Professional Documents
Culture Documents
CASE DIGEST
Herbert Diano
&
John Rhil Ramos
Law 1
Obligations and Contracts
MWF 5:00-6:00pm
Courts Ruling:
According to the court, this is an example of an obligation with a penal
clause. A penal clause, expressly recognized by law, is an accessory undertaking to
assume greater liability on the part of an obligor in case of breach of an obligation. It
functions to strengthen the coercive force of the obligation and to provide, in effect, for
what could be the liquidated damages resulting from such breach. The obligor would
then be bound to pay the stipulated indemnity without the necessity of proof on the
existence and on the measure of damages caused by the breach. Although a
court may not at liberty ignore the freedom of the parties to agree on such
terms and conditions as they see fit that contravene neither law nor morals,
good customs, public order or public policy, a stipulated penalty, nevertheless,
may be equitably reduced by the courts if it is iniquitous or unconscionable or if the
principal obligation has been partly or irregularly complied with.
WHEREFORE, the petition is DENIED.
SO ORDERED.
Facts:
Petitioner Central Colleges of the Philippines (CCP), an educational institution,
contracted the services of respondents Dynamic planners and Construction Corporation
(DPCC) to be its general contractor for the construction of its five (5)-storey school
building. The construction of the entire building would be done in two phases with each
phase valued at P124,000,000.00. To guarantee the fulfillment of the obligation, DPCC
posted three (3) bonds, all issued by the Philippine Charter Insurance Corporation. The
Phase 1 of the project was completed without issue. A down payment for the Phase 2 of
the project was thereafter made. However, Phase 2 of the project encountered
numerous delays. Only 47% of the work to be done was actually finished. CCP wrote
DPCC and PCIC informing them of the breach in the contract and its plan to claim on
the construction bonds. DPCC wrote PCIC confirming the delay, at the same time,
requesting for the extension of its performance and surety bonds because the supposed
revision of the plans would require more days. PCIC approved DPCCs request for
extension of the bonds. However, negotiations to continue with the construction
between CCP and DPCC reached an end. CCP hired another contractor to work on the
school site. CCP sent a letter to PCIC of its final demand for the payment of
P13,924,351.47 as indicated in the bonds. The latter denied formers claims against the
three bonds.
Issue:
Whether or not there is a legal delay or default in part of DPCC. If there is, what
are the legal remedies of CPP in relation to the delay?
Courts Ruling:
Article 1169 of the New Civil Code provides: Those obliged to deliver or to do
something incur in delay from the time the obligee judicially or extrajudicially demands
from them the fulfillment of their obligation. The civil law concept of delay or default
commences from the time the obligor demands, judicially or extrajudicially, the
fulfillment of the obligation from the obligee. Hence, DPCC incurred delay from the time
CCP called its attention that it had breached the contract and extrajudicially demanded
the fulfillment of its commitment against the bonds. It is the obligors culpable delay, not
merely the time element, which gives the obligee the right to seek the performance of
the obligation. Thus, the court held that due to DPCCs inexcusable delay, CCP has a
legal right to demand but cant compel DPCC the fulfillment of its obligation for it is a
violation on the principle of civil servitude. Moreover, CCP can hire another contractor to
fulfill the obligation of DPCC in the expense of DPCC. Also CCP can demand and
compel DPCC to pay damages suffered by CCP due to the delay.