Professional Documents
Culture Documents
Table of Contents
1. Preface .......................................................................................................................................... 3
2. Introduction ................................................................................................................................ 4
3. Standard Operating Practices SOPs .............................................................................. 6
3.1 Components ........................................................................................................................... 7
3.2 References .............................................................................................................................. 7
4. Risk Management ..................................................................................................................... 8
5. Work Over Rig Summary................................................................................................. 11
6. Equipment ................................................................................................................................. 13
6.1 Rig Carrier Chassis ......................................................................................................... 13
6.2 Diesel Engine........................................................................................................................ 16
6.3 Mud / Slush Pump .............................................................................................................. 20
6.4 Draw Works .......................................................................................................................... 23
6.5 Crown Block .......................................................................................................................... 25
6.6 Travelling Block ................................................................................................................... 27
6.7 Hook Assembly .................................................................................................................... 29
6.8 Swivel...................................................................................................................................... 31
6.9 Rotary Table ......................................................................................................................... 33
6.10 Mud Agitator ...................................................................................................................... 35
6.11 Air Compressor ................................................................................................................. 37
6.12 Centrifugal Pumps ........................................................................................................... 40
6.13 Transmission (Allison) .................................................................................................... 42
6.14 Hydro-Matic Brake ........................................................................................................... 44
6.15 AC Generator ..................................................................................................................... 46
6.16 Electric AC Motors............................................................................................................ 50
6.17 Pneumatic / Hydraulic Winch ...................................................................................... 54
7. Annexures ................................................................................................................................. 56
Version 1, June-2014
Page : 1
Version 1, June-2014
Page : 2
1. Preface
ONGC is a capital intensive organization having Plant and Machinery Assets of more than
Rs.67000 Crores. ONGC stands as No.1 E&P Company of India with its operation in various
parts of the country and in other countries through OVL. The management of this large
volume of capital asset demands an effective and efficient Equipment Management System
in place. The Equipment Management includes planning, procurement, operation,
maintenance, overhaul, health, performance and finally its reliability, safety and discards of
equipment. A systematic approach to equipment management (Inception to Discard) finally
results in an effective equipment life cycle management.
ONGC a MAHARATNA has been managing a large number of equipment at its installation
spread across various parts of India with qualified executives managing operation and
maintenance to a global level. ONGC with its foresight to effectively manage its equipment
set up Directorate of Equipment Management in the year 1982 and presently being
referred as Technical Services since 2004.
Technical Services as a service provider, is responsible for the effective Equipment Life
Cycle Management by framing norms, policies and guidelines for equipment maintenance &
replacement. Primarily, these include Technical & Energy Audit, up-gradation of technical
skills, and standardization of specifications, quality assurance services, failure analysis and
promotion of creative and innovative skills.
A step forward with objective to meet global standards, Technical Services is introducing
Standard Operating Practices (SOP) to upgrade present equipment management system.
Version 1, June-2014
Page : 3
2. Introduction
EQUIPMENT MANAGEMENT was instituted in the year 1982 and has been instrumental in
bringing out approved norms, policies and guidelines for equipment operation, maintenance,
overhaul, replacement and numbers of equipment requirement as stand by for
uninterrupted operation. The equipment management in any organization starts from
purchase equipment to its disposal, the period in between includes its operation &
maintenance. The function in brief is projected by the sequence as under.
ONGC being a large organization with work centres referred as Assets, Basins & Plants,
located across various parts of the country, the function of equipment life cycle
management also becomes part of Work Centres. Technical Services, being a service
provider in the organization, is assigned with role of providing guidelines for primarily
managing equipment life. This function is achieved by different arms of Technical Services.
As per image above, all the functions are part of Work Centres operating the equipment. At
organization level, the preventive maintenance and overhauling requirement are centralized
through application of SAP Module. The SAP Module has been updated with equipment
preventive maintenance program and overhaul program based on fixed periodicity &
operating hours. The details of spares of equipment (Bill of Material), consumption for
preventive maintenance & overhauling are also part of this module to provide support for
the installations and Work Centres to monitor actions carried out and to be carried out.
