28390 Federal Register / Vol. 71, No.

94 / Tuesday, May 16, 2006 / Notices

3. Consider and act on other business. NUCLEAR REGULATORY on the cooling time and burnup of fuel that
COMMISSION is to be loaded into the NUHOMS HD 32PTH
4. Public comment. DSC [Dry Shielded Canister] will not require
FOR FURTHER INFORMATION CONTACT: [Docket Nos. 50–280 and 50–281] any physical changes to Part 50 structures,
systems, or components, nor will there be
Patricia Batie, Manager of Board Virginia Electric and Power Company any changes to the performance requirements
Operations, at (202) 295–1500. (Dominion); Surry Power Station, Unit of existing structures, systems, or
Special Needs: Upon request, meeting Nos. 1 and 2; Notice of Consideration components. Handling of spent fuel storage
notices will be made available in of Issuance of Amendments to Facility casks has previously been evaluated for
Operating Licenses, Proposed No Surry. When older cask designs stored under
alternate formats to accommodate visual
the Surry ISFSI [Independent Spent Fuel
and hearing impairments. Individuals Significant Hazards Consideration Storage Installation] site specific license are
who have a disability and need an Determination, and Opportunity for a returned to the station, they will be handled
accommodation to attend the meeting Hearing and controlled in the same manner as the
may notify Patricia Batie at (202) 295– initial loading and movement of these casks.
The U.S. Nuclear Regulatory
1500. The response of the plant to previously
Commission (the Commission) is analyzed Part 50 accidents is not adversely
Dated: May 11, 2006. considering issuance of amendments to impacted, and current analyses of
Victor M. Fortuno, Facility Operating License Nos. DPR–32 radiological releases, including those for the
and DPR–37, issued to Virginia Electric fuel handling accident, will continue to
Vice President for Legal Affairs, General
Counsel & Corporate Secretary.
and Power Company (the licensee), for bound activities related to spent fuel cask
operation of the Surry Power Station, loading, handling, and storage.
[FR Doc. 06–4588 Filed 5–11–06; 5:16 pm] (2) The possibility of a new or different
Unit Nos. 1 and 2, located in Surry
BILLING CODE 7050–01–P County, Virginia. kind of accident from any accident
The proposed amendments would previously evaluated is not created.
Neither fuel handling nor the loading and
add a requirement to Title 10 of the handling of the NUHOMS HD 32PTH DSC
NATIONAL TRANSPORTATION Code of Federal Regulations, (10 CFR) will be affected by operation under 10 CFR
SAFETY BOARD part 50 license to restrict the minimum 50.68(b) or by placing additional constraints
cooling time and burnup of spent fuel on selection of fuel to be stored in the DSC.
Notice of Sunshine Act Meeting assemblies that will be placed into When older cask designs stored under the
storage in the NUHOMS HD spent fuel Surry ISFSI site specific license are returned
TIME: 9:30 a.m., May 23, 2006. dry storage system at Surry 1 and 2 to the station, they will be handled and
starting in the summer of 2006. controlled in the same manner as the initial
PLACE: NTSB Conference Center, 429 loading and movement of these casks. The
L’Enfant Plaza, SW., Washington, DC Specifically, the proposed amendments
existing process used to ensure that fuel
20594. would add Figure 5.4–2 to the Technical assemblies selected for dry storage comply
Specifications (TSs) to ensure that the with the specific cask and ISFSI licensing
STATUS: The two items are open to the NUHOMS HD canister remains requirements will be used to select the fuel
public. subcritical during operations in the assemblies to be placed in the NUHOMS HD
MATTERS TO BE CONSIDERED:
Surry 1 and 2 spent fuel pool. 32PTH DSC. The requirements of the
Before issuance of the proposed proposed new Technical Specification will
7768, Aircraft Accident Brief— license amendments, the Commission only represent additional limitations that
Controlled Flight Into Terrain, Learjet will have made findings required by the must be considered during this selection
Atomic Energy Act of 1954, as amended process.
35A, N30DK, San Diego, California,
(the Act), and the Commission’s (3) There is not a significant reduction in
October 24, 2004. a margin of safety.
regulations.
7758, Aircraft Accident Brief— The Commission has made a
The Code of Federal Regulations identifies
Departure From Controlled Flight, compliance with 10 CFR 50.68(b) as an
proposed determination that the acceptable alternative to compliance with 10
Learjet 24B, N600XJ, Helendale, amendments request involve no CFR 70.24. The emphasis of 10 CFR 70.24 is
California, December 23, 2003. significant hazards consideration. Under on detection of criticality events, while the
NEWS MEDIA CONTACT: Ted Lopatkiewicz, the Commission’s regulations in 10 CFR requirements of 10 CFR 50.68(b) emphasize
Telephone: (202) 314–6100. part 50, § 50.92, this means that prevention of inadvertent criticality events.
operation of the facility in accordance Operation under 10 CFR 50.68(b) is therefore
Individuals requesting specific with the proposed amendment would preferable to ensure that Surry complies with
accommodations should contact Chris not (1) involve a significant increase in the intent of General Design Criterion 62,
Bisett at (202) 314–6305 by Friday, May which specifically directs that criticality
the probability or consequences of an should be prevented during fuel storage and
19, 2006. accident previously evaluated; or (2) handling. The existing criticality limits for
The public may view the meeting via create the possibility of a new or the Surry Spent Fuel Pool and New Fuel
a live or archived Webcast by accessing different kind of accident from any Storage Area will be maintained. The
a link under ‘‘News & Events’’ on the accident previously evaluated; or (3) NUHOMS HD spent fuel storage system is
NTSB home page at http:// involve a significant reduction in a currently under review for general licensing,
www.ntsb.gov. margin of safety. As required by 10 CFR and has been shown to comply with the
50.91(a), the licensee has provided its criticality requirements identified in 10 CFR
FOR FURTHER INFORMATION CONTACT: part 72. Compliance with the proposed Surry
analysis of the issue of no significant
Vicky D’Onofrio, (202) 314–6410. Technical Specification will further ensure
hazards consideration, which is that the system remains safely subcritical
Dated: May 12, 2006. presented below: during all handling and storage operations
sroberts on PROD1PC70 with NOTICES

