Professional Documents
Culture Documents
and
Civil Engineering aspects of SH/MH
INTRODUCTION
A Micro Hydro (Or A Small Hydro) Power Project Is A System Of Electricity Generation By
Water Driven Forces And Power Is Supplied To Villages/Cities For Different Uses.
Generally Hydro Energy From MHP Is Basically Used For Lightening.
Diesel Type Mills For Grain Grinding, Rice Hulling Etc. Are Replaced By Electrical Driven
Type.
History of Micro hydro in Nepal - since 1960 after establishment of Balaju Yantra Shala
assisted by Swiss and at the same period United Mission to Nepal (UMN) support also
initiated.
Water Mills were used extensively during 1970.
Private Manufacturing Companies spread up in eighties.
Contd..
Most of the equipments/components e.g.. Gate Valves, Turbines, Trash
racks, MS Pipes for penstocks, Conductors and Load Controllers are in
general locally manufactured in Nepal.
Generators are imported from abroad especially from India and China, and
also from Europe in some cases.
Standardization started in late eighties.
Intermediate Technology Development Group (ITDG) and Agricultural
Development Bank Nepal (ADB/N) contributed for enhancement of
technological base of the micro hydro installations in the country.
After establishment of Alternative Promotion Centre quality aspects of micro
hydro power project has been given more emphasize and standards has
been
established
installations steps.
in
survey,
design,
manufacturing/fabrication
and
Type of Scheme
Capacity
Isolated
Grid
>10MW
300KW- 10
MW
<300KW
Note: 1. Above category was made by Adam Harvey and et all, Micro Hydro
Design Manual
2. Micro Hydro Schemes may or may not generate electricity, may be grid
connected also and normally are of Run of River Type.
Size
Category
Pico Hydro
Micro Hydro
Mini Hydro
Small Hydro
Large Hydro
Ideal Design
Optimize the use of resources.
An ideal design should be such that based on it an experienced installer should be
able to construct the scheme independently of, with only nominal assistance from,
the designer.
Conclude the findings and recommend to the concerned parties developer, donor,
approval committee etc. for required action.
Design guidelines
Various organizations and institutions has developed
design guidelines incorporating the national and
international standards, country situation, enhancing
available indigenous technology etc.
Example Micro Hydro Design Manual by Adam
Harvey ITDG
Detail Feasibility Study and Design Guidelines
AEPC, Nepal
Manual for Decentralized Distribution & Generation
Projects (Based on Community Participan)
Uttaranchal Renewable Energy Development Agency
(UREDA), India
Etc.
CIVIL COMPONENTS
Intake
Weir
Spillway
Desilting Basin
Headrace Canal/ Pipe
Forebay
Support Structures
Support Piers
Anchor blocks
Machine Foundation
Power House
Tailrace
Civil Components
of;+/rgfx?
Micro Hydro
n3' hnljB't cfof]hgfsf l;len
Trashrack
Intake
Headrace
Canal
Canal
Sp
ilw
ay
WEIR
ilti
s
e
D
sin
Ba
g
n
i
silt
De
asin
B
ng
Crossing
Forebay
Cr
oss
ing
Anchor Block
Canal
Weir
ay
ilw
p
S
Support Pier
a
ols
Kh
Riv
er/
Kh
ola
Spillway
Anchor Block
Forbay
Support Piers
Spill way
Penstock Pipe
Anchor Block
Source
Power House
Power House
e
ac
ilr
a
T
Tailrace
Major Civil Components Of Micro Hydro Scheme
Diversion Works
The diversion works of a micro-hydropower scheme control the flow
of water from the source river in to the headrace.
The diversion structures comprise
a diversion weir,
Diversion Weir
A diversion weir is a low structure (small dam) placed across the
river which diverts the river flow safely in to the hydropower system
through side intake.
The weir can be of a permanent, semi -permanent or temporary
nature.
The main function of a weir is to ensure that the channel flow is
maintained with the river in low flow period.
Temporary Weir
Temporary weir is constructed using boulders available at the site,
stone masonry in mud mortars placed across a part or all of the river
width.
This is the traditional method used by Nepali farmers and quite
extensively used in micro hydro schemes in Nepal.
It is simple and low cost but it is not possible to divert all of the river
flow in dry season by this structure.
It is suitable only for the diversion of flows below 1 m3/sec
Semi Permanent Weir
Gabion structures can be use as semi permanent weir.
If there is no significant boulder movement along the river stretch at the
intake area, it may be effective
It can tolerate some ground movement without significant damage on
its body
As the gabion wires are more vulnerable to damage by moving
boulders, it cannot used in the steep streams, which carry such
boulders.
