Professional Documents
Culture Documents
Name of Work: Improvements to road from KM 28/0 to 42/4 of Kadiri-Hindupur road in Anantapuram
District.
1 CRUSHER
42/4
28/0
Kadiri-Hindupur road
11/0
0/0
1/6
Km
0/0
Km
to
11/0
to
1/6
1.60
CT
1.10
28/0
17.00
19.70
19.70
+ 14.40/2 =
or
26.90
27.00
Kms
2 BITUMEN
42/4
28/0
KH Road
0/0
341.20
Refinery at Chennai
Refinary to Kadiri IB through Anantapur-Chennai road
341.20
Kadiri Municipality
Km
0.0
to
1.0
1.00
Kadiri-Hindupur road
Km
0/0
to
28/0
28.00
370.20
+ 14.40/2 =
377.4
or
377.00
Kms
3 SAND
Sand quarry at Km 48/8+3.00 Km C.T. of Kadiri-Hindupur road
48/8
42/4
Sand quarry
28/0
L2
CT
Km
42/2
to
48/8
3.30
6.60
9.90
9.90
+ 14.40/2 =
or
17.10
17.00
Kms
3 SAND
Sand quarry at Km 113/2 of NH-205 + 8.00 Kms
48/8
42/4
Sand quarry
28/0
L2
CT
0.22
8.00
Km
113.2
to
144.2
31.00
In M-ODC Road
Km
0.0
to
32.555
32.555
In Kadiri-Hindupur road
Km
19.8
to
28.000
8.200
79.98
79.98
+ 14.40/2 =
or
87.18
87.00
Kms
28/0
KH Road
19/8
M-ODC Road
0/0
Km
144.2
to
81.0
CT
63.20
0.22
Km
0/0
to
32/555
32.56
Km
19/8
to
28.0
8.20
104.18
+ 14.40/2 =
or
(R&B) Section,Kadiri
111.38
111.00
Kms
Executive Engineer
(R&B) Division,
Dharmavaram
Superintending Engineer
(R&B) Circle,Anantapur
Name of Work ::
(It is linked throughout
Estimate )
Amount
73.77
316.93
316.93
316.93
73.77
875.09
Varies with pipe
dia.
BITUMEN
Place
DATA
RMR
RMR
RMR
1/22/2015
22-Jan-15
Leads
5.00
27.00
27.00
27.00
5.00
87.00
111.00
Rates
377.00
###
###
###
###
Rates
6000.00
###
###
###
LEAD
Grade 80/100
Grade 60/70
CRMB 55 Grade
Emulsion (MS)
CEMENT / STEEL
CEMENT
HYSD Steel
6 mm Mild Steel
MS STEEL
ALLOWANCES
ITEM
Name
Value
Labour unicipal Area Allowance
%
Metal
%
Gravel
%
Sand
%
Overhead Charges ( R)
5.00 %
Overhead Charges ( B)
15.00 %
Contractors Profit
10.00 %
VAT
0.00 %
Local
Entry%
Centering Charges
Widening and Strenghening of Kadiri-Hindupur road (Old Rayachoti-KadiriTumkur Road) from Km 28/0 to 42/400 in Anantapuram Dist.,
S.No
Specification in Brief
Hyper Link
to DATA
Rates
Exact
Rates
Rounded
V. VENKATA NARAYANA
9440818440, 07799139399,
vvnhighways.blogspot.in
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
PAGE_70
PAGE_68
PAGE_68
PAGE_50
PAGE_58
PAGE_48
PAGE_94
PAGE _94
PAGE_95
PAGE_95
PAGE_96
PAGE_96
PAGE_67
PAGE_67
PAGE_104
PAGE_104
PAGE_104
PAGE_104
PAGR_104
PAGE_104
PAGE_104
PAGE_104
PAGE_110
PAGE_141
PAGE_141
PAGE_123
PAGE_124
APRDC
PAGE_146
113.71
145.04
151.73
18.98
65.39
222.49
114.00
145.00
152.00
19.00
65.00
222.00
1726.01
1679.34
1428.03
1795.35
1792.22
1462.37
15.40
7.53
1888.74
2125.02
1983.25
2293.48
1896.15
2132.43
1990.66
2300.89
1984.92
1726.00
1679.00
1428.00
1795.00
1792.00
1462.00
15.00
8.00
1889.00
2125.00
1983.00
2293.00
1896.00
2132.00
1991.00
2301.00
1985.00
50.53
51.32
34.56
10.94
12.28
162.28
51.00
51.00
35.00
11.00
12.00
162.00
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
NABARD
NABARD
PAGE_125
PAGE_125
PAGE_125
PAGE_132
PAGE_132
PAGE_135
PAGE_138
PAGE_138
PAGE_138
PAGE_95
PAGE_331
PAGE_331
PAGE_345
PAGE_331
PAGE_345
PAGE_323
PAGE_321
PAGE_462
PAGE_331
PAGE_455
SSR600
PAGE_272
SSR800
PAGE_272
SSR1000
PAGE_272
SSR1200
PAGE_272
PAGE_462
PAGE_522
PAGE_523
PAGE_335
PAGE_335
PAGE_336
PAGE_336
PAGE_472
PAGE_472
PAGE_477
PAGE_501
PAGE_472
162.28
162.00
7352.71
6990.40
7389.06
8402.54
8446.70
9149.06
9729.86
9527.48
9620.33
342.78
162.00
162.00
7353.00
6990.00
7389.00
8403.00
8447.00
9149.00
9730.00
9527.00
9620.00
343.00
4114.14
4585.38
6535.77
4277.03
6010.59
4114.00
4585.00
6536.00
4277.00
6011.00
26.90
124.83
512.13
4585.38
5043.92
2761.08
3291.78
4287.49
5083.31
6860.93
8055.64
9169.52
###
512.13
1135.74
708.73
5818.40
5312.45
6432.65
6803.77
6934.29
7564.68
6881.80
6909.97
394.76
27.00
125.00
512.00
4585.00
5044.00
2761.00
3292.00
4287.00
5083.00
6861.00
8056.00
9170.00
###
512.00
1136.00
709.00
5818.00
5312.00
6433.00
6804.00
6934.00
7565.00
6882.00
6910.00
395.00
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
V. VENKATA NARAYANA
9440818440, 07799139399,
365.24
5108.13
1874.96
512.13
1306.42
###
###
###
###
365.00
5108.00
1875.00
512.00
1306.00
###
###
###
###
1793.09
72.32
PAGE_455 5312.45
PAGE_472 5985.96
PAGE_452
97.48
PAGE_220
71.91
PAGE_130
198.60
EinC
4527.43
EinC
5965.79
EinC
289.83
EinC
195.23
EinC
121.83
PAGE_334 3965.07
PAGE_453 3979.00
PAGE_23
574.71
Temp
317.53
EinC
991.00
EinC
568.00
PAGE_128
282.87
PAGE_129
388.65
PAGE_5_23
184.50
PAGE_5_39
70.30
Page_225
832.34
1793.00
72.00
5312.00
5986.00
97.00
72.00
199.00
4527.00
5966.00
290.00
195.00
122.00
3965.00
3979.00
575.00
318.00
991.00
568.00
283.00
389.00
185.00
70.00
832.00
PAGE_472
PAGE_500
PAGE_522
PAGE_462
PAGE_463
PAGE_489
PAGE_490
PAGE_448
PAGE_460
PAGE_422
PAGE_461
vvnhighways.blogspot.in
PREPARED on 10-12-2014
518201.00
To
(R&B) Division,
Sangareddy,
ZAHEERABAD
MEDAK Dist.
Date :12-05-2010
Sir,
Sub :-
of 8.0 m Bridge at km 3/4-6 on Chittempally- Koukuntla Road in Rangareddy dist " for a
amount of Rs 165.00 Lakhs along with Report, data, lead statement, RMR and drawings . Th
report accompanying the estimate dealt in detail the necessities and provisions made in th
estimate.
Yours faithfully
Enclosures ::
1) Report, Estimates, RMR, Drawings.
Engineer,
on ChittempallyReg.
ruction of 3 vents
cle, Hyderabad to
nicate.
fully
e Engineer,
ZAHEERABAD
SPECIFICATION REPORT
Specification report accompanying the Estimate " Widening and Strenghening of
Kadiri-Hindupur road (Old Rayachoti-Kadiri-Tumkur Road) from Km 28/0 to 42/400 in Anantapuram
Dist., "
Amount of Estimate : Rs.
Shamshabad - Shabad is an important link road radiating from NH 7 and connecting
other important roads. It is very near to International Airport at Shamshabad. The existing single lane
Bituminous road is damaged, carriageway edges reduced and the berms are not sufficient also the
C.D. works are narrow. All these bad conditions are creating problems to the road user and the
existing with is not catering to many fold increased traffic. The surface is no at all suitable for fast
moving vehicles.
In view of the above mentioned conditions of the Road and as per the instructions of
Higher officials a detailed _____ estimate for the Road is prepared to widen from existing single
lane to Double lane and bringing the total road to traffic worthy by strengthening , with the following
provisions.
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
The estimate is prepared based on common SSR 2014-15 . The quarries and their leads are
taken from approved Quarry and Lead Charts. The work will be carried out as per specifications and
codal guide lines and relevant circular instructions issued time - to -time.
Early approval to the estimate is solicited.
0
0
Asst. Executive Engineer
Executive Engineer,
GOVERNMENT OF
TELANGANA
ROADS & BUILDINGS
DEPARTMENT
HYDERABAD - INDIA
WIDENING AND STRENGHENING OF KADIRIHINDUPUR ROAD (OLD RAYACHOTI-KADIRITUMKUR ROAD) FROM KM 28/0 TO 42/400 IN
ANANTAPURAM DIST.,
D. P. R.
AMOUNT OF ESTIMATE
Rs
Lakhs
GENERAL ABSTRACT
S.No
Description
Amount
(Rs.)
Remarks
4000000
Sub Total
4000000
4.0%
160000
5.0%
200000
1.0%
54000
7
6
5000
4000000
Executive Engineer,
(R&B) Division, _____ ___
GENERAL ABSTRACT
NAME OF THE WORK :
DESCRIPTION
AMOUNT Rs
PART - A
1
Road work
18429756
TOTAL PART - A Rs
18429756
PART - B
2
3
4
5
6
7
8
921488
184298
368595
413668
5000
100000
4177196
Total Rs
24600000
AE
DEE-3
EE-1/R
DCE ( R )
E-in-C ( R&B)
Admn, State Roads, RSW & Bldgs
-Kadiri-Tumkur
AMOUNT Rs
18429756
18429756
921488
184298
368595
413668
5000
100000
4177196
24600000
y be modified as
( R&B)
ds, RSW & Bldgs
Name of Work ::- Widening and Strenghening of Kadiri-Hindupur road (Old Rayachoti-
DETAILED ESTIMATE
MEASUREMENTS
Sno
Description
No
LENT
BRDT
DPT
Quantity
Rate
Per
Amount
10
Forming embankment with Side earth by mechanical means up to SDR including pre-watering of
soil , removal of top soil, excavation of soils , depositing the soils on the embankment, spreading
soil, breaking clods, sectioning , grading and consolidation with 8 to 10 Tonnes Vibratory Road
Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and operational
charges of T&P and seigniorage charges, complete for finished item of work as per MoRT&H
specification 305 (4th revision) (Payment will be made based on levels for finished item of work).
1
1
1 x 1 1000.00
1.00
1.000
1000.00
cum
1 x 1
1.00
1.00
1.000
1.00
cum
1 x 1
1.00
1.00
1.000
1.00
cum
1002.00
say
1002.00
1002000
1
2
Forming embankment with borrowed useful earth from outside road boundary by mechanical means
up to SDR with all leads and lifts including pre-watering of soil at borrow area, removal of top soil,
excavation of soils at borrowed area, conveyance of soil, depositing the soil on the embankment,
spreading soil, breaking clods, sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory
Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and
operational charges of T&P and seigniorage charges, complete for finished item of work as per
MoRT&H specification 305 (4th revision) (Payment will be made based on levels for finished item of
work).
2
2
1 x 1 1000.00
1.00
1.000
1000.00
cum
1 x 1
1.00
1.00
1.000
1.00
cum
1 x 1
1.00
1.00
1.000
1.00
cum
1002.00
say
1002.00
2
3
Earthwork excavation in soils up to SDR by mechanical means including trimming bottom and side
slopes in accordance with requirements of lines , grades and cross sections etc., complete including
seigniorage charges for finished item of work for trench cutting as per MoRT&H specification
301(4th Revision) and as directed by the Engineer-in-Charge
3
3
1 x 1 1000.00
1.00
1.000
1000.00
cum
1002000
1 x 1
1.00
1.00
1.000
1.00
cum
1 x 1
1.00
1.00
1.000
1.00
cum
10
1002.00
say
1002.00
1002000
3006000
3006000
3006000
VAT on Part "A".
3006000
L.S for Quality control charges on Part "A",
3006000
L.S. for Price adjustment Road Work,
L.S for Road Safety works for caution, junction boards, studs etc.
@
@
@
4.00%
1.00%
3.00%
Rs:
Rs:
Rs:
Rs:
120200
30100
90200
400000
Rs:
5000
Rs: 14648500
18300000
Total Amount Rs.
1 83 00 000
3
3
Executive Engineer
CALCULATIONS
No
LENT
BRDT
DPT
Name of Work ::- Widening and Strenghening of Kadiri-Hindupur road (Old Rayachoti-
DETAILED ESTIMATE
MEASUREMENTS
Sno
Description
###
###
1
###
###
1
###
###
1
###
No
LENT
BRDT
DPT
Quantity
Rate
Per
Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of
scarified material with all leads and lifts up to 1000 m as per MoRT&H (4 th Revision) Specn.
No.305.4.3
say
12619.00
12619.00
Sm
7.50 1.00
say
1893.00
cum
1,462.00 1.00
Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix
macadam specification including cost, of all materials and including premixing the material with
water at OMC in Mechanical mix plant carriage of mixed material by
say
1893.00
cum
1,985.00 1.00
Providing and applying Prime Coat with bitumen emulsion (Medium Setting) bulk using
emulsion pressure distributor on prepared surface of Granular base including cleaning of road
surface and spraying emulsion at the rate of 0.60 Kg/sqm using emulsion pressure distributor
for finished item of work etc., complete for finished item of work as per MoRT&H
Specification 502 (4th Revision) and as directed by the Engineer-in-charge.
###
1
###
###
say
12619.00
sm
34.60 1.00
Providing and applying tack coat with bitumen Emulsion (Medium setting) (Bulk) using Emulsion
pressure distributor at the rate of 0.20 Kgs per sqm on the prepared bituminous/granular surface
cleaned with mechanical broom for finished item of work as per MoRT&H Specification 503 (4 th
revision) and as directed by the Engineer-in-Charge.
say
25238.00
sm
10.90 1.00
Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an average
output of 37.5 tones per hour using HBG crushed aggregates of Grading - II as per table 500-4 of
MoRT&H specification 504 (4th Revision) premixed with bituminous binder of 60/70 grade @ 3.3%
by weight of TOTAL mixture, transported to site, laid over a previously prepared surface with
mechanical paver finisher to the required grade, level and alignment and rolled as per Clauses 501.6
and 501.7 to achieve the desired compaction for finished item of work as directed by the Engineer-inCharge including hire and operational charges all T&P and all other contingent charges necessary
including cost of all materials etc., complete and as per MoRT&H specification No. 504(4th
Revision) .
###
###
2
say
cum
7,353.00 1.00
Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using HBG
crushed aggregates of Grading -2 as per table 500-15 of specification 508 of MoRT&H (4 th Revision),
premixed with bituminous binder 60/70 grade @ 5% of mix and filler, transporting the hot mix to work
site, laying with mechanical paver finisher to the required grade, level and alignment, rolling with
smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRT&H
Specification 508 (4th Revision) complete for finished item of work in all respects as directed by
Engineer-in-charge. (Payment will be made based on levels for finished item of work)
###
###
631.00
316.00
say
316.00
cum
9,149.00 1.00
Forming shoulders with barrowed useful selected earth having MDD of not less than 1.75 Gms/CC
from out side road boundary by mechanical means with all leads and lifts including prewatering of soil
at barrow area, removal of top soil, excavation of soils at barrowed area, conveyance of soil,
depositing the soils on the embankment, spreading soils, beaking clods, sectioning and consoilidation
with vibratory road roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all
hire and operational charges of T&P and complete for finished item of work as per MoRT&H
specification 305 ( 4th revision) ( Payment will be made based on levels for finished item of work).
###
###
1
2493.00
say
say
###
304.00
cum
27.00 1.00
Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and
fine aggregate conforming to table 1000-2 of MoRT&H including cost, conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other
incidental and operational charges of all T&P etc., complete for finished item of work as per
MoRT&H specification 1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge
for foundations
68.00
say
68.00
cum
4,585.00 1.00
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, and conveyance of all materials to site and all labour charges , centering,
machine mixing, laying in position, Compacting, Vibrating and curing including all other incidental
and all other operational charges of T&P required etc., complete as per MoRT&H Specification
1500,1700, 2200 (4th Revision) for Sub structure .
###
###
152.00 1.00
304.00
###
###
cum
Earthwork excavation in soils up to SDR by mechanical means for foundations of structures as per
drawing and technical specification including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing sides of bottom, back filling the excavation earth to
the extent required etc., complete including charges for finished item of work as per MoRT&H
specification 304(4th Revision) and as directed by the Engineer-in-Charge
###
###
2493.00
540.00
say
540.00
cum
5,312.00 1.00
CALCULATIONS
Amount
10
94643
2767566
3757605
No
LENT
BRDT
DPT
436617
328.125
6.09375
275094
4639743
2891084
540
378936
8208
311780
2868480
18429756
Name of Work :- Widening and Strenghening of Kadiri-Hindupur road (Old Rayachoti-Kadiri-Tumkur Road) from Km 28/0 to 42/400 in
Anantapuram Dist.,
S.No
Specification in Brief
Unit
Earth/ Gravel
Metal/ Stone
Sand
cum
cum
cum
Quantity
Factor
Quantity
Factor
Quantity
Factor
Quantity
10
5
1.000
1 cum
2797.00
Granular Sub-base
1 cum
1893.00
WBM Gr II
2797.000
1.280
2423.04
1 cum
1.450
0.00
WBM Gr III
1 cum
1.530
0.00
1 cum
1.320
2498.76
1 sqm
0.004
0.00
1 sqm
1 sqm
1 cum
0.027
0.00
10
SDBC
1 cum
316.00
1.462
461.85
11
1 cum
631.00
1.415
892.94
12
Gravel Shoulders
1 cum
13
VCC(1:4:8)
1 cum
0.900
0.00
0.450
14
VCC(1:3:6)
1 cum
68.00
0.900
61.20
0.450
30.60
15
1 cum
540.00
0.900
486.00
0.450
243.00
16
1 cum
0.900
0.00
0.450
0.00
17
1 cum
0.900
0.00
0.450
0.00
18
1 cum
0.900
0.00
0.450
0.00
19
1 cum
0.900
0.00
0.450
0.00
20
1 cum
21
1 cum
1.200
0.000
22
1 cum
1.200
0.000
23
1 cum
1.200
0.00
24
1 cum
25
1 cum
1.180
0.00
0.090
0.00
26
1 cum
27
1 cum
28
1 cum
1.200
0.000
29
0.002
0.000
30
Plastering in CM(1:5) 12 mm
1 sqm
0.151
0.000
31
1 sqm
0.113
0.00
32
1 cum
1.330
0.00
33
1 sqm
0.078
0.00
34
1 sqm
0.040
0.00
35
1 sqm
0.030
0.00
36
1 cum
1.258
0.00
0.326
0.00
37
1 cum
1.158
0.00
0.347
0.00
25 mm with BT 60/70
1893.00
1.280
1.200
1.200
0.000
0.000
0.000
Total Quantity
Rate
Amount Rs
0.00
2797.00
6823.79
273.60
22.00
50.00
40.00
61534.00
341190.00
10944.00
Total Amount Rs
413668.00
Name of Work:- Widening and Strenghening of Kadiri-Hindupur road (Old Rayachoti-Kadiri-Tumkur Road)
from Km 28/0 to 42/400 in Anantapuram Dist.,
Cart Track
Mahbubnagar - Mannanur
Wanaparthy - Jadcherla
Wanaparthy - Jadcherla
Wanaparthy - Jadcherla
Wanaparthy - Jadcherla
Wanaparthy - Jadcherla
Wanaparthy - Jadcherla
Site Spreads in
Site average Lead
road
road
road
road
road
road
road
km
km
km
km
km
km
km
1.10
9.40
28.40
28.40
28.40
28.40
28.40
28.40
c) Site Spreads in
d) Site average Lead
km
km
km
km
km
km
km
km
45.00
to km
(48.1 - 45) /2
Total Lead
.WEIGHTED AVERAGE LEAD
x
to
to
to
to
to
to
to
road
road
road
road
km
km
km
km
0.60
34.20
45.00
45.00
45.00
45.00
45.00
45.00
=
=
=
=
=
=
=
=
0.66
24.80
16.60
16.60
16.60
16.60
16.60
16.60
48.10
SAY
=
=
=
1.55 km
126.61 km
127.00 km
( REFINERY AT CHENNAI)
0.00
0.00
0.00
0.00
to
to
to
to
km
km
km
km
45.00
45.00
45.00
45.00
km
45.00
to km
(48.1 - 45) /2
Total Lead
.WEIGHTED AVERAGE LEAD
48.10
SAY
=
=
=
=
=
555.00
45.00
45.00
45.00
45.00
=
=
=
1.55 km
736.55 km
737.00 km
0
0
Asst. Executive Engineer
R&B Section, ___ ___ ___
km
km
km
km
km
km
km
km
km
km
km
km
km
km
377.00 km
Lead
Conveyance Rates
754.00 km
1.50
754.00 km
1.50
Bulk
(80/100)
Bulk
(60/70)
CRMB
Gr 55
Emulsion
(M.S)
43414.38
44329.74
45817.20
39418.00
0.00
0.00
0.00
0.00
43414.38
44329.74
45817.20
39418.00
0.00
0.00
0.00
0.00
Deduct loading
--
--
--
--
--
--
--
--
--
--
--
--
Total
43414.38
44329.74
45817.20
39418.00
1.5 x 754
1131.00
1131.00
1131.00
1.5 x 754
TYPE OF BITUMEN
Add VAT @
0.00 %
0.00 %
1131.00
Total
44545.38
45460.74
46948.20
40549.00
OR SAY
44545.38
45460.74
46948.20
40549.00
Name of Work ::
Widening and Strenghening of Kadiri-Hindupur road (Old Rayachoti-Kadiri-Tumkur Road) from Km 28/0 to 42/400 in Anantapuram Dist.,
RMR.