Vicky D’Onofrio, (1) The probability of occurrence or the (e.g., load, unloading, handling,
Federal Register Liaison Officer. consequences of an accident previously decontamination, etc.) that are conducted at
evaluated is not significantly increased. the station prior to transfer of the DSC to the
[FR Doc. 06–4618 Filed 5–12–06; 1:57am] Operation under 10 CFR 50.68 for use of ISFSI, even under the more restrictive
BILLING CODE 7533–01–M the NUHOMS HD system and condition of assuming the DSC is fully
implementation of additional requirements loaded with fuel of the maximum allowable

VerDate Aug<31>2005 16:06 May 15, 2006 Jkt 208001 PO 00000 Frm 00095 Fmt 4703 Sfmt 4703 E:\FR\FM\16MYN1.SGM 16MYN1
Federal Register / Vol. 71, No. 94 / Tuesday, May 16, 2006 / Notices 28391

reactivity and flooded with unborated water. any hearing will take place after the petitioner in the proceeding, and
Application of a fuel burnup credit in this issuance. The Commission expects that how that interest may be affected by the
criticality analysis ensures that the full the need to take this action will occur results of the proceeding. The petition
soluble boron concentration required in the very infrequently. should specifically explain the reasons
Spent Fuel Pool water by Surry plant Written comments may be submitted
Technical Specifications is available to
why intervention should be permitted
provide defense in depth to an inadvertent
by mail to the Chief, Rules and with particular reference to the
criticality event. The older cask designs Directives Branch, Division of following general requirements: (1) The
stored under the Surry ISFSI site specific Administrative Services, Office of name, address and telephone number of
license will be handled in the same manner Administration, U.S. Nuclear Regulatory the requestor or petitioner; (2) the
used to initially load and move these casks, Commission, Washington, DC 20555– nature of the requestor’s/petitioner’s
and the criticality requirements that were 0001, and should cite the publication right under the Act to be made a party
previously determined to be acceptable for date and page number of this Federal to the proceeding; (3) the nature and
safe loading, unloading and handling of these Register notice. Written comments may extent of the requestor’s/petitioner’s
casks will remain applicable. also be delivered to Room 6D59, Two property, financial, or other interest in
Based on the above discussion, Surry White Flint North, 11545 Rockville
operation under 10 CFR 50.68(b) and
the proceeding; and (4) the possible
implementation of the proposed Technical
Pike, Rockville, Maryland, from 7:30 effect of any decision or order which
Specification for use of the NUHOMS HD dry a.m. to 4:15 p.m. Federal workdays. may be entered in the proceeding on the
storage system, and continued handling of Documents may be examined, and/or requestors/petitioner’s interest. The
older cask designs under the original copied for a fee, at the NRC’s Public petition must also identify the specific
licensing basis for these casks, will not Document Room (PDR), located at One contentions which the petitioner/
involve a significant increase in the White Flint North, Public File Area O1 requestor seeks to have litigated at the
probability or consequences of an accident F21, 11555 Rockville Pike (first floor), proceeding.
previously evaluated. The possibility of a Rockville, Maryland. Each contention must consist of a
new or different kind of accident from any The filing of requests for hearing and specific statement of the issue of law or
accident previously evaluated is also not petitions for leave to intervene is fact to be raised or controverted. In
created, and there is no significant reduction
discussed below. addition, the petitioner/requestor shall
in a margin of safety. Therefore the
Within 60 days after the date of provide a brief explanation of the bases
requirements of 10 CFR 50.92(c) are met, and
