The soffit must be made in the profile of the structure with corrections for short-term and
long-term deflections. In other words, the soffit is set to be cambered geometry or casting
curve.
external forms, core forms and front bulkhead, which is one segment long and are moved
along the run. When two cantilever arms are cast symmetrically there are two sets of movable
forms, one on either side of the pier segment. The external forms usually have a fixed height
equal to the deepest segment of the run. The core forms and the movable leading bulkhead
must be adjustable in height when the deck has a variable depth.
The long line method was the first method used for precasting segments as it has the obvious
advantage that all the geometry control is done when constructing the soffit, thus simplifying this
process during segment production. Traditionally, the soffit is fixed for the entire length, and the
ground support is stiff enough that the settlements of any segment do not affect the achieved
geometry. The long line forms used for the San Francisco-Oakland East Bay Bridge provided for
adjustment in the soffit geometry as well as slight horizontal curvature.
The disadvantages of this method are:
generally no allowance for smaller horizontal or vertical variations. In other words, all the
spans must have the same shape in their theoretical profile and alignment
if the soffit is fixed, it can be made only for one casting curve, which must be used for all the
casting runs. In general, large variations in casting geometry are difficult to obtain
the forms are rarely re-usable from one project to another
However, in order to make this casting method more practical for real bridge cases, some slight
variations have always been made. Particularly, the soffit can be divided into individual panels for
each segment which are still supported by a common stiff foundation, but which allow some slight
vertical adjustments by means of shims or screw jacks to suit differences in the casting curves.
)
Chapter 9. 0- Production of Precast Segments
27 of 55
r--0
Removal sequence
Segments corllpleled
cantilever was controlled simply by setting the bulkhead to the correct height.
28 of 55
Figure 9.18 -Pakse Bridge- General View of the Long Line Bed
(Photo courtesy ofParsons)
Figure 9.19- Pakse Bridge- View of the Soffit Support Structure and Form Guide Rails
(Photo courtesy ofParsons)
29 of 55
To benefit from the obvious geometry control advantage of the long line method while
compensating for its shortfalls, radical changes to the long line method have been made for two
current projects:
For the curbside expansion at BW! Airport (Figures 9.20 and 9.21), the segments have a nontraditional shape as they consist of two lateral solid concrete beams with a large deck slab
supported on steel transverse floor beams. The geometry of each run is different and complex, but
a run consists of a maximum of four segments. The alignment is set prior to each run by fixing
curved rails to a stiff concrete platform following the theoretical aligmnent shape. The forms are
then fixed to these rails and can be adjusted in height.
Figure 9.20- BWI Curbside Expansion Ramps- General View of the Long Line Bed
(Photo courtesy of Par.>ons)
~,)
30 of 55
-~
Figure 9.21- BWI Curbside Expansion Ramps- View of the Form Support Structure
(Photo courtesy ofParsons)
)
For the San Francisco-Oakland Bay Skyway Bridge replacement project, 44 cantilever arms are
cast with the long line method, out of which 10 have a curved alignment (see Figures 9.22 and
9.23). The soffit form consists of individual forms for each segment, individually supported on
short shoring towers which are set on a concrete slab but not fixed. Due to the weight of each
segment (750T), the settlements are not negligible and must be considered to account for geometry
control.
A custom-made geometry control software was used to track the as-cast geometry and provide
adjustments for the segments.
31 of 55
Figure 9.22- San Francisco-Oakland Bay Bridge Skyway- General View ofLong Line Bed
(Photo courtesy ofParsons)
Figure 9.23- San Francisco-Oakland Bay Bridge Skyway- General View of a Long Line Bed
(Photo courtesy of Parsons)
32 of 55
9.2.2
space requirements are much less compared to the long line method
the entire manufacturing process is centralized
the system is extremely adaptable to geometry variations such as horizontal and vertical
curvature and super-elevation transitions which are obtained without increase in costs
the forms are reusable for other projects.
The disadvantage of the system is that the match casting segment must be very accurately placed.
There is no tolerance for large casting errors.
Illustrations of short line forms in use are shown in Figures 9.26 through 9.31.
)
Bulkhead
MovaU/e beams
I o carry core
forms
33 of 55
Bulkhead
--~il>ft
Natatr-cul
seamenf
'1:==~-- screWB/}ack
Adjuslmenf
..-
Reils
Figure 9.25- Casting Cell (Short Line Method)
\)
Chapter 9. 0- Production of Precast Segments
34 of 55
Figure 9.27- Bulkhead and Wing Forms, Lee Roy Selmon Crosstown Expressway Tampa, FL
(Photo courtesy ofSouthern Forms, Inc.)
Figure 9.28- Wing Form Supports, Lee Roy Selmon Crosstown Expressway Tampa, FL
(Photo courte.\y of Southern Forms, Inc.)
\J
Chapter 9. 0- Production of Precast Segments
35 of 55
Figure 9.29- Diaphragm Segment Form, Lee Roy Selmon Crosstown Expressway, Tampa, FL
(Photo courtesy of Southern Forms, Inc.)
i.")
36 of 55
.'!
Figure 9.31 - Completed Diaphragm Segment, Lee Roy Selmon Crosstown Expressway Tampa, FL
(Photo courtesy ofSouthern Forms, inc.)
9.3
Match Casting
This is a method where fresh concrete of the new segment is cast against the already hardened
concrete of the old segment. A bond breaker (usually a mixture of wax, soap, and talcum powder,
but there are also chemical compounds) is applied to the hardened concrete surface in order to
ensure that the segments will come apart. The match casting technique, as applied now on
thousands of segments, is based on the fact that, provided proper precautions are taken, the
segments will come apart cleanly, and, upon erection, will join together perfectly with the one
joint being almost invisible.
The precautions are merely the careful application of the bond breaker and the avoidance of
jamming protrusions which make it physically difficult to break the bond.
For correct fit at the time of erection, the joint faces must not have been altered, except for a light
sandblasting. This generally means that no work can be done on the joint faces, and that segments
must be stressed in such a way that differential deformation cannot occur.
)
Chapter 9. 0- Production of Precast Segments
37 of 55
9.4
Casting Curve
The casting curve is made up of two important components:
1.
The required geometric profile, which is actually the horizontal and vertical curvature and
super-elevation shown on the plans, and
2.
The compensation of deflections. Both the deflections which occur during construction and
the long-term deflections.
The deflections which occur during construction are shown in Figure 9.32. While erecting the
five-segment cantilever shown in Fignre 9.32(a) in the five steps required, both self-weight and
post-tensioning deflections increase as the cantilever increases. Fignre 9.32(b) shows the
deflections after each step. The situation at the end of erection is shown in Figure 9.32(c). The
combined effect of self-weight and post-tensioning will result in some deflection. To have a
horizontal profile after this erection takes place, a casting curve should be provided which is
precisely opposite the calculated deflection line.
In Figure 9.33, structural deflections are shown combined with the geometric profile. The
required geometry of the structure is shown in Figure 9.33(a). The deflections occurring during
construction are shown in Fignre 9.33(b). The structural deflections are compensated in Figure
9.33(c), and finally added to the geometric profile of Figure 9.33(a) to form the casting curve in
Figure 9.33(d).
A casting curve should be shown on the contract drawings based on the details and construction
methods assumed in the design. The casting curve is verified and modified as necessary by the
Contractor based on the details and construction procedures selected for the project.
Deflection dUe
to canl.IJe-t~t&r
post- tensioning
Lh!-llec l.ion
du~
to
selrJIJM'.ight
Fig11re 6.1 ?(b)
Casting cl.trPe
ror simple
rree c.ant.iletl'er-
Figure 6-17(c)
38 of 55
9.5
walls and floors, of plywood or other suitable material, held rigidly by a frame to accurately
define the main concrete surfaces (outside webs and slab soffits)
bulkhead templates cut and/or marked to the proper section size with standard post-tensioning
duct locations accurately defmed
wing cantilever and templates marked and fitted with locators as needed for transverse post
Using a jig of this type also permits rebar, post-tensioning duct positions, and any other hardware
locations to be accurately fJXed and marked up for repeated use. Duct profiles can be traced onto
the walls to ease assembly, and so on. String lines are used to check rebar, cover and duct
positions from open surfaces.
,c=
IT
II
Figure 6.18(a)
Figure 6.18(bJ
Caml>er={-0..~
I I
Figure 6.18(c)
39 of 55
Because segments can vazy a little in shape from each other, contain different post-tensioning duct
and anchorage arrangements, and because the rebar cage will deform in transportation from the jig
to the casting cells, final adjustments must be made after placing the cage in the casting cell.
For pier segments, abutment segments, and expansion joint segments, the typical segment jig
could be modified or a separate jig made. Sometimes the pier and expansion joint segments are
cast in separate casting cells. In such cases, it nright be convenient to fabricate the cage directly in
the casting cell itself.
It is advisable to periodically check the accuracy of jigs and templates as they can deteriorate with
repeated use and adjustments.
Special care is needed when using epoxy-coated rebar in order to avoid damage to the coating
during fabrication. The use of padding materials in the jigs and templates and padded slings will
help. Damaged epoxy coating must be repaired using a "paint-on" epoxy.
Soffits and
outside
surfaces
40 of 55
9.6
All aspects ofiostallatiou ofpost-teusioning ducts and anchomges should be io accordance with
Chapter 3 -Post-Tensioning Duct and Tendon Installation of the FHW A "Post-Tensioniog
Tendon Installation and Grouting Manual."
9.7
Slings
)
Chapter 9. 0- Production of Precast Segments
41 of 55
9.8
9.9
42 of 55
for are:
I.
First, make sure that the forms are thoroughly cleaned, all joints are tight and sealed, all ducts
are aligned and secure, and everything is in its proper place. The form should be lightly oiled
for stripping, and the face of the match cast segment given a coating of a suitable bondbreaking agent.
2.
Place the concrete in the specified sequence (see Figure 9.36). A good placing procedure
should prevent the concrete placed in the bottom of the web from spilling into the bottom
slab. This movement of the web concrete can easily displace rebar and ducts and can pull
concrete away from heavily reinforced bottom anchorages or the web itself, causing
honeycombing. Some flow of the concrete is unavoidable, but it can be minimized by using
the following procedure, which is considered good practice. Other sequences of concrete
placement have also been used successfully, and the procedure presented here is not intended
to prohibit other practices which have provided good results.
(a) The first concrete should be placed in the middle portion of the bottom slab, leaving about
six to twelve inches clear of the side forms at the bottom of the webs. It is possible to do this
by a delivery chute through a trap in the top slab soffit or by a chute through the bulkhead
end. Concrete consistency needs to be flowable enough to fill congested areas, while stiff
enough to avoid blowout of bottom slab during pours four and five (Figure 9.36).
(b) Place the second concrete in the webs and compact it around the bottom comers to
complete the bottom slab. Concrete lifts in webs are recommended to be no more than 24
inches in height.
(c) Finally, place the concrete in the top slab working from the center and outside edges
towards the web. Strike off the top surface and finish as described below.
3.
Use skips, chutes or pumps to deliver concrete, and do not let it fall from a great height as this
causes segregation, and the impact can damage ducts and displace rebar. Concrete placement
should be in accordance with approved procedures and specifications.
4.
Keep as continuous a delivery as possible; avoid holdups which can allow the concrete
already placed to take on an initial set. Sometimes deliberate short waits are necessary,
especially after placing the bottom slab and web comer concrete so that it can stiffen just
enough to take the weight of the rest of the web concrete, but be careful that this waiting is
not overdone to avoid cold joints. Often, use is made of retarders in the concrete mix to
Make proper use of the internal "poker" vibrators to thoroughly consolidate the concrete.
These types of vibrators should be pushed into the concrete for no more than two feet or so,
and should slowly be withdrawn from the same location. Do not move the vibrator sideways
while still in the concrete. Do not use the internal '"poker" vibrators to move concrete around
or to drag it from the webs into the bottom slab, for example, as this will cause poor
compaction and honeycombing. Avoid contact of the vibrator with rebar and post-tensioning
43 of 55
6.
Make sure concrete is thoroughly compacted, especially in awkward areas such as the corners
around heavily reinforced anchorage zones and within spirals. Sound compaction is essential.
7.
The fmish on the top surface should be accomplished by a screed. As this is usually the riding
surface, great care is needed in fmishing. In spite of this being the last job for the day, it
should not be hurried.
8.
Consult specific DOT requirements for placing and finishing concrete tolerancy and
procedures.
t.oadi11g concn:~le
fro-tn webs is uol
good prnctice.
Uf'LNQJ' Use
1nlt.>I'tlal
VJbr<lor
to rno,,e co/lcref(~.
llus wUJ cause
!JoneyconJbiiiC.
It
Opening lor
vibrator-seal
lviU' trup.
Leave BH lo 12 .. clear of
botton1 of inside web fortn
for 2nd. and :Jrd loads.
_QQ_Jj_QJ
mo>~ve~ii.i:i:,:~~~r;;::~
concrete around
Use internal
witiJ internal
vi bra tors- it csn
easily cause voids.
disturb interface
Risk of voids
vibrator to
between loads
and consolidate
llroroughly. ;:
2nd.
l.oad
1st. Load
1"-6.
()
44 of 55
When frnishing a concrete surface, it is important to keep the concrete live for working by proper
vibration, tamping and floating, and leave as if not to add water to wet any stiff areas. This will
create patches of weaker surface material which will dust and wear badly in use. In order to take
advantage of workable concrete, the initial leveling and frnishing should following immediately
after placement. This is the best time to get the surface level. The best quality can be achieved by
frnishing the segments to a smooth finish, and then providing a transversely grooved riding surface
cut after erection of the structure. A small amount of extra cover is specified to allow for the
depth removed by the grinding process prior to grooving.
Be careful not to spoil the top surface when and if the concrete is to be covered for curing. (Use
means to support tarps and prevent contact with top surfaces, etc.)
The top surface of the bottom slab should be finished in a similar manner, although the appearance
of the surface finish is not so critical, it should, nevertheless, be accurate. Mechanical screeds
need not be used on the bottom slab.
)
Chapter 9. 0- Production of Precast Segments
45 of 55
9.12 Curing
In order to achieve a production rate of one segment per day from one casting cell, it is essential to
ensure that curing is proper and sufficient to provide the necessary strength and control of
shrinkage, etc. Project Specifications or Special Provisions prescribe the curing procedures to be
followed.
Curing procedures depend upon the type of concrete, its chemical hardening processes,
temperature and exposure conditions. It is common practice to cover the segment with tarpaulins
and apply steam to maintain a controlled temperature and humidity. Other methods have been
used, including burlap, blankets, water, etc.
With a production rate of one segment per day, clearly the curing process in the casting cell cannot
be more than a few hours from the completion of the casting in the evening to the start of survey
and stripping the next morning. This is why a controlled environment is essential. The segment
curing may be obtained with chemical compounds or water, and should be in accordance with the
contract documents.
46 of 55
9.13 Forms
Stripping of forms should not start until the concrete has reached the required strength. This is
usually specified at 2500 psi. At this strength, it is normally possible to ease off the side forms,
remove the core form, and pull back the match cast segment provided that the top slab is selfsupporting. At this strength, the segment could also be moved on its pallet but not lifted. In case
the reinforcing provided is incapable of carrying the weight of the unsupported top slab at 2500
psi, then transverse post-tensioning must be stressed in full or in part. This would require a higher
strength often specified at 4000 psi. It is customary to break cylinders in order to verify that these
strengths are in fact obtained. Transverse post-tensioning of the top slab in the storage yard is
illustrated in Figure 9.39.
Stripping the forms should be done with care, as it is very easy to cause spalling and other damage
when the concrete is young.
Figure 9.39- Transverse Post-Tensioning of the Top Slab in the Storage Yard
Most casting cell forms are removable in whole pieces (Figure 9.40), but it is advisable to leave
removal of any special block-out forms for as long as possible, as it is very easy to break the edges
ofblockouts.
Stripping and pulling back the match cast segment should be done with particular care. If the
bond breaker has not been properly applied, portions can be broken off either segment. The shear
keys are especially vulnerable. Also, the movement mechanism on the pallets must be examined
and understood by the stripping crew. Loosening of jacks and tilting of the pallet can "lift" the
newly cast segment (see Figure 9.41). This motion can easily damage the shear keys and must be
avoided. Segments may be separated by the following methods:
47 of 55
48 of 55
Inside formwork
~Bulkhead
New
segment
/
/
/
This key
will not
jam
Tllis key wi/1
jam&- break
_ _--t;=ya--
CAUTIO!i;.
In order to break the bond
bet ween the matcb-casl a.nd
bulkhead. it is normal to
no simple solution.
)
Figure 9.41-Striking Match Cast Segment
49 of 55
control. If plinths are shown, the contract documents will specify the design criteria, usually CIP once the
structure is erected. Alternates to allow rebar couplers to avoid projected rebar or to allow the plinth
construction at the casting yard may be present. The plinth layout will detail intermittent gaps to provide
deck drainage. The requirements for concrete surface treatments for secondary plinth pour areas can prove
costly. Also, some upcoming projects are requiring the concrete plinth rebar to be fiberglass. Carefully
review project specifications.
The locations of specialwork, switchgear, high strength rail, rail expansion joints and rail anchors will
require close shop drawing detailing. Address clearance issues with an RFI to avoid casting yard delays.
Identification of the design, location and installation requirements of all LRT features will be crucial. The
system integration placement requirements will probably necessitate a fulltime electrician at the casting
yard.
50 of 55
..
Figure 9.45- CJP plinths with final preparation before rail placement
51 of 55
Methods used for traction power system electrification include a third rail or installing a series of overhead
catenary lines (OCS) to operate the trains. Either option will add to the standard coordination factors at the
casting yard. The industry does utilize AC and DC traction power systems. Most modern light rail projects
are using DC traction electrification system (TES), so our focus is DC current.
52 of 55
DC stray current can cause corrosion of the transit system infrastructure grounding safeguards will be built
into the structure. The post-tensioning system and concrete reinforcement may have grounding system to
eliminate the cumulative effects of the stray current to increase the longevity of the structure. These
measures will also ensure personal safety of the passengers, operators and maintenance crews. Proper
training of production crews and QC/QA staff will ensure competent work procedures are maintained.
Post-tensioning
The contract documents may require grounding the post-tensioning system due to stray current migrating to
the PT tendons. Each tendon will normally require grounding only at one post-tensioning anchorage. One
method is to prep ao area on the backside of the post-tension anchor and attach the ground wire with an
exothermic weld. The individual copper jumper wires can be crimped together and attached to the topslab
reinforcement mat.
53 of 55
Topslab Reinforcement
The upper layer of reinforcement of the topslab may require grounding. One method requires tackwelds on all or a portion of this reinforcement mat. This will entail the use of ASTM A 706 weldable
rebar, which should be specified in the contract documents. A ground wire is then attached with a
crimping tool.
Miscellaneous Metals
Project specifications could require all metallic embeds to be grounded, including patron barriers, hand
rails, expansion joints, access hatches, etc. Grounding continuous items like handrails may mitigate
the grounding requirement to every 40 feet. These requirements can be project specific. Verify if a
copper jumper wire is necessary or addition rebar pieces and tie-wire will suffice. An item checklist
with specific requirements and frequency will mitigate cost and inspection needs.
54 of 55
No.2 is a styrofoam blockout that will enable the ground wires to be connected to the conduit system
within the precast structure.
.)
Chapter 9. 0- Production of Precast Segments
55 of 55
TABLE OF CONTENTS
3
3
Lifting Holes Cast in the Top Slab of Segments
3
Inserts Embedded in the Segment Webs and Protruding Above the Top Slab
4
Lifting Slings or C Hook Frame
5
Handling and Transporting of Precast Segments in Precast Yard
6
Handling precast segment from the new-cast position to the match-cast position 6
Procedures for Handling, Transporting and Erecting Precast Segments
10.3
10.3.1
10.3.1.1
10.3.1.2
10.3.1.3
10.3.2
10.3.2.1
10.3.2.2
10.3.2.3
10.3.3
10.4
10.4.1
10.4.2
10.4.2.1
10.4.2.1.1
10.4.2.1.2
10.4.2.1.3
10.4.2.1.4
10.4.2.1.5
10.4.2.1.6
10.4.2.2
10.4.2.2.1
10.4.2.2.2
10.4.2.2.3
10.4.2.2.4
10.4.2.3
Transporting Precast Segments from the Precast Yard to the Erection Site
Transporting Precast Segments via Water Using Barges
Loading
Transport
Unloading
Transporting Precast Segments Off-site via Land
Loading
Transport
Unloading
Transporting Precast Segments On-site via Land
Erection of Precast Segmental Bridges
Factors for the Selection of Precast Segmental Bridge Erection Methods
Erection Methods for Precast Segmental Bridges
Erection Methods for Span-by-Span Type Bridges
Underslung Trusses with Crane on Ground or Barge Mounted on Water
Erection on Underslung Trusses with Crane or Derrick/Lifter on Deck
Erection with an Overhead Gantry
Full Span Erection with Winches I Strand Jacks
Full Span Carrier I Erector
Full Span Erection on Shoring Falsework
Erection Methods for Balanced Cantilever Bridges
Balanced Cantilever Erection by Crane on Ground or on Water
Balanced Cantilever Erection by Overhead Gantries
Balanced Cantilever Erection with Beam and Winch/Strand Jacks
6
11
11
11
12
12
14
14
14
15
15
19
19
21
22
22
24
25
27
28
29
30
30
32
34
36
37
I of37
TABLE OF FIGURES
Figure 10.1
Figure 10.2
Figure 10.3
Figure 10.4
Figure 10.5
Figure 10.6
Figure 10.7
Figure 10.8
Figure 10.9
Figure 10.10
Figure 10.11
Figure 10.12
Figure 10.13
Figure 10.14
Figure 10.15
Figure 10.16
Figure 10.17
Figure 10.18
Figure 10.19
Figure 10.20
Figure 10.21
Figure 10.22
Figure 10.23
Figure 10.24
Figure 10.25
Figure 10.26
Figure 10.27
Figure 10.28
Figure 10.29
Figure 10.30
Figure 10.31
Figure 10.32
5
7
Straddle Carrier Transporting Segments to Storage. New Baldwin Bridge. CT
7
Gantry Crane on Rails, Singapore LRT
Storing and Stacking of Segments
10
Double Stacking of Segments
10
Barge Transportation of a Segment Hauler
13
13
Barge Transportation of Segment
Gantry Loading Segment on Segment Transport Vehicle, New Baldwin Bridge, CT 16
Truck and Segment on Trailer, New Baldwin Bridge, Connecticut
16
Delivery of Segment to Launching Gantry, New Baldwin Bridge, Connecticut
17
Segment Lifted by Launching Gantry, New Baldwin Bridge, Connecticut
17
Delivery of 85 Ton Diaphragm Segment for the Boston Central Artery Project
18
Crane Erection of Span-by-Span Bridges on Underslung Trusses
22
Crane Erection of Span-by-Span Bridge on Underslung Trusses
23
24
Span-by-Span Erection on Underslung Trusses with Crane or Deck
Span-by Span Erection with an Overhead Gantry
25
Span-by-Span Overhead Gantry Segment Erection
26
Full Span Overhead Erection with Winches
27
Full Span Erection, James River Bridges, Rl
27
Full Span Carrier I Erector
28
Full Span Erection on Shoring Falsework
29
Full Span Erection on Shoring Falsework
29
Balanced Cantilever Erection by Crane
30
Balanced Cantilever Erection by Crane
31
Balanced Cantilever Erection by Barge Mounted Crane
31
Balanced Cantilever Erection by Overhead Gantry
32
Balanced Cantilever Erection by Overhead Gantry
33
Balanced Cantilever Erection by Overhead Gantry
33
Balanced Cantilever Erection with Beam and Winch
34
Balanced Cantilever Erection with Beam and Winch SFO Skyway Bridge
35
Special Erector Used on the Dallas High Five Project, TX
36
Special Erector Used on the Dallas High Five Project, TX
37
Handling Segments
2 of37
10.1
Typically lifting holes are positioned through the top slab near the inside or outside of the webs.