Version 1, June-2014
Page : 4
Version 1, June-2014
Page : 5
SOPs ensure Equipment and personnel safety through compliance with recommended
procedures, guidelines issued for
1. Equipment installation as recommended by manufactures / suppliers.
2. Equipment start-up checks / steps for starting.
3. Equipment Operations including monitoring of operating parameters and taking
corrective action in case of deviations.
4. Preventive maintenance activities as per approved/ recommended schedule.
5. Equipment Overhaul to restore/ maintain equipment health, efficiency, reliability
and performance.
The equipment health, efficiency, reliability, safety and performance depend on its
condition. If equipment is operated within recommended limits of load and operating
parameters, it shall result in higher availability & reliability during its complete lifecycle.
The scope of this manual is to issue STANDARD OPERATING PRACTICES for equipment
and personnel safety covering all aspects of equipment lifecycle, from its installation to
disposal.
For all equipment, however big or small, the OEM/ OES issues a manual covering guidelines
and procedures for equipment pre start checks, operation and maintenance. In a single
document, the Operating Practices shall cover all areas of equipment management including
equipment installation, pre-start, operation, preventive maintenance, overhaul, safety and
regulatory requirements.
Version 1, June-2014
Page : 6
3.1 Components
a.
b.
3.2 References
a. ONGC Norms, Policies and Guidelines circulated by Technical Services or any other
authority /agency.
b. Original Equipment Manufacturer (OEM) manual / guidelines of operation,
maintenance & overhauling and safety requirement during equipment maintenance.
c.
d.
e.
f.
Version 1, June-2014
Page : 7
4. Risk Management
ONGC has rolled out a structured risk management process across the organization. All
SBUs (Assets, Basins, Plants, Institutes and Select Services) are aware of the risk
management process. Risk owners, risk controllers and risk coordinators have already been
nominated at all SBUs and risk register is being filled up on quarterly basis.
The risk identification, categorization, assessment and mitigation plan across the life cycle
of all equipment has to be worked out for every installation, i.e. drilling rig/ work-over rig in
association with identified stakeholders. The risks so identified must then be maintained as
a risk register for "Onshore drilling rig/ work over rig equipment".
The risk can arise from:
OIL & NATURAL GAS CORPORATION LIMITED
RISK REGISTER - SERVICES
Work Centre
Asset, Basins
Risk Description
Equipment failure
Root causes
Wrong
Selection
equipment
Mitigating Factors
of
Statutory requirements
not met
Improper
equipment
specification
and
operating instructions
Improper
installation
equipment
Inadequate preventive
maintenance
Delayed
Overhaul
Equipment
Inadequate Equipment
Protection
Version 1, June-2014
Remarks
Page : 8
RISK CONTROLLER
RISK OWNER
RISK ORIGIN
HEAD - SBU:
UNIT LEVEL
UNIT LEVEL
RISK OWNER
RISK CONTROLLER
Version 1, June-2014
Page : 9
Version 1, June-2014
Page : 10
Version 1, June-2014
Page : 11
ROM-UPET 100
A 50
10
IR 750
ROM-UPET - 50
Total
15
Version 1, June-2014
1
7
10
IR 500
BHEL - 120
8
1
8
1
10
Total
Tripura Asset
Assam Asset
Karaikal Asset
CW 50
Cambay Sub-Asset
Ankleshwar Asset
CW 100
Mehsana Asset
Type of Work
Over Rig / Work
Centre
Ahmedabad Asset
5
1
1
11
9
1
53
Page : 12
6. Equipment
6.1 Rig Carrier Chassis
The Work-over Rigs are carrier / chassis mounted for easy mobility so that it can be
deployed at any location as per operational requirement. For smooth operation as well as
relocation, maintaining rig carrier is equally important. A rig carrier may have the complete
chassis, suspension, transmission, power take-off, gear box and engine to drive.
INSTALLATION
The Work-over Rig unit is completely made ready for use by the rig manufacturer. The
chassis is mounted with desired equipment and other systems as per rig make, design and
capacity. There is no separate installation of the unit except as under
1. The rig carrier is deployed at the location to carry out work over operation.
2. It shall be correctly aligned with the oil well to be used for carrying out the operational
process.
