You are on page 1of 3

ATP Calculations

Currently there are two types of availability checks active in the


production Z2 & Z3
-

Stock types considered for ATP calculation

B & C will be considered (in case of external)


F & C will be considered (in case on in-house)

In case on externally procured material Planned delivery time


and GR processing time on MRP2 tab are considered in
calculating stock

In case of internally manufactured material Total Replenishment


Lead Time on MRP3 tab is considered in calculating stock.

Example 1:
Material XXXX has Z2 availability check, procured externally, and has
planned delivery time of 10 days and GR processing time of 1 day.
Case -1: SO received today 03/21 with requested delivery date of 03/25
and quantity 10 EA
Calculation:ATP checks stock type C and B as
Today date
03/21
+
Planned delivery time
10 days (calendar days)
+
GR processing time

1 day (work days)

ATP checks stock position till 04/01 and confirms the order.
Let us assume the following is the stock position
Stock type C
5 EA
Stock type B
20 EA(Delivery date on PO
04/01)
ATP stock will show stock

25 EA

Confirmation date is proposed based on pick-pack time and


routing (factory calendar).
Case -2: SO received today 03/21 with requested delivery date of 03/25
and quantity 50 EA
Calculation is the same as above in case -1 i.e. 25 EA
There will be a change in the confirmation dates as

Quantity
03/25
Quantity
-

25 EA
25 EA

Confirmation date
Confirmation date

04/01

Example 2:
Material XXXX has Z2 availability check, manufactured in house, and has
total replenishment lead time of 10 days.
Case -1: SO received today 03/21 with requested delivery date of 03/25
and quantity 10 EA
Calculation:ATP checks stock type C and F as
Today date
03/21
Tot. RLT
10 days (work days)

ATP checks stock position till 04/04 and confirms the order.
Let us assume the following is the stock position
Stock type C
5 EA
Stock type F
20 EA(Delivery date on Prod.
Ord. 04/01)
ATP stock will show stock

25 EA

Confirmation date is proposed based on pick-pack time and


routing (factory calendar).
Case -2: SO received today 03/21 with requested delivery date of 03/25
and quantity 50 EA
Calculation is the same as above in case -1 i.e. 25 EA
There will be a change in the confirmation dates as
Quantity
25 EA
Confirmation date
03/25
Quantity
25 EA
Confirmation date
04/04

Example 3:
Material YYYY has Z3 availability check, manufactured in house, and has
total replenishment lead time of 10 days.
Case -1: SO received today 03/21 with requested delivery date of 03/25
and quantity 10 EA
Calculation:ATP checks stock type C and F as
Today date
03/21
Tot. RLT
10 days (work days)

+
+

ATP checks stock position till 04/04 and confirms the order.
Let us assume the following is the stock position
Stock type C
5 EA
Stock type F
20 EA(Delivery date on Prod Ord
04/01)
ATP stock will show stock

25 EA

Confirmation date is proposed based on pick-pack time and


routing (factory calendar).
Case -2: SO received today 03/21 with requested delivery date of 03/25
and quantity 50 EA
Calculation is the same as above in case -1 i.e. 25 EA
There will be a change in the confirmation dates as
Quantity
25 EA
Confirmation date
03/25
Quantity
25 EA
Rejected with J0

You might also like