You are on page 1of 3

Republic of the Philippines

Department of the Interior and Local Government


Regional Office No. 10 Northern Mindanao
Km. 3, Masterson Ave., Upper Carmen, Cagayan de Oro City
9000

A TERMINAL REPORT
On
BOTTOM-UP BUDGETING PROGRAM REVIEW FOR REGIONAL POVERTY
REDUCTION ACTION TEAM MEMBERS IN REGION 10

RATIONALE
The Bottom-up Budgeting Program is now on its fourth year of
implementation in pursuing and attaining the Philippine Development Plans
goal of inclusive growth and poverty reduction and promoting good
governance at the local level.
special

attention

for

Along the way, there were areas that need

enhancement

for

more

effective

program

implementation. Thus, there is a need for the RPRAT members to have its
Program Review.
OBJECTIVES
At the end of the Program Review, participants were able to:
Came up with a recommendation on the identified bottlenecks of
the program implementation per agency
Present their respective agencies Catch-Up plan for BuB projects to
reach the 80%-50% target completion rate by 15 September 2015
PARTICIPANTS
The respective members of the Regional Poverty Reduction Action
Team- Technical Working Group (RPRAT-TWG) were the participants of the
first day (29 June 2015) and their respective Regional Directors on 30 June
2015, for the presentation and critiquing of workshop output prepared by
the Technical Working Group per agency member.

HIGHLIGHTS
Day 1 29 June 2015
The activity started with an invocation led by Ms. Frecyne Dimple M.
Paylangco, BuB staff followed by an audio presentation of the Philippine
National Anthem.
OIC-RD Nilo P. Castaares gave his Welcome Remarks for the activity.
He stressed the importance of the two (2) day Program Review and how it
can serve as a guiding tool for the member agencies to focus on the
essentials of BuB implementation as well as emphasizing the 80%-50%
target completion rate for each agency on the 2013-2014 BuB projects and
2015 BuB projects respectively by 30 September 2015.
Each member agency were then asked to present their agencies status
of project implementation as of 29 June 2015. After which, the participants
were then instructed to identify common issues and concerns besetting each
in

the

course

of

the

implementation

of

the

projects

and

their

recommendations.
Lastly, the agencies were subjected into a workshop in coming up with
their Catch-up Plan to attain the 80%-50% target completion rate for each
agency on the 2013-2014 BuB projects and 2015 BuB projects respectively
by 30 September 2015.

Day 2 30 June 2015


A recap of the first (1st) day was done by LGOO VI Hazel L. Occea,
BuB Regional Focal Person for DILG.
During this day, the workshop output of the RPRAT-TWG regarding
their respective Catch-up Plans were presented before their Regional
Directors
Please refer to separate sheet for the highlights of the issues and
concerns.

CLOSING REMARKS
The activity formally ended at around 4:30 PM of 30 June 2015.
LGOO VI Hazel L. Occea gave a parting message for the RPRAT-TWG and
Regional Directors emphasizing the importance of abiding with the timeline

set by each agency in their catch up plan to attain the 80%-50% target
completion rate for each agency on the 2013-2014 BuB projects and 2015
BuB projects respectively by 30 September 2015.

Prepared by:

LGCDD Documentation Committee

Noted by:

FOSTER N. ANAYRON
Chief, LGCDD