22-Jan-15
SSR :: 2014-15
316.93
316.93
316.93
316.93
316.93
316.93
316.93
316.93
588.00
944.00
984.00
780.00
656.00
504.00
308.00
340.00
70.00
70.00
70.00
70.00
70.00
70.00
70.00
--
147.00
236.00
246.00
195.00
164.00
126.00
77.00
--
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
1121.93
1566.93
1616.93
1361.93
1206.93
1016.93
771.93
656.93
10
11
12
13
14
15
16
17
18
456.00
588.00
944.00
984.00
780.00
656.00
504.00
308.00
340.00
316.93
316.93
316.93
316.93
316.93
316.93
316.93
316.93
316.93
456.00
588.00
944.00
984.00
780.00
656.00
504.00
308.00
340.00
70.00
70.00
70.00
70.00
70.00
70.00
70.00
70.00
--
114.00
147.00
236.00
246.00
195.00
164.00
126.00
77.00
--
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
956.93
1121.93
1566.93
1616.93
1361.93
1206.93
1016.93
771.93
656.93
TOTAL RATE
Seigniorage
Charges
Machine Crushing
Charges
588.00
944.00
984.00
780.00
656.00
504.00
308.00
340.00
1
2
3
4
5
6
7
8
Initial Rate
of Material
10
Loading &
unloading charges
(7-5)
9
Stacking
Charging
(4-5)
8
Nature of Metal
Conveyance
rate
25%
on (9)
11
S.No
Weighted
Average Lead
Blasting Charges
Date ::
12
%
13
On (6+9)
Value
14
SUM of
( 8 to12&14 )
15
12
13
14
15
16
17
1
2
3
4
5
6
1
2
3
4
588.00
456.00
419.00
164.00
316.93
316.93
316.93
316.93
588.00
456.00
419.00
164.00
70.00
70.00
70.00
70.00
-----
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.00
0.00
0.00
0.00
974.93
842.93
805.93
550.93
45.00
95.00
316.93
316.93
45.00
95.00
-70.00
---
0.00
0.00
0.0
0.0
0.00
0.00
361.93
481.93
120.90
120.90
120.90
120.90
120.90
120.90
532.00
692.00
822.00
1036.00
994.00
620.00
316.93
316.93
316.93
316.93
316.93
316.93
532.00
692.00
822.00
1036.00
994.00
620.00
70.00
70.00
70.00
70.00
70.00
70.00
133.00
173.00
205.50
259.00
248.50
155.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.0
0.0
0.00
0.00
0.00
0.00
0.00
0.00
1051.93
1251.93
1414.43
1681.93
1629.43
1161.93
( QUARRY LEADS )
27.00 316.93 0.00
27.00 316.93 0.00
27.00 316.93 0.00
27.00 316.93 0.00
120.90
120.90
120.90
120.90
262.00
252.00
144.00
1260.00
-----
0.00
0.00
0.00
0.00
0.0
0.0
0.0
0.0
0.00
0.00
0.00
0.00
--
0.00
0.0
0.00
652.93
638.93
530.93
1576.93
37.55
176.77
----
0.00
0.00
0.00
0.0
0.0
0.0
0.00
0.00
0.00
1481.09
1337.09
1217.09
Gravel
5.00
73.77
0.00
68.40
103.00
316.93
262.00
74.00
316.93
252.00
70.00
316.93
144.00
70.00
316.93 1260.00
0.00
Cost of each Bond Stone
73.77
103.00
--
2
3
4
87.00
87.00
87.00
875.09
875.09
875.09
0.00
0.00
0.00
68.40
68.40
68.40
606.00
462.00
342.00
875.09
875.09
875.09
5
6
7
8
Cement
HYSD Steel
MS Steel
6 mm Mild Steel
6000.00
43000.00
44000.00
44000.00
606.00
462.00
342.00
----
6000.00
43000.00
44000.00
44000.00
Executive Engineer
R&B Sub-Division___
TOTAL RATE
SUM of
( 8 to12&14 )
15
DATA
SSR :: 2014-15
SNo
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
Quantity Unit
2
Date :: 22-Jan-15
Description of Item
Rate
per
Amount
Forming embankment with Side earth by mechanical means up to SDR including pre-watering of soil ,
removal of top soil, excavation of soils , depositing the soils on the embankment, spreading soil,
breaking clods, sectioning , grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @
OMC to meet requirement of table 300-2 of MoRT&H, including all hire and operational charges of
T&P and (excluding seigniorage) charges, complete for finished item of work as per MoRT&H
specification 305 (4th Revision) (Payment will be made based on levels for finished item of work).
0.02
0.50
day
day
0.0
345.00
295.00
1.00
1.00
154.40
A=
TOTAL
(B) Machinery
Rate as per G.I. Ms. No 10, Dt 26/7/2005
Motor Graders for Grading @ 100 cum per hour
Water tanker 6 KL
Vibratory roller 8T
TOTAL
(A + B )
100.00
1.00
4.00
1.00
cum
hour
hour
hour
5.00
9844.70
492.24
10.00
10336.94
1033.69
100.00
cum
(E ) Seigniorage charges
Earth
0.00
100.00
cum
13.00
3216.00
624.00
2678.30
1.00
1.00
1.00
1.00
B=
6.90
147.50
154.40
0.00
154.40
1.00
1300.00
3216.00
2496.00
2678.30
9690.30
9844.70
0.00
11370.63
113.71
114.00
R&B Sub-Division___
1
1
1
1
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
2
3
Forming embankment with borrowed useful earth from outside road boundary by mechanical means
up to SDR with all leads and lifts including pre-watering of soil at borrow area, removal of top soil,
excavation of soils at borrowed area, conveyance of soil, depositing the soil on the embankment,
spreading soil, breaking clods, sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory
Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and
operational charges of T&P and (excluding seigniorage) charges, complete for finished item of work
as per MoRT&H specification 305 (4th Revision) (Payment will be made based on levels for finished
item of work).
0.04
1.00
day
day
0.0
345.00
295.00
308.80
TOTAL
100.00
160.00
cum
t.km
(B) Machinery
Rate as per G.I. Ms. No 10, Dt 26/7/2005
Tipper (for 1 Km = 160x1 = 160) t.km
Add 10% of cost of carriage to cover
cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour
Motor Graders for Grading @ 100 cum per hour
Water tanker 6 KL
Vibratory roller 8T
TOTAL
(A + B)
13.00
7.22
2575.60
3216.00
624.00
2678.30
A=
13.80
295.00
308.80
0.00
308.80
1.00
t.km
1300.00
1155.20
1.00
1.00
1.00
1.00
B=
115.52
1287.80
3216.00
2496.00
2678.30
12248.82
12557.62
1.00
1.00
0.50
1.00
4.00
1.00
hour
hour
hour
hour
5.00
12557.62
627.88
10.00
13185.50
1318.55
100.00
cum
(E ) Seigniorage charges
Earth
0.00
100.00
cum
1.00
0.00
14504.05
145.04
145.00
1
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
3
4
4
4
4
4
4
4
4
4
4
4
4
4
(4th Revision) With a lead of 5KM (Payment will be made based on levels for finished item of
work).
Page 68,69 of MoRT&H SDB
Unit : Cum
Taking out put = 100 Cum
(A) Labour
Mate
0.04
day
345.00
1.00
1.00
day
Mazdoor unskilled
295.00
1.00
0.0
100.00
800.00
cum
t.km
A=
13.80
295.00
308.80
0.00
308.80
1.00
t.km
1300.00
5776.00
1.00
1.00
1.00
1.00
B=
577.60
0.00
0.00
2496.00
2678.30
12827.90
13136.70
308.80
TOTAL
(B) Machinery
Rate as per G.I. Ms. No 10, Dt 26/7/2005
Tipper ( for 5 Km = 160 x 5 = 800) t.km
Add 10% of cost of carriage to cover
cost of loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour
Motor Graders for Grading @ 100 cum per hour
Water tanker 6 KL
Vibratory roller 8T
TOTAL
(A + B )
13.00
7.22
2575.60
3216.00
624.00
2678.30
4.00
1.00
hour
hour
hour
hour
5.00
13136.70
656.84
10.00
13793.54
1379.35
100.00
cum
(E ) Seigniorage charges
Earth
0.00
100.00
cum
1.00
0.00
15172.89
151.73
152.00
0.08
2.00
day
day
0.0
345.00
295.00
cum
1.00
B=
2340.00
2340.00
617.60
TOTAL
180.00
A=
27.60
590.00
617.60
0.00
617.60
1.00
1.00
(B) Machinery
Rate as per G.I. Ms. No 10, Dt 26/7/2005
13.00
TOTAL
1
4
4
4
4
4
4
4
4
4
4
4
4
4
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
5
6
6
6
6
6
(A + B )
7
2957.60
5.00
2957.60
147.88
10.00
3105.48
310.55
180.00
cum
(E ) Seigniorage charges
Earth
0.00
180.00
cum
1.00
0.00
3416.03
18.98
19.00
Removal of unserviceable soils up to SDR including excavation, loading and disposal up to 1000 m
etc., complete including (excluding seigniorage) charges for finished item of work as per MoRT&H
specification 301(4th Revision) and as directed by the Engineer-in-Charge
0.08
2.00
day
day
0.0
345.00
295.00
617.60
A=
TOTAL
360.00
16.36
cum
hour
1.00
1.00
(B) Machinery
Rate as per G.I. Ms. No 10, Dt 26/7/2005
Tippers 5.50 cum capacity
13.00
922.00
TOTAL
(A + B )
1.00
1.00
B=
27.60
590.00
617.60
0.00
617.60
4680.00
15083.92
19763.92
20381.52
5.00
20381.52
1019.08
10.00
21400.60
2140.06
360.00
cum
(E ) Seigniorage charges
Earth
0.00
360.00
cum
1.00
Removal of unserviceable soils by Manual means up to SDR including excavation, loading and
disposal up to 1000 m etc., complete including (excluding seigniorage) charges for finished item of
work as per MoRT&H specification 301(4th Revision) and as directed by the Engineer-in-Charge
Page 48 of MoRT&H SDB
Unit : Cum
Taking out put = 120 Cum
(A) Labour
0.00
23540.66
65.39
65.40
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
6
7
1.80
45.00
day
day
Mate
Mazdoor unskilled
345.00
295.00
1.00
1.00
0.0
621.00
13275.00
13896.00
0.00
13896.00
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
13896.00
A=
TOTAL
10.00
hour
(B) Machinery
Tippers 5.50 cum capacity
922.00
TOTAL
(A + B )
1.00
B=
9220.00
9220.00
23116.00
5.00
23116.00
1155.80
10.00
24271.80
2427.18
120.00
cum
(E ) Seigniorage charges
Earth
0.00
120.00
cum
1.00
0.00
26698.98
222.49
222.50
0.48
2.00
10.00
day
day
day
0.0
hour
hour
hour
hour
(B) Machinery
Motor grader 3.35M Blade @50 cum/Hr.
Vibratory roller 8T
Tractor - Rotavator (223+11=234)
Water tanker 6 KL
A=
165.60
714.00
2950.00
3829.60
0.00
3829.60
3216.00
2678.30
422.00
624.00
1.00
1.00
1.00
1.00
B=
19296.00
16069.80
5064.00
1872.00
42301.80
1305.26
1.00
250610.56
345.00
357.00
295.00
3829.60
TOTAL
6.00
6.00
12.00
3.00
TOTAL
1.00
1.00
1.00
(C) Material
Close graded Granular sub-base material as per
Table 400-1, Grading I material of MORT&H
53-9.5mm IRC & MORT&H HBG/HBT Chips @ 50 %
192.00
cum
1
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
7
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
76.00
cum
115.20
cum
998.60
1.00
75893.35
656.93
1.00
C=
75678.34
402182.25
448313.65
5.00
448313.65
22415.68
10.00
470729.33
47072.93
383.20
cum
(F ) Seigniorage charges
Metal
0.00
300.00
cum
1.00
0.00
517802.26
1726.01
1726.00
0.48
2.00
10.00
day
day
day
0.0
hour
hour
hour
hour
(B) Machinery
Motor grader 3.35M Blade @50 cum/Hr.
Vibratory roller 8T
Tractor - Rotavator (223+11=234)
Water tanker 6 KL
A=
165.60
714.00
2950.00
3829.60
0.00
3829.60
3216.00
2678.30
422.00
624.00
1.00
1.00
1.00
1.00
B=
19296.00
16069.80
5064.00
1872.00
42301.80
1438.18
1.00
193291.39
998.60
1.00
95865.28
345.00
357.00
295.00
3829.60
TOTAL
6.00
6.00
12.00
3.00
TOTAL
1.00
1.00
1.00
(C) Material
Close graded Granular sub-base material as per
Table 400-1, Grading II material of MORT&H
26.5-9.5mm IRC & MORT&H HBG/HBT Chips @ 35 %
134.40
cum
96.00
cum
8
8
8
8
8
8
8
8
8
8
8
8
8
8
8
9
153.60
cum
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
9
656.93
1.00
C=
100904.45
390061.12
436192.52
TOTAL
(A + B +C)
5.00
436192.52
21809.63
10.00
458002.15
45800.22
384.00
cum
(F ) Seigniorage charges
Metal
0.00
300.00
cum
1.00
0.00
503802.37
1679.34
1679.00
0.40
2.00
10.00
day
day
day
0.0
A=
138.00
714.00
2950.00
3802.00
0.00
3802.00
3216.00
2678.30
422.00
624.00
1.00
1.00
1.00
1.00
B=
19296.00
16069.80
5064.00
1872.00
42301.80
1111.93
1.00
149443.39
894.43
1.00
42932.64
656.93
1.00
C=
132437.09
324813.12
370916.92
345.00
357.00
295.00
3802.00
TOTAL
6.00
6.00
12.00
3.00
hour
hour
hour
hour
(B) Machinery
Motor grader 3.35M Blade @50 cum/Hr.
Vibratory roller 8T
Tractor - Rotavator (223+11=234)
Water tanker 6 KL
TOTAL
1.00
1.00
1.00
(C) Material
Coarse graded Granular sub-base material as per
Table 400-1, Grading III material of MORT&H
9.5 to 4.75 mm IRC & MORT&H HBG/HBT Chips @ 35 %
Avg. rate of (9.5-11.2),(5-7)
134.40
cum
48.00
cum
cum
201.60
TOTAL
(A + B +C)
1
9
9
9
9
9
9
9
9
9
9
9
9
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
10
5.00
370916.92
18545.85
10.00
389462.77
38946.28
384.00
cum
(F ) Seigniorage charges
Metal
0.00
300.00
cum
1.00
0.00
428409.05
1428.03
1428.00
0.40
2.00
8.00
day
day
day
0.0
345.00
357.00
295.00
3212.00
A=
TOTAL
6.00
6.00
12.00
3.00
hour
hour
hour
hour
1.00
1.00
1.00
(B) Machinery
Motor grader 3.35M Blade @50 cum/Hr.
Vibratory roller 8T
Tractor - Rotavator (223+11=234)
Water tanker 6 KL
138.00
714.00
2360.00
3212.00
0.00
3212.00
3216.00
2678.30
422.00
624.00
1.00
1.00
1.00
1.00
B=
19296.00
16069.80
1177.26
1.00
158224.19
TOTAL
1872.00
37237.80
(C) Material
Coarse graded Granular sub-base material as per
Table 400-2, Grading I material of MORT&H
53-26.5 mm IRC & MORT&H HBG/HBT Chips @ 35 %
134.40
cum
172.80
cum
1256.93
1.00
217197.50
76.80
cum
656.93
1.00
C=
50452.22
425873.91
466323.71
TOTAL
(A + B +C)
5.00
466323.71
23316.19
10.00
489639.90
48963.99
1
10
10
10
10
10
10
10
10
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
11
384.00
cum
(F ) Seigniorage charges
Metal
0.00
1.00
300.00
cum
0.00
538603.89
1795.35
1795.00
0.40
2.00
8.00
day
day
day
0.0
345.00
357.00
295.00
3212.00
A=
TOTAL
6.00
12.00
6.00
3.00
hour
hour
hour
hour
1.00
1.00
1.00
(B) Machinery
Motor grader 3.35M Blade @50 cum/Hr.
Tractor - Rotavator (223+11=234)
Vibratory roller 8T
Water tanker 6 KL
138.00
714.00
2360.00
3212.00
0.00
3212.00
3216.00
422.00
2678.30
624.00
1.00
1.00
1.00
1.00
B=
19296.00
TOTAL
16069.80
1872.00
37237.80
(C) Material
Coarse graded Granular sub-base material as per
Table 400-2, Grading II of MORT&H
26.5-4.75mm IRC & MORT&H HBG/HBT Chips @ 75%
288.00
96.00
cum
1256.93
1.00
361995.84
cum
656.93
1.00
C=
63065.28
425061.12
465510.92
TOTAL
(A + B +C)
5.00
465510.92
23275.55
10.00
488786.47
48878.65
384.00
cum
(F ) Seigniorage charges
Metal
0.00
300.00
cum
1.00
0.00
537665.12
1792.22
1
11
11
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
12
7
1792.00
0.40
2.00
8.00
day
day
day
0.0
345.00
357.00
295.00
3212.00
A=
TOTAL
6.00
12.00
6.00
3.00
hour
hour
hour
hour
1.00
1.00
1.00
(B) Machinery
Motor grader 3.35M Blade @50 cum/Hr.
Tractor - Rotavator (223+11=234)
Vibratory roller 8T
Water tanker 6 KL
138.00
714.00
2360.00
3212.00
0.00
3212.00
3216.00
422.00
2678.30
624.00
1.00
1.00
1.00
1.00
B=
19296.00
998.60
1.00
254642.15
656.93
1.00
C=
84743.97
339386.12
379835.92
TOTAL
16069.80
1872.00
37237.80
(C) Material
Coarse graded Granular sub-base material as per
Table 400-2 of MORT&H
9.5-4.75mm IRC & MORT&H HBG/HBT Chips @ 66%
255.00
cum
129.00
cum
5.00
379835.92
18991.80
10.00
398827.72
39882.77
384.00
cum
(F ) Seigniorage charges
Metal
0.00
300.00
cum
1.00
0.00
438710.49
1462.37
1462.00
1
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
13
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
14
Scarifying the existing granular surface to a depth of 50 mm by Manual means including all labour
charges etc., complete as per MoRT&H (4th Revision) Specn. No.305.4.3 for finished item of work.
0.20
5.00
5.00
day
day
cum
0.0
345.00
295.00
42.11
1333.47
1.00
1.00
1.00
A=
TOTAL
(A )
69.00
1475.00
-210.53
1333.47
0.00
1333.47
1333.47
5.00
1333.47
66.67
10.00
1400.14
140.01
100.00
sqm
1540.15
15.40
15.40
Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of
scarified material with all leads and lifts up to 1000 m as per MoRT&H (4th Revision) Specn.
