STEFFI G.

SICLOT

ACTIVITY

Page 1
WEEK 1

DURATION
D1

Lead Time
Clear The Site
Fencing The Site
Mobilization
Construct Temp. Site Office
Purchase Of Materials
Lay-Out And Scaffolding
Footing Excavation
Re-Bars Preparation And Formworks

18
1
1
2
1
2
1
2
3

Concreting Of Footing

Bending And Install Column Rebars


3
Formwork For Columns
Concreting Of Columns
Bend And Install Of Beam And Girders
Install Beam Forms
Install Second Slab Formworks

2
4
4
3
3

Bend And Install 2nd Flr Slab Rebars


4
Roughing-In (Electrical)
Roughing-In (Plumbing)
Concreting Beams Girders And Slab

3
4
7

D2

D3

D4

PROFPRAC 3

WEEK 2
D5

D6

D1

D2

D3

D4

WEEK 3
D5

D6

D1

D2

D3

D4

WEEK 4
D5

D6

D1

D2

D3

D4

WEEK 5
D5

D6

D1

D2

D3

D4

D5

D6

STEFFI G. SICLOT
Remove Column Formwork
Install 2nd Floor Wood Girders
Install 2nd Floor Wood Joists
Install Roof Framing And Roof
Rafters/Trusses

Page 2

2
3
2
4

Install Perimeter 2nd Flr Wood Studding


4
Install 1st Floor Hollow Block Wallings
3
Install 2nd Flr Partition Framing
Install Purlins, Facia Boards
Lay-Out Roofing Sheets
Install Gutters, Flashing, Riderolls, And
Valley Gutters

Install Window Jambs


Install Door Jambs
Install Outside Walling (1"x6" V-Cut)

2
3
4

4
4
4

Install 2nd Flr T&G Floor


Install 2"x2" Ceiling Joints
Install All Plywood Panels
Install All Ceiling Boards Are Outside
Eaves

4
3
5
3

PROFPRAC 3

STEFFI G. SICLOT
Grade And Gravel Fill (1st Flr)
Concrete Of 1st Floor Slabs
Plastering Of CHB (1st Floor Wall)
Lay-Out Of Fire-Place Form And Concreting
Works

Page 3

1
6
6
3

Fabrication & Installation Of Wooden Stair

7
Install All Panel And Flush Doors
Install Windows Aluminum Framing
Install Window Glass & Screens
Lay-Out & Installation Of Tiles For Toilets,
Floors, Kitchen Counters

3
2
3

Fabricate Kitchen Cabinets & Bedroom Closets

9
Finishing All Other Floorings Vinyl, Wood Tiles,
Granulithic, Wash-Outs, Etc.

Install Lighting Fixtures, Etc.


Install All Plumbing Fixtures, Etc.
Install All Finishing Hardwares
Start Of Painting Works (Interior)
Start Of Painting Works (Exterior)

3
4
3
5
5

PROFPRAC 3

STEFFI G. SICLOT
Remove All Scaffolding, Rebars, And
Clean-Up

Secure Certificate Of Occupancy


Moving-In

Page 4

1
1

PROFPRAC 3

STEFFI G. SICLOT

Page 5

WEEK 6
D1

D2

D3

D4

WEEK 7
D5

D6

D1

D2

D3

D4

WEEK 8
D5

D6

D1

D2

D3

D4

PROFPRAC 3

WEEK 9
D5

D6

D1

D2

D3

D4

WEEK 10
D5

D6

D1

D2

D3

D4

D5

WEEK 11
D6

D1

D2

D3

D4

D5

WEEK 12
D6

D1

D2

D3

D4

D5

W
D6

D1

STEFFI G. SICLOT

Page 6

PROFPRAC 3

STEFFI G. SICLOT

Page 7

PROFPRAC 3

STEFFI G. SICLOT

Page 8

PROFPRAC 3

STEFFI G. SICLOT

Page 9

WEEK 13
D2

D3

D4

D5

WEEK 14
D6

D1

D2

D3

D4

D5

WEEK 15
D6

D1

D2

D3

D4

D5

WEEK 16
D6

D1

D2

D3

PROFPRAC 3

STEFFI G. SICLOT

Page 10

PROFPRAC 3

STEFFI G. SICLOT

Page 11

PROFPRAC 3

STEFFI G. SICLOT

Page 12

PROFPRAC 3