The holes may be formed using corrugated PT duct pieces, tapered inserts, or other methods may
be specified by the Engineer.
The exact positioning of these lifting holes is critical. It is important to develop a proper
positioning and restraining device that will hold the forms in place during the concreting
operations. More than one positioning device might_:!Je needed to accommodate the variations in
the lifting hole layout. It is important to develop a quality control procedure to insure that the right
layout is used. The bars may be overloaded, the segment may not hang properly or the lifting
frame may not fit if these holes are not positioned correctly, or if they move during the concrete
pour.
The lifting frame is secured to the segment through the formed holes with PT bars (Figure
IO.l(a)). The slope and cross fall of the segment can be adjusted by changing the connection
points on the lifting frame, by varying the sling length, or by hydraulically adjusting the relative
position of the frame and the segment.
It is essential the proper stressing requirements of the PT bars is followed when securing the frame
to the segment. The system could be designed to rely on the friction developed between the frame
and the segment to insure that the bars are working in tension. If the bars are not stressed properly.
the frame could slip and shear the PT bars.
After erection of the segments, the lifting holes should to be plugged with an approved non-shrink
grout, or as specified by the Engineer. The hole forms used in the casting yard should provide a
surface that will insure a proper bond between the plug and the segment, and prevent the plug
from falling out.
)
Chapter 10.0 Procedures for Handling, Transporting and Erecting Segments
3 of37
Providing access to form, pour, strip and finish the bottom of the holes, especially when they are
outside the webs may require the use of rolling platforms, personnel lifts, or other movable
platforms. Access inside tall and sloped segments may require the use of sophisticated movable
scaffolding to reach the lifting holes locations.
10.1.21nserts Embedded in the Segment Webs and Protruding Above the Top Slab
Lifting devices that could be embedded in the web include high strength bars, looped strand
bundles, or special inserts.
The high strength bar, plate, nut and coupler assemblies are encased in aPT duct. Care must be
taken when placing the assemblies to ensure that the bottom nut and upper coupler are fully
engaged on the bar.
Because of the lack of visual confirmation, this system poses a risk of accidents if the nuts,
couplers and bars are not properly engaged and secured. However, with proper quality control, it
has been used successfully on many projects. The lifting bars, couplers and nuts typically cannot
be reused because they are embedded in the concrete. High strength lifting bars should never be
welded or exposed to arcing.
The lifting frame is secured to the embedded PT bars. The slope and cross fall of the segment can
be adjusted by changing the connection points on the lifting frame, by varying the sling length, or
by hydraulically adjusting the relative position of the frame and the segment.
It is essential to follow the proper stressing requirement of the PT bars when securing the frame to
the segment. The system may be designed to rely on the friction developed between the frame and
the segment to insure that the bars are working in tension. If the bars are not stressed properly, the
frame may slip and shear the PT bars.
After the segments are erected, the bars may require trimming to provide adequate concrete cover,
When looped strand bundles are used to lift the segments, the loop embedment length and details
must be properly designed. The top of the loop should be encased in a metallic light weight pipe
section and then bent in a U shape. The pipe section is used to make sure that the load is evenly
distributed among the strands. The bottom of the loop should be properly secured to the web rebar
as detailed on the shop drawings. The strand loops should be properly positioned in the segment
and a recess form should be used around each loop penetration. The proper positioning of this
recess form may be problematic and hard to maintain during the pour.
After erection, the loops are trimmed inside the recess to provide the proper concrete cover. The
recess is then filled with the specified grout or patching material. The recess detail should be
analyzed carefully in order to keep the patch from popping out under traffic.
4 of37
The exact positioning of any of these inserts is critical. It is important to develop positioning and
restraining device that will hold the inserts in place and plumb during the concreting operations.
More than one positioning device may be needed to accommodate the variations in the lifting
insert layout. A quality control procedure is required to insure that the right layout is used. The
inserts may get overloaded, the segment may not hang properly, or the lifting frame may not fit if
these inserts are not positioned correctly, or if they move during the concrete pour.
The use of embedded rebar to lift the segments is not recommended.
This method is not suitable for balanced cantilever erection, or in sitmi.tions where the segment
must be placed in its final position prior to disconnecting from the erection equipment.
Slings are commonly used to lift the segments for precast segmental erection using underslung
trusses or falsework. Wood, plastic, or rubber softeners or shoes should be used around the
segment edges to prevent any damage to the segment or slings.
Another segment handling system that does not require the use oflifting holes or embedded inserts
is the C hook lifting frame (Figure IO.l(c)).This lifting frame can get quite heavy when handling
large segments and could affect the selection and size of the erection equipment.
In some situations, a combination of lifting devices might be used on the same segment. The
segment could be lifted with a sling in the casting yard and during transport, and then erected with
a lifting frame at the erection site. The segment structural integrity should to be verified
regardless of which lifting system is used. At least one lifting option that is acceptable to the
designer should be shown on the contract drawings.
Tiu:nbuck/es or
lor control
~celp$
of crosstaJJ
C-Hook
Fl;:~rt
1./(bJ
with slings,
Shim
Profiled shim
Figure 10.1-Hand/ingSegments
... )
Chapter I 0.0 Procedures for Handling, Transporting and Erecting Segments
5 of37
2)
3)
4)
5)
6)
The sides and bottoms of the inner core form are loosened up. The concrete should
have attained the minimum strength requirements identified in the casting manual
before performing this operation. None of the form elements supporting the concrete
should be distrubed. The segment should not be exposed to excessive vibration.
Typically no post tensioning is required to perform these operations. It is essential
that the as-cast survey of both new cast and match cast segments be performed
before starting any loosening or stripping activities on the forms.
The match-cast segment is broken free from the new-cast segment. The segments
should be separated as indicated in the casting manual and in accordance with the
recommendations of the form designer. Typically, the soffit table under the match
cast segment is tilted slightly as the tables are pushed apart using horizontal
hydraulic or mechanical jacks. It is important to keep in mind that the segment
separation takes place while the concrete is still relatively green, and the shear keys
are especially vulnerable to breakage.
The match-cast segment is rolled away on its soffit. Once the segments are separated,
the match cast segment is rolled on its table using a winch, a hydraulic system, or a
loader.
The inner core form is lowered and retracted and the wing forms are lowered. When
the concrete has reached the appropriate strength and, if required, the transverse PT
is stressed. The transverse PT may be stressed in stages. The form elements
supporting the concrete can be removed, the core form is folded and retracted, and
the wing forms are lowered.
The new-cast is freed from the bulkhead. Depending of the form design, the new cast
segment may be separated from the bulkhead using the same method as for the
separation ofthe match cast segment. The segments should be handled carefully in
order to avoid shear key breakage.
The new cast segment is rolled on the soffit form. Once the new cast segment is
separated from the bulkhead, it is rolled on its table using a winch, a hydraulic
system or a loader. Later, after the rebar cage installation, the new cast segment is
rolled again, and is set and adjusted in the match cast position.
10.2.2 Handling and Transporting of Precast Segments From the Casting Area
to the Storage Area
Depending on the yard set up, point and patch needs, PT requirements, grouting, transverse PT
pour backs, and other finishing issues, the segment will be moved to either an intermediate
finishing area or directly to the storage area where it will be finished.
Before lifting the segment, the concrete should have reached the specified lifting strength and the
required transverse PT should be stressed.
Storage areas should be properly prepared to prevent any settlement under the segments.
Once the segment is connected to the lifting frame or to the slings, it can be moved to the storage
yard.
6 of37
Commercially available equipment could be used to move the segments from the casting area to
the storage area. However, due to the site conditions, yard layout, optimization of the operations
and economics, custom built equipment may be better suited for the project (see Figure 10.2).
Figure 10.2- Straddle Carrier Transporting Segments to Storage, New Baldwin Bridge, Connecticut
(photo courtesy of Perini/Homsi)
7 of37
The segment lifting frame dimensions and weight should be considered in reference to the
capacity of handling equipment.
Safety details such as wheels guards equipped with automatic engine kill switches, travel alarms,
air horns, proper communication between the operator and the spotters, and other safety devices
are essential to the safe operation of the large handling equipment in the narrow runways of the
storage area.
Some of the typical methods used to move the segments in the yard are:
1) Cranes with or without tractor/trailers or special carrier
Depending on the project needs, the availability of equipments and economics, the
segments may be moved using large cranes to either load the segments on tractor/trailers
or special carriers, or to crawl with the segment directly into the storage area. This
method may be inefficient, but may be used if the storage area layout can accommodate
large runways for the travel and swing radii of the cranes and the transporters.
2) Rail Mounted Gantry Cranes (see Figure 10.3)
If the yard layout is rectangular and all the segments can be stored on a long and narrow
strip of land, a rail mounted gantry crane would be the ideal solution. This type of
equipment can operate in very narrow runways and optimizes utilization of the storage
area. The rail mounted crane can typically straddle several segments.
If electric power is available, this type of gantry could be operated using electric
umbilical cords running off the permanent power grid. This solution is usually more
economical that equipping the gantries with generators.
Rail mounted gantry cranes require special foundations under the rails and should include
provision to correct for any ground settlement under the tracks during the life of the
project. These gantries require relatively flat terrain.
3) Rubber Tired Straddle Cranes
If the storage area is square or irregular, a rubber tired straddle crane might be needed.
These cranes typically straddle one or two segments and will require multiple runways.
The runways should be wide enough to allow the safe operation ofthe equipment
between the rows of segments.
This equipment is typically capable offour wheel steering and four wheel drive
operations. These features are quite helpful when negotiating tight turns in the yard.
The tire pressure exerted by the straddle cranes is quite high and requires proper soil
preparation. Furthermore, measures should be taken to constantly monitor and dress up
the runways. Ignored ruts and depressions will affect the operation of the equipment, and
will cause premature wear and tear on the drive and steering mechanisms. Proper
drainage throughout the casting yard must be provided to avoid water ponding in the
runways.
The path and turning radius of straddle cranes must be considered when laying out the
casting yard. The straddle crane manufacturer should be made aware of the soil
conditions and terrain topography in order to properly size the drive and steering systems.
8 of37
The soil conditions in the storage area must be analyzed and proper soil preparation must be
provided to minimize any settlement under the weight of the segments.
Crane mats or concrete pads may be needed to spread the load. The segments should be stored on
hard timber blocks using a three-point support configuration (Figure I 0.4) in order to avoid
warping the segment during the storage period. Warping of the segments would cause
complications in fit up of the segments during the erection and the fmal geometry of the bridge.
Variable depth segments require more complex cribbing due to their sloped bottom soffits, in
order to keep the segments vertical and provide proper stability.
The storage area should be monitored periodically, especially after heavy rain, to check for any
settlement of the segment supports. If a settlement is observed that would jeopardize the stability
of the segment, or if the three-point support configuration has been compromised, the segments
should be relocated, and the settlement problem should be corrected.
Double stacking of the segments is not always permitted, but is possible depending on the design
of the segment (See Figure 10.5). It is essential that the designer check the effects oflocalized
loadings due to stacking to avoid cracking. Double stacking requires the approval of the Engineer.
The segments should be periodically checked for any damage resulting from the double stacking.
Barrier rebar projections must be considered when double stacking. Double stacking of severely
variable depth segments is not recommended.
When double stacking is being considered it is essential to check that the segment handling
equipment has the clearance to clear two segments with rebar projections on dunnage, as well as a
for storage.
Finishing of the segment could be done in the fmishing area or in the storage area. Access should
be provided for transverse post-tensioning and grouting, cleaning of the joint faces, point and
patch, secondary pours, and repair of small defects. If secondary pours are needed, it is important
to provide runways wide enough to accommodate concrete trucks or other delivery methods.
9 of37
Check localized
condiUons for
structural adequacy
(Engineer)
10 of37
10.3 Transporting Precast Segments from the Precast Yard to the Erection Site
Before the segments are transported to the erection site, it is important to verify that all quality
control documents are properly completed, and that the segment has been accepted for
incorporation in the bridge. As a minimum, the segment should be checked for the following:
I)
2)
3)
4)
5)
10.3.1.1 Loading
If the casting yard does not have access to a navigable waterway, the segments will be transported as
described in section 10.3.1.2 to a location with access to a navigable waterway.
If the casting yard has easy access to a navigable waterway, the following items must be considered:
I) Any permitting issues that would restrict access to the waterway from that property.
2)
Water depth adjacent to the edge of the project. Dredging permit requirements, and
buried utilities in the vicinity of the property shore line.
3)
Abutters issues
4)
Waterway width and the potential for blocking the channel during the loading of segments
5)
6)
7)
)
Chapter I 0.0 Procedures for Handling, Transporting and Erecting Segments
llof37
If a slip or finger bulkhead type is selected, the barges could be loaded directly with the straddle crane used
in the storage yard.
If a bulkhead parallel to the waterway is selected, the segments will be delivered to the bulkhead area by
the straddle crane and will be loaded on the barge using a crane with enough capacity to reach to the
centerline of the barge. This method will require additional sets of segment storage pads and lifting frames
at the bulkhead to stage the segments during the transfer from the straddle crane to the loading crane.
10.3.1.2 Transport
The barges used for segment transport must be checked by a qualified Engineer or Marine Architect to
certifY the integrity and fitness of these barges. Figure 10.6 shows barge transportation of a segment
hauler. Another view of segment transport by barge is shown in Figure 10.7.
ABS certification may be required.
A proper cribbing and tie-down system must be provided to secure the segments during the transport.
Variable depth segments require a more complex and adjustable cribbing and tie-down system.
The hull of the barge must be checked and strengthened as necessary to accommodate the segment loads.
The depth of the waterway, especially outside the navigational charmels, must be checked and cleared of
any obstructions.
Water depths affected by tides, seasonal variations and prevailing winds, should be evaluated.
Freezing rivers and waterways could have a major impact on the segment delivery. The weather forecast
should be checked prior to loading and moving the barges. Since barge towing is quite weather dependent,
the logistics of transport, on-site mooring and storage should be studied in details. The path of the tugboat
and the loaded barges should be checked for overhead obstructions, low clearance bridges, movable bridge
schedules and operational reliability, etc ...
10.3.1.3 Unloading
When the segments are delivered to the erection site it is necessary to pressure wash the exposed faces,
especially the match cast faces and any exposed steel or secondary pour back area in order to wash off the
salt spray. If the PT ducts were not properly sealed prior to the trip, they must also be flushed with potable
water and dried with oil free compressed air.
If the segments can be delivered within the reach of the erection equipment, they will be unloaded directly
from the barge.
Depending on the wave action and swells in the area, connecting the lifting frames to the segments could be
difficult and might require special attachments to guide, hold and secure the frame to the segment as the
lifting bars are being tightened and stressed. Pinch point type injuries and falls are a serious concern during
this operation.
Due to the potential of bouncing of the frame on the segment as it is being secured, the proper aligmnent of
the winch cables inside the block sheaves should verified prior to lifting the segment off the barge.
Proper access and fall protection should provide safe access to reach the top slab inside the box, the top of
the segments, and the areas to be pressure washed.
If the segments are being stored on barges near the erection site, proper mooring must be provided.
Mooring should be properly permitted and designed to withstand the local wind, water flow, waves, and
swell conditions.
12 of37
13 of 37
In some instances the large barges needed to transport the segments to the project vicinity are too large and
deep to get all the way to the erection site. In these situations, the segments could be transferred, at a great
expense, to smaller barges or could be unloaded and transferred to a land hauler at a potentially equal or
greater expense.
If the segments have to be transferred from the barges to land hauler in order to reach the erection
equipment, an unloading/staging area near site must be set up. This area will be set up with either a
bulkhead parallel to the shoreline a slip or fmger piers as discussed in theloading section above.
Water depth and dredging permits should to be investigated. The bulkhead parallel to the shoreline is the
most likely solution at the job site. If a bulkhead is used, the segments will be unloaded with a crane and
loaded on a tractor /trailer set up or a special hauler and transported to the erection equipment.
The haul road should be designed to accommodate the segment hauler's horse power and turning radiuses.
A low profile/rough terrain rubber tire straddle crane can be used to move the segments from the unloading
area to the staging area, and later on to the erection equipment.
10.3.2.1 Loading
The segments could be loaded on the hauler with the same straddle crane used in the storage yard.
Typically a section of the storage yard is designated as the loading area. This section should have easy
truck access and gantry crane rail crossing.
10.3.2.2 Transport
Several issues should be considered when analyzing the segment transport to the erection site:
i) The weight and dimensions of the segments often exceeds the legal load allowed on the local
streets and highways.
ii) The over-weight or over-dimension permitting procedures vary from one locality to another.
iii) The existing bridges in the immediate vicinity of the project, and sometimes the only access
to the erection site might be derated and load restricted.
iv) The haul route might be crossing overpasses, buried utilities, underground box culverts, etc ...
all of which might have different load rating.
v)
In some regions, no over-weight permits are issued in the spring due to ground thawing
concerns. No segments, heavy loads or equipment can be moved outside the project limits
during this period.
vi) Police and special escort vehicle might be required.
vii) Some locality with traffic congestion concerns or sensitive abutters may impose additional
etc ... along the haul route should be checked. The barrier rebar on top of the segments is
usually the controlling element.
ix) The distance from the casting yard to the erection site and the availability of haulers could
require the setting up of a staging area at the erection site.
Depending on the segment load and the permit requirements, multi-axle tractor trailer combination might
be used to haul the segments. For extra heavy segments, special selfleveling, all-wheel steering hydraulic
haulers can be used. Special tractors, weighted down with massive counterweights for extra traction, are
typically used to pull the special haulers. Some of these special haulers are self propelled, however, they
move at very slow speeds and could be restricted from travelling over highways. Under certain conditions
and if rail sighting are available at both the casting yard and at the erection site, transporting the segments
by rail might be a feasible solution. However, the unreliability of the rail system schedule and the lack of
control over the railroad operations make this solution a very risky choice.
14of37
10.3.2.3 Unloading
Whenever possible the segments should be delivered directly to the erection equipment.
In some instances, double handling the segments and storing them onsite cannot be avoided.
If staging areas are used, and if a crane is used to unload the segments, the crane and haulers will be needed
again later on to load and transport the segments to the erection equipment. Alternatively, the haulers can
be uuloaded with a low profile rough terrain straddle crane that will later on deliver the segments to the
erection equipment. If the segments are being delivered on top of the completed spans, the superstructure
should be check for the loaded hauler or straddle crane reactions. The haul roads should be designed to
accommodate the segment hauler's horse power and turning radiuses. If the segments have to be
transferred to a barge, the sarue set up discussed in "transport off site over water" should be considered.
15 of37
Figure 10.9- Truck and Segment on Trailer, New Baldwin Bridge, Connecticut
(photo courtesy of Perini!Homsi)
~.J
16 of 37
Figure 10.10- Delivery of Segment to Launching Gantry, New Baldwin Bridge, Connecticut
(photo courtesy of Perini/Homsi)
Figure 10.11- Segment Lifted by Launching Gantry, New Baldwin Bridge, Connecticut
(photo courtesy of Perini/Homsi)
17of37
Figure 10.12- Delivery of 85 Ton Diaphragm Segment for the Boston Central Artery Project
(Photo courtesy of Unistress Corporation)
18 of37
.)
Superstructure Design
The geometric characteristics of the superstructure including span length, pier height, horizontal curvature,
maximum grades and cross slope, and the degree of consistency and repeatability of these characteristics
throughout the project have a major impact on the erection methods used. Projects with small segments or
very tight radius curves require the use of cranes while large projects with repetitive span layout would
favor undersluog trusses or overhead gantries. Short projects with very high piers and heavy segments
might require a beam and winch set up to erect the heavy segments.
It is important to verify that the superstructure is capable of carrying the additional construction loads
introduced by the erection equipments. Ground or barge mounted cranes introduce minimal construction
load into the structure while overhead gantries tends to introduce some of the most significant loads the
bridge will ever see during the construction stages.
Access and Site Conditions
Access and site conditions are probably the most significant factors in determining the most efficient
erection method.
When working over land, the factors that should be considered range from environmental issues such as
wetlands and protected habitats to interferences with local traffic, businesses and railroad crossings.
When working over water, the factors that affect the selection process include:
Water conditions (depth, flow, ice, etc.)
Required permits
The feasibility and cost of constructing access trestles
Wave action and barge bounce must be taken in consideration when connecting the lifting beams
to the segments
Salt water splash on the match cast faces and inside the PT ducts must be addressed.
Proper design, analysis and certification of transport barges must be performed
Loading and unloading facilities must be studied and permitted.
19 of37
The availability of suitable real estate in the vicinity of the project site for a casting yard will influence the
erection and segment delivery methods. The distance from the precast yard to the bridge site will determine
the number of transport vehicles, the need to provide staging areas and double handling or barge docking
facilities at the erection site. In case the of a limited storage area where double stacking is being considered,
the segments must be checked for that loading condition, and proper dwmage and soil preparation must be
performed in order to avoid differential settlement.
The route from the precast yard location to the erection site will dictate the size and type of segment that
can be transported, especially if the route includes low overhead clearance or weight restrictions. Local
ordinances and permit requirements and costs also must be considered when selecting the casting yard
location.
The transport route from the casting yard to the erection site must be checked for overhead clearances
(power lines and overpasses) and for underground structures (utilities and culverts, etc.).
Transport permit requirements vary widely from one location to another and seasonal restrictions may
apply.
Project Team
The experience of the project team, which includes the Owner, Designer, CEI, Contractor's engineer and
the Contractor is another major factor that may affect the selection of the erection method. The more
experienced the team, especially the Contractor, the more open he will be to considering a sophisticated
erection method if it is deemed to be the most efficient way to construct the project.
The availability of skilled labor in the project market is another factor that should be considered during the
selection of complex erection methods.
Equipment Availability
The availability of erection equipment (cranes or specialized equipment), new or used, the competition
among the suppliers and the availability of steel fabricators during the selection process will affect the cost
and delivery schedule of the erection equipment, and will influence the selection process.
The additional costs associated with the mobilization, assembly and commissioning of new specialized
equipment, and the cost of refurbishing and modifying existing equipment, should not be underestimated as
it is a major component of the cost and time analysis in the selection process.
The more expensive specialized equipment will benefit from the economy of scale of larger projects where .
the initial investment can be depreciated over a large project.