No.305.4.3
0.01
0.25
day
day
0.0
345.00
295.00
1.00
1.00
77.20
A=
TOTAL
(B) Machinery
Tractor with ripper attachment @ 60 cum per hour
Front end loader 1 cum capacity
Tipper 5.50 cum capacity, 4 trips/Hour
TOTAL
(A + B )
422.00
1646.00
922.00
1.00
1.00
1.00
B=
3.45
73.75
77.20
0.00
77.20
0.08
0.20
0.23
hour
hour
hour
33.76
329.20
212.06
575.02
652.22
5.00
652.22
32.61
10.00
684.83
68.48
100.00
sqm
753.31
7.53
7.50
1
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
15
Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade II - HBG/HBT ( IRC ) Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7&9
of MoRT&H Specification 404 of 4th Revision for Water Bound Macadam specification including
cost, conveyance and (excluding seigniorage) charges and spreading in uniform thickness, hand
packing, rolling with Power Road Roller 8- 10 Tonnes in stages to proper grade and camber applying
and brooming requisite type ' A ' screenings as per table 400-8&9 and binding materials as to fill up
the interstices of coarse aggregates, watering and compacting to the required density for finished item
of work as per MoRT&H specification 404 (4th Revision) and as directed by the Engineer-in-Charge
(Payment will be made based on levels for finished item of work)
10.08
2.00
250.00
nos.
nos.
nos.
0.0
hour
hour
(B) Machinery
smooth wheeled roller 8 Ton
water tanker 6 KL
345.00
357.00
295.00
77941.60
A=
3477.60
714.00
73750.00
77941.60
0.00
77941.60
1146.70
624.00
1.00
1.00
B=
13760.40
14976.00
28736.40
805.93
974.93
1616.93
1.00
1.00
1.00
175531.55
195356.47
28166.92
1111.93
1.00
64047.17
656.93
1.00
C=
18919.58
482021.69
588699.69
TOTAL
12.00
24.00
TOTAL
217.80
200.38
17.42
cum
cum
cum
57.60
cum
28.80
cum
(C) Material
63mm IRC HBG/HBT metal
45mm IRC HBG/HBT metal
22.40 mm IRC HBG/HBT M/C metal
Screenings 13.2mm@ 0.12cum/10sqm
(Ave of 9.5-11.2 mm & 5-7 mm M/C )
Binding material @ 0.06 cum / 10sqm
(Rate of 2.36mm & Below)
TOTAL
(A + B +C)
1.00
1.00
1.00
5.00
588699.69
29434.98
10.00
618134.67
61813.47
522.00
cum
(F ) Seigniorage charges
Metal
0.00
360.00
cum
1.00
0.00
679948.14
1888.74
1889.00
1
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
16
Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade III -HBG/HBT ( IRC ) Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7&
9 of MoRT&H Specification 404 of 4th Revision for Water Bound Macadam specification including
cost, conveyance and (excluding seigniorage) charges and spreading in uniform thickness, hand
packing, rolling with Power Road Roller 8- 10 Tonnes in stages to proper grade and camber applying
and brooming requisite type ' B ' screenings as per table 400-8&9 and binding materials to fill up the
interstices of coarse aggregates, watering and compacting to the required density for finished item of
work as per MoRT&H specification 404 (4th Revision) and as directed by the Engineer-in-Charge
(Payment will be made based on levels for finished item of work)
10.08
2.00
250.00
nos.
nos.
nos.
0.0
345.00
357.00
295.00
A=
3477.60
714.00
73750.00
77941.60
0.00
77941.60
1146.70
624.00
1.00
1.00
B=
13760.40
14976.00
28736.40
974.93
1616.93
1.00
1.00
348235.25
126783.48
714.43
1.00
61726.75
656.93
1.00
C=
18919.58
555665.06
662343.06
77941.60
TOTAL
12.00
24.00
hour
hour
(B) Machinery
smooth wheeled roller 8 Ton
water tanker 6 KL
TOTAL
357.19
78.41
cum
cum
86.40
cum
28.80
cum
1.00
1.00
1.00
(C) Material
45mm IRC HBG/HBT metal
22.40mm IRC HBG/HBT M/C metal
Screenings 11.2mm @0.18cum/10sqm
Avg. of (2.36-5),( 2.36mm & below)
Binding material @ 0.06 cum / 10sqm
(Rate of 2.36mm & Below)
TOTAL
(A + B +C)
5.00
662343.06
33117.15
10.00
695460.21
69546.02
550.80
cum
(F ) Seigniorage charges
Metal
0.00
360.00
cum
1.00
0.00
765006.23
2125.02
2125.00
1
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
17
Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade II - HBG/HBT ( IRC ) Metal (Machine crushed metal for 45mm and below) as per Table 400-7&9 of
MoRT&H Specification 404 of 4th Revision for Water Bound Macadam specification including cost,
conveyance and (excluding seigniorage) charges and spreading in uniform thickness, hand packing,
rolling with Power Road Roller 8- 10 Tonnes in stages to proper grade and camber applying and
brooming requisite type ' A ' screenings as per table 400-8&9 and binding materials as to fill up the
interstices of coarse aggregates, watering and compacting to the required density for finished item of
work as per MoRT&H specification 404 (4th Revision) and as directed by the Engineer-in-Charge
(Payment will be made based on levels for finished item of work)
10.08
2.00
250.00
nos.
nos.
nos.
0.0
A=
3477.60
714.00
73750.00
77941.60
0.00
77941.60
1146.70
624.00
1.00
1.00
B=
13760.40
14976.00
28736.40
805.93
1121.93
1616.93
1.00
1.00
1.00
175531.55
224812.33
28166.92
1111.93
1.00
64047.17
656.93
1.00
C=
18919.58
511477.55
618155.55
345.00
357.00
295.00
77941.60
TOTAL
12.00
24.00
hour
hour
(B) Machinery
smooth wheeled roller 8 Ton
water tanker 6 KL
TOTAL
217.80
200.38
17.42
cum
cum
cum
57.60
cum
28.80
cum
(C) Material
63mm IRC HBG/HBT metal
45mm IRC HBG/HBT M/C metal
22.40 mm IRC HBG/HBT M/C metal
Screenings 13.2mm@ 0.12cum/10sqm
(Ave of 9.5-11.2 mm & 5-7 mm M/C )
Binding material @ 0.06 cum / 10sqm
(Rate of 2.36mm & Below)
TOTAL
(A + B +C)
1.00
1.00
1.00
5.00
618155.55
30907.78
10.00
649063.33
64906.33
522.00
cum
(F ) Seigniorage charges
Metal
0.00
360.00
cum
1.00
0.00
713969.66
1983.25
1983.00
1
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
18
Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade III - HBG/HBT ( IRC ) Machine crushed metal as per Table 400-7& 9 of MoRT&H Specification 404
of 4th Revision for Water Bound Macadam specification including cost, conveyance and (excluding
seigniorage) charges and spreading in uniform thickness, hand packing, rolling with Power Road
Roller 8- 10 Tonnes in stages to proper grade and camber applying and brooming requisite type ' B '
screenings as per table 400-8&9 and binding materials to fill up the interstices of coarse aggregates,
watering and compacting to the required density for finished item of work as per MoRT&H
specification 404 (4th Revision) and as directed by the Engineer-in-Charge (Payment will be made
based on levels for finished item of work)
10.08
2.00
250.00
nos.
nos.
nos.
0.0
hour
hour
(B) Machinery
smooth wheeled roller 8 Ton
water tanker 6 KL
345.00
357.00
295.00
77941.60
A=
3477.60
714.00
73750.00
77941.60
0.00
77941.60
1146.70
624.00
1.00
1.00
B=
13760.40
14976.00
28736.40
1121.9300
1616.93
1.00
1.00
400742.18
126783.48
714.43
1.00
61726.75
656.93
1.00
C=
18919.58
608171.99
714849.99
TOTAL
12.00
24.00
TOTAL
357.19
78.41
cum
cum
86.40
cum
28.80
cum
(C) Material
45mm IRC HBG/HBT M/C metal
22.40mm IRC HBG/HBT M/C metal
Screenings 11.2mm @0.18cum/10sqm
Avg. of (2.36-5),( 2.36mm & below)
Binding material @ 0.06 cum / 10sqm
(Rate of 2.36mm & Below)
TOTAL
(A + B +C)
1.00
1.00
1.00
5.00
714849.99
35742.50
10.00
750592.49
75059.25
550.80
cum
(F ) Seigniorage charges
Metal
0.00
360.00
cum
1.00
0.00
825651.74
2293.48
2293.00
1
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
19
Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade II - HBG/HBT ( IRC ) Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7&9
of MoRT&H Specification 404 of 4th Revision for Water Bound Macadam specification including
cost, conveyance and (excluding seigniorage) charges and spreading in uniform thickness, hand
packing, rolling with Vibratory Road Roller 8- 10 Tonnes in stages to proper grade and camber
applying and brooming requisite type ' A ' screenings as per table 400-8&9 and binding materials as
to fill up the interstices of coarse aggregates, watering and compacting to the required density for
finished item of work as per MoRT&H specification 404 (4th Revision) and as directed by the
Engineer-in-Charge (Payment will be made based on levels for finished item of work)
10.08
2.00
250.00
nos.
nos.
nos.
0.0
A=
3477.60
714.00
73750.00
77941.60
0.00
77941.60
2678.30
624.00
1.00
1.00
B=
16069.80
14976.00
31045.80
805.93
974.93
1616.93
1.00
1.00
1.00
175531.55
195356.47
28166.92
1111.93
1.00
64047.17
656.93
1.00
C=
18919.58
482021.69
591009.09
345.00
357.00
295.00
77941.60
TOTAL
6.00
24.00
hour
hour
(B) Machinery
Vibratory road roller 8 Ton
water tanker 6 KL
TOTAL
217.80
200.38
17.42
cum
cum
cum
57.60
cum
28.80
cum
1.00
1.00
1.00
(C) Material
63mm IRC HBG/HBT metal
45mm IRC HBG/HBT metal
22.40 mm IRC HBG/HBT M/C metal
Screenings 13.2mm@ 0.12cum/10sqm
(Ave of 9.5-11.2 mm & 5-7 mm M/C )
Binding material @ 0.06 cum / 10sqm
(Rate of 2.36mm & Below)
TOTAL
(A + B +C)
5.00
591009.09
29550.45
10.00
620559.54
62055.95
522.00
cum
(F ) Seigniorage charges
Metal
0.00
360.00
cum
1.00
0.00
682615.49
1896.15
1896.00
1
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
20
Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade III - HBG/HBT ( IRC ) Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7&
9 of MoRT&H Specification 404 of 4th Revision for Water Bound Macadam specification including
cost, conveyance and (excluding seigniorage) charges and spreading in uniform thickness, hand
packing, rolling with Vibratory Road Roller 8- 10 Tonnes in stages to proper grade and camber
applying and brooming requisite type ' B ' screenings as per table 400-8&9 and binding materials to
fill up the interstices of coarse aggregates, watering and compacting to the required density for
finished item of work as per MoRT&H specification 404 (4th Revision) and as directed by the
Engineer-in-Charge (Payment will be made based on levels for finished item of work)
10.08
2.00
250.00
nos.
nos.
nos.
0.0
hour
hour
(B) Machinery
Vibratory road roller 8 Ton
water tanker 6 KL
345.00
357.00
295.00
77941.60
A=
3477.60
714.00
73750.00
77941.60
0.00
77941.60
2678.30
624.00
1.00
1.00
B=
16069.80
14976.00
31045.80
974.93
1616.93
1.00
1.00
348235.25
126783.48
714.43
1.00
61726.75
656.93
1.00
C=
18919.58
555665.06
664652.46
TOTAL
6.00
24.00
TOTAL
357.19
78.41
cum
cum
86.40
cum
28.80
cum
(C) Material
45mm IRC HBG/HBT metal
22.40mm IRC HBG/HBT M/C metal
Screenings 11.2mm @0.18cum/10sqm
Avg. of (2.36-5),( 2.36mm & below)
Binding material @ 0.06 cum / 10sqm
(Rate of 2.36mm & Below)
TOTAL
(A + B +C)
1.00
1.00
1.00
5.00
664652.46
33232.62
10.00
697885.08
69788.51
550.80
cum
(F ) Seigniorage charges
Metal
0.00
360.00
cum
1.00
0.00
767673.59
2132.43
2132.00
1
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
21
Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade II - HBG/HBT ( IRC ) Metal (Machine crushed metal for 45mm and below) as per Table 400-7&9 of
MoRT&H Specification 404 of 4th Revision for Water Bound Macadam specification including cost,
conveyance and (excluding seigniorage) charges and spreading in uniform thickness, hand packing,
rolling with Vibratory Road Roller 8- 10 Tonnes in stages to proper grade and camber applying and
brooming requisite type ' A ' screenings as per table 400-8&9 and binding materials as to fill up the
interstices of coarse aggregates, watering and compacting to the required density for finished item of
work as per MoRT&H specification 404 (4th Revision) and as directed by the Engineer-in-Charge
(Payment will be made based on levels for finished item of work)
10.08
2.00
250.00
nos.
nos.
nos.
0.0
hour
hour
(B) Machinery
Vibratory road roller 8 Ton
water tanker 6 KL
A=
3477.60
714.00
73750.00
77941.60
0.00
77941.60
2678.30
624.00
1.00
1.00
B=
16069.80
14976.00
31045.80
805.93
1121.93
1616.93
1.00
1.00
1.00
175531.55
224812.33
28166.92
1111.93
1.00
64047.17
656.93
1.00
C=
18919.58
511477.55
620464.95
345.00
357.00
295.00
77941.60
TOTAL
6.00
24.00
TOTAL
217.80
200.38
17.42
cum
cum
cum
57.60
cum
28.80
cum
(C) Material
63mm IRC HBG/HBT metal
45mm IRC HBG/HBT M/C metal
22.40 mm IRC HBG/HBT M/C metal
Screenings 13.2mm@ 0.12cum/10sqm
(Ave of 9.5-11.2 mm & 5-7 mm M/C )
Binding material @ 0.06 cum / 10sqm
(Rate of 2.36mm & Below)
TOTAL
(A + B +C)
1.00
1.00
1.00
5.00
620464.95
31023.25
10.00
651488.20
65148.82
522.00
cum
(F ) Seigniorage charges
Metal
0.00
360.00
cum
1.00
0.00
716637.02
1990.66
1991.00
1
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
22
Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade III - HBG/HBT. ( IRC ) Machine crushed metal as per Table 400-7& 9 of MoRT&H Specification 404
of 4th Revision for Water Bound Macadam specification including cost, conveyance and (excluding
seigniorage) charges and spreading in uniform thickness, hand packing, rolling with Vibratory Road
Roller 8- 10 Tonnes in stages to proper grade and camber applying and brooming requisite type ' B '
screenings as per table 400-8&9 and binding materials to fill up the interstices of coarse aggregates,
watering and compacting to the required density for finished item of work as per MoRT&H
specification 404 (4th Revision) and as directed by the Engineer-in-Charge (Payment will be made
based on levels for finished item of work)
10.08
2.00
250.00
nos.
nos.
nos.
0.0
345.00
357.00
295.00
A=
3477.60
714.00
73750.00
77941.60
0.00
77941.60
2678.30
624.00
1.00
1.00
B=
16069.80
14976.00
31045.80
1121.93
1616.93
1.00
1.00
400742.18
126783.48
714.43
1.00
61726.75
656.93
1.00
C=
18919.58
608171.99
717159.39
77941.60
TOTAL
6.00
24.00
hour
hour
(B) Machinery
Vibratory road roller 8 Ton
water tanker 6 KL
TOTAL
357.19
78.41
cum
cum
86.40
cum
28.80
cum
1.00
1.00
1.00
(C) Material
45mm IRC HBG/HBT M/C metal
22.40mm IRC HBG/HBT M/C metal
Screenings 11.2mm @0.18cum/10sqm
Avg. of (2.36-5),( 2.36mm & below)
Binding material @ 0.06 cum / 10sqm
(Rate of 2.36mm & Below)
TOTAL
(A + B +C)
5.00
717159.39
35857.97
10.00
753017.36
75301.74
550.80
cum
(F ) Seigniorage charges
Metal
0.00
360.00
cum
1.00
0.00
828319.10
2300.89
2301.00
1
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
23
Providing, Laying, Spreading and compacting graded HBG/HBT crushed stone aggregate to Wet Mix
macadam specification including cost, (excluding seigniorage) of all materials and including
premixing the material with water at OMC in Mechanical mix plant carriage of mixed material by
tipper to site , laying in uniform layers with paver in base courses on well prepared surface and
compacting with Vibratory roller to achieve the desired density etc., as directed by the Engineer-inCharge and as per MoRT&H specification.406 (4th Revision) for finished item of work. (Payment will
be made based on levels for finished item of work)
0.48
2.00
10.00
nos.
nos.
nos.
0.0
hour
hour
hour
hour
hour
hour
(B) Machinery
Wet mix plant of 60 ton hr. capacity
Electric generating set 125 KVA
front end loader 1 cum capacity
Mechanical Paver finisher 100 TPH
Vibratory roller 8-10 T
Water tanker
345.00
357.00
295.00
3829.60
A=
165.60
714.00
2950.00
3829.60
0.00
3829.60
1646.00
1320.00
1646.00
2249.00
2678.30
624.00
1.00
1.00
1.00
1.00
1.00
1.00
B=
10863.60
7920.00
9876.00
13494.00
10445.37
1872.00
54470.97
1435.26
1.00
127881.96
TOTAL
6.60
6.00
6.00
6.00
3.90
3.00
TOTAL
(C) Material
45 to 22.40mm IRC HBG/HBT metal @ 30%
Avg. rate of (40-45), (25-27), (19-22mm )
22.4-2.36mm IRC HBG/HBT metal @ 40%
1.00
1.00
1.00
89.10
cum
118.80
cum
1194.93
1.00
141957.68
89.10
cum
656.93
1.00
C=
58532.46
328372.10
386672.67
TOTAL
(A + B +C)
5.00
386672.67
19333.63
10.00
406006.30
40600.63
297.00
cum
(F ) Seigniorage charges
Metal
0.00
225.00
cum
1.00
0.00
446606.93
1984.92
1985.00
1
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
24
25
Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG/HBT
machine crushed stone aggregates @ 0.004 cum / sqm on a layer of bitumen binder of VG 10 grade
@ 0.75 kg / sqm including cost, (excluding seigniorage) and conveyance of all materials to work site
and laid on prepared surface and rolling with 8-10 T Power Road Roller etc., complete for finished
item of work as per MoRT&H Specification 510 (4th Revision) and as directed by the Engineer-incharge.
0.44
9.00
2.00
nos.
nos.
nos.
0.0
345.00
295.00
357.00
1.00
1.00
1.00
A=
151.80
2655.00
714.00
3520.80
0.00
3520.80
357.00
507.50
1.00
1.00
2570.40
3654.00
2567.00
1.00
15402.00
922.00
1646.00
1498.00
1146.70
1.00
1.00
1.00
1.00
B=
5532.00
9876.00
8988.00
6880.20
52902.60
44545.38
1.00
300681.32
1016.93
1.00
C=
36609.48
337290.80
393714.20
3520.80
TOTAL
(B) Machinery
Mechanical broom @ 1250 sqm/hr.
Air compressor 250 cfm
Hydraulic self propelled
chip spreader @ 1500 sqm/hr.
Tipper 10Tonne capacity for carriage of stone chips
from stock pile on road side to chip spreader
Front end loader 1 cum bucket capacity
Bitumen pressure distributor @1750 sqm/hr.
smooth wheeled roller 8 Ton
TOTAL
(C) Material
Bitumen VG 10 @ 0.75 Kg/sqm
Crushed stone chippings 6 mm
nominal size @0.004 cum/sqm
TOTAL
(A + B +C)
7.20
7.20
hour
hour
6.00
hour
6.00
6.00
6.00
6.00
hour
hour
hour
hour
6.75
MT
36.00
cum
5.00
393714.20
19685.71
10.00
413399.91
41339.99
36.00
cum
(F ) Seigniorage charges
Metal
0.00
9000.00
sqm
1.00
Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG/HBT
machine crushed stone aggregates @ 0.004 cum / sqm on a layer of bitumen binder of VG 30 grade
@ 0.75 kg / sqm including cost, (excluding seigniorage) and conveyance of all materials to work site
and laid on prepared surface and rolling with 8-10 T Power Road Roller etc., complete for finished
item of work as per MoRT&H Specification 510 (4th Revision) and as directed by the Engineer-incharge.