3. The correct positioning, jacking up the carrier, levelling, raising the rig mast and
making the rig ready for operation shall be carried out as per manufacturer
recommendations and procedure outlined.
START UP CHECKS
Start-up checks are required to be carried out when the carrier is to be relocated. Before it
is moved the desired checks are
1. Carrier engine instruments are functional.
2. Air system pressure maintained as per recommendations.
3. Lube oil in power steering system.
4. Lube / brake oil up to indicated level.
5. Lube oil level and condition in Gear box.
6. Lube oil level and condition in transmission system, if applicable.
7. Radiator water level / coolant if recommended.
8. Fuel level in fuel tank.
9. Greasing of suspension bearings / pins / springs.
10. Greasing of wheel bearings, if applicable.
11. Checking of air pressure in wheels.
12. Checking and greasing of steering system.
Version 1, June-2014
Page : 13
Version 1, June-2014
Page : 14
Version 1, June-2014
Page : 15
Version 1, June-2014
Page : 16
Lube oil analysis including wear debris analysis. (Refer Equipment Health checkup for drilling & work over rigs issued by Technical service).
Version 1, June-2014
Page : 17
OVERHAUL
Engine is subjected to deterioration of its components during operation and need to be
replaced at scheduled interval. Engine health and performance can be restored by overhauls
that depend on operating hours. It may be
1. Top Overhaul It may include replacement of cylinder head components such as
valves, valve inserts, piston rings, cleaning of radiator/Heat exchanger, testing and
calibration of injectors etc.
2. Average Overhaul It includes top overhaul and additionally piston, cylinder heads,
bearing and other components of cooling water pump, lube oil pump and inspection
of bearings.
3. Capital Overhaul It includes average overhaul and additionally replacement of all
bearings, inspection of crankshaft & resize of bearing to next size if required,
cleaning / replacement of heat-exchangers, replacement of injectors, replacement of
lube oil and water pump components.
SAFETY SYSTEM
Safety system on an engine is provided to caution operation to take corrective measures in
case of deviation in its operating parameters and to protect engine from damage & failure.
The safety system is provided with alarm system and engine shut down system. The
parameters monitored and included in system are 1. Lube oil: - Low pressure alarm & shut down.
2. Lube oil temperature: - High temperature Alarm & shut down.
3. Cooling system pressure: - Alarm & shut down.
4. Cooling system temperature: - High temperature Alarm & shut down.
5. Engine high Vibration alarm.
6. Lube oil low level alarm.
7. Engine over speed alarm & shut down.
8. To carry out any maintenance activity the work permit shall always be taken as per
organization policy / guidelines.
ENVIRONMENT & EMISSION CONTROL
1. Used lube oil, filters and other components if not disposed properly may damage the
environment. The guideline has been provided to return these items to designated
locations (Stores) for further disposal action. (Refer guidelines for storage, Handling
and Disposal of Lubricants issued by Technical service).
2. Similarly measurement of engine exhaust is to be carried out for complete burning of
fuel and to monitor contents of CO, CO2, SO2, NO2 etc. The central pollution control
board (CPCB) has issued guidelines for emission parameters depending on the
Version 1, June-2014
Page : 18
Version 1, June-2014
Page : 19
Version 1, June-2014
Page : 20
performance
by
timely
inspection
and
preventive
3. Securing discharge hose connections with metallic chain / wire to prevent injury in
case of hose failure.
Version 1, June-2014
Page : 21
Version 1, June-2014
Page : 22
Page : 23
2.
Timely inspection and adjustment of brake, clutch assemblies & Equalizer beam.
3.
4.
5.
Wire rope used for draw works shall be of correct size and configuration.
6. Wire ropes / manila ropes used for other applications such as material handling,
connection / de-connection of string assembly using cathead system shall be of
recommended size and shall be replaced if found damaged.
7.
8. To carry out any maintenance activity the work permit shall always be taken as per
organization policy / guidelines.
ENVIRONMENT CONTROL
The consumables / used components shall be disposed at designated places only or
returned to stores for disposal as per approved guidelines / regulatory requirements.