20 of37
-)
10.4.2.1
10.4.2.1.1
10.4.2.1.2
10.4.2.1.3
10.4.2.1.4
10.4.2.1.5
10.4.2.1.6
10.4.2.2
10.4.2.2.1
10.4.2.2.2
10.4.2.2.3
10.4.2.2.4
10.4.2.3
. . J
Chapter 10.0 Procedures for Handling, Transporting and Erecting Segments
21 of37
Access along the bridge alignment must be maintained for the following operations:
Foundations and substructure construction
Pier bracket installation and relocation
Segment delivery
Erection crane access and swing radius
Material delivery
Support operations
Access must be maintained throughout the erection phase. This could be quite costly if working
over the water mainly due to trestle and /or barges and tugboat costs.
This method is quite dependent on the weather conditions especially when working on the water.
This method is governed by the maintenance of traffic rules when working on land.
If working over water, special loading and unloading facilities must be provided.
The pier brackets supporting the trusses are typically cycled and erected on the leading pier by the
erection crane.
,J
Chapter 10.0 Procedures for Handling, Transporting and Erecting Segments
22 of37
Winches and selflaunching oflong trusses: In this method, the long trusses are designed
to be self contained and are capable of self launching from pier to pier using winches
mounted on the deck or on the trusses.
Jacks and grips to push long trusses forward: In this method, the long trusses are designed
to be self contained aod are capable of self launching from pier to pier using a hydraulic
jacking mechanism mounted to the superstructure and a perforated rail attached to the
trusses.
Crane and C hook to relocate short trusses: In this method, the short trusses are fitted
with a C hook allowing the trusses to be relocated by cranes from span to span.
Crane dragging trusses on pier brackets rollers or on C hook trailers: In this method, long
trusses can be relocated from pier to pier using a ground based crane that will partially
support the nose end of the trusses while the tail of the trusses are rolling on the pier
brackets. The trusses are pulled forward toward the next pier. For short trusses the trusses
can be fitted with a C hook attached to trailers on top of the deck. The trusses can be
relocated from pier to pier using a ground based crane that will partially support the nose
end of the trusses and pull it forward toward the next pier while the rear of the trusses are
supported by the C hook on Trailers. This method should be avoided although it is
sometimes shown in the contract drawings. Dragging the trusses with cranes is a very
delicate aod risky operation because of the high potential of side loading the crane boom.
Combinations of the above
The precast yard location and distance from the bridge site has a major impact on the erection
operations. If the continuous delivery of segments using a reasonable number of trucks cannot be
maintained, the segments will have to be delivered to the site off shift and stored near the erection
site. This operation will result in added cost due to the double handling.
23 of37
Figure 10.15- Span-by-Span Erection on Underslung Trusses with Crane or Derrick/Lifter on Deck
(drawing courtesy ofFlatiron Constructors, Inc.)
Access the pier locations must be provided for the following operations:
Foundations and substructure construction
Pier bracket installation and relocation
Access must be maintained throughout the erection phase.
operations.
The bridge length and the distance that the segment haulers have to back up on the bridge deck
also impact the erection operations.
Self-launching of the pier brackets is difficult with underslung trusses so it is likely that separate
ground or water based equipment will be required to install and remove the brackets.
~
Chapter I 0.0 Procedures for Handling, Transporting and Erecting Segments
24 of37
10.4.2.1.3 Span-by Span Erection with an Overhead Gantry (Figures 10.16 and 10.17)
Depending on the Over Head Gantry (OHG) design, all major segment erection operations could
be performed from the OHG and/or the constructed deck.
Typically OHGs are more complicated and more expensive than underslung trusses.
The segments can be delivered from ground/water level or from behind OHG on the newly erected
structure.
In order to speed up the erection operations the segments could be stored under the OHG on the
bridge alignment.
Span-by-Span erection using and OHG method is typically an efficient solution for light rail
applications where the total span weights are relatively low, but it has also been used successfully
on highway bridges.
Some OHGs are hinged to accommodate tighter radii.
The use of an OHG typically provides a greater clearance envelop under the structure
Must check for overhead clearances: overpasses, power lines, etc.
This method is also a good solution for the erection of short spans and abutment spans if the OHG
is already on site to erect the balance cantilever spans.
During the relocation from pier to pier, OHGs are typically self contained and are self launching.
In special situations, the OHG may need the assistance of a crane to relocate some of its supports.
...
)
Chapter I 0.0 Procedures for Handling, Transporting and Erecting Segments
25 of37
26 of37
10.4.2.1.4 Full Span Erection with Winches I Strand Jacks (Figures 10.18 and 10.19)
Access along the bridge alignment must be maintained for the following operations:
Foundations and substructure construction
Casting or assembly of superstructure
Winch assembly, installation and relocation
Segment or concrete delivery
Construction equipment access
Material delivery
Support operations
The superstructure could be PC segments, assembled on the ground under their final position or
CIP full span, either cast on the ground under their final position or delivered on barges.
This method also requires additional temporary bottom slab PT to carry the span self weight
during the lifting
)
Chapter I 0.0 Procedures for Handling, Transporting and Erecting Segments
27 of37
Access to the pier locations must be provided for the foundations and substructure construction.
This type of erection equipment is typically used on light rail projects where the span weights are
relatively low. However it has also been used on larger structures.
The initial investment in equipment for this method is quite significant. To be economically
feasible, this method must be used on very large and repetitive projects where the cost of the
equipment can be depreciated over many spans.
28 of37
10.4.2.1.6 Full Span Erection on Shoring Falsework (Figures 10.21 and 10.22)
Access along the bridge alignment must be maintained for the following operations:
Foundations and substructure construction
Shoring assembly and relocation
Segment delivery
Erection crane access and swing radius
Material delivery
Support operations
This method can accommodate very tight radii
The use of commercially available scaffolding and cranes minimizes the investment in specialized
adjustment, towers bracing, header beams installation, jacks installation, dismantling the system
after erection and relocation to the next span.
This method is also slow relative to SBS erection with either overhead or underslung trusses if
only one span offalsework is used. To match the speed of a gantry or truss at least two sets of
falsework will be required.
...
This system is feasible where the maintenance of traffic is not an issue. A more complex
falsework system will be required to erect over traffic or railroads.
29 of37
10.4.2.2
Access along the bridge aligoment must be maintained for the following operations:
Foundations and substructure construction
Pier bracket installation and relocation (if needed)
Segment delivery
Erection crane access and swing radius
Material delivery
Support operations
Access must be maintained throughout the erection phase. This could be quite costly if working
over the water mainly due to trestle and /or barges and tugboat costs.
This method is quite dependent on the weather conditions especially when working on the water.
This method is governed by the maintenance of traffic rules and ground access conditions when
working on land.
If working over water, special loading and unloading facilities must be provided.
Personnel, material delivery and post- tensioning operations are less efficient when working over
water
The use of readily available cranes eliminates the investment in specialized equipment making this
method the most economical solution for balanced cantilever erection where easy ground access is
available.
This method imposes the lightest construction loads on the superstructure.
It can accommodate tight radii and steep grades.
The cranes should be sized to erect the pier segments (typically the heaviest) and all other
segments.
Typically the crane works from the end of the cantilever. Special attention should be paid to the
midspan segments where the crane could get boom bound while erecting from the side of the
bridge.
By using ground based cranes, the erection can proceed from pier to pier without having to wait
for the closure pour and continuity post-tensioning activities.
With multiple cranes the erection could proceed simultaneously on several headings.
30 of37
Unlike the specialized erection gantries and trusses, the same cranes can be used to support
various activities throughout the project. Furthermore, after the completion of the project these
cranes can be readily used on other projects.
31 of37
10.4.2.2.2
Depending on the Over Head Gantry (OHG) design, all major segment erection operations could
be performed from the OHG and/or the constructed deck. These would include:
Personnel access to work area
Pier brackets erection
Pier segment erection
Installation of post-tensioning platforms
Overhead service cranes
Material deliveries
Pier access
Closure pour forming, pouring, and stripping support
Integral fmishing bridges
A cost-benefit analysis is needed to determine what options make economic sense.
It is a very cost effective method if:
Local electricians, hydraulic mechanics and suppliers of metric odds and ends should be identified
early on and should be involved in the commissioning of the equipment.
32 of37
Assembly and commissioning of the custom made OHGs typically takes much longer and costs
more than anticipated.
Due to the project layout and the construction sequences, the OHGs may have to be relocated from
one aligmnent to another. This relocation often can be accomplished using one of the following
methods:
Dismantling, trucking, reassembling and re-commissioning
)
Figure 10.27- Balanced Cantilever Erection by Overhead Gantry
(photo courtesy ofPerini/Homsi)
33 of37
10.4.2.2.3
34 of37
(J
This method can lift very heavy segments very high and can be more economical than an
equivalent crane or OHG.
A separate operation is needed to either erect precast pier segments or falsework for a cast-in-
35 of37
10.4.2.2.4 Balanced Cantilever Erection with Special Erectors {Figures 10.31 and 10.32)
)
!
On certain projects, the typical erection methods discussed above are not well suited for the site conditions.
In these situations, special equipment must be developed designed and fabricated. As with any other
erection equipment proper review for conformance with the applicable US codes, by a qualified designer, is
a necessity. Furthermore these special erection methods tend to be prototypes and as such longer
fabrication, commissioning and debugging times should be anticipated.
l)
Chapter I 0.0 Procedures for Handling, Transporting and Erecting Segments
36 of37
Figure 10.32- Special Erector Used on the Dallas High Five Project, TX
(photo courtesy ofDEAL/Rizzani De Becher USA)
Safety Using Special Erection Equipment Requires:
Properly trained labor force
Checklists and procedures
Experienced site supervision and construction staff
..... )
Design-Build projects and Design-Bid-Build projects, that allow redesign or Value engineering to
suit the contractor needs and expertise, lead to optimization, creativity and more competitive
bidding.
37 of37
TABLE OF CONTENTS
. -
11.0
Erection Details
11.1
Permanent Post-Tensioning
10
11
12
13
14
15
16
17
18
19
11.2
Temporary Post-Tensioning
20
11.3
23
11.4
30
11.5
Temporary Supports
31
11.6
Midspan Closure
32
11.7
33
)
Chapter 11.0- Erection Details
I of34
TABLE OF FIGURES
CONSTRUCTION PRACTICES HANDBOOK FOR
CONCRETE SEGMENTAL AND CABLE-5UPPORTED BRIDGES
CHAPTER 11.0 ERECTION DETAILS
Figure 11.1
21
Figure 11.2
21
Figure 11.3
22
Figure 11.4
25
Figure 11.5
26
Figure 11.6
27
Figure 11.7
28
Figure 11.8
28
Figure 11.9
29
Figure 11.10
31
Figure 11.11
32
Figure 11.12
33
Figure 11.13
34
2 of34
Permanent Post-Tensioning
Permanent post-tensioning tendons are installed and stressed as erection of segments proceeds.
Both internal and external tendons are used. Internal tendons are located in ducts inside the
concrete slabs and webs. They are conunonly used in case of balanced cantilever erection.
External tendons are located in polyethylene sheathing which is placed in the interior space of the
box girder. External tendons are attached to the structure at the pier diaphragms and at deviation
blocks.
Comprehensive information on post-tensioning technology is presented in Chapter 3 ~ "PostTensioning Duct and Tendon Installation" of the FHWA "Post-Tensioning Tendon Installation
and Grouting Manual" presented in Section II of this Handbook. As an addendum to Section II of
the Handbook, information on safety during stressing operations, alternative procedures for
calibration of jacks and gauges, and temporary tendon corrosion protection is presented below,
and in Section 11.3.
Safety
PoSt-tensioning stressing operations create very high forces in the tendons and surrounding
concrete. Therefore, precautions must be taken to prevent personal injury or damage to the
structure. Prior to starting stressing operations, inspect anchorages and surrounding concrete.
Clear the work area of debris to allow for unobstructed movement of the stressing crew.
Read and understand all operating and safety instructions for the stressing equipment before
stressing tendons. Make sure that all safety stickers applied to the equipment are intact, legible
and understood by the stressing crew. Comprehensive discussion of safety issues related to
stressing of post-tensioning tendons is presented in Section 11.3.
Calibration
The FHWA Post-Tensioning Tendon Installation and Grouting Manual requires that all
calibrations be performed with specific service gauges and a master gauge as a system. Gauges
are often damaged on the job sites as a result of impact or shock, and often two service gauges do
not last the normal six-month period between recalibrations. Recalibration of jacking systems is
time consuming and expensive, but can be avoided if the service and master gauges are calibrated
at a dead weight indicator to read true pressure. The dead weight indicator must be calibrated and
traceable through the National Bureau of Standards. The contractor should seek approval from the
engineer prior to beginning stressing operations to use dead weight-indicated gauges in order to
replace damaged gauges without having to recalibrate the ram and gauges as a system.
Temporary Tendon Corrosion Protection
Temporary corrosion protection is required for tendons that must be left ungrouted for extended
periods due to cold weather or other circumstances. Vapor Phase Inhibitor Powder (VPI Powder)
was used for this purpose for many years, but use of this product was abandoned due to health
hazard concerns. Currently, corrosion inhibiting oils are being used for temporary corrosion
protection which have detrimental effects on bond. Recently, VpCI Powder has been developed
which is non-toxic and biodegradeable. Use ofVpCI Powder is reconunended in preference to
corrosion inhibiting oils. Product and material safety data on VpCI Powder may be obtained
from: Cortec Corporation, 4119 White Bear Parkway, St. Paul, MN 55110
Toll Free (800) 4-CORTEC, Phone (651) 429-1100, Fax (651) 429-I I22
Email: info@cortecvci.com, Internet http://www.CortecVpCI.com
Details on post-tensioning systems available for use in segmental bridge construction in the United
States are presented in Sections 11.1.1 through I 1.1. 8.
3 of34
'
prtlstreSSciicorii:rell> iri.North .Anl!!i:iCa. 'Ilie Andemon PrlS!'tTensil>riing.Systeni (APS)has evolved win the otijlinal
Amei:iC311 syswmto in.clpdeay~ ofi1Tmato:i"':andmthadodeveloped ato~nd.theP;>eific Rlm.
~Transparent sheathing for.ciHi:niai tendons inside box jtir<lern is one oflhespeeiid mth0ds emplOyed by
Al'S. VisuJil il>Sj>eCtion bOth. dutilig and i~r !lroutili~ can be done bj virtue of the liniL~Y (85%) oftbe
sh.,thirig. which is <:OIDPO.Sed <>fElhylene B~e<J.Ioflomer (llBQ.DopbJe Cll$ing at b0 th the anchor (fig.!) and the
deviator makes/it possi~!e tpr ~e leijdon jo bl><replaee<l. The available EBI transparent sh"'!thlngs.are ShOW!> in
Tablet.
Jriint
/-1\
''
"
\'
1J
} >
\;
,.\I { ''{I!
'1 I
:0" <
lJ
tt
:1
f !
\r
\1
Table. I.
No. ofOB'Strands.
Dianleter
TranspPnmt Sheathing
(mm)
UnitMass(kg/m)
O.D.
I.D.
12
88.3
79.9
l.lJO
19
l!O;S
100.7
1.45
21
1362
126.1
1.90
Fax: +813-3437-9581
<gijutsu~bu@anderson~tech.co.jj:l>
Unit.Length.
9m
(Straight)
<rickanderson@harbornet.com>
:.)
Chapter 11.0- Erection Details
4 of34
... ~
11.1.1
*Super Corrosion PJ'<Itective {Supto) Strand R!rn()n-grout type of temlons isano!het feature of
APS; A modified adh~ive resin ba.sed on. hign dens,ity p<>lyethyl~!' fills !he. inn.er spaces among wires wilh0 ut
eausing ilhra\'elling' imd coatS !he outer wires. The natura of the resin and the injection method are such as to
elimh\ale pinholes. Ordirtliry wedgesican be usedt<l !lril' the bare strand through Supro coating.
e Fig!lre $ illuslrllteS Supro!Srib Unbonded Tendon for slabs.
l'ig!lre <i ill~tra!es'Supro !>(ultiStr&ld"teJ]donf<:>r slay cables, as 115ed in !he ex!r;i-dose bridge io Japan sbQwnin
Figure7.
Fig-5
Fig.~6
Supro Multi-SJrand-Tendon
(Prefabricated)
Fig...-7
Mijiakodagawa-I1ridge
5 of34
11.1.2
AVAR
Foim Travelers
- Installation Labor
- Value Engineering
Smart~~
~'hg'daDOT
C!:rnra:lot:Pt:CCMCnn~
Pwt-te~aildform
T~tljAVAA
forfc'min. 6,500-Psi
dffnensionsIn inChes
NO~ of
Anchorage strands
0.6"Q
SPS 12.6
12
SPS 19.6
19
SPS22.6
22
SPS27.6
27
SPS31.6
31
SPS 37.6
37
eA
11 112
141/2
151/2
17
18
20
17
17
17
20
22
24
eC
o_o_
oF
71/4
3318
4
4118
4318
4718
5112
31/4
13
15
17
18
8114
9
95/8
10-518
11112
41/4
4112
43/4
51/4
5314
20
22
NxP
#4
5tums@4
5tums@4
"#4
#4
5tums@l4
#5
#5
116
5tums4
6tums@3
6turns-@3
Spacing
9
10
11
11
12
13
16
18
20
21
23
25
r
0:
si
_L_
No. of
oc
o_o_
9x9
09
e11
20
26
6
7318
B 1/4
3
33/8
4
3
3112
41/4
0.6"0
MP9.6
MPR 12.6
MPR 19.6
9
12
19
Anchorage Strands
oF
10
#4
111/4
14"112
#5
#5
NxP
Slums
2
2
7tums@2
6tums
11
121/2
15112
6 of34
11.1.2
A\f/iD
;r,::.;;r-..;;:.o;;.
dimensions in Ind:les
A1
N2
.c
E
O.D.
13.314
17114
171/4
19114
20112
13314
161/4
161/4
19114
20112
16
20
19
20
20
73/8
81/4
9
10
33/8
4
41/8
4314
5
3112
4114
4112
5
5114
0.6~~
SP12.6
SPW.S
SP22.6
SP27.6
SP31.6
'12
19
22
27
31
10518
Edge Anchor
Pistarice Spacing
9
1.1
11
12
13
14112
18
18
20
21
No. of
Anchorage Strands
A1
A2
E
O.D.
45/8
33/8
6
91/8
21/8
2112
15/8
2
2
0~6'"0
FS4.6
10112
FM4.6
9518
d1mens10ns 1n mehes
as an option, 1"'x3" flat duct may be used
Q~"'
Lj}I t!IJ3
FS Anchorage
( @@0@@)
'--'
FM Anchorage
All listed systems use 0.6'" diameter strand per ASTM A 416, 270 ksi l_ow relaxation
The above AVAR systems are currenUy or have earlier been installed on the following segmental bridyes:
Rosecrans and Kramer Bridges in Los Angeles. CA, Big I in Albuquerque, NM ~ Spaghetti Bowl in Las Vegas, NV
Oyster Point, So San Francisco, CA- Benicia-Martinez Bridge in Benicia, CA- New Bay Bridge Skyway Structure
in Oakland , CA- Richmond-San Rafael Bridge, CA- Smart Highway Bridge, VA- Los Angeles-River Bridge, CA
Riverside Bridge, Mount Vernon, WA
7 of34
11.1.3
DVWIDAG-SYSTEMS INTERNATIONAL
DYVII!D"l.> l'osHenSicnlog ~ems for S!'!!mental Conslr!lion'and tliP (;Qilsfrcu~l!on'
The 1)'{\yjO~-M:~~lPO&t~T~:~--isshown -for hooded apptleationstiW_ may~~tl1:friri)$li.".a$'~-~ t~~
-~gvwioAG,MU~~fraM:_Ei-frats&nrnfr~em--~-9$~-(),~--tl~~~-~a'!li:lS.
,1)~-
"""'*""'~ 1)1><'
~~~,,.;.'[
Pfate~_e--$0'
~J!~:~~i?F~
Loop Anchor..ga Hv
fiif;Aii~~~F/;.;- __
)\h:::
os,
00
5}7
Oil
00
:12.
1S' ''!:!
27
::n
:-:_:e::
C!xrP!er
~li
DSt Syste.rt.-100
1!4,
..il ::.
E-mail: dsiamerica@dsiamerlca.com
wWw.dsianierica.eom
8 of34
11.1.3
DYWIDAG-SYSTEMS INTERNATIONAL
"fOOT~P~
Top_Viaw
Ooct1)
Pla.Slidlut<{ 1}
SldeViaw
)
Chapter 11.0- Erection Details
9 of34
11.1.4
FREYSSINET
44880 Falcon Place, Suite 105
Sterling, VA 20166
(703) 378-2500 FAX: (703) 378-2700 freyssinet@freyssinetusa.com
nCIS anchorage
Versatility
The -system is designed for a wide range
of applications with the same anchorage
t)pe:
Accomodares aU internationally
avaiJable sizes and grades of
15mm strand (15.2 and 15.7
Compactness
Size
3Cl5
4CI5
7C15
_9Cl5
12CI5
!3C!S
I9CI5
22C15
25CI5
25CI5P
27Cl5
31CI5
37Cl5
55CI5
A
150
150
180
225
240
250
300
330
360
350
350
385
420
510
B
110
120
150
185
200
210
250
275
300
290
290
320
350
420
c
120
125
186
260
D
85
95
346
110
150
150
160
185
220
230
220
120
230
466
255
516
300
165
246
256
430
400
360
360
H
50
50
55
55
65
70
80
90
95
95
100
105
110
145
~I
~2
40
"50
45
60
65
80
80
95
105
110
110
115
65
70
85
85
100
110
115
120
115
120
125
130
160
135
165
These very compact ar~chorages provjde efficient transfer of the prestressing forces into the concrete, fucilitating
more economical designs by:
reducing web thicknesses in beams and box girders, reduced blister-and rib dimensioru;
allowing for a greater concentratiOn Ofanchorages and pre-stress force at the anchorage zones;
reducing post~tensi~ming anchor blocks dimensions thereby minimizing strand deviations.
10 of34
11.1.4
9Cl_5
HCJ5
13CI.i
19Cl5
21Cl5
J!CI5
II of34
11.1.5
JACKS
Two finesofhigh perfonnanet! lll!d durability DEL jacks exist for lhe stressing of strand cables, with or
withom automatic gripping an!! release, ofadequate weight and size for their function and lhe size and length
ofcables;
T J~tcks
Equipadwilh automatic. frontgrippinglrelcasingand wedge sealing devices, they perfonn a
streSSing/wedge operatiiJD.in less than l 0 minutes and ~strand tails of0.3..meters only for
nonnal tendonsizes. They are the recommended option for short tendonsand precise streSSing
openitions_, induding_wedg.e s_eating lo~ c~:mtrol. SeaU{)ss is Jimite4 at-3 m~ ..
The ligbteS!, easiest to handle and maintain multistrandjacks. They feature rear band operated
gripping and semi-automatic releasing. Seat loss. is limited at 10 mm.
.
PUMPING UNITS
DEL Multistrand Pumping Units include all the hydraulic control devices for!he opern(ion. Theybave been
ergonomically designed for heavy duty and low maintenance. Electrical or gas power, optionally.
T Pumps Three circuit, fur Stressing, Relnlction and Wedge Seating, they feature.2 ganges for superior
control. Used with T jacks.