0.00
454739.90
50.53
50.50
1
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
25
26
26
26
26
26
26
26
26
26
26
0.44
9.00
2.00
nos.
nos.
nos.
345.00
295.00
357.00
1.00
1.00
1.00
0.0
A=
151.80
2655.00
714.00
3520.80
0.00
3520.80
357.00
507.50
2567.00
1.00
1.00
1.00
2570.40
3654.00
15402.00
922.00
1646.00
1498.00
1146.70
1.00
1.00
1.00
1.00
B=
5532.00
9876.00
8988.00
6880.20
52902.60
45460.74
1.00
306860.00
1016.93
1.00
B=
36609.48
343469.48
399892.88
3520.80
TOTAL
(B) Machinery
Mechanical broom @ 1250 sqm/hr.
Air compressor 250 cfm
Hydraulic self propelled chip spreader @ 1500 sqm/hr.
Tipper 10Tonne capacity for carriage of stone chips
from stock pile on road side to chip spreader
Front end loader 1 cum bucket capacity
Bitumen pressure distributor @1750 sqm/hr.
smooth wheeled roller 8 Ton
TOTAL
(C) Material
Bitumen VG 30 @ 0.75 Kg / sqm
Crushed stone chippings 6 mm
nominal size @0.004 cum/sqm
TOTAL
(A + B +C)
7.20
7.20
6.00
hour
hour
hour
6.00
6.00
6.00
6.00
hour
hour
hour
hour
6.75
MT
36.00
cum
5.00
399892.88
19994.64
10.00
419887.52
41988.75
36.00
cum
(F ) Seigniorage charges
Metal
0.00
9000.00
sqm
1.00
461876.27
51.32
51.30
Providing and applying Prime Coat with bitumen emulsion (Medium Setting) bulk using emulsion
pressure distributor on prepared surface of Granular base including cleaning of road surface and
spraying emulsion at the rate of 70 Kg/sqm using emulsion pressure distributor for finished item of
work etc., complete for finished item of work as per MoRT&H Specification 502 (4th Revision) and
as directed by the Engineer-in-charge.
0.08
2.00
nos.
nos.
0.0
345.00
295.00
1.00
1.00
617.60
TOTAL
0.00
A=
NEW
27.60
590.00
617.60
0.00
617.60
1
26
26
26
26
26
26
26
26
26
26
26
26
26
26
26
26
26
26
26
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
27
2
2.80
2.80
2.00
1.00
hour
hour
hour
hour
(B) Machinery
Mechanical broom @ 1250 sqm/hr.
Air compressor 250 cfm
Emulsion pressure distributor @1750 sqm/hr.
water tanker 6 KL
357.00
507.50
860.00
624.00
1.00
1.00
1.00
1.00
B=
999.60
1421.00
1720.00
624.00
4764.60
MT
(C) Material
Bitumen Emulsion @ 0.70 Kgs/sqm
40549.00
1.00
C=
99345.05
99345.05
104727.25
TOTAL
2.45
TOTAL
(A + B +C)
5.00
104727.25
5236.36
10.00
109963.61
10996.36
3500.00
sqm
120959.97
34.56
34.60
Providing and applying tack coat with bitumen Emulsion (Medium setting) (Bulk) using Emulsion
pressure distributor at the rate of 0.20 Kgs per sqm on the prepared bituminous/granular surface
cleaned with mechanical broom for finished item of work as per MoRT&H Specification 503 (4th
Revision) and as directed by the Engineer-in-Charge.
0.08
2.00
no
no
0.0
345.00
295.00
A=
27.60
590.00
617.60
0.00
617.60
357.00
507.50
860.00
1.00
1.00
1.00
B=
999.60
1421.00
1720.00
4140.60
40549.00
1.00
C=
28384.30
28384.30
33142.50
617.60
TOTAL
2.80
2.80
2.00
hour
hour
hour
(B) Machinery
Mechanical broom Hydraulic @ 1250 sqm/hr.
Air compressor 250 cfm
Emulsion pressure distributor @1750 sqm/hr.
TOTAL
0.700
MT
1.00
1.00
(C) Material
Bitumen Emulsion @ 0.20 Kgs/sqm
TOTAL
(A + B +C)
5.00
33142.50
1657.13
10.00
34799.63
3479.96
3500.00
sqm
38279.59
10.94
10.90
1
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
28
29
29
29
29
29
29
29
29
29
29
29
29
Providing and applying tack coat with bitumen VG 10 Grade using Bitumen pressure distributor at the
rate of 0.20 Kgs per sqm on the prepared bituminous/granular surface cleaned with mechanical broom
for finished item of work as per MoRT&H Specification 503 (4th Revision) and as directed by the
Engineer-in-Charge.
0.08
2.00
no
no
0.0
345.00
295.00
617.60
A=
27.60
590.00
617.60
0.00
617.60
357.00
507.50
1498.00
1.00
1.00
1.00
B=
999.60
1421.00
2996.00
5416.60
44545.38
1.00
C=
31181.77
31181.77
37215.97
TOTAL
2.80
2.80
2.00
hour
hour
hour
(B) Machinery
Mechanical broom Hydraulic @ 1250 sqm/hr.
Air compressor 250 cfm
Emulsion pressure distributor @1750 sqm/hr.
TOTAL
0.700
MT
(C) Material
Bitumen VG 10 @ 0.20 Kg/sqm
1.00
1.00
TOTAL
(A + B +C)
5.00
37215.97
1860.80
10.00
39076.77
3907.68
3500.00
sqm
42984.45
12.28
12.30
Providing , laying of close graded premix surfacing material ( Mixed seal surfacing) of 20 mm
thickness by hot mix plant using HBG/HBT crushed aggregates of 13.2mm to 0.09mm (Type 'B') as
per table 500-26 of specification 512 of MoRT&H (4th Revision), premixed with bituminous binder
VG 30 grade @ 19 Kg per 10 Sqm area, including cost and (excluding seigniorage) of all materials
and transporting the hot mix to work site, laying with mechanical paver finisher to the required grade,
level and alignment, rolling with smooth wheeled roller 8 to 10 Tonnes as per MoRT&H Specification
512 (4th Revision) complete for finished item of work in all respects as directed by Engineer-incharge.
0.84
nos.
14.00
5.00
nos.
nos.
0.0
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
4130.00
1785.00
6204.80
0.00
1
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
29
30
30
30
30
30
30
30
30
30
30
30
30
hour
hour
hour
hour
hour
TOTAL
(B) Machinery
Hot mix plant 40 to 60 TPH
Generator 250 KVA
Front end loader 1 cum capacity
Mechanical Paver finisher @ 100 TPH
Smooth wheeled roller 8-10 Tonnes
6204.80
19120.00
1850.00
1646.00
2249.00
1146.70
1.00
1.00
1.00
1.00
1.00
B=
229440.00
11100.00
9876.00
13494.00
6880.20
270790.20
45460.74
1.00
885575.22
1002.93
1.00
C=
277560.88
1163136.10
1440131.10
TOTAL
(C) Material
(i) Bitumen VG 30 Grade @19 kg per 10 sqm
(ii) Aggregate
Avg. of (19-22, 12-14, 9.5-11.2, 5-7mm
and 2.36mm & below)
For Type 'B' HBG/HBT M/C aggregates
13.2mm to 0.09mm @ 0.27 cum per 10 sqm
Average rate of IRC HBG/HBT M/C metal of sizes
(12-14)(9.5-11.2)(5-7)(2.36-5)( 2.36mm&below)
TOTAL
(A + B +C)
A=
TOTAL
12.00
6.00
6.00
6.00
6.00
19.48
M.T
276.75
cum
5.00
1440131.10
72006.56
10.00
1512137.66
151213.77
276.75
cum
(F ) Seigniorage charges
Metal
0.00
10250.00
sqm
1.00
0.00
1663351.43
162.28
162.00
Providing , laying of close graded premix surfacing material ( Mixed seal surfacing) of 25 mm
thickness by hot mix plant using HBG/HBT crushed aggregates of 13.2mm to 0.09mm (Type 'B') as
per table 500-26 of specification 512 of MoRT&H (4th Revision), premixed with bituminous binder
VG 30 grade @ 23.75 Kg per 10 Sqm area, including cost and (excluding seigniorage) of all
materials and transporting the hot mix to work site, laying with mechanical paver finisher to the
required grade, level and alignment, rolling with smooth wheeled roller 8 to 10 Tonnes as per
MoRT&H Specification 512 (4th Revision) complete for finished item of work in all respects as
directed by Engineer-in-charge.
0.84
nos.
14.00
5.00
nos.
nos.
0.0
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
4130.00
1785.00
6204.80
0.00
1
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
31
31
31
31
31
31
31
31
31
31
31
hour
hour
hour
hour
hour
TOTAL
(B) Machinery
Hot mix plant 40 to 60 TPH
Generator 250 KVA
Front end loader 1 cum capacity
Mechanical Paver finisher @ 100 TPH
Smooth wheeled roller 8-10 Tonnes
6204.80
19120.00
1850.00
1646.00
2249.00
1146.70
1.00
1.00
1.00
1.00
1.00
B=
229440.00
11100.00
9876.00
10795.20
6880.20
268091.40
45460.74
1.00
885575.22
1002.93
1.00
C=
277560.88
1163136.10
1437432.30
TOTAL
(C) Material
(i) Bitumen VG 30 Grade @23.75 kg per 10 sqm
(ii) Aggregate
Avg. of (19-22, 12-14, 9.5-11.2, 5-7mm
and 2.36mm & below)
For Type 'B' HBG/HBT M/C aggregates
13.2mm to 0.09mm @ 0.27 cum per 10 sqm
Average rate of IRC HBG/HBT M/C metal of sizes
(12-14)(9.5-11.2)(5-7)(2.36-5)( 2.36mm&below)
TOTAL
(A + B +C)
A=
TOTAL
12.00
6.00
6.00
4.80
6.00
19.48
M.T
276.75
cum
5.00
1437432.30
71871.62
10.00
1509303.92
150930.39
276.75
cum
(F ) Seigniorage charges
Metal
0.00
205.00
cum
1.00
0.00
1660234.31
8098.70
202.47
202.00
Providing , laying of close graded premix surfacing material ( Mixed seal surfacing) of 25 mm
thickness by hot mix plant using HBG/HBT crushed aggregates of 13.2mm to 0.09mm (Type 'B') as
per table 500-26 of specification 512 of MoRT&H (4th Revision), premixed with bituminous binder
CRMB grade @ 23.75 Kg per 10 Sqm area, including cost and (excluding seigniorage) of all
materials and transporting the hot mix to work site, laying with mechanical paver finisher to the
required grade, level and alignment, rolling with smooth wheeled roller 8 to 10 Tonnes as per
MoRT&H Specification 512 (4th Revision) complete for finished item of work in all respects as
directed by Engineer-in-charge.
0.84
nos.
14.00
5.00
nos.
nos.
345.00
1.00
289.80
295.00
357.00
1.00
1.00
4130.00
1785.00
6204.80
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
31
32
0.0
32
32
32
32
32
32
32
32
5
6204.80
hour
hour
hour
hour
hour
TOTAL
(B) Machinery
Hot mix plant 40 to 60 TPH
Generator 250 KVA
Front end loader 1 cum capacity
Mechanical Paver finisher @ 100 TPH
Smooth wheeled roller 8-10 Tonnes
0.00
6204.80
19120.00
1850.00
1646.00
2249.00
1146.70
1.00
1.00
1.00
1.00
1.00
B=
229440.00
11100.00
9876.00
10795.20
6880.20
268091.40
46948.20
1.00
914550.94
1002.93
1.00
C=
277560.88
1192111.82
1466408.02
TOTAL
(C) Material
(i) Bitumen VG 30 Grade @23.75 kg per 10 sqm
(ii) Aggregate
Avg. of (19-22, 12-14, 9.5-11.2, 5-7mm
and 2.36mm & below)
For Type 'B' HBG/HBT M/C aggregates
13.2mm to 0.09mm @ 0.27 cum per 10 sqm
Average rate of IRC HBG/HBT M/C metal of sizes
(12-14)(9.5-11.2)(5-7)(2.36-5)( 2.36mm&below)
TOTAL
(A + B +C)
A=
TOTAL
12.00
6.00
6.00
4.80
6.00
19.48
M.T
276.75
cum
5.00
1466408.02
73320.40
10.00
1539728.42
153972.84
276.75
cum
(F ) Seigniorage charges
Metal
0.00
205.00
cum
1.00
0.00
1693701.26
8261.96
206.55
207.00
Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an average
output of 37.5 tones per hour using HBG/HBT crushed aggregates of Grading - II as per table 500-4
of MoRT&H specification 504 (4th Revision) premixed with bituminous binder of VG 30 grade @
3.3% by weight of TOTAL mixture, transported to site, laid over a previously prepared surface with
mechanical paver finisher to the required grade, level and alignment and rolled as per Clauses 501.6
and 501.7 to achieve the desired compaction for finished item of work as directed by the Engineer-inCharge including hire and operational charges all T&P and all other contingent charges necessary
including cost of (excluding seigniorage) charges on all materials etc., complete and as per
MoRT&H specification No. 504(4th Revision) .
0.84
nos.
14.00
nos.
345.00
1.00
289.80
295.00
1.00
4130.00
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
32
5.00
nos.
Mazdoor skilled
357.00
1.00
0.0
6204.80
A=
1785.00
6204.80
0.00
6204.80
19120.00
507.50
2249.00
1850.00
1646.00
1.00
1.00
1.00
1.00
1.00
229440.00
1116.50
13494.00
11100.00
9876.00
1146.70
2678.30
1.00
1.00
4472.13
10445.37
1646.00
1.00
B=
6419.40
286363.40
45460.74
1.00
675091.99
1438.18
1.00
166886.41
1111.93
1.00
129028.36
714.43
1.00
C=
41451.23
1012457.99
1305026.19
TOTAL
12.00
2.20
6.00
6.00
6.00
hour
hour
hour
hour
hour
3.90
3.90
hour
hour
3.90
hour
14.85
MT
116.04
cum
116.04
cum
TOTAL
(B) Machinery
Hot Mix Plant 40 to 60 TPH
Air Compressor 250 cfm
Mechanical Paver finisher 100 TPH
Generator 250 KVA
Front end loader 1 cum bucket capacity
Smooth wheeled roller 8-10 tones
for initial break down rolling
Vibratory roller 8 tones for intermediate rolling
Finish rolling with 6-8 tones
smooth wheeled tandem roller.
TOTAL
(C) Material
Bitumen VG 30 @ 3.3 %
of weight of mix=205x2.2=450 ton
ii) Aggregate
TOTAL weight of mix = 450 tones
weight of bitumen - 14.85 tones
Weight of aggregate = 450-14.85 = 435.15 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
Grading - II (19 mm nominal size)
25-10mm IRC & MORT&H HBG/HBT Chips @ 40%
Avg. of(25-27),(19-22),(12-14) (9.5-11.2)
10-5 mm IRC & MORT&H HBG/HBT Chips @ 40 %
Avg. of (9.5-11.2),( 5-7)
58.02
cum
5.00
1305026.19
65251.31
10.00
1370277.50
137027.75
290.10
cum
(F ) Seigniorage charges
Metal
0.00
205.00
cum
1.00
0.00
1507305.25
7352.71
7353.00
1
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
33
Providing and laying of 50mm thick Bituminous Macadam with 100-120 TPH Btch Mixt Plant/ 4060 TPH HMP using HBG/HBT crushed aggreg ates of Grading - II as per table 500-7 of MoRT&H
specification 504 (4th Revision) premixed with bituminous binder of VG 30 grade @ 3.4% by weight
of TOTAL mixture, transported to site, laid over a previously prepared surface with mechanical paver
finisher to the required grade, level and alignment and rolled as per Clauses 501.6 and 501.7 to
achieve the desired compaction for finished item of work as directed by the Engineer-in-Charge
including hire and operational charges all T&P and all other contingent charges necessary including
cost of (excluding seigniorage) charges on all materials etc., complete and as per MoRT&H
specification No. 504(4th Revision) .
0.84
nos.
14.00
5.00
nos.
nos.
0.0
6.00
2.20
6.00
6.00
6.00
hour
hour
hour
hour
hour
3.90
3.90
hour
hour
3.90
hour
15.30
MT
115.92
cum
115.92
cum
57.96
289.80
cum
TOTAL
TOTAL
(B) Machinery
Batch Mix Plant (Hot mix Plant 100 TPH capacity)
Air Compressor 250 cfm
Mechanical Paver finisher 100 TPH
Generator 250 KVA
Front end loader 1 cum bucket capacity
Smooth wheeled roller 8-10 tones
for initial break down rolling
Vibratory roller 8 tones for intermediate rolling
Finish rolling with 6-8 tones
smooth wheeled tandem roller.
TOTAL
(C) Material
Bitumen VG 30 @ 3.4 %
of weight of mix=205x2.2=450 ton
ii) Aggregate
TOTAL weight of mix = 450 tones
weight of bitumen - 15.30 tones
Weight of aggregate = 450-15.3 = 434.70 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 289.80 cum
Grading - II (19 mm nominal size)
25-10mm IRC & MORT&H HBG/HBT Chips @ 40%
Avg. of(25-27),(19-22),(12-14) (9.5-11.2)
10-5 mm IRC & MORT&H HBG/HBT Chips @ 40 %
Avg. of (9.5-11.2),( 5-7)
NEW
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
A=
4130.00
1785.00
6204.80
0.00
6204.80
24171.00
507.50
2249.00
1850.00
1646.00
1.00
1.00
1.00
1.00
1.00
145026.00
1116.50
13494.00
11100.00
9876.00
1146.70
2678.30
1.00
1.00
4472.13
10445.37
1646.00
1.00
B=
6419.40
201949.40
45460.74
1.00
695549.32
1438.18
1.00
166713.83
1111.93
1.00
128894.93
714.43
1.00
C=
41408.36
1032566.44
1
33
33
33
33
33
33
33
33
33
33
33
33
33
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
(A + B +C)
7
1240720.64
5.00
1240720.64
62036.03
10.00
1302756.67
130275.67
289.80
cum
(F ) Seigniorage charges
Metal
0.00
205.00
cum
1.00
0.00
1433032.34
6990.40
6990.00
Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an average
output of 37.5 tones per hour using HBG/HBT crushed aggregates of Grading - II as per table 500-4
of MoRT&H specification 504 (4th Revision) premixed with bituminous binder of VG 10 grade @
3.4% by weight of TOTAL mixture, transported to site, laid over a previously prepared surface with
mechanical paver finisher to the required grade, level and alignment and rolled as per Clauses 501.6
and 501.7 to achieve the desired compaction for finished item of work as directed by the Engineer-inCharge including hire and operational charges all T&P and all other contingent charges necessary
including cost of (excluding seigniorage) charges on all materials etc., complete and as per
MoRT&H specification No. 504(4th Revision) .
0.84
nos.
14.00
5.00
nos.
nos.
0.0
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
A=
4130.00
1785.00
6204.80
0.00
6204.80
19120.00
507.50
2249.00
1850.00
1646.00
1.00
1.00
1.00
1.00
1.00
229440.00
1116.50
13494.00
11100.00
9876.00
1146.70
2678.30
1.00
1.00
4472.13
10445.37
1646.00
1.00
B=
6419.40
286363.40
44545.38
1.00
681544.31
TOTAL
12.00
2.20
6.00
6.00
6.00
hour
hour
hour
hour
hour
3.90
3.90
hour
hour
3.90
hour
TOTAL
(B) Machinery
Hot Mix Plant 40 to 60 TPH
Air Compressor 250 cfm
Mechanical Paver finisher 100 TPH
Generator 250 KVA
Front end loader 1 cum bucket capacity
Smooth wheeled roller 8-10 tones
for initial break down rolling
Vibratory roller 8 tones for intermediate rolling
Finish rolling with 6-8 tones
smooth wheeled tandem roller.
