MidAmerican Energy Company filed on persons other than the Applicant. notice.
proposed changes to its FERC Electric The Commission encourages The Commission’s Rules of Practice
Tariff, Original Volume No. 11 (Sales electronic submission of protests and and Procedure require all intervenors
Tariff) for sales of capacity and energy interventions in lieu of paper using the filing documents with the Commission
within the MidAmerican control area, to ‘‘eFiling’’ link at http://www.ferc.gov. to serve a copy of that document on
VerDate Aug<31>2005 15:18 May 01, 2006 Jkt 208001 PO 00000 Frm 00025 Fmt 4703 Sfmt 4703 E:\FR\FM\02MYN1.SGM 02MYN1
25836 Federal Register / Vol. 71, No. 84 / Tuesday, May 2, 2006 / Notices
each person in the official service list specified comment date for the applicable, and the Project Number of
for the project. Further, if an intervenor particular application, either a the particular application to which the
files comments or documents with the competing development application or a filing refers. Any of the above-named
Commission relating to the merits of an notice of intent to file such an documents must be filed by providing
issue that may affect the responsibilities application. Submission of a timely the original and the number of copies
of a particular resource agency, they notice of intent to file a development provided by the Commission’s
must also serve a copy of the document application allows an interested person regulations to: Magalie Salas, Secretary,
on that resource agency. to file the competing application no Federal Energy Regulatory Commission,
k. Description of Project: The later than 120 days after the specified 888 First Street, NE., Washington, DC
proposed project would use flows comment date for the particular 20426. A copy of any motion to
discharged from Pacific Gas & Electric’s application. A competing license intervene must also be served upon each
(PG&E) Upper Centerville Canal, application must conform with 18 CFR representative of the Applicant
licensed as Project No. 803 and consist 4.30(b) and 4.36. specified in the particular application.
of: (1) An intake located at the end of p. Notice of Intent: A notice of intent t. Agency Comments: Federal, state,
PG&E’s Upper Centerville Canal, (2) a must specify the exact name, business and local agencies are invited to file
proposed 3,800 foot penstock, (3) a address, and telephone number of the comments on the described application.
proposed powerhouse having a total prospective applicant, and must include A copy of the application may be
installed capacity of 515-kilowatts, (4) a an unequivocal statement of intent to obtained by agencies directly from the
proposed 13.8-kilovolt 1.5 mile submit, if such an application may be Applicant. If an agency does not file
transmission line, and (5) appurtenant filed, either a preliminary permit comments within the time specified for
facilities. The proposed project would application or a development filing comments, it will be presumed to
have an average annual generation of application (specify which type of have no comments. One copy of an
1,430,000 kilowatt-hours, which would application). A notice of intent must be agency’s comments must also be sent to
be sold to a local utility. served on the applicant(s) named in this the Applicant’s representatives.
l. Locations of Applications: A copy of public notice.
the application is available for q. Proposed Scope of Studies under Magalie R. Salas,
inspection and reproduction at the Permit: A preliminary permit, if issued, Secretary.
Commission in the Public Reference does not authorize construction. The [FR Doc. E6–6574 Filed 5–1–06; 8:45 am]
Room, located at 888 First Street, NE., term of the proposed preliminary permit BILLING CODE 6717–01–P
Room 2A, Washington DC 20426, or by would be 36 months. The work
calling (202) 502–8371. This filing may proposed under the preliminary permit
also be viewed on the Commission’s would include economic analysis, DEPARTMENT OF ENERGY
Web site at http://www.ferc.gov using preparation of preliminary engineering
the ‘‘eLibrary’’ link. Enter the docket plans, and a study of environmental Federal Energy Regulatory
number excluding the last three digits in impacts. Based on the results of these Commission
the docket number field to access the studies, the Applicant would decide
document. For assistance, call toll-free whether to proceed with the preparation Notice of Application Accepted for
1–866–208–3676 or e-mail of a development application to Filing and Soliciting Motions To
FERCOnlineSupport@ferc.gov. For TTY, construct and operate the project. Intervene, Protests and Comments
call (202) 502–8659. A copy is also r. Comments, Protests, or Motions to Take notice that the following
available for inspection and Intervene: Anyone may submit hydroelectric application has been filed
reproduction at the address in item h. comments, a protest, or a motion to with the Commission and is available
above. intervene in accordance with the for public inspection:
m. Individuals desiring to be included requirements of Rules of Practice and a. Type of Application: Preliminary
on the Commission’s mailing list should Procedure, 18 CFR 385.210, .211, .214. Permit.
so indicate by writing to the Secretary In determining the appropriate action to b. Project No.: 12659–000.
of the Commission. take, the Commission will consider all c. Date filed: March 6, 2006.
n. Competing Preliminary Permit: protests or other comments filed, but d. Applicant: Richard V. Williamson.
Anyone desiring to file a competing only those who file a motion to e. Name of Project: Stony Creek Water
application for preliminary permit for a intervene in accordance with the Power Project.
proposed project must submit the Commission’s Rules may become a f. Location: On Stony Creek, near
competing application itself, or a notice party to the proceeding. Any comments, Stonyford, Colusa County, California.
of intent to file such an application, to protests, or motions to intervene must The proposed project will be located
the Commission on or before the be received on or before the specified within the Mendocino National Forest.
specified comment date for the comment date for the particular g. Filed Pursuant to: Federal Power
particular application (see 18 CFR 4.36). application. Act, 16 U.S.C. 791(a)–825(r).
Submission of a timely notice of intent Comments, protests and interventions h. Applicant Contact: Mr. Richard V.
allows an interested person to file the may be filed electronically via the Williamson, 1842–M Camino Verde,
competing preliminary permit Internet in lieu of paper; See 18 CFR Walnut Creek, CA 94597, (925) 457–
application no later than 30 days after 385.2001(a)(1)(iii) and the instructions 2971.
the specified comment date for the on the Commission’s Web site under ‘‘e- i. FERC Contact: Etta Foster, (202)
particular application. A competing filing’’ link. The Commission strongly 502–8769.
preliminary permit application must encourages electronic filing. j. Deadline for filing comments,
conform with 18 CFR 4.30(b) and 4.36. s. Filing and Service of Responsive protests, and motions to intervene: 60
rmajette on PROD1PC67 with NOTICES
o. Competing Development Documents: Any filings must bear in all days from the issuance date of this
Application: Any qualified development capital letters the title ‘‘COMMENTS’’, notice.
applicant desiring to file a competing ‘‘RECOMMENDATIONS FOR TERMS All documents (original and eight
development application must submit to AND CONDITIONS’’, ‘‘PROTEST’’, or copies) should be filed with Magalie R.
the Commission, on or before a ‘‘MOTION TO INTERVENE’’, as Salas, Secretary, Federal Energy
VerDate Aug<31>2005 15:18 May 01, 2006 Jkt 208001 PO 00000 Frm 00026 Fmt 4703 Sfmt 4703 E:\FR\FM\02MYN1.SGM 02MYN1