E Pumps Two circuit, for Stressing and Retraction. They work at mid-high oil pressure for.lowest
maintenance, in accordance with their corresponding E jacks.
GROUTING MACHINES
The tnixture of cement. water and admixtures must be done under a strid--Ihixing time and
velocity control and must not coutain lumps nor any air bubbles during injection into the
ducts.
DEL grouting machines include the mixing and injecting opern(ion in a single piece of
equipmen~
Av. Nativitas 429 * 16090 Xocbimilco. D.F. *Mexico* Phone +(52)(55) 5615 7561 *Fax 5676 66'20
Email mexpresamtxpresa.eom * www.mexpresa.com
12 of34
11.1.5
ANCHORAGES
AS Active, Standard
A~tive or Stressing anchorages are-those located anhe-str:essiilg -ends Oftendons, DEL AS
anchorages-are suppliedinChtding-wedges, lVedge & bearing plates,trailsition and:g'rout
port. Grout caps, whether-and as-required..
Design may_ ~pe_cifY active anchor3_ges.on both ends of aPT tendon evewthollgh stressing
is-carried o~t_at one_ only,..For wedge seating 19S!' recup,era~ioih__sliiJ,nS: can:_he:-plaeetl
be_twee_n wedge plate and-be_aringpJate, thrm,gll-a lift-iJJf.
AR Active, Adjustable
for:- t~nsion-adjUstment aftedock-..off.
They~ supplied
completeaSfOi-:AS type;
including adjusting_nut
COUPLERS
Ffixed
Used for prestressed concrete elements' post-tensiOned_ c_onnec_tion. Also called_
Continuity Anchorages, they are supplied complete with_ standard bearing plate &
coupler body, swage heads, strand concentrator,- shell and grout ports.
trumpe~
,.,_
M Mobile
For muJtistrand cable extension. Used mostly in repair jobs _for big sjze cables. They are
supplied complete with strand _concentrators & deviators, single couplers, sheU and grout
ports.
)
Chapter I I .0- Erection Details
13 of34
The SDl MultiSlraod SJ'Ste:m is the firSt all-hew port~k:nsion 5Dl PoSt-Tens:iOn'iilg hardwai:e has--b'een-prolren thrOugh th-e.
ing system to be inlro-duced irf over a detade. The syStEm rigofOUs i<!sting and appHl'lal procedures of the C;nfOmta
''ias desigr.affrom the ground-up- to--a:ddr<?S tOda)''s design Department ofTransportaOOr.- and-other regula~ory -agend~"S
and construction practices,. including !he-tlse-oJ lightweight, hath domestic. ar.d intr:mationat
high-str~r.gth
-,anchorages in structural dements vlith mngtosted relnfo!'cing Systems, Inc. of Campbe!l, California, a total of 21 _n~w SOl
for use
porates mrnerous teclmi!:al .advances that -simplifY field place. on the new San FranciscoOakland Bay Bridge Skyway
Structures, the
n~'f
SOl furnishes comprehensive hardware solutions fur and the Sakhalin Offshore Oil Platform currently under conpostte'nshming- projects warldW'ide, indudmg a broad range strudioh ncar Vladivostok. Russfu. SDI .vas awarded theof ;;nchor heads ;:fld bearing p!a_tes for 1 to 37 o.G:.inch diamt~ndons,
eter slrand
the new post-tensioning system pcoMes a prac"Jc;l ;md ful~: l_;;ur;ching Erection De><ic:es (SLEDs) that .1re lirtlng th~
integrated solution for :the ct.:nstructicn of i;;;gmer.t=! bridges 8oo ton precast deck segments from barges into position
and other engineering strl.iduro_
o:; the
superstrm:wr~-
',J
Chapter 11.0- Erection Details
14 of34
i!!IJ SCHWAGER
IIIIIIDAVIS INC
.. j
WWWSCHWACHt:oAYIS.CQM
TLEFHONf: 4<08-2lh-9JOO
15 of34
16 of34
Anchorage VSL.Type.SA
VSLAB+ System
__.__
ANCHORAGE!
TENDON SIZES
0.5"
DUCT SYSTEMS
0.6"
PT-PLUsn~
GALVANIZED
METAL
EXTERNAL
VSLAB+
SA
4. 5
1to55
1 to 55
ES
..
ECI
7, 12, 19!22, 31
)
Chapter 11.0- Erection Details
17 of34
Tll~WilliaJ;n$ Syst~m
. .Williams Pre,stre.ssing 1 Post.Tensiorling systems :consist ofhi!l~ ten siTe steel bars aVailable in liVe
dilJmeters from 1" (46 min) to 2-112" (65 11Jill) with guaranteed tensile strenglhs.lo 718 kips {3460 kN).
They are P(OVided withi:old.rolledlhreadsoverallora portion ofthe bar's length. All tension components
for the~ystems a.re designed fo develop .100$ of the bar strength. All components of the. systems are
d~signed and m~nufactl[red in the United States. Williams All-Thread-Bar systems have been field proven
around theworfd.
Applications
. .
. . . . .. , .
Williams All-Thread-Bars were developed for use as Pre'S!reilsi!lg 6ars, Over !he yeats many other
applications have heen adoptedsuch as:
.. . .
!'lie Test
Anchors
~oek An~hofl!
-,.- ~O~Ctete: Ties
,Hanger Bolts
Jacks
Shear Pins
18 of34
'
http://www.williamsform.com
exceed
'Eifediva c:cis:s secliooal areas shown are as. required lrj ASTht A 7.22-98. Achlal iueas rray_
theSe' valutis~
~ ACf355.1R m:vcnJ.U1 imitates ail U!limall:i.streog!b.ln Shear has a rofll}e:d:.a b) .7-ofifie l&ti~Da!.l t;;i;sie ~---De:si1iB
safelyfactillsfclsafesbear~based-Oillhe~ofuie.
-_
--,_'-- - '
""'ro p<~ -
:~~:::.:T~==d~==~~ihi!~Steei
)
The ~ltd !hoti!d not'e~ 70% oilhe specified rniniroom let~sie- &tl'ef'lgfh(lf~~sleel
The rnaxim.tm ieslbad should no_t exooeo 00% oflhe spedOOd iTWiimJm mi'ls&f stmlgthorlhe prestrnSngsteet
Properties
Threads
or .
__ /
19 of34
When using couplers with post-tensioning bars, it is critical that the couplers are properly engaged
on each bar before stressing. Bars being coupled should be marked one half the coupler length
from the end of each bar and the bars engaged to the mark prior to stressing. Insufficient
engagement of the coupler could result in failure of the connection during or after stressing and
possible damage or injury.
In cantilever construction, the temporary bars are only normally needed for the last two or three
segments of the cantilever since permanent tendons are installed for most segments. Occasionally,
when using continuously coupled bars, it may not be possible to retrieve them after the closure has
been made at the midspan. In this case, it is advantageous to plan the temporary post-tensioning
so that most of the bars can be recovered prior to adding the last cantilever segment. Temporary
bars and particularly their anchors and couplers are expensive, so maximum reuse is desirable.
20 of34
,_)..
.. _
. r. bars (external}
re-formed recesses
Tension
71op
Tempocarv
c_onstruction
stresses for
cantile-ver
Bottom
r--; P. "r.
_ .
Camp.
M/S +
bars........-,
Compression
r
J 8
P/A
compression on
epoxy joint
)
Elastic shortening of
concrete from !!11 P. T.
--Jt-'-
Direction of erection
______::ii~~~,....JL::.__\1-_i_l!___\:-~
e
,?::=3
When using continuously
coupled P. T. bars make
sure there is adequate
clearance (c) for
movement of couplers
caused by combined
elastic effects
---=:r=:
An alternative to a
21 of34
--lrFinal join l
-'
cantilever
(SII)>O
(SI)
(L)bar
_n:----
JniUal
JOint
r - position
-L
1--
--~c
':I
Oireor.fum o/ ercrtJon
.~
Chapter 11.0- Erection Details
22 of34
2.
When cutting the steel bands that bind the tendon coils, remember that the coils are under
pressure and will want to open up and uncoil like a spring when the bands are released.
Strand coils (packs) must always be contained in a proper dispensing unit prior to cutting the
bands. Use extreme care when pulling the loose strand end out of the pack center as the
spring force induced from coiling tends to push the strand out of the pack.
The cut ends of the strands/bars can be extremely sharp and care should be exercised when
handling tendons. Deburr ends of the strand/bar.
3.
Do not weld or burn near post-tensioning materials to prevent sparks or hot slag from
4.
5.
touching any portion of the strand or bar which will be under stress.
6.
ultimate tensile strength (GUTS). Usage is typically limited to 20 times. Check internal
threads of nuts and couplers before stressing.
23 of34
5.
Prior to use, visually inspect the jack for signs of oil leakage or damage.
Prior to use, check and read all safety instructions and stickers. Any stickers that are not intact
must be replaced prior to anyone using the jacks.
Free cycle the jack for operation, check and bleed air. All air must be purged from the jack or
seals may be damaged.
Some twisting of the pulling head can occur during shipping or handling. Be sure that internal
jack parts are aligned. The jack cannot be installed unless all tubes are in line. If a center hole ram
is used the check no 4 will not be needed.
Jacks arrive with reusable pulling wedges in good condition. Consult equipment supplier
regarding scheduled change, replacement or maintenance.
2.
Observe all relevant OSHA standards e.g. use of protective clothing and devices, grounding
of electrical equipment, control of work area, etc.
All system components must be in good working condition prior to use. Inspect daily for
signs of wear or damage. Do not use if grippers are worn excessively, hoses are cracked,
pressure gauge is in operable, or other defects are observed.
3.
After inspection, test run system (see operating instructions) to insure all components are in
I.
4.
5.
6.
7.
..:J
24 of34
Install pattern plate on tendon and slide to anchor head, secure outer strands and then slide back.
This assures strands are in correct holes. Misalignment of strands will cause damage to jack and
tendon during stressing.
2.
Check alignment of anchor head hole-pattern (Figure 11.4) with that of jack. Confirm second
stressing end is also aligned.
WEDGE
JACK FRONT
Install dead-end keeper plate if required. This may eliminate the need for a man watching the
dead-end during stressing, and keeps the anchor plate wedges and strand tight.
4.
Be sure the jack piston is in the full return position. In this position, the automatic stressing head
tube will be protruding and the wedges will be open. Lift jack and align axis of jack with that of
the tendons, slide jack over the strands to anchor head. Jack support must contact the wedge plate
surface before stressing begins.
)
Chapter ll.O -Erection Details
25 of34
0000000
CORRECT
INCORRECT
2.
Appropriate warning signs should be clearly displayed. Warning signal (i.e. horn) shall be used to
alert personnel in area that stressing operations are active.
People not involved with this work should keep clear and follow any safety instructions from
competent operators. Safety Rails I Barricades shall be present to prevent other personnel from
entering an area where stressing operations are going on.
11.3.9 Communications
It is extremely important to establish proper communication among the stressing crew, especially, when
simultaneous stressing operation takes place. Proper communication devices (i.e. radios) shall be present
for communication among stressing crew.
26 of34
8.
9.
)
Chapter 11.0 - Erection Details
27 of34
Figure II. 7- Stressing Personnel Located Away from the Stressing Ram
11.3.15_Fall Hazard
The number-one leading cause of construction-related injuries and fatalities is attributed to falls from
height. In work areas with unprotected sides where employee could fall six feet or more, wear safety
harness and connect to lanyards with deceleration device. Personnel should be tied off 100% of the time
that they are subject to fall hazard.
28 of34
the coupler length (Figure 11.9). The end of the bars should be engaged in the coupler up to mark. Bar
supplier should instruct about the minimum engagement. If enough thread is not engaged in the coupler, the
bar will fail when stressed.
Bar Coupler
Min Engagement
0.5L- 0.5"
Min Engagement
0.5L- 0.5" - - - -
-~)
Chapter 11.0- Erection Details
29 of34
When erecting a cantilever, it is necessary to lift the segments in such a way that they hang
precisely in the position ofthe previously erected segment in order to align the shear keys and
temporary post-tensioning bars during the epoxy jointing process. If the position of the two
segments does not match, the segment will bear temporarily only on a few keys, which might lead
to cracks when jointing. It is quite easy to align the segments if two lifting points (i.e., beam and
winch) are used, one over each web. With a single central lift, it is necessary to lift slightly off
center so that the segment hangs at the required crossfall. This can be done by using a lifting
frame with laterally slotted holes for the attachment of the slings (Figure 7 .l (a)). In any case, the
lifting device used for erection must have the means to adjust the position of the segments.
Lifting segments at a present crossfall is not necessary when they are to be placed on an erection
truss as with span-by-span construction.
30 of34
,-
P. T. bars
stressed
lo 50%
L--~.rPier
segment
Profiled packs
secured by
snug ligllt
ltorizonla/
P.r. bars
Sleeve
/.____(_aJ_ _I---~
Pot bearing
Alternati.ve anchorages:
P T. =.Post-tensioning
.. )
Figure 11.10 -Erection Systems: Setting ofa Pier Segment and Start of Cantilever
31 of34
/ I
I
Jacks
wit IJ
locking
deviceS-/
..-7r:
I
~ Out
of lmli1ncc
by ienrpontr.v
Useful fot
l 'ilrtied
l owcrs
rut -ved or
Unbalance
G~1-11l1J'
Unbalance
Usually the midspan closure is a nominal two- to five-foot gap. Sometimes, however, it can be
larger, and might be as long as a segment. In such cases, the added weight of concrete can cause a
deflection and rotation at the closure. For the precast segments, this effect is compensated for in
the casting curve. The cast-in-place joint itself requires careful placement of the concrete working
from one end of the segment to the other to avoid any tendency to "crack" or open up at the
bottom of the joints between the segments and the cast-in-place concrete. If the anticipated
deflection or rotation is likely to be very large, such as with a very large closure, then
consideration should be given to casting the bottom slab first and applying a nominal posttensioning force (say, 100 kips) through it prior to completing the rest of the pour. This will help
to avoid cracks in the joints.
The weight of the frrst cast-in-place joint connecting two cantilevers causes an unbalance which is
usually controlled by the stability tower (Figure 11.12). This tower will deflect under the effects
of the additional load. This deflection will lower the elevation at the cantilever end where the
cast-in-place splice is poured. The arnonnt of this deflection should be carefully predetermined
and compensated for. Cantilever tips also move because of the effect of sun radiation on the deck.
The effect of temperature effects on the casting of midspan splices is described in Section 13.9.2.
32 of34
\_)
_,/ /
H
Steel beam "Strong Backs
~~
'
//
P. T =Post-tensioning
..
)
Chapter I I .0- Erection Details
33 of34
The bridge deflections are generally calculated by the contractor's specialty engineer and reviewed
by the DOT or a consultant. The reason is clear. Only the contractor, after making out his
schedule, can know for snre when and how the structure will be constructed. Exceptions to this
rule occur, for example, when the designer decides to prescribe the sequence, and has determined
from his calculations that the effect of the schedule is minor (in case of short spans).
During the design process (pre-bid), the designer must analyze this structure for compliance with
specifications based on the construction sequence clearly shown on the contract drawings. During
construction, the contractor or the contractor's specialty engineer will calculate deflections based
on the anticipated construction schedule.
.4
II
A
11
'h!
'2'
[:;;:::==;===11(1===;;:::==;]1
A
A
A
A
'i
k ; .:::J 11 C::
I~ :
A:
:A
A
A
II
II
A
A
t :: 4 == = =-= Ls: -= j
e gc-.:::::::;A;::::===:=;n;::::=---:Jg
ri~;:==:;=======;====;JI
LA
A
21
11
i'
:;:3 II C::: :~
'k'
II
B. Erec:l cantilevers
C. Close tailspan splice and
post- tensioning
/). Deflection caused by ''C'" above
E. ComperJsation of de!JectioJJs by
c'" above
F. Completed structure
c.
"c"" a/Jove
F'
Completed structure
[a)
(b)
34 of34
TABLE OF CONTENTS
Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
Purposes of Epoxy
Types and Application of Epoxy
Duct Coupler Devices
FREYSSINET Post-Tensioning Systems
VSL Segmental Duct Coupler
General Technologies, Inc. Precast Segmental Duct and Duct Coupler
Prepackaged Grout
BASF Construction Chemicals- Building Systems
Epoxy and Prepackaged Grout for Segmental Bridge Construction
12.4.1 BASF Construction Chemicals- Building Systems Epoxy
and Prepackaged Grout for Segmental Bridge Construction
12.4.2 SIKA Corporation Epoxy Resin for Segmental Bridge Construction
12.4.3 SIKA Corporation Prepackaged Grouts for Segmental Bridge Construction
12.0
12.1
12.2
12.3
12.3.1
12.3.2
12.3.3
12.4
12.4.1
3
3
3
6
7
8
9
10
13
14
15
16
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
I of 16
TABLE OF FIGURES
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
12.1
12.2
12.3
12.4
12.5
12.6
12.7
12.8
12.9
12.1 Oa
12.1 Ob
3
4
5
6
11
11
12
15
16
16
16
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
2 of16
Purposes of Epoxy
The purposes of using an epoxy resin in the joint between the segments are:
12.2
To maintain the strnctnral integrity of the joint and maintain a monolithic concrete
segment
To completely fill any minor surface imperfections and irregularities between the match
cast surfaces
To provide a water and grout tight seal, preventing chloride intrusion
To act as a lubricant when erecting the segments
To ensure a tight fit between the segments so that the compressive and shear stresses are
transmitted directly across the joint
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
3 ofl6
Segmental bridge epoxies are specially formulated as either normal or slow setting resins. For
segment-by-segment erection, the normal set epoxies are typically used and for span-by-span
erection, the slow set epoxies are typically used. In addition, they are formulated for use in
different temperature ranges, from 20'F to 115'F. It is important to use the correct pot life and
correct temperature range to ensure adequate working time and proper strength gain of the epoxy.
Prior to application, the joint surfaces must be clean and sound. They may be dry or damp, but
free of standing water or frost. It is important to remove dust, laitance, grease, oils, curing
compounds, impregnations, waxes, foreign particles, disintegrated materials and any other
contaminants before applying epoxy.
Mixing of the epoxy is typically done in the pails. The pre-proportioned units allow for all of Part
A (base resin) to be mixed with all of Part B (hardener). The units should never be hatched down
on site. The epoxy should be mixed for a minimum of3 minutes with a low-speed (400-600 rpm)
rotary drill fitted with an appropriate mixing paddle. The sides of the pail should be scraped down
during mixing to ensure there are no streaks of unmixed epoxy in the container. When fully
mixed a uniform gray color should be achieved.
Application requirements are stated in the specifications. Application is typically done by hand,
using protective, disposable rubber gloves. Since the application time may be short, sufficient
labor should be available to coat the joint in the time allowed. The epoxy should be applied to
both faces of the segments to a thickness of approximately 1116 in. on each face. This is sufficient
to lubricate the segments and ensure against joint leakage in the completed structure.
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
4 of 16
When the segments are brought together and stressed, excess epoxy is squeezed out. For joints
over traffic, procedures must be implemented to avoid dropping epoxy on automobiles. The epoxy
should be left approximately I in. clear around any ducts and approximately Y, in. shy of the
outside edges. Once the segments have been joined and stressed, all excess epoxy should be
cleaned. Leaving it to harden may make it more difficult to remove later on. It is essential to
swab all the ducts before the epoxy cures so that any epoxy squeezed into them does not create an
obstruction for the tendons. The use of duct coupler devices simplifies the placement of the epoxy
and ensures that the epoxy will not be squeezed into the duct when the segments are stressed.
When bridge piers are constructed with pre-cast concrete boxes, epoxy should also be used
between the segments for the same reasons described above. The only difference in application is
the epoxy is applied in a horizontal and overhead orientation, rather than in a vertical orientation
as on the spans (see Figure 12.4).
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
5 of 16
Figure 12.4- Epoxy resin being applied to precast bridge pier segments
Details on commercially available epoxies are presented in Sections 12.4.1 and 12.4.2.
12.3
eliminate the problems related to squeezing epoxy into the joint. These devices also eliminate the
need to swab out ducts after the segments have been pre-stressed together. Details on three
commercially available duct coupler devices are presented in Sections 12.3.1, 12.3.2 and 12.3.3.
Plastic duct is also shown in Sectionl2.3.2.
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
6 ofl6
Advantages of LIASEAL:
l..eak-tight connections prevent ingress of segment epoxy during segmental erection and the ingress ofe>.1emnl aggressive
agents (wat;:r, chlorides, etc.) over the service life of the structure.
Leak tight connections prevent cement grout leakage and crossovers during grout injection.
LIASEAL components are non-metallic, cannot corrode and offer permanent protection to internal tendon prestressing slecl
at segmental bridge joints.
LIASEAL can be used with HDPEIHDPE ducts to provide a complete leak"'tight plastic encapsulation of the tendons.
Mechanical engagement
Scre\\ing
Chapter 12.0- Epoxy Jointing. Duct and Duct Coupler Devices, and Prepackaged Grout
7 of 16
Design Features:
Complete encapsulation of
post-tensioning tendons
through segment joints
Casting Features:
Bulkhead
Inflatable Mandrel
Coupler Sleeve
Seals
Erection Features:
No components projecting
from segments during segment
erection
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
...
8 of 16
).
Zero Vofd'/f'
-
Monostrond
Encapsv/alian
w/ Me/a/ Ring
Zerov~
Ccp
Zero vOk::fl?Ccp
Chapter 12.0- Epoxy Jointing, Ductand Duct Coupler Devices, and Prepackaged Grout
9 ofl6
12.4
Prepackaged Grout
Prepackaged grouts were developed to reduce or eliminate bleed water voids in the ducts, and to
achieve complete filling of the duct with a cementitious grout. Prepackaged grouts are
recommended for use on all segmental bridge projects. Even when prepackaged grouts are used,
it is necessary to inspect all anchorage areas for bleed water voids within 24 to 48 hours after
grouting, until the inspection agency is assured that there are no bleed water voids. Subsequent
spot inspections of one or more anchorage per span may be conducted provided no voids are
found. Any voids discovered must be filled immediately with cementitious grout, preferably by
vacuum grouting.
The cement grout injected into a post-tensioning duct is often the last line of defense against
corrosion of the steel tendon. Inspection of the tendons is often difficult, and therefore severe
corrosion may go undetected for a long period oftime before failure occurs. The steel tendons
are susceptible to corrosion damage because of the high steel stress and the small wire diameter,
and if allowed to corrode, there is a danger of structural distress. This underscores the need for
the use of quality prepackaged cement grout during the construction of the post-tensioned
structures.
Prior to the use of prepackaged grouts, site blended grouts were typically used in post-tensioned
applications. The biggest problem with the site blended grouts was the bleed water that would
form in the ducts. This bleed water migrates towards the upper end of the duct where it
accumulates, and is subsequently absorbed into the matrix. This in turn leaves large voids within
the duct containing the cable, and this makes the cable more vulnerable to deleterious chemical
attack and/or corrosion. In addition, bleed water itself, and deleterious chemicals that are
sometimes admixed, migrate with the bleed water and accelerate strand corrosion. For these
reasons, site blended grouts are not recommended for use on segmental bridges.