TOTAL
15.30
MT
(C) Material
Bitumen VG 10 @ 3.4 %
of weight of mix=205x2.2=450 ton
ii) Aggregate
1
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
34
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
116.04
cum
116.04
cum
4
TOTAL weight of mix = 450 tones
weight of bitumen - 14.85 tones
Weight of aggregate = 450-14.85 = 435.15 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 290.1 cum
Grading - II (19 mm nominal size)
25-10mm IRC & MORT&H HBG/HBT Chips @ 40%
Avg. of(25-27),(19-22),(12-14) (9.5-11.2)
10-5 mm IRC & MORT&H HBG/HBT Chips @ 40 %
Avg. of (9.5-11.2),( 5-7)
1438.18
1.00
166886.41
1111.93
1.00
129028.36
714.43
1.00
C=
41451.23
1018910.31
1311478.51
58.02
cum
5.00
1311478.51
65573.93
10.00
1377052.44
137705.24
290.10
cum
(F ) Seigniorage charges
Metal
0.00
205.00
cum
1.00
0.00
1514757.68
7389.06
7389.00
Providing and laying of Dense Graded Bituminous Macadam with hot mix plant producing an
average output of 37.5 tones per hour using HBR/HBT crushed aggregates of Grading - II as per table
500-4 of MoRT&H Specification 504 (4th Revision) premixed with bituminous binder of VG 30
grade @ 4.50% of weight of total mixture, transported to site, laid over a previously prepared surface
with mechanical paver finisher to the required grade, level and alignment and rolled as per Clauses
501.6 and 501.7 to achieve the desired compaction for finished item of work as directed by the
Engineer-in-Charge including hire and operational charges all T&P and all other contingent charges
necessary including cost of (excluding seigniorage) charges of all materials etc., complete and as per
MoRT&H specification No. 504 (4th Revision) (Excluding VAT Charges)
0.84
nos.
14.00
5.00
nos.
nos.
0.0
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
A=
4130.00
1785.00
6204.80
0.00
6204.80
1.00
1.00
210320.00
13494.00
TOTAL
11.00
6.00
hour
hour
TOTAL
(B) Machinery
Hot Mix Plant 40 to 60 TPH
Mechanical Paver finisher 100 TPH
19120.00
2249.00
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
35
36
6.00
6.00
hour
hour
1850.00
1646.00
1.00
1.00
11100.00
9876.00
3.90
3.90
hour
hour
1146.70
2678.30
1.00
1.00
4472.13
10445.37
3.90
hour
1646.00
1.00
B=
6419.40
266126.90
45460.74
1.00
920579.99
1438.18
1.00
123611.57
1111.93
1.00
89199.02
714.43
656.93
1.00
1.00
C=
81873.68
3764.21
1219028.47
1491360.17
36
36
36
36
20.25
MT
TOTAL
(C) Material
Bitumen VG 30 @ 4.50 %
of weight of mix=205x2.2=450 ton
ii) Aggregate
TOTAL weight of mix = 450 tones
weight of bitumen - 20.25 tones
Weight of aggregate = 450-20.25 = 429.75 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.50 cum
Grading - II (19 mm nominal size)
25-10 mm IRC & MORT&H HBG/HBT Chips @ 30 %
85.95
cum
80.22
cum
114.60
5.73
cum
cum
5.00
1491360.17
74568.01
10.00
1565928.18
156592.82
286.50
cum
(F ) Seigniorage charges
Metal
0.00
205.00
cum
1.00
Providing and laying of Dense Graded Bituminous Macadam with with 100-120 TPH Batch Mix
type/ 40-60 TPH hot mix plant using HBR/HBT crushed aggregates of Grading - II as per table 50010 of MoRT&H Specification 505 (4th Revision) premixed with bituminous binder of VG 30 grade @
4.50% of weight of total mixture, transported to site, laid over a previously prepared surface with
mechanical paver finisher to the required grade, level and alignment and rolled as per Clauses 501.6
and 501.7 to achieve the desired compaction for finished item of work as directed by the Engineer-inCharge including hire and operational charges all T&P and all other contingent charges necessary
including cost of (excluding seigniorage) charges of all materials etc., complete and as per MoRT&H
specification No. 505 (4th Revision) (Excluding VAT Charges)
0.00
1722521.00
8402.54
8403.00
NEW
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
36
0.84
nos.
345.00
1.00
289.80
14.00
5.00
nos.
nos.
Mate
Mazdoor working with HMP, mechanical broom,
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of construction.
Mazdoor skilled
295.00
357.00
1.00
1.00
0.0
6204.80
A=
4130.00
1785.00
6204.80
0.00
6204.80
24171.00
2249.00
1850.00
1646.00
1.00
1.00
1.00
1.00
145026.00
13494.00
11100.00
9876.00
1146.70
2678.30
1.00
1.00
4472.13
10445.37
1646.00
1.00
B=
6419.40
200832.90
45460.74
1.00
920579.99
1438.18
1.00
123611.57
1111.93
1.00
89199.02
714.43
656.93
1.00
1.00
C=
81873.68
3764.21
1219028.47
1426066.17
6.00
6.00
6.00
6.00
hour
hour
hour
hour
3.90
3.90
hour
hour
3.90
hour
20.25
MT
85.95
cum
80.22
cum
TOTAL
TOTAL
(B) Machinery
Batch Mix Plant (Hot mix Plant 100 TPH capacity)
Mechanical Paver finisher 100 TPH
Generator 250 KVA
Front end loader 1 cum bucket capacity
Smooth wheeled roller 8-10 tones
for initial break down rolling
Vibratory roller 8 tones for intermediate rolling
Finish rolling with 6-8 tones
smooth wheeled tandem roller.
TOTAL
(C) Material
Bitumen VG 30 @ 4.50 %
of weight of mix=205x2.2=450 ton
ii) Aggregate
TOTAL weight of mix = 450 tones
weight of bitumen - 20.25 tones
Weight of aggregate = 450-20.25 = 429.75 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.50 cum
Grading - II (19 mm nominal size)
114.60
5.73
cum
cum
5.00
1426066.17
71303.31
10.00
1497369.48
149736.95
286.50
cum
(F ) Seigniorage charges
Metal
0.00
195.00
cum
1.00
0.00
1647106.43
8446.70
8447.00
1
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
37
Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using
HBG/HBT crushed aggregates of Grading -2 as per table 500-15 of specification 508 of MoRT&H
(4th Revision), premixed with bituminous binder VG 30 grade @ 5.4% of mix and filler, transporting
the hot mix to work site, laying with mechanical paver finisher to the required grade, level and
alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired
compaction as per MoRT&H Specification 508 (4th Revision) complete for finished item of work in
all respects as directed by Engineer-in-charge. (Payment will be made based on levels for finished
item of work)
0.84
nos.
14.00
5.00
nos.
nos.
0.0
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
A=
4130.00
1785.00
6204.80
0.00
6204.80
19120.00
2249.00
1850.00
1646.00
1.00
1.00
1.00
1.00
210320.00
13494.00
11100.00
9876.00
1146.70
2678.30
1.00
1.00
4472.13
10445.37
1646.00
1.00
B=
6419.40
266126.90
45460.74
1.00
1022866.65
998.60
1.00
162222.03
714.43
656.93
1.00
1.00
C=
83481.15
3744.50
1272314.33
1544646.03
TOTAL
11.00
6.00
6.00
6.00
hour
hour
hour
hour
3.90
3.90
hour
hour
3.90
hour
22.50
M.T
(B) Machinery
Hot mix plant 40 to 60 TPH
Mechanical Paver finisher @ 100 TPH
Generator 250 KVA
Front end loader 1 cum capacity
Power road roller 8 ton for initial
break down rolling
Vibratory roller 8 ton for intermediate rolling
Finish rolling with 6-8 ton
smooth wheeled tandem roller.
TOTAL
(C) Material
Bitumen VG 30 Grade@ 5.00 % of
weight of mix=205x2.2=450 ton
(ii) Aggregate
TOTAL weight of mix = 450 tones
Weight of bitumen - 22.25 tones
Weight of aggregate = 450-22.25 = 427.75 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
Grading - II (10 mm nominal size)
9.5- 4.75 mm IRC & MORT&H HBG/HBT Chips @ 57 %
162.450
cum
Avg. of (9.5-11.2),(5-7),(2.36-5),
5mm & below IRC & MORT&H HBG/HBT Chips@ 41 %
116.850
5.70
cum
cum
5.00
1544646.03
77232.30
37
37
37
37
37
37
37
37
37
38
10.00
1621878.33
285.00
cum
0.00
195.00
cum
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
7
162187.83
1.00
0.00
1784066.16
9149.06
9149.00
Providing 40mm thick compacted Bituminous Concrete by hot mix plant using HBG/HBT crushed
aggregates of Grading 2 as per table 500-18 of specification 509 of MoRT&H (4th Revision),
premixed with modified Bitumen CRMB 55 Grade @ 5% of mix and filler, transporting the hot mix to
work site, laying with hydrostatic sensor paver finisher to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MoRT&H Specification 509 (4th Revision) complete for finished item of work in all respects as
directed by Engineer-in-Charge (Payment will be made based on levels for finished item of work)
(Excluding VAT Charges)
0.84
nos.
14.00
5.00
nos.
nos.
0.0
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
A=
4130.00
1785.00
6204.80
0.00
6204.80
19120.00
2249.00
1850.00
1646.00
1.00
1.00
1.00
1.00
210320.00
13494.00
11100.00
9876.00
1146.70
2678.30
1.00
1.00
4472.13
10445.37
1646.00
1.00
B=
6419.40
266126.90
46948.20
1.00
1056334.50
TOTAL
11.00
6.00
6.00
6.00
hour
hour
hour
hour
3.90
3.90
hour
hour
3.90
hour
(B) Machinery
Hot mix plant 40 to 60 TPH
Mechanical Paver finisher @ 100 TPH
Generator 250 KVA
Front end loader 1 cum capacity
Power road roller 8 ton for initial
break down rolling
Vibratory roller 8 ton for intermediate rolling
Finish rolling with 6-8 ton.
smooth wheeled tandem roller
TOTAL
22.50
MT
(C) Material
Bitumen CRMB Grade 55 @ 5.00 %
of weight of mix=205x2.2=450 ton
ii) Aggregate
TOTAL weight of mix = 450 tones
Weight of bitumen - 22.25 tones
Weight of aggregate = 450-22.25 = 427.75 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
Grading - II (13 mm nominal size)
1
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
38
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
85.50
cum
1284.43
1.00
109818.77
1111.93
1.00
79225.01
714.43
656.93
1.00
1.00
C=
87553.40
3744.50
1336676.18
1609007.88
Avg. of (14-12),(9.5-11.2)
10-5 mm IRC & MORT&H HBG/HBT Chips @ 25 %
71.25
cum
122.55
5.70
cum
cum
5.00
1609007.88
80450.39
10.00
1689458.27
168945.83
285.00
cum
(F ) Seigniorage charges
Metal
0.00
191.00
cum
1.00
0.00
1858404.10
9729.86
9730.00
Providing 40mm thick compacted Bituminous Concrete by hot mix plant using HBG/HBT crushed
aggregates of Grading 2 as per table 500-18 of specification 509 of MoRT&H (4th Revision),
premixed with modified Bitumen VG 30 Grade @ 5% of mix and filler, transporting the hot mix to
work site, laying with hydrostatic sensor paver finisher to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per
MoRT&H Specification 509 (4th Revision) complete for finished item of work in all respects as
directed by Engineer-in-Charge (Payment will be made based on levels for finished item of work)
(Excluding VAT Charges)
0.84
nos.
14.00
5.00
nos.
nos.
0.0
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
A=
4130.00
1785.00
6204.80
0.00
6204.80
19120.00
2249.00
1850.00
1646.00
1.00
1.00
1.00
1.00
210320.00
13494.00
11100.00
9876.00
1146.70
2678.30
1.00
1.00
4472.13
10445.37
TOTAL
11.00
6.00
6.00
6.00
hour
hour
hour
hour
3.90
3.90
hour
hour
(B) Machinery
Hot mix plant 40 to 60 TPH
Mechanical Paver finisher @ 100 TPH
Generator 250 KVA
Front end loader 1 cum capacity
Power road roller 8 ton for initial
break down rolling
Vibratory roller 8 ton for intermediate rolling
Finish rolling with 6-8 ton.
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
39
40
3.90
hour
40
40
40
40
40
40
40
40
40
40
40
1646.00
1.00
B=
6419.40
266126.90
45460.74
1.00
1022866.65
1284.43
1.00
109818.77
1111.93
1.00
79225.01
714.43
656.93
1.00
1.00
C=
87553.40
3744.50
1303208.33
1575540.03
TOTAL
22.50
MT
85.50
cum
71.25
cum
122.55
5.70
cum
cum
(C) Material
Bitumen VG 30 Grade 55 @ 5.00 %
of weight of mix=205x2.2=450 ton
ii) Aggregate
TOTAL weight of mix = 450 tones
Weight of bitumen - 22.25 tones
Weight of aggregate = 450-22.25 = 427.75 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 285 cum
Grading - II (13 mm nominal size)
13.2-10 mm IRC & MORT&H HBG/HBT Chips @ 30%
Avg. of (14-12),(9.5-11.2)
10-5 mm IRC & MORT&H HBG/HBT Chips @ 25 %
5.00
1575540.03
78777.00
10.00
1654317.03
165431.70
285.00
cum
0.00
191.00
cum
1.00
1819748.73
9527.48
9527.00
Providing 40mm thick compacted Bituminous Concrete with 100-120 TPH Batch Mix type/ 40-60
TPH hot mix plant using HBG/HBT crushed aggregates of Grading 2 as per table 500-17 of
specification 507 of MoRT&H (4th Revision), premixed with modified Bitumen VG 30 Grade @ 5.4
% of mix and filler, transporting the hot mix to work site, laying with hydrostatic sensor paver finisher
to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers
to achieve the desired compaction as per MoRT&H Specification 507 (4th Revision) complete for
finished item of work in all respects as directed by Engineer-in-Charge (Payment will be made based
on levels for finished item of work) (Excluding VAT Charges)
0.84
nos.
14.00
5.00
nos.
nos.
0.0
0.00
NEW
345.00
1.00
289.80
295.00
357.00
1.00
1.00
6204.80
4130.00
1785.00
6204.80
0.00
1
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
40
41
41
41
6.00
6.00
6.00
6.00
hour
hour
hour
hour
3.90
3.90
hour
hour
3.90
hour
24.30
MT
4
TOTAL
(B) Machinery
Batch Mix Plant (Hot mix Plant 100 TPH capacity)
Mechanical Paver finisher @ 100 TPH
Generator 250 KVA
Front end loader 1 cum capacity
Power road roller 8 ton for initial
break down rolling
Vibratory roller 8 ton for intermediate rolling
Finish rolling with 6-8 ton.
smooth wheeled tandem roller
TOTAL
(C) Material
Bitumen VG 30 @ 5.40 %
of weight of mix=205x2.2=450 ton
ii) Aggregate
TOTAL weight of mix = 450 tones
Weight of bitumen - 24.30 tones
Weight of aggregate = 450-24.30 = 425.70 tones
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 283.8 cum
Grading - II (13 mm nominal size)
A=
6204.80
24171.00
2249.00
1850.00
1646.00
1.00
1.00
1.00
1.00
145026.00
13494.00
11100.00
9876.00
1146.70
2678.30
1.00
1.00
4472.13
10445.37
1646.00
1.00
B=
6419.40
200832.90
45460.74
1.00
1104695.98
1284.43
1.00
109356.37
1111.93
1.00
78891.43
714.43
656.93
1.00
1.00
C=
87184.75
3728.73
1383857.26
1590894.96
85.14
cum
Avg. of (14-12),(9.5-11.2)
10-5 mm IRC & MORT&H HBG/HBT Chips @ 25 %
70.95
cum
122.03
5.68
283.80
cum
cum
5.00
1590894.96
79544.75
10.00
1670439.71
167043.97
283.80
cum
(F ) Seigniorage charges
Metal
0.00
191.00
cum
TOTAL
(A + B +C)
1.00
Construction of Gravel shoulders including cost, (excluding seigniorage) charges and conveyance of
all materials to work site and spreading in uniform layers by approved means, on prepared surface
and compacting with vibratory roller to achieve the desired density at OMC etc., complete for finished
item of work as per MoRT&H Specification 401& 407 (4th Revision) and as directed by the
Engineer-in-charge. ( Payment will be made based on levels for finished item of work ).
0.00
1837483.68
9620.33
9620.00
1
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
41
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
0.40
2.00
8.00
day
day
day
345.00
357.00
295.00
1.00
1.00
1.00
0.0
3212.00
hour
hour
(B) Machinery
Vibratory roller 8T
Water tanker 6 KL
TOTAL
6.00
3.00
2678.30
624.00
TOTAL
384.00
cum
(C) Material
Gravel
A=
138.00
714.00
2360.00
3212.00
0.00
3212.00
1.00
1.00
B=
16069.80
1872.00
17941.80
C=
67879.68
67879.68
89033.48
176.77
TOTAL
(A + B +C)
5.00
89033.48
4451.67
10.00
93485.15
9348.52
384.00
cum
(F ) Seigniorage charges
Gravel
0.00
300.00
cum
1.00
0.00
102833.67
342.78
343.00
Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG/HBT crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost, (excluding
seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying,
Vibrating, curing etc., including all other incidental and operational charges of all T&P etc.,
complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision)
and as directed by the Engineer-in-Charge for base coarse below CC Pavement.
0.64
1.00
15.00
no
no
no
0.0
A=
220.80
357.00
4425.00
5002.80
0.00
5002.80
1161.93
1337.09
6000.00
1.00
1.00
1.00
B=
15686.06
9025.36
14580.00
39291.42
453.00
1.00
2718.00
345.00
357.00
295.00
5002.80
TOTAL
13.50
6.75
2.43
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT M/C metal
Sand at site
Cement at site
hour
( C) Machinery
Concrete mixer 0.4/0.28 cum
TOTAL
6.00
1.00
1.00
1.00
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
42
43
6.00
2.00
hour
hour
861.70
624.00
1.00
1.00
C=
5170.20
1248.00
9136.20
53430.42
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
43
TOTAL
(A + B +C)
5.00
53430.42
2671.52
10.00
56101.94
5610.19
13.50
6.75
cum
cum
(F ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
61712.13
4114.14
4114.00
Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG/HBT crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost, (excluding
seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying,
Vibrating, curing etc., including all other incidental and operational charges of all T&P etc.,
complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision)
and as directed by the Engineer-in-Charge for base coarse below CC Pavement.
0.64
1.00
15.00
no
no
no
0.0
345.00
357.00
295.00
5002.80
A=
TOTAL
13.50
6.75
3.45
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT M/C metal
Sand at site
Cement at site
hour
hour
hour
TOTAL
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
Water tanker 6 KL
220.80
357.00
4425.00
5002.80
0.00
5002.80
1161.93
1337.09
6000.00
1.00
1.00
1.00
B=
15686.06
9025.36
20700.00
45411.42
45411.42
453.00
861.70
624.00
1.00
1.00
1.00
C=
2718.00
5170.20
1248.00
9136.20
59550.42
TOTAL
6.00
6.00
2.00
1.00
1.00
1.00
TOTAL
(A + B +C)
5.00
59550.42
2977.52
10.00
62527.94
6252.79
1
43
43
43
43
43
43
43
43
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
44
13.50
6.75
cum
cum
(F ) Seigniorage charges
METAL
SAND
0.00
0.00
1.00
1.00
15.00
cum
7
0.00
0.00
68780.73
4585.38
4585.00
Vibrated cement concrete M 35 grade using 20mm & 10mm HBG/HBT crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, (excluding seigniorage) conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,
1700, 2100 & 2702 (4th Revision) and as directed by the Engineer-in-Charge for C.C Pavement.
0.86
1.50
20.00
no
no
no
0.0
345.00
357.00
295.00
6732.20
A=
TOTAL
8.10
5.40
6.75
6.33
cum
cum
cum
MT
(B) Material
Cost of 20mm HBG/HBT M/C metal
Cost of 10mm HBG/HBT M/C metal
Sand at site
Cement at site
hour
hour
TOTAL
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
296.70
535.50
5900.00
6732.20
0.00
6732.20
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
B=
13623.63
6760.42
9025.36
37980
67389.41
67389.41
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
82009.81
TOTAL
6.00
6.00
1.00
1.00
1.00
TOTAL
(A + B +C)
3.50
82009.81
2870.34
5.00
84880.15
4244.01
10.00
89124.16
8912.42
13.50
6.75
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
98036.58
6535.77
6536.00
1
44
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
45
Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG/HBT crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H and using fly ash (replacing
cement by fly ash to the extent of 15% and sand by 10%) including cost, (excluding seigniorage)
conveyance of all materials to site and labour charges, centering, machine mixing, laying, Vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision) and as directed
by the Engineer-in-Charge for base coarse below CC Pavement.
