Professional Documents
Culture Documents
2.2 REINFORCEMENT
2.2.1 INTRODUCTION
The use of plain concrete in structural work is limited, because the tensile strength of concrete is
only about 1/10th of its compressive strength. Hence if a beam with plain concrete will fail in the
bottom when the top portion can still take ten time stress. By inserting the steel bars in the
bottom of the beam to take the tensile stress, the beam is made ten times as strong as a plain
beam. Therefore a combination of concrete and steel makes for economy. When steel will
expand or compress equally together provide there is no slip of the bars in the concrete. The
deformation of both materials will be equal also.
The bond between steel and concrete is destroyed if the steel is greasy or painted, while in the
other hand slight rusting of the steel may increase the bond.
The steel and mild steel bars were the most widely used elements for the reinforcement.
Available diameters of the bars are 6, 8, 10, 12, 16, 20, 25, 32Reinforcement is bend or
deformed to get the required shapes. That process is called bar bending. According to the
bar schedule that process was done. When preparing the bar schedule the shape of the length, no
of members, and the total required bars were obtained from the structural drawings, by
calculated and scaled.
MILD STEEL
This is a soft carbon steel. It is ductile and elasticable. It has 0.25 %carbon,
99 %iron and rest of it composing of manganese, sulfur, & phosparus. The strength of this type
of steel is 250 N/mm 2. In our site these bars were used to stirrups. The outer surface of the bars is
plain rounded. It is easy to work.
TOR STEEL
It is not deformed bars widely use in the construction work. It has helical ribs running along the
surface of the bar. Due to pressure of the ribs the bond between the steel and concrete is
considerably increased. It contains .4 % carbon 7. 99 % iron. These bars used as main bars of
slabs, columns, beams..etc.
14
University of Moratuwa
Chapter 2
1.5
1.5
0.75
Walls
1.5
15
University of Moratuwa
Chapter 2
Lapping
T20
T20
Lapping length = 45 *
16
University of Moratuwa
Chapter 2
(2.)
T40
Lapping
T20
Lapping length =45 *
= 45* 20 (small bar diameter)
= 900 mm
2.2.7 CRANK OF BAR
Y
X
Y: X =1:10
2.2.8 CLEANING REINFORCEMENT
A wire brush was used to remove all loose rust and scale. Mud, form oil, paint etc, can be
removed by a solvent which is not oil based, e.g. petrel. If the steel is rusted, remember the
following point
Loose, flakey or soft rust must be removed, as it will prevent the concrete bonding to the
steel.
Heavy corrosion reduces the effective size of reinforcement, and an engineers advice
should be sought before using it.
Very light rust causes no problems and it can even improve the bond between steel and
concrete.
17
University of Moratuwa
Chapter 2
Bar must be bent accurately to the dimensions shown on the bending schedule.
Otherwise, the cover may not be obtained when the steel is positioned in the structure
fixed.
If steel has been bent and then straightened, it should not be bent again at the same point
or near the same point.
18
University of Moratuwa
Chapter 2
concrete cover specified in the drawing is obtained in the order to protect the reinforcement from
rusting or chemical attack.
Where bars cross or where there is a lapped splice, bars should be tied together with either soft
iron wire (tie wire) or specially made wire ties( bag ties).The most suitable size of wire is 1.6
mm diameter (do not use wire less than 1. 25 mm diameter). Bag ties can be obtained in various
lengths, but 150 mm is suitable for most purposes.
19
University of Moratuwa