Post-tensioning techniques
There are two types of post-tensioning methods: unbonded and bonded (grouted). An unbonded
tendon is one in which the prestressing steel is not actually bonded to the duc1fconcrete that
surrounds it except at the anchorage points. In this form of post-tensioning, the tendon (seven-
wire stand) is simply coated with a corrosion inhibiting grease and encased in a plastic protective
sheath. In bonded systems, two or more seven-wire strands are installed in steel or plastic ducts
in the concrete. The strands are stressed and anchored at a connnon site. After the tendons are
stressed surrounding duct is filled with a prepackaged cement grout that provides corrosion
protection to the strands. As seen in Figure 12.5, bonded post-tensioning offers multiple layers
of corrosion protection to the steel tendon. Protective measures include surface treatment of the
concrete, the concrete itself, the duct, the grout, and possibly, strand or bar coating such as
epoxy or galvanizing.
In order for the grout to provide protection to the steel, it should form a good bond between the
duct and the steel. A grout having good bond characteristics, transmits forces from the concrete
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
10 of 16
.)
may crack easily thereby creating easy access for the ingress of moisture and deleterious
chemicals such as deicing salts. The grout functions to provide corrosion protection by
passivating the steel strands due to its high alkalinity, which in turn is provided by the hydration
of potassium, sodium and calcium ions in the Portland cement. Complete filling of the ducts
with a non-bleed grout ensures that there is no damage due to freezing and expansion of trapped
water/moisture, which in turn prevents damage to the external concrete. This can only be
consistently achieved with the use of prepackaged grouts having been formulated to have zero
bleed.
High permeability resistant characteristics of the prepackaged grout ensure that no deleterious
chemicals (deicing Cr) have easy access to the encased steel. Chloride ions destroy the
passivating iron-oxide layer on the steel surface, which in turn exacerbates steel corrosion. In
addition, carbon dioxide from the atroosphere, if allowed to penetrate through the cement grout,
could reduce the pH and thereby could lead to loss of passivity, and ultimately, corrosion.
Therefore, it is important that the prepackaged grout have a low permeability .
II ofl6
Non-shrink
Low exotherm
Impermeable to moisture, chlorides and chemicals
Resistant to impact, vibration and stress
)
Figure 12. 7- Prepackaged epoxy grout poured into anchorage zone
Details on commercially available, prepackaged grouts are presented in Sections 12.4.1 and 12.4.2
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
12 of 16
DBASF
The Chemical Company
cable grout.
Masterflow 928.
"Set 45 Hot
Protection
for
8. Chloride
Concrete
"Enviroseal
40"
Silane waterbased penetrating
sealer.
9. Bonding Bridge Overlays &
cold joints, Concresive Liquid LPL epoxy.
lO.Key Way grouting "Set 45" magnesium phosphate based concrete.
Non-shrink, chloride resistant and rapid setting even in freezing temperatures
BASF Construction Chemicals - Building Systems
889 Valley Park Drive Shakopee, MN 55379
Customer Service 800-433-9517 Technical Service 800-243-6739
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
13 of 16
DBASF
Bridge Repair
1. Crack
Repair
of
Structural Elements
Concresive Standard SLV
epoxy used for injection grouting of fine cracks.
Structurally bonds concrete.
,~)
14 of 16
Normal Set
Slow Set
Figure 12.8- Applying Sikadur 31, SBA on Central Artery Bridge in Boston, MA
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
15 of 16
Chapter 12.0- Epoxy Jointing, Duct and Duct Coupler Devices, and Prepackaged Grout
16 of 16
TABLE OF CONTENTS
13.0
13.1
13.2
13.3
13.4
13.5
13.6
13.7
13.8
13.9
13.9.1
13.9.2
...
Geometry Control
General
Casting Cell Geometry Control System
Tools Used for Geometry Control
Geometry Control of the First Pier Segment
Field Survey Checking During Erection
Systematic Error
Achieved Profiles
Pier Shaft Segments
Temperature Effects
Temperature Expansion and Contraction
Temperature Gradient
3
3
7
12
13
13
14
15
15
15
15
18
)
Chapter 13- Geometry Control
I of 19
TABLE OF FIGURES
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
Figure
13.1
13.2
13.3
13.4
13.5
13.6
13.7
13.8
13.9
13.10
13.11
13.12
13.13
13.14
13.15
13.16
13.17
13.18
13.19
13.20
4
4
6
7
8
8
9
10
11
12
14
14
15
16
16
17
17
18
19
19
2 of 19
General
The geometry control of precast segmental bridges is achieved io the casting yard. The "shortline" casting system is based on making very fine adjustments to each match cast segment in the
casting cell, and therefore requires precision; more so than the 11 }ong-line" system where the
geometry control is maioly achieved when building the soffit. The following discussion
concentrates on the "short-line" system since it is more commonly used, although the principles
apply to both systems.
Precision geometry control has nothing to do with the sizes, thickness variations or tolerances of
the component pieces of the segments, important though as these are to the overall quality of the
finished product. The precision is required for measuring the relative as-cast position of the new
segment in relation to its match cast neighbor. These measurements are critical.
The setup required for this io the casting yard is shown in Figure 13.1. The aligmnent is
controlled by an instrument on a permanent base and a permanent target. Neither instrument nor
target should be disturbed throughout the production, otherwise control must be reestablished. For
this, adequate bench marks should be maiotained. The casting cell is always plumb, level and
usually square so the geometry control is established, mainly by positioning the old segment as
prescribed by the castiog curve and as shown in Figures 13.2(a) and (b).
As the first segment is cast and the top slab has been fmished, four elevation bolts, A, B, C, and D,
as well as two centerline markers, E and F, are installed. The following morning, the elevations of
the tops of the bolts are recorded and the centerline is scribed onto the centerline markers. Now
the segment can be rolled forward for match casting.
After the first segment is moved to the match casting position, it is reset to the instructions
provided by the casting curve. The centerline will be as it was before, unless the bridge is curved.
In case of a curved bridge, an offset "0" is used as shown in Figure 13.2(a). The vertical curvature
is handled similarly. But even if the bridge is flat, it is necessary to adjust for the deflections
which occur during construction. As mentioned, the amount of adjustment to be made is
determined by the casting curve which can be part of the shop drawings. Note that if the segment
would be positioned in such a way that both centerline markers are in line with instrument and
target and the bolt elevations are the same as those measured before the segment was moved, the
segment would lioe up exactly with the next segment-to be poured.
Geometry control for precast segmental bridges requires an excellent surveyor. He should be on
the job daily and keep accurate records. In spite of his competence, his work should be
meticulously checked by the inspector since errors are expensive and time consuming to correct.
After the old segment is properly reset and the setup for the new segment is complete, the new
segment can be cast. The following morning, the surveyor marks the center line and records the
bolt elevations of the new segment. In addition, before the old segment is moved, the elevations
of its bolts and its centerline position are checked to determine if the old segment has moved
during casting the new segment. It is often noted that position changes of the "old segment" occur
due to settlement of the soffit rails by the segment weight, due to vibrating of fresh concrete
against it, or due to forces applied to it while closing the forms.
3 ofl9
"'f>'
level boll
Old ,...gment
N.e w SErgment
---
lllS'lrument
llorbtoni.,J
refe#Wl!Cf!
Levt!!l boll
Ne-w .segment.
~;:S:~~;:~p=lo~ne
__________~-,
OM segment
ELEVATION
/n
Cenler line
A
IE
Form always
plumb, level
~c
ll.J
square
Segment rotalion
Amount of
offset
determines
horizontal
curvature
Level bolls ~
1 ~Target
anrl usually
(a)
Old segment
lJ.
Ne. w ..
'(b)
'
B
D
"old"
Amount of till
rcurva l ure
l-r
El.EVAT[(JN
-r-
det-ermines vertical
4ofl9
When constructing a bridge using girders or whole spans cast in place, it is normal practice to set
forms to within 1/100 feet (1/8 inch) of the desired position duly corrected for anticipated
deflections. Each new segment should be cast to stay within this tolerance based on as-cast
surveys of the previous segments. As accuracy depends upon consistency, it is important that the
same individuals make the critical"as cast" observations at the same time each day prior to
stripping the forms ofboth the new and the old match cast segments. Usually, this is the first
thing each morning before the daily crews arrive and when weather conditions are most stable
from day to day.
Note that all the critical readings are those after casting. While it is important to have an accurate
set up before casting, this is unlikely to remain so during the casting operation. Some movement,
however slight, will occur, so the true achieved geometry is recorded after casting. It is possible to
compensate for casting errors by adjusting the position of the next set up and so on. In fact, the
major challenge in geometry control lies in keeping track of casting errors and correcting for them.
Erection of the first segment, usually a pier segment, is critical and should be done as accurately as
possible. This segment should be placed to an accuracy of Ill 000 feet.
It is very important that all the information from the casting operations and the calculated "as cast"
actual relative positions of the segments be carried through the field erection process as well.
This poses some practical difficulties because it is by no means as easy to obtain the same
accuracy in the field as in the casting yard. However, the field setting is only required at each pier
segment or start of a successive run, and it is worthwhile doing this correctly. Placing a large
chunk of concrete with a crane to an accuracy of a few thousandths of a foot is difficult. In
practice, it is possible to use shims, packs and wedges to maneuver the segments to an acceptable
accuracy. Also, by installing supplementary transverse alignment markers while in the casting
cell, the horizontal adjustment ofthe pier segment can be set in the field using the base line of the
full segment width, thereby not relying solely upon the shorter, front to back; longitudinal
centerline marks (Figure 13.3).
During erection, elevations and horizontal alignment should be checked to see if they are in
agreement with the calculated as cast positions. If not, then adjustments may be necessary. Such
compensations include: re-orienting or rotating the cantilever after erection, calculating a
compensatory setting for the next cantilever, or shimming the joints. The latter should only be
used as a last resort as it can unpredictably lead to "correction of corrections," and so on.
Moreover, it is not effective for short cantilevers or deep girders.
5 of 19
een-lertine
Precision within the geometry control system is essential in order to avoid errors in the geometry
of the structure. A source of error in aligmnent may arise from the deformation characteristics of
the concrete being different from those assumed. Deformations of concrete are difficult to predict
with any degree of accuracy, and most attempts are, at best, sophisticated judgments. In
segmental construction the actual deflection can differ from the theoretical just as in precast girder
production, where identical girders can differ in camber by a few inches. However, with precast
segmental construction most of the shrinkage has usually occurred during storage, and the
concrete has matured substantially by the time of erection. This helps to eliminate the significant
variations likely with young concrete.
6ofl9
13.2
Geometry control is achieved in the casting cell by means of a system illustrated in Figures 13.1 and 13.2.
The elevation control bolts A, B, C, Din Figure 13.2 are set over the webs as these are stable locations
where no vertical deflection occurs from transverse flexure or post-tensioning. For example, wing tips can
sometimes deflect upward by Y. inch from post-tensioning. Horizontal control is established by setting the
match cast segment at the necessary skew at offsets measured at centerline hairpins E and F. Vertical
alignment is set by adjusting jacks on the soffit carriage of the match-cast segment until the elevation bolts
are above or below the plane of the top of the bulkhead by a desired amount.
Normally, the geometry of a segmental bridge surface is defined by establishing three dimensional global
coordinates (easting, northing, and elevation) at the centerline and equidistant to the left and right over each
web at each joint (Figure 13 .4). These coordinates are directly calculated from the stationing, Instantaneous
radius of curvature, longitudinal profile grade and snperelevation at each joint. Global elevations are
adjusted for camber (the opposite of deflection). Normally, camber adjustment for global structural
torsional twist is rarely needed but could be incorporated if necessary.
Global
v"""""
'
j'
7 ofl9
Three consecutive joints defme the intrinsic geometric surface shape of two consecutive segmentsnamely: the previously made match-cast segment and the yet to be made new-cast segment.
Station
8 ofl9
If it is assumed that the after-cast coordinates of the match-cast segment are already known from previous
observations and calculations, it is a tedious but relatively straightforward mathematical process to imagine
setting the cell-bulkhead at the desired position of next (new-cast) joint in global space (Figure 13.5) and
transforming the global coordinates of the two known joints and the new desired (bulkhead) joint from 3-D
global space to the local coordinates of the casting-cell. The latter are defined by the bulkhead and cell
centerline (Figure 13.6). This transformation provides the set-up of the match-cast segment relative to the
desired bulkhead location for the new-cast segment.
To reference the new segment to the cell and facilitate after-cast observations, four new elevation bolts and
two new centerline hairpins are placed in the top of the new-cast segment, close to match-cast joint and
bulkhead. Those close to the bulkhead (bolts Ao and C, and centerline pinE,) define the position of the
bulkhead joint. Those close to the match-cast face (bolts B, and D, and centerline pin F ,) relate directly to
those next to them on the match-cast segment (Am, Cm and E.,) and thus to the previous bulkhead joint.
Likewise, those at the far end of the match-cast segment (Bm. Dm and F.,) relate to the previous (A", C" and
E" -not shown) and the previous bulkhead joint.
r"rEie,effon Bolts
(Vertical Control)
Cefl
L..
Bulkhead
Face
'-''""'""on
Top
of Bulkhead (Typ.)
)
Chapter 13 - Geometry Control
9 ofl9
Joint jj
Previous
Ch
Match-Cam
Segment
Sight-line
Center
Hairpin
Jomti
LeftLe
Ceil
Left
Em
em
'=======~~-~m==~~~~--==~~~~-====--1
~
B.c
De
New-cas!
Segment
Cell
Righi
Right Length
=Cctocm
cb
Standard 'd'
Fixed
Bulkhead
.J
Chapter 13 - Geometry Control
10 ofl9
Observations are made to an accuracy of (J.OOl feet. It is recommended that readings are by two separate
teams or lead surveyors. The alignment of the cell and elevation and attitude of the bulkhead should be
checked regularly by reference to remote bench marks or survey points to guard against (unlikely but
possible) error due to drift of equipment.
Processing of numbers may be graphical or numerically by computer. It is recommended that a graphical
plot to an exaggerated scale be run as a separate check against computations and to provide a visually
recognizable warning in advance of error.
The above is a basic introduction to geometry control needs and techniques. It is not the intent here to
present a full thesis. Geometry control calculations are tedious; they are best made by a computer program
and further explanation would add little to this guide.
Variations on the basic process are possible to accommodate situations where occasional elevation bolts
and centerline hairpins cannot be placed in their desired locations to avoid construction details such as
block-outs - or to accommodate breaks in superelevation across the width of the segment or an offset
profile grade line - and so on. The key is always to respect that elevation bolts over the webs defme vertical
control and centerline hairpins define horizontal control.
It is important that little or no twist is inadvertently introduced when moving a new-cast segment into the
match-cast position- a simple check is illustrated in Figure 13.9
~"'I
:?>"'"
- - -- -'
Inadvertent twisted
setting
------.'it
G>-----------------------..
.
...............
Bulkhead
11 ofl9
13.3
Offsets: Centerline offsets are measured from the casting cell centerline using a metal
scale fitted with a center point which sits in a pnnch mark on the hairpins. A spirit level
shonld be attached to this scale so that it is set horizontal. Also, it should be held at right
angles to the centerline of sight in the cell (Figure 13.10).
(2)
Elevations: Elevation readings on the bolts are made with a precision level placed on top
of the fixed mounting, reading onto a leveling rod fitted with a scale divided down to at
least .005 feet. In order to make sure the readings are taken at exactly the same point
each time, the leveling rod should be fitted with a center point which sets into a punch
mark in the top of the bolt.
(3)
(4)
Lateral offsets to the level bolts should be measured from the centerline hairpins. It is
preferable to have the bolt positions accurately marked on the bulkhead so that they are
always at the exact required offset from the centerline (Figure 13.8).
With care and precision, the readings obtained will allow precise processing using threedimensional coordinate geometry computations which are the most accurate when it
comes to defining curved surfaces in space. Good recordkeeping is essential as well.
There have been occasions when accidentally one or more of the geometry control
hairpins or bolts were lost. This is not irretrievable. It is usually possible to continue
construction by using known relative positions of adjacent undamaged markers. What it
means is merely a little less predictable control over the erection aligmnent.
Spirit
levelling
bubble
Pfnely divided
metal scale
pirit level.
.
Cenler point
c( ha,.,dend
sl'eeJ
Center
punc!J
stirrup
HoNZ!J!!Iaf Qflsel$
Cenl-er point of
h~t:delJ
ed steel ___
an ball -
12 of 19
13.4
When moving this segment from temporary storage into the match-casting position, it is simply set
to the same position it had after casting by reading the same elevation on the bolts and the same
offsets on the markers; This gives a starting point from which all other segments can be
subsequently referenced, assuming that there is no casting curve adjustment to be made. If there is
a casting curve adjustment needed, it can be made at this time. The bolt and centerline marker
readings are also used for setting the first segment in its required attitude in the erected structure.
The technique is again part of regular geometry control procedures and will not be elaborated
further here.
The main feature of the first segment which, if it is a pier or abutment segment, is usually shorter
than the typical segments, is to establish a transverse horizontal control line on the surface of the
segment in the casting cell (Figure 13.11 ). This provides a greater base line length to align the
segments in the field. The normal procedure is to determine either a radial line or a line parallel to
the bulkhead and establish this on the center of the segment with horizontal alignment hairpins set
as far out on the segment wings as possible. This requires that this line be observable on the
bridge, either from above or from the ground below. In the latter case, the line has to be scribed
onto the end faces of the wings, and two observation stations must be established on the ground on
either side of the pier (Figure 13.13).
Precise setting and checking of the first erected segment is essential since any error in its position
is magnified proportional to the ratio of the length of the cantilever or continuous run of segments
and the transverse base line width.
)
13. 5
should match the theoretical horizontal geometry. The only errors occurring should be slight
deviations due to casting errors and corrections. The overall line should closely track the desired
line.
A generous tolerance should be allowed for the vertical alignment since this is subject to all kinds
of variations due to construction loads, creep, shrinkage, temperature, post-tensioning variations,
and so on. However, the alignment should closely agree with the required alignment at the time of
erection when duly corrected for these effects. It is difficult to put a precise figure on this
tolerance as it depends upon the type of construction. For cantilever construction, the vertical
alignment should generally be within one- to two-inch per cantilever length of I 00 feet, and
similar cantilevers should behave comparably. (This latter point is a guide to the accuracy of the
initial material assumptions and calculations).
Any substantial variations from line and level or any trends noticed early in the construction
should be subject to close study, and corrective action should be taken. The latter would include
checking procedures for errors, especially systematic errors, amending casting curves for future
segments and perhaps shimming the joints with glass fiber matting to adjust the alignments. The
use of shims is a "last resort" since it causes stress concentration on the segments and prevents the
joints from closing properly, which may cause problems during grouting.
13 of 19
Pre-determine and
set lhis angle in the
casling--cell
f
f. C;rsling-cell - ----~
1e,.L1on bolts
...- Tempornry
lmlkl!ead
- [-.
..
Auxiliary llD irpins to_/
ll"iiiJSflei"'Se
Casting-eel/
bulk/lead
scl
Alain longitudinal
center line hairpiiJs
13.6
Systematic Error
It is worthwhile giving some consideration to the implications of making a systematic error in
each casting operation either as a result of a computational method error or as a physical defect of
the equipment which is systematically repeated in each segment of a nm. Figure 13.12 shows the
effect which creates a total small systematic error (e). The final error after "n'' segments amounts
to n(n-1 )e/2. In other words, a systematic error of .002 feet in each segment would amount to an
off line error of .09 feet after 10 segments and .38 feet after 20 segments. Clearly, systematic
errors must be avoided, and the use of proven techniques should be encouraged.
e::;trror
---r
n-1
___L
It can be_ slioivn lllal tile effect of
error
E.
1'1
sm<1/l consistent
11
14 ofl9
13.7
Achieved Profiles
Figures l3 .13 and 13.14 illustrate the kinds of variations in cantilever and span-by-span profiles.
Figures 13.15 and 13.16 show the means of correcting a profile by shimming a joint. It is
emphasized that this should only be done if absolutely necessary as a last resort. It can lead to
complications and is not entirely predictable.
13.8
13.9
Temperature Effects
In some cases this temperature effect may cause problems during construction. Figure 13.18(a)
for example shows a structure with a fixed pier in the center: After the cantilever on this fixed
pier is erected a connection is made to the remainder of the structure. The connection should be
able to pull the erected part of the structure over its bearings in order to take care of the
temperature movement. If the connection is not strong enough, the cast-in-place splice will crack
(Figure 13.18(b)).
-------~
for anticipated
(a)
..
Canl.,fl
~------
---
+-
07
___
deformations - - ,
+ .
=:.-------!__
__________ =
Required t/Jeoretic:al
final grade
Canl/2
-~---- ~
----=-
(b)
{c)
Figure 13.13 -Alignment of Cantilever Structure (Three Span)
15 ofl9
Actual
T/woretical
t.hus fnr
----
ITT1
1'heroUt::al
re.quired
.prolile
l---
"'
If observed profile do_es JJot match deslred and if it is -c/enr tiJa-_l they
will conlinue t-o diverge, lhen some correc:tive ac:Uon is possible by
shimming the joints willl woven glass fiber matting embedded iii tile epo.y.
Usun-ltJ -llw rcrnaining cantilever seg-me.-nts IJa ve a:IJea(fy -been ca$l by ibis
time ma-k-ing correcUons by cast-ing cOJnpe-ns:a-Ho-ns impossib-le.
StJiJnming should be -doue only if a.bsolutelyr necx:Jssa_ry, and t-hen it shnuld
be lwpl t-o a nJinim.um be.cnuse tis c./fee-l is not pred-ictnbie ruJCl t-lu~
l/Jicl<er joints can lead more easily to intrusions of epoxy nJto duels. etc
Sbou
\J
Chapter 13 -Geometry Control
16ofl9
1 Layer
None
Shimming jlJint trith wuven glass fibre mat.t:Jng lo
pmlillde wedge shaped jlJinl to corr;ect sliltnment.
It is r:ecoml'(leiJ.deq fh1. no mare {han 2 laJil!rs
tpsximum be u.s~d in any joint.
Layering as shown would Up next segments
d.oimwards.
To tip next segments upwards. shim from bottom
ott~asiona.llr
be ner:es$ary
in canUietrer constrUtill.ion.
)
Mea-sure C10rner;- or
(9
l
(iJ )ObS"efVatioJis
r-- -It I!
.)
@
Scg.
Seg
,.
~-~-
-1r:_ r--
4 \
Seg 3
Seg, 2
Sec
17 of19
(I)
(2)
cast the splice when the deflection at the cantilever ends is the greatest (say 3
p.m.)
(3)
At sunrise, the next day stress as mauy tendons as allowed by the strength of the
"still green" concrete. Usually this is two or four tendons, which is enough to
compress the splice so that the subsequent temperature deflection will not crack
the concrete at the splice at the bottom.
If the splice were cast in the morning, it is possible that the temperature effect will crack
the bottom of the closure joint before the day is over.
18ofl9
'%*'
(b)
Not exposed,
temperature=
(a)
{c)
n
II
:J p. m
(appro.< I
10 p.m. (appro.><)
..