there is not a significant hazards publication of this notice, the licensee for the contention and a concise
consideration. may file a request for a hearing with statement of the alleged facts or expert
respect to issuance of the amendments opinion which support the contention
The NRC staff has reviewed the to the subject facility operating license and on which the petitioner intends to
licensee’s analysis and, based on this and any person whose interest may be rely in proving the contention at the
review, it appears that the three affected by this proceeding and who hearing. The petitioner/requestor must
standards of 10 CFR 50.92(c) are wishes to participate as a party in the also provide references to those specific
satisfied. Therefore, the NRC staff proceeding must file a written request sources and documents of which the
proposes to determine that the for a hearing and a petition for leave to petitioner is aware and on which the
amendments request involve no intervene. Requests for a hearing and a petitioner intends to rely to establish
significant hazards consideration. petition for leave to intervene shall be those facts or expert opinion. The
The Commission is seeking public filed in accordance with the petition must include sufficient
comments on this proposed Commission’s ‘‘Rules of Practice for information to show that a genuine
determination. Any comments received Domestic Licensing Proceedings’’ in 10 dispute exists with the applicant on a
within 30 days after the date of CFR part 2. Interested persons should material issue of law or fact.
publication of this notice will be consult a current copy of 10 CFR 2.309, Contentions shall be limited to matters
considered in making any final which is available at the Commission’s within the scope of the amendments
determination. PDR, located at One White Flint North, under consideration. The contention
Normally, the Commission will not Public File Area O1F21, 11555 must be one which, if proven, would
issue the amendments until the Rockville Pike (first floor), Rockville, entitle the petitioner to relief. A
expiration of 60 days after the date of Maryland. Publicly available records petitioner/requestor who fails to satisfy
publication of this notice. The will be accessible from the Agencywide these requirements with respect to at
Commission may issue the license Documents Access and Management least one contention will not be
amendments before expiration of the 60- System’s (ADAMS) Public Electronic permitted to participate as a party.
day period provided that its final Reading Room (PDR) on the Internet at Those permitted to intervene become
determination is that the amendments the NRC Web site, http://www.nrc.gov/ parties to the proceeding, subject to any
involve no significant hazards reading-rm/doc-collections/cfr/. If a limitations in the order granting leave to
consideration. In addition, the request for a hearing or petition for intervene, and have the opportunity to
Commission may issue the amendments leave to intervene is filed by the above participate fully in the conduct of the
prior to the expiration of the 30-day date, the Commission or a presiding hearing.
comment period should circumstances officer designated by the Commission or If a hearing is requested, the
change during the 30-day comment by the Chief Administrative Judge of the Commission will make a final
period such that failure to act in a Atomic Safety and Licensing Board determination on the issue of no
timely way would result, for example in Panel, will rule on the request and/or significant hazards consideration. The
derating or shutdown of the facility. petition; and the Secretary or the Chief final determination will serve to decide
Should the Commission take action Administrative Judge of the Atomic when the hearing is held. If the final
prior to the expiration of either the Safety and Licensing Board will issue a determination is that the amendments
sroberts on PROD1PC70 with NOTICES

