Professional Documents
Culture Documents
UDK 69.008:728.1+624.057.5
Construction cost
of tunnel form buildings
Authors:
Professional paper
A residential building with a lateral load resisting system, adopted as a reference example,
is considered in the paper. The system is made of shear walls realized using the tunnel
form technology. The building is modelled for a varying number of floors, and the model
is also used to consider the applicability of the technology with regard to construction
costs. The influence of the type of soil on construction costs is also considered. The results
obtain show that mistakes made in determining the soil class may lead to inadequate
decisions during selection of the most favourable number of floors, and in the design of
structural elements and foundations of buildings.
Key words:
construction costs, number of floors, tunnel form technology, shear wall system, type of soil
Struni rad
135
Graevinar 2/2013
1. Introduction
136
(1)
Graevinar 2/2013
Figure 1. a) Floor plan with two elevators; b) Floor plan with four elevators
12
18
24
30
36
42
48
54
15
15
20
20
20
20
40
70
80
12
18
24
30
36
42
48
54
Basement
16.80
33.60
50.40
67.20
84.00
100.80
117.60
134.40
151.20
Installation story
Typical floor
11
17
21
27
32
37
42
48
Flat
20
44
68
84
108
128
148
168
192
137
Graevinar 2/2013
3. Cost analysis
Static soil analyses were carried out for each analytical model
(having a different number of floors), all of which consisted
of identically sized and symmetrically placed shear walls in
both directions. Cost analysis results were then evaluated
from two different aspects. First, the models were compared
in terms of number of floors regardless of their costs, so as
to measure rationality of the tunnel form system. Then the
allowable bearing capacity of soil was changed to investigate
effects of soil type on the total construction cost.
Variation of cost with respect to the number of floors: a) total costs; b) unit cost per apartment
Table 3. The cost of components as related to the total construction cost
Components
Number of floors
Formwork [%]
Reinforcement [%]
Concrete [%]
Foundation [%]
Roof [%]
Earth-work [%]
43,76
18,06
15,09
16,64
5,18
1,27
12
40,70
23,99
20,00
11,2
3,49
0,86
18
36,59
27,17
24,78
8,37
2,48
0,61
24
33,08
28,41
27,94
7,97
1,80
0,79
30
31,30
32,47
27,96
7,16
1,49
0,90
36
31,08
33,53
28,11
6,19
1,20
0,80
42
22,98
37,77
32,28
5,60
0,85
0,53
48
16,39
40,69
35,90
6,11
0,58
0,36
54
14,72
40,98
36,28
7,55
0,42
0,30
138
Graevinar 2/2013
Figure 3. Variation of cost with respect to the number of floors: a) total costs; b) unit cost per apartment
Allowable
bearing
capacity
12
18
24
30
36
42
48
54
250 kN/m2
Mat Fndn.
Mat Fndn.
Mat Fndn.
Pile Fndn.
Pile Fndn.
Pile Fndn.
Pile Fndn.
Pile Fndn.
Pile Fndn.
500 kN/m2
Mat Fndn.
Mat Fndn.
Mat Fndn.
Mat Fndn.
Mat Fndn.
Mat Fndn.
Pile Fndn.
Pile Fndn.
Pile Fndn.
139
Graevinar 2/2013
Allowable
bearing capacity
12
18
24
30
36
42
48
54
250 kN/m2
100
69,28
60,64
68,23
67,48
63,94
87,85
125,63
135,13
500 kN/m
100
69,68
59,89
59,81
59,22
56,84
85,09
118,40
127,87
140
4. Conclusions
In construction industry, the financial model of the project
should be accurately established during the decision
making process, so as to enable adequate handling of
potential problems due to cash flow, and to prevent loss of
national resources. This can only be achieved by accurate
estimation of total costs already at the pre-design phase.
The distribution of costs varies depending on the structural
system selected for the building, and on the size and type of
structural elements.
In recent times, the use of tunnel formwork systems in the
construction of multi-story reinforced concrete buildings
has become very common in Turkey. Design engineers
should not only be knowledgeable of design principles, but
should also be familiar with economic aspects of tunnel form
systems. The effects of the number of typical floors and local
soil conditions on the structural design and total cost should
be estimated ahead of time. Project investors would like to
know the budget in order to secure adequate financing for
the investment. It is therefore important to make realistic
cost estimations as soon as practicable. Analyses of a
number of tunnel work projects, consisting of a number of
different parameters, were conducted in this study. Cost
analysis results are summarized as follows:
-- It was concluded that, due to significant increase in
construction costs, 42 floors and above would not be rational
for shear wall buildings (or similar structures) constructed
using tunnel form systems. In cases when the number of
floors is not selected in accordance with the structural
system, the design of structural components results in
larger element sizes, which in turn causes losses in terms of
material. As the thickness of shear walls increases, the total
building weight also increases, which is why more expensive
foundation systems must be used and more reinforcement
must be placed. The reason for the increase in shear wall
thickness can be related to greater displacements as the
building becomes taller, i.e., thicker walls are needed to
provide rigidity and to prevent excessive drift of taller
buildings. The size of structural elements should not be
increased significantly, and larger lateral (earthquake and
wind) loads due to increase in height should be taken into
account by selecting an efficient structural system instead
of using larger element size
Graevinar 2/2013
to take full advantage of this technology. For example,
analytic results obtained in this study show that use of
tunnel form systems is not rational for low-rise shear
wall buildings due to very high unit costs per apartment.
Therefore, tunnel form systems are more advantageous in
mass housing constructions since the life span of tunnel
formwork is longer compared to conventional formwork
systems, although initial investment costs are higher.
It should also be noted that the use of traditional timber
formworks may be more economical and preferable for
relatively small-scale construction projects.
It can be concluded that tunnel form systems, which are
widely used in the construction of reinforced concrete shear
wall buildings, lose rationality based on the criteria presented
in this study. This paper attempts to provide helpful
recommendations to design engineers through comparison
of different models with appropriate criteria.
REFERENCES
[1] Hall, M., Tomkins, C.: "A cost of quality analysis of a building
project: towards a complete methodology for design and
building" Construction Management and Economics, 19 (2001)
727-740..
[2] Ansal, A. M., Lav, A.M.: "Geotechnical Factors in 1992 Erzincan
Earthquake", 5th Conference on Seismic Zonation, Nice, Vol. 1,
667-674, 1995.
[3] Ansal, A.M., engezer, B.S., yisan, R. and Genolu, S.: "The
Damage Distribution in March 13, 1992 Earthquake and Effects
of Geotechnical Factors", Soil Dynamics and Geotechnical
Earthquake Engineering, Balkema, Rotterdam, 413-434, 1993.
[4] anak, H., G, M.: "Effect of misdetecting local soil classes
on lateral loads acting on buildings", XVI. Technical Congress of
Civil Engineering, Ankara, 2001.
[5] Harmankaya, Z. Y.: "Effects Of Number Of Storeys And Concrete
Class On The Building Cost Of The Multi Storied Buildings In
Turkey", Master thesis, Gazi University, Ankara, Turkey (in
Turkish), 2010.
[6] STA Computer Engineering and Consulting Limited Company
"STA4-CAD V13, Analysis and Design of Multi-storey Reinforced
Buildings", Ankara, Turkey, 2010.
141