)
Chapter 13 -Geometry Control
19 ofl9
TABLE OF CONTENTS
14.0
14.1
Bearings
14.2
Expansion Joints
(Transflex or Waboflex)
10
14.2.5 Bearings and Expansion Joints Supplied by The D.S. Brown Company
12
14.2.5 Bearings and Expansion Joints Supplied by The D.S. Brown Company
13
14
15
14.2.7 Bearings and Expansion Joints Supplied by Watson Bowman Acme Corporation 16
14.2.7 Bearings and Expansion Joints Supplied by Watson Bowman Acme Corporation 17
I of 17
TABLE OF FIGURES
Figure 14.1
Neoprene Bearings
Figure 14.2
Pot Bearings
Figure 14.3
Figure 14.4
Figure 14.5
Transflex Joint
Figure 14.6
Modular Joint
Figure 14.7
Figure 14.8
10
Figure 14.9
11
2 ofl7
Since the product supplied is seldom equal to that shown on the plans, the contractor will submit
shop drawings which will be provided to the inspector for his use in the field after they have been
approved.
Upon delivery to the site, the inspector needs to verify that the product is in agreement with the
shop drawing and is properly installed.
14.1
Bearings
There are two types of bearings commonly used on segmental bridge projects: neoprene bearings
with or without sliding pad, and pot bearings.
Neoprene bearings are more desirable bearings for their simplicity of installation and
maintenance-free performance, However, both load bearing and movement capacity limit the
application of neoprene bearings to short spans and short distances between expansion joints.
Neoprene bearings with sliding pads have more movement capability and therefore allow longer
distances between expansion joints (see Figure 14.1).
Pot bearings are available for large loads and movements and is therefore the type of bearing most
used. Pot bearings consist of a base plate containing a rubber cushion inside a low cylinder or ring
which allows a small rotation in the base plate. This is the reason for the name "pot" bearing. The
top plate rests on a piston which rests on the rubber cushion inside the cylinder. Since this rubber
disc is under high pressure, a seal is required to prevent the rubber from squeezing out of the
"pot." The top plate can have one of three arrangements either allowing or preventing movement:
fixed, free or guided. A typical fixed bearing which does not allow movement, a free bearing, and
a guided bearing are shown schematically in Figure 14.2.
Bearings are usually bolted down to the pier and have dowels at the top to provide horizontal
fixity to the structure.
14.1.1
Bearing Installation
Important items for bearing installation are:
Temperature adjustment
3 of 17
..
4 ofl7
Pot Plate
F'IXEO*
(No movement)
Sole Plate
Guide Bars
Piston
Masonry Plate
UNJ~OtRECTiONAL.
EDGE:GUIOED
)
Teflon/Stainless Steel
Sliding Surface
Sealing Rings
Elastomeric Disc
MULIIOIRECTICNAL*
~)
Chapter 14.0- Bearings and Expansion Joints
5 of17
This 118 inch space should be carefully divided into two equal amounts on each side. ofthe top
plate and preferably kept constant with wooden inserts until the bearing is placed. The guides now
have some movement capabilities both ways and some tolerance to tum.
6 ofl7
7 of17
mechanically locked within a machined edge rail cavity with an anchoring arrangement suitable for current
design code requirements.
The steel edge member(s) shall be A-588 or A-36 grade steel with a galvanized finish. The strip seal edge
member cavity which accepts the Neoprene sealiog element locking lug shall be machined to fully engage
the sealing element and prevent leakage. The Neoprene sealing element shall be additionally adhered with a
single component moisture curing adhesive.
Proper grade and temperature adjustments shall be made at time of joint setring in accordance with the
manufacturer's recommendations as outlined in the shop drawing submittals.
The advantages provided by a Strip Seal System are simplistic design, movement versatility, armored edge
protection, and mechanically locked in place Neoprene sealing element.
14.2.2 Molded, Steel Reinforced Rubber Cushion Bolt-Down Systems, (Transflex or Waboflex)
The Transflexjoint is shown in Figure 14.5.
8 of17
9 of17
Finger joints tend to be generic in origin and manufactured by steel fabrication companies as per project
specific design requirements.
10ofl7
Careful placement and installation is required to assure appropriate structural support beneath the finger
plates. Additional care is necessary to align the fingers to assure linear movement and prevent
misalignment and possible damage.
The principal disadvantage of finger joints is trough location and the inability to effectively maintain and
clean below grade troughs.
11 ofl7
14.2.5 Bearings and Expansion Joints Supplied by The D.S. Brown Company
LOAD TESTING
Anchorage Illustration
12 of 17
..
14.2.5 Bearings and Expansion Joints Supplied by The D.S. Brown Company (Continued)
Bearing Assemblies
D.S. Brown is one of the leading suppliers of structural bearing assemblies. With extensive experience and
utilizing the latest technologies, D.S. Brown can efficiently design, manufacture and test Versiflex= HLMR
pot-style, spherical and elastomeric bearing assemblies for all
types of construction.
)
V ersiflexTM elastomeric bearing assemblies are custom
P: 419.257.3561 F: 419.257.2200
Email: cyoungless@dsbrown.com
URL: www.dsbrown.com
13 of 17
ECvid< dmlr.a.o for runoff water and are deslgned to minimize troffie noise.
14ofl7
Q\4\l.U'Y
ClPEC jcints are designed fur quality, with a proven history of durnbility and reliability :as demonstrated by the
satisfactory performance in a wide variety of structural projects fur more than 30 years. CrPEC joinl" offur.
Excellent traffic comfort,
Protection ofsurfaces under the joint,.
Long life,
30
. !EPS
so
,~JEP8
80
"" """'
2S
60
7S
2S
105
mini
60
60
"'
-"'"" ...
])
""''
mini
JJO
10
!40
10
9Q
10
SIZCStnmm
,..,
li
90
"
"
""
1..,
61)
$91
95 59'
15ofl7
14.2. 7 Bearings and Expansion Joints Supplied by Watson Bowman Acme Corporation
Background Information
Located in Amherst, New York, Watson Bowman Acme Corp. has been at the industry forefront of design
and manufacturing expansion control devices for the bridge construction industry. From its modest
beginnings in the 1950's, designing small movement pavement seals for concrete highway applications in
New York, to producing today's state of the art large movement seismically designed modular expansion
joint devices on the world's largest segmental concrete structures. Watson Bowman Acme has provided
technical support and product solutions for the most complex and challenging applications.
As an ISO 9001-2000 Quality Certified Company, Watson Bowman Acme quality initiatives provide a
focus on continual improvement and relentless customer objectives.
Over 90 employees are dedicated to design, manufacture, sales and service of bridge expansion control
systems, and related fabricated steel products, such as. hand rail, scuppers, drains, and miscellaneous steel
requirements.
Watson Bowman Acme provides product selection and related performance, sizing and costing
recommendations for engineering firms and contractors.
Watson Bowman Acme has been selected as a product supply partner on some of the most prestigious
segmental concrete bridges and design/build projects in Norlb America. The Cooper River Bridge, New
Susquehanna River Bridge, and Four Bears Bridge are a sampling of projects utilizing Watson Bowman
Acme products and services.
Manufacturer shall provide shipping and lifting assemblies for jobsite handling of modular
expansion joint devices.
2.
Temperature adjustment chart and placement instructions should be included in shop drawing
submittal package.
3. Manufacturer should identifY lift points and lifting requirements for handling and maneuvering
modular joint assembly at jobsite. (Figure I)
4.
Hardware for opening and closing joint assembly in accordance with temperature adjustment shall
be supplied by manufacturer. (Figure 2)
16 of 17
11.2. 7 Bearings and Expansion Joints Supplied by Watson Bowman Acme Corporation
Continued
Figure 1
5.
6.
Figure 2
Appropriate hardware for placement and grade setting of modular joint assembly must be
identified, communicated and agreed by the supplier and contractor.
Contractor shall inquire of manufacturer, any proprietary innovation or methodology to assist or
facilitate installation efficiencies.
7. After temperature adjustment and grade setting of modular joint assembly, the contractor must
effectively place formwork around joint assembly in blackout area in preparation of closure
concrete pour. (Figure 3)
8. Formwork must be placed to assure protection and integrity of support box openings, preventing
concrete intrusion within modular joint assembly support boxes. Rebar must be tied into support
boxes, (Figure 4)
9. All shipping and placement hardware is removed after closure pour is complete and cured.
Figure 3
Figure 4
17 of 17
.)
TABLE OF CONTENTS
Lessons Learned
15.1.0 General
4
4
4
6
7
7
7
9
9
9
10
10
10
10
11
12
12
12
12
13
14
14
14
14
15
15
15
16
16
16
18
18
15.4.0 References
19
I ofl9
TABLE OF FIGURES
Figure 15.1
Figure 15.2
Figure 15.3
Figure 15.4
Figure 15.5
Figure 15.6
Figure 15.7
10
Figure 15.8
11
Figure 15.9
13
6
Figure 15.10
Figure 15.11
17
Figure 15.12
17
>
15
.J
Chapter 15.0- Lessons Learned
2 of 19
--)
3 of 19
desigu or unintentional. It is important to design and detail to mitigate typical problem areas, in addition to
taking particular care dnring casting.
The presence of numerous internal tendons in balanced cantilever structures raises the potential for certain
types of delamination, where the tendon force causes a portion of the flange to separate from the segment.
The frrst type is in the upper and lower flanges, where segments near the pier segment or mid-span house
multiple tendon ducts. This translates to a significant portion of the flange that is effectively voided dnring
erection, as grouting is generally not performed until the cantilever is complete. The multiple voids create
a weak plane that can lead to splitting of the flange. This can be mitigated by adding "J" ties to secure the
top and bottom mats ofrebar (see Figure 15.1). Generally, this is only a concern with longer spans, where
the ducts would constitute a significant fraction of the flange area. Particular care is necessary in long span
cast-in-place balanced cantilever bridges with a large number of ducts near piers.
HALF SECTION
.)
'--
4 ofl9
Another area where delamination should be addressed is in the bottom flange of variable depth segments. The
change in angle at the segment joint creates a natural deviation in the bottom flange tendons. This deviation bas a
tendency to pull out, delaminating the bottom flange. Supplemental stirrups are required in the vicinity to restrain
the deviating tendons. A common configuration is shown in Figure 15.2.
BOTTOM FLANGE
SECTION
LONGITUDINAL SECTION
)
Chapter 15. 0 - Lessons Learned
5 of19
Hairpins
[l
"ilai-rpins
.-:JIIO\IL
'
Sec-lion A
CurVl!d pa-,.1 of te-ndon mu~t be
/CC'ated in b/Jster Hail'pin r~inforcmg
concentrated in <'ut'VC' of tendon leug{h.
15.2.3 Cracking
Cracking occurs often in concrete structures for a variety of reasons. When noticed, cracking should
always be reported to the engineer so that the cause may be detemtined. Some common causes of cracking
are;
Figure 15.4 shows the situation where new concrete is cast against old concrete. This, of course, occurs at
every cast-in-place joint. Cracks as shown may appear. These are shrinkage cracks which are difficult to
avoid. To control the cracking, additional reinforcing steel or transverse post-teosioning may be provided
near the joint faces in the cast-in-place concrete
Figure 15.5 shows crack patterns, which may occur at blisters where high forces are introduced into the
concrete. This type of cracking may be reduced or elintioated by locating blisters at slab-web intersections,
by limiting the force (number and size of strand) anchored in a single blister, and by use of rebar to control
crack width.
Figure 15.6 shows cracking at a post-tensioning anchor. Concrete at anchors placed on the edges of thin
slabs is susceptible to cracking. Teodon sizes should not be larger than 4x 0.6-inch-diameter strands on a
nine-inch-thick edge. The anchorage area is normally reinforced to control or elintioate this cracking.
6 ofl9
7 of 19
or rein-forcing
~
w
I~
Precast
seg~ents
J.
Precast. segm~nls-
.J
/Web
Segment ,iomt
'
~Tendons
'-
Crgcking at Blisrers
Cracks
~Segmenl jam!$
//
if'Eb
Cracking
in
jci~l
~~----
Anchonge
blister
j--".
------------- ------
-~-----
---~---
,._-:-_;7Y
--~----
1~ndons
_L..
8 of19
Cra.ck
.1
\J
Chapter 15. 0 - Lessons Learned
9 ofl9
This can be mitigated by several methods. An effort can be made to distribute the tendon forces across the
section, possibly by adding smaller anchors near the segment wing tips. Alternatively, an explicit
calculation of the distribution ofloads into the superstructure can be performed, as is frequently the case in
cable-stayed superstructures. During construction, it is possible to combat the problem by specifying a
lower allowable stress in segment joints, or requiring a minimum compression at the joints when the
stresses are calculated by conventional methods.
are stressed determines the magnitude of the secondary post-tensioning forces, which can be significant.
. __)
10 of 19
The use of a more generous number of3 inch diameter drain holes, reinforced with spirals, and provided
with wire covers to prevent bird intrusion into the box is recommended. Water depths covering external
ducts have been reported, which resulted in some corrosion in tendons.
15.2.141nspection Access
Design of segmental box girder bridges with inadequate inspection access, such as shown in Figure 15.8, is
unacceptable.
11 of 19
process to finish the job by the project completion date. While this issue does not generally impact the quality of the
completed project, it does impact the commercial viability of segmental construction from the Contractor's
perspective, and it represents a "lesson learned" in that context.
determine precisely the weight of the erection equipment (particularly erection gantrys) aod other loadings,
with respect to the assumed loadings in the contract documents.
12 of 19
-)
~-~~'~~"'" Eccentricity
Causes Secondary
Shear
13 of 19
piers directly from the superstructure to footings do not induce any moments in piers. On the other hand,
pier brackets do induce forces and moments in piers due to out of balance loads. Post-Tensioning tendons
from the superstructure to the footing have been used to support our-of-balance moments successfully, but
are more flexible from the stand point oflimiting cantilever deflections.
significant and costly errors still occur. Global graphical plots of aligmnent and elevation control computer
output are necessary to disclose numerical errors that may be overlooked. Additional quality control both
during segment production and in erection is recommended as follows:
casting curves and geometry control procedure must be meticulously reviewed and double
checked
geometry control readings and set up calculations must be independently checked
the position of the instrument, target and form bulkhead, which are all supposed to be at fiXed
positions, should be checked frequently using independent bench marks
erection elevations and horizontal alignment controls should be provided for use during
erection to check whether or not the correct alignment will be obtained.
14 of 19
segment. A comprehensive study of segment warping was conducted at the University of Texas at
Austin(?) This study indicates that warping of segments will not be a problem when the width/length
(W/L) ratio of the segment is less than 6. Procedures are recommended in the study when theW/Lis
greater than 6. Applying the steam to both segments in their entirety will reduce the curvature.
)
Chapter 15. 0 - Lessons Learned
15 of 19
Locate the blockage location, and chip into the duct to remove the blockage.
In event installation of one or more tendons is not possible, utilize alternative provisional ducts required by
contains a tendon which is supposed to be straight. However, due to insufficient support the tendon sagged
in between the joints, thus creating a possibility for tendon pop-out, delaminations or bending cracks.
Figure 15.12 shows two curved tendons at a diaphragm one over the other. When there is adequate
distance between the tendons, a large radius of curvature, and properly compacted concrete in-between the
ducts, no problems usually develop. However, during construction both the distance as well as the concrete
quality between the ducts may be less then intended. As a consequence, duct "b" can be pressed into duct
"a," spalling the concrete and causing a problem with the stressing of the tendon in duct "a."
)
Chapter 15. 0 - Lessons Learned
16 of 19
'r
'
cracks
.!1---r-.1-" ~ I ]
F
J\
I
Goint ;;ack
spa/lin11
Delamins.tion
):
'
FII'Hl
Imprintof duct
Original
position
of t.endon
Position of
tendon ttffcr
fai/we
Manlw/e -
17 of 19
Good quality control on the mixing. It helps to color the hardener differently from the resin so
that proper mixing can be checked visually.
2)
After soft epoxy has been noted, the cause established, and an engineering review indicates that
keys across the joint are adequate (which they may well be), no further structural repair is
required.
3)
The material in the joint should be tested in order to find out if there may be a problem with the
durability.
I)
Grout tendons and recess pockets, if possible, before the onset of frost. Note that grout can itself freeze and
that it does not help to grout when it freezes or at low temperatures.
2)
If certain tendons and/or anchor pockets cannot be grouted, they must be emptied of water by:
a.
b.
3)
If ducts are to be left ungrouted for a long period of time, temporary corrosion protection of the tendon
must be provided.
J
Chapter 15.0- Lessons Learned
!8 of 19
15.4.0
References
(1)
(2)
(3)
(4)
(5)
Muller, Jean M., "25 Years of Concrete Segmental Bridges Survey of Behavior and
Maintenance Costs", J. Muller International, 1990.
(6)
Controlling Twist in Precast Segmental Concrete Bridges, Breen, John E., PCI
Journal, V. 30, No. 4, July- August 1985, pp. 86-111.
(7)
-....__ _ _/
19 of 19
.")
TABLE OF CONTENTS
)
16.0
16.1
Motivation of Stakeholders
16.2
16.3
16.4
Preconstruction Conference
16.5
16.6
16.7
16.8
16.9
16.10
16.11
16.12
16.13
16.14
16.15
16.16
Safety
16.17
Environmental Issues
16.18
16.19
16.20
Summary
I of 11
FHWA, the Engineer of Record (EOR), the CEI team and perhaps on occasion from additional
technical review consultants.
Regardless of the input, the Owner is the ultimate decision maker. The Owner must weigh and
evaluate the technical merits of the advice of these sources together with their experience and
expertise to arrive at a decision that is in the best interest of the Owner. This decision process may
include factors other than those that are purely technical in nature.
The Contractor - The Contractor has the role with the most risk. While most engineers and
inspectors claim to understand the Contractor's risk, many have no real grasp of its true potential.
With one bad decision on one project, the Contractor can put his firm out of business. The
Contractor's goal is to build the project in reasonable conformity with the plans, specifications and
special provisions provided by the Owner while maximizing his potential for profit. As nothing is
assured, Contractors try to have a cushion to offset the unknown problems that will arise.
Successful Contractors usually adopt "the glass is half empty and I think it has a slow leak"
approach. The Contractor's role also includes managing his workers; dealing with suppliers; as
well as interfacing with the CEI team and Owner. Often the CEI team focuses only on the
technical aspects of an issue and does not realize that the Contractor must weigh the technical
against many other aspects as well.
The Contractor's Engineer- The Contractor's Engineer role is strictly defined by his contractual
agreement with the Contractor, which outlines the specific tasks he is to perform. He bases his
submittals and decisions on his experience, which might be very extensive.
He provides the
Contractor with specific engineering and technical advice. This input might not agree with the
EOR's or Owner's engineering opinion but the Contractor will rely on it.
The CEI Team - It is the responsibility of the CEI Team to administer, monitor, and inspect the
Construction Contract such that the project is constructed in reasonable conformity with the plans,
specifications, and special provisions developed for the project. The CEI team therefore needs to
coordinate the interests of the Owner, requirements of the Designer, the work of the Contractor,
the submittals of the Contractor's Engineer and the issues and concerns of multiple jurisdictions,
utility owners and abutters. The CEI team's ultimate objective is to ensure that the Owner gets
what he contracted for as indicated in the Contract documents, all regulations and permits are
adhered to, the project gets completed on schedule, the quality of the work meets or exceeds
industry standards, Contractor payments are processed timely and changes are promptly and
equitably addressed. The CEI Team is placed on the project to make decisions and to facilitate the
Chapter I 6. 0- Construction Engineering & Inspection of Segmental Construction
2 of I I
construction process and is not 1here to simply escalate issues up 1he ladder to the Owner for
resolution. Some issues require escalation, however many more can be resolved at the project
level. The CEI team's role is also to provide validation of1he design assumptions; 1hat is key, and
1he tasks that 1he CEI team performs (surveys, material testing, etc) are merely an aspect of 1he
validation process. The full roles and responsibilities of 1he CEI team are more 1han can be
addressed in this chapter. The intent of the following guidelines is to identify for consideration
those that may be particularly important to consider in segmental construction.
..)
Chapter 16. 0- Construction Engineering & Inspection of Segmental Construction
3 ofll
assumed.
\J
'
4 of !I
incorporating the latest technology to expedite the process is in the best interest of all concerned.
The RJ:I process is a well established to address questions and or proposed changes and can
similarly be streamlined by use of the latest technology. Some Owners may accept a completely
paperless system while others will be open to the use of digital technology for expediting
submittals and reviews while retaining hard copies for permanent records. Discussing and
resolving how these are to be handled early on will get everyone on the same page and into an
efficient production mode.
survey and data reduction analysis system checks. In addition to the traditional geometry control
survey for match casting it is very important that each segment be thoroughly checked after
casting for dimensional tolerances and casting defects. It is easy to understand that repairs
5 ofll
identified in the casting yard and corrected before shipment will be much less costly that the same
repair that is identified during or just prior to erection when the erection of that segment is now on
the critical path.
Things to look for include, but are not limited to, a recheck on duct positions at the match cast
joints, exit orientation angles for embedded PT ducts, broken shear keys, crushed or out of
position PT ducts, bearing surfaces, embedded items etc.
It is important that information is communicated from the casting yard to the jobsite for any
repairs or corrections that need to be done after erection; such as repairs to match cast face.
If there are elements at the interface of substructure and superstructure that are dimensionally very
tight, as-builts should be taken for coordination with the subsequent casting.
EOR will typically also review the procedures, but more often from a perspective of loading on
the permanent, partially constructed structure to make sure that the permanent structure can
support the erection loads and are consistent with those assumed during the design. Sometimes
several iterations of these submittals may be required to reach approval of a package fulfilling all
contract requirements. Load testing of the specialized equipment is typically specified and will be
witnessed and approved by the CEI Team.
member of CEI Team sign off on each step of the procedures. An example of an erection
launching procedure signed by CEI Team and Contractor field engineer is included at the end of
this chapter. This is especially important for erection gantries where failures of the past have most
often been related to critical steps being missed or improperly carried out, usually during
launching. The consequences of a gantry failure - serious injury or fatality, property damage,
schedule impact and associated costs can be crippling on a project. Attention to details, staying
with the approved sequence and insistence on competent supervision are critical. The minimum
qualifications of the Contractor's personnel operating these major pieces of equipment should be
specified in the contract and strictly enforced.
and with the details of corrosion protection provided by grouting. The CEI Team must pay
particular attention to ensure the applied forces are as per the design requirements by confirming
jack calibrations, gauge pressures and reconciling elongations. Any inconsistencies must be
6 of I I
and the CEI Team should keep detailed records of post tensioning and grouting and reconcile
these routinely to make sure complete sets of data will be turned over to the Owner at the
completion of the project. Examples of a stressing record and a grouting record are included at the
end of this chapter.
Sometimes these devices must work in harmony with seismic restainers/buffers and eac:;h element
must be installed correctly and within specified tolerance if they are to work together. A thorough
review of all related tolerances is recommended prior to precasting and substructure construction
to make sure that all elements will be able to be installed correctly. The CEI team and Contractor
should reach agreement early on procedures for setting and verifYing how this will be achieved as
part of the Quality Control Program.