0.64
1.00
15.00
no
no
no
0.0
cum
cum
MT
MT
(B) Material
Cost of 40mm HBG/HBT M/C metal
Sand at site
Cement at site
Fly ash
345.00
357.00
295.00
5002.80
TOTAL
13.50
6.075
2.933
1.274
1161.93
1337.09
6000.00
1.00
1.00
1.00
A=
220.80
357.00
4425.00
5002.80
0.00
5002.80
1.00
1.00
1.00
15686.06
8122.82
17598.00
1.00
B=
41406.88
1.278
MT
6.00
6.00
2.00
hour
hour
hour
5.00
55545.88
2777.29
10.00
58323.17
5832.32
13.50
6.075
cum
cum
(F ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
453.00
861.70
624.00
1.00
1.00
1.00
C=
1.00
1.00
2718.00
5170.20
1248.00
9136.20
55545.88
0.00
0.00
64155.49
4277.03
4277.00
1
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
46
Vibrated cement concrete M 35 grade using 20mm & 10mm HBG/HBT crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) and
using fly ash (replacing cement by fly ash to the extent of 15% and sand by 10%) including cost,
(excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine
mixing, laying, vibrating, curing etc., including all other incidental and operational charges of all T&P
etc., complete for finished item of work as per MoRT&H specification 1500, 1700, 2100 & 2702
(4th Revision) and as directed by the Engineer-in-Charge for C.C Pavement.
0.86
1.50
20.00
no
no
no
0.0
cum
cum
cum
MT
MT
MT
(B) Material
Cost of 20mm HBG/HBT M/C metal
Cost of 10mm HBG/HBT M/C metal
Sand at site
Cement at site
Fly ash
Conveyance charges of fly ash
345.00
357.00
295.00
6732.20
TOTAL
8.10
5.40
6.08
5.381
1.576
1.576
1681.93
1251.93
1337.09
6000.00
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1.00
1.00
1.00
1.00
13623.63
6760.42
8129.51
32286
1.00
1.00
1.00
1.00
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
453.00
861.70
TOTAL
(A + B +C)
B=
60799.56
1.00
1.00
C=
2718.00
5170.20
7888.20
75419.96
3.50
75419.96
2639.70
5.00
78059.66
3902.98
10.00
81962.64
8196.26
13.50
6.080
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
90158.90
6010.59
1
46
46
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
47
48
48
48
48
48
48
48
48
48
48
48
48
7
6011.00
0.32
8.00
day
day
By MECHANICAL MEANS
Page 323 of MoRT&H SDB
Unit : Cum
Taking out put = 240 Cum
(A) Labour
Mate
Mazdoor unskilled
0.0
cum
(B) Machinery
Rate as per G.I. Ms. No 10, Dt 26/7/2005
345.00
295.00
2470.40
A=
TOTAL
240.00
1.00
1.00
13.00
TOTAL
(A + B)
1.00
B=
110.40
2360.00
2470.40
0.00
2470.40
3120.00
3120.00
5590.40
5.00
5590.40
279.52
10.00
5869.92
586.99
240.00
cum
(E ) Seigniorage charges
Earth
0.00
240.00
cum
1.00
0.00
6456.91
26.90
27.00
Earth work in excavation by Manual means for foundation of structures as per drawing and technical
specification, including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing of sides and bottom and backfilling with approved material complete
including (excluding seigniorage) charges for finished item of work as per MoRT&H specification
304(4th Revision) and as directed by the Engineer-in-Charge
0.14
3.50
day
day
By MANUAL MEANS
Page 321 of MoRT&H SDB
Unit : Cum
Taking out put = 10 Cum
(A) Labour
Mate
Mazdoor unskilled
0.0
345.00
295.00
1.00
1.00
1080.80
TOTAL
(A)
A=
48.30
1032.50
1080.80
0.00
1080.80
1080.80
1
48
48
48
48
48
48
48
48
48
48
48
48
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
49
5.00
1080.80
54.04
10.00
1134.84
113.48
10.00
cum
(D ) Seigniorage charges
Earth
0.00
10.00
cum
1.00
0.00
1248.32
124.83
125.00
Providing first class bedding with Granular material below the pipes of Hume pipe culverts suitably
compacted / rammed including cost, (excluding seigniorage) and conveyance of materials to site etc.,
complete as per drawing and MoRT&H Specification 2900 ( 4th Revision) and as directed by the
Engineer-in-Charge.
0.28
7.00
no
no
0.0
cum
(B) Material
Cost of Granular material
hour
hour
(C ) Machinery
Plate compactor/Power rammer/road roller
Water tanker 6 KL capacity
345.00
295.00
A=
96.60
2065.00
2161.60
0.00
2161.60
2161.60
176.77
1.00
B=
2121.24
2121.24
48.00
624.00
1.00
1.00
C=
120.00
31.20
151.20
4434.04
TOTAL
12.00
TOTAL
2.50
0.05
TOTAL
(A + B +C)
1.00
1.00
5.00
4434.04
221.70
10.00
4655.74
465.57
12.00
cum
(F ) Seigniorage charges
Granular material
0.00
10.00
cum
1.00
0.00
5121.31
512.13
512.00
1
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
50
51
51
51
51
51
Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG/HBT crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost, (excluding seigniorage)
conveyance of all materials to site and labour charges, centering, machine mixing, laying, Vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision) and as directed
by the Engineer-in-Charge for foundations ( Bridges )
0.64
1.00
15.00
no
no
no
0.0
A=
220.80
357.00
4425.00
5002.80
0.00
5002.80
1161.93
1337.09
6000.00
1.00
1.00
1.00
B=
15686.06
9025.36
20700.00
45411.42
453.00
861.70
624.00
1.00
1.00
1.00
C=
2718.00
5170.20
1248.00
9136.20
59550.42
345.00
357.00
295.00
5002.80
TOTAL
13.50
6.75
3.45
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT M/C metal
Sand at site
Cement at site
TOTAL
6.00
6.00
2.00
hour
hour
hour
1.00
1.00
1.00
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
Water tanker 6 KL capacity
TOTAL
(A + B +C)
5.00
59550.42
2977.52
10.00
62527.94
6252.79
13.50
6.750
cum
cum
(F ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
Providing Vibrated Cement Concrete ( 1:3:6 ) using 40mm size HBG/HBT crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost, (excluding seigniorage)
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per MoRT&H specification 1500,1700, 2200 (5th Revision) and as directed
by the Engineer-in-Charge for body walls
Page331,455 of MoRT&H SDB
Unit = cum
Taking output = 15 cum
(A) Labour
0.00
0.00
68780.73
4585.38
4585.00
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
51
52
0.64
1.00
15.00
no
no
no
Mate
Mason
Mazdoor
345.00
357.00
295.00
1.00
1.00
1.00
0.0
5002.80
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT M/C metal
Sand at site
Cement at site
hour
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
Water tanker 6 KL capacity
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
A=
220.80
357.00
4425.00
5002.80
0.00
5002.80
1161.93
1337.09
6000.00
1.00
1.00
1.00
B=
15686.06
9025.36
20700.00
45411.42
453.00
861.70
624.00
1.00
1.00
1.00
C=
2718.00
5170.20
1248.00
9136.20
59550.42
TOTAL
13.50
6.75
3.45
TOTAL
6.00
6.00
2.00
TOTAL
(A + B +C)
10.00
59550.42
5955.04
5.00
65505.46
3275.27
10.00
68780.73
6878.07
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
75658.80
5043.92
5044.00
Cost of NP3 class Hume pipes of 600 mm dia. including cost and conveyance to site including
loading unloading transportation and taxes etc. complete .
1.00
RM
1.00
RM
1.00
RM
1.00
RM
1.00
RM
1.00
RM
2099.00
41000.00
4000.00
1.00
2099.00
44000.00
3.6440
10.93
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
52
53
1.00
RM
6000.00
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
53
1.00
RM
1.00
RM
85.00
0.1829
340.00
62.186
124.37
5.00
106.00
km
km
2234.30
111.00
89.00
4.13
KM
5.00
1.00
Total Rate:
Rate per RM
89.00
437.78
2761.08
2761.08
Providing, laying Reinforced cement concrete Hume pipes of 600mm Dia., NP-3 class for pipe
culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying,
jointing of 600mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and
hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (4th
Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for
finished item of work.
0.14
0.50
3.00
no
no
no
0.0
RM
(B) Material
Cost of 600 mm Dia pipes
345.00
357.00
295.00
1111.80
A=
TOTAL
12.50
1.00
1.00
1.00
2761.08
TOTAL
(A + B)
1.00
B=
48.30
178.50
885.00
1111.80
0.00
1111.80
34513.50
34513.50
35625.30
5.00
35625.30
1781.27
10.00
37406.57
3740.66
12.50
RM
41147.23
3291.78
3292.00
1
53
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
54
55
55
55
55
55
Cost of NP3 class Hume pipes of 800 mm dia. including cost and conveyance to site including
loading unloading transportation and taxes etc. complete .
1.00
RM
1.00
RM
1.00
RM
1.00
RM
1.00
1.00
RM
RM
1.00
RM
1.00
1.00
5.00
106.00
RM
RM
km
km
3447.00
1.00
3447.00
41000.00
44000.00
10.3544
31.06
4000.00
6000.00
95.00
0.2671
340.00
90.814
181.63
3659.69
111.00
119.00
4.80
KM
5.00
1.00
Providing, laying Reinforced cement concrete Hume pipes of 800mm Dia., NP-3 class for pipe
culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying,
jointing of 800mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and
hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (4th
Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for
finished item of work.
119.00
508.80
4287.49
4287.49
1
55
55
55
55
55
55
55
55
55
55
55
55
55
55
55
55
55
55
55
55
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
56
0.18
0.50
4.00
no
no
no
(A)
Mate
Mason
Mazdoor
345.00
357.00
295.00
1.00
1.00
1.00
0.0
1420.60
A=
TOTAL
12.50
RM
(B) Material
Cost of 800 mm Dia pipes
4287.49
TOTAL
(A + B)
1.00
B=
7
62.10
178.50
1180.00
1420.60
0.00
1420.60
53593.63
53593.63
55014.23
5.00
55014.23
2750.71
10.00
57764.94
5776.49
12.50
RM
63541.43
5083.31
5083.00
Cost of NP3 class Hume pipes of 1000 mm dia. including cost and conveyance to site including
loading unloading transportation and taxes etc. complete .
1.00
RM
1.00
RM
1.00
RM
1.00
RM
1.00
RM
1.00
RM
1.00
RM
1.00
RM
1.00
RM
5379.00
5379.00
41000.00
44000.00
20.2440
1.00
60.73
4000.00
6000.00
115.00
0.4028
340.00
136.952
273.90
1
56
56
56
56
56
56
56
56
56
56
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
57
58
58
58
58
58
58
58
58
58
58
5.00
106.00
km
km
4
Revised cost = Initial cost as per Table+R1+R2
=5379+60.73+273.904
Lead Charges For 111 KM
Lead
Lead charges for First 5 KM Distance
Lead charges for balance Distance
7
5713.63
111.00
188.00
9.05
KM
5.00
1.00
Total Rate:
Rate per RM
188.00
959.30
6860.93
6860.93
Providing, laying Reinforced cement concrete Hume pipes of 1000mm Dia., NP-3 class for pipe
culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying,
jointing of 1000mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and
hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (4th
Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for
finished item of work.
0.18
0.50
4.00
no
no
no
0.0
345.00
357.00
295.00
1420.60
A=
TOTAL
12.50
RM
(B) Material
Cost of 1000 mm Dia pipes
1.00
1.00
1.00
6860.93
TOTAL
(A + B)
1.00
B=
62.10
178.50
1180.00
1420.60
0.00
1420.60
85761.63
85761.63
87182.23
5.00
87182.23
4359.11
10.00
91541.34
9154.13
12.50
RM
100695.47
8055.64
8056.00
Cost of NP3 class Hume pipes of 1200 mm dia. including cost and conveyance to site including
loading unloading transportation and taxes etc. complete .
1.00
RM
1.00
RM
1.00
RM
7477.00
41000.00
44000.00
1.00
7477.00
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
58
59
1.00
RM
27.3500
1.00
RM
(3.55+21.25*140/125)
R1= Variation (increase/ decrease) in cost
(Rs. Per meter) due to change in cost of M.S. Rods
R1 = ( S2- S1)/1000 X Ws
R1 = ( 44000 - 41000 )/ 1000 X 27.35
1.00
RM
4000.00
1.00
RM
59
59
59
59
59
59
59
59
59
59
59
59
59
59
59
59
1.00
RM
1.00
RM
82.05
6000.00
120.00
0.4976
340.00
169.184
338.37
5.00
106.00
km
km
7897.42
111.00
228.00
9.85
KM
5.00
1.00
Total Rate:
Rate per RM
228.00
1044.10
9169.52
9169.52
Providing, laying Reinforced cement concrete Hume pipes of 1200mm Dia., NP-3 class for pipe
culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying,
jointing of 1200mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and
hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (4th Revision)
and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for finished item of
work.
0.28
1.00
6.00
no
no
no
0.0
345.00
357.00
295.00
2223.60
A=
TOTAL
12.50
RM
(B) Material
Cost of 1200 mm Dia pipes
9169.52
TOTAL
(A + B)
1.00
1.00
1.00
1.00
B=
96.60
357.00
1770.00
2223.60
0.00
2223.60
114619.00
114619.00
116842.60
59
59
59
59
59
59
59
59
60
5.00
116842.60
5842.13
10.00
122684.73
12268.47
12.50
RM
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
60
61
61
61
61
61
134953.20
10796.26
10796.00
Filling in between body walls with gravel including cost ,conveyance and (excluding seigniorage) of
all materials to site etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H
Specification No. 2200 & 2907(4th Revision) and as per Drawing and technical specifications for
finished item of work
0.28
7.00
no
no
0.0
cum
(B) Material
Cost of Gravel
hour
hour
(C ) Machinery
Plate compactor/Power rammer/road roller
Water tanker 6 KL capacity
345.00
295.00
A=
96.60
2065.00
2161.60
0.00
2161.60
2161.60
176.77
1.00
B=
2121.24
2121.24
48.00
624.00
1.00
1.00
C=
120.00
31.20
151.20
4434.04
TOTAL
12.00
TOTAL
2.50
0.05
TOTAL
(A + B +C)
1.00
1.00
5.00
4434.04
221.70
10.00
4655.74
465.57
12.00
cum
(F ) Seigniorage charges
GRAVEL
0.00
10.00
cum
1.00
Providing dry rough stone revetment 300 mm thick with HBG/HBT stone of not less than 300 mm
size including cost, (excluding seigniorage) charges and conveyance of materials to site and including
labour charges for packing the stones for revetment etc., complete for finished item of work as per
MoRT&H specification 2504 ( 4th Revision ) and as directed by the Engineer-in-Charge for Pitching
of slopes
Page 522 of MoRT&H SDB
Unit = cum
Taking out put = 1 cum
(A) Labour
0.00
5121.31
512.13
512.00
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
61
62
0.04
0.35
0.75
no
no
no
Mate
Mason
Mazdoor for laying stones, filling quarry spalls
345.00
357.00
295.00
1.00
1.00
1.00
0.0
360.00
cum
cum
(B) Material
Cost of Rough stone HBG/HBT 300mm thick
Cost of stone spalls
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
62
A=
TOTAL
1.00
0.20
550.93
361.93
TOTAL
(A + B )
1.00
1.00
B=
7
13.80
124.95
221.25
360.00
0.00
360.00
550.93
72.39
623.32
983.32
5.00
983.32
49.17
10.00
1032.49
103.25
1.20
cum
(E ) Seigniorage charges
METAL
0.00
1.00
cum
1.00
0.00
1135.74
1135.74
1136.00
Providing and laying filter material with Gravel underneath pitching in slopes including cost,
(excluding seigniorage) charges and conveyance of materials to site including labour charges etc.,
complete for finished item of work as per MoRT&H Specification 2504 (4th Revision) and as directed
by the Engineer-in-Charge
0.05
0.25
1.00
no
no
no
0.0
345.00
357.00
295.00
401.50
A=
TOTAL
1.20
cum
1.00
1.00
1.00
(B) Material
Cost of gravel
176.77
TOTAL
(A + B )
1.00
B=
17.25
89.25
295.00
401.50
0.00
401.50
212.12
212.12
613.62
5.00
613.62
30.68
10.00
644.30
64.43
1.20
cum
(E ) Seigniorage charges
GRAVEL
0.00
1.00
cum
1.00
0.00
708.73
708.73
1
62
62
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
63
7
709.00
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1161.93
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
1.00
D=
9411.63
6811.82
1690.11
9025.36
24780.00
51718.92
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
7888.20
66339.32
345.00
357.00
295.00
6732.20
TOTAL
8.10
4.05
1.35
6.75
4.13
cum
cum
cum
cum
MT
TOTAL
(B) Material
Cost of 40mm HBG/HBT metal
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
6.00
6.00
1.00
1.00
1.00
TOTAL
(A + B +C)
4.00
66339.32
2653.57
15.00
68992.89
10348.93
10.00
79341.82
7934.18
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
87276.00
5818.40
5818.00
1
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
64
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG/HBT
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and
all labour charges , centering, machine mixing, laying in position, Compacting, Vibrating and curing
including all other incidental and all other operational charges of T&P required etc., complete as per
MoRT&H Specification 1500,1700, 2200 (4th Revision) for Sub structure .
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1161.93
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
1.00
B=
9411.63
6811.82
1690.11
9025.36
24780.00
51718.92
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
66339.32
345.00
357.00
295.00
6732.20
TOTAL
8.10
4.05
1.35
6.75
4.13
cum
cum
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT metal
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
TOTAL
6.00
6.00
hour
hour
1.00
1.00
1.00
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
(A + B +C)
4.00
66339.32
2653.57
5.00
68992.89
3449.64
10.00
72442.53
7244.25
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
79686.78
5312.45
5312.00
1
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
65
Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG/HBT
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and
all labour charges ,centering, machine mixing, laying in position, Compacting , Vibrating and curing
including all other incidental and all other operational charges of T&P required etc., complete as per
MoRT&H Specification 1500,1700, 2100 (4th Revision) for footings and Raft foundation .
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1161.93
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
1.00
D=
6274.42
9082.42
3380.21
9025.36
30960.00
58722.41
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
7888.20
73342.81
345.00
357.00
295.00
6732.20
TOTAL
5.40
5.40
2.70
6.75
5.16
cum
cum
cum
cum
MT
TOTAL
(B) Material
Cost of 40mm HBG/HBT metal
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
6.00
6.00
1.00
1.00
1.00
TOTAL
(A + B +C)
4.00
73342.81
2933.71
15.00
76276.52
11441.48
10.00
87718.00
8771.80
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
96489.80
6432.65
6433.00
1
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
66
Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG/HBT
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and
all labour charges , centering, machine mixing, laying in position, Compacting, Vibrating and curing
including all other incidental and all other operational charges of T&P required etc., complete as per
MoRT&H Specification 1500,1700, 2200 (4th Revision) for Sub structure .
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1161.93
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
1.00
B=
6274.42
9082.42
3380.21
9025.36
30960.00
58722.41
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
73342.81
345.00
357.00
295.00
6732.20
TOTAL
5.40
5.40
2.70
6.75
5.16
cum
cum
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT metal
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
TOTAL
6.00
6.00
hour
hour
1.00
1.00
1.00
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
(A + B +C)
10.00
73342.81
7334.28
15.00
80677.09
12101.56
10.00
92778.65
9277.87
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
102056.52
6803.77
6804.00
1
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
67
Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG/HBT crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 10002) including cost, (excluding seigniorage) conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and
operational charges of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification
1500,1600,1700 & 2200 (4th Revision ) and as directed by the Engineer-in-Charge for Bed blocks &
Backing walls
0.86
1.50
20.00
no
no
no
0.0
cum
cum
cum
MT
(B) Material
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
B=
13623.63
6760.42
9025.36
30720.00
60129.41
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
74749.81
345.00
357.00
295.00
6732.20
TOTAL
8.10
5.40
6.75
5.12
TOTAL
6.00
6.00
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
(A + B +C)
1.00
1.00
1.00
10.00
74749.81
7474.98
15.00
82224.79
12333.72
10.00
94558.51
9455.85
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
104014.36
6934.29
6934.00
1
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
68
Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG/HBT crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 10002) including cost, (excluding seigniorage) conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and
operational charges of all T&P etc., complete as per approved drawings and as directed during
execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H
specification 1500,1600,1700 & 2200 (4th Revision ) and as directed by the Engineer-in-Charge for
Deck slab
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
B=
13623.63
6760.42
9025.36
30720.00
60129.41
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
74749.81
345.00
357.00
295.00
6732.20
TOTAL
8.10
5.40
6.75
5.12
cum
cum
cum
MT
(B) Material
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
TOTAL
6.00
6.00
hour
hour
1.00
1.00
1.00
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
(A + B +C)
20.00
74749.81
14949.96
15.00
89699.77
13454.97
10.00
103154.74
10315.47
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
113470.21
7564.68
7565.00
1
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
69
Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG/HBT crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 10002) including cost, (excluding seigniorage) conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per drawing BD/1-69( A) but
excluding cost of steel and its fabrication charges as per MoRT&H specification 1500, 1600,1700,
& 2702 (4th Revision) and as directed by the Engineer-in-Charge for Wearing coat over Deck slab.