STATUTORY / REGULATORY PROVISIONS
Any guidelines, norms issued for safe operation, maintenance by OEM and/ or regulatory
agencies shall be followed. Reference to some of the guidelines / regulations issued by
statutory agencies is enclosed as annexure.
Version 1, June-2014
Page : 24
Version 1, June-2014
Page : 25
Version 1, June-2014
Page : 26
Version 1, June-2014
Page : 27
Version 1, June-2014
Page : 28
Version 1, June-2014
Page : 29
Version 1, June-2014
Page : 30
6.8 Swivel
The swivel is connected to hook and facilitates rotation of string assembly during work-over
operation. The high pressure hose to circulate mud is also connected through the swivel. It
is an equipment of hoisting system.
INSTALLATION
Swivel is not rigidly installed and is one of the moving hoisting equipment. Since the
equipment cannot be repaired at its location, the health of equipment shall be ensured at
the time of installation. It is stacked at derrick floor after connection with mud pump hose
and Kelley and is connected to hook as required for carrying out work-over operation on the
well.
START UP
Replacement of lube oil of appropriate grade and greasing of its moving joints / connections
shall be carried out before start up at new location. The wash pipe assembly provided in
swivel to support mud connection and to allow rotation without any mud leakage shall be
checked greased and components replaced before start up. The condition of oil seals at top
& bottom shall also be checked for any leakage.
OPERATION
The swivel is not provided with any driving equipment as it is one of hoisting equipment and
is used for providing rotation support and mud flow support of string assembly.
PREVENTIVE MAINTENANCE
The preventive maintenance activities are
1. Periodic replacement of lube oil/oil seals (both at Top & Bottom) as per schedule.
2. Greasing of hook hinge / moving connections.
3. Check wash pipe integrity for swivel.
4. Greasing of wash pipe seal / packing assembly.
5. Replacement of wash pipe assembly and its seal assembly.
OVERHAUL
Overhauling is replacement of bearings and other components as required. It may be
depending on condition / operating hours as per OEM recommendations or norms /
guidelines issued by Technical Services. (Also refer equipment health check-up for drilling &
work over rig issued by technical services).
SAFETY
Swivel is connected with mud pump high pressure hose connections and the hose is secured
through its length by chain/suitable mechanism to swivel to prevent injury in case of hose
failure. It shall be properly secured at the time of installation. Swivel is used during string
rotation and is stacked at derrick floor and care shall be taken while stacking or
reconnecting to the drill string assembly.
Version 1, June-2014
Page : 31
ENVIRONMENT CONTROL
The consumables / used components shall be disposed at designated places only or
returned to stores for disposal as per approved guidelines / regulatory requirements.
STATUTORY / REGULATORY PROVISIONS
Any guidelines, norms issued for safe operation, maintenance by OEM and/ or regulatory
agencies shall be followed. Reference to some of the guidelines / regulations issued by
statutory agencies is enclosed as annexure.
Version 1, June-2014
Page : 32
Page : 33
SAFETY
The rotary table is provided with lock system to prevent reverse rotation. It is to prevent
opening of string assembly connections and safety of well in emergency situations. The
condition & performance of lock system shall always be checked and kept in working
condition.
ENVIRONMENT CONTROL
The consumables / used components shall be disposed at designated places only or
returned to stores for disposal as per approved guidelines / regulatory requirements.
STATUTORY / REGULATORY PROVISIONS
Any guidelines, norms issued for safe operation, maintenance by OEM and/ or regulatory
agencies shall be followed. Reference to some of the guidelines / regulations issued by
statutory agencies is enclosed as annexure.
Version 1, June-2014
Page : 34
Version 1, June-2014
Page : 35
Version 1, June-2014
Page : 36
Page : 37
Page : 38
Version 1, June-2014
Page : 39
Version 1, June-2014
Page : 40
Version 1, June-2014
Page : 41
Version 1, June-2014
Page : 42
Version 1, June-2014
Page : 43
Version 1, June-2014
Page : 44
A Hydromatic Brake must have an adequate circulating system that will provide cool
water at all times for the loads that it will be required to handle. It is imperative that
the water used in the circulating system be fresh and free of all foreign substance.