16.16 Safety
The Contractor is responsible for overall site safety and for all persons and property on the site and
will normally have one or more full time on-site safety representatives assigned to oversee the
work and ensure compliance with all local and federal safety requirements. That being said,
Owners and CEI consultants who have been involved in post accident investigations and the
lengthy and costly litigation that can result from a serious accident fully understand the importance
of a detailed and comprehensive accident prevention program.
Attendance of the CEI team in Contractor toolbox meetings is strongly recommended particularly
prior to the start of any new operation. The submittal of construction work plans and review by
CM should address how the physical work will be performed including associated Job Hazard
Analyses (JHAs) that must be reviewed and fully understood by the workforce. The Owner may
provide or request the CEI team to include trained safety personnel specifically assigned to the
Chapter I 6. 0- Construction Engineering & Inspection of Segmental Construction
7 ofll
project that can conduct daily site inspections and be the go-to person on the Owner/CEI side with
regard to safety issues. It is connnon practice for safety to be the frrst item of discussion at weekly
or bi-weekly progress meetings and these are an excellent forum to address safety planning and or
corrective actions. However the concept of"Safety is everyone's responsibility" is a good one for
all of us to remember each and every day. This can be achieved by adoption of the philosophy that
no one should walk by an unsafe act or condition without taking corrective action or bringing to
the attention of the appropriate individuals who can.
responsibility of the designer and contractor. The CEI team should be capable of taking an active
role in resolving these types of disputes which requires a good understanding of design principles,
construction and industry practices and as well as dispute resolution procedures. It cannot be
understated that these issues are best resolved by the people in the field as they occur and a sincere
effort by the parties to the Contract should be made to do that for the benefit of all concerned.
successful project. The CEI Team needs to take the lead in ensuring that these key ingredients are
in their project. These keys to success include:
Teamwork - The Owner, Contractor, Designer and CEI Team must all be working for a
quality project that is built on-time and makes money for the Contractor. Many projects have
"Formal Partnering" events every quarter and then have adversarial relations on the day-to-
day business of building the project. Teamwork or Partnering must be a large aspect of the
day-to-day interaction between the parties on-site. Since the CEI team has the most daily
interaction with the Contractor, they have the most opportunity to foster teamwork.
8 of II
Respect of other points of view - For the project to succeed, egos must be checked at the
door. All too often, parties do not listen well to each other and refuse to acknowledge any
other point of view besides their own. That does not work. The CEI team should take the
lead in fostering good communication and understanding. They need to clearly state their or
the Owner's understanding and then solicit the Contractor's understanding. Then, if there are
any differences, all of the parties need to work together to come to a consensus decision that
Maximize project level decisions - The CEI team is placed on a project to administer it and
this includes making appropriate project decisions. If decisions are not addressed at the
lowest practical level, then the project suffers delays and usually claims result. The
Contractor places personnel at the project with the authority to make decisions and if the
Owner and CEI team also have on-site personnel with the authority and willingness to make
decisions, then the project stands a great chance of being a success.
16. 20 Summary
Quite simply, the CEI Team should be a part of the solution and not part of the problem. The CEI
Team can affect the project success by their actions or inactions! Inaction is not representing the
best interest of the Owner. There is no place for adversarial attitudes on part of the CEI team.
Further, it is imperative that the CEI team lead by example with a cooperative attitude. Also,
when the Contractor sees that the CEI Team is working with them on a daily basis, then positive
relationships result and the Contractor responds by working more with the CEI Team and Owner.
If the CEI Team is helping the project succeed, then the Contractor makes money and the Owner
gets the project he envisions. Everyone wins.
Each project starts with a sense of trepidation, since the project staff usually does not know each
other well. If the CEI team shows a willing attitude every day, then the Contractor will soon
reciprocate. Someone has to be the first to be cooperative and it is in the project's best interest if it
is the CEI Team.
Below is a list of some positive steps that the CEI Team should consider. While this list is not all
encompassing, it helps set the framework for project success.
Be consistently fair - There needs to be a realization that it is much harder to tighten the
requirements once you have relaxed them. The project requirements should not vary
from day to day or from inspector to inspector. The CEI team manager need to ensure
inspection point of view, then the CEI team manager should explain the importance to
everyone including the Contractor. This helps educate the work force and improve
quality.
There also needs to be a realization that there is interpretation to plans and specifications.
Often a Contractor has a different interpretation and it is the CEI team's role to help
resolve differences between the different interpretations.
interpretation is different from the Owner's but may still be valid. By being an open
minded thorough listener there is a much greater chance of resolving these differences
9 of II
specification tolerance on critical areas. For instance, the location tolerance for #4
reinforcing used for temperature cracking control is obviously not as critical as the
Give the Contractor a "clean slate" everyday. The CEI Team can't have their judgment
clouded by the past. Even ifthe Contractor is not being cooperative, the CEI Team has to
judge each issue on its merits alone. This is very difficult but it is also extremely
important.
Be Proactive - The CEI Tearn needs to organize and hold meetings in advance of any
operation to ensure that all parties have the same understanding of the requirements. The
earlier that these meetings can be held the better, to allow more time to react to any
comments that arise.
The CEI team needs to share ideas with the Contractor that might help him and the
project. This can be anything from alerting him to required submittals to a different way
that another Contractor performed an operation. The CEI Team needs to identify issues
before they impact the construction schedule.
The CEI team also needs to hold meetings well in advance of any major submittals. The
goal is to develop clear consensus of requirements and acceptance criteria. If this occurs,
Show respect to all Contractor personnel - The largest single mistake that a CEI team can
make is in thinking that the Contractor is stupid, greedy or wants to do poor quality work.
This is simply not true. It is also important to explain to the work force why certain
aspects are more critical. For example conveying the importance of accurate positioning
of confinement or bursting reinforcing behind post-tensioning. If the work force
understands the importance, then the quality will increase. If the work force thinks that
the inspector is merely being a "bad cop" who is beating them with the specifications,
then quality will suffer.
Finally, the Contractor's Engineer should be treated with the "Golden Rule". They
should be treated like the CEI Team would like to be treated. There should be no
resubmittals for petty reasons.
Provide Technical advice to the Owner- The CEI team should always hold meetings with
the Owner in advance of any meetings with the Contractor. At these meetings the CEI
Team and others can openly share information with the Owner so that he has the most
information to make decisions for the project on technical issues. This might not be in
line with recommendations from some advisors, but once the Owner has made the
decision, then the CEI Team needs to present this to the Contractor and maintain a
constant message. The Owner makes his decision based on many factors and, for the best
interest of the project, the CEI Team needs to support this decision once it is made.
As part of the discussions with the Owner, the CEI Team needs to realize that the
Contractor and his Engineer also have experience and expertise. It is very easy to simply
agree with the Owner but it is in their best interest to give an honest opinion. Sometimes
advisors need to give honest opinion and, where possible, cite examples from similar
work elsewhere. Without good reason, no Owner wants to go outside the norm of
industry practice. Also the Owner will not want to make a decision based on incomplete
information.
!Oofll
Motivating the Contractor - As discussed above, all the parties have motivators. For a
Contractor it is much easier to get results using the "carrot" rather than the "stick". If the
CEI Team can show the Contractor why his actions are costing him money, he will
change his actions. The CEI Team should make "early mistakes" costly within the
allowances of the project scope, so that the Contractor will strive to avoid them. If "early
mistakes" are treated too leniently, then there is no incentive to avoid them. Once he has
established processes in place, they are difficult to change so it is important to get quality
incorporated early. A very true adage is that it is always cheaper to do it right the first
time.
Do not surprise anyone- This seems obvious but it often occurs. If there needs to be a
strong letter to the Contractor about an issue, the CEI T earn should have already had
meetings with the Contractor about that issue. If it arose suddenly, then the CEI team
needs to have a face-to-face meeting with the Contractor and discuss the contents of the
letter. Ifanyone gets a strongly worded letter "out of the blue", then relations sour
quickly and the project suffers.
Stoppage of work should be the last resort - The CEI Team has many tools at their
disposal to ensure quality and compliance. If an issue escalates to the point that the
project will be stopped, then things have gone very wrong. If the project is stopped then
it is likely that the project will not finish on time and there will be claims. This is
sometimes necessary but usually it is not in the "Best interest of the Owner".
The CEI Team is in a unique position between the Owner and the Contractor to help the project achieve
success. The CEI Team needs to maintain professional distance from the Contractor but also take positive
actions to help the project. The CEI Team on successful projects is "part of the solution". The CEI staff is
engaged by the Owner and the EOR to help facilitate the construction process though coordination and
communication and not to be a "bad cop" that documents daily infractions. All Owners are urged to ensure
that the CEI staff who are present on-site be structured so that they help the project get completed with
quality, within budget and on time .
. _)'
Chapter 16. 0- Construction Engineering & Inspection of Segmental Construction
llofll
TABLE OF CONTENTS
CONSTRUCTION PRACTICES HANDBOOK FOR
CONCRETE SEGMENTAL AND CABLE-SUPPORTED BRIDGES
CHAPTER 17.0 CONSTRUCTION INSPECTION GUIDELINES FOR
SEGMENTAL CONCRETE BRIDGES
17.1
17.1.1
17.1.2
17.2
17.3
17.4
17.5
3
3
5
7"
8
11
15
17
18
20
21
21
22
23
26
28
29
30
31
33
34
35
36
37
38
40
40
40
I of40
Table17.1
Table 17.2
Table 17.1
Figure 17.1
Figure 17.2
Figure 17.3
Figure 17.4
Figure 17.5
Figure 17.6
Figure 17.7
Figure 17.8
Figure 17.9
Figure 17.10
Figure 17.11
Figure 17.12
Figure 17.13
Figure 17.14
Figure 17.15
Figure 17.16
Figure 17.17
Figure 17.18
Figure 17.19
Figure 17.20
Figure 17.21
Figure 17.22
Measurement of Form
Adaption of Form to Section Changes
Typical Requirements for Form Adjustments
Standard Fabrication Cutting and Bending Tolerances
Example of Poorly Bent Rebar
Requirement for Tight Tolerances
Jig for Fabrication of Rebar Cage
Reinforcing Steel at Post-Tensioning Anchors
Handling of Prefabricated Rebar Cage
Typical Post-Tensioning Anchorages (Strand Systems)
Plastic Ducts and Grout Vent Connection
Aid for Solving Rebar Conflicts
Tolerances on Anchor Placement
Geometry Control - Reference Hardware and Axes
Casting Cell Survey Control Arrangement
Measuring Equipment
Observations (After Casting)
Three-Dimensional Geometry Control Data Sheet
Casting Sequence for Regular Precast Segments
Handling Segments
Repair of Honeycombed Area
Stacking Segments
4
13
19
3
5
6
9
10
10
12
14
14
16
16
18
20
21
22
23
24
25
27
30
32
33
.)
-
2 of40
'
Plumb
Level
---'"--''---'---~..LI.~Top of rail
-r ----~--
I ~----~-- -r
I I 'I'- ....-1-- I I
I 1_.. -1
1'- I I
.j- ......1
I
--1I
'lf- _.... I
I
I
~ Square
'i---I
-}
I ' - _,J
Inner form
)
~--
3 of40
Table 1
Completed segment tolerance for segmental box girder bridge construction.
(To correlate tolerances, see sketches below.)
Finished segment tolerances should not exceed the following:
Overall depth of segment
y, inch
y, inch
Length of match-cast segment (not cumulative)
I 0.4 mm/m, I in. max. (25 rom)
Y, in. but not greater than + 2 in. per span
Length of cast-in-place segment
%in. (9.5 rom)
Web thickness
%in. (9.5 rom)
Depth of bottom slab
%in. (9.5 rom)
Depth of top slab
1/16 in/ft (5.2. mm/m), % in. max (25 rom)
Overall top slab width
Y, in. (12.5 rom)
Diaphragm thickness
y, in. in I 0 ft ( 1.0 mm/m)
Grade of form edge and soffit
Y. in. (3.2 rom)
Tendon hole location
!4 in. (6.3 rom)
Position of shear keys
\> in. (6.3 rom), per 20ft. (2.0 mm/m), but Jess
Deviation of segment ends from a plane in width
than Y, in. (12.5 rom)
or depth
\> in. (6.3 rom) maximum
Deviation of surface from a plane at any location
measured with a I 0 ft. straight edge
POSmO~OF~
SH~R KEVSLY------l-1------wee
J
-rr~------....~.+T-------------
.,. '-
KEY__....,
J.
OlAPHRAGM
TtiiGKNES$
------~
LONGITUDINAL SECTION
i' j
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
4 of40
Dimensional checks are necessary at the bulkhead side and the matchcast side, as well as in
between. Dimensions of the matchcast and bulkhead sides should be identical. Variations in
dimensions at the two ends may result in mortar leakage, or require large forces on the "old"
segment to close the form which may move the segment out of alignment.
The form should be reassembled as required to revise and verify dimensions of the section for all
variations in web and bottom slab dimensions (see Figure 17.2). Most balanced cantilever bridges
require thickening of the bottom slab, and sometimes thickening of the webs near the pier. For
this reason, forms may have to accommodate several section changes.
Dimensional location of any items attached to the form to secure their position during casting of
concrete, and requiring removal before shipping the forms should be noted.
L-_ _
In sp:m.
Bottomslab thickening
Near pier
17.1.2
Form Operation
The geometry control of precast segmental bridges is based on the assumptions that the soffit of
the new segment is level and bulkhead face of the new segment is plumb or perpendicular to the
soffit (see Figure 17 .I). This should be carefully checked using an instrument and, since the
bulkhead could potentially move each time a segment is cast, should be checked for each new
segment set up.
The "old" segment needs to be placed in a certain position in respect to the form (see Figure 17.3).
After appropriate setting of the "old" segment, the position should be fine tuned to within a 1116
in. tolerance. Mechanisms such as hydraulic jacks or screw jacks are used to accomplish this
adjustment. The position changes to be controlled by such mechanisms are: rotation in the
horizontal plane, rotation in the vertical plane through the bridge centerline, and rotation in the
vertical plane perpendicular to the bridge centerline. In addition, the "old" segment should be able
to move in, and perpendicular to the direction of the bridge centerline.
The seals between the various form panels themselves and between the form panels and the "old
segment" must prevent mortar leakage from the fresh concrete. Such leakage affects both quality
and appearance of the segments. The seals are a major feature of form design and, since they are
usually flexible rubber or neoprene gaskets, they require regular cleaning and maintenance.
Checking of seals is a continuous task during production. Of particular importance is the seal
between old segment and form panels, because the position of the old segment is not fixed and the
seal and form must adapt to the old segment's rotated position. Any movement of the old segment
during closing of the form will cause errors in the bridge alignment.
)
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
5 of40
Use of form oil as necessary to reduce adherence between the form and the segment, particularly
in top slab overhangs. Bond between the vertical faces of the new and old segments is reduced by
generous application of the specified bond-breaker, usually a mixture of soap and talcum powder.
A procedure for bond breaking shall be shown on the segment shop drawings or described in the
Construction Special Provisions to ensure that shear keys and the segment faces are not damaged
during the process of breaking the bond between segments.
Inspection of the forms during castiog of the initial segments should verify that the form allows
for inspection of rebar, post tensioning duct and anchorages as well as other embedded items in
the form. Such inspections mainly relate to clearances, post-tensioning anchor-duct aligmnent,
and embedded item locations. The inspector should be able to enter the form for this inspection
prior to closing the inner form.
For concreting, it is important that the concrete can be brought to its final location without
dropping from a great height and without having to move it with a vibrator. Special chutes, slides
or openings in the top slab form are usually required to place the bottom slab concrete. For
finishing of the deck, it is important that the top surface can be screeded by placing a screed over
the "old" segment and the form bulkhead. The form design should minimize obstructions which
interfere with the use of the screed.
The initial inspection of form operation should verify that the form is provided with access ladders
and safe working platforms with railings all around.
Qld
Uc:=:=:==l-se-'Jim"""'eH.,.,jt
Ra!atfog
in boriznn!al
plane
Adjust segment
length
ii
J----1...---.-j\
\lr
I
Rotation About
Deck .4:
')
.
.
6 of40
VeriJY that the form is clean and that movable parts are oiled and greased as required. Because of
the many mechanical parts used in the form, e.g. for collapsing the inner form and adjusting the
position ofthe "old segment", hardened concrete spills, not properly and regularly cleaned, will
make the form inoperable.
Verify that seals are clean and flexible. Proper functioning of seals in preventing loss of mortar is
essential to production of segments of acceptable quality. It is essential that seals be cleaned daily,
and that any hardened concrete is removed. Seals are usually neoprene and are easily damaged.
They should be repaired or replaced as necessary.
Verify that the form oil approved for use on the project is applied. in accordance with the
manufacturer's instructions.
Check to ensure that the form is adjusted correctly for the segment to be cast. This is particularly
important whenever there is a change in bottom slab or web thickness or other section variation.
Inspect to ensure that recesses, attachments for embedded items, and boles in the bulkhead are set
up properly for casting the next segment. The ouly item that is sure to vary from segment to
segment is the post-tensioning. This variation occurs in both cantilever post-tensioning and
continuity post-tensioning. For this, anchor recesses may have to be removed or added. Holes for
tendon ducts in the bulkhead must be closed or opened. It is very demanding and important that
the contractor and inspector independently check the post-tensioning in each segment. !fan error
is made here, the consequences are very serious.
Check closure of the form around the bulkhead, between the bottom slab form and side form, and
around the "old segmeuf'. Closing the form at bulkhead and at bottom slab form usually does not
present great problems since bolts through the form can exert enough-clamping force to achieve
the seal. Closure around the "old segment" where clamping through the form is not possible, is
more problematic and this is where the effort should be concentrated.
Check the temperature of the form immediately before casting concrete. The combination oflow
slump concrete and forms heated by the sun to high temperatures may cause a condition where the
water in the concrete evaporates as soon as the concrete contacts the form. This leads to an
unsatisfactory surface condition. Forms should preferably be placed under cover from the
weather. Alternatively, the form can be cooled with water prior to casting. Ifthis is done, excess
water must be removed prior to concrete placement, e.g. with compressed oil-free air. Care must
be taken in removing excess water not to remove the form oil.
7 of40
Ensure that the steel has passed all required tests and has been approved for nse on the
project. This indicates that the quality and mill tolerances of the rebar are acceptable.
VerifY that the steel has been properly tagged and that the tags show bar diameter, bar number
and the segment it is intended for. This is the responsibility of the contractor, but should be
checked occasionally by the inspector.
Check reinforcement for cutting and bending tolerances, and reject any reinforcement not
within tolerance.
Unless specified to the contrary, steel will be cut and bent in accordance with standard tolerances
set by CRSI (Concrete Reinforcement Steel Institnte). These tolerances are as shown in Figure
17.4. For straight bars, only cutting tolerances apply. If important, a higher tolerance can be
demanded at additional charge, or alternatively, a lap splice provided. For normal segmental
design, the I" cutting tolerance should be acceptable.
Bends are made around pins which are designed in such a way that the steel is bent to the correct
radius. The radius of bar bends is important and shonld be checked since bars Jose some quality at
bends. If bent, the Joss of quality can be dramatic, especially in case of thicker bars (#6 and up).
Bar bends are also important for the fit of bars. A badly bent bar may not function properly as
demonstrated in Figure 17 .5. The location of bends is also very important as shown in Figure
17.6. The vertical bars shown rarely fit if bent in accordance with the standard tolerances. These
bars should either be made in two sections, or be bent to tighter tolerances at additional cost
Check epoxy coating in accordance with special provisions. Epoxy coating can be damaged
during handling or by field cuttings. Corrosion will concentrate on uncoated areas. For this
reason, damaged areas of the coating must be repaired.
8 of40
.5)
rl
=,./d)
H-plus or
!Binus o. az L.
lor bar sizes
#8
Spiral or circular tie
~md
larger
Tie or stirrup
90{+)or{-)2.5'
tF==~
....
.s
E!
.)
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
9 of40
Correct
Crack
Wrong
Figure 17.5- Example ofPoorly Bent Rebar
tolentnce
1 standard
No tolerance
problem
tolerance
not suitable
l!Jierance
Figure 17.6 -Requirement for Tight Tolerances
10 of 40
Segment dimensions. Inspection for segment dimensions, day to day, will be required on
projects where segments have a lot of variation on the bottom slab, web thicknesses and
length of the overhang. In this case, the template for making rebar cages must allow variable
dimensions and these dimensions should be verified.
b.
Bar diameters. There is no tolerance on the use ofbar diameters. For example, #4 bars cannot
be used instead of#5's and conversely. Aoy deviation in bar diameters should be checked
with the Owner's Engineer
c.
Number and spacing ofbars. The spacing ofbars (center to center distance ofbars in the same
mat) showo on the shop drawings should be within a normal tolerance of I". In some cases
larger tolerances could be allowed; for example, when openings or embedded items prevent
placement of a bar. Table 17.3 provides guidance to the inspector to judge the importance of
accurate rebar placement. Whatever the case, the total number of bars showo in the shop
drawings to be placed in a mat should always be present. Additional bars can usually be
d.
Number of ties. Ties should generally be wire ties uuless the shop drawings indicate the use of
weldable steel, in which case the cage may be sp<?t welded. The number of wire ties is
specified in the standard specifications. Spot welding should always be reviewed and
approved by the Engineer.
e.
Length oflap splices. The minimum length oflap splices is showo on the shop drawings. The
minimum length should be verified in the cage. There is no tolerance on this minimum length,
but lap splices may be longer than required. In case field splices are required, dimensions of
minimum lap splices are provided in Table 17.2.
f.
Number of distance keepers. Guidelines for the number of support chairs for top mats
provided in the standard specifications.
g.
Size of distance keepers. Size of distance keepers is most important since it determines the
cover and therefore the durability of the concrete segment. In addition, it determines the
II of40
Soffits and
outside
surfaces
12 of40
Table 17.2 -Minimum LAP Splice Dimensions for High Strength Concrete
Wi:leht
Arell
0<376
O.ll
4
5
6
7
M~S
Q20
{$00
1.043
1,$1)2
0.31
.62$
.750
r-Z"
Z.644
MO
'0.79
UIO
.815
1.000
1..121!
2' i"
2' -9"
3?--6"
4'-6"
1.27
1.270
-15''
4"-4"'
9
10
2.mo
3AOO
4.303
OA4
P-tr
l'- 0"
f' -.6"
3''
B
r' -,a~
l' -:3!'
r' -1"
2-' -:On
2'--s~
SJ ---8''
:a
J'-2:i>
r;-of'<'
P'-0"
P-0'"
l' -7"
Jl-0"'
P-tr'
v~-o"
l'-_l~
P-1"'
i'- 5"
.2' -7"
~ 6"
l' -6"
l' -ll''
4" 7"
2 o
5' Ill"
7' 5'"
2'-tr
1' 2""
r~.
s~
p J l''
2' 6"
. :l' -2
"'
!"
-.2'~
!'- ltv'
2' .'6''
l-t -.4"
4?
2"
5.'-~
Class ''A"- Low str.ess splice; with no mare than="% are.LA.P spltced.
C/Ql<s "e~ -/(;Ol<'SII'ess ~lice. more than '4 bars are L.4P1Iplieed.
