Professional Documents
Culture Documents
Abstract
The paper describes the rehabilitation of the main road at
the Kosova site, where due to appearance of the same
th
named landslide in May of 2014 has been significant
damage of the road and complete stopping of traffic.
Thanks to the fact that the landslide in the road zone has
stopped on the terrace of Bosna River, the original
approach to the rehabilitation has been based on the
presence of deposited materials in the toe part of
landslide which presented counter-weight in the bottom
of the slope and imposed as natural rehabilitation
solution. Existing landfill material had been additionally
secured by stone-drainage ribs in function of securing the
shore, landslides toe, roads trunk and slope of the
cutting above the road, and road stabilization was
performed in five lines of insurance.
Prior state
Detrusive (progressive) landslide caused the destruction
of several buildings in the hamlet Sejmenovii, and toe
part has done a significant damage to a road in about 120
meters.
Solution approach
In order of emergent of traffic, intervention approach was
taken to repairmen. Alternative relocation of the road on
the opposite side of the river or circumvent of the
mountain sides, marked an extensive investigation and
preparation of project documentation with the bridge
over the river or high cuts or a tunnel on the hillside,
with an expensive and longtime construction. Therefore,
the rest of the existing road area.
Geological conditions
Wider area of the terrain on landslide location is
composed by Jurassic-Crataceous clastic-carbonate and
Upper Cretaceous carbonate sediments.
Causes of landslide
In circumstances of intense dampening and flooding, and
with elevation of groundwater level (as in May 2014th),
clayey fractions have swollen and turned into liquid state,
unstable state, and debris more permeable fractions have
become corridors for more free turbulent water
flowing, which altogether resulted in activation of sliding
process and apperance of consequent type.
Besides that, by engineering-geological and geotechnical
terrain observations it has been seen that surface
materials are subject to erosion and denudation, and also
with lower saturation turn into liquid state. Therefore,
sliding begun gradually from upper part and spreaded to
lower parts of the slope, all to the road.
Investigation works
In given circumstances are done trial pits under the
traffic and behind the wall. It has been determined that
limestone substrate is on a depth of around 4 m, and in
the zone behind the wall, is clayey debris, clay and rock
fragments, with water under hydrostatic pressures.
Rehabilitation
Stabilization of the road was performed in five "lines"
with elements of insurance:
1. insurance river Bosna consisted of rockfilling large
blocks of stone resting on a solid limestone (rocky)
surface in the river bed, thus preventing erosion coast;
2. ensuring the landfill on the river terrace is derived with
rock-drainage rib along the foot of the landfill with two
streams of the water, which prevented possibly later
moves of the mass landfill, as counterweight;
3. insurance along the lines of the former retaining wall
was presented with a longitudinal rock-drainage rib for
draining water with three-row concrete gabions over ribs;
4. ensuring the slope of the cutting is achieved by crossdrains whose end parts (as in previous drainage
elements) laid under the existing and potential sliding
surfaces and
5. load of roadway construction resting on mass of
landslide foot is achieved by removing the upper parts of
the landfill and the execution of cross-stone ribs on the
same grids which are laid and ribs on the slope, which
structure has provided roadway as a complete solid zone
of required (large) capacity.
Conclusion
Based on the presented solution, with investment of less
than 1 mil. , rehabilitation and stabilization of road, and
the establishment of traffic was carried out for less than a
month after the occurrence of landslides. Considerable
savings were made with durable functionality of the road.
Reference
Fund of professional-technical documentation, Design&QC Sarajevo
Main design of immediate intervention on road M17-005: Karue
Ozimica, km 9+050 km 9+270 in order to enable road for traffic
on landslide area in Kosova, Design&QC Sarajevo, 2014
Engineering geology, chosen chapters, Baagi M. (2007), Civ. Fac.
Un. Sarajevo, [ISBN 551.1/.4: 624] (075.8), 173 p.
Basic geological map, sheet Zavidovii M 1:100 000, SZG Beograd,
1973
Rehabilitation of main road M17 on Kosova locality,
Engineering-geological-geotechnical terms of rehabilitation,
Report, Design&QC Sarajevo, 2014