Brackish or corrosive water, when used in the circulating system, causes corrosion that
accelerates cavitation and erosion within a brake.
2.
When a Hydromatic Brake has been properly installed, it requires no special care. It
should be inspected at regular periods, such as should be done with the entire rig. Each
grease fitting on the brake should be lubricated with a good grade of No. 2 waterproof
grease equivalent on each round trip. It is recommended that same type waterproof
grease be used consistently, as some types are not compatible with others.
3.
The rotor in a Hydromatic Brake is also designed to serve as an impeller for discharging
heated water at the discharge ports. The rate of discharge is approximately the same as
the rate at which cool water enters the brake, provided the discharge line from the
brake is not restricted. During the running in of a stand of pipe with a Hydromatic Brake
revolving in the direction to create resistance, a sufficient volume of cool water must be
available at the brake inlet, at pressures between the minimum and maximum
recommended, to displace the water in the brake as it is heated.
4.
5.
6.
OVERHAUL
Overhauling is replacement of bearings and other components as required. It may be
depending on condition / operating hours as per OEM recommendations or norms /
guidelines issues by Technical Services.
SAFETY
Hydro-matic Brake is installed for safe operation of rig and for its expected performance,
compliance to recommended safety practices is essential.
ENVIRONMENT
Equipment grounding and noise attenuation practices for electrical and electromagnetic
interference should be properly followed and should be according to manufacturers
recommendations.
STATUTORY / REGULATORY PROVISIONS
Any guidelines, norms issued for safe operation, maintenance by OEM and/ or regulatory
agencies shall be followed. Reference to some of the guidelines / regulations issued by
statutory agencies is enclosed as annexure.
Version 1, June-2014
Page : 45
6.15 AC Generator
The Alternating Current Generators on Work-over rigs of ONGC are cooled by the flow of air
through the machine.
The machine armature (stator) comprises low-loss steel laminations assembled under
pressure. The steel laminations are blocked axially by a welded ring. The stator coils are
inserted and blocked in the slots, then impregnated with varnish, and polymerised to ensure
maximum resistance to mould, excellent dielectric rigidity and perfect mechanical linking.
The revolving field coil (rotor) comprises a stack of steel laminations, stamped and cut to
reproduce the indentation of the projecting poles. The steel lamination stack-up is
terminated at each end with high-conductivity electrical plates. To enable parallel operation
between machines, and in order to ensure stability, high electrical conductivity bars are
inserted in holes crossing the poles from one side to the other. These bars are welded with
the stack end laminations in order to obtain a complete cage winding.
The SOP for alternators is expected to ensure:
1. Safe operation
2. High efficiency and reliability
3. Low maintenance cost
4. Improved life cycle
5. Low noise pollution
Following documents should be diligently maintained at site:
1. Manufacturers instruction sheets
2. Manufacturers installation instructions
3. Manufacturers operating manual
INSTALLATION
Following practices should be followed with regard to installation:
1. All installation checks should be completed according to manufacturers written
instructions.
2. While accepting delivery of new alternators, it should be ensured that they are
received packed in secure cartons and covered for protection against dirt and
moisture during transit and outdoor storage.
3. Alternators should be stored in clean dry space, protected from dirt, fumes, water,
corrosive substances and physical damage.
4. Handling should be done with proper lifting equipment using lugs or eyebolts
provided by the manufacturer.
Version 1, June-2014
Page : 46
Version 1, June-2014
Page : 47
Version 1, June-2014
Page : 48
Version 1, June-2014
Page : 49
Page : 50
Version 1, June-2014
Page : 51
Version 1, June-2014
Page : 52
Version 1, June-2014
Page : 53
Page : 54
OVERHAUL
Overhauling is replacement of bearings, shafts, clutch assemblies, actuators, valves,
filters/strainers and other components as required. The overhauling may be required
depending upon severity of operation, run hours, observations during preventive
maintenance activities.
SAFETY
Since winch is used for material handling, person operating the winch shall ensure safety of
material handled and person involved. The ropes, slings, belts, hooks, overload sensing
and shut off device etc. used shall be of approved rating and recommended for use.