comment period or the notice period, it notice of a hearing or an appropriate request involve no significant hazards
will publish in the Federal Register a order. consideration, the Commission may
notice of issuance. Should the As required by 10 CFR 2.309, a issue the amendments and make it
Commission make a final No Significant petition for leave to intervene shall set immediately effective, notwithstanding
Hazards Consideration Determination, forth with particularity the interest of the request for a hearing. Any hearing

VerDate Aug<31>2005 16:06 May 15, 2006 Jkt 208001 PO 00000 Frm 00096 Fmt 4703 Sfmt 4703 E:\FR\FM\16MYN1.SGM 16MYN1
28392 Federal Register / Vol. 71, No. 94 / Tuesday, May 16, 2006 / Notices

held would take place after issuance of www.nrc.gov/reading-rm/adams.html. process allows resolution of issues
the amendments. If the final Persons who do not have access to relating to siting. At any time during the
determination is that the amendments ADAMS or who encounter problems in term of an ESP (up to 20 years), the
request involve a significant hazards accessing the documents located in permit may be referenced in an
consideration, any hearing held would ADAMS, should contact the NRC PDR application for a CP or COL. The staff
take place before the issuance of any Reference staff by telephone at 1–800– evaluated possible alternatives to the
amendment. 397–4209, 301–415–4737, or by e-mail proposed action (issuance of an ESP at
Nontimely requests and/or petitions to pdr@nrc.gov. the North Anna ESP site) including the
and contentions will not be entertained no action alternative and alternative
Dated at Rockville, Maryland, this 1st day
absent a determination by the of May, 2006. sites in its DEIS to determine if there
Commission or the presiding officer of was an obviously superior alternate site.
For the Nuclear Regulatory Commission.
the Atomic Safety and Licensing Board In the supplement to the DEIS the
that the petition, request and/or the Stephen R. Monarque, staff will evaluate only the impacts of
contentions should be granted based on Project Manager, Plant Licensing Branch II– the changes proposed for the cooling
a balancing of the factors specified in 10 1, Division of Operating Reactor Licensing, system for postulated Unit 3 and the
CFR 2.309(c)(1)(i)–(viii). Office of Nuclear Reactor Regulation. power increase from 4300–4500 MWt
A request for a hearing or a petition [FR Doc. E6–7497 Filed 5–15–06; 8:45 am] for postulated Units 3 and 4. Scoping
for leave to intervene must be filed by: BILLING CODE 7590–01–P was previously conducted for the
(1) First class mail addressed to the original DEIS and the the changes
Office of the Secretary of the described in the revision to the
Commission, U.S. Nuclear Regulatory NUCLEAR REGULATORY application do not appear to change the
Commission, Washington, DC 20555– COMMISSION scope of the environmental evaluation
0001, Attention: Rulemaking and [Docket No. 52–008] required by 10 CFR 52.18. Therefore,
Adjudications Staff; (2) courier, express pursuant to 10 CFR 51.72(c), additional
mail, and expedited delivery services: Dominion Nuclear North Anna, LLC; scoping is unnecessary and will not be
Office of the Secretary, Sixteenth Floor, Notice of Intent To Prepare a conducted. The Final Environmental
One White Flint North, 11555 Rockville Supplement to the Draft Environmental Impact Statement will contain both the
Pike, Rockville, Maryland, 20852, Impact Statement for the North Anna staff’s evaluation of the changes
Attention: Rulemaking and ESP Application proposed in the April 13, 2006, revision
Adjudications Staff; (3) E-mail to the application and the staff’s
addressed to the Office of the Secretary, On September 25, 2003, the U.S. evaluation of those areas that were not
U.S. Nuclear Regulatory Commission, Nuclear Regulatory Commission (NRC, affected by the revision.
HEARINGDOCKET@NRC.GOV; or (4) or the Commission) received an A copy of the application, including