0.90
1.50
21.00
no
no
no
0.0
A=
310.50
535.50
6195.00
7041.00
0.00
7041.00
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
B=
13623.63
6760.42
9025.36
36600.00
66009.41
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
295.00
1.00
D=
663.75
663.75
81602.36
345.00
357.00
295.00
7041.00
TOTAL
8.10
5.40
6.75
6.10
cum
cum
cum
MT
(B) Material
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
TOTAL
6.00
6.00
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
2.25
no
1.00
1.00
1.00
15.00
81602.36
12240.35
10.00
93842.71
9384.27
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
103226.98
6881.80
6882.00
1
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
70
Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG/HBT crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 10002) including cost, (excluding seigniorage) conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per Approved drawing but excluding
cost of steel and its fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2704
(4th Revision) and as directed by the Engineer-in-Charge for Approach slab.
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
B=
13623.63
6760.42
9025.36
36300.00
65709.41
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
80329.81
345.00
357.00
295.00
6732.20
TOTAL
8.10
5.40
6.75
6.05
cum
cum
cum
MT
(B) Material
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
TOTAL
6.00
6.00
hour
hour
1.00
1.00
1.00
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
(A + B +C)
2.00
80329.81
1606.60
15.00
81936.41
12290.46
10.00
94226.87
9422.69
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
103649.56
6909.97
6910.00
1
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
Construction of pre cast VRCC Railing of M20 grade using HBG/HBT crushed stone aggregate of
size not exceeding 12 mm and fine aggregate conforming to table 1000-2 true to line and grade,
tolerance of vertical RCC post not to exceed 1 in 500, center to center spacing between vertical posts
not to exceed 2000mm, leaving adequate space between vertical posts for expansion including cost,
(excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine
mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all
T&P as per approved drawings and as directed during execution but excluding cost of steel and its
fabrication charges as per approved drawings and technical specifications for finished item of work
as per MoRT&H Specification 2703, 1500, 1600, 1700(4th Revision)
0.86
1.50
20.00
no
no
no
0.0
cum
cum
cum
MT
(B) Material
Cost of 12mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
0.0924
0.0832
cum
cum
0.2125
0.3881
cum
cum
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1414.43
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
B=
11456.88
6760.42
9025.36
30720.00
57962.66
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
72583.06
345.00
357.00
295.00
6732.20
TOTAL
8.10
5.40
6.75
5.12
TOTAL
6.00
6.00
hour
hour
1.00
1.00
1.00
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
(A + B +C)
12.00
72583.06
8709.97
15.00
81293.03
12193.95
10.00
93486.98
9348.70
13.50
6.750
cum
cum
(G ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
102835.68
6855.71
1
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
71
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
72
0.3881
cum
4
Cost of Railing for one side
Cost per = 6.74 M
Cost per 1 RM =
Cost per 1 RM =
Hand rails without foot paths (Output =12.719 RM)
Material
M20 grade VRCC
No. of vertical end posts = 2 x 0.30x 0.20 x0.77 =
Internal vertical posts = 6x0.18x0.20x0.77 =
hand rail in2 tier =12.719-(2x0.3+6x0.18)=11.04 RM
quantity of RCC = 2x11.04x0.115x0.165 =
0.6776
cum
6855.71
1.00
0.0924
0.1663
cum
cum
0.4189
0.6776
cum
cum
6855.7120
1.00
2660.70
394.76
395.00
4645.43
365.24
365.00
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG/HBT
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials
to site and all labour charges for machine mixing, laying in position, Compacting , Vibrating and
curing including all other incidental and all other operational charges of T&P required etc., complete
as per MoRT&H Specification 1500,1700, 2100 ,2700 (4th Revision) for leveling course
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1161.93
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
1.00
B=
9411.63
6811.82
1690.11
9025.36
24780.00
51718.92
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
66339.32
345.00
357.00
295.00
6732.20
TOTAL
8.10
4.05
1.35
6.75
4.13
cum
cum
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT metal
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
6.00
6.00
TOTAL
(A + B +C)
5.00
66339.32
1.00
1.00
1.00
3316.97
72
72
72
72
72
72
72
72
72
72
73
10.00
69656.29
13.50
6.750
cum
cum
(F ) Seigniorage charges
METAL
SAND
0.00
0.00
15.00
cum
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
73
7
6965.63
1.00
1.00
0.00
0.00
76621.92
5108.13
5108.00
Providing Grouted Revetment with rough stone (HBG/HBT) of not less than 300 mm size grouted
with 0.20 cum of CC (1:4:8) including cost, (excluding seigniorage) charges and conveyance of
materials to site and including labour charges for packing the stones for revetment etc., complete for
finished item of work as per MoRT&H specification 2504 ( 4th Revision ) and as directed by the
Engineer-in-Charge for quadrennial revetment.
0.64
1.00
15.00
no
no
no
0.0
A=
220.80
357.00
4425.00
5002.80
0.00
5002.80
1161.93
1337.09
6000.00
1.00
1.00
1.00
B=
15686.06
9025.36
14580.00
39291.42
453.00
861.70
624.00
1.00
1.00
1.00
C=
2718.00
5170.20
1248.00
9136.20
53430.42
3562.03
345.00
357.00
295.00
1.00
1.00
1.00
13.80
124.95
221.25
360.00
0.00
360.00
345.00
357.00
295.00
5002.80
TOTAL
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT M/C metal
Sand at site
Cement at site
hour
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
Water tanker 6 KL capacity
0.04
0.35
0.75
no
no
no
0.0
13.50
6.75
2.43
TOTAL
6.00
6.00
2.00
TOTAL
360.00
A=
TOTAL
0.20
1.00
cum
cum
1.00
1.00
1.00
(B) Material
Cost of CC(1:4:8)
Cost of Rough stone HBG/HBT 300mm thick
3562.03
550.93
TOTAL
(A + B )
1.00
1.00
B=
712.41
550.93
1263.34
1623.34
1
73
73
73
73
73
73
73
73
73
73
73
73
73
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
74
5.00
1623.34
81.17
10.00
1704.51
170.45
1.1800
0.090
cum
cum
(F ) Seigniorage charges
METAL
SAND
0.00
0.00
1.00
cum
1.00
1.00
0.00
0.00
1874.96
1874.96
1875.00
Back filling behind Abutments with gravel including cost ,conveyance and (excluding
seigniorage) of all materials to site etc., complete as per Clause 710.1.4 of IRC : 78and as per
MoRT&H Specification No. 2200 (4th Revision) and as per Drawing and technical specifications
for finished item of work
0.28
7.00
no
no
0.0
345.00
295.00
A=
96.60
2065.00
2161.60
0.00
2161.60
176.77
1.00
B=
2121.24
2121.24
48.00
624.00
1.00
1.00
C=
120.00
31.20
151.20
4434.04
2161.60
TOTAL
12.00
cum
(B) Material
Cost of Granular material
TOTAL
2.50
0.05
hour
hour
1.00
1.00
(C ) Machinery
Plate compactor/Power rammer/road roller
Water tanker 6 KL capacity
TOTAL
(A + B +C)
5.00
4434.04
221.70
10.00
4655.74
465.57
12.00
cum
(E ) Seigniorage charges
GRAVEL
0.00
10.00
cum
1.00
0.00
5121.31
512.13
512.00
1
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
75
76
76
76
Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm
HBG/HBT metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications
to a thickness of not less than 600mm with smaller size towards the soil and bigger size towards the
wall and provided over the entire surface behind the abutment, wing wall and return wall to the full
height compacted to a firm condition including cost and conveyance of all metal (excluding
seigniorage) charges ,and all labour charges as directed by the departmental officers as per drawing
and Technical specifications as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (4th
Revision) for finished item of work.
0.32
7.00
1.00
no
no
no
0.0
A=
110.40
2065.00
357.00
2532.40
0.00
2532.40
481.93
974.93
1.00
1.00
B=
2891.58
5849.58
8741.16
624.00
1.00
C=
37.44
37.44
11311.00
345.00
295.00
357.00
2532.40
TOTAL
6.00
6.00
cum
cum
(B) Material
Filter media of stone aggregate conforming
to clause 2504.2.2 of MoRT&H
Cost of 150mm size IRC soling stone
Cost of 40mm size IRC metal
hour
(C ) Machinery
Water tanker 6 KL capacity
TOTAL
0.06
1.00
1.00
1.00
TOTAL
(A + B +C)
5.00
11311.00
565.55
10.00
11876.55
1187.66
12.00
cum
(F ) Seigniorage charges
METAL
0.00
10.00
cum
1.00
Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement
including cutting, bending, binding rods, tying grills, placing them in position etc., complete including
cost and conveyance of binding wire and all handling charges and operational charges etc., and
including over lapping welding if required etc., complete for all R.C.C items for finished item of work
as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th Revision) and as per I.S.1786 of 1985 for Super structure of R.C.C
items.
0.00
13064.21
1306.42
1306.00
1
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
76
77
77
77
77
77
77
77
77
77
77
77
77
77
77
77
77
77
77
77
77
77
77
0.44
3.00
8.00
no
no
no
Taking output = 1 MT
(A) Labour
Mate
Black smith
Mazdoor
345.00
345.00
295.00
1.00
1.00
1.00
0.0
3546.80
MT
Kg
TOTAL
(B) Material
HYSD bars including overlaps
Binding wire ( Building SSR item no.757 )
A=
TOTAL
1.05
8.00
43000.00
70.00
TOTAL
(A + B )
1.00
1.00
B=
151.80
1035.00
2360.00
3546.80
0.00
3546.80
45150.00
560.00
45710.00
49256.80
5.00
49256.80
2462.84
10.00
51719.64
5171.96
1.00
MT
56891.60
56891.60
56892.00
Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement
including cutting, bending, binding rods, tying grills, placing them in position etc., complete including
cost and conveyance of binding wire and all handling charges and operational charges etc., and
including over lapping welding if required etc., complete for all R.C.C items for finished item of work
as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th Revision) and as per I.S.1786 of 1985 for Sub structure of R.C.C
items.
0.34
2.00
6.50
no
no
no
0.0
345.00
345.00
295.00
2724.80
A=
TOTAL
1.05
6.00
MT
Kg
1.00
1.00
1.00
(B) Material
HYSD bars including overlaps
Binding wire ( Building SSR item no.757 )
43000.00
70.00
TOTAL
(A + B )
1.00
1.00
B=
117.30
690.00
1917.50
2724.80
0.00
2724.80
45150.00
420.00
45570.00
48294.80
5.00
48294.80
2414.74
10.00
50709.54
5070.95
1.00
MT
55780.49
1
77
77
77
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
78
79
79
79
79
79
79
79
79
7
55780.49
55780.00
Rate per 1 MT
Rate per 1 MT
Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement
including cutting, bending, binding rods, tying grills, placing them in position etc., complete including
cost and conveyance of binding wire and all handling charges and operational charges etc., and
including over lapping welding if required etc., complete for all R.C.C items for finished item of work
as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th Revision) and as per I.S.1786 of 1985 for foundations of R.C.C
items.
0.40
2.00
6.00
no
no
no
0.0
345.00
345.00
295.00
2598.00
A=
TOTAL
1.05
6.00
MT
Kg
(B) Material
HYSD bars including overlaps
Binding wire ( Building SSR item no.757 )
1.00
1.00
1.00
43000.00
70.00
TOTAL
(A + B )
1.00
1.00
B=
138.00
690.00
1770.00
2598.00
0.00
2598.00
45150.00
420.00
45570.00
48168.00
5.00
48168.00
2408.40
10.00
50576.40
5057.64
1.00
MT
55634.04
55634.04
55634.00
Providing Uncoated Mild Steel bars ( Fe-250 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as
per MoRT&H specification 1600 &2200 (4th Revision) and as per I.S.1786 of 1985 .
0.28
1.50
5.50
no
no
no
345.00
345.00
295.00
1.00
1.00
1.00
96.60
517.50
1622.50
1
79
79
79
79
79
79
79
79
79
79
79
79
79
79
79
79
79
79
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
80
2
0.0
5
2236.60
A=
TOTAL
1.05
6.00
MT
Kg
TOTAL
(B) Material
Mild steel bars including overlaps
Binding wire ( Building SSR item no.757 )
44000.00
70.00
TOTAL
(A + B )
1.00
1.00
B=
7
2236.60
0.00
2236.60
46200.00
420.00
46620.00
48856.60
5.00
48856.60
2442.83
10.00
51299.43
5129.94
1.00
MT
56429.37
56429.37
56429.00
Sand filling in foundation including cost, (excluding seigniorage) and conveyance of all materials to
site and watering, tamping etc., complete for finished item of work as per MoRT&H specification
1207 (4th Revision) and as directed by the Engineer - in - Charge.
0.01
0.30
day
day
0.0
345.00
295.00
91.95
A=
TOTAL
1.20
cum
1.00
1.00
(B) Material
Sand for filling
1217.09
TOTAL
(A + B )
1.00
B=
3.45
88.50
91.95
0.00
91.95
1460.51
1460.51
1552.46
5.00
1552.46
77.62
10.00
1630.08
163.01
1.200
cum
(E ) Seigniorage charges
SAND
0.00
1.00
cum
1.00
0.00
1793.09
1793.09
1793.00
1
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
81
Providing Weep holes in VCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe
extending through the full width of the structure at 1.00m C/C in both horizontal and vertical direction
so that the weep holes in each horizontal direction is staggered from the weep holes laying above and
below lines as shown in drawing including cost and conveyance of the A.C pipes and labour charges
for cutting to required length, placing the pipe with a slope of about 1V : 20H towards stream side
face etc., complete for finished item of work for weep holes as per MoRT&H specification 2706 &
2200 (4th Revision)
0.51
1.05
MT
cum
6000.00
1481.09
1.00
1.00
a=
3060.00
1555.14
4615.14
4615.14
345.00
295.00
1.00
1.00
13.80
265.50
279.30
0.00
279.30
4894.44
TOTAL
0.04
0.90
no
no
(b) Labour
Mate
Mazdoor
0.0
279.30
b=
TOTAL
Cost per 1 Cum (a+b)
31.50
10.00
30.00
0.05
RM
no
no
cum
(A) Material
RM
collars for AC pipe
MS clamps
Cement mortar (1:3)
34.00
15.00
5.00
4894.44
1.00
1.00
1.00
1.00
A=
1071.00
150.00
150.00
244.72
1615.72
1615.72
345.00
357.00
295.00
1.00
1.00
1.00
10.35
178.50
73.75
262.60
0.00
262.60
1878.32
TOTAL
0.03
0.50
0.25
no
no
no
(B) Labour
Mate
Mason
Mazdoor
0.0
262.60
B=
TOTAL
(A + B )
5.00
1878.32
93.92
10.00
1972.24
197.22
0.0525
cum
0.00
30.00
RM
1.00
0.00
2169.46
72.32
72.30
1
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
82
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG/HBT
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming
to table 1000-2) including cost, seigniorage and conveyance of all materials to site and all labour
charges , centering, machine mixing, laying in position, Compacting, Vibrating and curing including
all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H
Specification 1500,1700, 2200 (4th Revision) for Dividers .
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1161.93
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
1.00
B=
9411.63
6811.82
1690.11
9025.36
24780.00
51718.92
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
66339.32
345.00
357.00
295.00
6732.20
TOTAL
8.10
4.05
1.35
6.75
4.13
cum
cum
cum
cum
MT
(B) Material
Cost of 40mm HBG/HBT metal
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
TOTAL
6.00
6.00
hour
hour
1.00
1.00
1.00
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
(A + B +C)
4.00
66339.32
2653.57
5.00
68992.89
3449.64
10.00
72442.53
7244.25
13.5000
6.750
cum
cum
0.00
0.00
15.00
cum
1.00
1.00
0.00
0.00
79686.78
5312.45
5312.00
1
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
83
84
84
84
84
Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG/HBT crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 10002) including cost, seigniorage conveyance of all materials to site and labour charges, centering,
machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges
of all T&P as per approved drawings and as directed during execution but excluding cost of steel and
its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (4th
Revision ) and as directed by the Engineer-in-Charge for Cover slabs over Side drains
0.86
1.50
20.00
no
no
no
0.0
A=
296.70
535.50
5900.00
6732.20
0.00
6732.20
1681.93
1251.93
1337.09
6000.00
1.00
1.00
1.00
1.00
B=
13623.63
6760.42
9025.36
30720.00
60129.41
453.00
861.70
1.00
1.00
C=
2718.00
5170.20
7888.20
74749.81
345.00
357.00
295.00
6732.20
TOTAL
8.10
5.40
6.75
5.12
cum
cum
cum
MT
(B) Material
Cost of 20mm HBG/HBT metal
Cost of 10mm HBG/HBT metal
Sand at site
Cement at site
hour
hour
(C ) Machinery
Concrete mixer 0.4/0.28 cum
Generator set 33 KVA
TOTAL
6.00
6.00
1.00
1.00
1.00
TOTAL
(A + B +C)
4.00
74749.81
2989.99
5.00
77739.80
3886.99
10.00
81626.79
8162.68
13.5000
6.750
cum
cum
0.00
0.00
15.00
cum
1.00
1.00
Plastering in CM (1:5) 12 mm thick including cost and conveyance of all materials , seigniorage
charges , labour charges , curing etc. complete for finished item of work as directed by the Engineer
-in-Charge
Page 452 & 333 of MoRT&H SDB
Unit = 10 sqm
Taking output = 10 sqm
0.00
0.00
89789.47
5985.96
5986.00
1
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
84
85
85
85
85
85
85
85
85
85
85
85
85
0.04
0.50
0.50
day
day
day
A) Labour
Mate
Mason
Mazdoor
345.00
357.00
295.00
1.00
1.00
1.00
0.0
339.80
A=
TOTAL
0.144
cum
B) Material
Cement Mortar (1:5)
3501.24
TOTAL
(A + B )
1.00
B=
7
13.80
178.50
147.50
339.80
0.00
339.80
504.18
504.18
843.98
5.00
843.98
42.20
10.00
886.18
88.62
0.1512
cum
0.00
10.00
sqm
0.303
1.05
MT
cum
1.00
974.80
97.48
97.50
Sub-Analysis
Cement Mortar (1:5)
(a) Material
Cement
Sand for Mortar
6000.00
1337.09
1.00
1.00
a=
1818.00
1403.94
3221.94
345.00
295.00
1.00
1.00
13.80
265.50
279.30
0.00
279.30
3501.24
TOTAL
0.04
0.90
day
day
(b) Labour
Mate
Mazdoor
0.0
0.00
279.30
b=
TOTAL
Rate per cum (a+b)
Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered
concrete surfaces
0.12
2.00
1.00
day
day
day
0.0
345.00
357.00
295.00
1050.40
TOTAL
b) Material
1.00
1.00
1.00
A=
41.40
714.00
295.00
1050.40
0.00
1050.40
85
85
85
85
85
85
85
85
85
85
85
85
86
6.00
Liters
Paint
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
86
240.00
1.00
B=
TOTAL
(A + B )
7
1440.00
1440.00
2490.40
5.00
2490.40
124.52
10.00
2614.92
261.49
40.00
sqm
2876.41
71.91
71.90
Providing, laying and rolling of Built-up-spray grout layer over prepared base consisting of a two
layer composite construction of compacted crushed coarse HBG/HBT aggregates using motor grader
for aggregates. key stone chips spreader may be used with application of bituminous binder of VG 10
Grade after each layer, and with key aggregates placed on top of the second layer to serve as a Base
conforming to the line, grades and cross-section specified, the compacted layer thickness being 75 mm
0.40
8.00
2.00
nos.
nos.
nos.
0.0
345.00
295.00
357.00
3212.00
1.00
1.00
1.00
A=
138.00
2360.00
714.00
3212.00
0.00
3212.00
2567.00
1.00
15402.00
1498.00
922.00
2678.30
1646.00
1.00
1.00
1.00
1.00
B=
5138.14
9220.00
16069.80
9876.00
55705.94
44545.38
1.00
400908.42
166.65
1.00
49995.33
154.39
1.00
C=
6021.05
456924.80
515842.74
6.00
hour
3.43
10.00
6.00
6.00
hour
hour
hour
hour
9.00
ton
300.00
cum
39.00
cum
5.00
515842.74
25792.14
10.00
541634.88
54163.49
1
86
86
86
86
86
86
86
86
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
87
88
88
88
88
88
88
88
88
339.00
cum
(F ) Seigniorage charges
METAL
0.00
1.00
3000.00
sqm
0.00
595798.37
198.60
199.00
Providing BT Patch work using 40 mm HBG/HBT metal with required quantity of 10-12 mm size
HBG/HBT Machine crushed key chips and VG 10 grade Bitumen including removal material in the
pot holes trimming the edges to provide vertical faces , cleaning applying tack coat , filling the pot
holes compacting with power Road Roller of 8 to 10 Tonnes finishing and blinding the surface using
stone dust/ sand , including cot of all materials T&P , and labour charges for all operations etc. at site
of complete
2.86
day
Unit = cum
Taking output = 1 cum
(A) Labour
Mazdoor
0.0
295.00
A=
843.70
843.70
0.00
843.70
1.00
309.61
B=
309.61
44545.38
1.00
1870.91
1121.93
1206.93
1.00
1.00
C=
1346.32
156.90
3374.12
0.00
1.00
0.00
4527.43
4527.43
4527.00
843.70
TOTAL
0.27
hour
(B) Machinery
Finish rolling with 6-8 ton
smooth wheeled tandem roller.