-fligh.lress splice, with no more than If biJJ:sare LAP spliced:
Class "C~ -liigh stresiNif)liee; more lhan I'~ bars are L.4J' spliced:
_)
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
13 of40
Anchor recess
Plan
Slings
14 of 40
The shop drawings show dimensions of the individual pieces and how these pieces should be
assembled. There usually are at least two different tendon sizes, but sometimes more. All sizes
should be covered by drawings and all hardware sizes should be checked. For checking hardware,
the contractor must provide a sample of each item selected from the stockpile on the job.
Wedges and wedge seats for post-tensioning hardware are subject to machine tolerances which are
extremely smalL These tolerances are the responsibility of the post-tensioning materials supplier.
The inspector should limit inspection to obvious details such as length and number of pieces used
to make up the wedge. Bearing plates are sometimes cut.
Tolerances are as follows:
Bearing Plate
Anchor Head
Wedges and Wedge Seats,
Duct Size, galvanized metal
Thickness
Length & Width
Area
Diameter
2%%
3/16"
- 0.0 s.i.
As Bearing Plate
Per Manufacturer
1/16"
Maoy types of anchors are forgings or castings which may have gone drrough a number of
machine operations. The inspector is concerned only with a visual inspection of the surfaces.
Casting errors are normally not visible. The conical surfaces for wedges in aochor head should be
smooth. The wedge should be able to easily slide into it. The anchor head, if aoy, should bear
flush against the bearing plate. The outside surface of wedges should be smooth and cleao and the
inside surfaces serrated over their whole length. At the tip of the wedge, the teeth are usually filed
down for a short distance to ensure that the strand force is distributed over the length of the wedge.
Where the shop drawings indicate that the components should have drilled holes for attachments
of any kind, their presence should be checked.
All post-tensioning hardware and duct material should be stored in a manner so that it will be
protected from corrosion aod entraoce of foreign materiaL Wedges should be stored inside. Duct
material and aochorages should be stored on wooden platforms and protected from the weather.
Ends of ducts should be capped to prevent entrance of foreign material during storage .
.J
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
15 of40
Permanent Cap
-Positive Seal
-Integral Vent
Positive Duct
Connection
Bond
Encapsulation
Positive
Connections
16 of40
)
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
17 of40
, ..
T2
1'5
T4
L
B3
Figure 17.12 -Aid for Solving Rebar Conflicts
18of40
~,)
Placing Bars
T 1 through T3
Functionffolerance
Placing Tolerance
T4, Ts
- parallel to face of
slab I"
w1,W2
- parallel to face of
slab I"
W3,W4
-parallel to face of
slab I"
- parallel to face of
slab I"
)
Bt, B2, B3
maintained.
- parallel to face of
slab I"
R 1 ,R2
- parallel to face of
slab 1"
19 of 40
---~~10~0~====]]ot.2
Sltrpe tole.ra'nce :J: 2%
J/4 ..
20 of40
~'I
Centet-rrne hal:fpins
----"\.
)~ .. /
....-;
. _/
'
- .
C\
21 of40
with a leveling bubble (Figure 17.16(a)). It is not essential, but it is convenient to have a
surveyor's level mounted on the instrument tower to maintain a constant datum.
Elevations in the castiog cell are related to the joint defined by the top of the bulkhead which
should preferably be horizontal and inunovable. (All elevations used to calculate the as-cast
positions are actually relative to each other, with the top of the bulkhead joint as the common
reference).
With most segmental bridges, it is sufficiently accurate to measure the bolt elevations by standing
the leveling staff on the domed bolt head. However, with severe super elevation, it is always
necessary to measure the elevation at the same required distance from the centerline. At Linn
Cove the center puoch marks for length measurements on the left and right bolts were
conveniently used for the elevations by attaching a hardened steel center point to the bottom of the
leveling rod (Figure 17.16(b)).
..)
Chapter 17.0 Construction Inspection Gnidelines for Concrete Segmental Bridges
22 of40
Scale
'/
Spirit leVel
17.9.3
(b) The offsets from the centerline of the cell to the centerline marks previously made on both
ends of the match cast segment (ocl and oc2) and new centerline marks must be made on
each hairpin of the newly cast segment. At the bulkhead, this is placed directly on the
centerline of the casting cell (offset= 0) and at the match cast face, at the same offset as on
the adjacent match cast hairpin (ocl).
(c) The exact length measurement of the newly cast segment at the centerlines of the left and
right elevation control bolts. These are essential to the 3D method. They are made by making
a center punch mark on each of the A and C elevation bolts and taking the lengths between
like bolts on the cast and match cast segments. (i.e. between A and AI and between C and
Cl).
(d) The small distances of the bolts and centerline hairpins from the joints (db and de
respectively). It is to be noted that on some projects, the joints were truly radial and not
perpendicular to the chords of the segments. This has implications for the casting machine
and the derivation of the joint geometiy. See Section 17.10.
A sample data sheet for the recording and processing of observations using the three dimensional
geomelly control system, is shown in Figure 17.18.
23 of40
'
........
..12
Jolnlll
'1112
Bl
'
.I
'
'
~1
:!
....
....
Joint I
'
Loft
11,.
JoJnt,B
Bulkhead
24 of40
Project: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ Date: _ _ _ _ _ _ __
Observing Engineer: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __
THREE DIMENSIONAL GEOMETRY CONTROL PROGRAM INPUT
Rod Reading
Ad Previous
Input Value
BI~
m~
Alpha~
Gamma=
_____
[AI- B] and
[Cl- D]
from previous casting
Alpha~
Gamma~
en~-----
AJI~
de_ _ _.
db-~---
LENGTH (INPUT
A
B
LRM
LLM
LRC
LLC
c
D
AI
All
CI
ocl
oc2
CII
DMI
DM2
DM3
DM4
._ _ __
OUTPUT: Record new Alpha and Gamma for processing next casting:
Alpha~
[AI- B]
Gamma~
[AI- 8] ~
DC3
DC4
DC!
DC2
Left
Cent{!r
Right
Eastings (X)
Northings (Y)
Elevation Z
'.)
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
25 of40
26 of40
In many cases, the top slab is the riding surface. The finishing operation is therefore
important and should be carefully inspected. The top of the slab should be first struck off
either by hand or mechanically. Either a vibrating or rolling screed works well for an
initial pass and leveling. The surface should then be worked using a straight edge from the
bulkhead to the matchcast segment and a light application ofbullfloats to provide a
smooth, even, uniform dense fmish.
Cylinders are broken for each major event.
Check strength for stripping forms
Check strength for segment transport
Check strength for transverse post-tensioning
Check strength for completion of curing
Check strength for 28-day strength
Check strength for spare
Total
I cylinder
I cylinder
I cylinder
I cylinder
3 cylinders
I cylinder
8 cylinders
The cylinder for checking strength for stripping should be stored with the segment under
the burlap placed on the deck. This duplicates early strength results closely. Remove the
cylinder just prior to breaking.
Match-cured cylinder mold or maturity measuring devices may also be used for
measuring early strength.
II
12
27 of40
After casting, segment is to be covered with burlap and kept wet during pre-steaming
period or covered with curing blankets held just clear of the top surface and having no
gaps.
Upon completion of the four-six hour pre-steaming period, the segment is to be steam
cured. Specifications provide the details of the steam curing cycle.
Upon completion of the steam curing cycle, check strength, strip forms and move
segment to "old" match cast position.
While the segment is in the "old" (matchcast) position, continue curing by the
application of an approved curing membrane to all exposed surfuces except the end
joint faces. These should be coated with an approved bond breaking compound which
will also act as a "seal" for curing. Curing may continue in this manner until the
segment is at least 72 hours old and the strength is at least 4000 psi.
When it is in the matchcast "old" position, the segment receives a second curing in
conjunction with casting of the next segment.
After completion of the second steam curing cycle, check strength of old segment. If
the cylinder break is 4000 psi or higher, stop curing. If break is less than 4000 psi,
continue curing in storage until segment is 72 hours old. Curing in storage is by
placing wet burlap on top and hanging over all sides. Burlap is covered with
Polyethelene sheets.
28 of40
2.
Upon removal of inner form and outer form, check webs for casting defects.
If casting defects are present (honeycombing near aochors for example), this is the
most suitable time to determine whether or not the segment will be accepted. If not
accepted, it can be removed and a new one made. If it is likely that the segment cao
be repaired, it should be accepted provisionally subject to acceptable repair.
3.
After removal of forms, break bond between "old" and "new" segments.
Breaking bond is accomplished by the method or process shown on the shop
drawings. This process must ensure separation of the segment without damage to the
keys or the face of the segment.
4.
Inspect joint between the "old" and "new" segment for key breakage.
The keys ensure that the weight of the last segment of a caotilever will be carried by
the caotilever. Generally, the margin of safety allows a small percentage of the keys
to be broken. Guidelines for the extent of the damage permissible to keys should be
submitted by the contractor and approved for use. It is not recommended that keys are
repaired prior to erection. Any repair made to the matchcast surfaces will lead to
fitting problems aod usually to severe spalling upon erection. The better practice is
therefore to establish a guideline for acceptable key breakage aod make the repair
after erection.
5.
..)
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
29 of40
2.
The inspector must verify that the required concrete strength for handling is
achieved. The concrete strength required for lifting the segments is provided in the
special provisions. If not, it should be proposed by the contractor and approved for
use.
3.
The inspector must verify that that the lifting frame is safely attached to the
segment. These attachments are generally bolts (Fignre 17 .20) which go through the
top slab. These bolts shouid be evenly torqued. For lighter segments lifting loops are
sometimes used. These loops should bear evenly against the pipe or dowel passing
through the loops. Lifting loops should be placed with a template prior to casting to
ensnre this. C hooks shonld be carefully positioned with the lifting line in the center
of gravity of the segment. If used, the contractor submits this location for each
different segment type and the inspector should verify that it is placed properly.
Turnbuckles or
jacks for control
of crossfall
C-flook
hardwood packs to
a void damage to
corners when lifting
with slings.
Shim
Profiled shim
30 of40
The appearance ofthe repair concerns color and surface finishing. Since most repairs are
darker than the surrounding concrete, it is best to make trial mixes of the mortars proposed for
repairs at the time of approval so that color differences can be judged. These trial mixes
should be made before they are needed. Much skill is required for making good looking
repairs. Part of the procedure submitted by the contractor should be names and qualifications
of the person(s) making the repairs.
Durability of repairs is determined by the quality of the repair material and the bond of the
repair material to the old concrete. Bond is determined by surface preparation, type of binding
agent and method of filling the void. The different types of voids require treatment. Figure
17.21 shows repair of a hole in the web which can be effectively repaired, more easily than
surface damage. Other issues to be addressed are curing and shrinkage of the repair.
Structural adequacy is determined by the location of the void in the structure. Segmental box
girders are often over-designed. The high concrete strength of5500-6000 psi is usually only
needed in the support area (bottom slab and webs) and in post-tensioning anchor zones. In
other areas, it ensures a high quality and durable product. Therefore, repairs may often be
judged by their durability rather than by structural adequacy. Structural adequacy is generally
assured by the composition of the repair mix. This mix should have adequate strength, and it
should be a concrete mix. This means that it should depend on cement aud not on an epoxy
resin or similar material for strength. Such materials are strong but also more elastic than
concrete and cannot therefore always perform a structural function.
B. Repair of Cracks. Most cracks over a certain size are repaired by epoxy injection. This is
.. J
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
31 of40
C. An inspector should be present while a repair is being made. Any defect discovered in a
segment will be cause for delays, costs, meetings, etc. All are reasons for a well-meaning
superintendent to cover up the defect before it is discovered. This is uoacceptable practice.
Repairs thus made should be removed and redone in the presence of an inspector. The
inspector should also be present when forms are removed from a segment so that he has frrst
hand information about defects when these occur.
D. The inspector shonld ensure that no repairs extend into the joint faces. Repairs of joint
faces and shear keys should not be made. If defects occur in the joint faces, the repair should
be postponed until after the erection of the segment. Any doubt about feasibility of repair of
voids or cracks should be resolved by consultation between the Construction Engineering
Inspector and the Construction Engineer.
3:1 Slope
Wrong
1-Piece
form
Form designed
for 1:2" !ills
Figure 17.21 -Repair ofHoneycombed Area
32 of40
location and tolerances. A tolerance of 1" on size of support blocks and 2" on their location
should be workable.
\'-=!=;._,...;
I '-
deflection
Suppart
Pli!~ed
Corz7Jct
')
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
33 of40
Segments should have a uniform appearance. This means even color and few or minor surface
defects. The most common surface defect is that caused by air bubbles. This occurs when
plywood or steel forms are used but seems to be somewhat controllable. If size (more than
1/2" diameter) and number are such that the quality of the segment is clearly affected, the
bubbles have to be sealed in accordance with an approved repair procedure.
Generally the bond breaker will adhere to the joint faces and will have to be removed by very
light sandblasting. The sandblasting also should remove the laitance. Thus, the epoxy will be
applied to strong material and will provide an excellent bonded joint with high tensile
strength. The sandblasting should be as light as possible to achieve this. Strong sandblasting
can remove too much material which would reduce the fit obtained with the matchcasting
procedure.
Ducts should be checked for alignment and cleanliness and anchors and recesses for presence
of mortar. Recesses should be cleaned out so far that the jack will fit into it. Anchors should
be entirely free from mortar.
The segment should be checked for cracks, spalls, damage to keys and repairs including
repairs on matchcast faces.
Any defect should be repaired in accordance with the approved repair procedure, and the
repair should be approved before payment for the segment is made.
The 28-day strength of the segment should be checked. If the 28-day strength is not achieved,
it should be decided whether or not to accept the segment.
:)
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
34 of40
35 of 40
The erection manual will indicate the type of equipment the contractor proposes to use. Usually
this will be cranes. The manual will describe lifting capacity of the crane at the maximum boom
required and where the crane will be placed.
In case of crane erection, erection manuals will be simple documents indicating erection
sequences, descriptions of basic operations, geometry control data and stressing data. In case of
erection methods using special equipment such as erection trusses, launching girders or gantry, the
erection manual will be more complicated. Inspectors should, however, not be asked to work with
erection manuals too complicated to implement, inspect or even understand. For an example, an
erection manual describing movement of a launching girder in 30 steps, each of which can lead to
problems if not executed correctly, should not be approved for use. In any case, the steps should
be clear.
The rated lifting capacity of the crane assumes that the crane has a firm place to stand, outriggers
can be placed properly and boom will not be exceeded.
The inspector should ensure that any custom designed equipment used for the project has been
inspected by inspectors qualified to perform such inspections. The inspection of special
equipment should be performed by qualified persons. The inspector should be familiar with
cranes, welds, or bolted connections as dictated by the erection equipment.
The inspector should verifY that there is an operation manual for custom designed equipment.
Since neither the designer nor the fabricator of the equipment will operate it, a comprehensive
manual is required for this. The manual should be understandable to the operator. The manual
should preferably not only address how to operate the equipment correctly, but also what can go
wrong. Especially in case of heavy equipment, it is very important that operations are simple.
The inspector should verifY that a test load program of the equipment has been planned and that
this program is implemented. This test loading program should be designed in such a way that all
operations are tested, not only lifting but also moving the equipment in both loaded and unloaded
conditions.
The inspector should ensure that the circumstances assumed for operation of erection equipment
are in fact, existing in the field. In some known cases, equipment failed during test loading or first
use. Often the reason was that design assumptions were not in agreement with field conditions.
The inspector should ensure that that the equipment operator is experienced in accordance with
project requirements, and is instructed to transfer loads from equipment to structure gradually.
Sudden release of the segment from the crane will magnify the effect of the segment weight and
will apply forces to the structure it has not been designed to support.
)
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
36 of40
17.19
Ensure that falsework is built from approved plans. Falsework used for construction of
segmental bridges is subjected to heavy loading. Consequences of a failure can be disastrous
and the design for such falsework should therefore be prepared with the same care as the
bridge plans themselves. There should be a good set of drawings supported by calculations.
Construction of the falsework should be inspected. A good guide for the design and inspection
of falsework is the "California Falsework Manual" available from Caltrans.
2.
Ensure that the plans indicate assumptions for subsoil conditions and seek evidence that
these assumptions are met or exceeded in the field. Usually falsework is supported on
spread footings so subsoil conditions come into play. Geotechnical advice is required to both
ascertain safe bearing capacity as well as predicted settlements. Predicted settlements are
needed in order to be able to set the elevation of the top of the falsework. A tolerance for
settlements must be provided in the plans. If exceeded, the falsework designer must be
notified.
3.
Check that the falsework is erected in accordance with the approved plans. Also have the
designer of the falsework inspect it. In case of specialty systems, ensure that the manufacturer's erection instructions are being followed. Because of the temporary nature of the work,
falsework plans are sometimes not treated with the same care as bridge plans. In addition, the
contractor often substitutes joist sizes and modifies the plans as he sees fit. This practice has
been the cause of serious failures. Inspection of the falsework by the designer should make
the contractor aware of his responsibilities. Erection of specialty systems requires strict
adherence to manufacturer's instructions. Inspection of the erection by a manufacturer's
representative should provide the necessary assurances.
4.
Monitor the falsework while it is being loaded and at regular intervals after it has been
loaded. When the falsework is being loaded, check for excessive member deflections and
shifting of members. Monitor jacks. Use an instrument to check settlement of footings. In case
the falsework is to be in service for a long time, monitor the condition of the falsework and
the settlement periodically.
5.
Check that elevations of the top of the falsework are as required and ensure that
anticipated settlements are taken into account. Footing settlements cause the final
elevations to be lower. It is a good practice to estimate beforehand the amount of settlement
expected and compensate for this in setting the elevation of the top ofthe falsework. Such
estimates are made by geotechnical engineers and should be provided on the plans.
6.
37 of 40
Ensure that the epoxy resin is approved for use on the project. The Special Provisions
require completion of several tests to be made on the epoxy resio. The approved epoxy will
have passed these tests.
2.
Ensure that the contractor is implementing the safety recommendations from the
supplier. Containers with epoxy resin carry warnings regarding toxicity of the materials and
iostructions in cases of emergency. The contractor should point out the hazards to the workers
and should have the required supplies available on site in case of an emergency.
3.
Ensure that a supplier's representative is present at the time of first use on the project.
The consequences of errors made in mixing, application and removal of epoxys are costly and
generally unnecessary. The presence of a manufacturer's representative thoroughly familiar
with the product pays off, and the inspector should insist on it. For maximum benefit, all
persons working with the material should be present at this first application.
4.
If there are several types of epoxy on the project, ensure that labeling is such that they
cannot be interchanged. Epoxy resins must be formulated specially for a variety of
conditions. The ambient temperature is most important. An epoxy resin formulated for use in
cold weather would set ahnost immediately if used in warm weather. Reversely, an epoxy
resin formulated for hot weather would cure only after a long time if used in cold weather.
Since weather conditions vary, epoxy resin suppliers formulate their product for a particular
weather condition and if erection over several seasons is anticipated, there will be several
formulations supplied. These should be kept apart.
5.
Ensure that the two components of the epoxy are properly mixed. Epoxy consists of a
resin and a hardener, often referred to as components A and B. As long as these are kept
separated, the resin will not set. In order to function as designed, the two components A and B
must be very thoroughly mixed. If not, the resin will not set. Improper mixing has been the
cause of high repair costs. Good mixing is generally ensured by:
(a) Using manufacturer1s recommended equipment in accordance with manufacturer1s
instructions.
(b) In addition to the above, using different colors for components A and B. If the color of
the mix is uniform, the resin and hardener are properly mixed.
6.
Ensure that pot life and open time requirements are adhered to. Although there is a
certain safety range, one should understand that epoxy will bind and cure only if used within
these specified time limits.
7.
Ensure that joint faces are properly prepared. A good bond of the epoxy to the concrete is
only achieved if the joints are dry and clean.
(a) Dry is usually defined as "absence of surface water". This means that epoxy cannot be
used when it rains. Also, after a rain, the joints should be dried off (preferably with a
moderately hot torch).
(b) Clean means that the joint has been lightly sandblasted to remove cement paste and bond
breaker and that subsequent soiling is removed by wire brush.
38 of40
')
...
8.
Ensure that conditions for use of epoxy are met. The conditions for use of epoxy are
humidity (see item 7) and ambient temperature range as prescribed by the manufacturer
and/or specifications.
9.
Ensure that the epoxy is properly applied to the joint faces. Usually the Special
Provisions indicate the amount of epoxy per square foot of joint or the average thickness of
the layer, also whether or not the epoxy has to be applied on one or on two faces. Epoxy needs
to he placed in between tendon ducts so that a seal is formed at each duct which should prevent grout from crossing over into ducts other than the one being grouted. Usually workers
apply epoxy with a gloved hand. Though primitive, this is a most effective method.
10. Ensure that excess epoxy is removed from exterior joint faces. Since epoxy is applied to
the joint in a much greater quantity than required for filling the joint, much of it will be
squeezed out upon applying the temporary prestress. This excess forms a bead at the joint
faces, on both the inside and outside of the box girder. On the inside, this bead is usually left
in place. On the outside, however, this is unsightly and treatment is necessary. Treatment first
of all means that the outside should be accessible for work and inspection.
The treatment can consist of removing the epoxy with a tool as long as it is soft. This will
leave a mark accentuating the joint. In case the box will receive a surface treatment, this is the
simplest way to remove the epoxy bead. Alternatively, the epoxy can be removed without
leaving marks by chiseling it off after it hardens. This, however, is more time consuming.
11. Ensure that excess epoxy is cleaned from tendon ducts. As epoxy beads form on the
outside, the same occurs at the tendon ducts. Squeezed out epoxy will enter the ducts. This
epoxy is removed by inserting a brush with a long handle into each duct. This is done
immediately after applying the temporary post-tensioning and releasing the segment from the
crane.
12. Ensure that the curing process is being monitored. Epoxy will perform its function, which
is to provide tensile strength at the joint and seal the joint from moisture penetration, only if it
is cured. Normally the epoxy will cure, but on occasion, a bad batch or badly mixed batch will
not set. In order to monitor this, simple field tests have been devised such as gluing a small
concrete test cube against the inside of the box with the epoxy used for the joint. The next day
a firm blow with a sledge hanuner will either fail the epoxy or the concrete. Although not
very scientific, this "test" surely indicates whether or not something is obviously wrong.
The special provisions may prescribe tests to be performed on the epoxy during erection. Such
tests usually apply to the strength ofthe epoxy.
If, for some reason, a segment cannot be erected and epoxy has been applied to the joint faces,
the epoxy must be removed. In order to avoid delays, the contractor should submit a procedure for this for approval. The usual procedure consists of:
(a) Scraping off as much of the epoxy as possible while it is still soft.
(b) Bum off the remainder with a low heat torch.
(c) Sandblast the joint to thoroughly clean the joint.
13. Ensure that tests prescribed by the Special Provisions to be performed during erection
are made.
14. Ensure that there is an approved procedure for removal of epoxy from joint faces.
"J
Chapter 17.0 Construction Inspection Guidelines for Concrete Segmental Bridges
39 of 40
the work depends on the concrete achieving early strength. Post-tensioning generally occurs long
before the concrete achieves design strength and post-tensioning anchor sizes may have to be
adapted for use with lower strength concrete. The sequence of segment concreting has to be
40 of40