facsimile transmission addressed to the application pursuant to Title 10 of the the environmental report, is available
Office of the Secretary, U.S. Nuclear Code of Federal Regulations, Part 52 (10 for public inspection at the
Regulatory Commission, Washington, CFR part 52) from Dominion Nuclear Commission’s Public Document Room
DC, Attention: Rulemakings and North Anna, LLC (Dominion) for an (PDR), located at One White Flint North,
Adjudications Staff at (301) 415–1101, early site permit (ESP) for the North 11555 Rockville Pike (first floor),
verification number is (301) 415–1966. Anna ESP site located in Louisa County, Rockville, Maryland 20852 and via the
A copy of the request for hearing and Virginia near the town of Mineral. On Agencywide Documents Access and
petition for leave to intervene should December 10, 2004, the NRC issued a Management System (ADAMS) Public
also be sent to the Office of the General Federal Register notice (69 FR 71854) Electronic Reading Room on the Internet
Counsel, U.S. Nuclear Regulatory announcing the availability of NUREG– at the NRC Web site, http://
Commission, Washington, DC 20555– 1811, ‘‘Draft Environmental Impact www.nrc.gov/reading-rm/adams.html.
0001, and it is requested that copies be Statement for an Early Site Permit (ESP) The accession number for the revised
transmitted either by means of facsimile at the North Anna ESP Site’’ (DEIS) and application is ML061180180. Future
transmission to 301–415–3725 or by e- sought comment on the DEIS. On April publicly available documents related to
mail to OGCMailCenter@nrc.gov. A copy 13, 2006, Dominion submitted a the application will also be posted in
of the request for hearing and petition revision to its application. The revision ADAMS. Persons who do not have
for leave to intervene should also be to the application described changes to access to ADAMS or who encounter
sent to the Ms. Lillian M. Cuoco, the cooling water system for postulated problems in accessing the documents
Esquire, Senior Counsel, Dominion Unit 3 at the North Anna ESP site and located in ADAMS should contact the
Resources Services, Inc., Building 475, an increase in power level for both NRC Public Document Room staff by
5th Floor, Rope Ferry Road, Waterford, postulated Units 3 and 4. telephone at 1–800–397–4209 or 301–
Connecticut 06385, attorney for the The purpose of this notice is to inform 415–4737, or by e-mail to pdr@nrc.gov.
licensee. the public that pursuant to 10 CFR The Louisa County Library, located at
For further details with respect to this 51.72, the NRC will be preparing a 881 Davis Highway, Mineral, Virginia
action, see the application for supplement to its DEIS in support of the has agreed to make the application
amendment dated February 14, 2006, review of the ESP application. A available to local residents. The
which is available for public inspection subsequent Federal Register notice will application is also available on the NRC
at the Commission’s PDR, located at announce the availability of the Web page at http://www.nrc.gov/
One White Flint North, Public File Area supplement to the DEIS and will request reactors/new-licensing/esp/north-
O1 F21, 11555 Rockville Pike (first public comments on the supplement. anna.html. For further information
floor), Rockville, Maryland. Publicly An applicant may seek an early site regarding the proposed action, contact
sroberts on PROD1PC70 with NOTICES

available records will be accessible from permit in accordance with subpart A of Mr. Nitin Patel, Project Manager at
the Agencywide Documents Access and 10 CFR part 52 separate from the filing telephone number 301–415–3201 or by
Management System’s (ADAMS) Public of an application for a construction mail at U.S. Nuclear Regulatory
Electronic Reading Room on the Internet permit (CP) or combined license (COL) Commission, ATTN: Nitin Patel, Mail
at the NRC Web site, http:// for a nuclear power facility. The ESP Stop 0–4D9A, One White Flint North,

VerDate Aug<31>2005 16:06 May 15, 2006 Jkt 208001 PO 00000 Frm 00097 Fmt 4703 Sfmt 4703 E:\FR\FM\16MYN1.SGM 16MYN1