Seepage can be control by using an impermeable membrane.
Permanent weir
If flow is limited during dry season and river does not carry large boulders
permanent weir may be built across the river.
These are constructed of mass concrete, stone masonry in cement mortar and
If a weir across part of the river width is sufficient, it should not be extended
across the entire width.
The weir length should allow safe passage of design flood.
The weir height should be as low as possible but should be such that the
water level rises above the upper edge of the intake mouth.
The weir profile should be such that it is possible for the bed load to move
the boulders to roll over it.
Side Intake
A structure built along a river bank and in
front of a canal / conduit end for diverting
the required water safely. Side intakes are
simple, less expensive, easy to build and
maintain.
Site Intake
Bottom Intake
HYDROLOGY
!" #
Design Discharge
11 month (~92%) exceedance criteria in MHP context
The installed capacity should be available to the Community
at least 11 months a year (12 Months for REDP Projects)
Maximum demand during the winter season
The driest season (12 month exceedance) is winter (mid Jan
mid Feb) for streams that are snow fed & April May for
streams that come from spring sources.
In the absence of flow exceedance criteria, schemes could be
oversized.
~ 80-85 % of 11/12 months Discharge is taken as the designed
discharge
and
d.
Forebay
a. Shall house an overflow spillway, a drain valve or stop log
gate to flush sediment, and a trash rack, Disposal
requirement of spilled water
b. Length, width, submergence for PSP, leakage etc. are
mentioned
c. Thickness of concrete
Penstock
a. Excavation/ depth in case of PVC/HDPE
b. Types, sizes, of support piers, anchor blocks
c. Movement and clearances in support structures
d. About acting forces and their transmission
e. Air vent and size
Power house
a.
b.
c.
d.
e.
f.
Tailrace
a. Water level with respect to turbine runner
b. V notch weir provision
c. Energy dissipating provision
Q
A=
V
$%
%&
'
%()
'* )
+
W=
Q = AC 2g(hr hh )
ve
lT
na
ol
at
ra
ra
Ca
Kh
50
G
l
ve g
r a in
G lu s h
F
1:
ay
r/
30
illw
iv e
n n
i o t io
ab c
G r o te
P
1:
Sp
CREST
B
B
Possible Layout
Left flood wall
Sp
illw
ay
Q = flow in m3/s
A = cross sectional area of
canal (up to water depth), m2
S = Slope of the energy
grade line ~ ground slope
n = roughness coefficient of
canal, also called Mannings
roughness
R = Hydraulic radius, A/P,
P = Wetted perimeter sum
of lengths of two sides and
width of canal up to water
depth: w + 2h
1
Qn
23
Q = AR
S, S =
23
n
AR
0
&'''
+
VC =
Ag
T
Canal
Spillway sizing
Spillway required to spill
excess flows during
floods or for canal
maintenance
downstream:
2
1
hovertop
=
CW xLweir
0.667
,
2
Spillway sizing
Cw for different weir
Profile
3
Headrace
4.0 m
1.3 m
,
4
5
2.
3.
4.
Q 4 xQ
V= =
2
A d
y = wt (a)
L = V p t (b)
Q = BV p y (c)
=> From a, b, c, Q = BLw
dlimit
h < 10 m, dlimit = 0.3 0.5 mm
10 m < h < 100 m,
dlimit = 0.2 0.3 mm
h >100 m, dlimit = 0.1 0.2 mm
V=
Q
< 0.44 d lim it
By
Desilting Basin
Desilting Basin
hsubmergence
V2
= 1.5
2* g
1
2.5
Trash Rack
Airvent Pipe
A. Block-1
Expansion Joint
Penstock Pipe
Sluice gate
Over Flow Length = 6.00
W(settling) = 2.50
Forebay
SUPPORT STRUCTURES
Penstock
Alignment
Support piers
Support piers
Use of Tar paper
(asbestos sheet)
minimizes friction
between pipe &
support pier
Base plate
provides
additional safety
Diameter (mm)
Thickness mm
2
4
6
100
200
300
400
support piers spacing in meter
2
2
2.5
3
3
3
3
4
4
4.5
5
5
500
3
4
6
Machine Foundation
Turbine
Tailrace
canal
Generator
A
PLAN
Turbine
Generator
SECTION - AA
0.70
ry r
on rta
as mo
e m /s
on c
St 1:4
in
1.2
Anchor rods
(20 mm dia.)
Machine Foundation
Power House
CGI Sheet Roofing
Penstock Pipe
ELC
BT
Valve
W1
OPERATOR
W QUARTER
T
G
D1
D1
W1
75 mm PCC (1:2:4)
200 mm soling
Thank You!