ENVIRONMENT CONTROL
The consumables / used components shall be disposed at designated places only or
returned to stores for disposal as per approved guidelines / regulatory requirements.
STATUTORY / REGULATORY PROVISIONS
Any guidelines, norms issued for safe operation, maintenance by OEM and/ or regulatory
agencies shall be followed. Reference to some of the guidelines / regulations issued by
statutory agencies is enclosed as annexure.
Version 1, June-2014
Page : 55
7. Annexures
7.1 Norms and Policies Issued by Technical Services
1. Life cycle period of major equipment for LCC based equipment purchases.
2. Norms for Noise and Exhaust emissions for rotating equipment.
3. Policy for revamping of onshore work over rig.
4. Policy for equipment health check-up for drilling & work over rig.
5. Policy for discard of onshore work over rigs.
6. Revised equipment replacement policy for drilling rigs and work over rigs.
7. Capitals overhaul norms for onshore work over rig equipment.
8. Standby equipment norms for onshore work over rig equipment.
9. Storage, handling and disposal of lubricants.
Version 1, June-2014
Page : 56
Sr.
No.
OISD
Standard/GDN/RP
No
OISD-STD-105
Sep-2004
OISD-STD-106
Oct-2010
OISD-RP-110
Aug-1999
OISD-STD-113
Oct-2013
OISD-STD-119
Jul-2008
OISD-STD-120
Jul-2008
OISD-RP-122
Jul-2008
OISD-RP-123
Jul-2008
OISD-RP-126
Aug-2007
10
OISD-STD-127
Oct-2010
11
OISD-STD-132
Jul-2012
12
OISD-STD-137
13
OISD-RP-146
Aug-2000
14
OISD-RP-147
Oct-2002
15
OISD-RP-148
Aug-2000
Version 1, June-2014
STANDARD NAME
CURRENT
EDITION IN
VOGUE
Oct-2010(Under
Revision)
Page : 57
OISD
Standard/GDN/RP
No
16
OISD-STD-171
Jul-1998
17
OISD-GDN-180
Lightning Protection
Jul-1999
18
OISD-STD-184
Aug-2000
19
OISD-STD-187
Aug-2000
20
OISD-STD-189
Jul-2012
21
OISD-STD-190
Aug-2000(Under
Revision)
22
OISD-GDN-202
Oct-2002(Under
Revision)
23
OISD-GDN-203
Sep-2003
24
OISD-STD-216
Oct-2010
25
OISD-GDN-218
Oct-2004
Version 1, June-2014
STANDARD NAME
CURRENT
EDITION IN
VOGUE
Page : 58
Sr.
No.
OISD
Standard/GDN/RP
No
OISD-RP-110
OISD-STD-137
OISD-RP-146
Aug-2000
OISD-RP-147
Oct-2002
OISD-RP-148
Aug-2000
OISD-GDN-180
Lightening Protection
July-1999
OISD-STD-216
Oct-2010
STANDARD NAME
OMR
Version 1, June-2014
CURRENT EDITION
IN VOGUE
Aug -1999
Oct-2010(Under
Revision)
Page : 59
Sr.
No.
Standard
Technical Services
July-2006
Technical Services
Nov-2010
Technical Services
June-2006
Technical Services
Jan-2009
Technical Services
Jan-2010
Technical Services
Jan-2013
(Under Revision)
Technical Services
Mar-2010
Technical Services
Dec-2009
Technical Services
July-2011
10
OISD-STD-105
Sep-2004
11
OISD-STD-119
Jul-2008
12
OISD-STD-120
Jul-2008
13
OISD-RP-122
Jul-2008
14
OISD-RP-123
Jul-2008
15
OISD-RP-126
Aug-2007
Version 1, June-2014
STANDARD NAME
CURRENT EDITION
IN VOGUE
Page : 60
OISD-STD-127
Oct-2010
17
OISD-STD-171
Jul-1998
18
OISD-STD-187
Aug-2000
19
OISD-GDN-203
Sep-2003
20
OISD-GDN-218
Oct-2004
Version 1, June-2014
Page : 61