1146.70
TOTAL
0.042
M.T
1.20
0.13
cum
cum
(C) Material
Bitumen
(ii) Aggregate
40 - 45 mm IRC HBG/HBT m/c chips
9.5 to 11.2 mm IRC HBG/HBT m/c chips
TOTAL
1.33
cum
Providing B.T Patch work for pot holes using 9.5 to11.2mm HBG/HBT metal with required quantity
of 10-12 mm size HT key chips and VG 10 grade Bitumen including removal of the loose material in
the pot holes, trimming the edges to provide firm vertical faces, cleaning applying tack coat, filling
pot holes with mix duly tamping to fill up all corners, tamping and compacting with 8 to 10tons road
roller and finishing including cost of all materials , T&P and lobour charges for all operations etc.
complete for finished item of work as directed by Engineer-in-charge
2.86
day
Unit = cum
Taking output = 1 cum
(A) Labour
Mazdoor
0.0
295.00
843.70
TOTAL
A=
843.70
843.70
0.00
843.70
1
88
88
88
88
88
88
88
88
88
88
88
88
88
88
88
89
89
89
89
89
89
89
89
89
89
89
89
89
89
2
0.27
hour
(B) Machinery
Finish rolling with 6-8 ton
smooth wheeled tandem roller.
1146.70
1.00
309.61
B=
309.61
44545.38
1.00
3207.27
1206.93
1.00
C=
1605.22
4812.48
0.00
1.00
0.00
5965.79
5965.79
5966.00
TOTAL
0.072
M.T
1.33
cum
(C) Material
Bitumen VG 10 Grade
(ii) Aggregate
9.5 to 11.2 mm IRC HBG/HBT m/c chips
TOTAL
1.33
cum
(D ) Seigniorage charges
METAL
(A + B +C+D)
Rate per cum
Rate per cum
Providing BT patch work for pot holes of depth ranging from 50 to 70mm ,using 40mm HBG/HBT
metal with required quantity of 10-12 mm size HBG/HBT key chips and VG 10 grade bitumen at 42
kgs/1Cum of work for filling the pot holes and sealing the filled up pot hole with a 15mm thick layer
using 10-12mm HBG/HBT chips and VG 10 grade bitumen at 72 /Kgs /1Cum., including removal of
the loose material in the pot holes ,trimming the edges to provide firm vertical faces ,cleaning
,applying tack coat ,filling the pot holes to compacting and finishing and blinding the surface using
stone dust/sand ,including cost of all materials ,T&P and labour charges for all operations etc.,
complete.
Unit - 1 Sqm
Materials
Pot hole filling:
0.04950
0.00585
1.89000
cum
cum
Kgs
1121.93
1206.93
44.5454
1.0
1.0
1.0
55.54
7.06
84.19
1.0
1.0
1.0
24.08
1.97
48.11
0.01995
0.00300
1.08000
cum
cum
Kgs
1206.93
656.93
44.5454
10.00
88.65
8.87
89
89
TOTAL
89
Labour charges
89
17.700
A=
229.82
1.0
50.62
2.8600
no
89
15.00
50.62
7.59
89
0.0
58.21
0.00
40.00
1.80
89
89
89
89
89
89
89
0.045
cum
TOTAL
B=
60.01
89
89
89
0.045
cum
0.00
1.00
89
0.00
(A+B+C)
%
90
90
90
90
90
90
90
90
90
90
Add VAT
289.83
1.0
0.00
289.83
289.80
Providing BT patch work for pot holes of depth ranging from 25 to 35mm ,using 20-25mm HBG/HBT
metal with required quantity of 10-12 mm size HBG/HBT key chips and VG 10 grade bitumen at 72
kgs/1Cum of work for filling the pot holes and sealing the filled up pot hole with a 15mm thick layer
using 10-12mm HBG/HBT chips and VG 10 grade bitumen at 80 /Kgs /1Cum., including removal of
the loose material in the pot holes ,trimming the edges to provide firm vertical faces ,cleaning
,applying tack coat ,filling the pot holes to compacting and finishing and blinding the surface using
stone dust/sand ,including cost of all materials ,T&P and labour charges for all operations etc.,
complete.
Unit - 1 Sqm
Materials
Pot hole filling:
0.0345
0.0039
0.0030
2.1600
cum
cum
cum
Kgs
1616.93
1206.93
656.93
44.5454
1.00
1.00
1.00
1.00
55.78
4.71
1.97
96.22
90
62.46
TOTAL
90
6.25
A=
164.93
1.0
25.31
Labour charges
90
90
0.00
289.83
89
89
89
90
2.8600
no
8.850
25.31
3.80
29.11
0.00
40.00
1.20
90
90
15.00
90
0.0
90
90
90
90
0.030
cum
90
TOTAL
90
90
90
0.030
90
0.00
cum
(C ) Seigniorage charges
METAL
30.31
1.00
0.00
(A+B+C)
%
Add VAT
90
90
90
0.00
B=
195.23
195.23
1.0
0.00
195.23
195.20
1
91
Providing BT patch work for pot holes of depth ranging from 15 to 25 mm ,using 10-12mm
HBG/HBT metal and VG 10 grade bitumen at 80 kgs/1Cum of work for filling the pot holes and
sealing the filled up pot hole with a 15mm thick layer using 10-12mm HBG/HBT chips and VG 10
grade bitumen at 72 /Kgs /1Cum., including removal of the loose material in the pot holes ,trimming
the edges to provide firm vertical faces ,cleaning ,applying tack coat ,filling the pot holes to
compacting and finishing and blinding the surface using stone dust/sand ,including cost of all
materials ,T&P and labour charges for all operations etc., complete.
Unit - 1 Sqm
Materials
Pot hole filling:
91
91
91
91
91
91
91
91
91
0.0266
0.003
1.440
91
10.00
cum
cum
Kgs
1206.93
656.93
44.5454
1.0
1.0
1.0
32.10
1.97
64.15
91
34.07
TOTAL
91
3.41
A=
101.63
1.0
16.87
Labour charges
91
91
2.8600
no
5.900
16.87
2.53
19.40
0.00
40.00
0.80
91
91
15.00
91
0.0
91
91
91
91
0.020
91
TOTAL
91
91
91
0.020
91
0.00
cum
0.00
B=
20.20
1.00
0.00
(A+B+C)
%
Add VAT
121.83
121.83
1.0
91
91
91
92
92
92
92
92
92
0.00
121.83
121.80
0.62
no
345.00
1.00
213.90
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
92
93
6.00
9.00
no
no
Mason
Mazdoor
357.00
295.00
1.00
1.00
0.0
93
93
93
A=
2142.00
2655.00
5010.90
0.00
5010.90
652.93
638.93
1.00
1.00
1958.79
1597.33
1576.93
4743.24
1.00
1.00
B=
1245.77
7352.03
12153.92
17164.82
5010.90
TOTAL
3.00
2.50
cum
cum
0.79
1.55
No
cum
(B) Material
Stone = 5.50 cum
CRS Stone = 0.60 * 5.00 = 3.00
Rough Stone = 0.50 * 5.00 = 2.50
Through and bond stone
( 35 no x 0.24m x 0.24m x 0.39m = 0.79 cum )
Cement mortar (1:3)
TOTAL
(A + B )
5.00
17164.82
858.24
10.00
18023.06
1802.31
6.29
1.63
cum
cum
0.00
0.00
5.00
cum
0.51
1.05
MT
cum
1.00
1.00
19825.37
3965.07
3965.00
Sub-Analysis
Cement Mortar (1 cement:3 sand)
(a) Material
Cement
Sand for Mortar
6000.00
1337.09
1.00
1.00
a=
3060.00
1403.94
4463.94
1.00
1.00
13.80
265.50
279.30
0.00
279.30
4743.24
TOTAL
0.04
0.90
day
day
(b) Labour
Mate
Mazdoor
345.00
295.00
0.0
279.30
TOTAL
b=
0.00
0.00
1
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
93
94
94
0.10
1.20
1.20
no
no
no
(A) Labour
Mate
Mason
Mazdoor
345.00
357.00
295.00
1.00
1.00
1.00
0.0
A=
34.50
428.40
354.00
816.90
0.00
816.90
652.93
638.93
1.00
1.00
352.58
293.91
1576.93
4743.24
1.00
1.00
B=
252.31
1565.27
2464.07
3280.97
816.90
TOTAL
0.54
0.46
cum
cum
0.16
0.33
No
cum
(B) Material
Stone = 1.00 cum
CRS Stone = 0.60 * 1.00 = 0.54
Rough Stone = 0.50 * 1.00 = 0.46
Through and bond stone
( 7 no x 0.24m x 0.24m x 0.39m = 0.16 cum )
Cement mortar (1:3)
TOTAL
(A + B )
5.00
3280.97
164.05
5.00
3445.02
172.25
10.00
3617.27
361.73
1.16
0.35
cum
cum
(E ) Seigniorage charges
METAL
SAND
0.00
0.00
1.00
cum
0.51
1.05
MT
cum
1.00
1.00
3979.00
3979.00
3979.00
Sub-Analysis
Cement Mortar (1 cement:3 sand)
(a) Material
Cement
Sand for Mortar
6000.00
1337.09
1.00
1.00
a=
3060.00
1403.94
4463.94
345.00
295.00
1.00
1.00
13.80
265.50
279.30
0.00
279.30
4743.24
TOTAL
0.04
0.90
day
day
(b) Labour
Mate
Mazdoor
0.0
279.30
TOTAL
b=
0.00
0.00
1
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
94
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
95
0.020
0.250
0.250
no
no
no
Unit = cum
Taking output = 1.25 cum
(A) Labour
Mate
Mazdoor for pneumatic breaker
Mazdoor for Loading and unloading
345.00
357.00
295.00
1.00
1.00
1.00
0.0
169.90
A=
TOTAL
0.670
0.270
hour
hour
(B ) Machinery
Air compressor 250 cfm with 2 leads of
pneumatic breaker @ 1.5 cum per hour
Tractor Trolley
507.50
415.00
TOTAL
(A + B )
1.00
1.00
B=
6.90
89.25
73.75
169.90
0.00
169.90
340.03
112.05
452.08
621.98
5.00
621.98
31.10
10.00
653.08
65.31
1.25
cum
718.39
574.71
575.00
Dismantling of existing structures like culverts , bridges, retaining walls and other structures
comprising of masonry, cement, concrete, wood work , steel work, including T&P and scaffolding
wherever necessary sorting the dismantled material, disposal of unserviceable materials and stacking
the materials with all lifts and lead of 1000 m ( By Mechanical means in Rubble Masonry in
Cement Mortar)
0.030
0.750
no
no
0.0
345.00
295.00
231.60
A=
TOTAL
0.270
hour
(B ) Machinery
Tractor Trolley
1.00
1.00
415.00
TOTAL
(A + B )
1.00
B=
10.35
221.25
231.60
0.00
231.60
112.05
112.05
343.65
5.00
343.65
17.18
10.00
360.83
36.08
1.25
cum
396.91
317.53
318.00
1
96
96
96
96
96
96
97
97
97
97
97
97
98
Providing 25.4 mm mastic pads for Longitudinal joints, Transversal expansion joints and
Construction joints of approved quality including cost, conveyance and placing in position, etc.,
complete as directed by the Engineer-in-charge.
1.00
Sqm
Unit = Sqm.
(A) Material
Rate as per Building SSR Item No.197
Rate per sqm
991.00
1.00
991.00
991.00
Providing 12.7 mm mastic pads for contraction joints of approved quality including cost, conveyance
and placing in position, etc., complete as directed by the Engineer-in-charge.
1.00
Sqm
Unit = Sqm.
(A) Material
Rate as per Building SSR Item No.198
Rate per sqm
568.00
1.00
568.00
568.00
98
( A ) 50 mm thick
98
98
Unit = sqm
98
98
98
0.320
day
Mate
345.00
1.00
110.40
98
6.000
2.000
day
day
295.00
357.00
1.00
1.00
1770.00
0.0
2594.40
A=
5188.80
2567.00
1498.00
1.00
1.00
15402.00
3849.86
98
98
98
98
TOTAL
b)
Machinery
98
98
98
98
98
6.000
2.570
hour
hour
98
98
98
98
714.00
2594.40
0.00
10.000
6.000
hour
hour
922.00
2678.30
1.00
1.00
9220.00
16069.80
6.000
hour
1646.00
1.00
9876.00
B=
54417.66
98
TOTAL
98
98
98
c)
22.500
ton
Material
44545.38
1002271.05
98
98
98
270.000
cum
110.28
29774.44
98
67.500
cum
154.39
10421.06
98
TOTAL
98
(A + B +C)
6
C=
7
1042466.55
1102073.01
98
98
5.00
1102073.01
55103.65
10.00
1157176.66
115717.67
337.50
cum
(F ) Seigniorage charges
METAL
0.00
4500.00
sqm
98
98
98
98
98
98
98
98
98
98
99
1.00
0.00
1272894.33
282.87
282.90
99
99
99
Unit = sqm
99
99
99
Labour
99
0.400
day
Mate
345.00
1.00
138.00
99
99
8.000
2.000
day
day
295.00
357.00
1.00
1.00
2360.00
714.00
99
99
0.0
99
99
3212.00
3212.00
0.00
A=
6424.00
Machinery
99
99
99
6.000
hour
2567.00
1.00
15402.00
99
2.570
hour
1498.00
1.00
3849.86
922.00
2678.30
1.00
1.00
9220.00
16069.80
1646.00
1.00
9876.00
B=
54417.66
99
99
99
10.000
6.000
hour
hour
99
6.000
hour
99
TOTAL
99
99
99
99
99
c)
30.600
405.000
ton
44545.38
1.00
1363088.63
cum
197.23
1.00
79879.16
128.66
1.00
10421.06
C=
1453388.85
99
99
99
Material
81.000
cum
99
7
1514230.51
(A + B +C)
99
99
5.00
1514230.51
75711.53
10.00
1589942.04
158994.20
486.00
cum
(F ) Seigniorage charges
METAL
0.00
4500.00
cum
99
99
99
99
99
99
99
1.00
0.00
1748936.24
99
388.65
99
388.70
99
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
specification 509 and 503 for laying operations only for completion of work in all
respects and as directed by Engineer -in-Charge.
1.35
21.00
6.00
nos.
nos.
nos.
0.0
1.00
1.00
1.00
465.75
6195.00
1770.00
8430.75
0.00
8430.75
8430.75
16.86
1268.00
1.00
5072.00
209.00
1146.70
1.00
1.00
627.00
6880.20
12579.20
1.00
62.90
345.00
295.00
295.00
8430.75
TOTAL
4.00
hour
3.00
6.00
hour
hour
0.5%
(B) Machinery
Mini hot mix plant (SDB of MOST 1994-95 page 131 )
Bitumen boiler oil fired 1000 lire capacity
fitted with spray set
Three wheeled 80 -100 kN static roller
Sundries such as maintenance of diversion , traffic control and
sign boards and for quality control
Miscellaneous items such as tarring outfits, Bournal, coconut
oil, soap and wheel burrows etc.,
1
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
4
Miscellaneous items such as tarring
outfits, Bournal, coconut
oil, soap and wheel burrows etc.,
TOTAL
Cost per 500 sqm
Rate per 1.00 Sqm
7.00
1.00
0.400
nos.
nos.
nos.
( II ) TACK COAT
Unit = sqm
Taking output = 1800 sqm
(A) Labour
Hot Mazdoor
Sprayer
Trained mate / Supervisor
0.0
100.00
12742.10
12742.10
25.48
1.00
1.00
1.00
2065.00
345.00
138.00
2548.00
0.00
2548.00
2548.00
1.42
209.00
415.00
1.00
1.00
1254.00
2490.00
3744.00
3744.00
1.00
18.72
295.00
345.00
345.00
2548.00
TOTAL
6.00
6.00
hour
hour
(B) Machinery
Bitumen boiler oil fired 1500 lire capacity
fitted with spray set
Farm Tractor
Sundries
Sundries such as maintenance of diversion , traffic
control and sign boards and for quality control
Miscellaneous items such as nozzle,
joint paper, oil soap etc.,
TOTAL
Cost per 1800 sqm
Rate per 1.00 Sqm
0.5%
100.00
3862.72
3862.72
2.15
1.1050
mt
9.00
4.50
cum
cum
Unit = 1 sqm
Taking out put = 500 sqm
(A) Material
(i) Bitumen VG 10 Grade @ 22.10 kg per 10 sqm
( ii ) Aggregate
Crushed Aggregate 13.2 mm
Crushed Aggregate 11.2 mm
TOTAL
Cost per 500 sqm
Rate per 1 sqm
( B) Labour & Machinery charges
TOTAL ( A + B )
(C ) Over Head Charges
@ (5%-VAT) on Labour Component
18.28
27.63
45.91
44545.38
1.00
49222.64
1361.93
1206.93
1.00
1.00
12257.37
5431.19
66911.20
66911.20
133.82
A=
B=
45.91
179.73
1
100
100
100
100
100
100
100
100
100
100
100
100
100
100
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
2
1.00
3
%
4
@ 1.0%
18.28
1.00
7
0.18
179.91
45.91
1.00
4.59
0.0270
cum
(F ) Seigniorage charges
METAL
0.00
1.00
0.00
184.50
184.50
184.55
SEAL COAT
Unit = sqm
Taking output = 1100 sqm
1.00
1.00
22.00
6.00
nos.
nos.
nos.
nos.
(A) Labour
Mate/ Supervisor
Mazdoor ( skilled )
Mazdoor ( unskilled )
Skilled Mazdoor for checking line and levels.
345.00
345.00
295.00
295.00
0.0%
A=
TOTAL
6.50
6.00
1.00
1.00
1.00
1.00
hour
hour
(B) Machinery
Bitumen boiler oil fired 1000 lire capacity
fitted with spray set
Three wheeled 80 -100 kN static roller
Sundries
Sundries such as maintenance of diversion , traffic
control and sign boards and for quality control
Miscellaneous items such as nozzle,
joint paper, oil soap etc.,
TOTAL
0.5%
1.0800
mt
9.900
cum
(C) Material
(i) Bitumen VG 10 Grade @9.80 kg per 10 sqm
(ii) Aggregate
Crushed Aggregate of 6.70 mm size defined as passing
IS 9.5 mm Sieve and retained
on IS 2.36 mm sieve @ 0.09 cum/ 10 sqm.
TOTAL
345.00
345.00
6490.00
1770.00
8950.00
0.00
8950.00
209.00
1146.70
1.00
1.00
1358.50
6880.20
8238.70
8238.70
1.00
41.19
B=
100.00
8379.89
44545.38
1.00
48109.01
1016.93
1.00
C=
10067.61
58176.62
1
101
101
101
101
101
101
101
101
101
101
101
101
101
101
101
1.00
8950.00
1.00
D=
E=
89.50
89.50
75596.01
17329.89
1.00
F=
1732.99
1732.99
0.00
1.00
0.00
77329.00
70.30
70.00
TOTAL
10.00
9.9000
1100.00
cum
sqm
(F ) Seigniorage charges
METAL
TOTAL Cost for 1100 sqm = (E+F)
Rate per 1 sqm
Rate per 1 sqm
Amount
7
7
Executive Engineer (R&B)
(R&B) Roads, ___ ___ ___
Superintending Engineer,
(R&B) Circle, ____________
Superintending Engineer
1) Certified that the Leads provided in the lead statement are the shortest.
2) Certified that the Distances noted herein are correct.
3) Certified that the quarries are nearest and are having sufficient yield.
4) Certified that the routs shown are nearest.
5) Certified that the description of the variety of materials noted are correct to the
best of my knowledge.
6) Certified that the Land available for the road formation is sufficient and no land
acquisition is required
7) Certified that the Hard Blasted Trap is obtained by Blasting, Hence Blasting
charges are allowed on Trap metal.
8) Certified that the reach in the Estimate is not proposed in any other schemes.
9) Certified that the side earth is not available for formation, hence Barrowed soils
with 1000 m lead is provided in the estimate.
Superintending Engineer